semi-annual social monitoring report - adb.org · pdf file4th semi annual social safeguard...
TRANSCRIPT
Semi-Annual Social Monitoring Report Project Number: 42173-013 Period: January – June 2017
BAN: Dhaka Environmentally Sustainable Water
Supply Project
Part A: Distribution Network Improvement
Part B: Intake, Raw Water Pipeline, WTP, Treated Water Pipeline and Distribution Network
Prepared by Dhaka Water Supply and Sewerage Authority on behalf of the Ministry of Local Government and Rural Development and Cooperatives – Government of Bangladesh for the Asian Development Bank. This semi-annual social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
1
Government of the People`s Republic of Bangladesh Ministry of Local Government, Rural Development and Co-operatives
Dhaka Environmentally Sustainable Water Supply Project (DESWSP) ADB Loan No-3051-BAN (SF)
Funded by:
ADB, EIB, AFD and Government of Bangladesh
SEMI ANNUAL SOCIAL and RESETLEMENT SAFEGUARD MONITORING REPORT
( Part A Distribution Network Improvement DNI ICB 02.7)
Year 2017: (Jan.-June 2017)
Submitted: July 2017
PREPARED BY:
Kunhwa Engineering & Consulting Co. Ltd., Korea
in Joint Venture with
Development Design Consultants Ltd., Bangladesh
Farhat Consulting Engineers and Architects Ltd., Bangladesh
in association with
Vernacular Consultants Ltd., Bangladesh
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
2
Table of Contents
ABBREVIATIONS...................................................................................................................................... 3
1 Executive Summary ........................................................................................................................... 4
2 Major Positive & Negative issues ....................................................................................................... 4
3 Background of the Report and Project Description ............................................................................. 5
4 Social Safeguard Impacts .................................................................................................................. 5
5 Scope of Monitoring ........................................................................................................................... 6
5.1 Internal Monitoring...................................................................................................................... 6
5.2 External Monitoring .................................................................................................................... 6
6 Scope of Impacts ............................................................................................................................... 6
7 Institutional Arrangement and Capacity .............................................................................................. 9
7.1 Institutional Arrangement ............................................................................................................ 9
7.2 Compensation and Rehabilitation: ............................................................................................ 10
7.3 Disclosure and public consultation: ........................................................................................... 10
7.4 Monitoring Results- Findings .................................................................................................... 10
7.5 Grievance Redress Mechanism (GRC) ..................................................................................... 10
7.6 Compliance Status ................................................................................................................... 10
8 Follow up Actions, Recommendations and Disclosure ...................................................................... 10
9 Required Action to be Monitored and Reported During the Next Monitoring Report .......................... 11
10 Appendixes ...................................................................................................................................... 11
i. List of Affected Persons and Entitlements ........................................................................................ 12
ii. List of Potentially affected person ..................................................................................................... 13
iii. Public Consultation Details............................................................................................................... 21
iv. Summary of minutes of disclosure meetings in each DMA with signature sheet and grievance ........ 26
v. Photographs of the affected areas, consultation meetings, reconstruction activities, etc.................... 44
vi. Copies of AP`s certification of payment (signed by the AP`s) ............................................................ 49
vii. Safeguards Compliance Monitoring Form & Checklist Safeguards Review Mission .......................... 61
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
3
ABBREVIATIONS
ADB Asian Development Bank
AP Affected People
DWASA Dhaka Water Supply and Sewerage Authority
DMC Design Management Consultant
DESWSP Dhaka Environmentally Sustainable Water Supply Project
DMA's District Metering Areas
EMP Environmental Management Plan
EA Executing Agency
EIA Environmental Impact Assessment
EMP Environmental Management Plan
FGD Focus Group Discussion
GAP Gender Action Plan
GRC Grievance Redress Committee
IP Indigenous People
NGO Non-Government Organization
RP Resettlement Plan
RF Resettlement Frame Work
WASA Water Supply and Sewerage Authority
GoB Government of Bangladesh
Ha Hectare
ICB International Competitive Bidding
IPP Indigenous People`s Plan
PMU Project Management Unit
PCU Project Coordination unit
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
4
1 Executive Summary
The project package No. ICB 2.7 is prepared as part of a new project titled – Dhaka Environmentally Sustainable Water supply Project (DESWSP), implemented similarly as contracts under DWSWSP. Dhaka Environmentally Sustainable Water Supply Project (DESWSP) has been implementing activities in an around 16 District Metering Areas (DMAs) to improve water supply status to certain limit in the network in Dhaka City. The activities broadly include i) rehabilitation or replacement of 376 km distribution pipeline of diameters varies from 150-500 mm and ii) rehabilitation of approximately 32000 house connections including installation of meters for serving more than 12 million population. iii) Resettlement of project affected people caused from implementation of this project activity in accordance with ADB policy and national rules and legislations. The Resettlement activities are being implemented under International Contract Bidding (ICB) packages 2.7 of zone-6 & through one Non-government Organization (NGO) (Samahar) since February 2015. There is no land acquisition under the proposed package. The main resettlement impact is the potential reduction in the income of shops and other businesses if the presence of trenches, excavated soil, and machinery make access difficult for customers for a long time. Issues of involuntary resettlement is being addressed according to national legislation (Government of Bangladesh Acquisition of immovable Property Ordinance, 1982), and ADB Safeguard Policy Statement (SPS), 2009, and DWASA Policy (Resettlement Policy Framework, 2013). A Resettlement Framework (RF) was developed for DESWSP to provide the mechanism through which Resettlement Plans (RP) is being prepared for each Hydraulic area (DMA) in the detailed design stage. Update Status during Reporting Period (Jan.- June 2017)
ICB 02.7, 607 : A total number 8 (Eight) APs identified in DMA 607
ICB 02.7, 606 : A total number 9 (Nine APs identified in DMA 606
ICB 02.7, 605 : A total number 22 (Twenty Two) APs identified in DMA 605
ICB 02.7,608 : A total number of 9 (Nine) APs identified in DMA 608
ICB 02 .7 610 : A total number of 35 (Thirty Five) APs Identified in DMA 610
DMA MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During January to June 2017 (BDT)
Remarks
607 06 Submitted 08 08 No 16500
606 06 Submitted 09 09 110250 26000 Grievance
605 06 Submitted 22 22 No 44200
608 06 Submitted 9 08 No 18000
610 06 Submitted 35 0 No 0 Not paid
Total= 83 47 104700
The partner NGO SAMAHAR is working on resettlement issues in 02.7.
2 Major Positive & Negative issues
Positive issues:
The local people informed well ahead about the construction work
The local people do not need to pay extra money for installation of new piped system Increased awareness among communities regarding project activities and benefit.
Increased community support and cooperation Reduced suffering of the community people during physical work as much as possible.
Paid compensation to APs ahead of physical work. Increased cooperation and coordination between physical resettlement works plan and
implementation
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
5
Negative issues Delay payment of contractors against grievance caused the dis-satisfaction of the local people as
well as APs.
Water supply quantity and quality may be hampered during physical work in some places and Communication in the localities hampered during physical work
In sufficient visit of the Resettlement NGO staff hampered the progress of the Construction work of the contractors
Due to insufficient visit of the NGO staff, sometimes the potential APs deprive from their compensation (who loss their income during construction.)
The social safeguard, and grievance issues of the local people are being hampered due to contractors negligence.
3 Background of the Report and Project Description
This semi-annual report covers period of January-June, 2017 and prepared on the designed ADB Social Safeguard Monitoring reporting structure. Among other Resettlement activities, the report is restricted describing information on identification of APs and their compensation payment status since inception. The project, DESWSP provides services to improve quality water supply, water pressure in the pipe lines, cost recovery, reduce water loss and gradual ground water depleting in Dhaka city. The Project is refurbishing existing water supply networks to repair leaks, increase capacity and pressure, remove illegal connections and provide a new system of metering to streamline leak detection and control and Aid cost recovery; Rehabilitation and reconstruction of the water supply system under the project are likely to have impacts (permanent and temporary) to the dwellers in the project sites.
Involuntary Resettlement impact that anywhere occurs from this project will be addressed according to ADB Safeguard policy statement (SPS) 2009 policy and Government of Bangladesh (GoB) Acquisition and Requisition of Immovable Property Ordinance 1982 (APIRO).
4 Social Safeguard Impacts
Involuntary Resettlement are prescribed in Safeguard Requirements 2 , of the ADB SPS (2009). The objectives are to: (i) avoid involuntary resettlement ,wherever possible;
(ii) minimize, involuntary resettlement by exploring project and design ,alternatives; (ii i) enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-
project levels; and (iv) improve the standards of living of the displaced poor and other vulnerable groups
. During the reporting period January to June 2017, physical activities have been done in DMA 607,606,605,608 and 610. During implementing the physical activities, if any existing utility services are damaged; respective contractors repair those damages by their own initiatives and/or by respective departments.
Table 1: Summary of Identified Impacts of DMAs
Reporting period (Jan. to June 2017)
Mitigation Action – Compensation Made
Permanent Impact
Land Acquisition Ha N/A
Community Resources Disconnected underground telephone lines, some water supply lines, which are being repaired by the contractor immediately
Affected Person
Vulnerable APs N/A
Temporary Impact N/A
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
6
Affected Shops None
Owners-Shopkeepers None
Tenants-Shopkeepers None
Vulnerable Hawkers None
Affected APs 47
Socio-economic Data (Estimated)
BD (Tk.1,04,700)
5 Scope of Monitoring
5.1 Internal Monitoring
The purpose of the monitoring is to assess the progress of resettlement works, and identifying potential progress and difficulties. The Resettlement NGO SAMAHAR is responsible to prepare a separate RP for each DMA under Distribution Network Improvement component. The Resettlement and Awareness Expert of MSC and Gender and Safeguard Officer of PMU are responsible to carry out the internal monitoring, who are performing the social impact assessment, finalizing the RP (prepared by the Resettlement NGO)and preparation of Semi Annual Social Safeguard Monitoring Report. After clearance of ADB PMU disclose the report on its website and public places. The key indicators which are being monitored regularly by MSC and PMU are:
1. Selection of APs as per policy described in the resettlement plan 2. Payment of the compensation to all affected persons in various categories, according to the
compensation policy described in the resettlement plan. 3. Public information and dissemination and consultation procedures 4. Adherence to grievance procedures and outstanding issues requiring management’s
attention 5. Compensation status of Female headed/elderly and disable APs
5.2 External Monitoring
ADB requires that the borrower retain qualified and experienced external experts to verify monitoring information for projects with significant impacts and risks. An external resettlement monitoring expert will be engaged by the PMU to undertake resettlement monitoring and evaluation. It is under process
6 Scope of Impacts
The Project Resettlement Impacts will be observed in roads where new pipes will be installed. The nature and extent of Resettlement Impacts will be assessed through conducting field survey in all roads, lanes and sub-lanes under all DMAs. Prescribed tools used to record Resettlement Impacts and socio-economic information, which include:
i. Numbers and types of ownership of affected shops and other business; ii. Average business incomes, rent paid by tenants and numbers of employees; iii. Numbers and types of affected hawkers, average daily incomes and any rent paid; iv. Numbers and types of affected structures (including common property and resources) and
replacement costs: and v. Any other Resettlement Impacts.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
7
The following Tables shows the status of RPs, identified APs and compensation payment status upto Jan-Jun 2017 of 16 DMAs.
ICB-02.7 DMA no. 601 Zone 6
DMA MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated During-Janu-
June,17 (BDT)
Remarks
601 6 Yes 15 15 - 32500 Work ongoing
ICB-02.7, DMA 602, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan-June 17 (BDT)
Remarks
602 6 Yes 02 02 5000 Work
completed ICB-02.7, DMA 603 Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan.-June. 17 (BDT)
Remarks
603 6 Yes 8 8 No 16500 Work
completed
ICB-02.7, DMA 604, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated During- Jan-
June 17 (BDT)
Remarks
604 6 Yes 16 16 - No 36500 Work completed
ICB-02.7, DMA 605, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated During- Jan-
June 17 (BDT)
Remarks
605 6 Yes 35 22 No 44200/- Under construction
ICB-02.7 DMA no. 606 Zone 6
DMA MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated During-Janu-
June,17 (BDT)
Remarks
606 6 Yes 47 47 - No 107750 Grievance (Appen iv)
ICB-02.7, DMA 607, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan-June 17 (BDT)
Remarks
607 6 Yes 08 08 - 14750 Work
completed
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
8
ICB-02.7, DMA 608 Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan.-June. 17 (BDT)
Remarks
608 6 Yes 9 9 No 18000 Under
construction
ICB-02.7, DMA 609, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compens
ated
Amount compensated earlier (BDT)
Amount compensated During- Jan-
June 17 (BDT)
Remarks
609 6 Yes 26 26 - no 62000 Under construction
ICB-02.7, DMA 610, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan-June
17 (BDT)
Remarks Not Paid
610 6 Yes 35 - -no Not yet done Construction work is not start
ICB-02.7 DMA no. 611 Zone 6
DMA MODS Zone
Submitted RP
Total Affected Person
Persons compensate
d
Amount compensated earlier (BDT)
Amount compensated During-Janu-
June,17 (BDT)
Remarks
611 6 Not yet done
Not yet done
no Not yet done Design not approved
ICB-02.7, DMA 612, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan-June 17 (BDT)
Remarks
612 6 Yes 8 8 19500 19500 Under
construction ICB-02.7, DMA 613 Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated
During- Jan.-June. 17 (BDT)
Remarks
613 6 Yes 22 22 No Not yet done RP docs
under process
ICB-02.7, DMA 614, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensat
ed earlier (BDT)
Amount compensated
During- Jan-June
17 (BDT)
Remarks
614 6 Not yet done
Not yet done
Not yet done
Not yet done
Not yet done Design is not approved
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
9
ICB-02.7, DMA 615, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated During- Jan-
June 17 (BDT)
Design is not approved
615 6 Not yet done
Not yet done
Not yet done
Not yet done Not yet done Design is not approved
ICB-02.7, DMA 616, Zone 6
DMA
MODS Zone
Submitted RP
Total Affected Person
Persons compensated
Amount compensated earlier (BDT)
Amount compensated During- Jan-
June 17 (BDT)
Remarks
616 6 Not yet done
Not yet done
Not yet done
Not yet done Not yet done Design is not approved
Identification of APs: APs will receive compensations for business and income losses, also assistance for relocation of their business cause by project implementation. NGO surveyed all roads of the respective DMAs where physical work will be implemented. They have assessed compensation amount for APs in roads which will be blocked temporarily for 4-5 days. In this period total 83 APs have been identified and among them 47 have been compensated.
7 Institutional Arrangement and Capacity
7.1 Institutional Arrangement
Dhaka Water Supply and Sewerage Authority (DWASA) is both for Executing Agency (EA) and Implementation Agency (IA) for implementation of the project. A Project Management Unit (PMU) has been established with a Safeguard Implementation Unit (SIU) with a staff of Social and Gender Development Officer. The SIU Social and Gender Development Officer assisted by the Resettlement Expert of MSC will oversee the implementation of involuntary resettlement safeguard work under the project with support of the resettlement NGO SAMAHAR. The other staff responsible for looking the safeguard issue of the project include: one Executive Engineers, two Assistant Engineers and two Sub-assistant Engineers. The Project Director and two Deputy Project Directors and one Senior Water Supply Engineer administer the overall activities;
Consultant (MSC): The Resettlement Expert and Social and Gender Expert are responsible for taking care of the Resettlement work of all pipeline rehabilitation contracts ICB 02.7. One Contract Management Expert, three Assistant Residential Engineers (ARE) and six Sub-Assistant Residential Engineers (SARE) working for supervision and quality control of physical construction/implementation work and also cooperate with the Resettlement team for Resettlement activities. The engaged NGO staff works in close cooperation with CME`s team and takes care to solve day to day problems of disturbed/ disrupted/affected people within the ongoing construction areas.
NGO; The Resettlement NGO consists of 9 members team is assigned for pipeline installation
rehabilitation contract/package 2.7. The NGO is responsible for ensuring all the required field
work and training associated with the resettlement work. The NGO is working in close
coordination with DWASA PMU for public awareness campaign to ensure dissemination of key
message that are Gender sensitive, in a format easily understood by resident of the project area,
possible implementation schedule, possible disruptions, Grievance Redress Procedure The
NGO will generate awareness about employment opportunity, entitlements, compensation etc.
The NGO assist DWASA and LIC to provide water connection through formation of CBO
(Community Based Organization).
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
10
The engineering design continues for implementation of pipeline, house connection & other civil works continued for the contracts ICB 2.7. During implementation, the NGO staff discussed the implementation issues with the local people, affected persons and various organizations including schools, mosques, kitchen markets, shopping malls or other important places where to the rickshaws, dependent women and children for ensuring their easy movement to the area during implementation of the project work.
