John R. Kasich, Governor
Jerry Wray, Director
Jeffrey M. Hisem, Administrator, Office of Estimating
OHIO DEPARTMENT OF TRANSPORTATION
AN EQUAL Opportunity EMPLOYER
Summary of
Contracts
Awarded
2013
1 | P a g e
Table of Contents
• Section I: Summary of Contracts Awarded for Calendar Year 2012 by Fund Type PAGE 2
• Section II: Summary of Contracts Awarded for Calendar Year 2012 by Project Type PAGE 3
• Section III: Summary of Contracts Awarded for Calendar Year 2011 by Contractor PAGE 5
• Section IV: Summary of Contracts Awarded for Calendar Year 2012 by District/County PAGE 25
• Section V: Summary of Contracts Awarded for Calendar Year 2012 by Item PAGE 38
2 | P a g e
Summary of Contracts Awarded for the Calendar Year 2013 by Fund Type
Description of Classification Number of Total Contract
Contracts Amt by Type
Total Contracts Awarded Federal 544 $1,677,371,127.69
Total Contracts Awarded Non-Federal 179 $193,810,678.45
Grand Total of Contracts Awarded 723 $1,871,181,806.14
During Calendar Year
3 | P a g e
Contracts Awarded for the Calendar Year 2013
by Type of Project
Type Project Type Total Total Awarded
Code Contracts Amount
03 MAJOR RECONSTRUCTION 11 $392,867,296.04
04 MAJOR WIDENING 4 $110,872,807.21
05 MINOR WIDENING 6 $63,466,943.00
08 NEW BRIDGE 2 $21,479,559.63
10 PREVENTIVE MAINTENANCE 21 $27,568,767.79
11 SPOT PATCHING 7 $8,078,982.39
2L TWO LANE RESURFACING 146 $257,518,909.61
4L FOUR LANE RESURFACING 32 $134,929,111.87
B1 BRIDGE REPLACEMENT (1 BRIDGE) 55 $364,738,018.47
B2 BRIDGE REPLACEMENT (2 BRIDGES) 16 $34,069,638.94
B3 BRIDGE REPLACEMENT (3 BRIDGES) 1 $1,072,284.00
BH BRIDGE REPAIR 102 $183,609,610.55
BP BRIDGE PAINTING 4 $2,996,348.11
BW BIKEWAYS 6 $5,779,550.55
CS CRACK SEALING 7 $1,914,145.17
CU CULVERT REPLACEMENT 36 $11,305,339.64
F FENCING 1 $328,639.25
GR GUARDRAIL REBUILDING 20 $16,352,085.65
HE HERBICIDAL SPRAYING 8 $877,927.51
I INTERCHANGE 4 $28,690,445.23
LG LIGHTING 10 $6,190,294.25
LS LANDSCAPING 5 $1,720,685.32
4 | P a g e
Contracts Awarded for the Calendar Year 2013
by Type of Project
Type Project Type Total Total Awarded
Code Contracts Amount
MS MISCELLANEOUS 73 $83,597,841.19
MW MOWING 12 $7,640,204.48
NW NOISE WALLS 4 $8,972,653.50
PA PARKING AREAS 7 $5,711,252.80
PM PAVEMENT MARKING 24 $21,820,735.79
PR PRUNING/OR TREE/BRUSH REMOVAL 2 $279,305.00
RG RAILROAD GRADE SEPARATION 1 $12,324,028.86
RM RAISED PAVEMENT MARKERS 10 $1,699,887.13
S SIGNALIZATION 20 $8,900,585.01
SD SALT DOME 6 $2,853,935.59
SL SLIDE REPAIR 32 $12,874,562.03
SN SIGNING 4 $833,166.20
SS SPOT SAFETY 7 $6,699,339.91
X INTERSECTION 17 $20,546,918.47
Total Amount Awarded for All Project Types $1,871,181,806.14
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
5 | P a g e
21ST CENTURY CONCRETE CONSTRUCTION INC 7 $3,367,000.00 $3,144,355.05 -7
13925 ENTERPRISE AVE
Cuyahoga
CLEVELAND OH, 44135
A & A SAFETY INC 9 $7,027,000.00 $6,529,218.91 -7
1126 FERRIS RD
Clermont
AMELIA OH, 45102
A & B ASPHALT CORPORATION 4 $3,903,999.99 $3,672,260.83 -6
1780 ENON RD
Clark
SPRINGFIELD OH, 45502
A P O'HORO COMPANY 10 $34,219,000.01 $30,396,000.00 -11
P O BOX 2228
Mahoning
YOUNGSTOWN OH, 44504
ACI CONST CO INC 2 $438,000.00 $415,565.89 -5
2959 S US 23
Seneca
ALVADA OH, 44802
ADLETA INC 1 $715,000.00 $724,246.27 +1
389 S WAYNE AVE
Hamilton
CINCINNATI OH, 45215-4522
AERO-MARK INC 6 $6,999,000.00 $6,809,617.75 -3
10423 DANNER DR
Portage
STREETSBORO OH, 44241
ALAN STONE CO INC 3 $2,114,000.00 $1,807,510.30 -14
1324 ELLIS RUN RD
Washington
CUTLER OH, 45724
ALL ASPECTS CONTRACTING INC 2 $366,000.00 $191,621.45 -48
2800 EUCLID AVE SUITE 312C
Lorain
CLEVELAND OH, 44035
ANTHONY ALLEGA CEMENT CONTRACTOR INC 2 $51,375,000.00 $46,866,848.33 -9
5585 CANAL RD
Cuyahoga
VALLEY VIEW OH, 44125
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
6 | P a g e
APBN INC 4 $7,190,000.00 $5,846,459.84 -19
670 ROBINSON RD
Mahoning
CAMPBELL OH, 44405
ARMSTRONG STEEL ERECTORS INC 3 $1,772,000.00 $1,872,308.58 +6
50 SOUTH FOURTH ST P O BOX 577
Licking
NEWARK OH, 43058
ATSALIS BROTHERS PAINTING CO 1 $16,705,000.00 $11,132,215.99 -33
24595 GROESBECK HIGHWAY
WARREN MI, 48089
B & G TRUCKING & CONSTRUCTION INC 1 $607,000.00 $372,017.00 -39
11330 MARKET ST P O BOX 308
Mahoning
NORTH LIMA OH, 44452
BANSAL CONSTRUCTION INC 1 $268,000.00 $296,061.01 +10
3263 HOMEWARD WAY
Butler
FAIRFIELD OH, 45014
BARRETT PAVING MATERIALS INC 20 $38,256,635.01 $39,170,683.99 +2
3751 COMMERCE DR
Warren
MIDDLETOWN OH, 45005
BAUMANN ENTERPRISES INC 1 $311,000.00 $167,722.51 -46
4801 CHAINCRAFT RD
Cuyahoga
GARFIELD HTS OH, 44125
BBR DRILLING COMPANY INC 2 $1,617,000.00 $1,127,751.05 -30
41462 PALMER RD
Belmont
BELMONT OH, 43718
BCC OHIO INC 5 $1,268,000.00 $1,397,856.56 +10
P O BOX 229
Huron
NEW LONDON OH, 44851
BEAVER EXCAVATING COMPANY 4 $166,272,426.85 $157,083,650.33 -6
P O BOX 6059
Stark
CANTON OH, 44706
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
7 | P a g e
BECDIR CONSTRUCTION COMPANY 3 $4,355,000.00 $3,902,376.82 -10
15764 W AKRON-CANFIELD RD
Mahoning
BERLIN CENTER OH, 44401
BELGRAY, INC 2 $477,000.00 $450,546.32 -6
800 E FIRST ST
Montgomery
DAYTON OH, 45402
BLUFFTON PAVING INC 1 $2,072,000.00 $2,004,762.85 -3
P O BOX 26
Allen
BLUFFTON OH, 45817
BOG CONSTRUCTION INC 6 $3,788,000.00 $3,635,758.70 -4
8235 HUXLEY RD
Mahoning
BERLIN CENTER OH, 44401
BOONE COLEMAN CONSTRUCTION INC 1 $136,000.00 $113,783.40 -16
32 STATE ROUTE 239
Scioto
W PORTSMOUTH OH, 45663
BRIDGE OVERLAY SYSTEMS INC 6 $2,555,000.00 $2,298,001.91 -10
400 E MAIN ST SUITE 2
Mahoning
CANFIELD OH, 44406
BROOKS CONSTRUCTION COMPANY INC 1 $149,000.00 $111,550.00 -25
6525 ARDMORE AVE
FORT WAYNE IN, 46809
BROWN COUNTY ASPHALT INC 2 $2,294,000.00 $1,859,495.77 -19
11254 HAMER RD
Brown
GEORGETOWN OH, 45121
BROWN COUNTY CONSTRUCTION CO INC 1 $1,091,000.00 $1,074,329.54 -2
8108 US ROUTE 52
Brown
ABERDEEN OH, 45101
BRUMBAUGH CONSTRUCTION INC 4 $4,497,000.00 $3,734,908.00 -17
P O BOX 309
Darke
ARCANUM OH, 45304
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
8 | P a g e
BRYPAN LLC 3 $1,927,000.00 $2,028,279.10 +5
1525 DITMORE STROLL
Licking
NEWARK OH, 43055
BUCKEYE EXCAVATING & CONSTRUCTION INC 2 $244,000.00 $206,585.90 -15
191 SR 61 EAST
Huron
NORWALK OH, 44857
BUDS INC 11 $5,119,000.00 $4,787,323.46 -6
6260 NEWARK RD
Muskingum
NASHPORT OH, 43830
BURTON SCOT CONTRACTORS LLC 5 $5,046,000.00 $5,179,757.22 +3
11330 KINSMAN RD
P O BOX 389
Geauga
NEWBURY OH, 44065
CENTRAL-ALLIED ENTERPRISES INC 5 $9,556,000.00 $9,150,905.56 -4
1243 RAFF RD S W
Stark
CANTON OH, 44710
CG COLE CONSTRUCTION LLC 1 $422,000.00 $361,772.29 -14
12351 PROSPECT RD
Cuyahoga
STRONGSVILLE OH, 44149
CHAGRIN VALLEY PAVING INC 2 $2,801,106.10 $2,533,401.30 -10
17290 MUNN RD
Geauga
CHAGRIN FALLS OH, 44023
CIVIL CONSTRUCTION INC 2 $217,000.00 $207,732.62 -4
10310 STATE ROUTE 161
Madison
PLAIN CITY OH, 43064
CLEVELAND BARRICADING SYSTEMS LLC 1 $100,000.00 $80,408.00 -20
2608 GREAT LAKES WAY
Medina
HINCKLEY OH, 44233
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
9 | P a g e
COLUMBUS ASPHALT PAVING INC 4 $1,797,000.00 $1,799,157.33 0
1196 TECHNOLOGY DR
Franklin
GAHANNA OH, 43230
COMPLETE GENERAL CONSTRUCTION COMPANY 25 $71,332,771.52 $75,408,296.37 +6
1221 EAST FIFTH AVE
Franklin
COLUMBUS OH, 43219
COOPERS EXCAVATING LLC 3 $1,264,000.00 $980,143.54 -22
7251 BETHLEHEM ROAD
Adams
WINCHESTER OH, 45697
CORNERSTONE ELECTRIC INC 2 $1,702,000.00 $1,271,257.20 -25
14375 WEST CALLA RD
Columbiana
SALEM OH, 44460
COSMOS INDUSTRIAL SERVICES INC 2 $2,778,000.00 $2,724,350.25 -2
9103 DETROIT AVE
Cuyahoga
CLEVELAND OH, 44102
COUNTRYSIDE GARDENS INC 1 $223,000.00 $264,784.55 +19
3272 ST RT 502
Darke
GREENVILLE OH, 45331
CRAIG EDWARD SUSANY INC 1 $898,000.00 $747,047.90 -17
13535 MARKET STREET
Mahoning
NORTH LIMA OH, 44452
CROSS ROADS CONSTRUCTION INC 4 $1,092,000.00 $1,198,296.55 +10
3155 HARDING LANE
Guernsey
CAMBRIDGE OH, 43725
CUSTOM MOWING 1 $454,000.00 $402,040.60 -11
5728 MAD RIVER ROAD
Highland
HILLSBORO OH, 45133
CUYAHOGA FENCE LLC 1 $315,000.00 $328,639.25 +4
3100 EAST 45TH ST SUITE 516
Cuyahoga
CLEVELAND OH, 44127
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
10 | P a g e
D G M INC 7 $5,389,000.01 $5,486,521.15 +2
1881 ADAMS RD
Pike
BEAVER OH, 45613
D V WEBER CONSTRUCTION 1 $31,000.00 $20,538.00 -34
65876 ST RT 124 P O BOX 116
Meigs
REEDSVILLE OH, 45772
DALTONS INC 1 $51,000.00 $59,730.73 +17
936 LITTLE EAGLE DRIVE
WARSAW IN, 46580
DEANGELO BROTHERS INC 2 $214,000.00 $217,254.02 +2
100 NORTH CONAHAN DR
HAZLETON PA, 18201
DEITERING LANDSCAPING INCORPORATED 1 $231,000.00 $281,305.00 +22
6700 ROAD 5
Putnam
LEIPSIC OH, 45856
DENNISON BRIDGE INC 3 $1,564,000.00 $1,382,165.78 -12
500 STILLWATER AVE
Tuscarawas
DENNISON OH, 44621
DIORIO PAVING CO INC 2 $1,111,900.00 $1,102,765.00 -1
1200 SOUTH STATE ST
Trumbull
GIRARD OH, 44420
DOT CONSTRUCTION CORP 1 $1,267,000.00 $1,447,111.19 +14
535 NORTH BROAD ST STE 5
Mahoning
CANFIELD OH, 44406
DOUBLE JAY CONSTRUCTION INC 1 $564,555.00 $704,608.45 +25
25 HARRISBURG DR
Montgomery
ENGLEWOOD OH, 45322
DOUBLE Z CONSTRUCTION COMPANY 6 $15,299,000.00 $14,454,531.99 -6
2550 HARRISON RD
Franklin
COLUMBUS OH, 43204
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
11 | P a g e
DURA MARK INC 2 $481,000.00 $432,055.86 -10
2940 PROGRESS PARK DR
Summit
STOW OH, 44224
E S WAGNER COMPANY 1 $28,975,000.00 $28,694,795.61 -1
840 PATCHEN RD
Lucas
OREGON OH, 43616
EAGLE BRIDGE CO 9 $11,295,000.00 $11,308,509.70 0
800 S VAN DEMARK RD
Shelby
SIDNEY OH, 45365
EAGLE INDUSTRIAL PAINTING LLC 1 $1,347,000.00 $1,041,174.26 -23
1311 CHANTILLY CIR NW
Stark
NORTH CANTON OH, 44721
ECLIPSE CO LLC 3 $670,000.00 $672,123.52 0
11554 EAST WASHINGTON ST
Geauga
CHAGRIN FALLS OH, 44023
ERIE BLACKTOP INC 2 $3,526,000.00 $3,911,060.25 +11
4507 TIFFIN AVE
Erie
SANDUSKY OH, 44870
EVERS WELDING CO INC 3 $694,000.00 $335,650.00 -52
4849 BLUE ROCK RD
Hamilton
CINCINNATI OH, 45247
FLORENCE CEMENT COMPANY 1 $821,000.00 $740,745.00 -10
12585 23 MILE ROAD
SHELBY TOWNSHIP MI, 48315
FOILL INC 2 $822,000.00 $762,126.00 -7
201 E NORTH ST
Pike
WAVERLY OH, 45690
FOREST CITY ERECTORS INC 2 $346,000.00 $375,185.86 +8
8200 BOYLE PKWY
Summit
TWINSBURG OH, 44087
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
12 | P a g e
FOUST CONSTRUCTION INC 1 $341,000.00 $244,213.15 -28
1700 WILSON
Trumbull
GIRARD OH, 44420
G E BAKER CONSTRUCTION INC 1 $137,000.00 $89,463.67 -35
6555 WHARTON RD
Wayne
SHREVE OH, 44676
GEDDIS PAVING & EXCAVATING INC 1 $1,386,000.00 $1,394,724.88 +1
1019 WAMBA AVE
Lucas
TOLEDO OH, 43607
GENERAL TEMPERATURE CONTROL 1 $2,000,000.00 $2,040,000.00 +2
970 WEST WALNUT ST
Franklin
CANAL WINCHESTER OH, 43110
GEORGE J IGEL & CO INC 1 $551,000.00 $638,939.54 +16
2040 ALUM CREEK DR
Franklin
COLUMBUS OH, 43207
GERKEN PAVING INC 10 $20,604,000.00 $19,285,644.89 -6
9-072 U S 24
Henry
NAPOLEON OH, 43545
GREAT LAKES CONSTRUCTION CO 6 $44,217,000.00 $42,822,229.66 -3
2608 GREAT LAKES WAY
Medina
HINCKLEY OH, 44233
GRIFFIN PAVEMENT STRIPING INC 1 $115,000.00 $101,289.89 -12
2383 HARRISON RD
Franklin
COLUMBUS OH, 43204
HELMS AND SONS EXCAVATING 3 $1,191,000.00 $1,013,037.70 -15
1753 LIMA AVE
Hancock
FINDLAY OH, 45840
HENRY W BERGMAN INC 1 $394,000.00 $460,184.30 +17
218 E NINTH ST
Ottawa
GENOA OH, 43430
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
13 | P a g e
INDIANA RELINE INC 1 $178,000.00 $151,576.00 -15
P O BOX 5
Noble
SULPHUR SPRINGS IN, 43788
INTERNATIONAL CONTRACTORS CORP 5 $970,000.00 $816,000.00 -16
450 EAST STARR AVE
Franklin
COLUMBUS OH, 43201
INTERSTATE IMPROVEMENT INC 1 $257,000.00 $262,507.74 +2
P O BOX 8
FAIRBAULT MN, 55021-0008
INTERSTATE ROAD MANAGEMENT CORP 1 $412,000.00 $365,363.00 -11
322 ROCKY ROAD
HAZLETON PA, 18201
J & J SCHLAEGEL INC 1 $410,000.00 $334,880.32 -18
518 MIAMI ST
Champaign
URBANA OH, 43078
J D WILLIAMSON CONSTRUCTION CO INC 3 $9,077,000.00 $9,153,886.06 +1
441 GENEVA AVE, PO BOX 113
Summit
TALLMADGE OH, 44278
J RANCK ELECTRIC INC 5 $2,338,000.00 $2,283,617.05 -2
1993 GOVER PARKWAY
MT PLEASANT MI, 48858
JEFFREY CARR CONSTRUCTION 1 $960,000.00 $913,114.05 -5
4164 ERIE AVENUE SW
Stark
MASSILLON OH, 44646
JET EXCAVATING COMPANY 1 $858,000.00 $797,794.64 -7
4354 SOUTH RANGE RD
Mahoning
NEW MIDDLETOWN OH, 44442
JOHN R JURGENSEN COMPANY 14 $154,263,600.00 $141,975,561.14 -8
11641 MOSTELLER RD
Hamilton
CINCINNATI OH, 45241
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
14 | P a g e
JUTTE EXCAVATING INC 2 $1,948,000.00 $1,506,733.44 -23
1140 FT RECOVERY-MINSTER RD
Mercer
FORT RECOVERY OH, 45846
KARVO PAVING COMPANY 12 $42,112,100.01 $41,307,602.43 -2
4524 HUDSON DR
Summit
STOW OH, 44224-1702
KEFFLER BRIDGE COMPANY 1 $3,824,000.00 $4,091,537.05 +7
9790 AKRON-CANFIELD RD
Mahoning
CANFIELD OH, 44406
KELSTIN INC 1 $558,000.00 $329,777.00 -41
183 SOUTH GAMBLE ST
Richland
SHELBY OH, 44875
KENMORE CONSTRUCTION CO INC 3 $50,693,000.00 $47,902,557.29 -6
700 HOME AVE
Summit
AKRON OH, 44310
KMX PAINTING INC 3 $3,150,000.00 $2,532,507.50 -20
4328 MC CARTNEY RD
Mahoning
LOWELLVILLE OH, 44436
KOKOSING CONSTRUCTION COMPANY INC 28 $79,279,564.15 $79,313,019.72 0
886 MC KINLEY AVE
Franklin
COLUMBUS OH, 43222
KOSKI CONSTRUCTION CO 2 $2,356,000.00 $2,281,980.55 -3
P O BOX 1038
Ashtabula
ASHTABULA OH, 44005-1038
KUHLMAN BUILDERS INC 1 $115,500.00 $154,491.00 +34
P O BOX 432
Putnam
OTTAWA OH, 45875
LAFAYETTE ELECTRIC INC 2 $538,500.00 $491,816.65 -9
1050 LAFAYETTE RD
Medina
MEDINA OH, 44256-3549
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
15 | P a g e
LAKE ERIE CONSTRUCTION COMPANY 12 $11,866,000.00 $12,534,275.00 +6
25 NORWALD ROAD
P O BOX 777
Huron
NORWALK OH, 44857
LAKE ERIE ELECTRIC OF TOLEDO INC 2 $327,010.00 $294,040.00 -10
12763 MIDDLETON PIKE
Wood
BOWLING GREEN OH, 43402
LASH PAVING INC 5 $10,134,000.00 $9,869,643.45 -3
P O BOX 296
Belmont
COLERAIN OH, 43916
LINKEL COMPANY 5 $3,471,000.00 $3,708,941.13 +7
1081 MORRIS RD
BATESVILLE IN, 47006
M & B ASPHALT CO INC 2 $3,317,000.00 $2,937,559.20 -11
1525 WEST COUNTY RD #42
P O BOX 240
Seneca
TIFFIN OH, 44883
M P DORY CO 8 $4,002,000.01 $3,963,118.63 -1
2001 INTEGRITY DR SOUTH
Franklin
COLUMBUS OH, 43209
MARK HAYNES CONSTRUCTION INC 3 $7,220,000.00 $6,876,977.05 -5
3130 ST RT 18 E
Huron
NORWALK OH, 44857
MARUCCI & GAFFNEY EXCAVATING CO 4 $3,131,000.01 $2,951,821.15 -6
18 HOGUE ST
Mahoning
YOUNGSTOWN OH, 44502
MCVOYT CONSTRUCTION COMPANY INC 1 $85,000.00 $67,561.55 -21
1840 EAST HOOPPOLE RIDGE RD
Morgan
MCCONNELSVILLE OH, 43756
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
16 | P a g e
MELWAY PAVING CO INC 1 $3,600,000.00 $4,043,318.20 +12
7571 ST RT 83
Holmes
HOLMESVILLE OH, 44633
MERCIER'S INC 4 $560,000.00 $494,930.32 -12
7442 SHIPLEY AVENUE
HARMANS MD, 21077
MIDWEST CONTRACTING INC 2 $351,000.00 $316,201.59 -10
1428 ALBON RD
Lucas
HOLLAND OH, 43528
MILLER BROS CONST INC 3 $12,911,900.00 $11,317,835.54 -12
1613 S DEFIANCE ST, P O Box 30
Fulton
ARCHBOLD OH, 43502
MILLER CABLE COMPANY 6 $2,846,004.00 $2,423,865.00 -15
210 S BROADWAY ST P O BOX 68
Seneca
GREEN SPRINGS OH, 44836
MILLER YOUNT PAVING INC 1 $204,000.00 $168,778.00 -17
522 PERKINS JONES RD
Trumbull
WARREN OH, 44483
MOSSER CONSTRUCTION INC 4 $23,724,858.00 $21,438,587.29 -10
122 S WILSON AVE
Sandusky
FREMONT OH, 43420
MR EXCAVATOR INC 2 $550,000.00 $472,850.81 -14
8616 EUCLID CHARDON RD
Lake
KIRTLAND OH, 44094
NEWTON ASPHALT PAVING INC 1 $814,000.00 $723,558.20 -11
8344 CENTRAL RD NW
Tuscarawas
STRASBURG OH, 44680
NORTHSTAR ASPHALT INC 3 $4,442,000.00 $4,398,304.19 -1
P O BOX 2646
Stark
NORTH CANTON OH, 44720
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
17 | P a g e
OBERLANDER'S TREE & LANDSCAPE LTD 1 $177,000.00 $162,775.00 -8
1874 EAST MANSFIELD ST
Crawford
BUCYRUS OH, 44820
OGLESBY CONSTRUCTION INC 7 $8,607,000.00 $8,290,950.16 -4
1600 TOLEDO RD
Huron
NORWALK OH, 44857
OHIO-WEST VIRGINIA EXCAVATING CO 3 $1,293,000.00 $1,015,418.61 -21
56461 FERRY LANDING ROAD
P O BOX 128
Belmont
SHADYSIDE OH, 43947
PAGE EXCAVATING INC 6 $1,120,000.00 $876,402.76 -22
2398 APPLEGATE RD
Richland
LUCAS OH, 44843
PARELLA-PANNUNZIO INC 1 $1,050,000.00 $1,091,901.20 +4
720 NORTH MERIDIAN RD
Mahoning
YOUNGSTOWN OH, 44509
PARK ENTERPRISE CONSTRUCTION CO INC 1 $2,200,000.00 $2,235,830.57 +2
560 BARKS RD W
Marion
MARION OH, 43302
PARKER CORPORATION 6 $2,806,000.00 $2,131,400.92 -24
ST RT 7
Meigs
TUPPERS PLAINS OH, 45783
PARNELL & ASSOCIATES INC 1 $63,000.00 $67,863.50 +8
P O BOX 217 143 N 7TH STREET
Guernsey
CAMBRIDGE OH, 43725
PDK CONSTRUCTION INC 3 $1,190,000.01 $984,599.02 -17
34070 CREW RD P O BOX 683
Meigs
POMEROY OH, 45769
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
18 | P a g e
PERK COMPANY INC 2 $5,536,000.00 $5,811,612.43 +5
8100 GRAND AVE SUITE 300
Cuyahoga
CLEVELAND OH, 44104-3110
PERRAM ELECTRIC INC 7 $3,918,350.00 $3,951,112.00 +1
6882 RIDGE RD
Medina
WADSWORTH OH, 44281
PINNACLE PROPERTY MAINTENANCE 1 $256,000.00 $221,773.00 -13
3141 SILVER DR
Franklin
COLUMBUS OH, 43224
PRUS CONSTRUCTION COMPANY 1 $209,000.00 $132,855.30 -36
5325 WOOSTER RD
Hamilton
CINCINNATI OH, 45226
R & I CONSTRUCTION INC 3 $2,114,000.00 $2,048,107.22 -3
2931 STATE ROUTE 67 SOUTH
Seneca
TIFFIN OH, 44883
R B JERGENS CONTRACTORS INC 3 $3,909,000.00 $3,686,387.31 -6
11418 N DIXIE DR
Montgomery
VANDALIA OH, 45377
R C CONSTRUCTION COMPANY AND SON INC 2 $261,000.00 $210,797.00 -19
8096 FEDERAL ROAD
Washington
CUTLER OH, 45724
R F SCURLOCK CO 1 $1,995,000.00 $1,635,109.87 -18
3220 FIFTH STREET P O BOX 308
Muskingum
TRINWAY OH, 43842-0335
R G ZACHRICH CONSTRUCTION INC 1 $319,000.00 $302,267.00 -5
10105 HALLER ST
Defiance
DEFIANCE OH, 43512
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
19 | P a g e
R J RUNGE CO 1 $708,000.00 $547,415.00 -23
PO BOX 977
P O BOX 977
Ottawa
PORT CLINTON OH, 43452
R T VERNAL PAVING CO INC 1 $1,001,000.00 $901,743.67 -10
11299 SOUTH AVE EXTENSION PO BOX 519
Mahoning
NORTH LIMA OH, 44452-0519
R W ROBINSON INC 3 $915,000.00 $884,870.61 -3
87 EAST STATE
P O BOX 325
Richland
BELLVILLE OH, 44813
RACK & BALLAUER EXCAVATING CO INC 1 $117,000.00 $109,244.00 -7
11321 PADDY'S RUN RD
Butler
HAMILTON OH, 45013
RATZLAFF CONSTRUCTION COMPANY INC 1 $531,000.00 $464,716.71 -12
41 GRABILL COURT
Ross
CHILLICOTHE OH, 45601
RELIANT ENTERPRISES LLC 1 $1,365,000.00 $1,635,127.75 +20
3364 SNEAKVILLE RD
LAWRENCEBURG IN, 47025
RIDGE ELECTRIC CO INC 1 $344,000.00 $358,175.00 +4
3323 MAGNOLIA RD NW
Stark
MAGNOLIA OH, 44643
RIETSCHLIN CONSTRUCTION INC 4 $2,486,000.00 $2,394,954.92 -4
4240 BAKER RD
Crawford
CRESTLINE OH, 44827
RIGHTER COMPANY INC 3 $1,099,000.00 $1,136,247.17 +3
2424 HARRISON RD
Franklin
COLUMBUS OH, 43204
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
20 | P a g e
ROADWAY SERVICES INC 1 $187,000.00 $150,962.73 -19
9-072 US 24
P O BOX 607
Henry
NAPOLEON OH, 43545
ROBERTS PAVING INC 1 $2,475,000.00 $2,053,562.93 -17
4354 WILDCAT RD
Highland
HILLSBORO OH, 45133
RUDZIK EXCAVATING INC 1 $854,000.00 $690,640.00 -19
401 LOWELLVILLE RD
P O BOX 206
Mahoning
STRUTHERS OH, 44471
RUHLIN COMPANY 3 $32,006,000.00 $28,059,408.94 -12
P O BOX 190
Medina
SHARON CENTER OH, 44274
RUHLIN/IGEL US 23 - JV 1 $73,984,500.00 $71,462,914.41 -3
6931 RIDGE RD
Medina
SHARON CENTER OH, 44274-
S R W ENVIRONMENTAL SERVICES INC 1 $110,000.00 $87,930.00 -20
55 WEST TECHNECENTER DR STE C
Clermont
MILFORD OH, 45150
SAND RIDGE EXCAVATING 1 $705,000.00 $711,071.79 +1
20251 ROAD I-17
Putnam
CLOVERDALE OH, 45827
SCHALK BROTHERS INC 2 $665,000.00 $563,988.90 -15
3481 NORTH TWP RD 69
Seneca
TIFFIN OH, 44883
SCODELLER CONSTRUCTION INC 6 $2,668,000.00 $1,853,286.42 -31
51722 GRAND RIVER AVE
WIXOM MI, 48393-2303
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
21 | P a g e
SHAW & HOLTER INC 1 $1,067,000.00 $922,289.41 -14
2625 COONPATH RD NE
Fairfield
LANCASTER OH, 43130-8868
SHELDON GANTT INC 1 $424,000.00 $317,723.50 -25
1500 NORTH MAIN ST
Trumbull
NILES OH, 44446
SHELLY & SANDS INC 97 $229,979,209.21 $226,215,496.25 -2
1515 HARMON AVE
Franklin
COLUMBUS OH, 43223
SHELLY COMPANY 51 $137,295,300.06 $140,309,245.95 +2
80 PARK DR BOX 266
Perry
THORNVILLE OH, 43076
SITETECH INC 1 $134,000.00 $122,734.00 -8
35700 EAST ROYALTON RD
Lorain
GRAFTON OH, 44044
SMITH PAVING & EXCAVATING INC 1 $2,747,407.00 $2,801,715.25 +2
4426 N OLD STATE RD
Huron
NORWALK OH, 44857
SPECIALIZED CONSTRUCTION INC 1 $1,126,000.00 $1,207,983.10 +7
711 HARVARD AVE
Cuyahoga
CUYAHOGA HEIGHTS OH, 44105
SPIEKER CO 1 $2,015,000.00 $1,687,101.00 -16
8350 FREMONT PIKE
Wood
PERRYSBURG OH, 43551
STANLEY MILLER CONSTRUCTION COMPANY 2 $1,059,000.00 $916,328.94 -13
2250 HOWENSTINE DR SE
Stark
EAST SPARTA OH, 44626
STRAWSER CONSTRUCTION INC 6 $7,786,000.00 $7,309,389.34 -6
1595 FRANK RD
Franklin
COLUMBUS OH, 43223
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
22 | P a g e
STRAWSER PAVING CO INC 1 $930,000.00 $879,399.04 -5
1595 FRANK RD
Franklin
COLUMBUS OH, 43223
SUBURBAN MAINTENANCE & CONSTRUCTION INC 3 $901,000.00 $905,743.00 +1
16330 YORK RD
Cuyahoga
NORTH ROYALTON OH, 44133
SUNESIS CONSTRUCTION CO 6 $12,620,160.00 $12,070,006.26 -4
2610 CRESCENTVILLE RD
Butler
WEST CHESTER OH, 45069
SUPERIOR PAVING & MATERIALS INC 3 $5,382,000.00 $4,969,629.12 -8
5945 WHIPPLE AVE NW
Stark
NORTH CANTON OH, 44720
TERRACE CONSTRUCTION CO INC 4 $9,882,400.00 $10,287,904.29 +4
3965 PEARL RD
Cuyahoga
CLEVELAND OH, 44109
THOMPSON INTERSTATE MOWING INC 1 $559,000.02 $471,164.65 -16
12878 ST RT 62 N
Highland
LEESBURG OH, 45135
TOM MAYLE & SONS CONSTRUCTION INC 3 $1,627,000.00 $1,730,626.80 +6
P O BOX 151
Washington
BARTLETT OH, 45713
TOWNSEND TREE SERVICE COMPANY LLC 1 $133,000.00 $106,012.44 -20
101 SOUTH MAIN ST
PARKER CITY IN, 47368-0128
TRAFFTECH INC 1 $279,000.00 $258,812.00 -7
7000 HUBBARD AVE
Cuyahoga
CLEVELAND OH, 44127
TRUCCO CONSTRUCTION CO INC 4 $10,169,390.00 $9,284,042.96 -9
3531 AIRPORT RD
Delaware
DELAWARE OH, 43015
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
23 | P a g e
TRUMBULL-GREAT LAKES-RUHLIN - JV 1 $292,417,000.00 $272,986,001.00 -7
P O BOX 6774
PITTSBURGH PA, 15212-
TUCSON INC 2 $1,347,000.00 $1,146,983.86 -15
3497 UNIVERSITY DR NE
Tuscarawas
NEW PHILADELPHIA OH, 44663
U S UTILITY CONTRACTOR COMPANY 1 $65,000.00 $43,280.00 -33
3592 GENOA RD
Wood
PERRYSBURG OH, 43551
UNILLIANCE INC 1 $125,000.00 $96,754.50 -23
3346 S FOUR MILE HOUSE RD
Ottawa
OAK HARBOR OH, 43449
UNION INDUSTRIAL CONTRACTORS INC 2 $2,701,000.00 $2,479,191.72 -8
1800 EAST 21ST STREET
P O BOX 1718
Ashtabula
ASHTABULA OH, 44004
V O MENUEZ & SON INC 5 $2,773,000.00 $2,581,677.42 -7
1016 S WASHINGTON ST
Holmes
MILLERSBURG OH, 44654
VAN CUREN SERVICES INC 1 $113,000.00 $116,530.00 +3
P O BOX 91 10555 KINSMAN ROAD
Geauga
NEWBURY OH, 44065-9724
VERNON NAGEL INC 3 $520,000.00 $511,261.00 -2
O-154 CO RD 11-C
Henry
NAPOLEON OH, 43545
VTF EXCAVATING LLC 1 $714,000.00 $647,419.42 -9
8398 CELINA-MENDON RD
Mercer
CELINA OH, 45822
Summary of Contracts Awarded for the Calendar Year 2013 by Contractors
Contractor Contracts Estimated Contract Percent
Awarded Cost Price
24 | P a g e
W G STANG LLC 1 $54,000.00 $53,105.00 -2
2403 JACKSONBURG RD
Butler
HAMILTON OH, 45011
W L MARKERS INC 4 $727,000.00 $663,613.35 -9
2808 FISHER RD
Franklin
COLUMBUS OH, 43204
WALLS BROS ASPHALT CO INC 1 $1,815,000.00 $1,964,995.51 +8
3690 HOLLANSBURG-SAMPSON RD
Darke
GREENVILLE OH, 45331
WARD CONSTRUCTION CO 1 $90,000.00 $64,278.32 -29
385 OAK ST
Putnam
LEIPSIC OH, 45856
WILLIAM M PATTON CO INC 1 $121,000.00 $135,900.00 +12
P O BOX 28165
Franklin
COLUMBUS OH, 43228
ZEMBA BROS INC 1 $690,000.00 $636,206.00 -8
3401 EAST PIKE
Muskingum
ZANESVILLE OH, 43701
Grand total of Contracts Awarded 723 $1,956,615,146.97 $1,871,181,806.14 -4
During Calendar Year
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
25 | P a g e
District 01
ALLEN 4 $128,446,615.18
ALLEN DEFIANCE HANCOCK HARDIN 4 $1,870,546.58
ALLEN DEFIANCE HANCOCK PAULDING 2 $2,117,293.38
ALLEN HANCOCK WYANDOT 1 $243,900.00
ALLEN PAULDING HARDIN HANCOCK 1 $1,295,375.75
ALLEN WYANDOT 1 $154,491.00
DEFIANCE 2 $1,128,415.79
DEFIANCE PAULDING 1 $3,120,817.81
HANCOCK 3 $11,646,700.53
HANCOCK WYANDOT 1 $2,803,469.66
HARDIN 3 $1,542,062.34
PAULDING 1 $58,433.25
PAULDING DEFIANCE WYANDOT HANCOCK 1 $212,016.00
PUTNAM 2 $2,618,450.47
VAN WERT 1 $2,966,768.61
WYANDOT 3 $1,799,705.66
District 01 Total 31 $162,025,062.01
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
26 | P a g e
FULTON 1 $204,240.00
FULTON HENRY LUCAS OTTAWA 2 $1,972,865.61
HENRY 3 $12,977,804.60
HENRY LUCAS 1 $4,255,085.51
HENRY WOOD 1 $2,273,031.49
LUCAS 11 $56,990,841.31
LUCAS OTTAWA 2 $4,448,833.57
LUCAS OTTAWA SANDUSKY WOOD 1 $374,665.00
LUCAS WOOD 1 $262,507.74
LUCAS WOOD HENRY OTTAWA 1 $151,000.00
LUCAS WOOD WILLIAMS 1 $205,923.80
OTTAWA 6 $25,091,697.99
SANDUSKY 3 $3,018,489.93
SENECA 2 $2,887,778.83
WILLIAMS 2 $3,679,248.40
WOOD 11 $6,175,693.19
WOOD LUCAS 3 $9,102,355.90
WOOD SENECA 1 $1,837,157.60
District 02 Total 53 $135,909,220.47
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
27 | P a g e
District 03
ASHLAND 8 $10,170,520.96
ASHLAND CRAWFORD ERIE HURON 6 $1,928,897.01
ASHLAND CRAWFORD RICHLAND WAYNE 1 $659,834.00
ASHLAND HURON 1 $293,734.23
ASHLAND RICHLAND 1 $2,910,515.82
CRAWFORD 5 $2,083,695.90
CRAWFORD RICHLAND HURON LORAIN 1 $1,207,983.10
ERIE 6 $2,699,835.62
ERIE LORAIN 2 $170,208.00
ERIE MEDINA ASHLAND CRAWFORD 1 $584,445.00
HURON 6 $7,063,356.16
LORAIN 10 $22,696,331.66
MEDINA 9 $6,698,030.15
MEDINA LORAIN 1 $132,334.20
RICHLAND 8 $4,976,892.35
RICHLAND ASHLAND 1 $3,092,512.19
WAYNE 5 $5,063,223.96
WAYNE MEDINA 1 $1,931,595.54
District 03 Total 73 $74,363,945.85
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
28 | P a g e
District 04
ASHTABULA 8 $13,383,408.61
ASHTABULA MAHONING PORTAGE STARK 3 $1,190,686.25
ASHTABULA MAHONING TRUMBULL 1 $372,017.00
ASHTABULA TRUMBULL MAHONING STARK 1 $333,627.50
MAHONING 15 $37,228,692.83
MAHONING PORTAGE SUMMIT 1 $286,617.14
MAHONING PORTAGE TRUMBULL 1 $3,037,565.81
MAHONING TRUMBULL 1 $400,066.00
PORTAGE 6 $11,339,419.92
PORTAGE STARK SUMMIT 3 $1,673,811.98
STARK 13 $20,188,943.34
STARK SUMMIT 2 $646,405.86
STARK SUMMIT PORTAGE 1 $436,802.11
SUMMIT 17 $130,132,320.01
SUMMIT STARK 1 $334,367.50
TRUMBULL 13 $25,798,936.62
District 04 Total 87 $246,783,688.48
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
29 | P a g e
District 05
COSHOCTON 3 $1,731,924.53
COSHOCTON FAIRFIELD GUERNSEY KNOX 5 $1,293,873.76
COSHOCTON FAIRFIELD MUSKINGUM 1 $1,299,483.85
COSHOCTON GUERNSEY KNOX 1 $212,000.00
COSHOCTON LICKING GUERNSEY 1 $343,780.00
FAIRFIELD 4 $9,775,574.20
FAIRFIELD GUERNSEY MUSKINGUM PERRY 1 $162,150.08
FAIRFIELD LICKING 3 $8,781,144.46
FAIRFIELD LICKING MUSKINGUM PERRY 1 $368,977.40
FAIRFIELD PERRY 1 $4,548,980.05
GUERNSEY 8 $13,707,508.70
KNOX 5 $6,513,379.03
LICKING 15 $32,718,041.03
MUSKINGUM 6 $8,054,155.14
MUSKINGUM GUERNSEY COSHOCTON LICKING 1 $909,295.15
PERRY 2 $2,020,512.71
District 05 Total 58 $92,440,780.09
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
30 | P a g e
District 06
DELAWARE 5 $7,094,152.30
DELAWARE FAYETTE FRANKLIN MADISON 1 $2,272,272.00
DELAWARE FAYETTE MADISON MARION 1 $176,988.38
DELAWARE FRANKLIN 1 $479,562.61
DELAWARE FRANKLIN MADISON UNION 1 $402,040.60
DELAWARE MARION MORROW PICKAWAY 1 $379,728.75
DELAWARE MARION MORROW UNION 1 $195,000.00
DELAWARE MORROW 1 $451,632.36
DELAWARE UNION 1 $1,590,358.66
FAYETTE FRANKLIN MADISON MORROW 1 $762,301.79
FRANKLIN 27 $162,050,000.55
FRANKLIN DELAWARE 1 $3,858,796.35
FRANKLIN DELAWARE UNION MADISON 1 $707,337.00
FRANKLIN FAYETTE 1 $1,090,333.05
FRANKLIN MARION UNION 1 $1,335,683.50
FRANKLIN PICKAWAY 1 $2,604,419.35
MADISON 4 $4,055,888.02
MARION 5 $6,187,716.22
MORROW 1 $51,800,000.00
PICKAWAY 4 $9,166,981.05
UNION 5 $6,628,202.39
District 06 Total 65 $263,289,394.93
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
31 | P a g e
District 07
AUGLAIZE 9 $12,112,373.49
AUGLAIZE CHAMPAIGN CLARK DARKE 3 $1,386,892.00
AUGLAIZE CHAMPAIGN LOGAN MERCER 1 $1,606,030.01
AUGLAIZE CLARK LOGAN MIAMI 1 $244,812.00
AUGLAIZE LOGAN MERCER MIAMI 1 $471,164.65
CHAMPAIGN 4 $2,801,765.59
CLARK 4 $4,673,154.75
CLARK LOGAN MIAMI MONTGOMERY 1 $674,375.00
CLARK MIAMI MONTGOMERY 2 $434,512.00
DARKE 3 $3,877,821.33
LOGAN 3 $3,019,366.91
MERCER 3 $1,219,739.30
MIAMI 9 $8,731,549.76
MIAMI SHELBY 1 $758,910.00
MONTGOMERY 13 $63,050,957.94
MONTGOMERY CLARK MIAMI 1 $546,788.97
MONTGOMERY MERCER DARKE MIAMI 1 $125,125.00
SHELBY 3 $2,495,040.00
SHELBY MIAMI LOGAN MERCER 1 $106,012.44
District 07 Total 64 $108,336,391.14
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
32 | P a g e
District 08
BUTLER 6 $1,084,847.37
BUTLER CLERMONT CLINTON GREENE 2 $3,774,394.77
BUTLER GREENE PREBLE 1 $676,969.13
BUTLER WARREN 1 $947,875.00
CLERMONT 6 $47,168,236.12
CLERMONT HAMILTON 1 $217,836.15
CLINTON 3 $13,106,747.07
CLINTON WARREN 1 $1,398,269.81
GREENE 5 $18,545,524.04
GREENE HAMILTON 1 $720,051.89
GREENE WARREN 1 $13,851,867.55
HAMILTON 16 $57,992,136.67
HAMILTON BUTLER PREBLE GREENE 1 $1,635,127.75
HAMILTON WARREN 2 $8,998,705.07
PREBLE 2 $940,614.97
WARREN 5 $3,329,988.12
WARREN PREBLE BUTLER HAMILTON 1 $2,044,665.00
District 08 Total 55 $176,433,856.48
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
33 | P a g e
District 09
ADAMS 4 $2,551,456.69
ADAMS BROWN HIGHLAND JACKSON 3 $1,584,798.12
ADAMS BROWN HIGHLAND LAWRENCE 1 $1,417,120.00
ADAMS BROWN HIGHLAND PIKE 1 $98,428.36
BROWN 8 $4,378,400.22
BROWN ADAMS HIGHLAND ROSS 1 $1,569,347.20
BROWN HIGHLAND ADAMS PIKE 1 $782,987.08
BROWN HIGHLAND ROSS SCIOTO 1 $874,998.43
HIGHLAND 5 $2,829,304.81
JACKSON 2 $3,677,989.10
LAWRENCE 7 $3,173,223.50
PIKE 7 $4,905,642.27
PIKE ROSS 1 $147,700.00
ROSS 6 $4,715,275.70
ROSS PIKE 2 $5,345,140.40
ROSS SCIOTO 1 $586,699.88
SCIOTO 6 $5,784,381.80
SCIOTO LAWRENCE 1 $3,274,741.05
District 09 Total 58 $47,697,634.61
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
34 | P a g e
District 10
ATHENS 10 $10,250,964.43
ATHENS GALLIA HOCKING MEIGS 4 $2,201,012.65
ATHENS GALLIA NOBLE WASHINGTON 1 $285,892.85
ATHENS HOCKING 1 $1,744,132.20
ATHENS MORGAN 1 $1,569,286.30
GALLIA 4 $2,280,297.65
HOCKING 5 $6,702,870.59
MEIGS 6 $2,857,201.44
MEIGS ATHENS 1 $554,192.95
MEIGS VINTON 1 $974,644.71
MONROE 5 $4,460,123.88
MONROE NOBLE WASHINGTON 1 $1,041,174.26
MORGAN 3 $1,189,860.40
MORGAN WASHINGTON 1 $1,718,281.69
NOBLE 2 $1,534,169.36
NOBLE MORGAN ATHENS WASHINGTON 1 $537,475.00
VINTON 5 $1,303,228.60
VINTON ATHENS 1 $2,316,699.90
WASHINGTON 12 $5,931,848.49
WASHINGTON ATHENS GALLIA MEIGS 1 $369,945.00
District 10 Total 66 $49,823,302.35
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
35 | P a g e
District 11
BELMONT 13 $21,879,115.97
BELMONT CARROLL COLUMBIANA HARRISON 3 $3,018,814.09
BELMONT CARROLL HARRISON 1 $183,558.25
BELMONT COLUMBIANA HARRISON HOLMES 1 $358,175.00
BELMONT COLUMBIANA HOLMES JEFFERSON 1 $617,709.28
CARROLL HARRISON 1 $1,360,513.88
COLUMBIANA 13 $15,825,413.43
HARRISON 6 $6,491,020.48
HOLMES 4 $5,708,755.74
HOLMES TUSCARAWAS CARROLL COLUMBIANA 1 $91,444.00
JEFFERSON 4 $6,060,510.81
JEFFERSON HARRISON BELMONT 1 $99,358.37
TUSCARAWAS 10 $17,133,542.00
District 11 Total 59 $78,827,931.30
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
36 | P a g e
District 12
CUYAHOGA 28 $384,827,557.35
CUYAHOGA GEAUGA LAKE 3 $3,875,240.10
CUYAHOGA LAKE 3 $4,739,495.25
CUYAHOGA LAKE GEAUGA 1 $258,812.00
GEAUGA 5 $25,085,668.59
LAKE 4 $5,781,681.16
District 12 Total 44 $424,568,454.45
Summary of Total Contracts
Awarded for the Calendar Year 2013 by District and County
37 | P a g e
Multiple Districts
Dist County Number of Projects Total Contract Amount
01 DEFIANCE 1 $150,962.73
10 WASHINGTON
03 ASHLAND 1 $786,965.06
04 ASHTABULA MAHONING STARK
05 COSHOCTON 1 $2,864,747.18
11 HOLMES
05 COSHOCTON LICKING 1 $246,690.00
11 BELMONT JEFFERSON
05 FAIRFIELD PERRY 1 $3,884,935.25
10 HOCKING
05 GUERNSEY 1 $397,379.76
11 BELMONT CARROLL TUSCARAWAS
05 LICKING 1 $636,206.00
07 CLARK
05 LICKING 1 $373,484.70
12 CUYAHOGA
07 CHAMPAIGN CLARK 1 $1,225,174.30
08 BUTLER CLERMONT
09 ROSS LAWRENCE PIKE 1 $115,599.00
10 GALLIA
Multiple District Total 10 $10,682,143.98
Grand Total of Contracts Awarded During Calendar Year 723 $1,871,181,806.14
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
38 | P a g e
100E00300 70.000 LS SPECIAL - PREMIUM ON RAILROADS' 15,559.4584 10,778.1960 $754,473.72
PROTECTIVE PUBLIC LIABILITY AND PROPERTY
DAMAGE LIABILITY INSURANCE
100E50000 6.000 LS SPECIAL - DISPUTE REVIEW BOARD 106,400.0000 107,900.0000 $647,400.00
100E50200 2.000 LS SPECIAL - DEPARTMENT'S SHARE OF THE 35,000.0000 35,000.0000 $70,000.00
DISPUTE RESOLUTION ADVISOR
100E99010 21.000 LS SPECIAL - PROFESSIONAL LIABILITY 5,648.7397 4,454.5714 $93,546.00
INSURANCE
103E05000 696.000 LS PREMIUM FOR CONTRACT PERFORMANCE BOND 14,694.5382 13,001.1281 $9,048,785.19
AND FOR PAYMENT BOND
103E06000 3.000 LS PREMIUM FOR CONTRACT PERFORMANCE BOND, 323,505.7392 136,500.0000 $409,500.00
PAYMENT BOND AND MAINTENANCE BOND
103E99010 23.000 LS SPECIAL - PREMIUM FOR CONTRACT 57,029.7322 62,375.1426 $1,434,628.28
PERFORMANCE BOND AND FOR PAYMENT BOND
107E99000 16.000 LS SPECIAL - UTILITY COORDINATION 6,180.5529 6,143.7500 $98,300.00
108E10000 37.000 LS SPECIAL - CPM PROGRESS SCHEDULE 12,165.5611 8,052.8911 $297,956.97
108E30000 49.000 LS SPECIAL - CPM PROGRESS SCHEDULE SHORT 3,308.3179 2,488.7478 $121,948.64
DURATION PROJECTS
108E99000 14.000 LS SPECIAL - CPM PROGRESS SCHEDULE 9,828.2166 7,416.1136 $103,825.59
108E99100 6.000 LS SPECIAL - CPM PROGRESS SCHEDULE FOR 3,171.6557 3,400.0000 $20,400.00
SHORT DURATION PROJECTS
111E10000 6.000 LS SPECIAL - DEPARTMENTS SHARE FACILITATED 11,750.0000 11,958.3333 $71,750.00
PARTNERING COSTS
201E11000 405.000 LS CLEARING AND GRUBBING 12,681.3896 11,073.6179 $4,484,815.24
201E11001 38.000 LS CLEARING AND GRUBBING, AS PER PLAN 37,131.3124 32,646.2524 $1,240,557.59
201E21800 20.000 EACH TREE REMOVED, 18" SIZE 699.6713 548.3000 $10,966.00
201E21801 190.000 EACH TREE REMOVED, 18" SIZE, AS PER PLAN 407.4211 362.2105 $68,820.00
201E23000 21.000 EACH TREE REMOVED, 30" SIZE 1,166.7191 747.4286 $15,696.00
201E23001 37.000 EACH TREE REMOVED, 30" SIZE, AS PER PLAN 741.1486 687.4324 $25,435.00
201E24800 3.000 EACH TREE REMOVED, 48" SIZE 1,864.4286 958.6667 $2,876.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
39 | P a g e
201E24801 10.000 EACH TREE REMOVED, 48" SIZE, AS PER PLAN 1,153.7500 1,047.5000 $10,475.00
201E26001 4.000 EACH TREE REMOVED, 60" SIZE, AS PER PLAN 2,421.2500 2,387.5000 $9,550.00
201E26510 1.000 EACH STUMP REMOVED, 30" SIZE 536.0000 105.0000 $105.00
201E26533 40.000 EACH STUMP REMOVED, AS PER PLAN 293.4375 286.8750 $11,475.00
201E99000 22.000 LS SPECIAL - CLEARING AND GRUBBING 19,277.2293 16,849.0655 $370,679.44
202E11000 57.000 LS STRUCTURE REMOVED 14,778.5792 12,334.2218 $703,050.64
202E11001 11.000 LS STRUCTURE REMOVED, AS PER PLAN 76,398.4706 64,400.2182 $708,402.40
202E11002 28.000 LS STRUCTURE REMOVED, OVER 20 FOOT SPAN 94,949.7856 84,115.4539 $2,355,232.71
202E11003 33.000 LS STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS 137,272.4238 150,960.8788 $4,981,709.00
PER PLAN
202E11004 8.000 EACH STRUCTURE REMOVED 1,260.5173 1,200.3813 $9,603.05
202E11200 11.000 LS PORTIONS OF STRUCTURE REMOVED 5,685.1912 5,906.0836 $64,966.92
202E11201 44.000 LS PORTIONS OF STRUCTURE REMOVED, AS PER 109,186.7969 71,029.7200 $3,125,307.68
PLAN
202E11203 129.000 LS PORTIONS OF STRUCTURE REMOVED, OVER 20 122,406.1179 83,088.0013 $10,718,352.17
FOOT SPAN, AS PER PLAN
202E11301 799.900 CY PORTIONS OF STRUCTURE REMOVED, AS PER 824.2167 973.7638 $778,913.63
PLAN
202E11304 0.300 SY PORTIONS OF STRUCTURE REMOVED 2,383.3333 3,000.0000 $900.00
202E11305 8,067.000 SY PORTIONS OF STRUCTURE REMOVED, AS PER 252.8985 384.8017 $3,104,195.00
PLAN
202E11401 1,127.000 LB PORTIONS OF STRUCTURE REMOVED, AS PER 11.5042 9.4474 $10,647.24
PLAN
202E11501 49.000 EACH PORTIONS OF STRUCTURE REMOVED, AS PER 757.3897 338.9584 $16,608.96
PLAN
202E20010 424.000 EACH HEADWALL REMOVED 255.9120 238.5177 $101,131.49
202E20011 4.000 EACH HEADWALL REMOVED, AS PER PLAN 1,213.7990 575.0000 $2,300.00
202E22900 23,559.000 SY APPROACH SLAB REMOVED 29.3994 27.0616 $637,545.31
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
40 | P a g e
202E22901 1,294.000 SY APPROACH SLAB REMOVED, AS PER PLAN 59.5389 32.3447 $41,854.00
202E23000 1,206,164.000 SY PAVEMENT REMOVED 7.1655 7.0151 $8,461,342.80
202E23001 90,267.000 SY PAVEMENT REMOVED, AS PER PLAN 10.7008 8.6397 $779,882.15
202E23010 370,759.900 SY PAVEMENT REMOVED, ASPHALT 5.1829 4.1883 $1,552,863.96
202E23011 9,773.000 SY PAVEMENT REMOVED, ASPHALT, AS PER PLAN 4.6993 7.2527 $70,881.12
202E23500 377,878.000 SY WEARING COURSE REMOVED 4.7358 4.3564 $1,646,203.96
202E23501 23,335.000 SY WEARING COURSE REMOVED, AS PER PLAN 8.7278 8.0254 $187,273.69
202E23800 2,966.000 SY BASE REMOVED 5.6289 5.5998 $16,609.00
202E23801 1,640.000 SY BASE REMOVED, AS PER PLAN 30.0875 35.0000 $57,400.00
202E23900 9,114.000 SY CONCRETE BASE REMOVED 8.0950 7.0020 $63,816.00
202E24001 237.000 SY BRICK BASE REMOVED, AS PER PLAN 8.4000 10.0000 $2,370.00
202E30000 464,790.500 SF WALK REMOVED 1.7186 1.7378 $807,712.99
202E30001 104,665.000 SF WALK REMOVED, AS PER PLAN 1.3193 1.1475 $120,102.52
202E30200 48.000 FT STEPS REMOVED 34.9168 39.6333 $1,902.40
202E30204 2.000 LS STEPS REMOVED 678.7611 150.0000 $300.00
202E30500 2,121.000 FT CONCRETE MEDIAN REMOVED 5.9772 6.0371 $12,804.60
202E30600 7,422.000 SY CONCRETE MEDIAN REMOVED 12.3921 11.3534 $84,265.16
202E30601 348.000 SY CONCRETE MEDIAN REMOVED, AS PER PLAN 25.0000 25.0000 $8,700.00
202E30700 51,497.000 FT CONCRETE BARRIER REMOVED 11.4769 11.6321 $599,017.32
202E30701 1,668.000 FT CONCRETE BARRIER REMOVED, AS PER PLAN 38.4716 20.5755 $34,320.00
202E30704 546.000 FT CONCRETE BARRIER REMOVED FOR STORAGE 7.2983 3.0000 $1,638.00
202E30800 2,230.000 SY TRAFFIC ISLAND REMOVED 12.6845 11.1365 $24,834.33
202E30801 306.000 SY TRAFFIC ISLAND REMOVED, AS PER PLAN 12.8833 9.5000 $2,907.00
202E30900 3.000 SY PORTION OF TRAFFIC ISLAND REMOVED 72.7278 75.0000 $225.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
41 | P a g e
202E32000 151,612.000 FT CURB REMOVED 3.8046 4.2898 $650,385.80
202E32001 8,710.000 FT CURB REMOVED, AS PER PLAN 6.3616 7.1350 $62,145.95
202E32300 507.000 FT GRANITE CURB REMOVED FOR REUSE 15.0000 15.0000 $7,605.00
202E32500 39,935.000 FT CURB AND GUTTER REMOVED 4.3501 4.3920 $175,396.26
202E32501 776.000 FT CURB AND GUTTER REMOVED, AS PER PLAN 19.9565 19.3711 $15,032.00
202E32600 877.000 FT GUTTER REMOVED 5.0876 5.0738 $4,449.70
202E32700 605.000 SY GUTTER REMOVED 13.4036 13.5105 $8,173.85
202E32800 3,028.000 SY CONCRETE SLOPE PROTECTION REMOVED 19.8979 17.6368 $53,404.29
202E34900 3,757.000 FT PIPE REMOVED 11.7877 15.9449 $59,905.10
202E35100 125,351.000 FT PIPE REMOVED, 24" AND UNDER 11.2618 10.4770 $1,313,301.56
202E35101 23,017.000 FT PIPE REMOVED, 24" AND UNDER, AS PER PLAN 13.3935 7.8279 $180,175.00
202E35200 14,633.000 FT PIPE REMOVED, OVER 24" 27.0756 21.8014 $319,020.00
202E35201 273.000 FT PIPE REMOVED, OVER 24", AS PER PLAN 75.3320 42.1538 $11,508.00
202E35700 44.000 FT ASBESTOS PIPE REMOVED 61.8786 23.8409 $1,049.00
202E38000 626,157.750 FT GUARDRAIL REMOVED 1.4631 1.2288 $769,417.63
202E38001 76,581.750 FT GUARDRAIL REMOVED, AS PER PLAN 1.6892 1.4924 $114,286.90
202E38100 7,444.500 FT GUARDRAIL REMOVED FOR STORAGE 1.8179 1.7325 $12,897.40
202E38101 39,390.500 FT GUARDRAIL REMOVED FOR STORAGE, AS PER 2.0240 1.6405 $64,620.01
PLAN
202E38200 18,386.000 FT GUARDRAIL REMOVED FOR REUSE 1.9810 1.7985 $33,066.75
202E38201 43,471.000 FT GUARDRAIL REMOVED FOR REUSE, AS PER PLAN 2.1783 1.5587 $67,759.10
202E38300 3,894.500 FT GUARDRAIL REMOVED, BARRIER DESIGN 1.5133 1.6557 $6,448.00
202E38401 1,881.000 FT GUARDRAIL REMOVED FOR STORAGE, BARRIER 2.9211 2.6475 $4,980.04
DESIGN, AS PER PLAN
202E38500 4,285.500 FT BRIDGE RAILING REMOVED 6.4860 8.0981 $34,704.50
202E38501 225.000 FT BRIDGE RAILING REMOVED, AS PER PLAN 5.4333 2.8000 $630.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
42 | P a g e
202E38601 544.000 FT BRIDGE RAILING REMOVED FOR STORAGE, AS 8.2333 5.0000 $2,720.00
PER PLAN
202E38602 100.000 FT BRIDGE RAILING REMOVED FOR REUSE 33.3333 23.0000 $2,300.00
202E38603 7,309.000 FT BRIDGE RAILING REMOVED FOR REUSE, AS PER 32.3923 25.3951 $185,613.00
PLAN
202E38700 1,139.000 EACH GUARDRAIL POST REMOVED 6.5544 3.5808 $4,078.50
202E38800 29.000 EACH GUARD POST REMOVED 26.1411 31.4828 $913.00
202E42000 563.000 EACH ANCHOR ASSEMBLY REMOVED, TYPE A 204.6009 205.5352 $115,716.30
202E42001 320.500 EACH ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER 264.7105 220.7644 $70,755.00
PLAN
202E42010 69.000 EACH ANCHOR ASSEMBLY REMOVED, TYPE E 160.7015 149.7580 $10,333.30
202E42011 35.000 EACH ANCHOR ASSEMBLY REMOVED, TYPE E, AS PER 175.0000 150.0000 $5,250.00
PLAN
202E42040 175.000 EACH ANCHOR ASSEMBLY REMOVED, TYPE T 79.7628 76.7497 $13,431.20
202E42041 21.000 EACH ANCHOR ASSEMBLY REMOVED, TYPE T, AS PER 77.5000 75.0000 $1,575.00
PLAN
202E42050 41.000 EACH ANCHOR ASSEMBLY REMOVED, TYPE B 134.9046 137.4390 $5,635.00
202E42206 1,031.000 EACH ANCHOR ASSEMBLY REMOVED 168.1826 168.3515 $173,570.42
202E42210 22.000 EACH ANCHOR ASSEMBLY REMOVED, BARRIER DESIGN 218.0435 217.9545 $4,795.00
202E42301 67.000 EACH ANCHOR ASSEMBLY REMOVED FOR STORAGE, 237.5000 250.0000 $16,750.00
TYPE A, AS PER PLAN
202E42310 21.000 EACH ANCHOR ASSEMBLY REMOVED FOR STORAGE, 872.5000 895.0000 $18,795.00
BARRIER DESIGN, TYPE A
202E42509 20.000 EACH ANCHOR ASSEMBLY REMOVED FOR STORAGE, AS 210.8417 220.0460 $4,400.92
PER PLAN
202E42600 2.000 EACH ANCHOR ASSEMBLY REMOVED FOR REUSE, TYPE 257.5000 250.0000 $500.00
A
202E42620 1.000 EACH ANCHOR ASSEMBLY REMOVED FOR REUSE, TYPE 416.0833 236.5000 $236.50
E-98
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
43 | P a g e
202E42807 50.000 EACH ANCHOR ASSEMBLY REMOVED FOR REUSE, AS 83.3333 50.0000 $2,500.00
PER PLAN
202E42810 7.000 EACH ANCHOR ASSEMBLY REMOVED FOR REUSE, TYPE 290.0465 194.2857 $1,360.00
E
202E42812 27.000 EACH ANCHOR ASSEMBLY REMOVED FOR STORAGE, 174.1667 175.0000 $4,725.00
TYPE E
202E43001 6.000 EACH ANCHOR ASSEMBLY POST REMOVED, AS PER 55.0000 75.0000 $450.00
PLAN
202E47000 442.000 EACH BRIDGE TERMINAL ASSEMBLY REMOVED 81.6629 75.8778 $33,538.00
202E47100 4.000 EACH BRIDGE TERMINAL ASSEMBLY REMOVED FOR 108.3717 100.2300 $400.92
STORAGE
202E47200 7.000 EACH BRIDGE TERMINAL ASSEMBLY REMOVED FOR 104.3686 75.4457 $528.12
REUSE
202E47201 8.000 EACH BRIDGE TERMINAL ASSEMBLY REMOVED FOR 662.8600 984.3000 $7,874.40
REUSE, AS PER PLAN
202E47800 9.000 EACH IMPACT ATTENUATOR REMOVED 350.4181 253.3333 $2,280.00
202E48000 6,525.000 FT CABLE BARRIER REMOVED 1.6156 1.6935 $11,050.00
202E52990 216.000 EACH SPECIAL - PARKING BLOCK REMOVED 28.6849 20.4008 $4,406.57
202E53000 19.000 EACH SPECIAL - PARKING BLOCK REMOVED AND 89.0400 90.0000 $1,710.00
REPLACED
202E53010 1,006.000 EACH SPECIAL - PARKING BLOCK REMOVED AND 47.6175 50.6680 $50,972.00
RESET
202E53100 75.000 EACH MAILBOX REMOVED 43.3938 46.3244 $3,474.33
202E53101 1.000 EACH MAILBOX REMOVED, AS PER PLAN 212.7500 130.0000 $130.00
202E56000 59.000 LS BUILDING DEMOLISHED 14,984.7985 14,513.6459 $856,305.11
202E56001 15.000 LS BUILDING DEMOLISHED, AS PER PLAN 15,803.5394 11,325.3000 $169,879.50
202E56100 34.000 EACH BUILDING DEMOLISHED 8,250.5631 9,789.5588 $332,845.00
202E58000 222.000 EACH MANHOLE REMOVED 404.2804 336.9102 $74,794.06
202E58001 2.000 EACH MANHOLE REMOVED, AS PER PLAN 1,213.4960 600.0000 $1,200.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
44 | P a g e
202E58100 1,036.000 EACH CATCH BASIN REMOVED 303.1470 258.2839 $267,582.12
202E58101 125.000 EACH CATCH BASIN REMOVED, AS PER PLAN 291.1438 315.3940 $39,424.25
202E58200 137.000 EACH INLET REMOVED 324.7616 327.1393 $44,818.09
202E58300 57.000 EACH CATCH BASIN OR INLET REMOVED 331.0937 329.5088 $18,782.00
202E58400 2.000 EACH INLET ABANDONED 612.5000 500.0000 $1,000.00
202E58500 22.000 EACH CATCH BASIN ABANDONED 446.4563 612.5600 $13,476.32
202E58501 2.000 EACH CATCH BASIN ABANDONED, AS PER PLAN 1,251.5870 2,088.0600 $4,176.12
202E58700 8.000 EACH MANHOLE ABANDONED 619.4167 400.0000 $3,200.00
202E60010 58.000 EACH MONUMENT ASSEMBLY REMOVED 123.9875 97.8921 $5,677.74
202E62000 5.000 EACH JUNCTION BOX REMOVED 287.8571 280.0000 $1,400.00
202E62700 11.000 EACH SEPTIC TANK REMOVED 1,192.6230 718.1818 $7,900.00
202E66000 16.000 EACH SPECIAL - DRILLED WATER WELL ABANDONED 1,139.8142 1,106.2500 $17,700.00
202E66500 11.000 EACH UNDERGROUND STORAGE TANK REMOVED 5,969.5582 3,176.6209 $34,942.83
202E67000 3.000 EACH REGULATED UNDERGROUND STORAGE TANK 10,716.1714 9,666.6667 $29,000.00
REMOVED
202E67001 1.000 EACH REGULATED UNDERGROUND STORAGE TANK 5,579.4000 2,000.0000 $2,000.00
REMOVED, AS PER PLAN
202E70000 23,213.000 FT SPECIAL - FILL AND PLUG EXISTING CONDUIT 21.9191 20.1685 $468,171.40
202E70100 19,204.000 FT SPECIAL - PIPE CLEANOUT 26.1517 17.7988 $341,808.58
202E75000 155,929.000 FT FENCE REMOVED 2.1872 1.8636 $290,589.46
202E75001 10,365.000 FT FENCE REMOVED, AS PER PLAN 2.9717 1.9945 $20,672.50
202E75101 888.000 FT FENCE REMOVED FOR STORAGE, AS PER PLAN 3.1429 2.4000 $2,131.20
202E75200 3,088.000 FT FENCE REMOVED FOR REUSE 3.6548 3.9631 $12,238.20
202E75201 64.000 FT FENCE REMOVED FOR REUSE, AS PER PLAN 22.0417 20.0000 $1,280.00
202E75250 40.000 EACH GATE REMOVED 136.5021 111.8438 $4,473.75
202E75254 4.000 EACH GATE REMOVED FOR REUSE 210.0000 101.2500 $405.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
45 | P a g e
202E75255 4.000 EACH GATE REMOVED FOR REUSE, AS PER PLAN 413.4783 312.5000 $1,250.00
202E75260 1,901.000 FT VANDAL PROTECTION FENCE REMOVED 6.8536 6.8907 $13,099.25
202E75600 72.000 EACH METER VAULT REMOVED 164.7474 104.8611 $7,550.00
202E75601 6.000 EACH METER VAULT REMOVED, AS PER PLAN 799.2985 1,059.3333 $6,356.00
202E75610 30.000 EACH VALVE BOX REMOVED 128.1056 114.1667 $3,425.00
202E75700 2.000 LS CONTROL CENTER REMOVED 1,127.6909 850.0000 $1,700.00
202E75704 1.000 EACH REMOVAL OF EXISTING CONTROL CENTER AND 540.9925 700.0000 $700.00
FOUNDATION
202E75711 209.000 FT EXISTING CONDUIT CLEANED, AS PER PLAN 35.4550 2.4100 $503.69
202E75800 4.000 EACH DISCONNECT EXISTING CIRCUIT 156.4980 148.4900 $593.96
202E98000 50.000 LS REMOVAL MISC.: 11,952.4838 6,706.0414 $335,302.07
202E98100 1,871.000 EACH REMOVAL MISC.: 146.5879 114.3040 $213,862.86
202E98200 706,492.000 FT REMOVAL MISC.: 1.7591 1.0735 $758,389.02
202E98300 31,811.000 SY REMOVAL MISC.: 14.6198 12.1291 $385,838.91
202E98400 57,804.000 SF REMOVAL MISC.: 2.1749 1.8639 $107,741.81
202E98500 5,294.000 CY REMOVAL MISC.: 185.8657 100.0336 $529,578.13
202E98510 924.000 MNHR REMOVAL MISC.: 212.7370 62.0130 $57,300.00
202E98600 14.000 EACH ABANDON MISC.: 855.4091 1,148.5714 $16,080.00
202E99000 2.000 LS SPECIAL - STRUCTURE REMOVED 46,549.5458 18,325.0000 $36,650.00
202E99010 11.000 LS SPECIAL - PORTIONS OF STRUCTURE REMOVED 97,866.6992 102,313.7273 $1,125,451.00
202E99020 9.000 LS SPECIAL - PAVEMENT REMOVED 54,378.4382 75,546.9144 $679,922.23
202E99100 18.000 LS SPECIAL - REMOVAL, MISC.: 18,609.7047 24,404.3544 $439,278.38
203E01890 2,670.000 SY SPECIAL - SOIL STERILANT 1.2115 1.3096 $3,496.50
203E02000 36,920.000 CY SPECIAL - ENGINEERED FILL 54.6289 47.5771 $1,756,547.50
203E07500 2.000 EACH SPECIAL - PNEUMATIC PIEZOMETER 3,242.8571 3,250.0000 $6,500.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
46 | P a g e
203E10000 2,414,636.400 CY EXCAVATION 10.3760 8.2299 $19,872,328.12
203E10001 175,695.000 CY EXCAVATION, AS PER PLAN 19.3323 17.0484 $2,995,313.56
203E20000 2,457,297.300 CY EMBANKMENT 7.4357 5.7107 $14,032,922.26
203E20001 30,719.000 CY EMBANKMENT, AS PER PLAN 18.2594 13.8632 $425,864.58
203E22000 690.000 CY EMBANKMENT, USING NATURAL SOILS, 10.2180 18.4800 $12,751.20
703.16.A
203E35000 16,802.000 CY GRANULAR EMBANKMENT 29.3570 26.3618 $442,931.00
203E35001 3,054.000 CY GRANULAR EMBANKMENT, AS PER PLAN 53.4644 41.3600 $126,313.56
203E35110 34,299.000 CY GRANULAR MATERIAL, TYPE B 37.9966 31.6055 $1,084,035.33
203E35120 5,714.000 CY GRANULAR MATERIAL, TYPE C 36.5621 39.5144 $225,785.00
203E35121 27.000 CY GRANULAR MATERIAL, TYPE C, AS PER PLAN 72.0180 44.9900 $1,214.73
203E35130 2,424.000 CY GRANULAR MATERIAL, TYPE D 33.3025 24.0000 $58,176.00
203E35140 198.000 CY GRANULAR MATERIAL, TYPE E 42.7588 32.0000 $6,336.00
203E40000 792.000 CY BORROW 46.3767 39.0982 $30,965.75
203E40001 1,795.000 CY BORROW, AS PER PLAN 15.1823 9.1086 $16,350.00
203E57150 2,320.000 CY SPECIAL - FOUNDATION EXCAVATION 35.7750 56.5500 $131,196.00
203E65000 32.000 EACH SPECIAL - SETTLEMENT PLATFORM 1,128.6101 1,298.0441 $41,537.41
203E98000 22,414.000 CY ROADWAY, MISC.: 23.1360 23.7080 $531,391.50
203E98100 1,386.000 SY ROADWAY, MISC.: 37.7977 15.2457 $21,130.50
203E98300 6,354.000 FT ROADWAY, MISC.: 83.8403 35.1798 $223,532.20
203E98500 3.000 LS ROADWAY, MISC.: 41,930.9500 15,683.3333 $47,050.00
203E98600 3.000 EACH ROADWAY, MISC.: 897.0775 1,500.0000 $4,500.00
203E99000 20.000 LS SPECIAL - EARTHWORK 749,319.6922 763,256.4640 $15,265,129.28
203E99100 5.000 LS SPECIAL - MISC.: 3343064.9726 2418556.0000 $12,092,780.00
204E10000 1,271,690.000 SY SUBGRADE COMPACTION 1.5706 1.2434 $1,581,270.46
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
47 | P a g e
204E10001 622.000 SY SUBGRADE COMPACTION, AS PER PLAN 3.2666 4.0000 $2,488.00
204E13000 149,057.000 CY EXCAVATION OF SUBGRADE 13.0682 11.8315 $1,763,565.38
204E13001 39,375.000 CY EXCAVATION OF SUBGRADE, AS PER PLAN 17.0487 15.9409 $627,671.75
204E20000 33,041.000 CY EMBANKMENT 6.0996 6.1406 $202,890.37
204E20001 81.000 CY EMBANKMENT, AS PER PLAN 75.0000 75.0000 $6,075.00
204E21000 675.000 CY GRANULAR EMBANKMENT 45.9095 42.2687 $28,531.40
204E30010 65,903.000 CY GRANULAR MATERIAL, TYPE B 34.5321 30.6778 $2,021,759.60
204E30011 22,273.000 CY GRANULAR MATERIAL, TYPE B, AS PER PLAN 33.7703 23.6338 $526,395.00
204E30020 29,654.000 CY GRANULAR MATERIAL, TYPE C 36.2823 32.5310 $964,673.08
204E30021 26,775.000 CY GRANULAR MATERIAL, TYPE C, AS PER PLAN 37.6183 28.0000 $749,700.00
204E30030 3,419.000 CY GRANULAR MATERIAL, TYPE D 42.0105 37.9532 $129,762.00
204E30040 1,843.000 CY GRANULAR MATERIAL, TYPE E 24.0622 30.7500 $56,672.25
204E30041 186.000 CY GRANULAR MATERIAL, TYPE E, AS PER PLAN 46.8152 52.8065 $9,822.00
204E30050 30.000 CY GRANULAR MATERIAL, TYPE F 85.0000 85.0000 $2,550.00
204E45000 1,292.260 HOUR PROOF ROLLING 190.9135 172.5398 $222,966.24
204E50000 234,368.000 SY GEOTEXTILE FABRIC 1.4509 1.2096 $283,491.09
204E50001 1,300.000 SY GEOTEXTILE FABRIC, AS PER PLAN 5.8328 5.0475 $6,561.75
204E50100 194.000 SY GEOTEXTILE FABRIC, 712.09, TYPE A 3.3480 9.1400 $1,773.16
205E10050 36,451.000 CY LIME STABILIZED EMBANKMENT 5.4960 5.1000 $185,900.10
205E10300 4,108.000 TON LIME 138.3890 141.2950 $580,440.00
205E10500 5,755.000 CY CEMENT STABILIZED EMBANKMENT 4.6180 4.0000 $23,020.00
205E10550 788.000 TON CEMENT 115.3426 111.9530 $88,219.00
205E20000 1.000 LS CONTRACTOR DESIGNED LIME SOIL 25,654.5220 22,000.0000 $22,000.00
206E10010 13,795.000 SY LIME STABILIZED SUBGRADE, 12 INCHES DEEP 5.3667 6.6000 $91,047.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
48 | P a g e
206E10020 151,044.000 SY LIME STABILIZED SUBGRADE, 14 INCHES DEEP 4.1651 3.9042 $589,712.00
