social monitoring report - adb.org · this social monitoring report is a document of the borrower....
TRANSCRIPT
Social Monitoring Report
Biannual Monitoring Report
Loan/Grant no: L2587NEP/G0182NEP/G0183NEP
January-June2016
NEP: Energy Access and Efficiency
Improvement Project
Prepared by the Government of Nepal for the Asian Development Bank. This Social Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
NOTES:
The fiscal year (FY) of the Government of Nepal and its agencies ends on 16 July. FY before a
calendar year denotes the year in which the fiscal year ends, e.g., FY 2016 ends on 16 July
2016.
In this report, "$" refers to US dollars.
This resettlement monitoring report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 3.
CURRENCY EQUIVALENTS
(9 July 2016)
Currency unit - Nepalese Rupee (NRs)
NRs1.00 - 108.11
US $1.00 - 1.00
ACRONYMS
ADB - Asian Development Bank
AP - Angle Point
AP - Affected Persons
CDC - Compensation Determination Committee
CDO - Chief District Officers
CFUG - Community Forest Users Group
DDTL - Dumre-Damauli Transmission Line
EA - Executing Agency
ESSD - Environment and Social Studies Department
FY - The fiscal year
GoN - Government of Nepal
ha - Hectare
HHs - Households
kV - Kilo Volt
MD - Managing Director
MVA - Mega Volt Ampere
MW - Megawatt
NEA - Nepal Electricity Authority
PIU - Project Implementation Unit
PM - Project Manager
RoW - Right of Way
RP - Also used as Land Acquisition and Resettlement Plan
SPS - Safeguard Policy Statement
sq.m - Square Meter
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 4.
Table of Contents
ABBREVIATION
A. BACKGROUND ............................................................................................................. 6
A-1 Subproject Components and Physical Progress ............................................................. 6
A-2 Monitoring Requirements and Frequency of Submission ................................................ 9
A-2-1 Scope of Semi Annual Monitoring Report ....................................................................... 9
A-2-2 Reporting Period ............................................................................................................10
B CHANGES IN PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES .........10
C QUALITATIVE AND QUANTITATIVE DATA ................................................................10
D MONITORING PARAMETERS/INDICATORS AND METHODS ...................................10
E. SEMI ANNUAL MONITORING RESULTS .....................................................................11
E-1 Progress on Documentation and Approval ....................................................................11
E-2 Monitoring Results Compared Against Previously Established Benchmarks .................11
E-3 Monitoring Results Compared Against the Objectives of Safeguards ............................12
E-3-1 Safeguard Provision for Energy Access & Efficiency Improvement Project ....................12
F. PROGRESS ON ACQUISITION AND COMPENSATION ..............................................13
F-1 Compensation for Affected Land ....................................................................................13
F-2 Compensation Payment for Affected Structures .............................................................14
F-3. Livelihood Restoration ....................................................................................................15
F-4. Ensuring IPs Identity, Human Right, Livelihood and Cultural Uniqueness .......................16
F-5. Other Progress Made in Technical, Environmental, & Resettlement Activities .......... Error!
Bookmark not defined.
F-6 Grievance Redressal Mechanisms .................................................................................16
F-7. Minimizing Scope of Land Acquisition .............................. Error! Bookmark not defined.
G GAPS AND CORRECTIVE ACTION PLAN FOR MITIGATION .....................................19
H RECORDS ON DISCLOSURE OF MONITORING INFORMATION ... Error! Bookmark not
defined.
H-1 Identification of Key issues, Recommendations for Improvement .... Error! Bookmark not
defined.
I MONITORING ADJUSTMENT MEASURES RECOMMENDED...... Error! Bookmark not
defined.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 5.
J ADJUSTMENT IN INSTITUTIONAL ARRANGEMENT FOR IMPLEMENTING THE
MONITORING PLAN ....................................................... Error! Bookmark not defined.
K PROPOSED MAJOR ITEM OF FOCUS FOR NEXT REPORT ......................................20
List of Table:
Table 1-1: Project Components and Overall Implementation Status ........................................... 7
Table A-2: Subproject Components having Land Acquisition and Resettlement Impacts ........... 9
Table E-1: Submitted Grievances and Status ............................................................................17
Table F-1: Project Affected Land As Estimated During Feasibility & Implementation Phases ....19
Table F-2: Details on Acquired Land, Affected HHs and Compensation Paid HHs .............. Error!
Bookmark not defined.
Table F-3: Households having Affects on Structures and Compensation Distribution Status
................................................................................................... Error! Bookmark not defined.
Table F-4: Households Considered for Skill Livelihood Restoration TrainingError! Bookmark
not defined.
Table F-5: Major Progress Made in Dumre-Damauli ................... Error! Bookmark not defined.
Table H-1: Underlying Issues and Measure to Address ............... Error! Bookmark not defined.
Table K-1: Focus of Next Semi Annual Report ..........................................................................21
Table 4-2: Entitlement Matrix ....................................................................................................23
APPENDICES
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 6.
A. BACKGROUND
1. Presently Nepal is facing significant peak-load supply constraints in the electricity
system, due to constrained generation and network capacity. Energy Access and Efficiency
Improvement Project (EAEIP) is to address these issues and provide a useful catalyst for further
sector reform and physical investment, leading to the sector’s sustainable growth in the longer
term. A secure and predictable electricity supply will enable social and economic benefits to
materialize, and will ensure improved conditions for schools, hospitals, and other social services.
The targeted loss-reduction investments will close the gap between the cost of supply and
average retail tariff and will establish important precedents for management of design,
construction and management of distribution networks in Nepal.