Issues discussed/message disseminated: During time/ period of physical work execution in particular road, ensuring uninterrupted water supply/alternative supply for interrupted consumers, keeping road accessible/ensuring alternative traffic arrangement, disconnection oil legal connections, legalization of illegal connections and compensation payment to APs. A transparent, fair and effective complaint procedure has been established by the NGO to the potential APs and the concerned residents who may be affected by construction, through distributing leaflets and leaving contact cell phone number of Executive Engineer of PMU/PCU, Resettlement Expert of MSC, NGO officials and contractor`s assigned persons Site Engineers of Contractors office address etc.
7.2 Compensation and Rehabilitation:
Compensation payment to the all identified APs in the reporting period (Jan.- June 2017) has been made.
7.3 Disclosure and public consultation:
A series of public discussion and public disclosure meeting organize by NGO SAMAHAR, in DMA 605, 606, 607,608 and 610.The meeting details, signature sheet and photographs are attached in Appendix-III and IV.
7.4 Monitoring Results- Findings
Up to the reporting period, 11 RP have been submitted to the ADB. Total 160 APs have compensated till to June 2017. Out of them 22 are women and two of them are disabled. Out of total AP’s 9 APs have been paid under grievance from DMA 606. More four APs from DMA 609 and 605 have raised grievance about their income loss. In average 17% civil labour are being involved in civil works and they received payment as like as men. Total 9 public consultation meetings and 3 public disclosure meetings have been held within six months (Jan.-June, 2017, where 503 participants were present. Among them 171 (34%) were women.
7.5 Grievance Redress Mechanism (GRC)
Dhaka WASA has established GRC. During the reporting period (Jan.-June 2017) MSC received complain from 11 APs from DMA 606. A series of meetings were held on the spot. The GRC meeting was also held at DWASA office on 15.11.2016, (Minutes of the meeting enclosed in Appendix iv ). The NGO staff listed the name of APs and assessed their socio-economic condition. The GRC assessed the validity and identified 9 APs and determined Total amount of Tk. 2 6000 (twenty six thousand). The compensation has been paid to APs in January, 2017.
7.6 Compliance Status
Approval No Category
Sector Social Financial Economic Others Safeguard
ADB Loan No.3051 BAN
√ √ √ √ √ √
Note: Satisfactory – all covenants in the category are being completed.
8 Follow up Actions, Recommendations and Disclosure
The following actions need to be taken;
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
11
a. More intensive supervision of safeguard activities at the field level from the Dhaka WASA side.
9 Required Action to be Monitored and Reported During the Next Monitoring Report
In the next monitoring period the followings have to be monitored and reported:
a. RP preparation for all other DMAs where work will start
b. Ensuring compensation of APs before implementation of work
c. Obtaining approval of RPs from the ADB
d. Ensuring alternative water supply to the households where connection would be disrupted during
implementation by the contractor, and
e. Monitoring removal of excavated earth from the road.
f. Ensure contractor payment to the APs in time against grievance.
Payment Received by the Affected Persons (DMA-607, 605, 608 and 606) under Resettlement Works 1. ADB Loan No-3051 BAN (SF) 2. Name of Services: NGO for Resettlement in the Area of ICB 02.7 3. Name of NGO: Shamahar Information of Disclosure, Consultation and Participation
Public Consultation
Conducting public disclosure meetings at key stages have been done to inform the public regarding
the progress and future plans and to provide copies of Summary Resettlement Plans in Bangla.
During detailed design conducted Focus Group Discussions (FGD) together with the MSC
Resettlement Specialist with stakeholders and public meetings (large and small-scale) to discuss and
plan construction work with individual communities to reduce disturbance and other impacts and
provide a mechanism through which stakeholders can participate in project monitoring and
evaluation. Ensuring the views of women and vulnerable groups are equally represented in project
committees and other decision making bodies. Resettlement impact was assessed by conducting a
reconnaissance and house connection survey in all roads of DMA 605,607, 606,608 and 610. The
NGO SAMAHAR collected data on: numbers, types and ownership of affected shops and other
business; incomes, rent paid by tenants, and numbers of employees; numbers of types of affected
hawkers, average income and any rent paid; numbers of types of affected structures (including
common property resources) and replacement costs; any other resettlement impacts. Details of
consultation, the key issues raised and their incorporation in the project and resettlement plan is
presented in Appendixes III.
10 Appendixes i. List of Affected Persons and Entitlements
ii. List of Potentially affected person
iii. Public consultations details.
iv. Summary of minutes of disclosure meetings in each DMA with signature sheet
v. Photographs of the affected areas, consultation meetings, reconstruction activities,
etc.
vi. Copies of AP`s certification of payment (signed by the AP`s)
vii. Safeguards Compliance Monitoring Form & Checklist Safeguards Review Mission
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
12
Appendix-1
i. List of Affected Persons and Entitlements ( Jan-June 2017)
Sl. No.
Number of DMAs
Number of APs Compensated
Compensated Amount Remarks
1. 605 22 44200
2. 607 08 16500
3. 606 09 26000 Grievance
4. 608 08 18000
5 610 0 0 Not yet
distributed
Total 47 1,04,700
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
13
Appendix-2
ii. List of Potentially affected person
DMA 605
SL #
Name of AP Father’s / Mother’s Name Address Age Type of Business Average
Profit / Day
Proposed Day
Total Amount
(TK.)
1
Reba Late Abdul Goni Hawlader / Surja Banu
1156 West nandipara 55 Others (Tea Stall) 500.00 5 2500.00
2 Dipok Paran Krishna/Purnima 1870 West Nandipara 32 Shoe Repair 400.00 5 2000.00
3 Shafiqul Late Siraj Mia/Late Tahera Akter Shop- 08 Ramij Uddin Super Market Nandipara
53 Fruits & Vegetables 400.00 5 2000.00
4 Abul Kashem Late Abu Taher / Milon Begum Shop-01, Ramij Uddin Super Market Nandipara
34 Fruits & Vegetables 400.00 5 2000.00
5 Khokon Mia Late Abu Taher / Milon Begum Shop-05, Ramij Uddin Super Market Nandipara
37 Fruits & Vegetables 400.00 5 2000.00
6 Helal Intu Mia /Amina Khatun 1159 Nandipara Bazar 32 Fruits & Vegetables 400.00 5 2000.00
7 Ripon Tofazzal Hossain / Alea Begum 1144 Nandipara Bazar 31 Cloths 400.00 5 2000.00
8 Murad Tofazzal Hossain / Alea Begum 1159, Nandipara Bazar 20 Others (Cosmetics) 350.00 5 1750.00
9 Mahfuz Ahmed Yunus Mia / Ayesha Begum 1497/98 Nandipara Main Road 30 Fruits & Vegetables 450.00 5 2250.00
10 Md. Raju Mobarak Mollik / Momtaz Begum 1497/98 Nandipara Main Road 18 Fruits & Vegetables 400.00 5 2000.00
11 Noor Mohammad Chan M ia / Noorjahan 1497/98 Nandipara Main Road 28 Fruits & Vegetables 400.00 5 2000.00
12 Abdus Salam Late Fazar Ali / Late Shamorthaban Bibi
1497/98 Nandipara Main Road 48 Fruits & Vegetables 400.00 5 2000.00
13 Monir Hossain Late Suruj Mia / Noorjahan Begum 1499 Nandipara Main Road 38 Fruits & Vegetables 400.00 5 2000.00
14 Kali Bhuyan Late Babul Mia / Late Elma 1499 Nandipara Main Road 50 Fruits & Vegetables
400.00 5 2000.00
15 Jhunu Mia Late Kalam Mia / Late Tahazzatunnesa
1499 Nandipara Main Road 60 Fruits & Vegetables 400.00 5 2000.00
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
14
SL #
Name of AP Father’s / Mother’s Name Address Age Type of Business Average
Profit / Day
Proposed Day
Total Amount
(TK.)
16 Mofizuddin Late Abdul Malek / Late Tara Banu 1499 Nandipara Main Road 52 Fruits & Vegetables 400.00 5 2000.00
17 Kabir Hawlader Late Absus Sattar Hawlader / Lalmoti Begum
1497/98 Nandipara Main Road 48 Fruits & Vegetables 400.00 5 2000.00
18 Fazlul Haque Late Amzad Hossain / Late Ambia Khatun
1497/98 Nandipara Main Road 38 Fruits & Vegetables 400.00 5 2000.00
19 Nazrul Islam Late Ismail Mia / Sajeda Begum 1497/98 Nandipara Main Road 54 Fruits & Vegetables 400.00 5 2000.00
20 Anwar Hiossain Siddikur Rahman / Hosney Ara 1497/98 Nandipara Main Road 28 Fruits & Vegetables 450.00 5 2250.00
21 Rafique Aziz Mia / Rijia Begum 1497/98 Nandipara Main Road 20 Fruits & Vegetables 350.00 5 1750.00
22 Shahin Amir Hossain / Ferdousi Begum 1497/98 Nandipara Main Road 18 Fruits & Vegetables 350.00 5 1750.00
Total Amount: Forty Four Thousand Two Hundred Fifty Taka 44250.00
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
15
Appendix-2 List of Potentially affected person
DMA 607
SL #
Name of AP Father’s Name/Mother’s
Name Address Age
Type of Business
Average Profit/ Day
Proposed Day to
Compensate
Total Amount
(TK.)
1
Saheda Altaf Hossain / Mojitunnessa 77/3,Meradia Main Road, Meradia
38 Others(Tea stall) 400 5 Day’s 2000
2 Mithun Das Lolit Das / Anjona 60/GA, Meradia Main
Road, Meradia 20 Shoe Repair 400 5 Days 2000
3 Dulaly Begum Late Nagor kha / Late
Amironnessa 60/GA, Meradia Main Road, Meradia
48 Food 350 5 Days 1750
4 Md.Jahed Ali Late Abdul Jabbar / Surjo
Banu 54,Meradia Main Road, Meradia
55 Fruits & Vegetables
350 5 Days 1750
5 Romon Das Late Kali charan Das/ Late
Palori Rani 14,Grave Yard Road, Meradia
55 Shoe Repair 350 5 Days 1750
6 Rahima Begum
Yunus Howlader / Late Jobeda bebi
14,Grave Yard Road, Meradia
40 Food 350 5 Days 1750
7 Morjina Begum
Late Moinuddin / Late Jamiron
14,Grave Yard Road, Meradia
48 Food 350 5 Days 1750
8 Gopal Das Late Narandra Das/ Suro
Bala 179/1,Meradia Main Road, Meradia
58 Shoe Repair 400 5 Days 2000
Total 14750
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
16
Appendix-2 List of Potentially affected person ( Grievance)
DMA 606
SL #
Name of AP Father’s Name/Mother’s
Name Address Age
Type of Business
Average Profit/ Day
Proposed Day to
Compensate
Total Amount (TK.)
1. Liakat Ali Late, Abdur Razzak/Late Jurbanu Nessa
House# 193, Road#02, North Goran, Khilgoan, Dhaka
55 Others (Tea
Stall) 500 7 3500
2. Abdul Barek Late, Asor Ali/ Bahaton Begum
House# 193, Road#02, North Goran, Khilgoan, Dhaka
47 Other (Mobile
Phone) 500 7 3500
3. Abdur Rahaman Late, Sayod Ali/Late Badrunessa
House# 194, Road#02, North Goran, Khilgoan, Dhaka
58 Others
(Refrijar Repair)
500 7 3500
4. Md. Harun Late, Mojur Ali/Late Morusha Bibi
House# 146, Road#276, (Grave yard Road), South
Mothertek 38
Others (Tea Stall)
500 5 2500
5. Jakir Hossain Abdus Samad/Joibahar House# 146, Road#276,
(Grave yard Road), South Mothertek
35 Others (Tea
Stall) 500 6 3000
6. Md. Mithu Late, Kawsar Hossain/ Shaheda Begum
House# 152, Road#276, (Grave yard Road), South
Mothertek 25
Fruits & Vegetables
500 5 2500
7. Md. Faruq Late, Kolimuddin/ Abeda khtun
House# 146, Road#276, (Grave yard Road), South
Mothertek 50 Food 500 6 3000
8. Shuvo Late, Akkas Ali/ Aiesha Begum
House# 149, Road#276, (Grave yard Road), South
Mothertek 32
Others (Mobile Phone)
500 5 2500
9. Abdul Wahab Late, Tofizuddin/ Late, Sabeda Khatun
House# 149, Road#276, (Grave yard Road), South
Mothertek 55 Others (tailor) 500 4 2000
Total Taka 26000
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
17
Appendix-2 List of Potentially affected person
DMA 608
SL #
Name of AP Father’s / Mother’s Name Address Age Type of
Business
Average Profit /
Day
Proposed Day
Total Amount
(TK.)
1
Md. Kamal Hossain
Late Abdul Wahab/Johura Begum
Road # 7, Reazbag Khilgaon Dhaka
40 Shoe Repair 400.00 5 2000.00
2 Sumon Das Late Fholan Das / Late Jotsna Rani
Block # A, Road # 12/1 Tilpapara, Khilgaon, Dhaka
40 Shoe Repair 400.00 5 2000.00
3 Nirod Chandra Late Nihar Chandra / Late Binodini
Block # A, Road # 5, Tilpapara, Dhaka
66 Shoe Repair 400.00 5 2000.00
4 Md. Khorshed Alam
Late Abul Khair / Shabatunnesa
Lane # 1, Shantipur, Khilgaon, Dhaka
50 Others
( Tea Stall) 500.00 5 2500.00
5 Md. Nizam Mia Late Hashem Mia / Late Asia Begum
Lane # 1, Shantipur, Khilgaon, Dhaka
65 Fruits and Vegetables
500.00 5 2500.00
6 Nasima Begum Late Nasir Uddin / Joitun Nessa
Block # A, Road # 23/1, Khilgaon Chowrasta
38 Others
( Tea Stall) 500.00 5 2500.00
7 Nikhil Chandra Sarker
Late Roychand Sarker / Late Mukta Rani
Road # 5, North Goran Bazar Road
60 Others
( Tea Stall) 400.00 5 2000.00
8 Khodeza Begum Late Noor Mohammad / Late Asiron
Road # 5, 117 North Goran Bazar Road
55 Food 400.00 5 2000.00
9 Md. Mozibur Rahman
Late KaziKamar Uddin/ Late Nosifonnessa
Road # 5, 117 North Goran Bazar Road
50 Others
(Tea Stall) 500.00 5 2500.00
Total: Twenty Thousand Takas Only 20000.00
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
18
Appendix-2 List of Potentially affected person
DMA 610
SL
# Name of AP Father’s / Mother’s Name Address Age
Type of
Business
Average
Profit /
Day
Proposed
Day
Total
Amount
(TK)
1
Md. Akbor Hossain
Late Tofazzal Hossain / Nurunnessa
464/1, Ekramunessa School Road, West Rampura.
45 Others
(Teal Stall ) 500 5 2500.00
2 Md. Khokon Sheikh
Late Amin Uddin Sheikh / Late Sukurunnessa
464/3-2, East Oolan S.R-1, West Rampura.
66 cloth 500 5 2500.00
3 Md. Ali Hossain Late Alimuddin / L. Meherjan 464/3-2, East Oolan S.R-1, West Rampura.
60 Fruits &
Vegetables 500 5 2500.00
4 Md. Sobuj Mia Late Sunpor Ali / Late Jahura Kathun
161/4/1-B, East Oolan S.R-1, West Rampura.
52 Fruits &
Vegetables 400 5 2000.00
5 Md. Shahed Khan
Late Abdul Aziz Khan / Late Rezia Begum
161, East Oolan, S.R-1, West Rampura.
60 Fruits &
Vegetables 500 5 2500.00
6 Md. Mizan Abdus Satter / Marium
199/A,East Oolan S.R-17, West Rampura.
35 Fruits &
Vegetables 500 5 2500.00
7 Shailen Babu Late Polan Babu/ Neroda Bala
199/A, 12 no Road Oolan, West Rampura.
45 Shoe Repair 400 5 2000.00
8 Monwara Begum Late Matiur Rahman / Kirtica
191/B, Khaleda Para Goli, S.R #2, West Rampura.
60 Food 500 5 2500.00
9 Anukul Das Poresh Chandra Das /Late Shoshi Rani
20/1, Oolan Bazar Main Road, Rampura
27 Shoe Repair 400 5 2000.00
10 Banu Begum Late Karam Ali/Labia 20/1, Oolan Bazar Main Road, Rampura
45 Others
(Teal Stall ) 500 5 2500.00
11 Raj Kumar Late Fotik Chandra Das/ Santi Rani Das
2/6, Oolan Bazar Main Road, Rampura
40 Shoe Repair 400 5 2000.00
12 Mina Begum LateJahangir /Late Shindhu 314, Oolan Bazar Main Road, Rampura.
50 Food 500 5 2500.00
13 Bishnu Late Ramkanto /Late Bathashi
314, Oolan Bazar Main Road, Rampura.
40 Shoe Repair 400 5 2000.00
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
19
SL
# Name of AP Father’s / Mother’s Name Address Age
Type of
Business
Average
Profit /
Day
Proposed
Day
Total
Amount
(TK)
14 Abdur Rahim Latechandu Mia/Late Ayesha Kathun
314, Oolan Bazar Main Road, Rampura.
