slides

46
07-03-2014 1 LEAN MANUFACTURING Module-2 1 POM04 Value Stream Mapping A very powerful tool for implementing the lean transformation process is Value Stream Mapping (VSM). Value stream mapping is a pencil and paper tool that helps you to see and understand the flow of material and information as a product makes its way through the value stream. A value stream is all the actions (both value added and non- value added) currently required to bring a product through the main flows essential to every product. 2 Value Stream Mapping Current State Map Follow a product’s production path from customer to supplier, and carefully draw a visual representation of every process in the material and information flow. Future State Map Ask a set of key questions and draw the map of how value should flow in the future (desired flow). 3 Value Stream Mapping 4

Upload: pravit08

Post on 19-Oct-2015

13 views

Category:

Documents


0 download

DESCRIPTION

lean

TRANSCRIPT

  • 07-03-2014

    1

    LEAN MANUFACTURING

    Module-2

    1

    POM04

    Value Stream Mapping

    A very powerful tool for implementing the lean transformation

    process is Value Stream Mapping (VSM).

    Value stream mapping is a pencil and paper tool that helps you

    to see and understand the flow of material and information as

    a product makes its way through the value stream.

    A value stream is all the actions (both value added and non-

    value added) currently required to bring a product through the

    main flows essential to every product.

    2

    Value Stream Mapping

    Current State Map

    Follow a products production path from customer to supplier, and

    carefully draw a visual representation of every process in the

    material and information flow.

    Future State Map

    Ask a set of key questions and draw the map of how value should

    flow in the future (desired flow).

    3

    Value Stream Mapping4

  • 07-03-2014

    2

    Value Stream Mapping5

    Steps

    Select one value stream - a product familyWalk the physical flow of material no data collectionWalk the flow again, collecting dataDraw the Current State MapIdentify opportunities to eliminate waste and create flowDraw the Future State MapGenerate a Value Stream PlanStart making the improvementsConduct Value Stream ReviewsRepeat the cycle

    Selecting a Product Family6

    A Product Family

    A family is group of products that pass through similar processing steps and over common equipment in the downstream process and have similar work

    contents.

  • 07-03-2014

    1

    Value Stream Mapping Icons1

  • 07-03-2014

    2

    Value Stream Mapping Icons2

  • 07-03-2014

    3

    Value Stream Mapping Icons3

  • 07-03-2014

    1

    Terms one should know before mapping

    1

    Customer Need

    Demand : Number of units per day the customer wants.

    Available Working Time: Scheduled working time minus breaks ,meetingand clean up time

    Inventory

    WIP : Number of units waiting to be worked on or waiting to be moved.

    Finished: Number of units in stores or waiting to be shipped .

    Terms one should know before mapping

    2

    Each Process StepCycle Time : The time between one part coming off the process and thenext part coming off.

    Number of people: Required to operate the process

    Uptime: The percentage of time the equipment is available to run ,whenit is needed to run

    Batch Size: Typical lot size or minimum.

    Change Over Time: The time from the last good piece of one batch to thefirst good piece of the next batch.

    EPE..Every part every ____ .How often do you changeover to producethis part.

    Terms one should know before mapping

    3

    Each Process Step

    Takt Time TT : Available time per day/demand per day.

    Inventory(Measured in days) = Number of units /demand perday

    Overall Flow

    Process Lead Time : The time for a unit to make all the way through the process (Sum of Inventory days + Sum of Cycle times).

    Processing Time: The time actually spent performing work on the unit(Sum of Cycle times)

    4

    ACME STAMPING CASE

    STUDY

  • 1

  • 2

  • 3

  • 4

  • 5

  • 6

  • 3/7/2014

    1

    Whats wrong with Acmes Value Stream?

    1

    Traditional mass production thinking about economies of scale

    Batches pushed through = Waste

    Look at VA time compared to time in plant

    LEAN MANUFACTURING

    Module-2 & Module-3

    2

    POM04

    Draw the Future State3

    The Purpose

    Highlight the Sources of Waste

    Eliminate them

    In short period of time

    The Goal

    To build a chain of production where the individual processesare linked to the customer(s) either by continuous flow(the best ) or

    pull and each process gets as close as possible to producing only

    what the customers(need) when they need it

    Guidelines for Drawing a Future State

    Guideline#1 Produce to Takt Time

    4

    What is the Takt Time for the chosen Product family?

    Takt time = Available working time = 27600 seconds per shift = 60 seconds

    Customer demand 460 units per shift

    This Takt time means in order to meet the customer demand in

    the available time Acme needs to produce a steering bracket

    every 60 seconds in its assembly operation

    This number does not include time for equipment downtime,

    change overs between left and rightdrive brackets or

    scrap and rework

  • 3/7/2014

    2

    Guidelines for Drawing a Future State

    Guideline#2 Develop Continuous flow when ever possible

    5

    Continuous flow refers to one piece at a time ,with each item is passed from one processing step to the next without stagnation (and

    many other wastes) in between

    Continuous flow is the most efficient way to produce and one should use lot of creativity in trying to achieve it.