2. The Project was approved on 27 November 2009, signed on 11 March 2010 and
declared effective on 4 June 2010. The Project consists of Asian Development Fund (ADF) loan
($65 million at the time of approval) and the grants from Climate Change Fund ($ 0.3 million) and
Clean Energy Fund ($4.2 million). Key dates related to the project are as follows:
Loan/Grant Original Closing
Date
Revised Closing Date
1st
Extension 2nd
Extension
Loan 2587 31 Mar 2015 Up to 31 Dec 2015 Up to 30 Dec 2016
Grant 0182 31 Mar 2013 Up to 30 Sept 2014 -
Grant 0183 31 Mar 2013 Up to 30 Sept 2014 Up to 30 Sept 2015
3. The loan financing covers 5 components- comprising components for improving
transmission, distribution and generation assets of NEA, loss reduction and support for
implementing public-private partnerships (PPP) in NEA’s distribution centers. The grant financing
covers distribution of the Compact Fluorescent Lamp (CFL) program across the country, and
solar powered energy efficient street-lighting.Successful implementation of the Project will
ensure:
I. Opportunities for hydropower development,
II. Increase accessibility to clean energy,
III. Reduction of outage in the distribution network, and total network loss, and
IV. Supply of efficient and reliable energy
4. Implementation of the Project expected to bring several positive impacts also in the
socio-economic scenario of different subproject locations contributing towards poverty reduction.
There will be raise on employment opportunities in the production sectors due to reliable and
efficient electricity supply and employment opportunity will also be generated during construction
period.
A-1 Subproject Components and Physical Progress
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 7.
5. Some of the subproject components achieved tangible progress both in terms of
implementing construction works as well as compensation disbursement activities. They include
construction of: (i) Chapali Substation, (ii) Distribution Substations and Switching Stations, (iii)
Butwal-Kohalpur 132 kV Second Circuit stringing (about 230 km), (iv) Expansion of Matatirtha
Substation, (v) Renewable Energy Street Lighting. A summary description of subprojects under
each component and their overall status and key issues are briefly presented in Table: 1-1.
S.
N
Sub-Projects
Overall Implementation Status
a. Middle Marshyangdi - Dumauli – Marshyangdi 132 kV Transmission Line and related
Substation Works
1.1 132 kV new Transmission Line
construction between Dumre to
Damauli (about 20 km)
- Completed foundation works for 30 towers out of 63
towers,
- Compensation paid to 28 households out of
permanently acquired land for tower construction
(29 Nos),
- Updated cadastral survey of Dumre-Damauli 132 kV
TL identifying affected households their land parcels
and other assets due to restriction of land in Dumre-
Damauli section for maintaining Right of Way (9
meter both sides)
- Imported technical equipment required for TL
construction
-Work currently stopped due to disputes between
contractor and NEA
1.2 Construction of a new 15 MVA, 132
kV/33 kV sub-station at Marshyangdi
-Major civil works completed and installation ongoing.
1.3 Reinforcement of Damauli sub-
station with construction of two 132
kV line bays,
-Civil work related to bay extension completed.
Foundation work of new control buildings in
Markichowk and Damauli ongoing.
1.4 Extension of 132 kV line bays at
Middle Marshyandi and Marshyandi
switchyards
All civil works completed and installation ongoing.
B. Butwal-Kohalpur 132 kV Second Circuit Transmission Line
This component will facilitate transferring power imported from India to Mahendranagar to the west
and center of the country. The project involves stringing of the second circuit on an existing 132 kV
line built on double circuit towers, increasing the power import capacity by up to 100MW about 205
km).The project is completed.
C. Construction of Chapali Substation and Associated Works
This sub-project includes construction of a new 30 MVA, 132 kV/11 kV sub-station, installation of 15
km of underground 11 kV distribution line for 6 feeders at Chapali, and extension of two 66 kV GIS
line bays at Lainchaur sub-station and installation of 7.5 km, 66 kV underground cable from
Lainchaur to Chabahil. All physical work except extension of GIS line bays at Lainchaur is
completed. Testing and commissioning of installed facility is also remaining. Presently two
transformers has encountered problem during testing and commissioning and rectification work is
ongoing.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 8.
S.
N
Sub-Projects
Overall Implementation Status
a. Middle Marshyangdi - Dumauli – Marshyangdi 132 kV Transmission Line and related
Substation Works
D. Expansion of Matatirtha Substation
Construction of additional 132 kV bays, installation of two transformers, and construction of 33 kV
and 11 kV lines to connect the existing circuits. Project is completed.
E. Installation of Capacitator Banks
Installation of approximately 220 MVAR of capacitor banks for reactive power compensation
at eight transmission sub-stations Project is completed.
Construction of Substation and Switching Stations
1 Construction of 6/8 MVA
distribution sub-station
constructions at Jhapa, Siraha,
Barahathawa,Paraul
Completed and in operation since 2015.
2 Construction of switching station in
Swayambhu, Mulpani
All work completed. Mulpani S/S already charged and
Swayambhu yet to be charged.
3 Construction of 6/8 MVA
distribution sub-station
construction at Dhanushadham)
6/8 MVA Substation construction works completed but
33 kV line to charge the substation yet to be
completed.
4 Construction of 6/8 MVA
distribution sub-station
constructions at Mainapokhar
(Bardiya), Kusma (Parbat),
Phedi(kaski), Mirmi (Syangja)
Work ongoing. Expected to complete within
December 2016.
5 RoW for 33 kV line (2 m both side)
for Dhanushadham (3 km)
Minor works and tapping to NEA’s system is
remaining. The RoW of transmission line is along the
road and hence has no impact due to construction
activities.
6 RoW for 33 kV line (2 m both side)
for Mainapokhar (Bardiya) S/S (2
km)
Completed stringing works except in small stretch.
There were no impacts due to stringing activities as
NEA adequately purchased land required for the
substation and associated (RoW) works.
This component aims for partial rehabilitation of Marsyangdi (69 MW) Gandak (15 MW) hydropower
plants to increase efficiency of their electricity generation at both power stations and reduce self-
consumption, providing an estimated additional 4 GWh of energy per year. This component is
composed of (a) replacement of weir control system and modernization of excitation systems at
Marshyangdi; and (b) installation of trash rack cleaning system at Gandak for the improvement of
plant availability. All installation works related to Marsyangdi HP and Gandak Power House
completed. Testing and commissioning of Trash Rack Cleaning Machine in Gandak Power House is
yet to be carried out.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 9.
S.
