status of small hydro and micro hydro_country presentation nepal
DESCRIPTION
Presented at IIT, RoorkeeTRANSCRIPT
Country Presentation onHydropower Development in Nepal
Presentation By:Saroj AcharyaHydropower EngineerDepartment of Electricity Development (DoED), Ministry of [email protected]
Subash TuladharEngineerDepartment of Electricity Development (DoED), Ministry of [email protected]
Pashupati Prasad KhatriEnergy Development OfficerRenewable Energy for Rural Livelihood (GoN/UNDP/WB), DDC, Bajhang
Rojina SharmaEngineer, AEPC, Ministry of Environment
19th Annual International Training course on Small Hydro Power Development, IIT Roorkee,2012
Presentation Outline1. Country profile
2. Hydropower development and status
3. Country Policy and Private sector
5. Small Hydropower
6. Alternative Energy (Micro-Hydro, Mini Grid, Gasifier, CDM)
7. Photo Gallery
General
Land Locked Country
Area 147,181 sq. km.
Population 26 Million
No coal and natural gas source availableRiver Network More than 6,000 rivers and rivulets An annual 224 billion cubic meter of surface run off‐ Total Hydropower Potential of 83,000 MW and more
Country Profile
Ecological Regions
Indian Plains Terai
Siwalik hills
Middle hills
High Mountains
High Himalayas
Tibetan Plateau
67 m amsl
8848 m amsl
`180-250 km cross-section
<<< Hydropower Sites >>>
Hydropower Development
First Hydropower Plant: Pharping (500kW), 1911 A.D.
Hydropower Potential of the country 83,000 MW
Micro hydro installed (Dec. 2011) 12MW
Total Installed Capacity (2011) 705.566MW
Under Construction 931.133 MW
Hydropower Development Status
Parameter Classification
<100kW Micro hydro
101 kW- 1 MW Mini hydro
1-25 MW Small hydro
>25 MW Medium and Large hydro
Hydropower Classification
Thermal7.57%
Solar0.01%
Hydro92.42%
Installation By type (MW)
Contribution of small hydro
Installation by category
Small hydro28%
Medium and Large72%
Installed Capacity (MW)
Category Installed Capacity (MW)
Hydropower 652.05
Thermal (Diesel) 53.41
Solar 0.1
Total 705.566
Category Installed Capacity (MW)
Small Hydropower 181.05
Medium and Large 471
Total 652.05
S. N Name Installed Capacity, MW
1 Upper Tamakoshi 456.00
2 Chamelia 30.00
3 Kulekhani III 14.00
4 Upper Trishuli 3"A" 60.00
5 Rahughat 32.00
6 From Private Sector 338.73
Total 930.73
Projects Under Construction
Planned Projects (Other than Private sector)S. N Name Installed Capacity, MW
1 Upper Trishuli-3'B' 37.00
2 Budhi Gandaki 600.00
3 Upper Seti (Storage) 128.00
4 Seti Trishuli (Storage) 128.00
5 Upper Modi 'A' 42.00
6 Nalsyagu Gad (Storage Project) 1335.00
Total 1335.00
Agencies InvolvedMinistry of Energy, Department of Electricity Development Regulatory body Policy making Issuing license and facilitation Identification study and solicitation of hydropower projects Study and development of hydropower projectsNepal Electricity Authority Electrification PPA (Power purchase agreement), Transmission and distribution Project study and construction, Operation and maintenanceMinistry of Environment /Alternative Energy Promotion Center Promotes Renewable Energy TechnologiesElectricity Tariff Fixation Committee Fixes the tariff
Private Sector (IPPs) Development Construction and Operation Transmission up to substation
Country Policy Develop hydropower as much as possible to contribute in
economic growth of the country Privatization and Market economy was adopted Electric power supply industry or utility was opened up for
private and investment came to play after the Electricity Act (1992)
Nepal is one of the countries to start BOOT scheme in Hydropower Licensing Procedures (Two stage licensing procedure) -Survey License (for study and PPA) -Generation License (35 years including construction
period, for construction and Operation) Virtually anyone could get a license and license fee is very nominal
so many could apply and get license
Country Policy… No EIA required for <50MW Project Minimum royalty is charged during the payback period (for first 10 years) PPP (Public Private Partnership ) to encourage Local People in the
