standart cina untuk welding
TRANSCRIPT
Standard of Ministry of Electrical Power P.R. China
The Specification of Erection and Acceptance for Power Plant Construction
Welding Section
Issue by Ministry of Electrical Power P.R. China
1
CONTENTS
Chapter 1 General
Chapter 2 Welding personnel
Chapter 3 Base metal & welding materials
Chapter 4 Preparation before welding
Chapter 5 Welding technology
Chapter 6 Post-weld heat treatment
Chapter 7 Quality inspection
Chapter 8 Quality criterion
Chapter 9 Technical documentation
2
Chapter 1 General
1.0.1 This specification is applicable to the welding work of boiler, pressure piping, vessels and
steel structures in the design , fabrication, erection and maintenance of thermal power generating plant (with unit capacity ≤ 600MW) of electrical power industry .
1.0.2 This specification is applicable to the welding technologies of manual arc welding, tungsten
argon arc welding, flame gas welding and automatic submerged arc welding on carbon steel (with carbon content≤ 0.35%), common low-alloy steel and heat resisting steel. For
other materials and welding technologies, technical requirements shall be drawn up
according to this specification and relevant technical standards.
1.0.3 The erection & acceptance of foreign electrical power units shall be carried out according to
this specification except that be specified in the construction contract.
1.0.4 Quality inspection of welding seam shall be carried out separately based on the working
condition and quality requirements of components.
1.0.5 For inspection upon materials and welding joints of equipment , ball test, welding
technology test , welding seam quality inspection and technical examination of welding
operators shall be carried out according to corresponding regulations.
1.0.6 In carrying out welding work , relevant safety, fire prevention , environment protection and
other regulations shall be strictly observed.
Chapter 2 Welding Personnel
2.0.1 Welding personnel include welding technicians, welding quality supervisors , welding
inspectors, welding operators and heat- treatment workers.
2.0.2 Any enterprise should appoint the chief of welding speciality and the full-time welding
quality inspectors.
2.0.2.1 The chief of welding speciality shall have a great deal of welding knowledge and
experience , take the charge of all welding technology and quality management and the
qualification examination of welding personnel.
2.0.2.2 The enterprise and its chief section should organize the technical training to all welding
personnel to raise their technical , theoretical and management level.
2.0.3 Basic requirements upon welding personnel and their work content
2.0.3.1 Welding technicians
(1) The technicians, who takes the technical management of welding work for the first
time , shall have been trained in a systematically way and have gained , at least ,
one-year vocational experience, and shall passed examination and obtained the
qualification certificate.
3
(2) Keeping informed on general status of project; observing this specification strictly;
working out organization design of welding construction and drawing up technical
measures with reality conditions and training program for welding operators, and
participating the work of examination committee of welding operators;
(3) Based upon technical measures, explaining technical intention to relevant personnel
and guiding technique and supervising ;
(4) Organizing the assessment of welding technology and preparing operational guideline
for welding work;
(5) Participating the quality acceptance of important pipes and parts;
(6) Recording, checking and sorting out welding technical data and participating the
preparation of technical summary and handing over technical documents on
completion.
2.0.3.2 Supervisors of welding quality
(1) Supervisors of welding quality shall have gained the educational background of
middle school or higher and required skills and experience, moreover, they shall pass
the special examination and obtain the qualification certificate ;
(2) Be in charge of determining the items to be check , signing and issuing inspection
files, supervision of welding quality , accepting and assessing welding projects;
(3) Participating the audit of technical measures , supervising the implementation of
technical measures at the work site , stopping any violation of regulations in welding
operation in time and reporting to relevant department;
(4) Accumulating and summarizing of quality controlment data & documents , cooperating
with relevant personnel in handing over the data & documents on completion;
(5) Determining the welding seams to be examined, recording the results strictly and
urging relevant department to do the work of quality inspection better;
(6) Checking the qualification certificates of welding operators , overseeing their skill
status. For those whose welding results frequently fail to meet the requirements,
supervisors have the authority to cease their welding work and suggest the welder
examination committee to suspend their qualification certificates.
2.0.3.3 Welding inspectors
(1) The welding inspectors shall have undergone specialized technical training and
succeeded in passing the examination and obtaining qualification certificates before
being assigned for corresponding welding inspection work.
(2) Welding inspectors shall perform inspecting , checking and assessing the quality of
welding seams in conformity with this specification and relevant standards;
(3) Welding inspectors shall inspect timely upon the localities determined by the welding
quality supervisor and raise up accurate and correct conclusion;
(4) Welding inspectors shall fill , marshal and reserve all the data and documents of
4
inspection.
(5) Welding inspectors shall refuse doing the NDT if the joint visual examination is not
passed.
2.0.3.4 Welding operators
(1) Welding operators shall have been trained with welding knowledge and practical
operating vocational skills and have been examined ;
(2) Those welding operators, who are assigned to carry out welding work of the following
component, shall be qualified in passing the relevant technical examination;
a. Bearing steel structures: boiler steel framework (main columns and main beams),
hoisting equipment structures, and rooftrees of main machine hall;
b. Boiler heating surface tubes ;
c. Pipes and vessels with working pressure above 0.1Mpa ;
d. Vessels for storing flammable and explosive medium (fluid or gas) and their
transporting pipes;
e. Welding up non-bearing components on bearing structure under supervision.
f. Welding up the parts which will rotate at high speed
(3) Welders shall observe the professional ethics , carrying out welding operation strictly
according to the given technology and measures, observing welding operational
guidance given in this specification or by his/her employer.
(4) Welders shall carefully read the operational guidance before starting welding , and
shall refuse any welding operation inconsistent with the guidance . Any major quality
problem shall be reported timely to the relevant personnel, on occurring , and shall not
be treated without authorization.
(5) The examination shall be taken again for the qualified welder having been interrupted
welding operation of supervised parts for more than six months.
(6) The qualified welder shall not allowed to do the welding works exceed the extent of
his qualified items.
2.0.3.5 Heat treatment worker
(1) Heat treatment workers shall have undergone specialized technical training and
succeeded in passing the qualification examination;
(2) Heat treatment worker shall observe the relevant stipulations in this specification and
welding technical measures regarding to heat treatment , execute the operations
without mistake and make the data record accurately;
(3) On the completion of heat treatment, the worker shall proceed to self-inspection and
have the heat treatment data and documents sorted well for accumulation.
Chapter 3 Base Metal & Welding Materials
5
3.0.1 Prior to welding , the grade of the materials to be welded shall be found out in order to
select the relevant weld materials and to ascertain the appropriate processes of welding
and heat treatment.
3.0.2 The steels to be welded shall conform with the national standards (or ministerial
standards , technical standards ) . Imported steels shall correspond to the contract
requirements or the standards of the country.
3.0.3 The quality of welding materials such as welding electrodes, welding wires, tungsten rods,
argon gas, oxygen, acetylene and flux shall conform with national standards (or relevant
standards)
3.0.4 There shall be qualification certificates for steels , welding electrodes and wires from the
manufacturers . In case these are lacking or there is any doubt raised upon their quality,
tests on random sampling from each batch shall be carried out and only those being
tested to be qualified, can be put in use.
3.0.5 The selection of welding electrodes and wires shall be based upon comprehensive
considerations for chemical composition, mechanical and anti-cracking properties,
carbon-diffusion, preheating, post-weld heat treatment of weld-butting as well as usage
condition , etc. .
3.0.5.1 In welding of same type steel, the selection of welding electrodes (wires) shall in general
conform with the following requirements:
(1) The chemical composition and mechanical properties of welding seam metal shall
correspond with those of parent metal;
(2) Possessing superior technological properties.
3.0.5.2 In welding of different type steels, the selection of welding electrodes (wires) shall in
general conform with the following requirements:
(1) For steel , which both sides not austenic stainless steel , welding electrodes (wires)
whose composition matches with that of the side containing less alloy , or lies in
between the content of both sides , can be employed;
(2) For one side being austenic stainless steel , welding electrodes (wires) of stainless
steel with higher nickel content can be employed;
3.0.6 Thorium-tungsten rods shall be used for tungsten argon arc welding , and the purity of
argon gas shall not be lower than 99.95%.
3.0.7 The purity of oxygen used for oxygen-acetylene welding shall be above 98.5%. The purity of acetylene shall be conform with the requirements of GB6819-86 《Solution of Calcium
Carbide》. The calcium carbide used for producing acetylene shall be provided with
shipping certificate , the quality of calcium carbide for flame welding can be determined by
the way of testing sulphur and phosphorus contents contained in the welding seam
(according to the standards for welded metal); The gas employed in butt welding shall
6
have been in general filtered. The calcium carbide , which has not been checked or
whose impurity exceeds standard value , shall not be used for welding.
Chapter 4 Preparations before Welding
4.0.1 The location of welding seams shall be away from the areas of stress concentration and
shall be easy for welding operating and heat treatment . In general , it shall conform with
the following requirements:
4.0.1.1 For butt welding of boiler heating surface tubes, the center line of the welding seam shall
be spaced from the starting point of tube bend or from external wall of drum or header as
well as from the sides of suspension or hanger bracket for at least 70mm ; the space
between two butt welds shall not be less than 150mm ;
4.0.1.2 For butt welding of pipes, the space between center line of the welding seam and the
starting point of pipe bending shall be not less than the external diameter of pipe, and not
less than 100mm (except welded , forged or cast pipe piece) and the space to the side of
suspension or hanger bracket shall be at least 50mm . In addition , space between butt
welding seams shall not be less than both the pipe diameter and 150mm .
