strategic plan progress report - sfmta...feb 02, 2019  · • 2019 communications work plan was...

44
Strategic Plan Progress Report SFMTA Board of Directors Policy and Governance Committee Meeting February 26, 2019

Upload: others

Post on 01-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Strategic Plan Progress Report

SFMTA Board of Directors

Policy and Governance Committee Meeting

February 26, 2019

Page 2: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 1: Create a safer transportation experience for everyone.

Objective 1.1: Achieve Vision Zero by eliminating all traffic deaths.

Objective 1.2: Improve the safety of the transit system.

Objective 1.3: Improve security for transportation system users.

Page 3: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0

2

4

6

8

5.2

FY19 Target: 6.4

Muni collisions per 100,000 miles

FY19FY18

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0

2

44.1FY19 Target: 4.3

SFPD-reported Muni-related crimes per 100,000miles

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0

10

20

1

23

2

Target: 0

Traffic fatalities

Calendar year cumulative total

FY19FY18

201920182017

2010 2011 2012 2014 2015 2016 2017 20180%

20%

40%

60% 57%

54%

FY19 Target (At a stop): 61%

FY19 Target (On a vehicle): 62%

Customer rating: Feeling safe and secure on Muni

On a vehicleAt a stop

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 1 Metrics

3

Page 4: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 1.1: Achieve Vision Zero by eliminating all traffic deaths.

Action 1.1.3: Implement Safe People: Increase community awareness of Vision Zero to create more support for improved traffic safety.

• Initiated the Vision Zero Street Team’s Rapid Response Outreach -- this group works closely with the community in which there was a fatal collision to understand the community’s concerns and communicate that Vision Zero is our priority and no death is acceptable.

• 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation plan will be completed in February.

• New three-year Office of Traffic Safety (OTS) grant application to continue Motorcycle Safety campaign submitted. Year three planning underway.

4

Page 5: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 1.2: Improve the safety of the transit system.

Action 1.2.4: Reduce right and left sideswipe collisions.

Implementation of all eleven recommendations to reduce sideswipes is complete; indications are that the solutions resulted in a 17% reduction in sideswipes.

5

New Initiative: Testing bright LED lights at the tail of the bus in addition to the bumper reflective tape.

Ongoing Work: • Monitoring the impact of these solutions

on reducing sideswipes, including tracking buses with safety decals.

• Refreshing our safety awareness posters with new timely safety messages, including rain-related information.

• Updating the digital safety messaging to our operators.

Page 6: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 1.3: Improve security for transportation system users.

Action 1.3.1: Update employee badge system.

• The ProWatch software upgrade is complete.

• Initiated cross-divisional effort to coordinate the new badging system with email, payroll, and access control functions for more efficient reassignments and separations.

• Security team will take the lead with Communications on distribution of new badges for staff.

6

Page 7: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 2: Make transit and other sustainable modes of transportation the most attractive and preferred means of travel.Objective 2.1: Improve transit service.

Objective 2.2: Enhance and expand use of the city’s sustainable modes of transportation.

Objective 2.3: Manage congestion and parking demand to support the Transit First Policy.

Page 8: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20..

40..

60..

80..

55.3%

Target: 85%

Muni on-time performance (System-wide)

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20%

40%

60%

80%

100..

74.3%

Target: 95%

Muni on-time performance (Terminal departures)

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

5%

10..

15..

20%

16.8%

% of Muni trips with service gaps

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20%

40%

60%

80%

100..95.2%

Target: 98.5%

% of scheduled Muni service hours delivered

FY19FY18

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 2 Metrics

8

Page 9: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

5%

10..

15.. 14.1%Target: 15%FY19 Target: 15%

% of Muni bus trips over capacity (PM Peak)

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20%

40%

60%

80%

100..99.5%

Target: 98%

Operational availability of elevators at Muni stations

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

5%

10..

15..