206E10030 611.000 SY LIME STABILIZED SUBGRADE, 16 INCHES DEEP 4.3640 2.0000 $1,222.00
206E10300 4,545.000 TON LIME 150.6318 151.3976 $688,102.06
206E10500 37,908.000 TON CEMENT 103.3865 101.9271 $3,863,851.84
206E11000 1,349,774.000 SY CURING COAT 0.2834 0.2526 $340,953.18
206E11001 173,962.000 SY CURING COAT, AS PER PLAN 1.0642 1.1359 $197,598.65
206E15001 3,141.000 SY CEMENT STABILIZED SUBGRADE, AS PER PLAN 6.1826 9.5239 $29,914.50
206E15010 56,303.000 SY CEMENT STABILIZED SUBGRADE, 12 INCHES 3.4228 4.3588 $245,412.16
DEEP
206E15020 1,036,298.000 SY CEMENT STABILIZED SUBGRADE, 14 INCHES 2.6860 2.6906 $2,788,270.18
DEEP
206E15030 7,976.000 SY CEMENT STABILIZED SUBGRADE, 16 INCHES 5.0170 5.9440 $47,409.00
DEEP
206E20000 62.000 HOUR TEST ROLLING 162.0168 175.0000 $10,850.00
206E25030 158,239.000 SY LIME KILN DUST STABILIZED SUBGRADE, 16 3.1125 3.6500 $577,572.35
INCHES DEEP
206E25100 7,311.000 TON LIME KILN DUST 47.4500 47.2500 $345,444.75
206E30000 9.000 LS CONTRACTOR DESIGNED LIME SUBGRADE 20,458.4768 17,653.4656 $158,881.19
208E10000 1.000 LS PRE-BLAST CONDITION SURVEY 7,894.2017 5,000.0000 $5,000.00
208E12000 1.000 LS BLASTING CONSULTANT 11,231.6350 2,400.0000 $2,400.00
208E13000 1.000 LS AIR BLAST AND NOISE CONTROL 2,132.9083 1,000.0000 $1,000.00
208E14000 1.000 LS VIBRATION CONTROL AND MONITORING 2,416.2417 1,000.0000 $1,000.00
208E14001 3.000 LS VIBRATION CONTROL AND MONITORING, AS PER 15,549.1667 17,796.6667 $53,390.00
PLAN
208E15000 3,531.000 SY PRESPLITTING 36.8267 26.0000 $91,806.00
208E16000 1.000 LS HYDROLOGIST 30,988.3600 18,800.0000 $18,800.00
209E10000 4,560.000 FT DITCH CLEANOUT 11.2461 9.5955 $43,755.50
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
49 | P a g e
209E10001 4,700.000 FT DITCH CLEANOUT, AS PER PLAN 10.7639 11.6266 $54,645.00
209E15000 834.280 STA RESHAPING UNDER GUARDRAIL 38.7674 32.3668 $27,002.95
209E15001 608.010 STA RESHAPING UNDER GUARDRAIL, AS PER PLAN 159.8502 127.1058 $77,281.59
209E15050 10.450 MILE RESHAPING UNDER GUARDRAIL 1,686.3214 594.3541 $6,211.00
209E60200 4,582.000 STA LINEAR GRADING 43.4408 56.5993 $259,338.16
209E60201 1,980.300 STA LINEAR GRADING, AS PER PLAN 154.3935 124.1017 $245,758.50
209E60500 328.560 MILE LINEAR GRADING 1,054.2159 957.7106 $314,665.38
209E60501 5.690 MILE LINEAR GRADING, AS PER PLAN 6,453.9579 5,951.4328 $33,863.65
209E70000 11,932.000 CY BORROW 41.0534 33.4971 $399,687.65
209E72000 8.970 STA PREPARING SUBGRADE FOR SHOULDER PAVING 777.3690 777.3690 $6,973.00
209E72001 14,402.980 STA PREPARING SUBGRADE FOR SHOULDER PAVING, 21.7986 19.2398 $277,110.18
AS PER PLAN
209E72050 6.020 MILE PREPARING SUBGRADE FOR SHOULDER PAVING 2,586.1711 2,016.2791 $12,138.00
209E72051 1,391.280 MILE PREPARING SUBGRADE FOR SHOULDER PAVING, 915.8214 853.9741 $1,188,117.12
AS PER PLAN
209E80000 296.000 EACH GRADING MAILBOX APPROACHES 54.6343 46.3294 $13,713.50
209E80050 41.000 EACH GRADING DRIVE APPROACHES 75.3723 79.7561 $3,270.00
209E98300 1,747.000 SY LINEAR GRADING, MISC.: 4.4428 2.1236 $3,710.00
251E01000 118,044.000 SY PARTIAL DEPTH PAVEMENT REPAIR 23.7685 21.9237 $2,587,957.63
251E01001 237,869.000 SY PARTIAL DEPTH PAVEMENT REPAIR, AS PER 31.0182 29.1246 $6,927,829.62
PLAN
251E01010 8,989.000 CY PARTIAL DEPTH PAVEMENT REPAIR 189.8614 185.0113 $1,663,067.00
252E01000 5,294.000 SY FULL DEPTH RIGID PAVEMENT REMOVAL AND 82.0841 82.1970 $435,150.96
FLEXIBLE REPLACEMENT
252E01001 1,096.000 SY FULL DEPTH RIGID PAVEMENT REMOVAL AND 92.0297 95.5999 $104,777.50
FLEXIBLE REPLACEMENT, AS PER PLAN
252E01500 138,039.000 FT FULL DEPTH PAVEMENT SAWING 1.7648 1.4851 $205,004.86
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
50 | P a g e
253E01000 110,055.000 SY PAVEMENT REPAIR 33.5211 28.8539 $3,175,518.65
253E01001 78,345.000 SY PAVEMENT REPAIR, AS PER PLAN 30.1306 28.1473 $2,205,197.18
253E02000 51,834.880 CY PAVEMENT REPAIR 166.2045 156.2245 $8,097,876.63
253E02001 8,400.000 CY PAVEMENT REPAIR, AS PER PLAN 209.8298 216.6134 $1,819,552.80
253E90000 10,426.000 CY PAVEMENT REPAIR, MISC.: 166.8567 155.6021 $1,622,307.50
253E90100 197.000 SY PAVEMENT REPAIR, MISC.: 60.0952 47.3193 $9,321.91
254E01000 16744479.000 SY PAVEMENT PLANING, ASPHALT CONCRETE 1.2680 1.1274 $18,877,330.26
254E01001 1,763,769.000 SY PAVEMENT PLANING, ASPHALT CONCRETE, AS 1.4641 1.4478 $2,553,669.35
PER PLAN
254E01010 7,948.000 SY PAVEMENT PLANING, PORTLAND CEMENT 3.7224 3.1203 $24,800.00
CONCRETE
254E01011 6,831.000 SY PAVEMENT PLANING, PORTLAND CEMENT 5.7942 5.8067 $39,665.55
CONCRETE, AS PER PLAN
254E01600 95,244.000 SY PATCHING PLANED SURFACE 2.6367 2.1221 $202,119.68
254E01601 275.000 SY PATCHING PLANED SURFACE, AS PER PLAN 8.7156 11.9382 $3,283.00
254E90100 5,132.000 SY PAVEMENT PLANING, MISC.: 4.5455 2.6921 $13,815.90
255E10001 9,342.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 101.8309 98.9811 $924,681.00
REPLACEMENT, CLASS C, AS PER PLAN
255E10010 400.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 150.0000 175.0000 $70,000.00
REPLACEMENT, CLASS QC1
255E10011 724.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 142.6658 151.2376 $109,496.00
REPLACEMENT, CLASS QC1, AS PER PLAN
255E10100 2,274.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 125.5744 111.4697 $253,482.00
REPLACEMENT, CLASS FS
255E10101 18,797.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 143.5221 115.2184 $2,165,759.88
REPLACEMENT, CLASS FS, AS PER PLAN
255E10110 684.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 180.0000 180.0000 $123,120.00
REPLACEMENT, CLASS QC FS
255E10111 20,614.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 91.4883 94.3762 $1,945,470.00
REPLACEMENT, CLASS QC FS, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
51 | P a g e
255E10150 9,379.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 96.6246 84.2301 $789,994.00
REPLACEMENT, CLASS MS
255E10151 13,988.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 136.4945 123.7110 $1,730,469.56
REPLACEMENT, CLASS MS, AS PER PLAN
255E10161 900.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 164.0000 178.0000 $160,200.00
REPLACEMENT, CLASS QC MS, AS PER PLAN
255E10500 2,343.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 187.1378 174.0738 $407,855.00
REPLACEMENT, CLASS RRCM
255E10501 7,826.000 SY FULL DEPTH PAVEMENT REMOVAL AND RIGID 239.7485 206.8891 $1,619,113.98
REPLACEMENT, CLASS RRCM, AS PER PLAN
255E20000 383,866.000 FT FULL DEPTH PAVEMENT SAWING 1.8512 1.8103 $694,930.29
255E20001 2,682.000 FT FULL DEPTH PAVEMENT SAWING, AS PER PLAN 1.8248 1.7891 $4,798.40
255E98000 4,922.000 CY FULL DEPTH REPAIR, MISC.: 346.7967 220.0000 $1,082,840.00
256E10000 17,374.000 SF BONDED PATCHING OF PORTLAND CEMENT 22.5476 21.1006 $366,602.00
CONCRETE PAVEMENT, TYPE A
256E10001 585.000 SF BONDED PATCHING OF PORTLAND CEMENT 35.6000 23.0000 $13,455.00
CONCRETE PAVEMENT, TYPE A, AS PER PLAN
256E10100 55.000 SF BONDED PATCHING OF PORTLAND CEMENT 270.8947 148.6364 $8,175.00
CONCRETE PAVEMENT, TYPE B
257E10000 229,886.000 SY DIAMOND GRINDING PORTLAND CEMENT 3.6380 2.3457 $539,251.75
CONCRETE PAVEMENT
257E10001 108,851.000 SY DIAMOND GRINDING PORTLAND CEMENT 3.7283 3.8722 $421,495.10
CONCRETE PAVEMENT, AS PER PLAN
258E10000 2,862.000 EACH RETROFIT DOWEL BARS 61.9000 58.0000 $165,996.00
301E46000 185,411.500 CY ASPHALT CONCRETE BASE, PG64-22 119.6672 114.1989 $21,173,792.28
301E46001 3,467.000 CY ASPHALT CONCRETE BASE, PG64-22, AS PER 146.4132 142.9573 $495,633.12
PLAN
301E46010 147.000 CY ASPHALT CONCRETE BASE, PG64-28 160.8000 160.0000 $23,520.00
301E48000 949.000 CY ASPHALT CONCRETE BASE, PG64-22 193.7452 205.6220 $195,135.28
(DRIVEWAYS)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
52 | P a g e
302E46000 242,108.640 CY ASPHALT CONCRETE BASE, PG64-22 101.2746 90.7664 $21,975,329.49
304E20000 361,226.600 CY AGGREGATE BASE 42.1013 38.7024 $13,980,349.14
304E20001 125,995.000 CY AGGREGATE BASE, AS PER PLAN 43.0627 35.4112 $4,461,638.57
304E99000 10.000 LS SPECIAL - AGGREGATE BASE 122,135.5270 151,787.9860 $1,517,879.86
305E10000 19.000 SY 6" CONCRETE BASE 72.2150 59.0000 $1,121.00
305E11000 19.000 SY 7" CONCRETE BASE 51.2700 54.0000 $1,026.00
305E12000 8,999.000 SY 8" CONCRETE BASE 44.2500 39.0000 $350,961.00
305E13000 6,627.000 SY 9" CONCRETE BASE 54.7771 50.2215 $332,818.00
305E13001 18,883.000 SY 9" CONCRETE BASE, AS PER PLAN 49.4621 50.3850 $951,420.00
305E13010 5,649.000 SY 9" CONCRETE BASE, CLASS QC1 45.5000 49.0000 $276,801.00
305E14000 4,951.000 SY 10" CONCRETE BASE 59.3437 57.7988 $286,162.00
305E14001 1,413.000 SY 10" CONCRETE BASE, AS PER PLAN 79.7450 76.8556 $108,597.00
305E14010 8,623.000 SY 10" CONCRETE BASE, CLASS QC1 55.7300 50.0000 $431,150.00
305E14011 7,315.000 SY 10" CONCRETE BASE, CLASS QC1, AS PER 60.0000 55.0000 $402,325.00
PLAN
305E17000 317.000 SY 13" CONCRETE BASE 62.8200 59.5000 $18,861.50
305E17500 10,107.000 SY CONCRETE BASE, MISC.: 36.0771 23.3411 $235,908.24
305E99000 3.000 LS SPECIAL - CONCRETE BASE 107,223.2500 138,715.0000 $416,145.00
407E10000 2,016,514.000 GAL TACK COAT 2.0612 2.0178 $4,068,937.10
407E10001 6,962.000 GAL TACK COAT, AS PER PLAN 2.5609 2.1661 $15,080.50
407E13900 46,090.000 GAL TACK COAT, 702.13 2.6040 2.5591 $117,947.11
407E14000 769,210.000 GAL TACK COAT FOR INTERMEDIATE COURSE 2.1481 2.0873 $1,605,549.02
407E14001 273.000 GAL TACK COAT FOR INTERMEDIATE COURSE, AS 2.5000 2.0000 $546.00
PER PLAN
407E14010 14,468.000 GAL TACK COAT FOR INTERMEDIATE COURSE, 2.7613 2.5486 $36,873.65
702.13
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
53 | P a g e
407E20000 80,289.000 GAL TACK COAT, TRACKLESS TACK, INTERMEDIATE 4.6758 4.9504 $397,460.38
COURSE
407E20001 1,401.000 GAL SPECIAL - TACK COAT, TRACKLESS TACK, 5.2500 6.5000 $9,106.50
INTERMEDIATE COURSE, AS PER PLAN
407E20100 178,743.000 GAL TACK COAT, TRACKLESS TACK, SURFACE 4.3728 4.2626 $761,911.24
COURSE
407E20101 1,990.000 GAL SPECIAL - TACK COAT, TRACKLESS TACK, AS 3.2000 2.0000 $3,980.00
PER PLAN
407E20500 101,828.000 GAL SPECIAL - TACK COAT, TRACKLESS TACK 3.4128 3.9207 $399,238.24
407E20510 40,547.000 GAL SPECIAL - TACK COAT, TRACKLESS TACK FOR 3.8201 4.3756 $177,418.40
INTERMEDIATE COURSE
408E10000 290,455.000 GAL PRIME COAT 3.7687 3.4292 $996,014.12
408E10001 287,797.000 GAL PRIME COAT, AS PER PLAN 3.4051 3.3035 $950,734.65
409E30000 1,624.000 FT SAWING AND SEALING ASPHALT CONCRETE 12.0402 13.2414 $21,504.00
PAVEMENT JOINTS
409E30001 59,053.000 FT SAWING AND SEALING ASPHALT CONCRETE 2.3921 2.6257 $155,053.77
PAVEMENT JOINTS, AS PER PLAN
409E98000 120,267.000 SY SEALING, MISC: 0.7000 0.7000 $84,186.90
409E98010 207,624.000 LB SEALING, MISC.: 1.3205 1.2299 $255,349.93
410E10000 1,111.000 CY TRAFFIC COMPACTED SURFACE, TYPE A 29.1706 23.6904 $26,320.00
410E10001 50.000 CY TRAFFIC COMPACTED SURFACE, TYPE A, AS 43.7025 59.8100 $2,990.50
PER PLAN
410E11000 460.000 CY TRAFFIC COMPACTED SURFACE, TYPE B 52.8233 65.0435 $29,920.00
410E12000 8,399.000 CY TRAFFIC COMPACTED SURFACE, TYPE A OR B 45.2443 44.0822 $370,246.60
410E13000 717.000 CY TRAFFIC COMPACTED SURFACE, TYPE C 57.1029 49.6304 $35,585.00
410E14001 400.000 CY TRAFFIC COMPACTED SURFACE, AS PER PLAN 39.3867 33.5500 $13,420.00
411E10000 5,513.000 CY STABILIZED CRUSHED AGGREGATE 51.2968 48.6590 $268,257.25
411E10001 30.000 CY STABILIZED CRUSHED AGGREGATE, AS PER 113.3802 145.3333 $4,360.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
54 | P a g e
421E10010 180,541.000 SY MICROSURFACING, SURFACE COURSE 2.5985 2.2068 $398,419.37
421E10011 1,559,644.000 SY MICROSURFACING, SURFACE COURSE, AS PER 2.0286 2.1737 $3,390,181.87
PLAN
421E10020 563,797.000 SY MICROSURFACING, LEVELING COURSE 1.5523 1.2763 $719,556.31
422E10000 578,842.000 SY SINGLE CHIP SEAL WITH POLYMER BINDER 1.7889 1.7357 $1,004,669.90
422E10001 634,221.000 SY SINGLE CHIP SEAL WITH POLYMER BINDER, AS 1.8801 1.7238 $1,093,251.96
PER PLAN
422E20000 28,794.000 SY DOUBLE CHIP SEAL WITH POLYMER BINDER 3.1018 2.8600 $82,350.84
422E20001 210,935.000 SY DOUBLE CHIP SEAL WITH POLYMER BINDER, AS 3.0855 3.0704 $647,664.75
PER PLAN
423E00100 3,000.000 LB CRACK SEALING, TYPE I 3.2300 1.2500 $3,750.00
423E00104 3,893.000 LB CRACK SEALING, TYPE II 3.0667 5.0000 $19,465.00
423E00108 2,067.000 LB CRACK SEALING, TYPE III 5.2261 8.0435 $16,626.00
423E00200 3,270.000 SY CRACK SEALING, TYPE I 6.8550 6.7100 $21,941.70
423E00220 1,484,047.000 SY CRACK SEALING, TYPE II OR TYPE III 0.3232 0.3232 $479,679.89
423E00250 2,314,533.000 SY CRACK SEALING, TYPE IV 0.2579 0.2334 $540,204.11
423E98000 61,013.000 LB CRACK SEALING, MISC.: 3.8300 1.8000 $109,823.40
423E98100 4,402,255.000 SY CRACK SEALING, MISC.: 0.3134 0.2759 $1,214,787.76
423E98200 71,655.000 FT CRACK SEALING, MISC.: 0.8403 0.7069 $50,649.40
424E10000 693.000 CY FINE GRADED POLYMER ASPHALT CONCRETE, 179.5840 175.0000 $121,275.00
TYPE A
424E10001 3,512.000 CY FINE GRADED POLYMER ASPHALT CONCRETE, 196.7851 187.3366 $657,926.00
TYPE A, AS PER PLAN
424E12000 27,265.000 CY FINE GRADED POLYMER ASPHALT CONCRETE, 191.9637 177.4877 $4,839,201.30
TYPE B
424E12001 44,259.000 CY FINE GRADED POLYMER ASPHALT CONCRETE, 180.1618 172.8277 $7,649,180.84
TYPE B, AS PER PLAN
442E00200 17,084.000 CY ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, 163.0000 166.0000 $2,835,944.00
TYPE A (446)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
55 | P a g e
442E00201 56,498.500 CY ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, 138.0272 130.6480 $7,381,417.09
TYPE A (446), AS PER PLAN
442E00301 7,735.000 CY ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, 150.8678 134.9871 $1,044,125.00
TYPE B (446), AS PER PLAN
442E10000 195,320.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5MM, 155.2789 150.9062 $29,474,992.40
TYPE A (446)
442E10001 62,242.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5 164.7745 161.9250 $10,078,533.62
MM, TYPE A (446), AS PER PLAN
442E10050 974.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5MM, 189.7809 178.0833 $173,453.18
TYPE B (446)
442E10051 95,276.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5 161.1292 152.0899 $14,490,513.48
MM, TYPE B (446), AS PER PLAN
442E10100 108,563.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 128.4491 121.9456 $13,238,776.00
19MM, TYPE A (446)
442E10101 16,205.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 19 125.7364 119.3634 $1,934,283.75
MM, TYPE A (446), AS PER PLAN
442E10150 91,881.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 124.6220 116.2597 $10,682,055.11
19MM, TYPE B (446)
442E10500 15,360.000 CY ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, 142.3423 136.0407 $2,089,585.00
TYPE A (448)
442E10501 560.290 CY ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, 278.7251 295.6496 $165,649.50
TYPE A (448), AS PER PLAN
442E10510 50.000 CY ASPHALT CONCRETE SURFACE COURSE, 9.5MM, 205.0000 210.0000 $10,500.00
TYPE A (448) (DRIVEWAYS)
442E20000 38,094.500 CY ASPHALT CONCRETE SURFACE COURSE, 12.5MM, 169.3860 158.6296 $6,042,913.98
TYPE A (448)
442E20001 21,843.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5 177.2383 174.0018 $3,800,720.50
MM, TYPE A (448), AS PER PLAN
442E20050 51.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5MM, 246.6133 232.0000 $11,832.00
TYPE B (448)
442E20051 5,067.000 CY ASPHALT CONCRETE SURFACE COURSE, 12.5 182.3101 175.4329 $888,918.74
MM, TYPE B (448), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
56 | P a g e
442E20100 9,386.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 139.0062 130.7094 $1,226,838.00
9.5MM, TYPE A (448)
442E20101 21,165.500 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 134.0469 124.7894 $2,641,230.50
9.5 MM, TYPE A (448), AS PER PLAN
442E20200 35,590.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 128.1324 123.5123 $4,395,804.10
19MM, TYPE A (448)
442E20201 32,134.800 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 19 128.7147 132.2740 $4,250,597.50
MM, TYPE A (448), AS PER PLAN
442E20250 794.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 152.7960 156.6952 $124,416.00
19MM, TYPE B (448)
442E90000 1,283.000 CY ASPHALT CONCRETE, MISC.: 4.2500 2.5000 $3,207.50
442E99000 23.000 LS SPECIAL - FLEXIBLE PAVEMENT 2602201.7092 2911428.6113 $66,962,858.06
446E46040 651.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 144.1704 141.8800 $92,363.88
TYPE 2, PG64-28
446E46050 983.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 154.5625 147.7976 $145,285.00
TYPE 2, PG64-22
446E46060 134.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 193.4075 192.0000 $25,728.00
TYPE 2, PG70-22
446E47020 24,805.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 142.0836 133.9875 $3,323,559.00
PG64-22
446E47028 96.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 217.8900 221.0000 $21,216.00
PG70-22M
446E47029 72,399.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 149.5819 141.5145 $10,245,511.26
PG70-22M, AS PER PLAN
446E50000 5,817.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1H 154.0000 155.0000 $901,635.00
448E46010 3,601.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 157.2687 154.6949 $557,056.50
TYPE 1, PG64-28
448E46020 114,248.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 133.0180 129.2536 $14,766,970.60
TYPE 1, PG64-22
448E46021 28,788.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 136.2860 134.4147 $3,869,530.27
TYPE 1, PG64-22, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
57 | P a g e
448E46024 704.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 260.4954 241.0782 $169,719.02
TYPE 2, PG64-22 (DRIVEWAYS)
448E46040 4,850.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 143.0704 137.2009 $665,424.26
TYPE 2, PG64-28
448E46041 2,735.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 137.7558 117.3792 $321,032.00
TYPE 2, PG64-28, AS PER PLAN
448E46050 188,548.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 120.1422 114.6435 $21,615,804.22
TYPE 2, PG64-22
448E46051 15,807.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 112.0816 100.6939 $1,591,669.20
TYPE 2, PG64-22, AS PER PLAN
448E46060 45.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 351.8524 400.5556 $18,025.00
TYPE 1, PG64-22 (UNDER GUARDRAIL)
448E46061 6,506.400 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 230.9879 226.6017 $1,474,361.54
TYPE 1, UNDER GUARDRAIL, PG64-22, AS PER PLAN
448E46081 2,011.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 138.6883 150.0000 $301,650.00
TYPE 1, PG70-22, AS PER PLAN
448E46091 3,947.000 CY ASPHALT CONCRETE INTERMEDIATE COURSE, 169.9100 187.7300 $740,970.31
TYPE 2, PG70-22M, AS PER PLAN
448E46900 3,142.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 179.3909 184.3397 $579,195.20
PG70-22
448E46901 1,567.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 205.5489 209.1640 $327,760.00
PG70-22, AS PER PLAN
448E46904 118,195.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 148.6117 145.8415 $17,237,740.31
PG70-22M
448E46905 101,460.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 145.0671 141.4082 $14,347,275.49
PG70-22M, AS PER PLAN
448E47004 8,512.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 160.0000 160.0000 $1,361,920.00
PG76-22M
448E47010 569.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 199.6553 198.6204 $113,015.00
PG64-28
448E47020 209,943.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 145.2502 139.3563 $29,256,887.47
PG64-22
448E47021 13,260.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 176.2896 172.5655 $2,288,219.17
PG64-22, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
58 | P a g e
448E47050 27.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 2, 363.7500 370.0000 $9,990.00
PG64-22
448E48020 1,610.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 269.7628 271.1217 $436,505.91
PG64-22 (DRIVEWAYS)
448E48021 5,254.000 CY ASPHALT CONCRETE SURFACE COURSE, TYPE 1, 202.7609 189.4628 $995,437.75
PG64-22 (DRIVEWAYS), AS PER PLAN
448E90000 400.000 CY ASPHALT CONCRETE, MISC.: 226.9077 189.0550 $75,622.00
448E91000 1,820.000 SY ASPHALT CONCRETE, MISC.: 23.9676 14.1022 $25,666.00
448E99000 9.000 LS SPECIAL - FLEXIBLE PAVEMENT 187,480.2259 215,158.0556 $1,936,422.50
451E10000 433.000 SY 6" REINFORCED CONCRETE PAVEMENT 69.2408 60.0944 $26,020.89
451E10001 1,780.000 SY 6" REINFORCED CONCRETE PAVEMENT, AS PER 56.3499 43.1688 $76,840.50
PLAN
451E10010 345.000 SY 6" REINFORCED CONCRETE PAVEMENT, CLASS 63.2323 55.2174 $19,050.00
QC1
451E13000 3,684.000 SY 8" REINFORCED CONCRETE PAVEMENT 61.1994 54.6816 $201,447.00
451E13001 725.000 SY 8" REINFORCED CONCRETE PAVEMENT, AS PER 69.3200 85.1000 $61,697.50
PLAN
451E13010 1,083.000 SY 8" REINFORCED CONCRETE PAVEMENT, CLASS 67.7716 49.7819 $53,913.75
QC1
451E13011 79.000 SY 8" REINFORCED CONCRETE PAVEMENT, CLASS 84.4286 50.0000 $3,950.00
QC1, AS PER PLAN
451E14000 27,245.000 SY 9" REINFORCED CONCRETE PAVEMENT 55.7297 47.3353 $1,289,649.10
451E14001 1,151.000 SY 9" REINFORCED CONCRETE PAVEMENT, AS PER 110.8059 94.8671 $109,192.00
PLAN
451E15000 2,124.000 SY 10" REINFORCED CONCRETE PAVEMENT 70.3520 67.6600 $143,709.84
451E15500 674.000 SY 11" REINFORCED CONCRETE PAVEMENT 74.6667 70.0000 $47,180.00
451E16000 2,218.000 SY 12" REINFORCED CONCRETE PAVEMENT 80.5875 74.6498 $165,573.28
451E16001 373.000 SY 12" REINFORCED CONCRETE PAVEMENT, AS PER 166.0937 98.9531 $36,909.50
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
59 | P a g e
451E16011 5,381.000 SY 12" REINFORCED CONCRETE PAVEMENT, CLASS 78.0000 75.0000 $403,575.00
QC1, AS PER PLAN
451E20000 192,548.000 SY REINFORCED CONCRETE PAVEMENT, MISC.: 0.6834 0.7711 $148,467.50
451E30000 6,609.000 FT SPECIAL - PRESSURE RELIEF JOINT, TYPE A 151.1319 129.8211 $857,987.80
451E32000 2,713.000 FT SPECIAL - PRESSURE RELIEF JOINT, TYPE C 58.6534 58.9005 $159,797.00
451E98000 722.000 SY REINFORCED CONCRETE PAVEMENT, MISC.: 84.0095 64.8338 $46,810.00
451E99000 1.000 LS SPECIAL - REINFORCED CONCRETE PAVEMENT, 233,691.5000 241,383.0000 $241,383.00
AS PER CONCEPTUAL DOCUMENTS
452E10000 4,631.000 SY 6" NON-REINFORCED CONCRETE PAVEMENT 48.6052 47.0030 $217,671.00
452E10001 2,862.000 SY 6" NON-REINFORCED CONCRETE PAVEMENT, AS 52.7105 50.8375 $145,496.95
PER PLAN
452E10010 317.000 SY 6" NON-REINFORCED CONCRETE PAVEMENT, 65.4900 59.7000 $18,924.90
CLASS QC1
452E10011 275.000 SY 6" NON-REINFORCED CONCRETE PAVEMENT, 70.0000 70.0000 $19,250.00
CLASS QC1, AS PER PLAN
452E10050 424.000 SY 6" NON-REINFORCED CONCRETE PAVEMENT, 68.8000 44.0000 $18,656.00
CLASS QC MS
452E10051 400.000 SY 6" NON-REINFORCED CONCRETE PAVEMENT, 56.8700 47.0000 $18,800.00
CLASS QC MS, AS PER PLAN
452E11000 461.000 SY 7" NON-REINFORCED CONCRETE PAVEMENT 62.5796 55.2603 $25,475.00
452E11001 47.000 SY 7" NON-REINFORCED CONCRETE PAVEMENT, AS 76.1340 60.0000 $2,820.00
PER PLAN
452E12000 31,962.000 SY 8" NON-REINFORCED CONCRETE PAVEMENT 46.6648 42.9754 $1,373,581.10
452E12001 9,345.000 SY 8" NON-REINFORCED CONCRETE PAVEMENT, AS 51.1353 48.3975 $452,274.54
PER PLAN
452E12010 868.000 SY 8" NON-REINFORCED CONCRETE PAVEMENT, 75.8099 53.1855 $46,165.00
CLASS QC1
452E12011 525.000 SY 8" NON-REINFORCED CONCRETE PAVEMENT, 67.5000 62.5000 $32,812.50
CLASS QC1, AS PER PLAN
452E12050 87.000 SY 8" NON-REINFORCED CONCRETE PAVEMENT, 68.2000 50.0000 $4,350.00
CLASS QC MS
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
60 | P a g e
452E13000 30,688.000 SY 9" NON-REINFORCED CONCRETE PAVEMENT 49.3766 47.2993 $1,451,521.80
452E13001 6,836.000 SY 9" NON-REINFORCED CONCRETE PAVEMENT, AS 55.4483 50.7684 $347,052.73
PER PLAN
452E13010 11,904.000 SY 9" NON-REINFORCED CONCRETE PAVEMENT, 55.5336 51.1203 $608,536.00
CLASS QC1
452E13050 5,829.000 SY 9-1/2" NON-REINFORCED CONCRETE PAVEMENT 55.0583 50.0000 $291,450.00
452E14000 63,385.000 SY 10" NON-REINFORCED CONCRETE PAVEMENT 51.5758 44.7217 $2,834,683.44
452E14001 15,032.000 SY 10" NON-REINFORCED CONCRETE PAVEMENT, AS 64.7269 63.5842 $955,797.00
PER PLAN
452E14010 7,452.000 SY 10" NON-REINFORCED CONCRETE PAVEMENT, 63.4976 62.2932 $464,208.75
CLASS QC1
452E14011 45.000 SY 10" NON-REINFORCED CONCRETE PAVEMENT, 71.3750 71.0000 $3,195.00
CLASS QC1, AS PER PLAN
452E14101 921.000 SY 11" NON-REINFORCED CONCRETE PAVEMENT, AS 107.5000 110.0000 $101,310.00
PER PLAN
452E14110 6,306.000 SY 11" NON-REINFORCED CONCRETE PAVEMENT, 59.8000 54.5000 $343,677.00
CLASS QC1
452E15000 24,719.000 SY 12" NON-REINFORCED CONCRETE PAVEMENT 64.5455 56.4882 $1,396,332.00
452E15001 849.000 SY 12" NON-REINFORCED CONCRETE PAVEMENT, AS 67.2243 70.0000 $59,430.00
PER PLAN
452E15020 56.000 SY 13.5" NON-REINFORCED CONCRETE PAVEMENT 106.2000 114.0000 $6,384.00
452E15030 461.000 SY 12" NON-REINFORCED CONCRETE PAVEMENT, 133.9575 90.0000 $41,490.00
CLASS QC MS
452E15060 2,187.000 SY 14.5" NON-REINFORCED CONCRETE PAVEMENT 85.1600 82.3200 $180,033.84
452E16020 4,957.000 SY 13" NON-REINFORCED CONCRETE PAVEMENT, 76.9800 72.0000 $356,904.00
CLASS QC1 WITH QC/QA
452E17200 20,383.000 SY NON-REINFORCED CONCRETE PAVEMENT, MISC.: 60.8338 52.0567 $1,061,071.00
452E99000 5.000 LS SPECIAL - NON-REINFORCED CONCRETE 591,726.7141 545,167.0040 $2,725,835.02
PAVEMENT, AS PER CONCEPTUAL DOCUMENT
502E11100 2.000 LS STRUCTURE FOR MAINTAINING TRAFFIC 197,500.0000 350,000.0000 $700,000.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
61 | P a g e
502E12201 1.000 LS STRUCTURE FOR MAINTAINING TRAFFIC 215,799.8750 100,000.0000 $100,000.00
(PEDESTRIAN), AS PER PLAN
503E11100 254.000 LS COFFERDAMS, CRIBS AND SHEETING 20,578.4059 15,141.4033 $3,845,916.44
503E11101 69.000 LS COFFERDAMS, CRIBS AND SHEETING, AS PER 148,354.1538 128,299.9732 $8,852,698.15
PLAN
503E21100 55,896.000 CY UNCLASSIFIED EXCAVATION 40.9154 40.4940 $2,263,450.71
503E21101 56,833.000 CY UNCLASSIFIED EXCAVATION, AS PER PLAN 32.3259 22.5719 $1,282,831.50
503E21103 200.000 CY UNCLASSIFIED EXCAVATION, INCLUDING 43.0000 39.0000 $7,800.00
SHALE, AS PER PLAN
503E21105 24.000 CY UNCLASSIFIED EXCAVATION, INCLUDING ROCK, 248.4375 162.5000 $3,900.00
AS PER PLAN
503E21300 133.000 LS UNCLASSIFIED EXCAVATION 13,407.5509 10,615.0563 $1,411,802.49
503E21301 40.000 LS UNCLASSIFIED EXCAVATION, AS PER PLAN 26,444.7806 27,967.1648 $1,118,686.59
503E21302 2.000 LS UNCLASSIFIED EXCAVATION INCLUDING SHALE 65,399.3438 61,250.0000 $122,500.00
503E21303 1.000 LS UNCLASSIFIED EXCAVATION INCLUDING SHALE, 36,325.9320 27,000.0000 $27,000.00
AS PER PLAN
503E21320 3.000 LS UNCLASSIFIED EXCAVATION, INCLUDING ROCK 10,104.8600 9,743.0233 $29,229.07
503E21321 2.000 LS UNCLASSIFIED EXCAVATION, INCLUDING ROCK, 18,490.0000 17,960.0000 $35,920.00
AS PER PLAN
503E21330 1.000 LS UNCLASSIFIED EXCAVATION INCLUDING ROCK 405,850.2580 287,251.2900 $287,251.29
AND/OR SHALE
503E22200 33.000 CY UNCLASSIFIED EXCAVATION INCLUDING ROCK 92.7500 85.0000 $2,805.00
AND/OR SHALE
503E31100 3,564.000 CY ROCK EXCAVATION 45.9681 19.8175 $70,629.60
503E31101 3,750.000 CY ROCK EXCAVATION, AS PER PLAN 22.2565 14.5406 $54,527.40
503E31500 1.000 LS STRUCTURAL EXCAVATION, MISC.: 1776250.0000 990,000.0000 $990,000.00
504E11100 16,448.000 SF STEEL SHEET PILING LEFT IN PLACE 32.3686 25.7863 $424,133.00
504E11101 1,444.000 SF STEEL SHEET PILING LEFT IN PLACE, AS PER 25.2286 24.6000 $35,522.40
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
62 | P a g e
505E11100 84.000 LS PILE DRIVING EQUIPMENT MOBILIZATION 20,082.8702 17,256.1106 $1,449,513.29
507E00100 53,102.000 FT STEEL PILES HP10X42, FURNISHED 23.1839 22.1586 $1,176,664.20
507E00150 44,480.000 FT STEEL PILES HP10X42, DRIVEN 12.6901 11.9970 $533,626.60
507E00151 1,760.000 FT STEEL PILES HP10X42, DRIVEN, AS PER PLAN 15.5000 18.5000 $32,560.00
507E00200 45,695.000 FT STEEL PILES HP12X53, FURNISHED 29.5613 37.4182 $1,709,823.50
507E00201 380.000 FT STEEL PILES HP12X53, FURNISHED, AS PER 32.1667 26.5000 $10,070.00
PLAN
507E00250 41,095.000 FT STEEL PILES HP12X53, DRIVEN 11.7425 7.4428 $305,862.90
507E00300 13,015.000 FT STEEL PILES HP14X73, FURNISHED 35.6921 32.9013 $428,210.00
507E00350 10,507.000 FT STEEL PILES HP14X73, DRIVEN 13.3541 8.5416 $89,747.00
507E00400 44,121.500 FT STEEL PILES, MISC.: 57.3458 61.0315 $2,692,800.05
507E00410 1.000 EACH STEEL PILES, MISC.: 4,024.6250 3,994.5000 $3,994.50
507E00500 61,082.000 FT 12" CAST-IN-PLACE REINFORCED CONCRETE 13.0969 14.2532 $870,614.20
PILES, DRIVEN
507E00550 67,702.000 FT 12" CAST-IN-PLACE REINFORCED CONCRETE 28.3714 26.6600 $1,804,936.60
PILES, FURNISHED
507E00600 23,932.000 FT 14" CAST-IN-PLACE REINFORCED CONCRETE 15.0089 14.8792 $356,089.00
PILES, DRIVEN
507E00650 26,628.000 FT 14" CAST-IN-PLACE REINFORCED CONCRETE 40.1036 43.0475 $1,146,269.00
PILES, FURNISHED
507E00700 16,660.000 FT 16" CAST-IN-PLACE REINFORCED CONCRETE 17.3126 15.6166 $260,173.00
PILES, DRIVEN
507E00750 17,625.000 FT 16" CAST-IN-PLACE REINFORCED CONCRETE 47.8145 43.9223 $774,130.00
PILES, FURNISHED
507E00880 450.000 FT 20" CAST-IN-PLACE REINFORCED CONCRETE 13.3571 8.0000 $3,600.00
PILES, DRIVEN
507E00890 500.000 FT 20" CAST-IN-PLACE REINFORCED CONCRETE 78.9286 100.0000 $50,000.00
PILES, FURNISHED
507E71200 6,380.000 FT SPECIAL - PILE ENCASEMENT 160.9141 129.7599 $827,868.18
507E92201 918.000 FT PREBORED HOLES, AS PER PLAN 95.5852 60.9139 $55,919.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
63 | P a g e
507E93300 752.000 EACH STEEL POINTS OR SHOES 112.7002 111.8469 $84,108.86
507E93301 510.000 EACH STEEL POINTS, OR SHOES, AS PER PLAN 96.0831 81.9686 $41,804.00
507E98000 4,422.950 FT PILING, MISC.: 94.2623 96.3446 $426,127.55
509E10000 23636983.000 LB EPOXY COATED REINFORCING STEEL 1.1926 1.0058 $23,774,894.30
509E10001 5,289,328.000 LB EPOXY COATED REINFORCING STEEL, AS PER 1.1804 1.2045 $6,371,097.28
PLAN
509E20001 84,000.000 LB REINFORCING STEEL, REPLACEMENT OF 1.2310 1.0244 $86,049.00
EXISTING REINFORCING STEEL, AS PER PLAN
509E25000 145,304.000 LB REINFORCING STEEL 1.2906 1.0249 $148,919.68
509E25001 174,894.000 LB REINFORCING STEEL, AS PER PLAN 1.8567 1.5484 $270,806.90
510E09950 1,476.000 EACH DOWEL HOLES WITH CEMENT GROUT 19.5990 16.6694 $24,604.00
510E10000 38,624.000 EACH DOWEL HOLES WITH NONSHRINK, NONMETALLIC 20.1305 21.4153 $827,142.92
GROUT
510E10001 2,559.000 EACH DOWEL HOLES WITH NONSHRINK, NONMETALLIC 18.7503 14.3423 $36,702.00
GROUT, AS PER PLAN
511E21522 1,402.000 CY CLASS QC2 CONCRETE WITH QC/QA, 686.6667 700.0000 $981,400.00
SUPERSTRUCTURE
511E21534 338.000 CY CLASS QC2 CONCRETE WITH QC/QA, 950.0000 1,150.0000 $388,700.00
SUPERSTRUCTURE
511E21535 202.000 CY CLASS QC2 CONCRETE WITH QC/QA, 776.3400 864.7000 $174,669.40
SUPERSTRUCTURE, AS PER PLAN
511E31500 195.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 502.8889 250.0000 $48,750.00
511E31502 249.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 598.6375 650.0000 $161,850.00
511E31506 144.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 698.8791 475.0000 $68,400.00
511E31600 300.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 592.8493 614.4500 $184,335.00
511E31601 230.000 CY CLASS S CONCRETE, SUPERSTRUCTURE, AS PER 661.0999 460.4233 $105,897.35
PLAN
511E31612 33.000 CY CLASS QC2 CONCRETE WITH QC/QA, 808.5000 975.0000 $32,175.00
SUPERSTRUCTURE
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
64 | P a g e
511E32200 662.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 776.8149 732.2729 $484,764.64
511E32201 447.100 CY CLASS S CONCRETE, SUPERSTRUCTURE, AS PER 833.2804 685.3934 $306,439.40
PLAN
511E32205 7.000 CY CLASS S CONCRETE, SUPERSTRUCTURE, AS PER 1,409.2857 1,350.0000 $9,450.00
PLAN
511E32210 37.000 CY CLASS QC2 CONCRETE, SUPERSTRUCTURE 847.2000 1,256.0000 $46,472.00
511E33300 226.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 679.3333 770.0000 $174,020.00
511E33310 128.400 CY CLASS QC2 CONCRETE, SUPERSTRUCTURE 1,047.8234 992.2508 $127,405.00
511E33312 262.000 CY CLASS QC2 CONCRETE WITH QC/QA, 686.1667 600.0000 $157,200.00
SUPERSTRUCTURE
511E33402 2.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 2,759.6700 3,790.0000 $7,580.00
511E33412 105.000 CY CLASS QC2 CONCRETE, SUPERSTRUCTURE 776.6667 625.0000 $65,625.00
511E33413 10.000 CY CLASS QC2 CONCRETE, SUPERSTRUCTURE, AS 1,044.9400 1,044.9400 $10,449.40
PER PLAN
511E33414 67.000 CY CLASS QC2 CONCRETE WITH QC/QA, 1,124.0000 495.0000 $33,165.00
SUPERSTRUCTURE
511E34000 32.000 CY CLASS S CONCRETE, SUPERSTRUCTURE 869.0000 869.0000 $27,808.00
511E34013 1,532.000 CY CLASS QC2 CONCRETE WITH QC/QA, 388.3333 320.0000 $490,240.00
SUPERSTRUCTURE, AS PER PLAN
511E34400 1,018.300 CY CLASS S CONCRETE, SUPERSTRUCTURE 961.3683 864.8437 $880,670.30
511E34401 97.200 CY CLASS S CONCRETE, SUPERSTRUCTURE, AS PER 1,167.9751 1,162.9430 $113,038.06
PLAN
511E34410 90.000 CY CLASS QC2 CONCRETE, SUPERSTRUCTURE 1,236.8373 978.4500 $88,060.50
511E34411 5.000 CY CLASS QC2 CONCRETE, SUPERSTRUCTURE, AS 1,983.4700 1,836.4140 $9,182.07
PER PLAN
511E34413 19.000 CY CLASS QC2 CONCRETE WITH QC/QA, 986.7500 979.0000 $18,601.00
SUPERSTRUCTURE, AS PER PLAN
511E34434 416.500 CY CLASS S CONCRETE, BRIDGE DECK 803.0914 649.9400 $270,700.00
511E34435 239.000 CY CLASS S CONCRETE, BRIDGE DECK, AS PER PLAN 622.0000 630.0000 $150,570.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
65 | P a g e
511E34436 120.000 CY CLASS S CONCRETE, BRIDGE DECK (PARAPET) 614.3902 502.6250 $60,315.00
511E34437 73.000 CY CLASS S CONCRETE, BRIDGE DECK (PARAPET), 679.5475 654.1096 $47,750.00
AS PER PLAN
511E34444 1,874.500 CY CLASS QC2 CONCRETE, BRIDGE DECK 572.6469 492.2454 $922,714.00
511E34445 228.000 CY CLASS QC2 CONCRETE, BRIDGE DECK, AS PER 764.1667 700.0000 $159,600.00
PLAN
511E34446 2,777.000 CY CLASS QC2 CONCRETE WITH QC/QA, BRIDGE 619.1177 544.4887 $1,512,045.14
DECK
511E34447 745.000 CY CLASS QC2 CONCRETE WITH QC/QA, BRIDGE 598.3921 648.9195 $483,445.00
DECK, AS PER PLAN
511E34448 372.000 CY CLASS QC2 CONCRETE, BRIDGE DECK 525.9874 474.9892 $176,696.00
(PARAPET)
511E34449 93.000 CY CLASS QC2 CONCRETE, BRIDGE DECK 756.6949 865.2688 $80,470.00
(PARAPET), AS PER PLAN
511E34450 1,096.000 CY CLASS S CONCRETE, MISC.: 463.5342 493.7359 $541,134.53
511E34451 105.000 CY CLASS QC2 CONCRETE WITH QC/QA, BRIDGE 763.3333 880.0000 $92,400.00
DECK (PARAPET), AS PER PLAN
511E34500 48.000 CY CLASS C CONCRETE, BEAMS AND DIAPHRAGMS 532.8383 210.0000 $10,080.00
511E40500 247.000 CY CLASS C CONCRETE, PIER ABOVE FOOTINGS 480.5214 430.0000 $106,210.00
511E40512 641.000 CY CLASS QC1 CONCRETE WITH QC/QA, PIER 634.1963 661.9023 $424,279.35
ABOVE FOOTINGS
511E41000 861.000 CY CLASS C CONCRETE, PIER ABOVE FOOTINGS 882.8585 850.9071 $732,631.04
511E41010 242.000 CY CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS 807.4650 835.8471 $202,275.00
511E41012 235.000 CY CLASS QC1 CONCRETE WITH QC/QA, PIER 837.3853 622.6693 $146,327.28
ABOVE FOOTINGS
511E41013 48.000 CY CLASS QC1 CONCRETE WITH QC/QA, PIER 903.3333 1,100.0000 $52,800.00
ABOVE FOOTINGS, AS PER PLAN
511E41510 4.500 CY CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS 2,225.8000 1,268.0000 $5,706.00
511E42000 71.000 CY CLASS C CONCRETE, PIER ABOVE FOOTINGS 1,095.4444 1,200.0000 $85,200.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
66 | P a g e
511E42010 909.000 CY CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS 514.0033 450.2640 $409,290.00
511E42500 64.300 CY CLASS C CONCRETE, PIER CAP 1,376.4614 1,412.9393 $90,852.00
511E42510 109.000 CY CLASS QC1 CONCRETE, PIER CAP 1,118.0810 994.4128 $108,391.00
511E43000 25.000 CY CLASS C CONCRETE, PIER 940.5000 700.0000 $17,500.00
511E43200 532.000 CY CLASS C CONCRETE, PIER 796.0238 745.3517 $396,527.12
511E43201 13.000 CY CLASS C CONCRETE, PIER, AS PER PLAN 1,394.0000 1,394.0000 $18,122.00
511E43250 14.300 CY CLASS S CONCRETE, PIER CAP 1,544.5000 1,173.0000 $16,773.90
511E43500 1,476.000 CY CLASS C CONCRETE, ABUTMENT INCLUDING 503.0253 492.7934 $727,363.00
FOOTING
511E43501 1,526.000 CY CLASS C CONCRETE, ABUTMENT INCLUDING 496.8703 455.4513 $695,018.64
FOOTING, AS PER PLAN
511E43510 368.000 CY CLASS QC1 CONCRETE, ABUTMENT INCLUDING 572.0061 571.2092 $210,205.00
FOOTING
511E43512 308.000 CY CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT 541.4511 684.8701 $210,940.00
INCLUDING FOOTING
511E43513 213.000 CY CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT 405.0000 300.0000 $63,900.00
INCLUDING FOOTING, AS PER PLAN
511E44100 1,193.000 CY CLASS C CONCRETE, ABUTMENT NOT INCLUDING 577.4547 572.7373 $683,275.57
FOOTING
511E44101 45.000 CY CLASS C CONCRETE, ABUTMENT NOT INCLUDING 537.5000 450.0000 $20,250.00
FOOTING, AS PER PLAN
511E44110 704.000 CY CLASS QC1 CONCRETE, ABUTMENT NOT 441.2043 372.1094 $261,965.00
INCLUDING FOOTING
511E44112 215.000 CY CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT 557.8360 575.7518 $123,786.63
NOT INCLUDING FOOTING
511E45500 287.000 CY CLASS C CONCRETE, ABUTMENT 563.7690 637.9617 $183,095.00
511E45501 1.000 CY CLASS C CONCRETE, ABUTMENT, AS PER PLAN 1,769.9740 2,662.0000 $2,662.00
511E45510 39.000 CY CLASS QC1 CONCRETE, ABUTMENT 738.1330 746.1538 $29,100.00
511E45511 16.000 CY CLASS QC1 CONCRETE, ABUTMENT, AS PER 841.8800 940.0000 $15,040.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
67 | P a g e
511E45700 978.500 CY CLASS C CONCRETE, ABUTMENT 683.4372 609.1418 $596,045.21
511E45701 54.000 CY CLASS C CONCRETE, ABUTMENT, AS PER PLAN 859.8982 889.0741 $48,010.00
511E45710 183.000 CY CLASS QC1 CONCRETE, ABUTMENT 653.5288 565.9071 $103,561.00
511E45711 5.000 CY CLASS QC1 CONCRETE, ABUTMENT, AS PER 2,600.1000 2,581.5000 $12,907.50
PLAN
511E45712 95.000 CY CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT 661.8263 653.9474 $62,125.00
511E46000 1,400.370 CY CLASS C CONCRETE 709.2959 619.1595 $867,052.37
511E46001 171.000 CY CLASS C CONCRETE, AS PER PLAN 833.0025 768.9883 $131,497.00
511E46010 493.000 CY CLASS QC1 CONCRETE 548.8480 500.0063 $246,503.10
511E46011 50.000 CY CLASS QC1 CONCRETE, AS PER PLAN 1,324.8447 1,250.0000 $62,500.00
511E46200 1,215.000 CY CLASS C CONCRETE 532.6937 546.9177 $664,505.00
511E46201 1.500 CY CLASS C CONCRETE, AS PER PLAN 1,616.6125 1,000.0000 $1,500.00
511E46210 624.000 CY CLASS QC1 CONCRETE 481.1744 412.4341 $257,358.85
511E46500 4,147.000 CY CLASS C CONCRETE, FOOTING 372.4297 334.6362 $1,387,736.18
511E46501 263.000 CY CLASS C CONCRETE, FOOTING, AS PER PLAN 512.2117 432.2738 $113,688.00
511E46510 2,509.000 CY CLASS QC1 CONCRETE, FOOTING 343.7683 334.1068 $838,273.90
511E46511 164.000 CY CLASS QC1 CONCRETE, FOOTING, AS PER PLAN 565.9712 369.3724 $60,577.08
511E46512 545.000 CY CLASS QC1 CONCRETE WITH QC/QA, FOOTING 381.3721 417.4583 $227,514.78
511E46600 163.020 CY CLASS C CONCRETE, HEADWALL 1,094.7422 1,061.2897 $173,011.45
511E46601 16.500 CY CLASS C CONCRETE, HEADWALL, AS PER PLAN 963.4575 514.5491 $8,490.06
511E46610 26.960 CY CLASS QC1 CONCRETE, HEADWALL 753.1923 719.3249 $19,393.00
511E46611 81.600 CY CLASS QC1 CONCRETE, HEADWALL, AS PER 956.9463 593.8900 $48,461.42
PLAN
511E47000 95.100 CY CLASS C CONCRETE, CULVERT 714.1423 505.7834 $48,100.00
511E50000 318.000 CY CLASS HP CONCRETE, BRIDGE DECK 701.0917 724.9686 $230,540.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
68 | P a g e
511E50001 10,192.000 CY CLASS HP CONCRETE, BRIDGE DECK, AS PER 598.6881 597.9007 $6,093,803.44
PLAN
511E50100 64.000 CY CLASS HP CONCRETE, BRIDGE DECK (PARAPET) 740.1250 400.0000 $25,600.00
511E50101 1,633.000 CY CLASS HP CONCRETE, BRIDGE DECK 488.1996 477.4478 $779,672.20
(PARAPET), AS PER PLAN
511E50200 139.000 CY CLASS HP CONCRETE, SUBSTRUCTURE 756.2500 650.0000 $90,350.00
511E50201 907.000 CY CLASS HP CONCRETE, SUBSTRUCTURE, AS PER 705.1591 625.4686 $567,300.00
PLAN
511E50210 119.100 CY CLASS QC1 CONCRETE, SUBSTRUCTURE 772.4757 474.3872 $56,499.52
511E50212 6.000 CY CLASS QC1 CONCRETE WITH QC/QA, 1,136.8000 600.0000 $3,600.00
SUBSTRUCTURE
511E51001 797.000 CY CLASS HP CONCRETE, SUPERSTRUCTURE, AS 530.1761 538.9074 $429,509.20
PER PLAN
511E51501 271.000 CY CLASS HP CONCRETE, SIDEWALK, AS PER PLAN 333.0450 269.7196 $73,094.00
511E52000 31.000 LS CLASS HP CONCRETE, TEST SLAB 781.3886 680.6452 $21,100.00
511E53000 39.000 CY CLASS HP CONCRETE, MISC.: 1,456.6667 1,000.0000 $39,000.00
511E53010 1,146.000 CY CLASS QC1 CONCRETE, MISC.: 539.9556 358.0404 $410,314.31
511E53012 1,755.000 CY CLASS QC2 CONCRETE, MISC.: 448.5639 422.8680 $742,133.42
511E53014 13.000 CY CLASS QC3 CONCRETE, MISC.: 564.2000 125.0000 $1,625.00
511E60000 1,949.000 SY SPECIAL - BRIDGE DECK GROOVING 4.8818 4.8332 $9,419.89
511E71100 1,191.300 CY CONCRETE, MISC.: 501.0095 465.5465 $554,605.49
511E71200 59,764.000 SF CONCRETE, MISC.: 16.1139 11.8812 $710,065.25
511E71300 210.000 SY CONCRETE, MISC.: 94.5400 109.0000 $22,890.00
511E81100 4,060.000 FT CONCRETE, MISC.: 43.6667 65.0000 $263,900.00
511E81200 1.000 LS CONCRETE, MISC.: 5,540.0000 3,700.0000 $3,700.00
511E81300 12,790.000 EACH CONCRETE, MISC.: 94.4032 82.1725 $1,050,985.72
511E81500 717.000 CF CONCRETE, MISC.: 264.9516 229.6792 $164,680.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
69 | P a g e
512E10000 543.000 SY SEALING OF CONCRETE SURFACES 22.3696 31.4309 $17,067.00
512E10001 18,513.000 SY SEALING OF CONCRETE SURFACES, AS PER 16.6589 17.0786 $316,175.20
PLAN
512E10050 56,918.000 SY SEALING OF CONCRETE SURFACES (NON-EPOXY) 9.2699 8.6419 $491,881.35
512E10051 27,787.000 SY SEALING OF CONCRETE SURFACES 8.5205 6.7793 $188,375.93
(NON-EPOXY), AS PER PLAN
512E10100 207,551.400 SY SEALING OF CONCRETE SURFACES 19.2884 16.8455 $3,496,313.95
(EPOXY-URETHANE)
512E10101 48,028.000 SY SEALING OF CONCRETE SURFACES 17.0396 18.5228 $889,613.50
(EPOXY-URETHANE), AS PER PLAN
512E10300 9,324.000 SY SEALING CONCRETE BRIDGE DECKS WITH HMWM 20.0071 20.8759 $194,646.98
RESIN
512E10400 76,135.360 SY TREATING OF CONCRETE BRIDGE DECK WITH 8.3343 7.8219 $595,524.99
SRS
512E10401 7,122.000 SY TREATING OF CONCRETE BRIDGE DECK WITH 8.6220 8.2910 $59,048.74
SRS, AS PER PLAN
512E10600 1,033.300 FT CONCRETE REPAIR BY EPOXY INJECTION 93.3799 113.0991 $116,865.34
512E10601 782.000 FT CONCRETE REPAIR BY EPOXY INJECTION, AS 106.8434 91.4396 $71,505.80
PER PLAN
512E33000 19,661.000 SY TYPE 2 WATERPROOFING 20.3586 19.5860 $385,080.94
512E33001 1,745.000 SY TYPE 2 WATERPROOFING, AS PER PLAN 27.8694 31.7387 $55,384.00
512E33010 19,669.000 SY TYPE 3 WATERPROOFING 27.9794 27.8123 $547,040.83
512E33011 342.000 SY TYPE 3 WATERPROOFING, AS PER PLAN 28.8333 28.0000 $9,576.00
512E33300 2,580.000 SY TYPE A WATERPROOFING 19.0569 14.2976 $36,887.77
512E44400 2,515.700 SY TYPE B WATERPROOFING 30.9808 34.4036 $86,549.18
512E44401 25.000 SY TYPE B WATERPROOFING, AS PER PLAN 63.8590 90.0000 $2,250.00
512E56100 1,541.000 SY SPECIAL - BUTYL RUBBER MEMBRANE 48.8182 48.4796 $74,707.00
WATERPROOFING
512E56202 3,468.000 SY SPECIAL - ASPHALTIC PANEL 46.2435 32.1915 $111,640.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
70 | P a g e
512E67200 2,477.000 SY SPECIAL - WATERPROOFING, MISC.: 54.6678 52.4247 $129,856.00
512E67400 55,427.000 SF SPECIAL - WATERPROOFING, MISC.: 1.1436 0.7000 $38,798.90
512E71500 279.000 SY SPECIAL - URETHANE TOP COAT SEALER 23.6451 20.3598 $5,680.38
512E73500 22,805.000 SY SPECIAL - TREATING CONCRETE BRIDGE DECKS 15.0194 14.0069 $319,427.45
WITH GRAVITY FED RESIN
512E73501 2,337.000 SY TREATING CONCRETE BRIDGE DECKS WITH 16.7341 18.0351 $42,148.04
GRAVITY FED RESIN, AS PER PLAN
512E74000 76,877.000 SY REMOVAL OF EXISTING COATINGS FROM 13.2812 12.6085 $969,302.24
CONCRETE SURFACES
512E75000 51.000 FT SPECIAL - SEALING, MISC.: 29.6756 15.7500 $803.25
512E75010 2,182.000 SF SPECIAL - SEALING, MISC.: 16.4506 15.5605 $33,953.00
512E75500 2,145.000 SY SPECIAL - SEALING, MISC.: 13.6281 19.0523 $40,867.20
512E99000 34.000 LS SPECIAL - SEALING OF CONCRETE 15,524.9558 20,057.7206 $681,962.50
513E10001 6.000 LS STRUCTURAL STEEL MEMBERS, LEVEL UF, AS 14,078.5185 15,500.0000 $93,000.00
PER PLAN
513E10080 1.000 LS STRUCTURAL STEEL MEMBERS, LEVEL 4 1173234.4840 1222172.4200 $1,222,172.42
513E10200 12,111.000 LB STRUCTURAL STEEL MEMBERS, LEVEL UF 9.5718 6.7033 $81,183.25
513E10201 397,514.000 LB STRUCTURAL STEEL MEMBERS, LEVEL UF, AS 9.1835 10.3374 $4,109,269.63
PER PLAN
513E10220 406,200.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 1 1.8267 2.0800 $844,908.10
513E10221 497,178.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 1, AS 2.0213 1.5647 $777,938.13
PER PLAN
513E10240 3,637,673.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 2 24.1216 1.3674 $4,974,031.68
513E10241 462,618.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 2, AS 1.6618 1.6762 $775,422.64
PER PLAN
513E10260 5,051,896.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 3 1.2169 1.1728 $5,924,833.27
513E10261 1,975,278.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 3, AS 1.4666 1.5253 $3,012,904.05
PER PLAN
513E10280 5,504,242.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 4 1.5242 1.4921 $8,212,876.54
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
71 | P a g e
513E10281 5,347,846.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 4, AS 1.6252 1.6057 $8,586,997.65
PER PLAN
513E10300 3,028,247.000 LB STRUCTURAL STEEL MEMBERS, LEVEL 5 1.5237 1.5516 $4,698,626.92
513E15001 28.000 EACH STRUCTURAL STEEL MEMBERS, SPECIALIZED 4,841.6667 4,240.0000 $118,720.00
MULTI ROTATIONAL BEARING (SMR), LEVEL UF, AS PER PLAN
513E17001 85.000 EACH STRUCTURAL STEEL MEMBERS, MODULAR 988.3333 915.0000 $77,775.00
EXPANSION JOINT, LEVEL UF, AS PER PLAN
513E20000 524,996.000 EACH WELDED STUD SHEAR CONNECTORS 3.7545 3.1375 $1,647,181.35
513E20001 17,632.000 EACH WELDED STUD SHEAR CONNECTORS, AS PER 3.3704 3.2000 $56,422.40
PLAN
513E21000 43.000 EACH TRIMMING OF BEAM END 264.8563 201.1660 $8,650.14
513E21001 78.000 EACH TRIMMING OF BEAM END, AS PER PLAN 317.2479 338.1410 $26,375.00
513E21500 8,662.000 LB REPLACEMENT OF DETERIORATED END 5.8471 4.5470 $39,386.00
CROSSFRAMES
513E21501 49,075.000 LB REPLACEMENT OF DETERIORATED END 4.0362 3.7602 $184,532.50
CROSSFRAMES, AS PER PLAN
513E21600 15,531.000 LB STRUCTURAL STEEL FOR REHABILITATION, AS 6.7569 6.5244 $101,329.80
PER PLAN
513E90000 527,898.000 LB STRUCTURAL STEEL, MISC.: 1.3671 1.6100 $849,891.90
513E95000 12,253.100 FT STRUCTURAL STEEL, MISC.: 27.0658 24.1182 $295,522.35
513E95020 14.000 LS STRUCTURAL STEEL, MISC.: 10,442.3385 10,601.9693 $148,427.57
513E95030 23,389.000 EACH STRUCTURAL STEEL, MISC.: 79.7048 46.1917 $1,080,376.86
513E95050 1,178.000 SF STRUCTURAL STEEL, MISC.: 28.2500 34.0000 $40,052.00
514E00050 1,028,369.000 SF SURFACE PREPARATION OF EXISTING 8.6604 7.9762 $8,202,465.49
STRUCTURAL STEEL
514E00051 580,788.000 SF SURFACE PREPARATION OF EXISTING 12.5847 11.9901 $6,963,683.75
STRUCTURAL STEEL, AS PER PLAN
514E00056 1,569,309.000 SF FIELD PAINTING OF EXISTING STRUCTURAL 2.1290 1.5280 $2,397,955.15
STEEL, PRIME COAT
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
72 | P a g e
514E00057 18,778.000 SF FIELD PAINTING OF EXISTING STRUCTURAL 3.3033 2.9480 $55,357.50
STEEL, PRIME COAT, AS PER PLAN
514E00060 1,948,657.000 SF FIELD PAINTING STRUCTURAL STEEL, 2.2787 2.0953 $4,083,017.00
INTERMEDIATE COAT SYSTEM OZEU
514E00061 41,995.000 SF FIELD PAINTING STRUCTURAL STEEL, 3.5705 3.7748 $158,521.35
INTERMEDIATE COAT, AS PER PLAN
514E00066 1,235,850.000 SF FIELD PAINTING STRUCTURAL STEEL, FINISH 2.2992 1.7584 $2,173,173.59
COAT
514E00067 754,802.000 SF FIELD PAINTING STRUCTURAL STEEL, FINISH 1.7237 1.4858 $1,121,475.48
COAT, AS PER PLAN
514E00100 25.000 LS SURFACE PREPARATION OF EXISTING 73,039.6860 68,442.4800 $1,711,062.00
STRUCTURAL STEEL
514E00200 26.000 LS FIELD PAINTING OF EXISTING STRUCTURAL 17,668.1581 14,136.4615 $367,548.00
STEEL, PRIME COAT
514E00300 27.000 LS FIELD PAINTING STRUCTURAL STEEL, 17,384.1485 14,638.8148 $395,248.00
INTERMEDIATE COAT SYSTEM OZEU
514E00400 27.000 LS FIELD PAINTING STRUCTURAL STEEL, FINISH 16,232.6085 12,762.7407 $344,594.00
COAT SYSTEM OZEU
514E00504 2,343.000 MNHR GRINDING FINS, TEARS, SLIVERS ON 102.1379 93.4094 $218,858.32
EXISTING STRUCTURAL STEEL
514E00505 18.000 MNHR GRINDING FINS, TEARS, SLIVERS ON 125.2933 125.0000 $2,250.00
EXISTING STRUCTURAL STEEL, AS PER PLAN
514E10000 1,389.000 EACH FINAL INSPECTION REPAIR 315.9160 266.2960 $369,885.16
514E20001 2,027.000 SF FIELD PAINTING OF DAMAGED STRUCTURAL 158.2474 49.8420 $101,029.67
STEEL, AS PER PLAN PLAN
514E27700 44,359.000 SF FIELD PAINTING, MISC.: 31.1517 30.9702 $1,373,808.60
514E27710 432.000 FT FIELD PAINTING, MISC.: 62.7963 20.5000 $8,856.00
514E27800 10.000 LS FIELD PAINTING, MISC.: 61,032.8336 43,390.8510 $433,908.51
514E80010 2,623,500.000 LB SPECIAL - SHOP PAINTING AND FIELD 0.3472 0.3828 $1,004,240.00
TOUCH-UP OF STRUCTURAL STEEL
514E99000 7.000 LS SPECIAL - BRIDGE PAINTING 250,682.8614 263,898.5800 $1,847,290.06
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
73 | P a g e
515E10031 5.000 EACH PRESTRESSED CONCRETE NON-COMPOSITE BOX 10,680.0000 14,100.0000 $70,500.00
BEAM BRIDGE MEMBERS, LEVEL 1, B17-48, AS PER PLAN
515E10070 18.000 EACH PRESTRESSED CONCRETE NON-COMPOSITE BOX 14,268.1200 12,832.0000 $230,976.00
BEAM BRIDGE MEMBERS, LEVEL 1, B27-48
515E12020 8.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 9,335.7500 9,250.0000 $74,000.00
BRIDGE MEMBERS, LEVEL 1, CB17-36
515E12030 33.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 6,733.3333 6,350.0000 $209,550.00
BRIDGE MEMBERS, LEVEL 1, CB17-48
515E12040 21.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 11,107.2394 10,957.1429 $230,100.00
BRIDGE MEMBERS, LEVEL 1, CB21-36
515E12050 32.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 11,802.6527 11,725.0000 $375,200.00
BRIDGE MEMBERS, LEVEL 1, CB21-48
515E12070 12.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 13,835.7143 14,600.0000 $175,200.00
BRIDGE MEMBERS, LEVEL 1, CB27-48
515E12071 19.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 13,337.6842 12,047.3684 $228,900.00
BRIDGE MEMBERS, LEVEL 1, CB27-48, AS PER PLAN
515E12090 8.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 23,608.3333 18,125.0000 $145,000.00
BRIDGE MEMBERS, LEVEL 1, CB33-48
515E12091 15.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 19,707.2329 19,351.1187 $290,266.78
BRIDGE MEMBERS, LEVEL 1, CB33-48, AS PER PLAN
515E12100 1.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 23,000.0000 30,000.0000 $30,000.00
BRIDGE MEMBERS, LEVEL 1, CB42-36
515E12110 57.000 EACH PRESTRESSED CONCRETE COMPOSITE BOX BEAM 18,366.5098 17,275.4386 $984,700.00
BRIDGE MEMBERS, LEVEL 1, CB42-48
515E14020 32.000 EACH STRAIGHT STRAND PRESTRESSED CONCRETE 12,800.0000 12,800.0000 $409,600.00
BRIDGE I-BEAM MEMBERS, LEVEL 2, TYPE 4
515E15000 10.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 11,732.8493 11,200.0000 $112,000.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 2
515E15010 18.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 12,800.0000 12,800.0000 $230,400.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 3
515E15011 12.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 13,730.0000 14,500.0000 $174,000.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 3, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
74 | P a g e
515E15020 75.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 14,805.8185 13,269.3333 $995,200.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 4
515E15030 46.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 35,647.3885 31,647.8261 $1,455,800.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 4 MOD. (60 IN.)