N
Sub-Projects
Overall Implementation Status
a. Middle Marshyangdi - Dumauli – Marshyangdi 132 kV Transmission Line and related
Substation Works
Proposed to address high technical and non-technical losses in medium voltage and low voltage
distribution networks in Kathmandu Valley. Series of pilot projects have been prepared by NEA; 16
11 kV feeders and downstream low voltage networks with unacceptably high losses have been
identified and are to be rebuilt from the 11 kV feeder circuit breaker down to the customer service
connection and revenue meter. These pilot projects been aimed to be “model networks” that can be
replicated across Nepal. They will incorporate best international practice with respect to design,
construction and commercial operation. Work is ongoing and expected to complete by December
2016.
NEA is planning to form strategic partnerships with private sector entities for management and
operation of the urban electricity supply systems with the support of ADB. NEA has completed
franchising model, bidding guidelines, and related legal and bidding documentation and other
ground level works. Consultants’ inputs for this component are completed.
The supply and delivery of CFLs lamps is completed. 750,000 CFLs were distributed in 24
distribution center of NEA spread over 24 districts of Nepal.
Installations of 1316 number of new solar street lighting systems and retrofitting of 185 existing
street light also completed and are currently under operational. Similarly 50 kWp grid tied solar roof
top and 10 kWp back up system installed in Bir Hospital. Additionally 100 kWp grid tied solar system
installed in Nepal Electricity Authority Training Center and currently under operation
A-2 Monitoring Requirements and Frequency of Submission
6. As per the SPS 2009 and ADB reporting guidelines, a semi-annual safeguard monitoring
report is required in the projects having involuntary resettlement impacts. The semi-annual report
to be based on the periodical report submitted by the Project to NEA, field verification and
meeting and consultation with affected persons, and the relevant NEA and project staff.
A-2-1 Scope of Semi Annual Monitoring Report
7. The Semi Annual report contains information on execution of different
subprojects/components and implementing land acquisition and resettlement activities and
compliance of safeguard application. The scope of this biannual report is specifically focused to
the following project components having land acquisition and resettlement scope/impact (Table
A-2).
Table A-2: Subproject Components having Land Acquisition and Resettlement Impacts
S.N. Subproject Components
1. Dumre-Damauli New 132 kV Transmission Line Construction (about 20 km)
2 Construction a new 30 MVA, 132 kV/11kV Sub-station of Chapali
3 Construction of distribution sub-station at Baniyani
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 10.
4 Construction of distribution sub-station at Dhanushadham
5 Construction of distribution sub-station at Paraul, Mahottari
6 Construction of distribution sub-station at Barthawa, Sarlahi
7 Construction of distribution sub-station at Dhikurpokhari/Banskot, Kaski,
8 Construction of distribution sub-station at Kusma, Parbat
9 Construction of distribution sub-station at Mainapokhar, Bardiya
10 Construction of switching sub-station at Mulpani (1 ropani 8 Aana)
Note: Land required for the components 3-10 in the above table either were purchased through direct negotiation or constructed
in available Government land.
A-2-2 Reporting Period
8. The reporting period of this semiannual report covers from January to June 2016.
B. CHANGES IN PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES
9. There are some changes on the scope to restrict the use of private land in Dumre -
Damauli 132 kV new Transmission Line project (about 20 km) for maintaining the RoW (9 meter
both side). Similarly, NEA directly purchased some land through negotiation required for
constructing distribution substation/switching stations and some of them were also constructed in
available Government land. This change has also brought differences on the number of affected
households compared to estimate made during feasibility phase. This change has been
incorporated in the updated draft LARP and cadastral survey prepared on February 2015.
However, finalization of alignment route and RoW yet to be confirmed with the support of
technical person/contractor through site verification, review of updated cadastral report, and
consultation with local communities likely to have RoW impact.
C. QUALITATIVE AND QUANTITATIVE DATA
10. The monitoring report contains both quantitative and qualitative data. Quantitative data
related to resettlement/acquisition impacts, affected persons, affected assets, and compensation
payment status was collected from NEA record at central level or relevant project offices.
Likewise, information related to quality of quantitative data and subjective information were
collected through consultation, meeting, discussion, unofficial dialogue with Project officials,
project affected families, local communities, and other stakeholders.
D. MONITORING PARAMETERS/INDICATORS AND METHODS
11. Screening of resettlement category and classification of impact is the main parameter of
monitoring. Based on screening and classification of safeguard impacts in accordance to ADB
SPS 2009, monitoring parameter has been determined as following:
a) Category A: If the proposed project is likely to have significant involuntary
resettlement impacts to 200 or more persons will be physically displaced from
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 11.
home, 200 or more persons lose 10% or more of their productive or income
generating assets or 200 or more persons experience a combination of both.
b) Category B: If the proposed subproject includes involuntary resettlement impacts
that are not deemed significant.
c) Category C: The proposed subproject has no involuntary resettlement impact.
d) In addition, any voluntary donation was verified by an independent third party to in
accordance with the project resettlement framework.
12. In accordance to above classification, the resettlement impacts of the Energy Access
and Efficiency Improvement Project has been classified as category “A” as the project affects
more than 200 persons including those having RoW impact on their land structures and other
assets. Some other basic monitoring parameters/indicators were considered for semi- annual
reporting which also include: (i) type of acquisition impacts, (ii) extent of impacts, (iii) measures
adopted to mitigate the impacts, (iv) implementation status of mitigating measures, (v)
consultation and dissemination, (vi) Grievance redressal, (vii) compensation payment, (viii) Deed
transfer (ix) resettlement and rehabilitation etc.
E. SEMI ANNUAL MONITORING RESULTS
13. Monitoring is essential for proper implementation of social safeguard measures.
Monitoring is also vital for updating the baseline conditions and for assessing social/resettlement
impacts and ensuring effective mitigation measures. The monitoring process should generate
meaningful information and improve the implementation of mitigation measures. Some of the key
progress observed in the project are summarized as follows:
E-1 Progress on Documentation and Approval
14. In accordance to changes in technical design NEA has recently (on Feb 2016) updated
the cadastral survey for the 132 kV TL route from Dumre-Damauli. This has facilitated to assess
the scope of RoW impact on land and other assets due to stringing of new 132 kV transmission
line. In the same line, the feasibility phase LARP also being updated incorporating the changes
on acquisition scope and progress made on social safeguard implementation.