17.6%

Target: 15%FY19 Target: 15%

% of Muni bus trips over capacity (AM Peak)

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20%

40%

60%

80%

100..97.8%

Target: 97%

Operational availability of escalators at Muni stations

FY19FY18

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 2 Metrics

9

Page 10: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

2,000

4,000

6,000

8,0007,559

FY19 Target: 6,000

Muni mean distance between failure (Trolley Coach)

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

2,000

4,000

6,000

4,962

FY19 Target: 5,300

Muni mean distance between failure (LRV)

Includes Breda car performance

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

5,000

10,0..

11,297

FY19 Target: 10,000

Muni mean distance between failure (Motor Coach)

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

1,000

2,000

3,000 3,128FY19 Target: 2,700

Muni mean distance between failure (HistoricStreetcar)

FY19FY18

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 2 Metrics

10

Page 11: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

2013 2014 2015 2016 20170%

20%

40%

60%54%

FY19 Target: 58%

Sustainable transportation mode share

2010 2011 2012 2014 2015 2016 2017 20180%

20%

40%

60%

80%

63%

FY19 Target: 72%

Customer rating: Overall customer satisfaction withMuni

% rating of good or excelent

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

200,000

400,000

600,000

800,000

671,480

FY19 Target: 729,208

Muni ridership

FY 18 Q2 FY 18 Q3 FY 18 Q4 FY 19 Q1

0%

20%

40%

60%

80%

69.6%

FY19 Target: 35%

% of metered hours that meet parking occupancytargets

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 2 Metrics

11

Page 12: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 2 Metrics

In support of Objective 2.2:

• Average weekday bicycle trips

• Average weekday taxi trips

In support of Objective 2.3:

• Muni average travel time on key transit segments

12Note: Reported results are subject to change as data quality improves or new data become available.

Metrics under development:

Page 13: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 2.1: Improve transit service.

Action 2.1.3: Leverage multi-departmental functions and systems within the Transportation Management Center (TMC). • Harris radio cutover is scheduled to be completed on 3 March 2019. Rail

dispatching is scheduled to transition to the TMC on 23 March 2019.

• Productivity goals have been established and have been incorporated into the Controllers annual performance plans.

• Platform Audio Video (PAV) training plan has been developed. All Public Information Officers have been trained. TMC Controllers have received initial training but will receive a refresher round.

• The TMC transition is not yet complete. All auxiliary positions are not staffed. However, those that are currently in either the Operations Control Center (OCC) or TMC have been trained in coordinating activities and response with TMC Management and Controller staff.

• All tools have been identified and most are currently being used by Controllers assigned to line management. Controllers are actively using the headway monitoring tool along with the performance queue and other support applications to manage service.

13

Page 14: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 2.2: Enhance and expand use of the city’s sustainable modes of transportation.

Action 2.2.4: Complete bikeshare system expansion.

• GoBike station-based system (February 2019):• Average weekday daily trips in SF: nearly 7000

• Total number of stations: 152 (out of 320 stations at full build-out)

• Fleet size: 1,900 (out of 4,500 at full build-out)

• Percentage of the fleet with eBikes: 50%

• Stationless systems: • Completed the stationless shared mobility user survey.

• All stationless operators are now at 100% lock-to design for both bikes and scooters.

14

Page 15: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 2.3: Manage congestion and parking demand to support the Transit First Policy.

Action 2.3.2: Develop a curb management strategy.

• Finalizing interim curb management guidelines for streetscape project managers to incorporate curb management outreach, data collection and implementation into their projects.

• Initial draft of curb management framework complete.

• Curb management roadshow starts with the SFMTA Executive Team and Senior Management Team in next few weeks.

• Anticipated informational item at the Policy and Governance Committee and/or the full SFMTA Board of Directors in summer 2019.

15

Page 16: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 3: Improve the quality of life and environment in San Francisco and the region.Objective 3.1: Use Agency programs and policies to advance San Francisco's commitment to equity.Objective 3.2: Advance policies and decisions in support of sustainable transportation and land use principles.Objective 3.3: Guide emerging mobility services so that they are consistent with sustainable transportation principles.Objective 3.4: Provide environmental stewardship to improve air quality, enhance resource efficiency, and address climate change.Objective 3.5: Achieve financial stability for the agency.