515E15040 46.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 21,725.0000 20,356.5217 $936,400.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 4 MOD. (66")
515E15050 15.000 EACH DRAPED STRAND PRESTRESSED CONCRETE 40,635.3543 43,583.3333 $653,750.00
BRIDGE I-BEAM MEMBERS, LEVEL 3, TYPE 4 MOD. (72")
515E20000 329.000 EACH INTERMEDIATE DIAPHRAMS 1,299.1578 1,189.3769 $391,305.00
515E20001 19.000 EACH INTERMEDIATE DIAPHRAMS, AS PER PLAN 1,436.3066 1,394.7368 $26,500.00
515E30000 1,402.000 FT HIGH EARLY STRENGTH KEYWAY GROUT 29.2928 23.2036 $32,531.50
516E01301 860.000 FT ELASTOMERIC STRIP SEAL WITHOUT STEEL 71.7797 69.9360 $60,145.00
EXTRUSIONS, AS PER PLAN
516E10000 698.000 FT PREFORMED ELASTOMERIC COMPRESSION JOINT 50.9616 31.7908 $22,190.00
SEAL
516E10001 757.000 FT PREFORMED ELASTOMERIC COMPRESSION JOINT 54.8211 42.9250 $32,494.22
SEAL, AS PER PLAN
516E10500 72.000 FT STRUCTURAL EXPANSION JOINT INCLUDING 520.0000 520.0000 $37,440.00
ELASTOMERIC COMPRESSION SEAL
516E10501 170.000 FT STRUCTURAL EXPANSION JOINT INCLUDING 390.6590 438.0529 $74,469.00
ELASTOMERIC COMPRESSION SEAL, AS PER
PLAN
516E10900 148.000 FT ELASTOMERIC COMPRESSION SEAL 71.9358 88.3668 $13,078.28
516E10901 853.000 FT ELASTOMERIC COMPRESSION SEAL, AS PER 102.0414 111.6178 $95,210.00
PLAN
516E11210 2,349.500 FT STRUCTURAL EXPANSION JOINT INCLUDING 431.4897 424.0182 $996,230.85
ELASTOMERIC STRIP SEAL
516E11211 7,118.200 FT STRUCTURAL EXPANSION JOINT INCLUDING 565.8894 554.7658 $3,948,933.78
ELASTOMERIC STRIP SEAL, AS PER PLAN
516E12201 180.200 FT STRUCTURAL STEEL EXPANSION JOINT, AS PER 371.7910 343.4240 $61,885.00
PLAN
516E12400 112.000 FT SPECIAL - MODULAR EXPANSION JOINT 1,991.6667 1,750.0000 $196,000.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
75 | P a g e
516E13000 74.000 SF 1/4" PREFORMED EXPANSION JOINT FILLER 7.4414 3.4595 $256.00
516E13200 10,160.600 SF 1/2" PREFORMED EXPANSION JOINT FILLER 4.5160 3.8101 $38,712.66
516E13201 388.000 SF 1/2" PREFORMED EXPANSION JOINT FILLER, 21.0000 21.0000 $8,148.00
AS PER PLAN
516E13400 1,014.000 SF 3/4" PREFORMED EXPANSION JOINT FILLER 6.2541 4.4677 $4,530.25
516E13600 64,791.700 SF 1" PREFORMED EXPANSION JOINT FILLER 5.7269 5.3496 $346,611.56
516E13601 476.000 SF 1" PREFORMED EXPANSION JOINT FILLER, AS 15.2022 9.3949 $4,471.95
PER PLAN
516E13900 7,553.000 SF 2" PREFORMED EXPANSION JOINT FILLER 8.1096 7.3976 $55,874.16
516E13901 6,492.000 SF 2" PREFORMED EXPANSION JOINT FILLER, AS 7.6595 7.2351 $46,970.00
PER PLAN
516E14010 78.200 FT SPECIAL - POURED POLYURETHANE JOINT SEAL 42.7800 42.7800 $3,345.40
516E14014 3,162.000 FT INTEGRAL ABUTMENT EXPANSION JOINT SEAL 27.6160 24.1437 $76,342.40
516E14015 566.080 FT INTEGRAL ABUTMENT EXPANSION JOINT SEAL, 28.4463 26.9685 $15,266.35
AS PER PLAN
516E14020 6,699.000 FT SEMI-INTEGRAL ABUTMENT EXPANSION JOINT 30.3248 28.9685 $194,059.93
SEAL
516E14021 2,343.000 FT SEMI-INTEGRAL ABUTMENT EXPANSION JOINT 53.7101 30.5209 $71,510.36
SEAL, AS PER PLAN
516E14600 1,955.000 FT STRUCTURAL JOINT OR JOINT SEALER, MISC.: 104.8974 114.4797 $223,807.72
516E20010 29.000 SF 1" ELASTOMERIC ERECTION STRIP 171.6667 165.0000 $4,785.00
516E25000 2,044.000 SF NYLON REINFORCED NEOPRENE SHEETING 13.3507 15.2869 $31,246.50
516E31000 4,992.000 FT JOINT SEALER 16.4563 12.6840 $63,318.60
516E31001 1,662.000 FT JOINT SEALER, AS PER PLAN 11.6347 12.1354 $20,169.00
516E31010 218.000 FT 2" DEEP JOINT SEALER 8.5767 9.0000 $1,962.00
516E31011 6,292.000 FT 2" DEEP JOINT SEALER, AS PER PLAN 14.8640 16.3408 $102,816.00
516E31200 2,862.000 FT SPECIAL - SAWING AND SEALING BITUMINOUS 18.9858 18.3537 $52,528.20
CONCRETE JOINTS
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
76 | P a g e
516E31250 230.000 FT SPECIAL - SAWING AND SEALING CONCRETE 19.7647 19.7125 $4,533.88
JOINTS
516E31300 3,182.400 FT SPECIAL - POLYMER MODIFIED ASPHALT 124.4898 127.2062 $404,821.10
EXPANSION JOINT SYSTEM
516E31301 84.000 FT SPECIAL - POLYMER MODIFIED ASPHALT 222.0286 200.0000 $16,800.00
EXPANSION JOINT SYSTEM, AS PER PLAN
516E31400 35.040 CY SPECIAL - POLYMER MODIFIED ASPHALT 7,542.2937 7,230.9441 $253,372.28
EXPANSION JOINT SYSTEM
516E31401 0.900 CY SPECIAL - POLYMER MODIFIED ASPHALT 14,949.0000 11,425.0000 $10,282.50
EXPANSION JOINT SYSTEM, AS PER PLAN
516E41100 515.000 EACH 1/8" PREFORMED BEARING PAD 30.1457 20.5440 $10,580.16
516E41200 5.000 SF 1/8" PREFORMED BEARING PAD 43.7500 100.0000 $500.00
516E41600 73.000 SF 1" ELASTOMERIC BEARING PAD 139.2040 69.3400 $5,061.82
516E42000 34.000 EACH ELASTOMERIC BEARING PAD, MISC.: 406.6581 426.4706 $14,500.00
516E42600 314.000 FT ELASTOMERIC BEARING PAD, MISC.: 102.9036 88.7261 $27,860.00
516E43001 36.000 EACH ELASTOMERIC BEARING WITH LOAD PLATE, AS 481.0000 500.0000 $18,000.00
PER PLAN
516E43100 376.000 EACH ELASTOMERIC BEARING WITH INTERNAL 109.4023 87.5511 $32,919.20
LAMINATES ONLY (NEOPRENE)
516E43101 2.000 EACH ELASTOMERIC BEARING WITH INTERNAL 2,050.0000 2,800.0000 $5,600.00
LAMINATES ONLY (NEOPRENE), AS PER PLAN
516E43200 182.000 EACH ELASTOMERIC BEARING WITH INTERNAL 216.5085 260.0486 $47,328.84
LAMINATES ONLY (NEOPRENE)
516E43201 92.000 EACH ELASTOMERIC BEARING WITH INTERNAL 208.5429 169.5652 $15,600.00
LAMINATES ONLY (NEOPRENE), AS PER PLAN
516E43300 32.000 EACH ELASTOMERIC BEARING WITH INTERNAL 216.1811 182.0000 $5,824.00
LAMINATES ONLY (NEOPRENE)
516E44000 211.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,091.6972 975.5924 $205,850.00
LAMINATES AND LOAD PLATE (NEOPRENE)
516E44001 58.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,199.8122 781.0345 $45,300.00
LAMINATES AND LOAD PLATE (NEOPRENE), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
77 | P a g e
516E44100 280.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,185.7059 1,115.7824 $312,419.08
LAMINATES AND LOAD PLATE (NEOPRENE)
516E44101 1,096.000 EACH ELASTOMERIC BEARING WITH INTERNAL 917.2093 906.5369 $993,564.40
LAMINATES AND LOAD PLATE (NEOPRENE), AS PER PLAN
516E44200 159.000 EACH ELASTOMERIC BEARING WITH INTERNAL 922.4172 896.8106 $142,592.88
LAMINATES AND LOAD PLATE (NEOPRENE)
516E44201 754.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,118.9310 1,234.7660 $931,013.60
LAMINATES AND LOAD PLATE (NEOPRENE), AS PER PLAN
516E44300 76.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,255.3284 1,216.0839 $92,422.38
LAMINATES AND LOAD PLATE (NEOPRENE)
516E44301 60.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,627.9688 2,125.3333 $127,520.00
LAMINATES AND LOAD PLATE (NEOPRENE), AS PER PLAN
516E44400 29.000 EACH ELASTOMERIC BEARING WITH INTERNAL 1,423.1044 1,351.7241 $39,200.00
LAMINATES AND LOAD PLATE (NEOPRENE)
516E44401 58.000 EACH ELASTOMERIC BEARING WITH INTERNAL 2,098.9130 2,724.1379 $158,000.00
LAMINATES AND LOAD PLATE (NEOPRENE), AS PER PLAN
516E45304 120.000 EACH REFURBISH BEARING DEVICE 452.5326 533.4333 $64,012.00
516E45305 700.000 EACH REFURBISH BEARING DEVICE, AS PER PLAN 841.9030 538.5012 $376,950.85
516E46000 17.000 EACH BEARING DEVICE, BOLSTER 2,616.6921 2,488.2953 $42,301.02
516E46200 52.000 EACH BEARING DEVICE, ROCKER 2,145.6143 1,798.5342 $93,523.78
516E46201 106.000 EACH BEARING DEVICE, ROCKER, AS PER PLAN 1,595.2877 1,468.4528 $155,656.00
516E46501 270.000 EACH BEARING, PTFE (TEFLON), AS PER PLAN 450.3577 570.2741 $153,974.00
516E46700 32.000 EACH RESET BEARING 291.5686 149.1250 $4,772.00
516E46701 64.000 EACH RESET BEARING, AS PER PLAN 1,198.7342 317.5000 $20,320.00
516E46800 40.000 EACH SPECIAL - REFURBISH AND RESET BEARING 750.0000 750.0000 $30,000.00
516E46801 44.000 EACH REFURBISH AND RESET BEARING, AS PER PLAN 572.0455 309.0909 $13,600.00
516E46900 387.000 EACH BEARING DEVICE, MISC.: 1,049.6849 912.2443 $353,038.56
516E47000 2.000 LS JACKING AND TEMPORARY SUPPORT OF 13,951.8182 8,500.0000 $17,000.00
SUPERSTRUCTURE
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
78 | P a g e
516E47001 122.000 LS JACKING AND TEMPORARY SUPPORT OF 18,200.8407 12,627.3548 $1,540,537.29
SUPERSTRUCTURE, AS PER PLAN
517E70000 7,905.800 FT RAILING (TWIN STEEL TUBE) 136.8219 138.9871 $1,098,803.97
517E70001 7,333.830 FT RAILING (TWIN STEEL TUBE), AS PER PLAN 133.9289 121.8878 $893,904.55
517E71501 308.000 FT RAILING (CONCRETE PARAPET WITH DOUBLE 152.2554 150.0000 $46,200.00
PIPE RAIL), AS PER PLAN
517E72201 75.000 FT RAILING (DEEP BEAM RAIL WITH STEEL 59.2000 60.0000 $4,500.00
TUBULAR BACKUP AND TYPE 1 STEEL POSTS
AND ANCHOR BOLTS), AS PER PLAN
517E72205 39.000 FT RAILING (DEEP BEAM RAIL WITH STEEL 46.9811 45.8974 $1,790.00
TUBULAR BACKUP AND TYPE 1 STEEL POSTS), AS PER PLAN
517E72300 625.630 FT RAILING (DEEP BEAM RAIL WITH STEEL 85.3144 86.7132 $54,250.40
TUBULAR BACKUP AND TYPE 2 STEEL POSTS AND ANCHOR BOLTS)
517E72301 125.000 FT RAILING (DEEP BEAM RAIL WITH STEEL 111.3846 90.7000 $11,337.50
TUBULAR BACKUP AND TYPE 2 STEEL POSTS
AND ANCHOR BOLTS), AS PER PLAN
517E72306 39.000 FT RAILING (DEEP BEAM RAIL WITH STEEL 73.7244 74.8077 $2,917.50
TUBULAR BACKUP AND TYPE 2 STEEL POSTS)
517E72307 1,876.500 FT RAILING (DEEP BEAM RAIL WITH STEEL 92.9953 77.5626 $145,546.25
TUBULAR BACKUP AND TYPE 2 STEEL POSTS), AS PER PLAN
517E72710 1,614.460 FT RAILING (DEEP BEAM BRIDGE RETROFIT 92.7718 92.7013 $149,662.60
RAILING)
517E72750 1,399.000 FT RAILING (THRIE BEAM RETROFIT) 50.1902 48.5001 $67,851.60
517E72751 87.500 FT RAILING (THRIE BEAM RETROFIT), AS PER PLAN 47.7143 47.7143 $4,175.00
517E73501 562.000 FT RAILING, PIPE, AS PER PLAN 128.2276 129.2770 $72,653.66
517E74001 263.000 FT RAILING, TIMBER, AS PER PLAN 201.1000 195.0000 $51,285.00
517E75001 34.000 FT RAILING, ALUMINUM, AS PER PLAN 32.7800 15.0000 $510.00
517E75120 295.000 FT RAILING (CONCRETE PARAPET WITH TWIN 172.2500 150.0000 $44,250.00
STEEL TUBE RAILING)
517E75121 947.170 FT RAILING (CONCRETE PARAPET WITH TWIN 178.6651 138.8408 $131,505.85
STEEL TUBE RAILING), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
79 | P a g e
517E75124 450.000 FT RAILING (CONCRETE PARAPET WITH TWIN 152.0000 155.0000 $69,750.00
STEEL TUBE RAILING), USING HIGH PERFORMANCE CONCRETE
517E75125 131.000 FT RAILING (CONCRETE PARAPET WITH TWIN 154.6333 154.0000 $20,174.00
STEEL TUBE RAILING) USING HIGH PERFORMANCE CONCRETE, AS PER PLAN
517E75301 773.000 FT RAILING, CONCRETE PARAPET WITH CHAIN 443.6400 412.5600 $318,908.88
LINK FENCE, AS PER PLAN
517E75501 341.000 FT BRIDGE RAILING REBUILT, AS PER PLAN 52.4802 57.3167 $19,545.00
517E75600 1,223.000 FT DEEP BEAM BRIDGE RETROFIT RAILING 94.8556 91.6942 $112,142.00
517E76201 3,224.000 FT RAILING FACED, AS PER PLAN 134.7173 107.5676 $346,798.00
517E76300 12,024.500 FT RAILING, MISC.: 248.6995 229.9113 $2,764,568.87
517E76302 684.000 EACH RAILING, MISC.: 267.2195 185.3868 $126,804.60
518E12000 20.000 EACH SCUPPERS, INCLUDING SUPPORTS 1,215.1250 1,236.5000 $24,730.00
518E12200 26.000 EACH SCUPPERS, INCLUDING SUPPORTS 1,098.0392 1,142.3077 $29,700.00
518E12201 49.000 EACH SCUPPERS, INCLUDING SUPPORTS, AS PER 1,786.8763 1,368.8980 $67,076.00
PLAN
518E12300 95.000 EACH SCUPPERS, INCLUDING SUPPORTS 1,782.7643 1,723.4105 $163,724.00
518E12301 1.000 EACH SCUPPERS, INCLUDING SUPPORTS, AS PER PLAN 2,991.8500 2,835.5000 $2,835.50
518E12500 287.000 EACH NEW SCUPPER, MISC.: 201.2429 130.8258 $37,547.00
518E12700 69.000 EACH SCUPPER, VERTICAL EXTENSION 401.7895 351.1159 $24,227.00
518E12701 16.000 EACH SCUPPER, VERTICAL EXTENSION, AS PER PLAN 240.0000 250.0000 $4,000.00
518E12900 26.000 EACH SCUPPER, LENGTHENING 402.4795 362.0192 $9,412.50
518E12901 24.000 EACH SCUPPER, LENGTHENING, AS PER PLAN 655.1404 708.5833 $17,006.00
518E21100 36.000 CY POROUS BACKFILL 95.3333 75.0000 $2,700.00
518E21101 31.000 CY POROUS BACKFILL, AS PER PLAN 86.8257 60.6452 $1,880.00
518E21200 21,189.200 CY POROUS BACKFILL WITH FILTER FABRIC 69.9349 66.7440 $1,414,252.04
518E21201 383.000 CY POROUS BACKFILL WITH FILTER FABRIC, AS 75.1639 67.7937 $25,965.00
PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
80 | P a g e
518E21220 1.000 LS POROUS BACKFILL 1,868.0000 1,500.0000 $1,500.00
518E21230 38.000 LS POROUS BACKFILL WITH FILTER FABRIC 4,813.0582 5,026.8726 $191,021.16
518E21231 12.000 LS POROUS BACKFILL WITH FILTER FABRIC, AS 3,849.0133 3,637.5000 $43,650.00
PER PLAN
518E22200 106.000 SF SPECIAL - STEEL DRIP STRIP 12.7500 10.0000 $1,060.00
518E22300 13,215.900 FT SPECIAL - STEEL DRIP STRIP 11.7695 11.6342 $153,756.36
518E22301 172.000 FT SPECIAL - STEEL DRIP STRIP, AS PER PLAN 18.8667 25.0000 $4,300.00
518E39800 505.000 FT 4" PERFORATED CORRUGATED PLASTIC PIPE 9.6200 10.8178 $5,463.00
518E39900 354.000 FT 4" NON-PERFORATED CORRUGATED PLASTIC 20.9341 28.1356 $9,960.00
PIPE, INCLUDING SPECIALS
518E40000 26,472.250 FT 6" PERFORATED CORRUGATED PLASTIC PIPE 8.7155 7.8273 $207,207.51
518E40001 221.000 FT 6" PERFORATED CORRUGATED PLASTIC PIPE, 10.1032 9.5430 $2,109.00
AS PER PLAN
518E40010 5,370.000 FT 6" NON-PERFORATED CORRUGATED PLASTIC 12.7954 10.4927 $56,345.94
PIPE, INCLUDING SPECIALS
518E40011 3,040.000 FT 6" NON-PERFORATED CORRUGATED PLASTIC 14.7829 12.3562 $37,562.76
PIPE, INCLUDING SPECIALS, AS PER PLAN
518E40012 939.000 FT 6" NON-PERFORATED CORRUGATED PLASTIC 13.8279 18.3783 $17,257.24
PIPE
518E41200 66.000 FT 6" NON-PERFORATED HELICAL CORRUGATED 17.5333 16.0000 $1,056.00
STEEL PIPE, INCLUDING SPECIALS, 707.01
518E42000 1,019.000 FT 8" PERFORATED CORRUGATED PLASTIC PIPE 12.7670 11.5466 $11,766.00
518E42010 288.000 FT 8" NON-PERFORATED CORRUGATED PLASTIC 17.6986 16.6424 $4,793.00
PIPE, INCLUDING SPECIALS
518E42201 831.000 FT 8" PERFORATED CORRUGATED STEEL PIPE, 23.7924 26.8375 $22,302.00
707.01, AS PER PLAN
518E42301 502.000 FT 8" NON-PERFORATED CORRUGATED STEEL PIPE, 34.1057 37.7888 $18,970.00
INCLUDING SPECIALS, 707.01, AS PER PLAN
518E42400 390.000 FT 6" PERFORATED PIPE, INCLUDING SPECIALS 12.0000 9.0000 $3,510.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
81 | P a g e
518E51100 899.000 FT 8" PIPE DOWNSPOUT, INCLUDING SPECIALS 238.7500 220.0000 $197,780.00
518E51200 649.000 FT PIPE DOWNSPOUT, INCLUDING SPECIALS 451.3100 282.0108 $183,025.00
518E60011 245.000 FT TROUGH HORIZONTAL CONDUCTOR, AS PER PLAN 89.7725 53.0000 $12,985.00
518E61400 7.000 EACH SPECIAL - KEYWAY DRAIN 138.0000 138.0000 $966.00
518E62100 1,785.000 FT STRUCTURE DRAINAGE, MISC.: 36.2340 31.3927 $56,036.00
518E62200 10.000 EACH STRUCTURE DRAINAGE, MISC.: 408.7500 245.0000 $2,450.00
518E62600 939.000 SF STRUCTURE DRAINAGE, MISC.: 17.0146 25.4686 $23,915.00
518E63300 3.000 LS STRUCTURE DRAINAGE, MISC.: 48,085.3888 75,666.6667 $227,000.00
519E10000 450.000 SY SPECIAL - PATCHING CONCRETE BRIDGE DECK 231.1305 210.9903 $94,945.64
OVERLAY WITH MICRO- SILICA MODIFIED CONCRETE
519E11100 5,637.000 SF PATCHING CONCRETE STRUCTURE 96.5443 88.1201 $496,733.09
519E11101 35,643.000 SF PATCHING CONCRETE STRUCTURE, AS PER PLAN 78.7171 74.1381 $2,642,505.52
519E11600 261.000 SF SPECIAL - PATCHING CONCRETE STRUCTURE, 132.6812 101.8314 $26,578.00
MISC.:
519E11710 17.000 SY SPECIAL - PATCHING CONCRETE STRUCTURES, 840.5722 823.5294 $14,000.00
MISC.:
519E11720 2,280.000 FT SPECIAL - PATCHING CONCRETE STRUCTURE, 117.1394 107.3088 $244,664.00
MISC.:
519E11900 787.300 CY SPECIAL - PATCHING CONCRETE STRUCTURE, 3,689.0942 3,426.3271 $2,697,547.32
MISC.:
519E12200 75.000 SY SPECIAL - PATCHING CONCRETE BRIDGE DECK 479.8333 466.0000 $34,950.00
- TYPE A
519E12300 3,142.000 SY SPECIAL - PATCHING CONCRETE BRIDGE DECK 267.3445 255.5773 $803,024.00
- TYPE B
519E12304 513.000 SY SPECIAL - PATCHING CONCRETE BRIDGE DECK 347.0888 319.0156 $163,655.00
- TYPE C
519E12500 21.000 SY SPECIAL - PATCHING CONCRETE BRIDGE DECK 790.2174 738.0952 $15,500.00
- TYPE A, B OR C
519E12510 471.000 SY SPECIAL - PATCHING CONCRETE BRIDGE DECK 372.9873 332.4096 $156,564.92
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
82 | P a g e
519E12600 2,226.000 FT SPECIAL - CONCRETE REPAIR BY EPOXY 87.6380 81.0475 $180,411.75
INJECTION
519E12800 23.000 SY SPECIAL - BRIDGE DECK SURFACE 2,562.5000 2,500.0000 $57,500.00
PREPARATION, MISC.:
519E60000 1.000 LS SPECIAL - PATCHING CONCRETE STRUCTURE, MISC.: 8,650.0000 10,400.0000 $10,400.00
520E11100 187.000 SF PNEUMATICALLY PLACED MORTAR 192.5000 85.0000 $15,895.00
522E12200 121.500 FT STRUCTURAL PLATE CORRUGATED METAL 2,277.4000 2,187.0000 $265,720.50
STRUCTURE
523E20000 84.000 EACH DYNAMIC LOAD TESTING 3,635.3208 3,283.6471 $275,826.36
523E20500 14.000 EACH RESTRIKING 1,937.5000 2,300.0000 $32,200.00
524E94500 247.000 FT DRILLED SHAFTS, 24" DIAMETER 129.1840 90.0000 $22,230.00
524E94503 4,303.000 FT DRILLED SHAFTS, 24" DIAMETER, ABOVE 67.9199 58.9594 $253,702.50
BEDROCK, AS PER PLAN
524E94504 113.000 FT DRILLED SHAFTS, 24" DIAMETER, INTO 275.3045 265.9646 $30,054.00
BEDROCK
524E94505 12,789.000 FT DRILLED SHAFTS, 24" DIAMETER, INTO 73.6936 60.7034 $776,336.00
BEDROCK, AS PER PLAN
524E94600 178.000 FT DRILLED SHAFTS, 30" DIAMETER 113.5550 100.0000 $17,800.00
524E94603 3,153.000 FT DRILLED SHAFTS, 30" DIAMETER, ABOVE 73.2302 76.9616 $242,660.00
BEDROCK, AS PER PLAN
524E94604 432.000 FT DRILLED SHAFTS, 30" DIAMETER, INTO 572.2907 365.8032 $158,027.00
BEDROCK
524E94605 9,420.950 FT DRILLED SHAFTS, 30" DIAMETER INTO 149.8047 193.1921 $1,820,052.75
BEDROCK, AS PER PLAN
524E94700 220.000 FT DRILLED SHAFTS, 36" DIAMETER 167.1217 83.8500 $18,447.00
524E94702 6,260.000 FT DRILLED SHAFTS, 36" DIAMETER, ABOVE 198.0357 103.7235 $649,308.98
BEDROCK
524E94703 7,283.000 FT DRILLED SHAFTS, 36" DIAMETER ABOVE 143.6137 137.6569 $1,002,555.48
BEDROCK, AS PER PLAN
524E94704 854.000 FT DRILLED SHAFTS, 36" DIAMETER, INTO 971.5524 691.2961 $590,366.88
BEDROCK
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
83 | P a g e
524E94705 3,827.000 FT DRILLED SHAFTS, 36" DIAMETER, INTO 144.7926 118.9439 $455,198.20
BEDROCK, AS PER PLAN
524E94801 1,187.000 FT DRILLED SHAFTS, 42" DIAMETER, AS PER PLAN 244.3291 252.5971 $299,832.80
524E94802 1,125.000 FT DRILLED SHAFTS, 42" DIAMETER, ABOVE 318.2370 241.3298 $271,496.01
BEDROCK
524E94803 2,865.000 FT DRILLED SHAFTS, 42" DIAMETER, ABOVE 189.2618 227.6653 $652,261.00
BEDROCK, AS PER PLAN
524E94804 76.000 FT DRILLED SHAFTS, 42" DIAMETER, INTO 727.2497 830.4063 $63,110.88
BEDROCK
524E94805 2,311.000 FT DRILLED SHAFTS, 42" DIAMETER, INTO 225.2158 118.4331 $273,699.00
BEDROCK, AS PER PLAN
524E94900 1,519.000 FT DRILLED SHAFTS, 48" DIAMETER 335.3720 519.0191 $788,390.00
524E94901 4,462.000 FT DRILLED SHAFTS, 48" DIAMETER, AS PER 221.0000 210.0000 $937,020.00
PLAN
524E94902 230.000 FT DRILLED SHAFTS, 48" DIAMETER, ABOVE 631.6250 650.9565 $149,720.00
BEDROCK
524E94903 1,513.000 FT DRILLED SHAFTS, 48" DIAMETER ABOVE 406.2505 353.2716 $534,500.00
BEDROCK, AS PER PLAN
524E94904 216.000 FT DRILLED SHAFTS, 48" DIAMETER, INTO 1,089.0741 915.0000 $197,640.00
BEDROCK
524E94905 333.000 FT DRILLED SHAFTS, 48" DIAMETER, INTO 294.8491 177.0721 $58,965.00
BEDROCK, AS PER PLAN
524E94906 544.000 FT DRILLED SHAFTS, 54" DIAMETER, ABOVE 413.8333 635.0000 $345,440.00
BEDROCK
524E94907 91.000 FT DRILLED SHAFTS, 54" DIAMETER, ABOVE 180.2615 117.6154 $10,703.00
BEDROCK, AS PER PLAN
524E94908 144.000 FT DRILLED SHAFTS, 54" DIAMETER, INTO 1,458.0000 1,248.0000 $179,712.00
BEDROCK
524E94909 224.000 FT DRILLED SHAFTS, 54" DIAMETER, INTO 250.7814 195.0893 $43,700.00
BEDROCK, AS PER PLAN
524E94914 66.000 FT DRILLED SHAFTS, 60" DIAMETER, ABOVE 1,035.4167 862.5000 $56,925.00
BEDROCK
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
84 | P a g e
524E94918 166.000 FT DRILLED SHAFTS, 60" DIAMETER, INTO 1,319.0244 1,359.5181 $225,680.00
BEDROCK
524E94930 405.000 FT DRILLED SHAFTS, 66" DIAMETER, ABOVE 446.1643 336.2346 $136,175.00
BEDROCK
524E94931 282.000 FT DRILLED SHAFTS, 66" DIAMETER, ABOVE 290.0000 290.0000 $81,780.00
BEDROCK, AS PER PLAN
524E95000 6,013.850 FT DRILLED SHAFTS, MISC.: 68.0508 47.5717 $286,089.27
524E95100 16.000 EACH DRILLED SHAFTS, MISC.: 2,591.6667 3,000.0000 $48,000.00
524E95200 2.000 LS DRILLED SHAFTS, MISC. 16,858.3333 15,000.0000 $30,000.00
526E10000 753.000 SY REINFORCED CONCRETE APPROACH SLABS 213.2303 245.7718 $185,066.15
(T=12")
526E10001 1,046.000 SY REINFORCED CONCRETE APPROACH SLABS 227.1564 237.6176 $248,548.00
(T=12"), AS PER PLAN
526E15000 1,115.000 SY REINFORCED CONCRETE APPROACH SLABS 228.3571 231.2574 $257,852.00
(T=13")
526E15001 2,154.000 SY REINFORCED CONCRETE APPROACH SLABS 265.2271 190.7370 $410,847.56
(T=13"), AS PER PLAN
526E25000 3,000.000 SY REINFORCED CONCRETE APPROACH SLABS 212.1438 218.2158 $654,647.54
(T=15")
526E25001 9,041.000 SY REINFORCED CONCRETE APPROACH SLABS 227.3351 223.5844 $2,021,426.88
(T=15"), AS PER PLAN
526E30000 611.000 SY REINFORCED CONCRETE APPROACH SLABS 240.8471 252.0376 $153,995.00
(T=17")
526E30001 3,669.000 SY REINFORCED CONCRETE APPROACH SLABS 255.1091 242.5743 $890,005.08
(T=17"), AS PER PLAN
526E98100 128.000 SY APPROACH SLABS, MISC.: 332.9323 406.4063 $52,020.00
526E98200 320.000 FT APPROACH SLABS, MISC.: 15.7781 21.0563 $6,738.00
526E99000 15.000 LS REINFORCED CONCRETE APPROACH SLABS, AS 50,240.8605 59,868.8000 $898,032.00
PER CONCEPTUAL DOCUMENTS
530E00200 71.000 LS SPECIAL - STRUCTURE, MISC.: 55,399.4159 28,027.0631 $1,989,921.48
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
85 | P a g e
530E00400 251,354.000 EACH SPECIAL - STRUCTURE, MISC.: 10.6631 9.0225 $2,267,853.04
530E00520 8.000 DAY SPECIAL - STRUCTURE, MISC.: 1,008.6743 900.0000 $7,200.00
530E00600 55,798.000 SF SPECIAL - STRUCTURE, MISC.: 11.9204 12.6410 $705,345.17
530E00800 2,719.000 SY SPECIAL - STRUCTURE, MISC.: 57.3245 33.3174 $90,590.00
530E01100 277.000 CY SPECIAL - STRUCTURE, MISC.: 87.8430 83.9982 $23,267.50
530E01300 15,882.000 FT SPECIAL - STRUCTURE, MISC.: 28.9580 23.9441 $380,280.00
530E10700 5.060 MFBM SPECIAL - STRUCTURE, MISC.: 15,179.8419 11,745.0593 $59,430.00
530E13000 41,229.000 SF SPECIAL - FORM LINER 7.5821 6.7466 $278,156.05
530E14000 3.000 LS SPECIAL - STRUCTURAL SURVEY AND 9,223.3465 13,333.3333 $40,000.00
MONITORING OF VIBRATION
530E99000 5.000 LS SPECIAL - STRUCTURE FOUNDATION 54,216.9167 33,200.0000 $166,000.00
530E99010 6.000 LS SPECIAL - SUBSTRUCTURE 54,803.9426 37,501.5000 $225,009.00
530E99020 7.000 LS SPECIAL - SUPERSTRUCTURE 208,667.9919 158,985.7143 $1,112,900.00
530E99030 29.000 LS SPECIAL - STRUCTURE REHABILITATION 588,824.0243 477,413.6517 $13,844,995.90
530E99040 14.000 LS SPECIAL - STRUCTURES 892,819.2910 991,407.0000 $13,879,698.00
530E99050 1.000 LS SPECIAL - RETAINING WALL 64,958.4000 6,500.0000 $6,500.00
530E99100 36.000 LS SPECIAL - MISC.: 4874693.5692 5452027.8056 $196,273,001.00
601E10000 281.000 SY RIPRAP 52.9728 29.3915 $8,259.00
601E10001 112.000 SY RIPRAP, AS PER PLAN 38.3825 45.6400 $5,111.68
601E11000 3,090.130 SY RIPRAP USING 6" REINFORCED CONCRETE SLAB 102.2277 95.8009 $296,037.25
601E11001 480.000 SY RIPRAP USING 6" REINFORCED CONCRETE 144.9504 158.4729 $76,067.00
SLAB, AS PER PLAN
601E12000 116.000 SY RIPRAP, WITH GROUT 76.1950 70.9050 $8,224.98
601E20000 21,981.000 SY CRUSHED AGGREGATE SLOPE PROTECTION 24.4131 25.0941 $551,594.04
601E20001 1,055.000 SY CRUSHED AGGREGATE SLOPE PROTECTION, AS 25.1972 19.7621 $20,849.00
PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
86 | P a g e
601E20010 662.000 CY CRUSHED AGGREGATE SLOPE PROTECTION 60.5485 72.7372 $48,152.00
601E20011 238.000 CY CRUSHED AGGREGATE SLOPE PROTECTION, AS 56.6176 38.2353 $9,100.00
PER PLAN
601E21000 7,147.000 SY CONCRETE SLOPE PROTECTION 65.9922 67.5292 $482,631.00
601E21001 977.000 SY CONCRETE SLOPE PROTECTION, AS PER PLAN 117.5217 93.7973 $91,640.00
601E21050 4,891.180 SY TIED CONCRETE BLOCK MAT, TYPE 1 70.4976 70.7827 $346,211.09
601E21060 4,339.000 SY TIED CONCRETE BLOCK MAT, TYPE 2 64.6340 56.3778 $244,623.30
601E21070 1,470.000 SY TIED CONCRETE BLOCK MAT, TYPE 3 67.5516 51.2782 $75,379.00
601E21100 1,905.000 SY SLOPE PROTECTION, MISC.: 55.8645 54.5507 $103,919.00
601E22000 58.000 SY INTERLOCK PRECAST CONCRETE BLOCKS 349.0000 180.0000 $10,440.00
601E25000 1,642.000 CY DUMPED ROCK FILL, TYPE A 70.0577 59.6667 $97,972.80
601E25001 2,411.000 CY DUMPED ROCK FILL, TYPE A, AS PER PLAN 68.1617 50.2500 $121,152.75
601E26000 696.000 CY DUMPED ROCK FILL, TYPE B 86.9480 88.5611 $61,638.56
601E26001 44.000 CY DUMPED ROCK FILL, TYPE B, AS PER PLAN 80.7160 102.0000 $4,488.00
601E27000 361.000 CY DUMPED ROCK FILL, TYPE C 87.4632 84.1828 $30,390.00
601E27001 3,348.000 CY DUMPED ROCK FILL, TYPE C, AS PER PLAN 69.7980 58.8964 $197,185.00
601E28000 484.000 CY DUMPED ROCK FILL, TYPE D 70.4532 73.4554 $35,552.40
601E28001 1,389.000 CY DUMPED ROCK FILL, TYPE D, AS PER PLAN 43.4044 45.6429 $63,398.00
601E28101 105.000 CY DUMPED ROCK FILL, AS PER PLAN 96.6840 97.4200 $10,229.10
601E32000 752.000 CY ROCK CHANNEL PROTECTION, TYPE A WITH 81.9085 62.0336 $46,649.26
FILTER
601E32004 2,297.000 CY ROCK CHANNEL PROTECTION, TYPE A WITH 378.6462 75.5279 $173,487.54
FABRIC FILTER
601E32010 375.000 CY ROCK CHANNEL PROTECTION, TYPE A WITH 104.4554 119.7467 $44,905.00
AGGREGATE FILTER
601E32100 4,121.700 CY ROCK CHANNEL PROTECTION, TYPE B WITH 73.0283 68.6113 $282,795.15
FILTER
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
87 | P a g e
601E32101 65.000 CY ROCK CHANNEL PROTECTION, TYPE B WITH 89.5310 77.5077 $5,038.00
FILTER, AS PER PLAN
601E32104 4,466.680 CY ROCK CHANNEL PROTECTION, TYPE B WITH 75.9555 70.9427 $316,878.56
FABRIC FILTER
601E32110 2,211.000 CY ROCK CHANNEL PROTECTION, TYPE B WITH 95.4306 83.8213 $185,328.88
AGGREGATE FILTER
601E32200 1,794.150 CY ROCK CHANNEL PROTECTION, TYPE C WITH 76.6446 66.3375 $119,019.41
FILTER
601E32204 5,830.410 CY ROCK CHANNEL PROTECTION, TYPE C WITH 81.9111 81.6950 $476,315.54
FABRIC FILTER
601E32205 718.000 CY ROCK CHANNEL PROTECTION, TYPE C WITH 87.9329 81.9345 $58,829.00
FABRIC FILTER, AS PER PLAN
601E32210 2,035.000 CY ROCK CHANNEL PROTECTION, TYPE C WITH 67.0309 64.9352 $132,143.14
AGGREGATE FILTER
601E32300 156.000 CY ROCK CHANNEL PROTECTION, TYPE D WITH 96.1752 80.5449 $12,565.00
FILTER
601E32304 23.000 CY ROCK CHANNEL PROTECTION, TYPE D WITH 106.4790 109.1739 $2,511.00
FABRIC FILTER
601E34100 633.000 CY ROCK CHANNEL PROTECTION, TYPE B WITHOUT 82.6354 64.7867 $41,010.00
FILTER
601E34200 415.000 CY ROCK CHANNEL PROTECTION, TYPE C WITHOUT 50.6928 49.1786 $20,409.10
FILTER
601E34201 57.000 CY ROCK CHANNEL PROTECTION, TYPE C WITHOUT 144.0000 136.8947 $7,803.00
FILTER, AS PER PLAN
601E34300 62.000 CY ROCK CHANNEL PROTECTION, TYPE D WITHOUT 135.4020 98.9842 $6,137.02
FILTER
601E34301 60.000 CY ROCK CHANNEL PROTECTION, TYPE D WITHOUT 127.1800 90.0000 $5,400.00
FILTER, AS PER PLAN
601E34400 135.000 CY ROCK CHANNEL PROTECTION, WITH GROUT 146.7347 101.2593 $13,670.00
601E34401 177.000 CY ROCK CHANNEL PROTECTION, WITH GROUT, AS 165.8202 110.2486 $19,514.00
PER PLAN
601E35000 14,764.000 CY ROCK CHANNEL PROTECTION, MISC.: 53.3901 45.7340 $675,216.80
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
88 | P a g e
601E35100 2.000 LS ROCK CHANNEL PROTECTION, MISC.: 3,327.4530 2,150.0000 $4,300.00
601E37500 2,001.000 FT PAVED GUTTER, TYPE 1-2 55.1080 56.9090 $113,875.00
601E37501 596.000 FT PAVED GUTTER, TYPE 1-2, AS PER PLAN 48.7845 43.0403 $25,652.00
601E38000 302.000 FT PAVED GUTTER, TYPE 1-4 61.4444 62.8892 $18,992.55
601E38101 40.000 FT PAVED GUTTER, TYPE 1-6, AS PER PLAN 155.7500 93.0000 $3,720.00
601E38400 1,169.000 FT PAVED GUTTER, TYPE 2 39.3560 49.3003 $57,632.00
601E38501 341.000 FT PAVED GUTTER, TYPE 3, AS PER PLAN 62.5000 40.0000 $13,640.00
601E39501 8.000 FT PAVED GUTTER, TYPE 5, AS PER PLAN 88.0880 56.5000 $452.00
601E40000 30.000 FT PAVED GUTTER, MISC.: 66.7580 49.7000 $1,491.00
601E40040 32.000 SF PAVED GUTTER, MISC.: 25.7600 22.2800 $712.96
602E10000 4.000 CY BRICK MASONRY 736.5789 1,750.0000 $7,000.00
602E15001 5.000 CY BLOCK MASONRY, AS PER PLAN 583.3333 300.0000 $1,500.00
602E20000 1,016.710 CY CONCRETE MASONRY 1,127.5655 1,086.4842 $1,104,639.40
602E20001 315.460 CY CONCRETE MASONRY, AS PER PLAN 948.4808 828.3485 $261,310.82
602E97000 4,914.000 SF MASONRY, MISC.: 54.7950 44.1870 $217,135.00
602E98000 1.000 LS MASONRY, MISC.: 2,500.0000 5,000.0000 $5,000.00
602E98100 4,122.000 FT MASONRY, MISC.: 15.3479 10.0383 $41,378.00
602E98200 1,570.000 CY MASONRY, MISC.: 692.3943 481.1783 $755,450.00
602E98300 144.000 EACH MASONRY, MISC.: 626.4236 527.7778 $76,000.00
603E00100 2,084.000 FT 4" CONDUIT, TYPE B 17.0960 16.0997 $33,551.85
603E00101 522.000 FT 4" CONDUIT, TYPE B, AS PER PLAN 13.7298 17.5862 $9,180.00
603E00200 1,921.000 FT 4" CONDUIT, TYPE C 14.7044 10.6464 $20,451.70
603E00201 100.000 FT 4" CONDUIT, TYPE C, AS PER PLAN 12.9375 14.7500 $1,475.00
603E00300 200.000 FT 4" CONDUIT, TYPE D 11.5000 10.0000 $2,000.00
603E00400 3,927.000 FT 4" CONDUIT, TYPE E 13.9658 7.8118 $30,677.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
89 | P a g e
603E00401 50.000 FT 4" CONDUIT, TYPE E, AS PER PLAN 6.9167 3.6000 $180.00
603E00406 3,488.900 FT 4" CONDUIT, TYPE F 14.1263 11.9662 $41,748.75
603E00410 3,963.000 FT 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET 14.7900 14.0071 $55,510.16
603E00510 41,733.000 FT 6" CONDUIT, TYPE F FOR UNDERDRAIN 15.5497 12.7504 $532,113.33
OUTLETS
603E00900 14,067.000 FT 6" CONDUIT, TYPE B 18.8956 16.4216 $231,003.01
603E00901 1,780.000 FT 6" CONDUIT, TYPE B, AS PER PLAN 65.4529 73.4506 $130,742.00
603E01004 36.000 FT 6" CONDUIT, TYPE B, DUCTILE IRON PIPE 159.8000 122.0000 $4,392.00
ANSI CLASS 52, MECHANICAL JOINTS AND FITTINGS
603E01100 6,579.000 FT 6" CONDUIT, TYPE C 18.4365 13.5891 $89,402.36
603E01101 4,440.000 FT 6" CONDUIT, TYPE C, AS PER PLAN 46.7698 40.5697 $180,129.60
603E01200 210.000 FT 6" CONDUIT, TYPE D 13.1755 12.1429 $2,550.00
603E01400 6,596.000 FT 6" CONDUIT, TYPE E 11.4987 10.2113 $67,354.00
603E01500 12,612.000 FT 6" CONDUIT, TYPE F 15.1430 13.2135 $166,648.54
603E01501 310.000 FT 6" CONDUIT, TYPE F, AS PER PLAN 16.8706 15.7161 $4,872.00
603E01800 3,136.000 FT 8" CONDUIT, TYPE B 68.8034 67.6167 $212,046.00
603E01801 3,082.000 FT 8" CONDUIT, TYPE B, AS PER PLAN 105.9644 89.9955 $277,366.00
603E01906 36.000 FT 8" CONDUIT, TYPE B, DUCTILE IRON PIPE 172.4000 134.0000 $4,824.00
ANSI CLASS 52, MECHANICAL JOINTS AND FITTINGS
603E02000 1,577.000 FT 8" CONDUIT, TYPE C 34.7862 26.0562 $41,090.67
603E02001 1,318.000 FT 8" CONDUIT, TYPE C, AS PER PLAN 67.5111 70.4552 $92,860.00
603E02500 615.000 FT 8" CONDUIT, TYPE E 17.5828 18.7553 $11,534.50
603E02600 1,042.000 FT 8" CONDUIT, TYPE F 19.9779 17.6948 $18,438.00
603E02601 25.000 FT 8" CONDUIT, TYPE F, AS PER PLAN 21.6667 37.0000 $925.00
603E03100 42.000 FT 10" CONDUIT, TYPE B 84.7113 61.2857 $2,574.00
603E03300 165.000 FT 10" CONDUIT, TYPE C 33.6369 30.3424 $5,006.50
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
90 | P a g e
603E03301 100.000 FT 10" CONDUIT, TYPE C, AS PER PLAN 21.6250 27.5000 $2,750.00
603E03601 10.000 FT 10" CONDUIT, TYPE E, AS PER PLAN 15.0000 16.0000 $160.00
603E03700 58.000 FT 10" CONDUIT, TYPE F 29.2580 16.5862 $962.00
603E04200 635.000 FT 12" CONDUIT, TYPE A 61.0203 64.0595 $40,677.80
603E04400 46,882.000 FT 12" CONDUIT, TYPE B 57.0179 53.4882 $2,507,632.90
603E04401 6,966.000 FT 12" CONDUIT, TYPE B, AS PER PLAN 95.4253 77.3069 $466,470.00
603E04411 23.000 FT 12" CONDUIT, TYPE B, DUCTILE IRON PIPE 362.1875 500.0000 $11,500.00
ANSI CLASS 53, PUSH-ON JOINTS AND FITTINGS, AS PER PLAN
603E04600 18,899.000 FT 12" CONDUIT, TYPE C 44.3086 37.6031 $710,661.36
603E04601 1,055.000 FT 12" CONDUIT, TYPE C, AS PER PLAN 35.3483 40.6773 $42,914.50
603E04900 2,593.000 FT 12" CONDUIT, TYPE D 40.8956 35.5213 $92,106.77
603E04901 48.000 FT 12" CONDUIT, TYPE D, AS PER PLAN 86.4633 74.3900 $3,570.72
603E05100 150.000 FT 12" CONDUIT, TYPE E 32.7031 24.0467 $3,607.00
603E05200 3,285.000 FT 12" CONDUIT, TYPE F 56.2232 45.7299 $150,222.86
603E05700 3,743.000 FT 15" CONDUIT, TYPE A 66.2405 43.9221 $164,400.56
603E05701 249.000 FT 15" CONDUIT, TYPE A, AS PER PLAN 49.6814 33.2129 $8,270.00
603E05900 34,085.000 FT 15" CONDUIT, TYPE B 63.2240 63.7273 $2,172,145.68
603E05901 1,732.000 FT 15" CONDUIT, TYPE B, AS PER PLAN 82.4196 83.3756 $144,406.54
603E06100 12,113.000 FT 15" CONDUIT, TYPE C 51.3821 48.0775 $582,363.18
603E06101 235.000 FT 15" CONDUIT, TYPE C, AS PER PLAN 41.2925 38.9149 $9,145.00
603E06400 865.000 FT 15" CONDUIT, TYPE D 53.1422 43.1775 $37,348.50
603E06401 25.000 FT 15" CONDUIT, TYPE D, AS PER PLAN 73.7050 67.0000 $1,675.00
603E06700 3,683.000 FT 15" CONDUIT, TYPE F 60.4744 58.8407 $216,710.13
603E07200 555.000 FT 18" CONDUIT, TYPE A 82.1103 68.1900 $37,845.47
603E07201 3,803.000 FT 18" CONDUIT, TYPE A, AS PER PLAN 51.4364 35.0000 $133,105.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
91 | P a g e
603E07400 16,366.000 FT 18" CONDUIT, TYPE B 64.1607 58.6226 $959,416.80
603E07401 1,688.000 FT 18" CONDUIT, TYPE B, AS PER PLAN 120.1054 144.2559 $243,504.00
603E07600 4,878.000 FT 18" CONDUIT, TYPE C 60.6581 49.7217 $242,542.46
603E07900 724.000 FT 18" CONDUIT, TYPE D 51.3081 46.3547 $33,560.80
603E08200 229.000 FT 18" CONDUIT, TYPE F 86.8479 66.1943 $15,158.50
603E08700 147.000 FT 21" CONDUIT, TYPE A 76.6000 68.0000 $9,996.00
603E08701 132.000 FT 21" CONDUIT, TYPE A, AS PER PLAN 88.8000 75.0000 $9,900.00
603E08900 5,697.000 FT 21" CONDUIT, TYPE B 79.5037 77.6694 $442,482.66
603E08901 820.000 FT 21" CONDUIT, TYPE B, AS PER PLAN 162.6286 135.7198 $111,290.20
603E09100 2,839.000 FT 21" CONDUIT, TYPE C 72.8152 64.3337 $182,643.44
603E09400 268.000 FT 21" CONDUIT, TYPE D 65.6000 46.0000 $12,328.00
603E09700 185.000 FT 21" CONDUIT, TYPE F 87.1373 54.9189 $10,160.00
603E10200 1,014.000 FT 24" CONDUIT, TYPE A 96.5252 96.0009 $97,344.88
603E10201 702.000 FT 24" CONDUIT, TYPE A, AS PER PLAN 68.8620 55.5769 $39,015.00
603E10400 10,464.000 FT 24" CONDUIT, TYPE B 78.6294 78.6540 $823,035.77
603E10401 737.000 FT 24" CONDUIT, TYPE B, AS PER PLAN 136.7852 143.3799 $105,671.00
603E10600 3,858.000 FT 24" CONDUIT, TYPE C 73.2814 68.5886 $264,614.92
603E10601 15.000 FT 24" CONDUIT, TYPE C, AS PER PLAN 97.3229 85.0000 $1,275.00
603E10900 238.000 FT 24" CONDUIT, TYPE D 56.6053 50.2601 $11,961.90
603E11200 87.000 FT 24" CONDUIT, TYPE F 98.4123 61.1149 $5,317.00
603E11700 281.000 FT 27" CONDUIT, TYPE A 102.3922 93.0828 $26,156.28
603E11900 1,939.000 FT 27" CONDUIT, TYPE B 108.4578 102.7376 $199,208.24
603E12100 945.000 FT 27" CONDUIT, TYPE C 89.0603 88.4637 $83,598.20
603E13200 872.000 FT 30" CONDUIT, TYPE A 124.8882 147.0745 $128,249.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
92 | P a g e
603E13400 1,058.000 FT 30" CONDUIT, TYPE B 99.0521 86.8960 $91,936.00
603E13401 1,209.000 FT 30" CONDUIT, TYPE B, AS PER PLAN 184.5021 203.8925 $246,506.00
603E13600 1,682.000 FT 30" CONDUIT, TYPE C 97.3472 81.4512 $137,000.96
603E14700 52.000 FT 33" CONDUIT, TYPE A 215.0167 203.7750 $10,596.30
603E14900 180.000 FT 33" CONDUIT, TYPE B 93.5667 90.0000 $16,200.00
603E14901 5.000 FT 33" CONDUIT, TYPE B, AS PER PLAN 180.0000 200.0000 $1,000.00
603E15100 8.000 FT 33" CONDUIT, TYPE C 425.9188 373.4200 $2,987.36
603E16200 2,297.000 FT 36" CONDUIT, TYPE A 151.5628 161.3271 $370,568.43
603E16201 174.000 FT 36" CONDUIT, TYPE A, AS PER PLAN 87.9391 70.0000 $12,180.00
603E16400 5,134.000 FT 36" CONDUIT, TYPE B 163.7488 170.6113 $875,918.57
603E16600 3,630.000 FT 36" CONDUIT, TYPE C 86.7548 86.5260 $314,089.50
603E19200 1,076.000 FT 42" CONDUIT, TYPE A 170.2994 158.4728 $170,516.77
603E19400 1,354.000 FT 42" CONDUIT, TYPE B 145.3506 157.1162 $212,735.32
603E19600 253.000 FT 42" CONDUIT, TYPE C 107.1802 107.3083 $27,149.00
603E20700 1,418.000 FT 48" CONDUIT, TYPE A 225.2003 212.1774 $300,867.61
603E20701 311.000 FT 48" CONDUIT, TYPE A, AS PER PLAN 210.4784 163.2476 $50,770.00
603E20900 530.000 FT 48" CONDUIT, TYPE B 188.3993 234.4424 $124,254.49
603E21100 840.000 FT 48" CONDUIT, TYPE C 157.4924 200.7760 $168,651.82
603E22200 402.000 FT 54" CONDUIT, TYPE A 283.0228 284.3582 $114,312.00
603E22400 377.000 FT 54" CONDUIT, TYPE B 225.0184 257.2944 $97,000.00
603E22600 83.000 FT 54" CONDUIT, TYPE C 181.2500 225.0000 $18,675.00
603E22601 42.000 FT 54" CONDUIT, TYPE C, AS PER PLAN 571.2500 525.0000 $22,050.00
603E23600 895.000 FT 60" CONDUIT, TYPE A 256.5794 209.7698 $187,744.00
603E23601 96.000 FT 60" CONDUIT, TYPE A, AS PER PLAN 237.9622 158.2500 $15,192.00
603E23800 54.000 FT 60" CONDUIT, TYPE B 178.5060 171.0000 $9,234.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
93 | P a g e
603E23801 785.000 FT 60" CONDUIT, TYPE B, AS PER PLAN 249.4250 221.8500 $174,152.25
603E24000 225.000 FT 60" CONDUIT, TYPE C 169.3502 180.1733 $40,539.00
603E25000 30.000 FT 66" CONDUIT, TYPE A 650.3233 475.0000 $14,250.00
603E25001 108.000 FT 66" CONDUIT, TYPE A, AS PER PLAN 310.4433 167.0000 $18,036.00
603E25404 58.000 FT 66" CONDUIT, TYPE D 299.2556 351.9400 $20,412.52
603E26000 461.000 FT 72" CONDUIT, TYPE A 309.2474 273.7679 $126,207.00
603E26001 45.000 FT 72" CONDUIT, TYPE A, AS PER PLAN 445.1882 415.0000 $18,675.00
603E27600 40.000 FT 78" CONDUIT, TYPE D 281.6667 300.0000 $12,000.00
603E28000 735.000 FT 84" CONDUIT, TYPE A 558.4592 564.5907 $414,974.16
603E28401 1,392.000 FT 84" CONDUIT, TYPE C, AS PER PLAN 573.5663 452.7550 $630,234.96
603E32000 406.000 FT 108" CONDUIT, TYPE A 485.5167 325.0000 $131,950.00
603E38000 108.000 FT 144" CONDUIT, TYPE A 1,992.5000 1,550.0000 $167,400.00
603E40801 28.000 FT 168" CONDUIT, TYPE A, AS PER PLAN 1,581.4080 1,375.0000 $38,500.00
603E52200 88.000 FT 14" X 23" CONDUIT, TYPE A, 706.04 149.8333 160.0000 $14,080.00
603E52300 70.000 FT 19" X 30" CONDUIT, TYPE A, 706.04 184.8833 170.0000 $11,900.00
603E52306 48.000 FT 19" X 30" CONDUIT, TYPE D, 706.04 106.6000 98.0000 $4,704.00
603E52400 131.000 FT 22" X 34" CONDUIT, TYPE A, 706.04 140.0000 125.0000 $16,375.00
603E52500 207.000 FT 24" X 38" CONDUIT, TYPE A, 706.04 173.3634 159.2029 $32,955.00
603E52700 142.000 FT 29" X 45" CONDUIT, TYPE A, 706.04 190.6000 173.0000 $24,566.00
603E52704 413.000 FT 29" X 45" CONDUIT, TYPE C, 706.04 179.7856 137.4576 $56,770.00
603E52900 78.000 FT 34" X 53" CONDUIT, TYPE A, 706.04 198.3333 200.0000 $15,600.00
603E52902 99.000 FT 34" X 53" CONDUIT, TYPE B, 706.04 225.6000 180.0000 $17,820.00
603E52904 589.000 FT 34" X 53" CONDUIT, TYPE C, 706.04 197.7191 168.5399 $99,270.00
603E53000 118.000 FT 38" X 60" CONDUIT, TYPE A, 706.04 295.6533 260.0000 $30,680.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
94 | P a g e
603E53004 10.000 FT 38" X 60" CONDUIT, TYPE C, 706.04 450.0000 375.0000 $3,750.00
603E53100 245.000 FT 43" X 68" CONDUIT, TYPE A, 706.04 292.0017 254.0000 $62,230.00
603E53300 72.000 FT 53" X 83" CONDUIT, TYPE A, 706.04 439.2120 450.0000 $32,400.00
603E53400 40.000 FT 58" X 91" CONDUIT, TYPE A, 706.04 650.0000 475.0000 $19,000.00
603E57510 10.000 FT 42" X 29" CONDUIT, TYPE B 282.0450 610.0000 $6,100.00
603E59000 60.000 FT 95" X 67" CONDUIT, TYPE A 560.8420 630.0000 $37,800.00
603E70001 82.000 FT CONDUIT, TYPE A, PRECAST REINFORCED 2,286.4683 1,963.4146 $161,000.00
CONCRETE FLAT TOPPED THREE SIDED CULVERT, AS PER PLAN
603E71000 78.000 FT CONDUIT, TYPE A, PRECAST REINFORCED 1,232.6343 1,129.2308 $88,080.00
CONCRETE ARCH SECTIONS
603E71001 311.800 FT CONDUIT, TYPE A, PRECAST REINFORCED 3,120.6103 3,045.6464 $949,632.53
CONCRETE ARCH SECTIONS, AS PER PLAN
603E92904 17.000 FT 4' X 4 CONDUIT, TYPE A, 706.05 1,047.9775 600.0000 $10,200.00
603E94700 87.000 FT 6' X 4' CONDUIT, TYPE A, 706.05 492.5000 450.0000 $39,150.00
603E94720 112.000 FT 6' X 6' CONDUIT, TYPE A, 706.05 517.4900 644.9600 $72,235.52
603E94800 241.000 FT 8' X 4' CONDUIT, TYPE A, 706.05 718.5408 536.9295 $129,400.00
603E94900 94.000 FT 8' X 5' CONDUIT, TYPE A, 706.05 462.7850 500.0000 $47,000.00
603E94910 589.000 FT 8' X 6' CONDUIT, TYPE A, 706.05 620.7466 653.0560 $384,650.00
603E94911 36.000 FT 8' X 6' CONDUIT, TYPE A, 706.05, AS PER 718.7600 737.0000 $26,532.00
PLAN
603E94920 81.000 FT 8' X 7' CONDUIT, TYPE A, 706.05 717.4286 596.0000 $48,276.00
603E94921 75.000 FT 8' X 7' CONDUIT, TYPE A, 706.05, AS PER 587.4875 500.5000 $37,537.50
PLAN
603E95000 46.000 FT 10' X 5' CONDUIT, TYPE A, 706.05 893.5533 1,000.0000 $46,000.00
603E95001 219.000 FT 10' X 5' CONDUIT, TYPE A, 706.05, AS PER 266.3713 294.8402 $64,570.00
PLAN
603E95400 102.000 FT 10' X 7' CONDUIT, TYPE A, 706.05 778.8080 743.5294 $75,840.00
603E95401 110.000 FT 10' X 7' CONDUIT, TYPE A, 706.05, AS PER PLAN 930.8000 890.0000 $97,900.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
95 | P a g e
603E95500 275.000 FT 10' X 8' CONDUIT, TYPE A, 706.05 786.7515 706.2655 $194,223.00
603E95501 65.000 FT 10' X 8' CONDUIT, TYPE A, 706.05, AS PER 886.1850 1,150.0000 $74,750.00
PLAN
603E95521 88.000 FT 10' X 9' CONDUIT, TYPE A, 706.05, AS PER 599.0000 525.0000 $46,200.00
PLAN
603E95600 188.000 FT 12' X 4' CONDUIT, TYPE A, 706.05 689.9449 643.6170 $121,000.00
603E95800 108.000 FT 12' X 6' CONDUIT, TYPE A, 706.05 740.9428 637.2222 $68,820.00
603E95801 84.000 FT 12' X 6' CONDUIT, TYPE A, 706.05, AS PER 878.2150 590.0000 $49,560.00
PLAN
603E96000 122.000 FT 12' X 8' CONDUIT, TYPE A, 706.05 767.0000 675.0000 $82,350.00
603E96010 57.000 FT 12' X 9' CONDUIT, TYPE A, 706.05 922.6733 765.0000 $43,605.00
603E96200 60.000 FT 12' X 10' CONDUIT, TYPE A, 706.05 1,225.6729 884.3700 $53,062.20
603E96339 204.000 FT 14' X 10' CONDUIT, TYPE A, 706.05, AS 1,181.2925 1,150.6945 $234,741.68
PER PLAN
603E96401 135.000 FT 16' X 5' CONDUIT, TYPE A, 706.05, AS PER 1,260.0693 1,061.8889 $143,355.00
PLAN
603E96441 210.000 FT 16' X 6' CONDUIT, TYPE A, 706.05, AS PER 891.4222 750.0000 $157,500.00
PLAN
603E96448 354.000 FT 16' X 7' CONDUIT, TYPE A, 706.05 1,315.1124 1,544.6328 $546,800.00
603E96451 84.000 FT 16' X 8' CONDUIT, TYPE A, 706.05, AS PER 1,108.5714 970.0000 $81,480.00
PLAN
603E96471 48.000 FT 18' X 7' CONDUIT, TYPE A, 706.05, AS PER 1,107.4089 1,057.0000 $50,736.00
PLAN
603E96477 48.000 FT 18' X 5' CONDUIT, TYPE A, 706.05, AS PER 1,174.4925 1,127.9700 $54,142.56
PLAN
603E96481 60.000 FT 18' X 8' CONDUIT, TYPE A, 706.05, AS PER 1,218.0000 1,065.0000 $63,900.00
PLAN
603E96485 110.830 FT 18' X 10' CONDUIT, TYPE A, 706.05, AS 1,404.0083 1,242.8800 $137,748.39
PER PLAN
603E96487 48.000 FT 20'X7' CONDUIT, TYPE A, 706.05, AS PER 1,326.3333 1,040.0000 $49,920.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
96 | P a g e
603E96497 86.000 FT 20' X 6' CONDUIT, TYPE A, 706.05, AS PER 1,452.7231 1,253.6512 $107,814.00
PLAN
603E96499 44.000 FT 20' X 8' CONDUIT, TYPE A, 706.05, AS PER 1,399.3722 1,178.2000 $51,840.80
PLAN
603E96550 7,614.000 FT FIELD PAVING OF EXISTING PIPE 134.2402 120.8182 $919,909.85
603E96551 651.000 FT FIELD PAVING OF EXISTING PIPE, AS PER 121.1297 128.2874 $83,515.08
PLAN
603E96600 7,677.000 FT CONDUIT, BORED OR JACKED: 358.8853 375.6415 $2,883,800.00
603E96601 2,562.000 FT CONDUIT, BORED OR JACKED, AS PER PLAN 366.4848 387.7738 $993,476.49
603E96650 5.000 CY SPECIAL - GROUTING VOIDS AROUND 850.3450 1,500.0000 $7,500.00
CORRUGATED METAL PIPES
603E97010 62.000 FT SLOTTED DRAIN, TYPE 2 119.9375 103.0000 $6,386.00
603E97011 65.000 FT SLOTTED DRAIN, TYPE 2, AS PER PLAN 98.0000 98.0000 $6,370.00
603E98100 33.000 EACH CONDUIT, MISC.: 2,386.4777 1,630.8242 $53,817.20
603E98200 2.000 LS CONDUIT, MISC.: 384,070.0000 475,500.0000 $951,000.00
603E98300 8,374.000 FT CONDUIT, MISC.: 383.0214 168.3352 $1,409,638.60
603E98400 2,355.000 SY CONDUIT, MISC.: 10.9700 14.0000 $32,970.00
603E98500 11,820.000 CY CONDUIT, MISC.: 70.2680 58.0795 $686,500.00
603E98600 3,345.000 SF CONDUIT, MISC.: 47.4000 28.8000 $96,336.00
603E99000 5.000 LS SPECIAL - DRAINAGE 682,933.6316 847,004.0000 $4,235,020.00
604E00300 37.000 EACH CATCH BASIN, CITY OF CLEVELAND NO. 1 2,556.5932 3,075.6757 $113,800.00
604E00301 193.000 EACH CATCH BASIN, CITY OF CLEVELAND NO. 1, AS 3,157.2840 2,619.3482 $505,534.20
PER PLAN
604E00400 240.000 EACH CATCH BASIN, NO. 3 2,746.8249 2,500.6577 $600,157.84
604E00401 31.000 EACH CATCH BASIN, NO. 3, AS PER PLAN 3,143.9161 3,532.2581 $109,500.00
604E00800 573.000 EACH CATCH BASIN, NO. 3A 2,048.5661 1,831.5665 $1,049,487.58