E-2 Monitoring Results Compared Against Previously Established Benchmarks
15. By the time of preparing this report, compensation payment has been completed for (i)
permanently acquired land through formal acquisition for Chapali Transmission Substation and
land acquired through negotiation for other eight (8) Distribution Substations including Switching
Stations, (ii) affected structures/sheds in Chapali Substation (4 residential sheds) and in Butwal-
Kohalpur 132 kV Second Circuit (3 structures), and (iii) As reported by field based Environment
Management Unit (EMU) under the ESSD out of 29 permanently affected households due to
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 12.
acquisition of their private land for constructing transmission towers (Dumre-Damauli) 28
households have already been compensated. However, land for 132 kV Dumre – Damauli
transmission line yet to be restricted for maintaining RoW and compensated. Although NEA has
updated cadastral survey it has yet to be verified through field test and confirmed by the
contractor.
E-3 Monitoring Results Compared Against the Objectives of Safeguards
E-3-1 Safeguard Provision for Energy Access & Efficiency Improvement Project
16. As per LARP (being updated), the project has impacted the land owned by about 8981
persons of 3042 households (about 20.65 ha which also included government land in some RoW
section) and 17 residential structures/sheds and associated assets required for constructing (i)
132 kV transmission towers through permanent acquisition, (ii) Distributions and transmission
substations (6.88 ha) and for (iii) restricting land to maintain RoW of new 132 kV transmission line
(about 20 km) between Dumre-Damauli (13.77 ha).
17. NEA acquired Land through two different processes for EAIP, they are; (i) though
expropriation and (ii) acquisition through direct negotiation. As provisioned in Land Acquisition Act
1977 and SPS 2009, safeguard provisions and compliance monitoring is applicable only for the
land acquired through expropriation, but ADB safeguard provision is not applicable for the land
acquired through negotiation because Negotiated settlements help avoid expropriation and
eliminate the need to use governmental authority to remove people forcibly (ADB SPS-2009) and
thus, Safeguard Requirements does not apply to negotiated settlements. However, the negotiated
settlement shall offer adequate and fair price for land and/or other assets. Land Acquisition Act
1977 Clause 27, also states that all process described in the may not be followed for acquiring
land through direct negotiation. NEA purchased about 6.88 ha of land through negotiation for
constructing distribution substations and switching stations.
18. The Entitlement Matrix (EM) of Land Acquisition and Resettlement Plan (LARP) ensures
safeguarding provisions for the land and other affected assets due to the project under the
Project. The major safeguard provision made for the displaced households having impact on their
land and other assets acquired through expropriation but not through negotiation in Energy
Access and Efficiency Improvement Project also includes:
(i) Permanent acquisition of agricultural/ Residential/ commercial and other
private lands by landowners: Cash compensation at replacement cost based
on current market price. Provision of land for land compensation will be made for
those APs having complete loss of land in accordance to the prevailing Act.
1 &
3 There may be some changes on the number of affected households and persons after the finalization of Project’
Resettlement Plan (RP) as the RP is being updated.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 13.
(ii) Land restricted to use except for cultivation along the RoW of transmission
lines: One time cash compensation for the land restricted to maintain RoW of the
new transmission lines, except to use for agriculture purpose.
(iii) Loss of residential / commercial and other structures by titleholders: Cash
compensation for the loss of built–up structures at full replacement costs based
on current market price.
(iv) Loss of residential / commercial structures by squatters: Cash
compensation for the loss of built–up structures at full replacement costs.
(v) Loss of agricultural crops, fruit and wood trees: One time cash compensation
for the temporary loss of agricultural crops along the corridor of RoW due to
stringing of T/L at current market price based on average production of the
affected area, etc.
19. The entitlement matrix of the project showing detailed entitlement provisions for different
types of losses is included in Appendix-1.
20. Land acquisition and compensation distribution activities in most of the
components/subprojects except in Dumre-Damauli have almost been completed. Even in Dumre-
Damauli subproject, compensation has been paid to 28 out of 29 households whose land has
been acquired permanently to construct towers.
F. PROGRESS ON ACQUISITION AND COMPENSATION
F-1 Compensation for Affected Land
21. An estimated area of 206,450.14 sqm (20.65 ha) of land have been impacted by the
Project. Of the total affected land about 137,396 sqm (13.77 ha) of land is having only RoW
impact and about 69,053.24 sqm (6.88 ha) land have already been acquired permanently. Of the
total permanently acquired 69,053.24 sqm (6.88 ha) of land, 25,834.32 sqm land was purchased
through direct negotiation. The project has compensated for acquired land in most of the
subproject/component location including permanently acquired land to construct transmission
towers.
22. A total of 123 affected households have received compensation for their loss of land and
structures. The compensated households include; (i) 28 households for permanently acquiring
land to erecting new transmission towers, (ii) 70 households for acquiring land to Chapali
substations, (iii) 25 households with whom NEA purchased land through direct negotiation for
distributions/switching stations. Table F-2 and F-3 provides summary of acquisition and
compensation status of the project. Further details on land area and compensation amount will
also be incorporated in the LARP being updated.
Table F-2: Details on Acquired Land, Affected HHs and Compensation Paid HHs
S.N. Description Acquired Area
(sqm)
Affected
HHs (No)
Comp.
Paid
HHs (No)
Remaining
No of HHs
(Estimated)
Remarks
A. Middle Marshyangdi- Dumre-Dumauli – Marshyangdi 132 kV T/L & Related Works
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 14.
