smartmeter tm steering committee update – february 2012

14
©2011 Pacific Gas and Electric Company. All rights reserved. SmartMeter TM Steering Committee Update – February 2012

Upload: amalia

Post on 10-Feb-2016

89 views

Category:

Documents


1 download

DESCRIPTION

SmartMeter TM Steering Committee Update – February 2012. Agenda. Monthly Updates Release Status Update Deployment Status Update Schedule Update Deployment Update Budget Status – Expenditures by Workstream Budget Status – Benefits Issues / Risks Summary Program Metrics Appendix - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SmartMeter TM Steering Committee Update – February 2012

©2011 Pacific Gas and Electric Company. All rights reserved.

SmartMeterTM

Steering Committee Update – February 2012

Page 2: SmartMeter TM Steering Committee Update – February 2012

2Steering Committee February 2012 Report

Agenda► Monthly Updates

► Release Status Update

► Deployment Status Update

► Schedule Update

► Deployment Update

► Budget Status – Expenditures by Workstream

► Budget Status – Benefits

► Issues / Risks Summary

► Program Metrics

► Appendix

► Project Deployment Plan Progress

► Contingency Reconciliation

► SmartMeterTM Acronyms

Page 3: SmartMeter TM Steering Committee Update – February 2012

3Steering Committee February 2012 Report

Release Status Update

Challenges Actions/Status

EAC Funded Budget ITD Scope Schedule Resources Issues Risks

IT Releases: January 31, 2012

Release 1

Release 2

Release 3

Overall▪ IT continues to execute against the plan produced as output from the

Reconstruct effort. HAN enablement and Peak Time Rebate roadmaps are in progress.

Release 1▪ Provide model office, exception management for interval billing, and

performance & scalability improvements.

Release 2▪ Complete the integration of SmartMeterTM data to the existing outage

systems. This includes using the meter “last gasps,” “restoration,” and meter ping capabilities. Added electric head-end system upgrade to scope of this release to enable Secure Port and firmware push. Remote Connect/Disconnect phase 2 (RCD) and performance and scalability improvements are also part of this release.

Release 3▪ Improvements to meter data exception handling, NEMs deployment,

scalability improvements for the data warehouse, and tracking of momentary outages.

Overall▪ Project stabilization work complete for all components except MV90 and NEMs.

Release 1▪ Deployment of Release 1 on 7/29/11 with no issues. ▪ Project stabilization complete 9/1/11.

Release 2▪ Deployment complete 9/30/11.▪ Project stabilization complete 11/30/11.

Release 3▪ Deployment of all in-scope functionality except MV90 completed by 11/30.▪ Stabilization for all deployed components except NEMs is complete.▪ Resolution for MV90, NEMs and FSU upgrade (March 2012) issues underway.

▪ Currently testing delivered MV90 MDM vendor fixes▪ Preparing documentation for MV90 controlled deployment.▪ Awaiting resolution proposal for NEM MDM issues from vendor (ETC 2/29).

Page 4: SmartMeter TM Steering Committee Update – February 2012

4Steering Committee February 2012 Report

Deployment Status Update

Actions/StatusChallenges

EAC 2012 Forecast

(2012 EOY / CPI)

Scope Schedule Resources Issues Risks

Deployment: January 31, 2012

Endpoints (2012 YTD) *

Gas Network (2012 YTD)

Electric Network (2012 YTD)

* 2012 Schedule and installation targets under review

Endpoints▪ Workflow slow down. ▪ Increased rate of ‘Unable-To-Completes’ due to non-standard meter

installations in heavy urban areas and access refusals.▪ Cost-per-install higher than planned due to resource mix.

Electric Network▪ Complete electric network deployment, initial design scope.▪ Whether additional electric network is necessary is subject to ongoing

review.

Gas Network▪ Complete gas network deployment, initial design scope.▪ Whether additional gas network is necessary is subject to ongoing review.

