stybarrow subsea & fa for subsurface grp
DESCRIPTION
FA and subsea study for StybarrowTRANSCRIPT
-
STYBARROW EXECUTION PHASE
SUBSEA & FLOW ASSURANCE OVERVIEW for information only information may not be latest
-
AOAT21 April 2005Page 2
Revised Stybarrow Subsea Configuration
-
AOAT21 April 2005Page 3
Flowline Sizing: Stybarrow Production Flowlines A paired 8 flowline from H3 and H4 is specified, with a design liquids rate of
35000 bpd. Minimum turndown for stable flow from these wells is ~13500 blpd. A paired 7 flowline from H1 and H2 is specified, with a design liquids rate of
25000 bpd. Minimum turndown for stable flow from these wells is ~6000 blpd. The paired flowline configuration for the Stybarrow production wells is required to
allow hot oil circulation to warm the flowlines prior to restart. This minimises the volume of MeOH required to inhibit hydrates on restart (see later).
Insulation of 5.5W/m2K is specified for the Stybarrow production flowlines to achieve an 8 hour no touch cooldown period.
Ramp up rates are limited by sand control considerations only. Some ramp up slugging is evident, but this is within the surge capacity of the Test and HP separators.
-
AOAT21 April 2005Page 4
Stybarrow flowlines gas and liquid rates early life (~yr 1)STYBARROW H2 EARLY RISER TOP GAS AND LIQUID RATES
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
10 10.5 11 11.5 12
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H1 EARLY RISER TOP GAS AND LIQUID RATES
0
5000
10000
15000
20000
25000
2 2.5 3 3.5 4 4.5 5 5.5 6 6.5
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
12.6
12.8
13
13.2
13.4
13.6
13.8
14
14.2
14.4
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H3 EARLY RISER TOP GAS AND LIQUID RATES
0
5000
10000
15000
20000
25000
30000
35000
40000
1 2 3 4 5 6
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H4 EARLY RISER TOP GAS AND LIQUID RATES
0
5000
10000
15000
20000
25000
30000
35000
40000
1 2 3 4 5 6
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
-
AOAT21 April 2005Page 5
Stybarrow flowlines gas and liquid rates mid life (~yr 3)STYBARROW H1 MID RISER TOP GAS AND LIQUID RATES
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
1 2 3 4 5 6
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H2 MID RISER TOP GAS AND LIQUID RATES
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
10 11 12 13 14 15
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H3 EARLY RISER TOP GAS AND LIQUID RATES
0
5000
10000
15000
20000
25000
30000
35000
40000
1 2 3 4 5 6
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H4 M ID RISER TOP GAS AND LIQUID RATES
0
10000
20000
30000
40000
50000
60000
1 1.5 2 2.5 3 3.5 4 4.5 5
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
5
10
15
20
25
30
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
-
AOAT21 April 2005Page 6
Stybarrow flowlines gas and liquid rates late life (~yr 8+)STYBARROW H1 LATE RISER TOP GAS AND LIQUID RATES
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
6 6.5 7 7.5 8 8.5 9 9.5 10
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H2 LATE RISER TOP GAS AND LIQUID RATES
0
5000
10000
15000
20000
25000
30000
1 1.5 2 2.5 3
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H3 LATE RISER TOP GAS AND LIQUID RATES
0
5000
10000
15000
20000
25000
30000
35000
40000
1 2 3 4 5 6
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
2
4
6
8
10
12
14
16
18
20
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
STYBARROW H4 LATE RISER TOP GAS AND LIQUID RATES
0
10000
20000
30000
40000
50000
60000
70000
5 5.2 5.4 5.6 5.8 6 6.2 6.4 6.6 6.8 7 7.2 7.4 7.6
Time (hours)
L
i
q
u
i
d
s
r
a
t
e
(
b
l
p
d
)
0
5
10
15
20
25
30
G
a
s
R
a
t
e
(
M
M
s
c
f
d
)
Liquid flow rate at riser top Gas flow rate at riser top
-
AOAT21 April 2005Page 7
Flowline Sizing: Stybarrow Gas Lift Flowline The gas lift flowlines have been sized for a gas flow rate of 35 MMscfd to H3 and
H4 and then for 21 MMscfd from H3/H4 to H1/H2. A 4inch flowline from the riser base to Sty H3/H4 and on to Sty H1/H2 is
required. A 6inch riser is specified. For a gas lift compressor discharge pressure of 200 bara, the pressure at H3/H4
wellhead is 193-198 bara, and 183-194 bara at H1/H2 wellhead. The minimum gas lift rate for flow stability is ~2MMscfd
-
AOAT21 April 2005Page 8
Flowline Sizing: Eskdale Gas Injection Flowline A 6-inch riser and flowline for gas injection to Eskdale is specified. For a gas injection compressor discharge pressure of 280 bara (4060 psia), the
pressure at the injection wellhead is 296 bara (4298 psia). This exceeds the advised required injection pressure of 276 bara (4000 psia) at the wellhead.
