soil improvement works for an offshore land reclamation · consolidation in the vertical and...

12
Proceedings of the Institution of Civil Engineers Geotechnical Engineering 162 February 2009 Issue GE1 Pages 21–32 doi: 10.1680/geng.2009.162.1.21 Paper 700035 Received 02/07/2007 Accepted 10/10/2008 Keywords: geotechnical engineering/land reclamation Jian Chu Associate Professor, School of Civil and Environmental Engineering, Nanyang Technological University, Singapore Myint Win Bo Director (Geo-services), DST Consulting Engineers Inc., Thunder Bay, Ontario, Canada Arul Arulrajah Senior Lecturer, Swinburne University of Technology, Melbourne, Australia Soil improvement works for an offshore land reclamation J. Chu PhD, M. W. Bo DUC, MSc, PhD, CGeol, CSci, CEng, CEnv, EurGeol, EurEng, PGeo, FICE, FGS and A. Arulrajah PhD, CPEng, FIEAust The Changi East reclamation project was carried out in five phases along the foreshore of the east coast of Singapore. The water depths in the reclaimed area ranged from 5 to 15 m. The project involved hydraulic placement of 272 million m 3 of sand onto soft seabed marine clay up to 50 m thick. A linear total of 170,000 km of prefabricated vertical drains (PVDs) were installed for accelerating the consolidation process of the underlying soft marine clay. The soil improvement works covered a total area of approximately 1200 ha. In this paper, the site conditions and the soil improvement works adopted are described. Pilot tests with full-scale field instrumentations as well as laboratory and in situ tests were carried out to verify the design, check the effectiveness of the soil improvement works using PVDs, and establish the most suitable drain spacing. Field monitoring data obtained from both the pilot tests and the reclamation works are presented and interpreted. Degree of consolidation was calculated based on both settlement and pore pressure data. 1. INTRODUCTION The Changi East reclamation project was carried out between 1991 and 2005 in five phases to create 2000 ha of land for the expansion of the Changi International Airport and other infrastructure developments in Singapore. The location of the project and the site plan are shown in Figure 1. Phase 1 of the project comprised phases 1A, 1B and 1C, which commenced in 1991, 1993 and 1995 respectively. Each phase lasted about five years, with a couple of years’ overlap between the phases. Two other phases, called area A (south) and area A (north) commenced simultaneously in 1999. Area A (north) and area A (south) were completed in March 2004 and March 2005 respectively. The project involved hydraulic placement of 272 million m 3 of sand in seawater up to 15 m deep. As the majority of the reclamation area was underlain by a highly compressible layer of Singapore marine clay up to 50 m thick, approximately 170 million linear metres of prefabricated vertical drains (PVDs) together with surcharge up to 8 m thick were used to consolidate the seabed soft clay and improve its engineering properties. The total area of the soil improvement works was approximately 1200 ha. The hydraulically placed sand fill was generally in a loose state. Three deep compaction methods were deployed to densify the sand fill: dynamic compaction using heavy pounders, Mu ¨ ller resonance compaction (MRC) and vibroflotation. For dynamic compaction, heavy pounders were used in the areas where the required depth of compaction was 5–7 m. The weight of the pounders used ranged from 15 to 23 t, and drop height was from 20 to 25 m. MRC and vibroflotation methods were adopted in the areas where the thickness of compaction was 7–10 m. The equipment used for MRC was MS-100HF and MS-200H and for vibroflotation was V23, V28, V32, Keller S300 and Pennine BD400. Compaction of granular fill was carried out after the fill surcharge was removed. Densification of sand fill will not be covered in this paper owing to space limitations. For more detail, see References 1 and 2. The unit weight of the compacted sand fill was in the range 18–19 kN/m 3 . 2. SITE CONDITIONS The site conditions, as revealed by the site investigation carried out prior to reclamation, are as follows. The seabed at the reclamation area ranged from 3 to 15 mCD (Admiralty chart datum, where the mean sea level is at +1 . 6 mCD). In the northernmost part of the area the seabed sloped northwards from 5 to 15 mCD, and in the southern part it sloped southwards from 5 to 10 mCD. Deep hollows in the seabed, varying from 10 to 13 mCD, occurred in the eastern part of the area. A typical soil profile and the basic soil properties are shown in Figure 2. The soil profile can be divided into four layers: the upper marine clay; the intermediate layer which consisted of the stiff silty clay layer or/and the silty sand layer; the lower marine clay layer; and the old alluvium, a medium-dense to dense cemented clayey sand layer that is not shown in Figure 2. The thickness of the marine clay ranged from 5 to 55 m, and of the intermediate layer from 2 to 5 m. The large variation in the thickness of the marine clay layer was due to not only undulations in the surface of the underlying materials but also the self-weight consolidation of the clay in the area of thick deposition. As indicated in Figure 2, the upper and lower marine clay are highly compressible and high in water content. Except for the top few metres, the marine clays are generally lightly overconsolidated. The water content of the upper marine clay ranged from 50% to 85% and that of the lower marine clay from 40% to 65%. Both the upper and lower marine clays had almost 100% fines content, with 50% silt and 50% clay for the upper marine clay and 60% silt and 40% clay for the lower marine clay. The Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 21

Upload: phungcong

Post on 05-Sep-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Proceedings of the Institution ofCivil EngineersGeotechnical Engineering 162February 2009 Issue GE1Pages 21–32doi: 10.1680/geng.2009.162.1.21

