strengthening public financial management (pfm) system...
TRANSCRIPT
1
Strengthening Public Financial Management (PFM) System Project (TF 010452)
Implementation Review and Support Mission
December 14-18, 2014
Aide Memoire
I. Introduction
1. A World Bank (WB) team1 led by Mr. Manoj Jain (Lead Financial Management Specialist)
was in Kathmandu, Nepal during December 14-18, 2014 to conduct an Implementation Review and
Support Mission of the Strengthening Public Financial Management (PFM) System Project and also
prepare an Additional Financing (in response to a Government of Nepal request letter dated June 10,
2014) for USD 3.5 million.
2. The team met with the Financial Comptroller General, senior officials of the Financial
Comptroller General’s Office (FCGO) and officials of the Public Expenditure and Financial
Accountability (PEFA) Secretariat. A list of the persons met is included in Annex 1.
3. The team expresses its appreciation for valuable inputs, courtesies and cooperation extended
by officials met during the review. A wrap up meeting was held on December 18, 2014 which was
chaired by the Financial Comptroller General. This Aide Memoire (AM) summarizes the agreements
reached as discussed during the mission. As agreed during the wrap-up meeting, this AM will be
classified as a public document as per the World Bank’s Access to Information Policy.
II. Key Project Data
III. Achievement of Project Development Objective
4. The Project Development Objective (PDO) is to improve expenditure control and enhance
government accountability and transparency by strengthening the treasury system, improving
financial reporting and building PFM capacity. The team assessed the relevance of the PDO and
confirmed that it still remains relevant. The Results Framework however needs to be slightly refined
to appropriately capture the outputs and results that are likely to be obtained under the components of
the project, and to appropriately reflect the revision in implementation strategy for certain activities
under the project. Revised Results Framework will be finalized by February 2015. The achievements
of PDO level results as at November 30, 2014 is shown below :
1 The team was led by Mr. Manoj Jain (Lead Financial Management Specialist and Task Team Leader) and comprised of Mr. Anand
Pardhy (IT consultant), Mr. Shambhu Uprety (Procurement Specialist), Mr. Yogesh Malla (Financial Management Specialist), Ms.
Pragya Shrestha (Operations Analyst) and Mr. Nagendra Nakarmi (FM Assistant).
Project Data Projects Performance Ratings
Approval Date : October 31, 2011 Summary Ratings
Achievement of PDO
Implementation Progress
Monitoring & Evaluation
Project Management
Procurement
Financial Management
Counterpart funding
Last Now
S S
S S
S S
S S
S S
S S
S S
Effectiveness Date: October 31, 2011
Closing Date: June 30, 2015
Grant Amount : USD 4,300,000
Amount Disbursed
(As of December 31, 2014)
USD 4,192,140 (97.5%)
including advance of
USD 1.33 MN
Ratings: HS=Highly Satisfactory; S=Satisfactory; MS = Moderately Satisfactory; MU = Moderately Unsatisfactory;
U=Unsatisfactory; HU=Highly Unsatisfactory
2
Indicators Unit of Measurement Baseline
Year 3
Target
End-of-Project
Target
Status as of November
30, 2014/ Comments
PDO Level Results Indicators*
Percentage of overall budget
executed through the DTCOs
where the TSA system has been
implemented
% 7 85 98
Nearly 100%. Target
was achieved a year in
advance
Budget Execution Reports and
Financial Statements produced
by the TSA system on a real
time basis
No of districts Nil 65 75
For all 75 districts.
Quality and Timeliness
being improved upon
further.
Preparation of consolidated
financial statements for PILOT
Ministries in accordance with
Part 1, Cash IPSAS ; No Nil 1 2
Both the pilots have
been completed in
August 2014 (end of
project target already
achieved) and results
being analyzed to
upscale under additional
financing2.
Numbers of research studies into
high priority PFM areas
completed and disseminated No Nil 4 5
Two Reports
completed. Another five
are proposed in this
fiscal year which will
be completed by April
2015
The detailed component wise targets for year 3 (FY2013/14), end-of-project targets and current status
as of November 2014 are set out in Annex 5.
5. Remarkable Achievements: Rollout of the Treasury Single Account (TSA) under the
component 1 continues to be hallmark of the project with rollout having been achieved across all 75
districts across Nepal leading to 100% coverage of the budget. Real time budgetary expenditures is
now available to all stakeholders through the website of the FCGO which is having tremendous
impact on the decision making behaviors of the line managers, and has helped improve the
transparency in public finances.
6. Successful implementation of TSA and its results are clearly evident in the entire PFM cycle
and upgrade in several of (draft) PEFA II ratings is a testimony to this effect. Monthly budget
executions reports (Ministry wise, Spending District wise, Economic Classification wise) have been
further strengthened and are available on a timely basis, and posted on FCGO’s website. Daily reports
on aggregate budget implementation are also made available on the website and visual media (LED
CTVs) located at strategic locations. Further plans are being made to enhance the usefulness of
reports and strengthening accountability by reaching out to other stakeholders including demand side
such as CSOs and media.
7. Following recommendations from an international expert, business process for commitment
recording has now been finalized, TSA software upgraded and implementation has been initiated.
Following recommendation of a task force comprising of officials from FCGO, Nepal Rastra Bank
(NRB) and commercial banks, business process in respect of Revenue Management Information
Systems (RMIS) has been configured, software enhancement completed and pilots undertaken in three
large revenue receiving districts (Kathmandu, Lalitpur and Bhaktapur). License for Oracle has been
acquired and put into effect. Accounting Standards Board (ASB) successfully drafted the Nepalese
Financial Reporting Standards (modeled on International Financial Reporting Standards) after an
extensive consultative process, and the Institute of Chartered Accountants of Nepal (ICAN) has now
pronounced these standards with a road map for implementation. Nepal Public Sector Accounting
Standards (NPSAS) pilots in line departments have been successfully completed (award received by
2 International Consortium for Government Financial Management (ICGFM) has certified these financial statements in December, 2014.
3
GoN in this respect from International Consortium of Government Financial Management) and a
senior policy level workshop conducted to chalk out a strategy for a way forward.
8. Substantial efforts continued to be made under the third component in reaching out to the
various stakeholders across the country to more remote districts, demand side stakeholders, line
departments and general public in increasing PFM awareness and building a solid foundation for
ensuing PFM reform processes. Research work has been initiated in five high priority areas which
will be completed by April 2015. After an extensive consultation amongst several stakeholders,
second Public Expenditure and Financial Accountability (PEFA) Assessment for Nepal has been
finalized and is undergoing a final quality assurance and PEFA check (final report likely to be issued
shortly). Although the procurement of consultants for accounting manual has been completed, the
report is delayed and likely to be ready by April 15, 2015.
9. Financial Management and Disbursement: In FY2013/14, the expenditures incurred under
this project were NPR 127.09 million (75.31% of the approved budget). For FY2014/15, the approved
budget is NPR 195.19 million. The Team noted that the budget for counterpart fund is found to be
sufficient. As of December 31, 2014, the Project has disbursed USD 4.19 million, which is about
97.5% of allocated funds. There are no pending audit reports or audit issues. The review team
reminded that the audit report for FY2013/14 is due on January 15, 2015. Based on its progress, the
FM Performance is retained as ‘Satisfactory’.
10. Procurement: The Bank team reviewed the implementation status of the procurement plan.
Almost all of the planned procurement activities are being implemented satisfactorily. With regard to
the preparation works for the proposed Additional Financing, it has been agreed with the PEFA team
that procurement plan will be submitted to the Bank by February 15, 2015 and this will be entered
into the online SEPA system (Online Procurement Management System) for which the Bank
procurement team will provide necessary training. Considering the overall procurement progress
achieved, procurement performance rating has been retained as “Satisfactory”.
11. In view of the remarkable progress observed, the Implementation Progress is retained as
“Satisfactory”. The PDO still remains fully achievable and therefore “Achievement of PDO” is also
retained as “Satisfactory”. More detailed component wise implementation progress and agreements
reached during the review is provided in Annex 2.
IV Proposal for Restructuring of Ongoing project
12. The government made a request to reallocate savings of USD 0.5 million from component 2
to component 1, refine the Results Framework and extend the closing date of ongoing project by two
years. For this, FCGO and PEFA Secretariat prepared a detailed activity wise plan for each
component which will require additional time. The team assessed the plan along with the need for
extension during the review; and agreed that the project will be restructured to extend the closing date
by one year
13. The team has reviewed a detailed line item wise activity based plan for both existing project
and proposed AF, and noted that several activities/procurements to be initiated are contiguous and
will require finance both from existing project and AF proceeds to be able to undertake the activity on
a seamless basis for achievement of the objectives.
14. This will allow several activities which are complimentary in nature between the original
project and the proposed additional financing to continue alongside and help achieve the PDO. The
extension will also allow the government to complete the original scope of project activities in a
satisfactory manner. The table below depicts that there is a need to reallocate USD 0.5 million from
component 2(b) to Component 1 which shall be undertaken along with the processing of the AF
request.
4
Status of Project Cost as on December 18, 2014
Category Category
Description
Allocated
USD (A)
Disbursed
USD
Amt. yet to
be
documented
USD
Total as of
December 18,
2014 USD
Planned up
to extended
closing date
June 30,
2017 USD
Grand
Total
(Actual+
Planned
Exp.) USD
(B)
Balance
(A-B)
requiring
reallocation
1
Gd, CS, Trg
& Wksp, St
& OC under
Part 1
2,800,000 1,922,502 527,150 2,449,652 850,348 3,300,000 (500,000)
2
Gd, CS, Trg
& Wksp, St
& OC under
Part 2A
170,000 76,280 0.00 76,280 93,720 170,000 (0)
3
Gd, CS, Trg
& Wksp, St
& OC under
Part 2B
580,000 25,080 6,495 31,575 48,425 80,000 500,000
4
Gd, CS, Trg
& Wksp, St
& OC under
Part 3
750,000 172,591 130,530 303,121 446,879 750,000 0
Total 4,300,000 2,196,453 664,175 2,860,628 1,439,372 4,300,000 0.00
IV Proposal for Additional Financing
15. In addition to the request for extending the closing date and reallocation of categories in the
ongoing project, the government also submitted a request for additional financing for USD 3.5
million. The Project Development Objective (PDO) of AF would remain unchanged that is, “to
improve expenditure control and enhance government accountability and transparency by
strengthening the treasury system, improving financial reporting and building PFM capacity”.