The design flowrate of the gas injection flowline is 36MMscfd
GI Riser/Flowline Profile Pressure Profile
-
AOAT21 April 2005Page 9
Flowline Sizing: Stybarrow Water Injection Flowline Fracture pressure injection has been selected as the base case for water
injection based on the results of the injectivity studies. The required water injection pressure at the reservoir is;
For 25,000 bwpd to I1 with I2/I3 shut in, minimum 383 bara at I1 injection point For 110,000 bwpd total to I1/ I2 and I3, minimum 338 bara at any of the
injection points. The water injection system comprises a 10inch riser, a smooth bore 9 flowline to
I2 with an 9 jumper between I2 and I3, and a 6 flowline to I1. For the selected flowline configuration
The required topsides discharge pressure to flow 25,000 bwpd to I1 at an injection pressure of 383 bara is 185 bara.
A topsides pressure of 170 bara will provide 360 and 358 bara pressures at I1 and I2/I3 respectively.
The water injection pump has been specified with characteristics of a 200 bara(2900 psia) discharge pressure @ 25,000 bwpd and 170 bara discharge pressure at 110,000 bwpd.
-
AOAT21 April 2005Page 10
Flow Assurance IssuesISSUE PREVENTION MITIGATION REMEDIATION
Hydrates Insulation for steady state. CI for Eskdale Prod well.
Hydrate inhibitor injection during transient events (startup / shutdown).
Circulation of non-hydrating (stabilised crude oil) fluid to displace FWS fluid and warm flowline for start-up for Sty wells.
Blowdown and possibly flushing.
Hydrate inhibitor injection. MeOH
Blowdown from both sides of blockage.
Methanol injection to melt hydrate.
Pigging & flushing with non -hydrating fluid. Dead Crude
Sand Downhole sand control Ensure erosionalvelocities not exceeded
Provision for sand production monitoring and handling equipment on topsides
Asphaltenes Asphaltene risk considered low. Downhole CI not provided.
Well workover, chemical soak.
Scale Scale inhibitor injection at subsea tree.
Emulsions Continuous injection of demulsifier (at well/manifold).
-
AOAT21 April 2005Page 11
Hydrate Management: Stybarrow Production FlowlinesSHUTDOWN 8 hour no touch time on shutdown is achieved by flowline insulation Blowdown to the FPSO is required if start-up within 8 (4) hours cannot be achieved. The residual pressure at the wellhead is between 3 and 9 bara after blowdown. Batch MeOH injection into the tree and uninsulated piping between the tree and flowline
will be required for all production wells on shutdown. This should be carried out as soon as practical after the well is shut in.
Methanol injection into the well bore is required for shutdowns >8hours. Delayed SSSV closure to allow draining of fluids below SSSV is being considered.
START-UP Hot oil circulation will be used to warm the flowlines above the hydrate formation
temperature prior to restart of the production wells. Batch MeOH injection into the wellbore prior to restart (if not injected on shutdown). MeOH injection required for SSSV equalisation required if SSSV is closed. MeOH injection at tree during first 20-30mins of flow until well fluids are warmed as
indicated on the tree temperature monitoring may be required for shutdowns >2weeks.NORMAL OPERATION No continuous MeOH injection is required for Stybarrow.
-
AOAT21 April 2005Page 12
Hydrate Management: Eskdale Production and Gas Injection, and Stybarrow Gas Lift FlowlinesESKDALE PRODUCTION FLOWLINE High GLR makes the use of insulation to prevent flowline operation within the
hydrate formation region impractical. Insulation specification allows 2-3 hour period between shutdown and blowdown. Continuous MeOH injection at the well head is proposed. Alternatives to MeOH
(eg LDHIs) to be investigated during operations phase. Condensed water only is predicted during early years of operation. Free water
production is evident in late life.