Page 17: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

1/18 2/18 3/18 4/18 5/18 6/18 7/18 8/18 9/18 10/.. 11/.. 12/.. 1/190%

50%

100%

62.8%

96.5%FY19 Enrollment Target: 89%

FY19 Active Use Target: 61%

% of eligible population utilizing free or discountedMuni fare programs (Seniors)

1/18 2/18 3/18 4/18 5/18 6/18 7/18 8/18 9/18 10/.. 11/.. 12/.. 1/190%

20..

40..

28.0%

42.3%

FY19 Enrollment Target: 46%

FY19 Active Use Target: 33%

% of eligible population utilizing free or discountedMuni fare programs (People with disabilities)

1/18 2/18 3/18 4/18 5/18 6/18 7/18 8/18 9/18 10/.. 11/.. 12/.. 1/19

0%

20%

40%

60%

80%

34.5%

76.8%FY19 Enrollment Target: 66%

FY19 Active Use Target: 40%

% of eligible population utilizing free or discountedMuni fare programs (Youth)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec0

5

10

15

0Target: 0

Traffic fatalities in Communities of Concern

Calendar year cumulative total

% of eligible youth enrolled% active use among eligible youth

% of eligible people with disabilities enrolled% active use among eligible people with disabilities

% of eligible seniors enrolled% active use among eligible seniors

201920182017

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 3 Metrics

17

Page 18: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20%

40%

60%

80%73.8%

FY19 Target: 86%

Paratransit on-time performance

FY 12 FY 13 FY 15 FY 17 FY 180%

20%

40%

60%

80%

100..84.0%FY19 Target: 85.0%

Customer rating: Overall customer satisfaction withparatransit services

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

5%

10..

15..

20..

16.5%

FY19 Systemwide Gaps Avg: 18%

% of Muni trips with service gaps on Equity Strategyroutes

1990 2000 2005 2010 2012 2015 20160M

1M

2M

3M

2,547,222

2018 Target: 1.83M mtCO2e

Transportation sector carbon footprint (metric tonsCO2e)

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 3 Metrics

18

Page 19: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

5,000,000

10,000,0..9,816,356FY19 Target: 1000000000%FY19 Target: 10,000,000

Agency Electricity (kWh) consumption

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

500,000

1,000,0..

1,500,0..

2,000,0..

2,500,000

1,589,844

FY19 Target: 1,100,000

Agency Water (Gallons) consumption

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20..

40..

60..

32.2%

FY19 Target: 67%

Agency waste diversion rate

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

20,0..

40,0..34,646

FY19 Target: 3000000%Target: 30,000

Agency Natural Gas (Therms) consumption

FY19FY18

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 3 Metrics

19

Page 20: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY 17$0

$100

$200 220.39

FY19 Target: $229.21

Muni cost per revenue hour

FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY 17$0

$1

$2

$3

$43.54FY19 Target: $3.68

Muni cost per unlinked trip

FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY 170%

20%

40%

60%

80%

100..

18.3%FY19 Target: 12.5%

2007 reserve policy: 10%

Agency fund balance ratio

FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY 170%

10..

20..

30..

24.5%

FY19 Target: 26.7%

Muni farebox recovery ratio

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 3 Metrics

20

Page 21: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

FY 15 FY 16 FY 170%

50%

100.. 101.0%

FY19 Target: 112%

Muni cost recovery ratio

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 3 Metrics

21

Page 22: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

EXPENDITURESRevised

Budget (1)Actuals

Year to DateEncumbrances

Total Projection for the Year

Projected Saving/

(Overage)

SFMTA Agency Wide $150,306,100 $76,232,055 $8,648,373 $150,999,145 ($693,045)

Board of Directors $728,933 $326,416 ($10) $653,310 $75,623 Capital Programs and Construction $3,406,214 $2,115,985 $254,074 $3,406,214 $0

Communications $8,956,114 $3,127,677 $1,490,591 $8,322,588 $633,526

Director of Transportation $843,236 $596,020 $4,539 $853,073 ($9,837)

