status of the fair proton linac -...
TRANSCRIPT
STATUS OF THE FAIR PROTON LINACR. Brodhage, W. Vinzenz, M. Vossberg, M. Kaiser, GSI, Darmstadt, Germany
U. Ratzinger, IAP, Universität Frankfurt, Germany
AbstractFor the research program with cooled antiprotons at FAIR
a dedicated 70 MeV, 70 mA proton injector is required. Themain acceleration of this room temperature linac will beprovided by six CH cavities operated at 325 MHz. Withinthe last years, the assembly and tuning of the first powerprototype was finished. The cavity was tested with a pre-liminary aluminum drift tube structure, which was used forprecise frequency and field tuning. Afterwards, the finaldrift tube structure has been welded inside the main tanksand the galvanic copper plating has taken place at GSI work-shops. This paper will report on the recent advances withthe prototype as well as on the current status of the overallp-Linac project.
INTRODUCTIONThe proton linac for FAIR is mechanically grouped in
two sections, each having a length of about 9 m. Based onthe actual design the first section will consist of 3 coupledCH-cavities. Between both sections there will be a diagnos-tics area with a rebuncher for longitudinal beam matching.Investigations have shown that a simplified layout of the 2ndsection of the proton linac will be an improvement. There-fore, three simple CH cavities without a coupling cell willbe used, reducing the triplet lens number by three and sim-plifying the layout and tuning of the cavities a lot.
Figure 1: 3D-view of the coupled prototype cavity.
THE COUPLED PROTOTYPE CAVITYFigure 1 shows the prototype cavity which corresponds to
the second coupled cavity within the first section. The lowenergy part consists of 13 gaps, followed by the couplingcell and by the 14 gap high energy part. The whole cavityhas an inner length of about 2.8 m and the cylindrical tankshave an inner diameter of about 360 mm. The coupling cellhas a length of about 2βλ and hosts the focusing triplet lenswithin one large drift tube. The inter cavity tanks will alsohouse triplet lenses and some beam diagnostics additionally
(4 knob phase probes). They mechanically connect andsupport the neighbored cavities.
Table 1: Parameters of the Coupled CH Prototype Cavity
No. of gaps 13 + 14 = 27Frequency [MHz] 325.2Energy range [MeV] 11.7 - 24.3Beam loading [kW] 882.6Heat loss [MW] 1.35Total power [MW] 2.2Q0-value 15300Eff. shunt impedance [MΩ/m] 60Average E0T[MV/m] 6.4 - 5.8Kilpatrick factor 2.0Coupling constant [%] 0.3Aperture [mm] 20Total inner length [mm] 2800Inner diameter [mm] 360 / 434 / 364
Table 1 shows the main parameters of the prototype cavity.The prototype arrived at GSI in late 2013 and was preparedfor galvanic copper plating. Unfortunately the plating pro-cess on long cavities with a complex inner structure is nottrivial. Therefore lots of tests and investigations have beenperformed to realize a suitable copper layer. Figure 2 showsthe final result after gavanic plating and polishing.
Figure 2: Picture of the copper plated inner surface of CH 3
This cavity is presently at the p-Linac RF test stand andis assembled with all tuners and the triplet lens. The firstlow level measurements were already performed and showa good accordance with theory and previous results. Cop-per plating and welding have not effected the performanceand tolerances of the prototype. Further investigations andperturbation measurements of the field distribution will beperformed within the next weeks.
6th International Particle Accelerator Conference IPAC2015, Richmond, VA, USA JACoW PublishingISBN: 978-3-95450-168-7 doi:10.18429/JACoW-IPAC2015-THPF011
THPF0113702
Cont
entf
rom
this
wor
km
aybe
used
unde
rthe
term
soft
heCC
BY3.
0lic
ence
(©20
15).
Any
distr
ibut
ion
ofth
isw
ork
mus
tmai
ntai
nat
tribu
tion
toth
eau
thor
(s),
title
ofth
ew
ork,
publ
isher
,and
DO
I.