65 Others
(Teal Stall ) 500 5 2500.00
15 Sankor Das Chittya Ranjon Das/ Phulmoti 324, Oolan Bazar Main Road, Rampura.
57 Shoe Repair 400 5 2000.00
16 Suchitra Rani Late Mohendra Chandro Sheal /Late Bidubasene
192, Oolan Bazar Main Road, Rampura.
70 Fruits &
Vegetables 500 5 2500.00
17 Anowara Begum Late Hosen Baperi / Late Halima Begum
192, Oolan Bazar Main Road, Rampura.
45 Fruits &
Vegetables 500 5 2500.00
18 Md. Selim Mia Late Aroje Ali / Rabeya Begum.
283, Oolan Bazar Main Road, Rampura.
30 Fruits &
Vegetables 400 5 2000.00
19 Md. Harun Badsha
Abdus Salam / Samsun Nahar
334/2, Oolan Bazar Main Road, Rampura.
20 Fruits &
Vegetables 500 5 2500.00
20 Amena Begum LateMalek Munshi /Late Jaheda Begum
283, Oolan Bazar Main Road, Rampura.
45 Fruits &
Vegetables 500 5 2500.00
21 Abul Kashem
Late Abdul Goni/Golapi Begum
335, Oolan Bazar Main Road, Rampura.
34 Fruits &
Vegetables 400 5 2000.00
22 Md. Babul Akhter Late Mujibur Rahman/Late Fatema Begum
273, Oolan Bazar Main Road, Rampura.
45 Fruits &
Vegetables 500 5 2500.00
23 Shan Kumar Promod Kumar/Late Promila 240, WAPDA Main Road, Rampura.
35 Shoe Repair 400 5 2000.00
24 Salam Late Kamal/Mabia Khatun 240, WAPDA Main Road, Rampura.
40 Others
(Teal Stall ) 500 5 2500.00
25 Fazal Sarder
Late Gafur Ali /Reshma bibi 170, WAPDA Main Road, Rampura.
65 Others
(Bi Cycle Repair )
500 5 2500.00
26 Rup Kumar
Late Shuk Dev /Late Muroli 138, WAPDA Main Road, Rampura.
50 Shoe Repair 500 5 2500.00
27 Rasheda Begum Late Khorshed Alam/Tara Banu
138, WAPDA Main Road, Rampura.
35 Others
(Teal Stall ) 500 5 2500.00
28 Halima Begum
Late Ismail Bepari /Late Johura Begum
138, WAPDA Main Road, Rampura.
50 Others
(Teal Stall ) 500 5 2500.00
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
20
SL
# Name of AP Father’s / Mother’s Name Address Age
Type of
Business
Average
Profit /
Day
Proposed
Day
Total
Amount
(TK)
29 Khokon
Shaheb Ali /Komola Begum 140, WAPDA Main Road, Rampura.
45 Fruits &
Vegetables 400 5 2000.00
30 Gopal
Late Narayan /Late Jogomaya
167, WAPDA Main Road, Rampura.
70 Shoe Repair 500 5 2500.00
31 Shafiqul Islam
Sajahan/Hajera Begum 167, WAPDA Main Road, Rampura.
27 Others
(Teal Stall ) 500 5 2500.00
32 Shopon Das
Khitis Das /usha Rani 149, WAPDA Main Road, Rampura.
40 Shoe Repair 400 5 2000.00
33 Rasel
Faruq Patwari /Fatema Begum
220, WAPDA Main Road, Rampura.
26 Others
(Teal Stall ) 500 5 2500.00
34 Nipen Chandra Das
Gopal Chadra Das/Shova Rani
H-01, Mohanagar Project Main Road
40 Shoe Repair 400 5 2000.00
35 Jiban Anu Chandra/ Sulekha Rani H-01, B#C ,R#7, Mohanagar Project
27 Shoe Repair 400 5 2000.00
Total Affected Person 35 Total Amount 81000.00
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
21
iii. Public Consultation Details
Appendixes -03 DMA 605
SL No
Address Participants Type Purpose of Consultation Key Issue Discussed Interrogation on Design &
Resettlement Plan
1 Nasirabad Union Parishad
UP Chairman with Members, House Owners, MSC Representative, Local Elites, Local Leader, Contractors & NGO Personnel etc.
Project Information Dissemination; Support Seeking from UP bodies and Construction Work Procedure & Ready to get House Connection.
Project Description, Support seeking for contractors and keeping ready by showing house connection papers, Environmental and Social Safeguard Issues.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
2
Dhaka Metropolitan Residential College, Nandipara
Teachers, Retired Govt. Officials, House Owner’s, Guardians, MSC & WASA Representatives, Contractors Personnel NGO Personnel etc.
Awareness Rising, Information Dissemination, Problem Solving, Conflict management, Support seeking for the Contractor.
Awareness Rising Indicator’s, Grievance Raising Procedure, House Connection Process and problem solution process for Contractors Support.
Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion
3 Trimohiinee Adarsha High School
Teachers, Officials, House Owner’s, Guardians, WASA Representative, MSC Representative, Contractors Personnel and NGO Personnel etc.
Support Contractors, Managing Water Crisis, Gender Issues and Environmental and Safeguard Issues etc.
Project Implementation procedure and House service Connection & Pipe line Distribution issues, Environmental Issues and safeguard compliance.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
4 Dakkhingaon Union Parishad
UP Chairman with Members, House Owners, businessman, Retired Govt. Officials, MSC Representative, Local Elites, Local Leader, Contractors & NGO Personnel etc.
Resettlement Plan disclosing Project Information Dissemination, Support Seeking for construction work, Grievance Redressing, Road Repair & maintenance and compensation for AP.
Background of the Project, Resettlement Plan, Entitlement, Institutional Arrangement, Grievance Redress Mechanism, Open Discussion and Support Seeking Areas.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
22
Appendix – 03 Public Consultation Details
DMA-607
SL No
Address Participants Type Purpose of Consultation Key Issue Discussed Interrogation on Design &
Resettlement Plan
1 Sunlit Public Ideal School & College
Teachers, Officials, House Owners, Guardians, MSC Representative Contractors Personnel & NGO Personnel etc.
Importance of Project, Problem, Project New System, Meter Changing, Construction Duration. Support from Users
Project Description, Support from the Community to contractors and keeping ready of the house connection papers.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
2
Green Bird Basic Education and High School
Teachers, Officials, House Owner, Guardians, Retired Officials, Contractors Personnel, NGO Personnel etc.
Importance and Objective of the Project, Cutting Method, Meter Change, Advantage of new Supply Line and Support from Users
Awareness Rising Indicator’s, Grievance Raising Procedure, GRC formation Process and problem solution process
Implementation arrangement
and Grievance Redress
Mechanism incorporated in the
RP based on the discussion
3 Merit Model-e School & College
Teachers, Officials, House Owner’s, Guardians, Contractors Personnel and NGO Personnel etc.
Support Contractors, Objective and Importance of the Project, Construction Duration, Road Cutting method, Gender Issues and Environmental and Safeguard Issues etc.
Project Implementation procedure and HH Connection & Pipe line Distribution issues, Environmental Issues and safeguard compliance.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
4 Ward Counselor’s Office
House Owner’s, Govt. Officials, Businessmen, Local Elites, Civil Society Personnel, Contractors Personnel, MSC and the NGO Representatives.
Resettlement Plan Disclosing Project Information Dissemination, Support Seeking for construction work, Grievance Redressing, Road Repair & maintenance and compensation for AP.
Background of the Project, Resettlement Plan, Entitlement, Institutional Arrangement, Grievance Redress Mechanism, Open Discussion and Support Seeking Areas.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
23
Appendix 03 Public Consultation Details
DMA 606
Date No. of participants
and Address Participants Type
Purpose of Consultation
Key Issue Discussed Interrogation on Design & Resettlement Plan
1
Participants: 45,
Abdul Aziz School &
College Mothertek
Teacher’s and Residents of
DMA-606
Information
Dissemination and
Awareness Rising
Water Related Information,
Road Cutting Methods, Pipe
Installation Process etc.
Entitlement of APs; Implementation
arrangement and Grievance Redress
Mechanism incorporated in the RP based on
the discussion.
2
Participants: 24,
Ward Councilor’s
Office;
479 Mid Mothertek,
South Goran
Residents of the Area,
Social & Political Leader’s,
Ward Councilor and the
Local People
Awareness Rising,
Information
Dissemination and
Problem Solving
Awareness Raising on work
Procedure, Support seeking
and problem solution process
Entitlement of APs; Implementation
arrangement and Grievance Redress
Mechanism incorporated in the RP based on
the discussion.
3
Participants: 24,
Ward Councilor’s
Office;
41 Mid Mothertek,
Basabo, Sabujbag
Residents of the Area,
Social Leader’s, Ward
Councilor and the Local
People
Project Information
Disclosure Meeting
Importance of the Project,
Implementation Strategy and
HH Connection & Pipe line
Distribution.
Implementation arrangement and Grievance
Redress Mechanism incorporated in the RP
based on the discussion
Entitlement of APs; Implementation
arrangement and Grievance Redress
Mechanism incorporated in the RP based on
the discussion
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
24
Appendix – 03 Public Consultation Details
DMA 608
SL No
Address Participants Type Purpose of Consultation Key Issue Discussed
Interrogation on Design &
Resettlement Plan
1 Shantipur High School
Teachers, House Owners, MSC & WASA Representative, Local Elites, Local Leader, Contractors & NGO Personnel etc.
Project Information Dissemination; Support Seeking from UP bodies and Construction Work Procedure & Ready to get House Connection.
Project Description, Support
seeking for contractors and
keeping ready by showing
house connection papers,
Environmental and Social
Safeguard Issues.
Entitlement of APs; Implementation
arrangement and Grievance
Redress Mechanism incorporated in
the RP based on the discussion.
2 Model High School Khilgaon
Teachers, Retired Govt. Officials, House Owner’s, Guardians, MSC & WASA Representatives, Contractors Personnel NGO Personnel etc.
Awareness Rising, Information Dissemination, Problem Solving, Conflict management, Support seeking for the Contractor.
Awareness Rising Indicator’s,
Grievance Raising Procedure,
House Connection Process
and problem solution process
for Contractors Support.
Implementation arrangement and
Grievance Redress Mechanism
incorporated in the RP based on
the discussion.
3 Cambridge Model School & College
Teachers, Officials, House Owner’s, Guardians, WASA Representative, MSC Representative, Contractors Personnel and NGO Personnel etc.
Support Contractors, Managing Water Crisis, Gender Issues and Environmental and Safeguard Issues etc.
Project Implementation
procedure and HH Connection
& Pipe line Distribution issues,
Environmental Issues and
safeguard compliance.
Entitlement of APs; Implementation
arrangement and Grievance
Redress Mechanism incorporated in
the RP based on the discussion.
4 Pre Cadet Institute & High School
Teachers, Guardians, House Owners, businessman, Retired Govt. Officials, MSC & WASA Representative, Local Elites, Local Leader, Contractors & NGO Personnel etc.
Resettlement Plan disclosing Project Information Dissemination, Support Seeking for construction work, Grievance Redressing, Road Repair & maintenance and compensation for AP.
Background of the Project,
Resettlement Plan,
Entitlement, Institutional
Arrangement, Grievance
Redress Mechanism, Open
Discussion and Support
Seeking Areas.
Entitlement of APs; Implementation
arrangement and Grievance
Redress Mechanism incorporated in
the RP based on the discussion.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
25
Appendix – 03 Public Consultation Details
DMA 610 SL No
Address Participants Type Purpose of Consultation Key Issue Discussed Interrogation on Design &
Resettlement Plan
1 Quality Learners High School
Teachers, House Owners, MSC & WASA Representative, Local Elites, Local Leader, Contractors & NGO Personnel etc.
Project Information Dissemination; Support Seeking from UP bodies and Construction Work Procedure & Ready to get House Connection.
Project Description, Support seeking for contractors and keeping ready by showing house connection papers, Environmental and Social Safeguard Issues.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
2 Motherland School & College
Teachers, Retired Govt. Officials, House Owner’s, Guardians, MSC & WASA Representatives, Contractors Personnel NGO Personnel etc.
Awareness Rising, Information Dissemination, Problem Solving, Conflict management, Support seeking for the Contractor.
Awareness Rising Indicator’s, Grievance Raising Procedure, House Connection Process and problem solution process for Contractors Support.
Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion
3
Rampura Ekramunnesa Boys High School
Teachers, Officials, House Owner’s, Guardians, WASA Representative, MSC Representative, Contractors Personnel and NGO Personnel etc.
Support Contractors, Managing Water Crisis, Gender Issues and Environmental and Safeguard Issues etc.
Project Implementation procedure and HH Connection & Pipe line Distribution issues, Environmental Issues and safeguard compliance.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
4
Mohanagar Abashik Samaj Kallyan Samitee
House Owners, businessman, Retired Govt. Officials, MSC & WASA Representative, Local Elites, Local Leader, Contractors & NGO Personnel etc.
Resettlement Plan disclosing Project Information Dissemination, Support Seeking for construction work, Grievance Redressing, Road Repair & mainten ance and compensation for AP.
Background of the Project, Resettlement Plan, Entitlement, Institutional Arrangement, Grievance Redress Mechanism, Open Discussion and Support Seeking Areas.
Entitlement of APs; Implementation arrangement and Grievance Redress Mechanism incorporated in the RP based on the discussion.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
26
Appendix –4
iv. Summary of minutes of disclosure meetings in each DMA with signature sheet
Dhaka Environmentally Sustainable Water Supply (DESWSP)
Resettlement Intervention in the area of ICB-02.7
DM A – 605
Project Information Disclosure M eeting
Venue: Dakkhingaon Union Parishad Time: 11.00 am Introduction: A Project Information Disclosure Meeting the prime activity of the DESWS project held at Dakkhingaon Union Parishad on 08/02/2017 in the DMA – 605. House Owner’s, Govt. Officials, Businessmen, Union Parishad Member’s, Local Elites, Civil Society Personnel, Contractors Personnel, PMU & MSC representatives and the NGO Representatives were present in the Meeting. Agenda
1. Sharing on Project Information.
2. Discussion on activities for DMA System, Question and Answer.
3. Opinion of the participants
4. AOB
1. Sharing on Information:
a) Background: Dhaka, the capital of Bangladesh is facing shortage of water supply and demand is increasing day by day. Dhaka WASA is preparing Dhaka Environmentally Sustainable Water Supply Project (DESWSP) to supply treated surface water, collected from the river Meghna, to Dhaka city dwellers through the construction of Gandharbpur Water Treatment Plant Project (GWTPP). The project also includes distribution reinforcement and network improvements to reduce non-revenue water (NRW for safe water and support to low income communities (LICs). With financial assistance from ADB, AFD and EIB, this project aims to reduce abstraction of ground water amounting 150 million liter per day (MLM).
b) Resettlement Plan, Policy and Principals: A Resettlement Plan (RP) has been prepared for the project based on ADB’s Safeguard Policy Statement 2009 and Government of Bangladesh (GOB) Acquisition and Requisition of Immovable Property Ordinance 1982 (APIRO).
c) Entitlement: The project provides for compensation of all potential losses including potential income losses for vendors at replacement value. As required by ADB Safeguards Policy (2009) the project will provide compensation and resettlement assistance for households’ lost land, business, structures and other lost assets in connection with the project. The RP approach incorporates (i) compensation for lost assets; (ii) resettlement issues; (iii) impact mitigation with special attention to the women and vulnerable groups; and (iv) income generating support to the members of the physically displaced households and including them in the poverty reduction and livelihood enhancement program.
d) Institutional Arrangement: DWASA has established, for the Project, a PMU headed by a PD, who will be responsible for the overall execution of the Project. The PMU will be supported with an experienced NGO for the implementation of resettlement activities which include livelihood rehabilitation. DWASA will implement the RP through setting a Safeguard Implementation (SIU) headed by DPD at the DESWSP PMU. The SIU, under the overall responsibility of the PD, will undertake day-to-day activities with the appointed NGO. The concerned Safeguards Officer at the level of AE of SIU, appointed by PIU will be convener of the JVC and PVAC. The DPD of SIU will perform as convener of GRC and RAC. The resettlement assistance NGO will assist APs to put forth grievances and access information on opportunities for employment in project related activities, rights and entitlements and the grievance redress process, and make informed choices.
e) Grievance Redress Mechanism: To resolve all project related grievance and complaints a common social and environmental grievance redress mechanism is in place. Common and simple grievances will be sorted out at project site level by the Contractor’s Resettlement Supervisor, supervision staff of PMU and project NGO within 7 days. More serious complaints will be sent to the safeguard officer at the PMU to be resolved in 14 days. Any unresolved grievances will be forwarded to the Grievance Redress Committee GRC. Complaints and grievances which are not addressed by Grievance Redress committee (GRC) within 30 days will be sent to the Program
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
27
Steering Committee (SC) to be resolved within 7 days. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage.
