strategic investment model for future distribution network planning · 2019. 5. 30. · mpr4 to...
TRANSCRIPT
Strategic Investment Model for Future
Distribution Network Planning
Session 2 Goran Strbac | Imperial College London
Panos Papadopoulos | UK Power Networks
In partnership with:
2011. UK Power Networks. All rights reserved
The challenge…
• Validate that extra capacity was created in the FPP trial area using the
right interventions at the right places of the network
• Design, develop and leave a tool behind that can help UKPN and other
DNOs identify other areas of the network to optimise using the
appropriate interventions
Strategic Investment Model
Successful completion of the FPP Strategic Investment Model including
validation and testing of the model utilising data captured within the FPP trials
2
2011. UK Power Networks. All rights reserved
March Grid
RPF
36MVA
Legend
March Primary 11kV Network
G G
Whittlesey
Chatteris Primary 11kV Network
GBurnt
House
PV
Greenvale
Produce
WTG
Great Acre
Fen PV Longhill Road No.2
WTG
Boardinghouse
WTG
MPR1
33kV
MPR3
Peterborough
Central Grid
RPF
30MVA
Bu
ry 1
1kV
Ne
two
rk
G
G’s Fresh
PV
GRamsey 2
WTG
Funtham’s
Lane
Farcet
G
Allpress/HolyHouse
CHP
Bank Farm
PV
P90
G
Langwood
PV
G
G
G
Chaterris Road
WTG
G
Mepal Fen
WTG
G
MPR2
MPR4
To
Downham
T-Point
To
Northworld
Primary
Wissington
G5Honeysome Road
Chaterris PV
RPF limit assumes total connected
+ accepted generation. Constraint
at 132kV side of the network
DG growth and network constraints
2014 / 2015
33kV
132kV
11kV
Legend
Normally Open Point
FPP GeneratorG
132/33 kV Transformer
33/11 kV Transformer
Overload
Partly Overload
(4.8) (10.3)
(7.2)
(5.1) (1.1)
(7.0)
(x) Installed DG capacity Pudjianto, D., Djapic, P.,
Kairudeen, S. and Strbac, G.
(2014)
Strategic Investment Model for
future Distribution Network
Planning, report for the Flexible
Plug and Play Project:
Imperial College London, pp. 40
3
*Excludes all firm generators connected, only
few selected FPP generators are shown.
2011. UK Power Networks. All rights reserved
DG growth and network constraints
2016 / 2017
March Grid
RPF
36MVA
Legend
March Primary 11kV Network
G G
Whittlesey
Chatteris Primary 11kV Network
GBurnt
House
PV
Greenvale
Produce
WTG
Great Acre
Fen PV Longhill Road No.2
WTG
Boardinghouse
WTG
MPR1
33kV
MPR3
Peterborough
Central Grid
RPF
30MVA
Bu
ry 1
1kV
Ne
two
rk
G
G’s Fresh
PV
GRamsey 2
WTG
Funtham’s
Lane
Farcet
G
Allpress/HolyHouse
CHP
Bank Farm
PV
P90
G
Langwood
PV
G
G
G
Chaterris Road
WTG
G
Mepal Fen
WTG
G
MPR2
MPR4
To
Downham
T-Point
To
Northworld
Primary
Wissington
G5Honeysome Road
Chaterris PV
RPF limit assumes total connected
+ accepted generation. Constraint
at 132kV side of the network
33kV
132kV
11kV
Legend
Normally Open Point
FPP GeneratorG
132/33 kV Transformer
33/11 kV Transformer
Overload
Partly Overload
(x) Installed DG capacity
(20.0) (30.6)
(21.5)
(15.8) (3.1)
(29.4)
4
*Excludes all firm generators connected, only
few selected FPP generators are shown.