16. The original scope under component one involved implementation of the Treasury Single
Account, roll-out of FMIS and further enhancement of the FMIS to support commitment accounting
and improved financial reporting - aimed at strengthened expenditure controls and enhanced
transparency. For practical reasons, an iterative and incremental implementation approach was
adopted to achieve the above objectives where the government agreed to implement reforms in small
increments by learning from the previous iteration. Using this approach, first emphasis was on
implementing expenditure Treasury Single Account which has successfully been rolled out in all 75
districts, centralizing the payments through DTCOs by closing more than 14,000 bank accounts and
eliminating idle cash balances.
17. However, this iteration did not involve full implementation of two major activities of the
original scope: revenue TSA and commitment controls. These activities are now being piloted and
will be fully implemented under the proposed funding through additional financing. The government
plans to complete these reforms through AF component 1 and consolidate the TSA rollout by making
appropriate investment in IT equipment, hardware, networking and associated peripherals to enhance
the sustainability of the TSA system.
18. Under component 2, NPSAS pilots have been successfully undertaken in two ministries and
now the government is planning for up-scaling this rollout across all ministries. For this consultancy
support and necessary training/capacity building activities will be required. A practical rollout plan
will need to be drawn up which will take into account learnings from the previous pilot. An updated
note along with a rollout plan in this regard will be prepared by FCGO and shared with the Bank by
January 15, 2015.
19. Under Component 3, several achievements have been made by the PEFA Secretariat as
described in para 8. There is a need to continue to undertake the outreach, awareness, communication,
5
training, research and capacity building activities to support PFM reform in Nepal. In addition, the
proposed AF under this component will also help support build national PFM training and capacity
building capabilities by partnering with a local academic pioneer institution (like Nepal
Administrative Staff College) and working on developing a PFM core curriculum for public sector
practitioners. A strategy note in this respect will be prepared by the PEFA Secretariat and shared with
the Bank by January 15, 2015.
20. Due to change, management challenges involved in successful accomplishment of these
activities, the government anticipates a slower progress compared to the earlier rapid implementation
of the expenditure TSA, and therefore, has requested a period up to June 30, 2017 for AF. Further
Details in respect of additional financing are provided in the Annex 4.
21. The Program Coordination Committee (PCC) meeting of the MDTF has already endorsed the
above request in September 2014 in recognition of remarkable achievements made under the ongoing
project and the need for further building upon the success. The team will proceed to prepare the
additional financing, restructure the ongoing project for revising the Results Framework, for
reallocating the category and for extending the closing date by one year. Following critical actions
have been agreed to be completed prior to the appraisal of the proposed additional financing:
By February 15, 2015, FCGO to submit to the Bank for review the revised cost
estimates (along with procurement plan); and
By March 15, 2015, FCGO will create senior level IT position (Deputy FCG level) and
initiate process for hiring additional identified consultant positions (detailed in attached
aide memoire).
V. Project Cost
22. Tentative Allocation of Project Costs along with AF and Reallocation of Categories: The
AF aims to support all components under the Project (although majority will be allocated towards
component 1) and the closing date for ongoing project will be extended up to June 30, 2016 to
undertake all activities as envisaged. The table below provides a comparison between original SPFM
financing for the project and the proposed financing after reallocation, extension of closing date and
processing of AF:
Original Components Original Costs
(US$ million)
MDTF
Proposed restructuring Total Updated Cost
(US$ million)
Revised Estimated
Costs after
reallocation(US$
million)
MDTF
Additional
Project
Costs
(AF US$
million)
MDTF
Component 1:
Implementation of TSA 2.80 3.30 3.00 6.30
Component 2: 0.17 0.17 0.00 0.17
Component 2 (b) 0.58 0.08 0.15 0.18
Component 3: 0.75 0.75 0.35 1.15
Total: 4.30 4.30 3.50 7.80
VI. Next mission
23. The next mission is tentatively planned for March 2015.
6
VII. Summary of Agreed Actions
Agreed Actions Date Responsible
Agency
COMPONENT 1 Additional Financing request: As agreed during the review further updates to finalize
the activities and their linkages with existing PDO and a possible results framework. This would include (i) a revised financing plan and an updated cost table; (iii) an updated
procurement plan; and (iv) a revised timetable for the implementation of the proposed
activities under AF.
February 15, 2015 FCGO
Commitment Recording: More data, will need to be captured at the spending entity level (like overall budget amount, total amount committed for items above NPR 500,000,
% utilization of commitments over a period, aging analysis etc) to help analyze the trends
of the commitments across spending units, and make them more useful to the line managers in terms of budget control and implementation.
January 15, 2015 FCGO
Analysis of variations in financial statements: FCGO will finalize the analysis of
variations (and reasons thereof) that the year-end financial statements (for year ended July 16, 2012 & 2013) undergo before they are finally rendered to OAG for audit.
January 31, 2015 FCGO
Undertake a review of remaining bank accounts and applicable rules/regulations: undertake a review on what can be done to rationalize these bank accounts (given the
rules and regulations) as some of the accounts may not be active and for the others a TSA concept could be put in practice, but this requires amendment in rules/regulations. It was
agreed that FCGO will undertake a review of this area (preferably using a consultant)
February 28, 2015 FCGO
Hiring of IT Staff and consultants :
Hire two engineers (1 hardware engineer and 1 software engineer) will be on-board by
December 31, 2014. Seek final approval from cabinet for proposal for additional staff in FCGO (1 IT Director,
1 hardware engineer and 1 software engineer). This is an appraisal condition for the
additional financing as detailed later.
December 31, 2014 February 15, 2015
FCGO
FCGO
Rollout of Revenue Management Information Systems :
Submit a rollout plan and a detailed implementation note after learning from current
pilots and share with the Bank
January 31, 2015 FCGO
Accounting Manual: Consultant to submit a draft and share with the World Bank Finalize the draft and seek internal approval for implementation
February 28, 2015
April 15, 2015 FCGO
SLA Contract : Expedite procurement – publish notice
And SLA contract will be awarded by February 28, 2015.
Dec 31, 2014
Feb 28, 2015
FCGO
FCGO
Asset Register – To be initiated as agreed (in excel sheet) and fully populated January 31, 2015 FCGO
COMPONENT 2
Complete the audit of the two pilots NPSAS based financial statements March 31, 2015 FCGO OAG
Complete the training of the two pilot departments and help them prepare the NPSAS
compliant financial statements of FY2013/14 that can be rendered to audit to
demonstrate efficacy of the process. January 31, 2015
Line Ministries/
FCGO/OAG
Complete the audit of the 2013/14 financial statements prepared by the two line departments
April 30, 2015 Line Ministries/ FCGO/OAG
Submit a revised NPSAS implementation note (for AF) including a rollout plan and in
accordance with the discussions during the mission January 15, 2015 FCGO
COMPONENT 3
Complete the research work for awarded studies and share with the Bank
4 studies
1 study
March 31, 2015
April 30, 2015
PEFA Secretariat
Develop a note on the scope of the work and shift in strategy in terms of putting more focus on research and analytical studies
January 31, 2015 PEFA Secretariat
RF / Strategy in respect of Additional financing component to justify the new
investment January 31, 2015 PEFA Secretariat
PFM Reform Action Plan Phase 2 draft as developed by GoN to be shared for further discussion and quality assurance
January 31, 2015 MoF and PEFA Secretariat
Additional agreed actions from technical review (annex 3)
Renewal of Service Subscription/Technical Support of 2 McAfee IPS2850 appliances. December 31, 2014 FCGO
Following items are to create baseline which may be used in building RF for proposed AF
IT Asset Register for FCGO and all districts along with identification of replacements January 31, 2015 FCGO
Power Stats for Solar Power Backup – An average load shedding/power failure time for three categories of districts December 31, 2014 FCGO
Responses to Questionnaire from DTCOs December 31, 2014 FCGO
Server Utilization/Performance data on a daily basis January 31, 2015 FCGO
Network Utilization / Performance Statistics on a daily basis January 31, 2015 FCGO
Annex 1
Page 1 of 1
List of Persons Met
Financial Comptroller General Office
1. Mr. Shankar Prasad Adhikari Financial Comptroller General
2. Mr. Jagdish Regmi Joint Financial Comptroller General/ PEFA Coordinator
3. Mr. Jaydev Shrestha Joint Financial Comptroller General
4. Mr. Ramesh P Siwakoti Deputy Financial Comptroller General
5. Mr. Thaneshwar Gautam Deputy Financial Comptroller General
6. Mr. Netra P Subedi Deputy Financial Comptroller General
7. Mr. Baburam Subedi Member Secretary (PEFA Secretariat)
8. Mr. Sukhdev Baskota Deputy Financial Comptroller General
9. Mr. Baburam Gyawali Deputy Financial Comptroller General
10. Mr. Ishwar P Kafle Deputy Financial Comptroller General
11. Ms. Anupama Karki Account Officer (PEFA Secretariat)
12. Mr. Tolendra Karki Account Officer (PEFA Secretariat)
13. Mr. Sanjay Manandhar IT Consultant
Accounting Standards Board
14. Mr. Lok Man Singh Maskey CEO
Annex 2
Page 1 of 6
Summary of Implementation Status
The implementation progress under each component is summarized below.
Component 1: Implementation of Treasury Single Account (TSA) System.