development of SHPFacility for the developer to promote Sector Value added tax (VAT) is not levied on -the electricity tariff -the industrial machineries, equipment and spare parts imported Only 1 % custom duty on the imported devices, equipment, machineries
and spare parts Income tax holiday for the projects which will be completed within 2019 No income source looked into if investment is for hydropower till 2019
Involvement of Private Sector
Private Sector is equally contributing in hydropower development and in reduction of load shedding
Khimti Hydropower was the first hydropower project commercially operated from Private sector in 2000
Solicitation of SHP to IPPs: 6 projects, 171.5 MW
Private73%
27%
Installed Capacity MW
Contribution from Private sector at present
Category Installed Capacity (MW)
Public Sector 477.53
Private Sector 178.52
Total 656.05
S.N Name of the Project Operation (KW) Name of the Project Under Construction (KW)
1 Khimtikhola 60,000 Sanjen (Upper) 14,800
2 Bhotekoshi 36,000 Sanjen (Lower) 42,500
3 Chilime 2,2000 Middle Bhotekoshi 102,000
4 Jhimruk 12,000 Rasuwagadi 111,000
5 Indrawati III 7,500 Lower Modi I 9,900
6 Andhikhola 5,100 Sipring Khola 9,658
7 Mai Khola 4,500 Ankhu Khola-I 8,400
8 Khudi Khola 3450 Siuri Khola 4,950
9 Mardi Khola 3,100 Lower Indrawati 4,500
10 Piluwa Khola 3,000 Hewa Khola 4,455
11 Sunkoshi Small 2,500 Lower Piluwa 990
12 Ridi Khola ,2400 Mai SHP 9800
13 Thoppal Khola 1,650 Sanima Mai 15600
14 Chaku Khola 1,500
15 Patikhola 996
16 Pheme Khola 995
17 Upper Hadi Khola 991
18 Baramchi 4,200
19 Seti-II 979
20 Sisne Khola 750
21 Rairang 500
22 Salinadi 232
23 Sange Khola 183
Total 178,526 338,733
Hardly can get Long term study data (hydrology, meteorology etc.) Evacuation and transmission Line problem Should face some social problems as large projects Low tariff (PPA rates)(Low rate of return), Fixed PPA rate Financing Problems (Lack of capital) High interest rate on debt Poor Infrastructure and Accessibility issues All machines and equipments should be imported from outside Transmission line issues One Window leads to several doors (Lengthy approval process, several clearances
required)
Risks associated with hydropower development
Challenges and Issues in Hydropower Development
Environmental and social risks Financial risks Hydrological and GLOF Risks Inflation and currency exchange rate risks
Some Facts Very small amount of energy is harnessed in spite of its huge
potential Positive scenario for the development of SHP Local capacity is improving rapidly PPA rate has been fixed for Small Hydro Projects i.e. up to 25
MW Dry Season Rate : NRs 8.4 / KWh ( 10.5 US Cent ) Wet Season Rate : NRs 4.8/ KWh ( 6.0 US Cent) (Exchange rate: 1USD=NRS 80.00)
Cost per KW generation >USD 1500.00
Bijayapur SHP 4.5MWUnder Construction Ridi SHP 2.4MW
Under Operation
Mai SHP 15.6MWUnder Construction
Baramchi SHP 4.2MWUnder Operation
Introduction to AEPC
Established in 1996Now under the Ministry of EnvironmentGovernment agency working in the field of renewable energy
What does AEPC do????? Prepares Plans & Policies Coordinates between different agencies working in the field of RETs promotion Provides technical as well as financial support for RETsAchievements till date : MHPs :- 895 Nos., 12 MW
Programs of AEPC in RETs development
Renewable Energy for Rural Livelihood Program. (RERL), through DEESs and DEEUs (in DDC) covering all 75 districts.
Energy Sector Assistance Program (ESAP) through 7 RRESCs (local NGOs).
19
Main policies relating to RETs
Renewable (Rural) Energy Subsidy Mechanism, 2008
Renewable (Rural) Energy Subsidy Delivery Mechanism, 2008
Custom duty and VAT exemption on the equipments of different RETs
Rural Energy Policy, 2006
04/28/2023 20
CDM Project Cycle A project needs to satisfy a number of rules and conditions and has to go
through a series of procedures with the involvement of several independent entities in order to be classified as a CDM project activity.