4.0.1.3 The tube/pipe joints and receptacles of instrumentation , in general , shall not be placed at
/welding seam or in heat-affected-zone.
4.0.1.4 For butt welding of cylindrical shell , the center line of the welding seam shall be spaced
from the starting point of bending of sealing head for not less than the sum of wall
thickness plus 15mm , and , in addition , shall be not less than 25mm , but not more than
50mm .
4.0.1.5 For cylindrical shells and sealing heads with longitudinal welding seams ,the two adjacent
longitudinal seams shall be spaced more than 3 times of wall thickness and not less than
100mm.
4.0.1.6 The holes of welded-on tubes/pipes shall be opened away from the welding seams as
much as possible . The welding seams of tubes/pipes holes shall be kept not to coincide
heat-affected-zone of the adjacent weld seam . In case this is unavoidable , holes can be
opened on the welding seams or at its vicinity only after the following requirements have
been met:
(1) On both side of the pipe hole, the welding seam within 60mm away from the edge of
hole , shall base on the requirement of Table 8.0.3 , be non-destructively tested and
proven to be qualified;
(2) The edge of the hole shall not be on the defects of welding seams;
(3) The pipe joints shall have the stress relieved by post welding heat-treatment.
4.0.1.7 For lap welded joints, the dimension of lapping shall be not less than 5 times of the parent
metal thickness , and in any case , not less than 30mm.
7
8
4.0.2 The grooves of tubes/pipes, pressure vessels and steel structures shall be made
according to the stipulation of design drawings . In case there is no such stipulation , the
shape and dimension of grooves shall be selected with respect to the principle that it can
assure the welding quality with fewer quantity of filler metal ,ease of operating, improving
working condition , reducing welding stress and deformation , adapting to the requirement
of non-destructive testing , etc.
Shapes and dimensions of welding joints generally used are shown in Table 4.0.2.
Table 4.0.2 Basic patterns and sizes of weld joints
Structure size of joints Serial number
Patterns of joints
Patterns of bevel Diagram Welding
methods
Weldment thicknessδ
(mm) α β b (mm)
P (mm)
R (mm)
Scope
1 Ⅰ
Gas welding Electric welding
Buried arc welding
<3 ≤ 3
8~16 — —
1~2 1~2 0~1
— — Vessels and common steel structure
2 Ⅴ
Gas welding Electric
arc welding
Buried arc welding
≤ 6
≤ 16 >16~20
30º~35º — 1~3 1~3 0~1
0.5~2 1~2
7 —
All types of pressure pipes, pressure vessels and medium and thin pressure structure
3
Butt joint
U
Electric arc
welding ≤ 60 10º~15º — 2~3 2 5
Steam water tubing with medium and thick walls
9
To be continued
Structure size of joints Serial
number Patterns of joints Patterns of bevel Diagram Welding
methods
Weldment thickness
δ (mm)
α β b (mm)
P (mm)
R (mm)
Scope
4 Double V
Horizontal pipe
Electric arc
welding >16~60
30º~40º
8º~12º 2~5 1~2 5
Steam water tubing with medium and thick walls
5
Butt joint
Double V
Vertical pipe
Electric arc
welding >16~60
α 1=
35º~40º α 2=
20º~25º
β 1=
15º~20º β 2=
5º~10º
1~4 1~2 5
Steam water tubing with medium and thick walls
10
To be continued
Structure size of joints Serial
number Patterns of joints
Patterns of bevel Diagram Welding
methods
Weldment thickness
δ (mm)
α β b (mm)
P (mm)
R (mm)
Scope
6 Comprehensive shape
Electric arc
welding >60
20º~25º
5º 2~3 2 5
Steam water tubing with thick walls
7
Butt joint
Xshape
Electric arc
welding Buried
arc welding
>16 >20
30º~35º
— 2~3 0~1
2~4 7 —
Both sides welding large vessels and structure
11
To be continued
Structure size of joints Serial
number Patterns of joints
Patterns of bevel Diagram Welding
methods
Weldment thickness
δ (mm)
α β b (mm)
P (mm)
R (mm)
Scope
8 Closure head
Electric arc
welding
Pipe diameter
not limited
Process requirements of bevel of wall pipe of same thickness
Steam water tubing and collecting
box closure head
9
Butt joint
Casing cap
Electric arc
welding Diameter Process requirements of bevel of
wall pipe of same thickness
Steam water tubing and collecting
box casing cap
12
To be continued
Structure size of joints Serial
number Patterns of joints
Patterns of bevel Diagram Welding
methods
Weldment thickness
δ (mm)
α β b (mm)
P (mm)
R (mm)
Scope
10
Electric arc
welding
Diameter of pipe
Φ ≤ 76
50º~6030º~35
º 2~3 1~2
According to
difference of wall
thickness
Connection pipe socket of Steam water, meter and samples, etc
11
T Pipe socket
Electric arc
welding
Diameter of pipe
Φ 76~ 133
50º~6030º~35
º 2~3 1~2 —
Connection pipe socket or joint of common steam water pipe and vessels
13
To be continued
Structure size of joints Serial
number Patterns of joints
Patterns of bevel Diagram Welding
methods
Weldment thickness
δ (mm)
α β b (mm)
P (mm)
R (mm)
Scope
12 No bevel
Electric arc
welding Buried
arc welding
≤ 20 >8
— — 0~2 — —
Complete fusion structure is not required
Electric arc
welding Buried
arc welding
>20 50º
~60º — 0~2
≤ 2
δ 3
—
Complete fusion structure is not required
13
T shape
Single V pattern
Electric arc
welding Buried
arc welding
≤ 20 50º
~60º — 1~2 1~2 —
Complete fusion structure is required
To be continued
14
Structure size of joints Serial
number Patterns of joints
Patterns of bevel Diagram Welding
methods
Weldment thickness
δ (mm)
α β b (mm)
P (mm)
R (mm)
Scope
14 T shape K pattern
Electric arc
welding Buried
arc welding
>20 50º
~60º — 1~2 1~2 —
Complete fusion large structure is required
15 Butt joint
Gas arc welding Electric
arc welding Buried
arc welding
≤ 4
≥ 4
>8
— — 0~1 — — Vessels and structure
2) Pipes with wall thickness less than or equal to 6mm of heated surface can also be rendered and finished by argon-arc welding.
4) δ 1 value of closure head should accord with design; f value should accord with design and should not be less than 20mm. 3) Pipes with wall thickness larger than 6mm can be rendered by argon-arc welding and finished by electric arc welding.
1) Tungsten electrode argon-arc welding is same with electric arc welding in structure and size of weld junction .
15
5) The lapping size L equals to 5δ , and is not less than 30mm.
Notes :
4.0.3 In cutting off parent material and grooving ,the following requirements shall in general be
complied with:
4.0.3.1 It is preferable that the cutting off the pieces to be welded is done by machining,
especially for the kind of alloy steel which tends to become more or less hardened in
quenching , and for the pipes/tubes of steam/water with nominal diameter<100mm and
those with nominal diameter>100mm at working pressure above 3.9MPa .
4.0.3.2 If cutting pieces through the heat-method , e.g. flame cutting , the part of cutting edge
shall be long enough in order to remove the quench hardened and over-heated metal .
4.0.3.3 It is preferable that the grooving be done by machining . If groove cut by flame , the oxide
matter slag splashing and other debris thereon shall be thoroughly chiseled off and the
unsmoothness be trimmed;
4.0.4 In cutting off workpiece and grooves, the following requirements shall in general be
complied with:
(1) For alloy steel which tends to become more hardened in quenching ,the part of cutting
edge shall undergo surface flaw detection test after flame cutting;
(2) On the edge of groove which is cut through shears , there shall be no defects such as
cracks , rags , cut away edges , etc. on base metal.
(3) The size of the groove conform with the requirements in the drawing samples.
(4) There shall be no defects such as cracks in the scope of being cleaned specified in
4.0.5.
4.0.5 Before the piece to be welded being assembled , the surface of weld junction and oil
stain , paint , dirt and rust on the internal and external wall shall be thoroughly cleaned to
the metallic luster . At the same time , inspection shall be made to ascertain there are no
defects as cracks, entrapped layer , etc. . The scope of cleaning is stipulated as follows:
(1) For weld junction of manual welding , cleaning to be extended to over 10mm on both
sides;
(2) For weld junction by automatic submerged arc welding , cleaning to be extend to over
20mm on both sides;
(3) For weld junction of fillet welding, cleaning to be extend 10mm beyond the fillet weld
size.
4.0.6 The end surface of butting tube/pipe shall be perpendicular to the center line with a deviation allowance (△ f ) specified in Table 4.0.6.
Table 4.0.6 Deviation requirements of end surface to center line of tube/pipe
Illustration External diameter of pipe
(mm)
△ f
(mm)
≤ 60
>60~159
>159~219
0.5
1
1.5
16
>219 2
4.0.7 While the piece to be welded being butted , the inner walls shall be , in general , kept flat .
In case there is slight offset , its magnitude shall conform with the following requirements:
1) The part offset for single-sided butt welding shall be not more than 10% of the wall
thickness , and not more than 1mm;
2) The part offset for double-sided butt welding shall be not more than 10% of the
thickness of the piece to be welded , and not more than 3mm.