Paper 700035Received 02/07/2007Accepted 10/10/2008

Keywords: geotechnicalengineering/land reclamation

Jian ChuAssociate Professor, School of Civiland Environmental Engineering,Nanyang Technological University,Singapore

Myint Win BoDirector (Geo-services), DSTConsulting Engineers Inc.,Thunder Bay, Ontario, Canada

Arul ArulrajahSenior Lecturer, SwinburneUniversity of Technology,Melbourne, Australia

Soil improvement works for an offshore land reclamation

J. Chu PhD, M. W. Bo DUC, MSc, PhD, CGeol, CSci, CEng, CEnv, EurGeol, EurEng, PGeo, FICE, FGS andA. Arulrajah PhD, CPEng, FIEAust

The Changi East reclamation project was carried out in

five phases along the foreshore of the east coast of

Singapore. The water depths in the reclaimed area

ranged from 5 to 15 m. The project involved hydraulic

placement of 272 million m3 of sand onto soft seabed

marine clay up to 50 m thick. A linear total of 170,000

km of prefabricated vertical drains (PVDs) were installed

for accelerating the consolidation process of the

underlying soft marine clay. The soil improvement works

covered a total area of approximately 1200 ha. In this

paper, the site conditions and the soil improvement

works adopted are described. Pilot tests with full-scale

field instrumentations as well as laboratory and in situ

tests were carried out to verify the design, check the

effectiveness of the soil improvement works using PVDs,

and establish the most suitable drain spacing. Field

monitoring data obtained from both the pilot tests and

the reclamation works are presented and interpreted.

Degree of consolidation was calculated based on both

settlement and pore pressure data.

1. INTRODUCTION

The Changi East reclamation project was carried out between

1991 and 2005 in five phases to create 2000 ha of land for the

expansion of the Changi International Airport and other

infrastructure developments in Singapore. The location of the

project and the site plan are shown in Figure 1. Phase 1 of the

project comprised phases 1A, 1B and 1C, which commenced in

1991, 1993 and 1995 respectively. Each phase lasted about five

years, with a couple of years’ overlap between the phases. Two

other phases, called area A (south) and area A (north)

commenced simultaneously in 1999. Area A (north) and area A

(south) were completed in March 2004 and March 2005

respectively. The project involved hydraulic placement of 272

million m3 of sand in seawater up to 15 m deep. As the

majority of the reclamation area was underlain by a highly

compressible layer of Singapore marine clay up to 50 m thick,

approximately 170 million linear metres of prefabricated

vertical drains (PVDs) together with surcharge up to 8 m thick

were used to consolidate the seabed soft clay and improve its

engineering properties. The total area of the soil improvement

works was approximately 1200 ha.

The hydraulically placed sand fill was generally in a loose

state. Three deep compaction methods were deployed to

densify the sand fill: dynamic compaction using heavy

pounders, Muller resonance compaction (MRC) and

vibroflotation. For dynamic compaction, heavy pounders were

used in the areas where the required depth of compaction was

5–7 m. The weight of the pounders used ranged from 15 to

23 t, and drop height was from 20 to 25 m. MRC and

vibroflotation methods were adopted in the areas where the

thickness of compaction was 7–10 m. The equipment used for

MRC was MS-100HF and MS-200H and for vibroflotation was

V23, V28, V32, Keller S300 and Pennine BD400. Compaction

of granular fill was carried out after the fill surcharge was

removed. Densification of sand fill will not be covered in this

paper owing to space limitations. For more detail, see

References 1 and 2. The unit weight of the compacted sand

fill was in the range 18–19 kN/m3.

