details of contracts awarded upto january, 2006 from the...
TRANSCRIPT
Details of Contracts Awarded in April, 2006 from the Corporate Office
Tender Number
Date of Opening
Description of Item/Work Contract No. & date of
award
Contractor's Name
Quantity (for supply contract)Estimated Cost
(for Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tenderered Cost (for
Engg./Elect./ S&T/Mech.)
Value of Contract
Scheduled completion date
VNL/VM-MV/Chennai/01 dated Nov.21, 2005
09.01.06 Gauge Conversion of Metre Gauge Railway Line to Broad Gauge Line of Villupuram-Mayiladuturai Section on Southern Railway including all permanent way works including supply of ballast, P.Way material (except Rails and PSC Sleepers), connected electrical works in the entire section including OHE works in Villupuram yard, all civil works for bridges, buildings, footover bridges, platforms, earthwork, etc. and signaling and telecommunication works in the entire section from Villupuram – Mayiladuturai (122 kms)
17th April ‘06 M/s Tata-Kalindi-Unity, Infra Projects Ltd. (JV), Suryodaya 1-10-60/3, Begumpet, HYDERABAD-500 016
185.72 cr. 182.23 cr. 182.23 cr. 16.01.08
Details of Contracts Awarded upto January, 2006 from the Corporate Office
Tender Number Date of Opening
Description of Item/Work
Contract No. & date of award
Contractor's Name
Quantity (for supply contract) Estimated Cost (for Engg./Elect./S&T/Mech.)
Rate (for supply contract) Tenderered Cost (for Engg./Elect./S&T/Mech.)
Value of Contract
Scheduled completion date
C/DEE-RE/CEE dt.07.07.05 14.07.05
Manufacture and Supply of PSC Monoblock Sleepers for BG (1673 mm) to RDSO drawing No. T. 2496 to suit 60 kg UIC Rail as per IRS Specification No. T39-85 (Third Revision May 1996) as amended from time to time duly loaded into wagons/road vehicle for Delhi Sarai Rohilla-Rewari GC
27.07.05
1. M/s Track Innovations (India) Pvt. Ltd 2. M/s Econ Antri Ltd. 3. M/s Daya Engineering Works 4. M/s Rural Engineering Co. Pvt. Ltd. 5. M/s Arvind Construciton Co. Pvt. Ltd. 6. M/s Engipress Industries Ltd.
25000 Nos. 25000 Nos. 25000 Nos. 25000 Nos. 27000 Nos. 25000 Nos.
Per Sleeper rate Rs.706.40 + Freight - do - - do - - do - - do - - do -
Per Sleeper Rate Rs.17660000/- - do - - do - -do - Rs.19072800/- Rs.17660000/-
15.11.05
2005/RVNL/P/CC/PB dtd. 22.07.05 29.07.05
Design & Proof checking of Additional Openings in ROBs at Kosi Kalan and Bhuteshwar
03.08.05 M/s Unique Engineers 3.6 Lacs 3.33 Lacs 3.33 Lacs
23.08.05 (21 days from the date of issue of LOA)
2005/RVNL/CC/P/DEE/Palwal-Bhuteshwar dt.12.08.05 29.08.05
Detailed Design Engineering for Palwal - Bhuteshwar 3rd Line of NCR
12.09.05
M/s Scott Wilson Kirkpatrick India Pvt. Ltd.
53.01 Lacs 47.00 Lacs 47.00 Lacs
11.03.06 (06 months from the date of issue of LOA)
C/DEE/Aljn.-Gzb./3rd Line dt.12.08.05 29.08.05
Detailed Design Engineering for Aligarh - Ghaziabad 3rd Line (106 Km.) of NCR/NR
01.09.05
M/s Consulting Engineering Services (India) Pvt. Ltd., In JV with M/s Ntrust Technological Services Pvt. Ltd.
35.00 Lacs 31.00 Lacs 31.00 Lacs
28.02.06 (06 months from the date of issue of LOA)
2005/RVNL/CC/P/2005/Jn.-Tkd dt.16.09.05 29.09.05
Detailed Design Engineering for Jn. Cabin - Palwal 4th Line (34 Km.) of NR
07.10.05 M/s Dalal Mott Macdonald 16.94 Lacs 19.61 Lacs 19.61 Lacs
06.01.2006 (03 months from the date of issue of LOA)
RVNL/Project/DEE-RE/Contract/2005/05 dtd.08.08.05
24.08.05
Contract for Civil Engineering & track works in connection with DEE-RE GC work
02.09.05
M/s Kalindee Rail Nirman (Engg) Ltd (JV) with M/s Unity Infra Projects Ltd.
47.44 Cr. 46.79 Cr. 46.79 Cr.
(I) Phase-I - 31.03.06 (with maximum mega block period of 04 months) (ii) Phase-II - 31.07.06 (iii) Final Phase- 18 months
C/BPM-011/04 dtd.30.06.05 03.08.05
Bid Process Management with Guage Conversion (MG to BG) of Rly. Track in Rewari-Ringus-Phulera-Ajmer section (294.57 Km.) of NWR.
19.08.05
M/s Wilbur Smith Associates Pvt Ltd. in association with M/s Parsons Brinckerhoff India Pvt. Ltd.
1.05 Cr. 0.89 Cr. 0.89 Cr.
18.05.06 (09 months from the date of issue of LOA)
RVNL/Projects/RE-AJ/Contracts2005/02 dtd.09.08.05
29.09.05
All Permanent way works including supply of ballast, P.Way material (except rails and PSC sleepers) and connected electrical works in the entire section from rewari to Ajmer (294.56 kms.) in connection with
7.11.05 M/s IRCON International Ltd.
189.16 Cr. 173.31 Cr. 158.00 Cr.
16.08.07 (21 months from the date of issue of LOA)
the work of G.C. of Rewari - Ringus - Phulera - Ajmer section of NWR.
RVNL/Projects/RE-AJ/Contracts2005/02 dtd.09.08.05
29.09.05
All civil & electrical works for GC of MG Railway line to BG from Rewari to Ajmer (294.54 kms.) for converting the existing twin MG & BG single line section to BG double line section on NWR.
1.11.05
M/s Rani Constrictiom Pvt. Ltd. in JV with M/s Era Construction (India) Ltd.
52.00 Cr. 63.74 Cr. 63.74 Cr.
10.05.07 (18 months from the issue of LOA)
2005/RVNL/P/CC/MFBW dtd.17.10.05 09.12.05
Mobile Flash Butt Welding of 52 kg. Rail at site using Mobile Butt Welding plant for different construction projects under RVNL on Indian Rlys.
09.01.06 M/s Royal Forging Pvt. Ltd., Kolkata
11.03 Cr. 10.70 Cr. 10.70 Cr.
08.05.08 (28 months from the date of issue of LOA)
RVNL/GM/P/III/05/PSC Sleepers dtd.31.10.05 16.11.05
Manufacture and supply of PSC Mono Blcok sleepers for BG (1672 mm) to RDSO drawing No.T-2496 to suit 60 kg. UIC rail as per IRS specification MOT - 39 - 85 (3rd revision May 1996) as ammended from time to time, duly loaded into wagons/road vehicles for Keonjhar - Tomka new line Project, ECR.
10.12.05
1. M/s Mazda Concrete Products Ltd. 2. M/s Neelgiri Sleepers Pvt. Ltd. 3. M/s Pre-stressed Udyog (India) Pvt. Ltd.
130340 Nos. 30000 Nos. 40000 Nos.
Per Sleeper rate Rs.865/- + Freight - do - - do -
Per Sleeper Rate Rs.112744100/- Rs.25950000/- Rs.34600000/-
09.06.06 (6 months from the date of issue of LOA)
Details of Contracts Awarded upto January 2006 from the Corporate Office (S&T)
Tender No. Date of opening
Description of Item/work
Contract No.&date Contractor's Name Quantity(for supply contract) Estimated
Cost(for Engg.Elect.S&T/Mech.)
Rate (for supply contract) Tendered
Cost(for Engg/Elect/S&T/Mech,)
Value of Contract
Scheduled completion date
S&T/DEE-RW/BID dated
20.04.2005
16.06.2005 Supply & Installation of Signalling for replacement of existing signalling and Gauge Conversion of 2nd Meter Gauge to Broad Gauge line on Delhi Sarai Rohilla- Rewari Section (79 Km) of Northern Railway
S&T/DEE-RW/BID dated 21.10.2005
Consortium (Joint Venture) of M/s Bharat Rail Automation(P)Ltd, B-107 Mandpeshwar Ind.Estate, S.V.P. Road, Borivali(W), Mumbai-400092 and M/s Siemens Ltd, Pandurang Budhkar Marg, Worli, Mumbai-400018
39.00 crores 35.14 crores 35.14 crores 30.04.2007(20 months from the date of issue of
LOA)
CHENNAI PROJECT OFFICE Details of Contract placed during the month of October 2005 and November 2005
Tender No. Date of
opening. Description of item/work.
Contract No & date
Contractor’s Name. Qty. [for supply contract] Tendered Cost [for Engg./Elect./S & T/Mech.]
Rate [for supply contract] Tendered Cost [for Engg./Elect/S & T. /Mech.]
Value of contract.
Scheduled completion date.
RVNL/ATU-SA/Chennai/01
22.9.2005 GC bet. SA - ATU section [including Civil Engg., Electrical and S & T works
LOA No. RVNL/CPM/ATU-SA/Chennai/01/ dated 31.10.2005
M/S D.S. Constructions Ltd., C.66, South Extension II, New Delhi. 110 049.
56.69 Cr. -- 61,46,90,485.95 12 months from the date of award.
RVNL/ATU-SA/Chennai/02
20.9.12005 PMC for GC bet .SA - ATU
RVNL/CPM/ATU-SA/Chennai/02 dated 14.112005
M/S Aarvee Associates, Ravula Residency, Srinagar Colony, Hyderabad 82.
-- --- 1,01,18,500.00 12+ 12 months from the date of award.
[Pradeep Gaur] Chief Project Manager.
Details of tenders for Consultancy Services for Bankability , Financial Advisory & Marketing Studies for different Projects in 2005-06. Tender No. Date of
Opening Description of item/ Work Contract
No. & Date of award
Name of Contractor Rate of Supply
Quantity for supply
Contract Amount
Scheduled completion date
PP&D/BSPX-PRDP/TMS/2005
01/07/2005 Financial Advisory Services for Banaspani - -Paradip BG Doubling of Rly Line
04/7/2005 M/S Feedback Ventures (P) Ltd. New Delhi
N.A. N.A. Rs.1,84,034/- 04/8/2005
2005/Rajgoda-Haldia/BS/PP&D
01/07/2005 Consultancy services for Bankablility Services for Rajgoda – Haldia Doubling of Rly Line
20/7/2005 M/S P.W.C. Pvt. Ltd. New Delhi
N.A. N.A. Rs.7,50,000/- 17/10/2005
2005/Angul-Dub.- Sukinda Rd/BS/PP&D
01/07/2005 Consultancy services for Bankablility Services for Angul – Dubri – Sukinda Rd. New Rly Line Project
20/7/2005 M/S P.W.C. Pvt. Ltd. New Delhi
N.A. N.A. Rs.7,75,000/- 17/10/2005
2005/Igatpuri -Bhusaval/BS/PP&D
01/07/2005 Consultancy services for Bankablility Services for Igatpuri Bhusaval 3rd Line Project
20/7/2005 M/S P.W.C. Pvt. Ltd. New Delhi
N.A. N.A. Rs.7,50,000/- 17/10/2005
2005/Naupada-Gunupur-Thiruvali/BS/PP&D
01/07/2005 Consultancy services for Bankablility Services for Naupada - Gunupur – Thiruvali Guage Conversion
20/7/2005 M/S SBI Capital Markets Ltd. New Delhi
N.A. N.A. Rs.8,25,000/- 17/10/2005
2003/RFP/FA/PP&D
25/o6/2005 Financial Advisory Services for TKD – Dadri New Line Project
o5/8/2005 M/S Feedback Ventures (P) Ltd. New Delhi
N.A. N.A. Rs.3,50,000/- 04/11/2005
Details of tenders for Consultancy Services for implementation of RRAP for different Projects in 2005-06. Tender No. Date of
Opening Description of item / Work Contract No.
& Date of award
Name of Contractor
Rate of Supply
Quantity for supply
Contract Amount
Scheduled completion date
RVNL/CUT-BAR/PP&D/2005
T.B.25/5/2005 F.B.14/6/2005
implementation of RRAP for Cuttack – Barang Doubling of Rly Line
07 / 7 / 2005 M/S Advantage India Community Development New Delhi
N.A. N.A. Rs.4,81,250/- 06/11/2005
RVNL/Gooty-Pull. /PP&D/2005
T.B.30/6/2005 F.B. 2/7/2005
implementation of RRAP for Gooty – Pullampet Doubling of Rly Line
08 / 7 / 2005 M/S CRADLE Ranchi
N.A. N.A. Rs.7,14,000/- 08/01/2006
RVNL/ALJN-GZB /PP&D/2005
T.B.04/7/2005 F.B. 14/7/2005
implementation of RRAP for ALJN – GZB 3rd Line Project
01 / 8 / 2005 M/S Study Point Samiti, LKO
N.A. N.A. Rs.2,82,210/- 28/11/2005
RVNL/ThIr.-Arakonam /PP&D/2004
T.B.18/8/2005 F.B.26/10/2005
implementation of RRAP for Tiruvallur – Arakonnam 3rd Line Project
03 /01/2006 Sugam International Sansthan, LKO
N.A. N.A. Rs.3,83,648/- 02/6/2006
2005/RVNL/Barang-Khurda Rd. /PP&D
T.B. 20/8/2005 F.B.17/10/2005
implementation of RRAP for Barang - Khurda Rd. 3rd Line Project
03/01/2006 SugamInternational Sansthan, LKO
N.A. N.A. Rs.5,61,482/- 02/9/2006
2004/RVNL/Raichur-Guntakal /PP&D
T.B.22/8/2005 F.B.18/10/2005
implementation of RRAP for Raichur – Guntakal Doubling of Rly Line
03/01/2006 M/S D.M.T., New Delhi
N.A. N.A. Rs.7,88,006/- 31/10/2005
RVNL/Rajat.-Barang Doub. /PP&D/2005
T.B. 12/8/2005 F.B. 24/10/2005
implementation of RRAP for Rajatgarh – Barang Doubling of Rly Line
03/01/2006 M/S D.M.T., New Delhi
N.A N.A Rs.7,04,396/- 02/9/2006
Contracts awarded by Electrical Deptt./Rail Vikas Nigam Ltd.
S No. Name of work and location
Est. cost of project
Tendered cost
% above/ below SOR
Agreement No.
Agency Date of start
Time of completion
Physical progress
Name of E in C with
Address
Remarks
1 Updation of Detailed Project Report for Electrification of Nandlur-Guntkal Section
30.68 lacs 30.68 at par 2005/Elect/Gooty-Renigunta RE Dated 18.04.2006
RITES Ltd.
18.04.2006 Three month M/s RITES Ltd RITES Bhawan, No. 1, Sector - 29, Gurgaon 122001
2 Study in connecton with availing of new service connection at proposed TSS at Chhata
5.0 lacs 5.0 lacs at par 2005/Elect/Palwal-Bhuteshwar 3rd line date-18.08.2005
RITES Ltd.
19.08.2005 One month Completed M/s RITES Ltd RITES Bhawan, No. 1, Sector - 29, Gurgaon 122001
Tender Number Date of Opening
Description of Item/Work Contract No. & date of
award
Contractor's Name
Quantity (for supply
contract)Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply
contract)Tenderered
Cost (for Engg./Elect./S&T/Mech.)
Value of Contract
Scheduled completion date
2006/RVNL/GM-P-I/PCDE/ALJN-GZB
12.04.06 Proof Checking of designs/drawings for provision of 3rd line from Aligarh - Ghaziabad section (106 km.) on North Central Railway.
23.05.06 M/s Scott Wilson Kirkpatric India Pvt. Ltd. in association with M/s Scott Wilson Railways of Birmingham, U.K.
- 9.50 Lacs 9.50 Lacs 22.07.06
2005/RVNL/P-I/ALJN-GZB/02
23.12.05 Construction of Roadbed, Bridges, Facilities, Installation of Track (excluding Supply of Rails, Thick Web Switches & Weldable CMS Crossings) & Electrical (Railway Electrification & General Electrification) in connection with Provision of 3rd line on Aligarh - Ghaziabad Section (106 Kms.) in the State of Uttar Pradesh (India).
08.06.06 M/s IRCON - GANNON - Dunkerly - JV
188.03 Cr. 223.94 Cr. 223.45 Cr. 24 months from the date of
Commencement.
Details of Contracts Awarded in May-June, 2006 from the Corporate Office
Tender Number Date of Opening Description of Item/Work Contract No. & date of
award
Contractor's Name
Quantity (for supply contract)Estimated Cost
(for Engg./Elect./S&T/Mech.)
Rate (for supply
contract)Tenderered
Cost (for Engg./Elect./S&T/Mech.)
Value of Contract
Scheduled completion
date
PMC/RVNL/NDLS/ALJ-GZB/2005/02
28.12.2005 Project Management Consultancy for Construction of Roadbed, Bridges, Facilities, Installation of Track (Excluding Supply of Rails, Thick Web Switches & Weldable CMS Crossings) & Electrical Works (Railway Electrification and General Electrification) in connection with provision of 3rd Line on Aligarh – Ghaziabad Section (106 kms.) in the State of Uttar Pradesh (india).
10.07.06 M/s Lea Associates South Asia Pvt. Ltd.B-1/E-27, Mohan Cooperative Industrial Estate,Mathura Road, New Delhi-110044.
- Rs.4.90 Cr. Rs.4.90 Cr. 06.03.09
Details of Contracts Awarded in August, 2006 from the Corporate Office - Projects
DETAILS OF CONTRACTS AWARDED FROM MARCH 2005 TO AUGUST, 2006 BY RVNL OFFICE, SECUNDERABAD
S. No.
TENDER NO. & DATE
DATE OF OPENING
DESCRIPTION OF ITEM/WORK
CONTRACT NO.
DATE OF
AWARDCONTRACTORS'
NAME Estimated
Value of the Contract In Rs.
Date of completion REMARKS
1 RVNL/SC/GEOTECH/GTL-RC/4, DT. 14.02.2005
01.03.05 CONDUCTING GEOTECHNICAL INVESTIGATION FOR CONSTRUCTION OF MAJOR BRIDGES
RVNL/SC/GTL-RC/GEOTECH, DT. 19.03.2005
19.03.05 J.J.SOIL INVESTIGATIONS, VISAKHAPATNAM
434808 15.09.05 Work completed
2 RVNL/SC/GTL-RC/PMSC, DT. 22.03.2005
28.03.05 PROVIDING PROJECT MANAGEMENT SUB- CONSULTANCY SERVICES
RVNL/SC/GTL-RC/PMSC, dt. 01.04.2005
01.04.05 N.SURYANARAYANA, HYDERABAD
149500 30.09.05 Work completed
3 RVNL/SC/GTL-RC/FLS/6 , DT. 24.03.2005
02.04.05 FLS OF BG TRACK DOUBLING BETWEEN GTL - RC SECTION.
RVNL/SC/GTL- RC/FLS, DT. 06.04.2005
06.04.05 M/S. MAP WORLD TECHNOLOGIES, HYDERABAD
484970 15.06.05 Work completed
4 RVNL/SC/GTL-RC/6/MAPING , DT. 24.03.2005
04.04.05 MAPING OF EXISTING RLY. CORRIDOR AND PROVIDING DESIGNS, DRAWINGS, ETC. GTL- RC SECTION
RVNL/SC/GTL-RC/MAPING, DT. 05.04.2005
05.04.05 M/S. MAP WORLD TECHNOLOGIES, HYDERABAD
320000 07.05.05 Work completed
5 RVNL/SC/GTL-RC/L SECTIONS, DT. 18.04.2005
29.04.05 PREPARATION OF PLANS AND L SECTIONS AND YARD DRAWINGS - GTL-RC
RVNL/SC/GTL-RC/L SECTIONS, DT. 04.05.2005
04.05.05 K.VENUGOPAL, SECUNDEABAD
135500 04.09.05 Work completed
6 RVNL/SC/GTL-RC/ PILLERS, DT. 24.05.2005
03.05.05 FIXING OF CONCRETE PILLARS - FLS - DOUBLING BETWEEN GTL - RC SECTION.
RVNL/SC/GTL-RC/PILLARS0, DT. 04.05.2005
04.05.05 RAAGA CONSTRUCTIONS, HYDERABAD
243000 15.10.05 Work Completed
7 RVNL/SC/GTL-RC/BR. DRAWINGS, DT. 23.05.2005
03.06.05 PREPARATION OF DRAWINGS OF BRIDGES- GTL-RC DOUBLING WORKS
RVNL/SC/GTL-RC/BR. DRAWINGS, DT. 07.06.2005
07.06.05 K.VENUGOPAL, SECUNDEABAD
438000 15.06.05 Work completed
8 RVNL/SC/GTL-RC/FLS - KSG, DT. 08.06.2005
15.06.05 FLS OF BG TRACK DOUBLING BETWEEN KOSGI AND MATAMARRI STNS.
RVNL/SC/GTL-RC/FLS - KSG, DT. 15.06.2005
15.06.05 TOP VIEW TOPO MAPPERS, HYDERABAD
233042 31.08.05 Work Completed
9 RVNL/SC/GTL-RC/ S&T, DT. 05.08.2005
19.08.05 PREPARATION OF DESINGS AND DRAWINGS AND ESTIMATES FOR S&T WORKS. GTL - RC SECTION.
RVNL/SC/GTL-RC/S&T , DT. 05.09.2005
05.09.05 C. SUBRAHMANYAM, HYDERABAD.
349000 31.12.05 Work Completed
10 RVNL/SC/GTL-RC/ BUILDINGS, DT. 05.08.2005
19.08.05 PREPARATION OF GADs AND ESTIMATES FOR STATIONS AND SERVICE BUILDINGS
RVNL/SC/GTL-RC/BUILGINS , DT. 05.09.2005
08.09.05 VISION PLANNERS, HYDERABAD
42100 31.10.05 Work in progress
11 RVNL/SC/GY - PMT/ CONCRETE PILLARS0, DT. 10.10.2005
19.10.05 FIXING OF CONCRETE PILLARS IN CONNECTION WITH FIXING LAND BOUNDARIES - GY - PMT SECTION.
RVNL/SC/GY-PMT, DT. 22.10.2005
22.10.05 GAYATRI FLY ASH BRICK INDUSTRY, KAMALAPURAM
409500 18.12.05 Work completed
12 RVNL/SC/GY - PMT/ LAND PLANS, DT. 10.10.2005
19.10.05 PREPARATION & SUBMISSION OF LAND AQUISITION PROPOSALS AND PLANS TO REVENUE AUTHORITIES. GY-PMT SECTION.
RVNL/SC/GY-PMT, DT. 22.10.2005
22.10.05 P. KUMARASWAMY, KURNOOL
442800 21.12.05 Work in progress
13 12/DY.CE/C/RC-2005, LAND ACQUISITION SURVEY, DT. 28.09.2005
20.10.05 GTL - RC WORKS PROPOSED LAND ACQUISITION SURVEY FOR ISSUE OF 4 (i) NOTIFICATION. FIXING OF CENTER LINE PEGS.
RVNL/SC/GTL-RC, DT. 20.10.2005
20.10.05 NIKETAN CONSULTANTS, BANGALORE
334800 31.03.06 Work Completed
14 11/DY.CE/C/RC-2005, LAND ACQUISITION SURVEY, DT. 21.09.05
20.10.05
PORPOSED FIXING OF LAND BOUNDARIES WITH PRE-CASTE RCC PILLARS
RVNL/SC/GTL-RC, DT. 20.10.2005
20.10.05 NIKETAN CONSULTANTS, BANGALORE
451980 15.03.06 Work completed
15 RVNL/SC/GTL-RC/ GEOTECH/BR.1016, DT. 01.12.2005
14.12.05 PROPOSED PATCH DOUBLING OF TRACK BETWEEN GTL-RC - CONDUCTING GEOTECHNICAL INVESTIGATION FOR COSTRUCTION OF BR. NO.1016
RVNL/SC/ GEOTECH/ GTL-RC/BR.1016, DT. 15.12.2005
15.12.05 J.J.ASSOCIATES PVT. LTD., HYDERABAD
53850 14.01.06 Work completed
16 RVNL/SC/GTL-RC/PPM dated 18.11.05
02.12.05 Providing Project Management Sub-consultancy Services for GTL-RC and GY-PMT Projects
RVNL/SC/GTL-RC/PPM dated 18.11.05
02.12.05 Sri.N.Suryanarayana/Secunderabad
142000 01.04.06 Work Completed
17 RVNL/SC/GTL-RC/Conc Pillar/2 Dated 06.03.06
14.03.06 Fixing of Concrete Pillars in connection with fixing Land Boundaries for the proposed patch Doubling between Mantralayam Road
RVNL/SC/GTL-RC/Conc Pillar/2 Dated 14.03.06
14.03.06 M/s Inland Surveyors /Bellary
238560 31.05.06 Work completed
and Matmari Stations and Digitisation of Land Plans
18 RVNL/SC/GTL-RC/Addl.Drawings Dated 06.03.06
14.03.06 Patch Doubling of Track between GTL-RC Preparation of Conceptual Drawings,Scaled kEngg.Plans Etc
RVNL/SC/GTL-RC/Addl.Drawings/03 Dated 14.03.06
14.03.06 Sri.K.Venugopal /Sec.Bad
209100 13.09.06 Work in progress
19 RVNL/SC/OBVP-KP/Land Prop dated 01.03.06
10.03.06 Construction of New BG line between Obulvaripalli to Krishnapatnam Preparation and submissin of Land Acquisition proposals
RVNL/SC/OBVP-KP/Land Prop dated 10.03.06
10.03.06 M/s Top View Consultants/Hyderabad
477150 09.06.06 Work in progress
20 RVNL/SC/OBVP-KP/Conc.Pillars dated 24.03.06
10.04.06 Construction of New BG line between Obulvaripalli to Krishnapatnam Preparation and submissin of Land Acquisition proposals
RVNL/SC/OBVP-KP/Conc.Pillars dated 13.04.06
13.04.06 Sri.N.Nagabhushanam/Vijayawada
459000 12.06.06 Work completed
21 RVNL/SC/GY-PMT/Elec/X ings dated 31.03.06
12.04.06 Survey of Existing Powerline Crossings between GTL-PMT
RVNL/SC/GY-PMT/Elec/X ings dated 17.04.06
17.04.06 M/s Top View Consultants/Hyderabad
454250 01.06.06 Work completed
22 RVNL/SC/Transportation dated 28/04/06
28.04.06 Providing Transport Services to RVNL Secunderabad office.
RVNL/SC/Transportation dt. 29/4/06
29/04/06 M/s. SSV Tours and Travels, Hyderabad
99,000 4/11/06 Work in progress
23 RVNL/SC/GY-PMT/107/KP-RLO dated 06/04/2006
3/5/2006 Proposed soil investigation through Explortory Boring-cum-Lab Test at various bridge locations at Service-cum-Residential bldgs. bet. .Kondapuram-Rayalacheruvu Sec. of GTL division of SC Rly.
RVNL/SC/GY-PMT/107/KP-RLO dated 12/7/06.
12/7/06 M/s. Design Bureau, Plot No.N 3/91 IRC Village, Nayapalli. BHUBANESWAR
6,74,901 11/10/06 Work in progress
24 RVNL/SC/GY-PMT/107/PMT-MOO dated 06/04/2006
3/5/2006 Proposed soil investigation through Explortory Boring-cum-Lab Test at various bridge locations at Service-cum-Residential bldgs. bet. Pullampet-.Muddanuru Sec, of GTL division of SCR
RVNL/SC/GY-PMT/107/PMT-MOO dated 12/7/06.
12/7/06 M/s. Design Bureau, Plot No.N 3/91 IRC Village, Nayapalli. BHUBANESWAR
9,35,277 11/10/06 Work in progress
25 RVNL/SC/KP-OBVP/Soil.Inv. 1 dated 3/7/06
9/6/2006 Proposed soil investigation through Explortory Boring-cum-Lab Test at various bridge locations bet. Venkatachalam-Krishnapatnam port..
RVNL/KP-OBVP/Soil.Inv.1 dated 03/07/06
3/7/06 M/s. RITES Limited, RITES Bhavan, Kadbi Chowk, Nagpur 440 004
22,77,166 2/10/06 Work in progress
26 RVNL/SC/OBVP-KP/Transport dated 26/5/06
13/6/06 Providing transport services to RVNL at their Project office in Nellore
RVNL/SC/OBVP-KP/Transport dt. 13/6/06
13/6/06 M/s. Dhanya Car Travels, D. No.203, Vine yard castle, Secunderabad.
1,98,000 12/5/07 Work in progress
27 RVNL/SC/GY-PMT/104 dated 18/10/05
29/12/05 Patch doubling of Track between Gooty-Pullampet.
RVNL/SC/GY-PMT/104 dt. 7/7/06
7/7/06 M/s. Simplex Infrastructures Limited, Mumbai
170,74,07,793
6/1/09 Work in progress
28 RVNL/SC/House Keeping/2006-07 dated 25/7/06
29/07/006 Complete House Keeping of Regional Office of RVNL at Secunderabad.
RVNL/SC/House Keeping/20060-07 dated 01/08/06
1/8/06 M/s Sri Sai Associates/Neredmet/Secunderabad
1,40,000/- 31.07.07 Work in progress
29 RVNL/SC/Transport Services/2006-07 dated 20/8/06
29/07/06 Providing transport services to RVNL at their Project office in Secunderabad
RVNL/SC/Transport Services/2006-07 dt.01/08/06
1/8/06 M/s. Saptagiri Travels, Secunderabad.
