slides for pm web · earned value (ev) this is also described as the budgeted cost of work...
TRANSCRIPT
![Page 1: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/1.jpg)
Project ManagementProject Management
Merrie Barron, PMPand
Andrew R. Barron
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 2: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/2.jpg)
What is a Project Manager?What is a Project Manager?
100% responsible for the processes needed to managea project to a successful conclusion.
Managing the overall schedule to ensure work isassigned and completed on time and within budgetand in scope.
Identifying, tracking, managing and resolving projectissues
Identifying, responding to and managing project risk. Proactively communicating project information to all
stakeholders
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 3: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/3.jpg)
Who are the stakeholders?Who are the stakeholders?
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 4: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/4.jpg)
What is a Project Manager? What is a Project Manager? ((contdcontd.).)
Process Responsibilities Ensuring that the solution is of acceptable quality.
Proactively managing scope to ensure that only whatwas agreed to is delivered, unless changes areapproved through scope management
Defining and collecting metrics to give a sense forhow the project is progressing and whether thedeliverables produced are acceptable.
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 5: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/5.jpg)
What is a Project Manager?What is a Project Manager?
People ResponsibilitiesGeneral management skills needed to establishprocesses and make sure that people follow them
Leadership skills to get the team to willingly follow yourdirection (team building, motivational)
Sets reasonable, challenging and clear expectations ofpeople (proactive verbal and written communication)
Hold team members accountable for meeting theexpectations (performance feedback)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 6: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/6.jpg)
Project Management Areas ofProject Management Areas ofResponsibilityResponsibility
Establish objectives that can beachieved
Identify the requirements for the project Satisfy everyone’s needs Balance scope, time and cost (Triple
Constraint)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 7: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/7.jpg)
The Triple ConstraintThe Triple Constraint
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 8: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/8.jpg)
Scope CreepScope Creep
Add Time- delay the project to give you
more time to add the functionality ($)
Add Cost- recruit, hire or acquire more
people to do the extra work ($)
Cut Quality- trade off some non-essential
requirements for the new requirements ($)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 9: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/9.jpg)
Project Life CycleProject Life Cycle
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 10: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/10.jpg)
Initiating a ProjectInitiating a Project
A business case is created to define the problem oropportunity in detail and identify a preferred solution forimplementation
• A detailed description of the problem or opportunity• A list of alternative solutions available• An analysis of the business benefits, costs, risks and
issues• A description of the preferred solution• A summarized plan for implementation
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 11: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/11.jpg)
Define the project objectivesDefine the project objectives
Establish clear and realistic objectives
Good objectives are “clearly stated” andcontain a “measure” of how to assesswhether they have been achieved.
To be realistic, objectives must be “determinedjointly” by managers and those who performthe work.
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 12: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/12.jpg)
SMART ObjectivesSMART Objectives
Specific (get into the details) Measurable (use quantitative language
so that you know when you arefinished)
Acceptable (to Stakeholders) Realistic (given project constraints) Time Based (deadlines, not durations)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 13: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/13.jpg)
Project objective statementProject objective statement
State the objective of your project; what isthe business benefit?
The objectives should be concisely written sothey can be evaluated after the completion ofthe project to see whether they wereachieved
The objectives should be specific,measurable, attainable, realistic and timebound. (SMART)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 14: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/14.jpg)
Project PlanningProject Planning
Scope Planning; Specifies the Requirements forthe project
Preparing the Work Breakdown Structure
Project Schedule Development
Resource, Budget, Procurement, Quality andCommunication plans are created
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 15: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/15.jpg)
Scope PlanningScope Planning
How do you define Scope?
What are the deliverables you and your teamwill produce for the project?
What will your project deliver?
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 16: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/16.jpg)
Scope StatementScope Statement
The project scope statement may include: Product Scope Project Scope Deliverables Product/ Project acceptance criteria What is not part of the project Constraints or Assumptions
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 17: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/17.jpg)
Project RequirementsProject Requirements
Requirements answer the following questionsregarding the AS IS and TO BE states of thebusiness(who, what, where, when, how much, how does a
business process work)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 18: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/18.jpg)
Types of RequirementsTypes of Requirements Regulatory: Internal and external; usually non negotiable
Business: needs of the sponsoring organization; always from amanagement perspective
User: What the users need to do with the system or product
Functional and Non Functional : What the system needs to beable to do to satisfy the business and user needs in terms offunction and functionality
Technical: How the system needs to be designed andimplemented to provide required functionality and fulfillrequired operational characteristics.
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 19: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/19.jpg)
Work Breakdown Structure (WBS)Work Breakdown Structure (WBS)
Provides a framework for organizing and
managing the approved project scope
Helps ensure you have defined all the work
that makes up the project
Provides a framework for planning and
controlling costs and schedule information
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 20: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/20.jpg)
Sequence the ActivitiesSequence the Activities
What comes first, second, third, etc.
Look for relationships between activities
What can be done in parallel?
What activities must wait for others tocomplete?
Begin to identify the milestones
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 21: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/21.jpg)
Network DiagramNetwork Diagram
One Start and One End
Collection of any set of related tasks is apath.