2. SITE CONDITIONS

The site conditions, as revealed by the site investigation

carried out prior to reclamation, are as follows. The seabed at

the reclamation area ranged from �3 to �15 mCD (Admiralty

chart datum, where the mean sea level is at +1.6 mCD). In the

northernmost part of the area the seabed sloped northwards

from �5 to �15 mCD, and in the southern part it sloped

southwards from �5 to �10 mCD. Deep hollows in the seabed,

varying from �10 to �13 mCD, occurred in the eastern part

of the area. A typical soil profile and the basic soil properties

are shown in Figure 2. The soil profile can be divided into

four layers: the upper marine clay; the intermediate layer

which consisted of the stiff silty clay layer or/and the silty

sand layer; the lower marine clay layer; and the old alluvium,

a medium-dense to dense cemented clayey sand layer that is

not shown in Figure 2. The thickness of the marine clay

ranged from 5 to 55 m, and of the intermediate layer from 2

to 5 m. The large variation in the thickness of the marine clay

layer was due to not only undulations in the surface of the

underlying materials but also the self-weight consolidation of

the clay in the area of thick deposition. As indicated in Figure

2, the upper and lower marine clay are highly compressible

and high in water content. Except for the top few metres, the

marine clays are generally lightly overconsolidated. The water

content of the upper marine clay ranged from 50% to 85%

and that of the lower marine clay from 40% to 65%. Both the

upper and lower marine clays had almost 100% fines content,

with 50% silt and 50% clay for the upper marine clay and

60% silt and 40% clay for the lower marine clay. The

Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 21

Phase 1C

Phase 1A

Phase 1B

Phase 1C

A

B

Singapore Changi Airport

Changi coastal road

Area A – south Area A– north

Sea

0 500 1000 2000 3000 m

Project Area: ha Length ofvertical drain:million metre

Phase 1APhase 1BPhase 1CArea A – northArea A – south

Total

50152045191

450

2013

–28491350

140

Republic of Singapore

Location

N

Figure 1. Location and site plan of the project

Depth belowseabed: m

Soil description

Seabed 4·3 mCD�00

05

10

15

20

25

30

Upp

er m

arin

e cl

ay

Very soft marine clay withfragmented seashells

Soft silty clay with organic mattersSoft to stiff silty clay with sand

Firm to stiff silty clay

Soft to firm marine clay

Soft to stiff silty clay withorganic matters and fine sand

Watercontent: %

Clayfraction: %

Field vane shearstrength: kN/m2

Compressionindex

Preconsolidationpressure: kN/m2

0 50 100 20 2040 4060 60 800 0 0 0·5 1 1·5 2 0 100 200 300 400

Effective overburdenpressure

PL WC LL

Inte

rmed

iate

laye

rLo

wer

mar

ine

clay

Figure 2. Typical soil profile and basic properties of Singapore marine clay: PL, plastic limit; WC, water content; LL, liquid limit

22 Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al.

normalised undrained shear strength ratio, su=�9v, for themarine clay at normally consolidated conditions was in the

range 0.25 to 0.32 based on field vane shear tests.3 The

intermediate layer was formed by desiccation of the top layer

of the lower marine clay as the sea level dropped. The

intermediate layer was overconsolidated, stiff and low in both

compressibility and moisture content. The coefficient of

consolidation in the vertical and horizontal directions of the

original seabed soil, cv and ch respectively, as measured by

laboratory and in situ tests are shown in Figure 3. The in situ

tests and the Rowe cell test measured the ch values, and the

conventional oedometer test gave cv. The coefficient of

consolidation, back-calculated based on the field settlement

monitoring data at the end of soil improvement using PVDs,

is also shown in Figure 3. It can be seen that the back-

calculated ch values were actually lower than the ch values

measured by either in situ or laboratory tests. This was

partially due to the smear effect caused by the installation of

PVDs and the reduction in ch after the soil had been

consolidated into the normally consolidated (NC) state from

the originally overconsolidated (OC) state, as discussed by Chu

et al.4 Typical values of ch and cv in the NC state, and other

soil parameters for the Singapore marine clay at Changi, are

given in Table 1. The values of ch and cv varied with the

overconsolidation ratio (OCR). The values in the OC state were

much greater than those in the NC state, as discussed in detail

in Reference 4. Further description of the engineering

properties of the Singapore marine clay can be found in

References 5–8.

3. SOIL IMPROVEMENT WORKS

As mentioned, approximately 170 million linear metres of

PVDs were used in the project to improve the engineering

properties of the seabed soils. The spacing of the PVDs was

determined to achieve a 90% degree consolidation under a

specified surcharge load within a given duration. Hansbo’s

equations9 and a simplified soil profile were used in the design.

The soil parameters were taken from both laboratory and in

situ tests conducted for the specific site.4–7 The ranges of the

values are given in Table 1. Studies of the smear effect were

also carried out.7,10 Based on the studies, the permeability of

the smeared soil was taken as one-half or one-third that of the

undisturbed soil, and the diameter of the smear zone was four

to five times the equivalent diameter of the PVD. The initial

design required a drain space of 1.7 m. PVDs were installed

throughout the entire compressible layer down to the hard

stratum. Two types of PVD were used in the project: Colbond

CX1000 and Mebra MD7007. The specifications for the PVDs

are given in Table 2. The test methods that were adopted for

quality control tests are described in Reference 10. The PVDs

were installed when the sand fill reached a level slightly above

the high tide. A fill surcharge 8.5–12 m high was then applied.

The fill surcharge was chosen based on the anticipated

0

5

10

15

20

25

300 5 10 15 20

c cv n2or : m /year

Dep

th: m

SBTP

DMT

CPTu

Field

Rowe cell

Oedometer

Figure 3. Comparison of coefficient of consolidation measuredby different tests and back-analysis: SBPT, self-boringpressuremeter holding test; DMT, flat dilatometer holdingtest; CPTu, piezocone dissipation test; field, ch back-calculatedusing field settlement data

Parameter Upper marine clay Intermediate layer Lower marine clay

Unit weight, ª: kN/m3 14.2–15.7 18.6–19.6 15.7–16.7Water content: % 50–85 10–40 40–66Liquid limit: % 70–95 30–70 60–90Plastic limit: % 20–28 18–20 20–30Initial void ratio, e0 1.8–2.2 0.5–0.9 1.1–1.7Specific gravity, Gs 2.60–2.72 2.68–2.76 2.70–2.75Compression index, Cc 0.6–1.5 0.2–0.3 0.4–1.0Recompression index, Cr 0.1–0.2 0.02–0.15 0.05–0.2Secondary compression index, CÆ 0.012–0.025 0.004–0.023 0.012–0.023OCR 1.5–7.0 3.0–4.0 1.8–2.0Vertical coefficient of consolidation in NC state, cv: m

2/year 0.5–1.7 – 0.5–2.3Horizontal coefficient of consolidation in NC state, ch: m

2/year 2.0–4.0 – 3.0–6.0Coefficient of permeability: m/s 10�8 –10�9 – 10�9 –10�10

Table 1. Range of physical and compressibility parameters of Singapore marine clay at Changi, Singapore

Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 23

maximum future loads to be applied. As the ground settlement

was large, part of the fill used as surcharge would be sinking

gradually below the water level. This led to a reduction in the

surcharge load due to the submergence effect.11 The possible

variation in the surcharge load was taken into consideration in

the design. Consolidation of the soft clay layer took place

under the surcharge. The design specification for the pilot test

site was that a degree of consolidation of 90% should be

achieved in

18 months. The surcharge was removed 18 months after the

required degree of consolidation had been achieved. The

ground settlement was predicted based on a one-dimensional

consolidation settlement calculation in which oversimplified

soil profile and soil parameters were used. The predicted

settlements were in the range 150–250 cm for soil deposits of

different thicknesses.