3,78,000/- 31.07.07 Work in progress
Details of Contracts Placed during September 2006 from the Corporate Office (S&T) Tender No. Date of
opening Description of
Item/work Contract No.&
date Contractor's Name Quantity(for
supply contract) Estimated Cost(for
Engg.Elect. S&T/Mech.)
Rate (for supply
contract) Tendered Cost(for
Engg/Elect/ S&T/Mech,)
Value of Contract
Scheduled completion date
RVNL/S&T/RE-AII/BID dated 06.05.2006
12.07.2006 Supply & Installation of Signalling and Telecommunication equipment in connection with MG to BG Gauge Conversion on Rewari-Ringus-Phulera-Ajmer Section (294.57 km) of North Western Railway.
LOA No.RVNL/ S&T/RE-AII/Gen/ Vol.III dated 06.09.2006
Kiran Infra Engineers Ltd. B-141, Road No.9-D, Vishwakarma Industrial Area, Jaipur-302 013(Joint Venture with M/s Mangla Ispat(Jaipur) Ltd. B-234, Road No.9, V.K.I Area, Jaipur-302 013 & M/s Tirupati Plastomatics Pvt.Ltd, B-141, A-Road No. 9D, Vishkarma, Industrial Area, jaipur-302 013
Rs. 66.00 cr.
Rs.72.30 cr. Rs.72.30 cr. 18 Months from the date of issue of LOA(out of which the work in Rewari-Phulera section shall be completed in first 12 months time).
DETAILS OF CONTRACTS PLACED DURING THE CURRENT YEAR UPTO SEPTEMBER 2006 OF PROJECT DEPTT. CORPORATE OFFICE
S. No.
Tender/ICB No. Date of Opening
Description of Item/Work Contract No. & Date Contractor’s Name
Qty. (for supply
contract) Estimated Cost
(for Engg./Elect./ S&T/Mech.)
Rate (for supply
contract) Contract Cost (for
Engg./Elect. /S&T/Mech.)
Value of Contract
Scheduled Completion
Date
1 RVNL/BBS/Doubling-Third Line/Roadbed/ 2005/02
30-12-05 Contruction of Roadbed (except major bridges), facilities and general electrification in onnection with doubling of railway line between Barang-Rajatgarh (25 Km), Cuttack-Barang (12 Km) and 3rd line between Barang-Khurda Road (35 Km) in the state of Orissa.
RVNL/BBS/012/Tenders/ADB-Roadbed/25/4 dated 08-06-2006
M/s. HCIl-Adhikarya-ARSS (JV), Delhi.
1517213941 1535237906 1535237906 24 Months (From the date
of commencement
of work)
2 RVNL/BBS/Doubling-Third Line/ Major Bridges/2005/ 03
30-12-05 Construction of Major Bridges in connection with doubling of railway line between Barang-Rajatgarh (25 Km), Cuttack-Barang (12 Km) and 3rd line between Barang-Khurda Road (35 Km) in the state of Orissa, India.
RVNL/BBS/Tenders/ADB-Major Bridges/25/5 dated 28-06-2006
M/s. HCIl-Adhikarya-ARSS (JV), Delhi.
1236104235 1310294667 1310294667 24 Months (From the date
of commencement
of work)
3 RVNL/SC/GY-PMT/104 29-12-05 Patch Doubling of Track on Gooty-Pullampet Section of South Central Railway.
RVNL/SC/GY-PMT/104 dated 07-07-2006
M/s. Simplex Concrete Piles (India) Ltd., Mumbai.
1574479651 1707407793 1707407793 30 Months (From the date
of commencement
of work) 4 RVNL/BBS/Doubling-Third
Line/Track/2005/02-04 30-12-05 Suplly and Installation of Track
(excluding supply of rails), Signaling and OHE & associated equipment for 25 KV AC traction in connection with doubling of railway line between Barang-Rajatgarh (25 Km), Cuttack-Barang (12 Km) and 3rd line between Barang-Khurda Road (35 Km) in the state of Orissa.
RVNL/BBS/Tenders/Track/25/6 dated 08-08-2006
M/s. HCIl-Adhikarya-ARSS (JV), Delhi.
1383228297 1308585026 1308585026 24 Months (From the date
of commencement
of work)
5 RVNL/RPR/BYT-URK/01 28-12-05 Construction of Roadbed, Major & Minor Bridges and facilities, supply & instatllation of track (excluding supply of rails, thick web switches and weldable CMS crossing), signaling & Electrical (Rly. Electrification & general services) work in connection with provision of 3rd line in Bhatapara-Urkura section (58.71) in the state of Chhatisgarh, India.
RVNL/RPR/BYT-URK/01 dated 01-09-2006
M/s.Era-Patel-Advance-Kiran (JV), New Delhi.
1170590654 1147803541 1147803541 30 Months (From the date
of commencement
of work)
6 PMC/RVNL/BBS/ADB/DBL-Third Line/Roadbed-Track/2005/2
27-01-06 PMC for (i) Contruction of Roadbed (except major bridges), facilities and general electrification in connection with doubling of railway line between Barang-Rajatgarh (25 Km), Cuttack-Barang (12 Km) and 3rd line between Barang-Khurda Road (35 Km) in the state of Orissa; and (ii) Suplly and Installation of Track (excluding supply of rails), Signaling and OHE & associated equipment for 25 KV AC traction in connection with doubling of railway line between Barang-Rajatgarh (25 Km), Cuttack-Barang (12 Km) and 3rd line between Barang-Khurda Road (35 Km) in the state of Orissa.
PMC/RVNL/BBS/ADB/DBL-Third Line/Roadbed-Track/2005/2 dated 13-09-2006
M/s. Wilbur Smith Associates Pvt. Ltd., Bangalore.
-- 60966085 60966085 30 Months with defect liability period (From the date of
commencement of work)
7 RVNL/JP/T&Q/PMC/002 22-08-06 Project Management Consultancy Services for Gauge Conversion (MG to BG) of Railway Track in Rewari-Ringus-Phulera-Ajmer (294.57 KM) Section including electrical works, supply and replacement of existing signaling system of N. W. Railway
RVNL/JP/T&Q/PMC/2006/002/Part III dated 13-09-2006
M/s. Sowil Ltd. & Halcrow Consulting Indig Ltd. (JV), Noida.
68000000 57503600 57503600 33 Months with defect
liability period (From the date
of commencement
of work)
8 RVNL/SC/GY-PMT/PMC/106
3/4/2006 PMC for Patch Doubling of Track on Gooty-Pullampet Section of South Central Railway.
RVNL/SC/GY-PMT/ PMC/106 dated 29-09-2006
M/s. Aarvee Associates, Hyderabad.
60000000 57532019 57532019 30 Months excluding
defect liability period (From the date of
commencement of work)
Tender Number Date of Opening Description of Item/Work Contract No. & date of
award
Contractor's Name
Quantity (for supply contract)Estimated Cost
(for Engg./Elect./S&T/Mech.)
Rate (for supply
contract)Tenderered
Cost (for Engg./Elect./S&T/Mech.)
Value of Contract
Scheduled completion date
2006/RVNL/P/CC/PMC(PB) dt 25.04.2006
23.6.2006 Project Management Consultancy for “Construction of Palwal-Bhuteshwar 3rd Line Doubling(81 Kms) in the state of Haryana and Uttar Pradesh (India) including road bed facilities, bridge works, box pushing, flash butt welding, P. Way, miscellaneous civil works, electrical works including OHE and signaling and interlocking works on North Central Railway”
27.09.2006 M/s Scott Wilson,Kirkpatrick India Pvt Ltd.New Delhi-10044
- Rs.4.29 Cr. Rs.4.29 Cr. 27 Months from Commencement
date.
Details of Contracts Awarded from Sept.-Nov. 2006 from the GM/P-I Unit
Sl No
Tender Number
Date of Opening
Description of Item /Work Contract No & Date
Contractor's Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection
date.
1 ADB/RAIL IMP PROJ/01 12/1/2004
Construction of 2nd BG overriver Mahanadi in connectionto doubling of Talcher-Cuttack-paradeep section inOrissa,India
29.4.2005 M/s BBJ-GAMMON JV Rs 109,45,00,000 Rs 121,29,05,652 36 months
2 CUTTACK-BARANG SECTION
Construction of Substructureand foundation of KuakhaiBR No 557.
08.11.2004 M/s. TRG Industries Pvt. Ltd, /NewDelhi
Rs 31,41,22,088 Rs 29,08,59,908 Rs 29,08,59,908 540 days
3 RAJATHGARH-BARANG SECTION.
Construction of Substructureand foundation Mahanadi BRNO 22 at NARAJ.
25.11.2004 M/s. GAMMON India Pvt. Ltd.,/NewBombay
Rs 30,46,87,025 Rs 24,38,57,411 Rs 24,38,57,411 540 days
4 RAJATHGARH-BARANG SECTION.
Construction of Substructureand foundation of Major BRNo 17,18,19,32,34
10.11.2004 M/s. Hindustan Steel ConstructionLimited, Kolkata
Rs 10,02,99,249 Rs 9,67,94,412 Rs 9,67,94,412 240 days
Details of Contract Awarded by Project Office Bhubaneshwar upto Dec' 2006
5 RVNL/HDS-PRDP/BHUBANESHWAR/1/2005
6/27/2005 Construction of Br. No.134over Mahanadi 22 x 43.846mand Br. No.115 over Luna 13x 43.846m in connection withconstruction of new BG linebetween Haridaspur &Paradeep of East Coast
RVNL/BBSHDS-PRDP/MAHA-LUNA/SIMPLEX/14/13/2006/02 Dt30/01/2006
M/s Simplex Infrastructures Ltd.,502A, Poonam Chambers, 'A' Wing,5th Floor, Dr. A.B.Road, Worli,Mumbai - 400 018.
Rs 69,67,45,876 Rs 67,51,46,754 Rs 67,51,46,754 30 months
6 RVNL/BBS/TOMKA-KOENJHAR/1 dtd31/08/2005
10/24/2005 Supply and installation ofTrack, Signalling and YardLighting works forconstruction of Keonjhar -Tomka new BG Railway Linein Orissa, India.
RVNL/BBS/TOMKA-KDJR/14/10/2006/01 Dt20/12/2005
M/s HCIL-Kalindee-ARSS JV, F-5,Gautam Nagar, Gulmohar Park Road,New Delhi - 110 049
Rs 66,75,14,539 Rs 72,39,29,164 Rs 72,39,29,164 12 months
7 RFP/PMC/RVNL/BBS/HDS-PRDP/MAHA-LUNA/2005/1 Dtd.16.12.05
1/25/2006 Project managementconsultancy services forconstruction of Br.No.134over Mahanadi 22 x 43.846M& Br. No. 115 over LUNA 13x 43.846 M in connectionwith construction of new BGline between Haridaspur &Paradeep of East CoastRailway.
LOA-RVNL/BBS/TENDER/PMC-1-MAHA-LUNA/25/7/1332 Dt10/05/2006
M/s. SM Consultants,Plot No3489/6705, Near Kaling House , Po-RasulgarhBhubaneshwar
Rs 1,70,00,000 Rs. 1,38,24,000 Rs. 1,38,24,000 30 months
8 IFB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
12/30/2005 “Construction of Roadbed(except Major bridges),Facilities and GeneralElectrification for doubling ofRailway line between Barang-Rajatgarh (25 km), Cuttack –Barang (12 km) and 3rd linebetween Barang-Khurda Road(35 km) in the state of Orissa,India”
LOA-RVNL/BBS/TENDER/ADB-Roadbed/25/4 Dt08/06/2006
M/s HCIL-ADHIKARYA-ARSS JV,113-A, Kamla Nagar New Delhi -110 007
Rs 151,72,13,941 Rs 153,52,37,906 Rs 153,52,37,906 24 months
9 IFB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
12/30/2005 “Construction of MajorBridges in connection withdoubling of railway linebetween Barang-Rajatgarh(25 km), Cuttack – Barang(12 km) and 3rd line betweenBarang-Khurda Road (35km) in the state of Orissa,India”.
LOA-RVNL/BBS/TENDER/ADB-Major Bridges/25/5 Dt 28/06/2006
M/s HCIL-ADHIKARYA-ARSS JV,113-A, Kamla Nagar New Delhi -110 007
Rs 123,61,04,234 Rs 131,02,94,667 Rs 131,02,94,667 24 months
10 RVNL/Bhubaneswar/KEONJHAR-TOMKA/2 Dtd 21/03/2006
4/17/2006 “Flash butt welding of 60 KgRails at site using MobileFlash Butt Welding Plant inConstruction of Keonjhar –Tomka New BG Railway Linein the State of Orissa, India”
LOA-RVNL/BBS/TENDERS/TOMKA-KEONJHAR/1404 Dt29/05/2006
M/s RAIL WELDERS JVCENTURY TOWERS 5th Floor,Shakespere Sarini, Kolkata - 700017
Rs 3,50,00,000 Rs 3,30,60,000 Rs 3,30,60,000 6 months
11 Bid NoticeNo. PMC/RVNL/BBS/ADB/DBL-Third Line/Major Bridges/2005/3 Dt.15/12/2005,
27/01/2006 Project ManagementConsultancy Services forConstruction of MajorBridges in connection withdoubling of railway linebetween Barang-Rajatgarh(25 km), Cuttack – Barang(12 km) and 3rd line betweenBarang-Khurda Road (35km) in East Coast Railway inthe
LOA-RVNL/BBS/Contract/Expert Resort-SPA(PMC-Major Bridges) 14/25/1517 Dt 23/06/2006
EXPERT RESORTS & LAYOUTSPRIVATE LIMITED , 16/1, BhavaniMansion Road, American Colony,Kumar Park East, Bangalore- 560001
Rs 3,00,00,000 Rs 2,61,88,500 Rs 2,61,88,500 30 months
12 IFB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
12/30/2005 Supply & Installation ofTrack (excluding supply ofrails), Signaling andOverhead Equipment(OHE) & associatedequipment for 25 KV, ACtraction in connection withdoubling of Railway linebetween Barang Rajatgarh
LOA-RVNL/BBS/TENDER/ADB-Track/25/6 Dt 08/08/2006
M/s HCIL-ADHIKARYA-ARSS JV,113-A, Kamla Nagar New Delhi -110 007
Rs 138,32,28,297 Rs 130,85,85,026 Rs 130,85,85,026 30 months
13 RVNL/Bhubaneswar/KEONJHAR-TOMKA/2 Dtd 21/03/2006
4/17/2006 Depot Supply of Stone ballastin connection withconstruction of Keonjhar-Tomka new BG Railway Linein the state of Orissa, India."
LOA No.RVNL/BBS/Tenders/DKB-Supply ofBallast (Keonjhar-Tomka)/25/13/1774, dated 26/08/2006.
M/s ARSS InfrastructureProjects Limited.
Rs2,50,00,000 Rs2,50,00,000 Rs2,20,20,000 6 months
14 PMC/RVNL/BBS/ADB/DBL-Third Line/Road Bed/Track/2005/2 dated15/12/2005.
1/25/2006 (a) Project ManagementConsultancy for Constructionof Roadbed (except Majorbridges), Facilities andGeneral Electrification fordoubling of Railway linebetween Barang-Rajatgarh(25 km), Cuttack – Barang(12 km) and 3rd line betweenBarang-Khurda Road (35km) in the state of Orissa,India.(b) Project ManagementConsultancy for Supply andinstallation of track(excluding supply of rails,signaling and overheadequipment (OHE) &associated equipment for 25kV, AC traction, inconnection with doubling ofrailway line between Barang-Rajatgarh (25 km), Cuttack –Barang (12 km) and 3rd line
Notice ofAward No.PMC/RVNL/BBS/ADB/DBL-Third Line Bed -Track/2005/2, dated13/09/2006
M/s Wilbur SmithAssociates Pvt Ltd/Bangalore.
Rs 5,60,00,000 Rs 5,60,00,000 Rs6,09,66,085 30 months
15 FB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
38716 b) Project ManagementConsultancy for Supply andinstallation of track(excluding supply of rails,signaling and overheadequipment (OHE) &associated equipment for 25kV, AC traction, inconnection with doubling ofrailway line between Barang-Rajatgarh (25 km), Cuttack –Barang (12 km) and 3rd linebetween Barang-Khurda Road(35 km) in the state of Orissa,India
RVNL/BBS/ADB-Track/14/29/9, dated08/08/06
M/s HCIL-ADHIKARYA-ARSS JV,113-A, Kamla Nagar New Delhi -110 007
Rs 138,32,28,297 Rs 130,85,85,026 Rs 130,85,85,026
16 No.C/CPM/RVNL/BBS/LT/NIT/01, dtd.28/02/2006
3/31/2006 Providing consultancyservices for DetailedEngineering Design of majorbridges in connection withConstruction of new BG linebetween Haridaspur-Paradeep in East CoastRailway
RVNL/BBS/HDS-PRDP/14/ /15, dated
STUP Consultants P Ltd, P-11,DargaRoad,Park Circus,Kolkata-700017
Rs 45,00,000 Rs 39,69,000 Rs 39,69,000 3 months
17 RVNL/BBS/Limited TenderGoomty/4/25/19/18
9/8/2006 Proposal for execution ofstation GOOMTY with otherallied works for station NKW,HCNR,CLDR, SGDP andTGRL of Keonjhar-Tomkanew BG Rail Project of EastCoast Railway.
RVNL/BBS/GOOMTY/TAMKA-KDJR/PKM/14/34/2006/05,dated 12/10/2006
Mr. P K Mohanty,At/Po.-Patalda,Via-Astaranga,Dist.-Puri.
Rs 14,10,753 Rs 14,10,753 45 days
DETAILS OF CONTRACTS AWARDED BY PROJECT DEPTT. CORPORATE OFFICE UPTO DEC 2006 Tender No. Date of
Opening Description of item/work
Contact No/Date of Award
Contractor Name
Estimated Cost
Rate for Supply/Tender Cost
Value of Contract
Scheduled completion date.
RVNL/P/DEE-RE/Contract/2005 dt. 8.8.05
24.8.05 Civil,Track & Electrical work for DEE-RE GC
02.9.05 C/DEE-RE/05
M/s Kalindee Rail Nirman Engg Ltd (JV) with M/s Unity Infra Projects.
47.44 Cr 46.79 Cr 46.79 Cr 2.3.07
PMC/DEE-RE dt 23.11.05 PMC for DEE-RE GC work
2.12.05 M/s Lea Associates South Asia with Wilbur Smith, PNCS
1.82 Cr 1.82 Cr 1.82 Cr 2.3.07 + 12 months during defect liability period.
2005/RVNL/P/CC/ MPBW dt 17.10.05
9.12.05 Mobile flash butt welding of 52 kg rail for different projects under RVNL on Indian Rly
9.1.06 M/s Royal Forging Pvt Ltd, Kolkata
11.03 Cr 10.70 Cr 10.70 Cr 8.5.08
C/GHH-FN/044/ 2006
3.4.06 GC of GHH-Fn Branch Line, track works in connection with RRI of DEE, DEC, PTNR on N. Rly
21.6.06 M/s SMCC-SCC-PVCC JV, Jaisalmer
12.52 Cr 11.44 Cr 11.44 Cr 8.6.07
RVNL/CMS Xing Procurement/4 of 2006
20.7.06 Manufacture & supply of CMS xings for BG conforming to IRS-T-29-2000 for various Rail road projects in different regions of India.
15.12.06 M/s Bhilai Engg. Corporation Ltd.
8.84 Cr 9.13 Cr 9.13 Cr 14.9.07
RVNL/PIII/STM & PMC
17.10.06 Supply of small track machine for p.way work at different locations on Indian Railways.
28.11.06 28.11.06 6.12.06
M/s Kalindee Enterprises. New Delhi. M/s Laxmi Indl.Corp. Meerut. M/s Parikh
- 24.47 Lacs 1.47 lacs 9.30 lacs
24.47 lacs 1.47 lacs 9.30 lacs
27.2.07 27.2.07 5.3.07
Industries, Mumbai.
RVNL/Rail Proc/2/2006
20.4.06 Manufacture and supply of 7775 MT of 52 kg IRS rails (880) for different RVNL projects on Indian Railways.
1.12.06 M/s Steel Authority of India Ltd
- 30.36 Cr 30.36 Cr 30.11.07
RVNL/P-II/PSC Palwal Bhuteshwar
9.11.06 Manufacture & supply of 15000 Nos PSC sleepers for Palwal Bhuteshwar Project of RVNL.
27.11.06 M/s Hindustan Prefab Ltd., New Delhi.
1.29 Cr 1.29 Cr 1.29 Cr 26.5.07
DETAILS OF CONTRACTS BY PROJECTS OFFICE SECUNDERABAD PLACED DURING THE MONTH: JAN’ 2007
Tender Date of Description of item/work
Contract No. & date
Contractor’s Name
Quantity (for supply contract) estimated cost (for Engg. Elec. S&T/ Mech)
Rate (for supply contract Tendered cost (for Engg/ Elec/S&T/ Mech)
Value of Scheduled Comple-tion Number Opening Contract Date
RVNL/SC/GY-PMT/104 dated 18/10/05
29-12-2005
Earth work in formation, constn. Of bridges, service & residential bldgs., installation of track, remodelling of stn. yds. Elec. Wrks and other Misc. works along with testing and commissioning incl. supply of all materials except rails in connection with patch doubling of Gooty-Pullampet sec. of South Central Railway. (150.74 km.)
RVNL/SC/GY-PMT104 dated 12-10-06.
M/s. Sim-plex Infra-structures Limited, Mumbai
150.74 Route Kilometres
Engg. & Genl. Elec. Works Rs.157.33 Cr.
Rs.170.73 Cr.
06-04-2009
RVNL/2006/Elect/PMT-NRE/001 dated 13-03-06.
23-05-2006
Supply, Erection, Testing and commissioning of 25 Kv, 50 Hz, single phase, traction over head equipment switching station and other associated works in connection with patch doubling of Pullampet (Excl.), Nandalur (incl.) sec. of South Central Railway (29 Tkm)
RVNL/2006/Elect/PMT-NRE/001 dated 15-11-2006
M/s. Tata Projects Limited, Suryodaya Complex, Hyderabad.
Route Km. 21
Rs.5.99 Crores
Rs.8.40 Crores
17-09-2007.
DETAILS OF CONTRACTS AWARDED BY PROJECT OFFICE JAIPUR UPTO DECEMBER 2006
S. No.
Name of work and location
Est. cost of project
Tendered
Cost
% Above/ below SOR
Agreement No. Agency Date of start Time of Comp
Physical
Progress
Name of E in C with
Address (A) 189.43 Crs.
157.71* Crs (9.2%
below NIT Cost)
AL No. RVNL/Projects/RE-AJ/Contracts-
2005/02 Dated 17/11/2005
M/s IRCON Int. Limited, New Delhi
02/12/2005 21 Months
12% M/S Sowil-
Halcrow JV
Rewari-Ringus-Phulera-Ajmer Gauge
Conversion project (294.56
Km)
Rs.716.65 Crs. (B)
68.88 Crs.
63.75 Crs (7.4%
below NIT Cost)
AL No. RVNL/Projects/RE-AJ/Contracts-
2005/02 Date 11/11/2005
M/s RANI Construction Pvt. Ltd. in JV with M/s ERA Construction (India) Ltd.
26/11/2005 18 months
5% M/S Sowil-
Halcrow JV
(C) 10.33 Crs. As per
accepted rates of RB
contract
AL No. RVNL/Projects/RE-AJ/Contracts-
2005/03 (sleeper) Date 09/11/2005
M/S Donypolo Udhog limited,
Shamgarh
16.11.2006 12 months
64 % M/S Sowil-
Halcrow JV
10.65 Crs. As per
accepted rates of RB
contract
AL No. RVNL/Projects/RE-AJ/Contracts-
2005/03 (sleeper) Date 09/11/2005
Rural Engineering Co. Pvt. Ltd.
16.11.2006 12 months
66 % M/S Sowil-
Halcrow JV
1
10.74 Crs. As per
accepted rates of RB
contract
AL No. RVNL/Projects/RE-AJ/Contracts-
2005/03 (sleeper) Date 09/11/2005
Daya Engineering Works (SL) Ltd.
16.11.2006 12 months
65 % M/S Sowil-
Halcrow JV
10.65 Crs. As per
accepted rates of RB
contract
AL No. RVNL/Projects/RE-AJ/Contracts-
2005/03 (sleeper) Date 09/11/2005
Arvind Construction Co.
Pvt. Ltd.
16.11.2006 12 months
70 % M/S Sowil-
Halcrow JV
6.80 Crs
5.75 Crs (15.44 %
below estimated
cost)
AL No. RVNL/JP/T &
Q/PMC/2006/002/Part III
Date 13/09/2006
Sowil Limited & Halcrow
Consulting India Ltd (JV)
26.09.2006 33 months
6 % Appointed as
Engineer (PMC)
(A) 52.58 Crs.
48.05 Crs (9.12 % below
estimated cost)
Agreement No.RVNL/PIII/B
LDI-SMR/GC/CA-3
of 2006
M/S ERA Construction
(India) Limited
01.08.06 18 months
1% NW Railway
(B) 43.13 Crs.
39.42 Crs (9.21 % below
estimated cost)
Agreement No.RVNL/PIII/B
LDI-SMR/GC/CA-2 of 2006 dated
30.06.06
M/S ERA Construction
(India) Limited
27.05.06 18 months
Nil NW Railway
2 SMR-BLDI Gauge
Conversion project
(223 Km)
244.27 Crs.
(C) 29.98 Crs.
29.99 Crs (At Par of estimated
cost)
Agreement No.RVNL/PIII/B
LDI-SMR/GC/CA-1 of 2006 dated
30.06.06
M/S ERA Construction
(India) Limited
27.05.06 15 months
Nil NW Railway
DETAILS OF CONTRACTS CONCLUDED BY PROJECT DEPTT., CORPORATE OFFICE DURING DEC' 20061 2 3 4 5 6 7 8 9
Tender Number Date of Opening
Description of Item/work Contract No.& date Contractors Name Quantity (for supply contract) Estimated Cost ( for Engg., Elect,S&T
Quantity (for supply contract) Tendered Cost ( for Engg., Elect,S&T
Value of Contract
Scheduled completion date
RVNL/NDLS/ALJ-GZB/2005/01 DT. 14.10.05
23.12.05 Construction of Roadbed, Bridges, Facilities, Installation of Track (excluding Supply of Rails, Thick Web Switches & Weldable CMS Crossings) & Electrical (Railway Electrification & General Electrification) in connection with Provision of 3rd Line on Aligarh-Ghaziabad Section (106 Kms) in the State of Uttar Pradesh (India)
2005/RVNL/P/I/ALJN-GZB/02 DT.08.06.06
M/s . IRCON GANNON DUNKERLY LTD.JV, New Delhi
188.03 Cr. 223.94 Cr. 223.45 Cr. 13.07.08
PMC/RVNL/NDLS/ALJ-GZB/2005/02 dt. 16.11.05
28.12.05 PMC of Construction of Roadbed, Bridges, Facilities, Installation of Track (excluding Supply of Rails, Thick Web Switches & Weldable CMS Crossings) & Electrical (Railway Electrification & General Electrification) in connection with Provision of 3rd Line on Aligarh-Ghaziabad Section (106 Kms) in the State of Uttar Pradesh (India)
C/PMC/ALJN-GZB/2005/06 dt. 10.07.06
M/s Lea Associates South Asia Pvt. Ltd,
4.46 Cr. 4.97 Cr. 4.90 Cr. 06.03.09
2005/RVNL/P/CC/Civil Works
27.12.05 All Civil Engineering and connected General Electrical Works for Construction of Road bed facilities, Buildings, Box-pushing in existing 2 ROBs including Misc. works for Palwal-Bhuteshwar 3rd Line (81 Kms) on North Central Railway
2005/RVNL/P/CC/Civil Engg.dated 08.05.2006
M/s Era Construction India Ltd.
62.05 Cr. 62.05 Cr. 62.05 Cr. 07.11.07
2005/RVNL/P/CC/PMC(PB) dated 11.09.06
23.06.06 PMC of Construction of Palwal-Bhuteshwar 3rd Line Doubling (81 kms) in the State of Haryana and Uttar Pradesh (India) including Road bed facilities, Bridge works, Box Pushing, Flash Butt Welding, P.Way, Miscellaneous Civil works, Electrical works including OHE and Signalling and Interlocking Works on North Central Railway.
2005/RVNL/P/CC/PMC(PB)dated 27.09.06
M/s SCOTT WILSON Kirkpatric India Pvt.Ltd.
4.32 Cr. 4.28 Cr. 4.28 Cr. 26.12.08
Sl No
Tender Number
Date of Opening
Description of Item / Work Contract No & Date
Contractor's Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection
date.
1 RFP/PMC/ Sub-projects Dt 05/03/2004
26/06/2004 Project Management Consultancy forSubprojects:i) Supply and Installation of Trackand Signalling: Keonjhar-Tomka Section(96.355km) of Banspani-Daitari New RailwayLine. ii) Construction of 2nd bridge across riverMahanadi (32 x 65.4m) on Cuttack-NergundiSection of East Coast Main Line.
RVNL/ Projects/ K-T&M-B /PMC/Package-1
M/s SOWiL-Halcrow JV - - 8,32,39,618/- 48 months
2
ADB/RAIL IMP PROJ/01
01/12/2004 Construction of 2nd BG over river Mahanadi inconnection to doubling of Talcher-Cuttack-paradeep section in Orissa,India
Contract No.ADB/RAIL IMPPROJ/01 Dt.29.4.2005
M/s BBJ-GAMMON JV Rs 109,45,00,000/- Rs 121,29,05,652/- Rs 121,29,05,652/- 36 months
3 RVNL/HDS-PRDP/BHUBANESHWAR/1/2005
27/06/2005 Construction of Br. No.134 over Mahanadi 22 x43.846m and Br. No.115 over Luna 13 x43.846m in connection with construction ofnew BG line between Haridaspur & Paradeep of East Coast
RVNL/BBSHDS-PRDP/MAHA-LUNA/SIMPLEX/14/13/2006/02 Dt30/01/2006
M/s Simplex Infrastructures Ltd.,502A, Poonam Chambers, 'A' Wing,5th Floor, Dr. A.B.Road, Worli,Mumbai - 400 018.