4: Hadron AcceleratorsA08 - Linear Accelerators
ION SOURCE, LEBT & CHOPPERThe p-Linac frontend will be equipped with an ECR ion
source and a short LEBT consisting of two solenoids enclos-ing a diagnostics chamber which will house i.a. an allisonscanner, a faraday cup and a wien filter.
Table 2: Main Parameters of the ECR Source
Beam Intensity [mA] 100Beam Energy [keV] 95Proton Fraction [%] > 85
Subsequently to the second solenoid, there will be an elec-trical chopper. Two parallel copper plates will be loadedwith a bipolar voltage of ±15 kV. By passing this electricfield, the proton beam will be deflected to a tungsten platedcopper cone. Using intensive water cooling, this cone isable to absorb the protons at most of the time. With a max-imum repetition rate of 5 Hz, the chopper is switched offto produce short beam pulses with a length correspondingto the multiturn injection time of the synchrotron. Figure 3shows a 3D view of the complete LEBT together with theion source and the chopper. All parts except for the chopperare ready and and assembled at CEA, Saclay, Paris. TheChopper is currently under production and is expected to beintegrated in the LEBT in late 2015.
Figure 3: 3-D view of the ion soucre, LEBT and chopper
4-VANE RFQAn RFQ will be directly connected to the LEBT. Given
the high operating frequency of the p-Linac, the decisionto build a 4-vane type RFQ seems obvious. Neverthelesstwo other possibilities came into question and are still un-der investigation by the Univ. of Frankfurt. It has beendemonstrated that a 4-rod or even a ladder RFQ are powerfulenough to be considered in the p-Linac. The decision tofocus on a 4-vane RFQ was made together with internationalexperts in mid 2014. Since then the beam dynamics anddifferent vane shapes have been studied and a collaborationwith INFN, Legnaro is under preparation for production and
assembling this RFQ. Figure 4 shows a 3D view of the mostrecent RFQ simulation. Presuming a quick progression withthe collaboration and no unexpected design difficulties the4-vane RFQ can be ready until 2018.
Figure 4: 3-D view of the latest RFQ simulations
BUNCHERThe longitudinal beam matching before the RFQ at 95
keV and at the diagnostics area at 35 MeV and also behindthe complete p-Linac at 70 MeV is realised by three individ-ual buncher cavities. Each cavity has its own requirementsmainly caused by the varying beam energy. This resultsin three different lengths, so much that the the bunchershave two, four and six gaps respectively. The beam dynam-ics layout of a dedicated buncher is straight forward andwas finalized together with the CH-cavities’ beam dynamics.Mechanically the bunchers are not completely designed. Afinal technical layout can be acquired with modest resources.Figure 5 shows a first design study used for digital mock-upanalysis. This gives an idea of the simplicity of such bunch-ers. The realization is planned for next year and will not takelonger than 12 months.
Figure 5: 3-D view of a general 2-gap buncher layout
CH-CAVITIESThe main acceleration from 3 MeV up to 70 MeV will
be realized with six CH-cavities grouped into two sections,
6th International Particle Accelerator Conference IPAC2015, Richmond, VA, USA JACoW PublishingISBN: 978-3-95450-168-7 doi:10.18429/JACoW-IPAC2015-THPF011
4: Hadron AcceleratorsA08 - Linear Accelerators
THPF0113703
Cont
entf
rom
this
wor
km
aybe
used
unde
rthe
term
soft
heCC
BY3.
0lic
ence
(©20
15).
Any
distr
ibut
ion
ofth
isw
ork
mus
tmai
ntai
nat
tribu
tion
toth
eau
thor
(s),
title
ofth
ew
ork,
publ
isher
,and
DO
I.
which are separated by a dedicated diagnostics area at 35MeV. The first section will consist of three coupled CHeach housing a quadrupole triplet within the vacuum andRF penetrated area. These coupled cavities are not trivialto be build, but as the prototype CH has shown it can bedone, if an intense follow up is realised. The second sectionwill consist of three up to 3.5 m long common CH-cavities.These cavities have only quadrupole triplets in between andthe RF design is much more straightforward.Beam dynamics investigations have finally been con-
cluded. It could be shown, that the diagnostics area andthe LEBT between RFQ and first CH can be realized moresimple than initially expected. The next step is to implementthe latest changes into the RF simulations and to validatethe overall design. It is foreseen, that all parameters are de-fined shortly and tendering of the cavity production can startwithin this year. After the contractor is chosen it is planedto have the first cavity on campus after two years, meaningthat the production will be finished in 2018.