3.1. Pilot test

The soil profiles at this site varied erratically. Thus it was

necessary to verify the simplified design calculation, check the

effectiveness of the soil improvement works using PVDs, and

establish the most suitable drain spacing. For this purpose,

several pilot tests were conducted at different phases during the

project. The pilot tests were also used as full-scale model tests

to study the consolidation process of soft soil with or without

PVDs under both fill and surcharge loads; thus a better

understanding of the consolidation behaviour of soft soil, and

more reliable designs, could be achieved. All the pilot tests

were fully instrumented. Pore water pressures, settlements and

lateral displacements at the ground surface and other depths in

the soil, and surcharge loads, were monitored for the entire

duration of the pilot tests.

The results of the pilot test conducted during the construction

of phase 1B are presented in this paper. Figure 4 shows the

plan and section views of the pilot test area, which was 280 m

long and 230 m wide, and divided into four separate zones.

Three zones—lots 1.5, 1.7 and 2.0—were installed with drains at

square grid spacings of 1.5, 1.7 and 2.0 m respectively to study

the effect of drain spacing. The fourth zone, lot X, was used as

a control zone with no drain installed. All zones were 50 m

square. The details of the instrumentations are also shown in

Figure 4. The instrument types used were surface settlement

plate (SP), screw-type deep settlement gauge (DS), multilevel

settlement gauge (MS), liquid settlement gauge (SG), deep

reference point (DR), pneumatic piezometer (PP), open-type

piezometer (OP), vibrating-wire piezometer (PZ), water

standpipe (WS) and inclinometer (IN). Readings were taken

once a day or once every three days for the first month, and

once a week or once every two weeks for subsequent months.

The instruments for the control zone, lot X, were installed

offshore from a pontoon before fill was placed, whereas for the

other zones they were installed when the fill reached

+4.0 mCD. For lot X, the instrument clusters had to be specially

protected from the disturbance imposed during fill placement

and subsequent PVD installation.12 The original seabed level

was at �2.5 to �5.0 mCD. Reclamation by hydraulic pumping

of sand fill was used to bring the ground surface up to

+4.0 mCD. At this level, PVDs were installed. The fill surcharge

was then elevated to +10.0 mCD and subsequently lowered to

+5.5 mCD after a surcharge period of 18 months.

The construction sequence for the pilot area was as follows.

(a) Offshore soil investigation for the seabed soil was carried

out from a jack-up pontoon.

(b) Instruments were installed for the no-drain area under

marine conditions.

(c) The pilot area, 280 m long and 230 m wide, was reclaimed

to +4.0 mCD.

(d ) Detailed soil investigation was carried before soil

improvement works.

(e) PVDs were installed at the required spacings.

( f ) Instruments were installed for the three zones in which

PVDs had been installed.

(g) Surcharge was hydraulically placed to +10 mCD and

maintained for 18 months.

(h) Post-improvement soil investigation was carried out.

(i) The surcharge level was lowered to +5.5 mCD 18 months

after the surcharge was placed.

The sand fill materials were dredged from the sea. The mean

grain size ranged from 0.4 to 0.8 mm. It was clean sand, with

fines content less than 10%. The same sand was used as

surcharge. The underlying soil profile at the pilot site is shown

in Figure 4. The settlements monitored at different elevations

along or near the centreline of each zone are given in Figure 5.

As the soil profile was very erratic (Figure 4), the soil profile

for each zone is also shown in Figure 5 for easy reference. The

fill elevation at each zone is shown in Figure 5. The dates at

which PVDs were installed are also given in Figure 5. Applying

Asaoka’s method,13 the ultimate consolidation settlements were

estimated for the four zones, as shown in Figure 6 and Table 3.

Asaoka’s method is commonly adopted to estimate the ultimate

consolidation settlement, based on curves of field-monitored

settlement against time. The application of this method is

explained in many papers for example Reference 14. Based on

these ultimate settlement values, the degree of consolidation

achieved after about 18 months of preloading was calculated as

91%, 93%, 82% and 77% for lots 1.5, 1.7, 2.0 and X

respectively. Lot 1.7 achieved a slightly higher degree of

consolidation than lot 1.5. This was because there were more

sand lenses in lot 1.7, which accelerated consolidation in both

the vertical and horizontal directions. For the same reason, a

relatively high degree of consolidation was also achieved for

lot 2.0 and lot X. Nevertheless, the effect of drain spacing is

shown by the data. Using the slope of the Asaoka plot for lot

1.5 in Figure 6a, the equivalent ch value was roughly back-

calculated as 0.98 m2/year. It was assumed in the calculation

Parameter Value

Width: mm 100Thickness: mm 3–4Tensile strength (dry and wet) at 10% strain: kN .1Elongation: % ,30Discharge capacity (straight at 350 kPa): 10�6 m3/s . 25Discharge capacity (buckled at 350 kPa): 10�6 m3/s . 10Pore size, O95: �m ,75Permittivity: s�1 .0.005

Table 2. Specification for PVDs used for the Changi EastReclamation Project

24 Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al.

that the diameter of the smear zone was four times that of the

equivalent drain diameter, and that the permeability of the

smeared soil was half that of the intact soil. This back-

calculated ch value is similar to that presented in Figure 3. As

the general soil profile at the reclamation site, as shown in

Figure 2, resembled more closely that for lot 1.5, the pilot test

results suggest that a drain spacing of 1.5 m should be used.