Rs 69,67,45,876/- Rs 67,51,46,754/- Rs 67,51,46,754/- 30 months
4
RFP/PMC/RVNL/BBS/HDS-PRDP/MAHA-LUNA/2005/1 Dtd.16.12.05
25/01/2006 Project management consultancy services forconstruction of Br.No.134 over Mahanadi 22 x43.846M & Br. No. 115 over LUNA 13 x43.846 M in connection with construction ofnew BG line between Haridaspur & Paradeep of East Coast Railway.
LOA-RVNL/BBS/TENDER/PMC-1-MAHA-LUNA/25/7/1332 Dt10/05/2006
M/s. SM Consultants,Plot No3489/6705, Near Kaling House , Po-RasulgarhBhubaneshwar
Rs 1,70,00,000/- Rs. 1,38,24,000/- Rs. 1,38,24,000/- 30 months
5 No.C/CPM/RVNL/BBS/LT/NIT/01, dtd.28/02/2006
31/03/2006 Providing consultancy services for DetailedEngineering Design of major bridges inconnection with Construction of new BG linebetween Haridaspur-Paradeep in East CoastRailway
RVNL/BBS/HDS-PRDP/14/ /15,dated
STUP Consultants P Ltd, P-11,DargaRoad,Park Circus,Kolkata-700017
Rs 45,00,000/- Rs 39,69,000/- Rs 39,69,000/- 3 months
Report for the period upto Mar 2007:
Details of Contract Awarded by AGM/Bhubaneshwar
DELHI PROJECT OFFICE (ELECTRICAL DEPARTMENT) Details of Contract awarded upto 30.04.2007
S No. Date of Opening
Description of item/work letter of Acceptance No. and date
Contractor's Name Qty. (for supply contract)tendered cost (for Elect/S &T/Mech)
Rate. (for supply contract)tendered cost (for
Value of Contract scheduled Completion/completion
1 23.5.2006
Supply, erection, Testing and commissioning of25 KV, 50 Hertz, Single phase OHE, SWS andother associated works in connection with patchdoubling of PMT-NRE section of SCR.
2006/Elect/PMT-NRE/001 Dated-18.9.2006
M/s Tata Projects Ltd. Hyderabad.
5.99 crore
8.40 crore 12 months from the dare of award
2 14.9.2006
Supply, installation, Testing and commissioningof Split/ multi split type of High wall mounted/cassette type of ceiling mounted airconditioners along with asociated electricaldistribution (LT panel and power wiring ) andother works for the new corporate officepremises of RVNL at 1st floor of August KrantiBhawan ( Hudco Building ), Bhikaji CamaPalace, New Delhi.
2006/Elect/NCO/AC/64 Dated-18.09.2006
M/s L G Electronics , India Pvt. Ltd.
69.31 lakhs
56.54 lakhs9 including AMC for 4 yrs after expiry of warranty period)
Phase-I-30 days Phase-II 90 days
3 09.02.2007
Detailed Design Engineering in connection with RE of Nandalur-Guntakal in South Central Railway
RVNL/SC/NRE-GTL/DDE, dated-24.04.2007
M/s Consulting Engineering Services (India)Pvt. Ltd.in JV with M/s Ntrust Technological Services Pvt. Ltd. , 41-A, Maker Tower , 'E'Cuffe Parade, Mumbai- 400005
1.3 crore
Rs. 81,02,200/-(Rupees Eighty one lakh, Two thousand two hundred only)
Six Month
LIST OF CONTRACTS AWARDED BY CPM/JAIPUR UPTO JAN 2008 S. No. File No. Description of work Contract No.
& date Contractor’s
Name Estimated
Cost Tendered cost Value of
Contract Scheduled
Completion date
1.
RVNL/P-III/Bhildi-Samdari GC-1 dt. 28/11/05
All permanent way works including supply of ballast,p way material except rails and PSC sleepers from KM 121.41 to 223.44 between M. Bhinmal & Bhildi stations in c/w gauge conversion of existing MG railway line to BG line of BLDI-SMR section on NW Rly.
RVNL/PIII/B LDI-SMR/CA-2 OF 2006 DT. 30/6/06
M/S ERA Constructions (India) Limited
244.27crs.
39.42 crs. 39,422 crs. 18 months
2.
RVNL/PIII/Bhildi-Samdari GC-1 Dated 5/1/06
All permanent way works including supply of ballast, p way material except rails & Psc sleepers from KM 0.00 to 121.41 between Sandari & Bhinmal in c/w gauge conversion of existing MG Rly. Line to BG line of BLDI-SMR section on NW Rly.
RVNL/PIII/Bh ildi-Samdari GC/CA-3 of 2006 dt. 24.8.2006
M/S ERA Constructions
52.58 crs. 48.0548 18 months
3.
RVNL/PIII/ Bhildi-Samdari GC/1 dated 28.11.2005
All civil works for bridges & earthwork from Km 121.41 to 223.44 and buildings, FOBs, platforms, L-Xings & connected electrical works from Km 0.00 to 223.44 in c/w gauge conversion of existing MG railway line to BG line of Bhildi/Samdari section on NW Rly.
RVNL/PIII/B LDI-SMR/GC/CA-1 OF 2006 DT,. 30.6.2006
M/S ERA Constructions
29.99 crs. 29.9927 crs. 18 months
4.
RVNL/JP/T & Q Br. 3&54 Jacketing/2007/005 dt. 5/4/2007
Strengthening and modification of existing sub structure by way of jacketing, dowelling, raising of bed blocks, provision of additional piers, approach earth work, protection works on Br. No. 3 & 54 in c/w SMR-BLDI GC project
RVNL/JP/T &Q/Br.3&54 Jacketing/2007/005 dt. 6/8/2007
M/S Rachna Construction Coy.
8.40 crs. 8.50689 crs. 8.76406 crs. 09 months
5.
RVNL/JP/T&Q/Plate sGirder/2007/004 dt 5/4/2007
Fabrication, transportation and erection of welded plate girders of spans up to 818.3 m for various bridges including dismantling of existing MG girders in c/w gauge conversion of SMR—BLDI section on NW Railway.
RVNL/JP/T&Q/Plate Girder/2007/004 dt. 15/8/2007
M/S GPT-RAHEE (JV)
15.50crs. 14.072 crs. 13,6724 Crs. 8 months
6.
PMC
Project Management Consultancy for the track works, Civil Works, Ballast Supply, Signalling and Telecom, and Electrical works in connection with gauge conversion of Samdari-Bhildi Section (223 Km) over North Western Railway
RVNL/JP/T&Q/PMC/2007/008 dt. 1/12/2007
M/S Halcrow Consultant (I) Pvt. Ltd.
2,84,06,000 2.20cr 2,84,06,000 30 months
7.
SMR-Bagra
Misc.civil works including construction/modification of station buildings, S & T structures, platforms, level crossings Duty Huts, resting facilities for TMC staff and other connected works from SMR to Marwar Bagra (Including) on SMR-BLDI section
RVNL/JP/T&Q/Misc/2007/010 dt. 6/12/2007
M/S Kera Ram s/o Pusha Ram
4,81,20,717.30 4.50cr 4,81,20,717.30
12 Months
8.
Raniwara-BLDI
Misc. civil works including construction/modification of station buildings, S & T structures, platforms, level crossings Duty Huts, resting facilities for TMC staff and other connected works Rainwara (Excluding) to Bhildi on SMR-BLDI section.
RVNL/JP/T&Q/Misc/2007/012
M/s Bhinmal Contractors
4,23,45,804 4.03cr 4,23,45,804 12 Months
Detail of Contract awarded by Project Planning & Development Department, Corporate Office upto January 2008
S. No.
Tender No. Date of opening
Description of work/study
Contract No. & date
Contractor’s Name
Estimated cost of work
Tendered cost
Value of contract
Scheduled completion date
1 PP&D/HPT-VSG/2006
26.05.06 Traffic & Market study and Financial evaluation of doubling Hospet – Vasco section.
PP&D/HPT-VSG/2006 19.06.2006
M/s Feedback Ventures Pvt. Ltd.
_ R
s. 7
,30,
000/
-
_
One Month from the date of award of Contract 18.07.2006
2 PP&D/BSPX-JKPR/RE/2006
16.10.06 Bankability study for Banspani – Jakhapura RE project.
PP&D/BSPX-JKPR/RE/2006 09.11.2006
Infrastructure Development Corporation (Karnataka) Ltd.
_ R
s. 4
,96,
157/
- _
One Month from the date of award of Contract 08.12.2006
3 PP&D/DIGHI / Bankability Study/2006
06.11.06 Bankability study for New Line Indapur – Dighi Port (Agar Danda).
PP&D / DIGHI / Bankability Study/200601.12.2006
M/s Ernst & Young Pvt. Ltd.
_
R
s. 4
,40,
000/
-
_
One Month from the date of award of Contract 31.12.2006
4 PP&D/BSPX – DTR/2007
09.03.07 Traffic & Market study and Financial evaluation of doubling of Banspani – Tomka – Jakhapura section
PP&D / BSPX – DTR/2007 10.04.2007
M/s Feedback Ventures Pvt. Ltd.
_ R
s. 6
,94,
000/
-
_
Two Months from the date of award of Contract 09.06.2007
5 2007/PP&D/ DRFC/Pt-A / NSC/DLI -Chennai
02.04.07 Project Consultancy Services for Dedicated Freight Corridor, North – South Corridor ( Delhi – Chennai)
2007 / PP&D / DRFC / Pt.- A / NSC / DLI – Chennai 15.06.2007
M/s Wilbur Smith Pvt. Ltd.
_
R
s. 4
9,43
,840
/-
_
20 weeks from the date of award of Contract 01.11.2007
6 2007/PP&D/ DRFC Pt–B/EWC /KNM
02.04.07 Project Consultancy Services for Dedicated Freight Corridor, East – West Corridor (Kolkata –Nagpur – Mumbai)
2007 / PP&D / DRFC / Pt.–B / EWC / KNM 03.07.2007
M/s Wilbur Smith Pvt. Ltd.
_ R
s. 4
9,43
,840
/- _
20 weeks from the date of award of Contract 19.11.2007
7 2007/PP&D/ DRFC/Pt-C/EC/ Kharagpur - Vijayawada
17.09.07 Project Consultancy Services for Dedicated Freight Corridor, East – Coast Corridor (Kharagpur – Vijayawada)
2007 / PP&D / DRFC / Pt.-C / EC / Kharagpur – Vijayawada 29.10.2007
M/s Deloitte Touche Tohmatsu India pvt. Ltd.
_ R
s. 4
1,56
,000
/-
_
20 weeks from the date of award of Contract 16.03.2008
8 2007/PP&D/ DRFC/Pt-D/SC/ Chennai - Goa
17.09.07 Project Consultancy Services for Dedicated Freight Corridor, Southern Corridor (Chennai – Goa)
2007 / PP&D / DRFC / Pt.-D / SC / Chennai –Goa 02.11.2007
M/s Deloitte Touche Tohmatsu India pvt. Ltd.
_
R
s. 4
1,56
,000
/-
_
20 weeks from the date of award of Contract 20.03.2008
Details of Contract awarded upto January 2008 by Electrical Department, Corporate Office, RVNL SN Tender
No. Date of
Opening Description of item/work Contract
No. and date
Contractor’s Name
Qty. (for supply
contract) Estimated Cost (for
Elect./S&T/Mech.
Rate (for supply
contract) Tendered Cost (for
Engg./ Elect./ S&T/ Mech.
Value of Con-tract
Scheduled Completion
Date
1 2006/ Elect/ PMT-NRE/ 001
23.05.06 Supply, Erection, Testing & Commissioning of 25 KV, 50HZ, Single Phase, Traction Overhead Equipment, Switching Station and other associated works in connection with patch doubling of Pullampet (Excl) – Nandalur (Incl) section of Guntakal Division of S.C. Railway
2006/Elect/ PMT-NRE/ 001 Dated 18.09.2006
M/s Tata Projects Lmited “Suryodaya” 1-10-60/3, Begumpet Hyderabad – 500 016
Rs.5.99 crore - Rs.8.40 crore
12 months from the date of award
2 2006/ Elect/ NCO/ AC/ 64
14.09.06 Supply, Installation, Testing and Commissioning of Split/Multi-split type of High-wall mounted/Cassette type of Ceiling mounted Air Conditioners along with associated electrical distribution (LT panel and power wiring) and other works for the New Corporate Office Premises of Rail Vikas Nigam Limited at 1st Floor of August Kranti Bhawan, (HUDCO Building), Bhikaji Cama Place, New Delhi.
2006/Elect/ NCO/AC/ 64 Dated 18.09.06
M/s LG Electronics India Pvt. Ltd.
- - Rs.56.54 lakh (including AMC for 4 yrs after expiry of warranty period)
Phase-I: 30 days Phase-II: 90 days
3 RVNL/SC/ NRE-GTL/ DDE
09.02.2007 Detailed Design Engineering in connection with RE of Nandalur-Guntakal in South Central Railway.
RVNL/SC/ NRE-GTL/ DDE Dated 24.04.2007
M/s Consulting Engineering Services (India) Pvt. Ltd., in JV with M/s Ntrust Technological Services Pvt. Ltd., Cuffe Parade, Mumbai-05
Rs.1.3 crore - Rs.81.02 lakh
Six months
Sl No.
Tender Number
Date of Opening Description of Item /Work Contract
No. & Date Contractor's
Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection date.
1 IRCON/CC/TN/RVNL/04/06
31/08/2004 Construction of Sub-Structure consisting of WellFoundations, Piers, Abutments and OtherAncillary Works of 2nd Railway Bridge No. 557at Km 414/544 over River Kuakhai with span of20 × 45.72 metres for RVNL's Railway doublingproject in Cuttack-Barang section of East CoastRailway.
IRCON/2032RVNL.CBRP/TRG. Kuakhai/33,dated 09/12/2004
Main Contractor : M/sIRCON International Ltd.Sub Contractor : M/s TRGIndustries Pvt. Ltd, E - 461,Greater Kailash - II, NewDelhi
Rs 29,08,59,088 Contracted Rs26,70,09,000Final Rs21,35,70,000
Contracted Rs26,70,09,000Final Rs21,35,70,000
(540 daysFrom the date of commencementof work)Original Date of Complection01/05/2006.Actual Complection Date30/04/2006
2 IRCON/CC/TN/RVNL/04/07.
31/08/2004 Construction of Sub-Structures consitsting ofWell/Open Foundations, Piers, Abutments andother Ancillary works of 2nd Railway Bridge No.22 at Km. 437/2-438/4 over river Mahanadi withspan of 1 × 30.50 + 6 × 89.30 + 5 × 76.20 metresfor RVNL's Railway Doubling Projects inRajatgarh - Barang Section of East Coast Railway.
IRCON/2031/CIVIL/RVNL/RBRP/Mahanadi/Gammon/34, dated 05/01/2005
Main Contractor : M/sIRCON International Ltd.Sub Contractor : M/sGAMMON India Ltd./NewBombay
Rs 24,38,57,411 Rs 26,72,67,722 Rs 26,72,67,722 (540 days From the date of commencementof work) Original Complection Date24/05/2006Extended upto 31/10/2007, workis still in progress.
3 IRCON/CC/TN/RVNL/04/11.
06/09/2004 Construction of Sub-Structures consitsting ofPile/Open Foundations, Piers, Abutments andother Ancillary works of 2nd Railway Bridge No.17(3 × 30.5mPSC), 18 ( 1 × 30.5m PSC), 19 ( 1 ×30.5mPSC), 32 ( 2 × 12.2mPSC + 1 × 63mG) and34 ( 3 ×7.35 ×3.7m RCC Box at Km 432/36-40,434/12-14434/26-28, 442/16-20 and 443/8-10 forRVNL's Railway Doubling Project in Rajatgarh-Barang Section of East Coast Railway.
IRCON/2031/RVNL.RBRP/Major Bridges.HSCL/33, dated16/01/2005.
Main Contractor : M/sIRCON International LtdSub Contractor : M/s. Hindustan Steel ConstructionLimited, Kolkata
Rs 96,794,412 Contracted Rs8,79,66,762Revised Rs 5, 94, 97, 000
Contracted Rs8,79,66,762Revised Rs 5, 94, 97, 000
(240 days From the date of commencementof work) Original Complection Date08/07/2005Actual Complection Date15/06/2006.
Details of contracts/award of tenders by RVNL Bhubaneshwar upto January 2008
1 of 5
Sl No.
Tender Number
Date of Opening Description of Item /Work Contract
No. & Date Contractor's
Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection date.
4 RVNL/BBS/TOMKA-KOENJHAR/1 dtd 31/08/2005
24/10/2005 Supply and installation of Track, Signalling andYard Lighting works for construction of Keonjhar -Tomka new BG Railway Line in Orissa, India.
RVNL/BBS/TOMKA-KDJR/14/10/2006/01 Dt20/12/2005
M/s HCIL-Kalindee-ARSSJV, F-5, Gautam Nagar,Gulmohar Park Road, NewDelhi - 110 049
Rs 66,75,14,539 Rs 72,39,29,164 Rs 72,39,29,164 (12 months from the date ofcommencement ) Original Complection Date30/04/2007.Extension applied for 31/12/2007.Work in progress.
5 RVNL/Bhubaneswar/KEONJHAR-TOMKA/2 Dtd21/03/2006
17/04/2006 “Flash butt welding of 60 Kg Rails at site usingMobile Flash Butt Welding Plant in Constructionof Keonjhar – Tomka New BG Railway Line inthe State of Orissa, India”
RVNL/BBS/FBW/KT/FBW.JV/14/22/2006, dated 14/07/2007
M/s RAIL WELDERS JVCENTURY TOWERS 5thFloor, Shakespere Sarini,Kolkata - 700017
Rs 3,50,00,000 Rs 3,30,60,000 Rs 3,30,60,000 (6 months form the date ofcommencement of work)Original Complection Date28/11/2006.Extended and ActualComplection Date 15/03/2007.
6 RVNL/Bhubaneswar/KEONJHAR-TOMKA/2 Dtd21/03/2006
17/04/2006 Depot Supply of Stone ballast in connection withconstruction of Keonjhar-Tomka new BG RailwayLine in the state of Orissa, India."
RVNL/BBS/DEPOT-BALLAST/KT/ARSS/14/30/2006/04, dated02/09/2006
M/s ARSS InfrastructureProjects Limited.Sector - A, Zone - D,38, Mancheswar IndustrialEstate,Bhubaneswar - 10.
Rs2,50,00,000 Rs2,50,00,000 Rs2,20,20,000 ( 6 months form the date ofcommencement of work)Original and Actual ComplectionDate 25/02/2007.
7 RVNL/BBS/Limited TenderGoomty/4/25/19/18
08/09/2006 Proposal for execution of station GOOMTY withother allied works for station NKW,HCNR,CLDR, SGDP and TGRL of Keonjhar-Tomka new BG Rail Project of East CoastRailway.
RVNL/BBS/GOOMTY/TAMKA-KDJR/PKM/14/34/2006/05,dated 12/10/2006
Mr. P K Mohanty,At/Po.-Patalda,Via-Astaranga,Dist.-Puri.
Rs 14,10,753 Rs 14,10,753 (45 days form the date ofcommencement of work)Original and Actual Date26/11/2006.
8 RVNL/BBS/Keonjhar-Tomka/Ballast/SLT/LT /04/06
17/10/2006 Supply & leading of stone ballast by any suitablemeans in connection with construction of Keonjhar-Tomka new BG Railway line in the state ofOrissa.
RVNL/BBS/POB BALLAST/KT/ARSS/14/38/2007, dated06/01/2007
M/s ARSS InfrastructureProjects Limited.Sector - A, Zone - D,38, Mancheswar IndustrialEstate,Bhubaneswar - 10.
Rs 1,57,00,000 Rs 1,01,06,800 Rs 1,01,06,800 (2 months form the date ofcommencement of work withextension)Original Date of Complection17/02/2007.Actual Complection Date31/03/2007.
2 of 5
Sl No.
Tender Number
Date of Opening Description of Item /Work Contract
No. & Date Contractor's
Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection date.
9 RVNL/Bhubaneswar/KOENJHAR-TOMKA / Turn outsleeper/ST/ 01/06,dated 01/12/2006.
12/11/2006 Manufacture and supply of 12 sets of 1 in 8 ½PSC turnout sleepers for Keonjhar – Tomka NewLine Project
LOA No.RVNL/BBS/Tenders/Turnout Sleeper Procurement/ 25/27/2842. 15/01/2007
M/s Calcutta Spring Limited,18, R. N. Mukherjee Road,Kolkata - 700 001.
Rs.23,82,900 Rs.23,82,900 (1 months form the date ofcommencement of work )Original and Actual ComplectioDate 14/02/2007.
10 RVNL/Bhubaneswar/Keonjhar-Tomka/Miscellaneous /LT/05/06, dated31/10/2006
15/11/2006 Execution of miscellaneous works between km58.0 to 155km. With other allied works ofKeonjhar-Tomka new BG Rail Project of EastCoast Railway.
RVNL/BBS/TAMKA-KDJR/14/41/2006, dated06/03/2007
M/s Ramakanta Jena,Railway & State Govt.Contractor, Plot No. : GA -228, " Bipin Niwas",
Rs 52,22,798 Rs 52,22,798 ( 3 months form the date ofcommencement of work withextension)Original Complection Date17/04/2007.Actual Complection Date31/07/2007.
11 RVNL/Bhubaneswar/KEONJHAR-TOMKA/ballast/OT/01/07, dated28.5.2007.
25/06/2007 Supply, leading and loading of machine crushedhard Stone ballast to any type of Rly. Wagon atBGPL. Station yard (Depot) in connection withConstruction of Keonjhar – Tomka new BGRailway Line in the State of Orissa, India.
LOA RVNL/BBS/Tender/Supply &Leading ofStone Ballast toBOYB (KT)/25/30/3867
M/s Sri Durga Condev (P)Ltd,At. Kairapari, P.O. Kotsahi(Tangi), District : Cuttack, Orissa , Pin - 754 022
Rs 266,63,000 Rs 266,63,000 ( 2 months from the date ofcomencement of work ) Original Complection Date8/9/2007.Extention Complection Date31/12/2007.
12 IFB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
30/12/2005 “Construction of Roadbed (except Major bridges),Facilities and General Electrification for doublingof Railway line between Barang-Rajatgarh (25km), Cuttack – Barang (12 km) and 3rd linebetween Barang-Khurda Road (35 km) in thestate of Orissa, India”.
RVNL/BBS/ADB-Roadbed/14/24/2006, dated04/09/2006
M/s HCIL-ADHIKARYA-ARSS JV, 113-A, KamlaNagar New Delhi - 110 007
Rs 151,72,13,941 Rs 153,52,37,906 Rs 153,52,37,906 (24 months Form the date ofcommencement of work)Complection Date 06/09/2008.
3 of 5
Sl No.
Tender Number
Date of Opening Description of Item /Work Contract
No. & Date Contractor's
Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection date.
13 IFB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
30/12/2005 “Construction of Major Bridges in connection withdoubling of railway line between Barang-Rajatgarh (25 km), Cuttack – Barang (12 km) and3rd line between Barang-Khurda Road (35 km)in the state of Orissa, India”.
RVNL/BBS/ADB/Major Bridges/14/28/2006, dated04/09/2006
M/s HCIL-ADHIKARYA-ARSS JV, 113-A, KamlaNagar New Delhi - 110 007
Rs 123,61,04,234 Rs 131,02,94,667 Rs 131,02,94,667 (24 months Form the date ofcommencement of work)Complection Date 06/09/2008.
14 IFB-RVNL/BBS/Doubling-Third Line/2005/02-04 Dtd 16-10-2005
30/12/2005 Supply and installation of track (excluding supplyof rails, signaling and overhead equipment (OHE)& associated equipment for 25 kV, AC traction, inconnection with doubling of railway line betweenBarang-Rajatgarh (25 km), Cuttack – Barang (12km) and 3rd line between Barang-Khurda Road(35 km) in the state of Orissa, India".
RVNL/BBS/ADB/TRACK/14/29, dated09/10/2006
M/s HCIL-ADHIKARYA-ARSS JV, 113-A, KamlaNagar New Delhi - 110 007
Rs 138,32,28,297 Rs 130,85,85,026 Rs 130,85,85,026 (30 months Form the date ofcommencement of work)Complection Date 01/11/2008.
15 Bid Notice No.PMC/RVNL/BBS/ADB/DBL-Third Line/Major Bridges/2005/3 Dt.15/12/2005,
.27/01/2006 Project Management Consultancy Services forConstruction of Major Bridges in connection withdoubling of railway line between Barang-Rajatgarh (25 km), Cuttack – Barang (12 km) and3rd line between Barang-Khurda Road (35 km) inEast Coast Railway in the
RVNL/BBS/ADB/PMC-Major Br/Expert_SPA (JV)/14/25/2006, dated01/11/2006
EXPERT RESORTS &LAYOUTS PRIVATELIMITED , 16/1, BhavaniMansion Road, AmericanColony, Kumar Park East,Bangalore- 560001
Rs 3,00,00,000 Rs 2,61,88,500 Rs 2,61,88,500 (30 months Form the date ofcommencement of work)Complection Date 25/02/2009.
4 of 5
Sl No.
Tender Number
Date of Opening Description of Item /Work Contract
No. & Date Contractor's
Name
Quantity (for supply contract )
Estimated Cost (for Engg/Elect./S & T
/Mech.)
Rate (for supply contract)Tendered
Cost (for Engg./Elect./S & T
/Mech.)
Value of Contract
Scheduledcomplection date.
16 PMC/RVNL/BBS/ADB/DBL-Third Line/Road Bed/Track/2005/2 dated 15/12/2005.
27/01/2006 (a) Project Management Consultancy forConstruction of Roadbed (except Major bridges),Facilities and General Electrification for doublingof Railway line between Barang-Rajatgarh (25km), Cuttack – Barang (12 km) and 3rd linebetween Barang-Khurda Road (35 km) in thestate of Orissa, India.(b) Project ManagementConsultancy for Supply and installation of track(excluding supply of rails, signaling and overheadequipment (OHE) & associated equipment for 25kV, AC traction, in connection with doubling ofrailway line between Barang-Rajatgarh (25 km),Cuttack – Barang (12 km) and 3rd line betweenBarang-Khurda Road (35 km) in the state ofOrissa, India.
RVNL/BBS/ADB/PMC-Roadbed-Track/14/31/2006, dated29/11/2006
M/s Wilbur Smith AssociatesPvt Ltd/ Bangalore.75, 2nd Floor,14th Cross, R. T. Nagar, 1stBlock, Bangalore, Karnataka -560 032.
Rs 5,60,00,000 Rs 5,60,00,000 Rs6,09,66,085 (30 months Form the date ofcommencement of work)Complection Date 10/04/2009.
5 of 5
DETAILS OF CONTRACTS PLACED UPTO 31-01-2008 BY RVNL, SECUNDERABAD
Sl. No.
Tender Number Date of opening
Description of item/work
Contract No. & date
Contractor’s Name
Quantity (For supply contract) Estimted cost (for Engg., Elec.
S&T/Mech)
Rate (For supply
contract) Tendered cost (for Engg., Elec.
S&T/Mech)
Value of Contract
Scheduled completion date
.1 No.2006/ELECT/PMT-NRE/001 dated 13.3.2006
23-5-06 Supply, Erection, Testing and commissioning of 25 Kv OHE bet. Pullampet-Nandalur Sec. of Guntakal Divn. Of S.C. Railway
No.2006/Elec./PMT-NRE/001 dt. 15.11.06
M/s. Tata Projects Limited, Hyderabad. (TPL)
599.83 lakhs
599.83 lakhs
840.47 lakhs
12 months (02-(10-2007)
2 No.RVNL/SC/GY-PMT/104 dated 18-10-05
31/01/06 Gooty-Pullampet patch doubling
No.RVNL/SC/GY-PMT/Agt/104 dated 22-08-2006
M/s. Simplex Infrastructures Ltd., Mumbai
19223.74 Lakhs
19223.74 Lakhs
17074.07 Lakhs
30 + (6 Defect. Liability period) (06-04-2009)
3 No.RVNL/SC/GY-PMT/PMC/106 dated 02-12-05
27-03-06 Project Management Consultancy for Gooty-Pullampet patch doubling
No.RVNL/SC/GY-PMT/PMC/Agmt/106 dated 24.11.06
M/s. Aarvee Associates, Hyderabad
600.00 lakhs
600.00 lakhs
575.32 lakhs
30 + (6 Defect. Liability period (28-03-2009)
4 No.RVNL/SC/OBVP-KP/108 dated
01-09-2006
13-11-06 Venkatachalam to Krishnapatnam Phase I New BG Line
No.RVNL/SC/OBVP-KP/108 dated 27-06-2007
M/s.APR-VNR Joint Venture ,Hyderabad
4060.6 lakhs
4060.6 lakhs
4246.1 Lakhs
12 + (6 months defect liability period) (28-03-2008)
5 No.RVNL/SC/OBVP-KP/PMC/114 dated 25-05-06
09-07-07 Project Management Consultancy for Venkata-chalam to Krishnapa-tnam Phase I works
No.RVNL/SC/OBVP-KP/PMC/114 dated 05-11-07
M/s. Project Engineering Management Services-KITCO (JV), Tiruvananthapuram, Kerala
69.88 Lakhs
69.88 lakhs
84.66 lakhs
12 + (6 months defect liability period (09-09-08)
6 No.RVNL/SC/GTL-RC/112 dated
06-02-2007.
12-04-07 Guntakal-Raichur patch doubling .