604E00801 117.000 EACH CATCH BASIN, NO. 3A, AS PER PLAN 2,224.3337 1,929.0644 $225,700.53
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
97 | P a g e
604E00850 4.000 EACH CATCH BASIN, NO. 3A WITH SUMP 2,169.0000 2,490.0000 $9,960.00
604E01200 68.000 EACH CATCH BASIN, NO. 4 3,236.9246 3,141.7229 $213,637.16
604E01204 1.000 EACH CATCH BASIN, NO. 4 WITHOUT APRON 2,323.4700 2,500.0000 $2,500.00
604E01403 1.000 EACH CATCH BASIN, NO. 4A WITH E GRATE, AS PER 3,837.5355 2,850.0000 $2,850.00
PLAN
604E01600 38.000 EACH CATCH BASIN, NO. 5 3,033.7486 2,682.3168 $101,928.04
604E01605 1.000 EACH CATCH BASIN, NO. 5 WITHOUT APRON, AS PER 3,498.5775 5,000.0000 $5,000.00
PLAN
604E01901 1.000 EACH CATCH BASIN, NO. 5A WITH B GRATE, AS PER 3,042.1222 2,750.0000 $2,750.00
PLAN
604E02000 122.000 EACH CATCH BASIN, NO. 6 1,946.8783 1,826.1744 $222,793.28
604E02001 4.000 EACH CATCH BASIN, NO. 6, AS PER PLAN 2,309.4542 2,237.5000 $8,950.00
604E02400 12.000 EACH CATCH BASIN, NO. 7 1,478.6847 1,109.9800 $13,319.76
604E02401 6.000 EACH CATCH BASIN, NO. 7, AS PER PLAN 2,238.8750 4,000.0000 $24,000.00
604E02800 181.000 EACH CATCH BASIN, NO. 8 2,852.2637 2,356.2717 $426,485.18
604E02801 6.000 EACH CATCH BASIN, NO. 8, AS PER PLAN 3,068.8226 3,716.6667 $22,300.00
604E02804 1.000 EACH CATCH BASIN, NO. 8 WITHOUT APRON 2,700.0000 2,700.0000 $2,700.00
604E02906 2.000 EACH CATCH BASIN, NO. 8A 3,650.0000 2,700.0000 $5,400.00
604E04100 19.000 EACH CATCH BASIN, NO. 2-2A 1,503.6867 1,318.4826 $25,051.17
604E04101 1.000 EACH CATCH BASIN, NO. 2-2A, AS PER PLAN 2,404.8400 2,500.0000 $2,500.00
604E04500 316.000 EACH CATCH BASIN, NO. 2-2B 1,200.5600 1,063.1930 $335,968.99
604E04501 26.000 EACH CATCH BASIN, NO. 2-2B, AS PER PLAN 1,611.8939 1,686.7992 $43,856.78
604E04550 12.000 EACH CATCH BASIN, NO. 2-2B WITH SUMP 1,508.0863 1,438.7500 $17,265.00
604E04900 88.000 EACH CATCH BASIN, NO. 2-3 1,689.2496 1,436.9097 $126,448.05
604E04901 5.000 EACH CATCH BASIN, NO. 2-3, AS PER PLAN 2,460.0684 2,040.0000 $10,200.00
604E04950 3.000 EACH CATCH BASIN, NO. 2-3 WITH SUMP 2,346.9180 2,100.0000 $6,300.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
98 | P a g e
604E05300 24.000 EACH CATCH BASIN, NO. 2-4 2,208.0461 2,089.9179 $50,158.03
604E05700 4.000 EACH CATCH BASIN, NO. 2-5 2,486.7731 2,812.5000 $11,250.00
604E05701 1.000 EACH CATCH BASIN, NO. 2-5, AS PER PLAN 2,928.6633 1,600.0000 $1,600.00
604E06100 9.000 EACH CATCH BASIN, NO. 2-6 3,799.3941 3,111.1111 $28,000.00
604E06101 2.000 EACH CATCH BASIN, NO. 2-6, AS PER PLAN 3,020.5407 2,096.3150 $4,192.63
604E06110 1.000 EACH CATCH BASIN, NO. 2-6 WITH BICYCLE SAFE 3,197.8078 2,500.0000 $2,500.00
GRATE
604E08600 83.000 EACH CATCH BASIN, MISC.: 2,268.1874 2,107.0767 $174,887.37
604E09000 426.000 EACH CATCH BASIN ADJUSTED TO GRADE 493.8907 453.9060 $193,363.94
604E09001 290.000 EACH CATCH BASIN ADJUSTED TO GRADE, AS PER 517.7404 409.2997 $118,696.91
PLAN
604E09500 110.000 EACH CATCH BASIN RECONSTRUCTED TO GRADE 946.9393 883.5682 $97,192.50
604E09501 44.000 EACH CATCH BASIN RECONSTRUCTED TO GRADE, AS 1,042.4516 823.0707 $36,215.11
PER PLAN
604E09911 9.000 EACH CATCH BASIN FRAME AND GRATE, AS PER PLAN 1,281.9444 1,258.3333 $11,325.00
604E10100 33.000 EACH INLET, SIDE DITCH 1,087.7337 728.7879 $24,050.00
604E10101 1.000 EACH INLET, SIDE DITCH, AS PER PLAN 1,516.6667 900.0000 $900.00
604E10900 23.000 EACH INLET, NO. 2-6 3,758.5859 3,486.9565 $80,200.00
604E11300 2.000 EACH INLET, NO. 2-8 2,613.7500 2,400.0000 $4,800.00
604E11701 5.000 EACH INLET, NO. 2-10, AS PER PLAN 3,100.7674 2,346.3120 $11,731.56
604E14500 7.000 EACH INLET, NO. 3A 1,838.5876 1,957.1429 $13,700.00
604E17500 13.000 EACH INLET, NO. 2-A-6 2,723.8478 2,200.0000 $28,600.00
604E17501 17.000 EACH INLET, NO. 2-A-6, AS PER PLAN 3,122.3867 2,700.0000 $45,900.00
604E18300 3.000 EACH INLET, NO. 2-A-10 3,235.6478 2,950.0000 $8,850.00
604E18301 6.000 EACH INLET, NO. 2-A-10, AS PER PLAN 3,553.0100 3,500.0000 $21,000.00
604E18700 1.000 EACH INLET, NO. 2-A-12 4,210.1178 3,850.0000 $3,850.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
99 | P a g e
604E20510 22.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 6,725.8583 6,577.5750 $144,706.65
TYPE B
604E20511 2.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 5,157.5000 5,000.0000 $10,000.00
TYPE B, AS PER PLAN
604E20514 7.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 6,872.3684 7,057.1429 $49,400.00
TYPE B1
604E20521 1.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 5,225.0000 5,000.0000 $5,000.00
TYPE C, AS PER PLAN
604E20524 8.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 7,092.2222 7,031.2500 $56,250.00
TYPE C1
604E20530 22.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 6,435.2364 7,723.2464 $169,911.42
TYPE D
604E20531 9.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 6,476.0000 6,704.0000 $60,336.00
TYPE D, AS PER PLAN
604E20600 134.000 EACH INLET ADJUSTED TO GRADE 546.6920 609.1896 $81,631.40
604E20601 49.000 EACH INLET ADJUSTED TO GRADE, AS PER PLAN 599.6434 392.8571 $19,250.00
604E20800 27.000 EACH INLET RECONSTRUCTED TO GRADE 978.5158 1,015.7456 $27,425.13
604E20801 7.000 EACH INLET RECONSTRUCTED TO GRADE, AS PER 1,277.5061 1,200.0000 $8,400.00
PLAN
604E20900 12.000 EACH INLET FRAME AND GRATE 800.0000 850.0000 $10,200.00
604E22500 79.000 EACH INLET, MISC.: 575.9310 594.0380 $46,929.00
604E30100 11.000 EACH MANHOLE, NO. 1 3,094.7668 2,767.6436 $30,444.08
604E31500 477.000 EACH MANHOLE, NO. 3 2,816.7008 2,573.4622 $1,227,541.46
604E31501 133.000 EACH MANHOLE, NO. 3, AS PER PLAN 3,198.7762 2,681.6188 $356,655.30
604E31600 2.000 EACH MANHOLE, NO. 3 WITH 84" BASE I.D. AND 6" 7,849.8713 6,000.0000 $12,000.00
WEIR
604E31610 2.000 EACH MANHOLE, NO. 3 WITH 90" BASE I.D. AND 8" 7,245.4655 6,521.5600 $13,043.12
WEIR
604E32100 6.000 EACH MANHOLE, NO. 5 14,944.1538 12,333.3333 $74,000.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
100 | P a g e
604E32500 97.000 EACH MANHOLE, MISC.: 6,084.9900 5,002.0351 $485,197.40
604E33300 1.000 EACH MANHOLE FRAME 337.5000 200.0000 $200.00
604E33400 1.000 EACH MANHOLE COVER 300.0000 125.0000 $125.00
604E33501 5.000 EACH MANHOLE FRAME AND COVER, AS PER PLAN 800.0000 850.0000 $4,250.00
604E34500 950.000 EACH MANHOLE ADJUSTED TO GRADE 429.2972 419.7987 $398,808.73
604E34501 544.000 EACH MANHOLE ADJUSTED TO GRADE, AS PER PLAN 757.0073 906.3336 $493,045.50
604E35500 73.000 EACH MANHOLE RECONSTRUCTED TO GRADE 1,525.5985 1,214.2233 $88,638.30
604E35501 117.000 EACH MANHOLE RECONSTRUCTED TO GRADE, AS PER 1,540.5675 1,069.9570 $125,184.97
PLAN
604E36000 68.000 EACH GAS VALVE BOX ADJUSTED TO GRADE 248.2030 258.8750 $17,603.50
604E36600 980.000 EACH PRECAST REINFORCED CONCRETE OUTLET 224.7156 206.4245 $202,295.98
604E37000 69.000 EACH INSPECTION WELL 630.0365 559.1304 $38,580.00
604E37501 9.000 EACH JUNCTION CHAMBER, AS PER PLAN 113,786.0405 102,710.4644 $924,394.18
604E38500 121.000 EACH MONUMENT ASSEMBLY 749.0748 818.6688 $99,058.92
604E38501 90.000 EACH MONUMENT ASSEMBLY, AS PER PLAN 719.1367 811.6444 $73,048.00
604E39500 161.000 EACH MONUMENT BOX ADJUSTED TO GRADE 368.5800 380.7032 $61,293.21
604E39501 116.000 EACH MONUMENT BOX ADJUSTED TO GRADE, AS PER 412.8209 406.1193 $47,109.84
PLAN
604E39600 4.000 EACH MONUMENT BOX RECONSTRUCTED TO GRADE 583.9888 450.0000 $1,800.00
604E40500 265.000 EACH REFERENCE MONUMENT 420.9390 429.0258 $113,691.85
604E40520 58.000 EACH RIGHT-OF-WAY MONUMENT 383.7750 359.4828 $20,850.00
604E40521 10.000 EACH RIGHT-OF-WAY MONUMENT, AS PER PLAN 413.7500 330.0000 $3,300.00
604E40900 126.000 EACH MONUMENT, MISC.: 169.8270 157.2222 $19,810.00
604E45200 1.000 EACH FLAP GATE, 12" 1,162.0000 716.0000 $716.00
604E50000 136,050.000 LB SPECIAL - MISCELLANEOUS METAL 1.1787 1.0077 $137,097.50
604E60000 93.000 FT SPECIAL - TRENCH DRAIN 110.3917 80.0000 $7,440.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
101 | P a g e
604E80050 3.000 EACH WATER QUALITY BASIN, DETENTION 4,015.3250 9,000.0000 $27,000.00
604E98000 185.000 EACH DRAINAGE STRUCTURE, MISC.: 353.5407 294.0102 $54,391.88
604E98100 429.000 FT DRAINAGE STRUCTURE, MISC.: 713.2556 648.0186 $278,000.00
604E98200 1.000 LS DRAINAGE STRUCTURE, MISC.: 6,367.2950 8,000.0000 $8,000.00
605E05100 33,691.000 FT 4" SHALLOW PIPE UNDERDRAINS 8.1220 7.0209 $236,540.63
605E05101 766.000 FT 4" SHALLOW PIPE UNDERDRAINS, AS PER PLAN 10.5000 8.0000 $6,128.00
605E05110 3,831.000 FT 4" SHALLOW PIPE UNDERDRAINS WITH FABRIC 11.1181 10.8531 $41,578.25
WRAP
605E05200 2,357.000 FT 4" UNCLASSIFIED PIPE UNDERDRAINS 10.9806 9.1742 $21,623.58
605E05201 16.000 FT 4" UNCLASSIFIED PIPE UNDERDRAINS, AS PER 17.3100 2.0000 $32.00
PLAN
605E05210 1,158.000 FT 4" UNCLASSIFIED PIPE UNDERDRAIN WITH 13.5034 10.5237 $12,186.50
FABRIC WRAP
605E06000 91,352.000 FT 4" BASE PIPE UNDERDRAINS 7.1693 6.8222 $623,218.37
605E06001 3,530.000 FT 4" BASE PIPE UNDERDRAINS, AS PER PLAN 6.6000 3.0000 $10,590.00
605E06020 2,643.000 FT 4" BASE PIPE UNDERDRAINS WITH FABRIC 9.8080 6.8006 $17,974.00
WRAP
605E11000 5,150.000 FT 6" CONSTRUCTION UNDERDRAINS 9.7383 8.3187 $42,841.25
605E11100 259,030.000 FT 6" SHALLOW PIPE UNDERDRAINS 6.8860 6.4089 $1,660,087.30
605E11101 1,669.000 FT 6" SHALLOW PIPE UNDERDRAINS, AS PER PLAN 8.2663 7.1000 $11,849.90
605E11110 127,494.000 FT 6" SHALLOW PIPE UNDERDRAINS WITH FABRIC 9.1044 7.6820 $979,414.83
WRAP
605E11111 747.000 FT 6" SHALLOW PIPE UNDERDRAINS WITH FABRIC 11.4012 8.9000 $6,648.26
WRAP, AS PER PLAN
605E12200 2,126.000 FT 6" DEEP PIPE UNDERDRAINS 13.9250 16.8735 $35,873.00
605E12201 3,482.000 FT 6" DEEP PIPE UNDERDRAINS, AS PER PLAN 9.7875 6.7000 $23,329.40
605E12210 466.000 FT 6" DEEP PIPE UNDERDRAINS WITH FABRIC 14.7500 12.0000 $5,592.00
WRAP
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
102 | P a g e
605E12211 99,808.000 FT 6" DEEP PIPE UNDERDRAINS WITH FABRIC 7.9825 6.9500 $693,665.60
WRAP, AS PER PLAN
605E13300 27,399.000 FT 6" UNCLASSIFIED PIPE UNDERDRAINS 9.5240 9.6245 $263,702.51
605E13402 1,550.000 FT 6" UNCLASSIFIED PIPE UNDERDRAINS FOR 12.0642 10.4803 $16,244.50
SPRINGS
605E13410 23,782.000 FT 6" UNCLASSIFIED PIPE UNDERDRAINS WITH 12.6845 9.3375 $222,063.51
FABRIC WRAP
605E13411 9,104.000 FT 6" UNCLASSIFIED PIPE UNDERDRAINS WITH 8.5088 7.1800 $65,366.72
FABRIC WRAP, AS PER PLAN
605E13500 20,583.000 FT 6" ROCK CUT UNDERDRAINS 11.0251 9.6886 $199,420.57
605E13501 58,398.000 FT 6" ROCK CUT UNDERDRAINS, AS PER PLAN 7.3225 6.8400 $399,442.32
605E13510 2,623.000 FT 6" ROCK CUT UNDERDRAINS WITH FABRIC WRAP 16.6012 17.6878 $46,395.00
605E14000 445,169.000 FT 6" BASE PIPE UNDERDRAINS 5.4871 4.8422 $2,155,604.29
605E14020 146,757.000 FT 6" BASE PIPE UNDERDRAINS WITH FABRIC 7.0364 6.1460 $901,963.34
WRAP
605E31100 9,876.000 FT AGGREGATE DRAINS 41.7278 9.8708 $97,483.81
605E31101 14,814.000 FT AGGREGATE DRAINS, AS PER PLAN 7.4231 6.0450 $89,551.00
605E32200 1,050.000 FT AGGREGATE DRAINS FOR SPRINGS 12.0351 9.5400 $10,017.00
605E98000 300.000 FT UNDERDRAINS, MISC.: 10.7783 11.0000 $3,300.00
605E99000 8.000 LS SPECIAL - UNDERDRAINS 68,332.6243 85,874.3300 $686,994.64
606E10200 1,000.000 SF SPECIAL - NOISE BARRIER (REFLECTIVE), 33.2492 33.1200 $33,120.00
10' HEIGHT AND UNDER
606E10210 31,432.000 SF SPECIAL - NOISE BARRIER (REFLECTIVE), 22.3163 22.4435 $705,442.56
OVER 10' TO 14' HEIGHT
606E10220 158,226.000 SF SPECIAL - NOISE BARRIER (REFLECTIVE), 21.5030 20.6142 $3,261,701.83
OVER 14' TO 20' HEIGHT
606E10700 1,440.000 SF NOISE BARRIER PANEL REMOVAL AND 37.5000 50.0000 $72,000.00
REPLACEMENT
606E10810 10.000 EACH SPECIAL - NOISE BARRIER, MISC.: 1,052.5950 860.0000 $8,600.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
103 | P a g e
606E10900 1.000 LS SPECIAL - NOISE BARRIER, MISC.: 18,381.6250 17,000.0000 $17,000.00
606E10920 842.000 SF SPECIAL - NOISE BARRIER, MISC.: 158.9824 173.1532 $145,795.00
606E11000 43.750 FT GUARDRAIL, THRIE BEAM RAIL AND 25.8233 27.3000 $1,194.38
TRANSITION SECTION
606E12000 7,125.000 FT GUARDRAIL, TYPE 5MR 27.2328 26.8954 $191,630.00
606E13000 403,860.020 FT GUARDRAIL, TYPE 5 13.9244 12.5993 $5,088,344.33
606E13001 59,741.000 FT GUARDRAIL, TYPE 5, AS PER PLAN 11.8330 10.9563 $654,538.50
606E13010 200.000 FT GUARDRAIL, TYPE 5 WITH TUBULAR BACKUP 84.5773 88.0750 $17,615.00
606E13011 284.500 FT GUARDRAIL, TYPE 5 WITH TUBULAR BACKUP, 37.9168 44.4903 $12,657.50
AS PER PLAN
606E13020 100.000 FT GUARDRAIL, TYPE 5 WITH DOUBLE RAILS 18.3667 18.3500 $1,835.00
606E13030 27,070.000 FT GUARDRAIL, TYPE 5, USING 9 FOOT POSTS 15.4852 15.1528 $410,186.55
606E13031 712.500 FT GUARDRAIL, TYPE 5, USING 9 FOOT POSTS, 19.5878 20.1358 $14,346.75
AS PER PLAN
606E13040 225.000 FT GUARDRAIL, NESTED TYPE 5 WITH TUBULAR 89.1363 89.6000 $20,160.00
BACKUP
606E13050 4,418.750 FT GUARDRAIL, TYPE 5A 25.1391 18.5402 $81,924.38
606E13051 787.500 FT GUARDRAIL, TYPE 5A, AS PER PLAN 19.4067 18.9460 $14,920.00
606E14000 837.500 FT GUARDRAIL, TYPE 8 23.2459 20.2925 $16,995.00
606E15050 108,263.650 FT GUARDRAIL, TYPE MGS 14.3024 13.8543 $1,499,920.21
606E15100 46,721.250 FT GUARDRAIL, TYPE MGS WITH LONG POSTS 15.5314 15.3528 $717,303.30
606E15150 4,268.750 FT GUARDRAIL, TYPE MGS HALF POST SPACING 20.2114 18.8814 $80,600.00
606E15200 100.000 FT GUARDRAIL, TYPE MGS HALF POST SPACING 20.2000 20.2000 $2,020.00
WITH LONG POSTS
606E15250 475.000 FT GUARDRAIL, TYPE MGS QUARTER POST SPACING 27.9529 26.3368 $12,510.00
606E15300 100.000 FT GUARDRAIL, TYPE MGS QUARTER POST SPACING 34.4000 34.4000 $3,440.00
WITH LONG POSTS
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
104 | P a g e
606E15350 100.000 FT GUARDRAIL, TYPE MGS WITH SOCKETED POSTS 81.6000 81.6000 $8,160.00
606E15400 75.000 FT MGS GUARDRAIL, TYPE 8 23.4000 25.0000 $1,875.00
606E15500 5,064.250 FT GUARDRAIL, BARRIER DESIGN, TYPE 5 20.4587 20.4168 $103,395.88
606E15501 537.500 FT GUARDRAIL, BARRIER DESIGN, TYPE 5, AS 20.9430 20.9651 $11,268.75
PER PLAN
606E15550 3,956.250 FT GUARDRAIL, BARRIER DESIGN, TYPE MGS 23.1971 22.7188 $89,881.25
606E16000 470.000 FT GUARDRAIL REBUILT 34.6673 37.1277 $17,450.00
606E16051 50.000 FT GUARDRAIL REBUILT, TYPE MGS, AS PER PLAN 15.8000 15.8000 $790.00
606E16500 9,081.280 FT GUARDRAIL REBUILT, TYPE 5 10.1827 9.5065 $86,330.81
606E16501 87,481.250 FT GUARDRAIL REBUILT, TYPE 5, AS PER PLAN 7.7657 7.6887 $672,615.13
606E16550 25.000 FT GUARDRAIL REBUILT, TYPE 5, USING 9 FOOT 13.7500 12.0000 $300.00
POSTS
606E16551 1,100.000 FT GUARDRAIL REBUILT, TYPE 5, USING 9 FOOT 16.4173 15.9255 $17,518.00
POSTS, AS PER PLAN
606E16561 125.000 FT GUARDRAIL REBUILT, TYPE MGS WITH LONG 13.5556 13.5200 $1,690.00
POSTS, AS PER PLAN
606E16600 800.000 FT GUARDRAIL REBUILT, BARRIER DESIGN, TYPE 19.8000 19.8000 $15,840.00
5
606E16601 2,225.000 FT GUARDRAIL REBUILT, BARRIER DESIGN, TYPE 15.7895 14.9258 $33,210.00
5, AS PER PLAN
606E16661 200.000 FT GUARDRAIL REBUILT, BARRIER DESIGN, TYPE 20.1500 18.5000 $3,700.00
MGS, AS PER PLAN
606E16700 137.500 FT GUARDRAIL REBUILT, TYPE 5A 17.4591 16.9455 $2,330.00
606E16701 150.000 FT GUARDRAIL REBUILT, TYPE 5A, AS PER PLAN 16.8000 16.8000 $2,520.00
606E17000 1,500.000 FT RAISING TYPE 5 GUARDRAIL 3.9125 3.2000 $4,800.00
606E17290 2,563.500 FT GUARDRAIL, TYPE 5, LONG-SPAN 21.1742 19.9592 $51,165.35
606E17291 137.500 FT GUARDRAIL, TYPE 5, LONG-SPAN, AS PER 24.7950 24.0000 $3,300.00
PLAN
606E17300 2,600.000 FT GUARDRAIL, TYPE 5, 25' LONG-SPAN 21.4288 20.7838 $54,038.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
105 | P a g e
606E17301 381.000 FT GUARDRAIL, TYPE 5, 25' LONG-SPAN, AS PER 23.1918 20.6500 $7,867.65
PLAN
606E17350 1,350.000 FT GUARDRAIL, TYPE MGS, 25' LONG - SPAN 21.2711 20.7056 $27,952.50
606E17351 94.000 FT GUARDRAIL, TYPE MGS, 25' LONG-SPAN, AS 25.3533 24.2000 $2,274.80
PER PLAN
606E17500 15.000 EACH POST END ANCHOR (OR CONCRETE BLOCK END 868.6182 856.0000 $12,840.00
ANCHOR)
606E17700 121.000 EACH REPLACE EXISTING GUARDRAIL BLOCKOUT 8.6017 10.2727 $1,243.00
606E17750 11.000 EACH REPLACE EXISTING GUARDRAIL BLOCKOUT, 14.2857 15.4545 $170.00
TYPE MGS
606E17900 357.000 EACH GUARDRAIL POST 34.5177 31.2745 $11,165.00
606E17901 100.000 EACH GUARDRAIL POST, AS PER PLAN 36.0000 28.0000 $2,800.00
606E18500 463.000 EACH GUARDRAIL POST, 9 FEET 20.1939 15.6807 $7,260.15
606E18501 1,183.000 EACH GUARDRAIL POST, 9 FEET, AS PER PLAN 22.9285 16.3360 $19,325.50
606E19001 80.000 EACH GUARDRAIL POST, STEEL, AS PER PLAN 142.7826 74.0625 $5,925.00
606E20000 46.000 EACH FLARED END SECTION 48.6521 47.6087 $2,190.00
606E20050 11.000 EACH ROUNDED END SECTION 49.7143 53.1818 $585.00
606E22010 5.000 EACH ANCHOR ASSEMBLY, TYPE E-98 1,612.3070 1,690.0000 $8,450.00
606E25000 270.000 EACH ANCHOR ASSEMBLY, TYPE A 845.1863 807.1926 $217,942.00
606E25001 4.000 EACH ANCHOR ASSEMBLY, TYPE A, AS PER PLAN 500.0000 500.0000 $2,000.00
606E25500 3.000 EACH ANCHOR ASSEMBLY, BARRIER DESIGN, TYPE A 1,165.8333 1,183.3333 $3,550.00
606E25550 47.000 EACH ANCHOR ASSEMBLY, MGS TYPE A 936.6315 912.3404 $42,880.00
606E26000 278.000 EACH ANCHOR ASSEMBLY, TYPE B 1,532.8484 1,475.2086 $410,107.98
606E26050 24.000 EACH ANCHOR ASSEMBLY, MGS TYPE B 1,550.0041 1,548.4771 $37,163.45
606E26100 1,702.000 EACH ANCHOR ASSEMBLY, TYPE E 1,762.4338 1,766.4970 $3,006,577.89
606E26101 5.000 EACH ANCHOR ASSEMBLY, TYPE E, AS PER PLAN 1,292.5000 1,385.0000 $6,925.00
606E26150 251.000 EACH ANCHOR ASSEMBLY, MGS TYPE E 1,864.9373 1,843.9222 $462,824.48
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
106 | P a g e
606E26500 844.000 EACH ANCHOR ASSEMBLY, TYPE T 626.2454 598.0003 $504,712.23
606E26501 6.000 EACH ANCHOR ASSEMBLY, TYPE T, AS PER PLAN 574.4541 508.0000 $3,048.00
606E26550 2.000 EACH ANCHOR ASSEMBLY, MGS TYPE T 845.0000 845.0000 $1,690.00
606E27800 174.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE A 502.5776 458.2989 $79,744.00
606E27801 85.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE A, AS PER 490.0962 481.0000 $40,885.00
PLAN
606E27820 173.000 EACH ANCHOR ASSEMBLY, MGS TYPE T 810.7420 810.0386 $140,136.68
606E27821 2.000 EACH ANCHOR ASSEMBLY, MGS TYPE T, AS PER PLAN 902.8571 915.0000 $1,830.00
606E27841 136.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE B, AS PER 499.8614 472.2574 $64,227.00
PLAN
606E27850 8.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE E 1,004.0204 859.7500 $6,878.00
606E27851 687.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE E, AS PER 649.6607 609.5822 $418,783.00
PLAN
606E27900 20.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE T 472.5000 495.0000 $9,900.00
606E27901 59.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE T, AS PER 476.9318 470.3390 $27,750.00
PLAN
606E28050 1.000 EACH ANCHOR ASSEMBLY REBUILT, TYPE E-98 1,331.0000 1,408.0000 $1,408.00
606E28151 24.000 EACH ANCHOR ASSEMBLY REBUILT, MGS TYPE T, AS 375.0000 250.0000 $6,000.00
PER PLAN
606E31100 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE C 287.5000 200.0000 $200.00
606E31101 2.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 487.5000 487.5000 $975.00
C, AS PER PLAN
606E31500 8.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE D 558.3333 575.0000 $4,600.00
606E31501 2.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE D, AS PER 636.5000 623.0000 $1,246.00
PLAN
606E31600 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE D 275.0000 200.0000 $200.00
606E31601 3.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 525.0000 525.0000 $1,575.00
D, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
107 | P a g e
606E32000 4.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE E 583.3333 600.0000 $2,400.00
606E32100 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE E 262.5000 200.0000 $200.00
606E32101 3.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 473.3333 473.3333 $1,420.00
E, AS PER PLAN
606E32160 156.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE TST 1,180.6887 1,185.4069 $184,923.48
606E32161 5.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE TST, AS 1,421.8371 1,470.0000 $7,350.00
PER PLAN
606E32171 7.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 277.8571 277.8571 $1,945.00
TST, AS PER PLAN
606E32600 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE F 437.5000 350.0000 $350.00
606E32601 2.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 625.0000 625.0000 $1,250.00
F, AS PER PLAN
606E33050 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE G 312.5000 250.0000 $250.00
606E33051 2.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 437.5000 437.5000 $875.00
G, AS PER PLAN
606E33600 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE H 412.5000 350.0000 $350.00
606E33601 2.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 475.0000 475.0000 $950.00
H, AS PER PLAN
606E34100 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE J 285.0000 250.0000 $250.00
606E34101 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 350.0000 350.0000 $350.00
J, AS PER PLAN
606E35000 425.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 1 1,158.2210 1,127.4380 $479,161.16
606E35001 14.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 1, AS PER 1,113.0293 1,160.0000 $16,240.00
PLAN
606E35002 4.000 EACH MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 1,835.0000 1,835.0000 $7,340.00
606E35004 3.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 1, 1,691.0000 1,721.6667 $5,165.00
BARRIER DESIGN
606E35010 9.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 1 1,036.9154 1,119.2356 $10,073.12
606E35011 25.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 877.6000 877.6000 $21,940.00
1, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
108 | P a g e
606E35050 163.000 EACH MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 1,923.6019 1,901.7496 $309,985.18
606E35051 1.000 EACH MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, AS 1,932.8333 1,880.0000 $1,880.00
PER PLAN
606E35054 7.000 EACH MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, 2,889.4865 2,850.0000 $19,950.00
BARRIER DESIGN
606E35100 154.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 2 340.4015 314.0260 $48,360.00
606E35101 4.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 2, AS PER 337.5000 300.0000 $1,200.00
PLAN
606E35111 11.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 319.0909 319.0909 $3,510.00
2, AS PER PLAN
606E35114 48.000 EACH MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 363.2951 366.2252 $17,578.81
606E35120 10.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 3 1,377.3077 1,300.5000 $13,005.00
606E35121 1.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 3, AS PER 637.5000 250.0000 $250.00
PLAN
606E35130 6.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 3 1,821.4286 1,673.3333 $10,040.00
606E35131 6.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 240.8333 240.8333 $1,445.00
3, AS PER PLAN
606E35140 326.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 4 608.3012 593.3735 $193,439.76
606E35141 1.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE 4, AS PER 550.0000 550.0000 $550.00
PLAN
606E35150 5.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 4 432.3077 410.0000 $2,050.00
606E35151 4.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 365.0000 336.2500 $1,345.00
4, AS PER PLAN
606E35170 22.000 EACH BRIDGE TERMINAL ASSEMBLY, TYPE BR-1 1,349.2115 1,418.1818 $31,200.00
606E35181 1.000 EACH BRIDGE TERMINAL ASSEMBLY REBUILT, TYPE 1,050.0000 1,050.0000 $1,050.00
BR-1, AS PER PLAN
606E35500 6.000 EACH MGS BRIDGE TERMINAL ASSEMBLY REBUILT, 675.0000 500.0000 $3,000.00
TYPE 1
606E35600 6.000 EACH MGS BRIDGE TERMINAL ASSEMBLY REBUILT, 175.0000 200.0000 $1,200.00
TYPE 2
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
109 | P a g e
606E39001 2.000 EACH 36" CONCRETE ANCHOR REMOVED AND 380.0000 380.0000 $760.00
REPLACED, AS PER PLAN
606E40000 1.000 EACH SPECIAL - 36" CONCRETE ANCHOR 245.0000 245.0000 $245.00
606E50000 24,435.000 FT SPECIAL - RESHAPING BERM 0.4698 0.4632 $11,319.00
606E60002 22.000 EACH IMPACT ATTENUATOR, TYPE 1 3,590.2651 3,723.6364 $81,920.00
(UNIDIRECTIONAL)
606E60012 111.000 EACH IMPACT ATTENUATOR, TYPE 1 3,786.2278 3,591.7852 $398,688.16
(BIDIRECTIONAL)
606E60022 7.000 EACH IMPACT ATTENUATOR, TYPE 2 17,832.6062 19,996.2686 $139,973.88
(UNIDIRECTIONAL)
606E60028 52.000 EACH IMPACT ATTENUATOR, TYPE 2 17,537.9759 17,117.7394 $890,122.45
(BIDIRECTIONAL)
606E60032 1.000 EACH IMPACT ATTENUATOR, TYPE 3 21,450.0000 21,450.0000 $21,450.00
606E60033 3.000 EACH IMPACT ATTENUATOR, TYPE 3, AS PER PLAN 23,756.2500 23,400.0000 $70,200.00
606E60040 2.000 EACH IMPACT ATTENUATOR, TYPE 3 UNIDIRECTIONAL 25,040.0000 23,850.0000 $47,700.00
606E60050 7.000 EACH IMPACT ATTENUATOR, TYPE 3 16,372.9954 16,600.0000 $116,200.00
(BIDIRECTIONAL)
606E60060 10.000 EACH IMPACT ATTENUATOR REBUILT, TYPE 1 1,850.0000 1,850.0000 $18,500.00
(UNIDIRECTIONAL), AS PER PLAN
606E60070 10.000 EACH IMPACT ATTENUATOR REBUILT, TYPE 1 1,875.0000 1,875.0000 $18,750.00
(BIDIRECTIONAL), AS PER PLAN
606E61000 546.000 EACH IMPACT ATTENUATOR, MISC.: 707.2900 708.6465 $386,921.00
606E70000 1.000 EACH THRIE BEAM BULLNOSE 3,835.0000 3,550.0000 $3,550.00
606E71000 75.000 FT THRIE BEAM GUARDRAIL 21.5500 23.5000 $1,762.50
606E98000 184,492.250 FT GUARDRAIL, MISC.: 11.9316 12.1060 $2,233,467.30
606E98100 9,347.000 EACH GUARDRAIL, MISC.: 158.9399 140.8999 $1,316,991.70
606E98200 1.000 LS GUARDRAIL, MISC.: 45,867.0914 50,000.0000 $50,000.00
606E99000 12.000 LS SPECIAL - GUARDRAIL 121,977.0602 185,604.9050 $2,227,258.86
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
110 | P a g e
606E99200 1,526.000 EACH ANCHOR ASSEMBLY, MISC.: 469.4686 650.9771 $993,391.00
606E99300 2.000 LS SPECIAL - NOISE BARRIERS 1,672,416.2586 1,587,386.1850 $3,174,772.37
607E15000 69,830.000 FT FENCE, TYPE 47 7.2474 6.0901 $425,272.95
607E15001 30,970.000 FT FENCE, TYPE 47, AS PER PLAN 5.6819 5.8471 $181,086.00
607E15100 1,444.000 FT FENCE, TYPE 47RA 10.9134 10.4291 $15,059.60
607E16000 7,222.000 FT FENCE REBUILT, TYPE 47 7.8119 6.1257 $44,240.00
607E16001 260.000 FT FENCE REBUILT, TYPE 47, AS PER PLAN 21.2502 25.5077 $6,632.00
607E20000 12,366.000 FT FENCE, TYPE CL 17.9950 17.8992 $221,341.56
607E20001 515.000 FT FENCE, TYPE CL, AS PER PLAN 26.6395 26.1942 $13,490.00
607E20100 2,805.000 FT FENCE, TYPE CL, MISC.: 27.9628 24.8920 $69,822.00
607E22000 3,871.000 FT FENCE REBUILT, TYPE CL 16.5656 15.6069 $60,414.40
607E22001 69.000 FT FENCE REBUILT, TYPE CL, AS PER PLAN 41.7316 42.0348 $2,900.40
607E23000 17,357.000 FT FENCE, TYPE CLT 15.3197 15.0772 $261,694.60
607E23001 16,615.000 FT FENCE, TYPE CLT, AS PER PLAN 15.6671 16.0343 $266,409.80
607E23004 3,299.000 FT FENCE REBUILT, TYPE CLT 12.8404 12.4250 $40,990.00
607E23100 328.000 FT FENCE REBUILT 24.9344 24.3659 $7,992.00
607E23101 52.000 FT FENCE REBUILT, AS PER PLAN 19.1700 18.5000 $962.00
607E30000 60.000 FT FENCE, SNOW 10.4950 15.0000 $900.00
607E30001 2,531.000 FT FENCE, SNOW, AS PER PLAN 6.0108 3.7578 $9,511.00
607E35000 529.000 FT FENCE REMOVED AND REBUILT 14.2167 12.8280 $6,786.00
607E35001 877.000 FT FENCE REMOVED AND REBUILT, AS PER PLAN 88.1337 53.7180 $47,110.66
607E39900 6,765.000 FT SPECIAL - VANDAL PROTECTION FENCE, 6' 62.6448 71.5781 $484,225.75
STRAIGHT, COATED FABRIC
607E39901 11,340.000 FT VANDAL PROTECTION FENCE, 6' STRAIGHT, 64.0612 65.6265 $744,204.25
COATED FABRIC, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
111 | P a g e
607E39910 134.000 FT SPECIAL - VANDAL PROTECTION FENCE, 8' 119.5037 130.8060 $17,528.00
STRAIGHT, COATED FABRIC
607E39911 1,235.000 FT VANDAL PROTECTION FENCE, 8' STRAIGHT, 78.2493 78.1717 $96,542.00
COATED FABRIC, AS PER PLAN
607E39931 317.000 FT VANDAL PROTECTION FENCE, 12' CURVED, 138.6500 143.0000 $45,331.00
COATED FABRIC, AS PER PLAN
607E40000 1,305.000 FT SPECIAL - VANDAL PROTECTION FENCE 71.4102 69.0566 $90,118.82
607E40300 578.000 FT SPECIAL - VANDAL PROTECTION FENCE 40.0000 40.0000 $23,120.00
REMOVED AND REBUILT
607E50900 8.000 EACH GATE, TYPE CL 1,352.0428 1,258.7500 $10,070.00
607E50901 5.000 EACH GATE, TYPE CL, AS PER PLAN 1,383.3750 1,728.0000 $8,640.00
607E50902 2.000 EACH GATE, TYPE CL (MISC. HT.) 1,546.6063 1,850.0000 $3,700.00
607E61100 5.000 EACH GATE REBUILT, TYPE CL 1,397.3077 816.0000 $4,080.00
607E61101 1.000 EACH GATE REBUILT, TYPE CL, AS PER PLAN 565.0000 695.0000 $695.00
607E61111 3.000 EACH GATE REBUILT, AS PER PLAN 946.4186 432.0000 $1,296.00
607E61200 6.000 EACH GATE, TYPE CLT 1,603.1333 2,029.8333 $12,179.00
607E61201 2.000 EACH GATE, TYPE CLT, AS PER PLAN 2,976.4286 2,945.0000 $5,890.00
607E70000 50,812.000 FT FENCELINE SEEDING AND MULCHING 0.4822 0.4597 $23,359.92
607E98000 27,605.000 FT FENCE, MISC.: 27.8838 29.4660 $813,408.55
607E98100 277.000 EACH FENCE, MISC.: 290.9348 165.3971 $45,815.00
607E98200 1.000 LS FENCE, MISC.: 2,409.6250 300.0000 $300.00
607E99000 1.000 LS SPECIAL - FENCE 22,500.0000 25,000.0000 $25,000.00
608E10000 504,614.000 SF 4" CONCRETE WALK 4.2693 4.4157 $2,228,246.10
608E10001 228,216.000 SF 4" CONCRETE WALK, AS PER PLAN 5.2344 4.5618 $1,041,069.44
608E12000 29,685.000 SF 5" CONCRETE WALK 5.4367 4.5204 $134,186.75
608E12001 5,079.000 SF 5" CONCRETE WALK, AS PER PLAN 8.1305 4.0866 $20,756.00
608E13000 86,670.000 SF 6" CONCRETE WALK 4.5704 4.0602 $351,896.83
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
112 | P a g e
608E13001 63,345.000 SF 6" CONCRETE WALK, AS PER PLAN 5.4188 4.8252 $305,653.16
608E13020 772.000 SF 7" CONCRETE WALK 9.3540 7.0000 $5,404.00
608E15000 17,681.000 SF 8" CONCRETE WALK 7.5099 7.2632 $128,420.24
608E15001 38,338.000 SF 8" CONCRETE WALK, AS PER PLAN 6.1395 5.8197 $223,114.00
608E20000 5,716.000 SF 2" ASPHALT CONCRETE WALK 4.0808 3.4768 $19,873.40
608E20001 16,287.000 SF 2" ASPHALT CONCRETE WALK, AS PER PLAN 5.0000 4.5000 $73,291.50
608E20010 157.000 SF 3" ASPHALT CONCRETE WALK 5.0160 2.6400 $414.48
608E21000 3,673.000 SF 4" ASPHALT CONCRETE WALK 5.1986 6.1302 $22,516.36
608E21200 2,396.000 SF TEMPORARY ASPHALT CONCRETE WALK 4.9375 5.0000 $11,980.00
608E21201 1,500.000 SF TEMPORARY ASPHALT CONCRETE WALK, AS PER 2.8125 1.0000 $1,500.00
PLAN
608E30000 250.000 SF AGGREGATE WALK 7.8200 5.0000 $1,250.00
608E40000 115.000 FT CONCRETE STEPS, TYPE A 127.8780 101.3043 $11,650.00
608E40001 326.000 FT CONCRETE STEPS, TYPE A, AS PER PLAN 172.1286 221.9877 $72,368.00
608E41000 46.000 FT CONCRETE STEPS, TYPE B 124.5788 98.9348 $4,551.00
608E42000 10.000 FT CONCRETE STEPS, MISC.: 275.0000 100.0000 $1,000.00
608E49000 63.000 EACH CURB RAMP 378.9090 161.7341 $10,189.25
608E49001 174.000 EACH CURB RAMP, AS PER PLAN 979.1097 940.7802 $163,695.76
608E52000 40,306.000 SF CURB RAMP 10.9359 12.0078 $483,987.01
608E52001 43,068.000 SF CURB RAMP, AS PER PLAN 8.3092 8.2077 $353,488.00
608E52002 13,316.000 SF CURB RAMP 12.0028 11.6681 $155,372.65
608E52003 7,720.000 SF CURB RAMP, AS PER PLAN 15.1631 13.6680 $105,517.00
608E52010 8,399.000 SF CURB RAMP, TYPE A 10.9148 10.4500 $87,769.45
608E52011 1,230.000 SF CURB RAMP, TYPE A1, AS PER PLAN 14.5714 9.2500 $11,377.50
608E52020 13,497.000 SF CURB RAMP, TYPE A2 11.2094 11.1569 $150,584.81
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
113 | P a g e
608E52021 1,693.000 SF CURB RAMP, TYPE A2, AS PER PLAN 12.4964 13.6697 $23,142.80
608E52030 5,515.000 SF CURB RAMP, TYPE B1 10.5139 9.7104 $53,553.05
608E52031 283.000 SF CURB RAMP, TYPE B1, AS PER PLAN 13.7071 15.2367 $4,312.00
608E52040 8,738.000 SF CURB RAMP, TYPE D 11.2787 10.5932 $92,563.20
608E52041 1,275.000 SF CURB RAMP, TYPE D, AS PER PLAN 11.3576 9.2936 $11,849.30
608E52044 2,480.000 SF CURB RAMP, TYPE B3 13.4876 12.7853 $31,707.50
608E52045 877.000 SF CURB RAMP, TYPE B3, AS PER PLAN 13.2274 15.2486 $13,373.00
608E52050 1,028.000 SF CURB RAMP, TYPE E 9.9221 10.4076 $10,699.00
608E52051 419.000 SF CURB RAMP, TYPE E, AS PER PLAN 9.1843 8.0000 $3,352.00
608E52060 353.000 SF CURB RAMP, TYPE C2 11.2895 11.4074 $4,026.80
608E52061 72.000 SF CURB RAMP, TYPE C2, AS PER PLAN 12.8000 17.0000 $1,224.00
608E52070 7,190.000 SF CURB RAMP, TYPE D 11.2224 12.0463 $86,613.05
608E52071 640.000 SF CURB RAMP, TYPE D, AS PER PLAN 17.3525 14.0000 $8,960.00
608E52110 22.000 EACH CURB RAMP, TYPE A1 950.0000 950.0000 $20,900.00
608E52120 37.000 EACH CURB RAMP, TYPE A2 782.8589 870.0000 $32,190.00
608E52144 10.000 EACH CURB RAMP, TYPE B3 506.7324 455.8280 $4,558.28
608E52160 1.000 EACH CURB RAMP, TYPE C2 500.7920 400.9200 $400.92
608E52170 13.000 EACH CURB RAMP, TYPE D 950.0000 950.0000 $12,350.00
608E53010 85.000 SF DETECTABLE WARNING 41.3175 36.0000 $3,060.00
608E53011 1,289.000 SF DETECTABLE WARNING, AS PER PLAN 24.5144 30.6028 $39,446.96
608E53020 3,560.000 SF DETECTABLE WARNING 33.4960 30.0411 $106,946.20
608E53021 192.000 SF DETECTABLE WARNING, AS PER PLAN 60.4412 58.3333 $11,200.00
608E97200 120.000 EACH CURB RAMP, MISC.: 513.3841 541.8750 $65,025.00
608E98000 89,859.000 SF WALKWAY, MISC.: 12.4390 11.9529 $1,074,076.30
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
114 | P a g e
608E98200 100.000 EACH WALKWAY, MISC.: 11.7438 2.2000 $220.00
609E10000 1,048.000 FT ASPHALT CONCRETE CURB, TYPE 1 19.1012 20.6450 $21,636.00
609E12000 52,546.000 FT COMBINATION CURB AND GUTTER, TYPE 2 17.9005 17.3683 $912,634.40
609E12001 46,173.000 FT COMBINATION CURB AND GUTTER, TYPE 2, AS 15.1596 15.0198 $693,509.00
PER PLAN
609E14000 9,221.000 FT CURB, TYPE 2-A 6.7904 6.9934 $64,486.37
609E14001 7,107.000 FT CURB, TYPE 2-A, AS PER PLAN 8.7854 6.1080 $43,409.50
609E16000 782.000 FT CURB, TYPE 2-B 12.0246 7.6900 $6,013.60
609E16001 4,376.000 FT CURB, TYPE 2-B, AS PER PLAN 6.1846 6.3926 $27,974.00
609E18000 1,756.000 FT COMBINATION CURB AND GUTTER, TYPE 3 20.7945 18.5676 $32,604.70
609E18001 40.000 FT COMBINATION CURB AND GUTTER, TYPE 3, AS 28.3333 37.0000 $1,480.00
PER PLAN
609E23000 372.000 FT COMBINATION CURB AND GUTTER, TYPE 4 27.7634 27.3871 $10,188.00
609E23001 321.000 FT COMBINATION CURB AND GUTTER, TYPE 4, AS 27.6667 28.0000 $8,988.00
PER PLAN
609E24000 2,295.000 FT CURB, TYPE 4-A 17.0407 18.1872 $41,739.68
609E24001 40.000 FT CURB, TYPE 4-A, AS PER PLAN 52.6250 52.0000 $2,080.00
609E24500 2,274.000 FT CURB, TYPE 4-B 11.2396 9.6240 $21,884.90
609E24510 13,474.000 FT CURB, TYPE 4-C 22.3185 22.8397 $307,742.47
609E24511 4,290.000 FT CURB, TYPE 4-C, AS PER PLAN 18.8462 14.3715 $61,653.90
609E26000 114,170.000 FT CURB, TYPE 6 14.3237 13.9677 $1,594,687.37
609E26001 22,678.000 FT CURB, TYPE 6, AS PER PLAN 17.9713 13.6914 $310,493.50
609E28000 264.000 FT CURB, TYPE 7 25.9257 31.2356 $8,246.20
609E30000 217.000 FT CURB, TYPE 8 28.0128 27.9816 $6,072.00
609E30001 1,571.000 FT CURB, TYPE 8, AS PER PLAN 44.6255 58.5500 $91,982.00
609E50000 94.000 SY 4" CONCRETE TRAFFIC ISLAND 69.7361 105.3617 $9,904.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
115 | P a g e
609E54000 730.000 SY 6" CONCRETE TRAFFIC ISLAND 57.3005 63.8259 $46,592.92
609E57000 213.000 SY 8" CONCRETE TRAFFIC ISLAND 70.2021 55.8873 $11,904.00
609E58000 675.000 SY 9" CONCRETE TRAFFIC ISLAND 49.7388 47.9813 $32,387.40
609E58001 227.000 SY 9" CONCRETE TRAFFIC ISLAND, AS PER PLAN 102.5000 105.0000 $23,835.00
609E70000 630.000 SY 4" CONCRETE MEDIAN 53.5000 53.5000 $33,705.00
609E71000 3,948.000 SF CONCRETE MEDIAN 13.5000 6.0000 $23,688.00
609E72000 903.000 SY CONCRETE MEDIAN 64.3175 70.0472 $63,252.60
609E72001 3,236.000 SY CONCRETE MEDIAN, AS PER PLAN 70.6501 65.9419 $213,388.00
609E72100 53.000 CY CONCRETE MEDIAN 455.0000 455.0000 $24,115.00
609E96000 125.000 SY MEDIAN, MISC.: 109.8000 82.5000 $10,312.50
609E98000 20,018.000 FT CURB, MISC.: 30.4115 29.4343 $589,216.60
609E98100 1.000 EACH CURB, MISC.: 648.7500 1,000.0000 $1,000.00
610E50000 3,134.000 EACH SPECIAL - RETAINING WALL, MISC.: 496.4017 432.5150 $1,355,502.00
610E50010 95,686.000 SF SPECIAL - RETAINING WALL, MISC.: 21.6256 14.9032 $1,426,026.36
610E50020 6,628.000 FT SPECIAL - RETAINING WALL, MISC.: 50.0648 45.9419 $304,503.00
610E50030 955.000 SY SPECIAL - RETAINING WALL, MISC.: 88.7078 65.3889 $62,446.40
610E60000 19.000 LS SPECIAL - RETAINING WALL, MISC.: 139,051.9766 149,904.2105 $2,848,180.00
610E99000 1.000 LS SPECIAL - RETAINING WALL 8,558.8814 1,000.0000 $1,000.00
611E00100 403.000 FT 4" CONDUIT, TYPE B 19.7403 15.9156 $6,414.00
611E00200 158.000 FT 4" CONDUIT, TYPE C 10.3871 8.1646 $1,290.00
611E00400 550.000 FT 4" CONDUIT, TYPE E 6.6579 7.6364 $4,200.00
611E00401 90.000 FT 4" CONDUIT, TYPE E, AS PER PLAN 5.7723 2.8889 $260.00
611E00406 324.000 FT 4" CONDUIT, TYPE F 13.8880 13.5802 $4,400.00
611E00410 148.000 FT 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET 16.5067 11.0946 $1,642.00
611E00510 3,450.000 FT 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET 16.2503 13.0333 $44,964.86
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
116 | P a g e
611E00900 2,423.000 FT 6" CONDUIT, TYPE B 23.2320 22.9133 $55,519.00
611E01100 1,338.000 FT 6" CONDUIT, TYPE C 18.8065 17.8416 $23,872.00
611E01400 805.000 FT 6" CONDUIT, TYPE E 11.9203 9.3863 $7,556.00
611E01401 1,763.000 FT 6" CONDUIT, TYPE E, AS PER PLAN 10.8988 4.0000 $7,052.00
611E01500 1,223.000 FT 6" CONDUIT, TYPE F 16.8059 22.2911 $27,262.05
611E01501 107.000 FT 6" CONDUIT, TYPE F, AS PER PLAN 17.7000 8.0000 $856.00
611E01907 75.000 FT 8" CONDUIT, TYPE B, DUCTILE IRON PIPE 176.0000 180.0000 $13,500.00
ANSI CLASS 52, MECHANICAL JOINTS AND FITTINGS, AS PER PLAN
611E02000 19.000 FT 8" CONDUIT, TYPE C 45.6958 37.3711 $710.05
611E02001 40.000 FT 8" CONDUIT, TYPE C, AS PER PLAN 61.8333 20.0000 $800.00
611E02500 300.000 FT 8" CONDUIT, TYPE E 12.8125 7.6000 $2,280.00
611E02600 90.000 FT 8" CONDUIT, TYPE F 16.5700 14.2700 $1,284.30
611E03100 414.000 FT 10" CONDUIT, TYPE B 48.9860 24.0000 $9,936.00
611E03201 369.000 FT 10" CONDUIT, TYPE B, DUCTILE IRON PIPE 160.0000 200.0000 $73,800.00
ANSI CLASS 53, PUSH-ON JOINTS AND FITTINGS, AS PER PLAN
611E04200 69.000 FT 12" CONDUIT, TYPE A 68.7605 70.4841 $4,863.40
611E04400 4,406.000 FT 12" CONDUIT, TYPE B 57.9918 56.1428 $247,365.00
611E04401 430.000 FT 12" CONDUIT, TYPE B, AS PER PLAN 106.6667 75.0000 $32,250.00
611E04600 4,372.000 FT 12" CONDUIT, TYPE C 44.9938 42.8497 $187,338.75
611E04601 57.000 FT 12" CONDUIT, TYPE C, AS PER PLAN 68.7346 56.1930 $3,203.00
611E04900 220.000 FT 12" CONDUIT, TYPE D 44.2100 39.1836 $8,620.40
611E05200 434.000 FT 12" CONDUIT, TYPE F 48.0399 40.0589 $17,385.56
611E05700 48.000 FT 15" CONDUIT, TYPE A 94.8288 90.0000 $4,320.00
611E05701 15.000 FT 15" CONDUIT, TYPE A, AS PER PLAN 69.5540 112.7700 $1,691.55
611E05900 1,105.000 FT 15" CONDUIT, TYPE B 68.3961 54.8303 $60,587.49
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
117 | P a g e
611E06100 9,479.000 FT 15" CONDUIT, TYPE C 45.2647 30.4120 $288,275.00
611E06101 150.000 FT 15" CONDUIT, TYPE C, AS PER PLAN 96.6667 90.0000 $13,500.00
611E06400 30.000 FT 15" CONDUIT, TYPE D 45.8000 40.0000 $1,200.00
611E06700 397.000 FT 15" CONDUIT, TYPE F 60.7390 41.0680 $16,304.00
611E07200 83.000 FT 18" CONDUIT, TYPE A 100.9036 200.0000 $16,600.00
611E07400 2,046.000 FT 18" CONDUIT, TYPE B 64.8803 55.8973 $114,365.80
611E07600 1,379.000 FT 18" CONDUIT, TYPE C 55.4077 48.3112 $66,621.10
611E07900 132.000 FT 18" CONDUIT, TYPE D 45.4909 42.1212 $5,560.00
611E08200 74.000 FT 18" CONDUIT, TYPE F 78.3333 35.0000 $2,590.00
611E09100 725.000 FT 21" CONDUIT, TYPE C 61.9060 60.8748 $44,134.20
611E10200 61.000 FT 24" CONDUIT, TYPE A 100.2000 92.0000 $5,612.00
611E10400 1,487.000 FT 24" CONDUIT, TYPE B 87.3262 73.8810 $109,861.00
611E10401 99.000 FT 24" CONDUIT, TYPE B, AS PER PLAN 120.0000 100.0000 $9,900.00
611E10600 2,834.000 FT 24" CONDUIT, TYPE C 64.1150 54.1793 $153,544.06
611E10601 229.000 FT 24" CONDUIT, TYPE C, AS PER PLAN 136.5197 89.5590 $20,509.00
611E11900 205.000 FT 27" CONDUIT, TYPE B 94.2000 86.0000 $17,630.00
611E12100 1,207.000 FT 27" CONDUIT, TYPE C 73.0000 69.0000 $83,283.00
611E13200 87.000 FT 30" CONDUIT, TYPE A 132.4000 132.0000 $11,484.00
611E13400 204.000 FT 30" CONDUIT, TYPE B 190.0000 190.0000 $38,760.00
611E13401 110.000 FT 30" CONDUIT, TYPE B, AS PER PLAN 216.6667 165.0000 $18,150.00
611E13600 351.000 FT 30" CONDUIT, TYPE C 92.2555 87.0217 $30,544.60
611E13900 98.000 FT 30" CONDUIT, TYPE D 96.2750 90.0000 $8,820.00
611E15100 311.000 FT 33" CONDUIT, TYPE C 93.0933 66.5000 $20,681.50
611E16200 78.000 FT 36" CONDUIT, TYPE A 208.2280 110.0600 $8,584.68
611E16201 192.000 FT 36" CONDUIT, TYPE A, AS PER PLAN 214.3333 208.0000 $39,936.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
118 | P a g e
611E16400 96.000 FT 36" CONDUIT, TYPE B 136.9618 92.0000 $8,832.00
611E16600 137.000 FT 36" CONDUIT, TYPE C 234.7127 204.4964 $28,016.00
611E16901 112.000 FT 36" CONDUIT, TYPE D, AS PER PLAN 83.5000 50.0000 $5,600.00
611E23600 141.000 FT 60" CONDUIT, TYPE A 335.6813 291.6667 $41,125.00
611E25000 35.000 FT 66" CONDUIT, TYPE A 434.7875 190.0000 $6,650.00
611E26201 12.000 FT 72" CONDUIT, TYPE B, AS PER PLAN 8,136.0433 5,000.0000 $60,000.00
611E52900 64.000 FT 34" X 53" CONDUIT, TYPE A, 706.04 179.5300 160.0000 $10,240.00
611E53100 8.000 FT 43" X 68" CONDUIT, TYPE A, 706.04 365.0000 295.0000 $2,360.00
611E53901 102.000 FT 82"X128" CONDUIT, TYPE A, 706.04, AS PER 503.6900 537.3300 $54,807.66
PLAN
611E70000 196.000 FT CONDUIT, TYPE A, PRECAST REINFORCED 1,039.6233 1,114.2857 $218,400.00
CONCRETE THREE SIDED FLAT TOPPED CULVERT
611E70001 43.000 FT CONDUIT, TYPE A, PRECAST REINFORCED 3,143.9760 2,488.0000 $106,984.00
CONCRETE THREE SIDED FLAT TOPPED
CULVERT, AS PER PLAN
611E95200 96.000 FT 10' X 6' CONDUIT, TYPE A, 706.05 621.6000 525.0000 $50,400.00
611E95801 55.000 FT 12' X 6' CONDUIT, TYPE A, 706.05, AS PER 1,008.8000 978.0000 $53,790.00
PLAN
611E96321 72.000 FT 14' X 7' CONDUIT, TYPE A, 706.05, AS PER 959.3443 1,010.1200 $72,728.64
PLAN
611E96485 126.000 FT 18' X 10' CONDUIT, TYPE A, 706.05, AS 2,181.7420 2,137.0000 $269,262.00
PER PLAN
611E96487 38.000 FT 20'X7' CONDUIT, TYPE A, 706.05, AS PER 1,723.7100 1,122.0000 $42,636.00
PLAN
611E96550 1,873.000 FT FIELD PAVING OF EXISTING PIPE 115.8066 122.0400 $228,581.00
611E97200 5.000 EACH CONDUIT, MISC.: 2,843.1920 3,652.7600 $18,263.80
611E97300 2.000 LS CONDUIT, MISC.: 5,333.3333 3,500.0000 $7,000.00
611E97400 391.000 FT CONDUIT, MISC.: 1,121.0300 1,086.1893 $424,700.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
119 | P a g e
611E97800 14.000 LS SPECIAL - DRAINAGE 371,761.6122 370,423.6571 $5,185,931.20
611E98150 20.000 EACH CATCH BASIN, NO. 3 2,689.8841 2,930.0000 $58,600.00
611E98180 44.000 EACH CATCH BASIN, NO. 3A 2,070.4468 2,281.3498 $100,379.39
611E98230 63.000 EACH CATCH BASIN, NO. 4 3,343.3677 3,804.7937 $239,702.00
611E98270 1.000 EACH CATCH BASIN, NO. 4A 4,083.5833 5,103.0000 $5,103.00
611E98300 2.000 EACH CATCH BASIN, NO. 5 3,480.0000 2,900.0000 $5,800.00
611E98370 7.000 EACH CATCH BASIN, NO. 6 1,981.9718 2,010.0000 $14,070.00
611E98390 1.000 EACH CATCH BASIN, NO. 7 1,841.6667 1,250.0000 $1,250.00
611E98410 17.000 EACH CATCH BASIN, NO. 8 3,277.8160 3,396.5947 $57,742.11
611E98434 1.000 EACH CATCH BASIN, NO. 8A 3,173.8767 3,036.0000 $3,036.00
611E98450 4.000 EACH CATCH BASIN, NO. 2-2A 1,589.2308 1,325.0000 $5,300.00
611E98470 73.000 EACH CATCH BASIN, NO. 2-2B 1,374.9465 1,146.9578 $83,727.92
611E98510 31.000 EACH CATCH BASIN, NO. 2-3 1,607.4468 1,616.9355 $50,125.00
611E98511 2.000 EACH CATCH BASIN, NO. 2-3, AS PER PLAN 1,325.6250 1,200.0000 $2,400.00
611E98540 1.000 EACH CATCH BASIN, NO. 2-4 2,013.3333 2,200.0000 $2,200.00
611E98630 130.000 EACH CATCH BASIN ADJUSTED TO GRADE 562.0472 527.8158 $68,616.06
611E98631 19.000 EACH CATCH BASIN ADJUSTED TO GRADE, AS PER 1,672.2460 1,608.8421 $30,568.00
PLAN
611E98634 21.000 EACH CATCH BASIN RECONSTRUCTED TO GRADE 1,186.9764 778.8095 $16,355.00
611E98635 10.000 EACH CATCH BASIN RECONSTRUCTED TO GRADE, AS 1,126.9231 1,290.0000 $12,900.00
PER PLAN
611E98644 1.000 EACH CATCH BASIN GRATE 381.9000 400.0000 $400.00
611E98690 9.000 EACH CATCH BASIN, MISC.: 1,772.0561 1,322.2222 $11,900.00
611E98700 2.000 EACH INLET, SIDE DITCH 997.5000 1,000.0000 $2,000.00