Based on Figure 5, the rates of settlement after 18 months of

preloading are also estimated and presented in Table 3. The

values are between 0.06% and 0.08%/month, and are relatively

small. The secondary compression is also calculated using a

secondary compression index of 0.02 and a void ratio of 1 (see

Table 1 for typical values), and shown in Table 3. A secondary

compression rate of 0.005%/month is thus obtained, and this is

considered insignificant. However, secondary compression may

not be evaluated separately from primary consolidation, as

elaborated by Leroueil.15 Nevertheless, after the removal of

surcharge, the soil became overconsolidated, and the secondary

compression rate would have reduced.16

The pore water pressures measured at different depths together

with surcharge histories are shown in Figure 7 for lot 1.5 and

in Figure 8 for lot X (no drain area). These pore pressure

responses are typical as described by Tavenas and Leroueil.17

Based on Figures 7 and 8, the pore water pressure distribution

profiles for lot 1.5 and lot X are also plotted in Figure 9.

During the preloading, long-term piezocone (CPTu) holding

tests were also conducted at locations close to the selected pore

pressure transducers to verify the pore water pressures at

different depths. In conducting these tests, a piezocone was

pushed to a given depth and held there for over 30 h until the

change in pore pressure readings became negligible. The pore

pressures measured by CPTu and the pore pressures monitored

from the pilot test after the same durations (17 and 14 months

after surcharge for lot 1.5 and lot X respectively) are shown in

Figure 9. Good agreement between the piezometer readings and

the CPTu holding tests is observed for most of the points. This

also confirms that the pore pressures monitored in the pilot test

are reliable. The effect of PVDs can be clearly seen from a

comparison of the pore water pressure profiles for the 1.5 m

spacing zone and those for the no-drain zone shown in Figure

9. The average degree of consolidation for lot 1.5 and lot X can

also be estimated approximately based on the pore water

pressure profile using a method explained in Reference 14.

Based on the pore water pressure data shown in Figure 9, the

AA

WS Water standpipePP PiezometerSP Surface settlement plateDS Deep settlement gauge

MS Multilevel settlement device

SG Settlement gaugeIN Inclinometer

1·7 1·7 m�

1·5 1·5 m�

2·0 2·0 m� No drains

Run

way

C L28

0 m

230 m

(a)

1·7 m 1·5 m 2·0 m

MCD 0� �0 MCD

10 10

�10 �10

�20 �20

�30 �30

�40 �40

�50 �50

Sand surcharge

Sand fill Sand fill

SandSand

Sand

Sand

Sand

Marine clay

Cemented sand Cemented sand

Marine clay

(b)

Legend

Marine clay

Figure 4. Pilot test at Phase 1B: (a) plan; (b) section A–A

Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 25

average values of degree of consolidation achieved 17 and 14

months after surcharge are roughly 80% and 38% for lot 1.5

and lot X respectively. It can be seen that the degree of

consolidation estimated based on the pore water pressure is

smaller. There are two reasons for this. The first is the locations

where the instruments were installed. As only limited

instrumentation could be used, the settlement plates were

installed along the centreline, where the maximum settlements

Soil profile

Soil profile

Borehole DC-13(C)

Borehole DC-13(C)

Eleva-tion:mCD

Eleva-tion:mCD

Elevation:mCD

Elevation:mCD

Depth:m

Depth:m

Soiltype

Soiltype

Soilinstrument

Soilinstrument

4

4

0

0

Sand

Sand

Sand

Sand

Sand

Sand

Sand

SP-021

SP-011

3·5

3·5

DS-039

DS-026

�2·5

�3·4

DS-040

DS-027

�8·5

�9·9

�8·4

�8·3

DS-041

DS-028

�16·5

�12·6

�27·3

�25·6

�21·5

DS-042

DS-030

DS-024

DS-043

�38

�11·6

�12·5

�16·4

�17·5

�19·3

�34·2

�37·8

�23·1

�39·1

�28·8

43·1

32·75

41·8

27·1

38·2

23·3

20·4

16·5

15·6

12·3

12·4 Clay

Clay

Clay

Silt

Silt

Silt

12

12

10

10

8

8

6

6

4

4

2

2

Sur

char

ge: m

CD

Sur

char

ge: m

CD

PVD

PVD

4 Feb 1994

26 Feb 1994

23 Aug 1994

14 Sep 1994

11 Mar 1995

2 Apr 1995

27 Sep 1995

19 Oct 1995

14 Apr 1996

6 May 1996

0

0

20

20

40

40

60

60

80

80

100

100

120

120

140

140

160

160

180

180

200

200

Set

tlem

ent:

cmS

ettle

men

t: cm

0

0

200

200

400

400

600

600

800

800

DS-043

DS-024

DS-042

DS-030

DS-041

DS-028

DS-040

DS-027

DS-039

DS-026

SP-021

SP-011

(a)

(b)

�0·35

21·5

4·35

Figure 5. Settlements monitored from the pilot test for Phase 1B: (a) lot 1.5; (b) lot 1.7; (c) lot 2.0; (d) lot X. (In lot 1.5, DS-040malfunctioned owing to an insufficient gap between the screw plate and the protective casing)

26 Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al.