1. Acquisition of land for constructing 29
number of Transmission Towers falling in
Private land along Dumre-Damauli-Marki
Chowk section
27068
29
24
1
Th
roug
h A
cqu
isitio
n
2. Restriction to land for maintaining RoW for
Dumre – Damauli ( 9 m both side for 20 km)
section
119396.9 330 330[a]
3. Permanent Acquisition: Tower construction
(11.25* 7.92) for 15 MVA, 132kV/33kV New
Marsyangdi Sub-station at Markichock (5
nos)
445.06 4 4
4. RoW for New Marsyangi Sub-station (1km) 18000
Subtotal-A 164909.96 363 28 336
B. Construction of a new 30 MVA, 132 kV/11kV Sub-station at Chapali
3 Acquisition of land for the construction of a
new 30 MVA, 132 kV/11kV Sub-station at
Chapali
17297.16
70 70 - Through
Negotiation
Subtotal-B 17297.16 70 70 -
C. Construction of Distribution Substations/Switching Station
1 Construction of distribution sub-station at
Baniyani
0.694 1 1 -
Eithe
r a
va
ilab
le G
ove
rnm
en
t Lan
d o
r
Pu
rcha
se
d th
roug
h N
eg
otia
tio
n
Th
roug
h A
cqu
isitio
n
2 Construction of distribution sub-station at
Dhanushadham
3787.52 3 3 -
3 Construction of distribution sub-station at
Paraul, Mahottari
1925.35 9 9 -
4. Construction of distribution sub-station at
Barthawa, Sarlahi
5417.64 3 3 -
5 Construction of distribution sub-station at
Dhikurpokhari/Banskot, Kaski,
3179.62 2 2 -
6 Construction of distribution sub-station at
Kusma, Parbat
3052.44 3 3 -
7 Construction of distribution sub-station at
Mainapokhar, Bardiya
7708.6 3 3 -
8 Construction of switching sub-station at
Mulpani (1 ropani 8 Aana)
763 1 1 -
Sub-Total-C 25,834.32 25 25
206,450.14
(20.65 ha)
458 123 366
Source: Updated cadastral survey and technical design information, NEA, Feb 2016
[a]=The estimated area of land to be restricted for RoW and number of households to be affected to be confirmed after physical
verification and alignment route of 132 kV T/L. The contractor is yet be remobilized
Note: The final numbers will be incorporated in the updated RP
F-2 Compensation Payment for Affected Structures
23. Three subprojects; (i) Dumre-Damauli, (ii) Chapali Substation and (iii) Butwal –Kohalpur
2nd circuit stringing components have impact on 19 structures. Among them 4 are cattle sheds
and 15 are residential structures. Of the total households having impact on their structures 4
households in Chapali and 3 households in Butwal have already been compensated. Payment for
the structures affected due in Dumre-Damauli RoW is remaining (Table F-3). Further details in
affected land, structure, and compensation status will be incorporated in the updated Project
Resettlement Plan being updated.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 15.
Table F-3: Households having Affect on Structures and Compensation Distribution Status
S.N. Description Total
Affected
Structures
(No)
Affected
HHs (No)
Compensated
HHs (No)
Remaining
HHs(No)
A. Middle Marshyangdi- Dumre-Dumauli – Marshyangdi 132 kV T/L & Related Works
1. Residential structures (8) and cattle sheds
(4)
12 9
9
B. Construction of a new 30 MVA, 132 kV/11kV Sub-station at Chapali
2 Residential sheds 4 4 4
C. Butwal-Kohalpur 132 kV Second Circuit
3 3 3
Total 19 16 7 9
F-3. Livelihood Restoration
24. The updated cadastral survey shows about 329 households likely to be potential for
livelihood restoration/skill trainings in Dumre-Damauli subproject. The categories of potential
households listed for livelihood restoration/skill training also include: (i) single women headed
households, (ii) households having complete loss of structures, (iii) households having more than
10% land loss out of total holdings, (iv) households belonging to project affected indigenous
peoples including other vulnerable households and below poverty level households.
Table F-4: Households Considered for Skill Livelihood Restoration Training
S.N Vulnerability Category Vulnerable HHs by
Project Districts
(No.)
%
1. Single Women Headed Households 16 4.86
2. Households having full impact on residential structures 12 3.65
3. Households having more than 10 % of land loss 235 71.43
4. Dalit (minor caste) Households 18 5.47
5. Indigenous People’s Households 44 13.37
6. Below Poverty Level Households 4 1.22
Total Vulnerable Households 329 100
Source: Census, May – June 2005 (Updated Cadastral Survey 2016)
25. The project through its Resettlement Plan has allocated budget to implement skill
training/livelihood improvement activities to the family members of significantly affected,
indigenous and other vulnerable households. The ESSD already conducted several awareness
building, school support, and environmental and wild life conservation related programs. Imparting
such awareness program at community at project affected area and skill training to the family
member of significantly affected households would be supportive to such families to restart their
life as well as to ensure project’s direct benefit to local community and project affected family to
harness the benefit from the project as provisioned ADB Safeguard Policy (2009). However, the
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 16.
estimated number of households (Table F-4) potential for livelihood restoration/skill training may
be changed during the implementation phase due possibility of change the number of significantly
affected households.
F-4. Ensuring IPs Identity, Human Right, Livelihood and Cultural Uniqueness
26. The project not likely to have major impacts or it may not generate major issues related
to identity of Indigenous People (IP), human rights and cultural uniqueness. However, the project
has made provisions of livelihood enhancing training to the vulnerable including indigenous
significantly displaced households.
27. The Indigenous/Ethnic people in the project area having impact on their assets been
found streamlined with the main social stream sharing common cultural values and norms as well
as languages and benefiting from the similar economic opportunities. The IP and minors in the
project location are neither hunter nor pastoralist groups. They have not been found using solely
own distinct language for communication and social sharing, and not also having completely
independent culture and other traditional livelihood (e.g. fishing, hunting, collecting herbal plants).
F-6 Grievance Redressal Mechanisms
28. Land Acquisition Act encourages forming Grievance Redress Committee for solving the
grievances related to the project. Similarly, NEA in its website has also maintained contact
address to lodge the grievances. However, till direct Grievance Redressal method being adopted
in the subproject. According to this, project staff collects grievances received from DPs or other
stakeholders and local communities then forward to the Project Manager. The Project Manager
reports collected grievances to the Chief District Officer (CDO). The CDO as needed
review/verify and address the grievances through a joint meeting with representatives from the
project office and relevant government institution and local representatives from all political parties
and other stakeholders including affected persons on case to case basis. Some of the key
grievances submitted to the CDO under Dumre-Damauli 132 kV transmission line and their status
is given in Table E-1.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 17.