    Guidelines for Drawing a Future State

    6

    Isolated Islands

    Continuous Flow

    Guidelines for Drawing a Future State

    7

    Guideline#3 Use Supermarkets to control production where continuous

    flow does not extend upstream

    There are often spots in the value stream where continuous flow is not possible and

    batching is necessary. There can be several reasons for this including

    Some processes operate at very fast or slow cycle times.

    Some processes need to changeover to serve multiple product families( e.g. stamping orinjection molding)

    Some processes, such as those at suppliers, are far away and shipping one at a time isrealistic.

    Some processes have too much lead time or are too unreliable to couple directly to otherprocesses in a continuous flow

    Guidelines for Drawing a Future State

    8

    Install a pull system where continuous flow is interrupted(even when theupstream process must still operate in a batch mode

    A production kanban triggers production of parts while a

    withdrawal kanban is a shopping list that instructs the material handler to

    get and transfer parts

  • 3/7/2014

    3

    Guidelines for Drawing a Future State

    9

    Guideline#4 Try to send the customer schedule to only one production

    process

    By using supermarket pull systems you will typically need to schedule only onepoint in your door-to-door value stream. This point is called the pacemaker

    process because how you control production at this process sets the pace for all

    upstream processes.

    So the pacemaker is frequently the most downstream continuous flow processin the door-to-door value stream . On the future state map, the pacemaker is the

    production process that is controlled by the outside customers orders.

    Guidelines for Drawing a Future State

    10

    Guidelines for Drawing a Future State

    11

    Guideline#5 Leveling the production mix at the pacemaker

    Leveling the product mix means distributing the production of different products evenly over a time period .

    For example instead of assembling all the "Type A products in the morning and all the Type B in the afternoon ,leveling the mix

    means alternating repeatedly between smaller batches of A

    and B.

    Guidelines for Drawing a Future State

    12

    The icon for production leveling is this symbol, which is inserted into an

    information flow arrow.

  • 3/7/2014

    4

    Guidelines for Drawing a Future State

    13

    Guideline#6 Leveling the production volume

    Regularly release only small,consistent amount of work(usually between 5-60min worth) at the pacemaker process and simultaneously take away an equal

    amount of finished goods.We call this practice a paced withdrawal.

    We call the consistent increment of work the pitch, and often calculate thepitch increment based on packout container quantity(the number of parts one

    finished goods container holds) or a multiple or fraction of that quantity

    For example, if the takt time = 30 seconds and the pack size = 20 pieces, then

    pitch = takt time pack size= 30 sec 20 pcs = 10 minutes

    Guidelines for Drawing a Future State

    14

    Guideline#6 Leveling the production volume

    In other words ,every 10 minutesa) Give the pacemaker process instruction to produce one pack

    quantity

    b) Take away one finished pitch quantity

    One way to think of pitch is as your management time frame. How

    often do you know your performance to customer ?

    Guidelines for Drawing a Future State

    15

    Guideline#6 Leveling the production volume

    There are many ways to practice paced withdrawal of small,consistent quantities of work.

    A tool used at some companies to help both the mix and volume of

    production is load-leveling box or Heijunka box

    Guidelines for Drawing a Future State

    16

    Guideline#6 Leveling the production volume

    A load leveling box has a column of kanban slots for each pitch

    interval, and a row of kanban slots for each product type. In this system,

    kanban indicate not only the quantity to be produced but also how long

    it takes to produce that quantity (based on takt time).

    Kanban are placed(loaded) into the leveling box in the desired mixsequence by product type(see the leveling box illustration).The material

    handler then withdraws those kanban and brings them to the pacemaker

    process,one at a time,at the pitch increment

  • 3/7/2014

    5

    Guidelines for Drawing a Future State

    17

    Guideline#6 Leveling the production volume

    Guidelines for Drawing a Future State

    18

    Guideline#7 Develop the ability to make every part every day(then

    every shift every hour or pallet or pitch) in fabrication process upstream

    of the pacemaker process.

    This describes how frequently a process changes over to produce all part variations. An initial goal at many plants is to make at least every

    part every day for high-running part numbers.

    In general, we note either the batch sizes or EPEI in the data

    boxes.EPEI stands for Every part Every Interval-where interval is

    replaced with a time such as week,day,shift,hour,pitch or takt

    LEAN MANUFACTURING

    Module-3 Continuation

    19

    POM04

    Three Stages of lean application

    20

    Flow Stage

    The tools and concepts necessary to establish flow include

    Continuous flow-one for- one manufacturing. Work cells. Line balancing. Standardized work. Quick Changeover . Autonomous maintenance. In-process supermarkets. Kanban system. First-in,first out(FIFO) lanes.