would occur. As a result, the settlements would be

overestimated, which in turn led to an overestimation of the

degree of consolidation. The piezometers, on the other hand,

were installed at the centre of a square drain grid where the

highest pore water pressure was normally generated. As the

pore pressures near the drain would be much lower, the

average excess pore water pressures across the radial distance

to the drain would be smaller than that measured. Therefore

900 1000

Soil profile

Soil profile

Borehole DC-13(C)

Borehole DC-13(C)

Eleva-tion:mCD

Eleva-tion:mCD

Elevation:mCD

Elevation:mCD

Depth:m

Depth:m

Soiltype

Soiltype

Soilinstrument

Soilinstrument

0

0

Sand

Sand

Sand

Sand

Sand

Silt

SP-034

SP-001

3·5

�2·48

DS-056

DS-001

�2·5

�9·48

DS-057

DS-002

�6·1

�22·45

�6·1

�3·08

DS-058

DS-003

�13·4

�28·48

�9·4

�21.5

�23·5

�13·4

�29

�28·7 32·71

17·4

32·98

13·4

25.5

27·68

10·1

7·08

Clay

Clay

Clay

Clay

12

15

10

10

8

5

6

0

4

�5

2Sur

char

ge: m

CD

Sur

char

ge: m

CD

PVD

26 Feb 1994

17 Nov 1993

14 Sep 1994

5 Jun 1994

02 Apr 1995

22 Dec 1994

19 Oct 1995

10 Jul 1995

6 May 1996

25 Jan 1996 13 Aug 1996

0

0

20

20

40

40

60

60

80

80

100

100

120

120

140

140

160

160

180

180

200

200

Set

tlem

ent:

cmS

ettle

men

t: cm

0

0

200

200100

400

400300

600

600500

800

800700

DS-058

DS-003

DS-057

DS-002

DS-056

DS-001

SP-034

SP-001

(c)

(d)

4

�45·5

�62·5

49·48

66·48

Figure 5. (cont’d)

Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 27

the pore pressures measured by the piezometers are

overestimated, which in turn caused underestimation of degree

of consolidation. The second reason is the horizontal sand

seams in the soil. These sand seams can reduce the drainage

path considerably, particularly if vertical drains are not used.

This is likely to be the case for lot X. As shown in Figure 4,

sand seams existed in the pilot test area, although details of the

sand seams under lot X were not revealed through the soil

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100 120 140 160 180 200Si�1: cm

Si�1: cm Si�1: cm

Si�1: cm

Si:

cmS

i: cm

Si:

cmS

i: cm

(a)

0

20

40

60

80

100

120

140

160

180

200

0 20 40 60 80 100 120 140 160 180 200

(b)

0

20

40

60

80

0 20 40 60 80

(c)

0

20

40

60

80

100

0 20 40 60 80 100

(d)

Figure 6. Asoka method applied to: (a) lot 1.5; (b) lot 1.7; (c) lot 2.0; (d) lot X

Pilot test section

Lot 1.5 Lot 1.7 Lot 2.0 Lot X

Total clay thickness: m 21.0 16.75 11.4 22.0Measured final settlement: cm 163.5 176.0 59.5 77.0Estimated ultimate settlement: cm 180 190 73 100Degree of consolidation: % 91 93 82 77Estimated residual settlement: cm 16.5 14.0 13.5 23.0Rate of settlement after 18 months’ preloading: cm/month 1.7 1.3 0.7 1.5Strain rate after 18 months’ preloading: %/month 0.08 0.08 0.06 0.07Rate of secondary compression: %/month 0.004 0.004 0.004 0.004

Table 3. Ultimate settlement and degree of consolidation estimated for the pilot test

28 Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al.

investigation. However, the thin sand seams did not affect the

pore pressure measurements very much, unless the pore

pressure transducers happened to be installed at the sand seam

level. This explains why the degree of consolidation calculated

by settlement is much higher than that calculated by pore

pressure for lot X.

3.2. Field monitoring during soil improvement

In addition to the pilot tests, field instrumentation and

monitoring were also carried out during the reclamation and

soil improvement works.18,19 Curves of the variation of

settlement and pore water pressure with time at a location

with PVDs installed at 1.5 m square grid spacing are shown

in Figure 10. The soil profile at this location is also shown

in Figure 10. Using Asaoka’s method, the ultimate ground

settlement was estimated as 275 cm, as shown in Figure 11.

Using the data in Figure 10, the settlement and pore water

pressure distribution profiles with depth are also plotted in

Figure 12. The average degree of consolidation achieved at

the end of preloading was 90% based on the settlement data

and 87% based on the pore water pressure data. Again, the

pore water pressure was measured at the centre of the square

drain grid and thus represented the worst case. The

settlement profiles shown in Figure 12b indicate that there

were settlement developments at all depths over the whole

duration of preloading. However, the majority of the

settlement was concentrated in the top 15 m depth.

The effect of soil improvement in phase 1B can be shown by

the comparison of soil parameters shown in Figure 13. The data

in Figure 13a do not indicate a clear change in the moisture

content. This is common for soft clay with its moisture below

the liquid limit (see Figure 2), as discussed in Reference 19.

Therefore the variation of moisture content may not be a good

indicator for evaluating the effectiveness of soil improvement.