1. This component includes (a) implementation of a TSA system to enable real time budget
checks prior to authorizing payment on expenditure transactions across all District Treasury
Comptroller Offices (DTCOs) throughout the country and at the FCGO, and (b) further enhancement
of the modified financial management information system (FMIS) to include commitment accounting,
treasury/cash management, and financial reporting in accordance with International Public Sector
Accounting Standards (IPSAS) cash part I. The overall progress of the component is “satisfactory”.
2. Rollout of TSA: The component scope included rolling out and enhancing an existing TSA
system to ensure integrity of the budget during its execution and to strengthen treasury single account
through centralization of payments at 75 DTCOs. The new system has been rolled out to all 75
districts, completing the coverage of ex-ante budget execution control at all the districts, a year ahead
of the target date. The roll-out has also enabled the government to centralize the payment function at
the DTCOs and strengthen TSA by closing down about 14,000 accounts. In terms of coverage, TSA is
now able to cover almost 100% of budgeted revenue and expenditures3 of the GoN. The system is
able to support generation of consolidated cash flow statements for individual ministries as well as for
the government. This component has helped achieve first of the two major objectives.
3. Upgrading FMIS: The second objective which was planned to be achieved through up
gradation of FMIS to further strengthen the core treasury system is now proceeding satisfactorily.
This will include, amongst others, recording of commitments, cash forecasting reports, secure
automatic daily bank reconciliation, capturing of missing receipt information (e.g. customs, VAT,
etc.) and development of additional reports.
4. Commitment Recording: An international expert was hired through Bank executed trust
fund who helped (in collaboration with FCGO officials) developed a blue print for implementing the
commitment recording in the existing TSA system. Required software modifications in FMIS for
implementing the recommended blue print were thereafter developed in-house by the software
engineers of FCGO along with the development of the draft business process/reports and added to the
existing TSA system as a separate module. Implementation of this new utility has now been started
2014-15 with a threshold of NPR 500,000 (ie this module will capture all commitments above NPR
500,000) as a proof of concept. Early reports from 24 districts in this regard were shared with the
review team. More data, will need to be captured at the spending entity level (like overall budget
amount, total amount committed for items above NPR 500,000, % utilization of commitments over a
period, aging analysis etc) to help analyze the trends of the commitments across spending units, and
make them more useful to the line managers in terms of budget control and implementation during the
year. It was agreed that FCGO will collect this additional information and share it with World Bank
by January 15, 2015. This will help make any required adjustments in the business process and
reporting formats to allow for better informed decision making at the line department level. A detailed
business process is provided in Annex 5.
3 The expenditures include capital/donor funded projects. Payroll expenditures are recorded in the system on a summary voucher basis.
The system records debt related transactions on an ex-ante basis, along with devolution of budget central government incurred through District Development Committees (DDC) (4 ministries – Agriculture, Livestock, Health and Education). The un-conditional grants to
the local bodies and DDCs are recorded as expenditures at the time of transfer. These transactions contribute substantially towards
comprehensiveness of budget execution coverage within the system for better reporting and improved controls.
Annex 2
Page 2 of 6
5. Revenue management/Cash Management/Daily Bank Reconciliation: Earlier in the year,
a workshop was organized between FCGO, NRB and other stakeholders to brainstorm for enhancing
business processes in the area of cash management, remittances, bank reconciliations4 and overall
revenue management. A task force, in this regard, was formed comprising of officials from NRB,
FCGO and five commercial banks for brainstorming and developing a plan. This task force developed
a business process (an international expert hired under bank executed trust fund helped refine this
business process) and a software was configured accordingly by FCGO software engineers for testing.
Pilots in three districts (Kathmandu, Bhaktapur and Lalitpur) have been started with effect from the
beginning of this FY (2014-15) which amount to about 45% of the total revenue of the government.
An additional server will be required to be procured for this purpose, for which plans have been
prepared. Currently the reporting server, which was acquired earlier, is being used for the pilots. Pilots
faced significant issues in the beginning as several stakeholders (commercial banks, Nepal Rastra
bank, paying and collecting offices, FCGO etc.) were involved in this complicated work flow.
However FCGO officials have been successful in resolving many of these issues and the
implementation has now significantly improved. FCGO team shared recent daily bank reconciliations
for month of November for Kathmandu districts for three commercial banks. This is a significant
achievement considering that earlier these reconciliations use to take around 3-4 months on an
average. Lessons learnt from this pilot will be incorporated in the further rollout strategy of RMIS. It
is expected that this will be fully rolled out over the next two years with another 20+ districts with
effect from FY 2015/16. A roll out plan and an implementation note in this regard will be prepared
and shared with the Bank by January 31, 2015. Detailed business process is provided in Annex 6.
6. Upgrading Technology Infrastructure: In addition, the project scope also included upgrade
of the technology infrastructure to support a stable and responsive TSA system. In this regard, the
servers for the primary as well as the disaster recovery center have already been upgraded. All the 75
DTCOs are connected on-line to a central TSA server. Options for enhancing connectivity for the
balance districts (primarily remote/hill districts) will be explored under Additional financing.
7. IT Expertise: A team of IT experts/project funded consultants has been hired5 to provide
technical support and maintain the system. Recently these IT experts have started developing software
enhancements to existing FMIS (for commitment recording, and for enhancing cash/revenue
management), necessitating a need for hiring more professionals. It was therefore agreed that FCGO
will hire additionally 2 engineers. The review team was informed that this process is now quite
advanced and two engineers one hardware engineer and one software engineer) will be on-board by
December 31, 2014. Risk to ensuring sustainability of the IT/System with support primarily from
consultants is very high in FCGO. Therefore in the last review it was agreed to hire additional IT staff
in FCGO to help develop internal capabilities over the medium term. The team was informed that the
proposal for additional staff (1 IT Director, 1 hardware engineer and 1 software engineer) has been
approved by the Ministry of Finance. This will now need approval of the Cabinet which is expected
by February 15, 2015. This is an appraisal condition for the additional financing as detailed later.
8. Further rationalization of bank accounts: Through centralization of payments through the
TSA system, the government has also succeeded in consolidating its bank accounts by closing down
13,717 of its bank accounts. There are however still some operative bank accounts of the government
(1988 in total of which 445 are treasury managed accounts), which include accounts for current
expenditure, capital expenditure, revenue, retention money, special purpose and miscellaneous
accounts. Although with the TSA concept now fully implemented these accounts needs to be
incorporated into the TSA but there are several rules and requirements which mandate maintenance of
4 Though the respective bank branch faxes daily report to the DTCO and the respective bank HQ, the final bank reconciliation between
the bank and the FCGO takes place much later. Delayed reconciliation results in inaccurate reports in the TSA system, significant work at the end of the year to do the corrections and higher chances of erroneous/fraudulent transactions remaining undetected for
extended periods of time.
5 Numbers to be provided by FCGO.
Annex 2
Page 3 of 6
these bank accounts. There is a need to reform this area and undertake a review on what can be done
to rationalize these bank accounts. The team was also informed that some of these accounts may not
be active and for the others a TSA concept could be put in practice, but this requires amendment in
rules/regulations. It was agreed that FCGO will undertake a review of this area (preferably using a
consultant) and prepare a report for consideration at the policy level (by February 28, 2015).
9. Mapping for Financing Transactions: During the last review, it was agreed that FCGO will
operationalize the recording of all the financing transactions in the TSA system. Since the last mission
a manual has been developed for resolving the discrepancy between Government Finance Statistics
(GFS) recommended grouping/coding and current coding practices for financing transactions relating
borrowing, lending and investments. The review team was informed that this manual has been fully
put into practice by incorporating the provisions into the Chart of accounts (economic codes) and
guidance under the Financial Procedures Act.
10. Budget Execution Report (BER): The Team is pleased to learn of further progress made in
generating and disseminating Budget Execution Reports (BER). A daily budgetary status has been
made available which depicts aggregate revenue, expenditures and budgetary surplus/deficit with a
lag of a day. In addition following monthly reports are now available: (a) Ministry wise Economic
classification of the expenditures (b) Ministry wise budget, expenditures incurred and balance
available and (c) District wise budget expenditures. These reports are now being prepared in less than
three weeks after the month end and published on the web site
(www.fcgo.gov.np/publication/budgetexecutionreport). The Team recognizes this as a good
achievement in line with the Results Framework of the Project, and some more work can be done
going forward in order to improve the quality of the information. In the last review it was agreed that
FCGO will conduct an analysis of variations (and reasons thereof) that the year-end financial
statements (for year ended July 16, 2013) undergo before they are finally rendered to OAG for audit.
This review has been initiated and is likely to be completed and shared with the bank by January 31,,
2014. This will help establish the percentage of accuracy of these unaudited financial statements as
generated directly from the TSA system.
11. Accounting Manual: During the last review, it was agreed that the FCGO would hire a
consulting firm to develop the accounting manual after reviewing the existing acts and regulations and
identifying the inconsistencies in the current practices. A consultant has now been hired but the draft
manual is much delayed. The review team was informed that consultant will submit a draft by
February 28, 2015 and this will be finalized by April 15, 2015. Currently, the detailed accounting
procedures are scattered in financial regulations, acts, notifications, instruction memos and system
design documents.
12. Fiber connectivity: The review team was informed that 53 districts are now provided with
fiber connectivity. Remaining 22 DTCOs will continue to use ADSL technology to connect to the
main server till alternate options emerge in the market place. These 22 DTCOs contribute about 12%
of expenditures and about 1% of revenue.
13. Reporting access to Line ministries: The review team was informed that on-line access is
now made available to the Ministry of Education after an additional reporting server was installed in
May 2014. Plans are afoot to provide online access to other ministries.