Endpoints▪ Working with installation contractor to update 2012 deployment schedule.▪ Working with installation contractor to routinely review UTCs and resolve

them.▪ T-300 team assigned to supplement Gas Meter Swivels and Exchanges in

San Francisco and resolving 1S/2S electric exchanges.

Electric Network▪ Working with technology supplier and internal stakeholders to address

network coverage in ‘hard-to-reach’ areas.

Gas Network ▪ Network coverage issue to be resolved before the end of deployment.

Page 5: SmartMeter TM Steering Committee Update – February 2012

5Steering Committee February 2012 Report

2012

Legend

Schedule Update

Benefits

Field Delivery

Approved Milestone (delay)

‘Initial Design’ Network Deployed

Meter Reading Reductions (ITD)

As of 1/31/12

Forecasted Milestone (delay)Milestone MetBaseline Milestone

Forecasted Milestone (early) Milestone TBD

590 Positions Captured

9.0M Meters/Modules in service

Jun

IT Release Deployment

Release 2

Release 3

SM Operations Center

Release 1

Apr May OctSepAugJul Nov Dec

SMOC Phase 1.0 Deploy

Remote Connect Disconnect

Outage Identify & Scope

Exception Management Improvements and NEMs deploy

Exception Management Improvements and Momentary Outage Tracking

Performance & Scalability Improvements

Performance & Scalability Improvements

Exception Management Improvements

Electric ‘head-end’ system upgrade

FebJan Mar2011

Page 6: SmartMeter TM Steering Committee Update – February 2012

6Steering Committee February 2012 Report

Deployment UpdateAs of February 3, 2012

#s as of 02/3/122012 Targets under review

Page 7: SmartMeter TM Steering Committee Update – February 2012

7Steering Committee February 2012 Report

2012 Budget Status – Expenditures by Workstream

Year-to-Date Variance Explanations:Unfavorable YTD capital variance ($0.7M) primarily due to timing of IT spend of -$1.1M (#5), offset by fewer meter/module installations of $0.6M (#3).Favorable YTD expense variance ($0.6M) due to timing associated with: 1) underruns in Customer of $0.3M (#10) and Business Operations/PMO of $0.2M (#7).