Figure 13b shows a more than twofold increase in the

undrained shear strength as measured by field vane shear tests

using the uncorrected data. Corresponding to the increase in

undrained shear strength, there should be an increase in the

preconsolidation stress. However, the increase in

preconsolidation stress was only marginal, as shown in Figure

13c. This was due mainly to the uncertainties involved in the

12

200

8

150

4

100

0

50

�4

0

0

0

0·2

0·2

0·4

0·4

0·6

0·6

0·8

0·8

1·0

1·0

1·2

1·2

1·4

1·4

1·6

1·6

1·8

1·8

2·0

2·0

Fill

ele

vatio

n: m

Exc

ess

pore

pre

ssur

e: k

N/m

2

Time: years(a)

Time: years(b)

Vertical draininstallation8 Apr 2004

�8

�4 mCD

+10 mCD

Water level

PP-042

PP-041

PP-043

PP-044

PP-039

PP-040

Figure 7. Variations of (a) surcharge and (b) pore waterpressure with time measured in lot 1.5 (fill height notadjusted for settlement). Depth of instruments: PP-041,�6.5 mCD; PP-042, �17.0 mCD; PP-044, �21.0 mCD;PP-043, �24.7 mCD; PP-039, �28.3 mCD; PP-040,�32.0 mCD

200

150

12

8

4

0

�4

�8

Fill

ele

vatio

n: m �4 mCD

�10 mCD

Water level

0 0·2 0·4 0·6 0·8 1·0 1·2 1·4 1·6 1·8 2·0Time: years

(a)

100

50

0Exc

ess

pore

pre

ssur

e: k

N/m

2

0 0·2 0·4 0·6 0·8 1·0 1·2 1·4 1·6 1·8 2·0Time: years

(b)

PP-001

PP-002

PP-003

PP-004

PP-005

Figure 8. Variations of (a) surcharge and (b) pore waterpressure with time measured in lot X. Depth of instruments:PP-001, �6.48 mCD; PP-002, �12.38 mCD; PP-003,�14.98 mCD; PP-004, �19.48 mCD; PP-005, �24.48 mCD

�35

�30

�25

�20

�15

�10

�5

00 100 200 300 400 500

Pore pressure: kPa

Ele

vatio

n: m

Lot 1·5, 9 months

Lot X, 9 months

Lot 1·5, 17 months

Hydrostatic

Lot X, 14 months

Lot 1·5, CPTU

Lot X, CPTU

Surcharge

Lot X(no-drain area)

Lot1·5

Figure 9. Pore pressure distribution profiles

Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 29

preconsolidation stress determination using one-dimensional

consolidation tests, such as sample disturbances.

4. CONCLUSIONS

The multi-phase Changi East reclamation project was

undertaken to reclaim about 2000 ha land offshore along the

east coast of Singapore by depositing sand fill onto a thick

layer of soft seabed marine clay. Soil improvement works were

carried out to consolidate the soft marine clay using PVDs and

surcharge preloading. Full-scale pilot tests were carried out on

site with full instrumentation to verify the design, and to check

the effect of drain spacing on the soil improvement results. The

degree of consolidation was assessed using both settlement and

pore water pressure data. The following conclusions can be

drawn from the study.

(a) The pilot test has demonstrated that, under fill 10 m thick,

a degree of consolidation of 90% could be achieved within

18 months when PVDs with a 1.5 m square grid spacing

were used.

(b) Even when PVDs at this close spacing of 1.5 m are used,

the rate of consolidation can still be considerably

affected by horizontal sand seams. Therefore a detailed

site investigation is still necessary for the reclamation

project.

(c) The average degree of consolidation should be estimated

using both settlement and pore pressure data. The degree of

consolidation estimated using settlement is normally higher

than that using pore water pressure. This can be partially

explained by the fact that instruments are often installed at

locations where the highest settlement and pore pressure

values are measured. This leads to an overestimation of the

degree of consolidation when settlement data are used, and

PVD

Borehole PB-39 Instrument

Elevation:mCD

Originalseabed 3·29 mCD�

DS 93-Fine tomedium sand �4·1 mCD

PP 76-

PP 77-�9·91 mCD

DS 106-�10·9 mCD

DS 07-�14·8 mCD

PP 79-�17·8 mCD

DS-108�20 mCD

PP-80�22·9 mCD

DS 109-�27·8 mCD

PP 81-�27·8 mCD

PP 82-�32·08 mCD

DS 110-�34·1 mCD

Very softmarine claywith someseashellfragments

Soft silty clay

Firm silty clay

Soft marine clay

Dense clayeysand

Soft to firmsilty clay

Clayey sand

Silty sandDense silty sand

�5

�10

�15

�20

�25

�30

�35

�40

Ele

vatio

n: m

CD

Fill

ele

vatio

n: m

CD

Set

tlem

ent:

m

12

8

4

0

�40 0·5 1·0

Time: years2·0 2·5

0

2·0

2·5

3·0

0·5

1·0

1·5

0

1·5

Time: years

�10 mCD

DS-110

DS-108DS-107DS-106

DS-93

DS-109

SP-85

0·5 1.0 2.0 2·51·5

Pie

zom

etric

leve

l: m

CD

0

30

25

20

15

10

5

0

Time: years

PP-076PP-077PP-079PP-080PP-081PP-082Water level

0·5 1.0 2.0 2·51·5

Figure 10. Settlement and pore pressure monitored during reclamation

0

50

100

150

200

250

300

0 50 100 150 200 250 300Si�1: cm

Si:

cm

Figure 11. Asoka plot for the ground settlement measured inFigure 10

30 Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al.

an underestimation of the degree of consolidation when

pore pressure data are used.

(d ) Long-term CPTU holding tests are an effective way to

verify the monitored field pore pressure data.

ACKNOWLEDGEMENT

The authors would like to thank Mr Wei Guo for his help in the

preparation of some of the figures in this paper.