2. Discussion on activities for DMA System, Question and Answer: DMA – 5 is another critical
area of DMA system. Because of - this is the area where both Urban and Rural area exist here. There’s only one main road. Most Roads are semi pacca or Kancha. Mostly under developed area and mixed people are living with mixed culture of Poor & Rich. In this meeting major discussion s were question and answer. The NGO representative seeks support from the community people and the local leaders to solve all kinds of problem if any arose. The audience responded that the project personnel should also to take quick action resolving casualties. The followings are the concise of the discussion; FSL Representative: Engineer Rubel Hossain delivered his speech by briefing the construction procedure concisely about Road Cutting Method, Backfilling, House connection and other pros and corn of the construction work. He addressed some key points; a) Keeping Sufficient Pressure round the clock with Adequate Water Supply. b) Reducing water losses from 40% to 15% c) Establishing Spaghetti Chamber for distance houses d) Locate Meters 2 feet down from the floor e) Illegal Connections would not be existed. f) Broken, Nonfunctional and Older meters will be replaced by a newer one. g) All costs will be borne by the Project. h) Executing Construction works mostly open cut. i) Ensure water supply during construction by using DWASA water tank. j) Establishing a complain center.
Social Safeguard officer PMU: Mr. Tofazzal Hossain SG Officer raises some issues on social and environmental aspect. He informed the followings; Executing works with the HDD machine, sound pollution could be caused children, patients and old ages people and you should be careful about it. a) Soil dust will be produced in the construction site and you should monitor to remove the
wastage soil immediately after the trench cut. b) Contractors should arrange way to easy access for the people entering into the houses. c) Ensure safeguard compliance. MSC Representative: MSC Representative informed the followings; a) Ensuring Compensation for the vendors/hawkers if affected. b) Ensure compensation for the affected people if Grievance raised c) Ensure Female Participation of the labor involved. Question and Answer: NGO Representative seeks support from the house owner for message dissemination and awareness rising campaign during pre construction period, construction period and during commissioning. After the briefing session the representative of the Union parishad and the participants raised the following questions; a) How much time water supply interrupted during Construction? b) Who will be responsible to repair the roads? c) In some cases there are some differences of pipe diameter in the demand note and billing
papers – the question is which diameter will be accepted? d) How the bills of old and new meter be adjusted? e) How much time to take getting a new connection? f) After completion of the construction work if any problem arose then how it will be solved?
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
28
The technical persons of the meeting like SAE, SGO DWASA and Contractor Personnel replied the questions as follows; a) Water Supply will not stop during construction work. After completion of the construction works
both new and old pipeline will be under operation up to 7 seven days and when all house connection will be established the old connection will be stopped.
b) We compensate the right authority of the roads before starting the construction works will be responsible repairing the roads like City Corporation or LGED.
c) Surely the diameter written in the demand note will be ensured establishing house connection. If anybody missed the demand note then he/she must collect the duplicate copies from the MOD’s Zone – 6.
d) Existing bill of old meter and running bill of new meter will be adjusted and in this cases it will be happened in presence of 5 responsible persons of Contractor and WASA.
e) This will take hardly within 3 (Three) working days. f) Dhaka WASA is the sole responsible solving any problem but if the problem occurred within
one year the contractor people will solve the problem because they must stay in the field one year after the completion of the construction work.
3. Opinion of the participants: The participants were asked to show their interest and opinion from new
system of the project. Most of the participants informed that the area is much more troublesome than that of other area because this not fully rural or urban area. The new system is much better than that of the previous system we heard in this meeting. We have suffered with water crisis in this area from the very beginning. If the matter is true then it will be a dream for us. Most of the households erected building here unplanned way and very difficult having access to available water supply system. We are hopeful to have access to nonstop water supply system fulfilling our dream. The Chairman of this Union Parishad welcomed the Project Authority to establish this type of modern water supply system in his jurisdiction. He also called the residents of the area to come forward in support of the project.
4. AOB: As there was no more issue to discuss, the meeting closed with vote of thanks.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
31
Appendix –04 Project Information Disclosure Meeting
DMA – 608
Venue: Pre Cadet Institute & High School Time: 11.00 am Introduction: On 09/04/2017 A Project Information Disclosure Meeting held at Pre Cadet Institute & High School premises of DESWS project of DWASA in DMA-608. House Owner’s, Govt. Officials, Businessmen, Teachers, Guardians of the Student, Local Elites, Civil Society Personnel, Contractors Personnel, PMU & MSC representatives and NGO Representatives were present in the Meeting. Agenda
1. Sharing on Project Information. 2. Discussion on activities for DMA System, Question and Answer. 3. Opinion of the participants 4. AOB
1. Sharing on Information:
a) Background: Dhaka, the capital of Bangladesh is facing shortage of water supply and demand is increasing day by day. Dhaka WASA is preparing Dhaka Environmentally Sustainable Water Supply Project (DESWSP) to supply treated surface water, collected from the river Meghna, to Dhaka city dwellers through the construction of Gandharbpur Water Treatment Plant Project (GWTPP). The project also includes distribution reinforcement and network improvements to reduce non-revenue water (NRW for safe water and support to low income communities (LICs). With financial assistance from ADB, AFD and EIB, this project aims to reduce abstraction of ground water amounting 150 million liter per day (MLM).
b) Resettlement Plan, Policy and Principals: A Resettlement Plan (RP) has been prepared for the project based on ADB’s Safeguard Policy Statement 2009 and Government of Bangladesh (GOB) Acquisition and Requisition of Immovable Property Ordinance 1982 (APIRO).
c) Entitlement: The project provides for compensation of all potential losses including potential income losses for vendors at replacement value. As required by ADB Safeguards Policy (2009) the project will provide compensation and resettlement assistance for households’ lost land, business, structures and other lost assets in connection with the project. The RP approach incorporates (i) compensation for lost assets; (ii) resettlement issues; (iii) impact mitigation with special attention to the women and vulnerable groups; and (iv) income generating support to the members of the physically displaced households and including them in the poverty reduction and livelihood enhancement program.
d) Institutional Arrangement: DWASA has established, for the Project, a PMU headed by a PD, who will be responsible for the overall execution of the Project. The PMU will be supported with an experienced NGO for the implementation of resettlement activities which include livelihood rehabilitation. DWASA will implement the RP through setting a Safeguard Implementation (SIU) headed by DPD at the DESWSP PMU. The SIU, under the overall responsibility of the PD, will undertake day-to-day activities with the appointed NGO. The concerned Safeguards Officer at the level of AE of SIU, appointed by PIU will be convener of the JVC and PVAC. The DPD of SIU will perform as convener of GRC and RAC. The resettlement assistance NGO will assist APs to put forth grievances and access information on opportunities for employment in project related activities, rights and entitlements and the grievance redress process, and make informed choices.
f) Grievance Redress Mechanism: To resolve all project related grievance and complaints a
common social and environmental grievance redress mechanism is in place. Common and simple grievances will be sorted out at project site level by the Contractor’s Resettlement Supervisor, supervision staff of PMU and project NGO within 7 days. More serious complaints will be sent to the safeguard officer at the PMU to be resolved in 14 days. Any unresolved grievances will be forwarded to the Grievance Redress Committee GRC. Complaints and grievances which are not addressed by Grievance Redress committee (GRC) within 30 days will be sent to the Program Steering Committee (SC) to be resolved within 7 days. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
32
2. Discussion on activities for DMA System, Question and Answer: DMA-8 is one of the most crowded and busiest areas of DMA system. This is the area where both Residential and Commercial Buildings exist there. Most Roads are well constructed, wider and all kinds of vehicle run here. All major roads are planned for applying HDD method except some narrow roads. In this meeting major discussions were question and answer. The NGO representative seeks support from the community people and the local leaders to solve all kinds of problem if any arose. The audience responded that the project personnel should also to take quick action resolving casualties. The followings are the concise of the discussion;
FSL Representative:
Engineer Kawser Hossain of RCL Construction Ltd. delivered his speech by briefing the construction procedure concisely about Road Cutting Method, Backfilling, House connection and other pros and corn of the construction work. He addressed some key points;
a) Road Cutting Methods are HDD, OT and PB. b) HDEP (High Density Poly-phenyl) will be used. c) During House Connection CP (Connection Permission) & Last Billing Papers showing is a must. d) 24 Hour Sufficient Pressure with Adequate Water Supply will be kept. e) Water losses will be reduced from 40% to 15% f) No Illegal Connections would be existed. g) Broken, Nonfunctional, Older & Lost meters will be replaced by a newer one. h) All costs will be borne by the Project.
Social Safeguard officer Environment from PMU:
Mr. Sydur Rahman SG Officer Environment raises some issues on social and environmental aspect. He informed the followings…
a) During Construction Works with the HDD machine, sound pollution should control by the
Contractors as it were it couldn’t cause children, patients and old ages people should be kept it in
mind.
b) Soil dust will be produced in the construction site and Contractor should remove the wastage soil
immediately after the trench cut.
c) Contractors should arrange way to easy access for the people entering into the houses.
d) Ensure safeguard compliance.
e) No compromise of sand filling before laying the pipe.
MSC Representative:
MSC Representative informed the followings;
a) Awareness Rising conducted by the NGO to all corners of the DMA.
b) Affected Person selected for the compensation payment for the vendors/hawkers.
c) Contractor should ready for the affected people if Grievance raised
d) Ensure Female Participation of the labor involved.
Question and Answer:
NGO Representative seeks support from the house owner for message dissemination and awareness rising campaign during pre construction period, construction period and during commissioning. After the briefing session the representatives from the Community raised the following questions;
a) What will happen if the water meter stolen?
b) Is there any opportunities changing pipe installation direction in the road.
c) How much pressure existed in the pipeline after completion of the construction works?
d) Who will be responsible to repair the roads?
e) When we will have water in the new pipe line?
f) How much time to take getting a new connection?
g) When the construction works will be started and ended?
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
33
The technical persons of the meeting like SAE, SGO DWASA and Contractor Personnel replied the questions as follows;
a) The user must place a GD at the local police station. By showing this GD paper, a new meter will
be replaced without any cost. b) It will be depended on the situation of the road condition. c) Keeping 1 bar pressure is planned but it will be ensured when the treatment plan started. d) There are authorities like LGED, City Corporation and Roads & Highway to repair the Roads. e) After the completion of the commissioning, stopping water supply through the old pipeline. f) It is maximum 1 (One) week. g) It will be started very soon and will be continued up to three months.
3. Opinion of the participants: The participants were asked to show their interest and opinion from new
system of the project. Most of the participants informed that the area is much more crowded and busiest than that of other area because this fully urban area and there are people of residential and commercial. There are Households, Hotels, Institutions, Factories and many other water users here. The new system is much better than that of the previous system we heard in this meeting. We have suffered with water crisis in this area from the very beginning. We haven’t had sufficient and safe water during day time. In the midnight usually we get water though it is not qualitative. Mostly we get water from WASA is dirty; odor and polluted water. We are bound to use the dirty water because we haven’t alternative water sources of safe water. If the project is better than that of previous water then it will ensure our betterment. We are hopeful to have access to nonstop water supply system fulfilling our demand of safe water. Most of the representatives of the meeting appreciated this initiative and welcomed the Project Authority to establish this type of modern water supply system in this area. They also give commitment to the project authority for their all out assistance & support for the successful implementation of the construction works.
4. AOB: As there was no more issue to discuss, the meeting closed with vote of thanks.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
36
Appendix –4 Project Information Disclosure Meeting
DMA – 610
Venue: Mohanagar Abashik Samaj Kallyan Samittee Time: 02.00 pm Introduction: On 18/06/2017 A Project Information Disclosure Meeting held at Mohanagar Abashik Samaj Kallyan Samitte of DESWS project of DWASA in DMA-610. House Owner’s, Govt. Officials, Businessmen, Local Elites, Civil Society Personnel, Contractors Personnel, PMU & MSC representatives and NGO Representatives were present in the Meeting.
Agenda
1. Sharing on Project Information. 2. Discussion on activities for DMA System, Question and Answer. 3. Opinion of the participants 4. AOB
1. Sharing on Information:
a) Background: Dhaka, the capital of Bangladesh is facing shortage of water supply and demand is increasing day by day. Dhaka WASA is preparing Dhaka Environmentally Sustainable Water Supply Project (DESWSP) to supply treated surface water, collected from the river Meghna, to Dhaka city dwellers through the construction of Gandharbpur Water Treatment Plant Project (GWTPP). The project also includes distribution reinforcement and network improvements to reduce non-revenue water (NRW for safe water and support to low income communities (LICs). With financial assistance from ADB, AFD and EIB, this project aims to reduce abstraction of ground water amounting 150 million liter per day (MLM).
b) Resettlement Plan, Policy and Principals: A Resettlement Plan (RP) has been prepared for the project based on ADB’s Safeguard Policy Statement 2009 and Government of Bangladesh (GOB) Acquisition and Requisition of Immovable Property Ordinance 1982 (APIRO).
c) Entitlement: The project provides for compensation of all potential losses including potential income losses for vendors at replacement value. As required by ADB Safeguards Policy (2009) the project will provide compensation and resettlement assistance for households’ lost land, business, structures and other lost assets in connection with the project. The RP approach incorporates (i) compensation for lost assets; (ii) resettlement issues; (iii) impact mitigation with special attention to the women and vulnerable groups; and (iv) income generating support to the members of the physically displaced households and including them in the poverty reduction and livelihood enhancement program.
d) Institutional Arrangement: DWASA has established, for the Project, a PMU headed by a PD, who will be responsible for the overall execution of the Project. The PMU will be supported with an experienced NGO for the implementation of resettlement activities which include livelihood rehabilitation. DWASA will implement the RP through setting a Safeguard Implementation (SIU) headed by DPD at the DESWSP PMU. The SIU, under the overall responsibility of the PD, will undertake day-to-day activities with the appointed NGO. The concerned Safeguards Officer at the level of AE of SIU, appointed by PIU will be convener of the JVC and PVAC. The DPD of SIU will perform as convener of GRC and RAC. The resettlement assistance NGO will assist APs to put forth grievances and access information on opportunities for employment in project related activities, rights and entitlements and the grievance redress process, and make informed choices.
e) Grievance Redress Mechanism: To resolve all project related grievance and complaints a common social and environmental grievance redress mechanism is in place. Common and simple grievances will be sorted out at project site level by the Contractor’s Resettlement Supervisor, supervision staff of PMU and project NGO within 7 days. More serious complaints will be sent to the safeguard officer at the PMU to be resolved in 14 days. Any unresolved grievances will be forwarded to the Grievance Redress Committee GRC. Complaints and grievances which are not addressed by Grievance Redress committee (GRC) within 30 days will be sent to the Program Steering Committee (SC) to be resolved within 7 days. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
37
2. Discussion on activities for DMA System, Question and Answer: DMA-610 is the DMA of mixed Residential and commercial area. This is the area where both Residential and Commercial Buildings exist there. Most Roads are well constructed but narrow. All major roads are planned for applying HDD method except the narrow roads. In this meeting major discussions were question and answer. The NGO representative seeks support from the community people and the local leaders to solve all kinds of problem if any arose. The audience responded that the project personnel should also to take quick action resolving casualties. The followings are the concise of the discussion;
FSL Representative: Engineer Kawser Hossain of RCL Construction Ltd. delivered his speech by briefing the construction procedure concisely about Road Cutting Method, Backfilling, House connection and other pros and corn of the construction work. He addressed some key points;
a) Road Cutting Methods are HDD, OT and PB. b) HDEP (High Density Poly-phenyl) will be used. c) During House Connection CP (Connection Permission) & Last Billing Papers showing is a must. d) 24 Hour Sufficient Pressure with Adequate Water Supply will be kept. e) Water losses will be reduced from 40% to 15% f) No Illegal Connections would be existed. g) Broken, Nonfunctional, Older & Lost meters will be replaced by a newer one. h) All costs will be borne by the Project.
Social Safeguard officer Environment from PMU:
Mr. Tofazzal Hossain SG Officer Social and Safeguard raises some issues of social and also environmental issues. He informed the followings…
a) Wastage soil must be removed by the contractor within 24 hours. If not you are requested to
contact with us. b) There should enclosure where the road has been cut. c) During Construction Works with the HDD machine, sound pollution should control by the
Contractors as it were it couldn’t cause children, patients and old ages people should be kept it in mind.
d) Soil dust will be produced in the construction site and Contractor should remove the wastage soil immediately after the trench cut.
e) Contractors should arrange way to easy access for the people entering into the houses.
MSC Representative: MSC Representative informed the followings;
a) The old supply line would not be closed until the new connection established. b) Awareness Rising conducted by the NGO to all corners of the DMA. c) Affected Person selected for the compensation payment for the vendors/hawkers. d) Contractor should ready for the affected people if Grievance raised e) Ensure Female Participation of the labor involved.
