state route 30 over bessemer ave....aug 25, 2016  · quick facts project was let on 11/5/2015 with...

53
STATE ROUTE 30 OVER BESSEMER AVE. SUPERSTRUCTURE REPLACEMENT IN 57 HOURS Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11- 0 Bala Sivakumar, P.E HNTB, Vice President 1

Upload: others

Post on 20-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • STATE ROUTE 30 OVER

    BESSEMER AVE.

    SUPERSTRUCTURE REPLACEMENT IN 57 HOURS

    Louis J. Ruzzi P.E., PennDOT District 11-0 Bridge Engineer John Myler, PennDOT Assistant Construction Engineer, District 11- 0 Bala Sivakumar, P.E HNTB, Vice President

    1

  • Talking

    Points

    Quick Facts – Lou Ruzzi,PE, District Bridge Engineer, PennDOT District 11-0 (Pittsburgh area)

    Project Goals – Lou Ruzzi,PE

    Design Highlights – Bala Sivikumar, PE (HNTB)

    Construction Highlights and Lessons Learned – John Myler, Assistant Construction Engineer, PennDOT District 11-0 (Pittsburgh area)

    2

  • Existing

    Bridge

    3

  • Existing

    Bridge

    Location

    4

    1

    STATE ROUTE 30 over BESSEMER AVE

    Allegheny County, Pennsylvania

  • Existing

    Bridge

    Aerial

    5

  • Quick

    Facts

    Project was let on 11/5/2015 with 3 bidders

    Brayman Construction was the successful low bidder for $2,333,212.

    Second bidder bid the job for $3,130,000

    Third bidder was at $3,209,308

    Pre Bid meeting attended by 4 contractors

    HNTB was the designer

    Pre-Cast Abutment Caps, steel beam modules with concrete deck/barrier, Ultra High Performance Concrete (UHPC) joints between the modules with a latex placed over the deck, pre- cast approach slabs

    SR 30 ADT is 21,798 (2015) with 4% trucks 6

  • Detour

    Route

    7

  • Project

    Goals

    Replace the superstructure over a weekend

    Utilize as many precast/pre-fab elements as possible, UHPC and cover the deck with an appropriate overlay(latex) that would last a long time(20 years)

    Minimize impact to the adjacent property owner

    Applied many lessons learned from a previous project that was built in 7 days

    Considered innovative bidding

    Under-clearance from 13’-9” to 17’-2”

    8

  • Design

    Highlights

    Use of Pro Team Meeting plus subsequent constructability meetings to limit the number of alternatives

    Design the bridge as quickly as possible due to the condition of the existing T Beam bridge (falling debris from superstructure and a hole in the deck)

    9

  • Built 1930

    Carries State Route 30 over Bessemer Ave. in East Pittsburgh, PA; high traffic volume

    Concrete T-Beam Superstructure

    Span = 52’ - 2” -- curved alignment

    Concrete abutments on spread footing. Concrete strengths from 2.5 to 3.6 ksi

    Under-clearance from 13’-9” 17’-2”

    Project required a superstructure replacement with substructure rehab in a single weekend

    Existing

    Bridge

    10

  • Accuracy of As-Built Information to confirm fit

    Choice of ABC method that fits site constraints and 57 hour closure period

    Urban area; limited ROW; overhead wires

    Skew, curvature, super-elevation considerations for ABC design

    Removal and replacement of deteriorated portions of abutment walls

    Approach slab replacement

    ABC connections

    ABC

    Design

    Decisions

    11

  • LIDAR SURVEY : AS-BUILT BRIDGE MODEL

    12

  • As-Built Bridge Model

    Shows Bridge Elements to be Removed

    13

  • ABC Construction Sequence

    Pre-Weekend Closure

    Precut and brace abutment walls along frontface

    Sawcut roadway pavement at ends

    Repair abutment spalls and cracks

    14

  • ABC Construction Sequence

    Weekend Closure (57 Hours) continued

    Demolish superstructure, remove approach slabs and excavate backfill

    Sawcut abutment along backface and remove sections

    Connect abutments caps with dowels

    Erect the six superstructure modules with cranes

    Erect precast sleeper slabs and approach slabs

    Place accelerated cure UHPC closure pours

    Reopen to traffic — Monday 6 AM

    15

  • ABC Construction Sequence

    Post-Weekend Closure

    Backfill abutments with flowable fill (approach slabs are designed to support traffic loads)

    Place and cure rapid set Latex Modified Concrete (LMC) overlay to 1 ¼” depth and sawcut grooves