14. Access to the Office of the Auditor General (OAG): The review team was informed that
following extensive deliberations since the last review, on-line read-only, transaction level access of
the TSA system is now made available to up to five concurrent users from the OAG. This is expected
to substantially facilitate the use of Computer Aided Audit Techniques (CAAT) by OAG and
undertake/plan audits on the basis of assessed risks. Impact in this regard is likely to be felt in the
audit of the financial statements for 2014/15 which are likely to begin in December 2014.
Annex 2
Page 4 of 6
15. Oracle license: An ICB was conducted to procure Oracle license from authorized vendor
which helped substantial costs as compared to earlier sole sourced quotation, and the contract was
awarded there after. Implementation has now been completed with full acquisition of license by the
FCGO’s office.
16. SLA Contract: The review team was informed that the SLA contract for critical servers and
UPSs in Data Center has not been awarded yet due to transfer of procurement team. This is a very
important action that needs to be taken immediately due to potential risk that IT equipment and
architecture in FCGO face due to the absence of this support. Any downtime of these equipments
would mean a halt to FCGO’s business. FCGO has assured that notice will be published by Dec 31,
2014 and SLA contract will be awarded by February 28, 2015.
Component 2: Strengthening accounting and reporting practices in public and private sector
17. Component 2(a): Private sector accounting and reporting: The Accounting Standards
Board (ASB) has formulated 40 NFRSs and the Institute of Chartered Accountants of Nepal (ICAN)
has pronounced them in September 2013. ASB has planned some activities such as preparation and
development of NFRS for SMEs, guidance notes for 15 NFRSs, training for trainers on NFRSs and
exposure visit. The MoU between PEFA Secretariat and ASB which was till July 16, 2014 has been
extended to December 31, 2014 at no extra costs. A current status of work completed up to 1st
trimester has been shared according to which almost all work has been completed. ASB has
completed most of the actions such as 15 guidance notes drafted, conducted trainer the trainer (TTT)
program for qualified Chartered Accountants, publication of NFRSs etc. It is in process of translating
42 NFRSs to local language and complete within December 31, 2014
18. Component 2(b): Public sector accounting and reporting: The NPSAS compliant
financial statements for FY2011/12 and FY2012/13 pilot on two ministries (MOPIT and MOWCS)
have been completed. NPSAS based financial reports have been certified by ICGFM in a
valedictory function held recently in Washington DC, USA. For this the FCGO (with support from
consultants) also organized a high level stakeholder (OAG, MoF, NPC, FCGO, Line departments and
others) workshop in July 2014 to review the results of the NPSAS pilots, specifically to review the
costs and benefits of applying NPSAS, and to reach consensus on a recommended roadmap for
improving public sector accounting and reporting in Nepal. It was also suggested that the two pilot
departments after having been trained will start taking steps towards preparing NPSAS compliant
financial statement of FY2013/14 in these two line ministries and have it audited (to be completed by
March 31, 2015) and certified by the Office of Auditor General. It was agreed that F/S for 2013-14
will be completed by January 31, 2015 and the subsequent audit will be completed by April 30, 2015.
This will complete the pilot and help establish credence in these financial statements. This will also
help the stakeholders take a call on future roadmap of the implementation of NPSAS across line
ministries; after analyzing the costs and benefits and the need to comply with GON adoption of
NPSAS.
Component 3: Supporting the capacity building of the PEFA Secretariat
19. The objective of this component is to strengthen institutional capability for initiating,
coordinating and sustaining reforms to improve PFM across GON through strengthening the capacity
of PEFA Secretariat. The review team acknowledges the efforts of the PEFA secretariat and the
FCGO team in accelerating the program as agreed in the program document. Since the last mission,
Mr. Jagdish Regmi has been designated as a new PEFA Coordinator.
20. Communications: The team discussed the dissemination of results achieved under this
component, such as the 9 newsletters and 3 journals that have been published till date. Around 500
copies of newsletters and 300 copies of journals are published and disseminated to every district, PIU,
DPIU, ministry and training institutes. These are also uploaded online on the website of the PEFA
Annex 2
Page 5 of 6
Secretariat for wider circulation. There has also been good press coverage on PEFA Secretariat lead
events such as the ten articles have been published in several newspapers on the training of
Journalists. Further to this, the PEFA Secretariat has funded a radio program dedicated to
disseminating information on PFM reform through interviews with various public sector experts on
PFM. This program is broadcast on the first and last Friday of every month through Radio Nepal. The
PEFA Secretariat has also been successful in conducting a total of 50 field visits for the purpose of
building awareness and enhancing technical knowledge on PFM.
21. The PEFA Secretariat already has a strong communication strategy. Therefore, a short-term
communication expert will be hired as and when required to refine the strategy. It has also been
agreed that the PEFA Secretariat will prepare a strategy on the scope of work under this component to
focus also conducting research. A brief outline was shared by the PEFA Secretariat, Nepal during the
review which will now be elaborated.
22. Research and Studies: One of the PEFA mandate is to perform research studies supporting
PFM reform activities. Following five studies have been agreed upon to be undertaken:
Study on Internal Audit System in Nepal;
Feasibility study on establishing a National Institute of PFM;
Impact of government investment in public enterprises in terms of loan and share
investment; and
Impact of implementation of TSA in public finance;
Pattern and implication of off-budget items in public financial accountability;
The Team was informed that contracts have been awarded to conduct the four research
studies. In regards to the study on “Pattern and implication of off-budget items in public financial
Accountability”, proposals have been received and these proposals are, presently, being evaluated. It
was agreed with the PEFA Secretariat that this study will be complete by April 2015, while the other
four research studies will be complete by March 2015.
23. PEFA Secretariat and its Autonomy. To follow on the previous review team’s discussion
regarding the PEFA status, autonomy and sustainability, the Team was advised that a separate
authorization has been provided to the PEFA Secretariat. Second PEFA Assessment. Under the
leadership of the GON, the second PEFA assessment is now complete. The decision review meeting
took place on December 16, 2014 and was chaired by the Country Manager of the World Bank. The
meeting brought together government officials especially from MOF, FCGO and PEFA Secretariat,
Nepal, MDTF DPs along with the PEFA team from the World Bank. A virtual review of the report
was done in December 5, 2014, based on which a response matrix was circulated comprising of the
comments of all the peer reviewers and development partners. The findings from this assessment will
be the base for developing the PFM reform strategy. It was agreed with the PEFA Secretariat that the
second phase PFM action plan will be finalized with a consultation of broader stakeholders. . An
international expert can also be hired to help finalize the action plan on the request of PEFA
Secretariat, Nepal. The team was informed that a preliminary draft has already been prepared by the
government. This strategy will also be shared with the development partners who can help enhance
quality and the strategy will then be discussed in a higher level PFM steering committee. This action
plan will build into the MDTF future work program and the GON’s PFM program.
Annex 2
Page 6 of 6
Implementation Arrangements
24. The membership to the National level PFM Steering Committee, chaired by the Finance
Secretary, has been expanded to include 14 members including a member secretary – two private
sector representatives have been added to the committee. This committee provides overall guidance to
the PEFA Secretariat. Given broader spectrum of the PFM, the Bank team suggested to include the
ICAN, Accounting Standards Board and the Auditing Standards Board in the Steering Committee.
The working level committee, chaired by the PEFA Coordinator/Joint Financial Comptroller General,
has also expanded to include 10 members including a member secretary. The leadership of the PEFA
Secretariat has recently changed. The Joint Financial Comptroller General Mr. Jagdish Regmi is the
new Coordinator of the PEFA Secretariat following the transfer of the former Coordinator Mr. Dilli
Ram Sharma. The working level committee is mandated to meet every two months, and the team
encourages this meeting to be held more regularly as opposed to the current practice of meeting on a
trimester basis. PEFA Secretariat is functioning as a central platform to (i) facilitate support to the
PFM Steering Committee chaired by the Finance Secretary which provides vision for PFM reform,
(ii) support the implementation of the PFM Strategy Phase I, (iii) support in undertaking research and
analysis, including in-depth research on PFM in high priority areas or sectors, and (iv) develop and
implement communications strategy to raise awareness of PFM. The review team suggested that the
continuity of leadership in the PEFA Secretariat is crucial to drive the PFM agenda forward, and steps
should be taken in this regard to ensure staff continuity.
Annex 3
Page 1 of 3
Technical Review of the Proposed Additional Financing
1. A detailed technical review of the proposal submitted for Additional Financing under SPFDM
project was undertaken during the review mission. The revised additional financing costing received
was discussed which included 18 activities under Component 1, 4 activities under Component 2 and
22 activities under Component 3. With review and discussion, a revised list with costs and other
details will be provided by December 31, 2014. In terms of principles, revisions will be required on
account of :
(i) Pruning down of Training and study tour related expenses as existing project is already
providing for these activities. Only exceptional cases with justification to be
considered.
(ii) Pruning of incremental operational costs as this is also provided from existing project.
(iii) NPSAS roll out to cost USD 150,000 instead of USD 100,000
(iv) AF to Component III to include capacity building for In-country PFM training and to be
cost accordingly. Other activities under component III to be determined according to
strategic priorities of PEFA Secretariat in terms of research, communication and reach
out for which a note (including results to be obtained) will be prepared and shared.
2. The overall up-gradation of IT landscape of FCGO across Nepal and its requirement under
additional financing is based on the three consultants' reports - Data Center, Networking and Solar
Power Backup. These reports were the basis of design and cost estimates in Additional Financing.
The consultants’ reports are detailed current assessment along with suggested solution and Bill of
Material (BOM) for up-gradation. These recommendations have been reviewed in the last mission
from a strategic and cost benefit perspective while including them in the proposal for AF.
Summary of Review and Assessment
3. The Additional Financing is broadly divided into following eight broad categories with
tentative costs as established by technical review in the last mission. The aggregate requirement for
component 1 is tentatively estimated at USD 3.00 MN. However these costs are now being revised as
per discussion above and will be finalized by December 31, 2014.