Question and Answer: NGO Representative seeks support from the house owner for message dissemination and awareness rising campaign during pre construction period, construction period and during commissioning. After the briefing session the representatives from the Community raised the following questions;
a) What is DMA and how it works? b) How water pressure kept at tolerance limit if water supply not increased? c) Who will be responsible to repair the roads? d) How the illegal water user will have valid connection? e) When the construction works will be started and ended? The technical persons of the meeting like SAE, SGO DWASA and Contractor Personnel replied the questions as follows;
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
38
a) The DMA is a certain area measured by the authority where 3-5 water pumps supplies
adequate water for that particular area. b) There are 40% water losses in the existing system and also illegal users. If water supply not
increases yet the pressure will be kept by those 40% water of the system lost. c) It depends on the authority of the roads. Generally those are either Roads & Highway or City
Corporation. d) Anybody can apply for the new connection and DWASA will ensure it during construction
works. e) It will be started very soon and will be continued up to three months.
3. Opinion of the participants: The participants were asked to show their interest and opinion from
new system of the project. Most of the participants informed that the area is much more crowded
and busiest than that of other area because this fully urban area and there are people of
residential and commercial. There are Households, Hotels, Institutions, Factories and many other
water users here. The new system is much better than that of the previous system we heard in this
meeting. Most of the representatives of the meeting appreciated this initiative but they raised their
concern of their previous bitter experience of severe water crisis. Some of them proposed to have
a copy of the detailed design and they will throw their opinion if there need any change. They
urged that if the authority considers the claim the bills of sewerage and water bill separately. They
welcomed the Project Authority to establish this type of modern water supply system in this area.
They also give commitment to the project authority for their all out assistance & support for the
successful implementation of the construction works.
4. AOB: As there was no more issue to discuss, the meeting closed with vote of thanks.
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
44
Appendix – 5
v. Photographs of the affected areas, consultation meetings, reconstruction activities, etc.
Photo Gallery on Activities at DM A – 605
Project Information Disclosure Meeting on 08.02.17 Project Information Disclosure Meeting on 08.02.17
Public Consultation Meeting on 01.02.2017 Public Consultation Meeting on 12.02.2017
Public Consultation Meeting on 12.02.2017 Problem Solving Meeting on 18.02.2017
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
45
Photo Gallery on Activities at DMA – 607
Compensation Distribution to the AP Compensation Distribution to the AP
Compensation Distribution to the AP Compensation Distribution to the AP
Compensation Distribution to the AP
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
46
Photo Gallery on Activities at DMA – 607
Compensation Distribution to AP Compensation Distribution to AP
Discussion with APs on the Grievance Discussion with APs on the Grievance
Meeting on Grievance DMA 606
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
47
Appendix – 5
Photo Gallery on Activities at DM A – 608
Project Information Disclosure Meeting on 09.04.17
Project Information Disclosure Meeting on 09.04.17
Public Consultation Meeting on 30.03.2017 Public Consultation Meeting on 02.04.2017
Public Consultat ion M eet ing on 04.04.2017 Problem Solving M eet ing on 02.04.2017
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
48
Appendix – 5
Photo Gallery of Act ivity DM A-610
Public Consultation M eeting on 17.06.2017 Public Consultation M eet ing on 17.06.2017
Selected AP Photo Taken on 07/ 06/ 2017 Selected AP Photo Taken on 07/ 06/ 2017
Project Informat ion Disclosure Meet ing on 18.06.17 Project Information Disclosure Meet ing on 18.06.17
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
49
Appebdix-6 vi. Copies of AP`s certification of payment (signed by the AP`s)
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
61
Appendix-7 vii. Safeguards Compliance Monitoring Form & Checklist Safeguards Review Mission
Country : Bangladesh
Mission Date : November 2015
Project Data
Project Name : Loan 3051-BAN: Dhaka Environmentally Sustainable Water Supply Project
Safeguards Categorization A B C
IR
IP
A. Design and Engineering Status
Item Completion Status
(Y/N) Follow up required
(Y/N) Note
Final detailed engineering design of the project activity completed Yes Follow up Required
B. Institutional Status
Sl. No.
Item Status (Ready/Not
ready/NA) Remarks Note
1 Mobilization of key experts Ready
2 Mobilization of supporting staff and surveyor
Ready
3 Establishment of local offices
Ready
4 Appointment of government counterparts
Ready
C. IR/IP Safeguards Supervision Checklist (to be completed as relevant)
Item No.
Safeguards Related Task Status
(Ready/Not ready/ NA)
Progress to Date/ Remarks
1.0 MANAGEMENT
Institutional Arrangements
1.1 Financing and budget : (i) safeguard office and staff; (ii) RP/IPP cost
Ready
1.2 Establish Safeguard Unit: (i) resettlement offices (ii) resettlement staff as in RP (iii) safeguards’ database (iv) facilities (v) safeguards training
Ready
Updating of DD/RP/IPP based on Detailed Design
1.3 Update DD/RP/IPP: (i) revise based on DMS (ii) revise implementation schedule (iii) revise budget
Ready
1.4 Compensation rates: (i) approved by Government; (ii) Adequate as per RP/RF; (iii) APs informed.
Disclosure and Grievance Redress Arrangements
4th Semi Annual Social Safeguard Monitoring Report (Part-A)
62
Item No.
Safeguards Related Task Status
(Ready/Not ready/ NA)
Progress to Date/ Remarks
1.5 Disclose RP/IPP: (i) updated/final RP/IPP and/or (ii) sub-project
RPs; (ii) to the APs in local language; (iii) on ADB website.
Ready of Final
RP
1.6 Grievance redress committees: (i) clear terms of reference; (ii)
appointment decree; (iii) publicly disclosed among APs.
Ready
Monitoring and Reporting Arrangements
1.7 Set up internal monitoring system : (i) assess capacity and staff requirements; (ii) criteria of assessment ; (iii) reporting mechanism
Ongoing
1.8 Appoint external monitoring agency (as relevant): (i) recruitment schedule; (ii) TOR; (iv) baseline survey (v) reporting mechanism (vi) action taken by management on reports.
Not Ready
1.9 Reporting: (i) frequency; (ii) timeliness; (iii) identified issues; (iv)
action taken and/recommendation.
Ready
2.0 IMPLEMENTATION
Consultation
2.1 Consultation: (i) responsibility; (ii)stakeholders Identified; (iii) consultation and process; (iv) documentation
Ready
Mapping and Inventory
2.2 AP Identity cards & records Ready
2.3 Land acquisition activities: (i) maps of affected and relocation sites; (ii) acquisition & relocation schedule; (iii) coordination with the asset’s acquiring, transfer and registration bodies
Ready
2.4 Common property/ public assets: (i) final inventory; (ii) restoration plan and schedule; (iii) funding sources
Ready
Compensation, Relocation and Rehabilitation
2.5 Payment of compensation and entitlements (as stated in the RP): (i) schedule; (ii) records
Ready
2.6 Relocation of households (i) site readiness; (ii) housing construction & associated facilities
Ready
2.7 Income restoration plan (as stated in the RP): (i) activities; (ii) schedule
Ready
Monitoring and Reporting
2.8 Reporting: (i) semiannual monitoring reports; (ii) external monitoring and evaluation reports; (iii) completion report
Ready
Semi-Annual Social Safeguard Monitoring Report
BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
30 July 2017
346152 23 A Mott MacDonald
Mott MacDonald Plot 77, Level 6 Block-M Road 11 Banani Dhaka Dhaka 1213 Bangladesh T +880 (2) 986 1194 F +880 (2) 986 0319 mottmac.com/international-development
Semi-Annual Social Safeguard Monitoring Report
BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
30 July 2017
Euroconsult Mott MacDonald bv is a member of the Mott MacDonald Group. Registered in The Netherlands no. 09038921
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Issue and Revision Record
Revision Date Originator Checker Approver Description
A 30.07.2017
Dr. Rafeza Akter
Jean Louis Leterme
Nigel Osmaston
2nd Resettlement Monitoring Report
Document reference: 346152 | 23 | A
Information class: Standard
This document is issued for the party which commissioned it and for specific purposes connected with the above-
captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being
used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied
to us by other parties.
This document contains confidential information and proprietary intellectual property. It should not be shown to other
parties without consent from us and from the party which commissioned it.
This report has been pr epared sol el y for use by the party which commissi oned it (the ‘Client’) i n connecti on with the capti oned proj ect. It should not be used for any other purpose. N o person other than the Client or any party who has expressl y agreed ter ms of r eliance with us (the ‘Reci pient(s)’) may rel y on the content, i nformati on or any vi ews expressed i n the repor t. We accept no duty of care, responsi bility or liability to any other r eci pient of thi s document. This r eport is confi denti al and contains pr opri etar y intell ectual property.
ed to us by other par ties incl udi ng the client (‘D ata’). We have not i ndependentl y verified such D ata and have assumed it to
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Contents
Abbreviations 1
Executive summary 3
1 Background of the Monitoring Report 6
1.1 Project Description 6
1.2 Purpose of the Report 6
1.3 Category of RP 6
1.4 RP Update and Public Consultation 7
2 Scope of Impacts 8
3 Status of RP Implementation 10
3.1 Update of the RPs 10
3.2 Disclosure and Public Consultation 14
3.3 Payment of CCL and other Resettlement Benefits 14
3.4 Grievance Redress Mechanism (GRM) 14
4 Institutional Arrangement 15
5 Summary Monitoring Results and Key Findings 16
6 Compliance Status 18
7 Follow up Actions and Recommendation 19
Appendices 21
A. Summary of the Consultation Meetings 22
B. Composition of the Committees for RP Implementation 23
C. Meeting Minutes 27
D. Field Visit Report 36
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 1 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Abbreviations
Abbreviation Description
ADB Asian Development Bank
DBO Design-Build-Operate or Design-Build-Operation
DORP Development Organization for the Rural Poor
DDR Detailed Design Reports
DED Detailed Engineering Designs
DESWSP Dhaka Environmentally Sustainable Water Supply Project
DP Displaced Persons
DWASA Dhaka Water Supply and Sewerage Authority
EA Executing Agency
EIA Environmental Impact Assessment
EP Entitled Person
GEM General Entitlement Matrix
FGD Focus Group Discussion
GRC Grievance Redresses Committee
JVC Joint Verification Committee
MDSC Management, Design and Supervision Consultant
MLD Millions of Liters Per Day
MML Mott MacDonald Limited
MODS Maintenance Operations and Distribution Services
PD Project Director
PMC Project Management Consultant
PPMS Project Performance Management System
PMU Project Management Unit
PVAC Property Valuation Advisory Committee
QA Quality Assurance
RAC Resettlement Advisory Committee
RWP Raw Water Pipeline
SIU Safeguard Implementation Unit
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 2 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Abbreviation Description
SPS Safeguard Policy Statement
TA Technical Assistance
TOR Terms of Reference
WIA Water Intake Area
WTP Water Treatment Plant
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 3 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Executive summary
The objective of Dhaka Environmentally Sustainable Water Supply Project (DESWSP) is to
provide a reliable water supply for the Dhaka city by developing a surface water treatment plant
and distribution network to improve quality water supply, water pressure in the pipelines, cost
recovery, reduce water loss and gradual ground water depleting in Dhaka city.
The DESWSP is to be delivered through several contract packages by several consultants,
contractors and NGOs under DWASA’s Project Management Unit (PMU). Mott MacDonald is responsible for the three main construction contracts through their Management, Design and
Supervision Consultancy (MDSC) contract. Under MDSC, Mott MacDonald is acting as the
Employer’s designer for Packages 2 and 3 and as the supervision consultant for Packages 1, 2
and 3.Package 1 is to be let as a Design, Build & Operate (DBO) contract. Package 2 (P2)
comprises of 14 km. Treated Water Pipeline from Water Treatment Plant to Madani Avenue.
Packages 3 (P3) includes Distribution Reinforce Pipeline in North Dhaka City.
The total length of the alignment is approximately 36 kilometres. This starts from the Meghna
River and passes through Ariahazar and Rupganj upazila and reaches Madani Avenue in Dhaka
after crossing Sitalakhya and Balu rivers. This project will use 294 acres of land of which Dhaka
WASA owns 82 acres (in Gandhabpur) and Bangladesh Water Development Board (BWDB) with
Roads and Highways own another 24 acres. The rest of the land (188 acres) is privately owned.
Issues of involuntary resettlement are addressed according to National Legislation (Government
of Bangladesh Acquisition of immovable Property Ordinance, 1982), and ADB Safeguard Policy
Statement (SPS), 2009, and DWASA Policy. A Resettlement Framework (RF) was developed for
DESWSP to provide the mechanism through which the Executing Agency (EA) is updating
Resettlement Plans (RP) for each of the sections of P1 and P2.
Scope of land acquisition and resettlement impacts has already been identified based on the
preliminary design. The project will impact private and government land of different organizations
also structures, assets, crops and trees. As per preliminary design, a total area of 188 acres of
private land needs to be acquired for the construction of the water pump at the intake and for the
required pipelines.
DWASA is the EA, through the PMU will establish a monitoring system involving the Supervising
Officer (SO), Safeguard Implementation Unit (SIU) and NGO. Evaluation of the resettlement
activities will be undertaken during and after implementation of the RP. A qualified independent
monitor (External Monitoring Agency) has been engaged as third party monitor for RP
implementation.
DWASA has not established its own SIU yet to assist the PMU for managing social and
resettlement issues. DWASA with the support of MDSC relevant consultants will organize training
for PMU and NGO staff.
To carry out the resettlement activities, PMU has contracted a local NGO called DORP that
mobilized in February 2015. From that date the DORP has started/completed surveys and
information campaign to update a resettlement plans for some sections. The surveys in section 4
and 5 are yet to start as finalisation of the alignment is still awaiting.
Four committees namely Joint Verification Committee (JVC), Property Valuation Advisory
Committee (PVAC), Grievance Redress Committee (GRC) and Resettlement Advisory
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 4 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Committee (RAC) have been formulated by the PMU for each section of RPs. The GRC will be
responsible to assist the Affected People (APs) in case of complains at project level.
The progress of work carried out by the DORP so far was very slow and unsatisfactory before
regarding quality especially in the update of the required RPs but currently they are trying to
improve the progress. Meanwhile, steps are to be taken to replace Team Leader (TL) and Deputy
Team Leader (DTL) for improving the quality in updating RPs.
Few bureaucratic inertness with regard to Land Acquisition (LA) process also hinder progress of
RP implementation.
During the next reporting period Cash Compensation under Law (CCL) and other resettlement
benefits to the EPs are expected to be completed to four sections i.e., Section1, 2, 3 and 4.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 5 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 6 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
1 Background of the Monitoring Report
1.1 Project Description
This is a Semi-annual Resettlement Monitoring Report prepared for the PMU for onward
submission to ADB. The “Dhaka Environmentally Sustainable Water Supply Project” comprises
of Water Intake, Gandharbpur Water Treatment Plant, and Raw & Treated Water Mains.
Dhaka Environmentally Sustainable Water Supply Project (DESWSP) is to provide a reliable
water supply for the Dhaka city by developing a surface water treatment and distribution network.
(See detailed map of the full project given above) The total length of the alignment is
approximately 36 kilometres. This starts from the Meghna River and passes through Ariahazar
and Rupgonj upazilla and reaches Madani Avenue in Dhaka after crossing Sitalakhya and Balu
River. This part of the project is called P1 and P2. This project will require 294 acres of land of
which Dhaka WASA owns 82 acres in Gandharbpur and Bangladesh Water Development Board
(BWDB) with Roads and Highways owns another 24 acres. The rest are privately owned that will
need to be acquired.
A Resettlement Framework (RF) was developed for DESWSP to provide the mechanism through
which the EA will prepare Resettlement Plans (RP) for each section of the project. Issues of
involuntary resettlement will be addressed based on DWASA Policy (Resettlement Policy
Framework, 2013) following National Legislation (Government of Bangladesh Acquisition of
immovable Property Ordinance, 1982), and the ADB Safeguard Policy Statement (SPS), 2009.
Necessary Inputs to prepare the report (Semi-annual Social Safeguard Monitoring Report) were
provided by the DORP, the NGO responsible for implementation of the Resettlement Plans. The
report covers the progress made during the first half of the year 2017 and is presented according
to the format provided in the resettlement framework.
1.2 Purpose of the Report
Clause no. 18 (iii) of the Terms of Reference (ToR) of MDSC requires submission of Semi-annual
Social Safeguard Implementation Monitoring Report. Moreover, Appendix 3 of the Resettlement
Framework of the DESWSP mentioned, ‘Following requirements of the ADB Safeguard Policy Statement (2009) and the Operations Manual section on Safeguard Policy (OM F1),
borrowers/clients are required to establish and maintain procedures to monitor the status of
implementation of safeguard plans and ensure progress is made toward the desired outcomes
for projects categorized as A or B in Involuntary Resettlement and/or Indigenous People. The
borrowers/clients are required to submit semi-annual monitoring reports for ADB review.’ To comply with the requirement on behalf of the borrower (the DWASA), the MDSC is hereby
submitting the Semi-annual Social Safeguard Monitoring Report (SSSMR). This is the 2nd SSSMR
of the project RP implementation.
1.3 Category of RP
Considering the extent of significance of impacts, ADB has classified projects into four categories;
A, B, C and FI. The involuntary resettlement impacts of an ADB-supported project are considered
significant if 200 or more persons will be physically displaced from home or lose 10% or more of
their productive or income-generating assets. The project, which has significant involuntary
resettlement impacts, falls under category A. Thus, the DESWSP is classified as Category A. No
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 7 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
indigenous household has been found during the surveys; therefore, the project falls under
category C as regard to indigenous people categorization.