No.RVNL/SC/GTL-RC/112 dated 15-10-07
M/s. APR-MVR Joint Venture, Hyderabad
9670.50 lakhs
9670.50 lakhs
9399.34 lakhs
18+6 (6 months defect liability period) dated 23-02-09
Sl. No.
Tender Number Date of opening
Description of item/work
Contract No. & date
Contractor’s Name
Quantity (For supply contract) Estimted cost (for Engg., Elec.
S&T/Mech)
Rate (For supply
contract) Tendered cost (for Engg., Elec.
S&T/Mech)
Value of Contract
Scheduled completion date
7 No.C/ADB/Gooty-Pullampet/ Signalling (Vol.III) dated 10-11-04
20-04-05 S & T Works in Guntakal-Raichur patch doublinhg
No.C/ADB/Gooty-Pullampet/ Signalling (Vol.III) dated 08-11-06
M/s. Leighton Emrail-Kalindee (JV)
10589 Lakhs
10589 Lakhs
9681.31 lakhs
36 months (29-06-09)
8 No.RVNL/SC/GTL-RC/112 dated
06-02-2007.
12-04-07 Guntakal-Raichur patch doubling .
No.RVNL/SC/GTL-RC/112 dated 15-10-07
M/s. APR-MVR Joint Venture, Hyderabad
9670.50 lakhs
9670.50 lakhs
9399.34 lakhs
18+6 (6 months defect liability period) dated 23-02-09
9 No.RVNL/SC/GTL-RC/ 113 dated
21.05.2007
10/07/07 Project Management Consultancy for Guntakal-Raichur patch doubling .
No.RVNL/SC/GTL-RC/ PMC /113/Contract dated 11.12.2007
M/s. SOWiL Limited, Goodwill Avenue, Office No.2, 1st floor, A Wing, Plot No.1, Sector 40, Nerul (West) Navi Mumbai – 400706
200.40 lakhs 200.40 lakhs 121.00 Lakhs
18+6 (6 months defect liability period) dated 23-02-09
Details of Contracts Awarded from 01/01/2004 to May, 2008 from the Corporate Office (S&T)
S.No Tender No./ Purchase Order
No.
Date of Opening
Descripton of Item/Work Contract No. & Date
Contractor's Name Quantity (for supply contract)
Estimated Cost (for Engg. Elect. S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg/Elect/S&T/ Mech.)
Value of Contract
Scheduled Completion Date
1 S&T/DEE-RW/BID dated 20.04.2005
16.06.2005 Supply & Installation of Signalling for replacement of existing signalling and Gauge Conversion of 2nd Meter Gauge line on Delhi Sarai Rohilla- Rewari Section (79 Km) of Northern Railway
S&T/DEE-RW/BID dated 21.10.2005
Consortium (Joint Venture) of M/s Bharat Rail Automation(P)Ltd, B-107 Mandpeshwar Ind.Estate, S.V.P. Road, Borivali(W), Mumbai-400092 and M/s Siemens Ltd, Pandurang Budhkar Marg, Worli, Mumbai-400018
39.00 Crores 39.00 Crores 35.14 Cores 30.04.2007 (20 Months from the date of issue of LOA)
2 RVNL/S&T/RE-AII/BID dated06.05.2006
12.07.2006 Supply & Installation of Signallingand Telecommunication equipmentin connection with MG to BGGauge Conversion on Rewari-Ringus-Phulera-Ajmer Section(294.57 km) of North WesternRailway.
RVNL/S&T/RE-AII/BID dated 13.10.2006
Kiran Infra Engineers Ltd. B-141, Road No.9-D, Vishwakarma Industrial Area, Jaipur-302 013(Joint Venture with M/s Mangla Ispat(Jaipur) Ltd. B-234, Road No.9, V.K.I Area, Jaipur-302013 & M/s Tirupati Plastomatics Pvt.Ltd, B-141, A-Road No. 9D, Vishkarma, Industrial Area, Jaipur-302013
66.00 Crores 66.00 Crores 72,30,66,612 18 Months from the date of issue of LOA(out of which the work in Rewari-Phulera section shall be completed in first 12 months time).
3 Purchase OrderNo. RVNL/S&T-01/2006 dated5.6.2007
16.01.2007 Supply of Signaling and QuadCable in connection with Samdari-Bhildi Section and Gaziabad-Aligarh J. Section
Work awarded vide Purchase Order No. RVNL/S&T-01/2006 dated 5.6.2007
1) M/s Tirupati Plastomatics Pvt. Ltd., B- 141(A), Road No. 9-D, Vishwakarma Industrial Area, Jaipur - 302013.
2) M/s Paramount Wires & Cables Ltd., C-125, Naraina Industrial Area, Phase-1, New Delhi - 110028.
1) 507 KM
2) 277 KM
____
____
1) 7,25,31,461/-
2) 5,28,05,215/- 4 months from the date of issue of Purchase Order
4 RVNL/S&T (shifting)/GZB-ALJN/BID dt.05.04.2007
17.04.2007 Shifting of Signaling field equipmentin connection with 3rd Line work inGhaziabad-Aligarh section of NorthCentral Railway
Work awarded vide Ltter of Acceptance No. RVNL/S&T(Shifting)/GZB-ALJN/BID dated 30.5.2007
M/s Ashok Engineering Works, 13-C, Daud Nagar, Naini, Allahabad, Uttar Pradesh
1,98,32,273.66 1,98,32,273.66 1,97,33,112 4 months from the date of issue of LOA
5 RVNL/S&T/SMR-BLDI/BID dated15.10.2007
20.11.2007 Laying Commissioning & Testing of6 quad Cable and associatedTelecommunication Circuits inconnection with MG to BG GaugeConversion on Samdari - Bhildi(223.44 km) of North WesternRailway
RVNL/S&T/SMR-BLDI dated 16.04.2008
M/s Alcon Builders and Engineers Pvt. Ltd. B-1/51, Malviya Nagar, New Delhi - 110017
3,34,39,747 3,34,39,747 4,69,88,536 9 months from the date of isue of LOA
S. No.
Tender/ICB No. Date of Opening
Description of Item/Work Letter of Award No. Letter of Award Date
Contractor’s Name Qty. (for supply contract)
Estimated Cost (for Engg./Elect./
S&T/Mech.)
Rate (for supply contract in Rs.) Contract Cost
(for Engg./Elect. /S&T/Mech. in
Lakh/Cr.)
Value of Contract
Scheduled Completion Date
6 PMC/RVNL/BBS/ADB/DBL-Third Line/Roadbed-Track/2005/2
27-01-06 PMC for (i) Contruction of Roadbed (exceptmajor bridges), facilities and generalelectrification in connection with doubling ofrailway line between Barang-Rajatgarh (25 Km),Cuttack-Barang (12 Km) and 3rd line betweenBarang-Khurda Road (35 Km) in the state ofOrissa; and (ii) Suplly and Installation of Track(excluding supply of rails), Signaling and OHE &associated equipment for 25 KV AC traction inconnection with doubling of railway line betweenBarang-Rajatgarh (25 Km), Cuttack-Barang (12Km) and 3rd line between Barang-Khurda Road(35 Km) in the state of Orissa.
PMC/RVNL/BBS/ADB/DBL-Third Line/Roadbed-Track/2005/2
13-09-06 M/s. Wilbur Smith Associates Pvt. Ltd., Bangalore.
-- 6.09 Cr. 6.09 Cr. 30 Months with defect liability period(From the date ofcommencement of work)
7 RVNL/JP/T&Q/PMC/002 22-08-06 Project Management Consultancy Services forGauge Conversion (MG to BG) of Railway Trackin Rewari-Ringus-Phulera-Ajmer (294.57 KM)Section including electrical works, supply andreplacement of existing signaling system of N. W.Railway
RVNL/JP/T&Q/PMC/2006/002/Part III
13-09-06 M/s. Sowil Ltd. & Halcrow Consulting Indig Ltd. (JV), Noida.
6.80 Cr. 5.75 Cr. 5.75 Cr. 33 Months with defect liability period(From the date ofcommencement of work)
8 RVNL/SC/GY-PMT/PMC/106
03-04-06 PMC for Patch Doubling of Track on Gooty-Pullampet Section of South Central Railway.
RVNL/SC/GY-PMT/ PMC/106
29-09-06 M/s. Aarvee Associates, Hyderabad.
6.00 Cr. 5.75 Cr. 5.75 Cr. 30 Months excluding defect liabilityperiod (From the date ofcommencement of work)
9 RVNL/Rail Procurement/1 of 2005
24-02-06 Manufacture & Supply of 69775 MT 60 Kg UIC Rails (Grade 880, Class A) conforming to IRS-T-12-96 for various railroad projects in different regions of India.
2005/RVNL/P/III/Rail Supply/01
09-02-07 M/s. SAIL, New Delhi.
69775 MT 35500 255.38 Cr. 18 Months (From the date ofcommencement of work)
10 RVNL/CPM/MAS/IPL-ICTT/01
29-08-06 Provision of Rail Connectivity from Idappalli to ICTT, Vallarpadam for works of elevated structures, major and minor bridges and earthwork in Trivendrum Division of SR.
RVNL/CPM/MAS/IPL-ICTT/01
21-02-07 M/s. Afcons Infrastructure Ltd., Mumbai.
171.24 Cr. 167.81 Cr. 167.81 Cr. 24 Months (From the date ofcommencement of work)
11 2005/RVNL/P/CC.P.Way (PB)
24-03-06 Construction of all P.Way Works including supply of ballast and P.Way materials (excluding rails and PSC line sleepers), signaling and OHE for Palway-Bhuteshwar 3rd Line (81 Km) on North Central Railway.
2005/RVNL/P/CC/P.Way (PB)
20-03-07 M/s. Kalindee_Cobra (JV), New Delhi.
88.59 Cr. 118.70 Cr. 118.70 Cr. 18 Months (From the dateof commencement of work)
S. No.
Tender/ICB No. Date of Opening
Description of Item/Work Letter of Award No. Letter of Award Date
Contractor’s Name Qty. (for supply contract)
Estimated Cost (for Engg./Elect./
S&T/Mech.)
Rate (for supply contract in Rs.) Contract Cost
(for Engg./Elect. /S&T/Mech. in
Lakh/Cr.)
Value of Contract
Scheduled Completion Date
12 RVNL/Bhubaneshwar/HDS-PRDP/5
12-10-06 Construction of Roadbed including Major and Minor Bridges, Facilities and General Electrification in connection with construction of New BG Line between Haridaspur and Paradeep in East Coast Railway, in the State of Orissa, India
RVNL/BBS/Tender/HDS-PRDP/Roadbed-Major Bridges/25/21
19-06-07 M/s. HCIl-Adhikarya(JV), Delhi.
223.04 Cr. 276.35 Cr. 276.35 Cr. 24 Months (From the date ofcommencement of work)
13 RVNL/PII/PSC Sleepers /1 of 2007
15-03-07 ICB 170107: Manufacture and supply of PSCMonoblock sleepers for Broad Gauge (1673) bysetting up new sleeper plants for various railroadprojects in different regions of Inda - Lot No.17010704
RVNL/PSC Sleepers/1 of 2007/165
06-07-07 M/s. RaghavendraRail InfrastructurePvt. Ltd.,Secunderabad
225000 No. 1126.50 25.34 Cr. 18 Months (From the dateof commencement of work)
14 RVNL/PII/PSC Sleepers /1 of 2007
15-03-07 ICB 170107: Manufacture and supply of PSCMonoblock sleepers for Broad Gauge (1673) bysetting up new sleeper plants for various railroadprojects in different regions of Inda - Lot No.17010701.
RVNL/PSC Sleepers/1 of 2007/185
27-07-07 M/s. VamanPrestressing Co.Ltd., Mumbai.
210000 No. 1268.83 26.64 Cr. 18 Months (From the dateof commencement of work)
15 RVNL/JP/T&Q/Bridges /2007/010
20-08-07 Rebuilding, strengthening of major bridges andreplacement of PSC slab of minor bridges inconnection with GC of meter gauge line to broadgauge on Rewari-Ajmer Section of NorthWestern Railway.
2007/RVNL/P/CC/Bridges/011
12-09-07 M/s. R. C. Kapoor-M.M. Shawl (JV), New Delhi.
15.51 Cr. 17.52 Cr. 17.52 Cr. 12 Months (From the dateof commencement of work)
16 RVNL/PII/PSC Sleepers /1 of 2007
15-03-07 ICB 170107: Manufacture and supply of PSCMonoblock sleepers for Broad Gauge (1673) bysetting up new sleeper plants for various railroadprojects in different regions of Inda - Lot No.17010705
RVNL/PSC Sleepers/1 of 2007/36
01-11-07 M/s. Prestress IndiaPvt. Ltd., NaviMumbai.
170000 No. 1477.60 Cr. 25.11 Cr. 18 Months (From the dateof commencement of work)
17 RVNL/Raipur/SA-KH-KHD-ANP/5
29-11-07 Const. of Roadbed, Major & Minor bridges, TrackLinking (excluding supply of rails, sleepers, thickweb switches and spl. Sleepers), S&T, and OHE& General Electrical work in c/w doublingbetween Salka Road-Khongsara (25.8 KM) andKhodri-Anuppur (61.6 KM) on Bilaspur Division ofSECR in Chattisgarh and MP states, India.
RVNL/Raipur/SA-KH-KHD-ANP/5
15-04-08 M/s. DS Const. Ltd.-BEST and CromptionEngrs. Ltd. (JV), NewDelhi.
170.12 Cr. 177.49 Cr. 177.49 Cr. 24 Months (From the date ofcommencement of work)
Tender Number Date of Opening
Description of Item/Work Contract No. & date of
award
Contractor's Name Quantity (for supply contract)
Estimated Cost (for Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tenderered Cost (for Engg./Elect./
S&T/Mech.)
Value of Contract
Scheduled completion
date
2005/RVNL/P/CC/PB dtd. 22.07.05
29.07.05 Design & Proof checking of Additional Openings in ROBs at Kosi Kalan and Bhuteshwar
03.08.05 M/s Unique Engineers 3.6 Lacs 3.33 Lacs 3.33 Lacs 23.08.05
2005/RVNL/CC/P/DEE/Palwal-Bhuteshwar dt.12.08.05
29.08.05 Detailed Design Engineering for Palwal - Bhuteshwar 3rd Line of NCR
12.09.05 M/s Scott Wilson Kirkpatrick India Pvt. Ltd.
53.01 Lacs 47.00 Lacs 47.00 Lacs 11.03.06
2005/RVNL/CC/P/2005/Jn.-Tkd dt.16.09.05
29.09.05 Detailed Design Engineering for Jn. Cabin - Palwal 4th Line (34 Km.) of NR
07.10.05 M/s Dalal Mott Macdonald 16.94 Lacs 19.61 Lacs 19.61 Lacs 06.01.2006
2005/RVNL/CC/P/PCDE/Palwal-Bhuteshwar
6.03.06 Proof Check of Detailed Design Engineering in connection with Palwal-Bhuteshwar
28.03.06 M/s Dalal Mott Macdonald - 8.20 lakh. 8.20 Lacs 28.03.2006
2005/RVNL/P/CC/Civil Works
27.12.05 All Civil Engineering and connected General Electrical Works for Construction of Road bed facilities, Buildings, Box-pushing in existing 2 ROBs including Misc. works for Palwal-Bhuteshwar 3rd Line (81 Kms) on North Central Railway
8.5.2006 M/s Era Consutrction India Ltd.
62.05 Cr. 62.05 Cr. 62.05 Cr. 8.5.2006
2005/RVNL/P/CC/PMC (PB) dated 11.09.06
23.06.06 PMC of construction of palwal-Bhuteshwar 3rd Line Doyubling (81 kms) in the State of Haryana and Uttar Pradesh (India) including Road bed facilities, Bridge works, Box Pushing, Flash Butt Welding, P.Way, miscellaneous Civil works, Electrical works including OHE and Signalling and Interlocking works on North Central Railway
27.09.06 M/s Scott Wilson kirkpatric India Pvt. Ltd.
4.32 Cr. 4.28 Cr. 4.28 Cr. 26.12.08
RVNL/NDLS/ALJN-GZB/2005/01 dated
14.10.05.
23.12.2005 Construction of Roadbed, Bridges, Facilities, Installation of Track (excluding Supply of Rails, Thick Web Switches & Weldable CMS Crossings) & Electrical (Railway Electrification & General Electrification) in connection with Provision of 3rd line on Aligarh - Ghaziabad Section (106 Kms.) in the State of Uttar Pradesh (India).
08.06.06 M/s IRCON - GANNON - Dunkerly - JV
188.00 Crore 223.94 Cr. 223.45 Cr. 13.07.08
Details of Contracts Awarded upto Mar 2009 in connection with Palwal-Bhuteshawar and Aligarh-Ghaziabad 3rd line CPM/DLI
CPM_DLI_2April2009.xls Contract Awarded upto March 09
Tender Number Date of Opening
Description of Item/Work Contract No. & date of
award
Contractor's Name Quantity (for supply contract)
Estimated Cost (for Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tenderered Cost (for Engg./Elect./
S&T/Mech.)
Value of Contract
Scheduled completion
date
RVNL/NDLS/ALJN-GZB/2005/02 dated 16.11.05.
28.12.05 PMC for the Construction of Roadbed, Bridges, Facilities, Installation of Track (Excluding Supply of Rails, Thick Web switches and weldable CMS crossings( & Electrical (Railway Electrification and General Electrification) in connection with provision of 3rd Line on Aligarh - Ghaziabad Section (106 Kms) in the state of Uttar Pradesh)
10.07.06 LASA-Wilbur Smith Associates-JV
4.46 Cr. 4.97 Cr. 4.90 crores 06.3.09
2005/RVNL/P/CC/P.Way(PB) dated 20.3.2007.
Construction of all P.Way Works including supply of Ballast and P.Way Materials (Excluding Rails and PSC sleepers), Signalling and OHE for Palwal-Bhuteshwar 3rd Line (81 kms.) on NC Railway.
M/s Kalindee- Cobra JV. 88.59 Cr. 118.7 Cr. 118.7 Cr. 19.11.08
CPM_DLI_2April2009.xls Contract Awarded upto March 09
Tender No. Date of Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract) Estimated Cost (for Engg./Elect./S&T/Mech.)
Rate (for supply contract) Tendered Cost (for Engg./Elect./S&T/Mech.)
Value of Contract
Scheduled Completion Date
RVNL/P-III/BIN-BPL/Composite Works Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges, Track Linking (excluding supply of rails, thick web switches & sleepers), S&T and OHE & General Electrical work in connection with 3rd line between Habibganj & Bina (144.76 Km) on Bhopal Division of West Central Railway in the state of Madhya Pradesh (India) - Package No. 1 between Bina (Incl) to Ganj Basoda (Incl) chainage 975.16 to 928.500 (Km 46.66).
Notification of Award No. RVNL/P-III/BIN-BPL/Composite Works Tender/Package-1 dated 31.08.2009 (Contract agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC Division,Post Box No. 979,Mount Poonamalle Road,Manakakkam, Chennai-600089.
-- --
141,87,83,852 March, 2012
RVNL/P-III/BIN-BPL/Composite Works Tender
31.01.2009 Construction of Road Bed, Major and MinorBridges, Track Linking (excluding supply ofrails, thick web switches & sleepers), S&Tand OHE & General Electrical work inconnection with 3rd line between Habibganj& Bina (144.76 Km) on Bhopal Division ofWest Central Railway in the state ofMadhya Pradesh (India) - Package No. 2between GanjBasoda (Excl) to Sanchi (Incl)chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No. RVNL/P-III/BIN-BPL/Composite Works Tender/Package-2 dated 31.08.2009 (Contract agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC Division,Post Box No. 979,Mount Poonamalle Road,Manakakkam, Chennai-600089.
-- ‐‐
150,04,89,048 March, 2012
RVNL/P-III/BIN-BPL/Composite Works Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges, Track Linking (excluding supply of rails, thick web switches & sleepers), S&T and OHE & General Electrical work in connection with 3rd line between Habibganj & Bina (144.76 Km) on Bhopal Division of West Central Railway in the state of Madhya Pradesh (India) - Package No. 3 between Sanchi (Excl) to Habibganj (Incl) chainage 879.750 to 830.850 (Km 48.9).
Notification of Award No. RVNL/P-III/BIN-BPL/Composite Works Tender/Package-3 dated 31.08.2009 (Contract agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV), C/o M/S Nagarjuna Construction Company Limited,4th Floor, Uma Enclave, Road No. 9, HYDERABAD-500034.
-- ‐‐
135,64,97,042 March, 2012
Details of Contracts Placed upto the month August, 2009 under GM/P‐III
RAIL VIKAS NIGAM LIMITED / BHUBANESWAR
GM(Elect)/CO/RVNL FAX: (011)- 26738191 POSITION AS ON 04.10.2009
I. LIST OF TENDERS PENDING FOR FINALIZATION
S/N CV Date of Opening
Briefing Note
Preparation of comparative
statement
TC Minutes Finalized/ Accepted
Contract Value
(In Crores) 1. Design, Supply, Erection, Testing & Commissioning of SCADA(Supervisory Remote
Control and Data Acquisition) equipments along with Annual Maintenance Contract(AMC) for a period of Four Years after warranty period of Three years against the Railway Electrification work for Jakhapura-Tomka-Banspani section under Khurda Road Division of East Coast Railway, in the State of Orissa.
21.08.2009 Vetted on 16.09.09
(Technical)
-- BEC minutes (Technical) under
preparation.
1.13 Crs.
II. TENDERS UNDER INVITIATION
S/N Name of the work Date of Tender Notice
Date of Prebid meeting
Due date of Tender Opening
Estimated Tender Cost in Crores Remarks
NIL
III. CONTRACTS AWARDED
S/N Tender No.
Date of Opening Description of item/work
Letter of Acceptance No.
and date Contractor’s
Name
Qty. (for supply
contract) (for Elect/
S&T/Mech)
Rate. (for supply contract)
tendered cost (for Engg/Elect/
S &T/Mech)
Value of Contract (In Rs)
Scheduled Completion
period
1. 2007/ELECT/ BANSPANI/
OHE/82, dtd. 01.10.07
29.11.07 Supply, Erection, Testing and Commissioning of 25 kV AC 50 HZ single phase Traction Overhead Equipment and other associated works in connection with Railway Electrification of Tomka-Jaroli (144RKM/180 TKM) single line section of Khurda Road Division of East Coast Railway.
2007/Elect/ Banspani/
OHE/82/Gr.146 /6085,
dtd. 28.03.08
M/s. Cobra Instalaciones y Servicios, S.A., New Delhi.
-- Rs. 46,48,70,937/- 49,78,14,263/- 24 months i.e.
27.03.2010
2. RVNL/BBS/ HDS-PRDP/G/
HT-LT/OT/ 01/2008,
dtd. 08.01.08
15.02.08 Modification of 33 & 11 kV HT/LT Power Supply Line crossings over HDS-PRDP section of new railway track through UG, (XLPE) cable under the jurisdiction of KUR Division of East Coast Railway.
RVNL/BBS/ HDS-PRDP/G/ HT-LT/OT/01/
2008/6225, dtd. 31.05.08
M/s. Sarala Engineering Works, Kendrapada, Orissa.
-- Rs. 4,79,02,658/- 4,42,14,154/- 12 months i.e.
30.05.2009
1st Ext. up to 31.10.2009
3. RVNL/BBS/ Tomka-Jaroli/ GPS/AT-CLS/ OT/05/2008, dtd. 08.04.08
16.05.08 Supply, erection, testing and commissioning of XLPE armoured cables and its accessories for the commissioning of 10 KVA, 25/0.240 KV outdoor type auxiliary transformer and CLS works at 14 stations in Tomka-Jaroli section under Khurda Road Division of East Coast Railway in the state of Orissa.
RVNL/BBS/ Tomka-Jaroli/
GPS/AT-CLS/OT/ 05/2008/6480, dtd. 10.09.08.
M/s. AAYBEE Electrical & Construction, A-55, Saheed Nagar, Bhubaneswar-01
-- Rs. 89,03,258/- 80,04,029/- 12 months i.e.
09.09.2009
1st Ext. up to 31.03.2010
4. RVNL/BBS/ Tomka-Jaroli/
PSI/OT/07/ 2008,
dtd. 15.05.08
27.06.08 Design, supply, erection, testing & commissioning of 132/25 kV, 2 x 21.6 MVA, Traction-sub-Station, feeding post, shunt capacitor Bank and with other associated works at Keonjhar & Tomka, along with 9 nos. of Switching Stations in Tomka-Jaroli section under Khurda Road Division of East Coast Railway, in the State of Orissa.
RVNL/BBS/ Tomka - Jaroli/PSI/
OT/07/2008/6506, dtd. 22.09.08
M/s. GET Power Pvt. Ltd., 5th Floor, Apex Plaza, Nungambakkam High Road, Nungambakkam Chennai-34
-- Rs. 14,53,81,079/- 14,64,89,316/- 18 months i.e.
21.03.2010
(Cont…….P/2)
--2--
S/N Tender No.
Date of Opening Description of item/work
Letter of Acceptance No.
and date Contractor’s
Name
Qty. (for supply
contract) (for Elect/ S&T/
Mech)
Rate. (for supply contract)
tendered cost (for Engg/Elect/
S &T/Mech)
Value of Contract (In Rs)
Scheduled Completion
period
5. RVNL/BBS/3rd Line/Doubling/ GPS/AT-CLS/ OT/ 04/2008, dtd. 04.04.08
30.05.08 Supply, erection, testing and commissioning of 25 kV /240 V, 25 KVA oil filled outdoor type auxiliary transformers, XLPE cable, CLS panels and their accessories for the section of KUR-BRAG-RJGR/CTC in connection with 3rd line/doubling work under Khurda Road Division of East Coast Railway in the state of Orissa.
RVNL/BBS/3rd Line/Doubling/ GPS/AT-CLS/
OT/04/2008/6518, dtd. 26.09.08
M/s. Akshaya Kumar Das, Plot No. 502, Das Nivas, Nayapalli, Bhubaneswar-12
-- Rs. 87,51,472/- 87,84,931/- 12 months i.e.
25.09.2009 1st Ext. up to 31.03.2010
6. RVNL/BBS/Elect/Doubling-
3rd line/ ADB/ HT.MOD/OT/10/
2008, dtd. 22.10.2008.
28.11.08 Modification of 33kV & 11kV HT Power Line Railway track crossings of M/s. CESCO through underground (XLPE) cable between KUR-BRAG-RJGR/CTC section under Doubling/3rd line work in Khurda Road Division of East Coast Railway, in the State of Orissa.
RVNL/BBS/ Elect/ Doubling-3rd line/
ADB/HT. MOD/OT /10/2008/6806, dtd. 23.12.08
M/s. Kalinga Engineering & Architecture Works, 214, Gajapati Nagar, Bhubaneswar-05
-- Rs. 28,86,275/- 30,16,157/- Original 3 months
up to 22.03.09
4th Ext. up to 22.11.09
7. RVNL/BBS/ JKPR-HDS/PSI/ OT/08/2008, dtd.
03.09.2008
14.10.08 Design, supply, erection, testing & commissioning of additional 132/25 kV, 21.6 MVA, power transformer with associated equipments at Jakhapura Traction-Sub-Station, under Khurda Road Division of East Coast Railway, in the State of Orissa.
RVNL/BBS/ JKPR-HDS/PSI/OT/08/
2008, dtd. 05.02.09
M/s. Siddhartha Engineering Ltd. Plot No. 1389, Gandamunda Near Netaji Subhas Chandra Bose Park Bhubaneswar-30
-- Rs. 3,02,43,061/- 3,21,92,111/- 12 months i.e.
04.02.2010
8. RVNL/BBS/Elect(G)/Doubling-3rd line/ADB/Lift for MS/OT/09/2008, dtd. 10.10.2008.
27.11.08 Supply erection, and commissioning of 04 Nos. of service elevators (lifts) for 02 Nos. (G+8) Multistoried buildings at Bhubaneswar station area under the jurisdiction of Khurda Road division of East Coast Railway, in the State of Orissa.
RVNL/BBS/Elect. (G)/Doubling-3rd line /ADB/Lift for MS/ OT/09/2008/
7163, dtd. 29.04.09
M/s. OMEGA Elevators, 5/c, Archana Industrial Estate, Opp. Ajit Mills, Rakhial, Ahmedabad -23.
-- Rs. 78,83,920/- 65,52,000/- 06 months i.e.
28.10.2009
9. RVNL/BBS/ Tomka-
Jaroli/PSI/ OT/12/2008, dtd.
01.12.2008
22.01.09 Design, supply, erection, testing & commissioning of 132 kV single circuit two phase line on DC Tower from Keonjhar-TSS to Harichandanpur-TSS including 132/25 kV, 2 x 21.6 MVA, Traction-Sub-Station at Harichandanpur and their associate equipments in Tomka-Jaroli section under Khurda Road Division of East Coast Railway, in the State of Orissa.
RVNL/BBS/ Tomka -Jaroli/ PSI/OT/12/
2008/7271, dtd. 03.06.09.
M/s. Cobra-NMTPL(JV), B-324, New Friends Colony, New Delhi – 65
-- Rs. 17,94,71,272/- 18,44,90,426/- 18 months i.e.
02.12.2010
(S.K.Das)
GM(Elect)/RVNL/BBS
S.No Tender No. Date of Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract) Estimated Cost (for Engg./Elect./S&T/Mech.)
Rate (for supply contract) Tendered Cost (for Engg./Elect./S&T/Mech.)
Scheduled Completion Date
1 RVNL/P-III/BIN-BPL/Composite Works Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges, Track Linking (excluding supply of rails, thick web switches & sleepers), S&T and OHE & General Electrical work in connection with 3rd line between Habibganj & Bina (144.76 Km) on Bhopal Division of West Central Railway in the state of Madhya Pradesh (India) - Package No. 1 between Bina (Incl) to Ganj Basoda (Incl) chainage 975.16 to 928.500 (Km 46.66).
