SRTS STUDY OVERVIEW
Collect Data and Identify Barriers Establish School Routes Make Recommendations for Improvements Provide Opinion of Probable Cost for
Recommended Improvements
Data Collection
Sidewalk and Sign Inventory
Traffic Data Collection
Observing Student Dismissal Procedures
Parent Surveys
Barriers to Walking/Biking to School
Lack of Sidewalks along School Routes
Difficulty Crossing US 63
Establish School Route Plan
Establish School Route Plan
Most Direct Routes Utilize Existing Sidewalks Minimize Street Crossings Cross at STOP and Yield Signs Converge Routes Minimize US 63 and US 30 Crossings
School Route Plan - Tama
School Route Plan - Toledo
Recommendations
US 63 Crossing Alternatives 13th St. & Harding St. Intersection Sidewalk Improvements School Crosswalks Busing Policy
US 63 Crossing Alternative #1
US 63 Crossing Alternative #2
US 63 Crossing Alternative #3
13th St. & Harding St. Intersection
Adult Crossing Guard
Convert to 4-way STOP Sign Control
Convert to 4-way STOP w/ Channelized WB Right Turn Lane
Sidewalk/Crosswalk Improvements - Tama
Sidewalk/Crosswalk Improvements - Toledo
Opinion of Probable Costs
Unit Estimated Estimated Estimated EstimatedUnits Cost Quantity Cost Quantity Cost
SidewalkPriority 1 Square Yard $50 2,150 107,500$ 1,430 71,500$ Priority 2 Square Yard $50 11,020 551,000$ 11,530 576,500$ Priority 3 Square Yard $50 8,210 410,500$ 10,160 508,000$
US 63 CrossingOption 1 - Raised Median* Lump Sum $25,000 1 25,000$ 0 -$ Option 2 - Traffic Signal Lump Sum $39,000 1 39,000$ 0 -$ Option 3 - Advanced Warning Flashers Lump Sum $18,000 1 18,000$ 0 -$
13th St. & Harding St. ModificationsOption 1 - Adult Crossing Guard** Years $10,000 10 77,217$ 0 -$ Option 2 - Convert to 4-Way STOP Lump Sum $1,000 1 1,000$ 0 -$ Option 3 - Construct Channelized Free WB Right Turn Lump Sum 57500 1 57,500$ 0 -$
Crosswalk Markings Each Leg $150 24 3,600$ 23 3,450$
School Crossing Signs Each Sign $400 2 800$ 6 2,400$
TOTAL COST OF RECOMMENDED IMPROVEMENTS***
* Cost estimate only includes construction of the raised median, sidewalk, pavement markings and associated signage. ** Adult crossing guard cost represents the present value assuming an annual cost of $10,000 and an interest rate of 5%.*** Where options are presented, Total Cost only includes the cost of Option 1.
Tama Toledo
$ 1,175,617 $ 1,161,850