4. IT Organization Structure: IT infrastructure and its usage is fast becoming a lifeline for
FCG’s functions and therefore needs to be accorded highest priority. In this backdrop most important
one is building an IT Organization Structure of FCGO which is essential in sustaining and supporting
this project and moving forward in overall reform of PFM strategy and use of technology in effective
manner. This was stressed during last mission with an agreement that necessary steps have to be
initiated now to secure required positions before the appraisal of the AF request. There has been
movement by FCGO on this; the details are given in the main aide memoire.
5. IT and Office equipment’s: This has new procurement and replacement of obsolete
equipment. These include Desktops, Laptops, Printers, UPSs, Scanners, Photocopy and Fax machines.
WB team was told that the replacement numbers is based on old, obsolete, beyond repairs equipment,
though there is no written down policy on replacement. The estimated cost is $ 30,000 for FCGO and
$ 152,000 for DTCOs.
6. Data Center : The up gradation of Data Center include (a) Precision AC, Fire Detection
System, Electric Panel, Racks etc with an estimated cost of USD 168,000 and (b) Network devices,
Router, switches, Networking Monitoring System, Centralized Anti-Virus Software with an estimated
cost of USD 1,542,690. .
Annex 3
Page 2 of 3
7. Networking: Up-gradation of Network is a high priority to match the load associated with
TSA and RMIS upgrade. The current network system, switches, cabling are outdated, not efficient
and not as per recommended International Standards. Often, the limiting factor on performance is
network congestion or overloaded switches and routers. The cabling is CAT5 in the entire network
except for 2/-3 paying centers. The suggested CAT6 cabling which are more rigid; reduce noise and
are more flexible. Cat6 specifications provide significantly lower interference or near end crosstalk
(NEXT) in the transmission over CAT5. The result is less noise, fewer errors and higher data rates in
the transmission of the signal.
8. The up-gradation would also enable the entire network to control the functioning and move to
redundancy through remote control without manual intervention. This online monitoring would
enhance timely support from HQ and other regional centers. However there is no need to build a full
100% redundancy for routers at DTCOs and instead a 10% spares can be procured in case of
equipment failures. The estimated cost for active networking items (Routers, Switches) is $ 620,000
and for passive items (CAT6 and fiber cables, network panels, face plates, patch cords etc.) is $
251,000.
9. Solar Power Backup: Uninterrupted power supply is essential for any IT setup. With the
current situation of power in Nepal is not very good. There have been some districts where there is no
power for 7-8 hours. The solar power backup solution makes it ideal choice over other power backup
technologies. The financial figure under this line item is based on solar power consultant's report. In
last mission FCGO was told to rework on the models/capacity of equipment based on 50% load.
However FCGO has reworked costs based on 60% load.
10. RMIS Roll-out: The team was informed about the successful rollout of RMIS in three
districts of Kathmandu valley. During the rollout, the software was tweaked with the inputs from
concerned end users. The software is stable now. With the plan to rollout RMIS in all districts in next
two years, there is requirement of additional server for RMIS application. This will allow to create a
separate cluster for fail-safe operation. The data base server will remain same that of TSA. The team
has worked out a tentative cost of RMIS Roll-out at $ 143,000 which includes server cost.
11. CGAS Pilot Phase Implementation: This was discussed in this mission and it has been
confirmed that full implementation of CGAS is not under consideration. This will be initiated through
a separate project. The estimated cost for the pilot phase implementation is $ 30,000.
12. Support Services and Consultancies: Support services will be required for ensuring TSA
sustainability and to maintain high understanding, knowledge and operation of the TSA system by all
users. In addition AF will also fund consultancies for development of medium term strategy for
evolution towards full-fledged IFMIS/COTS solution, development of IT Strategy and conduct of
IT/Functional Audit. The revised cost for is estimated at $ 205,000. To be updated after receipt of
revised sheet.
13. Operating Costs: These are for supplies like, toners, fuel, maintenance contracts, repairs etc.
The estimate is $ 90,000. The team has asked FCGO not include this in AF but can be charged under
existing project cost since there will an extension of the existing project to the same date of AF.
PFM human Resource Development (details in the main aide memoire)
Assessment of IT Infrastructure and Actions Required
14. During the assessment and review the following observations were made:
(a) Unused / Under Utilization of one server
(b) Warranties of critical servers and UPS is over
(c) IT Asset Register
Annex 3
Page 3 of 3
15. PEFA coordinator informed that the transfer of the applications from old server to the RISC
server is was completed on November 15, 2014
16. WB team was informed that the SLA contract for critical servers and UPSs in Data Center has
not been awarded yet due transfer of procurement team. WB team alerted FCGO for not having SLA
in place for critical equipment. Any downtime of these equipments would mean a halt to FCGO’s
business. FCGO has assured that notice will be published by Dec 20, 2014 and SLA contract will be
awarded by February 15, 2015.
17. Team was also informed of non-renewal of service subscription/technical support of two
McAfee IPS2850 appliances. This is again critical as this is an appliance for any Intrusion Prevention.
If this is not renewed the software associated with the hardware stops working as informed by
McAfee. Thus FCGO’s server and Intranet security will be seriously compromised and becomes open
to vulnerable attacks. This should be done at the highest priority.
18. WB team also noticed that Asset Register has not been prepared. The importance of IT Asset
Register was highlighted in all the last missions with a specific emphasis in last mission. The Asset
Register is also required for WB team to assess the requirement of desktops, printers, laptops,
switches etc. under AF. FCGO doesn’t have any IT policy written down on replacement of IT
equipment. In the absence of Asset Register, it will be difficult to assess the replacement.
19. FCGO had provided responses to questionnaire from few DTCOs. More will be provided by Dec
31, 2014 which will help in analyzing support calls, network down time etc. which would help in RF.
20. IT Asset Register - The format was discussed and finalized with FCGO. The equipment to be
replaced should be identified, which should match with the breakdown of additional financing.
21. To establish baseline that will help measure the results achieved under the additional
financing following data needs to be gathered as discussed in detail during the mission :
a. Power Statistics – Under each category of districts, note power failure/load shedding
for every district and calculate average down time / no power in hours.
b. Responses to questionnaire – Based on responses, prepare an excel sheet giving no of
calls for HW and SW, FCGO response time and application response time.
c. Server Utilization – Take screen shot of utilization/performance parameters every day
during peak time of the day and save that in a word document.
d. Network Utilization – Save reports/screen shots of the PRTG network monitor, Record
various links’ utilization by clicking on the links. Store reports of SUBISU’s link status
report too.
Agreed Action Date Responsible
IT organization structure - re-structure, hiring of new consultants and hiring process of 3
new posts (1 Dy FCG – IT Director, 1 Software Engineer and 1 Hardware/Network engineer)
Cabinet Approval by
Feb 15, 2015 FCGO
Hiring of additional identified consultant positions (IT technicians for regional coverage
software/networking/hardware consultants for HQ) December 31, 2014 FCGO
Selection and award of Maintenance contract (SLA) for 3 servers, critical network equipment in Data Center and 2 UPSs and Diesel Generator at FCGO
February 15, 2015 FCGO
Renewal of Service Subscription/Technical Support of 2 McAfee IPS2850 appliances. December 31, 2014 FCGO
Following line items are to create baseline data which may be used in building RF and also to justify the investment.
IT Asset Register for FCGO and all districts along with identification of replacements January 31, 2015 FCGO
Power Stats for Solar Power Backup – An average load shedding/power failure time for
three categories of districts December 31, 2014 FCGO
Responses to Questionnaire from DTCOs December 31, 2014 FCGO
Server Utilization/Performance data on a daily basis January 31, 2015 FCGO
Network Utilization / Performance Statistics on a daily basis January 31, 2015 FCGO
Annex 4
Page 1 of 6
Proposal for Additional Financing
Background and Rationale for AF
1. The Project Development Objective (PDO) of AF would remain same that is, “to improve
expenditure control and enhance government accountability and transparency by
strengthening the treasury system, improving financial reporting and building PFM
capacity”.
Component 1: Implementation of Treasury Single Account (TSA) System (USD 3.00 million)
2. The original scope under component one involved: (i) implementation of the Treasury Single
Account for efficient cash management; (ii) roll-out of FMIS (Financial Management Information
System) for enhanced budget compliance during expenditure execution and payment process; (iii)
further enhancement of the FMIS to support commitment accounting and improved financial
reporting - aimed at strengthened expenditure controls and enhanced transparency. These were
considered to be the foundational elements to provide a basic platform before beginning an ambitious
journey of PFM reforms in Nepal.
3. For practical reasons, an iterative and incremental implementation approach was adopted to
achieve the above objectives. Under this approach, the government agreed to implement reforms in
small increments through iterative process, learning from the previous iteration and building onwards
incrementally through subsequent iterations. Using this approach, first emphasis was on implementing
expenditure Treasury Single Account, supported by FMIS roll-out in a phased manner across Nepal.
In this regards, expenditure payments of ministries at Kathmandu and the 75 districts were centralized
at the treasury offices, and processed through the FMIS, enabling the government close down more
than 13000 expenditure bank accounts of these ministries, thus eliminating idle cash balances in these
accounts. This comprised achieving 100% target during 2013, one year ahead of time. In addition,
FMIS was rolled-out to all the districts treasury offices to ensure budget compliance during the
expenditure payment processing at these offices. However, this iteration did not involve
implementation of two major activities of the original scope: revenue TSA and commitment controls.
4. Currently, DTCO receives expenditure account statements from the respective bank and
subsequently carries out expenditure account bank reconciliation almost on a daily basis. However,
the situation with revenue reporting is not the same. The banks do not report revenue collections to
the DTCOs in a timely manner, which leads to inaccurate information on government’s aggregate
cash position in the TSA. In addition, the foreign loans and grants receipts are not being captured in
the FMIS, due to inadequately defined procedures and lack of system functionality. This has further
contributed to inaccurate aggregate TSA cash position of the government in the FMIS.