1.4 RP Update and Public Consultation
The NGO contracted named DORP is assisting DWASA in updating the RPs and implementation
of the resettlement activities. The DORP has so far prepared three Draft RPs for Section-1 and
Section-2 and Section-4. DORP is now conducting field census /survey in another 3 sections to
assess and verify the impacts on APs for the RP updates as well as its implementation.
Regular consultations with the affected persons (APs) and other stakeholders are being
conducted by the DORP to ensure that they are fully aware of the project interventions and about
their entitlements in case of involuntary land acquisition and resettlement benefits for APs (titled
or non-titled holders). The format to report on the consultation carried out need to be reviewed to
emphasis more on the remarks made by the participants.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 8 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
2 Scope of Impacts
The initial Resettlement Plan for the project was prepared in 2013 and it indicated major impacts
on private land, scope of land acquisition and resettlement impacts has already been identified
based on the preliminary design. The project will impact private and government land of different
organizations also structures, assets, businesses and livelihood, crops and trees. As per
preliminary design, a total area of 188 acres of private land will need acquisition for the
construction of the intake area and the pipeline construction for package 1 and 2. See map
above.
The project area under Package 1 and 2 has been divided into six sections to update the RPs
conveniently. The sections are named as follows;
Section-1: Water Intake Area
Section-2: Water Intake to Baliapara (End of Araihazar)
Section-3: Darikhandi Chak (start of Rupganj) to Murapara via Gandharbpur WTP
Section-4: Water Treatment Plant Gandharbpur Area
Section-5: Rupganj (West bank of Sitalakhya River) to Balu River (East bank)
Section-6: Balu River (West bank) to Vatara along Madani Avenue up to Baridhara
RP Section1 & 2 require both private and government (govt.) land. No land acquisition is required
for the construction of the Water Treatment Plant as DWASA acquired a total of 82 acres of land
in Gandharbpur area in 1982-83. Besides, Dhaka WASA has signed a Memorandum of
Understanding (MoU) to receive back 2.83 ha of land from the Bangladesh Water Development
Board (BWDB) by DWASA for excavation of a canal for irrigation purpose. This arrangement has
been done under a MoU signed between DWASA and BWDB mentioned in the RP.
The Table 1 below presents the summary of the land requirements with areas and type of impacts
identified so far.
Table 1: Land Acquisition and Resettlement Impacts
Section of RPs
Locations Land Requirement (in acre)
Structure and other impacts
Comments / Status
Nos. Total Govt. Owned
Privately owned
1 Water Intake Area (WIA)
29.33 10.48 18.85 Agriculture Notice under Section 7 has been served by the DC office.
1 Intake to Balia Para
110.2 4.1 106.1 Agriculture, livelihood, and structure
Process of serving notice under section 7 is on-going
3 Darikhandi Chak (start of Rupganj) to Murapara via Gandharbpur WTP
61.07 23.67 37.41 Agriculture, structure and livelihood
Process of land acquisition is underway by the DC office. No notice has been issued so far.
4 Water Treatment Plant
82 DWASA land
No private land
Structure and agriculture
Land acquired in 1985 by DWASA
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 9 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
(WTP)
5 Rupganj (West bank of Sitalakhya river) to Balu river (East bank)
21.83 No government land
21.83 Structure, pond and agriculture
Same as section 3.
6 Balu river to Bhatara
Government land
4 km within road alignment
No private land
Temporary structures (squatters)
RAJUK provided permission to use but MoU to be finalized.
Source: DWASA
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 10 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
3 Status of RP Implementation
3.1 Update of the RPs
The DORP has been appointed in February 2015. First Draft RP for WTP was submitted to
DWASA in January 2016. The draft has since been resubmitted 5 times; last version has been
submitted on May 2017 which is being waited for ADB’s approval. Each time MDSC provided necessary feedback and detailed comments and advised them in providing full details of the
impacts, improve the accuracy of the data presentation, prepare budget based on approved
entitlement matrix and do proper editing of the document. In December 2016, the DORP
conducted a resurvey in WTP area as MDSC found out some discrepancies during field
monitoring. They also submitted a preliminary draft for the Intake area in November 2016.
DORP has submitted updated RPs twice for section-1; first draft in November 2016 and the
second version in March 2017 which has been submitted to ADB for their approval. ADB
has provided with their significant comments to review RPs for WTP and WIA. It is worth
mentioning that DORP is waiting for final approval of General Entitlement Matrix (GEM) to
be endorsed by ADB. The proposed GEM has been submitted to the Project Director (PD)
on June 2017. Once the GEM has been approved, DORP will send their comments-
responses matrices to the ADB. DORP had submitted a preliminary draft RP for Section-2 in
March 2017 without proper data and MDSC declined to make comment on that. Accordingly,
they submitted 2nd draft on May 2017 and MDSC reviewed and sent back them for editing.
Land acquisition work is in progress for Section-1: Intake area and Section-2: Intake to Baliapara.
Notice under section 7 has been served from the DC office to all Entitled Persons of Section-1 for
paying compensation money or CCL. In section 2 area all EPs got notice under section 6. Out of
them about 33% has been served notice under section 7 and the rest is expected to be served
soon to vacate the required land after receiving proper compensation and resettlement benefits.
On land acquisition matters DWASA has been following up with the DC office regularly in
Araihazar Upazila of Narayanganj District. DWASA has been keeping all communications with
the Ministry of Land on progress in land acquisition matters.
The Table 2 below provides in a nutshell the progress achieved about land acquisition and RP
preparation section wise. It shows updates on RP preparation stage, including progress on land
acquisition, data collection and planned date for submission of RPs.
Table 2: Status of Progress about Land Acquisition and RP Update
Sections Project Locations Land acquisition status Status of RP Updates
Section -1 Water Intake area DC office has served notice under section 7 to all EPs to pay compensation.
Draft RP has been submitted to ADB on March 2017. ADB has given comments on May 2017. DORP is preparing comments-responses matrix and will send to ADB by July 2017. They are now waiting for approval of General Entitlement Matrix (GEM) that has been prepared and submitted to PMU in June 2017.
Section -2 Intake to Baliapara (End of Araihajar)
Section 6 notice served to all EPs. Out of them about 33% EPs has received notice under section 7. The rest will get soon, serving is on-going.
Final Draft of RP has been submitted to PMU and to MDSC accordingly in May 2017. On behalf of PMU MDSC reviewed the RP and sent back to the DORP through
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 11 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
PMU for editing. Edited RP will be submitted by July 2017.
Section-3 Darikhandi Chak (start of Rupganj) to Murapara via Gandharbpur WTP
LA plan has been submitted to the Ministry of Land (MoL). DC office will conduct field survey (FS) for Rupganj area and send it to the MoL Central Land Acquisition Committee (CLAC) by the end of the August 2017 and DC office will serve the notice under section 3 by the end of September 2017.
Tentative date of first Draft RP submission is 25 September 2017.
Section -4 Water Treatment Plant
DWASA owned land Same as RP Section-1.
Section -5 Rupganj (West bank of Sitalakhya River) to Balu River (East bank)
CLAC should be held soon after DC’s approval. Tentative date of DC office’s FS is 1st week of August 2017.
First RP to be prepared and submitted by 30 September 2017 (from DORP to PMU).
Section-6 Balu River to Vatara Baridhara.
This section is along the RAJUK Road. Survey not yet commenced.
First RP to be prepared and submitted by 1 October 2017 (from DORP to PMU).
Source: DORP and DWASA
MDSC resettlement consultants reviewed the DORP’s work plan and provided feedback advising
them to make it more realistic. The progress achieved so far is presented in the Progress Reports
prepared by the DORP on monthly and quarterly basis. The Monthly Progress Report covered
the progress of the DORP activities for the respective month. Quarterly reports were a cumulative
reporting on three months progress. In this phase MDSC had reviewed five (5) Monthly Progress
Reports and one (1) Quarterly Progress Report is received in this period (January to June 2017) and
MDSC provided feedback with specific comments to DORP for improving their quality of documentation
and other works to focus on the critical isses. With reference to those reports, the progress made so far
by the DORP up to June 2017 is presented in the Table 3 as follows:
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 12 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Table 3: Cumulative Progress up to 30 June 2017
Tasks as per Work Plan Section 1 Intake
Section 2 Section 3 Section 4 Section 5 Section 6
No. % Total % Total % Total % Total % Total % Resettlement Plan Updating
Conducted SES data collection from Affected Household Heads
87 100 1275 100 991 25 232 100 - - - -
Conducted Consultation meeting with Ahs
2 100 12 100 - - 7 100 - - - -
Implementation of RP
Personal contact established with AHs and other Stakeholders
609 52 1847 54 1378 48 905 68 468 42 180 20
Community meetings held with AHs and other Stakeholders
35 60 51 40 68 62 48 72 21 42 - -
Distributed Leaflets to AHs and other Stakeholders
1,000 100 2000 100 - - - - - - - --
Distributed Booklets to AHs and other Stakeholders
300 100 700 100 - - - - - - - -
Joint verification completed by DWASA /DC assisted by DORP
21.37 acre
100 110.2 acre
100 - - - - - - - -
Video Filming done 21.36 Acre
100 14 km 100 - - - - - - - -
Assisted DC office to disburse the Notice under section 3 to Affected Persons (APs) members
260 100 2660 100 - - - - - - - -
Distributed the Notice under section 6 to AHs members
362 100 2985 100 - - - - - - -
Distributed the Notice under 89 100 660 33%
1 Previously DORP has surveyed 392 households but data was inadequate. At present resurvey is on-going.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 13 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Tasks as per Work Plan Section 1 Intake
Section 2 Section 3 Section 4 Section 5 Section 6
No. % Total % Total % Total % Total % Total % section 7 to Entitled Persons (EPs) members
Conducted Focus Group Discussion with eligible AHs to develop livelihood plan
04 100 11 100 - - 9 100 - - - -
Database
Developed software for data entry – This software to be updated to accommodate supplementary
1 100 1 100 1 100 1 100 1 100 1 100
Completed data entry using in “excel” sheet
89 100 1275 100 232 100
Submitted Draft ID card to PMU, DESWSP for approval
1 100 1 100 1 100 1 100 1 100 1 100
Submitted Draft Payment Voucher to PMU, DESWSP for approval
1 100 1 100 1 100 1 100 1 100 1 100
Payment Voucher to PMU, DESWSP for approval
Draft Prepared Draft Prepared Draft Prepared
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 14 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
3.2 Disclosure and Public Consultation
DORP has conducted thirty-five (35) consultation meetings including public consultation (21) and
FGDs (14) with the community and APs up to June 2017 in the Section 1, 2 and 4 Total 363
participants (male and female) were present at the meeting. A total of eleven (11) DORP staffs
were present at the meeting. The summary minutes of the meetings is provided in Appendix 1.
Main discussion issues were: people’s attitude towards project intervention, impacts on assets and livelihood, compensation and market price, livelihood restoration, organizations roles and
responsibilities, policy issues, etc. Key findings are noted below:
● APs and community people appreciated the project importance and requirements
● APs were upset about losing their ancestral property; but they will have no grievance if they
receive adequate compensation to buy another land with the compensation money.
● Initial brochure about the project and rights for compensation were distributed.
● List of required claim documents were provided by the DORP in the RP section 1 and 2 areas.
● Project implementation authority committed to pay fair compensation and resettlements for
lost assets and livelihood
In addition to the consultation meeting carried out during the preparation of the RPs, the approved
Entitlement Matrix will be disclosed before the APs before implementation which will start for WIA
and WTP by 17 August 2017.
The report/minutes of the consultation meetings need to be improved to address the issues /
remarks made by the participants
3.3 Payment of CCL and other Resettlement Benefits
As we see in Table 2, the compensation and rehabilitation following the approval of the updating
of RPs as well as top-up payment and resettlement benefits for land compensation has not yet
started in any of the sections. It is worth mentioning that the CCL payment will start very soon as
the notice under section 7 is being served for the RP section 1 and 2 areas. Payment of other
resettlement benefits will start after approval of the RPs by the ADB. The NGOs need to deploy
more assistance at the time of disbursing CCL.
3.4 Grievance Redress Mechanism (GRM)
The ministry of LGD has approved the proposal for the formation of four committees for smooth
implementation of RPs; these are Joint Verification Committee (JVC), Property Valuation Advisory
Committee (PVAC), Grievance Redress Committee (GRC) and Resettlement Advisory
Committee (RAC). These committees will be formed for each sections of RPs. Considering
present situation PMU has revised these committees and their Terms of References (ToR) and
got them approved by the ministry in June 2017.
The GRC will exclusively work for redressing grievance of the Aps. The GRC will receive,
evaluate, and facilitates the resolution of APs concerns, complaints and grievances about the
social safeguard issues linked to payment of fair compensation as per the GEM.
List of committees and their respective Terms of References (ToR) have been attached as
Appendix 2.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 15 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
4 Institutional Arrangement
DWASA is the Implementation Agency (IA) of the project. A PMU has been established with a
proposed SIU with a staff of Resettlement, Social and Gender Development Officer. DWASA will
establish its own SIU to assist PMU for managing social and resettlement issues. The SIU
Resettlement, Social and Gender Development Officer assisted by the Resettlement Expert of
MDSC will oversee the implementation of involuntary resettlement safeguard work under the
project with support of the resettlement NGO DORP. The other staffs responsible for looking the
safeguard issue of the project include: one Executive Engineer, two Assistant Engineers and
two Sub-Assistant Engineers. The Project Director and two Deputy Project Directors and one
Senior Water Supply Engineer administer the overall activities.
DESWSP is to be delivered through several contract packages by several consultants,
contractors and NGOs under DWASA’s PMU. Mott MacDonald is responsible for the three main
construction contracts, through their Management, Design and Supervision Consultancy (MDSC)
contract. Under MDSC, Mott MacDonald will act as the Employer’s designer for Packages 2 and 3, and as the supervision consultant for Packages 1, 2 and 3.
MDSC is being led by the Mott MacDonald Limited (UK) in association with Fichtner GmbH & Co.
KG (GER), Euroconsult Mott MacDonald (Netherland) & Yooshin Engineering Corporation (KOR),
BCL Associates Limited (Bangladesh), SARM Associates Limited (Bangladesh), Associates for
Development Services Limited (Bangladesh). The goal of MDSC is to provide all necessary
consulting services requirements to implement the DESWSP.MDSC resettlement consultants will
specifically monitor the RP implementation program. International and National Resettlement
Experts are assigned to review and assist RP implementation process.
DWASA and the INGO namely DORP signed an agreement on February 2015 to update and
implement RPs with the support of DWASA. DORP is working in close coordination with DWASA
PMU. The major tasks of DORP are: updating RP, Institutional development, skill training,
consultation and distribute ID cards to each AP DORP is responsible to assess impacts, market
price of the loss of the property and all field activities such as 100% census and survey, public
consultation and FGD with the APs and communities.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 16 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
5 Summary Monitoring Results and Key
Findings
The latest draft RP for WTP was submitted in December 2016. As per this RP a total of 234 APs
will have impacts on their livelihood, agricultural production, small businesses, and structures
(both dwellings and businesses). Summary of project’s impacts on APs in RP Section 1 (WIA), 2
(Intake to Baliapara) and 4 (WTP) is given in Table 4 below:
Table 4: Summary of Project Impacts for RP Section 1, 2 and 4
Sl. No.
Impacts/Types of losses Total (Nos./quantity0
Section-1 Section-2 Section-4
A Total Land required 11.88 ha. 44.59 ha.
33.20
i. Private Land to be acquired 7.63 ha. 42.93 ha
No private land required
ii. Government Land to be acquired 4.25 ha. 1.66 ha. 30.35 ha DWASA owned land and the rest 2.85 ha.
owned by BWDB
iii. Total affected households 87 1178 232
B Total affected population 535 5683 1148
C Total vulnerable Households (C1+C2)
3 198 84
C1 Female headed AHs [income below poverty line ( up to 1,44,000/year)]
- 31 1
C2 Male headed AHs [income below poverty line ( up to 1,44,000/year)]
3 167 81
D Total affected primary and secondary Structures (D1+D2)
- 52
D1 Affected primary structures (i+ii+iii) - 116 43
i: Affected residential Structures - 103 12
ii: Affected business structures - 5 30
iii. Affected residential-cum-business structure
- 8 01
D2 Affected secondary structures (i+ii) - 9
i. Total nos. of Sanitary Latrine affected
- 45 6
ii. Tube wells and Water Pump affected
- 64 3
E Affected business persons - 12 31
F Wage Laborers in business houses - 87 12
G Affected CPR (graveyard) - - 1
H Numbers of affected trees (including banana and bamboo)
09 6352 561
Source: RP WIA and WTP
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 17 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
MDSC is monitoring the activities that are being conducted by the DORP through paying field
visits and regular meetings between PMU and DORP to share the progress. Minutes of the
meeting and field visit report are attached herewith under Appendix 3 and Appendix 4
respectively.