    Apply epoxy resin protective coating to abutment surfaces

    16

  • Engineer’s ABC Schedule

    17

    Activity Duration (hrs)

    Superstructure & approach roadway removals, backfill excavation

    8

    Substructure saw-cutting and removal 6

    Install precast abutment caps 8

    Install superstructure modules 8

    Install approach slabs 4

    Place UHPC closure pours 5

    Cure time for UHPC 12

    Total Duration (ABC) 51 Hrs

  • ABC Replacement Using Prefabricated

    Bridge Elements

    54’-0” Single Span

    Composite Steel Modular Superstructure (shop painted)

    Straight Steel Beams with Variable Overhangs to Accommodate Curvature

    Accelerated Cure UHPC Closure Pours

    New Precast Abutment Caps to Address Deterioration and Super-elevation

    New Precast Approach Slabs

    18

  • New Superstructure Cross Section

    Design Live Load:

    AASHTO LRFD / PHL-93 OR P-82 (204 Kip PERMIT LOAD)

    Lightweight Concrete (5 ksi) to minimize lifting weights

    19

  • Crane sizes limited by overhead high voltage electrical lines (De-energized during ABC weekend).

    Lightweight Concrete (117 pcf) to minimize lifting weights

    Concrete Stresses During Erection:

    Not to Exceed Modulus of Rupture fr = 7.5*Sqrt(f'ci), Divided by a Safety factor of 1.5.

    Dead Loads Multiplied by a Factor of 1.25.

    Did not control design

    Lifting locations shown for each element

    Design

    Checks

    for

    Erection

    20

  • AutoCad Revit Software

    3D model of existing bridge using Lidar

    New elements modeled in 3D and superimposed on existing

    Virtual assembly of bridge during design

    Check fitup at each stage of assembly

    Several dimensional adjustments were made to precast elements to ensure fit

    3D renderings shared with Contractor

    3D

    Model

    for

    Design

    21

  • New Superstructure Plan

    Straight beams / modules. Bridge curvature accommodated using

    overhangs with variable widths 22

  • Removal of Deteriorated Sections

    23

  • Precast Abutment Caps

    Stepped to Match Superelevation

    24

  • Precast Cap Elevation

    25

    • Steel shims used to achieve proper seat elevations • Gap around shims filled with rapid set grout -- through

    grout ports in cap

  • Replace with Precast Abutment Cap

    26

  • 27

  • Superstructure Interior Module

    28

  • Superstructure Exterior Module

    Includes Sidewalk and Parapet

    29

  • Superstructure Modules Assembly

    30

  • Approach Slab Section

    31

  • Precast Sleeper Slab

    32

  • Abutment Spall and Crack Repairs

    33

  • CONSTRUCTION HIGHLIGHTS

    34

  • Bridge

    Demolition

    Friday 11:15 PM

    35

  • Bridge

    Demolition

    36

  • Bridge

    Demolition

    Friday 11:45 PM

    37

  • Precast

    Abutment

    Cap

    Saturday 1:00 PM

    38

  • Precast

    Abutment

    Cap

    39

  • Precast

    Abutment

    Cap

    Saturday 3:00 PM

    40

  • Precast

    Deck

    Panel

    Sunday 12:00 AM M2- 79 Ton with Rigging

    41

  • Precast

    Deck

    Panel

    Sunday 7:00 AM

    42

  • UHPC

    Placement

    Sunday 4:00 PM

    43

  • UHPC

    Placement

    44

  • New

    Bridge

    after 57

    Hours

    45

  • Approach

    Slab Flow

    Fill

    46

  • Profile

    Milling and

    LMC Prep.

    47

    Saturday 1:15 AM

  • LMC

    Placement

    48

    Saturday 6:20 AM

  • New

    Structure

    and

    Roadway

    49

    Sunday 12:00 PM

  • New

    Structure

    50

  • Time

    Lapse

    Video

    51

    https://youtu.be/0VMMq0fNWjg

  • Lessons

    Learned

    1. More time:

    a. Weekend closure duration

    b. Additional lead time

    2. Improve ability to level precast caps

    3. Reduce deck panel weights

    4. Discuss straight or hoop reinforcement in the UHPC joint.

    5. Water tight seal for UHPC

    6. Latex overlay is recommended

    7. Is structure dry fit necessary?

    8. 3D renderings were very helpful.

    52

  • Closing

    53

    Questions

    Contact info:

    Louis J. Ruzzi : [email protected]> John Myler : [email protected] Bala Sivakumar : [email protected]