5. Besides, the commitment controls is not being practiced currently. The line ministries issue
purchase-orders and contracts to the suppliers, without recording them in the system as commitments.
Due to this, the government does not have information on its aggregate commitments that could allow
appropriate cash planning to ensure commitments are paid in a timely manner to avoid any build-up
of potential payment arrears.
6. To overcome the above limitations, the government plans to implement the next iteration of
reforms in these two areas. This involves enhancing FMIS and rolling-out two additional modules
across the 75 districts: commitment management and revenue management- RMIS (Revenue
Management Information System). The development and roll-out of these modules will be preceded
by revisions in relevant policies and procedures.
7. The government plans to complete these reforms through AF and consolidate the TSA rollout
by making appropriate investment in IT equipment, hardware, networking and associated peripherals.
Annex 4
Page 2 of 6
due to the massive change management challenges involved in successful accomplishment of these
activities, the government anticipates a slower progress compared to the earlier rapid implementation
of the expenditure TSA, and therefore, has requested, in addition, an extension in project completion
date by two years- June 30, 2017.
8. Besides system roll-out mentioned above, the second area, and towards which major proceeds
of the AF will flow, relates to the upgrade of the IT infrastructure to enhance sustainability of the
systems. Key areas in this regards include networking equipment, power back-up equipment and IT
devices, including desktops, printers, etc.
9. Again the IT infrastructure upgrade has been carried out through an iterative approach. When
the project was initiated, the government had already developed and implemented the FMIS system in
the initial few districts. It was envisaged that the project will finance, among others, the IT equipment
for the central data center at the MOF and the district offices, including retroactive financing of
equipment at the already implemented districts. However, due to the limited availability of funds
under the project, the activities were prioritized. The key priority was given to the rapid roll-out of the
TSA at the 75 districts. The IT infrastructure in the above mentioned three key areas were expected to
be strengthened later with a perspective that sustaining investment will be made after achieving the
rollout, which required a huge behavioral change (withdrawal of cheque writing powers of line
departments and its spending units) and was anticipated to take much larger time. The networking
equipment acquired by government out of its own funds was often of low capacity and has now
become obsolete, as it has not been upgraded during the last four years. This was done partly to save
funds for the more prioritize activity of the TSA roll-out. Now that the system usage has increased
over the last year, there is a need to upgrade this equipment for higher availability, better monitoring
and performance management through centralized monitoring infrastructure. Similarly, the worsening
power outages necessitated acquisition of power back up equipment for only the large districts,
leaving many other districts without appropriate power back-ups when power outage has ranged from
8-16 hours. The data center, hosting high end servers, needs to be upgraded for better monitoring of
the data center environment suitable for these servers
10. WB team has reviewed and has done on-site evaluation of IT infrastructure upgrades
requested under proposed AF. These have been based on the three consultants ‘reports. The
consultants- networking consultant, power engineer and data center expert- were hired to make a
realistic assessment of the equipment requirements and submitted their reports earlier this year. Based
on these recommendations, the government in the next phase under AF plans to enhance and upgrade
its IT infrastructure and power-back-up arrangements more comprehensively and has requested to
fund these activities through AF6. The sustainability of current IT infrastructure at FCGO is a major
challenge with old/outdated, end-of-life/support for hardware and software. Aging or end-of-life
equipment poses difficulties/disruptions in maintaining smooth operation and also leads to enhanced
costs for maintenance. With the funding so far, results have been positive and the project needs to be
taken to next level. Also, the additional financing will ensure enough room for projected growth, more
applications and data for next three to four years and will also include maintenance.
11. The major portion of the hardware upgrade is in the areas of network Infrastructure and power
backup. Both these are vital areas in terms of maintaining continuity of operation to run day-to-day
business of FCGO and DTCOs. The availability and uptime of IT is important to maintain the
efficiency of FCGO and DTCOs. Given the scenario of not having IT staff at all the districts, day-to-
day support and maintenance remains a challenge. Delayed IT support leads to business delays. This
situation will improve to quite an extent, using centrally managed technologies e.g. managed devices
with centrally managed software for network and security. The upgrades on the network side will also
give better bandwidth which
6 The additional financing under component 1 lists 78% funding for IT Hardware and software and 22% for Consultancies for
Training/Support/Capacity Building.
Annex 4
Page 3 of 6
would improve application performance. This would lead to higher level of efficiency of FCGO and
DTCO’s staff. A detailed technical assessment of AF proposal (under component 1) is provided at
Annex 2.
Component 2: Strengthening accounting and reporting practices in public sector (USD 150,000)
12. Under component 2, NPSAS pilots have been successfully undertaken in two ministries and
now GoN is planning on up-scaling this rollout across all ministries. For this consultancy support and
necessary training/capacity building activities will be required to be undertaken. A practical rollout
plan will need to drawn up which will take into account learnings from the previous pilot. An updated
note along with a rollout plan in this regard will be prepared by FCGO and shared with the bank by
January, 15, 2015 for consideration under the AF.
Component 3: Supporting the capacity building of the PEFA Secretariat (USD 350,000)
13. Under Component 3 several achievements have been made by the PEFA Secretariat as
enunciated earlier. There is a need to continue to undertake the outreach, awareness, communication,
training, research and capacity building activities to support PFM reform in Nepal. In addition the AF
under this component will also help support build national PFM training and capacity building
capabilities by partnering with a local academic pioneer institution (like Nepal Administrative Staff
College) and working on developing a PFM core curriculum for public sector practitioners. A
strategy note in this respect will be prepared by PEFA Secretariat and shared with the Bank by
January 15, 2015.
14. Building country capacity for PFM Training Programs: Discussions revolved around
conducting accreditation courses on PFM In-country to address the huge demand that exists for these
courses and skill gaps as are evident in the undertaking of the PFM Reform program across GoN. The
objective of such a program would be to collaborate with both academic (Nepal Administrative Staff
College) and international professional institute (such as CIPFA, CIMA etc.) in order to enhance
knowledge on PFM among public officials. This pilot will later on develop into a full-fledged PFM
training project. For this purpose, the team also visited a prospective academic training institute. To
begin with, a training needs assessment will be included as part of the Feasibility study on
establishing a National Institute of PFM either on a standalone basis or as a department/wing under an
existing institution. This will help assess the need for short term and long term courses. In addition,
these courses will also provide a PFM certification/diploma. Alongside conducting this assessment,
the PEFA Secretariat will identify the national requirements to design the curriculum. The
international professional institute will provide trainers along with course materials while the national
academic institute will provide classrooms, academic infrastructure and also incorporate elements of
these classes to regular courses. The additional financing will fund faculty and the initial fees for the
selected long term courses. It was agreed that GoN will further research on prospective partners to
collaborate with. The implementation modality will be decided upon further discussions with the
prospective partner. Tentative cost estimate for this activity is USD 200,000 which will be confirmed
during further preparation.
15. The Bank team reviewed the updated estimates for the AF which was submitted on Nov 02,
2014. With the further review and suggestions from WB, PEFA coordinator has agreed to submit the
revised AF sheet by Dec 31, 2014. It was noticed that FCGO has not yet finalized Procurement Plan
for the existing project and additional financing as well. These will be submitted by Jan 15, 2015.
16. The project authorities have also included funding requirements for incremental IT staffing
through the AF. These consultants are currently developing, maintaining and supporting the system
and will continue to be deployed through the project extension. The earlier Mission had carried out
an in-depth review of the current IT staffing of the FCGO (Annex 2) and views that retention of key
IT staff and deploying of permanent IT staff of the government on critical positions is critical for the
Annex 4
Page 4 of 6
sustainability of the systems. The review team was informed that this proposal has been approved by
Ministry of Finance and will now go to Cabinet for final approval. A total of five positions have been
created (1 IT Director of the position of a Dy FCG, 2 engineers and 2 Computer operators) and for
which 6 other existing positions in FCGO have been surrendered. The review team was also informed
that after obtaining cabinet approval actual recruitment will take some time as it has go through the
normal bureaucratic channels. It was therefore agreed that FCGO will ensure that (i) necessary cabinet
approval for these 5 new positions is obtained by January 31, 2015 along with concomitant
deployment of the two engineers as consultants (1 hardware engineer and 1 software engineer) in the
FCGO team (appraisal condition).
17. Possible Results Framework under AF: Since the AF will finance existing scope of
activities in terms of PFM results, no revisions are proposed in the results framework (RF) of
component 1 to that extent. Results framework for component 2 and 3 would need to undergo certain
changes as detailed in previous aide memoire. Some suggestions were provided to the review team on
the results framework which are reflected below Since major parts of the AF are expected to flow into
IT infrastructure and for implementation of the RMIS/commitment module, following intermediate
results indicators can be possibly added to the result framework of the component one of the project:
Indicator Unit of
measure
Base-
line
Target values Frequency Data
Source
Responsibility
of data
collection
Description
2016 2017
Roll out of
RMIS at
districts and
paying
centers
No of
districts;
percentag
e of
overall
revenue
Nil 5 15 6 monthly Admin FCGO
RMIS will help
faster accurate
and reconciled
reports on
revenue side.
Rollout of
commitment
recording
across GoN
(Revision
from current
RF)
No of
districts;
percentag
e of
overall
expenditur
e above a
threshold
Nil
Implementat
ion initiated
across all 75
districts
Full
implementati
on along
with
complete
reporting
across all 75
districts
6 monthly admin FCGO
Commitment
information will
help managers
take appropriate
spending
decisions and
will help
improve
expenditure
efficiency
System
based
monitoring
of IT
networks
and devices
NA
Not
possible
Under
implementati
on
Possible 6 monthly
IT unit
of
FCGO
FCGO
Network
enhancement
will enable
remote
monitoring and
auto switching
Average
down time
of system in
last 6
months*
Hours
Xxxxx Xx Xx 6 monthly FMIS FCGO
Due to network
failures, the
system becomes
inaccessible to
the users. This
time should be
decreased or
eliminated.
