SHOWCASING THE STATUS OF

ROADS IN NAIROBI

PRESENTED DURING THE LAUNCH CEREMONY OF THE NAIROBI BUSINESS PARK EXTENSION HELD ON 2nd AUGUST, 2012

By: Eng. M. S. M. KAMAU, CBS, HSC

Permanent SecretaryMinistry of Roads

Page 2: Status of Nairobi Roads 2012- 2013
Page 3: Status of Nairobi Roads 2012- 2013

OUTLINE OF THE PRESENTATION

� Introduction

� Ongoing Road Projects in Nairobi

� Planned Road projects in Nairobi

� Private Sector Participation in Development of Road

Infrastructure

� Opportunities for Private sector Participation

� Way Forward

Page 4: Status of Nairobi Roads 2012- 2013

1.0 INTRODUCTION

� Economic pillar of the Vision 2030 is founded on road

transport infrastructure as an enabler.

� Connectivity through a network of roads, railways, ports,

airports, water and sanitation facilities, and

telecommunications.

� How does RSIP affect the operations of Nairobi Business

Park and the entire business environment?

Page 5: Status of Nairobi Roads 2012- 2013

1.0 INTRODUCTION

Vision 2030

Economic PillarSocial Pillar Political Pillar

Sound

Infrastructure

RoadsICT Ports and Harbours Railways

EnergyTransport TelecommunicationsWater & Sanitation

Airports

ICT Public sector

Reforms

Macro-economic

Stability SecurityLand Use

ReformsEnergy Human

Resources

Investment

Page 6: Status of Nairobi Roads 2012- 2013

� 1.1 Role of Road Transport in Business Development

� Efficient Road Transport vital for Business

� Mobility and access for people and goods

� Public Transport

� Linkages with other modes of transport

� Stimulate development of new undeveloped areas

1.0 INTRODUCTION

Page 7: Status of Nairobi Roads 2012- 2013

1.2 Challenges to Efficient Road Transport

� Traffic congestion

� Low capacity of existing Roads

� Inefficient Junction designs

� Increased demand

� Low levels of Investment in roads

� Poor spatial planning

� Encroachment on Road reserves

� Unregulated public transport

1.0 INTRODUCTION

Page 8: Status of Nairobi Roads 2012- 2013

1.3 Ministry’s Approach to the Challenges

� Proper maintenance of existing roads

� Expansion of existing Roads

� Opening and Construction of Missing Link Roads

� Construction of Bypasses

� Introduction of Bus Rapid Transit (BRT) Systems

� Proper coordination of land use

� Traffic management measures

� Demarcation and Protection of road reserves

� Private sector participation in infrastructure development

and Maintenance

1.0 INTRODUCTION

Page 9: Status of Nairobi Roads 2012- 2013

NAIROBI MISSING LINKS

Page 10: Status of Nairobi Roads 2012- 2013

NAIROBI BYPASSES MAP

2. NAIROBI EASTERN AND NORTHERN BYPASS

Page 11: Status of Nairobi Roads 2012- 2013

ONGOING PROJECTS

Page 12: Status of Nairobi Roads 2012- 2013

1. THIKA ROAD PROJECT� Financed by the African Development Bank and GoK.

� To ease congestion on the busy Nairobi – Thika corridor.

� Substantially complete

� Major challenges:

-Road safety

-Driver/ Road user education necessary

-Relocation of services

-Encroachment on road reserve/Land acquisition

Page 13: Status of Nairobi Roads 2012- 2013

2. NAIROBI EASTERN &NORTHERN BYPASS

� Financed by GoK and Chinese Government

� Channel traffic away from the city centre

� Eastern Bypass connects the busy Mombasa Road to Thika-Road

� Northern bypass connects Thika Road to Ruaka area and will eventually connect to Nairobi – Nakuru Highway.

Page 14: Status of Nairobi Roads 2012- 2013

PROJECTS ONGOING

2. NAIROBI EASTERN AND NORTHERN BYPASS

NK 0+000 - Start

EK 0+000 - Start

Page 15: Status of Nairobi Roads 2012- 2013

2.2 Nairobi Eastern and Northern Bypass

Outering Road Overpass Bridge (Km 1+000) Eastern Bypass

Dual Carriageway + Footpaths (KM 1+400 – KM 4+400) Eastern Bypass

Page 16: Status of Nairobi Roads 2012- 2013

3. NAIROBI WESTERN RING ROADS

� Part of the Missing Link Roads In Nairobi.

� Funded by the Government of Japan through a Grant of Kshs 1.9

Billion .

� Part of the missing link roads in Nairobi.

� Construction commenced in June 2011.