4.0.8 In butting pieces to be welded of different thickness , the following ways to solve the
deviation of thickness can be resorted:
1) Inside wall dimension unequal and external wall suited flat , the groove can be shaped
as shown in Fig. 4.0.8(a);
2) External wall dimension unequal and inside wall suited flat , the groove can be shaped
as shown in Fig. 4.0.8(b);
3) Both the inside and external wall dimensions unequal , the groove can be shaped as
shown in Fig. 4.0.8(c); 4) Inside wall dimensions unequal and difference of thickness≤ 5mm , the groove can be
shaped as shown in Fig. 4.0.8(d) , as long as the strength of piece to be welded is not
impaired.
Fig. 4.0.8 the solution on butt welding of pipe with different wall thickness (a)Inside wall dimension unequal (b)External wall dimension unequal
(c)Both the inside and external wall dimensions unequal (d)δ2-δ1 ≤ 5mm
17
4.0.9 In case the partial gap of weld junction is too large , it shall be imperative to mend it to
stipulated size strively. It is strictly forbidden to fill in foreign materials.
4.0.10 Welding electrodes and flux shall be kept in dry , ventilated house and the temperature shall be above 5℃ & the humidity of air less than 60% .
Welding electrodes and flux shall be baked according to the requirements of specification before being used ,but the times of baking shall not more than twice. Before being use , the welding
wires shall be cleaned to such degree removing any rust and oil stain up to metallic luster
appears.
Those electrodes to be used for important parts shall be kept in special dry box and the temperature at the range of 100~150℃.
Those electrodes kept above one year and to be used for important part ,shall undergo the exam
if any doubt ,it shall be used only when the results of exam conform with the requirements.
4.0.11 On assembling the pieces to be welded , care shall be taken to have them leveled up firmly in
order to avoid them getting deformed in the course of welding and heat treatment.
4.0.12 Except butting through cold drawing forth as stipulation in design , butting by force shall be
prohibited in order to avoid additional stress.
4.0.13 At the welding site , anti-blow , rainproof , snowproof and anti-freeze measures shall be
taken.
4.0.14 The course of welding include four stages , i.e., assembly , welding, heat-treatment , and
inspection . The course shall be continued only while the last stage conform with the
requirements.
4.0.15 Qualified welding operators shall take simulated exercises and pass the fracture surface
checking before they are assigned to welding up boiler heating surface tubes .
Chapter 5 Welding Technology 5.0.1 The allowable lowest ambient temperatures during welding are as follows: low carbon steels -10℃
low alloy steels and common low-alloy steels 0℃
medium and high alloy steels 10 ℃
5.0.2 The preheat temperature of various steel before being welded are shown in Table 5.0.2 ;
additionally the following stipulations shall be observed :
Table 5.0.2 Preheat Temperature
tube/pipe plate
Grade wall thickness
(mm)
Preheat
Temperature(°C)
thickness
(mm)
Preheat
Temperature(°C)
forge and carbon steel with c≤ 0.35% ≥ 26 100~200 ≥ 34 100~150
18
C-Mn(16Mn) ≥ 15 150~200 ≥ 30 100~150
Mn-V(15MnV) ≥ 15 150~200 ≥ 28 100~150
1/2Cr-1/2Mo(12CrMo) - - ≥ 15 150~200
1Cr-1/2Mo(15CrMo,ZG20CrMo) ≥ 10 150~250 ≥ 15 150~200
1 1/2Mn-1/2Mo-V(14MnMoV,18MnMoNbg) - - ≥ 15 150~200
1Cr-1/2Mo-V(12Cr1MoV,ZG20CrMo) - 200~300 - -
1 1/2Cr-1Mo-V(15Cr1Mo1V,ZG15Cr1Mo1V) ≥ 6 250~350 - -
2Cr-1/2Mo-VW(12Cr2MoWV) ≥ 6 250~350 - -
1 3/4Cr-1/2Mo-V ≥ 6 250~350 - -
2 1/4Cr-1Mo(12Cr2Mo) ≥ 6 250~350 - -
3Cr-1Mo-VTi(12Cr2MoVSiTiB) ≥ 6 250~350 - -
9Cr-1Mo - 300~400 - -
12Cr-1Mo-V - 300~400 - -
Notes: (1) When tungsten electrode argon-arc welding is utilized for rendering, 50℃can be lowered
than the temperature of lower limit.
(2) When the external diameter of pipe is larger than 219mm or wall thickness is larger than or
equal to 20mm, pre-heating can be performed with electrical heating method.
5.0.2.1 The preheat requirements shall be raised based upon the results of welding technological
test ; 5.0.2.2 For alloy steel pipes and their ancillary components (e.g. tee-piece , bent pipe)with wall
thickness≥ 6mm to be welded under an ambient temperature below 0℃ the preheated
temperatures shall be raised up 20~50℃ above the stipulated values given in Table 5.0.2 ;
5.0.2.3 Low alloy steel pipes with wall thickness <6mm and low carbon steel pipes with wall thickness>15mm to be welded under an ambient temperature below 0℃,shall also be
appropriately preheated ;
5.0.2.4 While welding up different type steels , the preheat temperature shall be selected in
accordance with that material with poorer weld ability or higher content of alloy ;
5.0.2.5 In welding up main pipe with stub , the preheated temperature shall conform with the
stipulation for main pipe ;
5.0.2.6 In welding up unpressurized components onto the pressure vessel , the preheated
temperature shall be selected according to the pressure vessel .
5.0.3 The width of preheat band shall be measured from the center of butting extending , not less
than 3 times of weldpiece wall thickness on each side .
5.0.4 In the course of welding, the temperature of interpass shall not be lower than the lower limit of preheat temperature and not higher than 400 ℃ .
5.0.5 In order to assure the inner side of pipe cleaned and the root layer quality of seam , the
welding method shall conform with the stipulation in Table 5.0.5 for pressure piping welding .
Table 5.0.5 Welding Methods of Pressure Pipe
19
Name of parts welding pass of root other pass
boiler heating surface pipe with p≥ 10MPa, δ≤ 6mm TIG TIG/SMAW
pipe/stub with p≥ 10MPa, δ>6mm TIG SMAW
pipe with p≥ 4MPa, t≥ 450°C TIG SMAW
reheated steam cool & hot pipes, bypass pipes TIG SMAW
pipes of cooling , lubricant and fuel , T/G TIG TIG/SMAW
boiler heating surface pipe with p<10MPa, δ≤ 6mm TIG TIG/SMAW
Other pipes TIG SMAW
5.0.6 For medium or high alloy steel pipes (Cr content ≥ 3% or total alloy content >5% ) , argon or
mixed gas shall be fill in to prevent the root layer from being oxidized or overburnt .
5.0.7 It is strictly forbidden to initiate arc , test the electric current amount or weld temporary
supports on the work pieces to be welded.
5.0.8 While tube/pipe being welded , there shall not be air-flow blowing through.
5.0.9 In tack-welding at root position of butt joint , similar requirements regarding welding materials ,
technology , operator and preheated temperatures as those stipulated for normal welding shall
come into effect . In addition , the following requirements shall be met :
5.0.9.1 After tack-welding at root position of butt joint, the quality of each welding point shall be
inspected . When defects being discovered , it shall be remove at once and tack-welding shall be
done again .
5.0.9.2 Care shall be taken to prevent damaged to base metal while removing temporary tack used
for tack-welding of large wall thickness pipes . The residual weld deposit shall be removed off and
repaired .
5.0.10 While tungsten argon arc welding being employed for root layer seam , in order to avoid the
occurrence of cracks , welding of next layer seam shall be timely carried out once the previous
layer has been inspected .
In welding up multi-layer and multi-run seams , attention shall be paid to the defects occurring in
each layer , and proceeding to the next layer can be continued only after the seam quality being
ascertained qualified by operator’s own inspection.
5.0.11 The pipe of large wall thickness and diameter shall be welded with multi-layer and multi-run
welding , when the thickness of the pipe more than 35mm , the following requirement shall be
met :
5.0.11.1 The thickness of root layer welded by tungsten argon arc welding shall be not less than
3mm;
5.0.11.2 The thickness of the rest layer of other pass shall not more than the electrode diameter plus
2mm;
5.0.11.3 The oscillation width of single pass shall not more than five times of diameter . For the
arrangement of multi-run pass of large wall thickness pipe see the Fig. 5.0.11.
20
Fig. 5.0.11 Pass arrangement for welding up thick-wall pipes
5.0.12 In order to minimize welding deformation and defects , it is preferable that welding by two
operators simultaneously at symmetrical positions for butt welding of pipes with diameter larger
than 194mm is to be resorted.
5.0.13 The welding of steel structure shall conform with welding procedure specifications .
5.0.14 In the course of welding , special attention shall be paid to the quality of joint and arc
extinction , the joint of multi-layer shall be stagger , while extinguishing arc , the fused bath shall
be filled up.
5.0.15 Welding shall be carried out continuously to completion except interruptions necessary for technology or inspection . In case of interruptions , measures (e.g. , post-heating , slow-cooling ,
or thermal insulation)shall be taken to prevent the occurrence of cracks . Close inspection on
whether any crack occurs shall be carried out before welding proceeding .
5.0.16 For butt welding of pipes or vessels with nominal diameter>1000mm,double-side welding at
symmetrical positions shall be employed . In order to ensure the quality of sealing end welding ,
root layer of welding seam shall be cleaned up , and the oxide shall be removed .
5.0.17 For the concealed welding seams which have to be inspected , inspection shall be done to
verify their qualification before going on the next process.
