Presentation Outline
• Early Milestones
• Technical Evaluation Process
• Best Value Selection Process
Early Milestones• August 1 – Bridge Collapses• August 4 – Issue Request for Qualifications• August 8 – Short Listed teams• August 23 – Request For Proposals released• September 14 – Technical Proposals received• September 18 – Financial Proposals received• September 19 – Project letting• Between September 19 and October 15
– Contract finalized• October 15 – Construction expected to begin
Procurement process
• Today’s letting is a step in process
• Contract must be executed before process is final
• Anticipate final contract in place by end of September 2007
Technical Evaluation Process
• Technical Review Committee– Six Members responsible for developing
average Technical Proposal Score for each team
• Minn. Statute, Section 161.3420, Subd 2
• Technical Advisors– Advise TRC with technical aspects of
proposals– Coordinates Process
Technical Evaluation Process• Process Oversight Committee
– Observation and Verification of Process
• Technical Subcommittees– Assist in identifying strengths and weaknesses
of each team• Aesthetic/Visual Quality• Roadway/Geometrics• Communication• Quality and Structural • Legal Financial
Evaluation Criteria
• Quality (50%)– Experience and authority of key individuals– Extent of quality control/quality assurance– Safety
– Measures to evaluate performance in construction
• Aesthetics/Visual Quality (20%)
• Enhancements (15%)– Geometric and structural enhancements
• Public Outreach/Involvement (15%)
Best Value Selection Process
• Design Build A+B, Best Value formula – Three Components
• “A” = Contract Bid Price• Plus “B” = Number of Days to Complete Project, which is
multiplied by $200,000 per day– $200,000 per day based on 50% of road user costs
• Divided by Technical Proposal Average Score (TPA)• Result = Adjusted Bid
(A) + (B x $200,000) divided by TPA = Adjusted bid • Contract awarded to lowest adjusted bid
Technical proposal scoring
• Scores fall within these categories and ranges Excellent – 100 - 91 percent Very good – 90 - 76 percent Good – 75 – 61 percent Fair – 60 - 50 percent
Data classificationTechnical proposal
items
Data Classification before contract award
Data classification
after contract award
Evaluation
Criteria
Confidential or protected – nonpublic
Public
Scoring
Methodology
Confidential or protected – nonpublic
Public
Evaluations Confidential or protected – nonpublic
Public
Proposals Private or nonpublic Public
Minnesota Statutes Section 13.72, Subdivision 11
Thank You:
Ames/LundaC.S. McCrossanFlatiron-Manson
Walsh Construction/American Bridge
http://www.dot.state.mn.us/i35wbridge/