April 28, 2023 20
Project Design Document (PDD) / Project Information Note (PIN)
Validation
Registration
Implementation
Monitoring and Reporting
Verification
Certification
Stakeholder consultations, Public comment
Project Participants (AEPC)
Host Country Approval
Designated Operational Entity
CDM – Executive Board
Host country - DNA
Public/Stakeholders
Independent Third Party
Baseline Studies
04/28/2023 21
AEPC CDM Projects
April 28, 2023 21
Name of Projects Project Proponent
Status
Biogas Support Program – Nepal Activity-1 (9708 plants)
Estimated Annual Emission Reduction: 46,990 tCO2e
AEPC Registered & CER issued
Biogas Support Program – Nepal Activity-2 (9688 plants)
Estimated Annual Emission Reduction: 46,893 tCO2e
AEPC Registered & CER Issued
Micro-hydro Promotion (capacity of 14.965 MW)
Estimated Annual Emission Reduction: 40,535 tCO2e
AEPC Registered
Biogas Support Program – Nepal Activity-3 (20,254 plants)
Estimated Annual Emission Reduction: 51,086 tCO2e
AEPC Request for registration
Biogas Support Program - Nepal Activity-4 (20,254 plants)
Estimated Annual Emission Reduction: 51,086 tCO2e
AEPC Request for registration
Nepal Biogas Support Program-PoA (20000 plants)
Estimated Annual Emission Reduction: 40,535 tCO2e
AEPC Final stage of validation
Promotion of the Improved Cooking Stove (ICS) – Nepal
Estimated Annual Emission Reduction: 113,128 tCO2e
AEPC Under Validation
Promotion of the Improved Water Mills (IWM) - Nepal
Estimated Annual Emission Reduction: 38,699 tCO2e
AEPC Under Validation
AEPC CDM Projects (contd…)
INCREASED ACCESS
TO ELECTRICITY
IMPROVED HEALTH AND SANITATION
LABOR SAVING & DRUDGERY REDUCTION
STRONG SOCIAL CAPITAL AND
EMPOWERMENT
BETTER EDUCATION
HUMAN RESOURCES
DEVELOPMENT
INTERNALIZATION OF RURAL ENERGY
IN DISTRICTS POLICY, PLANNING
AND MANAGEMENT
REDUCED CONSUMPTION OF
TRDITIONAL SOURCE OF ENERGY
INCREASED EMPLOYMENT, INCOME
AND CHEAPER SERVICES
MAJOR IMPACTENHANCED
LIVELIHOODPRESERVED
ENVIRONMENT
BIO-MASS GASIFIER (SARLAHI)PRE STRESSED RCC POLESPLANT SEED OILTHREE PHASE INDUCTION GENERATOR CONTROLLERPRESERVATIVE TREATMENT FOR MH WOODEN POLESPUMP AS TURBINETURGO TURBINEHORIZONTAL AXIS PELTRIC SETCOMPUTER AIDED DESIGN OF MICRO HYDRO SCHEMELOW COST RURAL LIGHTINGMOTOR STARTING SYSTEM FOR MICRO HYDRO SCHEMESGRID CONNECTION OF MICRO HYDRO SCHEMEMINI GRID CONNECTION OF MHPs
Mini Grid of Baglung 1st pilot project in Nepal. Implemented by Rural Energy Development
Programme (Now, RERL) Consultant :- Entec Consulting & Engineering,
Switzerland. Contractor/Supplier :- Ytek Controls Inc,
Deharadun, U.K., India Approx. Cost :- NRs. 15 millions. K2U2MGWC– Regulatory body
12kw
22kw
26kw
9 kw
14kw
25kw
23kw
Urja I Urja II Urja III Theule
Kalung Urja IVU Kalung
Technical Features
Transmission Length: 8 Km Transmission Voltage :11 kV No of Power Plants connected: 7 Total Installed Capacity of the Plants: 132 kW Total No of HH: 1400 Biggest Size of the Plant:26kW Smallest Size of the Plant:9kW Peak Load: 128kW(18:00-22:00)
PPA rate with IPP’s Mini grid shall purchase the power with
respective MHFG (IPP) in the rate of Rs 2.50/kWH.
Respective IPP shall be penalized if they are not able to supply the power as per the agreement made with the mini grid.
Tariff StructureS.No Domestic Consumer Minimum
Charge (NRs)Exempt (kWH)
1 Minimum Monthly Charge 70.00 20
2 Energy Charge
A UP to 20 Units 3.50
B 20 units-250 Units 7
3 Industrial Demand /HP Per Unit(NRS)
A Induction Motor based Tariff 10 7
B Other End uses - 7
Name of the Schemes
U.Kalung (12kW)
Kalung(22kW)
Urja I (26kW)
Urja II (9kW)
Urja III (25kW)
Urja IV (14kW)
Theule (24kW)
Generation(kWH)
4590 7020 8400 3720 8910 4650 7590
Maximum Capacity(kWh)
8640 15840 18720 6480 18000 10080 17280
load Factor 53.125 44.318 44.87 57.407 49.5 46.1343.92
Previous Income
7510 14200 16240 6500 16200 7200 14850
Income after Grid Connection.
11,475 17,550 21,000 9300 22275 11625 18975
Fact Sheet
Gasifier Bio-mass based gasifier pilot project in Madhuban
goth VDC of Sarlahi District Capacity of Gasifier plant :- 11kW No of HHS covered 122 (ward no 1 to 9 covered) Completed on Aug. 2011
• Rural Energy Systems bring positive benefits such as better light, reduced labour and drudgery, increased income, improved environment, better education, better health, value addition, social harmony, etc.
• MH is best means to increase access to electricity by the rural poor.
• Biogas and Improved Cooking Stoves are best means to reduce fuel-wood consumption.
Continued……….
• Women's involvement is high as rural energy bring positive changes in their lives.
• Rural energy is an effective entry-point for the poverty alleviation.
• Holistic development approach is needed for the sustainability of Rural Energy Systems.
• Demand for rural energy systems is high in remote districts
Continued………
• Local people are capable to implement and manage rural energy systems with guidance and capacity building.
• Community mobilization is the key for harnessing people's potentials, mainstreaming women and vulnerable groups and also ensuring equity.
• Decentralized institutional frameworks and operational modalities are required for wide-scale promotion of Rural Energy Systems.
Photo Gallery
Photos of Mini Grid
Photos of Gasifier
Thank You