5.0.18 On the completion of welding , a clear up shall be done around the seam which is to be
inspected by the operators on their own for qualifications . The embossed stamp bearing the
operators number or designation can then be applied near the welding seam.
5.0.19 For the steel which is liable to form delayed crack , heat treatment shall be applied soon after
welding . Otherwise , post-heat-treatment shall be required with a temperature preferably to be 250-350℃,followed by a slow cooling process and thermal insulation . The scope of heating is the
same as that of heat-treatment.
5.0.20 In case of defects exceeding the allowable range , mending by cutting out and patching can
be resorted as remedial measures . However , such mending can not be applied more than three times (twice for medium and high alloy steel)at the same location , and shall be done in
accordance to the stipulations as follows :
5.0.20.1 The defects are to be removed thoroughly;
5.0.20.2 Mending weld shall be carried out according to the technological requirements , and
specified procedures of mending .
21
5.0.20.3 For welds requiring immediate heat treatment , heat treatment shall be done once again
after mending .
5.0.21 The tools used for fixing cold drawn welding gap of pipes shall be dismounted only after
completion of en bloc butt welding and heat treatment.
5.0.22 Do not allow to correct the welding joint by heating.
Chapter 6 Post Welding Heat Treatment
6.0.1 The aim of heat treatment is to reduce the stress at the welding joint and to improve the
metallic structure and property of the seam . Consequently it shall be carried out in conformity
with the heat treatment specification and relevant stipulations.
6.0.2 Heat treatment shall be carried out for the following welding joints after they being welded:
6.0.2.1 Carbon steel pipes and pipe auxiliary components with wall thickness more than 30mm;
6.0.2.2 Carbon steel vessels with wall thickness more than 32mm;
6.0.2.3 Common low alloy steel vessels with wall thickness more than 28mm; 6.0.2.4 Thermal resisting steel pipes and their auxiliary components(except those in 6.0.3);
6.0.2.5 Weld pieces which required heat treatment as determined by welding technology test and
assessment .
6.0.3 The following parts which are welded by argon arc welding or low hydrogen electrodes and
treated by preheating and appropriately slow-cooling after welding , shall be exempted from heat
treatment . 6.0.3.1 Alloy steel pipes of 15CrMo 、12Cr2Mo with wall thickness ≤ 10mm and diameter≤ 108mm;
6.0.3.2 Pipes of 12Cr1MoV with wall thickness≤ 8mm and diameter≤ 108mm .
6.0.3.3 Pipes of 12Cr2MoWVB with wall thickness≤ 6mm and diameter≤ 63mm .
6.0.4 Post welding heat treatment generally is high temperature tempering.
The heat treatment temperatures and sustaining duration for commonly used steels are shown in
Table 6.0.4. Table 6.0.4 Post weld heat treatment temperature (°C)
temperature thickness(mm)
steel grade ≤ 12.5 >12.5~25 >25~37.5 >37.5~50 >50~75 >75~100 >100~125
(°C) sustaining duration(hour)
C≤ 0.35(20g,ZG25) , C-Mn(16Mn) 600~650 - - 1 1/2 2 2 1/4 2 1/2 2 3/4
1/2Cr-1/2Mo(12CrMo) 650~700 1/2 1 1 1/2 2 2 1/4 2 1/2 2 3/4
1Cr-1/2Mo(15CrMo,ZG20CrMo) 670~700 1/2 1 1 1/2 2 2 1/4 2 1/2 2 3/4
1Cr-1/2Mo-V(12Cr1MoV,ZG20CrMo) 720~750 1/2 1 1 1/2 2 3 4 5
1 1/2Cr-1Mo-V(ZG15Cr1Mo1V) 720~750 1/2 1 1 1/2 2 3 4 5
1 3/4Cr-1/2Mo-V 720~750 1/2 1 1 1/2 2 3 4 5
22
2 1/4Cr-1Mo(12Cr2Mo) 720~750 1/2 1 1 1/2 2 3 4 5
2Cr-1/2Mo-VW(12Cr2MoWVB) 750~780 3/4 1 1/4 1 3/4 2 3 1/4 4 1/4 5 1/4
3Cr-1Mo-VTi(12Cr2MoVSiTiB) 750~780 3/4 1 1/4 1 3/4 2 3 1/4 4 1/4 5 1/4
9Cr-1Mo 750~780 1/2 1 1 1/2 2 1/4 3 4 5
12Cr-1Mo 750~780 1/2 1 1/2 2 3 4 5
6.0.5 In the course of heat treatment , the ramming of temperature rise and drop are stipulated as
follows:
6.0.5.1 The ramp of temperature rise and drop can be in general calculated by 250X25/wall thickness ℃/hour , but not more than 300℃/hour;
6.0.5.2 In the course of temperature rise and drop , control is not required when the temperature is lower than 300℃ .
6.0.6 For post-weld heat treatment of weld-joint of different kinds of steel , the steel materials on the
two sides and the welding electrodes (wires) to be used shall be taken into synthetically
consideration . The heat treatment temperature shall in general not exceed the lower critical point
Ac1 of that side of steel with lower content of alloy .
6.0.7 The width of heated band in heat treatment , measured from the center line of seam , shall be ,
on each side , not less than three times of the tube wall thickness , and , in any case , not less
than 60mm .
6.0.8 The width of heat insulated band shall not less 5 times of pipe wall thickness from the center
line of weld seam on each side , in order to reduce the temperature grade .
6.0.9 The heating method shall keep the temperature evenly distributed on the interior and exterior
walls of the tube and on both sides of the seam , with the temperature diffidence between any two measuring points in heated area lower than 50℃while temperature sustaining .
Resistance-heating or induction heating shall be adopted for welding pipes with wall thickness
more than 100mm .
6.0.10 The temperature in heat treatment must be measured accurately and recorded automatically .
The instruments , thermocouples , and their accessories shall be calibrated accordingly .
6.0.11 In heat treatment , temperature measuring points shall be located symmetrical about the
center line of the seam . The number of the measuring points shall not be less than 2 . The
measuring points for horizontal piping shall be located symmetrically in verticality .
6.0.12 After heat treatment , the welding joint shall be stamped on the operator’s number or other
durable marks . The record shall be made on heat treatment .
Chapter 7 Quality Inspection 7.0.1 Serious attention shall be paid to the checking and inspecting of welding quality , implementing
23
a system of welding quality tri-grade checking and inspecting , and a combined way of
operator's own and specialized inspecting , making the inspection and assessment work better .
Welding quality checking include three stages as pre-welding , interim welding and post welding
inspection , it shall be implemented strictly according to the items and procedures .
7.0.2 Method , scope and amount of inspection upon welding joints are shown in Table 7.0.2 , the
following requirements shall also be met :
Table 7.0.2
type of inspection method and ratio(%)
welding extent visual examination
joint self-inspec
tion
special-ins
pection
radiographic
inspection
ultrasonic
inspection
hardness
check
spectrum
analysis
Ⅰ boiler heating surface tubes with work
pressure≥ 9.81MPa 100 100 25 25 5 10
Ⅰ
boiler body tubes/pipes & fits with
external diameter >159mm or wall
thickness >20mm and work pressure
≥ 9.81MPa
100 100 100 100 100
Ⅰ steam pipes with external diameter
>159mm, work temp≥ 450℃ 100 100 100 100 100
Ⅰ steam , water , oil , gas pipes with
work pressure >8MPa 100 100 50 100 100
Ⅰ
steam/water tubes/pipes &fits with
work temperature:
300℃<work temp≤ 450℃
100 50 50 100 100
Ⅰ pressure vessel with work pressure is
at the range of 0.1~1.6MPa 100 50 50 100 100
type of method of inspection and inspection ratio(%)
welding extent visual examination
joint self-inspec
tion
special-ins
pection
radiographic
inspection
ultrasonic
inspection
hardness
check
spectrum
analysis
Ⅱ boiler heating surface tubes with work
pressure≤ 9.81MPa 100 25 25 5 -
Ⅱ
steam tubes/pipes & fits with work
temperature:
150℃< work temp ≤ 300℃
100 25 5 100 -
Ⅱ
steam , water , oil , gas pipes with
work pressure is at range of
4MPa~8MPa
100 25 5 100 -
24
Ⅱ
steam , water , oil , gas pipes with
work pressure is at the range of
1.6MPa~4MPa
100 25 5 - -
Ⅱ steel structure bearing the still load 100 25 3) - -
Ⅲ
steam , water , oil , gas pipe with work
pressure is at the range of
0.1MPa~1.6MPa
100 25 1 - -
Ⅲ exhaust gas, wind, coal , coal powder,
coal ash pipes & fits 100 25 4) - -
Ⅲ nonpressure steel structure and
sealing structure 100 10 - - - -
Ⅲ
common support structure
(equipment support, ladder , plate,
pull hole ect.)
100 10 - - - -
Ⅲ
scattering water , drain water, drain
dirty and sampling tubes/pipes of
boiler water pressure test extent with
external diameter <76mm
100 100 - - - -
7.0.2.1 Welding seams , which do not pass the visual inspection , shall not undergo other items of
inspection.
7.0.2.2 NDT shall be done after heat treatment if the welding joint needs to be heat treated .
7.0.2.3 After alloy steel being welded, spectral analysis shall be done according to the following
requirements:
(1) Boiler heating surface tubes not less than 10%
(2) other tubes and pipes 100%
(3) Spectral analysis shall be done according to the quantity of welding joints that the welder
completed that day.