Table E-1: Submitted Grievances and Status
S.N. Submitted Grievances Action Taken and Status
Middle Marshyangdi - Dumauli – Marshyangdi 132 kV Transmission Line and related Substation Works
1. Local People’s Complain about AP 4-7
Bagbhanjyang: Displaced persons in
Bagbhangyang of Vyas Municipality, ward 11
have requested to shift/adjust the existing
location of AP towers (No. 4, 5, 6, 7) to avoid the
acquisition and RoW impacts on their
cultivating/residential/commercial land in
between these AP locations.
September 2015:
NEA discussed with the likely displaced persons and
local people,
CDO conducted all party meetings (2 times) at Damauli
on Sep 3 and 19, 2015 and repeatedly decided the
following: - requested NEA and affected community to
see the options/ scope for shifting the proposed T/T
location avoiding RoW impact on agricultural/residential
land provided the option is technically feasible.
- suggested NEA to clarify in all party meeting if shifting
is not possible.
ADB requested NEA for a joint (safeguard and
technical) mission in the problematic site to (i) share
affected persons’ view in the area and (ii) to assess
technical scope of shifting/adjusting the alignment for
avoiding/minimizing impacts
January-June 2016:
In January 17, 2016 a joint (safeguard and technical)
team of ADB and NEA visited Dumre-Damauli project
sites to access the issues in maintain RoW under
Dumre-Damauli T/L project.
The joint team discussed with local community in AP
4,5,6,7 and physically observed the proposed
alignment route between 4-5-6-7 and assessed the
scope of adjusting the transmission route for
avoiding/minimizing impacts on private land and
structures.
NEA will assess the possibility of shifting tower number
4-5-6-7 to reduce the impact on private land with support
from contactor’s team of surveyor and tower design
engineer.
2. Disturbance on Erecting AP-15 at Vyas
Municipality Ward No. 5: Local communities
have shown serious concern that construction of
Transmission Tower in the proposed location
(AP.15) may disturb for the existing play-ground
for sport activities and constructing stadium in
the future. So they have been requesting NEA
for slightly shifting of the existing Angle Point
(AP) location or to do some alternative
arrangement negotiating with local community.
During the joint safeguard mission in 17 th Jan 2016
one of the community representative reiterated their
demand for shifting back the tower in another plot of
Government land with gabion protection to increase
the area of existing ground. NEA will access the with
support from contactor’s team of surveyor and tower
design engineer.
Possibility support from contactor’s team of surveyor
and tower design engineer.
NEA has assessed the scope of shifting location for
AP 15 in another nearby plot of Government land
subject to the approval by the contractor.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 18.
F-7. Minimizing Scope of Land Acquisition
29. One of the objectives of Bank policy in Involuntary Resettlement is to minimize the scope
of acquisition as much as possible and practicable. Accordingly, as the calculation of acquired
and yet to be acquired land shows the project has been able to minimize the acquisition scope. It
is due to the reason that an estimated area of 259889.16 sq.m. or 25.99 ha of land was expected
3. Disturbance on Erecting AP- 57 and 58
located at Bhansar, Nayan Basti of Bhanu
Ward No 5:
Affected persons due to acquisition for towers
has been requesting advance compensations for
the likely affected residential structure and grain
storing structure before starting tower erecting
and stringing works.
Some land plotters are also requesting to confirm
whether their land will be affected by RoW
impact, if yes, also calculate and inform them the
estimated area likely to be affected before
starting the work.
One of the affected households Mr. Asa Bahadur
repeated the same demand during the joint
safeguard meeting in January 2016.
NEA is coordinating with the displaced households,
local people, persons likely to have RoW impact and
land plotters to inform them about the compensation
provision for the land and other assets (e.g.
structures) acquired for Transmission Towers and
RoW.
Processing for compensation distribution is pending
due to absence of Project Manager in the field and
NEA field based Resettlement Officers more
involvement in community forestry clearing activities
(As reported by field based NEA representative this
problem has been addressed)
I. New Marsyangdi 132 kV Second Circuit Stringing
1.
As reported by NEA project team, a household
affected during the first circuit stringing has been
disturbing for second circuit stringing work since
June 2015. This is mainly due to the reason that
the household did not receive compensation for
the projects impact during the first phase.
Project offered the remaining payment for the
mentioned impact. But the household is
demanding high and not allowing to work in
Marsyangdi-Middle Marsyangdi section.
The project team will explore the information on
compensation payment and organize another round
of meeting once contractor resumed the work.
4. Affected households in Yampaphant ,are also
disturbing second circuit stringing due to RoW
impact on their land both in the first as well as
second circuiting stringing. Some of them have
also submitted grievance to CDO, but not yet
heard.
One of the contacted persons (Bhanu Bhakta
Bhattarai) has also submitted grievance to
District Administration (DAO) office during
Mangsir 2071 (November 2014), but grievance
not heard.
Further discussion will be held in presence of CDO a
and other district authorities once contractor is
mobilized.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 19.
to be acquired for the project during feasibility. However, only about 206450.14 sq,m, (20.65 ha)
land has been estimated to be affected during the implementation. The recent estimate is about
53,439.02 sqm (5.34 ha) less than the feasibility phase estimate (Table: F-1). Utilization of
available GoN/NEA land for different subproject components is one of the main reasons of
reducing impact on the size of land during the implementation phase.