  • 3/7/2014

    6

    Three Stages of lean application

    21

    Continuous Flow

    Continuous flow can be summarized in a simple statement move one , make one(or move one small lot, move one small lot)

    Continuous flow processing means producing or conveying

    products according to three key principles

    Only what is needed

    Just when it is needed

    In the exact amount needed

    Three Stages of lean application

    22

    SMED:

    It is a theory and set of techniques that makes it possible to set up or changeover the equipment in less than 10 minutes.

    SMED begins with a thorough analysis of current setup procedures .It is applied inthree sequential stages:

    1) Distinguish between internal setup tasks that can performed only while the machine is

    shut down and external setup tasks that can be performed while the machine is running.

    2) Convert internal tasks to external tasks when possible ; improve storage and

    management of parts and tools to streamline external setup operations.

    3) Streamline all setup activities by implementing parallel operations(dividing the work

    between two or more people) using functional clamping methods instead of bolts,

    eliminating adjustments and mechanizing when necessary.

    Three Stages of lean application

    23

    Quick changeover:

    When you establish takt time ,create work cells and implement standardizedwork ,it is likely that you want to increase the variety of products flowing through

    the cells.

    Such flexibility requires tooling changes that do not disrupt continuous flow .Thismeans for achieving this goal is the quick changeover(QCO) method.

    QCO originates from a methodology called single-minute exchange ofdie(SMED) that was developed by Sheigo Shingo at Toyota.

    Three Stages of lean application

    24

    Autonomous maintenance

    Maintenance that is performed by the machine operator rather than the maintenance staff.

    Autonomous maintenance includes tasks such as lubricating and tighteningmachine parts.

    Autonomous maintenance is a basic element of total productivemaintenance

  • 3/7/2014

    7

    Three Stages of lean application

    25

    In-process Supermarkets

    A Supermarket of work-in-process may be necessary to ensure that flow is possible.

    It is used when there are multiple demands made on a machine or aprocess.

    Where obstacles to continuous flow exist , you can use an in-processsupermarket system

    Three Stages of lean application

    26

    Kanban System

    In Japanese , Kanban means card , billboard , or Sign .

    Kanban refers to the inventory control card used in a pull system.

    Kanban also is used synonymously to refer to the inventory controlsystem developed for use within Toyota Production System

    Three Stages of lean application

    27

    Types of Kanban

    Production Kanban: authorizes the production of goods

    Withdrawal Kanban :authorizes the movement of

    goods

    Signal Kanban: indicating the number of parts to beproduced in a batch operation

    Three Stages of lean application

    28

    FIFO Lanes

    Sometimes it is appropriate to use a FIFO(first-in,first-out) lane between decoupled processes instead of a supermarket to maintain a

    flow between them

    FIFO is like a chute that can hold a certain amount of Inventory ,with thesupplying process at the chute entrance and customer process at the exit.

    Parts leave the chute in the same order that they went in

    If the FIFO lane gets full ,the supplying process must stop producing until thecustomer has used some of the Inventory.

  • 3/7/2014

    8

    Three Stages of lean application

    29

    FIFO Lanes

    FIFO lanes are useful in the following situations

    Where multiple value streams meet before product customization and large batch operations where dissimilar parts go through an operation such as

    anodizing, welding, stamping or painting .

    Another example, you ship to an outside plating process one time per day.The plater can handle only 50 pieces per day. So you set up a FIFO lane sized

    to hold at most 50 pieces of plating work.

    Three Stages of lean application

    30

    FIFO Lanes

    Difference between Supermarket and FIFO

    31

    Supermarket

    Controlled inventory- downstream process pulls what it needs and the upstream process produces whats consumed.

    FIFO Lane

    Controlled inventory(required) fed to downstream process in a specific order.

    Sequenced pull from an upstream process with short lead time

    FIFO

    32

    In the case of custom products and job shops, the scheduling point often needs to be further upstream as shown below.

  • 3/7/2014

    9

    LEAN MANUFACTURING

    KAIZEN & TOTAL PRODUCTIVE

    MAINTENANCE

    33

    POM04

    KAIZEN

    Kaizen means breaking apart the current situation ,analyzing it

    and quickly putting it back together to make it better.

    34

    KAIZEN

    Kaizen events are sometimes called .

    35

    Kaizen Bursts

    Kaizen Blitzes

    KAIZEN Event Timing

    36

    In addition to the event itself ,there is event planningA few days , spread over weeks

    and follow-up

    A Typical Kaizen event is 3-5 days in lengthCan be shorter (< 1day) depending on the scopeMay be long enough to allow implementation and demonstration of results.

    A complex problem (e.g. , implementation of pull system) may be broken down into several Kaizens.

    Each must have a defined ,demonstrable end point

  • 3/7/2014

    10

    KAIZEN BENEFITS

    37

    Improvement get made

    Waste gets eliminated

    Results are seen quickly

    Participants learn skill and get experience

    Cross functional teams provide better understanding of end-to-end process

    The solution has strong user ownership

    Employee motivation is enhanced

    A successful event builds energy for the next steps.