Online
access of
real time
budget and
financial
information
to
departments
**
No
1 5 10 6 monthly FMIS FCGO
Online access
will help
improve the
decision making
at depts.
Annex 4
Page 5 of 6
Indicator Unit of
measure
Base-
line
Target values Frequency Data
Source
Responsibility
of data
collection
Description
2016 2017
Response
time of the
system at
sample
districts***
Seconds
XX XXX XXX 6 monthly FMIS FCGO
The improved
network will
improve the
response time of
the system
Number of
Calls from
DTCOs
regarding
system
failure,
troubleshooti
ng, ***
No
XX XXX XXX 6 monthly FMIS FCGO
Lower number
of calls means
better IT and
networking
systems in
operation
Audits
regarding
the Security
of IT
Infrastructur
e in FCGO
Third
party
audits
No
audits
Functional
audit carried
out
Full-fledged
IT audit
carried out
6 monthly FMIS FCGO
IT audits will
help make
environment and
landscape more
secure and
identify issues
that need
resolution
Rollout of
NPSAS
across Line
Ministries
No of
Ministries 2 depth
10
ministries.
26
ministries 6 monthly FMIS FCGO
Further rollout
across
Ministries
Capacity
building of
training
Institution
TBD
TBD TBD TBD TBD TBD TBD
TBD
Outcomes
from 3rd
component
(PEFA
Secretariat)
TBD
TBD TBD TBD TBD TBD TBD
TBD
IT Strategy,
organization
structure and
detailed plan
prepared and
implemented
IT strategy/
vision
document
prepared
Organization
structure
prepared and
adequate
staffing in
place
Proper
protocols for
IT
Infrastructur
e and assets
developed
and
implemented
TBD
TBD XX XXX 6 monthly Admin FCGO
FCGO needs to
have a proper
resourced IT
organization to
discharge its
functions
effectively and
efficiently
Annex 4
Page 6 of 6
Current Project Cost
18. Tentative allocation of project costs along with AF and reallocation: The AF will support
all components under the project (although majority will be allocated towards component 1) and The
closing date for existing project will also be extended up to June 30, 20117 to undertake all activities
as envisaged. The table below provides a comparison between original SPFM financing for the
project and the proposed financing after reallocation, extension of closing date and processing of AF
19. Based on the consultant reports and consultations, the tentative breakdown of AF is given below:
S No Description Project Cost US $ World Bank share @ 75%
1 Component 1 4,000,000 3,000,000
2 Component 2 200,000 150,000
3 Component 3 411,747 350,000
Total 4,611,747 3,500,000
Project Management under Additional Financing
Implementation Arrangements
20. Implementation arrangements will likely remain same as that of the original project with
project activities fully aligned with the existing government system. PEFA Secretariat will continue
to serve as the coordinator for the project with monitoring and reporting the implementation progress
of this project and the overall PFM reform program of GoN. TSA system implementation
(Component 1) will continued to be carried out by TSA unit/Treasury Section, separately established
within FCGO, which is coordinated by a Joint Financial Comptroller General. The Accounts
Strengthening Section of the FCGO will continue to be responsible for implementing Component 2
and the PEFA Secretariat will remain responsible for implementation of PFM related capacity
building program under Component 3. The PEFA Steering Committee will provide overall strategic
guidance and oversight. The PEFA secretariat under overall guidance of PFM Reform Steering
Committee and the PFM MDTF Program Coordination Committee will closely coordinate to have an
overall oversight of the PFM program.
Financial Management and Disbursement arrangements
21. The financial management arrangements remain unchanged. The current financial
management rating is “Satisfactory”. The implementing agency is maintaining financial management
system as per the government requirements and no changes are suggested to the current Financial
Management systems and processes. The ongoing review of the financial records reveals that the
procedures in place are considered adequate to ensure that the fiduciary risk is minimized. There are
no outstanding implementation progress reports (IPRs) and the audit reports. The disbursement will
continue to be report-based using the existing reporting formats. The intended funds flow and
Designated Account arrangements will remain the same as in the original project.
Procurement
22. The procurement arrangements will also remain same as that of the component 1 of the
original project. The TSA unit in conjunction with the IT unit will conduct the procurement of the
items under proposed additional financing. A procurement plan for existing project with 2 year
extension and for the additional financing will be prepared by January 7, 2014 and will be finalized
after complete detailed technical review of the proposed project has been completed.
Original Components Original Costs
(US$ million)
MDTF
Proposed restructuring Total
Updated
Cost (US$
million)
Revised Estimated Costs after
reallocation(US$ million)
MDTF
Additional Project Costs
(AF US$ million)
MDTF Component 1:
Implementation of TSA 2.80 3.30 3.00 6.30
Component 2: 0.17 0.17 0.00 0.17
Component 2 (b) 0.58 0.08 0.15 0.23
Component 3: 0.75 0.75 0.35 1.10
Total: 4.30 4.30 3.50 7.80
Annex 5
Page 1 of 2
SPFM Results Framework as of November 30, 2014
Indicator Unit of
Measure
Baseline
December
16, 2010
(*)
Year 2
Target
End-of-
Project
Target
Status as of November 30, 2014
PDO Level Results Indicators*
Percentage of overall
budget executed through
the DTCOs where the
TSA system has been
implemented
Percentage 7 85 98
100% of the budgeted expenditure
With effect from July 16, 2013. End-of-
project target already exceeded
Budget Execution
Reports and Financial
Statements produced by
the TSA system on a real
time basis
Number of
districts Nil 52 75
75 districts
End-of-project target already achieved
Preparation of
consolidated financial
statements for PILOT
Ministries in accordance
with Part 1, Cash IPSAS
;
Number Nil 1 2
IPSAS based financial statements prepared.
ICGFM has certified the statements on 2nd
December,2014
Numbers of research
studies into high priority
PFM areas completed
and disseminated
Number Nil 2 5
2 studies completed.
Other 4 contracts signed with the researchers
and study underway.
1 proposal under evaluation.
INTERMEDIATE RESULTS (Component 1)
Number of DTCOs
where TSA implemented No. 8 60 75
Implemented in all 75 districts.
End-of-project target already achieved
Number of Spending
Unit (SU) Bank
Accounts Closed
No. 1300 12000 14000
13717 bank accounts closed. Action plan
prepared and action started closing balance.
Number of FCGO , line
department and DTCO
staff trained or oriented;
and still deployed to
perform the functions
envisaged
No. 600 5000 5500
7026 staff have been trained and oriented.
End-of-project target already exceeded
Number of master
trainers trained (TSA and
IPSAS and working as
trainers under the project
No. 0 55 75
41 master trainers have been trained in TSA
Software redeveloped
after removing bugs as
reported in current
software;
-
Init
iate
d a
nd
Tes
ted
Fu
nct
ion
al Commitment recording system developed
and implemented from July16, 2014.
RMIS prepared enhancing cash
management/revenue management and
piloted in Kathmandu valley from July 16,
2014.
New features added in
software to meet and
additional feature such as
commitment accounting
- -
Init
iate
d
Fu
nct
ion
al Commitment recording system developed
and implementation started from July16,
2014.
Revenue Management
Information System developed and piloting
started from July 16, 2014.
INTERMEDIATE RESULTS (Component 2)
Preparation of
consolidated financial
statements for PILOT
Ministries in accordance
with Part 1, Cash IPSAS
Number - 1 2
Consolidated financial statements for
PILOT Ministries in accordance with Part 1,
Cash IPSAS is prepared and. They are
certified by ICGFM.
Annex 5
Page 2 of 2
Indicator Unit of
Measure
Baseline
December
16, 2010
(*)
Year 2
Target
End-of-
Project
Target
Status as of November 30, 2014
Listed SOEs prepare
accrual financial
statements in accordance
with IFRS
percentage 0 35% 100%
NFRS (based on IFRS) prepared, approved
and promulgated. Rollout promulgated by
ICAN. TOT provided by ASB in
collaboration with ASSOG.
Implementation of
commitment controls in
the budgetary entities of
GoN (within pilot
ministries)
- -
des
ign
ed
10
0%
of
bu
dg
etar
y
enti
ties
Commitment Control system developed and
implementation started from July 16, 2014.
Number of persons
trained in application of
new accounting
standards based on IFRS
No. - 225 225
20 people + TOT for 20 people
Number of GoN finance
and accounts staff trained
in application of Cash
based IPSAS and still
deployed to perform the
functions envisaged
No. 0 125 500
A workshop conducted with 60 participants
INTERMEDIATE RESULTS (Component 3)
Secretariat manual and
procedures prepared and
implemented
- -
Co
mp
lete
d
Imp
lem
ente
d Operations manual for PEFA secretariat has
been prepared in Nepali and approved by the
Secretariat. Is currently under
implementation
Number of National level
PEFA Steering
committee meetings
supported during the
project period
No. -
6
12
20 in total (16 during the project period)
Number of research
studies completed and
disseminated No. - 6 12
2 studies completed.
4 contracts have been made for conducting
studies.
1 proposal under evaluation.
Carried out repeat PEFA
assessment
-
Co
mp
lete
d
-
PEFA assessment Completed.
Report is going to be sent to the PEFA
Secretariat for final quality check.
Number of seminars &
workshops conducted for
raising PFM awareness
No. - 4 7
59 PFM orientation programs (9 central, 8
regional and 45 district level) conducted. A
high level ownership building program
conducted for the Secretaries of GON in
presence of Finance Minister.
PEFA journal published
and disseminated No.
- 3 volume of PEFA journal and 9th series of
newsletters have been published and
disseminated.
* - Baseline has been taken as the start of the retroactive financing i.e. December 16, 2010
Annex 6
Page 1 of 2
Commitment Accounting – Business process
1. The Gap analysis, done in early 2014, identified a number of issues, some of which have been
addressed. The Gap analysis identified procurement & commitment control as the main components
that are missing from the planned system. GON has received the funding from the World Bank to
address this issue.