FOCUSING MAGNETSInduced by the revised beam dynamics simulations some
modifications on the quadrupole triplets have been decided.The new layout of the magnets is simplified and unified forthe whole p-Linac. Only one kind of joke profile is used andonly to different lengths of triplets are used. All of theseTriplets will be housed in a general squared vacuum tankwhich also supports the adjacent cavities. Tendering of thetriplets took place in late 2014 and the contract with thecompany Danfysik was signed early 2015. This results indelivery of all magnets until 2017.
RF & POWER SUPPLIESThe main p-Linac components, such as the RFQ and the
CH cavities will be powered by seven 325 MHz klystrons.Benefiting from recent developments, under the participatingof CNRS, the klystrons will be delivered by the companyThales. The first klystron is already at GSI and is currentlyunder commissioning at the RF test stand. Full operabilityis foreseen for late summer in this year. The CH prototypewill also be ready by then and used as a resonant load forfurther testing of the klystron and the cavity itself. The powersupply for the klystron is at the moment realized with a leasemodulator. This device will be returned to CERN by the endof this year. In the meantime an optimized version of themodulator is under specification and will be ordered as soonas possible, and will be used for all p-Linac klystrons. Inaddition three solid state drivers with 45 kW power will beused to operate the buncher cavities. The 45 kW amplifiers
are on site since late 2014. Recently they have been testedwith a small 4-Rod RFQmodel used as a resonant load. Thistests could be performed with great success and the buncheramplifiers are therefore operational.
BEAM DIAGNOSTICSAll along the p-Linac a variety of beam diagnostic devices
will be installed. Many of which are part of foreign contri-butions. Beam position monitors for example will originatefrom CEA, Saclay, Paris. Figure 6 shows the BPM prototypewhich will later on be mounted to the exit of the quadrupoletriplets.
Figure 6: Picture of the BPM prototype with housing
CONCLUSIONThis paper showed the current status of the p-Linac. The
design of all major components is done and only minorchanges in specifications are expected. Tendering of themissing parts may have started until early 2016.
REFERENCES[1] U. Ratzinger, G. Clemente, C. Commenda, H. Liebermann, H.
Podlech, R. Tiede, W. Barth, L. Groening, “A 70 MeV Protonlinac for the FAIR facility based on CH cavities,” Proceedingsof LINAC 06, TH1004.
[2] G. Clemente, H. Podlech, U. Ratzinger, R. Tiede, S. Minaev,“HIPPI-Relevant Activities at IAP-Frankfurt on the Develop-ment of the Room Temperature CH-DTL,” CARE-Report-2008-014-HIPPI.
[3] G. Clemente, H. Podlech, R. Tiede, U. Ratzinger, L. Groening,S. Minaev, “Status of the 70 MeV, 70 mA CH Proton-DTL forFAIR,” Proceedings of EPAC 2006, TUPCH115.
6th International Particle Accelerator Conference IPAC2015, Richmond, VA, USA JACoW PublishingISBN: 978-3-95450-168-7 doi:10.18429/JACoW-IPAC2015-THPF011
THPF0113704
Cont
entf
rom
this
wor
km
aybe
used
unde
rthe
term
soft
heCC
BY3.
0lic
ence
(©20
15).
Any
distr
ibut
ion
ofth
isw
ork
mus
tmai
ntai
nat
tribu
tion
toth
eau
thor
(s),
title
ofth
ew
ork,
publ
isher
,and
DO
I.
4: Hadron AcceleratorsA08 - Linear Accelerators