    Things

    get done

    KAIZEN BENEFITS

    38

    Improvement get made

    Waste gets eliminated

    Results are seen quickly

    Participants learn skill and get experience

    Cross functional teams provide better understanding of end-to-end process

    The solution has strong user ownership

    Employee motivation is enhanced

    A successful event builds energy for the next steps.

    Things

    get done

    KAIZEN EVENT SPECIFIES

    39

    PLAN THE EVENT

    CONDUCT THE EVENT

    EVENT FOLLOW-UP

    PLANNING A KAIZEN EVENT

    40

    1.DEFINE THE SCOPE

    2.SET THE OBJECTIVES

    3.SELECT THE TEAM

    4. SELECT THE EVENT

    LEADER

    5.DECIDE ON EVENT

    LENGTH

    6.SCHEDULE THE EVENT

    7.ARRANGE THE

    PARTICIPANT AVAILABILITY

    8.ARRANGE THE

    MANAGEMENT AVAILABILTY

    9.DEFINE PREWORK

    10.SCHEDULE & DO

    PREWORK

    11.ARRANGE MEETING

    FACILITIES

    12.ARRANGE FOR

    PRODUCTION

    INTERRUPTIONS

  • 3/7/2014

    11

    CONDUCTING A KAIZEN EVENT

    41

    1.KICK OFF

    ,PURPOSE,SCOPE

    2.SET THE IMPROVEMENT

    TARGET

    3.TRAINING:

    PROCESS,TOOLS

    4. ANALYZE THE

    PROBLEM

    5.PROPOSE A

    SOLUTION

    6 .IMPLEMENT THE

    SOLUTION

    7.IMPROVE THE SOLUTION

    8.DOCUMENT THE

    SOLUTION

    9.DEFINE A CONTROL

    PLAN

    10.PRESENT RESULTS TO

    THE MANAGEMENT

    11.CELEBRATE THE

    SUCESS

    KAIZEN EVENT FOLLOW UP

    42

    1.PUBLICIZE THE

    PROCESS

    2.AUDIT THE

    PERFORMANCE

    (ON-GOING)

    3.LEVERAGE TO SIMILAR

    SITUATIONS

    Total Productive Maintenance

    43

    What is TPM?

    It is a holistic approach to equipment maintenance that strives to achieve

    perfect production.

    No Breakdowns. No small stops or slow running. No defects.

    In addition it values a safe working environment

    No accidents

    Source:http://www.leanproduction.com/tpm.html

    Total Productive Maintenance

    44

    TPM emphasizes proactive and preventive maintenance to maximize theoperational efficiency of the equipment

    The implementation of a TPM program creates a shared responsibility for equipment that encourages greater involvement by plant floor workers.

    It blurs the distinction between the roles of production and maintenance byplacing a strong emphasis on empowering operators to help maintain their

    equipment.

    In the right environment this can be very effective in improving productivity (increasing uptime, reducing cycle times, and eliminating defects).

  • 3/7/2014

    12

    Total Productive Maintenance

    45

    The Traditional TPM Model

    The traditional approach to TPM was developed in the 1960s and consists of 5S

    as a foundation and eight supporting activities (sometimes referred to as pillars).

    LEAN MANUFACTURING

    Module-5 SIX SIGMA

    46

    POM04

    Process Capability Study

    47

    A Process capability study is a systematic procedure for determining the capability of a process

    The Process capability study may include studies to improve the process and in turn the capability of the process.

    A Process capability study measures the capability of a specific piece of equipment or process under specific operating conditions.

    Process Capability Study

    48

    Steps for conducting a process capability study

    Defining the processing conditions

    Selecting a representative operator

    Ensuring that sufficient raw materials are available

    Ensuring that the measurement system is reliable

    Step 1:Preparing for the study: This involves

  • 3/7/2014

    13

    Process Capability Study

    49

    Steps for conducting a process capability study

    Running the process and collecting data

    Ensuring simultaneously that the process is stable using the same methods as for setting up a control chart

    Since common process capability calculations are based on a stable , normally distributed process . If the process is not stable , one should not

    conduct a process capability study.

    Calculating the process mean and process variation for the measured output.

    Step 2: Determine the process output: The process output can be determined by

    Process Capability Study

    50

    Steps for conducting a process capability study

    A specification normally consists of the nominal or ideal measure for the product and tolerance, which is the amount of variation acceptable to the

    customer.

    Step 3: Comparing the process output to the specification

    Tolerance limit is the difference between the upper specification limit(USL) and the lower specification limit(LSL).

    Process Capability Study

    51

    Steps for conducting a process capability study

    There are a variety of activities to improve a process such as 8D problem solving or mistake proofing.

    Step 4: Take action to improve the process.

    Process Capability Indices

    52

    The process Capability Index(Cp) is defined as the ratio of the specification width to the natural tolerance of the process.