Notification of Award No. RVNL/P-III/BIN-BPL/Composite Works Tender/Package-1 dated 31.08.2009 (Contract agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC Division,Post Box No. 979,Mount Poonamalle Road,Manakakkam, Chennai-600089.
--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-BPL/Composite Works Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,Track Linking (excluding supply of rails, thick webswitches & sleepers), S&T and OHE & General Electricalwork in connection with 3rd line between Habibganj & Bina(144.76 Km) on Bhopal Division of West Central Railwayin the state of Madhya Pradesh (India) - Package No. 2between GanjBasoda (Excl) to Sanchi (Incl) chainage928.500 to 879.750 (Km 48.75).
Notification of Award No. RVNL/P-III/BIN-BPL/Composite Works Tender/Package-2 dated 31.08.2009 (Contract agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC Division,Post Box No. 979,Mount Poonamalle Road,Manakakkam, Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-BPL/Composite Works Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges, Track Linking (excluding supply of rails, thick web switches & sleepers), S&T and OHE & General Electrical work in connection with 3rd line between Habibganj & Bina (144.76 Km) on Bhopal Division of West Central Railway in the state of Madhya Pradesh (India) - Package No. 3 between Sanchi (Excl) to Habibganj (Incl) chainage 879.750 to 830.850 (Km 48.9).
Notification of Award No. RVNL/P-III/BIN-BPL/Composite Works Tender/Package-3 dated 31.08.2009 (Contract agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV), C/o M/S Nagarjuna Construction Company Limited,4th Floor, Uma Enclave, Road No. 9, HYDERABAD-500034.
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way items/Guntakul-Raichur/1 of 2009/Switches; Lot No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm) for patch doubling of Guntakul-Raichur Section under CPM/RVNL/SC
RVNL/P-III/P.way items/Guntakul-Raichur/1 of 2009/Switches dated 30.03.2009
M/s VAE VKN Industries Pvt. Ltd., 24/5 Sriram Road, Civil Lines, Delhi-110054.
Manufacture ans Supply: Rs 1.02 Lakh for 60 kg 1 in 12 Switches and Rs 0.74 Lakh for 60 kg 1 in 8 1/2 Switches. Transportation: Rs 25.00 Th for 60 kg 1 in 12 Switches and Rs 22.50 Th for 60 kg 1 in 8 1/2 Switches.
Rs 1.77 Cr 30.09.2009
5 RVNL/P-III/P.way items/Guntakul-Raichur/1 of 2009/CMS Xing; Lot No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm) for patch doubling of Guntakul-Raichur Section under CPM/RVNL/SC
RVNL/P-III/P.way items/Guntakul-Raichur/1 of 2009/CMS Xing dated 30.03.2009
M/s VAE VKN Industries Pvt. Ltd., 24/5 Sriram Road, Civil Lines, Delhi-110054.
Manufacture ans Supply: Rs 2.04 Lakh for 60 kg 1 in 12 CMS Crossing and Rs 1.75 Lakh for 60 kg 1 in 8 1/2 CMS Crossing. Transportation: Rs 3.00 Th for 60 kg 1 in 12 CMS Crossing and Rs 2.40 Th for 60 kg 1 in 8 1/2 CMS Crossing.
Rs 3.02 Cr 30.09.2009
6 2006/RVNL/Mumbai/Bina-Bhopal/2006 dated 30.08.2006
30.06.2006 Coducting Final Location Surey(FSL) from the center line of the final alignment & detailed design Engg (DDE) Between Bina- Bhopal (138 Km) in WC Rly.
2006/RVNL/Mumbai/Bina- Bhopal/2006 dated 23.02.2006
M/s March Services & contractors Sagam Road, Pune-30
--- Rs 1.23 Cr 20.08.2007
Details of Contracts Placed upto the month September, 2009 under GM/P‐III
Page 1 of 14
Quarterly Progress Report of RVNL Works at Bhubaneswar From July’09 to Sept’09
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
1.RAJATHGARH-BARANG, CUTTACK-BARANG DOUBLING & KHURDA ROAD-BARANG THIRD LINE
a “Construction of Roadbed (except Major bridges), Facilities and General Electrification for doubling of Railway line between Barang-Rajatgarh (25 km), Cuttack – Barang (12 km) and 3rd line between Barang-Khurda Road (35 km) in the state of Orissa, India”.
RVNL/BBS/ADB-Roadbed/14/24/2006 Dt 04/09/2006
M/s HCIL-ADHIKARYA-ARSS JV, 113-A, Kamla Nagar New Delhi - 110 007
7/9/2006 24 to 36 months (Revised)
62%
CPM-I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 2 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
Civil Engineering works Electrification works Total
Rs 14816 Lakh Rs 356 Lakh Rs 15172 Lakh
Rs 14851 Lakh Rs 501 Lakh Rs 15352 Lakh
0.60% below 75.84% above 1.19 above
b “Construction of Major Bridges in connection with doubling of railway line between Barang-Rajatgarh (25 km), Cuttack – Barang (12 km) and 3rd line between Barang-Khurda Road (35 km) in the state of Orissa, India”.
Rs 12361 Lakh
Rs 13102 Lakh
(+) 6% RVNL/BBS/ADB-Major Bridges/14/28/06 Dt.04/09/2006
M/s HCIL-ADHIKARYA-ARSS JV, 113-A, Kamala Nagar New D0elhi - 110 007
7/9/2006 24 to 36 months (Revised)
73% CPM-I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 3 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
C Project Management Consultancy Services for Construction of Major Bridges in connection with doubling of railway line between Barang-Rajatgarh (25 km), Cuttack – Barang (12 km) and 3rd line between Barang-Khurda Road (35 km) in East Coast Railway in the State of Orissa.
Rs 300 Lakh
Rs 261 Lakh
(-) 13% LOA-RVNL/BBS/Contract/Expert Resort-SPA(PMC-Major Bridges) 14/25/1517 Dt 23/06/2006
EXPERT RESORTS & LAYOUTS PRIVATE LIMITED , 16/1, Bhavani Mansion Road, American Colony, Kumar Park East, Bangalore- 560001
29/8/2006 30 months 42 months (Revised)
82 % CPM-I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 4 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
d Supply & Installation of Track (excluding supply of rails), Signaling and Overhead Equipment (OHE) & associated equipment for 25 KV, AC traction in connection with doubling of Railway line between Barang Rajatgarh (25 Km), Cuttack – Barang (12 Km) and 3rd line between Barang – Khurda Road (35 Km) in the state of Orissa, India Civil Engineering Works
Rs 8087 Lakh
Rs 7088 Lakh
12.35% Below
RVNL/BBS/ADB-Track/14/29/2006, Dt 09/10/06
M/s HCIL-ADHIKARYA-ARSS JV, 113-A, Kamla Nagar New Delhi - 110 007
2/11/2006 30 months 36 Months (Revised)
43%
CPM-I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 5 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
S & T Works Electrical Works Total
Rs 3638 Lakh Rs 2107 Lakh Rs 13832 Lakh
Rs 3298 Lakh Rs 2700 Lakh Rs 13086 Lakh
9.34% Below 28.14% above (-) 5.4% Below
32% 21% 36 %
E a) Project Management Consultancy for Construction of Roadbed (except Major bridges), Facilities and General Electrification for doubling of Railway line between Barang-Rajatgarh (25 km), Cuttack – Barang (12 km) and 3rd line
Rs 700 Lakh
Rs 609 Lakh
(-) 13 %
RVNL/BBS/ADB/PMC-Roadbed-Track/14/31/2006
M/s Wilbur Smith Associates Pvt Ltd/ Bangalore.
11/10/06 30 Months 42 Months (Revised)
73% CPM-I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 6 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
between Barang-Khurda Road (35 km) in the state of Orissa, India. b) Project Management Consultancy for Supply and installation of track (excluding supply of rails, signaling and overhead equipment (OHE) & associated equipment for 25 kV, AC traction, in connection with doubling of railway line between Barang-Rajatgarh (25 km), Cuttack –
Page 7 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
Barang (12 km) and 3rd line between Barang-Khurda Road (35 km) in the state of Orissa, India
2. ANGUL-BUDHAPANK-SUKINDA ROAD/BAGHUAPAL IN EAST COAST RAILWAY
a “Conducting Confirmatory Final Location Survey & marking of center line of final alignment on ground, and preparation of land plan & schedule for carrying out land acquisition for proposed new
Rs 96 Lakh
Rs 72 Lakh
(-) 25 %
RVNL/BBS/CFLS/ANGL-SKND.RD/PS/14/47/2007/01, dated 23/11/2007
M/s Pioneer Surveyors, Swagat Garden Block – C, Ground floor Deshbandhu Nagar, Baguiati, Kolkata – 700 059.
23/10/07 12 Months 100% CFLS And 40 % Land Acquisition
CPM-II /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 8 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
BG line between Angul - Budhapank – Sukinda Road/Baghuapal in East Coast Railway.”.
3. Construction of Third line in Jakhapura – Haridaspur section on Howrah Chennai main line of Khurda Road Division of ECoR. a Construction of
Br No. 449 over river Brahmani ( 29 x 45.7m) in connection with 3rd line between Jakhapura and Haridaspur on Howrah – Chennai Main Line in East Coast Railway, in Orissa”.
Rs 9626 Lakh
Rs 9212 Lakh
(-) 4.3%
RVNL/BBS/HDS-JKPR/BRIDGE 449 ( BRAHMANI)/OT/14/51/2008/04, dated 08/08/2008
M/s BEB – DDS – RKD Joint Venture. 72/A, Mancheswar Industrial Estate. Bhubaneswar – 751 010.
09/08/08 08/08/10 22% CPM-II /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 9 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
b Construction of Roadbed, major and Minor Bridges and Track Linking (Excluding supply of rails and sleepers, turn out sleepers and thick web switches ) including S &T and OHE & General Electrical works in connection with third line between Jakhapura – Haridaspur ( 25.0 Km) on Khurda road Division of East Coast Railway in Orissa State, India”.
Rs 9128 Lakh
Rs 9693 Lakh
(+) 6.19%
RVNL/BBS/Tenders/HDS-JKPR/(Road Bed)/14/52/MCML-ECI JV/2008/05, dated 16/12/2008.
M/s McML Systems Pvt Ltd. – ECI Engineering & Construction Co. Ltd. # C9, Industrial Estate, Yelahanka, Bangalore – 560 064,
08/12/2008
18 months from the date of commencement.
16% CPM-II /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 10 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
7. PMC(Keonjhar-Tomka & 2nd Railway Bridge over river Mahanadi(Br. No.544)
Project Management Consultancy for Sub projects) Keonjhar-Tomka New BG line (96.355km) of Banspani-Daitari New Railway Line. ii) Construction of 2nd bridge across river Mahanadi (32 x 65.4m) near Cuttack of East Coast Main Line.
Rs. 832 Lakh
RVNL/ Projects/ K-T & M-B/ PMC/ Package 1 Dtd. 08/08/2005.
M/s. SOWiL-Halcrow JV Plot No-8, Near Satyakali Mandir, Satyanagar, Bhubaneswar-751007
20.04.2005 48 Months
99 %
CPM –II /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
8. Const. of Br N0.134 over Mahanadi and 115 over Luna -(HDS-PRDP)
Construction of Br. No.134 over Mahanadi 22 x 43.846m and Br. No.115 over Luna 13 x 43.846m in connection with construction of new BG line between Haridaspur &
Rs. 6967 Lakh
Rs 6751 Lakh
(-) 3.20%
RVNL/BBSHDS-PRDP/ MAHA-LUNA/SIMPLEX/14/13/2006/02 Dt 30/01/2006
M/s Simplex Infrastructures Ltd., 502A, Poonam Chambers, 'A' Wing, 5th Floor, Dr. A.B.Road, Worli,
09.12.2005 30 Months
60% CPM –I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 11 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
Paradeep of East Coast
Mumbai - 400 018.
9. Project Management Consultancy Const. of Br N0.134 over Mahanadi and 115 over Luna -(HDS-PRDP) Project management
consultancy services for construction of Br.No.134 over Mahanadi 22 x 43.846M & Br. No. 115 over LUNA 13 x 43.846 M in connection with construction of new BG line between Haridaspur & Paradeep of East Coast Railway.
Rs. 170 Lakh
Rs. 138 Lakh
(-) 18.68%
RVNL/BBS/Contracts/HDS-PRDP/MAHA-LUNA/PMC/14/21/2006
M/s. SM Consultants, Plot No 3489/6705, Near Kalinga House , Po- Rasulgarh Bhubaneswar
10.05.2006 30 Months 62% CPM – I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
10. Construction of Roadbed and Major Bridges in HDS-PRDP new BG Line.
Construction of Roadbed including Major & Minor Bridges, Facilities and General
(+) 23.90%
RVNL/BBS/HDS-PRDP/ ROADBED/14/45/2007 DT.24.08.20
HCIL-ADHIKARYA (JV)113-A, Kamla Nagar, New Delhi-
19.06.2007 24 Months 14% CPM – I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur,
Page 12 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
Electrification in connection with construction of New BG line between Haridaspur & Paradeep in East Coast Railway in the State of Orissa, India
1. Civil Engineering Works
2. General
Electrification work
Total Cost
Rs 22009 Lakh Rs. 295 lakh Rs. 22304 Lakh
Rs 27346 Lakh Rs 289 Lakh Rs. 27635 Lakh
07 110007 Bhubaneswar (Orissa) 751 023.
11. PMC for Roadbed HDS-PRDP
Project Management Consultancy for “Construction of Roadbed including Major and Minor Bridges, Facilities, General Electrification and Ballast Supply in connection with Construction of New BG Line between
Rs. 370 Lakh
Rs. 267 Lakh
(-) 38.27%
RVNL/BBS/PMC/HDS-PRDP/Rd&MBr/14/49/2007 dt. 31.12.2007.
M/s SMC-SMSS (JV), Plot No. 3489/6705, Near Kalinga House, Palasuni., P.O - Rasulgarh, Bhubaneswar
01.12.2007 30 Months
15% CPM – I /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 13 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
Haridaspur & Paradeep (82 Km) in East Coast Railway, in the State of Orissa, India.”
- 751010
12. RE S &T works of Jaroli – Tomka Section.
“Supply execution of Signaling and Telecommunication works in connection with Railway Electrification of Jaroli – Tomka Section in Jakhapura – Daitari – Bansapani Branch Line under Khurda Road Division of East Coast Railway in the State of Orissa”.
Rs 264 Lakh
Rs 327 Lakh
(+) 24% LAO No. RVNL/BBS/Tender/RE/S &T Works/Jaroli – Tomka/25/42/7622, dated 17.03.2009.
M/s Benzfab Tecnologies Pvt Ltd & National Engineering JV, A-19, Ground Floor, Sahid Nagar, Bhubaneswar – 751 007.
20.03.09 18 months + 6 months defect liability period.
22% General Manager (Elect) /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
Page 14 of 14
Sl No
Name of work and Location Est.Cost Tendered
Cost % above & below
SOR Agmt. No Agency Date of
Start Time of Comp
Physical
Progress
Name of E in C with address R
ema-
rks
13. DKB RE related works
Construction of type –I, II, III & IV quarters, tower wagon shed, PSI depot, AEE office, height gauge, arrangement for OHE mast on bridges and other ancillary works in connection with Jaroli – Tomka section ( 146.0 Km) on Khurda road division of East Coast Railway in Orissa State, India”.
Rs 112 Lakh
LOA No. RVNL/BBS/Tenders/JAROLI-TOMKA-OHE Related Civil Engineering Works/14/54/7226, dated 13/01/2008
M/s Chita Ranjan Swain, 128, Dharam Vihar, Jagamara, Khandagiri, Bhubaneswar
13.02.09 18 months 16% CPM – II /RVNL/BBS ‘B’ Block (West Wing), Ground Floor & 1st Floor, Rail Vihar, Chandrasekharpur, Bhubaneswar (Orissa) 751 023.
It is certified that “ All the works / Purchase/Consultancy contracts and other contracts in progress, as per the prescribed monetary limit have been reported in this QPR’s”
Details of contracts placed by PIU, Bangalore during the month 31st August 2009
Tender Number Date of Opening
Descrip- tion of Item/ Work
Contract No. & Date
Contractor’s Name
Quantity (for supply contract) Estimated Cost (for Engg./ Elect. S & T Mech.)
Rate (for supply contract) Tendered Cost (for Engg./ Elect./S &T Mech.)
Value of Contract
Scheduled Completion date
Rupees Rupees Rupees 2007RVNL/ Mumbai/HPT – TNGT Dated: 5.3.2000
16.5.2008
FLS/HPT-TNGT (245km) on SWR
RVNL/Mumbai/ FLS/HPT-TNGT/2008 Dated:2.7.2008
M/s.Hydroneum Systems, “Raghuvansh”, C.T.S.No.755/80, Plot No.78, 2nd floor, Mayur Colony, Kothrud, Pune – 411 038 M.S. (INDIA)
1,32,91,500
1,32,91,500
1,19,62,350
1.10.2010
Details of contracts placed by PIU, Bangalore during the month 30th
September 2009
NIL NIL NIL NIL NIL NIL NIL NIL NIL CPM/RVNL/Bangalore
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India) - Package No. 1
between Bina (Incl) to Ganj Basoda (Incl) chainage
975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India) - Package No. 2
between GanjBasoda (Excl) to Sanchi (Incl) chainage
928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India) - Package No. 3
between Sanchi (Excl) to Habibganj (Incl) chainage
879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. -
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot No.
31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.04.2010
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.04.2010
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bin
a- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 30.11.2009
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
Details of Contracts Placed upto the month March' 2010 under GM/P-III
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-
500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60 kg
1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 12.05.2010
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot No.
11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand, 3rd
& 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation: Rs
20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch 60
Kg.
Rs 3.92 Cr 16.05.2010
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 17.05.2010
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 17.05.2010
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
Tender Number Date of Opening Description of Item/WorkContract No. &
date of awardContractors Name
Quantity (for
supply contract)
Estimated cost (for
Engg./Elect. /S&T/
Mech.
Rate ( for supply
contract)
Tendered cost (for
Engg./Elect./
S&T/Mech
Value of
contract
Scheduled
completion date
NIL NIL NIL NIL NIL NIL NIL NIL NIL
Details of Contracts Awarded during February 2010 by PIU Mumbai
Page 1 of 4
Sl. No Tender Number Date of
opening
Description of item/work Contract No. & date Contractor’s Name Estima-ted cost Tendered cost Value of Contract Scheduled completion
date
(A)
1 No.RVNL/SC/GY-
PMT/104 dated 18-10-
05
31.01.06 Gooty-Pullampet patch
doubling
No.RVNL/SC/GY-
PMT/Agt/104 dated 22-08-
2006
M/s. Simplex Infrastructures
Ltd., Mumbai
19223.74 lakhs 19223.74 lakhs 17074.07 lakhs 30 + (6 Defect. Liability
period) (06-04-2009)
2 No.RVNL/SC/GY-
PMT/PMC/106 dated
02-12-05
27.03.06 Project Management
Consultancy for Gooty-
Pullampet patch doubling
No.RVNL/SC/GY-
PMT/PMC/Agmt/106 dated
24.11.06
M/s. Aarvee Associates,
Hyderabad
600 lakhs 600 lakhs 575.32 lakhs 30 + (6 Defect. Liability
period (28-03-2009)
3 No.RVNL/SC/OBVP-
KP/108 dated 01-09-
2006
13.11.06 Venkatachalam to
Krishnapatnam Phase I New
BG Line
No.RVNL/SC/OBVP-KP/108
dated 27-06-2007
M/s.APR-VNR Joint Venture
,Hyderabad
4060.6 lakhs 4060.6 lakhs 4246.1 lakhs 12 + (6 months defect
liability period) (28-03-
2008)
4 No.RVNL/SC/OBVP-
KP/PMC/114 dated 25-
05-06
09.07.07 Project Management
Consultancy for Venkata-
chalam to Krishnapa-tnam
Phase I works
No.RVNL/SC/OBVP-
KP/PMC/114 dated 5.11.07
M/s. Project Engineering
Management Services-KITCO
(JV), Tiruvananthapuram,
Kerala
69.88 lakhs 69.88 lakhs 84.66 lakhs 12 + (6 months defect
liability period (09-09-
08)
5 No.RVNL/SC/GTL-
RC/112 dated 06-02-
2007.
12.04.07 Guntakal-Raichur patch
doubling .
No.RVNL/SC/GTL-RC/112
dated 15.10.07
M/s. APR-MVR Joint Venture,
Hyderabad
9670.5 lakhs 9670.5 lakhs 9399.34 lakhs 18+6 (6 months defect
liability period) dated 23-
02-09
6 No.RVNL/SC/GTL-RC/
113 dated 21.05.2007
10.07.07 Project Management
Consultancy for Guntakal-
Raichur patch doubling .
No.RVNL/SC/GTL-RC/ PMC
/113/Contract dated
11.12.2007
M/s. SOWiL Limited, Navi
Mumbai – 400706
200.40 lakhs 200.40 lakhs 121.00 Lakhs 18+6 (6 months defect
liability period) dated 23-
02-09.
7 No:RVNL/SC/NRE-
GTL/RE/Civil/128
dt:13.04.09
21.05.09 Construction of Quarters and
Service Bldgs etc in connection
with Civil & Elecl works of RE
bet. Nandalur - Kondapauram
RVNL/SC/NRE-
GTL/RE/Civil/128 dt:13.04.09
M/s. Inter Continental (I) Ltd,
Hyderabad.
8.21 Crs 8.21 Crs 9.51 Crs 12 + 3 months
8 No:RVNL/SC/NRE-
GTL/RE/Civil/129
dt:13.04.09
21.05.09 Construction of Quarters and
Service Bldgs etc in connection
with Civil & Elecl works of RE
bet. Kondapuram - Guntakal.
RVNL/SC/NRE-
GTL/RE/Civil/129 dt:13.04.09
M/s. Inter Continental (I) Ltd,
Hyderabad.
9.95 Crs 9.95 Crs 12.09 Crs 12 + 3 months
9 No:RVNL/SC/NRE-
GTL/RE/Civil/130
dt:13.04.09
21.05.09 Construction of Tower wagon
shed, Loco trip shed etc in
connection with RE works bet.
Nandalur - Guntakal.
No:RVNL/SC/NRE-
GTL/RE/Civil/130 dt:13.04.09
M/s. Vishnu Constructions &
Company, Hyderabad.
3.88 Crs 3.38 Crs 4.94 Crs 12 + 3 months
DETAILS OF CONTRACTS AWARDED BY PIU/RVNL/SC UPTO 31.03.2010.
CIVIL
Page 2 of 4
Sl. No Tender Number Date of
opening
Description of item/work Contract No. & date Contractor’s Name Estima-ted cost Tendered cost Value of Contract Scheduled completion
date
DETAILS OF CONTRACTS AWARDED BY PIU/RVNL/SC UPTO 31.03.2010.
10 RVNL/SC/OBVP-
KP/Track
Maintenance/135
12.05.09 Obulavaripalli - Krishnapatnam
New BG line - Proposed
maintennce of newly
commissioned BG track
betgween Venkatachalam -
Krishnapatnam stations
including points, X-ings,
looplines etc, on Vijayawada
Divion of South Central
Railway
RVNL/SC/OBVP-KP/Track
Maintenance/135 dt:22.10.09
Sri D.Srinivas, Secunderabad 28.34 lakhs 28.34 lakhs 24.95 lakhs 21.10. 2010.
11 RVNL/SC/GY-
PMT/Bridge works/139
22.12.2010 Construction of Bridge No:601,
743 & 744
RVNL/SC/GY-PMT/Bridge
works/139 dt:23.11.2009
M/s.MEC-CC (JV)/Hyderabad 9.92 Crs 9.92 Crs 11.45 Crs 6 Months + 180 days
DLP
12 RVNL/SC/GY-
PMT/Fabrication
works/140
22.12.2010 Construction of FOBs and
COPs between GY-PMT
RVNL/SC/GY-
PMT/Fabrication works/140
dt:23.11.2009
M/s. Vishnu Constructions &
Company, Hyderabad.
7.75 Crs 7.75 Crs 8.91 Crs 6 Months + 180 days
DLP
(B)
13 No.2006/ELECT/PMT-
NRE/001 dated 13.3.06
23-5-06 Supply, Erection, Testing and
commissioning of 25 Kv OHE
bet. Pullampet-Nandalur Sec.
of Guntakal Divn. of S.C. Rly
No.2006/Elec./PMT-
NRE/001 dt. 15.11.06
M/s. Tata Projects Limited,
Hyderabad. (TPL)
599.83 lakhs 599.83 lakhs 840.47 lakhs 12 months (02-10-
2007). Extended up to
30-09-2009.
14 RVNL/SC/OBVP-
KP/OHE/120
31.08.07 Design, Supply, Erection,
Testing & Commissioning of 25
KV, 50HZ, Single Phase,
Traction Over-head
Equipment, etc Ph. I work
between Venkatachalam Road
Jn. to Krishnapatnam in
connection with laying of new
BG line between
Obulavaripalle -
Krishnapatnam section of
South Central Railway.
RVNL/SC/OBVP-
KP/OHE/120 dt:12-03-2008
M/s. Cobra Instalaciones y.
Servicios, S.A., NDLS
NA NA Rs.15.11 Crs. 11.03.2009. Extended
up to 15-10-2009
ELECTRICAL
Page 3 of 4
Sl. No Tender Number Date of
opening
Description of item/work Contract No. & date Contractor’s Name Estima-ted cost Tendered cost Value of Contract Scheduled completion
date
DETAILS OF CONTRACTS AWARDED BY PIU/RVNL/SC UPTO 31.03.2010.
15 RVNL/SC/NRE-
KDP/RE/121
27.01.08 Design, Supply, Erection,
Testing & Commissioning of 25
KV, 50HZ, Single Phase,
Traction Over-head Equipment
etc., between Nandalur (Excl)
and Kondapuram (Incl)
stations and S&T works of
Guntakal Division of South
Central Rly.
RVNL/SC/NRE-
KDP/RE/121/Agt.
Dated 21-07-08
M/s.Larsen & Toubro Limited,
Chennai
NA NA Rs.103.47 Crs 20-01-2010
16 RVNL/SC/GTL-
WADI/DDE/122
27.03.08 Detailed Design Engineering
(Electrical, Civil) for Railway
Electrification of –
Guntakal(excl)-Raichur-
Wadi(excl) and Wadi(excl) –
Gulbarga(incl) (265RKM)
(including patch doubling line
section) in Guntakal Division
on S.C. Rly and Solapur Divn
of Central Railway
RVNL/SC/GTL-WADI-
GR/DDE/Agt/122 Dt:18-07-
2008.
M/s. Balaji Rail Road Systems
Limited, Secunderabad.
NA NA Rs.58.41 lakhs 17.01.2009. Extended
up to 31.03.2010.
17 RVNL/SC/KDP-
GTL/RE/127
04.06.08 Design, Supply, Erection,
Testing & Commissioning of 25
KV, 50HZ, Single Phase,
Traction Over-head Equipment
etc.,for RE between
Kondapuram(Excl) – Guntakal
(Incl) Section of GTL Divn of
SC Rly.
RVNL/SC/KDP-GTL//RE/127
dt:17-11-2008
M/s.TATA Projects Limited,
Hyderabad
NA NA Rs.101.18 Crs 16.05.2010.
18 RVNL/SC/NRE-
GTL/TSS/119
08.07.08 Design, Supply, Erection,
Testing & Commissioning of
132/25 KV and 220/25 KV,
TSS at Kadapa, Muddanur,
Tadipatri and Gooty Nandalur -
Guntakal Section of Guntakal
Division of SC RLY.
RVNL/SC/NRE-
GTL/TSS/119, dt:04.12.2008
M/s. G.E.T. Power Pvt Limited,
Chennai
NA NA Rs.28.20 Crs 03.06.2010
Page 4 of 4
Sl. No Tender Number Date of
opening
Description of item/work Contract No. & date Contractor’s Name Estima-ted cost Tendered cost Value of Contract Scheduled completion
date
DETAILS OF CONTRACTS AWARDED BY PIU/RVNL/SC UPTO 31.03.2010.
19 RVNL/SC/VKT-
KP/SCADA/131
25.05.09 Design, Supply, Erection,
Testing & Commissioning of
Supervisory Remote Control &
Data Acquisition (SCADA)
equipment on section between
Venkatachalam RD JN and
Krishnapatnam on Vijayawada
Divn of SC Rly.
RVNL/SC/VKT-
KP/SCADA/131 dt.11.9.09
M/s Nelco, Navi Mumbai 11.05 lakhs 11.05 lakhs Rs.13.26 lakhs 3 months
20 RVNL/SC/NRE-
GTL/PMC/124
dt:17.12.09
14.05.09 Project Management
consultancy for erection,
Testing & Commissioning of
25 KV AC single phase 50 Hz
Traction OHE, Switching stns,
TSSs, SCADA, S&T works and
other associated civil works in
NRE (Excl) – GTL (Incl)
section of GTL Divn of SC
Railway
LOA No: RVNL/SC/NRE-
GTL/PMC/124 dt:17.12.09
M/s. United Rail Road
Consultants Ltd, Hyderabad
250.74 lakhs 250.74 lakhs 274.65 lakhs 36 months
( c)
21 No.C/ADB/Gooty-
Pullampet/ Signalling
(Vol.III) dated 10-11-04
20.04.05 S & T Works in Guntakal-
Raichur patch doublinhg
No.C/ADB/Gooty-Pullampet/
Signalling (Vol.III) dated 08-
11-06
M/s. Leighton Emrail-Kalindee
(JV)
10589 lakhs 10589 lakhs 9681.31 lakhs 36 months (29.6.09)
22 RVNL/S&T/Venk-
Krish/Bid dt:31.10.07
04.12.07 S&T works in five stations in
connection with new BG line
between Venkatachalm -
Krishnapatnam
RVNL/S&T/Venk-Krish/Bid
dt:15.07.08
M/s . VNR Infrastructures Ltd,
Hyderabad.