611E98811 2.000 EACH INLET, NO. 3C, AS PER PLAN 7,233.3333 9,500.0000 $19,000.00
611E98820 8.000 EACH INLET, NO. 3D 6,400.0000 7,200.0000 $57,600.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
120 | P a g e
611E98860 2.000 EACH INLET, NO. 2-A-10 4,733.3333 4,000.0000 $8,000.00
611E99094 32.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 4,375.0000 3,750.0000 $120,000.00
TYPE B
611E99104 4.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 5,650.0000 6,000.0000 $24,000.00
TYPE C
611E99105 3.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 8,250.0000 6,500.0000 $19,500.00
TYPE C, AS PER PLAN
611E99114 3.000 EACH INLET, NO. 3 FOR SINGLE SLOPE BARRIER, 6,500.0000 7,500.0000 $22,500.00
TYPE D
611E99150 56.000 EACH INLET ADJUSTED TO GRADE 666.4118 627.5893 $35,145.00
611E99154 35.000 EACH INLET RECONSTRUCTED TO GRADE 1,070.7317 1,082.8571 $37,900.00
611E99155 2.000 EACH INLET RECONSTRUCTED TO GRADE, AS PER 1,250.0000 1,250.0000 $2,500.00
PLAN
611E99574 25.000 EACH MANHOLE, NO. 3 2,872.7568 2,920.6400 $73,016.00
611E99580 3.000 EACH MANHOLE, NO. 3 WITH 84" BASE I.D. AND 6" 5,344.0000 6,400.0000 $19,200.00
WEIR
611E99586 1.000 EACH MANHOLE, NO. 3 W/108" BASE I.D. & 12" 9,600.0000 5,800.0000 $5,800.00
WEIR
611E99620 1.000 EACH MANHOLE, NO. 5 6,725.4900 4,400.0000 $4,400.00
611E99654 336.000 EACH MANHOLE ADJUSTED TO GRADE 493.2814 485.1518 $163,011.00
611E99655 189.000 EACH MANHOLE ADJUSTED TO GRADE, AS PER PLAN 511.8344 522.5397 $98,760.00
611E99660 14.000 EACH MANHOLE RECONSTRUCTED TO GRADE 758.0215 871.4286 $12,200.00
611E99661 1.000 EACH MANHOLE RECONSTRUCTED TO GRADE, AS PER 1,833.3333 1,500.0000 $1,500.00
PLAN
611E99690 5.000 EACH MANHOLE, MISC.: 5,797.5589 7,452.8000 $37,264.00
611E99710 84.000 EACH PRECAST REINFORCED CONCRETE OUTLET 225.7648 155.4248 $13,055.68
611E99720 2.000 EACH INSPECTION WELL 836.9936 1,500.0000 $3,000.00
611E99820 13,600.000 LB SPECIAL - MISCELLANEOUS METAL 1.2988 1.6662 $22,660.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
121 | P a g e
611E99830 163.000 FT SPECIAL - TRENCH DRAIN 183.3333 300.0000 $48,900.00
611E99900 7.000 EACH DRAINAGE STRUCTURE, MISC.: 10,432.5090 5,722.5714 $40,058.00
611E99910 80.000 FT DRAINAGE STRUCTURE, MISC.: 197.5000 45.0000 $3,600.00
613E41200 12,550.300 CY LOW STRENGTH MORTAR BACKFILL 86.8094 81.1725 $1,018,739.83
613E41201 711.000 CY LOW STRENGTH MORTAR BACKFILL, AS PER PLAN 86.6092 90.8889 $64,622.00
613E41251 321.000 CY LOW STRENGTH MORTAR BACKFILL (TYPE 1), 75.6984 52.0000 $16,692.00
AS PER PLAN
613E41300 1,133.000 CY LOW STRENGTH MORTAR BACKFILL (TYPE 2) 58.1913 68.9896 $78,165.21
614E11000 615.000 LS MAINTAINING TRAFFIC 50,182.2022 49,853.6360 $30,659,986.15
614E11001 59.000 LS MAINTAINING TRAFFIC, AS PER PLAN 204,990.2354 167,778.8807 $9,898,953.96
614E11110 54,609.000 HOUR LAW ENFORCEMENT OFFICER WITH PATROL CAR 68.3191 58.5715 $3,198,530.70
FOR ASSISTANCE
614E11111 202.000 HOUR LAW ENFORCEMENT OFFICER WITH PATROL CAR 66.0860 71.3366 $14,410.00
FOR ASSISTANCE, AS PER PLAN
614E11120 7,530.000 HOUR LAW ENFORCEMENT OFFICER WITH PATROL CAR 57.0768 52.1620 $392,780.00
FOR ENFORCEMENT
614E11300 41.000 EACH SPECIAL - WORK ZONE TRAFFIC SIGNAL 12,353.3779 10,887.3610 $446,381.80
614E11500 366.000 MNTH WORKSITE TRAFFIC SUPERVISOR 5,118.8538 3,146.9093 $1,151,768.80
614E11620 163,931.000 FT LINEAR DELINEATION 1.2434 0.9939 $162,929.76
614E11621 74,789.000 FT LINEAR DELINEATION, AS PER PLAN 1.2650 1.1537 $86,280.66
614E12200 5,043.500 FT SPECIAL - WORK ZONE GUARDRAIL 16.3033 14.9365 $75,332.00
614E12336 540.000 EACH WORK ZONE IMPACT ATTENUATOR 1,979.8506 1,783.7697 $963,235.66
(UNIDIRECTIONAL)
614E12337 3.000 EACH WORK ZONE IMPACT ATTENUATOR 4,877.3320 3,793.3333 $11,380.00
(UNIDIRECTIONAL), AS PER PLAN
614E12338 273.000 EACH WORK ZONE IMPACT ATTENUATOR 1,963.7959 1,807.5105 $493,450.37
(BIDIRECTIONAL)
614E12339 14.000 EACH WORK ZONE IMPACT ATTENUATOR 7,537.0192 9,082.1429 $127,150.00
(BIDIRECTIONAL), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
122 | P a g e
614E12346 114.000 EACH WORK ZONE IMPACT ATTENUATOR, QUADGUARD 2,109.2516 1,960.0979 $223,451.16
CZ (UNIDIRECTIONAL)
614E12348 88.000 EACH WORK ZONE IMPACT ATTENUATOR, QUADGUARD 2,033.8559 1,965.1756 $172,935.45
CZ, (BIDIRECTIONAL)
614E12350 111.000 EACH WORK ZONE IMPACT ATTENUATOR 2,117.1027 1,954.9550 $217,000.00
614E12410 256.000 EACH SPEED ZONE AHEAD SYMBOL SIGN 165.9466 143.4834 $36,731.74
614E12420 133.000 LS DETOUR SIGNING 9,321.2864 8,829.4290 $1,174,314.06
614E12421 13.000 LS DETOUR SIGNING, AS PER PLAN 6,152.4823 5,315.1538 $69,097.00
614E12460 9,365.000 EACH WORK ZONE MARKING SIGN 94.4351 92.3205 $864,581.14
614E12461 96.000 EACH WORK ZONE MARKING SIGN, AS PER PLAN 120.8654 100.2083 $9,620.00
614E12470 769.000 EACH WORK ZONE SPEED LIMIT SIGN 158.6127 138.6192 $106,598.14
614E12484 518.000 EACH WORK ZONE INCREASED PENALTIES SIGN 179.0526 165.6569 $85,810.29
614E12490 34.000 EACH RESUME LEGAL SPEED SIGN 140.7547 121.1765 $4,120.00
614E12500 669.000 EACH REPLACEMENT SIGN 182.0532 155.6002 $104,096.55
614E12600 3,603.000 EACH REPLACEMENT DRUM 51.2810 46.1523 $166,286.90
614E12740 35.000 EACH WORK ZONE LIGHTING SYSTEM 4,766.7882 4,883.9429 $170,938.00
614E12756 56.000 EACH WORK ZONE CROSSOVER LIGHTING SYSTEM 22,608.8126 22,386.2571 $1,253,630.40
614E12757 3.000 EACH WORK ZONE CROSSOVER LIGHTING SYSTEM, AS 26,198.3783 24,500.0000 $73,500.00
PER PLAN
614E12760 18.000 EACH SPECIAL - FLASHING ARROW PANEL 992.9667 781.1111 $14,060.00
614E12800 15,492.000 EACH WORK ZONE RAISED PAVEMENT MARKER 11.7256 13.1694 $204,021.05
614E12801 34,214.000 EACH WORK ZONE RAISED PAVEMENT MARKER, AS PER 9.7588 10.9298 $373,950.84
PLAN
614E13000 22,165.100 CY ASPHALT CONCRETE FOR MAINTAINING TRAFFIC 153.0584 152.9201 $3,389,488.50
614E13001 897.000 CY ASPHALT CONCRETE FOR MAINTAINING 237.9566 222.7893 $199,842.00
TRAFFIC, AS PER PLAN
614E13100 3,527.000 EACH BARRIER REFLECTOR 6.5596 7.1322 $25,155.16
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
123 | P a g e
614E13200 2,068.000 EACH BARRIER REFLECTOR, TYPE A 6.5919 6.7684 $13,997.00
614E13202 258.000 EACH BARRIER REFLECTOR, TYPE A2 10.6110 11.4957 $2,965.89
614E13300 30,568.000 EACH BARRIER REFLECTOR, TYPE B 5.8192 6.1923 $189,285.18
614E13302 1,855.000 EACH BARRIER REFLECTOR, TYPE B2 8.9462 8.2738 $15,347.88
614E13303 7.000 EACH BARRIER REFLECTOR, TYPE B2, AS PER PLAN 9.9500 5.0000 $35.00
614E13350 24,660.000 EACH OBJECT MARKER, ONE WAY 9.8308 9.1925 $226,687.22
614E13351 1,207.000 EACH OBJECT MARKER, ONE WAY, AS PER PLAN 10.4024 10.9942 $13,270.00
614E13360 6,924.000 EACH OBJECT MARKER, TWO WAY 12.4538 11.2852 $78,138.38
614E13600 1,102.000 EACH MAINTENANCE OF TRAFFIC - ONE LANE 143.2103 80.0363 $88,200.00
CLOSURE ON A TWO LANE HIGHWAY
614E13700 71.000 EACH MAINTENANCE OF TRAFFIC, ONE LANE CLOSURE 178.7873 119.3662 $8,475.00
ON A FOUR LANE UNDIVIDED HIGHWAY
614E13800 323.000 EACH MAINTENANCE OF TRAFFIC, ONE LANE CLOSURE 298.5172 242.1981 $78,230.00
ON A 4 LANE OR GREATER DIVIDED HIGHWAY
614E13900 3,567.000 EACH MAINTENANCE OF TRAFFIC FOR SHOULDER 86.5435 77.7390 $277,295.00
CLOSURE
614E15000 43,800.000 DLR SPECIAL - CALENDAR DAYS OF CONTRACT TIME 63.8654 57.1358 $2,502,550.00
FOR OPENING TO TRAFFIC (UNIT PRICE
FIELD SHOULD REFLECT NUMBER OF DAYS BID)
614E18000 548.000 EACH MAINTAINING TRAFFIC, MISC.: 537.1302 356.1157 $195,151.38
614E18002 9.000 LS MAINTAINING TRAFFIC, MISC.: 35,686.6944 33,089.1111 $297,802.00
614E18010 24,100.000 SF MAINTAINING TRAFFIC, MISC.: 6.0986 3.2241 $77,700.00
614E18020 1,643.000 HOUR MAINTAINING TRAFFIC, MISC.: 57.6269 55.1479 $90,608.00
614E18030 60,359.000 FT MAINTAINING TRAFFIC, MISC.: 9.2841 8.0521 $486,019.26
614E18400 904.000 DAY PORTABLE CHANGEABLE MESSAGE SIGN 39.7268 27.4004 $24,770.00
614E18401 37,964.000 DAY PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN 28.6805 27.0281 $1,026,093.58
614E18501 2.000 EACH PORTABLE CHANGEABLE MESSAGE SIGN, AS PER 4,750.0000 4,500.0000 $9,000.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
124 | P a g e
614E18511 3.000 MNTH PORTABLE CHANGEABLE MESSAGE SIGN, AS PER 1,016.6667 1,000.0000 $3,000.00
PLAN
614E18600 94.000 SNMT PORTABLE CHANGEABLE MESSAGE SIGN 795.8923 762.9303 $71,715.45
614E18601 1,414.000 SNMT PORTABLE CHANGEABLE MESSAGE SIGN, AS PER 745.7005 668.2275 $944,873.73
PLAN
614E18700 62.000 SNMT DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY 2,922.5352 2,730.6452 $169,300.00
614E18710 52.000 SNMT DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY 3,012.0438 2,802.7231 $145,741.60
WITH ALTERNATE WARNING SIGNS
614E20000 211.030 MILE WORK ZONE LANE LINE, CLASS I 539.7419 471.5631 $99,513.96
614E20001 151.530 MILE WORK ZONE LANE LINE, CLASS I, AS PER PLAN 348.8458 333.9496 $50,603.38
614E20100 402.120 MILE WORK ZONE LANE LINE, CLASS I, 642 PAINT 498.9326 455.9813 $183,359.21
614E20101 39.190 MILE WORK ZONE LANE LINE, CLASS I, 642 PAINT, 368.8813 411.2809 $16,118.10
AS PER PLAN
614E20200 25.760 MILE WORK ZONE LANE LINE, CLASS I, 740.06, 3,354.9655 3,057.1148 $78,751.28
TYPE I
614E20400 271.210 MILE WORK ZONE LANE LINE, CLASS II 410.6798 349.4841 $94,783.57
614E20500 43.750 MILE WORK ZONE LANE LINE, CLASS II, 642 PAINT 276.5223 108.5166 $4,747.60
614E20550 425.870 MILE WORK ZONE LANE LINE, CLASS III, 642 438.5338 461.6055 $196,583.92
PAINT
614E20600 8.300 MILE WORK ZONE LANE LINE, CLASS II, 740.06, 1,866.6667 2,600.0000 $21,580.00
TYPE I
614E21000 175.579 MILE WORK ZONE CENTER LINE, CLASS I 1,406.6711 1,182.7995 $207,674.76
614E21001 0.120 MILE WORK ZONE CENTER LINE, CLASS I, AS PER 5,278.0413 9,784.0000 $1,174.08
PLAN
614E21100 576.680 MILE WORK ZONE CENTER LINE, CLASS I, 642 1,167.3633 1,186.4876 $684,223.67
PAINT
614E21101 30.390 MILE WORK ZONE CENTER LINE, CLASS I, 642 1,391.7271 1,215.3129 $36,933.36
PAINT, AS PER PLAN
614E21200 16.130 MILE WORK ZONE CENTER LINE, CLASS I, 740.06, 10,668.4157 10,234.9968 $165,090.50
TYPE I
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
125 | P a g e
614E21400 1,115.780 MILE WORK ZONE CENTER LINE, CLASS II 436.8373 383.8292 $428,268.90
614E21500 504.610 MILE WORK ZONE CENTER LINE, CLASS II, 642 406.5001 312.6721 $157,777.46
PAINT
614E21550 340.970 MILE WORK ZONE CENTER LINE, CLASS III, 642 834.1029 797.2553 $271,840.12
PAINT
614E21600 51.410 MILE WORK ZONE CENTER LINE, CLASS II, 740.06, 1,004.2455 1,233.5878 $63,418.75
TYPE I
614E22000 401.890 MILE WORK ZONE EDGE LINE, CLASS I 1,181.5578 1,084.2795 $435,761.09
614E22001 577.800 MILE WORK ZONE EDGE LINE, CLASS I, AS PER 647.7469 636.7209 $367,897.34
PLAN
614E22100 803.200 MILE WORK ZONE EDGE LINE, CLASS I, 642 PAINT 720.2189 670.4509 $538,506.20
614E22101 188.480 MILE WORK ZONE EDGE LINE, CLASS I, 642 PAINT, 592.1089 637.0781 $120,076.48
AS PER PLAN
614E22200 151.580 MILE WORK ZONE EDGE LINE, CLASS I, 740.06, 5,757.9335 5,449.1125 $825,976.46
TYPE I
614E22201 0.690 MILE WORK ZONE EDGE LINE, CLASS I, 740.06, 5,993.2875 6.0100 $4.15
TYPE I, AS PER PLAN
614E22310 39.870 MILE WORK ZONE EDGE LINE, CLASS II 496.6000 319.9824 $12,757.70
614E22350 796.280 MILE WORK ZONE EDGE LINE, CLASS III, 642 490.7235 495.1376 $394,268.13
PAINT
614E23000 496,073.000 FT WORK ZONE CHANNELIZING LINE, CLASS I 0.7629 0.5764 $285,917.88
614E23001 181,070.000 FT WORK ZONE CHANNELIZING LINE, CLASS I, AS 0.5093 0.4964 $89,885.54
PER PLAN
614E23200 339,402.000 FT WORK ZONE CHANNELIZING LINE, CLASS I, 0.5660 0.5545 $188,196.40
642 PAINT
614E23201 57,549.000 FT WORK ZONE CHANNELIZING LINE, CLASS I, 0.6358 0.6129 $35,273.46
642 PAINT, AS PER PLAN
614E23400 195,377.000 FT WORK ZONE CHANNELIZING LINE, CLASS I, 1.9075 1.7846 $348,666.92
740.06, TYPE I
614E23401 5,070.000 FT WORK ZONE CHANNELIZING LINE, CLASS I, 2.6075 2.5100 $12,725.70
740.06, TYPE I, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
126 | P a g e
614E23600 300.000 FT WORK ZONE CHANNELIZING LINE, CLASS I, 2.0625 1.9000 $570.00
740.06, TYPE II
614E23650 55,067.000 FT WORK ZONE CHANNELIZING LINE, CLASS II 0.5222 0.4842 $26,665.95
614E23660 220.000 FT WORK ZONE CHANNELIZING LINE, CLASS II, 0.7100 0.7500 $165.00
642 PAINT
614E23680 131,358.000 FT WORK ZONE CHANNELIZING LINE, CLASS III, 0.5127 0.4972 $65,310.03
642 PAINT
614E24000 79,477.000 FT WORK ZONE DOTTED LINE, CLASS I 0.9195 0.9304 $73,942.76
614E24001 18,662.000 FT WORK ZONE DOTTED LINE, CLASS I, AS PER 0.4749 0.4954 $9,245.97
PLAN
614E24200 29,598.000 FT WORK ZONE DOTTED LINE, CLASS I, 642 0.7326 0.6287 $18,608.65
PAINT
614E24201 19,528.000 FT WORK ZONE DOTTED LINE, CLASS I, 642 0.6683 0.6470 $12,634.68
PAINT, AS PER PLAN
614E24400 36,784.000 FT WORK ZONE DOTTED LINE, CLASS I, 740.06, 1.5631 1.2928 $47,555.45
TYPE I
614E24610 21,381.000 FT WORK ZONE DOTTED LINE, CLASS III, 642 0.5244 0.5023 $10,739.25
PAINT
614E25000 16,493.000 FT WORK ZONE TRANSVERSE LINE, CLASS I 1.6832 1.5649 $25,810.21
614E25200 2,255.000 FT WORK ZONE TRANSVERSE LINE, CLASS I, 642 1.6912 1.4585 $3,289.00
PAINT
614E25400 2,721.000 FT WORK ZONE TRANSVERSE LINE, CLASS I, 4.6471 3.5921 $9,774.10
740.06, TYPE I
614E25620 3,484.000 FT WORK ZONE TRANSVERSE/DIAGONAL LINE, 1.5698 1.2968 $4,518.20
CLASS III, 642 PAINT
614E26000 32,870.000 FT WORK ZONE STOP LINE, CLASS I 4.2790 2.7879 $91,637.83
614E26001 4,070.000 FT WORK ZONE STOP LINE, CLASS I, AS PER 1.0944 1.1106 $4,520.00
PLAN
614E26200 21,587.000 FT WORK ZONE STOP LINE, CLASS I, 642 PAINT 3.3086 3.0239 $65,277.87
614E26201 1,375.000 FT WORK ZONE STOP LINE, CLASS I, 642 PAINT, 5.2050 2.5000 $3,437.50
AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
127 | P a g e
614E26400 5,233.500 FT WORK ZONE STOP LINE, CLASS I, 740.06, 6.7712 5.7902 $30,303.19
TYPE I
614E26610 19,800.000 FT WORK ZONE STOP LINE, CLASS III, 642 2.4664 2.3081 $45,700.70
PAINT
614E26611 2,010.000 FT WORK ZONE STOP LINE, CLASS III, 642 1.0500 1.1000 $2,211.00
PAINT, AS PER PLAN
614E27000 28,921.000 FT WORK ZONE CROSSWALK LINE, CLASS I 1.3298 1.2186 $35,243.90
614E27001 1,914.000 FT WORK ZONE CROSSWALK LINE, CLASS I, AS 0.5250 0.5500 $1,052.70
PER PLAN
614E27200 37,384.000 FT WORK ZONE CROSSWALK LINE, CLASS I, 642 1.4699 1.4829 $55,437.53
PAINT
614E27400 663.000 FT WORK ZONE CROSSWALK LINE, CLASS I, 2.1750 2.0000 $1,326.00
740.06, TYPE I
614E27620 18,415.000 FT WORK ZONE CROSSWALK LINE, CLASS III, 642 1.1689 1.0245 $18,866.55
PAINT
614E27621 957.000 FT WORK ZONE CROSSWALK LINE, CLASS III, 642 0.6250 0.6500 $622.05
PAINT, AS PER PLAN
614E28200 797.000 FT WORK ZONE GORE MARKING, CLASS II, 642 0.8175 1.6000 $1,275.20
PAINT
614E30000 1,239.000 EACH WORK ZONE LANE ARROW, CLASS I 50.7077 47.7253 $59,131.65
614E30200 633.000 EACH WORK ZONE LANE ARROW, CLASS I, 642 PAINT 45.9794 46.2648 $29,285.61
614E30400 173.000 EACH WORK ZONE LANE ARROW, CLASS I, 740.06, 140.5005 150.2880 $25,999.82
TYPE I
614E30650 553.000 EACH WORK ZONE LANE ARROW, CLASS III, 642 45.0455 50.5087 $27,931.30
PAINT
614E31000 5.000 EACH WORK ZONE WORD ON PAVEMENT, 72", CLASS I 129.3925 133.5480 $667.74
614E31200 5.000 EACH WORK ZONE WORD ON PAVEMENT, 72", CLASS 75.4525 95.3200 $476.60
I, 642 PAINT
614E31640 15.000 EACH WORK ZONE WORD ON PAVEMENT, 96", CLASS I 86.3984 94.0000 $1,410.00
614E31650 14.000 EACH WORK ZONE WORD ON PAVEMENT, 96", CLASS 135.5783 154.8500 $2,167.90
I, 642 PAINT
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
128 | P a g e
614E31670 9.000 EACH WORK ZONE WORD ON PAVEMENT, 96", CLASS 95.1703 118.8889 $1,070.00
III, 642 PAINT
614E31700 4.000 EACH WORK ZONE SCHOOL SYMBOL MARKING, 72", 200.0000 200.0000 $800.00
CLASS I
614E31720 2.000 EACH WORK ZONE SCHOOL SYMBOL MARKING, 72", 237.7188 295.0000 $590.00
CLASS I, 642 PAINT
614E31740 4.000 EACH WORK ZONE SCHOOL SYMBOL MARKING, 72", 190.0000 190.0000 $760.00
CLASS III, 642 PAINT
614E31742 4.000 EACH WORK ZONE SCHOOL SYMBOL MARKING, 96", 100.0000 100.0000 $400.00
CLASS I
614E31750 2.000 EACH WORK ZONE SCHOOL SYMBOL MARKING, 96", 100.0000 100.0000 $200.00
CLASS III, 642 PAINT
614E32000 12.000 EACH WORK ZONE RAILROAD SYMBOL MARKING, CLASS 327.8441 200.4542 $2,405.45
I
614E32210 4.000 EACH WORK ZONE RAILROAD SYMBOL MARKING, CLASS 184.4660 200.0000 $800.00
III, 642 PAINT
614E32700 66.000 SF WORK ZONE ISLAND MARKING, CLASS I 1.3688 1.0000 $66.00
614E40000 4,776.000 FT LONGITUDINAL CHANNELIZER 37.6783 42.1307 $201,216.00
614E40050 16.000 EACH BUSINESS ENTRANCE SIGN 241.9731 225.0000 $3,600.00
614E40051 58.000 EACH BUSINESS ENTRANCE SIGN, AS PER PLAN 345.7258 232.3638 $13,477.10
614E98100 1,237.000 FT WORK ZONE PAVEMENT MARKING, MISC.: 2.0625 2.3585 $2,917.50
614E98200 3.000 EACH WORK ZONE PAVEMENT MARKING, MISC.: 466.5650 513.2600 $1,539.78
614E99000 25.000 LS SPECIAL - MAINTAINING TRAFFIC 553,609.7984 480,478.8012 $12,011,970.03
615E10000 60.000 LS ROADS FOR MAINTAINING TRAFFIC 98,105.8127 105,044.0315 $6,302,641.89
615E10001 7.000 LS ROADS FOR MAINTAINING TRAFFIC, AS PER 60,795.5139 75,242.8571 $526,700.00
PLAN
615E15000 2.000 LS SPECIAL - TEMPORARY RAILROAD RUN-A-ROUND 89,176.5383 32,760.0300 $65,520.06
615E20000 160,689.000 SY PAVEMENT FOR MAINTAINING TRAFFIC, CLASS 41.9512 38.8390 $6,240,997.65
A
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
129 | P a g e
615E20001 378,584.000 SY PAVEMENT FOR MAINTAINING TRAFFIC, CLASS 37.6050 34.7919 $13,171,663.77
A, AS PER PLAN
615E25000 25,092.000 SY PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B 47.7651 47.1519 $1,183,136.03
615E25001 9,172.000 SY PAVEMENT FOR MAINTAINING TRAFFIC, CLASS 51.4771 48.9684 $449,137.90
B, AS PER PLAN
615E35001 9,381.000 SY PAVEMENT FOR MAINTAINING TRAFFIC, AS PER 18.7072 17.7354 $166,375.68
PLAN
615E99000 4.000 LS SPECIAL - TEMPORARY ROADS AND PAVEMENTS 86,428.0071 103,803.7500 $415,215.00
616E10000 21,410.930 MGAL WATER 32.0843 30.5736 $654,609.17
616E10001 1.000 MGAL WATER, AS PER PLAN 33.6667 50.0000 $50.00
616E20000 40.460 TON CALCIUM CHLORIDE 292.4114 332.7517 $13,463.13
616E99000 5.000 LS SPECIAL - DUST CONTROL 1,006.4286 1,198.0000 $5,990.00
617E10100 90,532.200 CY COMPACTED AGGREGATE, TYPE A 45.6583 43.7726 $3,962,825.28
617E10101 80,961.000 CY COMPACTED AGGREGATE, TYPE A, AS PER PLAN 38.1587 39.5360 $3,200,877.52
617E20000 604,573.000 SY SHOULDER PREPARATION 0.3021 0.1832 $110,746.72
617E25000 348.480 MGAL WATER 30.6863 32.2808 $11,249.23
617E99000 1.000 LS SPECIAL - COMPACTED AGGREGATE 119,505.4667 104,910.0000 $104,910.00
618E40100 706,867.000 FT RUMBLE STRIPS, TYPE 2 (ASPHALT CONCRETE) 0.3738 0.2863 $202,401.87
618E40101 41,059.000 FT RUMBLE STRIPS, TYPE 2 (ASPHALT 5.3737 5.2860 $217,035.93
CONCRETE), AS PER PLAN
618E40200 96,611.000 FT RUMBLE STRIPS, TYPE 2 (CONCRETE) 0.4342 0.4382 $42,336.60
618E40600 409.370 MILE RUMBLE STRIPS, TYPE 2 (ASPHALT CONCRETE) 810.0531 792.4035 $324,386.22
618E40700 5.040 MILE RUMBLE STRIPS, TYPE 2 (CONCRETE) 2,419.0717 2,379.1071 $11,990.70
618E41000 256.580 MILE EDGE LINE, RUMBLE STRIPE (ASPHALT 845.9445 857.5528 $220,030.91
CONCRETE)
618E42000 0.360 MILE EDGE LINE, RUMBLE STRIPE (CONCRETE) 10,750.0000 9,000.0000 $3,240.00
618E43000 4.130 MILE CENTER LINE, RUMBLE STRIPE (ASPHALT 4,996.1460 3,364.1646 $13,894.00
CONCRETE)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
130 | P a g e
619E16000 474.000 MNTH FIELD OFFICE, TYPE A 1,321.8817 1,182.9355 $560,711.44
619E16010 1,118.000 MNTH FIELD OFFICE, TYPE B 1,564.7255 1,460.1515 $1,632,449.43
619E16011 56.000 MNTH FIELD OFFICE, TYPE B, AS PER PLAN 1,896.0447 2,143.5436 $120,038.44
619E16020 474.000 MNTH FIELD OFFICE, TYPE C 2,511.9971 1,987.8846 $942,257.28
619E16021 261.000 MNTH FIELD OFFICE, TYPE C, AS PER PLAN 3,665.0340 4,177.3946 $1,090,300.00
619E99000 17.000 LS SPECIAL - FIELD OFFICE 28,729.5018 21,801.7082 $370,629.04
620E00500 5,853.000 EACH DELINEATOR, POST MOUNTED 34.5666 30.8505 $180,568.00
620E11000 90.000 EACH DELINEATOR, TYPE C, BRACKET MOUNTED 76.0154 77.8933 $7,010.40
620E31200 1,091.000 EACH DELINEATOR REMOVED FOR DISPOSAL 3.1850 1.5623 $1,704.50
620E31211 10.000 EACH DELINEATOR REMOVED AND REERECTED, AS PER 68.5000 37.0000 $370.00
PLAN
620E40200 11.000 EACH REFLECTOR, TYPE C 11.7186 8.0000 $88.00
620E60000 27.000 EACH REBOUNDABLE TUBULAR PYLON 89.9172 93.5185 $2,525.00
620E60500 20.000 EACH REMOVAL OF REBOUNDABLE TUBULAR PYLON 8.2500 6.5000 $130.00
621E00100 149,108.000 EACH RPM 20.0840 18.7983 $2,802,974.65
621E00101 7,817.000 EACH RPM, AS PER PLAN 9.8001 7.3787 $57,679.50
621E00300 475,600.000 EACH RPM REFLECTOR 3.4201 2.6699 $1,269,809.83
621E00301 54,682.000 EACH RPM REFLECTOR, AS PER PLAN 3.5275 3.5400 $193,574.28
621E10000 9,707.000 EACH RPM, LOW PROFILE YELLOW/YELLOW, 18.7714 18.4377 $178,974.93
621E10010 4,517.000 EACH RPM, LOW PROFILE, WHITE 20.6984 20.4152 $92,215.42
621E10020 3,158.000 EACH RPM, LOW PROFILE WHITE/RED 21.1129 21.4849 $67,849.35
621E10030 1,203.000 EACH RPM, LOW PROFILE YELLOW/RED 20.4306 20.1174 $24,201.24
621E54000 143,334.000 EACH RAISED PAVEMENT MARKER REMOVED 6.3548 6.1377 $879,737.29
621E54001 457.000 EACH RAISED PAVEMENT MARKER REMOVED, AS PER 13.6733 10.0000 $4,570.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
131 | P a g e
621E90000 5,659.000 EACH RPM, MISC.: 13.5250 12.9961 $73,545.00
621E91000 1.000 LS RPM, MISC.: 1,736.5880 1,300.0000 $1,300.00
621E99000 9.000 LS SPECIAL - RAISED PAVEMENT MARKERS 7,242.0906 9,325.5556 $83,930.00
622E10040 390.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE A1 81.2500 150.0000 $58,500.00
622E10060 22,242.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE B 54.1667 56.4267 $1,255,043.60
622E10061 2,147.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE B, 87.9142 89.0149 $191,115.00
AS PER PLAN
622E10100 1,535.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE B1 88.4224 95.2658 $146,233.00
622E10101 2,560.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE B1, 272.2734 243.9141 $624,420.00
AS PER PLAN
622E10120 1,614.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE C 112.9958 93.0623 $150,202.50
622E10121 216.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE C, 170.9831 179.3426 $38,738.00
AS PER PLAN
622E10140 5,668.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE C1 72.9698 78.2137 $443,315.00
622E10141 654.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE C1, 184.7317 254.5229 $166,458.00
AS PER PLAN
622E10160 11,352.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE D 76.4429 73.1790 $830,727.50
622E10161 12,312.000 FT CONCRETE BARRIER, SINGLE SLOPE, TYPE D, 65.4408 69.6674 $857,745.00
AS PER PLAN
622E10200 14.000 EACH BARRIER TRANSITION 5,830.5209 6,189.2857 $86,650.00
622E10201 5.000 EACH BARRIER TRANSITION, AS PER PLAN 4,572.7273 3,200.0000 $16,000.00
622E23304 660.000 FT CONCRETE BARRIER, TYPE A1 85.0000 85.0000 $56,100.00
622E23404 180.000 FT CONCRETE BARRIER, TYPE B1 195.0000 195.0000 $35,100.00
622E23504 265.000 FT CONCRETE BARRIER, TYPE C1 196.2500 170.0000 $45,050.00
622E23505 40.000 FT CONCRETE BARRIER, TYPE C1, AS PER PLAN 223.7500 205.0000 $8,200.00
622E24000 230.000 FT CONCRETE BARRIER, TYPE D 110.5939 100.4783 $23,110.00
622E24001 400.000 FT CONCRETE BARRIER, TYPE D, AS PER PLAN 36.1920 35.0000 $14,000.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
132 | P a g e
622E24840 21.000 EACH CONCRETE BARRIER END SECTION, TYPE B 6,015.7385 6,244.3124 $131,130.56
622E24841 4.000 EACH CONCRETE BARRIER END SECTION, TYPE B, AS 6,285.3778 6,212.5000 $24,850.00
PER PLAN
622E24850 4.000 EACH CONCRETE BARRIER END SECTION, TYPE B1 5,918.5714 3,140.0000 $12,560.00
622E24860 5.000 EACH CONCRETE BARRIER END SECTION, TYPE C1 5,198.8974 5,520.0000 $27,600.00
622E25000 75.000 EACH CONCRETE BARRIER END SECTION, TYPE D 2,967.8959 2,617.2453 $196,293.40
622E25001 14.000 EACH CONCRETE BARRIER END SECTION, TYPE D, AS 4,687.5000 3,528.5714 $49,400.00
PER PLAN
622E25004 111.000 EACH CONCRETE BARRIER, END ANCHORAGE, 2,169.2007 2,029.7962 $225,307.38
REINFORCED, TYPE B
622E25005 1.000 EACH CONCRETE BARRIER, END ANCHORAGE, 3,525.0000 3,300.0000 $3,300.00
REINFORCED, TYPE B, AS PER PLAN
622E25006 4.000 EACH CONCRETE BARRIER, END ANCHORAGE, 2,927.8510 2,750.0000 $11,000.00
REINFORCED, TYPE B1
622E25008 12.000 EACH CONCRETE BARRIER, END ANCHORAGE, 2,799.8240 2,795.8333 $33,550.00
REINFORCED, TYPE C
622E25009 7.000 EACH CONCRETE BARRIER, END ANCHORAGE, 4,385.0000 2,600.0000 $18,200.00
REINFORCED, TYPE C, AS PER PLAN
622E25010 32.000 EACH CONCRETE BARRIER END SECTION, TYPE D, 2,642.5948 2,639.2500 $84,456.00
REINFORCED
622E25011 4.000 EACH CONCRETE BARRIER END SECTION, TYPE D, 3,562.9240 3,911.3700 $15,645.48
REINFORCED, AS PER PLAN
622E25014 8.000 EACH CONCRETE BARRIER, END ANCHOR, 3,550.0000 3,575.0000 $28,600.00
REINFORCED, TYPE C1
622E25016 13.000 EACH CONCRETE BARRIER, END ANCHORAGE, 2,742.9697 3,423.0769 $44,500.00
REINFORCED, TYPE C1
622E25050 143.000 EACH CONCRETE BARRIER, END ANCHOR, 2,343.3388 2,406.3292 $344,105.07
REINFORCED, TYPE D
622E40020 825,959.000 FT PORTABLE CONCRETE BARRIER, 32" 8.9534 8.3814 $6,922,651.99
622E40021 13,210.000 FT PORTABLE CONCRETE BARRIER, 32", AS PER 14.2467 17.3058 $228,610.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
133 | P a g e
622E40030 965.000 FT PORTABLE CONCRETE BARRIER, 50" 20.2000 26.0000 $25,090.00
622E40031 212,454.000 FT PORTABLE CONCRETE BARRIER, 50", AS PER 11.5147 9.7427 $2,069,865.50
PLAN
622E40040 61,034.000 FT PORTABLE CONCRETE BARRIER, 32", BRIDGE 16.5764 14.3725 $877,210.50
MOUNTED
622E40041 5,420.000 FT PORTABLE CONCRETE BARRIER, 32", BRIDGE 17.7126 19.9391 $108,070.00
MOUNTED, AS PER PLAN
622E40046 640.000 FT PORTABLE CONCRETE BARRIER, 50", BRIDGE 22.0000 21.0000 $13,440.00
MOUNTED
622E40047 1,480.000 FT PORTABLE CONCRETE BARRIER, 50", BRIDGE 18.2045 15.5135 $22,960.00
MOUNTED, AS PER PLAN
622E40100 30.000 EACH PORTABLE CONCRETE BARRIER, "Y" CONNECTOR 1,452.4843 1,498.1983 $44,945.95
622E41000 101,475.000 FT PORTABLE BARRIER, 32" 10.9702 8.9404 $907,229.68
622E41011 69,924.000 FT PORTABLE BARRIER, 50", AS PER PLAN 13.1036 9.9715 $697,250.00
622E41020 6,887.000 FT PORTABLE BARRIER, 32", BRIDGE MOUNTED 17.0916 14.5807 $100,417.60
622E41030 310.000 FT PORTABLE BARRIER, 50", BRIDGE MOUNTED 25.2800 14.0000 $4,340.00
622E41050 4.000 EACH PORTABLE BARRIER, "Y" CONNECTOR 1,898.1437 2,725.0000 $10,900.00
622E80000 12,126.000 FT GLARE SCREEN 5.5860 6.6869 $81,085.00
622E90000 11,245.000 FT BARRIER, MISC.: 30.2146 34.8367 $391,739.00
622E99000 4.000 LS SPECIAL - CONCRETE BARRIER 256,969.8838 175,813.7700 $703,255.08
623E10000 346.000 LS CONSTRUCTION LAYOUT STAKES 12,742.7785 10,957.0319 $3,791,133.04
623E10001 65.000 LS CONSTRUCTION LAYOUT STAKES, AS PER PLAN 32,364.6172 13,810.3672 $897,673.87
623E11000 4.000 EACH SPECIAL - ELECTRICAL INSTRUMENTATION 15,360.9929 15,116.6000 $60,466.40
623E11100 40.000 HOUR TECHNICAL ASSISTANCE 169.0853 134.5000 $5,380.00
623E38500 28.000 EACH MONUMENT ASSEMBLY 774.7881 582.1429 $16,300.00
623E38501 66.000 EACH MONUMENT ASSEMBLY, AS PER PLAN 1,035.1522 969.0909 $63,960.00
623E39500 157.000 EACH MONUMENT BOX ADJUSTED TO GRADE 355.6869 357.6115 $56,145.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
134 | P a g e
623E39501 1.000 EACH MONUMENT BOX ADJUSTED TO GRADE, AS PER 749.7680 850.0000 $850.00
PLAN
623E40500 47.000 EACH REFERENCE MONUMENT 446.7644 489.8936 $23,025.00
623E40501 3.000 EACH REFERENCE MONUMENT, AS PER PLAN 272.0000 500.0000 $1,500.00
623E40520 2.000 EACH RIGHT-OF-WAY MONUMENT 550.6667 500.0000 $1,000.00
623E99000 21.000 LS SPECIAL - CONSTRUCTION LAYOUT STAKES 64,450.4925 74,866.7871 $1,572,202.53
624E10000 696.000 LS MOBILIZATION 55,694.2136 52,501.4432 $36,541,004.47
624E10001 1.000 LS MOBILIZATION, AS PER PLAN 12,181.6575 40,000.0000 $40,000.00
624E15000 2.000 EACH MOBILIZATION 34,852.5820 40,000.0000 $80,000.00
624E15001 205.000 EACH MOBILIZATION, AS PER PLAN 511.4851 561.4634 $115,100.00
624E99000 23.000 LS SPECIAL - MOBILIZATION 237,216.5313 287,954.7391 $6,622,959.00
625E00450 950.000 EACH CONNECTION, FUSED PULL APART 73.3264 77.6452 $73,762.93
625E00451 12.000 EACH CONNECTION, FUSED PULL APART, AS PER 88.4017 92.6000 $1,111.20
PLAN
625E00460 122.000 EACH CONNECTION, UNFUSED PULL APART 78.9456 76.9418 $9,386.90
625E00470 28.000 EACH CONNECTION, UNFUSED BOLTED 68.9627 64.5532 $1,807.49
625E00480 1,756.000 EACH CONNECTION, UNFUSED PERMANENT 75.6085 76.7508 $134,774.45
625E00481 51.000 EACH CONNECTION, UNFUSED PERMANENT, AS PER 117.9188 78.0000 $3,978.00
PLAN
625E00490 13.000 EACH CONNECTOR KIT, TYPE I 105.8333 120.0000 $1,560.00
625E00500 496.000 EACH CONNECTOR KIT, TYPE II 77.4737 65.9227 $32,697.64
625E00600 17.000 EACH CONNECTOR KIT, TYPE III 97.1969 74.2459 $1,262.18
625E00700 17.000 EACH CONNECTOR KIT, TYPE IV 64.3921 63.0147 $1,071.25
625E00900 6.000 EACH CONNECTOR KIT, TYPE VI 68.6283 62.1500 $372.90
625E00950 10.000 EACH CONNECTOR KIT, TYPE VII 66.0171 58.8500 $588.50
625E02500 27.000 EACH TRANSFORMER BASE, TYPE AT-A 406.8918 521.4815 $14,080.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
135 | P a g e
625E02501 41.000 EACH TRANSFORMER BASE, TYPE AT-A, AS PER PLAN 423.6737 394.3902 $16,170.00
625E02600 1.000 EACH TRANSFORMER BASE, TYPE AT-C 440.1925 440.0000 $440.00
625E02601 6.000 EACH TRANSFORMER BASE, TYPE AT-C, AS PER PLAN 133.7075 170.0000 $1,020.00
625E02700 1.000 EACH TRANSFORMER BASE, TYPE AT-X 480.1350 540.0000 $540.00
625E02803 115.000 EACH TRANSFORMER BASE, MISC.: 368.2342 332.6087 $38,250.00
625E10481 92.000 EACH LIGHT POLE, DECORATIVE, AS PER PLAN 3,925.8000 4,106.0641 $377,757.90
625E10490 227.000 EACH LIGHT POLE, CONVENTIONAL 1,833.6903 1,898.4568 $430,949.70
625E10491 194.000 EACH LIGHT POLE, CONVENTIONAL, AS PER PLAN 1,882.0877 1,792.2165 $347,690.00
625E10494 59.000 EACH LIGHT POLE, LOW MAST 1,774.4872 1,690.1742 $99,720.28
625E10495 60.000 EACH LIGHT POLE, LOW MAST, AS PER PLAN 2,112.5250 2,101.3333 $126,080.00
625E10500 182.000 EACH LIGHT POLE, MISC.: 1,653.3495 1,685.3206 $306,728.35
625E10503 22.000 EACH ERECTING LIGHT POLE (INSTALLATION ONLY), 347.3419 370.2273 $8,145.00
AS PER PLAN
625E10504 8.000 EACH ERECTING REUSABLE DOWNED LIGHT POLE 332.8100 340.0000 $2,720.00
625E10505 105.000 EACH ERECTING REUSABLE DOWNED LIGHT POLE, AS 359.0326 319.0476 $33,500.00
PER PLAN
625E10601 48.000 EACH LIGHT POLE ANCHOR L-BOLTS, AS PER PLAN 44.5967 56.4000 $2,707.20
625E10614 196.000 EACH LIGHT POLE ANCHOR BOLTS ON STRUCTURE 131.4529 106.3306 $20,840.80
625E10615 29.000 EACH LIGHT POLE ANCHOR BOLTS ON STRUCTURE, AS 319.3124 659.1741 $19,116.05
PER PLAN
625E11100 4.000 EACH LIGHT TOWER, BB90 11,754.3333 10,700.0000 $42,800.00
625E11200 13.000 EACH LIGHT TOWER, BB100 12,155.1579 11,307.6923 $147,000.00
625E11300 7.000 EACH LIGHT TOWER, BB110 13,205.0000 12,200.0000 $85,400.00
625E11400 2.000 EACH LIGHT TOWER, BB120 14,750.3333 14,000.0000 $28,000.00
625E12200 1.000 EACH LIGHT TOWER, BBB100 12,211.3333 11,300.0000 $11,300.00
625E12300 1.000 EACH LIGHT TOWER, BBB110 13,238.6667 12,250.0000 $12,250.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
136 | P a g e
625E13000 1.000 EACH LIGHT TOWER, BBBB80 11,612.4286 9,900.0000 $9,900.00
625E13100 18.000 EACH LIGHT TOWER, BBBB90 10,544.2788 10,688.0200 $192,384.36
625E13200 112.000 EACH LIGHT TOWER, BBBB100 11,688.9375 11,279.8082 $1,263,338.52
625E13204 13.000 EACH LIGHT TOWER, BBBB110 12,938.1021 13,232.0431 $172,016.56
625E13240 3.000 EACH LIGHT TOWER, BBBBB100 11,900.0000 12,000.0000 $36,000.00
625E13300 2.000 EACH LIGHT TOWER, BBBBBB80 11,618.1429 9,900.0000 $19,800.00
625E13400 40.000 EACH LIGHT TOWER, BBBBBB100 11,422.7521 9,671.7430 $386,869.72
625E13404 3.000 EACH LIGHT TOWER, BBBBBB110 13,680.5357 13,066.6667 $39,200.00
625E13460 1.000 EACH LIGHT TOWER, BBBBBBBB120 15,017.6667 14,300.0000 $14,300.00
625E13500 14.000 EACH LIGHT TOWER, MISC.: 771.2559 553.5714 $7,750.00
625E14000 91.000 EACH LIGHT POLE FOUNDATION, 24" X 6' DEEP 1,064.8905 1,029.2352 $93,660.40
625E14001 72.000 EACH LIGHT POLE FOUNDATION, 24" X 6' DEEP, AS 1,034.2205 1,031.3194 $74,255.00
PER PLAN
625E14100 208.000 EACH LIGHT POLE FOUNDATION, 24" X 8' DEEP 1,168.3296 975.9937 $203,006.68
625E14101 4.000 EACH LIGHT POLE FOUNDATION, 24" X 8' DEEP, AS 1,640.3025 1,450.0000 $5,800.00
PER PLAN
625E14200 43.000 EACH LIGHT POLE FOUNDATION, 24" X 10' DEEP 1,074.1442 1,046.8084 $45,012.76
625E14300 11.000 EACH MEDIAN LIGHT POLE FOUNDATION, 8' DEEP 3,150.0000 2,500.0000 $27,500.00
625E14306 53.000 EACH MEDIAN LIGHT POLE FOUNDATION, 10' DEEP 3,629.2852 3,801.8838 $201,499.84
625E14307 1.000 EACH MEDIAN LIGHT POLE FOUNDATION, 10' DEEP, 4,172.7500 4,152.0000 $4,152.00
AS PER PLAN
625E14400 5.000 EACH LIGHT POLE FOUNDATION REPAIR 216.6667 200.0000 $1,000.00
625E14401 27.000 EACH LIGHT POLE FOUNDATION REPAIR, AS PER 780.5206 339.8148 $9,175.00
PLAN
625E14500 45.000 EACH LIGHT POLE FOUNDATION 1,091.9199 1,115.7018 $50,206.58
625E14501 76.000 EACH LIGHT POLE FOUNDATION, AS PER PLAN 1,221.6309 1,188.7500 $90,345.00
625E14600 58.000 EACH LIGHT POLE FOUNDATION, MISC.: 844.1830 729.7407 $42,324.96
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
137 | P a g e
625E15000 1.000 EACH LIGHT TOWER FOUNDATION, 36" X 15' DEEP 5,672.7857 5,000.0000 $5,000.00
625E15100 3.000 EACH LIGHT TOWER FOUNDATION, 36" X 20' DEEP 6,442.4393 6,233.3333 $18,700.00
625E15200 158.000 EACH LIGHT TOWER FOUNDATION, 36" X 25' DEEP 6,809.9598 6,276.4937 $991,686.00
625E15300 40.000 EACH LIGHT TOWER FOUNDATION, 36" X 30' DEEP 7,159.3461 6,581.9625 $263,278.50
625E15700 3.000 EACH LIGHT TOWER FOUNDATION, MISC.: 10,435.7950 11,842.6700 $35,528.01
625E17900 4.000 EACH BRACKET ARM 789.1600 847.5000 $3,390.00
625E17901 18.000 EACH BRACKET ARM, AS PER PLAN 1,263.2866 1,314.4444 $23,660.00
625E17951 4.000 EACH BRACKET ARM, 6', AS PER PLAN 1,777.6250 2,610.5000 $10,442.00
625E17960 1.000 EACH BRACKET ARM, 8' 500.0000 500.0000 $500.00
625E18000 16.000 EACH BRACKET ARM, 10' 441.1585 397.0000 $6,352.00
625E18001 8.000 EACH BRACKET ARM, 10', AS PER PLAN 1,685.8358 1,821.2500 $14,570.00
625E18100 2.000 EACH BRACKET ARM, 12' 477.5143 447.0000 $894.00
625E18200 5.000 EACH BRACKET ARM, 15' 766.3184 650.2000 $3,251.00
625E18201 27.000 EACH BRACKET ARM, 15', AS PER PLAN 654.5658 546.4815 $14,755.00
625E18210 1.000 EACH BRACKET ARM, 16' 812.5000 800.0000 $800.00
625E18400 1.000 EACH BRACKET ARM, 20' 1,091.4400 719.0000 $719.00
625E18401 17.000 EACH BRACKET ARM, 20', AS PER PLAN 935.1056 876.4706 $14,900.00
625E18500 2.000 EACH BRACKET ARM, 25' 1,000.0000 1,300.0000 $2,600.00
625E18510 16.000 EACH BRACKET ARM, 30' 1,766.6969 1,815.2075 $29,043.32
625E18511 13.000 EACH BRACKET ARM, 30', AS PER PLAN 1,703.6021 1,794.7538 $23,331.80
625E18600 29.000 EACH BRACKET ARM, MISC.: 445.2407 318.2759 $9,230.00
625E19101 192.000 EACH BALLAST FOR TOWER LIGHT FIXTURE, AS PER 256.2572 220.2865 $42,295.00
PLAN
625E20000 5.000 EACH PORTABLE POWER UNIT 2,577.4423 2,350.8000 $11,754.00
625E21000 3.000 EACH LIGHT TOWER MAINTENANCE PLATFORM, TYPE A 6,374.3971 4,500.0000 $13,500.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
138 | P a g e
625E21200 7.000 EACH LIGHT TOWER MAINTENANCE PLATFORM, TYPE C 6,590.2886 4,500.0000 $31,500.00
625E22900 4,425.000 FT NO. 1/0 AWG 5000 VOLT DISTRIBUTION CABLE 5.2990 5.4475 $24,105.00
625E22990 14,497.000 FT NO. 6 AWG 600 VOLT DISTRIBUTION CABLE 2.0096 2.1269 $30,834.17
625E23000 16,891.000 FT NO. 4 AWG 600 VOLT DISTRIBUTION CABLE 2.5578 2.2463 $37,942.76
625E23001 2,348.000 FT NO. 4 AWG 600 VOLT DISTRIBUTION CABLE, 2.7400 2.2500 $5,283.00
AS PER PLAN
625E23100 30,232.000 FT NO. 2 AWG 600 VOLT DISTRIBUTION CABLE 2.7412 2.3712 $71,686.34
625E23200 166,705.000 FT NO. 4 AWG 5000 VOLT DISTRIBUTION CABLE 2.4639 2.4883 $414,811.20
625E23201 26,880.000 FT NO. 4 AWG 5000 VOLT DISTRIBUTION CABLE, 2.7453 2.3381 $62,847.80
AS PER PLAN
625E23300 41,007.000 FT NO. 2 AWG 5000 VOLT DISTRIBUTION CABLE 3.0538 3.0372 $124,545.72
625E23301 4,200.000 FT NO. 2 AWG 5000 VOLT DISTRIBUTION CABLE, 3.7017 3.4137 $14,337.50
AS PER PLAN
625E23302 11,169.000 FT NO. 6 AWG 5000 VOLT DISTRIBUTION CABLE 2.3483 2.4825 $27,727.26
625E23304 5,455.000 FT NO. 8 AWG 600 VOLT DISTRIBUTION CABLE 1.6767 1.7119 $9,338.50
625E23305 1,081.000 FT NO. 8 AWG 600 VOLT DISTRIBUTION CABLE, 2.1233 1.7500 $1,891.75
AS PER PLAN
625E23306 17,342.000 FT NO. 10 AWG 600 VOLT DISTRIBUTION CABLE 1.1636 0.9277 $16,087.55
625E23308 28,146.000 FT DISTRIBUTION CABLE, MISC.: 3.6726 2.9802 $83,879.96
625E23310 540.000 FT NO. 14 AWG 600 VOLT DISTRIBUTION CABLE 1.7667 1.5000 $810.00
625E23400 73,540.000 FT NO. 10 AWG POLE AND BRACKET CABLE 1.1297 0.9642 $70,904.76
625E23401 8,300.000 FT NO. 10 AWG POLE AND BRACKET CABLE, AS 1.0182 0.7952 $6,600.00
PER PLAN
625E23410 1,300.000 FT NO. 12 AWG POLE AND BRACKET CABLE 1.3750 1.5000 $1,950.00
625E24000 2,841.000 FT 1-1/2" DUCT CABLE WITH TWO NO. 4 AWG 600 7.1000 7.0000 $19,887.00
VOLT CABLES
625E24100 17,618.000 FT 1-1/2" DUCT CABLE WITH TWO NO. 4 AWG 5.6566 5.6156 $98,936.10
5000 VOLT CABLES
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
139 | P a g e
625E24101 6,000.000 FT 1-1/2" DUCT CABLE WITH TWO NO. 4 AWG 5.1682 4.5025 $27,015.00
5000 VOLT CABLES, AS PER PLAN
625E24300 583.000 FT 1-1/2" DUCT CABLE WITH TWO NO. 2 AWG 8.4818 7.2607 $4,233.00
5000 VOLT CABLES
625E24301 350.000 FT 1-1/2" DUCT CABLE WITH TWO NO. 2 AWG 7.0717 6.7143 $2,350.00
5000 VOLT CABLES, AS PER PLAN
625E24314 390.000 FT 1-1/2" DUCT CABLE WITH THREE NO. 1/0 AWG 14.7500 15.0000 $5,850.00
5000 VOLT CABLES
625E24320 111,475.000 FT 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 6.5430 6.3255 $705,130.86
5000 VOLT CABLES
625E24321 1,000.000 FT 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 7.3333 7.0000 $7,000.00
5000 VOLT CABLES, AS PER PLAN
625E24330 88,305.000 FT 1-1/2" DUCT CABLE WITH THREE NO. 2 AWG 7.8763 8.0007 $706,506.12
5000 VOLT CABLES
625E24331 200.000 FT 1-1/2" DUCT CABLE WITH THREE NO. 2 AWG 9.2500 8.7500 $1,750.00
5000 VOLT CABLES, AS PER PLAN
625E24400 50.000 FT DUCT CABLE, MISC.: 7.0000 5.0000 $250.00
625E25100 475.000 FT CONDUIT, 1", 725.04 10.1496 11.1050 $5,274.86
625E25102 280.000 FT CONDUIT, 1", 725.05 3.7000 2.6000 $728.00
625E25104 171.000 FT CONDUIT, 1", 725.051 2.9456 4.2400 $725.04
625E25300 4,034.000 FT CONDUIT, 1-1/2", 725.04 8.6335 6.3504 $25,617.60
625E25302 4,470.000 FT CONDUIT, 1-1/2", 725.05 3.6787 3.0541 $13,651.75
625E25303 2,515.000 FT CONDUIT, 1-1/2", 725.05, AS PER PLAN 3.1300 2.0000 $5,030.00
625E25307 166.000 FT CONDUIT, 1-1/2", 725.052, AS PER PLAN 3.0493 2.5000 $415.00
625E25400 42,376.000 FT CONDUIT, 2", 725.04 14.5955 11.6647 $494,302.62
625E25401 10,010.000 FT CONDUIT, 2", 725.04, AS PER PLAN 8.1641 8.0240 $80,320.00
625E25402 32,204.000 FT CONDUIT, 2", 725.05 4.0311 3.2202 $103,704.57
625E25403 5,731.000 FT CONDUIT, 2", 725.05, AS PER PLAN 5.3375 5.7716 $33,076.88
625E25405 95.000 FT CONDUIT, 2-1/2", 725.04, AS PER PLAN 67.5617 56.0000 $5,320.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
140 | P a g e
625E25408 9,773.000 FT CONDUIT, 2", 725.051 4.7849 4.9633 $48,506.40
625E25409 618.000 FT CONDUIT, 2", 725.051, AS PER PLAN 7.8750 6.0000 $3,708.00
625E25410 40.000 FT CONDUIT, 2", 725.052 4.7720 2.9000 $116.00
625E25411 1,281.000 FT CONDUIT, 2", 725.052, APP 4.2033 3.8000 $4,867.80
625E25500 21,000.000 FT CONDUIT, 3", 725.04 16.2770 13.7177 $288,072.00
625E25501 5.000 FT CONDUIT, 3", 725.04, AS PER PLAN 63.6975 25.0000 $125.00
625E25502 2,362.000 FT CONDUIT, 3", 725.05 6.4461 4.7486 $11,216.31
625E25503 9,690.000 FT CONDUIT, 3", 725.05, AS PER PLAN 5.9505 4.7738 $46,258.52
625E25504 651.000 FT CONDUIT, 3", 725.051 5.2037 5.2328 $3,406.53
625E25505 530.000 FT CONDUIT, 3", 725.051, AS PER PLAN 5.1000 5.4000 $2,862.00
625E25506 328.000 FT CONDUIT, 3", 725.052 8.9537 8.8802 $2,912.70
625E25507 489.000 FT CONDUIT, 3", 725.052, AS PER PLAN 7.6991 7.0000 $3,423.00
625E25550 71.000 FT CONDUIT, 3-1/2", 725.04 20.8300 19.6000 $1,391.60
625E25600 10,581.000 FT CONDUIT, 4", 725.04 19.6855 17.2600 $182,627.74
625E25602 996.000 FT CONDUIT, 4", 725.05 7.0819 10.5550 $10,512.78
625E25603 7,212.000 FT CONDUIT, 4", 725.05, AS PER PLAN 7.1566 5.2048 $37,537.09
625E25604 934.000 FT CONDUIT, 4", 725.051 7.1708 6.2506 $5,838.10
625E25605 6,553.000 FT CONDUIT, 4", 725.051, AS PER PLAN 7.1368 8.8480 $57,981.00
625E25721 6,257.000 FT CONDUIT, AS PER PLAN 12.2150 5.4300 $33,975.51
625E25740 477.000 FT CONDUIT, MULTICELL 14.8685 7.7094 $3,677.36
625E25802 6,155.000 FT CONDUIT, CONCRETE ENCASED 13.0460 15.7105 $96,697.86
625E25803 1,440.000 FT CONDUIT, CONCRETE ENCASED, AS PER PLAN 17.0455 10.0208 $14,430.00
625E25900 10,914.000 FT CONDUIT, JACKED OR DRILLED UNDER 30.8864 30.3734 $331,495.48
PAVEMENT
625E25901 1,695.000 FT CONDUIT, JACKED OR DRILLED, AS PER PLAN 34.9609 33.6484 $57,034.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
141 | P a g e
625E25902 48,242.000 FT CONDUIT, JACKED OR DRILLED, 725.04 28.8262 18.4387 $889,519.23
625E25903 849.000 FT CONDUIT, JACKED OR DRILLED, 725.04, AS 35.0528 31.6416 $26,863.70
PER PLAN
625E25904 397.000 FT CONDUIT, JACKED OR DRILLED, 725.05 28.6072 36.5995 $14,530.00
625E25906 624.000 FT CONDUIT, JACKED OR DRILLED, 725.051 23.0679 24.0071 $14,980.40
625E25907 493.000 FT CONDUIT, JACKED OR DRILLED, 725.051, AS 22.6312 19.7412 $9,732.40
PER PLAN
625E25908 1,785.000 FT CONDUIT, JACKED OR DRILLED, 725.052 30.4700 28.0000 $49,980.00
625E25910 6,633.000 FT CONDUIT CLEANED AND CABLES REMOVED 1.3340 0.7223 $4,790.87
625E25911 4,167.000 FT CONDUIT CLEANED AND CABLES REMOVED, AS 2.1316 1.0317 $4,299.00
PER PLAN
625E25920 38,166.000 FT CONDUIT, MISC.: 29.5935 24.7535 $944,741.39
625E25930 138.000 EACH CONDUIT, MISC.: 49.5724 75.3710 $10,401.20
625E26250 104.000 EACH LUMINAIRE, CONVENTIONAL 282.7799 269.6827 $28,047.00
625E26251 640.000 EACH LUMINAIRE, CONVENTIONAL, AS PER PLAN 346.2991 317.2633 $203,048.50
625E26260 166.000 EACH LUMINAIRE, HIGH MAST 709.4251 728.8012 $120,981.00
625E26261 793.000 EACH LUMINAIRE, HIGH MAST, AS PER PLAN 657.8483 672.3226 $533,151.80
625E26270 60.000 EACH LUMINAIRE, LOW MAST 690.9002 702.5333 $42,152.00
625E26271 87.000 EACH LUMINAIRE, LOW MAST, AS PER PLAN 727.0460 686.3775 $59,714.84
625E27401 5.000 EACH LUMINAIRE, POST TOP, AS PER PLAN 1,749.5750 1,700.0000 $8,500.00
625E27500 23.000 EACH LUMINAIRE, UNDERPASS 534.5351 518.0000 $11,914.00
625E27501 327.000 EACH LUMINAIRE, UNDERPASS, AS PER PLAN 517.1233 475.2188 $155,396.56
625E27520 3.000 EACH REMOVAL OF LUMINAIRE AND REERECTION 230.7180 205.0000 $615.00
625E27550 3.000 EACH LUMINAIRE, DECORATIVE 1,548.2000 1,308.0000 $3,924.00
625E27551 102.000 EACH LUMINAIRE, DECORATIVE, AS PER PLAN 1,623.8770 1,662.6157 $169,586.80
625E27561 107.000 EACH LUMINAIRE, INSTALLATION ONLY, AS PER 168.9802 123.9720 $13,265.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
142 | P a g e
625E27600 1,256.000 EACH LUMINAIRE, MISC.: 322.2736 326.5739 $410,176.88
625E27700 90,120.000 FXMT LUMINAIRE, MISC.: 2.3637 2.0220 $182,218.80
625E27800 110.000 EACH BALLAST, MISC.: 148.8362 126.1364 $13,875.00
625E28001 2.000 EACH GLARE SHIELD, AS PER PLAN 113.4000 150.0000 $300.00
625E29000 175,278.000 FT TRENCH 5.9974 5.4552 $956,169.45
625E29001 9,935.000 FT TRENCH, AS PER PLAN 5.1091 3.7258 $37,016.00
625E29002 111,139.000 FT TRENCH, 24" DEEP 7.4992 3.7682 $418,789.91
625E29003 7,694.000 FT TRENCH, 24" DEEP, AS PER PLAN 7.1539 4.6288 $35,614.00
625E29010 5,539.000 FT TRENCH, 30" DEEP 9.7723 9.2157 $51,045.60
625E29100 8,942.000 FT TRENCH, 36" DEEP 9.5693 9.1914 $82,189.75
625E29101 9,280.000 FT TRENCH, 36" DEEP, AS PER PLAN 7.2880 8.5000 $78,880.00
625E29400 1,312.000 FT TRENCH IN PAVED AREA 22.9655 20.7111 $27,172.90
625E29401 262.000 FT TRENCH IN PAVED AREAS, AS PER PLAN 27.6840 17.5000 $4,585.00
625E29500 2,340.000 FT TRENCH IN PAVED AREA, TYPE A 21.2846 22.4725 $52,585.55
625E29501 1,259.000 FT TRENCH IN PAVED AREA, TYPE A, AS PER 31.7436 26.5973 $33,486.00
PLAN
625E29600 4,727.000 FT TRENCH IN PAVED AREA, TYPE B 49.4597 45.9799 $217,347.00