    Cp = UTL-LTL/6

    UTL = upper tolerance limit

    LTL = lower tolerance limit

    = Standard deviation of the process

  • 3/7/2014

    14

    53

    Process Capability Study Process Capability Indices

    54

    The process Capability Index(Cp) is defined as the ratio of the specification width to the natural tolerance of the process.

    Cp = UTL-LTL/6

    UTL = upper tolerance limit

    LTL = lower tolerance limit

    = Standard deviation of the process

    Cp Value

    55

    Cp Value Evaluation Action

    Cp>1.67 Too much capabilty No concern of measure in product variation

    1.67>Cp>1.33 Sufficient capability Ideal condition,maintain it

    1.33>Cp>1.00 Moderate capabilty

    Process control has to be firm.When Cp is

    close to 1,rejections can occur

    1.00>Cp>0.67 Insufficient capability

    Rejections are there.100 percent inspection is

    required.Process needs to be controlled and

    improved

    0.67>Cp

    Capability very much

    insufficient

    Quality not satisfactory.Standards and

    processes need immediate review and

    improvement

    Sampling Methods

    56

    Sampling methods are classified into:

    1. Non-Probability sampling

    Judgmental sampling

    2. Probability sampling

    Simple random sampling Systematic samplingStratified samplingCluster sampling

  • 3/7/2014

    15

    Sampling Methods

    57

    Simple random samplingEvery item in the population has an equal probability of being selected

    Stratified samplingThe population is partitioned into groups, or strata, and a sample is

    selected from each stratum

    Systematic samplingEvery nth (4th, 5th etc.) item is selected

    Cluster samplingA typical group is selected, and a random sample is taken from within

    the group

    Judgment samplingExpert opinion is used to determine the location and characteristics of a definable sample group

    58

    Acceptance Sampling

    Acceptance sampling is an important field of statistical quality control that was popularized by Dodge and Romig .

    It was originally applied by the US military for testing of bullets during World War II.

    A decision may be made to accept or reject a lot or consignment of

    items sent by a vendor depending upon the number of defective (non

    conforming) items found in the sample drawn at random from the lot.

    59

    Sampling Plans

    There are three types of acceptance sampling plans.

    1. Single sampling plan

    2. Double sampling plan

    3. Multiple sampling plan

    60

    Sampling Plans

    Single sampling plan: When a decision on acceptance or rejection of the lot is made on the basis of only one sample , the acceptance is known as a

    single sampling plan.

    If N is the lot size from which the sample is drawn, n the sample size, c the

    number of allowable defectives in the sample, then the sampling plan shown.

  • 3/7/2014

    16

    61

    Single Sampling Plan

    Accept the lot

    Inspect a sample of n pieces

    If the number of defectives(m)

    Exceeds cDoes not exceed c

    Reject the lot

    62

    Double Sampling Plan

    In a double sampling plan ,the decision on acceptance or rejection of the lot is based on two samples .We take a second sample if we are not in a

    position to arrive at a decision about accepting or rejecting the lot on the

    basis of a single sample.

    63

    Double Sampling PlanInspect n1 Pieces

    If the number of defectives

    C1

  • 3/7/2014

    17

    Tools for Process Analysis

    Process Mapping

    65

    A process map or flowchart identifies the sequence of activities or the flow

    of materials and information in a process.

    Connector

    Process/Step/ActionDecision Begin/End

    Start/Stop

    LEAN MANUFACTURING

    Module-5 SIX SIGMA

    66

    POM04

    Measurement System Analysis(MSA)

    67

    A Measurement system analysis is an experimental and mathematical model of determining how much the variation within the measurement

    process contributes to overall process variability

    Accuracy vs Precision

    68

    Accuracy is defined as the closeness of agreement between an observed value and an accepted reference value or standard.

    Precision is defined as the closeness of agreement between randomly selected individual measurements or results.

    A measurement system may be precise but not accurate.

  • 3/7/2014

    18

    Accuracy vs Precision

    69

    Instrument A =0.248 in

    Instrument B = 0.259 in

    Standard value =0.25 in

    A is more accurate than B

    Example

    Instrument A =

    (0.248, 0.246, 0.251)

    Instrument B =

    (0.259,0.258,0.259)

    B is more precise than A

    Accuracy vs Precision

    70

    Repeatability vs Reproducibility

    71

    Repeatability or equipment variation is the variation observed when thesame operator measures the same part repeatedly with same device.

    Reproducibility, or operator variation, is the variation observed whendifferent operators measure the same parts using the same device.

    Measurement System Evaluation and Verification

    72

  • 3/7/2014

    19

    Measurement System Evaluation and Verification

    73

    LEAN MANUFACTURING

    Module-5 SIX SIGMA

    74

    POM04

    FAILURE MODE EFFECTS ANALYSIS(FMEA)

    75

    Failures are any errors or defects ,especially ones that affect the customer

    and can be potential or actual.

    FMEA is a step-by-step approach for identifying all possible failures in a

    design, a manufacturing or assembly process or a product or service.

    Effects analysis refers to studying the consequences of those failures.