2011. UK Power Networks. All rights reserved
DG growth and network constraints
2018 / 2019
March Grid
RPF
36MVA
Legend
March Primary 11kV Network
G G
Whittlesey
Chatteris Primary 11kV Network
GBurnt
House
PV
Greenvale
Produce
WTG
Great Acre
Fen PV Longhill Road No.2
WTG
Boardinghouse
WTG
MPR1
33kV
MPR3
Peterborough
Central Grid
RPF
30MVA
Bu
ry 1
1kV
Ne
two
rk
G
G’s Fresh
PV
GRamsey 2
WTG
Funtham’s
Lane
Farcet
G
Allpress/HolyHouse
CHP
Bank Farm
PV
P90
G
Langwood
PV
G
G
G
Chaterris Road
WTG
G
Mepal Fen
WTG
G
MPR2
MPR4
To
Downham
T-Point
To
Northworld
Primary
Wissington
G5Honeysome Road
Chaterris PV
RPF limit assumes total connected
+ accepted generation. Constraint
at 132kV side of the network
33kV
132kV
11kV
Legend
Normally Open Point
FPP GeneratorG
132/33 kV Transformer
33/11 kV Transformer
Overload
Partly Overload
(x) Installed DG capacity
(30.1) (36.5)
(25.6)
(20.6) (3.7)
(44.3)
5
*Excludes all firm generators connected, only
few selected FPP generators are shown.
2011. UK Power Networks. All rights reserved
DG growth and network constraints
2020 / 2021
March Grid
RPF
36MVA
Legend
March Primary 11kV Network
G G
Whittlesey
Chatteris Primary 11kV Network
GBurnt
House
PV
Greenvale
Produce
WTG
Great Acre
Fen PV Longhill Road No.2
WTG
Boardinghouse
WTG
MPR1
33kV
MPR3
Peterborough
Central Grid
RPF
30MVA
Bu
ry 1
1kV
Ne
two
rk
G
G’s Fresh
PV
GRamsey 2
WTG
Funtham’s
Lane
Farcet
G
Allpress/HolyHouse
CHP
Bank Farm
PV
P90
G
Langwood
PV
G
G
G
Chaterris Road
WTG
G
Mepal Fen
WTG
G
MPR2
MPR4
To
Downham
T-Point
To
Northworld
Primary
Wissington
G5Honeysome Road
Chaterris PV
RPF limit assumes total connected
+ accepted generation. Constraint
at 132kV side of the network
33kV
132kV
11kV
Legend
Normally Open Point
FPP GeneratorG
132/33 kV Transformer
33/11 kV Transformer
Overload
Partly Overload
(x) Installed DG capacity
(38.6) (38.8)
(27.2)
(24) (3.9)
(56.8)
6
*Excludes all firm generators connected, only
few selected FPP generators are shown.
2011. UK Power Networks. All rights reserved
DG growth and network constraints
2022 / 2023
March Grid
RPF
36MVA
Legend
March Primary 11kV Network
G G
Whittlesey
Chatteris Primary 11kV Network
GBurnt
House
PV
Greenvale
Produce
WTG
Great Acre
Fen PV Longhill Road No.2
WTG
Boardinghouse
WTG
MPR1
33kV
MPR3
Peterborough
Central Grid
RPF
30MVA
Bu
ry 1
1kV
Ne
two
rk
G
G’s Fresh
PV
GRamsey 2
WTG
Funtham’s
Lane
Farcet
G
Allpress/HolyHouse
CHP
Bank Farm
PV
P90
G
Langwood
PV
G
G
G
Chaterris Road
WTG
G
Mepal Fen
WTG
G
MPR2
MPR4
To
Downham
T-Point
To
Northworld
Primary
Wissington
G5Honeysome Road
Chaterris PV
RPF limit assumes total connected
+ accepted generation. Constraint
at 132kV side of the network
33kV
132kV
11kV
Legend
Normally Open Point
FPP GeneratorG
132/33 kV Transformer
33/11 kV Transformer
Overload
Partly Overload
(x) Installed DG capacity
(42.4) (39.3)
(27.6)
(25.6) (4.0)
(62.6)
7
*Excludes all firm generators connected, only
few selected FPP generators are shown.
