Status of TOB Modules & Rods. J. Incandela For the US CMS Tracking Group Tracker Week, Feb. 2004. US CMS Tracker Group. 20 joined group this past year – few more needed at both sites 10 left the group (includes KSU). Brown University R. Hooper, G. Landsberg, C. Nguyen, H. Nguyen - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Status of TOB Modules & Rods

Status of TOB Modules & Rods

J. Incandela

For the US CMS Tracking Group

Tracker Week, Feb. 2004

Page 2: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 2

US CMS Tracker Group

• Brown University• R. Hooper, G. Landsberg, C. Nguyen, H. Nguyen

• University of California, Riverside (UCR)• P. Gartung, G. Hanson, G.Y. Jeng, G. Pasztor

• University of California, Santa Barbara (UCSB)• A. Affolder, S. Burke, C. Campagnari, F. Garberson, D. Hale, J. Incandela, • P. Kalavase, S. Kyre, J. Lamb, R. Taylor, D. Stuart, D. White + technicians

• University of Illinois, Chicago (UIC)• E. Chabalina, C. Gerber, L. Nigra, T. Ten

• Fermilab (FNAL)• M. Demarteau, A. Ronzhin, K. Sogut, L. Spiegel, S. Tkaczyk + technicians

• University of Kansas (KU)• P. Baringer, A. Bean, L. Christofek, D. Coppage

• Mexican Consortium: • Cinvestav: H. Castilla, R. Perez, A. Sanchez• Puebla: E. Medel, H. Salazar• San Luis Potosi: A. Morelos

• University of Rochester (UR)• R.Demina, R. Eusebi, E. Halkiadakis, A. Hocker, S. Korjenevski, P. Tipton

20 joined group this past year – few more needed at both sites10 left the group (includes KSU)

20 joined group this past year – few more needed at both sites10 left the group (includes KSU)

Page 3: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 3

TEC R7

TEC R6 TEC R5P TEC R5S

TOB r-phi TOB stereo

Module Types Built in US

Page 4: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 4

Perspective

• Good parts are arriving• Deliveries will not be smooth – hybrids in particular are a worry

• Prof. David Stuart (UCSB) to take establish parallel US vendor

• The schedule requires • Higher than expected peak production rates

• Extremely robust and stable production lines

• Well trained personnel with backups

• Previous demonstrated module rate 15/day/site

• Module production rates now required:• FNAL: 18/day sustainable and 24/d peak

• UCSB: 21/d sustainable and 30/d peak

• Hybrids wirebonding and thermal testing• Several improvements have been made that reduce the cycle time

of the test-stand to around 30’ (was ranging from 45 to 70 minutes)

Page 5: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 5

Preparations

• Studied and then improved production work flow

• Analyzed failure modes of all systems• Find everything that could interrupt production: Acquire spares

http://hep.ucsb.edu/cms/cms.html

• Cross-train technicians• All persons with critical tasks must have backups

• Detailed written procedures for every task• Specific training required. Lines of responsibility established.

• A list of 25 procedures can be found at:

http://hep.ucsb.edu/cms/cms_procedures

• US Workshop held at UCSB January 21-22• Purpose: Exchange experience – standardize procedures

• Novel Format: Minimum of powerpoint, counterpoints met directly and in the lab around in equipment in many cases, to exchange ideas

• Led to a consideration of a new structure for communication in US

Page 6: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 6

FNAL Assembly Capacity

•Added second curing cabinet• 8 plates/day peak rate.

• provide moisture in winter.

•10 TOB assembly plates: • 6 R-Phi and 4 stereo.

•New people• Two technicians in March

Page 7: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 7

UCSB Assembly Plate/Capacity

Total of 24 plates!(#) = plates added in 2004

Module type Completed Plates

Plates In Process Total Daily Capacity

(# modules)

TOB r-phi 7 (2) 7 21

TOB stereo 3 (1) 3 9

TEC R5P 2 (2) 1 3 9

TEC R5S 2 (2) 1 3 9

TEC R6 5 (4) 5 15

TEC R7 2 (2) 1 3 9

Page 8: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 8

Modules Enter

Bonded, UntestedModules Shelf

ARCSTesting

If Failed

If Passed

Can We Fix It?Yes

Repairs

Repaired Modules Shelf

Needs RepairShelf in

Bonding Room

Failed ModulesShelf

No Good ARCSTested Modules

Shelf

LT Testing

Bad Thermal Cycle, NeedsRetest Shelf

Chosen forLT Test?

TEC or TOB?

TEC or TOB?

TEC ThermalCycled Ready For

Shipping Shelf

TOB ThermalCycled Ready For

Rod Assembly

TEC Not ThermalCycled Ready For

Shipping Shelf

TOB Not ThermalCycled Ready For

Rod Assembly

No

Yes

If Passed

IfFailed

TEC

TOB

Is the ProblemUnderstood?

Undiagnosed Modules Shelf

Yes NoTEC TOB

Module Testing: Example of Flow Plan

Page 9: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 9

Testing time trial

• Question• Can (30 hybrids + 30 modules)/day be comfortably sustained ?