625E29601 275.000 FT TRENCH IN PAVED AREA, TYPE B, AS PER 47.7098 34.9273 $9,605.00
PLAN
625E29700 770.000 FT TRENCH, MISC.: 13.9050 7.0468 $5,426.00
625E29900 19.000 EACH JUNCTION BOX 1,538.4989 1,497.2084 $28,446.96
625E29901 10.000 EACH JUNCTION BOX, AS PER PLAN 1,076.8651 1,206.1260 $12,061.26
625E29911 12.000 EACH TRANSITION JUNCTION BOX, AS PER PLAN 1,665.4000 1,657.2000 $19,886.40
625E29920 83.000 EACH STRUCTURE JUNCTION BOX 1,541.5960 1,463.3735 $121,460.00
625E29921 23.000 EACH STRUCTURE JUNCTION BOX, AS PER PLAN 1,556.5383 1,475.4783 $33,936.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
143 | P a g e
625E29930 33.000 EACH MEDIAN JUNCTION BOX 1,716.5214 1,863.4388 $61,493.48
625E29931 2.000 EACH MEDIAN JUNCTION BOX, AS PER PLAN 1,861.5250 1,823.4800 $3,646.96
625E29940 30.000 EACH BARRIER JUNCTION BOX 1,616.5341 1,605.0000 $48,150.00
625E30700 774.000 EACH PULL BOX, 725.08, 18" 714.4146 719.5517 $556,932.98
625E30701 124.000 EACH PULL BOX, 725.08, 18", AS PER PLAN 634.9208 569.8223 $70,657.97
625E30702 16.000 EACH PULL BOX, 725.06, 18" 628.2897 535.3144 $8,565.03
625E30706 543.000 EACH PULL BOX, 725.08, 24" 855.6016 785.9338 $426,762.07
625E30707 39.000 EACH PULL BOX, 725.08, 24", AS PER PLAN 836.0432 767.0282 $29,914.10
625E30708 4.000 EACH PULL BOX, 725.06, 24" 1,096.3119 1,093.7500 $4,375.00
625E30710 3.000 EACH PULL BOX, 725.08, 32" 922.8000 690.9000 $2,072.70
625E30720 59.000 EACH PULL BOX, 725.08, 36" 1,783.4296 1,720.8475 $101,530.00
625E30721 58.000 EACH PULL BOX, 725.08, 36", AS PER PLAN 1,381.4537 1,290.9483 $74,875.00
625E31320 32.000 EACH PULL BOX, 725.07, 18"X18" 599.8540 591.8250 $18,938.40
625E31410 7.000 EACH PULL BOX, 725.06, 13"X24" 527.5000 550.0000 $3,850.00
625E31411 2.000 EACH PULL BOX, 725.06, 13"X24", AS PER PLAN 558.1875 550.0000 $1,100.00
625E31421 65.000 EACH PULL BOX, 725.06, 17"X30", AS PER PLAN 664.4856 482.7329 $31,377.64
625E31430 5.000 EACH PULL BOX, 725.06, 24X36" 1,248.9850 1,100.0000 $5,500.00
625E31431 4.000 EACH PULL BOX, 725.06, 17X30", AS PER PLAN 898.6250 950.0000 $3,800.00
625E31451 57.000 EACH PULL BOX, AS PER PLAN 757.0456 802.2477 $45,728.12
625E31506 11.000 EACH PULL BOX REMOVED AND REPLACED 872.6417 688.6364 $7,575.00
625E31507 19.000 EACH PULL BOX REMOVED AND REPLACED, AS PER 803.5719 766.8947 $14,571.00
PLAN
625E31510 545.000 EACH PULL BOX REMOVED 177.4969 159.5818 $86,972.10
625E31511 16.000 EACH PULL BOX REMOVED, AS PER PLAN 234.8686 190.0000 $3,040.00
625E31600 288.000 EACH PULL BOX, MISC.: 923.5327 949.5468 $273,469.47
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
144 | P a g e
625E32000 1,932.000 EACH GROUND ROD 156.6680 154.4939 $298,482.16
625E32001 251.000 EACH GROUND ROD, AS PER PLAN 139.0935 128.2376 $32,187.63
625E33000 39.000 EACH STRUCTURE GROUNDING SYSTEM 3,889.5843 3,878.8656 $151,275.76
625E33001 2.000 EACH STRUCTURE GROUNDING SYSTEM, AS PER PLAN 5,409.5144 7,930.0000 $15,860.00
625E33100 30.000 EACH CIRCUIT BREAKER, TOWER LIGHTING 441.6133 404.4667 $12,134.00
625E33101 3.000 EACH CIRCUIT BREAKER, TOWER LIGHTING, AS PER 563.0200 423.0000 $1,269.00
PLAN
625E34000 18.000 EACH POWER SERVICE 3,896.3218 3,009.8839 $54,177.91
625E34001 77.000 EACH POWER SERVICE, AS PER PLAN 5,734.5707 5,276.2679 $406,272.63
625E34011 1.000 EACH POWER SERVICE REFURBISHED, AS PER PLAN 1,539.0425 2,100.0000 $2,100.00
625E34451 16.000 EACH CONTROL CENTER CABINET, COMPLETE, AS PER 2,446.3015 2,117.5625 $33,881.00
PLAN
625E34507 4.000 EACH CONTROL CENTER MAINTENANCE ITEM, AS PER 942.5723 471.0000 $1,884.00
PLAN
625E35000 26.000 EACH REERECT EXISTING LIGHT POLE 375.9271 340.3846 $8,850.00
625E35001 1.000 EACH REERECT EXISTING LIGHT POLE, AS PER PLAN 412.5000 400.0000 $400.00
625E35010 20.000 EACH REMOVE AND REERECT EXISTING LIGHT POLE 602.2632 644.9500 $12,899.00
625E35011 17.000 EACH REMOVE AND REERECT EXISTING LIGHT POLE, 579.7897 430.3912 $7,316.65
AS PER PLAN
625E35020 10.000 EACH RE-ERECT EXISTING LIGHT TOWER 2,446.3306 2,377.6000 $23,776.00
625E35100 6.000 EACH REERECT EXISTING LUMINAIRE 181.5623 131.0467 $786.28
625E35101 1.000 EACH REERECT EXISTING LUMINAIRE, AS PER PLAN 451.6667 300.0000 $300.00
625E35520 3.000 EACH REMOVE AND REERECT BRACKET ARM 358.9340 266.6700 $800.01
625E35521 27.000 EACH REMOVE AND REERECT BRACKET ARM, AS PER 228.3248 154.0741 $4,160.00
PLAN
625E36000 145,374.000 FT SPECIAL - PLASTIC CAUTION TAPE 0.2921 0.2019 $29,354.40
625E36001 10,636.000 FT PLASTIC CAUTION TAPE, AS PER PLAN 0.2894 0.2239 $2,381.36
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
145 | P a g e
625E36201 175.000 FT POWER CABLE FOR LIGHT TOWER, AS PER PLAN 14.5620 9.2857 $1,625.00
625E37001 1.000 LS SERVICE TO UNDERPASS LIGHTING, AS PER 10,164.4075 4,129.7900 $4,129.79
PLAN
625E37100 25.000 EACH SERVICE TO UNDERPASS LIGHTING 3,918.3893 3,703.1600 $92,579.00
625E37101 5.000 EACH SERVICE TO UNDERPASS LIGHTING, AS PER 15,875.5950 20,372.0000 $101,860.00
PLAN
625E37201 23,964.000 FXMT LIGHTING, MINIMAL MAINTENANCE, AS PER 4.2753 2.8259 $67,719.00
PLAN
625E37211 500.000 EACH LIGHTING, MINIMAL MAINTENANCE, AS PER 163.3333 100.0000 $50,000.00
PLAN
625E38000 4.000 LS HIGH VOLTAGE TEST 2,060.9450 2,353.7500 $9,415.00
625E39000 1.000 LS TEMPORARY LIGHTING 5,924.0040 5,000.0000 $5,000.00
625E39520 102.000 EACH PULL BOX CLEANED 134.7014 88.2843 $9,005.00
625E40000 22.000 LS SPECIAL - MAINTAIN EXISTING LIGHTING 13,532.5826 9,322.8118 $205,101.86
625E40004 2.000 EACH SPECIAL - MAINTAIN EXISTING LIGHTING 7,175.0000 8,750.0000 $17,500.00
625E40010 19.000 EACH SPECIAL - REPLACEMENT OF EXISTING 1,362.6880 1,424.2947 $27,061.60
LIGHTING UNIT
625E50000 100.000 EACH REPAIRING UNDERGROUND BREAK OF CABLE IN 292.3433 166.0000 $16,600.00
DUCT OR CONDUIT
625E50001 1.000 EACH REPAIRING UNDERGROUND BREAK OF CABLE IN 693.1700 440.0000 $440.00
DUCT OR CONDUIT, AS PER PLAN
625E50100 855.000 EACH TROUBLESHOOTING UNDERGROUND AND ABOVE 103.1094 46.3450 $39,625.00
GROUND CIRCUITRY PROBLEM
625E50400 6.000 EACH REPAIR INTEGRAL LUMINAIRE LOWERING 828.0615 542.5000 $3,255.00
MECHANISM OF TOWER LIGHTING FIXTURE
625E50401 11.000 EACH REPAIR INTEGRAL LUMINAIRE LOWERING 1,814.8949 1,973.1818 $21,705.00
MECHANISM OF TOWER LIGHTING FIXTURE, AS
PER PLAN
625E50451 12.000 EACH SECONDARY SURGE PROTECTOR, AS PER PLAN 225.0379 198.7500 $2,385.00
625E50500 61.000 EACH SPECIAL - EMERGENCY RESPONSE-KNOCKDOWN, 229.6098 196.7213 $12,000.00
ROADWAY HAZARD AND/OR LIVE EXPOSED WIRE
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
146 | P a g e
625E50510 30.000 HOUR SPECIAL - EMERGENCY RESPONSE-KNOCKDOWN, 89.5600 77.0000 $2,310.00
ROADWAY HAZARD AND/OR LIVE EXPOSED WIRE
625E60010 1.000 EACH LIGHT POLE REMOVED FOR REERECTION 282.6200 210.0000 $210.00
625E70001 23.000 EACH LIGHTING CONTACTOR, AS PER PLAN 372.8893 292.6087 $6,730.00
625E75350 89.000 EACH LIGHT TOWER REMOVED 1,559.3386 1,377.7115 $122,616.32
625E75351 28.000 EACH LIGHT TOWER REMOVED, AS PER PLAN 884.6667 600.0000 $16,800.00
625E75360 10.000 EACH LIGHT TOWER REMOVED FOR STORAGE 1,759.3541 1,188.4000 $11,884.00
625E75400 438.000 EACH LIGHT POLE REMOVED 202.5868 207.3287 $90,809.95
625E75401 132.000 EACH LIGHT POLE REMOVED, AS PER PLAN 110.4545 77.5000 $10,230.00
625E75402 1.000 EACH LIGHT POLE REMOVED FOR STORAGE 631.6225 1,100.0000 $1,100.00
625E75403 7.000 EACH LIGHT POLE REMOVED FOR STORAGE, AS PER 221.2526 204.8571 $1,434.00
PLAN
625E75410 40.000 EACH LIGHT POLE REMOVED FOR REUSE 221.7290 165.6250 $6,625.00
625E75500 331.000 EACH LIGHT POLE FOUNDATION REMOVED 206.6679 186.0627 $61,586.75
625E75501 32.000 EACH LIGHT POLE FOUNDATION REMOVED, AS PER 299.9450 311.7188 $9,975.00
PLAN
625E75502 1.000 EACH PORTION OF LIGHT POLE FOUNDATION REMOVED 409.4900 365.0000 $365.00
625E75503 8.000 EACH PORTION OF LIGHT POLE FOUNDATION 276.7818 274.5000 $2,196.00
REMOVED, AS PER PLAN
625E75505 12.000 EACH LUMINAIRE REMOVED FOR STORAGE, AS PER 55.3769 50.5000 $606.00
PLAN
625E75506 743.000 EACH LUMINAIRE REMOVED 52.9163 52.9960 $39,376.06
625E75507 11.000 EACH LUMINAIRE REMOVED, AS PER PLAN 40.0000 40.0000 $440.00
625E75508 111.000 EACH LUMINAIRE REMOVED FOR REUSE 67.6147 27.2973 $3,030.00
625E75510 27.000 EACH POWER SERVICE REMOVED 478.8782 379.2667 $10,240.20
625E75511 11.000 EACH POWER SERVICE REMOVED, AS PER PLAN 479.9505 286.3636 $3,150.00
625E75520 122.000 EACH LUMINAIRE SUPPORT REMOVED 137.7677 37.8770 $4,621.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
147 | P a g e
625E75522 193.000 EACH LUMINAIRE SUPPORT FOUNDATION REMOVED 309.9631 404.9606 $78,157.40
625E75540 81.000 EACH LIGHT TOWER FOUNDATION REMOVED 581.0907 650.7407 $52,710.00
625E75541 18.000 EACH LIGHT TOWER FOUNDATION REMOVED, AS PER 553.6582 366.8361 $6,603.05
PLAN
625E75550 89,331.000 FT DISTRIBUTION CABLE REMOVED 0.6183 0.5171 $46,194.32
625E75551 2,775.000 FT DISTRIBUTION CABLE REMOVED, AS PER PLAN 1.6069 1.6341 $4,534.70
625E75800 41.000 EACH DISCONNECT CIRCUIT 135.2989 177.1512 $7,263.20
625E75801 81.000 EACH DISCONNECT CIRCUIT, AS PER PLAN 143.9174 120.0306 $9,722.48
625E98000 2,222.000 EACH LIGHTING, MISC.: 440.7872 352.9777 $784,316.53
625E98100 55,462.000 FT LIGHTING, MISC.: 3.3759 4.3657 $242,129.80
625E98200 17.000 LS LIGHTING, MISC.: 51,854.6611 37,245.6294 $633,175.70
625E98700 260.000 HOUR LIGHTING, MISC.: 101.8341 86.9231 $22,600.00
625E99000 13.000 LS SPECIAL - LIGHTING 127,877.8135 160,982.8823 $2,092,777.47
626E00100 16,082.000 EACH BARRIER REFLECTOR, TYPE A 6.8746 6.2239 $100,092.12
626E00101 295.000 EACH BARRIER REFLECTOR, TYPE A, AS PER PLAN 5.1435 4.8508 $1,431.00
626E99000 10.000 LS SPECIAL - BARRIER REFLECTORS 626.3685 938.1000 $9,381.00
630E01101 104.000 FT GROUND MOUNTED SUPPORT, NO. 1 POST, AS 10.7683 8.0000 $832.00
PER PLAN
630E02100 14,273.700 FT GROUND MOUNTED SUPPORT, NO. 2 POST 7.9235 7.7969 $111,291.04
630E02101 1,956.000 FT GROUND MOUNTED SUPPORT, NO. 2 POST, AS 6.2605 6.5000 $12,714.00
PER PLAN
630E03100 38,807.900 FT GROUND MOUNTED SUPPORT, NO. 3 POST 8.4411 9.0137 $349,801.14
630E03101 4,841.500 FT GROUND MOUNTED SUPPORT, NO. 3 POST, AS 7.3568 6.6570 $32,229.80
PER PLAN
630E04100 1,745.600 FT GROUND MOUNTED SUPPORT, NO. 4 POST 9.8734 9.0215 $15,747.95
630E04101 91.000 FT GROUND MOUNTED SUPPORT, NO. 4 POST, AS 11.1465 11.6264 $1,058.00
PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
148 | P a g e
630E06100 34.000 FT GROUND MOUNTED SUPPORT, NO. 6 POST 13.3750 12.0000 $408.00
630E06400 2,255.700 FT GROUND MOUNTED SUPPORT, S4X7.7 BEAM 14.2375 13.3927 $30,209.96
630E06401 36.000 FT GROUND MOUNTED SUPPORT, S4X7.7 BEAM, AS 17.2143 18.0000 $648.00
PER PLAN
630E06500 2,333.550 FT GROUND MOUNTED SUPPORT, W6X9 BEAM 15.1465 14.4267 $33,665.39
630E07000 1,712.800 FT GROUND MOUNTED SUPPORT, W8X18 BEAM 24.9516 24.3127 $41,642.83
630E07500 993.250 FT GROUND MOUNTED SUPPORT, W10X22 BEAM 28.7002 27.8518 $27,663.80
630E07600 2,235.600 FT GROUND MOUNTED SUPPORT, W10X12 BEAM 18.3100 17.7228 $39,621.16
630E08000 2,359.700 FT GROUND MOUNTED SUPPORT, W12X30 BEAM 38.4810 37.9313 $89,506.60
630E08004 688.800 FT ONE WAY SUPPORT, NO. 3 POST 10.2262 10.2239 $7,042.19
630E08100 723.100 FT ONE WAY SUPPORT, NO. 4 POST 10.9706 10.0555 $7,271.12
630E08210 522.000 FT GROUND MOUNTED SUPPORT, PIPE 47.8968 39.8084 $20,780.00
630E08501 3.000 EACH STREET NAME SIGN SUPPORT, AS PER PLAN 746.4175 750.0000 $2,250.00
630E08510 1,584.500 FT STREET NAME SIGN SUPPORT, NO. 2 POST 9.5458 9.0150 $14,284.20
630E08520 1,061.000 FT STREET NAME SIGN SUPPORT, NO. 3 POST 10.7566 8.7632 $9,297.72
630E08530 97.000 FT STREET NAME SIGN SUPPORT, NO. 4 POST 12.9737 12.9562 $1,256.75
630E08600 1,010.000 EACH SIGN POST REFLECTOR 34.2183 31.9177 $32,236.90
630E08601 12.000 EACH SIGN POST REFLECTOR, AS PER PLAN 33.4353 35.0267 $420.32
630E09000 512.000 EACH BREAKAWAY BEAM CONNECTION 307.9917 300.5483 $153,880.72
630E09050 28.000 EACH TRIANGULAR SLIP BASE CONNECTION 258.6000 205.4000 $5,751.20
630E09051 4.000 EACH TRIANGULAR SLIP BASE CONNECTION, AS PER 444.6000 450.0000 $1,800.00
PLAN
630E09100 8.000 EACH SURFACE PREPARATION, EXISTING SUPPORT 593.7500 700.0000 $5,600.00
SECTION
630E09102 70.000 EACH SURFACE PREPARATION, NEW SUPPORT SECTION 245.6650 245.1429 $17,160.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
149 | P a g e
630E09106 78.000 EACH COATING, EPOXY INTERMEDIATE COAT, 267.7938 310.2564 $24,200.00
SUPPORT SECTION
630E09108 78.000 EACH COATING, URETHANE TOP COAT, SUPPORT 267.7938 310.2564 $24,200.00
SECTION
630E09120 69.000 EACH COATING, ORGANIC ZINC PRIME COAT, 234.9456 290.4348 $20,040.00
SUPPORT SECTION
630E10502 3.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 5,115.0000 4,700.0000 $14,100.00
DESIGN 5
630E10503 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 6,122.8500 6,525.0000 $6,525.00
DESIGN 5, AS PER PLAN
630E10703 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 6,385.4400 6,575.0000 $13,150.00
DESIGN 7, AS PER PLAN
630E10902 5.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 6,066.5983 5,920.0000 $29,600.00
DESIGN 9
630E11002 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 6,650.0000 6,100.0000 $12,200.00
DESIGN 10
630E11003 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 7,907.9125 8,300.0000 $8,300.00
DESIGN 10, AS PER PLAN
630E11102 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 9,590.4083 7,675.0000 $7,675.00
DESIGN 11
630E11103 3.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 8,889.9800 8,658.3333 $25,975.00
DESIGN 11, AS PER PLAN
630E11202 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 11,639.6250 14,300.0000 $14,300.00
DESIGN 12
630E11203 7.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 10,318.0053 9,964.2857 $69,750.00
DESIGN 12, AS PER PLAN
630E11206 4.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 11,142.9675 10,600.0000 $42,400.00
DESIGN 13
630E11208 4.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 12,781.6819 12,550.0000 $50,200.00
DESIGN 13, AS PER PLAN
630E11210 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 12,733.3333 12,450.0000 $12,450.00
DESIGN 14
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
150 | P a g e
630E11212 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-16.21, 16,562.5000 15,250.0000 $15,250.00
DESIGN 14, AS PER PLAN
630E20200 3.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 8,270.1915 7,077.6667 $21,233.00
DESIGN 2
630E20301 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 11,575.2850 9,350.0000 $18,700.00
DESIGN 3, AS PER PLAN
630E20400 3.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 10,066.1667 8,733.3333 $26,200.00
DESIGN 4
630E20401 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 13,325.7917 9,900.0000 $19,800.00
DESIGN 4, AS PER PLAN
630E20500 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 9,840.0000 9,840.0000 $9,840.00
DESIGN 5
630E20600 13.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 12,545.7734 11,959.2308 $155,470.00
DESIGN 6
630E20800 4.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 15,710.6244 14,095.0000 $56,380.00
DESIGN 8
630E20900 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 18,462.5000 17,000.0000 $17,000.00
DESIGN 9
630E21000 9.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 18,646.8557 18,695.5556 $168,260.00
DESIGN 10
630E21200 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 25,523.8950 25,300.0000 $50,600.00
DESIGN 12
630E21201 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-12.30, 60,875.0000 57,500.0000 $57,500.00
DESIGN 12, AS PER PLAN
630E30300 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-9.30, 11,148.8880 11,100.0000 $11,100.00
DESIGN 3
630E31101 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-9.10, 5,725.0000 8,000.0000 $16,000.00
DESIGN 1, AS PER PLAN
630E35500 17.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-7.65, 24,554.4622 24,450.2941 $415,655.00
DESIGN 6
630E35501 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-7.65, 24,344.0000 18,110.0000 $36,220.00
DESIGN 6, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
151 | P a g e
630E45500 11.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-7.65, 32,758.3395 31,845.0909 $350,296.00
DESIGN 8
630E45501 2.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-7.65, 47,840.6800 48,000.0000 $96,000.00
DESIGN 8, AS PER PLAN
630E55000 6.000 EACH CONCRETE BARRIER MEDIAN OVERHEAD SIGN 5,937.9807 6,166.6667 $37,000.00
SUPPORT FOUNDATION, TC-7.65
630E66500 6.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-15.115 44,230.6405 44,005.0000 $264,030.00
630E66501 1.000 EACH OVERHEAD SIGN SUPPORT, TYPE TC-15.115, 78,022.8275 78,250.0000 $78,250.00
AS PER PLAN
630E74500 6.000 EACH OVERHEAD SIGN SUPPORT, MISC.: 15,275.1325 16,755.8333 $100,535.00
630E75000 109.000 EACH SIGN ATTACHMENT ASSEMBLY 428.1374 391.1468 $42,635.00
630E75001 46.000 EACH SIGN ATTACHMENT ASSEMBLY, AS PER PLAN 848.8858 738.5870 $33,975.00
630E75400 1.000 EACH SPAN WIRE SIGN SUPPORT, TYPE TC-17.10, 6,909.6250 6,800.0000 $6,800.00
DESIGN 4
630E75800 5.000 EACH SPAN WIRE SIGN SUPPORT, TYPE TC-17.10, 10,243.6075 9,850.0000 $49,250.00
DESIGN 8
630E77000 3.000 EACH OVERPASS STRUCTURE MOUNTED SIGN SUPPORT, 3,326.3313 2,100.0000 $6,300.00
TYPE TC-18.24
630E77200 2.000 EACH OVERPASS STRUCTURE MOUNTED SIGN SUPPORT, 4,669.6633 3,250.0000 $6,500.00
TYPE TC-18.26, DESIGN 2
630E79000 183.000 EACH SIGN HANGER ASSEMBLY, SPAN WIRE 204.7201 184.0464 $33,680.49
630E79001 6.000 EACH SIGN HANGER ASSEMBLY, SPAN WIRE, AS PER 375.0077 422.0333 $2,532.20
PLAN
630E79100 194.000 EACH SIGN HANGER ASSEMBLY, MAST ARM 263.9378 264.1443 $51,244.00
630E79101 171.000 EACH SIGN HANGER ASSEMBLY, MAST ARM, AS PER 257.5974 249.7543 $42,707.98
PLAN
630E79500 742.000 EACH SIGN SUPPORT ASSEMBLY, POLE MOUNTED 76.9517 73.1381 $54,268.45
630E79501 54.000 EACH SIGN SUPPORT ASSEMBLY, POLE MOUNTED, AS 116.0487 122.7778 $6,630.00
PER PLAN
630E79600 8.000 EACH SIGN SUPPORT ASSEMBLY, BRIDGE MOUNTED, 951.7950 950.0000 $7,600.00
TYPE 1
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
152 | P a g e
630E79604 4.000 EACH SIGN SUPPORT ASSEMBLY, BRIDGE MOUNTED, 1,278.3333 1,135.0000 $4,540.00
TYPE 2
630E79610 4.000 EACH SIGN SUPPORT ASSEMBLY, BARRIER MOUNTED 1,110.8187 1,347.5000 $5,390.00
630E80100 33,186.250 SF SIGN, FLAT SHEET 14.8843 14.3444 $476,036.25
630E80101 3,631.470 SF SIGN, FLAT SHEET, AS PER PLAN 14.8393 13.1607 $47,792.66
630E80200 20,334.000 SF SIGN, GROUND MOUNTED EXTRUSHEET 15.5136 14.7560 $300,049.37
630E80201 2,426.000 SF SIGN, GROUND MOUNTED EXTRUSHEET, AS PER 15.0000 15.5000 $37,603.00
PLAN
630E80224 23,187.800 SF SIGN, OVERHEAD EXTRUSHEET 16.3886 16.0011 $371,031.38
630E80225 178.000 SF SIGN, OVERHEAD EXTRUSHEET, AS PER PLAN 17.8125 15.7500 $2,803.50
630E80300 410.000 SF SIGN, TEMPORARY OVERLAY 23.4946 24.5122 $10,050.00
630E80301 192.000 SF SIGN, TEMPORARY OVERLAY, AS PER PLAN 88.0703 107.1875 $20,580.00
630E80400 396.700 SF SIGN, PERMANENT OVERLAY 22.8849 21.5809 $8,561.15
630E80401 1.300 SF SIGN, PERMANENT OVERLAY, AS PER PLAN 23.7875 40.0000 $52.00
630E80500 336.000 EACH SIGN, DOUBLE FACED, STREET NAME 122.6429 123.7691 $41,586.42
630E80501 36.000 EACH SIGN, DOUBLE FACED, STREET NAME, AS PER 149.2851 106.6667 $3,840.00
PLAN
630E80510 11.000 EACH SIGN, STREET NAME 169.5214 158.6364 $1,745.00
630E80511 20.000 EACH SIGN, DOUBLE FACED, STREET NAME, TYPE H, 176.9157 128.0000 $2,560.00
AS PER PLAN
630E80600 3.000 EACH SIGN, DOUBLE FACED, MILE MARKER 71.0728 43.3333 $130.00
630E81000 6.000 EACH MAINLINE REFERENCE MARKER 116.2500 115.0000 $690.00
630E81020 12.000 EACH CONCRETE MEDIAN BARRIER SIGN BRACKET 387.5483 360.4167 $4,325.00
630E81100 1,319.400 SF SIGN ERECTED, FLAT SHEET 4.2878 4.1748 $5,508.25
630E81101 15.000 SF SIGN ERECTED, FLAT SHEET, AS PER PLAN 9.1250 10.0000 $150.00
630E81200 4,564.000 SF SIGN ERECTED, EXTRUSHEET 3.1336 3.0447 $13,896.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
153 | P a g e
630E81201 484.000 SF SIGN ERECTED, EXTRUSHEET, AS PER PLAN 8.0205 8.1426 $3,941.00
630E82000 73.000 EACH SIGN BACKING ASSEMBLY 81.4296 71.0274 $5,185.00
630E83000 1,882.500 SF COVERING OF SIGN 4.7866 4.7461 $8,934.50
630E84000 5.000 EACH CONCRETE BARRIER MEDIAN OVERHEAD SIGN 5,200.3271 4,081.1120 $20,405.56
SUPPORT FOUNDATION, TYPE TC-21.40
630E84500 545.000 EACH GROUND MOUNTED BEAM SUPPORT FOUNDATION 617.2385 588.4729 $320,717.72
630E84510 144.000 EACH RIGID OVERHEAD SIGN SUPPORT FOUNDATION 3,146.8264 3,084.6250 $444,186.00
630E84511 4.000 EACH RIGID OVERHEAD SIGN SUPPORT FOUNDATION, 7,733.9286 8,350.0000 $33,400.00
AS PER PLAN
630E84520 12.000 EACH SPAN WIRE SIGN SUPPORT FOUNDATION 2,551.2661 3,156.9417 $37,883.30
630E84600 28.000 EACH GROUND MOUNTED PIPE SUPPORT FOUNDATION 423.4643 529.8571 $14,836.00
630E84900 3,474.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 13.3552 13.7830 $47,882.17
DISPOSAL
630E84901 422.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 13.4657 11.8175 $4,987.00
DISPOSAL, AS PER PLAN
630E85000 236.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 16.4434 17.8076 $4,202.59
STORAGE
630E85001 216.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 21.0594 18.5917 $4,015.80
STORAGE, AS PER PLAN
630E85100 750.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 53.6046 53.2089 $39,906.67
REERECTION
630E85101 111.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 57.2887 58.1081 $6,450.00
REERECTION, AS PER PLAN
630E85200 10.000 EACH REMOVAL OF GROUND MOUNTED SIGN AND 36.4286 50.0000 $500.00
DELIVERY
630E85400 252.000 EACH REMOVAL OF GROUND MOUNTED MAJOR SIGN AND 89.4184 77.8355 $19,614.54
DISPOSAL
630E85600 35.000 EACH REMOVAL OF GROUND MOUNTED MAJOR SIGN AND 337.2909 277.0000 $9,695.00
REERECTION
630E86002 4,012.000 EACH REMOVAL OF GROUND MOUNTED POST SUPPORT 15.2185 14.7171 $59,045.17
AND DISPOSAL
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
154 | P a g e
630E86003 7.000 EACH REMOVAL OF GROUND MOUNTED POST SUPPORT 116.6207 67.1429 $470.00
AND DISPOSAL, AS PER PLAN
630E86006 72.000 EACH REMOVAL OF GROUND MOUNTED POST SUPPORT 17.2551 16.3688 $1,178.55
AND STORAGE
630E86010 114.000 EACH REMOVAL OF GROUND MOUNTED POST SUPPORT 82.1753 75.8404 $8,645.80
AND REERECTION
630E86011 1.000 EACH REMOVAL OF GROUND MOUNTED POST SUPPORT 150.0000 150.0000 $150.00
AND REERECTION, AS PER PLAN
630E86050 8.000 EACH REMOVAL OF GROUND MOUNTED POST SUPPORT 21.4286 20.0000 $160.00
AND DELIVERY
630E86102 515.000 EACH REMOVAL OF GROUND MOUNTED BEAM SUPPORT 145.0561 149.0140 $76,742.20
AND DISPOSAL
630E86250 4.000 EACH REMOVAL OF GROUND MOUNTED BEAM SUPPORT 735.6250 702.5000 $2,810.00
AND REERECTION
630E86272 2.000 EACH REMOVAL OF GROUND MOUNTED PIPE SUPPORT 71.3333 148.5000 $297.00
AND DISPOSAL
630E86274 1.000 EACH REMOVAL OF GROUND MOUNTED PIPE SUPPORT 447.0000 950.0000 $950.00
AND REERECTION
630E86310 9.000 EACH REMOVAL OF STRUCTURE MOUNTED SIGN AND 267.1035 215.7778 $1,942.00
DISPOSAL
630E86311 1.000 EACH REMOVAL OF STRUCTURE MOUNTED SIGN AND 531.2500 300.0000 $300.00
DISPOSAL, AS PER PLAN
630E86320 9.000 EACH REMOVAL OF STRUCTURE MOUNTED SIGN AND 469.8304 1,008.3333 $9,075.00
REERECTION
630E87000 68.000 EACH REMOVAL OF OVERHEAD MOUNTED SIGN AND 70.8310 52.1941 $3,549.20
STORAGE
630E87001 5.000 EACH REMOVAL OF OVERHEAD MOUNTED SIGN AND 75.8333 50.0000 $250.00
STORAGE, AS PER PLAN
630E87100 40.000 EACH REMOVAL OF OVERHEAD MOUNTED SIGN AND 374.1808 283.9850 $11,359.40
REERECTION
630E87400 405.000 EACH REMOVAL OF OVERHEAD MOUNTED SIGN AND 141.6312 132.6148 $53,709.00
DISPOSAL
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
155 | P a g e
630E87401 3.000 EACH REMOVAL OF OVERHEAD MOUNTED SIGN AND 382.5000 150.0000 $450.00
DISPOSAL, AS PER PLAN
630E87500 287.000 EACH REMOVAL OF POLE MOUNTED SIGN AND 20.8442 17.1498 $4,922.00
DISPOSAL
630E87501 4.000 EACH REMOVAL OF POLE MOUNTED SIGN AND 55.7111 30.0000 $120.00
DISPOSAL, AS PER PLAN
630E87510 347.000 EACH REMOVAL OF POLE MOUNTED SIGN AND STORAGE 17.2222 16.7274 $5,804.40
630E87511 17.000 EACH REMOVAL OF POLE MOUNTED SIGN AND 31.1551 11.4706 $195.00
STORAGE, AS PER PLAN
630E87520 125.000 EACH REMOVAL OF POLE MOUNTED SIGN AND 68.9418 76.2000 $9,525.00
REERECTION
630E88550 12.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 1,189.7675 1,200.0000 $14,400.00
STORAGE, TYPE TC-17.10
630E88901 1.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 4,280.0000 4,280.0000 $4,280.00
REERECTION, AS PER PLAN
630E89400 1.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 9,056.2500 9,800.0000 $9,800.00
REERECTION, TYPE TC-7.65
630E89702 23.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 856.6735 1,052.4348 $24,206.00
DISPOSAL
630E89703 3.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 905.2063 900.0000 $2,700.00
DISPOSAL, AS PER PLAN
630E89704 1.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 1,116.6667 950.0000 $950.00
DISPOSAL, TYPE TC-16.20
630E89706 31.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 910.7503 945.9677 $29,325.00
DISPOSAL, TYPE TC-12.30
630E89707 1.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 1,531.2500 1,500.0000 $1,500.00
DISPOSAL, TYPE TC-12.30, AS PER PLAN
630E89800 2.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 1,293.7500 1,500.0000 $3,000.00
DISPOSAL, TYPE TC-9.10
630E89802 24.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 1,451.4123 1,715.3333 $41,168.00
DISPOSAL, TYPE TC-7.65
630E89803 2.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 2,237.5000 3,000.0000 $6,000.00
DISPOSAL, TYPE TC-7.65, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
156 | P a g e
630E89804 2.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 2,112.7320 2,012.5000 $4,025.00
DISPOSAL, TYPE TC-15.115
630E89806 8.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 816.7255 738.7500 $5,910.00
DISPOSAL, TYPE TC-18.24
630E89808 5.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 725.0000 660.0000 $3,300.00
DISPOSAL, TYPE TC-18.26
630E89810 5.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 1,141.0450 1,222.0000 $6,110.00
DISPOSAL, TYPE TC-17.10
630E89811 1.000 EACH REMOVAL OF OVERHEAD SIGN SUPPORT AND 714.5556 700.0000 $700.00
DISPOSAL, TYPE TC-17.10 , AS PER PLAN
630E89812 1.000 EACH REMOVAL OF WOOD POLE AND DISPOSAL 690.0000 700.0000 $700.00
630E89894 10.000 EACH REMOVAL OF TEMPORARY OVERLAY SIGN AND 173.3333 20.0000 $200.00
DISPOSAL
630E89902 36.000 EACH REMOVAL OF MISCELLANEOUS TRAFFIC CONTROL 83.6563 98.7500 $3,555.00
ITEM
630E95000 2.000 LS SIGNING, MISC.: 21,245.0000 16,300.0000 $32,600.00
630E97700 455.000 EACH SIGNING, MISC.: 268.6315 249.9779 $113,739.93
630E97800 3,726.000 SF SIGNING, MISC.: 13.4466 10.9804 $40,913.00
630E97900 263.000 FT SIGNING, MISC.: 54.6660 41.3916 $10,886.00
630E99000 20.000 LS SPECIAL - SIGNS AND SUPPORTS 92,982.4297 92,723.0210 $1,854,460.42
631E84000 2.000 EACH SIGN SERVICE 1,053.4611 1,143.0000 $2,286.00
631E84300 8.000 EACH SIGN WIRED 398.9216 474.3225 $3,794.58
631E84301 45.000 EACH SIGN WIRED, AS PER PLAN 517.0000 250.0000 $11,250.00
631E85000 1.000 EACH DISCONNECT SWITCH, 30 AMP 555.0000 300.0000 $300.00
631E85100 2.000 EACH DISCONNECT SWITCH WITH ENCLOSURE, TYPE X 1,056.6667 1,076.0000 $2,152.00
631E85101 1.000 EACH DISCONNECT SWITCH WITH ENCLOSURE, TYPE 796.6667 750.0000 $750.00
X, AS PER PLAN
631E85500 2.000 EACH SWITCH ENCLOSURE MOUNTING BRACKET 302.3867 350.0000 $700.00
ASSEMBLY
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
157 | P a g e
631E87102 10.000 EACH BALLAST, TYPE CMRI-100-480 373.3333 200.0000 $2,000.00
631E88000 12.000 EACH PHOTOELECTRIC CONTROL 102.3370 92.5000 $1,110.00
631E90201 1.000 EACH CHANGEABLE MESSAGE SIGN, UNLIMITED 100,999.4650 73,816.3500 $73,816.35
MESSAGE, AS PER PLAN
631E90501 15.000 EACH INTERNALLY ILLUMINATED FIXED MESSAGE 2,303.9018 2,294.3333 $34,415.00
SIGN, AS PER PLAN
631E92000 3.000 EACH SIGN FLASHER ASSEMBLY 875.4358 1,095.4667 $3,286.40
631E92001 51.000 EACH SIGN FLASHER ASSEMBLY, AS PER PLAN 4,366.6655 3,485.0635 $177,738.24
631E92990 2.000 EACH SCHOOL SPEED LIMIT SIGN ASSEMBLY, 24" X 1,071.3233 813.9700 $1,627.94
36"
631E92991 2.000 EACH SCHOOL SPEED LIMIT SIGN ASSEMBLY, 24" X 2,026.9900 1,080.9700 $2,161.94
36", AS PER PLAN
631E93100 2.000 EACH SCHOOL SPEED LIMIT SIGN ASSEMBLY, 36" X 1,637.6250 1,500.0000 $3,000.00
75"
631E93201 9.000 EACH SCHOOL SPEED LIMIT SIGN ASSEMBLY, AS 5,514.9733 5,615.5556 $50,540.00
PER PLAN
631E93250 4.000 EACH SCHOOL SPEED LIMIT SIGN ASSEMBLY, MISC.: 3,575.5556 3,637.5000 $14,550.00
631E93300 3.000 EACH TIMER WITH ENCLOSURE 1,046.6589 1,059.8400 $3,179.52
631E94000 24.000 EACH REMOVAL OF LUMINAIRE AND STORAGE 124.5967 30.0000 $720.00
631E94200 39.000 EACH REMOVAL OF LUMINAIRE AND DISPOSAL 49.9204 43.5897 $1,700.00
631E94250 20.000 EACH REMOVAL OF LUMINAIRE 31.2856 35.0000 $700.00
631E94300 7.000 EACH REMOVAL OF DISCONNECT SWITCH AND STORAGE 245.8200 50.0000 $350.00
631E94304 1.000 EACH REMOVAL OF DISCONNECT SWITCH AND 205.3667 266.0000 $266.00
DISPOSAL
631E94350 4.000 EACH REMOVAL OF DISCONNECT SWITCH 116.0267 125.0000 $500.00
631E94400 24.000 EACH REMOVAL OF BALLAST AND STORAGE 94.3567 30.0000 $720.00
631E94406 4.000 EACH REMOVAL OF SIGNS WIRED 103.0591 116.5000 $466.00
631E94408 25.000 EACH REMOVAL OF SIGN WIRING AND DISPOSAL 115.6934 86.0000 $2,150.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
158 | P a g e
631E94412 37.000 EACH REMOVAL OF SIGN SERVICE AND DISPOSAL 160.7055 105.4865 $3,903.00
631E94413 4.000 EACH REMOVAL OF SIGN SERVICE AND DISPOSAL, AS 478.1250 375.0000 $1,500.00
PER PLAN
631E94420 12.000 EACH REMOVAL MISC.: 427.4910 248.2567 $2,979.08
631E94450 16.000 EACH REMOVAL OF BALLAST 26.6121 31.2500 $500.00
631E94470 2.000 EACH REMOVAL OF SIGN SERVICE 53.8475 50.0000 $100.00
631E95000 2.000 LS SIGN LIGHTING MISC.: 46,416.6667 74,250.0000 $148,500.00
631E97700 9.000 EACH SIGN LIGHTING MISC.: 1,006.6052 1,303.8889 $11,735.00
631E97800 120.000 FXMT SIGN LIGHTING, MISC.: 5.3333 1.0000 $120.00
632E00100 4.000 EACH VEHICULAR SIGNAL HEAD, 1 SECTION, 12" 372.4850 375.0000 $1,500.00
LENS, 1-WAY
632E00300 26.000 EACH VEHICULAR SIGNAL HEAD, 3 SECTION, 12" 423.3750 300.0000 $7,800.00
LENS, 1-WAY
632E00301 38.000 EACH VEHICULAR SIGNAL HEAD, 3 SECTION, 12" 662.8597 652.9700 $24,812.86
LENS, 1-WAY, AS PER PLAN
632E00401 1.000 EACH VEHICULAR SIGNAL HEAD, 4 SECTION, 12" 791.1825 757.5400 $757.54
LENS, 1-WAY, AS PER PLAN
632E00500 2.000 EACH VEHICULAR SIGNAL HEAD, 5 SECTION, 12" 699.0000 600.0000 $1,200.00
LENS, 1-WAY
632E00501 6.000 EACH VEHICULAR SIGNAL HEAD, 5 SECTION, 12" 1,103.7850 1,185.3200 $7,111.92
LENS, 1-WAY, AS PER PLAN
632E00900 1.000 EACH VEHICULAR SIGNAL HEAD, 1 SECTION, 12" 610.0000 590.0000 $590.00
LENS, 2-WAY
632E03200 3.000 EACH VEHICULAR SIGNAL HEAD, OPTICALLY 2,491.9375 3,120.6000 $9,361.80
PROGRAMMED, 3 SECTION, 12" LENS, 1-WAY
632E03201 6.000 EACH VEHICULAR SIGNAL HEAD, OPTICALLY 2,950.0000 2,500.0000 $15,000.00
PROGRAMMED, 3-SECTION, 12" LENS, 1-WAY,
AS PER PLAN
632E03204 1.000 EACH VEHICULAR SIGNAL HEAD, OPTICALLY 4,013.0750 5,074.6000 $5,074.60
PROGRAMMED, 5 SECTION, 12" LENS, 1-WAY
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
159 | P a g e
632E04000 34.000 EACH VEHICULAR SIGNAL HEAD, MISC.: 721.7425 619.6029 $21,066.50
632E04800 1.000 EACH VEHICULAR SIGNAL HEAD, (LED), 1 SECTION, 293.2875 207.0000 $207.00
12" LENS, 1-WAY
632E04801 10.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 407.5000 350.0000 $3,500.00
UNIT, 1 SECTION, 12" LENS, 1-WAY, AS PER
PLAN
632E04802 1.000 EACH VEHICULAR SIGNAL HEAD, (LED), 1 SECTION, 710.0000 700.0000 $700.00
12" LENS, 1-WAY, POLYCARBONATE
632E04803 7.000 EACH VEHICULAR SIGNAL HEAD, (LED), 1 SECTION, 433.8942 372.8571 $2,610.00
12" LENS, 1-WAY, POLYCARBONATE, AS PER
PLAN
632E04811 2.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 900.0000 800.0000 $1,600.00
UNIT, 1 SECTION, 12" LENS, 3-WAY, AS PER
PLAN
632E04910 6.000 EACH VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 850.0000 850.0000 $5,100.00
12" LENS, 1-WAY, WITH BACKPLATE (BLACK)
632E04911 271.000 EACH VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 682.4572 633.2287 $171,604.97
12" LENS, 1-WAY, WITH BACKPLATE
(BLACK), AS PER PLAN
632E04912 17.000 EACH VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 833.4065 716.5588 $12,181.50
12" LENS, 1-WAY, WITH BACKPLATE
(YELLOW)
632E04913 160.000 EACH VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 672.1301 633.4188 $101,347.00
12" LENS, 1-WAY, WITH BACKPLATE
(YELLOW), AS PER PLAN
632E04917 10.000 EACH VEHICULAR SIGNAL HEAD, (LED) BLACK, 1,214.2680 1,155.0000 $11,550.00
3-SECTION, 12" LENS, 2-WAY, WITH
BACKPLATE, AS PER PLAN
632E04921 69.000 EACH VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 1,101.0931 1,042.8623 $71,957.50
12" LENS, 1-WAY, WITH BACKPLATE
(BLACK), AS PER PLAN
632E04922 11.000 EACH VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 1,366.3500 1,312.9364 $14,442.30
12" LENS, 1-WAY, WITH BACKPLATE
(YELLOW)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
160 | P a g e
632E04923 34.000 EACH VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 1,017.5012 986.6471 $33,546.00
12" LENS, 1-WAY, WITH BACKPLATE
(YELLOW), AS PER PLAN
632E04925 18.000 EACH VEHICULAR SIGNAL HEAD, (LED) BLACK, 951.6928 748.6111 $13,475.00
4-SECTION, 12" LENS, 1-WAY, WITH
BACKPLATE, AS PER PLAN
632E05000 9.000 EACH VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 654.9100 623.2222 $5,609.00
12" LENS, 1-WAY
632E05001 70.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 682.5686 647.3021 $45,311.15
UNITS, 3-SECTION, 12" LENS, 1-WAY, AS PER PLAN
632E05005 92.000 EACH VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 605.7894 591.0935 $54,380.60
12" LENS, 1-WAY, POLYCARBONATE, AS PER PLAN
632E05006 57.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 760.4035 676.9298 $38,585.00
3-SECTION, 12" LENS, 1-WAY,
POLYCARBONATE WITH BACKPLATE
632E05007 398.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 721.4389 703.6428 $280,049.82
3-SECTION, 12" LENS, 1-WAY,
POLYCARBONATE, WITH BACKPLATE, AS PER PLAN
632E05011 1.000 EACH VEHICULAR SIGNAL HEAD, (LED) 3 SECTION 1,043.0717 990.0000 $990.00
12"LENS, 2-WAY, POLYCARBONATE, AS PER PLAN
632E05021 3.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 1,025.1667 885.0000 $2,655.00
UNITS, 3-SECTION, 12" LENS, 2-WAY, AS PER PLAN
632E05041 2.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 1,686.9064 1,640.6100 $3,281.22
UNITS, 3-SECTION, 12" LENS, 3-WAY, AS PER PLAN
632E05061 3.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 1,198.1220 1,183.3333 $3,550.00
UNITS, 4-SECTION, 12" LENS, 1-WAY, AS PER PLAN
632E05065 1.000 EACH VEHICULAR SIGNAL HEAD, (LED), 4-SECTION, 875.0000 900.0000 $900.00
12" LENS, 1-WAY, POLYCARBONATE, AS PER PLAN
632E05067 11.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 877.7606 825.1527 $9,076.68
4-SECTION, 12" LENS, 1-WAY,
POLYCARBONATE, WITH BACKPLATE, AS PER PLAN
632E05080 1.000 EACH VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 787.7575 631.0000 $631.00
12" LENS, 1-WAY
632E05081 30.000 EACH VEHICULAR SIGNAL HEAD WITH LED LAMP 1,096.8188 1,097.1667 $32,915.00
UNITS, 5-SECTION, 12" LENS, 1-WAY, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
161 | P a g e
632E05085 19.000 EACH VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 1,053.2069 922.8947 $17,535.00
12" LENS, 1-WAY, POLYCARBONATE, AS PER PLAN
632E05086 6.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 1,187.8175 1,091.0000 $6,546.00
5-SECTION, 12" LENS, 1-WAY,
POLYCARBONATE WITH BACKPLATE
632E05087 97.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 1,187.3067 1,088.3495 $105,569.90
5-SECTION, 12" LENS, 1-WAY,
POLYCARBONATE, WITH BACKPLATE, AS PER PLAN
632E05315 2.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 5 1,996.6667 1,775.0000 $3,550.00
SECTION, 12"LENS, 2-WAY, POLYCARBONATE,
WITH 2-WAY BACKPLATE, AS PER PLAN
632E05317 10.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 3 539.0833 484.0000 $4,840.00
SECTION, 12"LENS, 1-WAY, POLYCARBONATE, AS PER PLAN
632E05325 5.000 EACH VEHICULAR SIGNAL HEAD, (LED), BLACK, 5 901.4048 799.2000 $3,996.00
SECTION, 12"LENS, 1-WAY, POLYCARBONATE,
AS PER PLAN
632E10001 381.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 64.6060 66.0000 $25,146.00
LAMP UNIT, CIRCULAR RED, AS PER PLAN
632E10011 405.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 66.8480 68.0000 $27,540.00
LAMP UNIT, CIRCULAR YELLOW, AS PER PLAN
632E10021 381.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 67.2200 68.3000 $26,022.30
LAMP UNIT, CIRCULAR GREEN, AS PER PLAN
632E10031 51.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 69.8320 72.0500 $3,674.55
LAMP UNIT, CIRCULAR YELLOW ARROW, AS PER
PLAN
632E10041 49.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 70.9740 71.6500 $3,510.85
LAMP UNIT, CIRCULAR GREEN ARROW, AS PER PLAN
632E10051 25.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 110.8280 100.0000 $2,500.00
LAMP UNIT, WALKING PERSON SYMBOL, AS PER PLAN
632E10061 25.000 EACH RELAMP EXISTING SIGNAL SECTION WITH LED 94.3180 75.0000 $1,875.00
LAMP UNIT, UPRAISED HAND SYMBOL, AS PER PLAN
632E20510 2.000 EACH PEDESTRIAN SIGNAL HEAD (LED) , TYPE A2 580.1667 530.0000 $1,060.00
632E20511 26.000 EACH PEDESTRIAN SIGNAL HEAD (LED) , TYPE A2, 632.9566 587.3846 $15,272.00
AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
162 | P a g e
632E20601 12.000 EACH PEDESTRIAN SIGNAL HEAD, TYPE D2, AS PER 521.0014 472.5000 $5,670.00
PLAN
632E20720 10.000 EACH PEDESTRIAN SIGNAL HEAD (LED) , TYPE D2 496.4800 446.0000 $4,460.00
632E20721 48.000 EACH PEDESTRIAN SIGNAL HEAD WITH LED LAMP 525.5368 469.7942 $22,550.12
UNITS , TYPE D2, AS PER PLAN
632E20730 131.000 EACH PEDESTRIAN SIGNAL HEAD (LED) , 526.6195 478.9015 $62,736.10
(COUNTDOWN), TYPE D2
632E20731 497.000 EACH PEDESTRIAN SIGNAL HEAD (LED) , 501.3576 464.0194 $230,617.62
(COUNTDOWN), TYPE D, AS PER PLAN
632E20750 1.000 EACH ACCESSIBLE PEDESTRIAN PUSHBUTTON 2,019.5000 1,150.0000 $1,150.00
632E25000 1,099.000 EACH COVERING OF VEHICULAR SIGNAL HEAD 32.1118 20.6773 $22,724.34
632E25001 232.000 EACH COVERING OF VEHICULAR SIGNAL HEAD, AS 28.8743 25.5465 $5,926.79
PER PLAN
632E25010 366.000 EACH COVERING OF PEDESTRIAN SIGNAL HEAD 22.8278 18.1527 $6,643.88
632E25011 104.000 EACH COVERING OF PEDESTRIAN SIGNAL HEAD, AS 30.9626 29.0708 $3,023.36
PER PLAN
632E26000 237.000 EACH PEDESTRIAN PUSHBUTTON 183.2298 184.6342 $40,434.90
632E26001 249.000 EACH PEDESTRIAN PUSHBUTTON, AS PER PLAN 222.0834 228.7741 $54,219.45
632E26500 724.000 EACH DETECTOR LOOP 1,035.3678 1,031.9828 $747,155.56
632E26501 966.000 EACH DETECTOR LOOP, AS PER PLAN 906.9425 882.7316 $852,718.72
632E27004 30.000 EACH LOOP DETECTOR UNIT 134.9043 94.0000 $2,820.00
632E27005 41.000 EACH LOOP DETECTOR UNIT, AS PER PLAN 197.9452 184.8780 $7,580.00
632E27008 3.000 EACH LOOP DETECTOR UNIT, DELAY AND EXTENSION 420.0125 577.6600 $1,732.98
TYPE
632E27009 80.000 EACH LOOP DETECTOR UNIT, DELAY AND EXTENSION 281.6961 280.6525 $22,452.20
TYPE, AS PER PLAN
632E27103 24.000 EACH LOOP DETECTOR UNIT, 2 CHANNEL, AS PER PLAN 211.7944 199.5750 $4,789.80
632E27105 8.000 EACH LOOP DETECTOR UNIT, 2 CHANNEL, DELAY AND 376.8486 365.5000 $2,924.00
EXTENSION TYPE, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
163 | P a g e
632E27200 148.000 EACH LOOP DETECTOR TIE IN 73.7473 73.1480 $10,825.91
632E27201 59.000 EACH LOOP DETECTOR TIE IN, AS PER PLAN 101.7305 79.7458 $4,705.00
632E28201 1.000 EACH DISCONNECT SWITCH WITH ENCLOSURE, AS PER 875.8333 790.0000 $790.00
PLAN
632E29900 1,424.000 FT MESSENGER WIRE, 7 STRAND, 1/4" DIAMETER 8.1620 5.7659 $8,210.64
WITH ACCESSORIES
632E30000 365.000 FT MESSENGER WIRE, 3 STRAND, 1/4" DIAMETER 6.0728 4.6918 $1,712.50
WITH ACCESSORIES
632E30200 20,263.000 FT MESSENGER WIRE, 7 STRAND, 3/8" DIAMETER 8.9601 8.6105 $174,475.39
WITH ACCESSORIES
632E30201 940.000 FT MESSENGER WIRE, 7 STRAND, 3/8" DIAMETER 10.9252 8.4631 $7,955.30
WITH ACCESSORIES, AS PER PLAN
632E30300 3,461.000 FT MESSENGER WIRE, 7 STRAND, 7/16" DIAMETER 11.0650 11.9179 $41,247.75
WITH ACCESSORIES
632E30400 1,908.000 FT MESSENGER WIRE, 7 STRAND, 1/2" DIAMETER 10.5156 10.2562 $19,568.76
WITH ACCESSORIES
632E30600 16,217.000 FT TETHER WIRE, WITH ACCESSORIES 13.2522 10.9727 $177,944.89
632E30601 4,414.000 FT TETHER WIRE, WITH ACCESSORIES, AS PER 14.0052 12.1467 $53,615.64
PLAN
632E40200 13,912.000 FT SIGNAL CABLE, 2 CONDUCTOR, NO. 14 AWG 1.4776 1.5479 $21,534.16
632E40201 463.000 FT SIGNAL CABLE, 2 CONDUCTOR, NO. 14 AWG, 1.6700 1.3000 $601.90
AS PER PLAN
632E40300 24,268.000 FT SIGNAL CABLE, 3 CONDUCTOR, NO. 14 AWG 1.6752 1.5273 $37,065.48
632E40400 2,191.000 FT SIGNAL CABLE, 4 CONDUCTOR, NO. 14 AWG 1.9200 1.7865 $3,914.20
632E40500 78,476.000 FT SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG 1.9351 1.7986 $141,145.77
632E40501 3,377.000 FT SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG, 2.2428 1.9721 $6,659.75
AS PER PLAN
632E40700 138,009.000 FT SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG 2.2628 2.1238 $293,101.36
632E40701 29,396.000 FT SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG, 2.3451 2.0615 $60,598.80
AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
164 | P a g e
632E40900 8,331.000 FT SIGNAL CABLE, 9 CONDUCTOR, NO. 14 AWG 2.6343 2.5491 $21,236.38
632E40901 2,421.000 FT SIGNAL CABLE, 9 CONDUCTOR, NO. 14 AWG, 2.7214 2.5375 $6,143.35
AS PER PLAN
632E42200 361.000 FT SIGNAL CABLE, 2 CONDUCTOR, NO. 12 AWG 1.7025 1.8000 $649.80
632E42201 1,068.000 FT SIGNAL CABLE, 2 CONDUCTOR, NO. 12 AWG, 1.6811 1.3131 $1,402.40
AS PER PLAN
632E42500 1,491.000 FT SIGNAL CABLE, 5 CONDUCTOR, NO. 12 AWG 2.5029 2.7671 $4,125.80
632E42501 2,102.000 FT SIGNAL CABLE, 5 CONDUCTOR, NO. 12 AWG, 2.3754 1.9054 $4,005.20
AS PER PLAN
632E42700 4,510.000 FT SIGNAL CABLE, 7 CONDUCTOR, NO. 12 AWG 2.5680 2.7766 $12,522.28
632E42701 3,461.000 FT SIGNAL CABLE, 7 CONDUCTOR, NO. 12 AWG, 2.7474 2.3000 $7,960.30
AS PER PLAN
632E42900 1,513.000 FT SIGNAL CABLE, 9 CONDUCTOR, NO. 12 AWG 3.0366 3.7433 $5,663.65
632E43201 1,636.000 FT SIGNAL CABLE, 12 CONDUCTOR, NO. 12 AWG, 4.4833 3.9000 $6,380.40
AS PER PLAN
632E43300 1,854.000 FT SIGNAL CABLE, MISC.: 1.5892 1.0598 $1,964.94
632E53202 2,210.000 FT INTERCONNECT CABLE, 6 PAIR, NO. 19 AWG, 3.6312 3.3311 $7,361.75
SOLID, REA (PE-39)
632E53204 724.000 FT INTERCONNECT CABLE, 6 PAIR, NO. 19 AWG, 4.5000 4.0000 $2,896.00
SOLID, REA (PE-38)
632E62802 3,742.000 FT INTERCONNECT CABLE, INTEGRAL MESSENGER 3.5300 3.5900 $13,433.78
WIRE TYPE, 6 PAIR, NO. 19 AWG, SOLID, REA (PE-38)
632E62803 4,003.000 FT INTERCONNECT CABLE, INTEGRAL MESSENGER 4.3321 5.0405 $20,177.22
WIRE TYPE, 6 PAIR, NO. 19 AWG, SOLID, REA (PE-38), AS PER PLAN
632E62805 65.000 FT INTERCONNECT CABLE, INTEGRAL MESSENGER 3.5625 2.9500 $191.75
WIRE TYPE, 6 PAIR, NO. 19 AWG, SOLID, REA (PE-39), AS PER PLAN
632E62810 11,191.000 FT INTERCONNECT CABLE, MISC.: 1.7792 2.0789 $23,265.16
632E62820 18.000 EACH INTERCONNECT, MISC.: 2,456.6955 2,511.1111 $45,200.00
632E62830 3.000 LS INTERCONNECT, MISC.: 10,069.3533 11,710.0833 $35,130.25
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
165 | P a g e
632E63000 1.000 EACH PHONE DROP 654.0556 821.2500 $821.25
632E64000 106.000 EACH STRAIN POLE FOUNDATION 2,889.8174 2,547.4463 $270,029.31
632E64001 26.000 EACH STRAIN POLE FOUNDATION, AS PER PLAN 2,306.0483 2,350.4362 $61,111.34
632E64010 175.000 EACH SIGNAL SUPPORT FOUNDATION 3,038.3600 2,988.1199 $522,920.98
632E64011 152.000 EACH SIGNAL SUPPORT FOUNDATION, AS PER PLAN 2,902.4175 2,760.1143 $419,537.38
632E64020 190.000 EACH PEDESTAL FOUNDATION 676.1257 637.0098 $121,031.87
632E64021 62.000 EACH PEDESTAL FOUNDATION, AS PER PLAN 732.8161 711.1210 $44,089.50
632E65200 133,132.000 FT LOOP DETECTOR LEAD-IN CABLE 1.5197 1.4224 $189,368.31
632E65201 18,035.000 FT LOOP DETECTOR LEAD-IN CABLE, AS PER PLAN 1.6300 1.6100 $29,036.35
632E65202 2,000.000 FT LOOP DETECTOR LEAD-IN CABLE, INTEGRAL 4.7620 3.1500 $6,300.00