� Expected completion in March 2013

� Connect:

-Ngong Road to James Gichuru through Kileleshwa

-Gitanga Road to Waiyaki way through Kileleshwa

Page 17: Status of Nairobi Roads 2012- 2013
Page 18: Status of Nairobi Roads 2012- 2013

4. 4. 4. 4. UPGRADING OF LANGATA ROAD

� Financed by the Government of Kenya

� Upgrading to two lane dual carriage

� Contract Sum Kshs 2,671,000,000.00

� Underpass at Bomas Junction

� Pedestrian walkways and cycle tracks for cyclists

� Box culvert

� Other drainage works

� Completion by May 2013

Page 19: Status of Nairobi Roads 2012- 2013

\

Page 20: Status of Nairobi Roads 2012- 2013

5. NAIROBI SOUTHERN BYPASS

� Financed by the Chinese Government and the Government of

Kenya

� Contract sum Ksh.17,199,793,766.00 Separate grade

� intersections at Mombasa, Langata, Ngong and Kikuyu roads

� Commenced 2nd July, 2012

� Contract period is expected to be 36 months

� Expected completion by July 2015

Page 21: Status of Nairobi Roads 2012- 2013

5. NAIROBI SOUTHERN BYPASS

Scope Of Works:

� Construction of dual carriageway with a length of 28.6

kilometres

� 12 kilometre slip roads

� 8.5 kilometre service roads

� An extra 8 kilometre service roads whose location shall be

decided by the employer

� Three full interchanges at Bypass intersection with

Mombasa, Langata and Ngong roads

� Fly-overs (partial interchanges) at Community, Thogoto

and Dagoretti roads.

� Street lighting installation on the whole road

Page 22: Status of Nairobi Roads 2012- 2013

Interchange configuration on southern Bypass /Ngong Road Junction

Ngong RoadSouthern Bypass Road

Ngong

Nairobi

Kikuyu

Langata

Page 23: Status of Nairobi Roads 2012- 2013

6. NON- MOTORIZED TRAFFIC FACILITIES

� Statistics have shown that over 47% of Nairobi Residents walk to

and from work.

� Non-motorized traffic facilities have been integrated into the

designs of all road projects.

� NMT facilities include:

-Walkways

-Cycle Tracks

-Foot Bridges

� These also help to improve on road safety.

Page 24: Status of Nairobi Roads 2012- 2013

Cycle Track

Walkway

Page 25: Status of Nairobi Roads 2012- 2013

7. UPPER HILL ROADS

� Financed by Government of Kenya

� Implementation in two phases:

-Phase 1: Currently under construction

-Phase II: Currently under Design

Page 26: Status of Nairobi Roads 2012- 2013

7.1 UPPER HILL ROADS: Phase I

� Involves expansion of the existing roads by either dualling or

widening of the lanes

� Financed by the Government of Kenya

� Contract Sum : Kshs Kshs.2,002,892,599.00

� Commenced on 22nd May 2012

� Expected Completion: 22nd May 2014

Page 27: Status of Nairobi Roads 2012- 2013

7.2 UPPER HILL ROADS: Phase I

� The roads to be dualled are:

-Part of Hospital Road

-Elgon Road

-Kilimanjaro road

-Upper Hill road

-Bunyala road

Page 28: Status of Nairobi Roads 2012- 2013

8. OTHER ONGOING ROAD PROJECTS

NO. PROJECT FUNDING START DATE COMPLETION DATE

1 Upgrading of Eastleigh

Roads

GoK 13th March,

2012.

24th May 2013

2 Rehabilitation of South C

Roads

GoK 4th Dec, 2012 2nd Dec, 2013

3 Upgrading of Syokimau –

Katani Road

GoK 4th Dec, 2012 4th Dec, 2013

4 Upgrading of Kasarani-

Mwiki-Githurai Link Road

(Phase I)

GoK 19th Feb, 2012 20th Oct, 2013

Page 29: Status of Nairobi Roads 2012- 2013

8. 8. 8. 8. OTHER ONGOING ROAD PROJECTS

� The project for the improvement of Eastliegh roads cover the

following roads with a total of 2.1km:

-2nd Avenue Eastleigh

-15th Street and adjoining streets.

� 2nd Avenue Eastleigh and 15th Street link Juja Road to

1st Avenue Eastleigh.

Page 30: Status of Nairobi Roads 2012- 2013

8. OTHER ONGOING ROAD PROJECTS

� The scope of works include:

-Drainage Works

-Construction of Footpaths

-Construction of Bus-bays

-Reconstruction of the carriageway

-Junction Repairs

-Road furniture

� The project commenced on 13th March, 2012 and is

expected to be completed by 24th May 2013

Page 31: Status of Nairobi Roads 2012- 2013

PLANNED PROJECTS

Page 32: Status of Nairobi Roads 2012- 2013

1. PHASE II: ADAMS ARCADE – KAREN –

NGONG - BOMAS

� Negotiations ongoing for Funding by Chinese Government

� Upgrading 30km to Dual Carriage standards

� Estimated cost Kshs 15 Billion

� Separate Grade intersections at Dagoretti corner, Junction

with Southern Bypass and Karen Shopping Centre

Page 33: Status of Nairobi Roads 2012- 2013

2. PHASE II: ADAMS ARCADE – KAREN –

NGONG – BOMAS (Cont’d)