7.0.4 In case the NDT results shows some welding joints unqualified , in addition the defects shall
be repaired , and double quantity inspection shall be done on the seams welded by the operator
on the day . If there are still unqualified welding joints , the seams welded by the operator on that
day shall be considered unqualified .
7.0.5 The disqualification cause shall be found out in order to take appropriate measures and to
execute the reparation . Inspection shall be redone after repairing .
7.0.6 In case the heat treatment automatic recording curve unnormal , spot-check of hardness shall
be taken . Hardness of random sampling parts exceeds the stipulated range , the number for
rechecking on that shift shall be doubled and the causes shall be found out . Those joints which
prove to be disqualified shall undergo heat treatment once more .
7.0.7 In order to reflect the quality condition , the first qualification ratio of NDT shall be calculated
25
statistically by part and by whole after welding inspection. The calculation formula is shown as
follows :
First inspection qualification ratio of NDT = A B
A− 100%
A is quantity of welding joints of first inspected (not including the equivalent quantity of
re-inspection and repeated double quantity inspection).
B is quantity of disqualified welding joints (including cutting out and patching ,cutting , redoing)
Chapter 8 Criterion for Quality 8.0.1 By visual inspection , the quality of welding seams shall conform with the following
requirement :
8.0.1.1 The edge of welding seam shall transit smoothly to the parent metal , the outline dimension
of welding seam shall conform with the requirements of the design , its allowable dimension
shown in Table 8.0.1-1 . Table 8.0.1-1 Allowable outline dimension of welding seams (mm)
joint type
welding seam
and position
types
Ⅰ
Ⅱ
Ⅲ
butt welding joint reinforcement flat position 0~2 0~3 0~4
other position ≯ 3 ≯ 4 ≤ 5
butt welding joint difference of flat position ≤ 2 ≤ 2 ≤ 3
reinforcement other position ≤ 2 <3 <4
butt welding joint width of welding seam wider than groove <4 ≤ 4 ≤ 5
increase each side <2 ≤ 2 ≤ 3
leg of fillet weld δ+(2~3) δ+(2~4) δ+(3~5)
fillet welding joint fillet welding deviation of weld leg
dimension
<2 ≤ 2 ≤ 3
fillet welding joint
groove fillet welding
leg of a
fillet weld
δ≤ 20
δ>20
δ±1.5
δ±2
δ±2
δ±2.5
δ±2.5
δ±3
deviation
of weld leg
dimension
δ≤ 20
δ>20
<2
<3
≤ 2
<3
≤ 3
<4
Notes: a. Sharp groove, with depth larger than 1mm, is not allowed to appear on weld surface which
should not lower than matrix surface.
b. Weld leg of lap angle weld should be same with components in thickness.
26
8.0.1.2 The allowable range of superficial defects of welding seams are shown in Table 8.0.1-2 .
Table 8.0.1-2 Allowable range of superficial defects of welding seams
welding seam types quality requirements
defect name Ⅰ Ⅱ Ⅲ
crack, lack of fusion not allowed
root incomplete penetration
not allowed
depth≯ 10%δ & ≯ 1.5mm
total length ≯ 10% welding
seam length
not allowed for the root
welding seam with tungsten
argon arc welding
depth≯ 15%δ & ≯ 2mm
total length ≯ 15% welding
seam length
blowhole, slag inclusion not allowed
undercut
not required to
be repaired
depth≯ 0.5mm
total length of both side:
for pipe, ≯ 10% total length
of welding seam, & ≯ 40mm;
for plate, ≯ 10% total length
of welding seam
depth≯ 0.5mm
total length of both side:
for pipe, ≯ 20% total length
of welding seam
for plate, ≯ 15% total length
of welding seam
depth≯ 0.5mm
total length of both side:
for pipe, ≯ 20% total length
of welding seam
for plate, ≯ 20% total length
of welding seam
required to be
repaired
not allowed
convex root
≯ 2mm
for plate and pipe with diameter ≥ 108mm: ≯ 3
for pipe with diameter <108mm , shall content passing ball
test requirements as following:
while pipe diameter ≥ 32mm, it is 85% of pipe internal
diameter, while pipe diameter <32mm, it is 75% of pipe
internal diameter
excessive penetration ≤ 1.5mm ≤ 2mm ≤ 2.5mm
8.0.1.3 The allowable limits of welding angular distortion shown in Table 8.0.1-3 .
Table 8.0.1-3 Allowable limits of welding angular distortion
welding pieces deviation
θ ( ° ) α (mm)
plate pieces ≯ 3 -
diameter of pipe <100mm - ≯ 1/100
diameter of pipe ≥ 100mm - ≯ 3/200
8.0.1.4 The tubes/pipes offset of external wall shall conform with following requirements:
27
(1) Boiler heating surface tubes: ≤ 10% δ +1mm
(2) Other pipes : ≤ 10%δ and ≤ 4mm.
8.0.2 The inspection criterion of NDT on welding seam shall conform with the following
standards :
8.0.2.1 Pressure piping : (1) SD143-85《 The Specification of Erection and Acceptance for Power Plant
Construction(Radiographic Inspection on Butt-welding Seams of Pressure Piping) 》.
(2) SD67-83《 The Specification of Erection and Acceptance for Power Plant
Construction(Ultrasonic Inspection on Welding Seams of Piping)》.
8.0.2.2 The quality grade stipulation on various weld seams shown in Tab. 8.0.2 .
Table 8.0.2 The quality grade stipulation on various weld seams
welding seam type Ⅰ Ⅱ Ⅲ
method of inspection extent of boiler exceed extent of boiler
radiographic inspection Ⅱ Ⅱ Ⅱ Ⅲ
ultrasonic inspection Ⅰ Ⅰ Ⅰ Ⅱ
8.0.3 The hardness of welding seam after heat treatment shall , in general , not exceed
the Brinell hardness (HB) of parent metal plus 100 , and not exceed the following
stipulated :
total alloy content <3% , HB≤ 270
total alloy content 3%~10% , HB≤ 300
total alloy content >10% , HB≤ 350
Chapter 9 Annex
Annex A Chemical Compositions, Mechanical Performance And Reference Datum of Common Steel
Products of Power Plants
Annex B Chemical Compositions And Constant Temperature Mechanical Performance of Deposited
Metal of Common Welding Rod
Annex C Chemical Compositions of Common Welding Wire
Annex A Chemical Compositions, Mechanical Performance And Reference Datum
for Common Steel Products in Power PlantsChemical compositions and mechanical performance of
28
common steel products of power plants are shown as table A.
Table A Chemical Compositions And Mechanical Performance
of Common Steel Products of Power Plants
Brand Number Chemical Compositions(%) Serial
Number Steel Number Standard
Number C Mn Si