All tasks have at least one predecessor(except the beginning)
All tasks at have at least one successor(except the end)
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 22: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/22.jpg)
Assign ResourcesAssign Resources
Assign specific resources if known Assign generic resource roles
– “programmer 1”, “technical writer 1” Check for resource over-allocation or
under allocation
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 23: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/23.jpg)
Estimate DurationEstimate Duration
Factor in productive hours per day Factor in available workdays Determine how many resources on each
activity Take into account any part-time resources Calculate delays and lag times
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 24: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/24.jpg)
Estimate the DurationEstimate the Duration
Bottom Up Estimating Break down the work Estimate all work at the detailed level Add up the estimates for all detailed
activities Apply estimating techniques at the
activity level
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 25: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/25.jpg)
Estimation TechniquesEstimation Techniques
Expert Opinion Individual who has done it many times Internal or External to the organization Industry expert Utilize for new technology or unfamiliar
with the subject
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 26: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/26.jpg)
Estimation TechniquesEstimation Techniques
Published Estimating Data Articles Books Journals periodicals
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 27: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/27.jpg)
Estimating TechniquesEstimating Techniques
Previous history (actual hours tracked) Analogy (similar, not exact)
– Look for similar projects from the past
Example: Chicago project is 500 hours.Atlanta is similar size
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 28: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/28.jpg)
Estimating TechniquesEstimating Techniques
Ratio– Characteristics of project allow comparison– Projects are similar but different scale– The main factors that drive the effort are similar
Example- Chicago project is 500 hours. Orlando is half asbig. New York is twice as big
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 29: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/29.jpg)
Estimate the EffortEstimate the Effort
Parametric Modeling Characteristics of project allows use of a
model Use statistics, formulae, spreadsheets
Example- Highway is $1 million perlane per mile. How much for 10 milesof four lane highway?
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 30: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/30.jpg)
Critical PathCritical Path
Provides a graphical view of the project Predicts the time required to complete the project Shows which activities are critical to maintaining
the schedule and which are not. Demonstrates the longest path of the project Drives the project completion date Any delay will cause the entire project to be
delayed
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 31: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/31.jpg)
Calculating Critical PathCalculating Critical Path
Calculated automatically by projectmanagement tool
Can calculate manually byunderstanding early start, earlyfinish, late start and late finish
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 32: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/32.jpg)
Manage to the Critical PathManage to the Critical Path
If a critical path activity will not meet its enddate:– “Fast Track”-Overlap tasks or run in
parallel
– “Crash”-Additional resources to complete activities more quickly
– Swap resources with more experiencedresources
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 33: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/33.jpg)
Estimate CostEstimate Cost
Now you estimate the costs Determine the cost of labor, internal and
external Include all non-labor costs including:
– Hardware and software– Travel expenses– Training– Team building– Facilities– Maintenance/support costs
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 34: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/34.jpg)
Planned value and actual costPlanned value and actual cost
These are measures of the budgeted costs of work scheduled(PV) and actual cost of work performed (AC)
Planned value = total cost of the work scheduledPV = Hourly rate x total hours planned (scheduled)
Actual costs = earned value / planned valueAC = Hourly rate x total hours spent
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 35: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/35.jpg)
Earned value (EV)Earned value (EV)
This is also described as the budgeted cost of work performed(BCWP). This is the total cost of the work completed(performed) as of the reporting date.
Earned value = baseline cost x % work actually completed
% work actually completed = AC/EAC
EAC = Estimated at completion = estimated cost of the projectat the end of the project
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 36: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/36.jpg)
Schedule variance and scheduleSchedule variance and scheduleperformance indicatorperformance indicator
These are measures of how close the work is to beingaccomplished on schedule (SV) and the efficiency of utilizationof time (SPI)
Schedule variance = earned value – planned valueSV = EV – PV
If SV is negative then the project is behind scheduleIf SV is positive then the project is ahead of schedule
Schedule performance indicator = earned value / planned valueSPI = EV / PV
If CPI is > 1 then the project is efficient in utilizing timeIf CV is < 1 then the project is inefficient in utilizing time
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 37: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/37.jpg)
Cost variance and costCost variance and costperformance indicatorperformance indicator
These are measures of how close the work is to beingaccomplished on budget (CV) and the efficiency ofutilization of resources (CPI)
Cost variance = earned value – actual costCV = EV – AC
If CV is negative then the project is over budgetIf CV is positive then the project is under budget
Cost performance indicator = earned value / actual costCPI = EV / AC
If CPI is > 1 then the project is efficient in utilizing resourcesIf CV is < 1 then the project is inefficient in utilizing resources
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 38: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/38.jpg)
Project CloseProject Close
End of Project– Gain final approvals– Close the project– Final performance reviews– Gather final project metrics– End of Project meeting– Reallocate project staff– Turnover deliverables to support/operations– Close all contracts
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission
![Page 39: Slides for PM web · Earned value (EV) This is also described as the budgeted cost of work performed (BCWP). This is the total cost of the work completed (performed) as of the reporting](https://reader035.vdocuments.us/reader035/viewer/2022070917/5fb777ed539e4c22634d02a8/html5/thumbnails/39.jpg)
Project CloseoutProject Closeout
At project closeout, the project shouldbe evaluated, and all lessons learned
formally documented
Copyright: Barron and Barron (2014)No unlicensed reproduction without permission