GAS LIFT and GAS INJECTION FLOWLINES Gas will be dehydrated to a water dewpoint of -1degC at 300 bar at topsides. If glycol dehydration unit is unavailable or off-spec MeOH injection into the gas
compressor discharge lines will be utilised to inhibit condensed water. Provision for MeOH injection at the GI tree for use during backflow of gas for fuel
gas or well kickoff.
-
AOAT21 April 2005Page 13
Stybarrow Field Layout and Flowline Lengths
-
AOAT21 April 2005Page 14
Stybarrow Drill Centre A Water Injection I2, I3
Water Injection
10 riser
6 flowline to I1
9 smooth bore flowline to I2, I3
9 30m jumper between I2,I3
Future WI flowline will tie into I3
-
AOAT21 April 2005Page 15
Stybarrow Drill Centre B I1, H3, H4Production
8 flowlines to H3, H4
8 30m jumper between H3,H4 with isolation valve on each tree
4 gas lift to H4, then through tree to H3.
4 Gas lift flowlinecontinues to H1 and H2
-
AOAT21 April 2005Page 16
Stybarrow Drill Centre C H1, H2Production
7 flowlines to H1, H2
7 30m jumper between H1,H2 with isolation valve on each tree
4 gas lift to H2, then through tree to H1.
-
AOAT21 April 2005Page 17
Stybarrow Drill Centre D Esk H1, Esk I1Eskdale
4 flowline to Esk H1 (riser is 6)
4 30m jumper between production and injection trees.
6 gas injection flowline(and riser) to Esk I1.
-
AOAT21 April 2005Page 18
STY, ESK PROD TREEAAV
PMV PWV PCAWV
GLC
XOV
AMV
CIV1 CIV2 CIV3
Position TBD
Tree Frame
FIVProduction 8"
e.g. Scale Inhibitor 1/2" ID
e.g. Demulsiifier 1/2" ID
MeOH 1" ID
Annulus / Gas Lift 4"
SCSSV
DHPT
TT
PT
PT
PT
XSD
ZT
PT
TT
ZT
Subsea sand detectors installed on each tree
SSSV to be 400m below mudline to avoid hydrate formation in Stybarrow wells, and 500m below the mudline for the Eskdale wells
Non self-equalising SSSVsselected. This will require methanol injection for pressure equalisation prior to opening on restart.
Demulsifier, scale inhibitor and methanol to be injected at tree.
-
AOAT21 April 2005Page 19
ESK GI TREEAAV
PMV PWV PCVAWV
XOV
AMV
CIV1
Tree Frame
Injection / Production 8"
MeOH 1/2" ID
Annulus 4"
SCSSV
DHPT
TT
PT
PT
ZT
PT
TT
Upstream and downstream choke pressure and temperature monitoring and choke position provided.
Flow measurement at topsides
Annulus pressure monitoring
Downhole pressure monitoring
-
AOAT21 April 2005Page 20
STY WI TREEAAV
IMV IWV
ICV
XOV
AMV
Water Injection 8"
SCSSV
(Well I-1 only)
PTPT
PT
ZT
DHPT
Upstream and downstream choke pressure plus choke position monitoring provided.
Total water injection flow is measured topsides.
Annulus pressure monitoring provided.
Downhole pressure monitoring on I1 only
STYBARROW EXECUTION PHASERevised Stybarrow Subsea ConfigurationFlowline Sizing: Stybarrow Production Flowlines Stybarrow flowlines gas and liquid rates early life (~yr 1)Stybarrow flowlines gas and liquid rates mid life (~yr 3)Stybarrow flowlines gas and liquid rates late life (~yr 8+)Flowline Sizing: Stybarrow Gas Lift Flowline Flowline Sizing: Eskdale Gas Injection FlowlineFlowline Sizing: Stybarrow Water Injection FlowlineFlow Assurance IssuesHydrate Management: Stybarrow Production FlowlinesHydrate Management: Eskdale Production and Gas Injection, and Stybarrow Gas Lift FlowlinesStybarrow Field Layout and Flowline Lengths Stybarrow Drill Centre A Water Injection I2, I3Stybarrow Drill Centre B I1, H3, H4Stybarrow Drill Centre C H1, H2Stybarrow Drill Centre D Esk H1, Esk I1STY, ESK PROD TREEESK GI TREESTY WI TREE