2. During initial discussions with FCGO officers it was emphasized that the requirement was for
a simple system to record commitments in excess of a predetermined amount. Therefore a full
procurement system was not needed. The module which is developed is capable of documenting the
processes of:
a. Incurring the commitment (signing of a contract or issuing a purchase order)
b. The full or part clearance of the commitment on payment
3. The commitments are to be used in the calculation of the available budget. This will assist the
spending units in budget management and help to prevent any overspending. Commitments can be
documented for both the current budget year & future budget years. Future budget year commitments
can feed into both the annual budget process & MTEF to ensure that provision has been made.
4. Paying offices are already required to detail liabilities on the closure of each year. This is
documented on return OAG 18 & consists of payments they have been unable to make because the
release has been insufficient.
5. Spending Units are required to submit their cash requirements (OAG 20) for the fiscal year in
a monthly breakdown by economic item. In general, this has been achieved by dividing the annual
budget by twelve, rendering the exercise to be of little use. A commitment system for large items of
expenditure can be used to feed into the cash requirement forecast to give a more accurate picture.
6. Achievement of the main objective, to more realistically calculate the available budget
balance, depends on the creation of the commitment & its removal or reduction need to be
documented.
7. Paying offices currently document certificates of completion of service or delivery of goods.
Provision will also be made for capture of scans of these documents & scans of invoices. This will
more fully document the commitment process. It can be implemented at a later stage of development.
8. Commitment information can also feed into the monthly cash requirement (OAG 20),
submitted by paying offices.
Commitment Module System Flow
It has been decided that the system will be used for the contracts of value NPR 5 lakhs and above.
Spending units sends data to DTCOs after signing of the contract with all the details and payment
schedule. Payment schedule is month wise.
DTCO enters data, Project details, Contractor Details, Type of Service, Payment schedule and
contract details in Commitment Module of TSA.
As per the payment schedule and receipt of invoice, Spending units send request for payment to
DTCO and then it is processed for payment.
Commitment documentation is captured in a new table & is not incorporated into the transactions
table. With this it doesn’t impact on the existing operations of the database.
Annex 6
Page 2 of 2
The commitment data is fed into DTCO screen reports to show the available balances of
budget & release to ensure that no payment is authorized that would exceed these limits.Reporting is
currently being developed.
The main benefit of the commitment system is directed to Paying Offices and Line Ministries.
The system will enhance their ability to manage budget releases and increase the accuracy of the cash
requirement forecast (OAG 20). Therefore, the primary responsibility for documentation &
maintenance of commitments will be that of paying offices. The OAG 20 return is presently not
completed to a very high degree of accuracy. Once the commitment system is running satisfactorily
and with total rollout, this area can be revisited. Each Project Spending Unit has a procurement
section. They are responsible for the maintenance of contracts & issue of purchase orders.
DECS/TSA is maintained & operated at DTCO level; documentation of commitments will be
undertaken by DTCO officers on advice from each Paying Office. Each commitment should be
assigned a unique number. This will be paying office identification followed by a serially numbered
document within the paying office.
The current developed module of Commitment Recording doesn’t cover all expenditure item codes.
Only contracts & purchase orders in excess of a specific value NPR 5 lakhs and above) are
documented. The value is determined by analyzing expenditure transactions over previous years, with
the objective of capturing a predetermined percentage of irregular transactions. Provision has also
been made to capture previous years liabilities, currently advised on the OAG18 return. The
commitment table will document the following:
Commitment Identification (Spending Unit; Commitment Type; Serial number)
Supplier
Date of commitment
Estimated duration of the commitment in months
Estimate of amount payable in each specific month for the current year and totals for the next
two budget years.
Total agreement amount of commitment
Payment Schedule
Provision has not been made for capture of scans of: invoices, goods received notes &
completion of service certificates. Most paying offices do not have scanners & scanning at DTCOs
would increase the workload considerably. Payments made against commitments are advised to
DTCOs by paying offices. Required details to be advised are as follows:
Commitment identification
Paying office request for payment number
Date of request
Amount of payment
The commitments within DECSTSA are incorporated into the budget availability report.
Spending Units ensures that payment requests include cross referencing to any outstanding
commitment. The request does indicate if the commitment is part or full payment, in order that the
DTCO can delete or amend the commitment on authorizing the payment.
Paying Offices advise DTCOs of new commitments & existing commitment maintenance by Excel
spreadsheet in a prescribed format.
Annex 7
Page 1 of 4
Revenue Management Information System (RMIS) - Business process
Background
Bank branches are the government’s revenue collectors, but many are unable to supply timely
& accurate bank statements. This has delayed settlement & contributed to inaccuracies in determining
the weekly central treasury cash position. DTCOs & the FCGO are unable to reconcile the revenue
bank accounts. With the above it was proposed to develop a Revenue Management Information
System (RMIS) which would impose the correct recording of tax receipts on bank branches. Debtors
will be unable to discharge a debt with a paying office unless the receipt is correctly recorded in
RMIS. Bank statement transactions will be cross referenced to RMIS receipts, facilitating bank
reconciliation even if the statement is submitted late.RMIS will overcome long standing issues of
timeliness & accuracy of revenue collection.
Overview
1. The Revenue Management Information System (RMIS) is a module of the Integrated
Financial Management Information System (IFMIS). It is centralized web based system and access is
given to all revenue collecting bank branches.
2. It is managed by DTCOs with the assistance of a coordinating (Lead) bank for each District.
The RMIS system access is given to in DTCOs, Lead Banks and all revenue collecting bank branches
as well as FCGO & NRB to staff through login id and password.
3. Each deposit made by a taxpayer is documented in RMIS by the receiving bank and this
information is cross referenced to the deposit slip. This ensures reconciliation of bank statements with
RMIS data.
4. RMIS generates a unique ID. The taxpayer gets the services from paying office on
presentation of the deposit slip with the unique ID. This ensures that all taxpayer deposits are
documented within the system.
5. The DTCO will use RMIS to generate the daily revenue settlement amount for each bank.
This will later be reconciled with the bank branch statements.
6. The bank’s head office assists the DTCO to follow up any missing data or inaccuracies with
individual bank branches.
7. Revenue detail transaction data is accessible to FCGO. Additionally summary revenue data is
documented in FMIS.
8. Those Paying Offices responsible for revenue collection are connected to the RMIS system.
They verify that the bank deposit slip is genuine and update the transaction with the date of payment.
9. All of the following are connected to RMIS through Intranet/Internet:
DTCO & FCGO
NRB
LEAD BANKS
BANK BRANCHES & BANK HEAD OFFICES
REVENUE COLLECTING OFFICES (Also referred to as Paying Offices)
Annex 7
Page 2 of 4
RMIS System Flowchart
Bank
Paying Office
DTCO
Tax Payer fills out Deposit slip (2 copies)
Submits deposit slip to the bank along with
payment.
Bank stamps the slips and gives one to payee.
Bank enters the data in RMIS system which
generates a Unique ID for each transaction
Submits one stamped slip to the paying office
Paying office verifies the entry/record in the
RMIS system approves and give the services.
DTCO receives branch wise summary data
daily (electronic & hardcopy) from banks
DTCO Receives report from paying offices
monthly (electronic & hardcopy)
Reconciles Bank and Paying Office monthly
Connectivity is through Intranet for
Global Bank/Everest/RBB/NBL &
through Internet for NMB/NRB
Under pilot, 16 branches (80-85
counters) of above banks have
started using RMIS
Annex 7
Page 3 of 4
RMIS System Flow
Bank Branch
10. RMIS will document the following information entered by the receiving bank branch:
Unique ID of deposit slip
District and Sub District
Bank and Bank Branch
Paying Office
Payee details: name, address, telephone no. etc.
Payee VAT or PAN Number
Assessment Number
Account Code (Collecting Agency – Ministry & Department + Revenue indicator {1}).
Revenue Economic Code
Amount
Date of payment
Tax year
The revenue economic code must be created to make revenue data compatible with the format
for expenditure data. This will enable all transactions to be documented in a single table for analysis
at FCGO level.
11. RMIS system sequentially numbers each transaction within a bank branch and generates a
unique number referenced by Bank Branch Code – Transaction Number.
12. The bank branch should include the RMIS reference number on the deposit slip to ensure that
the bank statement can later be reconciled with RMIS data.
13. When data entry is complete, the two deposit slips are stamped & signed and one is given to
the payee. The bank voucher includes all data documented as in Paras 10 & 11, above.
14. The payee takes the stamped deposit slip to the relevant paying office.
Paying Offices
15. The paying office will receive the bank deposit slip from the payee and verify it is genuine by
reference to the unique ID in RMIS.
16. After verification the paying office updates the system with the date of submission of the
deposit slip by the payee. This may be some time after payment & may also be in a different
fiscal year to the date payment was made to the bank.
17. Paying offices only updates the submission date. They have read only access for all other data
relating to their paying office.
DTCO
18. The DTCO is responsible for data maintenance. He has sole responsibility for:
Resolving any queries through the bank head office and bank branch office and making
adjustment to RMIS. Reversal of entry if a cheque is referred to drawer. Authorising
daily settlement on close of DTCO business based on RMIS data. Bank reconciliation
when bank statement is received. Read the daily settlement for each bank branch.
Annex 7
Page 4 of 4
Bank Head Offices
19. Bank Head Offices have read only access to all data from their branches. The system
summaries the data into a daily settlement statement for each bank branch & the total to be
settled by NRB.
Nepal Rastra Bank NRB
20. NRB has read only access to all data.
21. The NRB report advises the daily settlement amount for each bank head office, which
summaries the settlement amounts for each of the main bank’s branches.
22. After agreeing the settlement amount with each bank head office, NRB make the settlement
transactions.