• Results• All hybrids and modules completely tested in a standard 8 hour day

• Only used 2 of 3 module test stands available • Further reductions of testing times have been accomplished since the trial

• Found that having full complement of testers in the room at one time actually improved efficiency and communication

• We were able to solve problems faster by shifting manpower and using the integrated experience of all the testers

• Answer: REQUIRED TESTING THROUGHPUT IS SUSTAINABLE

• Aside: Hybrids wirebonding and thermal testing• Several improvements have been made that reduce the cycle time of the test-

stand to around 30’ (was ranging from 45 to 70 minutes) • FNAL and UCSB up and running

Page 10: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 10

Module LT Systems

•LT systems in final form. • The last steps included

• Backplane modification: FNAL.

• CCU6 to CCU25: UCSB.

•Operation is now stable • I2C errors, missing records &

HV problems are gone.

•Running a 12 scenario.• Allows 20 modules/d/site

Page 11: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 11

Module Production Summary

• Resumed module production late 2004/early 2005• Pair v4 (type 18) with ST and v5 (type 19) with HPK sensors

• We need ST sensors (>=lot 4).

• FNAL:127 modules• 108 HPK: 84 L3&4, 24 L5&6

• 1 (marginal) Gantry placement failure, 2 handling accidents

• 19 STM: 12 L1&2(r), 7 L3&4

• UCSB: 65 modules – paused to study bias connection• 26 HPK: 24 L3&4, 2 L5&6

• 1 IV failure

• 33 R5S (TEC) 6 R5N (TEC)

• All modules test grade AVersion 3 sub-type 17Version 4 sub-type 18Version 5 sub-type 19

Page 12: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 12

Current Focus/Issues

• Bias connection: Ag epoxy studied intensely at UCSB.• 3 sensors (ST) out of 28 TOB modules were found to have poor or

open connections to the HV pad.• 20% of sensors on 36 subsequent modules found to have

unexpectedly high impedance bias line connections• Performed numerous tests and have consulted many experts• Yesterday found an important clue

• Gantry placement doesn’t disrupt the surface of the epoxy bead • We will now be able to devise a systematic remedy

• Completing encapsulation studies• Extreme thermal cycles of hybrids completed – no problems seen• Modules heavily irradiated

• No problems yet identified with encapsulation• Sent to UCSB for further study

• 75 modules encapsulated and to be tested at UCSB• Will now cycle 50 times -30 to + 50C (+80C)

Page 13: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 13

Encapsulation for Reinforcement

• Mainly protects bonds but also an alternative to module reinforcement.•Ideally hybrid bond encapsulation would be done by the vendor or at CERN.

•Other bonds would be encapsulated after the LT test.

• December UCSB did drop tests•No damage for up to 60 g

Page 14: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 14

ARCS Noise Issue

•Tests of recent FNAL production with HPK sensors found lower average noise - especially for 4-APV modules.

•Practical problem: Great modules fail the ARCS low noise cut!

•Production with STM sensors also showed lower noise.•Ruled out ARCS version and any hardware changes.

•Previously produced modules have unchanged noise performance.

•Points to new hybrid versions: may be batch related

•We should switch from absolute to relative cuts.•Absolute levels should nevertheless be used to flag and thus monitor variations

Page 15: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 15

ARCS Noise

Reluctant to upload XML files for ‘failing’ modules

Page 16: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 16

Rods

• Rod assembly well understood• An issue with the stiffer hybrid cable has been resolved

• Single rod testing is under control• Adding a few more "kinks" we get back to where we were with the

softer tails. More details in a presentation by Susanne Kyre to US rod testing meeting:

http://hep.ucsb.edu/people/kyre/stiff-tail-troubles.ppt

• Multi-rod• Have had and resolved many problems with software and hardware

• Achieved major milestones

• Still have some problems to solve

• Need experience with many rods to determine if there are issues with components.

Page 17: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 17

Stiff Tail Solution

•Stiffer tail deflects the intercconnect card (top left)

•Adding additional kinks to the tail eliminates the problem (top right)

Page 18: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 18

ROD Testing Status

• All equipment on hand at FNAL and UCSB• Single rod test stands • Multi-rod stands with capacity of 8(6) single (double)-sided rods

• Have been struggling with DAQ stability problems for long term (3 days) burn-in test• Much progress recently

• Frequent communications with Wim B. SW fixes• Improved grounding I2C communication much more reliable

• For the past week systems have been quite stable• Not sure that we are out of the woods yet• But we are clearly on the right track

• Starting to address bad channel diagnostic procedures• Drawing on US experience with module testing

Expect to be ready at start of full production

Page 19: Status of TOB Modules & Rods

US Production Status, CMS Tracker Week, Feb. 4, 2005 J. Incandela 19

Summary

• Have studied all possible threats to production stability• Purchased or manufactured spares

• Manpower not yet at comfortable level• FNAL 2 new technicians to start in March

• UCSB 1 technician just hired at UCSB, 2 more being sought• Have 4 new students plus 2 coming spring/summer

• Hiring 2-3 post-docs

• Further increased capacity to ~50 modules/day

• Systems• All stages of production have been exercised and are near to final

except rod testing