    Types of FMEAs

    76

    The different types of FMEA are:

    1. System- focuses on global system functions

    2. Design- focuses on components and subsystems

    3. Process-focuses on manufacturing and assembly processes

  • 3/7/2014

    20

    System FMEA

    77

    Analysis is at highest-level analysis of an entire system, made up of various

    subsystems.

    The focus is on system-related deficiencies, including

    System safety and system integration Interfaces between subsystems or with other systems Interactions between subsystems or with the surrounding environment Single-point failures (where a single component failure can result in complete failure of the entire system)

    Human Interactions

    Design FMEA

    78

    Analysis is at the subsystem level (made up of various components) or

    component level.

    The Focus is on product design-related deficiencies, with emphasis on

    Improving the design Ensuring product operation is safe and reliable during the useful life of the equipment.

    Interfaces between adjacent components.

    Design FMEA usually assumes the product will be manufactured according

    to specifications.

    Process FMEA

    79

    Analysis is at the manufacturing/assembly process level.

    The Focus is on manufacturing related deficiencies, with emphasis on

    Improving the manufacturing process Ensuring the product is built to design requirements in a safe manner, with minimal downtime, scrap and rework.

    Manufacturing and assembly operations, shipping, incoming parts, transporting of materials, storage, conveyors, tool maintenance, and

    labeling.

    Process FMEAs most often assume the design is sound

    FMEA Work Sheet

    80

  • 3/7/2014

    21

    81

    FMEA Example

    FMEA

    82

    SEV = How severe is effect on the customer?OCC = How frequent is the defect likely to occur?DET = How probable is detection of defect?

    RPN = Risk priority number in order to rank concernsRPN =SEV x OCC x DET

    RPN > 90 (requires corrective action)

    DESIGN OF EXPERIMENTS(DOE)

    83

    DOE is an entire field of statistics devoted to understanding the often complex relationships in a process and finding the most efficient and

    effective combination of factors producing the highest quality output.

    It can help you identify not only single factors that influence an outcome , but also interactions between factors that help or hinder.

    84

    Simple Design Experiment

    Outcome of Interest: % or number of lost sales

    Factors chosen for the study

    (based on brainstorming and

    discussion among team

    members about the most

    contributors

    Sequence in which customers are contactedExperience level of the sales personQuantity discounts

    Level for the factors

    Generally DOE test each

    factor at two levels , but some

    designs allows for three or

    more

    Sequence

    1. Customers receive a brochure , then a

    follow-up call

    2. Customers receive a call , then a follow-

    up brochure

    Experience level

    1. Less than six months

    2. Six months or more

    Quantity discounts

    1. 10 % discount if purchase totals $ 100

    more

    2. 15 % discount if discount if purchase

    totals $ 100 or more

  • 3/7/2014

    22

    85

    Simple designed experiments eight trials

    LEAN MANUFACTURING

    Module-5 SIX SIGMA

    86

    POM04

    Definitions of quality

    87

    Traditional Definition Quality means fitness for use

    Modern Definition Quality is inversely proportional to variability

    Quality Improvement is reduction in variability in processes and products

    What is Six Sigma?

    88

    Six sigma can be best described as a business process improvement

    approach that

    seeks to find and eliminate causes of defects and errors,reduces cycle times and cost of operations,improves productivity,better meets customer expectations, andachieves higher asset utilization and returns on investment in manufacturing and service processes.

    Six Sigma was born when Motorola published its Six Sigma quality programme in 1987.

  • 3/7/2014

    23

    What is Six Sigma?

    89

    Six sigma is based on three key quality principles

    Focusing on customers

    Critical to quality parameters (CTQs)

    Continuous improvement

    Employee participation and empowerment

    Six sigma is based on the philosophy of integrated systems based

    thinking

    Six Sigma

    90

    Defect

    Anything that does not meet customer requirements is called defect.

    Metric

    A metric is a verifiable measurement of some particular characteristic ,either numerically (e.g. percentage of defects ) or in qualitative terms (e.g. level of

    satisfaction poor or excellent).

    In Six sigma a defect or non-conformance is a measure of quality

    Defects per million Opportunities(DPMO)

    91

    Defects per unit

    Defects per million opportunities(DPMO)

    DPMO = (Number of defects discovered/opportunities for error)*1000000

    Defined as number of defects in a given unit of product or process.

    Opportunity for error = Number of units produced Opportunities for defects per unit

    Defects per million Oppurtunities(DPMO)

    92

    Use of DPMO is used to define quality broadly

    For Six Sigma projects ,the value is 3.4 defects per million opportunities

  • 3/7/2014

    24

    Defects per million Oppurtunities(DPMO)

    93

    If the average no of bags per customer is 1.6 and the airline recorded 3 lost bags for 8000 customers in one month .