Finance and Information Technology $119,642,405 $49,959,090 $33,346,850 $117,671,906 $1,970,499

Government Affairs $1,317,578 $535,397 $0 $1,307,557 $10,021

Human Resources $39,845,064 $14,133,747 $5,338,757 $38,390,191 $1,454,873

Safety $5,748,217 $2,370,529 $1,983,972 $7,031,402 ($1,283,185)

Sustainable Streets $164,990,935 $63,973,737 $39,468,338 $165,457,305 ($466,370)

Transit Services $679,027,402 $306,470,535 $52,595,120 $679,586,437 ($559,035)

Taxi and Accessible Services $39,045,082 $12,842,743 $20,204,736 $38,267,137 $777,945

TOTAL $1,213,857,280 $532,683,931 $163,335,340 $1,211,946,265 $1,911,015

(1) Revised budget includes encumbrance and manual carry forward from FY18 of $73.9 million.

Goal 3 FinancialsExpenditures (FY19 as of December 2018)

22

Page 23: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

REVENUE Revised Budget Actuals

Year to Date Total Projection

for the Year Projected Surplus/

(Deficit)

TRANSIT FARESCable Car Fares $27,851,989 $14,188,372 $26,885,956 ($966,033)Cash Fares $4,638,394 $1,968,604 $4,496,849 ($141,545)Other Fares $90,054,604 $44,581,021 $92,045,019 $1,990,415 Passes $81,338,312 $38,149,729 $79,870,067 ($1,468,245)TRANSIT FARES Total $203,883,299 $98,887,726 $203,297,891 ($585,408)PARKING FEES & FINESGeneral Fund Baseline Transfer $68,430,000 $34,215,000 $66,820,000 ($1,610,000)Citations and Fines $122,924,970 $59,654,882 $119,698,998 ($3,225,972)

Garage Revenue $73,231,655 $37,269,119 $73,395,670 $164,015

Meter Revenue $69,481,987 $30,439,287 $60,878,573 ($8,603,414)Permit Revenue $22,378,320 $9,013,657 $25,518,038 $3,139,718

PARKING FEES & FINES Total $356,446,932 $170,591,945 $346,311,279 ($10,135,653)Operating Grants $161,239,588 $40,733,587 $161,239,588 $0 Taxi Service $2,399,331 $805,047 $1,635,844 ($763,487)Other Revenues $34,150,468 $17,559,944 $38,053,962 $3,903,494 General Fund Transfer $336,320,000 $168,160,000 $353,130,000 $16,810,000

Fund Balance for Current Year Budget $33,200,000 $0 $33,200,000 $0

Transfer from Non-operating Fund $15,932,616 $15,932,616 $15,932,616 $0 Fund Balance from Prior Year Encumbrance Carry Forward $73,935,046 $73,935,046 $73,935,046 $0

TOTAL $1,217,507,280 $586,605,911 $1,226,736,226 $9,228,946

Goal 3 FinancialsRevenues (FY19 as of December 2018)

23

Page 24: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

FUND/DIVISIONAnnual Revised Budget

Actual FiscalYear to Date

(1)

Projection for Remaining

Months

End of Year Projection

Projected Surplus/(Deficit)

OPERATING FUND

TRANSIT SERVICES DIVISIONTransit Operators(2) $17,975,620 $18,254,312 $36,229,931 ($36,229,931)Transit Vehicle Maintenance $6,718,500 $8,770,617 $6,102,039 $14,872,656 ($8,154,156)

Transit – All Others $27,680,651 $6,243,061 $2,857,925 $9,100,986 $18,579,665

Subtotal Transit Services Division $34,399,151 $32,989,298 $27,214,276 $60,203,573 -25,804,422

SUSTAINABLE STREETS DIVISIONParking Control Officers $994,984 $903,609 ($1,537,194) ($633,585) $1,628,569 Sustainable Streets – All Others $629,714 $349,283 ($696,410) ($347,127) $976,841

Subtotal Sustainable Streets Division $1,624,698 $1,252,892 ($2,233,604) ($980,712) $2,605,410