MDSC resettlement consultants paid field visits to understand the progress made by the DORP
on resettlement issues, project alignment and observe the overall current situation in the project
area. Discussions were conducted with field staff to get their feedback and suggestions on RP
implementation and bottlenecks if any. Key findings are as follow:
● Monthly activities reports are prepared and submitted regularly to the DORP head office by
the field staff but improvement is expected to prepare more accurate work plan and report
about the critical issues
● Documented minutes are available from May 2015. Signatures of the meetings’ participants are present. These minutes need to focus more on the opinions and remarks made by the
attendees.
● Payment of CCL is going to take place soon. DORP field officials of Araihazar Upazila are
assisting with serving notice under 7 on behalf of DC officials and they are supporting EPs as
well to get papers ready for CCL. Proper supervision is required to ensure that the DORP staff
involved are carrying their duties with highest sincerity.
● Rupganj officials are busy with conducting socio-economic survey in RP Section-3.
● DORP is now trying to recover its slow progress by deploying more people. The new staff staff
to be deploy by DORP need to ensure fast and efficient work
● MDSC International and National Resettlement Expert are regularly supervising DORPs
activities and will continue guiding them to improve the quality of survey, report and monitoring.
● DORP has conducted resurvey to collect socio-economic data for RP section 1, 2 and 4 which
were inadequate before. Now they are carrying out resurvey for RP Section 3.
● Regular assistance has been provided by MDSC to develop the MIS which is urgently needed
but the progress is very slow and lack of support from the DORP management to employ
regularly staff.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 18 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
6 Compliance Status
The compliance as per loan agreement a list of covenants is described and some are related to
land acquisition and resettlement activities. The status of progress and compliance including all
covenants are provided in the Monitoring and Evaluation section of the Project’s Quarterly Progress Report and will not be repeated here.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 19 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
7 Follow up Actions and Recommendation
New National Resettlement Expert (NRE) has been appointed in MDSC from June 2017. She is
now taking over all charges of previous NRE. Held several meetings with DORP to expedite their
progress.
Progress of work carried out by the DORP so far is improving although still not up to satisfactory
level regarding quality and progress. Several meetings were held with DORP and PMU from time
to time where this was discussed. Immediate actions are required if the situation is to be
addressed as noted below:
● DORP has hired two Management Information and System (MIS) persons who are now
engaged in preparation of database. MDSC Resettlement Experts and Monitoring and
Evaluation (M&E) Expert is guiding them in doing proper thing.
● DORP has been asked to submit their new work plan in a realistic way start with August 2017
and onward focusing on remaining RP updates, work with the community, such as helping the
APs in getting the necessary compensation paper ready and restoring present livelihood,
utilities and social networking, etc.
● DORP should provide more pro-active service for RP Section 1 and 2 as the DC office has
been serving notice under section 7 for paying CCL.
● Separate consultation meetings with females should have been conducted to allow women to
voice their concerns on the project issues.
● Regular meeting should be scheduled between PMU (Safeguard Resettlement), DORP (TL
and DTL) and MDSC (Resettlement and M&E Experts) to review work progress.
Below is the monitoring format for activities to be done during implementation of the land
acquisition and resettlement as provided in the resettlement framework.
Table 5: Monitoring of Activities during Implementation
Sl no. Resettlement Plan Activities Completed Y/N
Remarks
A. Pre-Construction Activities and Resettlement Plan Activities
1 Approval of Final Resettlement Plan by ADB prior to contract award
2 Disclosure of Final Resettlement Plan on ADB and Executive Agency (EA) websites
3 Circulation of Summary RP in two languages i.e., English and Bangla to all stakeholders
4 Establishment of GRC and other committees for the RP finalization/ implementation
5 Recruitment/Appointment of External Monitoring Agency B. Resettlement Plan Implementation
1 Grievance Redress Committee and telephone hotlines established
2 Entitlements and grievance redress procedure disclosed
3 Finalization of list of APs, vulnerable APs and compensation/ assistance/ allowances
4 Finalization of list of affected common facilities and roads for closure; mitigation measures proposed
5 Affected persons received entitlements as per amounts and program specified in RP
6 Payment of compensation, allowances and assistance (No. of EPs)
7 Additional assistance for vulnerable households given (No. of vulnerable EPs)
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 20 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
8 Livelihood arrangements provided to vulnerable EPs
9 Reinstallation of affected common facilities
10 Grievances No. of grievances registered No. of grievances redressed Outstanding complaints Disclosure of grievance redress statistics
11 Consultation, participation and disclosure as per RP
12 Livelihood and Income Restoration activities: 1. Nos. of AHs resettled 2. Nos. of AHs attend the retraining program 3. Nos. of AHs replaced their agricultural land 4. Nos. of AHs join the micro finance program 5. Nos. of AHs reconstruct the loss businesses
C. Monitoring
1 Survey on socio-economic status of APs (including vulnerable APs) completed and compared with baseline survey results
2 Survey on satisfaction levels of APs with RP implementation completed
D. Labor
1 Implementation of all statutory provisions on labor like health, safety, welfare, sanitation, and working conditions by Contractors
2 Equal pay for equal work for men and women
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 21 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Appendices
A. Summary of the Consultation Meetings 22
B. Composition of the Committees for RP Implementation 23
C. Meeting Minutes 27
D. Field Visit Report 36
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 22 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
A. Summary of the Consultation Meetings
Key Issues of Discussion Participants Responses Project Response
Opinions regarding project intervention
Way of giving compensation by DWASA to the affected persons due to the project intervention.
Price and productivity of Land to be acquired
Land use and cropping pattern
Major livelihood activities in project area and impact on livelihood that may occur due to project intervention
Consultation meeting were held in congenial
environment and every participants
spontaneously took active participation in
discussion process. Consultation process
revealed that most of the affected persons
were found worried to lose their ancestral
land. They expressed their views that land is
their main source of livelihoods through the
generations. Nothing will compensate to the
loss of land. They became afraid as they are
going to lose their livelihood
opportunity/resource base due to land
acquisition.
They will not surrender their ancestral land, if
they will not be fairly compensated at current
market value of land. Agricultural activities
are the main livelihood means/resource
base. They grow paddy, jute, potatoes, sweet
potatoes, beans, sesame, mastered, onion
and different variety of vegetables. Besides,
different types of business enterprises
remain there. Some people work in these
business firms and in agricultural field. Some
peoples involved with fishing in nearby river.
Due to land acquisition for the project they will
have to loss income earning opportunity. On
the other hand they could not purchase
replacement land as land price is very high.
They demand fair price of their lost land at
current market price as the price of land is
very high. Without full compensation at
current market price, they will not surrender
their possession of acquired land. They
asked the authority concerned and DORP to
provide necessary services to collect
papers/documents required for getting CCL
without any intermediary or middlemen
interference.
They requested the project authority to
provide sufficient compensation immediately
for restoration of their livelihood.
However, They shown positive attitudes
towards project.
The project will take necessary
mitigation measure to compensate their
lost assets in accordance with ADB’s social safeguard policy Statement. All
kinds of technical and administrative
support will be provided to get
compensation from DC office as well as
to get resettlement benefit from DWASA.
The project will have appropriate action
strategy to mitigate negative impact on
livelihood and income of affected
populations. To restore livelihood and
income at least at the pre-project level is
the main policy principles of resettlement
plan. Detailed resettlement and
rehabilitation plan is being prepared in
accordance with Acquisition and
Requisition of Immovable Property
Ordinance (ARIPO), 1982 and
Safeguard Policy Statement (SPS-2009)
of ADB. According to SPS-2009, all
affected persons/AHs will be fairly
compensated at current market rate for
assets lost due to the project
intervention.
As per guidelines of ADB, the DWASA
prepared resettlement plan to restore
livelihood and income of affected
persons. All AHs will be compensated for
their lost at current market value of
assets. The project will brings more
income and employment opportunity.
Affected Persons will get priority to get
employment in project construction
works based on qualification and skill.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 23 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
B. Composition of the Committees for RP
Implementation
NGO services for Resettlement Implementation assistance for construction of Intake, Raw
Water Pipelines, 500 MLD Capacity WTP and Treated Water Pipeline up to Injection Point near
to American Embassy. Following committees will be working for the project to monitor and
ensure proper compensation process/activities:
Type of Committee Composition ToR
1. Joint Verification Committee (JVC)
a) Convener: Executive Engineer, DESWSP, Dhaka WASA
b) Member: Safe-guard Officer (Social Gender) DESWSP, DWASA
c) Member: Representative of the Deputy Commissioner (Land Acquisition Officer)
d) Member: Representative of the Public Works Department (PWD)
e) Member Secretary: Area Manager, DORP
f) Member: Representative from MDSC
a) Verify and assess physical assets, including structure, trees, crops, businesses, etc. to be affected on the project Right of Way (RoW).
b) Communicate and assist NGO for process the entitlements of the project-affected persons using JVC data as one of the determinants.
2. Property Valuation Advisory committee (PVAC)
a) Convener: Deputy Project Director/Executive Engineer, DESWSP, DWASA
b) Member: Safeguard Officer (Social and Gender) DESWSP, DWASA
c) Member: Representative of PWD
d) Member: Representative of Forest Department
e) Member: Representative of Agriculture Department
a) The PVAC will review the assessment made by the Resettlement NGO based on the market prices of the properties to be affected by the project as replacement cost after verification by the JVC.
b) Communicate and assist NGO for process the entitlements of the project-affected persons using PVAC data as one of the determinants for building the estimate of the replacement value.
c) PVAC may visit the site if necessary for verifying any information.
d) The committee will use CCL (Cash Compensation under
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 24 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
f) Member: Representative of Community Leader/Local Elite
g) Member Secretary: Area Manager, DORP
h) Member: Representative from MDSC
law), Current Market Value (CMV) assessed by the DC Office, PWD and NGO data in proposing Replacement Value of land, structures, common property resources and other losses prior to recommending to PMU.
e) For recommending to PMU the committee will take decision at two-third majority basis.
3. Resettlement Advisory committee (RAC).
a) Convener: Executive Engineer/Sub-Divisional Engineer, PMU, DESWSP, DWASA
b) Member: Representative of the Deputy Commissioner
c) Member: Representative of Local Elite/UP Chairman
d) Member: Representative of affected organization (if any)
e) Member: Representative of Displace person / Female Displace Person
f) Member Secretary: Area Manager, DORP
g) Member: Representative from MDSC
a) The committees will seek local inputs from the affected people and communities in the implementation process and assist DWASA in all matters related to resettlement.
b) The RACs will ensure local participation in the implementation of the resettlement plan.
c) Communicate and assist NGO for process the entitlements of the project-affected persons using NGO data verified and validated as one of the determinants
4. Grievance Redress Committee (GRC)
a) Convener: Deputy Project Director/ Executive Engineer DESWSP, DWASA
b) Member: Representative of UP Chairman/ Ward Councilor
c) Member: Female UP Member
d) Member: Representative of Displace person (Male/female)
e) Member Secretary: Representative from NGO
f) Member: Representative from MDSC
a) The Grievance Redress Committees (GRCs) will be established to ensure stakeholders’ participation in the implementation process and fair compensation to affected persons.
b) The APs can also call upon the resettlement NGO to assist them in presenting their grievances or queries to the GRC.
c) The GRCs will receive grievance cases from the affected persons through the resettlement implementation NGO.
d) Other than disputes relating to ownership right and award of
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 25 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
compensation by the Deputy Commissioner under the Court of Law, GRCs will review grievances involving all resettlement assistances, relocation, and other supports. Grievances will be redressed within 21 days from the date of lodging the complaints. In cases of complicated cases requiring additional investigations it will be resolved within a period of one month.
e) Grievances of indirectly displaced persons and/or persons displaced during project implementation will also be addressed by the GRC
f) Where land acquisition will not be involved but relocation of structures or vacating land for cultivation will be required, the GRCs will facilitate resolution of complaints regarding categorization of vulnerable affected persons, types of structures, and eligibility for compensation and assistance within the set guidelines and provisions of the resettlement plan.
g) Any complaints of ownership or other suits to be resolved by the judiciary system will not be resolved in GRCs. GRC will resolve all complaints, grievances related to compensation entitled by affected persons
h) The decisions of the GRC should be ideally be arrived at through consensus, failing which resolution will be based on majority vote. Any decision made by the GRC must be within the purview of social, resettlement and environmental policy framework.
i) A minimum of 4 (four) members shall form the quorum for the meeting of GRC.
j) If needed the GRC members may undertake field visit to verify
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 26 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
and review the issues at dispute, including titles/share, reasons for any delay in payment or other related matters.
k) In case the resolution is not accepted by the AP, the grievance will be forwarded to Project Director for final decision.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 27 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
C. Meeting Minutes
Discussed Issues Action on
1 Progress made by DORP on the Update of RP of the WTP Area and Other Sections
1.1 The PD stated that MDSC had earlier sent their comments on the RP of WTP submitted
by DORP. The comments have been provided in track changes and also a summary was
given for important issues to be reveiwed in the RP.
The PD will instruct DORP to
provide replies to the comments
by 8 February 2017. A response
matrix should be given by the
DORP on comments
incorporation.
Project title Management Design and Supervision Consultants (MDSC) for Dhaka Environmentally Sustainable Water Supply Project (DESWSP) under Dhaka DWASA
Subject Progress Review Meeting of DORP activities
Location Conference Room, PMU, DESWSP
Date 02.2.2017
Time of meeting 3:00 pm to 4:30 pm
Project number 346152
Attendees
Name Initials Company/unit/division
Md. Mahmudul Islam MMI PMU, DESWSP, Project Director (PD)
Md. Baharul Islam MBI PMU, DESWSP, Deputy Project Director (DPD)-1
Md. Mizanur Rahman MMR PMU, DESWSP, Executive Engineer
M. Monirul Islam MI DESWSP, Senior Water Supply Engineer
Md. Quaisarul Islam MQI MM MDSC, Deputy Team Leader
Jean LouisLeterme JLL MM MDSC, International Resettlement Expert (IRE)
Shireen Aktar SA MM MDSC, National Resettlement Expert (NRE)
Dr. Rafeza Akter RA MM MDSC, Social Development and Gender Specialist (SDGS)
Bashir Ahmed BA Team Leader, EMA
Recorded by JLL, IRE; SA, NRE and RA, SDGS, MM MDSC, DESWSP
Distribution All attendees + Team Leader, MM MDSC
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 28 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
MDSC opined that the replies to the comments is a standard practice and will enable the
reviewers to check whether the comments are properly addressed.
1.2 PD expressed his worries that delayed updating of WTP RP may hamper the other package activities and start of physical work in site and progress accordingly, such as DBO package expected to be contracted by April 2017 and resettlement activities of such package should be completed beforehand; otherwise they would not be able to start the required civil works..
The PD tends to dismiss present
respective Team Leader of
DORP with effect from 1 March
2017 as he has been proven as
inefficient.
1.3 DC office is moving forward about land acquisition (total 131.50 acre) in Araihazar upazila and served notice 6 in LA Case No 3/ 2015-16 (3 mouzas of 29.22 acre land) and LA Case No. 4/2015-16 (10 mouzas of 28.50 acre land) and awaiting for seving the notice 6 for LA Case No. 5/15-16 (7 Mouzas of 38.15 acre land) and LA Case No. 6/15-16 (6 mouzas of 35.63 acre land). Public Works Department (PWD) and Forest Department have already submitted their estimate to the DC office. Now the DC office will submit the estimate to the DESWSP, DWASA. The DC office is ready to start land acquistion and pay the necessary compensation but the prerequisite of a finalized RP is yet to be done. The PD will advise DORP to update the RPs of Section 1 and 2 following ADB as well as MDSC comments given for WTP ( section 4) RP and submit the RPs before 25.2.17
The PMU will notify DORP to
submit final RPs for section 1, 2
and 4 by 25 February 2017.
2 Person-months used by DORP up to December 2016
2.1 MDSC social safeguard team drew attention of the PD that DORP has already consumed almost 50% of their allotted person-months so far, though outputs are very minimal in terms of completion of RP update and implementation. Both MDSC and PMU expressed their worries about the remaining works and the ability of DORP to complete all the tasks within the stipulated time.
PMU will notify DORP to
complete all the works within the
remaining person-months.
2.2 The PD and MDSC noticed that DORP has already been paid bill for Livelihood Specialist, Training Specialist and Financial Specialist (Micro Finance) though they had minimum scope to use their inputs in this period. The MDSC team commented that the Livelihood and Training Specialist are supposed to give much input during RP implementation phase. Spending 50% of their person-months during this period is impossible while the RP is yet to be finalized. The PD wondered that DORP has collected bill against Communication/Public Health Specialist inputs as well though the least input was used in this respect. The MDSC team suggested the PD not to pay DORP further against those specialists until their inputs are appropriately needed.
The PD agreed to suspend the payment to DORP but date not mentioned.