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
A3
10
20
20G
22G
25
St35.8
St45.8
STPT38
STPT42
SB42
SB46
60
65
A-1
C
B
C
SB49
STPT49
12Mng
16Mng
16MnR
17Mn4
GB700
GB3087
GB3087
GB5031
GB713
GB699
DIN17175
DIN17175
JISG3456
JISG3456
JISG3103
JISG3103
ASTMA515
ASTMA515
ASTMA210
ASTMA178
ASTMA106
ASTMA106
JISG3103
JISG3456
GB713
GB713
GB6654
DIN17115/1
0.14~0.22
0.07~0.14
0.17~0.24
0.17~0.24 ≤ 0.26
0.22~0.30 ≤ 0.17
≤ 0.21
≤ 0.25
≤ 0.30
≤ 0.24
≤ 0.28
0.24~0.31
0.28~0.33 ≤ 0.27
≤ 0.35
≤ 0.30
≤ 0.35
≤ 0.31
≤ 0.33
≤ 0.16
0.12~0.20 ≤ 0.20
0.14~0.20
0.30~0.65
0.35~0.65
0.30~0.65
0.35~0.65
0.60~0.90
0.50~0.80
0.40~0.80
0.40~1.20
0.30~0.90
0.30~0.10 ≤ 0.90
≤ 0.90
≤ 0.90
≤ 0.90
≤ 0.93
≤ 0.8
0.29~1.06
0.29~1.06 ≤ 0.9
0.30~1.0
1.10~1.50
1.20~1.60
1.20~1.60
0.90~1.20
≤ 0.30
0.17~0.37
0.17~0.37
0.17~0.37
0.17~0.37
0.17~0.37
0.10~0.35
0.10~0.35
0.10~0.35
0.10~0.35
0.15~0.30
0.15~0.30
0.15~0.40
0.15~0.40 ≤ 0.10
—
≥ 0.10
≥ 0.10
0.15~0.30
0.10~0.35
0.20~0.60
0.20~0.60
0.20~0.60
0.20~0.40
To be continued
Chemical Compositions (%)
29
Cr Mo V Ni Ti B
—
≤ 0.15
≤ 0.25
—
—
≤ 0.25
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.25
≤ 0.25
—
—
≤ 0.25
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
Serial Brand Number Chemical Compositions (%)
30
Number Steel
Number
Standard
Number W Nb Cu S P
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
A3
10
20
20G
22G
25
St35.8
St45.8
STPT38
STPT42
SB42
SB46
60
65
A-1
C
B
C
SB49
STPT49
12Mng
16Mng
16MnR
17Mn4
GB700
GB3087
GB3087
GB5031
GB713
GB699
DIN17175
DIN17175
JISG3456
JISG3456
JISG3103
JISG3103
ASTMA515
ASTMA515
ASTMA210
ASTMA178
ASTMA106
ASTMA106
JISG3103
JISG3456
GB713
GB713
GB6654
DIN17115/1
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.25
≤ 0.25
—
—
≤ 0.25
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.050
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.04
≤ 0.04
≤ 0.035
≤ 0.035
≤ 0.040
≤ 0.040
≤ 0.040
≤ 0.040
≤ 0.058
≤ 0.060
≤ 0.058
≤ 0.058
≤ 0.040
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.050
≤ 0.045
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.04
≤ 0.04
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.048
≤ 0.050
≤ 0.048
≤ 0.048
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.050
31
To be continued
Mechanical Performance of Constant Temperature Critical
Pointac1/Ac3 σ s σ b
(MPa)
δ s
(%)
α k
(J/cm2) HB
(MPa)
Class
Number
SD340-89
185~235
196
226
245
265
275
215~235
235~255 ≥ 215
≥ 245
≥ 225
≥ 245
≥ 220
≥ 240
≥ 255
≥ 255
≥ 240
≥ 275
≥ 265
≥ 274
275~295
245~345
265~345
274~284
3754~60
333~490
392~588
412~549
420~560
450
360~480
410~529 ≥ 372
≥ 412
412~540
451~588
415~550
450~585 ≥ 414
≥ 414
≥ 415
≥ 485
480~617 ≥ 480
430~590
440~655
450~655
460~548
21~26
24
20
24
24
23
≥ 25
≥ 23
≥ 22
≥ 30
≥ 22
≥ 20
19~21
18~21
18~21
27v
49u
59u
71u
59u
59u
27v
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -1
Ⅰ -2
Ⅰ -2
Ⅰ -2
Ⅱ A-1
Ⅱ A-1
Ⅱ A-1
Ⅱ A
32
Brand Number Chemical Compositions Serial
Number Steel Number Standard
Number C Mn Si
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
19Mn5
15MnVg
15MnVR
20MnMo
15MnMoV
14MnMoVg
18MnMoNbg
12CrMo
15CrMo
12CrMoV
12Cr1MoV
ZG15Cr-1Mo1V
ZG20Cr-MoV
A
T1
P1
T11
P11
P12
P2
WC6
WC9
SB46M
STBA12
STBA13
STBA12
DIN17175
GB713
GB6654
JB755
JB755
GB713
GB713
GB5310
GB5310
GB3077
GB5310
JB2640
JB2640
ASTMA204
ASTMA209
ASTMA335
ASTMA213
ASTMA335
ASTMA335
ASTMA335
ASTMA217
ASTMA217
JISG3103
JISG3462
JISG3462
JISG3458
0.17~0.22
0.10~0.18 ≤ 0.18
0.17~0.23
0.12~0.18
0.10~0.18
0.17~0.23
0.08~0.15
0.12~0.18
0.18~0.15
0.08~0.15
0.14~0.20
0.18~0.25 ≤ 0.18
0.10~0.20
0.10~0.20 ≤ 0.15
≤ 0.15
≤ 0.15
0.10~0.20 ≤ 0.20
≤ 0.18
≤ 0.18
0.10~0.20
0.15~0.25
0.10~0.20
1.00~1.30
1.20~1.60
1.20~1.60
1.10~1.40
1.30~1.60
1.20~1.60
1.35~1.65
0.40~0.70
0.40~0.70
0.40~0.70
0.40~0.70
0.40~0.70
0.40~0.70 ≤ 0.90
0.30~0.80
0.30~0.80
0.30~0.60
0.30~0.60
0.30~0.61
0.30~0.61
0.50~0.80
0.40~0.70 ≤ 0.90
0.30~0.80
0.30~0.80
0.30~0.80
0.30~0.60
0.20~0.50
0.20~0.60
0.17~0.37
0.17~0.37
0.20~0.50
0.17~0.37
0.17~0.37
0.17~0.37
0.17~0.37
0.17~0.37
0.17~0.37
0.17~0.37
0.15~0.40
0.10~0.50
0.10~0.50
0.50~1.00
0.50~1.00 ≤ 0.50
0.10~0.30 ≤ 0.60
≤ 0.60
0.15~0.30
0.10~0.50
0.10~0.50
0.10~0.50
33
To be continued
Chemical Compositions (%)
Cr Mo V Ni Ti B
≤ 0.30
—
—
—
—
—
—
0.40~0.70
0.80~1.10
0.30~0.60
0.90~1.20
1.20~1.70
0.90~1.20 —
—
—
1.00~1.50
1.00~1.50
0.80~1.25
0.50~0.81
1.00~1.50
2.00~2.75 —
—
—
—
—
—
—
0.20~0.35
0.4~0.65
0.40~0.65
0.45~0.65
0.40~0.55
0.40~0.55
0.25~0.35
0.25~0.35
1.00~1.20
0.50~0.70
0.41~0.65
0.44~0.65
0.44~0.65
0.44~0.65
0.44~0.65
0.44~0.65
0.44~0.65
0.44~0.65
0.90~1.20
0.45~0.60
0.45~0.65
0.45~0.65
0.45~0.65
—
0.04~0.12
0.04~0.12 —
0.05~0.15
0.05~0.15 —
—
—
0.15~0.30
0.15~0.30
0.20~0.40
0.20~0.30 —
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.50
≤ 0.50
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
34
Brand number Chemical compositions (%) Serial
number Steel number Standard
number W Nb Cu S P
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
19Mn5
15MnVg
15MnVR
20MnMo
15MnMoV
14MnMoVg
18MnMoNbg
12CrMo
15CrMo
12CrMoV
12Cr1MoV
ZG15Cr-1Mo1V
ZG20Cr-MoV
A
T1
P1
T11
P11
P12
P2
WC6
WC9
SB46M
STBA12
STBA13
STPA12
DIN17175
GB713
GB6654
JB755
JB755
GB713
GB713
GB5310
GB5310
GB3077
GB5310
JB2640
JB2640
ASTMA204
ASTMA209
ASTMA335
ASTMA213
ASTMA335
ASTMA335
ASTMA335
ASTMA217
ASTMA217
JISG3103
JISG3462
JISG3462
JISG3458
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.10
≤ 0.10
—
—
—
—
—
—
—
—
—
—
0.025~0.050—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.50
≤ 0.50
—
—
—
—
≤ 0.040
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.03
≤ 0.03
≤ 0.040
≤ 0.045
≤ 0.045
≤ 0.030
≤ 0.030
≤ 0.045
≤ 0.045
≤ 0.030
≤ 0.045
≤ 0.040
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.040
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.03
≤ 0.03
≤ 0.035
≤ 0.045
≤ 0.045
≤ 0.030
≤ 0.030
≤ 0.045
≤ 0.045
≤ 0.035
≤ 0.04
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
35
To be continued
Mechanical Performance of Constant Temperature Critical
Point
Ac1/Ac3
σ s σ b
(MPa)
δ s
(%)
α k
(J/cm2) HB
(MPa)
Class
Number
SD340-89
300~310
335~390
335~390
353~372
441
490
440~510
206
235
225
255
343
313
255
207
207
207
207
207
207
275
275
255
206
206
206
510~610
490~675
490~675