# Work Stream Budget Actual Variance Budget Actual Variance #

A. Capital (000s)

1 BUSINESS OPERATIONS (PMO) $262 $331 ($68) $262 $331 ($68) $1,873 $49,633 1

2 SM OPERATIONS $0 $0 $0 $0 $0 $0 $0 $11,310 2

3 SM FIELD DELIVERY $5,314 $4,719 $595 $5,314 $4,719 $595 $57,106 $406,069 3

4 SM SOLUTIONS $863 $972 ($109) $863 $972 ($109) $19,752 $974,050 4

5 IT $701 $1,810 ($1,108) $701 $1,810 ($1,108) $10,480 $371,436 5

6 Capital Total: $7,141 $7,831 ($690) $7,141 $7,831 ($690) $89,739 $1,812,498 6

B. Expense (000s)

7 BUSINESS OPERATIONS (PMO) $240 $18 $222 $240 $18 $222 $1,357 $26,358 7

8 SM OPERATIONS $0 $0 $0 $0 $0 $0 $0 $56,594 8

9 SM CHANGE MANAGEMENT $0 ($11) $11 $0 ($11) $11 $150 $14,834 9

10 CUSTOMER $479 $155 $324 $479 $155 $324 $17,723 $97,194 10

11 SM FIELD DELIVERY $47 $1 $46 $47 $1 $46 $420 $17,994 11

12 SM SOLUTIONS $0 $11 ($11) $0 $11 ($11) $2,218 $68,000 12

13 IT $395 $361 $35 $395 $361 $35 $5,332 $133,484 13

14 Expense Total: $1,162 $535 $627 $1,162 $535 $627 $27,199 $414,459 14

C. Total: Capital + Expense (000s)

15 BUSINESS OPERATIONS (PMO) $502 $349 $154 $502 $349 $154 $3,229 $75,991 15

16 SM OPERATIONS $0 $0 $0 $0 $0 $0 $0 $67,904 16

17 SM CHANGE MANAGEMENT $0 ($11) $11 $0 ($11) $11 $150 $14,834 17

18 CUSTOMER $479 $155 $324 $479 $155 $324 $17,723 $97,194 18

19 SM FIELD DELIVERY $5,361 $4,720 $640 $5,361 $4,720 $640 $57,526 $424,063 19

20 SM SOLUTIONS $863 $983 ($120) $863 $983 ($120) $21,970 $1,042,050 20

21 IT $1,097 $2,170 ($1,073) $1,097 $2,170 ($1,073) $15,811 $504,920 21

24 Capital + Expense Total: $8,303 $8,366 ($64) $8,303 $8,366 ($64) $116,938 $2,226,957 24

Current Month - January Year to Date - January 2012AnnualBudget

Inception to Date Actual

*Revised based on final 2012 deployment schedule and timing.*Revised based on final 2012 deployment schedule and timing.

**

Page 8: SmartMeter TM Steering Committee Update – February 2012

8Steering Committee February 2012 Report

2012 Budget Status – Benefits

2007 2008 2009 2010 2011 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec ITD Actual #

1 Activated Meter Benefits: 111$ 4,705$ 26,055$ 56,313$ 20,269$ 2,479$ 2,412$ 2,452$ 2,492$ 2,533$ 2,575$ 2,617$ 2,660$ 2,704$ 2,749$ 2,794$ 2,840$ 109,932$ 1

2 Mainframe License Benefits: 1,250$ 5,000$ 5,000$ 5,000$ 5,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 21,250$ 2

3 Total: 1,361$ 9,705$ 31,055$ 61,313$ 25,269$ 2,479$ 2,412$ 2,452$ 2,492$ 2,533$ 2,575$ 2,617$ 2,660$ 2,704$ 2,749$ 2,794$ 2,840$ 131,182$ 3

4 2012 Cumulative Actual + Forecast: 2,479$ 4,891$ 7,343$ 9,835$ 12,368$ 14,943$ 17,560$ 20,221$ 22,925$ 25,674$ 28,468$ 31,308$ 4

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Budgeted Benefits:5 Monthly 2,373$ 2,412$ 2,452$ 2,492$ 2,533$ 2,575$ 2,617$ 2,660$ 2,704$ 2,749$ 2,794$ 2,840$ 5

6 Cumulative 2,373$ 4,785$ 7,237$ 9,729$ 12,262$ 14,837$ 17,454$ 20,115$ 22,819$ 25,568$ 28,362$ 31,202$ 6

Actual / Current Forecast:7 Monthly 3,724$ 2,412$ 2,452$ 2,492$ 2,533$ 2,575$ 2,617$ 2,660$ 2,704$ 2,749$ 2,794$ 2,840$ 7

8 Cumulative 3,724$ 6,136$ 8,588$ 11,080$ 13,613$ 16,188$ 18,806$ 21,466$ 24,170$ 26,919$ 29,713$ 32,553$ 8

9 YTD Variance 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 1,351$ 9

*

**

#

($ in thousands)

2011 and 2012 SmartMeter Balancing Account (SBA) actuals and forecasts consistent with the GRC Settlement of $0.92 electric / $0.02 gas activated meter-month savings and the discontinuation of mainframe license savings already captured in the 2008 base year results

2012 benefits, budget versus actual and forecast, do not include meter reading costs and benefits which are being recorded in the Meter Reading Memorandum Account beginning on January 1, 2011.