REFERENCES

1. BO M. W., CHU J. and CHOA V. The Changi East Reclamation

Project in Singapore. In Ground Improvement: Case

Histories (INDRARATNA B. and CHU J. (eds)). Elsevier, Oxford,

2005, pp. 247–276.

2. CHOA V., BO M. W., ARULRAJAH A. and NA Y. M. Overview

of densification of granular soil by deep compaction

methods. Proceedings of the 1st International Conference on

Ground Improvement Techniques, Macau, 1997, 131–140.

3. BO M. W., CHANG M. F., ARULRAJAH A. and CHOA V.

Undrained shear strength of the Singapore marine clay at

Changi from in-situ tests. Geotechnical Engineering:

Journal of the Southeast Asian Geotechnical Society, 2000,

31, No. 2, 91–107.

4. CHU J., BO M. W., CHANG M. F. and CHOA V. The

consolidation and permeability properties of Singapore

marine clay. Journal of Geotechnical and Geoenvironmental

Engineering, ASCE, 2002, 128, No. 9, 724–732.

5. BO M. W., ARULRAJAH A., CHOA V. and CHANG M. F. Site

characterization for a land reclamation project at Changi in

Singapore, Proceedings of the 1st International Conference

on Site Characterization, Atlanta, GA, 1998, 333–338.

6. BO M. W., ARULRAJAH A. and CHOA V. The hydraulic

conductivity of Singapore marine clay at Changi. Quarterly

Journal of Engineering Geology, 1998, 31, No. 4, 291–299.

7. BO M. W., CHU J., LOW B. K. and CHOA V. Soil Improvement:

Prefabricated Vertical Drain Techniques, Thomson

Learning, Singapore, 2003.

8. BO M. W., CHOA V. and HONG K. H. Material

(a) (b) (c)�40

�35

�30

�25

�20

�15

�10

�5

00 20 40 60 80

Moisture content: %

Ele

vatio

n: m

CD

Before After

0 20 40 60Vane shear strength: kPa

Before After

0 100 200 300Preconsolidation stress: kPa

Before After

Figure 13. Comparison of soil parameters measured before and after soil improvement: (a) moisture content; (b) field vane shearstrength; (c) preconsolidation stress

(a)

(b)

�40

�35

�30

�25

�20

�15

�10

�5

00 100 200 300 400 500 600

Pore water pressure: kPa

Ele

vatio

n: m

CD

Hydrostatic21 Sep 967 Oct 957 Apr 95Total load

Date of surcharge: 30 Dec 1994

�40

�35

�30

�25

�20

�15

�10

�5

00 0·5 1·0 1·5 2·0 2·5

Settlement: m

Ele

vatio

n: m

CD

7 Apr 959 Oct 9523 Sep 96

Date of surcharge: 30 Dec 1994

Figure 12. (a) Excess pore water pressures and (b)settlements measured at different elevations and durations inPhase 1B

Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al. 31

characterization of Singapore marine clay at Changi.

Quarterly Journal of Engineering Geology and

Hydrogeology, 2003, 36, No. 4, 305–319.

9. HANSBO S. Consolidation of fine-grained soils by

prefabricated drains. Proceedings of the 10th International

Conference on Soil Mechanics, Stockholm, 1981, 3, 677–682.

10. CHU J., BO M. W. and CHOA V. Practical consideration for

using vertical drains in soil improvement projects.

Geotextiles and Geomembranes, 2004, 22, Nos 1–2, 101–

117.

11. BO M. W., CHU J. and CHOA V. Factors affecting the

assessment of degree of consolidation. Proceedings of the

5th International Symposium on Field Measurements in

Geomechanics, Singapore, 1999, 481–486.

12. ARULRAJAH A., NIKRAZ H. and BO M. W. Factors affecting

field instrumentation assessment of marine clay treated

with prefabricated vertical drains. Geotextiles and

Geomembranes, 2004, 22, No. 5, 415–437.

13. ‘ASAOKA A. Observational procedure of settlement

prediction. Soils and Foundations, 1978, 18, No. 4, 87–101.

14. CHU J. and YAN S. W. Estimation of degree of consolidation

for vacuum preloading projects. International Journal of

Geomechanics, ASCE, 2005, 5, No. 2, 158–165.

15. LEROUEIL S. Compressibility of clays: fundamental and

practical aspects. Journal of Geotechnical Engineering,

ASCE, 1996, 122, No. 7, 534–543.

16. HIGHT D. W., BOND A. J. and LEGGE J. D. Characterisation of

the Bothkennar clay: an overview. Geotechnique, 1992, 42,

No. 2, 303–348.

17. TAVENAS F. and LEROUEIL S. The behaviour of embankments

on clay foundations. Canadian Geotechnical Journal, 1980,

17, No. 2, 236–260.

18. VAN DER MOLOEN M. and BERG R.-J. Soil improvement

works at Changi East, Singapore. Proceedings of the 8th

International Conference on Geosynthetics, Yokohama,

2006, 2, 475–480.

19. BO M. W., ARULRAJAH A. and CHOA V. Assessment of degree

of consolidation in soil improvement projects. Proceedings

of the 1st International Conference on Ground Improvement

Techniques, Macau, 1997, 71–80.

What do you think?To comment on this paper, please email up to 500 words to the editor at [email protected]

Proceedings journals rely entirely on contributions sent in by civil engineers and related professionals, academics and students. Papersshould be 2000–5000 words long, with adequate illustrations and references. Please visit www.thomastelford.com/journals for authorguidelines and further details.

32 Geotechnical Engineering 162 Issue GE1 Soil improvement works for an offshore land reclamation Chu et al.