370~529
588
635
590~635
412~559
441~638
440
471~638
490
490
450~585
378
379
413
413
413
379
482~655
482~655
451~588
382
412
382
19
17~18
17~18
18
17
16
16~17
21
21
22
21
14
14
23
22
22
30
22
22
22
20
20
59u
34v
47u
55u
69u
69u
59u
78u
59u
29.4u
29.4u
149~217
156~228
146
163
Ⅱ A
Ⅱ A-2
Ⅱ A-2
Ⅱ A-2
Ⅱ B-1
Ⅱ B-2
Ⅱ B-2
Ⅲ -2
Ⅲ -2
Ⅲ -3
Ⅲ -3
Ⅲ -3
Ⅲ -3
Ⅲ -1
Ⅲ -1
Ⅲ -1
Ⅲ -2
Ⅲ -2
Ⅲ -2
Ⅲ -1
Ⅲ -1
Ⅲ -1
Ⅲ -1
Ⅲ -1
36
Brand Number Chemical Compositions (%) Serial
Number Steel Number Standard
Number C Mn Si
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
STBA22
STBA20
STPA20
STBA23
STPA22
STPA23
SCPH21
15Mo3
13CrMo44
14MoV63
12Cr2MoWVT1B
12Cr3MoVSiTiB
12Cr2Mo
P22
STPA24
10CrMo910
1Cr5Mo
10Cr5MoWVTiB
P5
P9
STPA25
STPA26
X20CrMoV121
1Cr13
0Cr13Al
1Cr18Ni9
0Cr23Ni13
JISG3462
JISG3462
JISG3458
JISG3462
JISG3458
JISG3458
JISG5151
DIN17155/2
DIN17155
DIN17155
GB5310
GB5310
GB5310
ASTMA335
JISG3458
DIN17175
J B755
ASTMA335
ASTMA335
JISG3458
JISG3458
DIN17175
GB1220
GB1220
GB1220
GB1220
≤ 0.15
0.10~0.20
0.10~0.20 ≤ 0.15
≤ 0.15
≤ 0.15
≤ 0.20
0.12~0.20
0.10~0.18
0.10~0.18
0.08~0.15
0.09~0.15
0.08~0.15 ≤ 0.15
≤ 0.15
0.08~0.15 ≤ 0.15
0.07~0.12 ≤ 0.15
≤ 0.15
≤ 0.15
≤ 0.15
0.17~0.23 ≤ 0.15
≤ 0.08
≤ 0.15
≤ 0.08
0.30~0.60
0.30~0.60
0.30~0.60
0.30~0.60
0.30~0.60
0.30~0.60
0.50~0.80
0.50~0.70
0.40~0.70
0.40~0.70
0.45~0.65
0.50~0.80
0.40~0.70
0.30~0.60
0.30~0.60
0.40~0.70 ≤ 0.60
0.45~0.70
0.30~0.60
0.30~0.60
0.30~0.60
0.30~0.60 ≤ 1.00
≤ 1.00
≤ 1.00
≤ 2.00
≤ 2.00
≤ 0.50
0.10~0.50
0.10~0.50
0.50~1.00 ≤ 0.50
0.50~1.00 ≤ 0.60
0.15~0.35
0.10~0.35
0.10~0.35
0.45~0.75
0.60~0.90 ≤ 0.50
≤ 0.50
≤ 0.50
≤ 0.50
≤ 0.50
0.40~0.70 ≤ 0.50
0.25~1.00 ≤ 0.50
0.251.00 ≤ 0.50
≤ 1.00
≤ 1.00
≤ 1.00
≤ 1.00
37
To be continued
Chemical Compositions (%)
Cr Mo V Ni Ti B
0.80~1.25
0.50~0.80
0.50~0.80
1.00~1.50
0.80~1.25
1.00~1.50
1.00~1.50 —
0.70~1.10
0.30~0.60
1.60~2.10
2.50~3.00
2.00~2.50
1.90~2.60
1.90~5.60
2.00~2.50
4.00~6.00
4.50~6.00
4.00~6.00
8.00~10.00
4.00~6.00
8.00~10.00
10.00~12.50
11.50~13.50
11.50~14.50
17.00~19.00
22.00~24.00
0.45~0.65
0.40~0.65
0.40~0.65
0.45~0.65
0.45~0.65
0.45~0.65
0.45~0.65
0.25~0.35
0.45~0.65
0.50~0.70
0.50~0.65
1.00~1.20
0.90~1.20
0.87~1.13
0.87~1.13
0.90~1.20
0.40~0.60
0.48~0.65
0.45~0.65
0.90~1.10
0.45~0.65
0.90~1.10
0.80~1.20 —
—
—
—
—
—
—
—
—
—
—
—
—
0.22~0.32
0.28~0.42
0.25~0.35 —
—
—
—
—
0.20~0.33 —
—
—
—
0.25~0.35 —
—
—
—
—
—
—
—
—
—
≤ 0.50
—
—
—
—
—
—
—
—
—
≤ 0.60
—
—
—
—
—
0.30~0.80 ≤ 0.60
—
8.00~10.00
12.00~15.00
—
—
—
—
—
—
—
—
—
—
0.08~0.18
0.22~0.38 —
—
—
—
—
0.16~0.24 —
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.008
0.005~0.011 —
—
—
—
—
0.008~0.014 —
—
—
—
—
—
—
—
—
38
Brand number Chemical compositions (%) Serial
number Steel number Standard
number W Nb Cu S P
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
STBA22
STBA20
STPA20
STBA23
STPA22
STPA23
SCPH21
15Mo3
13CrMo44
14MoV63
12Cr2MoWVT1B
12Cr3MoVSiTiB
12Cr2Mo
P22
STPA24
10CrMo910
1Cr5Mo
10Cr5MoWVTiB
P5
P9
STPA25
STPA25
X20CrMoV121
1Cr13
0Cr13Al
1Cr18Ni9
0Cr23Ni13
JISG3462
JISG3462
JISG3458
JISG3462
JISG3458
JISG3458
JISG5151
DIN17155/2
DIN17155
DIN17155
GB5310
GB5310
GB5310
ASTMA335
JISG3458
DIN17175
J B755
ASTMA335
ASTMA335
JISG3458
JISG3458
DIN17175
GB1220
GB1220
GB1220
GB1220
—
—
—
—
—
—
≤ 0.10
—
—
—
0.30~0.55—
—
—
—
—
—
0.20~0.40—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.50
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.030
≤ 0.035
≤ 0.030
≤ 0.040
≤ 0.040
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.030
≤ 0.030
≤ 0.035
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.030
≤ 0.035
≤ 0.030
≤ 0.040
≤ 0.040
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.030
≤ 0.030
≤ 0.035
≤ 0.035
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.030
≤ 0.035
≤ 0.035
≤ 0.035
≤ 0.035
To be continued
39
Mechanical Performance of Constant Temperature Critical
Point
Ac1/Ac3
σ s σ b
(MPa)
δ s
(%)
α k
(J/cm2) HB
(MPa)
Class
Number
SD340-89
206
206
206
206
206
206
274
265~274
280~290
310~319
343
441
280
207
206
269~280
392
392
207
207
206
206
490
343
177
206
206
412
412
412
412
412
412
480
431~519
440~590
460~610
540~736
608~804
450~600
413
412
450~600
588
539~735
413
413
412
412
690~840
539
412
520
520
22
22
18
16
20
22
18
18
22
22
17
25
20
40
40
55u
98.1u
98.1u
156~241
≥ 159
≤ 183
≤ 187
≤ 187
685~815
Ⅲ -2
Ⅲ -1
Ⅲ -1
Ⅲ -2
Ⅲ -2
Ⅲ -2
Ⅲ -1
Ⅲ -2
Ⅲ -2
Ⅳ
Ⅳ
Ⅳ
Ⅳ
Ⅳ
Ⅳ
Ⅴ
G106 Ⅴ
Ⅴ
Ⅴ
Ⅴ
Ⅴ
Ⅵ
Ⅶ
Ⅷ
Ⅷ
40
Annex B Chemical Compositions And Mechanical Performance at Normal Temperature of Clad Metal
for Common Welding Rods
Chemical compositions and mechanical performance at normal temperature of clad metal for common
welding rods are shown as table B.
Table B Chemical Compositions And Mechanical Performance at Normal Temperature
of Clad Metal for Common Welding Rods
Model of Welding Rod Chemical Compositions (%)
Serial
Number Model Standard
Number
Original
Brand
Number
C Mn
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
E4303
E4301
E4320
E4316
E4315
E5001
E5016
E5015
E6015D1
E7015D2
E5003A1
E5015A1
E5503B1
E5515B1
E5503B2
E5515B2
E5503B2V
GB5117
GB5117
GB5117
GB5117
GB5117
GB5117
GB5117
GB5117
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
J 422
J 423
J 424
J 426
J 427
J 503
J 506
J 507
J 607
J 707
R 102
R 107
R 202
R 207
R 302
R 307
R 312
≤ 0.12
≤ 0.12
≤ 0.12
≤ 0.12
≤ 0.12
≤ 0.12
≤ 0.12
≤ 0.12
≤ 0.12
0.15 —
0.12
0.05~0.12
0.05~0.12 ≤ 0.12
0.05~0.12 ≤ 0.12
0.30~0.60
0.35~0.60
0.50~0.90
0.50~0.90
0.50~0.90
0.50~1.00
0.80~1.40
0.80~1.40
1.25~1.75
1.65~2.00 —
0.90
0.90
0.90
0.50~0.90
0.90
0.50~0.90
41
Chemical Compositions (%)
Si Cr Mo V Nb B
≤ 0.25
≤ 0.20
≤ 0.15
≤ 0.50
≤ 0.50
≤ 0.30
≤ 0.65
≤ 0.70
0.60
0.60 —
0.60
0.60
0.60 ≤ 0.50
0.60 ≤ 0.50
—
—
—
—
—
—
—
—
—
—
—
—
0.40~0.65
0.40~0.65
0.70~1.10
1.00~1.50
0.80~1.20
—
—
—
—
—
—
—
0.25~0.45
0.25~0.45 —
0.40~0.65
0.40~0.65
0.40~0.65
0.40~0.65
0.40~0.70
0.40~0.65
0.40~0.70
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
0.10~0.35
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
42
Model of Welding Rod Chemical Compositions (%)
Serial
Number Model Standard
Number
Original
Brand
Number
W Ni
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
E4303
E4301
E4320
E4316
E4315
E5001
E5016
E5015
E6015D1
E7015D2
E5003A1
E5015A1
E5503B1