3. Involvement of EMA
3.1 The MDSC team commented that EMA has been appointed too early they should have been appointed during RP implementation. Early appointment of EMA may hamper monitoring during implementation. However, the PD replied that EMA has been appointed according to ADB advice. The PD is expecting EMA to follow the land acquisition and start reporting on semi-annual basis as per their ToR.
BA mentioned that their Inception Report has not been approved yet by the PMU.
Team Leader of EMA has agreed
on semi-annual reporting but
beforehand they need to approve
their Inception Report by the
PMU.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 29 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Text Action on
1 As recommended by MDSC at the meeting held on 19 March 2017 in MDSC Office, DORP has confirmed
database migration from MS Access to MYSQL. From now onwards, DORP will use the software developed
using MySQL to enter and manage the data collected from the fields and later incorporate the additional
information to be collected from DC upon finalization of the list of EPs. They will also transfer the already
entered data in MS Access database and develop application for monitoring EP payments.
DORP
2 MDSC has advised DORP to prepare the system design document and submit it to MDSC for review within
2 weeks. DORP
3 The development of application in MY SQL will take 2-3 months, in the meantime they will use the data
recorded in MS Access and MS Excel for preparing the RPs.
DORP
Project title Management Design and Supervision Consultants, Dhaka Environmentally Sustainable Water Supply Project (DESWSP) under Dhaka Water Supply and Sewerage Authority (DWASA)
Subject Progress meeting on Development of AP Database
Location Meeting Room, MDSC Office
Date 30.03.2017
Time of meeting 2:30 pm to 4:00 pm
Project number 346152
Attendees
Name Initials Company/unit/division
Md. Mashiur Rahman MMR DORP, MIS Expert
Md. RakibulIslam MRI DORP, Database Manager
Preethi De Silva PDS MM MDSC, Monitoring and Evaluation (M&E) Expert
Shireen Akhter SA MM MDSC, Resettlement Expert
J L Leterme JLL MM MDSC, International Resettlement Specilaist
Dr. RafezaAkter RA MM MDSC, Social Development & Gender Specilaist
Md. Firoz Ahmed FA Livlihood Specilaist, DORP
Md. Hamayeet Uddin Chowdhury HUC IT & software Consultant, DORP
Md. Abdul Halim AH Resettlement Expert, DORP
Recorded by J L Leterme, MDSC, International Resettlement Specilaist&Preethi De Silva, M&E Expert, DESWSP
Distribution All Attendees
Team Leader/MM MDSC, Project Director/DESWSP, CEO/DORP
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 30 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Text Action on
4 DORP will continue and accelerate the collection of the IDs (husband and wife) and photos of the AHHs
which should constitute an Appendix of the RPs. DORP
5 DORP HAS promised to hire an editor to improve quality of witting of the RP. MDSC has advised DORP to
check in Section 2 RP and resubmit it for review. DORP
6 MDSC Team has advised to keep MMR (MS Access Developer) in application development team as he is
well familiar with RP databases and competent in design work. DORP
Text Action on
1 The PD informed that total no. of sections of Resettlement Plan (RP) has been divided into six (6)
sections instead of previously decided 7 sections. The sections are demarcated as follows:
Section-1: Water Intake Area
Section-2: Water Intake to Baliapara (End of Araihazar)
Section-3: Darikhandi Chak (start of Rupganj) to Murapara via Gandharbpur WTP
Section-4: Water Treatment Plant Gandharbpur Area
Section-5: Rupganj (West bank of Sitalakhya river) to Balu river (East bank)
DORP; for following
RP Update
Project title Management Design and Supervision Consultants, Dhaka Environmentally Sustainable Water Supply Project (DESWSP) under Dhaka Water Supply and Sewerage Authority (DWASA)
Subject Discussion on Resettlement and Safeguard Implementation Unit (SIU)
Location Conference Room, Project Management Unit (PMU), DESWSP
Date 10.04.2017
Time of meeting 11:30am to 3:00 pm
Project number 346152
Attendees
Name Initials Company/unit/division
Md. Mahmudul Islam MMI DESWSP, Project Director (PD)
Preethi De Silva PDS MM MDSC, Monitoring and Evaluation (M&E) Expert
Dr. RafezaAkter RA MM MDSC, Social Development & Gender Specilaist (SDGS)
Recorded by RA, MM MDSC, SDGS, DESWSP
Distribution All Attendees
Team Leader& Deputy Team Leader/MM MDSC, CEO/DORP
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 31 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Text Action on
Section-6: Balu river (West bank) to Vatara along Madani Avenue up to Baridhara
2 RA requested the PD to provide MDSC with the updated data on total land requirement (including
public and privately owned land) in each section of RP for project intervention. He stated that he
would provide all required data through email.
PD;
by this week (11 to 13
April 2017)
3 RA wanted to know the current status of serving notice to different sections from the Deputy
Commissioner’s office in terms of land acquisition and resettlement. The PD stated that Notice no.
6 has been served to the section 1 and section 2; Section 3, 5 and 6 are awaiting for Central Land
Acquisition meeting under the Ministry of Land
PD will check
4 To assist RP implementation under DESWSP, the DORP had prepared Terms of References (ToR)
for four (4) committees. The PD proposed the committees to the Ministry of LGRD and they
endorsed accordingly on 11 November 2015. Recently he has asked the MDSC safeguard team
for providing their comments on ToRs of 4 committees. Accordingly, Mr. J L Leterme, International
Resettlement Expert (IRE) sent his comments by e-mail and proposed that all Committees should
have one representative from the MDSC. Further, he said that the timeframe given to respond to
grievance at several levels in the TOR as 21 days should be followed by the DORP. DORP has
mentioned the timeframe in RP as 15 days.
RA stated that in Resettlement Advisory Committee (RAC) under point‘ d’ the term ‘stakeholder’ needs to be specified, i.e. who are those stakeholders other than DWASA, DC, local elite/UP
Chairman, affected persons, etc. In addition, she stated that one male and one female Displaced
Personnel representatives should be included in Grievance Redress Committee (GRC).
The PD has stated that representatives from DWASA will replace present ‘Conveners’ for all committees because project personnel should not act as conveners as it was proposed before.
Besides, he will add more tasks to the ToR. He would make a draft and would send to PDS for
comments.
PD+PDS will finalize
the ToR for all
Committees;
timeframe not
mentioned.
DORP will follow for
all sections of the RPs
5 PMU has formed a Safeguard Implementation Sub-Unit (SISU). RA commented that there is a
option in the PAM for only formation of Safeguard Implementation Unit (SIU), not Sub-unit. PDS
showed the relevant section number in Project Administration Manual (PAM) the PD. The PD has
agreed to reform SIU. He proposed to have two SIUs; one for Environmental Safeguard (ES) and
another for Social Safeguard (SS). SS-SIU will be headed by DPD-1 and ES-SIU will be headed by
one Executive Engineer. Safeguard Officer (Social, Gender and Resettlement) and Safeguard
Officer (Environment) of PMU will be members of the SS-SIU and ES-SIU respectively. In addition,
one Assistant Engineer (AE) will be appointed for each SIU.
The PD has requested PDS to make a list of tasks assignment for SIUs in line with the PAM. He
has also mentioned that MDSC National Resettlement Expert (NRE) will organize training for the
SIUs.
PD+PDS+NRE;
timeframe not
mentioned.
Text Action on
1 The PD instructed MDSC safeguard team to hold a meeting with staffs of DORP with regard to
market survey for WIA RP.
-
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 32 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Text Action on
2 JLL inquired how DORP staffs fixed the alignment of Right of Way (RoW) and geo-location on
satellite maps. They stated that their Surveyor worked with Project Management Unit (PMU)
Surveyor and Sub-Assistant Engineer to fix the alignment by using mouza map. Coordinates are
not used by them and they do not have any expert or efficient technical capacity to use GPS.
DORP will take
assistance from PMU
and MDSC for getting
coordinates.
3 DORP presented a general table to be used for Affected Households’ information and proposed compensation packages. MDSC team suggested to add more columns for more data like address
(district, upazila, union, mouza and village), National Identity (NID) number, plot wise land
information (plot nos., quantity of land, type of land, structures type, trees sizes) and proposed
compensation [Cash Compensation under Law (CCL) by the Deputy Commissioner (DC), Current
Market Value (CMV), Differentials, etc. as far as available from the DC)
DORP will incorporate
proposed improvements
by 23 April 2017
4 MDSC team requested the DORP to follow the standard reporting format for Market Survey. They
emphasized on inclusion of methodology in the market survey report as methodology is lacking.
The survey should also include details of the persons interviewed and should justified the choice of
these persons.
DORP will complete the
survey by the end of this
month (April 2017)
Project title Management Design and Supervision Consultants (MDSC), Dhaka Environmentally Sustainable Water Supply Project (DESWSP) under Dhaka Water Supply and Sewerage Authority (DWASA)
Subject Discussion on Market Survey Report for Water Intake Area (WIA) Resettlement Plan (RP)
Location Conference Room, MDSC, DESWSP
Date 23.04.2017
Time of meeting 12:00 am to 3:30 pm
Project number 346152
Attendees
Name Initials Company/unit/division
Jean Louis Leterme JLL MM MDSC, International Resettlement
Preethi De Silva PDS MM MDSC, Monitoring and Evaluation (M&E) Expert
Dr. Rafeza Akter RA MM MDSC, Social Development & Gender Specilaist (SDGS)
Md. Firoz Ahmed FA DORP, Livelihood Specialist
M. A. Halim MAH DORP, Resettlement Specialist
Recorded by RA, MM MDSC, SDGS, DESWSP
Distribution All Attendees
Project Director (PD), Team Leader and Deputy Team Leader, DESWSP; CEO,DORP
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 33 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Text Action on
5 The DORP was asked to finalize the report soon to be presented before the PVAC for
recommendation as well as endorsement by the PD and coordinate with the DC. DORP will
complete soon for
finalisation of the
entitlement packages
Project title Dhaka Environmentally Sustainable Water Supply Project (DESWSP) under Dhaka WASA (DWASA)
Subject Meeting on Budget Aproval for Resettlement Plan (RP) of Water Intake Area (WIA) and Progress of DORP
Location Conference Hall of Project Management Unit (PMU), DESWSP
Date 27.04.2017
Time of meeting 2:30 pm to 4:0 pm
Project number 346152
Attendees
Name Initials Org/unit/division
Md. Mahmudull Islam MMI Project Director (PD), DESWSP, DWASA
Md. Baharul Islam BI Deputy Project Director (DPD)-1, DESWSP, DWASA
Md. Mizanur Rahman MMR Executive Engineer (XEN), DESWSP, DWASA
M. Monirul Islam MI Senior Water Supply Engineer, DESWSP, DWASA
Md. Quaisarul Islam MQI MM MDSC, Deputy Team Leader (DTL)
Preethi De Silva PDS MM MDSC, Monitoring and Evaluation (M&E) Specialist
Dr. Rafeza Akter RA MM MDSC, Social Development and Gender Specialist (SDGS)
Joan louis laterme JLL MM MDSC, International Resettlement Expert (IRE)
Tofazzal Hossain TH Safeguard Officer (Social and Gender ), PMU, DESWSP
M.A. Halim MAH DORP, Resettlement Specialist
Md. Firoz Ahmed FA DORP, Livelihood Specialist
Md. Badiul Alam MBA Sub-Assistant Engineer (SAE), PMU, DESWSP, DWASA
Moh. Zobair Hasan ZH DORP, RPM
Nurunnahar NN DORP, Area Manager
Md. Ismail Hossain MIH DORP, Area Manager
Md. Ramjan Hossain MRH DORP,Surveyor
Lutfor Rahman LR DORP,Surveyor
Recorded by Tofazzal Hossen PMU, DESWSP and Dr.Rafeza Akter, MM MDSC DESWSP
Distribution All attendees + Team Leader, Deputy Team Leader, MM MDSC and Team Leader, Deputy Team Leader, DORP
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 34 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Text : Resettlement Plan and Implementation issues, Resettlement Specialist Action on
1 The PD welcome the participants of the meeting. -
2 The PD asked DORP regarding their latest status on RP submission and reasons for delay. The DORP
informed that they have updated the RP for section-1: Water Intake Area (WIA) as per MDSC’s advice and sumitted to the PMU, which he has already submitted to the ADB for their comments.
Now they are updating RP Section-2: Water Intake to Baliapara (End of Araihazar) as the MDSC refued to
give on commnents on the zero draft RP suspecting unreliable data. It will be submitted to the MDSC
thorugh PMU on 15 May 2017 for review.
DORP
3 Two kinds of liflets should be composed/printed; one for WTP area and another for other sections. PMU and DORP
4 The PD told that he will provide details with the LA case 3, 4, 5 and 6 that how many mouzas are covered
and what is the status of serving land acquisition notice in each area.
DORP
5 The Executive Engineer, Bangladesh Inland Water Transport Authoriy (BIWTA) has given a written approval
for using ttheir land for the DESWSP. At this moment he is in abroad, after his coming back a MoU will be
signed between both parties (BIWTA and DWASA) by 2 May 2017.
PMU and BIWTA
6 ADB review mission will come on 22 May 2017. In the upcoming ADB mission, the PD will talk about
reschedule the person-months of DORP who are engaged with DESWSP, DWASA.
PMU
7 DORP presented Current Market Value (CMV) for resettlement but PMU personnel were suspicious with
regard to authentic CMV data and prescribed for resurvey with new types of respondents as early as
possible. Afterwards, they will present the findings before the PMU and Property Valuation Advisory
Committee (PVAC) for recommendation.
DORP
8 If necessary, two computer operators will work in the office of DORP. PMU and DORP
9 Two Area Managers of the DORP will maintain regular coordination with the DC and PMU regarding
resettlement progress.
DORP
10 The PD requested the MDSC Resettlement Experts to provide him with a project in Bangaladesh, where
difference between Market Value of properties and DC’s payment rate was paid by the Project/Implementing/Executing Agency. He said that title of the project is enough as he can entrust PMU
staffs to get necessary details in order to convince management of DWASA.
JLL & RA
11 The PD has agreed to remind ADB with regard to approval of WTP RP (Section 4), whch was submitted to
ADB on 21 March 2017.
PD
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 35 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 36BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
D. Field Visit Report
To The Team Leader, MDSC
From Dr. Rafeza Akter, Social Development & Gender Specialist (SDGS), MDSC
Subject Field Visit to WTP on 21 May 2017
Date 23 May 2017
With reference to the Raw Water Pipeline area in Araihazar upazila my field visit report as follows:
I was accompanied by the International Environmental Expert and Monitoring & Evaluation Expert of MDSC. In addition, Md. Badiul Alam, Sub-
Assistant Engineer (SAE), and Md. Ashraf Ali, SAE from DWASA and two Resettlement Organizers of DORP namely Md. Anisur Rahman and
Faridur Rahman were also present.
Objective of the visit was to oversee DORP’s activities that they reach affected persons’ (APs) households. To ensure that the APs (especially
female APs) are informed and aware of entitlement, compensation and proper documentation that required for getting compensation. It is worth
mentioning that the DC has served land acquisition notice section 6 in the area.
Three locations of the pipe route were visited and discussed three Affected Persons (APs) randomly. It is found that all APs know about land to
be acquired. Their relevant information are as follows:
Information of Affected Persons (APs)
Sl. No.
Name of APs Age Occupation Village Land and other relevant information Phone no.
1 Mr. Abdur Rouf 85 Unemployed (aged)
Laxmipura He has three sons working as day laborers in nearby power loom factory. He has three 3 houses in his homestead land to be acquired. He purchased this land but he does not have any mutation deed along with him. He contacted land office but the respective officer seeks BDT 25000 as bribe. He is unable to pay that much money as he is very poor.
He or his family member could not tell the cell no. Anisur Rahman from DORP are requested to collect later.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 37BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Sl. No.
Name of APs Age Occupation Village Land and other relevant information Phone no.
2 Abdur Rashid 42 Farmer Laxmipura He merely owns 10 decimals of agricultural land which would be acquired by the project. His papers are up to date and he is mentally prepared to hand over the land against proper compensation.
01836880537
3 Parul Akter 30 Housewife Atadi She has three little girls. Her husband died nine months ago. She has 22 decimals land in joint ownership with their in-laws. Moreover, present Union Parishad (UP) Chairman and his brother has filed a case claiming ownership of 10 decimals of this land.
However, she owns 16 decimals pond area of her own which will also be acquired by the project. She needs attestation of the ownership documents from the UP office but they are not cooperating with her.
01959635799
Recommendation: The resettlement NGO and relevant government officials should help the APs in preparing legal documents for getting
compensation on due time as all of them are not well known about the process.
Mott MacDonald | Semi-Annual Social Safeguard Monitoring Report 38 BAN: Dhaka Environmentally Sustainable Water Supply Project (DESWSP) January-June 2017
346152 | 23 | A | 30 July 2017
Photos
Monitoring DORP’s Activities in Araihazar Field Office Public Gathering in Water Intake Area following Receipt of
Notice-6 & 7 and Required Papers
Meeting EPs in Raw Water Pipeline Area Visiting EPs house
Community Meeting at Water Treatment Plant Area Site Visit at Madani Avenue