($ in thousands)

SmartMeter Balancing Account (SBA) Credits *

2012 Benefits, Budget vs. Actual and Forecast **

Actual Remaining Budget

Page 9: SmartMeter TM Steering Committee Update – February 2012

9Steering Committee February 2012 Report

Issues Summary

Target Resolution Date Issue Impact Status Summary

Ongoing

Increasing number of installations affected by access refusals.

Increased costs, increase in unable to complete (UTC) back-log, customer change management.

Pursuing operational improvements to increase efficiency of UTC resolution. Ongoing engagement with customers across multiple communication channels to enhance customer understanding of SmartMeterTM program and benefits. Customer option to temporarily delay SM upgrade being offered, pending CPUC decision on PG&E’s opt-out application.

Page 10: SmartMeter TM Steering Committee Update – February 2012

10Steering Committee February 2012 Report

Risks Summary# Created On I P Score Prev.

Score Risk Impact Status Summary Assoc. Issue

1 9/30/2011 5 4 20 20 Increased forecast deployment costs and external resources requirement

Key drivers: Delays in deployment, resource availability and installation complexity

Increased installation costs and contract resources required to complete remaining installations effectively and timely

Working with Sourcing and suppliers to complete contracting process. Pursuing other identified opportunities to offset additional installation costs and increase installation efficiency within ongoing operations.

3 4/4/2008 5 3 15 15 Business processes enabled by new technology may not perform as intended.

Key drivers: Increased data volume and validation, underlying business processes.

Billing errors, customer complaints, inability to meet endpoint deployment goals.

Continuing to monitor technology performance and identifying mitigations to resolve any identified technology performance issues. Meter transition process checks updated to include new integrated standards with supplier for validating network design, meter connectivity and read performance. Planning for Full Deployment/Interval Billing via functionality deployments and additional process capability initiatives through 2011 underway.

4 9/1/2011 5 3 15 15 Network deployment and performance in ‘hard-to-reach’ areas can not be completed successfully.

Key drivers: Network performance in ‘hard-to-reach’ areas and availability of alternate solutions.

Deployment delays, resource planning and increased costs.

Pursuing resolution of network coverage in ‘hard-to-reach’ areas with technology supplier, including potential alternate network solutions.

Finalization of network design/equipment mix to complete network deployment in process with suppliers.

Page 11: SmartMeter TM Steering Committee Update – February 2012

11Steering Committee February 2012 Report

Program Metrics

#s as of 01/31/122012 Targets under review

December '11 January '12 Variance AnalysisMetric Key Performance Indicator Actual Target Var Actual Target Var Actual Target Var Actual Target Var

P1 SM Earnings Contribution ($M - estimated)

5.9$ 5.9$ 0.0% 5.5$ 5.5$ 0.0% 5.5 5.5 0.0% 71.2$ 70.8$ 0.6%

P2 OSHA Recordable Rate (YTD) 1.70 0.51 - 0.51 - 0.51

P3 MVI Recordable Rate (YTD) 3.10 0.98 - 0.98 - 0.98

C1 Customers enrolled in SmartRate (net)

22,136 (track only) 22,014 (track only)

C2 # of CPUC escalated Customer Complaints

5 (track only) 10 (track only) 10 (track only)

C10 Customer Complaint Rate (escalated to CPUC)

0.008% (track only) 0.020% (track only) 0.020% (track only)

D1Meters/Modules Installed -

Electric & Gas 65,008 175,072 -63% 49,736 TBD 49,736 TBD TBD TBD 2012 Targets under review

D5 UTC Rate 18.8% 5.0% 277% 18.1% TBD 18.1% TBD 8.4% TBD 2012 Targets under review

D7 UTCs open beyond 90 days 203,957 (track only) 213,485 (track only)

D8 CPI - Endpoints $74.87 $45.48 64.6% $80.22 TBD $80.22 TBD $82.97 TBD 2012 Targets under review