E5515B1
E5503B2
E5515B2
E5503B2V
GB5117
GB5117
GB5117
GB5117
GB5117
GB5117
GB5117
GB5117
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
J 422
J 423
J 424
J 426
J 427
J 503
J 506
J 507
J 607
J 707
R 102
R 107
R 202
R 207
R 302
R 307
R 312
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
43
To be continued Mechanical Performance of Constant
Temperature Chemical Compositions (%) Class Number
Re σ b(Mpa) δ s(%) α k(J/cm2) SD340-89
— S2≤ 0.035
P2≤ 0.050 412 ≥ 18 78.4 Ⅰ -1
— S≤ 0.035
P≤ 0.050 412 ≥ 18 78.4 Ⅰ -1
— S≤ 0.035
P≤ 0.050 412 ≥ 18 78.4 Ⅰ -1
— S≤ 0.035
P≤ 0.040 412 ≥ 22 137.2 Ⅰ -1
— S≤ 0.035
P≤ 0.040 412 ≥ 22 137.2 Ⅰ -1
— S≤ 0.035
P≤ 0.050 490 ≥ 16 58.8 Ⅰ -2
— S≤ 0.035
P≤ 0.040 490 ≥ 20 127.4 Ⅰ -2
— S≤ 0.035
P≤ 0.040 490 ≥ 20 127.4 Ⅰ -2
— S≤ 0.035
P≤ 0.035 588 ≥ 15 ≥ 27ν Ⅱ 4-2
— S≤ 0.035
P≤ 0.035 610 ≥ 15 Ⅱ 8
— S≤ 0.035
P≤ 0.040 490 ≥ 20 Ⅲ -1
— S≤ 0.035
P≤ 0.035 490 ≥ 22 Ⅲ -1
— S≤ 0.035
P≤ 0.035
540 ≥ 16 Ⅲ -2
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅲ -2
—
S≤ 0.035
P≤ 0.040 490 ≥ 16 78.4u Ⅲ -2
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅲ -2
44
S≤ 0.035 —
P≤ 0.040 490 ≥ 16 Ⅲ -3
Model of Welding Rod Chemical Compositions (%)
Serial
Number Model Standard
number
Original
brand
number
C Mn
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
E5515B2V
E6003B3
E6015B3
E5515B3VNb
E5515B2VWB
E5515B2VW
E5515B2VNb
E1-5McV-15
E1-9Mo-15
E2-11MoVN1-15
E2-11MoVNiW-15
E1-13-15
E6-19-10Nb-
E4-18-12Mo2-
E1-23-13-
E2-26-21-
E1-16-25Mo6N
E7-17-
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
R 317
R 402
R 407
R 417
R 347
R 327
R 337
R 507
R 707
R 807
R 817
R 827
G 207
G 217
A 132/A 137
A 202/A 207
A 302/A 307
A 402/A 407
A 507
G 302/G 307
0.05~0.12
0.05~0.12
0.05~0.12
0.05~0.12
0.05~0.12
0.05~0.12
0.05~0.12
0. 12
0.10
0.19
0.19
0.15~0.21
0.12 ≤ 0.12
0.08
0.08
0.15
0.20
0.12
0.10
0.90
0.90
0.90
0.90
1.00
0.70~1.10
0.60
0.50~0.90
1.00
0.50~1.00
0.5~1.00
0.50~1.00
1.00 ≤ 1.00
0.5~2.5
0.5~2.5
0.5~2.5
1.0~2.5
0.5~2.5
1.0
45
46
To be continued
Chemical Compositions (%)
S1 Cr Mo V Nb B
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.50
0.90
0.50
0.50 ≤ 0.50
0.90 ≤ 0.90
0.90
0.90
0.90
0.75
0.90
0.90
1.00~1.50
2.00~2.50
2.00~2.50
2.10~3.00
1.50~2.50
1.00~1.50
1.00~1.50
4.5~6.00
8.0~10.5
9.5~11.5
9.5~12.0
9.50~12.00
11.00~13.50
12.00~14.00
18.00~21.00
17.0~20.0
22.0~25.0
25.0~28.0
14.0~18.0
14.0~18.0
0.40~1.65
0.90~1.20
0.90~1.20
0.70~1.00
0.30~0.80
0.70~1.00
0.70~1.00
0.40~0.70
0.85~1.20
0.60~0.90
0.80~1.10
0.80~1.10
0.50
0.50
2.0~2.5
0.50
0.50
5.0~7.0
0.50
0.10~0.35 —
—
0.25~0.50
0.20~0.60
0.20~0.35
0.15~0.40
0.10~0.35 —
0.20~0.40
0.20~0.40
0.20~0.40 —
—
—
—
—
—
—
—
—
—
—
0.35~0.65 —
—
0.10~0.25 —
—
—
—
—
—
—
8×C~1.00
—
—
—
—
—
—
—
—
—
0.001~0.003 —
—
—
—
—
—
—
—
—
—
—
—
—
—
—
47
Model of Welding Rod Chemical Compositions (%)
Serial
Number Model Standard
Number
Original
Brand
Number
W Ni
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
E5515B2V
E6003B3
E6015B3
E5515B3VNb
E5515B2VWB
E5515B2VW
E5515B2VNb
E1-5McV-15
E1-9Mo-15
E2-11MoVN1-15
E2-11MoVNiW-15
E1-13-15
E6-19-10Nb-
E4-18-12Mo2-
E1-23-13-
E2-26-21-
E1-16-25Mo6N
E7-17-
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB5118
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
GB983
R 317
R 402
R 407
R 417
R 347
R 327
R 337
R 507
R 707
R 807
R 817
R 827
G 207
G 217
A 132/A 137
A 202/A 207
A 302/A 307
A 402/A 407
A 507
G 302/G 307
—
—
—
—
0.20~0.60
0.25~0.50 —
—
—
—
0.40~0.70 —
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
0.40
0.60~0.90
0.40~1.10
0.70~1.10
0.60 ≤ 0.60
9.0~11.0
11.0~14.0
12.0~14.0
20.0~22.5
22.0~27.0
0.60
48
To be continued
Mechanical Performance of Constant
Temperature Chemical Compositions (%) Class Number
Re Others σ b(Mpa) δ s(%) α k(J/cm2) SD340-89
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅲ -3
— S≤ 0.035
P≤ 0.035 590 ≥ 14 Ⅳ
— S≤ 0.035
P≤ 0.035 590 ≥ 15 Ⅳ
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅳ
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅳ
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅲ -3
— S≤ 0.035
P≤ 0.035 540 ≥ 17 Ⅲ -3
Cu20.50 S≤ 0.030
P≤ 0.035 540 ≥ 14 Ⅴ -1
Cu20.50 S≤ 0.030
P≤ 0.035 590 ≥ 16 Ⅴ -2
Cu20.50 S≤ 0.030
P≤ 0.035 730 ≥ 15 Ⅴ -3
Cu20.50 S≤ 0.030
P≤ 0.035 730 ≥ 15 Ⅴ -3
— S≤ 0.035
P≤ 0.040 Ⅴ -3
Cu20.50 S≤ 0.030
P≤ 0.035 450 ≥ 20 Ⅵ
— S≤ 0.030
P≤ 0.040 Ⅵ
Cu20.50 S≤ 0.030
P≤ 0.035 520 ≥ 25 Ⅷ
Cu20.50 S≤ 0.030
P≤ 0.035 520 ≥ 30 Ⅷ
Cu20.50 S≤ 0.030
P≤ 0.035 550 ≥ 25 Ⅷ
49
S≤ 0.030 Cu20.50
P≤ 0.030 550 25 Ⅷ
Cu20.50 N≥ 0.1
S≤ 0.030
P≤ 0.035 610 30
Cu20.50 S≤ 0.030
P≤ 0.035 450 20 Ⅶ
Annex C Chemical Compositions of Common Welding Wire
Chemical compositions of common welding wire are shown as table C.
Table C Chemical Compositions of Common Welding Wire Chemical Compositions (%) Serial
Number Steel Number Standard Number C Mn Si Cr Mo
1 H08A 0.30~0.55 ≤ 0.03
2 H08MnA GB1300-77
0.80~1.10 ≤ 0.07 ≤ 0.20
3 H08MnR YB/Z11-76
≤ 0.10
1.00~1.30 0.10~0.30 —
4 H08Mn2SiA ≤ 0.11 1.80~2.10 0.65~0.95
5 H10Mn2 ≤ 0.12 1.50~1.90 ≤ 0.07 ≤ 0.20
—
6 H08CrMoA ≤ 0.10 0.80~1.10
7 H13CrMoA 0.11~0.16 0.80~1.00 0.40~0.60
8 H08CrMoV
GB/Z1300-77
0.40~0.70 0.15~0.35
1.00~1.30
9 H08CrMnSiMoVA 1.20~1.50 0.60~0.90 0.95~1.25 0.50~0.70
10 H08Cr2MoA YB/Z11-76
≤ 0.10
0.40~0.70 0.15~0.35 2.00~2.50 0.90~1.20
11 H1Cr13 ≤ 0.15 0.30~0.60 0.30~0.60 12.00~14.00
12 H1Cr19Ni9 ≤ 0.14 0.50~1.00
13 H0Cr19Ni9Si2 ≤ 0.06 2.00~2.75
14 H1Cr19Ni9Ti ≤ 0.10 0.30~0.70
15 H1Cr19Ni10Nb ≤ 0.09 0.30~0.80
18.00~20.00
16 H1Cr25Ni13 ≤ 0.12 0.30~0.70 23.00~26.00
17 H1Cr25Ni20
GB1300-77
≤ 0.15
1.00~2.00
0.20~0.50 24.00~27.00
18 TIG-J50 — 0.06~0.12 1.20~1.50 0.60~0.85 —
—
50
19 TIG-R31 1.10~1.40 0.45~0.65
20 Tig-R40 0.75~1.05 0.45~0.70
2.20~2.50 0.95~1.25
21 TIG-R10 0.75~1.05 —
22 TIG-R30 0.75~1.050.45~0.70
1.10~1.40 0.45~0.65
51
Chemical Compositions (%) S P
V Notes Ti Nb Ni Rare earth Others Not larger
than
≤ 0.30
0.10
(addition amount)
A10.05 (addition amount)
0.30 0.30
0.40 0.40
—
0.15~0.35
≤ 0.30
0.20~0.40 ≤ 0.25
≤ 0.60
—
0.030 0.030
0.50~0.80
—
8.00~10.00
1.20~1.50 9.00~11.00
12.00~14.00—
17.00~20.00
— —
0.020
A10.05~0.15Zr0.04~0.10
—
0.03~0.06
0.23~0.35
—
0.03~0.06
—
— 0.05
(addition amount) —
0.25 0.25
Standards of
Shanghai power plant
erection factory.
52