Table F-1: Project Affected Land As Estimated During Feasibility & Implementation Phases
S.N. Description Sqm Ha
1. Area of Land to be Affected as Estimated during
Feasibility Phase
259889.16 25.99
2 Actual Area of Affected Land during Implementation 206450.14 20.64
3. Minimized Area from the Scope of Acquisition 53439.02 5.34
G. GAPS AND CORRECTIVE ACTION PLAN FOR MITIGATION
30. Following corrective actions has been recommended for addressing the issues and
accelerating the implementation of land acquisition and compensation distribution activities:
a. Institutional strengthening of ESSD also to support on designing resettlement
planning, support on implementing and monitoring activities;
b. Active involvement of Environmental Monitoring Unit under NEA/ Environmental
and Social Studies Department (ESSD/EMU) on RP Implementation Activities;
c. Regular communication and follow-up with project affected families;
d. Finalizing of updated cadastral survey report disclosing to local community,
project affected families and field verification of alignment route with the support
of contractor;
e. Addressing of all impending grievances with the support of relevant stakeholders
(e.g. local community, district level Government agencies, project affected
families and other stakeholders etc.);
f. Get the compensation rate fixed from Chief District Officer (CDO) for different
types of impacts and losses (e.g. impact on structures, impact on livelihood,
impact on trees and crops etc.) due to restriction of land for maintaining RoW in
Dumre-Damauli;
g. Address the grievance if any regarding compensation with the support of CDC,
CDO, and other stakeholders including local community;
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 20.
h. Ensure compensation distribution to all project affected households for different
types of losses;
i. Prepare database and inventories of project affected households and their
affected assets;
j. Prepare and finalize the list of affected indigenous, dalits and other significantly
affected vulnerable households (BPL HHs, women headed households, HHs
having disabled person, significantly affected households) to ensure them
additional support (e.g. skill training) as provisioned in the entitlement matrix;
k. Impart skill/livelihood restoration training to the family members of eligible target
groups/households with the support of local skill training providing institutes;
l. Collection of evidence that ensure the disbursement of compensation to the
affected households (e.g. copy of officially signed documents after receiving
compensation by DPs, Copy of land ownership transferred certificate (Lalpurja)
etc.;
m. Collection and compilation of copies of correspondence letters, meeting minutes,
submitted grievances and decisions made by the CDO or the project to be
maintained in NEA/EM Unit;
n. Timely submission of progress report;
o. Other activities related to land acquisition, compensation, skill training and
associated activities.
H. PROPOSED MAJOR ITEM OF FOCUS FOR NEXT REPORT
31. The next semiannual report will be focused on the progress of implementing and
complying safeguard activities as summarized in Table K-1.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 21.
Table K-1: Focus of Next Semi Annual Report
S.N
Description
1. Identification/conformation of households to be affected by Transmission line RoW.
2. RoW restriction and compensation distribution related works
3 Fixation of compensation for the RoW affected land and other associated structures
4. Fixation of compensation Rate for the structures affected due to RoW impact
5. Fix compensation rate for loss of crops and trees due to RoW impacts
6. 1. Update on proportion of land loss by affected persons due to RoW impact by reviewing information related
land ownership
7. Update information on loss of trees and structures due to RoW impact
8. Deed transfer of already compensated land for towers.
9. Compensation and deed transfer of remaining 1 affected household affected due to land acquisition for
tower.
10 Status of updated resettlement plan implementation -
12. Grievance redressal status of ongoing grievances.
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 22.
APPENDICES
Table 4-2: Entitlement Matrix APPENDIX-
1 Nature of Loss
Application Definition of AP Entitlements Actions Responsibility
A. Land Acquisition (Applicable in case of fresh acquisition and / or legally confirmed ownership on the ROW
Permanent acquisition
of agricultural/
Residential/ commercial
and other private lands
by landowners
Land and other assets
permanently acquired for the
Project
Person(s) with land titles Cash compensation at replacement cost
based on current market price. Provision of
land for land compensation will be made for
those APs having complete loss of land in
accordance to the prevailing Act3
Full compensation for the
loss of land at
replacement cost
NEA and CDO
Land restricted to use
except for cultivation
along the RoW of
transmission lines
Portion of land used to maintain
the RoW of newly constructed
T/L under the project and
restricted to use except for
agriculture purpose
Ownership of such land will
remain to the titleholders and will
have full right to utilize the land
for cultivation except to built
structure and plantation of trees
within the area of RoW
Person(s) with land titles One time cash compensation for the land
restricted to maintain RoW of the new
transmission lines, except to use for
agriculture purpose.
The rate of compensation to be fixed by
Compensation Fixation Committee (CFC) to
be formed under the prevailing Acts.
Compensation for land
restricted to maintain
RoW of the newly
constructed transmission
lines
NEA and CDO
Permanent acquisition
or restriction to use of
agricultural/
Residential/other private
commercial and other
private lands except for
cultivation by Tenants
Land and other assets
permanently acquired or
restricted to use except for
agriculture due to RoW impact
Registered tenant(s) Fifty percent cash amount as compensation
to the tenants out of the total compensation
fixed for the permanently acquired land or
land restricted to use except for agriculture
to maintain the RoW of new transmission
lines.
The remaining fifty percent compensation
amount will be given to the titleholders of the
affected land as provisioned in the prevailing
law of Nepal
Compensation for the
tenants of affected land
NEA and CDO
3 There is also provision of land for land compensation to the APs having complete loss of their land only if government land is available in the area (Land Acquisition Act 1977, Clause
14)
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 24.
Significant impact on
residential land due to
restriction to use due to
RoW of new
transmission line or
restriction to use land
for the construction of
residential building due
to ROW impact
Those having small size of
residential land within the
restricted RoW area of new
transmission line and also not
having alternative land to
construct their house (subject to
be confirmed by CFC).
Person(s) having significant
RoW impact of new
transmission line on their
residential land causing
restriction to construct
residential building
Cash compensation at replacement cost
based on current market rate subject to be
confirmed by the CFC that the AP(s) don’t
have any alternative land to build their house
Compensation to those
who will have significant
impact on their residential
land due to RoW causing
restriction to built
residential structure
NEA and CDO
Temporary effect on
land due to use by the
contractors during
construction phase
Land temporarily acquired by the
contractors during the
implementation phase
Person(s) owning land Contract to be signed between the APs and
property owner for temporary use/acquisition
of land/assets. The contract to confirm rental
rate/compensation and mode of payment.
Project Office and the Contractor to ensure
compensation for the land/assets temporarily
acquired during the construction phase.