MESSENGER WIRE TYPE, NO. 14 AWG
632E65203 1,576.000 FT LOOP DETECTOR LEAD-IN CABLE, INTEGRAL 2.5014 2.1079 $3,322.00
MESSENGER WIRE TYPE, NO. 14 AWG, AS PER PLAN
632E65300 39,453.000 FT LOOP DETECTOR LEAD-IN CABLE, 2 1.3910 1.2317 $48,592.55
CONDUCTOR, NO. 14 AWG
632E65301 1,000.000 FT LOOP DETECTOR LEAD-IN CABLE, 2 1.8750 0.9000 $900.00
CONDUCTOR, NO. 14 AWG, AS PER PLAN
632E67190 530.000 FT POWER CABLE, 1 CONDUCTOR, NO. 8 AWG 1.5650 1.3500 $715.50
632E67200 1,907.000 FT POWER CABLE, 2 CONDUCTOR, NO. 8 AWG 2.9053 3.2056 $6,113.06
632E67201 495.000 FT POWER CABLE, 2 CONDUCTOR, NO. 8 AWG, AS 2.9307 2.6484 $1,310.95
PER PLAN
632E67300 2,689.000 FT POWER CABLE, 3 CONDUCTOR, NO. 8 AWG 3.6498 5.2432 $14,098.89
632E68100 2,020.000 FT POWER CABLE, 1 CONDUCTOR, NO. 6 AWG 2.3087 2.2599 $4,565.08
632E68200 4,080.000 FT POWER CABLE, 2 CONDUCTOR, NO. 6 AWG 2.8863 2.4151 $9,853.60
632E68201 2,797.000 FT POWER CABLE, 2 CONDUCTOR, NO. 6 AWG, AS 2.5392 1.2900 $3,608.00
PER PLAN
632E68300 16,641.000 FT POWER CABLE, 3 CONDUCTOR, NO. 6 AWG 3.8612 4.1200 $68,560.60
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
166 | P a g e
632E68301 310.000 FT POWER CABLE, 3 CONDUCTOR, NO. 6 AWG, AS 4.2508 3.6863 $1,142.75
PER PLAN
632E69200 308.000 FT POWER CABLE, 2 CONDUCTOR, NO. 4 AWG 3.3850 3.6000 $1,108.80
632E69201 196.000 FT POWER CABLE, 2 CONDUCTOR, NO. 4 AWG, AS 3.3340 3.3000 $646.80
PER PLAN
632E69300 864.000 FT POWER CABLE, 3 CONDUCTOR, NO. 4 AWG 4.9461 4.8077 $4,153.85
632E69350 3,737.000 FT POWER CABLE, MISC.: 1.5378 1.2646 $4,725.99
632E69400 665.000 FT SERVICE CABLE, 2 CONDUCTOR, NO. 8 AWG 3.3033 3.0000 $1,995.00
632E69500 1,157.000 FT SERVICE CABLE, 2 CONDUCTOR, NO. 6 AWG 3.2648 4.3210 $4,999.40
632E69700 207.000 FT SERVICE CABLE, 3 CONDUCTOR, NO. 8 AWG 3.6250 3.0000 $621.00
632E69800 6,168.000 FT SERVICE CABLE, 3 CONDUCTOR, NO. 6 AWG 3.5361 4.1503 $25,598.75
632E69900 72.000 FT SERVICE CABLE, 3 CONDUCTOR, NO. 4 AWG 3.9838 2.0000 $144.00
632E70000 19.000 EACH POWER SERVICE 1,421.7423 1,468.9474 $27,910.00
632E70001 133.000 EACH POWER SERVICE, AS PER PLAN 1,600.0281 1,450.7902 $192,955.10
632E70200 13.000 EACH CONDUIT RISER, 1" DIAMETER 217.8596 211.0769 $2,744.00
632E70300 50.000 EACH CONDUIT RISER, 1-1/2" DIAMETER 173.6374 71.8000 $3,590.00
632E70400 56.000 EACH CONDUIT RISER, 2" DIAMETER 426.0103 324.4714 $18,170.40
632E70401 23.000 EACH CONDUIT RISER, 2" DIAMETER, AS PER PLAN 496.8362 520.2757 $11,966.34
632E70600 8.000 EACH CONDUIT RISER, 3" DIAMETER 529.3913 637.0000 $5,096.00
632E75013 2.000 EACH SIGNAL SUPPORT, TYPE TC-81.21 DESIGN 3 6,665.9900 4,397.9700 $8,795.94
POLE, WITH MAST ARMS TC-81.21 DESIGN 2
AND DESIGN 1, AS PER PLAN
632E75042 1.000 EACH SIGNAL SUPPORT, TYPE TC-81.21 DESIGN 4 7,253.4000 7,400.0000 $7,400.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 3
AND DESIGN 2
632E75063 1.000 EACH SIGNAL SUPPORT, TYPE TC-81.21 DESIGN 11 8,265.4883 7,160.0000 $7,160.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 4
AND DESIGN 1, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
167 | P a g e
632E75113 1.000 EACH SIGNAL SUPPORT, TYPE TC-81.21 DESIGN 12 9,370.8367 9,512.5100 $9,512.51
POLE, WITH MAST ARMS TC-81.21 DESIGN 11
AND DESIGN 3, AS PER PLAN
632E75123 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 5 11,733.3333 11,600.0000 $11,600.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 4
AND DESIGN 4, AS PER PLAN
632E75163 2.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 5 10,462.1600 9,700.0000 $19,400.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 12
AND DESIGN 3, AS PER PLAN
632E75172 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 6 10,838.1657 10,250.0000 $10,250.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 11
AND DESIGN 11
632E75173 3.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 6 13,389.3660 13,641.6667 $40,925.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 11
AND DESIGN 11, AS PER PLAN
632E75193 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 6 13,982.5383 14,400.0000 $14,400.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 12
AND DESIGN 11, AS PER PLAN
632E75208 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 7 14,874.9500 15,235.0000 $15,235.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 13
AND DESIGN 3
632E75209 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 7 14,688.0967 14,325.0000 $14,325.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 13
AND DESIGN 3, AS PER PLAN
632E75410 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 8 14,933.3333 16,000.0000 $16,000.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 13
AND DESIGN 11
632E75411 2.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 8 16,797.8567 15,850.0000 $31,700.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 13
AND DESIGN 11, AS PER PLAN
632E75450 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 9 14,473.5000 13,560.0000 $13,560.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 13
AND DESIGN 12
632E75464 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 9 16,425.6583 14,400.0000 $14,400.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 14
AND DESIGN 3
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
168 | P a g e
632E75480 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 10 16,611.8350 14,750.0000 $14,750.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 14
AND DESIGN 11
632E75481 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 10 19,065.6800 18,430.0000 $18,430.00
POLE, WITH MAST ARMS TC-81.21 DESIGN 14
AND DESIGN 11, AS PER PLAN
632E75484 1.000 EACH SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 10 16,219.7000 19,165.6000 $19,165.60
POLE, WITH MAST ARMS TC-81.21 DESIGN 14
AND DESIGN 12
632E76401 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 16,243.7500 15,550.0000 $15,550.00
TC-12.30 DESIGN 8 POLE, WITH MAST ARMS
TC-81.21 DESIGN 13 AND DESIGN 4, AS PER PLAN
632E77023 2.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 8,911.9367 11,500.0000 $23,000.00
TC-81.21 DESIGN 4 POLE, WITH MAST ARMS
TC-81.21 DESIGN 2 AND DESIGN 2, AS PER PLAN
632E77043 1.000 EACH COMBINATION SIGNAL SUPPORT, TC-81.21, 8,713.9275 9,040.0000 $9,040.00
DESIGN 4 POLE, WITH MAST ARMS TC-81.21
DESIGN 3 AND DESIGN 2, AS PER PLAN
632E77113 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 12,206.6233 14,500.0000 $14,500.00
TC-81.21 DESIGN 12 POLE, WITH MAST ARMS
TC-81.21 DESIGN 11 AND DESIGN 3, AS PER
PLAN
632E77196 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 17,050.0000 14,975.0000 $14,975.00
TC-12.30 DESIGN 7 POLE, WITH MAST ARMS
TC-81.21 DESIGN 11 AND DESIGN 12
632E77203 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 17,385.6350 16,000.0000 $16,000.00
TC-12.30 DESIGN 7 POLE, WITH MAST ARMS
TC-81.21 DESIGN 12 AND DESIGN 12, AS PER PLAN
632E77210 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 18,440.0000 17,400.0000 $17,400.00
TC-12.30 DESIGN 11 POLE, WITH MAST ARMS
TC-81.21 DESIGN 14 AND DESIGN 13
632E77230 11.000 EACH SIGNAL SUPPORT, MECHANICAL DAMPER FOR 780.8660 637.2727 $7,010.00
TC-81.21 MAST ARM (GREATER THAN 59' IN
LENGTH)
632E77231 1.000 EACH SIGNAL SUPPORT, MECHANICAL DAMPER FOR 1,225.5233 1,400.0000 $1,400.00
TC-81.21 MAST ARM (GREATER THAN 59' IN
LENGTH), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
169 | P a g e
632E80102 4.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 1 5,850.9329 4,944.0000 $19,776.00
632E80103 9.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 1, 5,043.6332 4,426.5844 $39,839.26
AS PER PLAN
632E80202 10.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 2 5,596.1273 4,342.0000 $43,420.00
632E80203 19.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 2, 4,631.3885 4,453.3084 $84,612.86
AS PER PLAN
632E80302 17.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 3 4,329.7426 3,427.7176 $58,271.20
632E80303 19.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 3, 5,803.4866 5,832.3368 $110,814.40
AS PER PLAN
632E80402 4.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 4 5,944.5353 5,962.5000 $23,850.00
632E80403 16.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 4, 5,978.4119 5,623.9931 $89,983.89
AS PER PLAN
632E80502 7.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 11 7,135.6939 6,028.6000 $42,200.20
632E80503 22.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 7,865.6765 7,586.4291 $166,901.44
11, AS PER PLAN
632E80602 2.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 12 7,810.1800 7,390.4500 $14,780.90
632E80603 15.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 8,442.9536 8,420.8093 $126,312.14
12, AS PER PLAN
632E80620 11.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 13 9,191.8149 8,963.6727 $98,600.40
632E80621 16.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 10,605.8253 10,532.3381 $168,517.41
13, AS PER PLAN
632E80628 5.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 14 10,520.7350 10,447.3400 $52,236.70
632E80629 15.000 EACH SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 12,292.2364 12,196.4667 $182,947.00
14, AS PER PLAN
632E80700 25.000 EACH SIGNAL SUPPORT, MISC.: 2,024.0038 2,435.7920 $60,894.80
632E80970 4.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 6,001.4167 5,500.0000 $22,000.00
TC-81.21, DESIGN 1
632E80971 2.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 10,270.5833 8,000.0000 $16,000.00
TC-81.21, DESIGN 1, AS PER PLAN
632E80980 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 5,034.6000 4,819.0000 $4,819.00
TC-81.21, DESIGN 2
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
170 | P a g e
632E80990 5.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 5,148.1231 5,050.8000 $25,254.00
TC-81.21, DESIGN 3
632E80991 2.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 7,000.1000 6,289.0000 $12,578.00
TC-81.21, DESIGN 3, AS PER PLAN
632E81000 2.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 6,172.5000 5,950.0000 $11,900.00
TC-81.21, DESIGN 4
632E81001 8.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 8,563.5382 7,520.1875 $60,161.50
TC-81.21, DESIGN 4, AS PER PLAN
632E81070 2.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 10,347.8000 10,675.0000 $21,350.00
TC-81.21, DESIGN 11
632E81071 11.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 9,477.5488 8,938.6364 $98,325.00
TC-81.21, DESIGN 11, AS PER PLAN
632E81080 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 7,664.3686 8,600.0000 $8,600.00
TC-81.21, DESIGN 12
632E81081 4.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 10,550.3433 9,987.7500 $39,951.00
TC-81.21, DESIGN 12, AS PER PLAN
632E81091 11.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 13,482.9430 12,987.3455 $142,860.80
TC-81.21, DESIGN 13, AS PER PLAN
632E81094 1.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 12,080.2000 13,800.0000 $13,800.00
TC-81.21, DESIGN 14
632E81095 4.000 EACH COMBINATION SIGNAL SUPPORT, TYPE 14,919.9385 13,696.8250 $54,787.30
TC-81.21, DESIGN 14, AS PER PLAN
632E81700 10.000 EACH COMBINATION SIGNAL SUPPORT, MISC.: 7,167.4444 8,738.5000 $87,385.00
632E82100 3.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 1 2,204.7429 2,227.9300 $6,683.79
632E82101 6.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 1, AS 4,994.7561 4,721.5650 $28,329.39
PER PLAN
632E82500 2.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 5 2,500.0000 1,650.0000 $3,300.00
632E82600 3.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 6 3,661.0556 3,293.3333 $9,880.00
632E82601 2.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 6, AS 3,905.2813 3,485.0000 $6,970.00
PER PLAN
632E82700 1.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 7 3,587.5000 3,525.0000 $3,525.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
171 | P a g e
632E82701 12.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 7, AS 4,735.0000 5,121.2100 $61,454.52
PER PLAN
632E82801 2.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 8, AS 4,267.7700 3,625.0000 $7,250.00
PER PLAN
632E82900 2.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 9 3,432.5000 2,312.5000 $4,625.00
632E82901 2.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 9, AS 4,541.7160 4,341.1000 $8,682.20
PER PLAN
632E83000 29.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 10 4,872.9576 4,577.4138 $132,745.00
632E83001 4.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 10, 5,830.6318 5,575.0000 $22,300.00
AS PER PLAN
632E83100 5.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 11 5,511.5789 5,464.0000 $27,320.00
632E83101 4.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 11, 5,976.2540 5,650.0000 $22,600.00
AS PER PLAN
632E83200 18.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 12 6,214.3425 6,191.1111 $111,440.00
632E83201 32.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 12, 6,438.6165 6,272.5000 $200,720.00
AS PER PLAN
632E83300 8.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 13 9,671.4624 5,675.0000 $45,400.00
632E83301 5.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 13, 13,895.8200 13,769.0000 $68,845.00
AS PER PLAN
632E83401 1.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 14, 15,170.3225 15,944.4100 $15,944.41
AS PER PLAN
632E83507 1.000 EACH STRAIN POLE, TYPE TC-81.10, DESIGN 10, 680.5850 510.0000 $510.00
INSTALLATION ONLY, AS PER PLAN
632E84700 2.000 EACH COMBINATION STRAIN POLE, TYPE TC-81.10, 5,200.0000 5,100.0000 $10,200.00
DESIGN 7
632E85000 2.000 EACH COMBINATION STRAIN POLE, TYPE TC-81.10, 5,250.0000 5,200.0000 $10,400.00
DESIGN 10
632E85100 1.000 EACH COMBINATION STRAIN POLE, TYPE TC-81.10, 5,716.6667 5,700.0000 $5,700.00
DESIGN 11
632E85200 3.000 EACH COMBINATION STRAIN POLE, TYPE TC-81.10, 6,682.9882 6,950.0000 $20,850.00
DESIGN 12
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
172 | P a g e
632E85321 4.000 EACH COMBINATION STRAIN POLE, TYPE TC-81.10, 13,809.0829 13,713.9950 $54,855.98
DESIGN 13, AS PER PLAN
632E85401 3.000 EACH COMBINATION STRAIN POLE, TYPE TC-81.10, 15,552.7675 16,209.3600 $48,628.08
DESIGN 14, AS PER PLAN
632E89251 13.000 EACH POLE ENTRANCE FITTING, AS PER PLAN 132.8000 25.0000 $325.00
632E89300 19.000 EACH WOOD POLE 1,418.2309 1,353.7347 $25,720.96
632E89301 9.000 EACH WOOD POLE, AS PER PLAN 1,101.2155 939.4444 $8,455.00
632E89400 14.000 EACH DOWN GUY 499.8121 571.0714 $7,995.00
632E89401 2.000 EACH DOWN GUY, AS PER PLAN 554.7380 565.0000 $1,130.00
632E89500 1.000 EACH PEDESTAL, 3' 374.3750 425.0000 $425.00
632E89600 15.000 EACH PEDESTAL, 8' 534.4274 518.3333 $7,775.00
632E89601 15.000 EACH PEDESTAL, 8', AS PER PLAN 853.4525 959.0400 $14,385.60
632E89610 2.000 EACH PEDESTAL, 9' 511.4100 370.0000 $740.00
632E89700 11.000 EACH PEDESTAL, 11' 710.5786 561.3636 $6,175.00
632E89701 26.000 EACH PEDESTAL, 11', AS PER PLAN 1,469.0569 1,923.0769 $50,000.00
632E89802 5.000 EACH PEDESTAL, 5', TRANSFORMER BASE 546.3462 641.0000 $3,205.00
632E89803 7.000 EACH PEDESTAL, 5', TRANSFORMER BASE, AS PER 538.7212 669.7629 $4,688.34
PLAN
632E89805 2.000 EACH PEDESTAL, 7', TRANSFORMER BASE, AS PER 579.7375 525.0000 $1,050.00
PLAN
632E89806 2.000 EACH PEDESTAL, 6', TRANSFORMER BASE 487.4000 300.0000 $600.00
632E89807 1.000 EACH PEDESTAL, 6', TRANSFORMER BASE, AS PER 772.1817 770.0000 $770.00
PLAN
632E89900 41.000 EACH PEDESTAL, 8', TRANSFORMER BASE 801.0327 577.8639 $23,692.42
632E89901 40.000 EACH PEDESTAL, 8', TRANSFORMER BASE, AS PER 807.1852 816.1500 $32,646.00
PLAN
632E89904 19.000 EACH PEDESTAL, 10', TRANSFORMER BASE 598.1493 571.3842 $10,856.30
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
173 | P a g e
632E89905 5.000 EACH PEDESTAL, 10', TRANSFORMER BASE, AS PER 1,620.2982 1,810.8400 $9,054.20
PLAN
632E90000 4.000 EACH PEDESTAL, 11', TRANSFORMER BASE 652.8971 710.0000 $2,840.00
632E90001 15.000 EACH PEDESTAL, 11', TRANSFORMER BASE, AS PER 752.7814 676.0000 $10,140.00
PLAN
632E90010 23.000 EACH PEDESTAL, MISC.: 1,095.7366 1,161.0591 $26,704.36
632E90020 178.000 EACH REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL 138.7461 132.5778 $23,598.85
ITEM
632E90030 12,920.000 FT REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL 0.7242 0.2322 $3,000.00
ITEM
632E90100 35.000 EACH REMOVAL OF TRAFFIC SIGNAL INSTALLATION 1,716.9803 1,237.5229 $43,313.30
632E90101 121.000 EACH REMOVAL OF TRAFFIC SIGNAL INSTALLATION, 2,410.9344 2,577.3800 $311,862.98
AS PER PLAN
632E90103 6.000 EACH REMOVAL OF TRAFFIC SIGNAL INSTALLATION 2,548.3388 2,250.0000 $13,500.00
FOR STORAGE, AS PER PLAN
632E90104 15.000 EACH REUSE OF TRAFFIC CONTROL ITEM 1,398.8529 1,036.7020 $15,550.53
632E90200 136.000 EACH REUSE OF VEHICULAR SIGNAL HEAD 263.7440 132.9779 $18,085.00
632E90201 6.000 EACH REUSE OF VEHICULAR SIGNAL HEAD, AS PER 381.4500 323.4433 $1,940.66
PLAN
632E90204 10.000 EACH REUSE OF LOOP DETECTOR UNIT 22.5000 10.0000 $100.00
632E90206 7.000 EACH REUSE OF SIGNAL SUPPORT 1,605.9180 415.7143 $2,910.00
632E90210 8.000 EACH REUSE OF PEDESTRIAN PUSHBUTTON 100.5420 57.0000 $456.00
632E90212 6.000 EACH REUSE OF CONTROLLER 1,519.8750 1,025.0000 $6,150.00
632E90213 3.000 EACH REUSE OF CONTROLLER, AS PER PLAN 1,920.9257 2,534.4333 $7,603.30
632E90300 11.000 LS SIGNALIZATION, MISC.: 68,745.1598 51,417.4164 $565,591.58
632E90400 459.000 EACH SIGNALIZATION, MISC.: 1,675.7132 1,753.5324 $804,871.36
632E90500 18,932.000 FT SIGNALIZATION, MISC.: 3.8076 3.1637 $59,894.75
632E99000 6.000 LS SPECIAL - TRAFFIC SIGNALS 329,341.0575 342,369.3033 $2,054,215.82
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
174 | P a g e
633E01501 5.000 EACH CONTROLLER UNIT, TYPE TS2/A1, WITH 14,693.8057 14,653.3500 $73,266.75
CABINET, TYPE TS2, AS PER PLAN
633E01541 2.000 EACH CONTROLLER UNIT, TYPE TS2/A2, AS PER 3,556.3564 3,087.5000 $6,175.00
PLAN
633E01551 60.000 EACH CONTROLLER UNIT, TYPE TS2/A2, WITH 16,109.4978 15,583.9117 $935,034.70
CABINET, TYPE TS2, AS PER PLAN
633E01580 1.000 EACH CONTROLLER UNIT, TYPE TS2/A2, WITH 11,300.0000 11,300.0000 $11,300.00
CABINET, TYPE TS1
633E01581 34.000 EACH CONTROLLER UNIT, TYPE TS2/A2, WITH 9,732.0128 10,562.7059 $359,132.00
CABINET, TYPE TS1, AS PER PLAN
633E01601 3.000 EACH CONTROLLER UNIT, TYPE 170E, WITH 17,631.1000 17,050.0000 $51,150.00
CABINET, TYPE 332, AS PER PLAN
633E01660 1.000 EACH CONTROLLER UNIT, TYPE 2070E, WITH 10,310.0000 10,500.0000 $10,500.00
CABINET, TYPE 332
633E01681 36.000 EACH CONTROLLER UNIT, TYPE 2070L, WITH 10,966.8302 10,326.5294 $351,102.00
CABINET, TYPE 332, AS PER PLAN
633E01691 1.000 EACH CONTROLLER UNIT, TYPE 2070L, AS PER PLAN 6,380.4000 5,150.0000 $5,150.00
633E01701 3.000 EACH CONTROLLER UNIT, TYPE 2070L, WITH 10,064.0100 9,508.3333 $28,525.00
CABINET, TYPE 336, AS PER PLAN
633E01831 2.000 EACH CONTROLLER UNIT, TYPE TS2/A2, FURNISH 4,733.9400 4,800.0000 $9,600.00
ONLY, AS PER PLAN
633E39000 2.000 EACH CONTROLLER, MASTER, TRAFFIC RESPONSIVE 4,559.8453 4,875.0000 $9,750.00
633E39001 2.000 EACH CONTROLLER, MASTER, TRAFFIC RESPONSIVE, 6,815.0814 5,511.5200 $11,023.04
AS PER PLAN
633E65001 12.000 EACH CABINET WITHOUT CONTROLLER, AS PER PLAN 6,204.6602 6,421.9800 $77,063.76
633E65501 2.000 EACH CABINET, TYPE TS-1, AS PER PLAN 7,777.2125 7,850.0000 $15,700.00
633E67000 107.000 EACH CABINET RISER 482.4982 431.7367 $46,195.83
633E67001 16.000 EACH CABINET RISER, AS PER PLAN 405.9968 400.0000 $6,400.00
633E67100 137.000 EACH CABINET FOUNDATION 1,384.2734 1,379.6992 $189,018.79
633E67101 53.000 EACH CABINET FOUNDATION, AS PER PLAN 1,602.7655 1,430.4040 $75,811.41
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
175 | P a g e
633E67200 158.000 EACH CONTROLLER WORK PAD 318.5254 219.6722 $34,708.21
633E67201 41.000 EACH CONTROLLER WORK PAD, AS PER PLAN 453.2983 406.3966 $16,662.26
633E67300 4.000 EACH PREEMPTION 384.1111 350.0000 $1,400.00
633E67301 7.000 EACH PREEMPTION, AS PER PLAN 750.5429 755.0000 $5,285.00
633E67310 12.000 EACH PREEMPTION RECEIVING UNIT 548.8889 435.0000 $5,220.00
633E67311 23.000 EACH PREEMPTION RECEIVING UNIT, AS PER PLAN 777.4574 701.8804 $16,143.25
633E67320 2,347.000 FT PREEMPTION DETECTOR CABLE 1.7538 1.3729 $3,222.20
633E67321 4,038.000 FT PREEMPTION DETECTOR CABLE, AS PER PLAN 1.9033 1.5135 $6,111.44
633E67350 4.000 EACH PREEMPTION PHASE SELECTOR 1,627.1111 1,300.0000 $5,200.00
633E67351 7.000 EACH PREEMPTION PHASE SELECTOR, AS PER PLAN 2,964.7300 2,576.9429 $18,038.60
633E67400 8.000 EACH PREEMPTION CONFIRMATION LIGHT 241.7910 150.6250 $1,205.00
633E67401 19.000 EACH PREEMPTION CONFIRMATION LIGHT, AS PER 632.3206 541.7132 $10,292.55
PLAN
633E67501 128.000 EACH UNINTERRUPTIBLE POWER SUPPLY (UPS), 1,267.1188 1,085.2109 $138,907.00
BATTERY REPLACEMENT, AS PER PLAN
633E68001 3.000 EACH REMOTE MONITORING STATION, AS PER PLAN 15,316.6370 14,466.6667 $43,400.00
633E68501 1.000 EACH TELEPHONE SERVICE, AS PER PLAN 2,446.9100 1,470.0000 $1,470.00
633E69000 70.000 EACH TIME SWITCH 7,283.2742 7,123.2766 $498,629.36
633E69100 66.000 EACH TIME SWITCH, SOLID STATE DIGITAL 6,392.9259 6,449.8727 $425,691.60
633E69101 1.000 EACH TIME SWITCH, SOLID STATE DIGITAL, AS PER 3,806.5620 3,800.0000 $3,800.00
PLAN
633E71000 4.000 EACH FLASHER CONTROLLER 750.2813 550.0000 $2,200.00
633E72000 1.000 LS TRAINING 2,250.6667 2,500.0000 $2,500.00
633E72500 2.000 LS SYSTEM ANALYSIS 10,082.8313 10,200.0000 $20,400.00
633E72501 1.000 LS SYSTEM ANALYSIS, AS PER PLAN 18,820.0000 23,100.0000 $23,100.00
633E74000 5.000 EACH UNINTERRUPTIBLE POWER SUPPLY (UPS) 4,041.4992 4,860.0000 $24,300.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
176 | P a g e
633E74001 33.000 EACH UNINTERRUPTIBLE POWER SUPPLY (UPS), AS 4,351.5544 3,724.2424 $122,900.00
PER PLAN
633E75000 11.000 EACH UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 4,658.8200 4,059.9200 $44,659.12
WATT
633E75001 158.000 EACH UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 4,419.4217 4,277.8101 $675,894.00
WATT, AS PER PLAN
633E99000 297.000 EACH CONTROLLER ITEM, MISC.: 3,525.8995 4,014.0223 $1,192,164.62
633E99100 2,760.000 FT CONTROLLER ITEM, MISC.: 1.9033 1.7276 $4,768.08
633E99300 4.000 LS CONTROLLER ITEM, MISC.: 10,401.9814 9,735.0000 $38,940.00
638E00390 315.000 FT 4" WATER MAIN POLYVINYL CHLORIDE PIPE 43.3400 15.8700 $4,999.05
FITTINGS
638E00600 220.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 75.4167 48.0000 $10,560.00
CLASS 52, PUSH-ON JOINTS AND FITTINGS
638E00601 842.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 110.8567 78.0000 $65,676.00
CLASS 52, PUSH-ON JOINTS AND FITTINGS,
AS PER PLAN
638E00700 180.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 252.0135 223.5288 $40,235.18
CLASS 52, MECHANICAL JOINTS AND FITTINGS
638E00701 81.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 276.6000 400.0000 $32,400.00
CLASS 52, MECHANICAL JOINTS AND
FITTINGS, AS PER PLAN
638E00800 1,137.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 90.3000 95.0000 $108,015.00
CLASS 52, BOLTLESS-RESTRAINED JOINTS AND
FITTINGS
638E00801 82.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 175.0000 175.0000 $14,350.00
CLASS 52, BOLTLESS-RESTRAINED JOINTS AND
FITTINGS, AS PER PLAN
638E00805 132.000 FT 6" WATER MAIN DUCTILE IRON PIPE ANSI 155.0000 150.0000 $19,800.00
CLASS 53, BOLTLESS-RESTRAINED JOINTS AND
FITTINGS, AS PER PLAN
638E01100 185.000 FT 6" WATER MAIN POLYVINYL CHLORIDE PIPE 119.2056 77.7622 $14,386.00
AND FITTINGS, AWWA CLASS 150
638E01101 53.000 FT 6" WATER MAIN POLYVINYL CHLORIDE PIPE 122.2320 175.0000 $9,275.00
AND FITTINGS, AWWA CLASS 150, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
177 | P a g e
638E01200 300.000 FT 8" WATER MAIN DUCTILE IRON PIPE ANSI 79.0000 100.0000 $30,000.00
CLASS 52, PUSH-ON JOINTS AND FITTINGS
638E01201 3,381.000 FT 8" WATER MAIN DUCTILE IRON PIPE ANSI 77.6817 65.0000 $219,765.00
CLASS 52, PUSH-ON JOINTS AND FITTINGS, AS PER PLAN
638E01300 97.000 FT 8" WATER MAIN DUCTILE IRON PIPE ANSI 234.4167 267.8789 $25,984.25
CLASS 52, MECHANICAL JOINTS AND FITTINGS
638E01301 175.000 FT 8" WATER MAIN DUCTILE IRON PIPE ANSI 94.6260 120.0000 $21,000.00
CLASS 52, MECHANICAL JOINTS AND FITTINGS, AS PER PLAN
638E01400 72.000 FT 8" WATER MAIN DUCTILE IRON PIPE ANSI 129.6000 81.0000 $5,832.00
CLASS 52, BOLTLESS-RESTRAINED JOINTS AND FITTINGS
638E01701 4,196.000 FT 8" WATER MAIN POLYVINYL CHLORIDE PIPE 62.0750 48.8423 $204,942.30
AND FITTINGS, AWWA CLASS 150, AS PER PLAN
638E01801 748.000 FT 10" WATER MAIN DUCTILE IRON PIPE ANSI 130.5933 135.0000 $100,980.00
CLASS 52, PUSH-ON JOINTS AND FITTINGS, AS PER PLAN
638E01900 18.000 FT 10" WATER MAIN DUCTILE IRON PIPE ANSI 140.0000 140.0000 $2,520.00
CLASS 52, MECHANICAL JOINTS AND FITTINGS
638E02000 1,336.000 FT 10" WATER MAIN DUCTILE IRON PIPE ANSI 139.4000 125.0000 $167,000.00
CLASS 52, BOLTLESS-RESTRAINED JOINTS AND FITTINGS
638E02404 545.000 FT 12" WATER MAIN DUCTILE IRON PIPE ANSI 99.1250 120.5000 $65,672.50
CLASS 53, PUSH-ON JOINTS AND FITTINGS
638E02500 27.000 FT 12" WATER MAIN DUCTILE IRON PIPE ANSI 441.0367 402.7900 $10,875.33
CLASS 52, MECHANICAL JOINTS AND FITTINGS
638E02501 114.000 FT 12" WATER MAIN DUCTILE IRON PIPE ANSI 189.3275 132.3100 $15,083.34
CLASS 52, MECHANICAL JOINTS AND FITTINGS, AS PER PLAN
638E02600 341.000 FT 12" WATER MAIN DUCTILE IRON PIPE ANSI 262.0000 250.0000 $85,250.00
CLASS 52, BOLTLESS-RESTRAINED JOINTS AND FITTINGS
638E02604 120.000 FT 12" WATER MAIN DUCTILE IRON PIPE ANSI 88.5000 87.0000 $10,440.00
CLASS 53, BOLTLESS-RESTRAINED JOINTS AND FITTINGS
638E03004 461.000 FT 16" WATER MAIN DUCTILE IRON PIPE ANSI 122.1250 137.0000 $63,157.00
CLASS 53, PUSH-ON JOINTS AND FITTINGS
638E03204 120.000 FT 16" WATER MAIN DUCTILE IRON PIPE ANSI 117.7500 114.0000 $13,680.00
CLASS 53, BOLTLESS-RESTRAINED JOINTS AND FITTINGS
638E04800 714.000 FT 3/4" COPPER SERVICE BRANCH 39.6228 26.8711 $19,186.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
178 | P a g e
638E04801 792.000 FT 3/4" COPPER SERVICE BRANCH, AS PER PLAN 31.6717 30.0000 $23,760.00
638E04900 880.000 FT 1" COPPER SERVICE BRANCH 34.3487 28.4091 $25,000.00
638E04951 167.000 FT 1-1/4" COPPER SERVICE BRANCH, AS PER 53.1120 39.5600 $6,606.52
PLAN
638E05000 100.000 FT 1-1/2" COPPER SERVICE BRANCH 57.6300 24.0000 $2,400.00
638E05100 533.000 FT 2" COPPER SERVICE BRANCH 52.2000 40.0000 $21,320.00
638E05101 947.000 FT 2" COPPER SERVICE BRANCH, AS PER PLAN 52.8317 43.0000 $40,721.00
638E05300 400.000 FT 3/4" POLYETHYLENE SERVICE BRANCH 33.6400 15.0000 $6,000.00
638E05400 526.000 FT 1" POLYETHYLENE SERVICE BRANCH 45.0254 36.7985 $19,356.00
638E05401 1,987.000 FT 1" POLYETHYLENE SERVICE BRANCH, AS PER 36.3940 40.0000 $79,480.00
PLAN
638E05501 57.000 FT 1-1/2" POLYETHYLENE SERVICE BRANCH, AS 49.7540 41.0000 $2,337.00
PER PLAN
638E06600 60.000 FT 14" STEEL PIPE ENCASEMENT, OPEN CUT 103.4000 100.0000 $6,000.00
638E06700 177.000 FT 16" STEEL PIPE ENCASEMENT, OPEN CUT 105.9688 64.0000 $11,328.00
638E06701 101.000 FT 16" STEEL PIPE ENCASEMENT, OPEN CUT, AS 136.0705 134.1089 $13,545.00
PER PLAN
638E07301 56.000 FT 16" STEEL PIPE ENCASEMENT, BORED OR 346.6660 258.0000 $14,448.00
JACKED, AS PER PLAN
638E07311 104.000 FT 24" STEEL PIPE ENCASEMENT, BORED OR 392.6667 490.0000 $50,960.00
JACKED, AS PER PLAN
638E07480 3.000 EACH 6" GATE VALVE 1,371.0225 1,466.6667 $4,400.00
638E07481 1.000 EACH 6" GATE VALVE, AS PER PLAN 1,219.0000 1,000.0000 $1,000.00
638E07490 11.000 EACH 8" GATE VALVE 1,827.7250 2,260.0000 $24,860.00
638E07491 1.000 EACH 8" GATE VALVE, AS PER PLAN 1,141.6667 1,025.0000 $1,025.00
638E07608 10.000 EACH VALVE BOX 229.7875 229.0000 $2,290.00
638E07690 2.000 EACH 2" GATE VALVE BOX AND VALVE BOX 581.7400 614.0000 $1,228.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
179 | P a g e
638E07691 11.000 EACH 2" GATE VALVE AND VALVE BOX, AS PER PLAN 783.5367 815.0000 $8,965.00
638E07800 19.000 EACH 6" GATE VALVE AND VALVE BOX 1,350.4025 2,025.5263 $38,485.00
638E07801 9.000 EACH 6" GATE VALVE AND VALVE BOX, AS PER PLAN 1,201.8704 1,096.6667 $9,870.00
638E07900 23.000 EACH 8" GATE VALVE AND VALVE BOX 1,354.6786 1,328.2609 $30,550.00
638E07901 6.000 EACH 8" GATE VALVE AND VALVE BOX, AS PER PLAN 1,935.1175 1,937.9300 $11,627.58
638E08000 2.000 EACH 10" GATE VALVE AND VALVE BOX 2,658.2444 3,000.0000 $6,000.00
638E08001 3.000 EACH 10" GATE VALVE AND VALVE BOX, AS PER 2,357.2692 2,733.3333 $8,200.00
PLAN
638E08100 2.000 EACH 12" GATE VALVE AND VALVE BOX 2,660.0000 2,500.0000 $5,000.00
638E08101 1.000 EACH 12" GATE VALVE AND VALVE BOX, AS PER 3,173.0000 3,050.0000 $3,050.00
PLAN
638E08102 2.000 EACH 16" GATE VALVE AND VALVE BOX 7,420.7500 6,950.0000 $13,900.00
638E08621 1.000 EACH 12" INSERTING VALVE AND VALVE BOX, AS 11,060.0000 8,500.0000 $8,500.00
PER PLAN
638E08710 1.000 EACH 12" CUTTING-IN SLEEVE 3,880.0000 800.0000 $800.00
638E08901 1.000 EACH 6" CUTTING-IN SLEEVE, VALVE AND VALVE 3,400.0000 2,500.0000 $2,500.00
BOX, AS PER PLAN
638E09100 1.000 EACH 10" CUTTING-IN SLEEVE, VALVE AND VALVE 5,330.0000 2,500.0000 $2,500.00
BOX
638E09200 2.000 EACH 12" CUTTING-IN SLEEVE, VALVE AND VALVE 5,960.0000 3,500.0000 $7,000.00
BOX
638E09201 2.000 EACH 12" CUTTING-IN SLEEVE, VALVE AND VALVE 5,450.0000 4,500.0000 $9,000.00
BOX, AS PER PLAN
638E09400 3.000 EACH 8" X 8" TAPPING SLEEVE, VALVE AND VALVE 3,162.1406 3,900.0000 $11,700.00
BOX
638E09500 2.000 EACH 10" X 4" TAPPING SLEEVE, VALVE AND VALVE 3,381.2500 3,000.0000 $6,000.00
BOX
638E10200 11.000 EACH 6" FIRE HYDRANT 3,361.6204 3,727.2727 $41,000.00
638E10201 10.000 EACH 6" FIRE HYDRANT, AS PER PLAN 5,074.0098 6,142.5000 $61,425.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
180 | P a g e
638E10300 10.000 EACH FIRE HYDRANT EXTENDED AND ADJUSTED TO 2,084.9067 2,528.7000 $25,287.00
GRADE
638E10400 10.000 EACH FIRE HYDRANT ADJUSTED TO GRADE 882.7612 1,051.4260 $10,514.26
638E10401 3.000 EACH FIRE HYDRANT ADJUSTED TO GRADE, AS PER 899.2827 833.3333 $2,500.00
PLAN
638E10480 12.000 EACH FIRE HYDRANT REMOVED 433.7428 630.8933 $7,570.72
638E10481 2.000 EACH FIRE HYDRANT REMOVED, AS PER PLAN 405.0000 115.0000 $230.00
638E10500 19.000 EACH FIRE HYDRANT REMOVED AND RESET 2,301.1686 2,314.1984 $43,969.77
638E10600 2.000 EACH FIRE HYDRANT AND GATE VALVE REMOVED AND 1,494.7633 1,369.0000 $2,738.00
RESET
638E10601 34.000 EACH FIRE HYDRANT AND GATE VALVE REMOVED AND 1,945.0811 2,200.0000 $74,800.00
RESET, AS PER PLAN
638E10700 3.000 EACH FIRE HYDRANT REMOVED AND DISPOSED OF 708.7479 510.0000 $1,530.00
638E10701 13.000 EACH FIRE HYDRANT REMOVED AND DISPOSED OF, AS 468.2500 325.0000 $4,225.00
PER PLAN
638E10800 1,246.000 EACH VALVE BOX ADJUSTED TO GRADE 248.7365 250.9002 $312,621.67
638E10801 315.000 EACH VALVE BOX ADJUSTED TO GRADE, AS PER PLAN 327.0160 259.9206 $81,875.00
638E10900 202.000 EACH SERVICE BOX ADJUSTED TO GRADE 129.4275 165.2108 $33,372.59
638E10901 37.000 EACH SERVICE BOX ADJUSTED TO GRADE, AS PER 291.4702 237.1622 $8,775.00
PLAN
638E11100 43.000 EACH METER AND CHAMBER REMOVED AND RESET 1,169.3929 1,027.9774 $44,203.03
638E11101 1.000 EACH METER AND CHAMBER REMOVED AND RESET, AS 2,575.5033 2,400.0000 $2,400.00
PER PLAN
638E11103 1.000 EACH METER AND VAULT REMOVED AND RESET, AS 5,194.3150 3,900.0000 $3,900.00
PER PLAN
638E11200 10.000 EACH METER, SETTING, STOP AND CHAMBER 1,598.0000 1,200.0000 $12,000.00
638E11201 2.000 EACH METER, SETTING, STOP AND CHAMBER, AS PER 3,696.1117 4,000.0000 $8,000.00
PLAN
638E11301 2.000 EACH 1" AIR RELEASE VALVE, AS PER PLAN 1,082.8900 1,080.0000 $2,160.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
181 | P a g e
638E11310 2.000 EACH 2" AIR RELEASE VALVE 1,287.5000 1,450.0000 $2,900.00
638E11500 2.000 MBF SHEETING AND BRACING ORDERED LEFT IN PLACE 1,859.0321 502.5000 $1,005.00
638E20306 821.000 FT SPECIAL - 8" WATER MAIN DUCTILE IRON 121.8148 122.5579 $100,620.00
PIPE WITH PUSH-ON JOINTS AND RETAINED
MECHANICAL JOINT FITTINGS, ANSI CLASS 52
638E20600 10.000 FT SPECIAL - 10" WATER MAIN DUCTILE IRON 266.7340 210.0000 $2,100.00
PIPE WITH PUSH-ON JOINTS AND RETAINED
MECHANICAL JOINT FITTINGS, ANSI CLASS 52
638E20906 805.000 FT SPECIAL - 12" WATER MAIN DUCTILE IRON 133.3980 125.0000 $100,625.00
PIPE WITH PUSH-ON JOINTS AND RETAINED
MECHANICAL JOINT FITTINGS, ANSI CLASS 52
638E21108 208.000 FT SPECIAL - 16" WATER MAIN DUCTILE IRON 368.7625 322.0000 $66,976.00
PIPE WITH PUSH-ON JOINTS AND RETAINED
MECHANICAL JOINT FITTINGS, ANSI CLASS 52
638E22804 20.000 FT SPECIAL - 16" STEEL CASING PIPE 222.6125 500.0000 $10,000.00
638E22900 13.000 FT SPECIAL - 20" STEEL CASING PIPE 322.2375 700.0000 $9,100.00
638E22904 32.000 FT SPECIAL - 24" STEEL CASING PIPE 123.6875 187.0000 $5,984.00
638E23006 7.000 EACH SPECIAL - 8" GATE VALVE WITH VALVE BOX, 1,803.0000 1,785.7143 $12,500.00
COMPLETE
638E23108 3.000 EACH SPECIAL - 12" GATE VALVE WITH VALVE BOX, 2,944.8315 3,600.0000 $10,800.00
COMPLETE
638E23500 1.000 EACH SPECIAL - 6" CUTTING-IN VALVE WITH VALVE 4,241.0375 3,050.0000 $3,050.00
BOX, COMPLETE
638E23506 10.000 EACH SPECIAL - 8" CUTTING-IN VALVE WITH VALVE 3,613.8286 3,952.0000 $39,520.00
BOX, COMPLETE
638E23602 4.000 EACH SPECIAL - 10" CUTTING-IN VALVE WITH 5,541.4389 6,500.0000 $26,000.00
VALVE BOX, COMPLETE
638E23604 2.000 EACH SPECIAL - 12" CUTTING-IN VALVE WITH 6,784.0222 7,625.0000 $15,250.00
VALVE BOX, COMPLETE
638E23700 1.000 EACH SPECIAL - 16" CUTTING-IN VALVE WITH 12,722.6125 11,965.0000 $11,965.00
VALVE BOX, COMPLETE
638E23808 4.000 EACH SPECIAL - 30" CUTTING-IN VALVE WITH 47,911.4875 42,000.0000 $168,000.00
VALVE BOX, COMPLETE
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
182 | P a g e
638E24500 5.000 EACH SPECIAL - 2" AIR RELIEF VALVE WITH VALVE 3,037.0182 4,900.0000 $24,500.00
BOX, COMPLETE
638E24600 9.000 EACH SPECIAL - FURNISHING AND SETTING 6" 5,360.0000 6,055.5556 $54,500.00
HYDRANT, COMPLETE
638E24700 11.000 EACH SPECIAL - EXTEND AND ADJUST HYDRANT TO 3,503.0676 2,064.0273 $22,704.30
GRADE, TYPE A
638E25000 18,000.000 LB SPECIAL - MISCELLANEOUS METAL WORK 1.9605 1.3917 $25,050.00
638E25302 2.000 EACH SPECIAL - INSTALL 5/8" METER SETTING, 1,128.6125 2,965.0000 $5,930.00
COMPLETE
638E25604 2.000 EACH SPECIAL - 5/8" METER VAULT 1,901.1875 2,164.0000 $4,328.00
638E26210 9.000 EACH SPECIAL - 6" DRAIN, COMPLETE 8,642.2549 10,666.6667 $96,000.00
638E26804 1.000 EACH SPECIAL - RETAP, RECONNECT AND EXTEND 1" 2,020.5250 1,500.0000 $1,500.00
WATER SERVICE CONNECTION, SHORT SIDE COMPLETE
638E27008 1.000 EACH SPECIAL - RETAP, RECONNECT AND EXTEND 1" 2,388.9250 1,500.0000 $1,500.00
WATER SERVICE CONNECTION, LONG SIDE COMPLETE
638E29404 6.000 EACH SPECIAL - EXTEND 5/8" WATER SERVICE 1,609.9354 1,687.5000 $10,125.00
CONNECTION, COMPLETE
638E30300 48.000 EACH SPECIAL - PLUGGING EXISTING SERVICE 1,170.0210 1,397.6354 $67,086.50
CONNECTION
638E30400 7.000 EACH SPECIAL - PLUGGING EXISTING WATER MAIN 1,802.3800 3,000.0000 $21,000.00
AND BRANCHES
638E30500 1.200 MBF SPECIAL - SHEETING LEFT IN PLACE 5,393.2983 1,116.6667 $1,340.00
638E42700 5.000 EACH SPECIAL - 6" HYDRANT ASSEMBLY, TYPE A 5,832.7875 6,250.0000 $31,250.00
638E42800 3.000 EACH SPECIAL - 6" HYDRANT ASSEMBLY, TYPE B 5,856.5913 7,030.0000 $21,090.00
638E43800 29.000 EACH SPECIAL - VALVE BOX ADJUSTED TO GRADE 248.7356 267.2414 $7,750.00
638E44006 5,000.000 LB SPECIAL - MISCELLANEOUS METAL WORK 2.2250 4.0000 $20,000.00
638E50000 369.000 FT SPECIAL - 6" WATER MAIN DUCTILE IRON 89.4563 79.7500 $29,427.75
PIPE ANSI CLASS 53, PUSH-ON JOINTS AND MECHANICAL JOINT FITTINGS
638E50100 367.000 FT SPECIAL - 8" WATER MAIN DUCTILE IRON 129.1336 125.4823 $46,052.00
PIPE ANSI CLASS 53, PUSH-ON JOINTS AND MECHANICAL JOINT FITTINGS
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
183 | P a g e
638E50120 344.000 FT SPECIAL - 12" WATER MAIN DUCTILE IRON 185.2570 202.3605 $69,612.00
PIPE ANSI CLASS 53, PUSH-ON JOINTS AND MECHANICAL JOINT FITTINGS
638E50150 2,034.000 FT SPECIAL - 16" WATER MAIN DUCTILE IRON 243.6259 144.7144 $294,349.00
PIPE ANSI CLASS 53, PUSH-ON JOINTS AND MECHANICAL JOINT FITTINGS
638E51070 1,491.000 FT POLYETHYLENE ENCASEMENT 1.9018 1.0000 $1,491.00
638E51090 13.000 EACH SPECIAL - 6" GATE VALVE WITH VALVE BOX, 961.0000 900.0000 $11,700.00
COMPLETE
638E51100 4.000 EACH SPECIAL - 8" GATE VALVE WITH VALVE BOX, 1,333.5929 1,075.0000 $4,300.00
COMPLETE
638E51110 26.000 EACH SPECIAL - 16" GATE VALVE WITH VALVE BOX, 6,131.8033 4,000.0000 $104,000.00
COMPLETE
638E51120 8.000 EACH SPECIAL - 12" GATE VALVE WITH VALVE BOX, 2,300.4913 1,987.5000 $15,900.00
COMPLETE
638E51200 1.000 EACH SPECIAL - 16" BUTTERFLY VALVE WITH VALVE 4,546.6250 6,000.0000 $6,000.00
BOX, COMPLETE
638E51400 15.000 EACH SPECIAL - FURNISHING AND SETTING 6" 3,222.5000 2,100.0000 $31,500.00
HYDRANT, COMPLETE
638E53500 48.000 EACH VALVE BOX ADJUSTED TO GRADE 145.6768 107.8125 $5,175.00
638E60100 4,353.000 FT SPECIAL - 6" DUCTILE IRON WATER PIPE AND 57.1464 51.9820 $226,277.50
FITTINGS (COL. 801)
638E60200 1,430.000 FT SPECIAL - 8" DUCTILE IRON WATER PIPE AND 133.0000 105.3846 $150,700.00
FITTINGS (COL. 801)
638E60400 1,003.000 FT SPECIAL - 12" DUCTILE IRON WATER PIPE 122.9977 126.7797 $127,160.00
AND FITTINGS (COL.801)
638E60500 5,346.000 FT SPECIAL - 16" DUCTILE IRON WATER PIPE 176.2500 160.0000 $855,360.00
AND FITTINGS (COL.801)
638E61500 66.000 CY SPECIAL - CONCRETE BLOCKING, CLASS C 120.0000 90.0000 $5,940.00
(COL. 801)
638E61510 25.000 CY SPECIAL - CONCRETE BLOCKING, CLASS C, 120.8640 151.0000 $3,775.00
INCREASE OR DECREASE (COL. 801)
638E61600 7,030.000 LB SPECIAL - FITTINGS, INCREASE OR DECREASE 2.7857 2.0896 $14,690.00
(COL. 801)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
184 | P a g e
638E61900 51.000 EACH SPECIAL - 6" VALVE AND APPURTENANCES 976.2961 855.0980 $43,610.00
(COL. 802)
638E62000 13.000 EACH SPECIAL - 8" VALVE AND APPURTENANCES 1,521.2353 1,470.7692 $19,120.00
(COL. 802)
638E62200 3.000 EACH SPECIAL - 12" VALVE AND APPURTENANCES 2,430.0000 2,200.0000 $6,600.00
(COL. 802)
638E62300 7.000 EACH SPECIAL - 16" VALVE AND APPURTENANCES 5,675.0000 5,900.0000 $41,300.00
(COL. 802)
638E63000 2.000 EACH SPECIAL - 8" X 8" TAPPING SLEEVE, VALVE 5,869.5960 6,390.0000 $12,780.00
AND APPURTENANCES (COL. 803)
638E63200 1.000 EACH SPECIAL - 16" X 6" TAPPING SLEEVE, VALVE 9,475.0000 8,500.0000 $8,500.00
AND APPURTENANCES (COL. 803)
638E63500 500.000 LB SPECIAL - IRON CASTING (COL. 804) 2.1250 1.0000 $500.00
638E63600 7.000 EACH SPECIAL - 3/4" WATER SERVICE TAP, 1,700.0000 1,800.0000 $12,600.00
COMPLETE (COL. 805)
638E63700 1.000 EACH SPECIAL - 1" WATER SERVICE TAP, COMPLETE 1,933.3333 2,250.0000 $2,250.00
(COL. 805)
638E64020 100.000 FT SPECIAL - 2" TYPE K COPPER WATER SERVICE 70.0000 55.0000 $5,500.00
(COL. 805)
638E64120 28.000 EACH SPECIAL - 3/4" WATER SERVICE TAP, 1,628.6891 1,562.8571 $43,760.00
TRANSFERRED (COL. 805)
638E64121 1.000 EACH SPECIAL - 3/4" WATER SERVICE TAP, 2,364.0000 1,800.0000 $1,800.00
TRANSFERRED (COL. 805), AS PER PLAN
638E64130 1.000 EACH SPECIAL - 1" WATER SERVICE TAP, 1,483.3333 2,250.0000 $2,250.00
TRANSFERRED (COL. 805)
638E64140 1.000 EACH SPECIAL - 1-1/2" WATER SERVICE TAP, 3,050.0000 3,100.0000 $3,100.00
TRANSFERRED (COL. 805)
638E64160 2.000 EACH SPECIAL - 4" WATER SERVICE TAP, 6,700.0000 6,200.0000 $12,400.00
TRANSFERRED (COL. 805)
638E64170 1.000 EACH SPECIAL - 6" WATER SERVICE TAP, 6,662.5000 4,900.0000 $4,900.00
TRANSFERRED (COL. 805)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
185 | P a g e
638E64500 46.000 FT SPECIAL - 16" CASING PIPE, OPEN CUT 178.2000 240.0000 $11,040.00
(COL. 806)
638E64504 25.000 FT SPECIAL - 24" CASING PIPE, OPEN CUT 412.5000 500.0000 $12,500.00
(COL. 806)
638E65104 613.000 FT SPECIAL - 24" CASING PIPE, BORED OR 505.0000 565.0000 $346,345.00
JACKED (COL. 806)
638E65400 40.000 EACH SPECIAL - VALVE BOX ADJUSTED TO GRADE 442.5862 288.1250 $11,525.00
(COL. 807)
638E65402 29.000 EACH SPECIAL - HEAVY DUTY VALVE BOX ADJUSTED 307.5521 240.5172 $6,975.00
TO GRADE (COL. 807)
638E65500 29.000 EACH SPECIAL - SERVICE BOX ADJUSTED TO GRADE 221.3265 185.3448 $5,375.00
(COL. 807)
638E65502 1.000 EACH SPECIAL - SERVICE BOX REMOVED AND RESET 343.0000 500.0000 $500.00
(COL. 807)
638E65600 67.000 EACH SPECIAL - COLUMBUS STANDARD HEAVY DUTY 550.4106 473.8806 $31,750.00
VALVE BOX (COL. 807)
638E65610 7.000 EACH SPECIAL - C.I. FERRULE VALVE BOX AND 143.6609 148.5714 $1,040.00
COVER (COL. 807)
638E65700 2.000 EACH SPECIAL - CUT AND PLUG 6" WATER LINE 864.5180 1,470.0000 $2,940.00
(COL. 808)
638E65800 2.000 EACH SPECIAL - CUT AND PLUG 8" WATER LINE 873.3333 720.0000 $1,440.00
(COL. 808)
638E65810 2.000 EACH SPECIAL - CUT AND PLUG 10" WATER LINE 1,080.0000 1,000.0000 $2,000.00
(COL. 808)
638E66200 84.000 FT SPECIAL - RELOCATE 6" WATER LINE (COL. 211.0000 180.0000 $15,120.00
808)
638E66210 80.000 FT SPECIAL - RELOCATE 8" WATER LINE (COL. 185.0000 155.0000 $12,400.00
808)
638E66220 25.000 FT SPECIAL - RELOCATE 12" WATER LINE (COL. 352.5000 360.0000 $9,000.00
808)
638E66250 25.000 FT SPECIAL - RELOCATE 6 INCH WATER LINE 517.5000 470.0000 $11,750.00
(COL. 808)
638E66600 2.000 EACH SPECIAL - FIRE HYDRANT (COL. 809) 3,127.3320 3,000.0000 $6,000.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
186 | P a g e
638E66602 10.000 EACH SPECIAL - FIRE HYDRANT, TYPE A (COL. 2,685.7143 2,850.0000 $28,500.00
809)
638E66604 2.000 EACH SPECIAL - FIRE HYDRANT, TYPE B (COL. 2,812.5000 2,500.0000 $5,000.00
809)
638E66610 8.000 EACH SPECIAL - FIRE HYDRANT, TYPE A, MODIFIED 2,875.0000 3,000.0000 $24,000.00
(COL. 809)
638E66700 18.000 EACH SPECIAL - FIRE HYDRANT, RELOCATED (COL. 1,895.5224 1,205.5556 $21,700.00
809)
638E67000 1.000 EACH SPECIAL - 6" HYDRANT EXTENSION (COL. 637.5000 350.0000 $350.00
810)
638E67010 3.000 EACH SPECIAL - 12" HYDRANT EXTENSION (COL. 708.7500 400.0000 $1,200.00
810)
638E67030 1.000 EACH SPECIAL - 24" HYDRANT EXTENSION (COL. 915.0000 460.0000 $460.00
810)
638E67400 251.000 CY SPECIAL - INCREASE OR DECREASE IN 43.5609 34.9004 $8,760.00
EXCAVATION (COL. 811)
638E67700 2.000 EACH SPECIAL - AIR RELEASE OUTLET RELOCATED 970.0000 500.0000 $1,000.00
(COL. 812)
638E69600 15.000 EACH SPECIAL - NEW CURB BOX (COL. 816) 178.6877 96.6667 $1,450.00
638E80600 6.000 FT SPECIAL - FURNISHING AND LAYING 6" 342.8425 186.5000 $1,119.00
DUCTILE IRON PIPE AND FITTINGS (CIN. 1101)
638E80800 7.000 FT SPECIAL - FURNISHING AND LAYING 10" 633.7500 635.0000 $4,445.00
DUCTILE IRON PIPE AND FITTINGS (CIN. 1101)
638E80900 263.000 FT SPECIAL - FURNISHING AND LAYING 12" 191.3328 73.1787 $19,246.00
DUCTILE IRON PIPE AND FITTINGS (CIN. 1101)
638E81000 67.000 FT SPECIAL - FURNISHING AND LAYING 16" 417.7425 251.0000 $16,817.00
DUCTILE IRON PIPE AND FITTINGS (CIN. 1101)
638E84020 19.000 FT SPECIAL - FURNISHING AND INSTALLING 30" 155.9700 55.0000 $1,045.00
STEEL CASING (CIN. 1108)
638E84500 26.000 CY SPECIAL - CONCRETE, CLASS C (CIN. 1110) 183.6025 75.0000 $1,950.00
638E84600 11.000 CY SPECIAL - CONCRETE, CLASS C, HIGH-EARLY 223.7250 150.0000 $1,650.00
STRENGTH (CIN. 1110)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
187 | P a g e
638E85800 1.000 EACH SPECIAL - FURNISHING AND INSTALLING FIRE 4,752.5550 2,675.0000 $2,675.00
HYDRANT (CIN. 1112)
638E86000 3.000 EACH SPECIAL - REMOVING FIRE HYDRANT (CIN. 461.4525 201.6667 $605.00
1114)
638E86100 1.000 EACH SPECIAL - FURNISHING AND INSTALLING FIRE 661.8200 265.0000 $265.00
HYDRANT EXTENSION (CIN. 1115)
638E86200 1.000 EACH SPECIAL - INSTALLING VALVE BOX, COMPLETE 607.8750 171.0000 $171.00
(CIN. 1116)
638E86300 2.000 EACH SPECIAL - FURNISHING AND INSTALLING 1,071.9750 1,550.0000 $3,100.00
VALVE BOX, COMPLETE (CIN. 1116)
638E86400 25.000 CY SPECIAL - ADDITIONAL EXCAVATION (CIN. 31.7100 23.0000 $575.00
1119)
638E86404 15.000 CY SPECIAL - EXPLORATORY EXCAVATION (CIN. 62.9325 85.0000 $1,275.00
1120)
638E86700 4.000 EACH SPECIAL - REMOVING EXISTING VALVE BOX 149.7463 95.0000 $380.00
(CIN. 1122)
638E87100 8.000 EACH SPECIAL - RESETTING EXISTING VALVE BOX, 212.0300 10.0000 $80.00
COMPLETE (CIN. 1125)
638E87604 94.000 FT SPECIAL - FURNISHING, INSTALLING AND 105.4450 162.0000 $15,228.00
CONNECTING 1" COPPER SERVICE PIPE (CIN.
