All Experimenters’Meeting
August 05, 2013
Startup 2013
Machine Status: Proton Source Commissioning and Studies
RFQ Injector Line (RIL) Linac Booster
Main Injector Startup and Tuning
Power Outages PS3 Power Outage
Oil Switch ReplacementImpacts PS3, PW5, & PC3Run on generator for ~1 weekConnect generator Monday, July 29th @ 0800 –
1000Disconnect generator Friday, August 9th @ 0800-
1000
Power Failures Feeder 46B
Wednesday, July 24th @ 2142Impact – Possible F0 ventilation systemFault located between P71 & F4Further isolation and repairs necessary
Kautz Road SubStation Status
MI backfed from Master SubStation○ Using Feeder 45 for MI conventional power which is
normally T85 on KRSWe ordered 6+ new surge arrestors (4.7k each) from
Hubbell and they were delivered on Friday, July 26th
Schedule: (Weather Dependent)○ Monday, August 5th replace T85 surge arrestors
No machine impact (In Progress)
○ Tuesday, August 6th replace T87 surge arrestorsNo beam during work 8-10 hoursAfter replacement, test both T85 and T87
There will be a 20 minute MI conventional power outage to remove the backfeed, not scheduled.
MI Startup Activities (~1 Week) Turn on power supplies and establish ramps Establish 8 Gev beam
Match MI8 line lattice with IPM Tune abort line @8 Gev
Establish 120 Gev beam Smooth orbits up the ramp Tune abort line @ 120 Gev
High field Orbit smoothing (quad moves) (Have data for 1st) Requires tunnel access (2x8 hrs)
Calibrate tune table MI8 line lattice matching (1st of 2 passes complete)
Dedicated beam study Extraction line tune up (NuMI) (Attempting extraction) Tune up for operation Deliver low intensity beam to NuMI beam line for target scans
Estimated to take an additional week after MI is tuned up for operations
Shutdown 2012
Schedules and Links:Schedule can be accessed from the Operations Home Page
- Schedules -> Operations Schedule
Direct link to schedule
- http://www-ad.fnal.gov/ops/schedule.html