Client Type: Utility-Fossil Power Plant
Challenge/Issue: Due to an aging protection system the client was required to upgrade all plant protection for 600MW steam turbine units, 50MW black start turbine, GSU, (3) auxiliary transformers
Equipment Involved: Protective relays, control cabinets, all components included with cabinets, interconnect cable
Solutions: Provide turnkey solution to include conceptual design, engineering, drawing upates, material procurement, relay cabinet assembly/testing, scheduling, logistics, demolition of existing protection system, installation of new protection system, testing and commissioning
Scope/Deliverables: Turnkey installation of redundant relaying configuration
Solution ProfileRelay Replacement