1126)
638E87800 1.000 EACH SPECIAL - RECONNECTING EXISTING SERVICE 1,163.4325 459.0000 $459.00
BRANCH (CIN. 1128)
638E88500 1.000 EACH SPECIAL - DISCONNECTING EXISTING SERVICE 537.7825 445.0000 $445.00
BRANCH (CIN. 1130)
638E88700 2.000 EACH SPECIAL - FURNISHING AND INSTALLING CURB 176.6475 50.0000 $100.00
AND ROADWAY BOX (CIN. 1131)
638E89650 6.000 EACH SPECIAL - RESETTING EXISTING 5/8" FROST 723.3525 551.0000 $3,306.00
PROOF METER SETTING (CIN. 1135)
638E89700 3.000 EACH SPECIAL - RESETTING EXISTING 3/4" 723.3475 551.0000 $1,653.00
FROST-PROOF METER SETTING (CIN. 1135)
638E89800 1.000 EACH SPECIAL - RESETTING EXISTING 1" 798.3550 551.0000 $551.00
FROST-PROOF METER SETTING (CIN. 1135)
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
188 | P a g e
638E90300 6.000 EACH SPECIAL - REMOVING CURB AND ROADWAY BOX 122.5000 60.0000 $360.00
(CIN. 1138)
638E98000 491.000 EACH WATER WORK, MISC.: 2,015.0006 2,234.5403 $1,097,159.29
638E98100 9.000 LS WATER WORK, MISC.: 24,176.0900 21,299.4444 $191,695.00
638E98200 542.000 CY WATER WORK, MISC.: 174.2103 83.9576 $45,505.00
638E98600 19,920.000 FT WATER WORK, MISC.: 94.8561 103.1992 $2,055,728.30
638E99000 1.000 LS SPECIAL - WATER WORKS 230,668.2267 252,004.6800 $252,004.68
641E99000 7.000 LS SPECIAL - PAVEMENT MARKING 81,538.1232 86,860.6243 $608,024.37
642E00090 4,261.454 MILE EDGE LINE 415.2223 390.6780 $1,664,856.47
642E00094 2,942.670 MILE EDGE LINE, 6" 530.8872 502.7525 $1,479,434.69
642E00100 11,189.280 MILE EDGE LINE, TYPE 1 367.7318 353.8179 $3,958,967.10
642E00101 69.000 MILE EDGE LINE, TYPE 1, AS PER PLAN 271.3333 280.0000 $19,320.00
642E00104 4,564.760 MILE EDGE LINE, TYPE 3 514.1383 506.5857 $2,312,442.03
642E00105 69.000 MILE EDGE LINE, 6", TYPE 1, AS PER PLAN 405.3333 420.0000 $28,980.00
642E00190 163.014 MILE LANE LINE 281.1548 243.1743 $39,640.82
642E00194 1,957.350 MILE LANE LINE, 6" 237.4836 223.5712 $437,607.11
642E00200 568.550 MILE LANE LINE, TYPE 1 186.8713 177.9568 $101,177.32
642E00201 14.000 MILE LANE LINE, TYPE 1, AS PER PLAN 67.0000 70.0000 $980.00
642E00204 2,438.070 MILE LANE LINE, TYPE 3 206.6273 202.3608 $493,369.69
642E00205 14.000 MILE LANE LINE, 6", TYPE 1, AS PER PLAN 111.3333 115.0000 $1,610.00
642E00214 607.810 MILE LANE LINE, 6", TYPE 1A 207.8500 235.7000 $143,260.82
642E00290 2,188.336 MILE CENTER LINE 527.8923 472.5284 $1,034,050.86
642E00300 8,789.560 MILE CENTER LINE, TYPE 1 475.9228 436.7995 $3,839,275.83
642E00301 26.320 MILE CENTER LINE, TYPE 1, AS PER PLAN 595.4838 498.7240 $13,126.42
642E00390 62,237.000 FT CHANNELIZING LINE 0.4097 0.3778 $23,515.01
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
189 | P a g e
642E00394 483,644.000 FT CHANNELIZING LINE, 12" 0.4039 0.3815 $184,504.12
642E00400 235,869.000 FT CHANNELIZING LINE, TYPE 1 0.3345 0.2937 $69,280.80
642E00401 500.000 FT CHANNELIZING LINE, TYPE 1, AS PER PLAN 0.2500 0.2000 $100.00
642E00404 521,607.000 FT CHANNELIZING LINE, TYPE 3 0.3707 0.3751 $195,667.10
642E00405 500.000 FT CHANNELIZING LINE, 12", TYPE 1, AS PER PLAN 0.3500 0.3000 $150.00
642E00490 20,208.000 FT STOP LINE 2.5986 2.6536 $53,623.20
642E00491 44.000 FT STOP LINE, AS PER PLAN 6.0675 6.0000 $264.00
642E00500 44,864.000 FT STOP LINE, TYPE 1 2.2150 2.1238 $95,284.40
642E00501 100.000 FT STOP LINE, TYPE 1, AS PER PLAN 2.0100 2.0000 $200.00
642E00590 18,137.000 FT CROSSWALK LINE 1.9791 1.8700 $33,916.85
642E00600 28,805.000 FT CROSSWALK LINE, TYPE 1 1.7426 1.6066 $46,279.22
642E00690 8,546.000 FT TRANSVERSE LINE 1.8808 1.7886 $15,285.55
642E00691 1,829.000 FT TRANSVERSE LINE, AS PER PLAN 2.9797 2.7004 $4,939.00
642E00700 183,762.000 FT TRANSVERSE LINE, TYPE 1 0.9856 1.0067 $184,987.87
642E00800 22,749.000 FT CURB MARKING, TYPE 1 0.5409 0.5154 $11,725.31
642E00900 44,256.000 SF ISLAND MARKING, TYPE 1 0.5773 0.6132 $27,136.05
642E00910 25,161.000 SF ISLAND MARKING 0.7583 1.0214 $25,699.90
642E00990 10.000 EACH RAILROAD SYMBOL MARKING 172.5000 200.0000 $2,000.00
642E01000 130.000 EACH RAILROAD SYMBOL MARKING, TYPE 1 153.6311 161.3462 $20,975.00
642E01001 5.000 EACH RAILROAD SYMBOL MARKING, TYPE 1, AS PER 122.0000 150.0000 $750.00
PLAN
642E01090 10.000 EACH SCHOOL SYMBOL MARKING, 72" 162.5357 155.0000 $1,550.00
642E01108 22.000 EACH SCHOOL SYMBOL MARKING, 96" 173.0488 199.5455 $4,390.00
642E01110 153.000 EACH SCHOOL SYMBOL MARKING, 96", TYPE 1 154.2247 160.0000 $24,480.00
642E01111 5.000 EACH SCHOOL SYMBOL MARKING, 96", TYPE 1, AS 126.0000 160.0000 $800.00
PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
190 | P a g e
642E01120 1.000 EACH SCHOOL SYMBOL MARKING, 120" 407.0000 250.0000 $250.00
642E01190 24,203.000 FT PARKING LOT STALL MARKING 0.8018 0.8163 $19,757.65
642E01191 1,453.000 FT PARKING LOT STALL MARKING, AS PER PLAN 0.5200 0.3500 $508.55
642E01200 34,517.000 FT PARKING LOT STALL MARKING, TYPE 1 0.6049 0.5826 $20,108.80
642E01201 1,028.000 FT PARKING LOT STALL MARKING, TYPE 1, AS 0.9450 1.2000 $1,233.60
PER PLAN
642E01290 1,193.000 EACH LANE ARROW 45.3161 50.1679 $59,850.35
642E01300 2,734.000 EACH LANE ARROW, TYPE 1 33.1307 28.0838 $76,781.00
642E01301 20.000 EACH LANE ARROW, TYPE 1, AS PER PLAN 26.8000 25.0000 $500.00
642E01390 3.000 EACH WORD ON PAVEMENT, 72" 72.6667 85.0000 $255.00
642E01400 10.000 EACH WORD ON PAVEMENT, 72", TYPE 1 66.5750 69.2000 $692.00
642E01408 296.000 EACH WORD ON PAVEMENT, 96" 53.8088 58.2770 $17,250.00
642E01410 297.000 EACH WORD ON PAVEMENT, 96", TYPE 1 44.9899 27.4444 $8,151.00
642E01490 438.000 FT DOTTED LINE, 4" 1.7405 1.0976 $480.75
642E01500 4,677.000 FT DOTTED LINE, 4", TYPE 1 0.8667 0.7368 $3,446.05
642E01508 24,983.000 FT DOTTED LINE, 6" 0.5392 0.4470 $11,166.45
642E01509 1,400.000 FT DOTTED LINE, 6", AS PER PLAN 0.8935 0.9286 $1,300.00
642E01510 223,715.000 FT DOTTED LINE, 6", TYPE 1 0.3177 0.3697 $82,718.29
642E01522 4,510.000 FT DOTTED LINE, 8", TYPE 1 0.2000 0.2500 $1,127.50
642E01550 505.000 FT DOTTED LINE, 12" 1.8875 2.0000 $1,010.00
642E01560 25,331.000 FT DOTTED LINE, 12", TYPE 1 0.3233 0.3752 $9,503.80
642E01600 6.000 EACH BIKE LANE SYMBOL MARKING 200.0000 200.0000 $1,200.00
642E01602 88.000 EACH BIKE LANE SYMBOL MARKING, TYPE 1 48.0130 41.0795 $3,615.00
642E01650 2.000 EACH BIKE LANE ARROW, TYPE 1 48.6000 45.0000 $90.00
642E01700 11.000 EACH HANDICAP SYMBOL MARKING 88.5311 76.3636 $840.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
191 | P a g e
642E01701 2.000 EACH HANDICAP SYMBOL MARKING, AS PER PLAN 65.8571 56.0000 $112.00
642E01702 32.000 EACH HANDICAP SYMBOL MARKING, TYPE 1 44.5209 49.5625 $1,586.00
642E20000 8.000 LS TWO-WAY RADIO EQUIPMENT 19.8007 34.0088 $272.07
642E20800 16.000 FT YIELD LINE 12.5000 15.0000 $240.00
642E30000 68,198.000 FT REMOVAL OF PAVEMENT MARKING 2.4973 1.3986 $95,384.83
642E30001 300.000 FT REMOVAL OF PAVEMENT MARKING, AS PER PLAN 1.4000 1.0000 $300.00
642E30010 880.000 SF REMOVAL OF PAVEMENT MARKING 2.1562 1.7466 $1,537.00
642E30020 160.000 EACH REMOVAL OF PAVEMENT MARKING 89.9087 82.5094 $13,201.50
642E30030 2.955 MILE REMOVAL OF PAVEMENT MARKING 3,570.2871 2,957.2115 $8,738.56
642E40000 6.000 EACH SPECIAL - AIR SPEED ZONE MARKING 638.5000 566.6667 $3,400.00
642E50000 245.110 MILE PAVEMENT MARKING, MISC.: 199.0766 213.1655 $52,249.00
642E50010 11.000 EACH PAVEMENT MARKING, MISC.: 180.0625 102.2727 $1,125.00
642E50020 589.000 FT PAVEMENT MARKING, MISC.: 1.9304 1.9304 $1,137.00
642E50040 2.000 LS PAVEMENT MARKING, MISC.: 1,425.0000 1,850.0000 $3,700.00
642E99000 4.000 LS SPECIAL - PAVEMENT MARKING 6,487.1490 20,663.7500 $82,655.00
643E00100 2,111.010 MILE EDGE LINE 591.7311 573.3998 $1,210,452.67
643E00101 406.680 MILE EDGE LINE, AS PER PLAN 587.5000 620.0000 $252,141.60
643E00104 857.640 MILE EDGE LINE, 6" 823.9642 800.1841 $686,269.86
643E00200 85.240 MILE LANE LINE 480.0043 443.6117 $37,813.46
643E00201 89.800 MILE LANE LINE, AS PER PLAN 287.5000 325.0000 $29,185.00
643E00204 694.410 MILE LANE LINE, 6" 345.3678 327.7328 $227,580.90
643E00300 1,062.000 MILE CENTER LINE 543.7631 536.8339 $570,117.60
643E00301 168.750 MILE CENTER LINE, AS PER PLAN 915.0000 980.0000 $165,375.00
643E00400 60,064.000 FT CHANNELIZING LINE 0.5597 0.4811 $28,898.81
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
192 | P a g e
643E00404 181,659.000 FT CHANNELIZING LINE, 12" 0.5622 0.4821 $87,573.24
643E00500 21,927.000 FT STOP LINE 3.0115 2.9587 $64,874.80
643E00600 7,600.000 FT CROSSWALK LINE 1.5341 1.3422 $10,200.40
643E00601 198.000 FT CROSSWALK LINE, AS PER PLAN 9.3333 12.0000 $2,376.00
643E00700 70,183.000 FT TRANSVERSE LINE 1.5124 1.4343 $100,665.48
643E01000 47.000 EACH RAILROAD SYMBOL MARKING 245.0000 210.0000 $9,870.00
643E01110 22.000 EACH SCHOOL SYMBOL MARKING, 96" 248.3333 220.0000 $4,840.00
643E01200 21,446.000 FT PARKING LOT STALL MARKING 0.7900 0.7200 $15,441.12
643E01300 1,167.000 EACH LANE ARROW 52.4383 50.0000 $58,350.00
643E01410 234.000 EACH WORD ON PAVEMENT, 96" 63.5748 61.7094 $14,440.00
643E01500 5,936.000 FT DOTTED LINE, 4" 1.4484 0.6223 $3,693.75
643E01510 41,486.000 FT DOTTED LINE, 6" 0.6675 0.6000 $24,891.60
643E01600 16.000 EACH HANDICAP SYMBOL MARKING 78.3333 100.0000 $1,600.00
643E30020 58.000 EACH REMOVAL OF PAVEMENT MARKING 71.9033 82.5800 $4,789.64
643E30030 30.200 MILE REMOVAL OF PAVEMENT MARKING 1,333.9778 1,751.7510 $52,902.88
643E40000 26.000 EACH SPECIAL - AIR SPEED ZONE MARKING 445.0000 450.0000 $11,700.00
643E50100 16.000 EACH PAVEMENT MARKING, MISC.: 323.2258 531.2500 $8,500.00
644E00100 755.381 MILE EDGE LINE 2,180.9103 2,132.7338 $1,611,026.60
644E00101 1.750 MILE EDGE LINE, AS PER PLAN 2,451.3675 2,444.0000 $4,277.00
644E00104 324.350 MILE EDGE LINE, 6" 2,934.3920 2,846.4023 $923,230.59
644E00200 56.232 MILE LANE LINE 1,287.5695 1,313.6968 $73,871.80
644E00201 4.630 MILE LANE LINE, AS PER PLAN 1,402.1126 1,335.8142 $6,184.82
644E00204 224.111 MILE LANE LINE, 6" 1,269.3251 1,195.6270 $267,953.15
644E00300 460.612 MILE CENTER LINE 3,230.0355 3,157.9845 $1,454,605.56
644E00301 11.544 MILE CENTER LINE, AS PER PLAN 4,755.4990 4,361.7013 $50,351.48
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
193 | P a g e
644E00400 211,226.000 FT CHANNELIZING LINE 1.3177 1.2565 $265,407.56
644E00401 5,165.000 FT CHANNELIZING LINE, AS PER PLAN 1.4857 1.4610 $7,546.32
644E00404 145,183.000 FT CHANNELIZING LINE, 12" 1.5834 1.5579 $226,180.17
644E00500 73,076.000 FT STOP LINE 5.9451 6.0016 $438,574.81
644E00501 3,832.000 FT STOP LINE, AS PER PLAN 5.2425 4.7028 $18,021.26
644E00600 129,566.000 FT CROSSWALK LINE 2.9736 2.8718 $372,086.79
644E00601 34,444.000 FT CROSSWALK LINE, AS PER PLAN 4.1999 3.3107 $114,033.57
644E00700 82,344.000 FT TRANSVERSE LINE 4.9858 4.9780 $409,904.54
644E00701 5,842.000 FT TRANSVERSE LINE, AS PER PLAN 2.0992 1.8984 $11,090.59
644E00900 7,329.000 SF ISLAND MARKING 2.9208 2.7937 $20,475.31
644E01000 93.000 EACH RAILROAD SYMBOL MARKING 499.7217 472.0475 $43,900.42
644E01100 48.000 EACH SCHOOL SYMBOL MARKING, 72" 479.1250 463.6667 $22,256.00
644E01110 42.000 EACH SCHOOL SYMBOL MARKING, 96" 521.5942 519.7162 $21,828.08
644E01120 12.000 EACH SCHOOL SYMBOL MARKING, 120" 626.4355 589.8333 $7,078.00
644E01200 52,345.000 FT PARKING LOT STALL MARKING 1.3372 1.1955 $62,580.49
644E01300 3,367.000 EACH LANE ARROW 84.0311 82.0183 $276,155.61
644E01350 10.000 EACH LANE REDUCTION ARROW 126.6000 135.0000 $1,350.00
644E01361 27.000 EACH WRONG WAY ARROW, AS PER PLAN 70.0000 70.0000 $1,890.00
644E01382 94.000 EACH WORD ON PAVEMENT, 48" 123.9632 124.3936 $11,693.00
644E01400 164.000 EACH WORD ON PAVEMENT, 72" 97.8774 92.7317 $15,208.00
644E01410 133.000 EACH WORD ON PAVEMENT, 96" 103.6918 95.1729 $12,658.00
644E01500 28,949.000 FT DOTTED LINE, 4" 1.5559 1.5456 $44,744.76
644E01502 439.000 FT DOTTED LINE, 5" 1.9067 1.4996 $658.34
644E01510 46,588.000 FT DOTTED LINE, 6" 1.1757 1.1082 $51,630.86
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
194 | P a g e
644E01514 20,178.000 FT DOTTED LINE, 8" 1.0266 1.0329 $20,840.95
644E01520 115.000 FT DOTTED LINE, 12" 1.1167 1.0000 $115.00
644E01600 60.000 EACH HANDICAP SYMBOL MARKING 126.5736 151.1667 $9,070.00
644E01602 4.000 EACH BIKE LANE SYMBOL MARKING 1,000.0000 1,000.0000 $4,000.00
644E01630 130.000 EACH BIKE LANE SYMBOL MARKING 293.6396 321.7077 $41,822.00
644E20000 1.000 LS TWO-WAY RADIO EQUIPMENT 32.4150 14.8300 $14.83
644E20800 175.000 FT YIELD LINE 9.9580 12.1200 $2,121.00
644E30000 39,457.000 FT REMOVAL OF PAVEMENT MARKING 2.1858 2.3062 $90,995.61
644E30020 134.000 EACH REMOVAL OF PAVEMENT MARKING 139.7666 85.5969 $11,469.98
644E30030 0.520 MILE REMOVAL OF PAVEMENT MARKING 4,279.2462 5,087.5000 $2,645.50
644E40000 3.000 EACH SPECIAL - AIR SPEED ZONE MARKING 1,875.0000 2,266.6667 $6,800.00
644E40010 64.000 SF SPECIAL - AIR SPEED ZONE MARKING 14.6667 24.0000 $1,536.00
644E50100 37.000 EACH PAVEMENT MARKING, MISC.: 361.6621 407.6692 $15,083.76
644E50300 5,794.000 FT PAVEMENT MARKING, MISC.: 3.1648 2.7554 $15,964.85
644E50400 22.658 MILE PAVEMENT MARKING, MISC.: 2,833.5729 2,610.0777 $59,139.14
644E99000 6.000 LS SPECIAL - PAVEMENT MARKING 94,927.1500 89,756.2600 $538,537.56
645E00110 2.590 MILE EDGE LINE, TYPE A3 16,839.7180 17,635.9459 $45,677.10
645E00116 0.540 MILE EDGE LINE, 6", TYPE A3 41,380.1351 38,696.2222 $20,895.96
645E00210 2.200 MILE LANE LINE, TYPE A3 8,170.0000 8,465.0000 $18,623.00
645E00216 0.240 MILE LANE LINE, 6", TYPE A3 26,725.3030 22,798.8750 $5,471.73
645E00310 0.280 MILE CENTER LINE, TYPE A3 35,137.4815 35,418.2857 $9,917.12
645E01300 72.000 EACH LANE ARROW, TYPE A1 200.0000 200.0000 $14,400.00
645E01400 12.000 EACH WORD ON PAVEMENT, 72", TYPE A1 300.0000 300.0000 $3,600.00
646E10000 355.330 MILE EDGE LINE 2,425.4968 2,340.4019 $831,615.00
646E10001 1.170 MILE EDGE LINE, AS PER PLAN 5,896.9542 6,427.3504 $7,520.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
195 | P a g e
646E10010 568.984 MILE EDGE LINE, 6" 2,698.6168 2,633.2749 $1,498,291.28
646E10100 45.530 MILE LANE LINE 1,590.2786 1,496.4079 $68,131.45
646E10101 6.990 MILE LANE LINE, AS PER PLAN 2,122.7130 1,972.8183 $13,790.00
646E10110 309.320 MILE LANE LINE, 6" 1,392.6112 1,322.9347 $409,210.15
646E10200 198.920 MILE CENTER LINE 3,409.3108 3,221.7200 $640,864.54
646E10201 0.270 MILE CENTER LINE, AS PER PLAN 20,981.4421 21,800.0000 $5,886.00
646E10300 111,118.020 FT CHANNELIZING LINE 1.4031 0.9764 $108,498.12
646E10310 169,373.000 FT CHANNELIZING LINE, 12" 1.9684 1.8615 $315,284.76
646E10400 10,294.000 FT STOP LINE 10.7610 10.0857 $103,821.77
646E10500 20,162.000 FT CROSSWALK LINE 4.7023 4.3594 $87,893.60
646E10501 2,195.000 FT CROSSWALK LINE, AS PER PLAN 12.9953 12.4834 $27,401.00
646E10600 22,348.000 FT TRANSVERSE LINE 71.4388 5.9956 $133,989.06
646E10601 371.000 FT TRANSVERSE LINE, AS PER PLAN 20.2850 20.0000 $7,420.00
646E10700 79.000 FT CURB MARKING 5.0750 5.0000 $395.00
646E10800 3,477.000 SF ISLAND MARKING 3.2832 2.9067 $10,106.60
646E10900 4.000 EACH HANDICAP SYMBOL MARKING 150.0000 200.0000 $800.00
646E20000 9.000 EACH RAILROAD SYMBOL MARKING 582.3250 545.5556 $4,910.00
646E20100 1.000 EACH SCHOOL SYMBOL MARKING, 72" 695.7250 700.0000 $700.00
646E20110 12.000 EACH SCHOOL SYMBOL MARKING, 96" 510.6667 431.6667 $5,180.00
646E20200 747.000 FT PARKING LOT STALL MARKING 2.1786 2.3000 $1,718.10
646E20300 1,875.000 EACH LANE ARROW 137.7373 126.2210 $236,664.40
646E20400 48.000 EACH WORD ON PAVEMENT, 72" 174.6990 176.8204 $8,487.38
646E20410 277.000 EACH WORD ON PAVEMENT, 96" 159.0774 164.0289 $45,436.00
646E20500 39,013.000 FT DOTTED LINE 2.2230 2.4919 $97,217.25
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
196 | P a g e
646E20501 1,653.000 FT DOTTED LINE, AS PER PLAN 3.9974 3.0962 $5,118.00
646E20502 420.000 FT DOTTED LINE, 4" 3.1312 3.4379 $1,443.90
646E20504 20,196.000 FT DOTTED LINE, 6" 2.7759 1.4824 $29,938.50
646E20510 31,179.000 FT DOTTED LINE, 12" 2.1782 1.8792 $58,592.50
646E20600 72.000 EACH BIKE LANE SYMBOL MARKING 134.7136 112.6250 $8,109.00
646E20710 1.000 EACH SPECIAL - AIR SPEED ZONE MARKING 1,998.7820 3,740.0000 $3,740.00
646E20800 58.000 FT YIELD LINE 13.0889 14.0000 $812.00
646E50000 2.000 EACH REMOVAL OF PAVEMENT MARKING 196.4444 175.0000 $350.00
646E50100 4,983.000 FT REMOVAL OF PAVEMENT MARKING 2.9010 3.8612 $19,240.48
646E50200 39,521.000 SF REMOVAL OF PAVEMENT MARKING 1.1333 1.0000 $39,521.00
646E50300 0.590 MILE REMOVAL OF PAVEMENT MARKING 7,156.9180 5,669.4915 $3,345.00
646E90000 4,176.000 FT PAVEMENT MARKING, MISC.: 3.4639 4.8541 $20,270.75
646E98000 70.000 EACH PAVEMENT MARKING, MISC.: 206.2025 244.4286 $17,110.00
646E99000 5.000 LS SPECIAL - PAVEMENT MARKING 17,228.7847 10,547.0000 $52,735.00
647E18010 6,000.000 FT CHANNELIZING LINE, TYPE B 5.5333 5.5000 $33,000.00
647E18012 6,557.000 FT CHANNELIZING LINE, 8", TYPE B125 5.9431 5.6298 $36,914.80
647E18014 32,000.000 FT CHANNELIZING LINE, 12", TYPE B90 7.3083 7.4750 $239,200.00
647E18016 1,455.000 FT CHANNELIZING LINE, 12", TYPE B125 6.9000 5.7500 $8,366.25
647E18052 1,159.000 FT STOP LINE, TYPE A125 15.3848 16.0599 $18,613.45
647E18060 8,184.000 FT STOP LINE, TYPE B 14.6569 14.3891 $117,760.00
647E18062 2,823.000 FT STOP LINE, TYPE B125 14.0527 14.0055 $39,537.60
647E20012 6,460.000 FT CROSSWALK LINE, TYPE B125 7.7817 7.9133 $51,119.90
647E20110 6,168.000 FT TRANSVERSE LINE, TYPE B 13.5922 13.2685 $81,840.00
647E20112 962.000 FT TRANSVERSE/DIAGONAL LINE, TYPE B125 13.8225 14.4660 $13,916.25
647E20202 2.000 EACH HANDICAP SYMBOL MARKING, TYPE A125 118.3333 180.0000 $360.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
197 | P a g e
647E20302 2.000 EACH RAILROAD SYMBOL MARKING, TYPE A125 1,119.3267 1,100.0000 $2,200.00
647E20310 20.000 EACH RAILROAD SYMBOL MARKING, TYPE B 771.3333 634.0000 $12,680.00
647E20312 7.000 EACH RAILROAD SYMBOL MARKING, TYPE B125 844.4444 828.5714 $5,800.00
647E20412 6.000 EACH SCHOOL SYMBOL MARKING, 72", TYPE B125 650.0000 633.3333 $3,800.00
647E20440 20.000 EACH SCHOOL SYMBOL MARKING, 96", TYPE B 735.3333 746.0000 $14,920.00
647E20512 1,607.000 FT PARKING LOT STALL MARKING, TYPE B125 3.9921 3.8797 $6,234.75
647E20602 110.000 EACH LANE ARROW, TYPE A125 315.4496 310.0000 $34,100.00
647E20610 214.000 EACH LANE ARROW, TYPE B 270.4339 196.4019 $42,030.00
647E20612 193.000 EACH LANE ARROW, TYPE B125 286.3025 275.4560 $53,163.00
647E20702 1.000 EACH WORD ON PAVEMENT, 72", TYPE A125 517.8200 500.0000 $500.00
647E20710 4.000 EACH WORD ON PAVEMENT, 72", TYPE B 435.0000 120.0000 $480.00
647E20810 435.000 FT DOTTED LINE, 4", TYPE B 4.1086 3.4138 $1,485.00
647E20812 383.000 FT DOTTED LINE, 4", TYPE B125 3.2950 3.1500 $1,206.45
647E20890 300.000 FT DOTTED LINE, 12", TYPE B90 5.8167 5.0000 $1,500.00
647E50000 1,000.000 FT REMOVAL OF PAVEMENT MARKING 3.1750 3.0000 $3,000.00
647E50010 29.000 EACH REMOVAL OF PAVEMENT MARKING 82.9710 88.7931 $2,575.00
647E50100 21.000 EACH PAVEMENT MARKING, MISC.: 652.4268 347.6190 $7,300.00
647E50110 7,623.000 SF PAVEMENT MARKING, MISC.: 19.9360 19.0000 $144,837.00
647E50120 5,130.000 FT PAVEMENT MARKING, MISC.: 8.1983 3.3975 $17,429.00
647E50130 2.746 MILE PAVEMENT MARKING, MISC.: 19,647.4978 444.4647 $1,220.50
647E60020 560.000 SF GREEN COLORED PAVEMENT FOR BIKE 18.3050 7.0000 $3,920.00
LANES,TYPE B90
648E00100 226.080 MILE EDGE LINE, 4" 1,125.7645 1,009.5791 $228,245.64
648E00104 34.700 MILE EDGE LINE, 6" 1,813.9747 1,468.0000 $50,939.60
648E00200 8.320 MILE LANE LINE, 4" 548.1801 552.7188 $4,598.62
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
198 | P a g e
648E00204 16.520 MILE LANE LINE, 6" 1,137.3077 766.6707 $12,665.40
648E00300 121.620 MILE CENTER LINE 1,516.1110 1,424.5937 $173,259.08
648E01500 140.000 FT DOTTED LINE, 4" 0.5500 0.5500 $77.00
648E01510 3,665.000 FT DOTTED LINE, 6" 0.6687 0.7379 $2,704.25
651E10000 496.000 CY TOPSOIL STOCKPILED 8.7833 8.5000 $4,216.00
652E10000 496.000 CY PLACING STOCKPILED TOPSOIL 16.6650 10.5000 $5,208.00
653E10000 16,199.000 CY TOPSOIL FURNISHED AND PLACED 22.5995 15.7322 $254,845.48
653E10001 1,334.000 CY TOPSOIL FURNISHED AND PLACED, AS PER 53.6580 65.8756 $87,878.00
PLAN
656E10000 250.000 MSF ROADSIDE CLEANUP 22.5000 7.0000 $1,750.00
659E00100 338.000 EACH SOIL ANALYSIS TEST 76.1826 50.7939 $17,168.35
659E00300 440,009.000 CY TOPSOIL 11.0968 8.1809 $3,599,649.69
659E00301 4,702.000 CY TOPSOIL, AS PER PLAN 31.6521 30.5090 $143,453.23
659E00500 279,741.000 SY SEEDING AND MULCHING, CLASS 1 0.8282 0.6696 $187,321.65
659E00510 169,240.000 SY SEEDING AND MULCHING, CLASS 2 0.4604 0.4618 $78,154.41
659E00530 17,621.000 SY SEEDING AND MULCHING, CLASS 3B 1.4830 1.3002 $22,910.94
659E00531 22,067.000 SY SEEDING AND MULCHING, CLASS 3B, AS PER 0.9200 0.4700 $10,371.49
PLAN
659E00540 17,367.000 SY SEEDING AND MULCHING, CLASS 3C 1.1613 1.5387 $26,722.80
659E00550 6,131.000 SY SEEDING AND MULCHING, CLASS 4A 1.5910 1.6079 $9,858.10
659E00560 43,524.000 SY SEEDING AND MULCHING, CLASS 4B 0.4001 0.3545 $15,429.92
659E00570 7,701.000 SY SEEDING AND MULCHING, CLASS 5A 0.3567 0.2900 $2,233.29
659E00580 44,291.000 SY SEEDING AND MULCHING, CLASS 5B 0.7426 0.4703 $20,830.08
659E10000 4,723,052.000 SY SEEDING AND MULCHING 0.6317 0.4508 $2,129,116.51
659E10001 71,499.000 SY SEEDING AND MULCHING, AS PER PLAN 1.5912 1.1320 $80,934.94
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
199 | P a g e
659E11000 853.000 SY SEEDING AND MULCHING FOR VEGETATED 2.2575 1.0000 $853.00
FILTER STRIP
659E14000 244,800.700 SY REPAIR SEEDING AND MULCHING 0.4224 0.3620 $88,607.50
659E14001 12,980.000 SY REPAIR SEEDING AND MULCHING, AS PER PLAN 0.6610 0.6094 $7,910.00
659E15000 213,238.700 SY INTER-SEEDING 0.1821 0.1374 $29,302.06
659E15001 105,850.000 SY INTER-SEEDING, AS PER PLAN 0.5242 0.4038 $42,737.50
659E20000 764.342 TON COMMERCIAL FERTILIZER 472.9202 490.6976 $375,060.81
659E20001 3.260 TON COMMERCIAL FERTILIZER, AS PER PLAN 882.6591 530.2393 $1,728.58
659E31000 1,049.905 ACRE LIME 51.8480 41.9462 $44,039.51
659E31001 3.500 ACRE LIME, AS PER PLAN 150.8275 153.3100 $536.59
659E35000 27,822.160 MGAL WATER 2.4554 1.7975 $50,011.19
659E35001 613.000 MGAL WATER, AS PER PLAN 12.4258 8.7449 $5,360.60
659E40000 8,847.680 MSF MOWING 2.4705 1.8466 $16,337.74
659E40001 822.000 MSF MOWING, AS PER PLAN 5.9333 2.3300 $1,915.26
659E98000 27,085.100 SY SEEDING, MISC.: 1.5348 1.4659 $39,703.22
659E98700 4.000 LS SEEDING, MISC.: 3,511.7647 4,125.0000 $16,500.00
659E99000 15.000 LS SPECIAL - PERMANENT EROSION CONTROL 33,383.1973 29,165.4013 $437,481.02
660E20000 936.000 SY SODDING REINFORCED 12.9834 12.9431 $12,114.75
660E25000 6,154.000 SY SODDING STAKED 6.1764 4.3626 $26,847.70
660E30000 492.800 SY SODDING UNSTAKED 6.7021 5.9297 $2,922.16
661E00500 788.000 CY MULCH 50.3172 52.1016 $41,056.09
661E00501 2,392.000 CY MULCH, AS PER PLAN 71.3883 52.7559 $126,192.00
661E12000 705.000 EACH GROUNDCOVER AND VINES, 1 YEAR, POTTED 29.6133 24.4200 $17,216.10
661E14000 10,324.000 EACH PERENNIALS 15.6256 15.4182 $159,177.10
661E14001 2,708.000 EACH PERENNIALS, AS PER PLAN 26.5678 22.5231 $60,992.45
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
200 | P a g e
661E20020 202.000 EACH DECIDUOUS SHRUB, 18" HEIGHT 29.6771 35.6337 $7,198.00
661E20021 459.000 EACH DECIDUOUS SHRUB, 18" HEIGHT, AS PER PLAN 51.5094 52.1820 $23,951.55
661E20040 129.000 EACH DECIDUOUS SHRUB, 2' HEIGHT 45.4876 48.0425 $6,197.48
661E20041 814.000 EACH DECIDUOUS SHRUB, 2' HEIGHT, AS PER PLAN 56.2041 49.9584 $40,666.10
661E20060 75.000 EACH DECIDUOUS SHRUB, 3' HEIGHT 44.6380 32.0000 $2,400.00
661E20070 67.000 EACH DECIDUOUS SHRUB, 30" HEIGHT 42.2454 41.7142 $2,794.85
661E20071 246.000 EACH DECIDUOUS SHRUB, 30" HEIGHT, AS PER PLAN 64.0000 60.0000 $14,760.00
661E20080 83.000 EACH DECIDUOUS SHRUB, 4' HEIGHT 62.5000 58.5000 $4,855.50
661E30020 612.000 EACH EVERGREEN SHRUB, 15" HEIGHT 26.8740 29.0000 $17,748.00
661E30041 70.000 EACH EVERGREEN SHRUB, 18" HEIGHT, AS PER PLAN 35.8380 32.5000 $2,275.00
661E30060 19.000 EACH EVERGREEN SHRUB, 2' HEIGHT 83.5433 64.5600 $1,226.64
661E30061 499.000 EACH EVERGREEN SHRUB, 2' HEIGHT, AS PER PLAN 56.0760 52.9138 $26,404.00
661E31000 368.000 GAL LANDSCAPE WATERING 1.0000 0.5000 $184.00
661E40040 106.000 EACH DECIDUOUS TREE, 1" CALIPER 163.9161 142.4528 $15,100.00
661E40060 14.000 EACH DECIDUOUS TREE, 1-1/2" CALIPER 403.5198 391.4286 $5,480.00
661E40080 32.000 EACH DECIDUOUS TREE, 2" CALIPER 328.3368 337.5000 $10,800.00
661E40081 63.000 EACH DECIDUOUS TREE, 2" CALIPER, AS PER PLAN 379.4466 309.2500 $19,482.75
661E40100 173.000 EACH DECIDUOUS TREE, 2-1/2" CALIPER 245.1206 279.0462 $48,275.00
661E40101 141.000 EACH DECIDUOUS TREE, 2-1/2" CALIPER, AS PER 453.7547 452.6057 $63,817.40
PLAN
661E40120 112.000 EACH DECIDUOUS TREE, 3" CALIPER 405.5916 366.1171 $41,005.12
661E40121 29.000 EACH DECIDUOUS TREE, 3" CALIPER, AS PER PLAN 298.7150 210.0700 $6,092.03
661E40140 67.000 EACH DECIDUOUS TREE, 4 " CALIPER 752.0732 789.9363 $52,925.73
661E50121 746.000 EACH EVERGREEN TREE, 6' HEIGHT, AS PER PLAN 145.8975 104.2950 $77,804.07
661E50141 46.000 EACH EVERGREEN TREE, 7' HEIGHT, AS PER PLAN 363.3000 450.0000 $20,700.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
201 | P a g e
661E50161 15.000 EACH EVERGREEN TREE, 8' HEIGHT, AS PER PLAN 249.6300 177.2700 $2,659.05
661E99500 8.000 EACH LANDSCAPING, MISC.: 4,819.3470 4,011.2038 $32,089.63
661E99900 5,315.000 EACH PLANTING, MISC.: 34.2051 33.4563 $177,820.40
661E99920 4,047.000 SF PLANTING, MISC.: 17.7604 12.0220 $48,653.00
661E99930 4,613.000 SY PLANTING, MISC.: 1.9825 2.5000 $11,532.50
661E99940 2.000 LS PLANTING, MISC.: 14,785.6250 19,875.0000 $39,750.00
661E99950 970.000 FT PLANTING, MISC.: 33.4106 38.4882 $37,333.60
661E99960 695.000 TON PLANTING, MISC.: 421.9569 412.6854 $286,816.35
662E30001 365.000 MGAL LANDSCAPE WATERING, AS PER PLAN 193.2389 493.6007 $180,164.25
662E30100 1.000 LS LANDSCAPE WATERING 577.0089 350.0000 $350.00
662E31000 31,596.000 GAL LANDSCAPE WATERING 0.6821 0.7103 $22,442.00
662E31001 224,200.000 GAL LANDSCAPE WATERING, AS PER PLAN 0.1046 0.1146 $25,685.80
666E10000 37.000 EACH PRUNING EXISTING TREE, 8 TO 16-INCH 235.1527 168.2432 $6,225.00
DIAMETER
666E10010 37.000 EACH PRUNING EXISTING TREE, 16 TO 24-INCH 310.2671 206.7568 $7,650.00
DIAMETER
666E10020 35.000 EACH PRUNING EXISTING TREE, 24 TO 36-INCH 293.9286 270.7143 $9,475.00
DIAMETER
666E10030 35.000 EACH PRUNING EXISTING TREE, 36 INCHES AND 368.9286 345.7143 $12,100.00
OVER
670E00500 19,743.000 SY SLOPE EROSION PROTECTION 1.9107 1.5071 $29,754.25
670E00510 691.000 SY SLOPE EROSION PROTECTION MAT, TYPE A 2.0400 2.4000 $1,658.40
670E00520 995.000 SY SLOPE EROSION PROTECTION MAT, TYPE B 2.3220 2.1000 $2,089.50
670E00550 2,066.000 SY SLOPE EROSION PROTECTION MAT, TYPE E 3.3525 2.7372 $5,655.00
670E00700 77,919.000 SY DITCH EROSION PROTECTION 1.6373 1.5168 $118,188.00
670E00710 43,988.000 SY DITCH EROSION PROTECTION MAT, TYPE A 1.6354 1.4151 $62,248.50
670E00720 4,440.000 SY DITCH EROSION PROTECTION MAT, TYPE B 1.7427 1.4983 $6,652.60
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
202 | P a g e
670E00730 524.000 SY DITCH EROSION PROTECTION MAT, TYPE C 2.8284 2.2459 $1,176.87
670E00750 258.000 SY DITCH EROSION PROTECTION MAT, TYPE E 5.1000 2.3000 $593.40
670E00760 612.000 SY DITCH EROSION PROTECTION MAT, TYPE F 1.9125 3.0000 $1,836.00
671E14000 26,640.000 SY EROSION CONTROL MAT 1.6478 2.2327 $59,480.00
671E15000 8,562.000 SY EROSION CONTROL MAT, TYPE A 1.8373 1.9965 $17,093.85
671E15010 2,235.000 SY EROSION CONTROL MAT, TYPE B 2.3861 2.4431 $5,460.30
671E15020 2,430.000 SY EROSION CONTROL MAT, TYPE C 3.7000 6.0000 $14,580.00
671E15040 11,899.000 SY EROSION CONTROL MAT, TYPE E 2.2578 2.7963 $33,273.40
671E15060 17,006.000 SY EROSION CONTROL MAT, TYPE G 3.2164 1.8659 $31,731.70
680E12500 740.000 FT SPECIAL - SNOW FENCE - TREE PROTECTION 12.4563 20.0000 $14,800.00
680E14550 21.000 EACH SPECIAL - TRASH RECEPTACLE 1,097.3375 1,320.0000 $27,720.00
680E16500 5.000 EACH SPECIAL - 6' WOOD BENCH 1,293.0833 1,378.0000 $6,890.00
680E44310 7,318.000 FT SPECIAL - 4" FORCE MAIN 30.3621 26.2062 $191,777.00
690E12000 836.000 SY SPECIAL - FILTER FABRIC 2.7503 1.1972 $1,000.85
690E12010 9,718.000 SY SPECIAL - GEOTEXTILE FABRIC 2.1543 2.1406 $20,802.00
690E12020 18,810.000 SY SPECIAL - GEOGRID 3.0109 2.9601 $55,679.84
690E12050 108,104.000 SY SPECIAL - REINFORCED MESH FOR TRANSVERSE 12.2707 11.8591 $1,282,011.63
AND/OR LONGITUDINAL JOINTS AND CRACKS
690E12060 6,485.000 SY SPECIAL - PAVEMENT OVERLAY FABRIC 14.3761 14.3347 $92,960.60
COMPOSITE
690E12150 3,969.000 GAL SPECIAL - ASPHALT REJUVENATING AGENT 19.7500 19.7500 $78,387.75
690E12160 3.000 LS SPECIAL - TESTING 4,200.0000 666.6667 $2,000.00
690E13000 3,290.000 FT SPECIAL - RUMBLE STRIPS 10.7501 9.9593 $32,766.00
690E20010 21.000 LS SPECIAL - AS-BUILT CONSTRUCTION PLANS 12,786.2479 11,650.0476 $244,651.00
690E20020 21.000 LS SPECIAL - FIELD SURVEYS 20,801.6250 17,013.3333 $357,280.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
203 | P a g e
690E20030 1.000 LS SPECIAL - UTILITY RELOCATION 100,615.3250 56,500.0000 $56,500.00
690E20040 12.000 LS SPECIAL - PRELIMINARY DESIGN 184,983.1333 185,500.0000 $2,226,000.00
690E20050 14.000 LS SPECIAL - FINAL DESIGN 110,920.4815 110,778.5714 $1,550,900.00
690E20060 1.000 LS SPECIAL - FINAL PLAN SUBMISSION 9,694.2857 3,000.0000 $3,000.00
690E20080 1.000 LS SPECIAL - SUBSURFACE INVESTIGATIONS 28,016.6667 20,000.0000 $20,000.00
690E20200 9.000 LS SPECIAL - PRELIMINARY PLANS FOR 215,514.3000 254,651.0000 $2,291,859.00
DESIGN-BUILD
690E20210 8.000 LS SPECIAL - FINAL PLANS FOR DESIGN-BUILD 169,311.8889 165,812.5000 $1,326,500.00
690E20220 22.000 LS SPECIAL - CONSTRUCTION PLANS FOR 50,841.6104 45,540.5000 $1,001,891.00
DESIGN-BUILD
690E20240 7.000 LS SPECIAL - ROADWAY 986,532.0578 964,153.7171 $6,749,076.02
690E21000 19.000 LS SPECIAL - MISC.: 4952557.8895 3955232.9763 $75,149,426.55
690E50000 103.000 EACH SPECIAL - MAILBOX SUPPORT 144.7508 153.4816 $15,808.60
690E50100 308.000 EACH SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE 129.5803 122.3301 $37,677.66
690E50200 56.000 EACH SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE 161.3531 157.8761 $8,841.06
690E50300 4.000 EACH SPECIAL - MAILBOX SUPPORT SYSTEM, 188.7900 135.0000 $540.00
MULTIPLE
690E50350 307.000 EACH SPECIAL - MAILBOX REMOVED AND RESET 156.1167 144.2123 $44,273.18
690E50500 224.000 EACH SPECIAL - CONCRETE PARKING BLOCK 102.0258 108.3482 $24,270.00
690E50560 35.000 EACH SPECIAL - BICYCLE RACK 812.2130 694.2000 $24,297.00
690E50600 197.000 EACH SPECIAL - BOLLARD 565.3724 528.9746 $104,208.00
690E50610 1.000 EACH SPECIAL - BOLLARD, HINGED 800.4250 750.0000 $750.00
690E65000 610.000 TON SPECIAL - WORK INVOLVING NON-REGULATED 38.4812 26.7539 $16,319.90
MATERIALS
690E65002 7.000 TON SPECIAL - WORK INVOLVING HAZARDOUS WASTE 209.1667 145.0000 $1,015.00
690E65010 5,953.500 TON SPECIAL - WORK INVOLVING SOLID WASTE 54.0531 42.8540 $255,131.00
690E65016 13,182.000 TON SPECIAL - WORK INVOLVING PETROLEUM 40.7487 36.8392 $485,613.76
CONTAMINATED SOIL
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
204 | P a g e
690E65020 9,772.000 GAL SPECIAL - WORK INVOLVING WATER 3.4487 1.7435 $17,037.00
690E65022 122,000.000 GAL SPECIAL - WORK INVOLVING NON-REGULATED 0.2375 0.2992 $36,500.00
WATER
690E65024 61,122.000 GAL SPECIAL - WORK INVOLVING REGULATED WATER 1.1583 0.9210 $56,290.50
690E65300 15.000 EACH SPECIAL - GROUND WATER MONITORING WELL 1,220.9740 700.0000 $10,500.00
ABANDONMENT
690E65310 9.000 EACH SPECIAL - GROUND WATER MONITORING WELL 1,229.1450 810.0000 $7,290.00
RECONSTRUCTION
690E65400 1.000 EACH SPECIAL - OIL SPILL KIT 687.0000 378.0000 $378.00
690E68000 120.000 CRHR SCALING 599.7857 250.0000 $30,000.00
690E70000 11.000 LS SPECIAL - ENVIRONMENTAL, MISC.: 7,609.2657 6,427.2727 $70,700.00
690E70020 14,930.000 TON SPECIAL - ENVIRONMENTAL, MISC.: 53.9737 30.8640 $460,800.00
690E70030 2,723.000 CY SPECIAL - ENVIRONMENTAL, MISC. 57.0575 65.0000 $176,995.00
690E70090 60,000.000 GAL SPECIAL - ENVIRONMENTAL, MISC.: 0.7460 0.5900 $35,400.00
690E70100 10,310.000 SF SPECIAL - ASBESTOS ABATEMENT 5.3647 3.3337 $34,370.75
690E71000 11.000 LS SPECIAL - ASBESTOS ABATEMENT 8,037.5677 5,064.5109 $55,709.62
690E71050 7.000 EACH SPECIAL - ASBESTOS INSPECTION 492.8571 485.7143 $3,400.00
690E76002 14,440.000 FT SPECIAL - 12" COMPOST FILTER SOCK FOR 4.5102 4.5229 $65,310.00
PERIMETER CONTROL
690E76012 1,710.000 FT SPECIAL - 12" COMPOST FILTER SOCK FOR 6.3103 6.9415 $11,870.00
DITCH CHECKS
690E76022 1,175.000 FT SPECIAL - 12" COMPOST FILTER SOCK FOR 9.3980 13.5851 $15,962.50
INLET PROTECTION
690E76032 960.000 FT SPECIAL - 12" COMPOST FILTER SOCK FOR 7.6667 7.0000 $6,720.00
RUNOFF DIVERSION DIKE
690E91000 2.000 LS SPECIAL - AS-BUILT CONSTRUCTION PLANS 3,657.1429 1,550.0000 $3,100.00
690E98000 1,702,539.000 EACH SPECIAL - MISC.: 1.9616 1.8286 $3,113,229.14
690E98100 71,181.500 FT SPECIAL - MISC.: 41.4422 40.2917 $2,868,025.10
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
205 | P a g e
690E98200 62,633.000 SF SPECIAL - MISC.: 13.9876 13.3234 $834,483.42
690E98300 126,537.000 SY SPECIAL - MISC.: 10.0634 7.9532 $1,006,375.17
690E98400 141.000 LS SPECIAL - MISC.: 53,038.5018 35,973.0232 $5,072,196.27
690E98500 3.000 MILE SPECIAL - MISC.: 3,150.0000 3,150.0000 $9,450.00
690E98600 6,746.000 HOUR SPECIAL - MISC.: 35.4123 32.9128 $222,030.00
690E98700 121,701.000 CY SPECIAL - MISC.: 32.3507 28.9599 $3,524,449.26
690E98800 214,299.000 TON SPECIAL - MISC.: 46.1927 41.2130 $8,831,912.00
690E98900 205,926.000 GAL SPECIAL - MISC.: 3.8582 3.8180 $786,223.63
690E99000 1,707.760 ACRE SPECIAL - MISC.: 90.1824 64.7095 $110,508.23
690E99200 6.000 CF SPECIAL - MISC.: 362.4815 626.0000 $3,756.00
690E99300 8.000 MGAL SPECIAL - MISC.: 8,183.3333 2,500.0000 $20,000.00
690E99400 33,008.000 LB SPECIAL - MISC.: 5.5795 4.8805 $161,095.78
690E99500 519.000 DAY SPECIAL - MISC.: 1,270.0000 985.0000 $511,215.00
690E99550 13.000 MNTH SPECIAL - MISC.: 5,129.0323 5,000.0000 $65,000.00
691E10000 2,974.000 ACRE SPECIAL - HERBICIDAL SPRAYING, WEED AND 51.3889 33.1738 $98,658.92
BRUSH CONTROL FROM ROAD
691E10100 1,970.000 ACRE SPECIAL - HERBICIDAL SPRAYING, WEED AND 44.5872 40.8453 $80,465.32
BRUSH CONTROL OFF ROAD
691E41000 743.000 MILE SPECIAL - HERBICIDAL SPRAYING 159.6763 130.1288 $96,685.72
691E41200 2,448.000 LB SPECIAL - HERBICIDAL SPRAYING 38.6691 16.5614 $40,542.23
691E41900 1,108.430 MILE SPECIAL - HERBICIDAL SPRAYING, GUARDRAIL 229.8070 199.1826 $220,779.94
691E42500 13,000.000 EACH SPECIAL - HERBICIDAL SPRAYING, 1.0040 1.7080 $22,204.00
DELINEATOR, SIGNPOST, LIGHTPOLE AND/OR THEIR FOUNDATIONS
691E50100 440.000 MILE SPECIAL - HERBICIDAL SPRAYING, 68.1828 63.0000 $27,720.00
RIGHT-OF-WAY FENCE
691E60050 2,242.000 QT SPECIAL - HERBICIDAL SPRAYING, MISC.: 82.3724 78.1504 $175,213.14
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
206 | P a g e
691E60060 614.000 OZ SPECIAL - HERBICIDAL SPRAYING, MISC.: 57.8150 18.6300 $11,438.82
691E60300 170.000 MILE SPECIAL - HERBICIDAL SPRAYING, MISC.: 196.8025 197.4682 $33,569.59
692E10100 37,411.010 ACRE SPECIAL - FIRST MOWING 38.8462 35.1161 $1,313,728.65
692E20100 51,961.820 ACRE SPECIAL - SECOND MOWING 35.9581 32.3596 $1,681,463.62
692E30100 37,030.010 ACRE SPECIAL - THIRD MOWING 36.1112 31.6746 $1,172,912.57
692E30270 60,246.620 ACRE SPECIAL - FOURTH MOWING 37.7729 31.6526 $1,906,964.92
692E30284 10,788.240 ACRE SPECIAL - FIFTH MOWING 34.9033 31.2211 $336,820.50
692E30400 14,696.010 ACRE SPECIAL - MOWBACK 40.3799 28.9721 $425,774.22
804E20009 14,575.000 FT FIBER OPTIC CABLE, 72 FIBER, AS PER PLAN 3.2050 2.7100 $39,498.25
804E20010 1,060.000 FT FIBER OPTIC CABLE, ARMORED, 18 FIBER 3.4450 3.5000 $3,710.00
804E20050 838.000 FT FIBER OPTIC CABLE, ARMORED, 48 FIBER 8.7667 9.0250 $7,562.95
804E30000 9.000 EACH FAN-OUT KIT, 6 FIBER 209.0142 128.3500 $1,155.15
804E30001 21.000 EACH FAN-OUT KIT, 6 FIBER, AS PER PLAN 107.0000 105.0000 $2,205.00
804E30011 27.000 EACH FAN-OUT KIT, 12 FIBER, AS PER PLAN 91.9420 30.0000 $810.00
804E32000 4.000 EACH DROP CABLE, 6 FIBER 366.2013 108.0375 $432.15
804E32001 21.000 EACH DROP CABLE, 6 FIBER, AS PER PLAN 237.0000 110.0000 $2,310.00
804E32011 12.000 EACH DROP CABLE, 12 FIBER, AS PER PLAN 526.7260 250.0000 $3,000.00
804E33000 2.000 EACH FIBER OPTIC PATCH CORD, 4 FIBER 172.2944 164.8250 $329.65
804E33001 33.000 EACH FIBER OPTIC PATCH CORD, 4 FIBER, AS PER 117.1382 145.9091 $4,815.00
PLAN
804E34000 2.000 EACH TERMINATION PANEL, 6 FIBER 260.5056 154.2750 $308.55
804E34012 13.000 EACH TERMINATION PANEL, 12 FIBER 228.1909 294.2308 $3,825.00
804E34023 11.000 EACH TERMINATION PANEL, 24 FIBER, AS PER PLAN 1,903.9475 1,508.2500 $16,590.75
804E35000 375.000 EACH FUSION SPLICE 68.9756 51.6982 $19,386.84
804E35001 36.000 EACH FUSION SPLICE, AS PER PLAN 50.2571 48.7000 $1,753.20
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
207 | P a g e
804E36001 113.000 EACH SLACK INSTALLATION, AS PER PLAN 239.7500 55.0000 $6,215.00
804E37000 9.000 EACH SPLICE ENCLOSURE 2,047.5994 1,064.6922 $9,582.23
804E37001 62.000 EACH SPLICE ENCLOSURE, AS PER PLAN 1,353.8573 906.4468 $56,199.70
804E37500 44.000 EACH FIBER OPTIC CONNECTOR 69.8748 87.5773 $3,853.40
804E37501 357.000 EACH FIBER OPTIC CONNECTOR, AS PER PLAN 73.7388 95.5294 $34,104.00
804E37701 3.000 LS FIBER OPTIC CABLE TESTING, AS PER PLAN 6,034.8821 6,341.4033 $19,024.21
804E38000 2.000 EACH FIBER OPTIC CABLE MODEM 1,445.4778 1,449.1500 $2,898.30
804E98000 91,169.000 FT FIBER OPTIC CABLE, MISC.: 3.9581 4.3676 $398,186.23
804E98100 66.000 EACH FIBER OPTIC CABLE, MISC.: 1,965.7557 1,721.2902 $113,605.15
815E30000 25.000 EACH SPREAD SPECTRUM RADIO 2,514.9786 2,327.8960 $58,197.40
815E30001 21.000 EACH SPREAD SPECTRUM RADIO, AS PER PLAN 3,200.7129 2,570.8581 $53,988.02
815E30100 3.000 LS TRAINING FOR SPREAD SPECTRUM RADIO 1,166.3378 1,241.6667 $3,725.00
816E30000 40.000 EACH VIDEO DETECTION SYSTEM 16,684.1294 15,105.8460 $528,704.61
816E30001 64.000 EACH VIDEO DETECTION SYSTEM, AS PER PLAN 9,732.0436 8,922.4981 $571,039.88
816E30100 6.000 LS TRAINING FOR VIDEO DETECTION SYSTEM 1,243.4429 1,087.5000 $6,525.00
817E00100 134.460 MILE EDGE LINE, 4" 939.3013 945.8697 $127,181.64
817E00104 50.760 MILE EDGE LINE, 6" 1,260.3305 1,264.9645 $64,209.60
817E00200 11.820 MILE LANE LINE, 4" 662.0568 568.2741 $6,717.00
817E00204 24.760 MILE LANE LINE, 6" 580.5125 531.1389 $13,151.00
817E00300 67.030 MILE CENTER LINE 1,202.4197 1,182.4447 $79,259.27
823E10000 71.000 LS CONSTRUCTION LAYOUT STAKES 20,553.7565 14,963.7183 $1,062,424.00
823E10001 3.000 LS CONSTRUCTION LAYOUT STAKES, AS PER PLAN 8,304.1818 7,428.6667 $22,286.00
823E11001 2.000 LS PROVIDING ELECTRONIC INSTRUMENTATION, AS 23,599.9144 7,640.0000 $15,280.00
PER PLAN
823E38500 64.000 EACH MONUMENT ASSEMBLY 814.6670 817.0313 $52,290.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
208 | P a g e
823E38501 8.000 EACH MONUMENT ASSEMBLY, AS PER PLAN 599.0000 555.0000 $4,440.00
823E39500 10.000 EACH MONUMENT BOX ADJUSTED TO GRADE 423.3333 412.5000 $4,125.00
823E39501 1.000 EACH MONUMENT BOX ADJUSTED TO GRADE, AS PER 299.0000 400.0000 $400.00
PLAN
823E40500 114.000 EACH REFERENCE MONUMENT 359.4937 372.6316 $42,480.00
823E40520 113.000 EACH RIGHT-OF-WAY MONUMENT 372.4741 474.5044 $53,619.00
823E40900 1.000 EACH MONUMENT, MISC.: 585.0000 200.0000 $200.00
823E99000 2.000 LS SPECIAL - CONSTRUCTION LAYOUT STAKES 11,100.0000 9,500.0000 $19,000.00
832E15000 142.000 LS STORM WATER POLLUTION PREVENTION PLAN 9,100.1969 7,276.3604 $1,033,243.18
832E30000 13315720.000 EACH EROSION CONTROL 1.0003 0.9996 $13,309,750.00
832E30001 17,600.000 EACH EROSION CONTROL, AS PER PLAN 1.0000 1.0000 $17,600.00
832E99100 7,745,500.000 EACH SPECIAL - CONSTRUCTION EROSION CONTROL 1.0000 1.0000 $7,745,500.00
834E11000 4,940.000 SF CONDUIT RENEWAL USING RESIN BASED LINER 27.0000 27.0000 $133,380.00
835E10000 972.000 FT EXFILTRATION TRENCH, TYPE A 115.7588 107.8658 $104,845.60
835E10001 224.000 FT EXFILTRATION TRENCH, TYPE A, AS PER PLAN 110.7500 113.0000 $25,312.00
835E10010 136.000 FT EXFILTRATION TRENCH, TYPE B 127.3556 101.1765 $13,760.00
835E10020 424.000 FT EXFILTRATION TRENCH, TYPE C 116.4239 135.7547 $57,560.00
836E10000 29,393.000 SY SEEDING AND EROSION CONTROL WITH TURF 4.3175 3.7267 $109,539.14
REINFORCING MAT, TYPE 1
836E10020 1,706.000 SY SEEDING AND EROSION CONTROL WITH TURF 2.6900 1.5977 $2,725.60
REINFORCING MAT, TYPE 2
836E10030 5,191.000 SY SEEDING AND EROSION CONTROL WITH TURF 7.8290 10.6319 $55,190.18
REINFORCING MAT, TYPE 3
837E10000 94.000 FT LINER PIPE 95.2000 80.5000 $7,567.00
837E10001 1,027.000 FT LINER PIPE, AS PER PLAN 363.2362 445.4012 $457,427.00
837E20000 711.000 CY BACKFILL FOR LINER PIPE 144.2121 164.3179 $116,830.00
837E20001 129.000 CY BACKFILL FOR LINER PIPE, AS PER PLAN 186.4200 150.0000 $19,350.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
209 | P a g e
838E20700 392.000 CY GABIONS 189.1786 200.0000 $78,400.00
838E20701 400.000 CY GABIONS, AS PER PLAN 337.6846 360.3500 $144,140.00
839E30000 21,107.000 FT TRENCH DRAIN WITH STANDARD GRATE 64.1611 59.2794 $1,251,210.00
839E30100 116.000 FT TRENCH DRAIN WITH PEDESTRIAN GRATE 166.4474 188.4483 $21,860.00
840E20000 54,833.000 SF MECHANICALLY STABILIZED EARTH WALL 21.6161 22.0521 $1,209,184.04
840E20001 153,622.000 SF MECHANICALLY STABILIZED EARTH WALL, AS 24.0893 26.9687 $4,142,984.00
PER PLAN
840E21000 46,393.000 CY WALL EXCAVATION 19.0481 11.9206 $553,030.57
840E22000 14,488.000 SY FOUNDATION PREPARATION 19.3332 15.7413 $228,060.29
840E22001 3,121.000 SY FOUNDATION PREPARATION, AS PER PLAN 23.2381 14.0000 $43,694.00
840E23000 93,076.000 CY SELECT GRANULAR BACKFILL 37.8354 35.1602 $3,272,575.21
840E23050 6,428.000 CY NATURAL SOIL 11.0614 11.9667 $76,922.11
840E24000 84.000 CY POROUS BACKFILL WITH FILTER FABRIC 66.2019 56.4286 $4,740.00
840E25000 1,000.000 FT DRAINAGE PIPE 7.5333 7.5000 $7,500.00
840E25010 16,394.000 FT 6" DRAINAGE PIPE, PERFORATED 7.7538 7.8335 $128,421.98
840E25020 852.000 FT 6" DRAINAGE PIPE, NON-PERFORATED 18.3069 23.3170 $19,866.05
840E26000 7,728.000 FT CONCRETE COPING 107.3780 98.4085 $760,501.03
840E26001 4,044.000 FT CONCRETE COPING, AS PER PLAN 116.1954 101.2760 $409,560.00
840E26050 111,318.000 SF AESTHETIC SURFACE TREATMENT 1.2805 1.0763 $119,814.00
840E27000 95.000 DAY ON-SITE ASSISTANCE 361.1104 365.6985 $34,741.36
840E28000 14.000 LS SGB INSPECTION AND COMPACTION TESTING 12,642.9426 14,759.0357 $206,626.50
842E10000 100.000 LB CORRECTING ELEVATION OF CONCRETE 16.2500 10.0000 $1,000.00
APPROACH SLABS WITH HIGH DENSITY POLYURETHANE
843E50000 6,419.000 SF PATCHING CONCRETE STRUCTURES WITH 72.8538 67.0996 $430,712.50
TROWELABLE MORTAR
843E50001 238.000 SF PATCHING CONCRETE STRUCTURES WITH 77.6924 87.1756 $20,747.80
TROWELABLE MORTAR, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
210 | P a g e
845E61000 3.000 MNHR GRINDING FINS, TEARS, SLIVERS ON 133.7143 130.0000 $390.00
EXISTING STRUCTURAL STEEL
847E10000 1,064.000 SY MICRO SILICA MODIFIED CONCRETE OVERLAY 84.2120 72.9840 $77,655.00
847E10001 19,127.000 SY MICRO SILICA MODIFIED CONCRETE OVERLAY, 52.7640 48.7117 $931,708.00
AS PER PLAN
847E10200 1,306.000 SY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 101.5750 95.2106 $124,345.00
847E10201 4,583.000 SY SUPERPLASTICIZED DENSE CONCRETE OVERLAY, 41.4149 28.7091 $131,574.00
AS PER PLAN
847E20000 23.000 CY MICRO SILICA MODIFIED CONCRETE OVERLAY 433.6238 160.8696 $3,700.00
(VARIABLE THICKNESS)
847E20001 410.000 CY MICRO SILICA MODIFIED CONCRETE OVERLAY 218.4353 145.3049 $59,575.00
(VARIABLE THICKNESS), AS PER PLAN
847E20200 32.000 CY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 196.6608 245.3125 $7,850.00
(VARIABLE THICKNESS)
847E20201 136.000 CY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 222.2268 168.3971 $22,902.00
(VARIABLE THICKNESS), AS PER PLAN
847E30000 19.000 LS TEST SLAB 818.4365 671.3158 $12,755.00
847E30200 206.000 CY FULL DEPTH REPAIR 179.0377 139.4078 $28,718.00
847E30201 8.000 CY FULL DEPTH REPAIR, AS PER PLAN 253.9583 100.0000 $800.00
847E30300 4,493.000 SY WEARING COURSE REMOVED, ASPHALT 9.0761 12.2404 $54,996.00
847E30301 1,919.000 SY WEARING COURSE REMOVED, ASPHALT, AS PER 10.0833 9.0000 $17,271.00
PLAN
847E30400 6,212.000 SY EXISTING CONCRETE OVERLAY REMOVED 17.6578 18.1389 $112,679.00
847E30401 17,855.000 SY EXISTING CONCRETE OVERLAY REMOVED, AS 14.2456 13.7610 $245,702.50
PER PLAN
847E50000 4,368.000 SY HAND CHIPPING 65.2032 54.6559 $238,737.00
848E10000 16,766.000 SY MICRO SILICA MODIFIED CONCRETE OVERLAY 43.8165 37.2363 $624,303.40
USING HYDRODEMOLITION
848E10001 30,894.000 SY MICRO SILICA MODIFIED CONCRETE OVERLAY 46.7479 45.4154 $1,403,062.00
USING HYDRODEMOLITION, AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
211 | P a g e
848E10100 584.000 SY LATEX MODIFIED CONCRETE OVERLAY USING 105.3750 85.0000 $49,640.00
HYDRODEMOLITION
848E10101 987.000 SY LATEX MODIFIED CONCRETE OVERLAY USING 75.5400 77.0000 $75,999.00
HYDRODEMOLITION, AS PER PLAN
848E10200 7,289.000 SY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 56.6223 52.8677 $385,353.00
USING HYDRODEMOLITION
848E10201 9,503.000 SY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 61.9280 56.8661 $540,398.22
USING HYDRODEMOLITION, AS PER PLAN
848E20000 44,277.000 SY SURFACE PREPARATION USING 56.2447 55.1265 $2,440,836.04
HYDRODEMOLITION
848E20001 21,613.000 SY SURFACE PREPARATION USING HYDRO 63.3725 63.0673 $1,363,074.00
DEMOLITION, AS PER PLAN
848E30000 436.000 CY MICRO SILICA MODIFIED CONCRETE OVERLAY 195.1910 174.4415 $76,056.50
(VARIABLE THICKNESS), MATERIAL ONLY
848E30001 596.000 CY MICRO SILICA MODIFIED CONCRETE OVERLAY 171.4222 173.2349 $103,248.00
(VARIABLE THICKNESS), MATERIAL ONLY, AS
PER PLAN
848E30100 30.000 CY LATEX MODIFIED CONCRETE OVERLAY 674.8491 689.6667 $20,690.00
(VARIABLE THICKNESS), MATERIAL ONLY
848E30200 659.000 CY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 147.3461 145.9105 $96,155.00
(VARIABLE THICKNESS), MATERIAL ONLY
848E30201 130.650 CY SUPERPLASTICIZED DENSE CONCRETE OVERLAY 191.9131 192.9943 $25,214.70
(VARIABLE THICKNESS), MATERIAL ONLY, AS PER PLAN
848E50000 3,014.000 SY HAND CHIPPING 94.4598 78.3348 $236,101.02
848E50001 84.000 SY HAND CHIPPING, AS PER PLAN 69.5714 69.5714 $5,844.00
848E50100 51.000 LS TEST SLAB 1,081.4359 831.4078 $42,401.80
848E50101 2.000 LS TEST SLAB, AS PER PLAN 350.0000 350.0000 $700.00
848E50200 300.500 CY FULL-DEPTH REPAIR 363.6146 266.4459 $80,067.00
848E50201 12.000 CY FULL DEPTH REPAIR, AS PER PLAN 529.6579 200.0000 $2,400.00
848E50300 14,773.000 SY WEARING COURSE REMOVED, ASPHALT 5.7818 5.6901 $84,059.86
848E50301 2,952.000 SY WEARING COURSE REMOVED, ASPHALT, AS PER 9.2101 13.7751 $40,664.00
PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
212 | P a g e
848E50320 30,125.000 SY EXISTING CONCRETE OVERLAY REMOVED 11.8344 11.2662 $339,394.81
848E50321 6,280.000 SY EXISTING CONCRETE OVERLAY REMOVED, AS 16.8202 18.5747 $116,648.95
PER PLAN
848E50340 4,972.000 SY REMOVAL OF DEBONDED OR DETERIORATED 36.1156 24.0758 $119,705.10
EXISTING VARIABLE THICKNESS CONCRETE OVERLAY
848E50341 292.000 SY REMOVAL OF DEBONDED OR DETERIORATED 65.3100 18.4863 $5,398.00
EXISTING VARIABLE THICKNESS CONCRETE OVERLAY, AS PER PLAN
848E90000 107.000 SY OVERLAY, MISC.: 72.8043 65.7500 $7,035.25
848E91000 7.000 CY OVERLAY, MISC.: 119.9729 191.0000 $1,337.00
848E99000 252.000 CY SPECIAL - CONCRETE OVERLAY, VARIABLE 100.0000 100.0000 $25,200.00
THICKNESS, MATERIAL ONLY
848E99100 5.000 LS SPECIAL - BRIDGE DECK CONCRETE OVERLAYS 194,440.0000 194,440.0000 $972,200.00
849E10000 18.000 LS DAMAGE ASSESSMENT 2,279.1729 786.7983 $14,162.37
849E10500 16.000 LS SURFACE PREPARATION 4,550.4745 2,899.1750 $46,386.80
849E10600 82.000 HOUR REPAIRING DAMAGED MEMBERS BY GRINDING 180.5882 160.2915 $13,143.90
849E10700 14.000 LS STRAIGHTENING DAMAGED MEMBERS 19,596.1849 18,774.0093 $262,836.13
861E10000 83,682.000 SY GEOGRID FOR SUBGRADE STABILIZATION 2.0977 2.1591 $180,673.75
861E10001 5,530.000 SY GEOGRID FOR SUBGRADE STABILIZATION, AS 5.5389 4.6000 $25,438.00
PER PLAN
862E00500 200.000 HOUR SCALING 405.5000 207.5000 $41,500.00
862E00650 13,255.000 SY SPECIAL - STEEL WIRE MESH 50.5000 42.5000 $563,337.50
863E00100 2,832.000 SY GEOGRID, TYPE P1 7.1087 3.4087 $9,653.40
863E00400 12,826.000 SY GEOGRID, TYPE P4 3.5650 3.6300 $46,558.38
863E00600 1,101.000 SY GEOGRID, TYPE S1 7.2967 3.3060 $3,639.89
863E00700 5,020.000 SY GEOGRID, TYPE S2 2.5850 2.8200 $14,156.40
863E00800 4,213.000 CY REINFORCED EMBANKMENT 32.7802 12.7794 $53,839.77
866E00100 58.000 EACH GROUND ANCHOR, 3,527.5287 3,750.0000 $217,500.00
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
213 | P a g e
866E00400 4.000 EACH PERFORMANCE TEST 1,220.8333 1,550.0000 $6,200.00
873E22000 14.390 MILE WORK ZONE EDGE LINE, CLASS I 1,225.0000 1,250.0000 $17,987.50
878E25000 33.000 LS INSPECTION AND COMPACTION TESTING OF 21,919.7047 22,365.1552 $738,050.12
UNBOUND MATERIALS
880E15000 115,210.000 CY ASPHALT CONCRETE (7 YEAR WARRANTY) 101.6269 91.5313 $10,545,325.00
882E10000 358,522.000 SY SINGLE CHIP SEAL WITH WARRANTY 1.6167 1.1800 $423,055.96
895E10010 5.000 EACH MANUFACTURED WATER QUALITY STRUCTURE, 17,171.6261 11,080.0000 $55,400.00
TYPE 1
895E10020 3.000 EACH MANUFACTURED WATER QUALITY STRUCTURE, 20,637.0921 15,043.1333 $45,129.40
TYPE 2
895E10040 1.000 EACH MANUFACTURED WATER QUALITY STRUCTURE, 30,666.6667 21,000.0000 $21,000.00
TYPE 4
896E10300 268,426.000 SY PORTLAND CEMENT CONCRETE PAVEMENT, 14" 51.1794 47.4093 $12,725,881.10
THICK (REINFORCED PER 451) (7 YEAR WARRANTY)
898E10200 6,642.000 CY QC/QA CONCRETE, CLASS QSC2, 709.9759 600.1611 $3,986,270.00
SUPERSTRUCTURE (DECK)
898E10201 5,156.000 CY QC/QA CONCRETE, CLASS QSC2, 562.3078 583.0178 $3,006,040.00
SUPERSTRUCTURE (DECK), AS PER PLAN
898E10210 9,088.200 CY QC/QA CONCRETE, CLASS QSC2, 641.5003 601.7862 $5,469,153.52
SUPERSTRUCTURE (DECK)
898E10211 22,970.000 CY QC/QA CONCRETE, CLASS QSC2, 677.3185 566.9495 $13,022,831.00
SUPERSTRUCTURE (DECK), AS PER PLAN
898E10220 2,454.000 CY QC/QA CONCRETE, CLASS QSC2, 707.1085 721.7202 $1,771,101.44
SUPERSTRUCTURE (DECK)
898E10221 168.000 CY QC/QA CONCRETE, CLASS QSC2, 654.6667 590.0000 $99,120.00
SUPERSTRUCTURE (DECK), AS PER PLAN
898E10230 439.000 CY QC/QA CONCRETE, CLASS QSC2, 683.6798 623.6902 $273,800.00
SUPERSTRUCTURE (DECK)
898E10231 344.000 CY QC/QA CONCRETE, CLASS QSC2, 610.4303 682.7371 $234,861.55
SUPERSTRUCTURE (DECK), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
214 | P a g e
898E10688 268.000 SY QC/QA CONCRETE, CLASS QSC2, 195.1253 167.5000 $44,890.00
SUPERSTRUCTURE (APPROACH SLAB), (T=12")
898E10689 4,877.000 SY QC/QA CONCRETE, CLASS QSC2, 137.2676 146.1146 $712,600.87
SUPERSTRUCTURE (APPROACH SLAB), (T=12"), AS PER PLAN
898E10702 448.000 SY QC/QA CONCRETE, CLASS QSC2, 213.0044 199.9554 $89,580.00
SUPERSTRUCTURE (APPROACH SLAB), (T=13")
898E10703 142.000 SY QC/QA CONCRETE, CLASS QSC2, 195.2556 195.0000 $27,690.00
SUPERSTRUCTURE (APPROACH SLAB), (T=13"),AS PER PLAN
898E10704 5,084.800 SY QC/QA CONCRETE, CLASS QSC2, 218.6765 217.0573 $1,103,693.00
SUPERSTRUCTURE (APPROACH SLAB), (T=15")
898E10705 17,407.000 SY QC/QA CONCRETE, CLASS QSC2, 220.8787 213.7627 $3,720,967.40
SUPERSTRUCTURE (APPROACH SLAB), (T=15"),
AS PER PLAN
898E10708 1,841.000 SY QC/QA CONCRETE, CLASS QSC2, 247.3064 221.8658 $408,455.00
SUPERSTRUCTURE (APPROACH SLAB), (T=17")
898E10709 4,542.000 SY QC/QA CONCRETE, CLASS QSC2, 278.0210 278.5568 $1,265,205.00
SUPERSTRUCTURE (APPROACH SLAB), (T=17"),
AS PER PLAN
898E11000 2,431.200 CY QC/QA CONCRETE, CLASS QSC2, 498.8636 468.8355 $1,139,832.76
SUPERSTRUCTURE (PARAPET)
898E11001 6,061.000 CY QC/QA CONCRETE, CLASS QSC2, 615.4811 623.5143 $3,779,120.24
SUPERSTRUCTURE (PARAPET), AS PER PLAN
898E11100 319.000 CY QC/QA CONCRETE, CLASS QSC2, 865.5675 642.1305 $204,839.64
SUPERSTRUCTURE
898E11101 184.000 CY QC/QA CONCRETE, CLASS QSC2, 657.9903 575.8696 $105,960.00
SUPERSTRUCTURE, AS PER PLAN
898E20000 2,300.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 605.4853 619.0222 $1,423,750.96
898E20001 5,575.000 CY QC/QA CONCRETE, CLASS QSC1, 337.0921 301.7695 $1,682,365.00
SUBSTRUCTURE, AS PER PLAN
898E20100 3,988.600 CY QA/QC CONCRETE, CLASS QSC1, SUBSTRUCTURE 679.0935 603.0352 $2,405,266.31
(PIER ABOVE FOOTING)
898E20101 1,808.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 703.5188 637.5166 $1,152,630.00
(PIER ABOVE FOOTING), AS PER PLAN
Summary of Contracts Awarded for Calendar Year 2013 by Item
Item Quantity U/M Item Description Avg Unit Avg Unit Total Amt
Number Price Bid Price Awded Awarded
215 | P a g e
898E20110 224.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 1,135.6033 1,137.8125 $254,870.00
(PIER CAP)
898E20130 184.000 CY QC/QA CONCRETE, CLASS QSC2, SUBSTRUCTURE 1,178.0103 1,062.2826 $195,460.00
(CAPPED PILE PIER)
898E20150 2,092.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 543.6424 380.3309 $795,652.15
(ABUTMENT)
898E20151 4,077.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 537.1702 535.6601 $2,183,886.40
(ABUTMENT), AS PER PLAN
898E20160 4,015.200 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 522.6216 477.0262 $1,915,355.50
(ABUTMENT INCLUDING FOOTING)
898E20161 3,644.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 529.7191 408.8005 $1,489,669.00
(ABUTMENT INCLUDING FOOTING), AS PER
PLAN
898E20300 4,389.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 301.0732 275.6965 $1,210,032.10
(FOOTING)
898E20301 2,607.000 CY QC/QA CONCRETE, CLASS QSC1, SUBSTRUCTURE 303.7680 230.5218 $600,970.30
(FOOTING), AS PER PLAN
898E98000 8,972.000 CY QC/QA CONCRETE, MISC.: 649.9356 606.6559 $5,442,917.00
900E10000 9,977.000 FT SPECIAL - RAIL ITEM, MISC.: 16.6830 19.1438 $190,998.09
900E12000 17,904.000 TKFT SPECIAL - RAIL ITEM, MISC.: 80.6595 88.0677 $1,576,763.52
900E16000 5,450.000 TON SPECIAL - RAIL ITEM, MISC.: 41.2071 35.3274 $192,534.27
900E19000 10,375.000 CY SPECIAL - RAIL ITEM, MISC.: 36.0474 36.5950 $379,673.00
950E50000 122.000 LS SPECIAL - FACILITIES, MISC.: 49,415.0982 43,551.4754 $5,313,280.00
950E51000 113.000 EACH SPECIAL - FACILITIES, MISC.: 1,180.0839 1,216.2630 $137,437.72
990E25400 1.000 LS LUMP SUM ADJUSTMENT - GENERAL / OTHER 64,500.0000 2,000.0000 $2,000.00
ITEMS
Total $1,871,181,806.14