SFMTA AGENCY WIDE $0 $0 $0 $0 $0

ALL OTHER DIVISIONS $838,164 $898,997 $656,242 $1,555,240 ($717,076)

TOTAL OPERATING FUND $36,862,013 $35,141,187 $25,636,914 $60,778,101 ($23,916,088)

NON-OPERATING FUNDCapital Programs & Construction $0 $2,625,522 $5,004,818 $7,630,340 ($7,630,340)

Sustainable Streets Engineering Programs $0 $903,852 $936,091 $1,839,944 ($1,839,944)

Total Non-Operating Fund $0 $3,529,374 $5,940,909 $9,470,284 ($9,470,284)TOTAL $36,862,013 $38,670,561 $31,577,823 $70,248,385 ($33,386,372)

(1) Reported overtime actuals and resulting deficit are net of cost recovery for events or services that includes reimbursements for payroll (both regular and overtime), overhead, and other non-labor costs as applicable. The total actual cost recoveries is $2.0M.(2) Transit Operators budget is included in Transit - All Others budget.

Goal 3 FinancialsOvertime Report (FY19 as of PPE 12.28.18)

24

Page 25: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 3 Metrics

In support of Objective 3.3:

• Number of trips using Emerging Mobility Services (EMS)

• EMS collisions per 100,000 miles

• Percent of EMS trips provided to and from Communities of Concern

• Number of EMS trips provided to people with disabilities

In support of Objective 3.5:

• Year-end investment toward State of Good Repair

25Note: Reported results are subject to change as data quality improves or new data become available.

Metrics under development:

Page 26: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 3.1: Use Agency programs and policies to advance San Francisco’s commitment to equity.

Action 3.1.6: Increase enrollment in Lifeline and Free Muni Program.

• Working with SFUSD staff to identify opportunities to incorporate Free Muni for Youth application into Free/Reduced Lunch application process in order to improve participation rates.

• Coordinating with Transit Services Division to add “Don’t forget to tag your Clipper card” to on-board vehicle messages in order to improve data collection efforts for Free Muni programs.

• Participating in weekly project management meetings for the implementation of the regional low-income adult single fare discount program on Clipper – estimated implementation November 2019.

26

Page 27: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 3.2: Advance policies and decisions in support of sustainable transportation and land use principles.

Action 3.2.3: Optimize the agency’s role in ongoing and emerging regional planning initiatives to support the key transit improvement efforts.

• Held brainstorming session among senior managers to identify key programs and initiatives in the region for our agency to track, both now and in the near future.

• Coordinating with partners at SFCTA and SF Planning to engage in MTC’s Horizon effort, taking part in March workshop.

27

Page 28: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

• Developing a Policy Framework that will assess the implications of autonomous vehicles in the city.

• Using the Emerging Mobility Guiding Principles approved by SFMTA Board and the SF County Transportation Authority as a guide for this work.

• Meeting with city and community stakeholders to better understand these potential impacts.

Objective 3.3: Guide emerging mobility services so that they are consistent with sustainable transportation principles.

Action 3.3.4: Develop the AV Policy Framework

28

Safety

Transit

Equitable Access

Disabled Access

Congestion

Sustainability

Financial Impact

Accountability

Labor

Collaboration

Page 29: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 3.4: Provide environmental stewardship to improve air quality, enhance resource efficiency, and address climate change.

Action 3.4.2: Increase the climate resiliency of San Francisco's multimodal transportation system. SFMTA Transit and Planning teams are working with three citywide planning projects to evaluate the risk of flooding to the transit system, coordinate research methodologies, share data, and leverage staff resources:

1. SF Sea Level Rise Vulnerability Assessment: draft assessment highlighting the vulnerability of the multimodal transportation system to flood risk will be shared in March.

2. Army Corps of Engineers General Investigation and Southeast Mobility Adaptation Study: kick-off workshop in March in the Bayview to engage the community on developing strategies to build more resilient communities, shorelines and transportation infrastructure (led by the Planning Department and the Army Corps of Engineers).

