solving environmental challenges · arpechim refinery lakes bioremediation remediation. solving...

32
Solving Environmental Challenges Paolo Mannone – Director of AECOM Environment Continental Europe Gheorghe Stoian – Head of Environment AECOM Romania February 2016

Upload: others

Post on 24-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Solving Environmental Challenges

Paolo Mannone – Director of AECOM EnvironmentContinental Europe

Gheorghe Stoian – Head of Environment AECOMRomania

February 2016

Page 2: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Building,Design &Planning

Water Transportation ManagementServices

Power &Energy

Construction

l Air QualityConsulting &Engineering

l Climate Adaptation &Sustainability

l EHS ManagementConsulting &Compliance

l Impact Assessment& Permitting

l ManagementInformation Systems

l Remediation,Restoration,Redevelopment

l Solid & HazardousWaste Services

l Water, NaturalResourcesManagement

l Architecturel Building

Engineeringl Designl Economicsl Facilities

Managementl Planningl Program/

ConstructionManagement

l Program CostConsultancy

l CommunityInfrastructure

l Design-Buildl Drinking Waterl Industrial Waterl Wastewaterl Water Resourcesl Stormwater &

WatershedManagement

l Aviationl Freight Raill Highways &

Bridgesl Mass Transitl Planningl Ports & Marinel Traffic

l EmergencyManagement &ContingencyOperations

l InformationManagementSystems

l Intelligence andClassified MissionSupport

l InternationalDevelopment

l Logistics, Operationsand Maintenance

l Procurementl Systems

Engineeringl Training and

Simulation

l Energy Efficiency& CarbonManagement

l Energy Planning& Economics

l EngineeringDesign

l Hydroelectricl Nuclearl Renewables &

AlternativePower

l Transmission &Distribution

l Commissioningl Constructionl Construction

Inspectionl Construction

Managementl Cost Managementl Project Controlsl Site Development /

Preparationl Stakeholder

Relations

Fully Integrated Engineering Firm

Environment

Page 3: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Fully Integrated Engineering Firm

“…OUR CAPABILITY TO OFFER INTEGRATED

ENGINEERING SERVICES ALLOW US TO BE

BETTER ENVIRONMENTAL CONSULTANTS ...”

Page 4: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

ASSET MANAGEMENT INTEGRATIONEnvironmentEnvironment

Page 5: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Key Figures

6.800ENV Staff 1.600

ENV Staff

800ENV Staff

150 Countries

85.000 Total Staff

9.200 Environment

Page 6: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Romania

§ Environmental Services

Page 7: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

ENVIRONMENT ROMANIA

Page 8: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Beside design and environmental consultingservices, AECOM also acts in Romania as a GeneralContractor for Environmental projects, through theEnvironment Business Line.

AECOM is registered in the National Register ofdevelopers for environmental studies, namely:environmental balances, impact studies,environmental reports, appropriate assessment.

– ESHIA – Environmental Social Health ImpactAssessment

– EIA, SEA and Environmental permitting– Water management permitting– Biodiversity– Waste management and reporting– VOC balances and reporting– Remediation and site restoration services– Waste management and reporting– Technical assistance– Construction/remediation supervision including full

works packages– Environmental status monitoring– Environmental due diligence– Environmental consultancy– Geographic Information System GIS Analysis– Water and wastewater management

WHAT WE DO

Page 9: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Presentation Title Page 9

SELECTED PROJECT EXPERIENCE

Page 10: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 10

ESHIA, Land Leasing and Engineering Services in Romania(confidential client)

Page 11: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 11

Independenta bio-treatment plant, Galati CountyConstruction

Page 12: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 12

Ticleni bio-treatment plant and landfill, Gorj CountyConstruction

Page 13: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 13

Barasti bio-treatment plant, Olt CountyConstruction

Page 14: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 14

Videle bio-treatment plant, Teleorman CountyConstruction

Page 15: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 15

Arpechim refinery lakes bioremediationRemediation

Page 16: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 16

Petrobrazi refinery internal lagoons cleanupRemediation

Page 17: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Food industry plant decommissioning and decontamination

February 16, 2016Solving Environmental Challenges Page 17

Page 18: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 18

Food industry plant decommissioning

Page 19: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

SEA, GENERAL TRANSPORT MASTER PLANFOR ROMANIA (GTMP)

February 16, 2016Solving Environmental Challenges Page 19

• Integrate environmental considerations into the preparation andadoption of GTMP;• Ensure that all necessary measures are taken to protect theenvironment and the protected areas, to reduce environmentalimpacts ;• Ensure the sustainable development of the GTMP.

Page 20: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 20

Rehabilitation of Industrial Sludge lagoon of 30 hectares inTg Mures

AECOM – JV partner in a design&build project,in collaboration with:

- Geiger Transilvania SRL,- Geiger Umweltsanierung GmbH and- Astor Com SRL.

Page 21: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Short description of the historical polluted site

February 16, 2016Solving Environmental Challenges Page 21

Satellite imagery of the sludge lagoon - 2013

Page 22: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Short description of the historical polluted siteImages of the lagoon in June 2014

February 16, 2016Solving Environmental Challenges Page 22

Page 23: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

The state of the sludge

February 16, 2016Solving Environmental Challenges Page 23

Page 24: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 24

Should we adapt the lagoon to the designor

Should we adapt the design to the lagoon?

Traditionalconcept

The concept will askadditional material.

Potential behaviorin time

or

Use the natural shape of the sludge and designing a more even covering layer

Current sludgeshape

Page 25: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 25

Optimal solution for implementation

Page 26: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 26

Challengesmaterials behavior

Overlapping on the adjacent strips of geogrid do not function properly on sludge

Page 27: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 27

A higher strength material was tested and which can be sewed for providing strength continuity

Solutions

Page 28: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 28

ChallengesSide extrusions of sludge when executing the internal dams

Page 29: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 29

A floating excavator was used to dig the internal dam routes and to level the excess of material. The same equipment wasused for leveling the already occurred side extrusions of the sludge.

SolutionsPreliminary removal of the sludge crust and side

sludge leveling

Page 30: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

February 16, 2016Solving Environmental Challenges Page 30

Works progress

Image taken in October 2015

Page 31: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Decision on new investments• Choosing the site location• Baseline surveys• Due Diligence – ESA Phase 1, 2• Romanian Environmental Balances• Risk studies• Decontamination works

Construction phase• Design and technical assistance• All required permitting services• Works Supervision / Works Management• Construction of industrial buildings and facilities• Remediation/decontamination works

Decommissioning• Site investigations (DD, ESA, Env. Balances)• Assessment of remediation needs and costs• Formalizing environmental liabilities• Decontamination/demolition works

Operation• Getting or renewal of Environmental Permit• IPPC - permit• Water management permit• Planning and coordination of environmental

monitoring• Support in reporting to authorities

o waste, including specific waste (packaging, tires etc)o VOC, other air/water emissions

We can offer individual or whole chain of services and works for different phases

February 16, 2016Solving Environmental Challenges Page 31

Page 32: Solving Environmental Challenges · Arpechim refinery lakes bioremediation Remediation. Solving Environmental ChallengesFebruary 16, 2016 Page 16 Petrobrazi refinery internal lagoons

Thank You!For any enquiries please contact:

GHEORGHE STOIAN

Head of EnvironmentalDepartment

[email protected]

Phone: +4 021 316 11 63

Mobile: +4 0756 135 051

PAOLO MANNONE

Director, Growth - EnvironmentContinental Europe

[email protected]

Phone: +39 02 422556 213Mobile: +39 348 93 73 361