D14 Total Weeks of Inventory on Hand - Electric Meters

9 6 50.0% 6 6 0.0%

D15 Total Weeks of Inventory on Hand - Gas Modules

11 6 83.3% 10 6 66.7%

O4 Transition Aging - Average Days 154 (track only) 93 (track only) 93 152 (track only)

O5 SM Billing accuracy % (SA) 99.92% 99.88% 0.0% 99.95% 99.88% 0.1% 99.95% 99.88% 0.1% 99.88% 99.88% 0.0%

O6 SM Billing timeliness % (SA) 99.89% 99.79% 0.1% 99.92% 99.79% 0.1% 99.92% 99.79% 0.1% 99.79% 99.79% 0.0%

O7 SM % Bills not estimated (BSEGs)

99.92% 99.90% 0.0% 99.95% 99.90% 0.1% 99.95% 99.79% 0.2% 99.90% 99.90% 0.0%

B2 Meters Activated - Electric & Gas (end of month)

151,291 (track only) 243,191 (track only) 243,191 (track only) 850,412 (track only)

2012 Year End ForecastYTDMonth Results Month Results

Page 12: SmartMeter TM Steering Committee Update – February 2012

12Steering Committee February 2012 Report

Project Deployment Plan Progress

2012 Targets under review

Page 13: SmartMeter TM Steering Committee Update – February 2012

13Steering Committee February 2012 Report

Contingency Reconciliation

Page 14: SmartMeter TM Steering Committee Update – February 2012

14Steering Committee February 2012 Report

SmartMeterTM Acronyms Acronym Definition Acronym Definition

ABS Advanced Billing System MARA My Account Re-ArchitectureAFCI Arc Fault Circuit Interrupter MDMS Meter Data Management SystemAMI Advanced Metering Infrastructure MLPP Meter Location Problem ProjectAP Access Point MPSC Meter Power Status CheckApps Applications MV-90 Multi Vendor - 90ASM Automated Storage Management MVI Motor Vehicle IncidentsBDG Business Development Group NEMS Net Energy Metering ServicesCC&B Customer Care and Billing NIC Network Interface CardCEDSA Centralized Electric Distribution System Assets OIR Order Instituting RulemakingCoE Center of Excellence OIS Outage Information SystemCPI Cost Per Install OMT Outage Management ToolsCPUC California Public Utilities Commission Ops OperationsDART Distribution Asset Reconciliation Tool OSHA Occupational Safety and Health AdministrationDC Data Center PCR Project Change RequestDCU Data Collector Unit PCT Programmable Communicating ThermostatDR Disaster Recovery PDP Peak Day PricingDRA Division of Ratepayer Advocates PDR Project Decision RequestDSCI Distribution Control Systems, Inc. PE Perfomance Engineering CompanyEA Ecologic Analytics PMO Project Management OfficeEAC Estimate at Completion PTR Peak Time RebateED Energy Division QBR Quarterly Business ReviewEMR Electric Meter Reader RCDC2 Remote Disconnect Phase 2EMT Electric Meter Technician Rev. RevisionEOM End-of-Month RF Radio FrequencyEON Emergency Outage Notification RFA Request For AuthorizationEOY End Of Year RV Restoration ValidationFA Functional Area SBA SmartMeter Balancing AccountsFD Field Delivery SM SmartMeterGE General Electric Co. SM Apps SmartMeter ApplicationsGFI Ground Fault Interrupter SMU SmartMeter UpgradeHAN Home Area Network SR Service RequestHC Head Count TBD To Be DeterminedIHD In-Home Devices TechArch Technical ArchitechtureISTS Information Systems and Technology Services TIC Technology Innovation CenterIT Information Technology TLM Transformer Load ManagementITD Inception To Date TOU Time Of UseIVR Interactive Voice Response UIQ Utility IQ - SSN softwareKC Knowledge Center UTC Unable To Complete (meter installation)KVAR Kilo-Volts-Amps Reactive YTD Year-To-DateLOB Line of Business

SmartMeter Acronyms