8.70 8.70 10.82 12 months.
23 RVNL/S&T/GTL -
RC/Bid dt:20.06.08
31.07.08 S&T works of Guntakal -
Raichur Patch doubling
No:RVNL/SC/GTL-RC/VNR-
1/09 dt:31.03.09
M/s. VNR Infrastructures
Limited, Hyderabad
14.18 14.18 15.29 12 months.
24 No.RVNL/
SC/NRE-KDP/RE/121
S&T works at 12 stations and
misc works in connection with
doubling of Raichur – Guntakal
section.
No.RVNL/
SC/NRE-KDP/RE/Agt/121 dt.
12.8.08
M/s. L&T Limited, ECC Divn.
Chennai
1587.3 1587.3 2090.47 18 months
Signal & Telecom
Sl. No. Tender No. Date of Opening
description of Item/Work Contract No. & Date
Contractor's Name Quantity (for supply contract) Estimate Cost (for Engg./Elect./S&T/Mech.)
Rate (for supply contract) Tender Cost (For Engg./Elect./S&T/Mech.)
Scheduled Completion Date
1
RVNL/KOL/PKU-KGP/PSI/OT/09/01/ Dt. 04.06.2009
23.07.2009 Design, Supply, Erection, Testing & Commissioning Of 132/27 Kv, 2 X 30/42 MVA, Traction-Sub-Station , with an additional bay and replacement of one existing 13/20MVA capacity, modification of 132KV incomming and out going 25KV Power Supply, TSS feeding post, with other associated works at Balichak Sub-Station, along with modification of opposite gantry in connection with 3rd line between Panskura-Kharagpur under Kharagpur Division Of South Eastern Railway in the State of West Bengal.
Contract Agreement No. RVNL/KOL/EL/PSI/OT/09/01/Vol-II dated 16/04/2010
M/s.PSC Engineers Pvt. Ltd. IT Building(3rd floor),Benfish,31,G.N.Block, Sector -V, Salt Lake City, Kolkata 700091.
Rs. 7,94,23,187/- Rs. 7,49,54,437/- 08-11-11
Details Contracts Placed upto the month March' 2010 under GM/P-III
Krs.d.vig. stat.
Details of Contracts/award of tenders by PIU/Chennai for the period from 01.01.2010 to
31.03.2010.
Sn
Ten
der
no.
Dat
e o
f o
pen
ing
Des
cri
pti
on o
f
item
/Wo
rk
Co
ntr
act
/LO
A n
o.
& d
ate
.
Co
ntr
acto
r’s
nam
e
Qty
. [f
or
sup
ply
co
ntr
act]
Est
imat
ed
Co
st [
for
En
gg
./E
lect
/S &
T
/Mec
h]
Rat
e [f
or
sup
ply
co
ntr
act]
Ten
der
ed
Co
st [
for
En
gg.
/
Ele
ct/S
& T
/Mec
h]
in R
s.
Val
ue
of
Co
ntr
act
in R
s.
Sch
edu
led
com
ple
tio
n d
ate.
NIL
CPM/Chennai
List of Contracts awarded by CPM/Jaipur for SMR-BLDI GC Project upto May 2010
S. No. Description of work Contract No. & date Contractor’s Name
Value of Contract
Completion date
1.
Misc. civil works including construction/modification of station buildings, S & T structures, platforms, level crossings Duty Huts, resting facilities for TMC staff and other connected works Marwar Bagra (Ex) to Rainwara (Including) on SMR-BLDI section.
RVNL/JP/T&Q/Misc/2007/013
M/s Kaluram Contractors (JV)
4.38 Crs
12 Months
2 Construction of 43 Staff Quarters at RAKHI, BALWARA, LADERMER, BAKRA ROAD, JAGAN NATH JI etc. Stations of Samdari-Bhildi Section of North Western Railway
RVNL/JP/T & Q / Quarters / 2008/01 dt 20.3.09
Kera Ram s/o Pusha Ram
2.62 Crs. 15 Months 1.7.10
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 1 between Bina (Incl) to Ganj Basoda (Incl)
chainage 975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 2 between GanjBasoda (Excl) to Sanchi
(Incl) chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 3 between Sanchi (Excl) to Habibganj (Incl)
chainage 879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. -
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot
No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.04.2010
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.06.2010.
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bin
a- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
Details of Contracts Placed upto the month May' 2010 under GM/P-III
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-
500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60
kg 1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.09.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot No.
11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand,
3rd & 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation:
Rs 20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch
60 Kg.
Rs 3.92 Cr 16.08.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 31.07.2010
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 16.08.2010
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road
projects in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
Details of Contracts Awarded from Dec.'06 to April, 2010 from the Corporate Office (S&T)
S.No Tender No./
Purchase Order
No.
Date of
Opening
Descripton of Item/Work Contract No. &
Date
Contractor's Name Quantity (for
supply contract)
Estimated Cost (for
Engg. Elect.
S&T/Mech.)
Rate (for supply
contract)
Tendered Cost
(for
Engg/Elect/S&T/
Mech.)
Value of
Contract
Scheduled Completion
Date
(2)
RVNL/S&T/RRPA/
Solar/REL/2008
Dtd.25.06.08 for
Qty.378 Panels.
(2) M/s Rajasthan Electronics &
Instruments Ltd. Jaipur
Rs.50 lacs
(Approx.)
(3)
RVNL/S&T/RRPA/
Solar/CEL/2008
Dtd.09.07.08 for
Qty.210 Panels
(3) M/s Central Electronics Ltd. Sahibabad
(UP)
Rs.33 lacs
(Approx)
2
TENDER
NO.RVNL/S&T/D
G/2008 Dated
25.03.2008
28.04.2008
Supply & Installation of DG sets of 15
KVA in connection with MG to BG
conversion on Rewari -Ringus-Ajmer
Section of NWR
P.O. no.
RVNL/S&T/DG/SE
E/2008 dt.
30.07.2008
M/s Shekhawati Electrical Engg. Jaipur 128 lacs 128 lacs Rs.108 lacs One (1) month from the
issue of P. Order
3
RVNL/S&T/SMR-
BLDI/BID dated
02.11.2007
20.12.2007
"Supply, Installation, Testing &
Commissioning of Signallling
Equipment with Route Setting Panle
Interlocking at 21 Stations in
Connection with MG to BG Gauge
Conversion on Samdari - Bhildi (223.44
KM) of North Western Railway"
C.A.
No.RVNL/S&T/SM
R-BLDI/ dtd.
17.07.08
JV of M/s Kiran Infra Engineers Ltd. & M/s
ELIOP, Spain
1881 lacs (approx.) 1881 lacs
(approx.)
2162 lacs
(Approx.)
12 months from the date
of issue of LOA
4
RVNL/S&T/VENK-
KRISH/BID dated
31.10.2007
04.12.2007
"Supply, Installation, Testing &
Commissioning of Signalling & Telecom
Equipment in connection with Route
Setting Panel Interlocking at 5 Stations
in connection with new BG Line in
Venkatachalam to Krishnapatnam of
South Central Railway".
C.A. No.
RVNL/S&T/VENK -
KRISH/BID dated
15.07.08
M/s VNR Infrastructures Ltd. #8-2-310/17,
Road NO. 14 Banjara Hills Hyderabad -34
870 lacs (Approx) 870 lacs
(Approx)
1082 lacs
(Approx)
12 months from the date
of issue of LOA
RVNL/
S&T/Solar/2008
dt.18.02.2008
24.03.2008
(1) M/s Tata BP Solar India Ltd. NDLS -1.
Three (3) P.Orders
placed :-
(1)
P.O. NO. RVNL/
S&T/RRPA/Solar/T
BP Dtd.25.06.08
for Qty.1764
panels.
1
Supply of Solar Panel based charging
system in connection with MG to BG
conversion on Rewari -Ringus -Phulera
-Ajmer Section of NWR
Rs.393 lacs
Rs.244 lacs
(approx)
Rs.393 lacs
Two (2 ) months from the
date of issue of P.
Orders
1 of 3
S.No Tender No./
Purchase Order
No.
Date of
Opening
Descripton of Item/Work Contract No. &
Date
Contractor's Name Quantity (for
supply contract)
Estimated Cost (for
Engg. Elect.
S&T/Mech.)
Rate (for supply
contract)
Tendered Cost
(for
Engg/Elect/S&T/
Mech.)
Value of
Contract
Scheduled Completion
Date
5
RVNL/S&T/GTL-
RC/BID dated
20.06.2008
31.07.2008
“Design, Supply, Installation, Testing &
Commissioning of Signalling &
Telecommunication Equipment with
Panel Interlocking (Route Setting type)
at 12 (TWELVE) stations and alteration
in Raichur Station in connection with
Doubling work in Raichur-Guntukal
Section of South Central Railway
C.A. No.
RVNL/S&T/GTL-
RC/BID dated
14.05.09
M/s VNR Infrastructures Ltd. #8-2-310/17,
Road NO. 14 Banjara Hills Hyderabad -34
1418 lacs (Approx) 1418 lacs (Approx) 1529.5 lacs
(Approx)
12 months from the date
of issue of LOA
6
Two (2) Purcahse
Orders placed:- (1)
No. RVNL/S&T/
Cables/Sriram/09-
10 dt.20.08.09
M/s Sriram Cables Pvt. Ltd. Flat No. 102,
A -8A, Rama Road, Adarsh Nagar, Delhi -
33
581 lacs
(Approx.)
7
(2)
No. RVNL/S&T/
Cables/Elkay/09-
10 dt.21.08.09
M/s Elkay Telelinks Ltd. Opposite Ranhera
Khera, Ballabgarh, Opposite Plot No. 84,
Sector -25, Faridabad - 05, Haryana
295.5 lacs
(Approx.)
8
RVNL/S&T/SolarP
anel/SMR-
BLDI/2009 dt,
29.06.2009
28.07.09
Supply of Solar Panel Based Charging
System in connection with MG to BG
conversion on Samdhari – Bhildi
Section of NWR.
RVNL/S&T/SolarP
anel/SMR-
BLDI/TATA/09-10
Dtd.10.12.09
M/s Tata BP Solar India Ltd. # 78, Phase -
1, Electronic City, Hosur Road, Bangalore,
- 560 100
251.6 lacs (Approx.)251.6 lacs
(Approx.)
224.3 lacs
(Approx.)
Two (2 ) months from the
date of issue of P.
Orders
9
RVNL/S&T/OFC/
GHH-FRK/BID
Dated
26/08/09
30.09.09
“Supply, Installation, Testing and
Commissioning of Telecommunication
Equipment in connection with GC work
in Garhi Harsaru - Farukhnagar section
(length 11.27 Km) of Northern Railway”
C.A. No.
RVNL/S&T/OFC/G
HH-FRK/Karan/09-
10 Dtd.05.02.10
M/s Karan Singh & Sons, #84/22, Anand
Vihar, Baghambari Road, Bharadajpuram,
Allahabad 211-006 (UP)
45.9 lacs (Approx.) 45.9 lacs (Approx.)49.6 lacs
(Approx)
45 days from the date of
issue of LOA
10
RVNL/S&T/SMR-
BLDI/OFC/BID
Dated
25/08/09
30.09.09
“Supply, Installation, Testing and
Commissioning of MUX Equipment and
Supply and Laying of Optical Fiber
Cable at Samdhari –Bhildi Section (224
KM) of North Western Railway”
C.A. No:
RVNL/S&T/OFC/S
MR-
BLDI/M.V.Omni/09-
10 Dtd.10.05.10
M/s M.V. Omni Projects (India) Ltd. #74,
New York Tower -A, S.G. Highway, Thaltej
Cross Road, Ahmedabad - 380054
313.98 lacs
(Approx.)
313.98 lacs
(Approx.)
359.20 lacs
(Approx.)
6 Months from the date
of issue of LOA
Procurement of various type/size
Signalling/ Power/ Quad Cables for
Raichur - Guntakul
704.4 lacs (Approx) 704.4 lacs (Approx)
Two (2 ) months from the
date of issue of P.
Orders
RVNL/S&T/Cable
s/Bid dated
08.04.09
11.05.2009
2 of 3
S.No Tender No./
Purchase Order
No.
Date of
Opening
Descripton of Item/Work Contract No. &
Date
Contractor's Name Quantity (for
supply contract)
Estimated Cost (for
Engg. Elect.
S&T/Mech.)
Rate (for supply
contract)
Tendered Cost
(for
Engg/Elect/S&T/
Mech.)
Value of
Contract
Scheduled Completion
Date
11
RVNL/S&T/19LC
G/2008 dated
05.08.08
12.08.08
Supply of Electrically Operated Lifting
barrier assembly complete in
connection with MG to BG conversion
on Rewari - Ringus- Phulera Section of
North Western Railway.
Work awarded vide
P.O. No.
RVNL/S&T/19/LCG
/2008 dated
25.08.2008
M/s Global Devices, #C-8/5, Ardee City,
Gurgoan, Haryana - 122 00319 sets -
54.67 lacs
(Approx.)
completed within 30
days of placement of
order
12
2005/RVNL/P/CC/
P.way(PW) dt.
12.01.2006
28.02.06
Construction of P.way works including
supply of ballast and P.way materials
(excluding rails, line, sleepers),
signalling and overhead power supply
works for Palwal - Bhuteshwar 3rd Line
(81 kms) on North Central Railway
2005/RVNL/P/CC/
P.way(PW) dt.
05.11.2007
M/s Kalindee - Cobra JV
(M/s Kalindee Rail Nirman (Engineers)
Ltd. & Cobra Instalaciones 4 Servicios
S.A.)
8859.28 lacs approx.8859.28 lacs
approx.
11870.70 lacs
(Approx.)
Extended upto
31.12.2010
13
2007/RVNL/S&T/
F.
Equipment/PWL-
BTSR/NCR/BID
dt. 03.10.2007
15.11.2007
Laying of HDP Pipe 120/200 mm dia
under Railway Track for laying
signalling/Telecom Cable in connection
with 3rd line work on Palwal -
Bhuteshwar Section on North Central
Railway.
No.
2007/RVNL/S&T/F.
Equip/PWL-
BTSR/NCR/Bid
dated 09.02.2008
M/s Creative Enterpreneurs, A-3/332,
Sector -8, Rohini, Delhi - 110085
140.71 lacs
(Approx)
140.71 lacs
(Approx)
76.03 lacs
(Approx.)
Completed within 3
months from the date of
issue of LOA.
14
No.2007/RVNL/S
&T/PMC(PB) dt.
01.11.2007
10.12.2007
Project Management Consultancy of
Signalling and Interlocking Works in
Construction of Palwal - Bhuteshwar
3rd Line Doubling (81 km) in the state
of Haryana and Uttar Pradesh (India)
on North Central Railway
No.
2007/RVNL/S&T/P
MC(PB) dated
23.06.2008
M/s Sai Consulting Engineers Pvt. Ltd. 4,
Kuldip Soceity, Near Ishwar Bhuban,
Navarangpura, Ahmedabad - 380009
90.42 lacs
(Approx).
18 months excluding
defect liability period
3 of 3
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 1 between Bina (Incl) to Ganj Basoda (Incl)
chainage 975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 2 between GanjBasoda (Excl) to Sanchi
(Incl) chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 3 between Sanchi (Excl) to Habibganj (Incl)
chainage 879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. -
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot
No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.09.2010*
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.06.2010.
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bin
a- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
Details of Contracts Placed upto the month June' 2010 under GM/P-III
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
8* RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-
500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60
kg 1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.09.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot No.
11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand,
3rd & 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation:
Rs 20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch
60 Kg.
Rs 3.92 Cr 16.08.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 31.07.2010
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 16.08.2010
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road
projects in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
Note: * Delivery Period Extended upto 30.09.2010.
Sl. No Tender Number Date of
opening
Description of item/work Contract No. & date Contractor’s Name Estima-ted cost Tendered cost Value of
Contract
Scheduled
completion date
(A)
1 No.RVNL/SC/GY-
PMT/104 dated 18-10-
05
31.01.06 Gooty-Pullampet patch
doubling
No.RVNL/SC/GY-
PMT/Agt/104 dated 22-08-
2006
M/s. Simplex Infrastructures
Ltd., Mumbai
19223.74 lakhs 19223.74 lakhs 17074.07 lakhs 30 + (6 Defect. Liability
period) (06-04-2009)
2 No.RVNL/SC/GY-
PMT/PMC/106 dated
02-12-05
27.03.06 Project Management
Consultancy for Gooty-
Pullampet patch doubling
No.RVNL/SC/GY-
PMT/PMC/Agmt/106 dated
24.11.06
M/s. Aarvee Associates,
Hyderabad.
600 lakhs 600 lakhs 575.32 lakhs 30 + (6 Defect. Liability
period (28-03-2009)
3 No.RVNL/SC/OBVP-
KP/108 dated 01-09-
2006
13.11.06 Venkatachalam to
Krishnapatnam Phase I New
BG Line
No.RVNL/SC/OBVP-KP/108
dated 27-06-2007
M/s.APR-VNR Joint Venture
,Hyderabad
4060.6 lakhs 4060.6 lakhs 4246.1 lakhs 12 + (6 months defect
liability period) (28-03-
2008)4 No.RVNL/SC/OBVP-
KP/PMC/114 dated 25-
05-06
09.07.07 Project Management
Consultancy for Venkata-
chalam to Krishnapa-tnam
Phase I works
No.RVNL/SC/OBVP-
KP/PMC/114 dated 5.11.07
M/s. Project Engineering
Management Services-KITCO
(JV), Tiruvananthapuram,
Kerala
69.88 lakhs 69.88 lakhs 84.66 lakhs 12 + (6 months defect
liability period (09-09-
08)
5 No.RVNL/SC/GTL-
RC/112 dated 06-02-
2007.
12.04.07 Guntakal-Raichur patch
doubling .
No.RVNL/SC/GTL-RC/112
dated 15.10.07
M/s. APR-MVR Joint Venture,
Hyderabad
9670.5 lakhs 9670.5 lakhs 9399.34 lakhs 18+6 (6 months defect
liability period) dated 23-
02-096 No.RVNL/SC/GTL-RC/
113 dated 21.05.2007
10.07.07 Project Management
Consultancy for Guntakal-
Raichur patch doubling .
No.RVNL/SC/GTL-RC/ PMC
/113/Contract dated
11.12.2007
M/s. SOWiL Limited, Navi
Mumbai – 400706
200.40 lakhs 200.40 lakhs 121.00 Lakhs 18+6 (6 months defect
liability period) dated 23-
02-09.7 No:RVNL/SC/NRE-
GTL/RE/Civil/128
dt:13.04.09
21.05.09 Construction of Quarters and
Service Bldgs etc in
connection with Civil & Elecl
works of RE bet. Nandalur -
Kondapauram
RVNL/SC/NRE-
GTL/RE/Civil/128
dt:13.04.09
M/s. Inter Continental (I) Ltd,
Hyderabad.
8.21 Crs 8.21 Crs 9.51 Crs 12 + 3 months
8 No:RVNL/SC/NRE-
GTL/RE/Civil/129
dt:13.04.09
21.05.09 Construction of Quarters and
Service Bldgs etc in
connection with Civil & Elecl
works of RE bet. Kondapuram -
Guntakal.
RVNL/SC/NRE-
GTL/RE/Civil/129
dt:13.04.09
M/s. Inter Continental (I) Ltd,
Hyderabad.
9.95 Crs 9.95 Crs 12.09 Crs 12 + 3 months
9 No:RVNL/SC/NRE-
GTL/RE/Civil/130
dt:13.04.09
21.05.09 Construction of Tower wagon
shed, Loco trip shed etc in
connection with RE works bet.
Nandalur - Guntakal.
No:RVNL/SC/NRE-
GTL/RE/Civil/130
dt:13.04.09
M/s. Vishnu Constructions &
Company, Hyderabad.
3.88 Crs 3.38 Crs 4.94 Crs 12 + 3 months
DETAILS OF CONTRACTS AWARDED BY PIU/RVNL/SC UPTO 30.06.2010.
CIVIL
10 RVNL/SC/OBVP-
KP/Track
Maintenance/135
12.05.09 Obulavaripalli -
Krishnapatnam New BG line -
Proposed maintennce of
newly commissioned BG track
betgween Venkatachalam -
Krishnapatnam stations
including points, X-ings,
looplines etc, on Vijayawada
Divion of South Central
Railway
RVNL/SC/OBVP-KP/Track
Maintenance/135
dt:22.10.09
Sri D.Srinivas, Secunderabad 28.34 lakhs 28.34 lakhs 24.95 lakhs 21.10. 2010.
11 RVNL/SC/GY-
PMT/Bridge works/139
22.12.2010 Construction of Bridge
No:601, 743 & 744
RVNL/SC/GY-PMT/Bridge
works/139 dt:23.11.2009
M/s.MEC-CC (JV)/Hyderabad 9.92 Crs 9.92 Crs 11.45 Crs 6 Months + 180 days
DLP
12 RVNL/SC/GY-
PMT/Fabrication
works/140
22.12.2010 Construction of FOBs and
COPs between GY-PMT
RVNL/SC/GY-
PMT/Fabrication works/140
dt:23.11.2009
M/s. Vishnu Constructions &
Company, Hyderabad.
7.75 Crs 7.75 Crs 8.91 Crs 6 Months + 180 days
DLP
(B)
13 No.2006/ELECT/PMT-
NRE/001 dated
13.3.06
23-5-06 Supply, Erection, Testing and
commissioning of 25 Kv OHE
bet. Pullampet-Nandalur Sec.
of Guntakal Divn. of S.C. Rly
No.2006/Elec./PMT-
NRE/001 dt. 15.11.06
M/s. Tata Projects Limited,
Hyderabad. (TPL)
599.83 lakhs 599.83 lakhs 840.47 lakhs 12 months (02-10-
2007). Extended up to
30-09-2009.
14 RVNL/SC/OBVP-
KP/OHE/120
31.08.07 Design, Supply, Erection,
Testing & Commissioning of
25 KV, 50HZ, Single Phase,
Traction Over-head
Equipment, etc Ph. I work
between Venkatachalam
Road Jn. to Krishnapatnam in
connection with laying of new
BG line between
Obulavaripalle -
Krishnapatnam section of
South Central Railway.
RVNL/SC/OBVP-
KP/OHE/120 dt:12-03-2008
M/s. Cobra Instalaciones y.
Servicios, S.A., NDLS
NA NA Rs.15.11 Crs. 11.03.2009. Extended
up to 15-10-2009
15 RVNL/SC/NRE-
KDP/RE/121
27.01.08 Design, Supply, Erection,
Testing & Commissioning of
25 KV, 50HZ, Single Phase,
Traction Over-head
Equipment etc., between
Nandalur (Excl) and
Kondapuram (Incl) stations
and S&T works of Guntakal
Division of South Central Rly.
RVNL/SC/NRE-
KDP/RE/121/Agt.
Dated 21-07-08
M/s.Larsen & Toubro Limited,
Chennai
NA NA Rs.103.47 Crs 20-01-2010
ELECTRICAL
16 RVNL/SC/GTL-
WADI/DDE/122
27.03.08 Detailed Design Engineering
(Electrical, Civil) for Railway
Electrification of –
Guntakal(excl)-Raichur-
Wadi(excl) and Wadi(excl) –
Gulbarga(incl) (265RKM)
(including patch doubling line
section) in Guntakal Division
on S.C. Rly and Solapur Divn
of Central Railway
RVNL/SC/GTL-WADI-
GR/DDE/Agt/122 Dt:18-07-
2008.
M/s. Balaji Rail Road Systems
Limited, Secunderabad.
NA NA Rs.58.41 lakhs 17.01.2009. Extended
up to 31.03.2010.
17 RVNL/SC/KDP-
GTL/RE/127
04.06.08 Design, Supply, Erection,
Testing & Commissioning of
25 KV, 50HZ, Single Phase,
Traction Over-head
Equipment etc.,for RE
between Kondapuram(Excl) –
Guntakal (Incl) Section of
GTL Divn of SC Rly.
RVNL/SC/KDP-
GTL//RE/127 dt:17-11-2008
M/s.TATA Projects Limited,
Hyderabad
NA NA Rs.101.18 Crs 16.05.2010.
18 RVNL/SC/NRE-
GTL/TSS/119
08.07.08 Design, Supply, Erection,
Testing & Commissioning of
132/25 KV and 220/25 KV,
TSS at Kadapa, Muddanur,
Tadipatri and Gooty Nandalur
- Guntakal Section of Guntakal
Division of SC RLY.
RVNL/SC/NRE-
GTL/TSS/119,
dt:04.12.2008
M/s. G.E.T. Power Pvt
Limited, Chennai
NA NA Rs.28.20 Crs 03.06.2010
19 RVNL/SC/VKT-
KP/SCADA/131
25.05.09 Design, Supply, Erection,
Testing & Commissioning of
Supervisory Remote Control &
Data Acquisition (SCADA)
equipment on section between
Venkatachalam RD JN and
Krishnapatnam on Vijayawada
Divn of SC Rly.
RVNL/SC/VKT-
KP/SCADA/131 dt.11.9.09
M/s Nelco, Navi Mumbai 11.05 lakhs 11.05 lakhs Rs.13.26 lakhs 3 months
20 RVNL/SC/NRE-
GTL/PMC/124
dt:17.12.09
14.05.09 Project Management
consultancy for erection,
Testing & Commissioning of
25 KV AC single phase 50 Hz
Traction OHE, Switching stns,
TSSs, SCADA, S&T works
and other associated civil
works in NRE (Excl) – GTL
(Incl) section of GTL Divn of
SC Railway
LOA No: RVNL/SC/NRE-
GTL/PMC/124 dt:17.12.09
M/s. United Rail Road
Consultants Ltd, Hyderabad
250.74 lakhs 250.74 lakhs 274.65 lakhs 36 months
21 RVNL/SC/NRE-
GTL/RE/SCADA/136
05.03.2010 Design, Supply, Erection and
Testing and commissiong of
SCADA bet. Nandalur and
GTL
LOA No:RVNL/SC/NRE-
GTL/RE/SCADA/136
dt:04.06.2010.
M/s. CMC Limited,
Hyderabad.
138.00 lkhs 138.00 lakhs 113.75 lakhs 12 months excluding 6
months defect liability
( c)
22 No.C/ADB/Gooty-
Pullampet/ Signalling
(Vol.III) dated 10-11-04
20.04.05 S & T Works in Guntakal-
Raichur patch doublinhg
No.C/ADB/Gooty-Pullampet/
Signalling (Vol.III) dated 08-
11-06
M/s. Leighton Emrail-Kalindee
(JV)
10589 lakhs 10589 lakhs 9681.31 lakhs 36 months (29.6.09)
23 RVNL/S&T/Venk-
Krish/Bid dt:31.10.07
04.12.07 S&T works in five stations in
connection with new BG line
between Venkatachalm -
Krishnapatnam
RVNL/S&T/Venk-Krish/Bid
dt:15.07.08
M/s . VNR Infrastructures Ltd,
Hyderabad.
8.70 8.70 10.82 12 months.
24 RVNL/S&T/GTL -
RC/Bid dt:20.06.08
31.07.08 S&T works of Guntakal -
Raichur Patch doubling
No:RVNL/SC/GTL-RC/VNR-
1/09 dt:31.03.09
M/s. VNR Infrastructures
Limited, Hyderabad
14.18 14.18 15.29 12 months.
25 No.RVNL/
SC/NRE-KDP/RE/121
S&T works at 12 stations and
misc works in connection with
doubling of Raichur –
Guntakal section.
No.RVNL/
SC/NRE-KDP/RE/Agt/121
dt. 12.8.08
M/s. L&T Limited, ECC Divn.
Chennai
1587.3 1587.3 2090.47 18 months
Signal & Telecom
Tender Number Date of Opening Description of Item/WorkContract No. &
date of awardContractors Name
Quantity (for
supply contract)
Estimated cost (for
Engg./Elect. /S&T/
Mech.
Rate ( for supply
contract)
Tendered cost (for
Engg./Elect./
S&T/Mech
Value of
contract
Scheduled
completion date
NIL NIL NIL NIL NIL NIL NIL NIL NIL
Details of Contracts Awarded during JUNE 2010 by PIU Mumbai
Sl. No Tender Number Date of
opening
Description of item/work Contract No. & date Contractor’s Name Estima-ted cost Tendered cost Value of Contract Scheduled completion
date
(A)
1 No.RVNL/SC/GY-
PMT/104 dated 18-10-
05
31.01.06 Gooty-Pullampet patch
doubling
No.RVNL/SC/GY-
PMT/Agt/104 dated 22-08-
2006
M/s. Simplex Infrastructures
Ltd., Mumbai
19223.74 lakhs 19223.74 lakhs 17074.07 lakhs 30 + (6 Defect. Liability
period) (06-04-2009)
2 No.RVNL/SC/GY-
PMT/PMC/106 dated
02-12-05
27.03.06 Project Management
Consultancy for Gooty-
Pullampet patch doubling
No.RVNL/SC/GY-
PMT/PMC/Agmt/106 dated
24.11.06
M/s. Aarvee Associates,
Hyderabad.
600 lakhs 600 lakhs 575.32 lakhs 30 + (6 Defect. Liability
period (28-03-2009)
3 No.RVNL/SC/OBVP-
KP/108 dated 01-09-
2006
13.11.06 Venkatachalam to
Krishnapatnam Phase I New
BG Line
No.RVNL/SC/OBVP-KP/108
dated 27-06-2007
M/s.APR-VNR Joint Venture
,Hyderabad
4060.6 lakhs 4060.6 lakhs 4246.1 lakhs 12 + (6 months defect
liability period) (28-03-
2008)4 No.RVNL/SC/OBVP-
KP/PMC/114 dated 25-
05-06
09.07.07 Project Management
Consultancy for Venkata-
chalam to Krishnapa-tnam
Phase I works
No.RVNL/SC/OBVP-
KP/PMC/114 dated 5.11.07
M/s. Project Engineering
Management Services-KITCO
(JV), Tiruvananthapuram,
Kerala
69.88 lakhs 69.88 lakhs 84.66 lakhs 12 + (6 months defect
liability period (09-09-
08)
5 No.RVNL/SC/GTL-
RC/112 dated 06-02-
2007.
