splost quick factsfile/… · splost 2014 quick facts educa onal impact of splost in 2014 1—new...

24
1 August 11, 2014 SPLOST 2014 Quick Facts EducaƟonal Impact of SPLOST in 2014 1—New school completed 22—RenovaƟon projects 5—New lighƟng in 5 high school’s gyms completed 89—Entry access control systems installed 37—School playscapes will be replaced 4—In addiƟon, four new schools under construcƟon (2015 opening) Economic Impact of SPLOST Over $215Million commiƩed to local rms Over $86Million expended to date Over 1,000 trade laborers employed this summer Over 50,000 labor hours worked per summer week Over 500,000 labor hours worked this summer Over 850,000 labor hours to date Zero Lost Time accidents since start in 2012 Over 300 local rms hold (sub)contracts or POs

Upload: others

Post on 13-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

1  August 11, 2014 

SPLOST 2014 Quick Facts 

Educa onal Impact of SPLOST in 2014

1—New school completed 

22—Renova on projects  

5—New ligh ng in 5 high school’s gyms completed 

89—Entry access control systems installed 

37—School playscapes will be replaced 

4—In addi on, four new schools under construc on (2015           

opening)  

 

Economic Impact of SPLOST

Over $215‐Million commi ed to local firms 

Over $86‐Million expended  to date 

Over 1,000 trade laborers employed this summer 

Over 50,000 labor hours worked per summer week 

Over 500,000 labor hours worked this summer  

Over 850,000 labor hours to date  

Zero Lost Time accidents since start in 2012 

Over 300 local firms hold (sub)contracts or POs 

 

 

 

Page 2: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

New South Fulton Elementary School

 

Quick Facts:

Total site area +/‐ 17.65 Acres 

Building size 126,612 S.F. 

42 Regular and 14 special classrooms  

Supports 850 FTE 

Core facilities support 1,000 FTE 

Project Team 

Collins Cooper Carusi Architects 

Evergreen Construction  

This three story school offers the same programmatic and site amenities found in all other Fulton County

Schools prototypes. The school is organized with K‐5 classrooms stacked in an academic wing and the core

functions—Media Center, Music, Gymnasium, Cafetorium and Administration suite stacked at the end of

the building.

Page 3: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

Hapeville Elementary School

This mul ple  phased  project  includes major  renova ons  and  building  systems  replacements  to  improve space  comfort  and  reduce  energy  consump on.    Significant  interior  renova ons  and  finishes  improve aesthe cs  in  classrooms,  corridors,  and  the media  center.    Exterior  improvements  include  repaving  the parking lot and improving drainage.   

 

Phase 2 (2014)

Comprehensive renovation including  

ceilings, lighting, flooring, and paint 

HVAC, and select systems replaced 

Project Team

Gardner Spencer Smith Tench & Jarbeau 

Triad Construction Company, Inc. 

Phase 1 (2013)

Parking lot resurfacing 

Grading and drainage improvements 

New PE flooring & windows 

Structural reinforcing gym walls 

Toilet rooms remodeled 

Page 4: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

Spalding Drive Elementary School

This multiple phased project includes modifications to the existing main entrance to enhance safety and

security and major renovations to the existing kitchen & serving area to relieve congestion. Building

systems replacements to improve space comfort and reduce energy consumption and significant interior

renovations to improve aesthetics.

 

Phase 2 (2014)

New flooring and finishes 

Major HVAC equipment and systems  

Complete lighting & ceilings  

Project Team

Manley Spangler Smith Architects 

Triad Construction Company, Inc. 

Phase 1 (2013)

New asphalt parking and service area 

Toilet room remodeling 

PE flooring replaced 

Regraded and grassed playfield  

Drainage improvements 

Page 5: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

Tri‐Ci es High School

This mul ple phased project  includes major  renova ons  to  the  exis ng  kitchen &  serving  area  to  relieve conges on.   Building systems replacements to  improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs. Bulldog Way is reconstructed, and the building roof is replaced.    

 

Phase 2 (2014)

Complete roofing scope 

Complete flooring & finishes scope 

Complete HVAC, lighting & ceilings  

Project Team

BRPH Architects 

Merit Construction  

Phase 1 (2013)

New Kitchen & equipment 

New Cafeteria & Serving Lines 

New roof (partial) 

New central plant 

New flooring and finishes (partial) 

HVAC, lighting & ceilings (partial) 

Page 6: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

Creekside High School

This multiple phased project includes modifications to the existing main entrance to enhance safety and 

security.  Major renovations to the existing kitchen & serving area to relieve congestion.  Building systems 

replacements to improve space comfort and reduce energy consumption and significant interior renovations 

to improve aesthetics.  