Compensation for the
temporarily acquired
land/assets by the
contractors
NEA and
Contractor
B. Loss of Residential /Commercial Structures (Applicable to the owners of the structures)
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 25.
Loss of residential /
commercial and other
structures by
titleholders
Residential/commercial and
other associated structures (e.g.
toilets, cattle shed etc) acquired
for the project
Owners of the affected
residential/commercial
and associated structures
Cash compensation for the loss of built–up
structures at full replacement costs based on
current market price.
The land occupied by the affected structure
within the RoW will not be permanently
acquired. However, the portion of land coming
under the RoW will be restricted to use except
for agriculture and the owners will be paid
compensation for the restricted portion of land
subject to be fixed by the CFC
Owners of affected structures will be allowed
to take/reuse their salvageable materials
The APs will be provided one time shifting
allowances to move the household effects
and materials. The allowance will be paid @
NRs 25,000 per affected households as
estimated based on consultation with the APs
on current market price.
The APs will also be provided transitional
allowance to meet to cost of renting
accommodation and other management cost
for a period of 4 months (estimated time to
rebuilt the house) @ NRs 5,000 per month
(Total NRs 20,000 per affected household)
Compensation for the
residential/commercial
structures
CDO/NEA
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 26.
Loss of residential /
commercial structures
by squatters
Structure on ROW / Govt. land
Owners of Structure Cash compensation for the loss of built–up
structures at full replacement costs.
The land occupied by the affected structure
within the RoW if owned by titleholders, the
portion of land coming under the RoW will be
restricted to use except for agriculture and the
owners will be paid compensation for the
restricted portion of land subject to be fixed by
the CFC
Owners of affected structures will be allowed
to take/reuse their salvageable materials
The APs will be provided one time shifting
allowances to move the effects and materials.
The allowance will be paid @ NRs 25,000
per affected households as estimated based
on consultation with the APs on current
market price.
The APs will also be provided transitional
allowance to meet to cost of renting
accommodation and other management cost
for a period of 4 months (estimated time to
rebuilt the house) @ NRs 5,000 per month
(Total NRs 20,000 per affected household)
Compensation for lost
assets to the squatters
NEA, CDO,
and NGO
C. Loss of Income Generating Activities (Whether or not land is legally occupied)
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 27.
Loss of agricultural
crops, fruit and wood
trees
- Loss of crops from the land
permanently acquired for the
project,
- Loss for crops likely to occur
during the construction phase
from the land restricted to use
except for agriculture to maintain
the RoW of new transmission
line, and
- Loss for crops likely to occur
on the agriculture land along the
existing RoW corridor while
stringing transmission the
transmission line including
second circuit.
Owner of crops or trees
One time cash compensation for the
temporary loss of agricultural crops along the
corridor of RoW due to stringing of T/L at
current market price based on average
production of the affected area.
Titleholders having loss of crops due to
permanent acquisition of land will be paid
compensation for 15 years, equivalent to the
average production of the acquired area to be
computed at their current market price.
One time compensation for loss of fruit trees
for average fruit production for next 15 years
to be computed at current market value.
One time compensation for loss of wood-trees
at current market value of wood (timber or
firewood, as the case may be).
Cash compensation for
the temporary/permanent
loss of crops/trees
CDO,NEA, District
Forest Office,
District Agriculture
Office and
Contractor
Loss of income by
commercial structure
owner / tenants
conducting businesses
from rented premises /
land
Business affected by
transmission line / sub-station
construction
Owner of business /
business tenants
operating business on
rented premises
One-time lump sum cash grant; minimum
one-month’s (assuming one month as the
minimum time required to shift and restart the
affected business) income based on the
nature of business and type of losses to be
assessed on a case-to-case basis.
Short-term compensation
for loss of income.
NEA and CDO,
NGO
Loss of business
premises
Business structure on acquired
land and/or legally confirmed
ownership rights on ROW
Owner /renter of business
premise
Shifting allowance will be paid to the affected
businesspersons on actual cost basis.
Removal /relocation
assistance
NEA and CDO,
and NGO
Loss of wages by
employees
Income reduced during period of
readjustment
Employees of businesses One-time financial assistance equivalent to
30 days wages (assuming 30 days as the
required time to restart the affected
business/work or to find new employment by
the wage employee) to be computed at local
wage rates.
Short-term compensation
for loss of income.
NEA and CDO
Energy Access and Efficiency Improvement Project: Loan 2587NEP
2nd
Semi Annual- Report – Jan 2016-Jun 2016 28.
Income restoration and
livelihood improvement
of the significantly
affected households
and other vulnerable
Households (e.g.
indigenous/ethnic/
minority caste group,
female headed etc)
Households having significant
impact on land /structures and
other vulnerable households
(e.g. indigenous/ethnic/ minority
caste group, female headed etc)
Households having
significant impact and
project affected vulnerable
project affected
households (e.g. Female
headed house, old and
disable head of
households without any
earning members, Dalits,
indigenous, minor caste,
below poverty level
households etc)
Enrollment of the family members on income
generation or skill training activities for the
improvement of household income. Each
family members to be involved in the
livelihood improvement activities will be
provided NRs 15.000 to get enroll in the skill
training or to start other livelihood
improvement activities (e.g. cattle farming,
keeping small shops etc)
The cost is estimated based on consultation
with the NGO and affected families and local
market to start small income generating
activities.
Involvement of vulnerable
households on livelihood
improvement activities
NEA, CDO,
and NGO
Loss of cultural &
community
structures
/facilities/resources
Community/cultural/religious
structures/resources affected by
the project
Temple/Monastery/Religio
us tree/Graveyard etc
Complete rehabilitation/restoration by the
Project; or, cash compensation for
restoring/reestablishment of the affected
cultural/community structures and
installations, to the recognized
patron/custodian.
Replacement /restoration
of
religious/cultural/commun
ity structure /facilities
NEA, CDO,
NGO, and local
Community
Unanticipated adverse
impact due to Project
intervention or
associated activity
The EA and Project implementation authorities will deal with any unanticipated consequence of the Project during and after the implementation in the light and
spirit of the principle of the entitlement matrix.