12.04.07 Guntakal-Raichur patch
doubling .
No.RVNL/SC/GTL-RC/112
dated 15.10.07
M/s. APR-MVR Joint Venture,
Hyderabad
9670.5 lakhs 9670.5 lakhs 9399.34 lakhs 18+6 (6 months defect
liability period) dated 23-
02-096 No.RVNL/SC/GTL-RC/
113 dated 21.05.2007
10.07.07 Project Management
Consultancy for Guntakal-
Raichur patch doubling .
No.RVNL/SC/GTL-RC/ PMC
/113/Contract dated
11.12.2007
M/s. SOWiL Limited, Navi
Mumbai – 400706
200.40 lakhs 200.40 lakhs 121.00 Lakhs 18+6 (6 months defect
liability period) dated 23-
02-09.7 No:RVNL/SC/NRE-
GTL/RE/Civil/128
dt:13.04.09
21.05.09 Construction of Quarters and
Service Bldgs etc in
connection with Civil & Elecl
works of RE bet. Nandalur -
Kondapauram
RVNL/SC/NRE-
GTL/RE/Civil/128
dt:13.04.09
M/s. Inter Continental (I) Ltd,
Hyderabad.
8.21 Crs 8.21 Crs 9.51 Crs 12 + 3 months
8 No:RVNL/SC/NRE-
GTL/RE/Civil/129
dt:13.04.09
21.05.09 Construction of Quarters and
Service Bldgs etc in
connection with Civil & Elecl
works of RE bet. Kondapuram -
Guntakal.
RVNL/SC/NRE-
GTL/RE/Civil/129
dt:13.04.09
M/s. Inter Continental (I) Ltd,
Hyderabad.
9.95 Crs 9.95 Crs 12.09 Crs 12 + 3 months
9 No:RVNL/SC/NRE-
GTL/RE/Civil/130
dt:13.04.09
21.05.09 Construction of Tower wagon
shed, Loco trip shed etc in
connection with RE works bet.
Nandalur - Guntakal.
No:RVNL/SC/NRE-
GTL/RE/Civil/130
dt:13.04.09
M/s. Vishnu Constructions &
Company, Hyderabad.
3.88 Crs 3.38 Crs 4.94 Crs 12 + 3 months
DETAILS OF CONTRACTS AWARDED BY PIU/RVNL/SC BY THE END OF JULY 2010
CIVIL
10 RVNL/SC/OBVP-
KP/Track
Maintenance/135
12.05.09 Obulavaripalli - Krishnapatnam
New BG line - Proposed
maintennce of newly
commissioned BG track
betgween Venkatachalam -
Krishnapatnam stations
including points, X-ings,
looplines etc, on Vijayawada
Divion of South Central
Railway
RVNL/SC/OBVP-KP/Track
Maintenance/135
dt:22.10.09
Sri D.Srinivas, Secunderabad 28.34 lakhs 28.34 lakhs 24.95 lakhs 21.10. 2010.
11 RVNL/SC/GY-
PMT/Bridge works/139
22.12.2010 Construction of Bridge No:601,
743 & 744
RVNL/SC/GY-PMT/Bridge
works/139 dt:23.11.2009
M/s.MEC-CC (JV)/Hyderabad 9.92 Crs 9.92 Crs 11.45 Crs 6 Months + 180 days
DLP
12 RVNL/SC/GY-
PMT/Fabrication
works/140
22.12.2010 Construction of FOBs and
COPs between GY-PMT
RVNL/SC/GY-
PMT/Fabrication works/140
dt:23.11.2009
M/s. Vishnu Constructions &
Company, Hyderabad.
7.75 Crs 7.75 Crs 8.91 Crs 6 Months + 180 days
DLP
(B)
13 No.2006/ELECT/PMT-
NRE/001 dated 13.3.06
23-5-06 Supply, Erection, Testing and
commissioning of 25 Kv OHE
bet. Pullampet-Nandalur Sec.
of Guntakal Divn. of S.C. Rly
No.2006/Elec./PMT-
NRE/001 dt. 15.11.06
M/s. Tata Projects Limited,
Hyderabad. (TPL)
599.83 lakhs 599.83 lakhs 840.47 lakhs 12 months (02-10-
2007). Extended up to
30-09-2009.
14 RVNL/SC/OBVP-
KP/OHE/120
31.08.07 Design, Supply, Erection,
Testing & Commissioning of
25 KV, 50HZ, Single Phase,
Traction Over-head
Equipment, etc Ph. I work
between Venkatachalam Road
Jn. to Krishnapatnam in
connection with laying of new
BG line between
Obulavaripalle -
Krishnapatnam section of
South Central Railway.
RVNL/SC/OBVP-
KP/OHE/120 dt:12-03-2008
M/s. Cobra Instalaciones y.
Servicios, S.A., NDLS
NA NA Rs.15.11 Crs. 11.03.2009. Extended
up to 15-10-2009
15 RVNL/SC/NRE-
KDP/RE/121
27.01.08 Design, Supply, Erection,
Testing & Commissioning of
25 KV, 50HZ, Single Phase,
Traction Over-head Equipment
etc., between Nandalur (Excl)
and Kondapuram (Incl)
stations and S&T works of
Guntakal Division of South
Central Rly.
RVNL/SC/NRE-
KDP/RE/121/Agt.
Dated 21-07-08
M/s.Larsen & Toubro Limited,
Chennai
NA NA Rs.103.47 Crs 20-01-2010
ELECTRICAL
16 RVNL/SC/GTL-
WADI/DDE/122
27.03.08 Detailed Design Engineering
(Electrical, Civil) for Railway
Electrification of –
Guntakal(excl)-Raichur-
Wadi(excl) and Wadi(excl) –
Gulbarga(incl) (265RKM)
(including patch doubling line
section) in Guntakal Division
on S.C. Rly and Solapur Divn
of Central Railway
RVNL/SC/GTL-WADI-
GR/DDE/Agt/122 Dt:18-07-
2008.
M/s. Balaji Rail Road Systems
Limited, Secunderabad.
NA NA Rs.58.41 lakhs 17.01.2009. Extended
up to 31.03.2010 with
LD.
17 RVNL/SC/KDP-
GTL/RE/127
04.06.08 Design, Supply, Erection,
Testing & Commissioning of
25 KV, 50HZ, Single Phase,
Traction Over-head Equipment
etc.,for RE between
Kondapuram(Excl) – Guntakal
(Incl) Section of GTL Divn of
SC Rly.
RVNL/SC/KDP-GTL//RE/127
dt:17-11-2008
M/s.TATA Projects Limited,
Hyderabad
NA NA Rs.101.18 Crs 16.05.2010.
18 RVNL/SC/NRE-
GTL/TSS/119
08.07.08 Design, Supply, Erection,
Testing & Commissioning of
132/25 KV and 220/25 KV,
TSS at Kadapa, Muddanur,
Tadipatri and Gooty Nandalur -
Guntakal Section of Guntakal
Division of SC RLY.
RVNL/SC/NRE-
GTL/TSS/119, dt:04.12.2008
M/s. G.E.T. Power Pvt
Limited, Chennai
NA NA Rs.28.20 Crs 03.06.2010
19 RVNL/SC/VKT-
KP/SCADA/131
25.05.09 Design, Supply, Erection,
Testing & Commissioning of
Supervisory Remote Control &
Data Acquisition (SCADA)
equipment on section between
Venkatachalam RD JN and
Krishnapatnam on Vijayawada
Divn of SC Rly.
RVNL/SC/VKT-
KP/SCADA/131 dt.11.9.09
M/s Nelco, Navi Mumbai 11.05 lakhs 11.05 lakhs Rs.13.26 lakhs 3 months. Extended
up to 31.08.10.
20 RVNL/SC/NRE-
GTL/PMC/124
dt:17.12.09
14.05.09 Project Management
consultancy for erection,
Testing & Commissioning of
25 KV AC single phase 50 Hz
Traction OHE, Switching stns,
TSSs, SCADA, S&T works and
other associated civil works in
NRE (Excl) – GTL (Incl)
section of GTL Divn of SC
Railway
LOA No: RVNL/SC/NRE-
GTL/PMC/124 dt:17.12.09
M/s. United Rail Road
Consultants Ltd, Hyderabad
250.74 lakhs 250.74 lakhs 274.65 lakhs 36 months.
21 RVNL/SC/NRE-
GTL/RE/SCADA/136
05.03.2010 Design, Supply, Erection and
Testing and commissiong of
SCADA bet. Nandalur and
GTL
LOA No:RVNL/SC/NRE-
GTL/RE/SCADA/136
dt:04.06.2010.
M/s. CMC Limited, Hyderabad. 138.00 lkhs 138.00 lakhs 113.75 lakhs 12 months excluding 6
months defect liability
( c)
22 No.C/ADB/Gooty-
Pullampet/ Signalling
(Vol.III) dated 10-11-04
20.04.05 S & T Works in Gooty -
Pullampeta patch doublinhg
No.C/ADB/Gooty-Pullampet/
Signalling (Vol.III) dated 08-
11-06
M/s. Leighton Emrail-Kalindee
(JV)
10589 lakhs 10589 lakhs 9681.31 lakhs 36 months (29.6.09)
23 RVNL/S&T/Venk-
Krish/Bid dt:31.10.07
04.12.07 S&T works in five stations in
connection with new BG line
between Venkatachalm -
Krishnapatnam
RVNL/S&T/Venk-Krish/Bid
dt:15.07.08
M/s . VNR Infrastructures Ltd,
Hyderabad.
8.70 8.70 10.82 12 months.
24 RVNL/S&T/GTL -
RC/Bid dt:20.06.08
31.07.08 S&T works at 12 stations and
misc works in connection with
doubling of Raichur – Guntakal
section.
No:RVNL/SC/GTL-RC/VNR-
1/09 dt:31.03.09
M/s. VNR Infrastructures
Limited, Hyderabad
14.18 14.18 15.29 12 months.
25 No.RVNL/
SC/NRE-KDP/RE/121
S&T works at 7 stations in
Nandaluru - Kondapur patch
;doubling.
No.RVNL/
SC/NRE-KDP/RE/Agt/121
dt. 12.8.08
M/s. L&T Limited, ECC Divn.
Chennai
1587.3 1587.3 2090.47 18 months
Signal & Telecom
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 1 between Bina (Incl) to Ganj Basoda (Incl)
chainage 975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 2 between GanjBasoda (Excl) to Sanchi
(Incl) chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) -
Package No. 3 between Sanchi (Excl) to Habibganj (Incl)
chainage 879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. --
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot
No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.09.2010*
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.08.2010**
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bin
a- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
Details of Contracts Placed upto the month July' 2010 under GM/P-III
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-
500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60
kg 1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.09.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot No.
11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand,
3rd & 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation:
Rs 20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch
60 Kg.
Rs 3.92 Cr 16.08.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 31.08.2010***
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 16.08.2010
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road
projects in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
Note: * Delivery Period Extended upto 30.09.2010.
** Delivery Period Extended upto 30.08.2010.
*** Delivery Period Extended upto 31.08.2010.
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India) - Package No. 1
between Bina (Incl) to Ganj Basoda (Incl) chainage
975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India) - Package No. 2
between GanjBasoda (Excl) to Sanchi (Incl) chainage
928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India) - Package No. 3
between Sanchi (Excl) to Habibganj (Incl) chainage
879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. --
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot No.
31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt. Ltd.,
24/5 Sriram Road, Civil Lines,
Delhi-110054.
Manufacture and Supply: Rs 1.25
Cr for 60 kg 1 in 12 Switches and
Rs 16.97 Lakh for 60 kg 1 in 8 1/2
Switches & Rs 4.24 Lakh for 52 kg
1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.09.2010
(extended)
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt. Ltd.,
24/5 Sriram Road, Civil Lines,
Delhi-110054.
Manufacture and Supply: Rs 2.47
Cr for 60 kg 1 in 12 CMS Crossing
and Rs 0.5 Cr for 60 kg 1 in 8 1/2
CMS Crossing. Transportation:
Rs 3.18 Lac for 60 kg 1 in 12 CMS
Crossing and Rs 0.6 Lac for 60 kg
1 in 8 1/2 CMS Crossing.
Rs 3.02 Cr 30.08.2010
(extended)
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bi
na- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
Details of Contracts Placed upto the month AUG' 2010 under GM/P-III
7 RVNL/BPL/S&T/HBJ-BPL-
BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor 6-
3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-500082.
Manufacture and Supply: Rs 3.22
Cr. for PSC Turnout Sleeper Set
for 1 in 12, 60 kg and Rs 52.63
Lakh for PSC Turnout Sleeper Set
1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60 kg
1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.09.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand, 3rd
& 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs 3.34
Cr. for PSC Turnout Sleeper Set
for 1 in 12, and Rs 25.26 Lac for
PSC T/out Sleeper Set 1 in 8 1/2
60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation: Rs
20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch 60
Kg.
Rs 3.92 Cr 16.08.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs 5.70
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 5.10 Lac for 1 in
81/2 Derailing Switches 52Kg.
Transportation: Rs 1.31 Lac for 1
in 8 1/2 52Kg Curved Switches and
Rs 1.08 Lac for 1 in 8 1/2 Derailing
Switches
Rs 13.19 Lac 31.08.2010
(extended)
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09 Cr
for Maintenance Tools, Rs 0.35 Cr
for Site Facilities & Rs 2.65 Cr for
Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs 2.33
Cr for 60 Kg CMS Crossing 1 in
12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 31.10.2010
(extended)
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr for
staff & Provision & maintenance
of Office for- Rs 2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road projects
in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
Note: * Delivery Period Extended upto 30.09.2010.
** Delivery Period Extended upto 30.08.2010.
*** Delivery Period Extended upto 31.10.2010.
**** Delivery Period Extended upto 31.08.2010.
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 1 between Bina (Incl) to Ganj Basoda (Incl) chainage
975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 2 between GanjBasoda (Excl) to Sanchi (Incl)
chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 3 between Sanchi (Excl) to Habibganj (Incl) chainage
879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. --
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot
No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.11.2010
(extended)
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.08.2010
(extended)
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bi
na- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
Details of Contracts Placed upto the month of Sept' 2010 under GM/P-III
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60 kg
1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.11.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand,
3rd & 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation:
Rs 20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch
60 Kg.
Rs 3.92 Cr 31.12.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 10.09.2010
(extended)
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 31.10.2010
(extended)
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road
projects in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
1
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
1 RVNL/CPM/ATU-SA/Chennai/
22.9.2005 GC work between SA - ATU section [including Civil Engg., Electrical and S & T works]
LOA No.RVNL/CPM/ATU-SA/Chennai/01 dt.31.102005
Agreement no. RVNL/Attur-Salem/01 dated 25.1.2006.
M/S D.S. Construction Ltd., C-66, South Extension II, New Delhi. 110 049.
56.69 Cr 0 614690485.96 18.11.2006./Extd Up to
31.12.2007+ 12 months Defect
Liability period.
2
RVNL/CPM/ATU-SA/Chennai/02
20.9.2005 Project Management Consultancy for GC between SA - ATU GC work.
LOA no. RVNL/CPM/ATU-SA/Chennai/02 dated 14.11.2005 Agreement no. RVNL/Chennai/PMC/02 dated3.4.2006
M/S Aarvee Associates, Ravula Residency, Srinagar colony, Hyderabad. 82.
-- 0 10118500.00
+
Service tax.
12 months + 12 months defects
liability period [31.12.2007 +
DLP]
3 RVNL/CPM/MAS/VM-MV/01.
02.01.2006 Gauge conversion of MG to BG between Villupuram and Mayiladuthurai section in Southern Railway.
-LOA no. RVNL/CPM/MAS/VM-MV/01 dt. 17.4.2006.Agreement no. RVNL/CPM/MAS/VM-MV/01 dated 21.7.2006
M/S Tata -Kalindi-Unity Infra Projects Ltd., [JV]
Suryodaya, 1-10-60/3, Begum pet, Hyderabad -16.
186 Cr. 0 1822269941.00 16.1.2008./ Extn. 15.11.2008/
Extn. 30.9.2009 30.12.2009.
2
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
4 RVNL/TRL-AJJ/01
22.2.2006 Project Management Consultancy for construction of 3 rd line between Tiruvallur and Arakkonam in Southern Railway.
LOA no. RVNL/TRL-AJJ/01 dt. 27.6.2006 Agreement no. RVNL/TRL-AJJ/02/PMC dt. 21.8.2006
M/S Expert _SPA [JV]
C/o Expert Resorts & Layout G-2, Pride Elite, No. 10, Museum Road, Bangalore. 25
-- 0 15893000.00 +
Service tax.
21 Months + 12 months DLP
15.11.2008 + DLP] Extd. 31.7.2010
5 RVNL/TRL-AJJ/01
02.01.2006 Construction of Roadbed, Bridges, Facilities, installation of Track [excluding supply of Rails, Thick web switches & weldable CMS Crossings] & Electrical [Rly. electrification and Genl. Electrification] Signalling and Telecommunication works in connection with provision of 3rd line between
LOA no. RVNL/TRL-AJJ/01 dt. 29.6.2006
Agreement no. RVNL/CPM/TRL-AJJ/Chennai/01 dt. 28.8.2006
M/S Larsen & Toubro Limited, Chennai. 89.
580123304 0 589425046.00 28.6.2007 / Extn.
Up to 31.7.2009
+ 180 days DLP
3
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
Tiruvallur and Arakkonam in S.Railway.
6 RVNL/VM-MV/Chennai/02
16.5.2006 Project Management Consultancy services for GC of MG to BG Rly. Line of VM - MV section in southern Railway. - 122 KMs
LOA no. RVNL/VM-MV/Chennai/02 dated 12.7.2006 Agreement no. RVNL/VM-MV/Chennai/02/PMC dt. 2.9.2006
M/S Expert_SPA [JV], Bangalore -25.
---- 0 37961020
+
Service Tax
March 2008 including DLP.
[31.8.2008 + DP]
7 RVNL/CPM/MAS/VM-MV/Minor Br.LT/03
18.12.2006 Construction of minor bridges with precast RCC box of various sizes between Villupuram and Mayiladuturai – Reach III
Agreement No. RVNL/CPM/MAS/VM-MV/Minor Br.LT/03 dated 28/03/2007
M/s. K.Rajan No. 4, 5th Cross Canara Bank Colony, Srinivasa Nagar Tiruchchirappalli – 620 017
16804835.00 0 17561052 30.10.2007/ Extd. Up to 31.10.2009/
31.3.2010
8 RVNL/CPM/MAS/IPL-ICTT/01
15.11.2006 Provision of rail connectivity from Idappalli to ICTT, Vallarpadam for works of elevated structures, major and minor bridges and earthwork in
LOA No. RVNL/CPM/MAS/IPL-ICTT/01 dated 21/02/2007
M/s. Afcons Infrastructure Ltd. Afcons House, 16 Shah Industrial Estate Andheri (W), Mumbai – 400 053
1678135436 0 1712431635 30.11.2008
Extd. Up to 21.2.2010
4
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
Trivandrum Division of Southern Railway
9 RVNL/CPM/MAS/TRL-AJJ/Pipe Culvert/LT - 2
24.3.2007 Extension of Pipe Culverts, Construction of Platform wall, Passenger amenities, Circulation area etc., in TRL - AJJ section.
RVNL/CPM/MAS/TRL-AJJ/Pipe Culvert/LT - 2
dt. 15.5.2007
M/S Harsha constructions, 70, Hunters Road,, Vasupujya, Vepery, Chennai - 600 112.
1.78 Crore 0 20339036 14.2.2008 Extd. Up to 30.9..2009
/30.4.2010
10 RVNL/CPM/MAS/VM-MV/Retaining Wall/LT -10
27.3.2007 Construction of retaining wall between KM 253/800 - 284/000 - Vallampadugai - Mayiladuthurai Reach V in VM - MV Section
RVNL/CPM/MAS/VM-MV/Retaining Wall/LT -10 dt.25.5.2007
Mr. L. Narasimha Reddy, 37/18, Dr. Gurusamy Road,Chetpet, Chennai - 600 031.
1.72 Crore 0 17249765 24.10.2007 Extd. Up to 30.10.2009
/10.6.2010
11 RVNL/CPM/MAS/VM-MV/Station Bldg.,/LT- 12
16.6.2007 Construction of Station Building at Thiruthuraiyur, Melpattambakkam and Tiruppadiripuliyur and Service Buildings
RVNL/CPM/MAS/VM-MV/Station Bldg.,/LT- 12 dated 7.7.2007
M/S Harsha constructions, 70, Hunters Road,, Vasupujya, Vepery, Chennai - 600
1.77 Crore 0 21821118 6.1.2008 Extd. Up to 30.10.2009/
31.3.2010 /30.6.2010
5
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
at Tiruppadiripuliyur in VM - MV Section.
112.
12 RVNL/CPM/MAS/VM-MV/Station Bldg.,/LT - 13
16.6.2007 Construction of Station Building at Kille, Chidambaram and Vaithiswaran Koil and Service Building at Chidambaram in VM-MV Section..
RVNL/CPM/MAS/VM-MV/Station Bldg.,/LT - 13 dated 7.7.2007
M/S Simhadri Constructions, 31/2, Welcome Colony, Anna Nagar West, Chennai - 600 101.
1.86 Crore 0 22861552 6.1.2008 Extd. Up to
30.8.2009/31.12.2009
13 RVNL/CPM/MAS/IPL-ICTT/LT -2
16.8.2007 Linking, Supply of Ballast and supply of Permanent way materials for the yard arrangements at Idapalli Yard.
LOA no. RVNL/CPM/MAS/IPL-ICTT/LT -2 dated 1.10.2007
Mr. Anil Kumar, Railway Contractor, Kodath House, Neduvannoor, Chowara PO, Alwaye - 683 571.
3.21 Crores 0 53914140 30.4.2008
Extd. Up to 31.12.2009 31.3.2010/ 30.6.2010.
6
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
14 RVNL/CPM/MAS/IPL-ICTT/LT-3
22.8.2007 Overhead Electrification and modification works at Idapalli Yard including provision of switching post in Trivandrum Division.
LO No. RVNL/CPM/MAS/IPL-ICTT/LT-3 dt. 20.12.2007
M/S Tirumurthi Hightech Co., Pvt./, Ltd., 54/25, GF - 2nd Street, Padi Pudunagar, Chennai - 600 101.
2.23 Cr. 0 23199802 19.6.2008 Extd. Up to 30.11.2009/
30.6.2010/ 31.8.2010
15 RVNL/CPM/MAS/VM-MV/OT-2
27.3.2008 Paving of Rail Level Goods Platform at Sirkazhi Yard, Improvements to LC Gates, Water Pipe line works for Coach watering at Mayiladuturai and Track Drainage arrangement at Sirkashi, Vaitheeswarankoil, Anadandavapuram and Mayiladuthurai junction in Villupuram - Mayiladuturai section.
RVNL/CPM/MAS/VM-MV/OT-2 dt.12.6.2008
Mr. R. Venkatakrishna Reddy, HO 9-53, New Dilsukh Nagar, Hyederabad. 500 060
3.5 Crore 0 35998144 11.12.2008 Extd. Up to
30.11.2009/ 31.3.2010
/15.10.2010.
7
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
16 RVNL/CPM/MAS/IPL-ICTT/S & T/OT-2
20.3.2008 Signaling arrangements at Idapalli Yard [Remodeling work] in connection with provision of Rail connectivity from Idapalli to International Container Transshipment
RVNL/CPM/MAS/IPL-ICTT/S & T/OT-2 dt. 10.5.2008
Mr. R.V. Abdul Majeed, Railway Contractor, P.Box No. 12, Chavakad, Trichur District, Kerala.
1.95 Crore 0 35134549 9.11.2008 Extd. Up to
30.11.2009/ 31.3.2010./
31.5.2010
17 RVNL/CPM/MAS/VM-MV/OT-5
19.5.2008 Additional works such as earth work in Platform, regarding of LC approach roads, laying of bituminous concrete in LCs, Gate lodge buildings, formation of approach roads to Goods Platforms, protection of embankment at vulnerable locations, painting of PSC
LOA No. RVNL/CPM/MAS/
VM-MV/OT-5 dated 21.7.2008.
M/S Eagle Earthmovers, 14, SCS Complex, South Car Street, Tiruchendur - 637211.
84551735 0 107977171 20.1.2009 Extd. Up to
30.11.2009/ 31.3.2010
/31.8.2010
8
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
girders, etc. between Villupuram and Cuddalore Port Junction. [including]
18 RVNL/CPM/MAS/VM-MV/OT -4
13.5.2008 Conversion of free/two 90 R & 60 KG Rail joints into short welded panels/long welded panels on loop & main lines in station yards in VM - MV section.
LOA no. RVNL/CPM/MAS/VM-MV/OT -4 dated 14.8.2008
M/S Sagar Thermit Corporation Ltd., B -67, APIE, Balanagar, Hyderabad - 500037.
7358600 0 10890728 13.2.2009 Extd. Up to 30.6.2009/
31.12.2009
19 RVNL/CPM/MAS/TRL-AJJ/OT-2
03.7.2008 Paving of Platform with GC, provision of pre-cast CC drain, Provision of Inspection Steps, Mini shelters on Platform & other Misc. works in TRL - AJJ Section.
LOA No.
RVNL/CPM/MAS/TRL-AJJ/OT-2 dated 20.8.2008
M/S Harsha Constructions, 51, Hunters road, Vasupujya apartment, Vepery, Chennai- 600112.
1.9382394 0 20936932 19.11.2008
Extd. Up to 30.9.2009/ 30.4.2010
9
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
20 RVNL/CPM/MAS/VM-MV/OT - 7
03.7.2008 Ballasting by Rail lorry and Hopper wagons, packing of tracks and other track works between Villupuram and Mayiladuturai.
LOA no. RVNL/CPM/MAS/VM-MV/OT - 7 dated 22.10.2008
M/S M. Mohandass, Railway Contractor, No. 91, PJN 2nd Street, Sholingur Road, Arakkonam - 631 101.
26866001 0 28047314 21.07.2009 Extd. Up to 30.10.2009
/31.3.2010/ 31.5.2010
21 . RVNL/CPM/MAS/VM-MV/OT-10
11.7.2008 Proposed improvements to LCs, earthwork in filling for Platforms and bridge back filling, painting of PSC girders, paving of goods platforms and other works between Parangipettai & Sirkazhi.
LOA No. RVNL/CPM/MAS/VM-MV/OT-10 dt. 22.10.2008
Mr. R. Venkatakrishna Reddy, HO 9-53, New Dilsukh Nagar, Hyederabad. 500 060
85892744 0 103303578 21.04.2008 Extd. Up to
30.10.2009/ 30.4.2010/ 30.6.2010/ 30.9.2010
10
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
22 RVNL/CPM/MAS/VM-MV/OT-09
11.7.2008 Proposed improvements to LCs, earthwork in filling for Platforms and bridge back filling, painting of PSC girders, paving of goods platforms and other works between Cuddalore Port Junction and Parangipettai.
LOA No. RVNL/CPM/MAS/VM-MV/OT-09 dt. 6.11.2008
M/S Kalindee Rail Nirman (E) Ltd., 2nd Floor, Building no. 9A, Cyber city, DLF Phase III, Guraon - 122002
60642004 0 76649581 05.05.2008
Extd. Up to 15.10.2009/
31.3.2010./
23 RVNL/CPM/MAS/IPL-ICTT/OT -3
29.12.2008 Supply of 50 mm size hard machine crushed stone ballast as per latest RDSO specification [IRS - GE-1 of June 2004] and stacking the same at places along side the track and yard as per the directions of the
LOA no. RVNL/CPM/MAS/IPL-ICTT/OT -3 dated 9.2.2009
M/S Vallamattam Stone Aggregates {P} Ltd. Pandappilly Post, Muvattupuzha, Ernakulam, Kerala - 686 672.
21216000 0 19497504 08.10.2009/
31.5.2010/ 31.8.2010.
11
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
24 RVNL/CPM/MAS/IPL-ICTT/OT-5
06.2.2009 1. Manufacture & supply of prestressed pretensioned concrete sleeper for Bridges with arrangements for fixing 60 Kg/52 Kg [UIC] and 52 Kg/90 R Guard Rail for Bridges as per RDSO drg. No. 4088 Alt. 3 including loading into Road Lorries.
2. Manufacture and supply of pre-stressed, pretensioned concrete sleepers for fixing 60 KG [UIC]/52 Kg running and 52 KG/90 R Guard Rail for bridge approaches as per
LOA no. RVNL/CPM/MAS/IPL-ICTT/OT-5 dated 9.3.2009
M/S Concrete Products & Construction Company, No. 398, [Old no. 766], Poonamallee High Road, Chennai. 600 010.
14091786 0 17626497 08.9.2009/
30.4.2010/ 31.7.2010.
12
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
RDSO Drg. No. 4089 to 4097 Alt.4 including loading into Road Lorries in the factory premises.
25 RVNL/CPM/MAS/IPL-ICTT/OHE/OT-4
06.3.2009 Design, Supply, erection and commissioning of traction Overhead equipment, auxiliary transformer stations including modification to existing OHEs between Idappalli and Vallarpadam in Trivandrum division of Southern Railway in the State of Kerala.
LOA no. RVNL/CPM/MAS/IPL-ICTT/OHE/OT-4 dated 6.5.2009
M/S Tirumurthi Hitech Co., PVT., Ltd., 54/55, Ground floor, Second Street, Padi Pudunagar, Chennai. 600 101.
45184014 0 48565428 05.02.2010/ 30.6.2010.