    No of defects discovered = 3 No of opportunities = 1.6 8000 = 12800 DPMO = (3/12800 ) 1000000 = 234.375

    Sigma Level

    Sigma Level = NORMSINV(1- Number of defects discovered/opportunities for error) + 1.5

    Sigma Conversion Table

    94

    DPMO & Sigma Level

    95

    HudsonBella company makes designer bags for several of its client stores

    in Oklahoma. During

    the quality inspection conducted on 500 random bags on each of its three

    manufacturing lines on

    Sep 5,

    2012, following defects were found:

    Line 1: 10 defects

    Line 2: 15 defects

    Line 3: 25 defects

    What is the overall sigma level at which HudsonBella is operating ?

    DPMO & Sigma Level

    96

    An electronics firm manufactures 500,000 circuit boards per

    month. A random sample of 5,000 boards is inspected every

    week for 5 characteristics. During a recent week, 2 defects were

    found for one characteristic, and one defect, each, was found for

    the other four characteristics. If these inspections produced defect

    counts that were representative of the population, what is the

    overall sigma level for the process? What is the sigma level for

    thecharacteristic that showed 2 defects?

  • 3/7/2014

    25

    Sigma Problem Solving Methodology

    97

    The problem solving methodology used in Six Sigma is called DMAIC

    (Define , Measure , Analyze , Improve , Control

    Define Phase

    What are the problems and their scope?Identify the customers and the critical to quality parametersAddress project management issues such as what will need to be done ,by whom and when.

    What are the independent and dependent variables affecting the project?

    Define Phase

    98

    The customer perception about quality attributes are updated from time

    to time by conducting customer surveys.

    Important tools used in this Phase

    Brainstorming

    Pareto Analysis

    Quality Function Deployment (QFD)

    Process Mapping

    Project Charter

    99

    In the Define phase ,the project leaders create a Project Charter.

    Necessary Project Charter Areas

    Project Title: It is important to the name the project with a properly descriptive title that will allow people to quickly view and select your project

    based on key words and phrases.

    Ex: If you are increasing Call Centre effectiveness, a possible title may be

    Call Centre Cycle time or Call Center Variation reduction.

    Project Charter

    100

    Necessary Project Charter Areas

    Black Belt/Green Belt: This is the person leading the process improvement project . It is important to identify the project leader so management knows

    who is leading the effort and others can locate the leader for gather further

    knowledge at a later date.

    Mentor/Master Black Belt: It is important to identify a resource for the project leader to lean on if any project questions or issues arise.

  • 3/7/2014

    26

    Project Charter

    101

    Necessary Project Charter Areas

    Project Start Date:

    Anticipated Project End Date

    Project Charter

    102

    Necessary Project Charter Areas

    Cost of Poor Quality:

    Process Importance

    Project Charter

    103

    Necessary Project Charter Areas

    Process Problem

    Process Start/Stop Points

    Project Goals

    Project Charter

    104

    Necessary Project Charter Areas

    Team Members

    Project Time Frame

    Project Measurements

  • 3/7/2014

    27

    105

    Measure Phase

    106

    Measuring the processes that impact the CTQs and the defects arising in

    the product due to the process.

    Identify causal relationships between the process performance(X) and Customer Value (Y), that is

    Y =f(x)

    Collect data

    Measure Phase

    107

    Important tools used in this Phase

    Process Mapping

    QFD

    Cause and effect matrix

    7 Quality control tools

    Calculation of process sigma and process capability studies

    Gauge R and R studies

    ANOVA

    Analyze Phase

    108

    Focus on why defects ,errors or excessive variation occurs

    Experiments are conducted to verify the hypothesized relationship

    Statistical thinking ,analysis and computer simulation techniques re used

  • 3/7/2014

    28

    Analyse Phase

    109

    Important tool used in this Phase

    Gap analysis and improvement goals

    Process map analysis

    Regression analysis

    ANOVA

    Test of hypothesis

    Improve Phase

    110

    Focuses on removing or resolving the problem and improving the performance measures of the CTQs

    Problem solutions often entail technical and organizational changes

    Improve Phase

    111

    Design of experiments techniques

    Test of hypothesis

    Important tools used:

    Control Phase

    112

    Focuses on how to maintain the improvements over time.

    Can include establishing the new standards and procedures ,training the workforce and instituting controls like check lists , periodic status reviews

    ,statistical process control charts etc.

  • 3/7/2014

    29

    LEAN MANUFACTURING

    Module-5 SIX SIGMA

    113

    POM04

    Analyzing and Prioritizing Customer Requirements

    114

    One approach to Prioritizing customer requirements is called a Kano Analysis based on the ground breaking work of Noriaki Kano, a key

    figure in the Japanese quality movement.

    Dr. Kano realized the importance of dividing customer requirements into three categories

    Dissatisfiers or Basic Requirements

    Satisfiers or Variable RequirementsDelighters or Latent Requirements

    Analyzing and Prioritizing Customer Requirements

    115

    Dissatisfiers or Basic Requirements: Dr Kano often called this type of requirement a Must Be:these features or performance requirements must

    be present to meet the minimal expectations of the customers.