 

Phase 3 (2015)

Complete roofing scope 

Complete flooring & finishes  

Complete HVAC, lighting & ceilings  

Project Team

CGLS Architects 

Merit Construction  

Phase 1 & 2 (2014)

Kitchen & equipment 

Cafeteria finishes & serving lines 

Roof (partial area) 

New central plant 

New flooring and finishes (partial) 

Front entrance enhancements 

HVAC, lighting & ceilings (partial area) 

Page 7: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

North Springs High School

This mul ple  phased  project  includes modifica ons  to  the  exis ng main  entrance  to  enhance  safety  and security.    Building  systems  replacements  to  improve  space  comfort  and  reduce  energy  consump on  and significant  interior  renova ons  to  improve  aesthe cs.  Casework  is  replaced  in  classrooms,  and  the  video produc on lab is remodeled. 

 

Phase 3 (2015)

Complete roofing scope 

Complete flooring & finishes 

Complete HVAC, lighting & ceilings  

Project Team

Cooper Carry Inc. 

Hogan Construction Group 

Phase 1 & 2 (2014)

Front entrance enhancements 

Roofing (partial areas) 

Flooring and finishes (partial areas) 

HVAC, lighting & ceilings (partial areas) 

White board and tack board replacement 

Page 8: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

Cha ahoochee High School

This mul ple  phased  project  includes modifica ons  to  the  exis ng main  entrance  to  enhance  safety  and security.   Major renova ons to the exis ng kitchen & serving area to relieve conges on.   Building systems replacements to improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs.  

  Phase 3 (2015)

Complete roofing scope 

Complete flooring & finishes 

Complete HVAC, lighting & ceilings  

Project Team

CGLS Architects 

Evergreen Construction 

Asphalt paving and bus canopy 

Phase 1 & 2 (2014)

New Kitchen & equipment 

New Cafeteria & Serving Lines 

New central plant 

New flooring and finishes (partial) 

Front entrance enhancements 

HVAC, lighting & ceilings (partial) 

Fire alarm system 

Page 9: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

 

August 11, 2014 

Roswell High School

This mul ple  phased  project  includes modifica ons  to  the  exis ng main  entrance  to  enhance  safety  and security.   Major renova ons to the exis ng kitchen & serving area to relieve conges on.   Building systems replacements to improve space comfort and reduce energy consump on and significant interior renova ons to improve aesthe cs.  

  Phase 3 (2015)

Complete roofing scope 

Complete flooring & finishes 

Complete HVAC, lighting & ceilings  

Project Team

CGLS Architects 

Evergreen Construction 

Asphalt paving and bus canopy 

Phase 1 & 2 (2014)

Kitchen & equipment 

Cafeteria & serving lines 

Front entrance enhancements 

Site improvements 

New central plant 

New flooring and finishes (partial areas) 

HVAC, lighting & ceilings (partial areas) 

Page 10: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

10 

 

August 11, 2014 

Dolvin Elementary School

This two‐phased project has a light touch in the first year.  First year improvements include limited pain ng and  refinishing  doors  and  casework,  and  re‐grading  grassing  the  playfield.    Second  phase work  includes HVAC,  electrical  and  plumbing  system  work,  and  aesthe c  improvements  including  pain ng,  flooring, ceilings.   

 

Phase 2 (2015)

Major electrical upgrades 

Complete flooring & finishes 

Complete HVAC, lighting & ceilings  

Asphalt Paving 

Canopy replacement 

Phase 1 (2014)

Regrading and grassing playground 

Minor interior finishes 

Project Team

Manley Spangler Smith Architects 

Swofford Construction  

Page 11: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

11 

 

August 11, 2014 

Woodland Elementary School

This first phase of a  two‐phased project  improves  landscaping and drainage at  the playfield,  replaces  the electrical service, and makes select interior improvements.  The more significant second phase renovates the serving lines, and improves systems and aesthe cs throughout the school. 

  Phase 2 (2015)

Complete roofing 

Complete flooring & finishes 

Complete HVAC, lighting & ceilings  

Project Team

Cooper Carry Inc. 

Merit Construction  

Windows  

Phase 1 (2014)

Playground improvements 

New Cafeteria & Serving Lines 

New roof (partial) 

New flooring and finishes (partial) 

HVAC, lighting & ceilings (partial) 

Page 12: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

12 

 

August 11, 2014 

Brookview Elementary School

This single‐phase project replaces select HVAC equipment to  improve  indoor air quality.   Life safety system improvements include a new fire alarm and emergency generator.  Aesthe c improvements include pain ng, flooring, and ceiling  le replacement.  Drainage and grassing is improved at the play area. 