� Dualling to four (4) Lanes

� Provision of service roads

� Provision for Walkways and cycle tracks

� Footbridges at selected points

� Detailed Engineering designs will be completed by end of

August 2012

� Expected to commence in early 2013 with a contract

period of 36 Months

� Expected completion by early 2016

Page 34: Status of Nairobi Roads 2012- 2013

3. Dualling of Outer Ring Road

� Financing Agreement signed with African development

Bank for Kshs 3.5 Billion

� Estimated cost Kshs 6.0 Billion

� Negotiations ongoing for additional funding

� Detailed Engineering designs completed

� Expected to commence in early 2013 with a contract period

of 36 Months

Page 35: Status of Nairobi Roads 2012- 2013

4. EU Funded Missing Link Roads

� Financing Agreement signed with European Delegation to

Kenya

� Estimated cost Kshs 3.5 Billion (€ 32.5 Million)

� Total of 13.6km of Missing Link Roads and 11.7 km of Non-

motorized Traffic facilities

� Detailed Engineering designs completed

� Expected to commence in January 2013 with a contract

period of 36 Months

� Expected Completion by January 2015

Page 36: Status of Nairobi Roads 2012- 2013

3. EU 3. EU 3. EU 3. EU Funded Missing Link RoadsFunded Missing Link RoadsFunded Missing Link RoadsFunded Missing Link Roads

MISSING LINK

No

NAME LENGTH (KM)

Missing Link Roads

M-1 Accra Road to Ngara Road 0.7

M-5 (Muratina St) General Waruingi St to Juja Road 3.0

M-10 Likoni Road Extension): Enterprise Road to Mombasa 1.8

M-15a Ring Road Parkland (Westlands Roundabout – Limuru

Road)

4.0

M-15b Ring Road Parkland Extension: (Limuru Road to

Thika road)

1.6

M-16 Quarry Road Extension: (Ladhies Road to Quarry

Road)

2.5

Total 13.6km

Page 37: Status of Nairobi Roads 2012- 2013

3. EU 3. EU 3. EU 3. EU Funded Missing Link RoadsFunded Missing Link RoadsFunded Missing Link RoadsFunded Missing Link Roads

MISSING LINK

No

NAME LENGTH (KM)

Non- Motorized Transport Routes

MISSING LINK

No

NAME LENGTH (KM)

NMT-16 Footpaths and cycle tracks on Jogoo Road 4.0

NMT-17 Footpaths and cycle tracks on Lusaka Road 5.2

NMT-18 Footpaths and cycle tracks on Rabai Road 2.5

Total 11.7km

Page 38: Status of Nairobi Roads 2012- 2013

5. Nairobi Urban Transport Improvement Project

�Financing Agreement signed with the World Bank

�Comprised of Six Components:

-JKIA – Museum Hill - Rironi Road

-Bus Rapid Transit for Nairobi BRT (Consultancy)

-Traffic Management Systems for Nairobi

-Mombasa Urban Transport Master Plan

-Light Rail transit for Nairobi

-Capacity Building Component

Page 39: Status of Nairobi Roads 2012- 2013

5. Nairobi Urban Transport Improvement Project

�BRT Corridors

-Haile Selassie – Ring Road Pumwani Junction

-Ring Road Ngara

-Juja Road

-Komarock Road to junction with Kangundo road

-Outering Road from Kangundo Road Junction to

-Komarock Road Junction

Page 40: Status of Nairobi Roads 2012- 2013

Juja Road

Outer Ring Road

Kangundo Road

Jogoo Road

Manyanja Road

Msa Road

Njiru

NCBD

Page 41: Status of Nairobi Roads 2012- 2013

6. GREATER EASTERN BYPASS

- To connect Mombasa Road (A109) at Lukenya Hills to Garissa Road

(A2) at Kilimambogo.

- Detailed engineering designs are ongoing.

7. GREATER SOUTHERN BYPASS

- To connect Mombasa Road (A109) at Athi River to Narok Road (B3) at

Suswa.

- Currently at planning Stage.

Page 42: Status of Nairobi Roads 2012- 2013

PRIVATE SECTOR PARTICIPATION IN

ROAD INFRASTRUCTURE

DEVELOPMENT

Page 43: Status of Nairobi Roads 2012- 2013

1. Funding Models for Road Infrastructure

� Entire Government funding

� Entire Private sector funding (PPP)

� Joint funding by both Government and Private sector.

Page 44: Status of Nairobi Roads 2012- 2013

2. OPPORTUNITIES FOR PRIVATE SECTOR

PARTICIPATION

� Road maintenance

� New Road development

� Public Transport (Bus Rapid Transit Systems - BRT)

� Toll Roads construction

� Toll Bridge construction

Page 45: Status of Nairobi Roads 2012- 2013

WAY FORWARD

1. Enhance investment in Road infrastructure

2. Proper maintenance of existing roads

3. Promote Safety in our roads

4. Encourage private sector participation in Infrastructure

financing and development

5. Improve Public Transport

6. Enhance good governance in Management of Roads.

7. Protection of Road Reserves

8. Proper coordination with other agencies with regard to

demarcation and protection of road corridors