3. Ocean Beach Master Plan: in implementation phase and project aims to improve the resiliency of the multimodal transportation system at the southern extent of the Great Highway, near Sloat Blvd.

29

Page 30: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 3.4: Provide environmental stewardship to improve air quality, enhance resource efficiency, and address climate change.

Action 3.4.4: Implement the Battery Electric Bus Pilot and establish support infrastructure for electric non-revenue sedans.• December 2018 – Advertised RFP for procurement of 9 40-foot

Battery-Electric buses from at least 3 different manufacturers. Bids due in mid-March 2019.

• February 2019 – Advertised RFP for procurement of the Woods Division Battery-Electric Bus Charging Solution. Bids due end of March 2019.

• CP&C continues to coordinate with PG&E through SFPUC to upgrade the Woods Division Yard utility power to accommodate the eBus Charging Solution infrastructure.

• PG&E’s draft System Impact Study (SIS) report detailing the available utility input power capacity to the site is expected to be issued this month, February 2019.

30

Page 31: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 3.5: Achieve financial stability for the agency.

Action 3.5.6: Implement an SFMTA Asset Management Program.

Completed:• Development an Agency-wide Asset Management Program

• MTC Regional Transit Capital Inventory Update completed in the summer.

• FTA Transit Asset Management Plan completed in the fall including new Asset Management Policies, State of Good Repair Policies, Asset Hierarchy and update Capital Asset Inventory

In Process: • 2018 State of Good Repair Report

• 10-Year SFMTA Asset Management Strategy.

• Going forward will include a 3% escalation factor for year of replacement to better accurately reflect the SFMTA's State of Good Repair needs.

31

Page 32: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 4: Create a workplace that delivers outstanding service.

Objective 4.1: Strengthen morale and wellness through enhanced employee engagement, support, and development.

Objective 4.2: Improve the safety, security, and functionality of SFMTA work environments.

Objective 4.3: Enhance customer service, public outreach, and engagement.

Objective 4.4: Create a more diverse and inclusive workforce.

Objective 4.5: Increase the efficiency and effectiveness of business processes and project delivery through the implementation of best practices.

Page 33: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

5

10

15

10.1

FY19 Target: 12.2

Workplace injuries per 200,000 hours

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

50

100

150

200

111

FY19 Target: 201

Muni employee commendations to 311

2014 2015 2016 2017 20180%

20%

40%

60%

50%

FY19 Target: 57%

Employee rating: Overall employee satisfaction

% rating of somewhat or very satisfied

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0

20

40

60

80

61.7FY19 Target: 68.5

Muni customer complaints per 100,000 miles

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 4 Metrics

33

Page 34: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

20%

40%

60%

80%80.5%

FY19 Target: 80%

% of Muni Passenger Service Reports addressedwithin timeliness standards

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

50%

100..

74.0%

FY19 Target: 90%

% of Color Curb Requests addressed withintimeliness standards

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

50%

100%

32.0%

FY19 Target: 90%

% of Muni Passenger Service Reports responded towithin timeliness standards

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

50%

100..100.0%

FY19 Target: 100%

% of Hazardous Traffic Sign Reports addressedwithin timeliness standards

FY19FY18

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 4 Metrics

34

Page 35: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

50%

100..

81.5%

FY19 Target: 90%

% of Parking Meter Malfunction Reports addressedwithin timeliness standards

Q1 Q2 Q3 Q40%

20%

40%

60%

80%90.3%

FY19 Target: 80%

% of Traffic and Parking Control Requestsaddressed within timeliness standards

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun0%

50%

100..98.6%

FY19 Target: 92%

% of Hazardous Traffic Signal Reports addressedwithin timeliness standards

2010 2011 2012 2014 2015 2016 2017 20180%

20%

40%

60% 55%FY19 Target: 57%

Customer rating: Muni communication with riders

% rating of good or excelent

FY19FY18

FY19FY18

FY19FY18

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 4 Metrics

35

Page 36: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

2013 2014 2015 2016 2017 20180%

20%

40%

60%

38%

FY19 Target: 57%

Employee rating: My concerns, questions, andsuggestions are welcomed and acted upon quicklyand appropriately

2017 20180%

20%

40%

60%53%

FY19 Target: 57%

Employee rating: I feel that the Agency valuesworkplace diversity

Note: Reported results are subject to change as data quality improves or new data become available.