13
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
26 RVNL/CPM/MAS/VM-MV/OT-11
18.2.2009 Construction of Service Building, Passenger amenities, General electrical work and other works between Parangipettai and Mayiladuthurai in Southern Railway.
LOA no. RVNL/CPM/MAS/VM-MV/OT-11 dated 25.5.2009
M/S Malathy Constructions, Nellore
35819945 0 42298452 24.11.2009/
31.1.2010/ 31.7.2010
31.10.2010.
27 RVNL/CPM/MAS/VM-MV/OT – 13
09.5.2009 Additional Civil & Electrical works between Villupuram and Mayiladuthurai in Southern Railway.
LOA no. RVNL/CPM/MAS/VM-MV/OT – 13 dt. 16.6.2009
M/S JPC—SRC [JV], No. 21-7-12, Madina Street, Salipetaq, Kakinada – 533 001.
52314592 0 59036022 15.2.2010/ 31.8.2010/ 31.10.2010
28 RVNL/CPM/MAS/ATU-SA/OT-3
25.5.2009
Residual S & T works between Attur and Salem in Southern Railway.
RVNL/CPM/MAS/ATU-SA/OT-3 dated 29.6.2009
Mr. R.V. Abdul Latheef, Railway Contractor, Guruvayr, Kerala.
2495877 0 3868609 28.9.2009/ 31.1.2010/ 31.8.2010.
29 . RVNL/CPM/MAS/OBVP – VKT/OT-3
12.9.2009 Earth work, Bridges and site facilities between new Manubolu station and Venkatachalam Road Junction in SC
LOA no. RVNL/CPM/MAS/OBVP – VKT/OT-3 dated 19.9.2009
M/S Railone – RSV –AVR [JV], H.No. 8-3-833/44 Plot no. 44, Phase I, Kamalapuri
140990079 0 129583753 18.5.2010/ 31.7.2010
14
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
Railway. Colony, Hyderabad – 500 073.
30 RVNL/CPM/MAS/IPL-ICTT/OT-6.
16.6.2009 Provision of Signalling and telecommunication arrangements at Vallarpadam Goods terminal yard, Southern Railway, in Kerala State.
LOA no. RVNL/CPM/MAS/IPL-ICTT/OT-6 dated 1.8.2009.
M/S Abdul Majeed, PB no. 12, Kalpaka, Arakkal Building, PO, Chavakkad, Tiruchur District, Kerala, 680056
18831467 0 24926269 31.1.2010/ 31.5.2010
31 RVNL/CPM/MAS/IPL-ICTT/OT -7
21.7.2009 Linking of Track between Idapalli and Vallarpadam [excluding Idappalli yard and including yard arrangements at Vallarpadam] in Trivandrum division of Southern Railway.
RVNL/CPM/MAS/IPL-ICTT/OT -7 dt.1.8.2009
M/S K.V. AniklKumar & K.V. Baiju [JV] Kodath House, Neduvannoor, Chowara PO, Always. 683 571.
53058301 0 61980207 30.4.2010/ 30.6.2010/ 30.9.2010
15
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
32 RVNL/CPM/MAS/OBVP – VKT/OT-2
25.8.2009 Supply of track materials, linking of track, collection and dumping of ballast, station building [including general electrical works] and Platform works between New Manubolu Station and Venkatachalam Road Junction in South Central Railway.
LOA no. RVNL/CPM/MAS/OBVP – VKT/OT-2 dated 25.9.2009
M/S Mohandoss –K. Dhanasekar [JV], 91, PJN II street, Sholingur road, Arakkonam – 631 001.
65327602 0 71632535 24.5.2010/ 31.8.2010/ 15.10.2010
33 RVNL/CPM/MAS/OBVP – VKT/OT-5
29.8.2009 Design, Supply, erection, testing and commissioning of traction over head equipment, auxiliary transformer stations including modifications to existing OHEs between New Manubolu Station and Venkatachalam
LOA no. RVNL/CPM/MAS/OBVP – VKT/OT-5 dated 29.9.2009
M/S MCML Electrical Systems Pvt., Ltd. – ECI Engineering & Construction Co., Ltd., [JV] 12 SM, KSSIDC Industrical Area, Yelahanka New Town, Bangalore – 560
37724147 0 33790256 28.6.2010
16
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
Road Junction in South Central Railway.
064
34 RFP/PMC/Tunnel/OBVP-VKT/2009.
21.12.2009 Carrying out site investivation, Detailed design and supervision for construction of Road bed including two tunnels [Chainages 18.481 - 19.712 KM and 23.284 - 30.26 KM] Bridges, P.Way, Electrifi9cation of track and S & T works, between chainages 17.1 KM to Chainage 356.00 KM from Nethavaripalli [excl.] to Vellikalluy [excl] section of
LOA no. RFP/PMC/Tunnel/OBVP-VKT/2009 dated 31.5.2010.
M/S AYESA India - Wilbur Smith Associates Inc. [JV] 502, 5
th Floor,
Time Tower, M.G. Road, Gurgaon - 122 001.
-- --0 32 12 01 750
17
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
Obulavaripalle - Venkatachalam new line on South Central Railway in Kadappa/Nellore Districts in the State of Andhra Pradesh [India]
35 RVNL/CPM/MAS/TRL - AJJ/4
th
Line/OT 1
18.6.2010 Construction of Roadbed, Bridges, Supply of ballast, installation of track [excluding supply of Rails and thick web switches], Electrical [Rly. Electrification and General Electrification] Signalling and Telecommunication works in S.Rly, Tamil Nadu.
LOA no. RVNL/CPM/MAS/TRL - AJJ/4
th Line/OT 1 dated
23.7.2010
M/S IVRCL Infrastructures & Projects Limited, MIHIR H no. 8-2-350/5/A/24/1B, Road no. 2, Banjara Hills, Hyderabad - 500 034.
717210381 0 650300055 01.9.2013
18
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
36 RVNL/CPM/MAS/OBVP-VKT/OT-6
06.8.2010 Execution of earthwork information, Bridges, Road under Bridges, Station Buildings, Staff quarters, General electrical works including power line crossings from KM 00 to KM 17 between Obulavaripalle to Nethavaripalle in South Central Railway in Andhra Pradesh.
LOA no. RVNL/CPM/MAS/OBVP-VKT/OT-6 dated 30.8.2010.
M/S BVSR - KVR [JV], 5-8-51/1, Fathe Sultan Lane, Nsampallyt, Hyderabad - 500
787884327 0 598792084 30.8.2012
37 RVNL/Chennai/TRL-AJJ/4th line/PMC
18.8.2010 Project Management consultancy for Construction of Roadbed, Bridges, Supply of ballast, installation of track [excluding supply of Rails and thick web switches], Electrical [Rly. Electrification
LOA no. RVNL/Chennai/TRL-AJJ/4th line/PMC dated 31.8.2010
M/S Theme Engineering Services Pvt.,Ltd. No. 203, Daedu Marg, Barakat Nasgar, Jaipur 302015
-- 0 23560000 31.8.2013
19
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
and General Electrification] Signalling and Telecommunication works in S.Rly, Tamil Nadu.
38 RVNL/CPM/OBVP/NET/PMC.
18.8.2010 Project Management Consultancy for new BG line between Obuluvaripalle and Venkatachalam - Execution of earthwork information, Bridges, Road under Bridges, Station Buildings, Staff quarters, General electrical works including power line crossings from KM 00 to KM 17 between Obulavaripalle to Nethavaripalle in South Central
RVNL/CPM/OBVP/NET/PMC dt. 31.8.2010.
M/S Data Technosys [Engg] Pvt. Ltd. TF-II, Asha Apartments, 19, Rana Mohan Rai Marg, Lucknow - 1.
-- 0 11280000 30.8.2012
20
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
Railway in Andhra Pradesh.
39 RVNL/CPM/MAS/IPL - ICTT/OT-8
29.6.2010 Construction of Inspection platform with hand rails for the elevated structure, provision of guide piles for the navigational channel and pile built up for the future piles in Trivandrum division of Southern Railway -
RVNL/CPM/MAS/IPL - ICTT/OT-8 dt. 14.7.2010
Mr. Anil Kumar, Railway Contractor, Kodath House, Neduvannoor, Chowara PO, Alwaye - 683 571
66448138 0 76415359
21
Details of Contracts/award of tenders by PIU Chennai for the period from 01.10.2005 to 30.10.2010.
Sl.
N
o.
Tender no. Date of
Opening.
Description of
item/work
Contract No. & date.
Contractor’s
name
Qty. [for supply
contract]
Estimated cost
[for
Engg./Elect/S &
T [Mech]
Rate[ for supply
Contract]
Tendered Cost for
Engineering/Elect/
S & T/Mech] in `
Value of
Contract in ` Scheduled
completion date.
40 RVNL/CPM/MAS/DG-VM/Bridges/OT-1
02.09.2010 Execution of major and precast minor Bridges from Villupuram to Ariyalur and form Valadi to Dindigul in Tiruchirapalli Division of Southern Railway.
RVNL/CPM/MAS/DG-VM/Bridges/OT-1 dt. 04.10.2010.
M/S Simplex Infrastructuures Limited, Simplex House, No. 27, Shakespeare Sarani, Kolkatta -700017.
1914797530 0 1683298983 30 months. [3.4.2013]
CPM/RVNL/Chennai
Detail of Contract awarded upto October, 2010 of Project Planning & Development Department
S. No.
Tender No. Date of opening
Description of work/study
Contract No. & date (LOA)
Contractor’s Name
Estimated cost of work
Tendered cost
Value of contract
Scheduled completion date
1 PP&D/RVNL/ HX-SBC/2010
23.08.10 Bankability study for Cuddapah-Bangalore New Line project.
PP&D/RVNL/ HX-SBC/2010 24/09/2010
M/s PricewaterhouseCoopers Pvt. Ltd.
12,89,340/-
Rs. 14,5
0,1
00/-
_
8 weeks from the date of acceptance of CV(06/10/2010) 2/12/2010
2 PP&D/RVNL/ KUR-BOLANGIR/2010
21.09.10 Bankability study for Khurda Road-Bolangir New Line project.
PP&D/RVNL/ KUR-BOLANGIR/2010 04/10/2010
M/S Deloitte Touche Tohmatsu India Pvt. Ltd.
15,00,000/-
R
s.9
,65,1
25/-
_
10 weeks from the date of acceptance of CV(15/10/2010) 25/01/2011)
3. RVNL/PP&D/Babkability/Buramara-Chakulia/10
25/03/10 Bankability study of Buramara-Chakulia New Line with upgradation of Rupsa-Buramara BG Line on SER.
RVNL/PP&D/Babkability/Buramara-Chakulia/10 30/04/2010
M/S Feedback Ventures Pvt. Ltd.
15,00,000/-
Rs.1
3,1
8,0
85/-
_ 3 months from the date of submission of Bank Guarantee (14/05/2010) 15/08/2010 (extended)
4. RVNL/PP&D/Babkability/Nallapadu-Guntakal/RE/10
09/04/10 Bankability study of electrification of Nallapadu-Guntakal section
RVNL/PP&D/Babkability/Nallapadu-Guntakal/RE/10 11/06/2010
M/s PricewaterhouseCoopers Pvt. Ltd
15,00,000/-
R
s.9
,91,5
14/-
_
3 months from the date of submission of Bank Guarantee (25/06/2010) 25/09/2010 (extended)
5. PP&D/RFP/BOT/CONSULT/2009/Pt. II
21.08.10 Project Consultancy services for development of PPP model in Railway projects.
PP&D/RFP/BOT/CONSULT/2009/Pt. II dated: 25.03.2010
M/s. RITES Ltd.
R
s. 15,0
0,0
00/-
_
26 weeks from the date of acceptance of LOA(25/03/2010) 25/09/2010 (extended)
ED/PP&D/RVNL
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 1 between Bina (Incl) to Ganj Basoda (Incl) chainage
975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 2 between GanjBasoda (Excl) to Sanchi (Incl)
chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 3 between Sanchi (Excl) to Habibganj (Incl) chainage
879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. --
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot
No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.11.2010
(extended)
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.08.2010
(extended)
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bi
na- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
Details of Contracts Placed upto the month of Oct' 2010 under GM/P-III
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60 kg
1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.11.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand,
3rd & 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation:
Rs 20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch
60 Kg.
Rs 3.92 Cr 31.12.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 10.09.2010
(extended)
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 31.10.2010
(extended)
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road
projects in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
S.No Tender No. Date of
Opening
Description of Item/Work Contract No. & Date Contractor's Name Quantity (for supply contract)
Estimated Cost (for
Engg./Elect./S&T/Mech.)
Rate (for supply contract)
Tendered Cost (for
Engg./Elect./S&T/Mech.)
Scheduled Completion
Date
1 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 1 between Bina (Incl) to Ganj Basoda (Incl) chainage
975.16 to 928.500 (Km 46.66).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-1 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.--
Rs 141.88 Cr March, 2012
2 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 2 between GanjBasoda (Excl) to Sanchi (Incl)
chainage 928.500 to 879.750 (Km 48.75).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-2 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. Larsen & Toubro Ltd,ECC
Division,Post Box No. 979,Mount
Poonamalle Road,Manakakkam,
Chennai-600089.
--
Rs. 150.05 Cr March, 2012
3 RVNL/P-III/BIN-
BPL/Composite Works
Tender
31.01.2009 Construction of Road Bed, Major and Minor Bridges,
Track Linking (excluding supply of rails, thick web
switches & sleepers), S&T and OHE & General Electrical
work in connection with 3rd
line between Habibganj &
Bina (144.76 Km) on Bhopal Division of West Central
Railway in the state of Madhya Pradesh (India) - Package
No. 3 between Sanchi (Excl) to Habibganj (Incl) chainage
879.750 to 830.850 (Km 48.9).
Notification of Award No.
RVNL/P-III/BIN-
BPL/Composite Works
Tender/Package-3 dated
31.08.2009 (Contract
agreement yet to be
done)
M/s. NCCL-ECIECCL-ARPL (JV),
C/o M/S Nagarjuna Construction
Company Limited,4th Floor, Uma
Enclave, Road No. 9,
HYDERABAD-500034. --
Rs 135.65 Cr March, 2012
4 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches; Lot
No. 31030801
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/Switches dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
1.25 Cr for 60 kg 1 in 12 Switches
and Rs 16.97 Lakh for 60 kg 1 in 8
1/2 Switches & Rs 4.24 Lakh for
52 kg 1 in 8 1/2 Switches.
Transportation: Rs 26.50 Lac for
60 kg 1 in 12 Switches and Rs
4.50 Lac for 52 kg 1 in 8 1/2
Switches & Rs 1.12 Lakh for 60 kg
1 in 8 1/2 Switches.
Rs 1.77 Cr 30.11.2010
(extended)
5 RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing; Lot
No. 31030802
27.06.2008 Manufacture and supply of P.way items for BG (1673mm)
for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/P.way
items/Guntakul-Raichur/1
of 2009/CMS Xing dated
30.03.2009
M/s VAE VKN Industries Pvt.
Ltd., 24/5 Sriram Road, Civil
Lines, Delhi-110054.
Manufacture and Supply: Rs
2.47 Cr for 60 kg 1 in 12 CMS
Crossing and Rs 0.5 Cr for 60 kg 1
in 8 1/2 CMS Crossing.
Transportation: Rs 3.18 Lac for
60 kg 1 in 12 CMS Crossing and
Rs 0.6 Lac for 60 kg 1 in 8 1/2
CMS Crossing.
Rs 3.02 Cr 30.08.2010
(extended)
6 RVNL/Mumbai/Bina-
BPL/ 2006 dated
30.08.2006
30.08.2006 Conducting Final Location Survey (FLS) marking the
center line of the final alignment on the ground and
Detailed Design Engg (DDE) for BG third line between
Bina-Bhopal (138.423 Km) in WC Rly.
RVNL/Mumb/RPS/FLS(Bi
na- BPL)/ 2006 dated
11.12.2006
M/s Monarch Services &
Contractors, Sinhagad Road,
Pune-411030
--- Rs 1.23 Cr 15.08.2010
Details of Contracts Placed upto the month of Nov' 2010 under GM/P-III
7 RVNL/BPL/S&T/HBJ-
BPL-BIN/2
09.06.2009 Supply, installing, modification, testing &commissing of
electronic interlocking system alongwith modification, in
relay based indoor signaling arrangement at PI/RRI/LC
gates, IBH etc. alongwith yard remodeling in connection
with the work of 3rd line between Habibganj & Bina
(144.76 Km) on Bhopal Division of West Central Railway
in the state of Madhya Pradesh (India)
No: RVNL/BPL/S&T/HBJ-
BPL-BIN/2 dated
23.10.2009
M/s Bharat Rail Automations (P)
Ltd. B-107, Mandpeshwar
Industrial Estate, SVP ROAD,
Borivali (W), Mumbai-400092
Signaling & Telecommuction - Rs
23,32,40,706/-
Rs 23.32 Cr 22.10.2011
8 RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for for patch doubling of Guntakul-Raichur Section under
CPM/RVNL/SC
RVNL/P-III/PSC Turnout
Sleeper Set/Guntakul-
Raichur/2009; Lot No.
5030901 dated
13.11.2009.
M/s Patil Rail Infrastructure Pvt
Ltd., The Grand, 3rd & 4th Floor
6-3-1090/B-4 Raj Bhawan Road,
Somaji guda, Hyderabad-500082.
Manufacture and Supply: Rs
3.22 Cr. for PSC Turnout Sleeper
Set for 1 in 12, 60 kg and Rs
52.63 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg .
Transportation: Rs 32.86 Lac for
PSC Turnout Sleeper Set for 60 kg
1 in 12 and Rs 6 Lakh for PSC
Turnout Sleeper Set 1 in 8 1/2 for
60 kg.
Rs 4.14 Cr 30.11.2010.
9 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803
04.09.2009. Manufacture and supply of P.way items for BG (1673mm)
for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120803 dated
17.11.2009
M/s Rayalaseema Concrete
Sleepers Pvt Ltd., The Grand,
3rd & 4th Floor 6-3-1090/B-4 Raj
Bhawan Road, Somaji guda,
Hyderabad-500082.
Manufacture and Supply: Rs
3.34 Cr. for PSC Turnout Sleeper
Set for 1 in 12, and Rs 25.26 Lac
for PSC T/out Sleeper Set 1 in 8
1/2 60 kg & Rs 10.9 lac for PSC
Turnout Sleeper Set for Derailing
Switch 60 Kg, Transportation:
Rs 20.90 Lac for PSC Turnout
Sleeper Set for 60 kg 1 in 12 and
Rs 1.68 Lakh for PSC Turnout
Sleeper Set 1 in 8 1/2 for 60 kg &
Rs 0.84 lac for PSC Turnout
Sleeper Set for Derailing Switch
60 Kg.
Rs 3.92 Cr 31.12.2010.
10 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120801
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120801 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
5.70 Lac for 1 in 8 1/2 52Kg
Curved Switches and Rs 5.10 Lac
for 1 in 81/2 Derailing Switches
52Kg. Transportation: Rs 1.31
Lac for 1 in 8 1/2 52Kg Curved
Switches and Rs 1.08 Lac for 1 in
8 1/2 Derailing Switches
Rs 13.19 Lac 10.09.2010
(extended)
11 RVNL/BPL/Elect/HBJ-
BIN/TSS
23.07.2009 Design, Supply, Erection, Testing & commissioning of
132/25 KV Traction Sub-station, Feeding Post, Fixed
Capacitor, bank System & other associated works at
BARETH & SANCHI, TRACTION SUB STATIONS,
Augmentation & replacement of traction transformers AT
BINA TSS, by providing 3rd bay & modification in existing
Feeding Posts at Sukhisewania, Gulabganj in connection
with Electrification of 3rd line on BINA- BHOPAL section
of BHOPAL DIVISION of WCR.
RVNL/BPL/Elect/HBJ-
BIN/TSS
dated18/19.01.2010
M/s S. L. Enterprises 41-A,
Phase-II, Mayapuri Industrial
State, Delhi-110064
Electrical Items-Rs 3.89 Cr for
CORE SOR Items, Rs 11.36 Cr for
Traction Transformer, Rs 0.12 Cr
for Maintenance spares,Rs 0.09
Cr for Maintenance Tools, Rs 0.35
Cr for Site Facilities & Rs 2.65 Cr
for Misc. Items,etc.
Rs 18.47 Cr 18.01.2012
12 RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No. 11120802
04.09.2009. Manufacture and supply of P.way items for BG
(1673mm)for Salka Road- Anuppur Section under
CPM/RVNL/Bilaspur.
RVNL/P-III/P.way
items/Salka Road-
Anuppur/2 of 2009; Lot
No.11120802 dated
18.11.2009
M/s Hindustan Engg. & Industries
Ltd., Mody Building, 27, Sir RN
Mukherji Marg, Kolkata-700001.
Manufacture and Supply: Rs
2.33 Cr for 60 Kg CMS Crossing 1
in 12, and Rs 17.75 Lac for 52 Kg
CMS Crossing 1 in 81/2
Transportation: Rs 2.53 Lac for
60 Kg CMS Crossing 1 in 12, and
Rs 0.24 Lac for 52 Kg CMS
Crossing 1 in 81/2.
Rs 2.53 Cr 31.10.2010
(extended)
13 RVNL/New Delhi/B-B-
H/PMC/Pt-II
15.10.2009 Project Management Consultancy forConstruction of
Road Bed, Major and Minor Bridges, Track Linking
(excluding supply of rails, thick web switches & sleepers),
S&T and OHE & General Electrical work in connection
with 3rd line between Habibganj & Bina (144.76 Km) on
Bhopal Division of West Central Railway in the state of
Madhya Pradesh (India)
Notification of Award No
RVNL/New Delhi/B-B-
H/PMC/Pt-II dated
23.03.2010
M/s Aarvee Associates
Architects, Engineers &
Consultants Pvt Ltd, Ravula
Residancy, Srinagar Colony,
Hyderabad-82.
Renumerations for -Rs 6.57 Cr
for staff & Provision &
maintenance of Office for- Rs
2.70 Lacs.
Rs 6.60 Cr 22.10.2012
14 No. RVNL/P-
III/TWS/2009/Pt I
25.02.2010 Manufacture and Supply of Curved Switches with ZU-
1–60/60E1A1 Thick Web Tongue Rail and UIC 60 (880
Grade) Stock Rail conforming to Indian Railway
Specifications IRS-T-10-2000 for various rail road
projects in different regions of India.
Notification of Award No
No. RVNL/P-
III/TWS/2009/Pt I
Dated 26.05.2010
M/s VAE VKN RTT (JV),
Century Towers,
5th Floor,
45 Shakespeare Sarani,
Kolkata. - 700 017
Manufacture and Supply: Rs
17.79 Cr for 60 kg 1 in 12 TWS
Transportation: Rs 36.84 Lac for
60 kg 1 in 12 TWS.
Rs 18.16 Cr 25.05.2011
Details of Contracts awarded with respect to RVNL/PIU/Bilaspur as on 31.12.2010
Tender
Number
Date of
Opening
Description of Item/Work Contract No
& date of
award
Contractor’s
Name
Quantity (for
supply
contract)
Estimated
Cost (for
Engg./Elect./
S&T/ Mech.)
Rate (for supply
contract)
Tendered Cost
(for Engg./Elect./
S&T/ Mech.)
Value of
Contract
Scheduled
Completion
date
RVNL/Raipu
r/SA -KH-
KHD-
ANP/5
Dt. 6/10/07
29.11.07 Construction of Road bed, Major & Minor
Bridges and Track linking (excluding supply of
Rails and Sleepers, Thick Web Switches and
special Sleepers) S&T and OHE & General
Electrical Work in connection with Doubling
between Salka Road- Khongsara (25.8 Km)
and Khodri-Anuppur (61.6 Km) on Bilaspur
Division of South East Central Railway in
Chhattisgarh and MP State, India.
RVNL/Raipur/
SA -KH-KHD-
ANP/ 5
Dt. 15/04/08
M/s DS
Constructions
Ltd, Best &
Crompton
Engineers Ltd.
(JV), C-66,
South
Extension-11,
New Delhi –
110049.
170.12 Cr. 177.498 Cr 177.498 Cr 30.05.2010
Extended
up to
30.06.2011
2008/RVNL/
Bilaspur/DR
Z-RGH
Dt.30.06.08
12.08.08 Conducting Final Location Survey, marking
centre line for Final Alignment on ground,
Design detailed Engineering, preparation of
Drawings and approval from RVNL/Railway for
doubling of Dallirajhara-Rowghat New Rail
link (95.00 Km) on Raipur Division of
S.E.C.Railway.
CPM/RVNL/BS
P/DRZ-
RGH/FLS/01
Dt.23.09.08
M/s Balaji Rail
Road Systems
Ltd, Plot No. 3,
Sitaram Nagar,
Staff Road,
Near Diamond
Point,
Secunderabad
500009
0.9022 Cr. 0.9497Cr 0.9497Cr 15.02.2009
extended up
to 31.12.10
2009/RVNL/
Bilaspur/DR
Z-ROW/02
Dt.12.03.09
16.06.09 Construction of Road bed, supply of ballast,
major & minor bridges, Residential and
service buildings & general electrical work etc.
, for Dallirajhara-Keoti section( 42 Kms) in
connection with a new rail link between
Dallirajhara and Rowghat in Raipur Division of
S.E.C.Railway in the state of Chhattisgarh
( India).
CPM/RVNL/BS
P/DRZ-
Keoti/SMS/73
6 Dt.20.10.09
M/s SMS
Infrastructure
Limited- 267
Ganesh
Phadnavis
Bhavan, Near
Triangular
Park,
Dharampeth,
Nagpur
440010
115.629 Cr 97.815 Cr. 97.81Cr. 09.06.2012
(30 months
including
Defect
Liability
Period of 6
Months)
RVNL/Raipu
r/SA-KH-
KHD-ANP/
PMC-2
dtd.19.11.0
7
21.12.07 Project Management Consultancy (PMC) for
Construction of Roadbed, Major and Minor
Bridges, Track Linking (excluding supply of
rails, sleepers, thick web switches & special
sleepers), S&T, and OHE and General
Electrical work in connection with doubling
between Salka Road- Khongsara ( 25.8 Km)
and Khodri- Anuppur (61.6 Km) on Bilaspur
Division of South East Central Railway in
Chhattisgarh & M.P. State ( India).
RVNL/Raipur/
SA-KH-KHD-
ANP/ PMC-2
dtd.29.04.08
M/s S.N.Bhobe
& Associates
Pvt.
Ltd,Banking
Complex No. II
Unit
No.10,Plot No.
9 & 10, Sector-
19A,Vashi,
Navi Mumbai-
400 705
NIL 3.34 Cr. 3.34 Cr. 23.12.2010
(30 months
including
Defect
Liability
Period of 6
Months)
Extended up
to
Dt.30.06.11.
RVNL/Bilasp
ur/DRZ-
ROW/PMC-
2/ dt. 21-
09-09
01.12.09 Project Management Consultancy (PMC)
tender for “CONSTRUCTION OF ROADBED,
SUPPLY OF BALLAST, P-WAY, MAJOR &
MINOR BRIDGES, RESIDENTIAL AND SERVICE
BUILDINGS, SIGNAL AND TELECOM &
ELECTRICAL WORK ETC., FOR DALLIRAJHARA –
ROWGHAT NEW RAIL LINK PROJECT IN
RAIPUR DIVISION OF SOUTH EAST CENTRAL
RAILWAY IN THE STATE OF CHHATTISGARH,
INDIA”
CPM/RVNL/BS
P/DRZ-
ROW/PMC(Te
nder)/1529
Dt.28.07.10
M/S Lion
Engineering
Consultant &
M/S
Consulting
Engineers
Group Ltd (JV),
Home No.14,
Deepak
Society,
Chhunna
NIL 3.0285 Cr 3.0285 Cr 13.09.2013
(36 months
including
Defect
Liability
Period of 6
Months)
DGM/P-I/RVNL/BSP
Bhatti, Kolar
Road, Bhopal
(MP)
2006/RVNL/
Raipur/Anu
ppur-
Bilaspur/3
Dt.22.11.06
04.01.07 Conducting Detailed Designing Engineering (
Civil, P.Way and Electrical Engineering), Yard
Drawings, Preparation of LOP Assistance in
land acquisition and forest clearances,
Detailed Construction Estimate and BOQ for
Doubling between Khodri-Anuppur (61.6Km)
and Salka Road-Khongsara (25.8KM) on
Bilaspur Division of South East Central
Railway.
CPM/RVNL/
Raipur/ Salka
Road-Annupur
Dt.16.01.07
M/S Monarch
Surveyors &
Contractor
Pvt. Ltd. Of 67,
Rujeta Appt.
Panmala,
Pune-30.
Rs.
57,30,000/-
Rs. 52,14,300/- Rs.
52,14,300/-
16.05.2007
Extended up
to 30.09.10
grant of
extension
under
process
upto
31.03.11
2006/RVNL/
Mumbai/
Bilaspur
Yard/ Fly
Over/04
Dt.23.11.06
04.01.07 Conducting Confirmatory Final Location
Survey (FLS) of Fly Over at Bilaspur yard and
making the centre line of final alignment on
the ground for BG double line conforming to
the standards of a Group A on FLYOVER and
at its approaches in connection with doubling
of Bilaspur-Anuppur section along with
Detailed Designing of (Civil, P.Way, and
Electrical Engineering) aspects, preparation of
Bill of Quantities including land acquisition on
SEC Railway.
CPM/RVNL/
Raipur/Salka
road-Anuppur
Dt.16.01.07
M/S Monarch
Surveyors &
Contractor
Pvt. Ltd. Of 67,
Rujeta Appt.
Panmala,
Pune-30.
Rs.
19,48,400/-
Rs. 18,12,012/- Rs.
18,12,012/-
30.03.07
Extended up
to 30.09.10
grant of
extension
under
process
upto
31.03.11