 

Project Team

Forman Seeley Fountain Architecture 

Swofford Construction  

Page 13: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

13 

 

August 11, 2014 

Barnwell Elementary School

This  single  phased  project  replaces  building  systems  to  improve  space  comfort  and  reduce  energy consump on.    To  accommodate  the  systems  replacements,  significant  interior  renova ons  including new ceilings and ligh ng will be replaced.  Exterior improvements include underground and surface storm water deten on and parking lot repaving. 

 

Project Team

Goode Van Slyke Architecture 

Triad Construction Company, Inc. 

Page 14: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

14 

 

August 11, 2014 

Camp Creek Middle School

This single‐phase project includes a new serving line and select kitchen equipment.  Carpe ng was replaced in  the Media Center, and flooring, pain ng and ceiling  les were replaced  to  improve aesthe cs.   Exterior improvements include repaving and sidewalks. 

 

Project Team

Collins Cooper Carusi  Architects 

Merit Construction 

Page 15: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

15 

 

August 11, 2014 

Haynes Bridge Middle School

This single‐phase project improves the kitchen and cafeteria serving lines and improves toilet rooms.  HVAC, ligh ng  and  window  replacements  improve  the  building  environment.    Signage  is  replaced  to  improve wayfinding.    Aesthe c  improvements  include marker  and  tack  board  replacement,  pain ng,  ceiling  and flooring, casework and locker replacement.   

 

Project Team

Collins Cooper Carusi Architects 

Amacher Bros. Construction Co. 

Page 16: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

16 

 

August 11, 2014 

Holcomb Bridge Middle School

This single‐phase project includes a new serving line and select kitchen equipment.  HVAC and roofing were replaced selec vely, and the bus canopy was expanded.  Flooring, pain ng and ceiling  les were replaced to improve aesthe cs.   Exterior  improvements  include  repaving,  sidewalks and  recondi oning  the  two  storm water deten on ponds. 

 

Project Team

Collins Cooper Carusi Architects 

Merit Construction 

Page 17: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

17 

 

August 11, 2014 

Parklane Elementary School

This single phase project repaves the front entry and parking lot, regrades and grasses the playfield to

improve drainage, replaces canopies at the bus lot. Interior work includes thermal insulation in the gym to

improve aesthetics and energy consumption, toilet room remodeling, and replacement of aged finishes.

 

Project Team

The Brown Design Group 

Southcore Construction Company, Inc. 

Page 18: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

18 

 

August 11, 2014 

Seaborn Lee Elementary School

This single‐phase project replaces select HVAC equipment and life safety systems including a new fire alarm and emergency generator.  Aesthe c improvements include toilet room renova ons, terrazzo crack repairs, refinishing  the  stage,  pain ng,  flooring,  and  ceiling  le  replacement.    Paving  is  replaced  at  the  bus  and parking lot. 

 

Project Team

Forman Seeley Fountain Architecture 

Swofford Construction  

Page 19: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

19 

 

August 11, 2014 

SL Lewis Elementary School

This single‐phase project improves several student, staff and accessible toilet rooms, replaces marker boards and tack boards, and improves aesthe cs by pain ng, replacing flooring and ceilings, recondi oning interior doors, replacing windows.  Interior safety is improved by replacing branch circuit wiring and devices.   

 

Project Team

Gardner Spencer Smith Tench & Jarbeau 

Swofford Construction  

Page 20: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

20 

 

August 11, 2014 

Alphare a HS So ball Concessions

 

Project Team

Goode Van Slyke Architecture 

Osprey Management 

This single phased project constructs a separate storage building and concession stand adjacent to the  

so ball field.     

Page 21: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

21 

 

August 11, 2014 

North Springs HS So ball Concessions

 

Project Team

Sy Richards Architect Inc. 

SouthCore Construction 

This single phased project constructs a separate concession stand adjacent to the  

so ball field with miscellaneous field upgrades.     

Page 22: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

22 

 

August 11, 2014 

Northview HS Track Renova ons

 

Project Team

Breedlove Land Planning 

Sports Turf Co./Sprinturf, LLC 

This single phased project replaces the exis ng track surface replacement with new surfacing and football 

field turf replacement. 

Page 23: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

23 

 

August 11, 2014 

Lake Windward Elementary School

This breakout package improves the play area and playscapes. A major renovation project is under design

and will be under construction by summer 2015.

 

Project Team

Breedlove Land Planning 

PE Structures & Associates 

Page 24: SPLOST Quick Factsfile/… · SPLOST 2014 Quick Facts Educa onal Impact of SPLOST in 2014 1—New school completed 22—Renova on projects 5—New ligh ng in 5 high school’s gyms

 

24 

 

August 11, 2014 

Westlake High School

This wall was improperly constructed during the construction of Westlake High School in SPLOST III. The wall was

removed and is being replaced. Construction quality is monitored constantly by onsite geo‐technical engineers and

two web cameras.

 

Project Team

GSST&J/Breedlove Land Planning 

Randolph & Company