Goal 4 Metrics

36

Page 37: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Goal 4 Metrics

In support of Objective 4.1:• Employee unscheduled absence rate• Employee wellness program utilization rate

In support of Objective 4.2:• Security incidents involving SFMTA employees

In support of Objective 4.3:• Community rating: Feeling of being informed about SFMTA projects

In support of Objective 4.5:• Percentage of capital projects initiated/completed on time • Percentage of capital projects completed within budget• Service critical operations and maintenance staff vacancy rate • Percentage of sign and meter work orders completed within timeliness

standards

37

Metrics under development:

Page 38: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 4.1: Strengthen morale and wellness through enhanced employee engagement, support, and development.

Action 4.1.2: Develop and implement training services.

In implementation:

• Respect in the Workplace

• Building and Leading Effective Teams

• Effective Meeting Facilitation

• Emotional Intelligence

Programs in development:

• How to have Difficult Conversations

• Effective decision-making process

• How to provide meaningful and helpful feedback

38

Page 39: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 4.2: Improve the safety, security, and functionality of SFMTA work environments.

Action 4.2.4: Develop an SFMTA Campus Master Plan.

39

Potrero Yard Modernization Project

Page 40: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 4.2: Improve the safety, security, and functionality of SFMTA work environments.

Action 4.2.4: Develop an SFMTA Campus Master Plan.

40

Potrero Yard Modernization Project

Page 41: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 4.3: Enhance customer service, public outreach, and engagement.

Action 4.3.4: Develop and implement the Customer Service Strategy.

• Working with Transit Managers to coordinate commendation promotions.

• Drafting a questionnaire for Passenger Service Report (PSR) investigators to identify process challenges and improvements.

• Muni Customer Service Team added to agencywide Salesforce Customer Relationship Management (CRM) system for improved customer communication and research.

• Awarded As-Needed Specialized Training Services for specialized training in customer service, incident de-escalation and management of implicit bias, as well as coaching for supervisors and managers.

41

Page 42: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 4.4: Create a more diverse and inclusive workforce.

Action 4.4.5: Establish guidelines for the SFMTA Internship Program recruitment process.

• The citywide internship program is a critical entry point to joining the SFMTA, as many interns later find full-time employment with the agency.

• Interns are hired into more than 10 different groups across the agency’s divisions.

• Opportunities include: summer placements in planning, engineering and project management; automotive programs with the Transit facilities; and placements at the Sustainable Streets’ Meter, Sign, and Paint Shops.

• Outreach is tailored to the program, including (but not limited to):• Communications and job postings to colleges and universities nationwide;

including 20+ local community colleges and smaller universities• College Interactive Career Workshops• Participation with Washington High’s Automotive Pathway Program• SFMTA site visits for local high school students

42

Page 43: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Objective 4.5: Increase the efficiency and effectiveness of business processes and project delivery through the implementation of best practices.

Action 4.5.3: Implement the Project Delivery Framework.

Seven of the 14 recommendations in the 2016 Project Delivery Framework have been completed, including:

• Most recently, a new Project Management Training Program (Recommendation 7) has been created

• All active Transit Division Projects are being added to the centralized PM system (Recommendation 5) for the Agency's new Quarterly Capital Report

• New KPIs have been developed for project delivery, and technical requirements have been developed for updates to the budget revision electronic system.

• A Project Management Office (PMO) General Notice was approved setting new standards on cost estimating with the development of a new cost estimating tool and to fully operationalize the Agency's Public Outreach and Engagement Requirements.

43

Page 44: Strategic Plan Progress Report - SFMTA...Feb 02, 2019  · • 2019 Communications work plan was finalized. Safe Routes to Schools planning work continues apace. A draft implementation

Next Strategic Plan Progress Update in May 2019.