STEREO SWG #16

March 27-28, 2007

Hilton Garden Inn

Greenbelt, MD

STEREO ‘Project’ StatusMarch 27, 2007

M. Kaiser•Handover from Project very smooth (see next)•In good financial shape

–CR not a problem –Total through end of mission is fine–Debbie Chipouras, Stephanie Gray, Valerie Lewnes

•Press/PAO activities doing well–Panorama and transit release in early March–3-D release April 23

•Senior review next round!•Guest investigator proposals due 5/11/2007•Please keep me informed!!

STEREO Organization During Phase B/C/DProject Manager

Nick ChrissotimosDeputy Project Manager

Jim AdamsDeputy Project Manager/Instruments

Mike DelmontDeputy Project Manager/Resources

Rich Ryan

Project ManagerNick Chrissotimos

Deputy Project ManagerJim Adams

Deputy Project Manager/InstrumentsMike Delmont

Deputy Project Manager/ResourcesRich Ryan

Project ScientistMichael Kaiser

Project ScientistMichael Kaiser

Deputy Proj. ScientistTerry Kucera

STEREO Science CenterBill Thompson-EITI

Instrument ManagementInstrument Management

IMPACT/ UCBInstrument Mgr. / Lil Reichenthal,

Renan Borelli

SWAVES/ UMNInstrument Mgr. / Paul Buchanan

SECCHI/ NRLInstrument Mgr. / Bernie Klein

PLASTIC/ UNHInstrument Mgr. / Art Jacques-OSC

Mission Systems EngineeringSystems Engineer / Shane Hynes – Swales

Instrument Systems Engineer / Lisa Bartusek, Steve Wasserzug-SwalesSystems Engineering / Joe Cerullo-ASRC

S/W Systems Engineering / Jerry Hengemihle-MTEL

Mission Systems EngineeringSystems Engineer / Shane Hynes – Swales

Instrument Systems Engineer / Lisa Bartusek, Steve Wasserzug-SwalesSystems Engineering / Joe Cerullo-ASRC

S/W Systems Engineering / Jerry Hengemihle-MTEL

AETD Engineering Support

STP Program Support OfficeConfiguration Management / D. Dusterwald-CSC, L. Hepler-CSC

Planning / T. Parr-CSC, K. Milligan-CSC, D. Wicks-CSC, J. Rogers-CSCBusiness Support / Mandy Tatum-SERV, Bobbie Power-SGT

STP Program Support OfficeConfiguration Management / D. Dusterwald-CSC, L. Hepler-CSC

Planning / T. Parr-CSC, K. Milligan-CSC, D. Wicks-CSC, J. Rogers-CSCBusiness Support / Mandy Tatum-SERV, Bobbie Power-SGT

System AssuranceSystems Assurance Mgr. / Michael Haynes

Quality Engineer / Pam Hopkins-HTSI, Larry Gibb-SRSTE

System AssuranceSystems Assurance Mgr. / Michael Haynes

Quality Engineer / Pam Hopkins-HTSI, Larry Gibb-SRSTE

Parts AssuranceAntonio Reyes-OSC

SafetyRichard Bolt

ReliabilityMatt Samuel-MUNIZ

Observatory ManagementObservatory Manager / Larry Christensen

Mark Jarosz

Observatory ManagementObservatory Manager / Larry Christensen

Mark Jarosz

JHU/APLEd Reynolds, Project Mgr.

GSFC Procurement OfficeRex Elliot

Contracting Officer / Julie Janus

GSFC Procurement OfficeRex Elliot

Contracting Officer / Julie Janus

Financial ManagerElaine Blazosky

Resource AnalystTracy Felton, Linnette Morales,

Beverly Thomas

General Business SupportJack Arrison-OSC

Business SupportBusiness Support

Project Support ManagerLeslie Cusick-SGT

Software Quality AssuranceMike Garner-HTSI

25 November 03

STEREO Phase E (MO & DA) Management Structure

Project Scientist – M. KaiserDeputy – T. Kucera

Resources– D. Chipouras

Mission Director – S. Odendahl

FDFAPL DSN

SSCDirector – W. Thompson

ScienceTeams

3/27/2007

Future Meetings• Scientific special sessions

– Spring EGU, Vienna April 15-20, 2007 (13 abstracts)• Session ST5 “The 3D Heliosphere at Solar Minimum”

– Spring AGU, Acapulco May 22-25, 2007 (25 abstracts)• Session SH-02 “STEREO: First Results”

– Spring SPD, Honolulu May 27-31, 2007 (TBD abstracts)• Abstracts were due last Wednesday

– IUGG, Perugia, Italy July 2-13, 2007 (49 total abstracts)• Session ASIV030 “New Results From Solar and Heliospheric

Missions”

• SWG– Full SWGs every ~ 6 months (Sept/Oct – volunteers needed)– Topical ‘workshops’ as they arise