2011. UK Power Networks. All rights reserved
The challenge required a multitude
of problems to be solved
• High DG penetration triggers network reinforcements
– Thermal overloads
– Voltage rise
– New protection
• A shift to more active network requires strong coordination between operation
and network planning:
– Interactions are complex and need to be supported by appropriate
modelling tools
• Multi year optimisation of investment and operation
– Incremental planning, currently based on load growth may not be very
efficient in systems with rapid changes (e.g. with high DG). Strategic
planning with generation growth uncertainties should be considered
8
2011. UK Power Networks. All rights reserved
Problem formulation to be solved by
the Strategic Investment Model
Minimise total operating and investment cost across multi-year time horizon by:
• Investment cost:
– Traditional network reinforcement
– Quadrature-boosters;
– Dynamic line rating capability;
– Reactive compensation;
– Advanced protection to improve reverse power capability in a substation.
• Operating cost:
– Cost of DG curtailment
– Network Losses
• Commercial arrangement:
− Firm connection
− LIFO, pro-rata
9
The SIM uses a multi-year security constrained AC Optimal Power Flow
algorithm to solve AC power flow problems and to model ANM.
2011. UK Power Networks. All rights reserved
Strategic Investment Model inputs
and outputs
10
• Generation & load growth scenarios
• Generation, network, load data
• Models of:
– Smart grid technologies devices
– Smart commercial arrangements
– Other smart solutions (other LNCF projects)
• Costs
• Timescales of traditional and smart solutions
• CO2 emissions of DG
• Electricity prices and carbon intensity of national generation mix
• Set of alternative solutions
Inputs
• Identify triggers for
network reinforcement
• Impacts on network and
DG operation
• Prioritisation of different
technical and commercial
solutions
• Curtailment estimation
Outputs Strategic
Investment
Model with an
Excel-based
interface
2011. UK Power Networks. All rights reserved
An example of a traditional network
reinforcement solution costing £5.1m
11
CAPEX: £5.1m
• Network based solution
• Passive operation
• Firm network access
• Low utilisation
2011. UK Power Networks. All rights reserved
The solution proposed by FPP’s SIM
reduces costs to £1.75m
12
SIM deploys minimum investment at the right location taking into account both
traditional and smart solutions. CAPEX: £1.75m
2011. UK Power Networks. All rights reserved
Learning outcome 1:
The value of FPP’s smart solutions
Cost (period 2014/18)
13
The FPP solutions are cost-effective
2011. UK Power Networks. All rights reserved
Comparison of emissions and cost
performance indicates a trade-off
14
Emissions of the FPP approach is slightly higher than the traditional solution due to
increased losses and curtailment of DG output but this is achieved at significantly
lower costs.