    The customers probably wont notice if these features or performance standards are met ,but they will notice and be extremely unhappy, if

    they are missing.

    Analyzing and Prioritizing Customer Requirements

    116

    Satisfiers or Variable Requirements.The better or worse you perform on those requirements,the higher or lower will be your rating from a customer.

    Price certainly is the most prevalent of the satisfiers:the less a customer has to pay for a given set of features or capabilities,the happier the

    customer.

    In Kanos terms ,these are the more is better category-the more a customer gets of these features,the more satisfied they are.

  • 3/7/2014

    30

    Analyzing and Prioritizing Customer Requirements

    117

    Delighters or Latent requirements: These are features,factors or capabilities that go beyond what customers expect or that target needs

    the customer cant express for themselves.

    No customer ever said Give me a Palm pilot

    KANO Model

    118

    High Customer

    Satisfaction

    LOW Customer

    Satisfaction

    Done Very

    Well

    Not done

    or

    Done

    Poorly

    Breakthrough Customer

    Needs/features:

    Delighters!!Core Competitive

    Requirements:

    Satsifiers!!

    Basic Requirements:

    DisSatsifiers!!

    Alternatives to Kano Analysis

    119

    Another way to identify priority customer requirements is to let yourcustomer tell you what they think.

    Show they a list of requirements youve developed and ask them torate them individually on a scale of 1 to 5 or rank them sequentially from

    most to least important.

    High level Process Maps

    120

    The final step in Define which will probably be on the agenda of your third of fourth team meeting will be to develop a picture of the

    process involved in the project by creating a high level flow chart

    Some teams are tempted to skip this steps but without it the team will take even longer to focus on the problem.

  • 3/7/2014

    31

    High level Process Maps

    121

    A block diagram flowchart deriving from Suppliers,Inputs,Process,Outputs and Customers.

    General Structure of SIPOC Process Map

    High level Process Maps

    122

    Suppliers:The people or organization that provides information ,material

    and other resources to be worked on in the process.

    Inputs :The information/materials provided by suppliers that are

    consumed or transformed by the process.

    Process :The series of steps that transform(and we hope,add value to)

    the inputs.

    Output :The product or service used by the customer

    Customer:The people,company or another process that receives the

    output from the process.

    High level Process Maps

    123

    Simple SIPOC Process Map

    Voice of the Customer

    124

    Customer requirements as expressed in customers own terms.

    Obtained through

    Comment cards and formal surveys

    Focus groups

    Direct customer contact

    Complaint analysis

    Internet monitoring

  • 3/7/2014

    32

    Cost of Quality(COQ)

    125

    Cost of quality are costs associated with avoiding poor quality or those

    incurred as a result of poor quality.

    Prevention costs are investments made to keep nonconforming products

    from occurring and reaching the customer.

    Quality planning costs

    Process control costs

    Training and general management costs

    Cost of Quality(COQ)

    126

    Appraisal costs are costs associated with efforts to ensure conformance to

    requirements , generally through measurement and analysis of data to

    detect non conformance

    Test and inspection costs

    Instrument maintenance costs

    Process measurement and control costs

    Cost of Quality(COQ)

    127

    Internal failure costs occur as a result of unsatisfactory quality found

    before the delivery of the product to the customer.

    Scrap and rework costs,including material ,labor and overheadCost of corrective actionDowngrading costs,such as revenue lost when selling a product at lower price because it does not meet specifications

    Process failures,such as unplanned downtime or unplanned equipment repair.

    Cost of Quality(COQ)

    128

    External failure costs occur after poor quality products reach the

    customer.

    Costs due to customer complaints and returns , including rework or returned cancelled orders and freight premiums.

    Product recall costs and warranty claims ,including the cost of repair or replacement as well as associated administrative costs

    Product liability costs , resulting from legal actions and settlements

  • 3/7/2014

    33

    PARETO ANALYSIS

    129

    Pareto analysis helps to identify the vital few from trivial many and provides direction for selecting projects for

    improvement.

    A Pareto diagram is a histogram of the data from the largest frequency to the smallest.

    Pareto diagrams are used to analyze cost of quality data.

    Practice Exercise : Pareto Diagram

    130

    Process Measurement

    131

    Measurement is the act of quantifying the performance dimensions of products,services, processes and other business acivities.

    Measurement phase involves collecting data for analysis

    Measures and indicators refer to the numerical information that results from measurement

    Process Metric

    132

    A metric is a unit of measurement that provides a way to objectively quantify a process

    Metrics are used to measure data. Metrics can be discrete(countable) or continuous.

    Example, dpmo (defects per million opportunities) is used to measure six sigma

  • 3/7/2014

    34

    Identifying and selecting process metrics

    133

    Example of a Pizza Ordering and filing process for home delivery

    Dashboards and Scorecards

    134

    Dashboards and scorecards provide a consistent source of

    information for tracking progress.

    Data collection

    135

    Data can be collected by data sheets or check sheets.

    1234Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6

    5