PREPARED BY OHS DEPT. APPROVED BY PRAMOD HARGUDE PAGE 1 OF 7 Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS TITLE DOC.NO. 2 / PIRE / OHS / SOP / SOP for Erecting the Pole with their Hard ware fitted on it. REVISION NO 00 I - INTEGRATED M-MANAGEMENT S - SYSTEM ISO 9001 ISO 14001 OHSAS-18001 DATE 05.05.2013 Purpose – To protect people working on Pole Erection by following safe method of pole climbing. Scope – All the sites of MEP, PIRE & all similar sites where distribution work is in progress. Responsibility – Executive responsibility lies with Site engineer & Site supervisor. Overall responsibility lies with the Site In-charge. Accountability – Overall accountability lies with Concern Business Head. Cross Reference – - Hazard Identification & Risk Assessment. - Site specific Tool Box Talk. - Incident DOSSIER. - Tender document. PPE to be use for pole erection – - Full Body Harness with kinetic absorber and double lanyard with scaffolding hook. - Safety Helmet. (Use of chin strap is mandatory). - Fall arrester - Kernmantle rope. (Please see the given below table for required karamental rope for pole climbing) Total length of pole Length of Pole above ground Karamental length required 6 mtr 5mtr 12 mtr 9 mtr 7.5 mtr 18 mtr 11 mtr 9 mtr 21 mtr 13 mtr 11 mtr 25 mtr Description of Pole Erection – 1. Unload the pole (PCC or RSJ pole) at site by vendor during dispatch at road side. 2. Shift the pole by contract workmen by manually at erection location.

Upload: elect570805

Post on 30-Nov-2015

101 views

Category:

Documents


9 download

DESCRIPTION

SOP FOR POLE ERECTION

TRANSCRIPT

Page 1: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 1 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

• Purpose – To protect people working on Pole Erection by following safe method

of pole climbing. • Scope – All the sites of MEP, PIRE & all similar sites where distribution work is in

progress. • Responsibility – Executive responsibility lies with Site engineer & Site supervisor.

Overall responsibility lies with the Site In-charge.

• Accountability – Overall accountability lies with Concern Business Head. • Cross Reference – - Hazard Identification & Risk Assessment. - Site specific Tool Box Talk. - Incident DOSSIER. - Tender document. • PPE to be use for pole erection –

- Full Body Harness with kinetic absorber and double lanyard with scaffolding

hook. - Safety Helmet. (Use of chin strap is mandatory). - Fall arrester - Kernmantle rope. (Please see the given below table for required karamental

rope for pole climbing)

Total length of pole

Length of Pole above ground

Karamental length required

6 mtr 5mtr 12 mtr 9 mtr 7.5 mtr 18 mtr

11 mtr 9 mtr 21 mtr 13 mtr 11 mtr 25 mtr

• Description of Pole Erection –

1. Unload the pole (PCC or RSJ pole) at site by vendor during dispatch at road side.

2. Shift the pole by contract workmen by manually at erection location.

Page 2: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 2 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

3. Dig the pit for erection of pole. Use insulated crowbar for digging purpose.

4. Pole erection done by manually.

5. Please see the given picture A - Do the assembly of pole i.e. fix the cross arm,

stay clamp, extension clamp for insulator and other hardware to be fixed on ground only and tie the Karamental Rope to top portion of pole also on ground as shown in given below picture. Also tie nylon rope at all four sides to hold the pole after erecting the same.

Picture A

All hardware fixed on pole on ground before erection as shown in above two pictures.

Page 3: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 3 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

Picture B

Picture C Pole Erection done by Manually Pole Erection done by Tractor mounted

crane

As shown in above picture, all hardware and Karamantal Rope need to be tie on ground level.

As shown in above picture, all hardware and Karamantal Rope need to be tie on ground level.

Page 4: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 4 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

6. Make sure that sufficient manpower should be available at site for pole erection.

7. Lift the pole manually into the pit as shown in given below Picture D.

Picture D

8. Trained supervisor must be available at site all the time. Conduct Tool Box Talk at site by supervisor / engineer and explain about the work to be carried out for a day with associated hazards and their control measures. Follow Site Specific Tool Box Talk format with Contractor declaration for record as evidence.

9. Grout the Stay clamp or earthing plates near the pole and tie the karamental both

end of rope with the clamp on ground as shown in given below Picture E. But make sure that rope should not get loosen.

Page 5: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 5 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

Picture E

10. After pole erection, Concreting to be done into the pit and after 24 hrs of concreting only after getting clearance from Site In-charge / Engineer, then only allow workman to climb on pole. Before climbing, workman must wear Full Body Harness with double lanyard with scaffolding hook and kinetic absorber as shown in given below pic.

Page 6: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 6 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

Workman climbing on pole with the help of Full Body Harness with Fall Arrester & Karamental Rope as shown below picture.

Demo of use of Full Body Harness with Fall Arrester & Karamental Rope.

Page 7: SOP for Pole Erection With All Hard Wire

PREPARED BY

OHS DEPT. APPROVED BY

PRAMOD HARGUDE

PAGE 7 OF 7

Godrej & Boyce Mfg. Co. Ltd. GODREJ ELECTRICALS & ELECTRONICS

TITLE DOC.NO. 2 / PIRE / OHS / SOP

/ SOP for Erecting the Pole with

their Hard ware fitted on it. REVISION

NO 00

I - INTEGRATED M-MANAGEMENT S - SYSTEM

ISO 9001 ISO 14001 OHSAS-18001

DATE

05.05.2013

11. Tie the Nylon Rope at all four sides to hold the same after lifting / erecting the pole. Check the condition of rope visually before start the activity. Do not use damage rope.

Nylon Rope got broken and for holding the pole use same rope by tying the knot as shown in picture. It is UNSAFE.