2011. UK Power Networks. All rights reserved
Learning outcome 2:
Strategic versus incremental planning
(1 of 2) Wind 1
Wind 2
PV 1 PETC-FARC_1 [13 MVA]
Wind 1 CHP 1 FARC_1-GLAS_1 [15 MVA]
Wind 2 PV 1 CHAT_2-BOAR_1 [31 MVA]
BOAR_1-MARCH [15 MVA] PV 3 BOAR_1-MARCH [31 MVA]
PV 1 MARCH132-MARCH [90 MVA] Wind 1 BANK_FM-MARCH [31 MVA]
Wind 1 GLAS_1-REDTT_1 Wind 2 MARCH132-MARCH [180 MVA]
Wind 2 Wind 2 B14-CHAT_2 RAMSEY [2 Mvar] PETC-FARC_1
WISS-NOWNT [31MVA] BOAR_1-MARCH BANK_FM-MARCH B14-CHAT_2 [19 MVA] FARC_1-GLAS_1
PETC-FARC_1 BOAR_1-BOAR BOAR_1-MARCH BHWS-B14 [30 MVA] B14-CHAT_2
FARC_1-GLAS_1 MARCH132-MARCH MARCH132-MARCH CHAT_2-BOAR_1 BOAR_1-MARCH
14/15 16/17 18/19 20/21 22/23
PV 1
Wind 1
PETC-FARC_1 [13 MVA]
B14-CHAT_2 [19 MVA] PV 1
BOAR_1-MARCH [31 MVA] Wind 1
MARCH132-MARCH [180 MVA] Wind 2
WISS-NOWNT [31MVA] GLAS_1-REDTT_1 FARC_1-GLAS_1 [15 MVA]
PETC-FARC_1 PV 1 BANK_FM-MARCH CHAT_2-BOAR_1 [31 MVA]
FARC_1-GLAS_1 Wind 1 PETC-FARC_1 BANK_FM-MARCH [31 MVA] PV 1
BOAR_1-MARCH Wind 2 BOAR_1-MARCH BHWS-B14 [30 MVA] Wind 2
MARCH132-MARCH BOAR_1-BOAR MARCH132-MARCH FARC_1-GLAS_1 REDTT_1-RAMSEY
14/15 16/17 18/19 20/21 22/23
Incre
men
tal
Strategic approach:
- Benefits from economies of scale
- Avoid reinforcing a network section twice in the short-term brings
forward network investment rather postponing with smart solutions
ANM
QB
DLR
New protection
New transformer
New OHL
15
2011. UK Power Networks. All rights reserved 16
Learning outcome 2:
Strategic versus incremental planning
(2 of 2)
Strategic investment approach ensures the least cost development of the system in
the long term while the incremental investment approach minimises the short-term
cost by using aggressive “smart” solutions but may lead to higher long-term cost as
the short-term decisions may be sub-optimal.
2011. UK Power Networks. All rights reserved
Learning outcome 3:
Least-Worst Regret development strategy
Connection to
Farcet or
Glassmoor ?
Traditional short-term strategy is to
connect the new DG to Glassmoor.
SIM chooses to connect to Farcet
(Least-Worst Regret solution) as the
future cost of reinforcing Peterborough
Central (PETC) – Glassmoor (GLAS) is
high.
Scenario Growth Capacity (MW) Wind Commercial
Solar PV Wind Commercial
Solar PV
Zero 0% 0% 104 47
Low 34% 82% 139 85
Medium 47% 173% 152 127
High 65% 251% 170 163
17
2011. UK Power Networks. All rights reserved
Least-Worst Regret
18
Due to high DG growth,
Peterborough Central to Farcet will
need to be reinforced and therefore
the connection of new DG will have
smaller effect.
2011. UK Power Networks. All rights reserved
Recommendation 1:
From incremental to to long-term
strategic planning
• More cost effective than the current traditional incremental investment
approach
• Optimal portfolio of smart and traditional network solutions
• Long-term strategic planning involves anticipatory investment
• Understand risks associated with uncertainty in future development
19
2011. UK Power Networks. All rights reserved
Recommendation 2:
Further development in commercial
frameworks
• Facilitate investment that provide flexibility to deal with uncertainty
– Balance the cost to existing and future network users and enable least cost
evolution to lower carbon future
• Develop mechanism/process to facilitate pro-active roll-out of FPP concepts
and solutions
20
2011. UK Power Networks. All rights reserved
For more information visit ukpowernetworks.co.uk/innovation
Successful deployment of new commercial arrangements and interoperable
smart grid components to deliver faster and cheaper DG connections
Engaged with 50+ DG developers
Interviewed 20
Trialled two DG access principles:
LIFO and Pro–rata capacity quota
Made 40 connection offers:
• 15 accepted, 54.4MW enabled,
£44m savings
Commissioned RF mesh wireless
network for wide area comms
Developed analysis tool for
investment options in DG
dominated networks
Integrated and commissioned smart
devices across 12 sites
Deployed IEC 61850 for
interoperability between solution
components
Installed and commissioned first
quad-booster at 33kV
Key achievements of Flexible Plug and Play
21