slab track nff system

Upload: sima-viorel

Post on 02-Jun-2018

289 views

Category:

Documents


9 download

TRANSCRIPT

  • 8/10/2019 Slab Track NFF System

    1/8

    Your bridge togreater economy.The New Slab TrackNFF System.

    ThyssenKrupp GfT Gleistechnik

  • 8/10/2019 Slab Track NFF System

    2/8

    02

  • 8/10/2019 Slab Track NFF System

    3/8

    03

    Your bridge to greater economy.The New Slab Track NFF System.

    1 NFF System in a bend

    2 Exploded installation drawing

    1 2

    crossfall +100 mm

    horizontal

    So, what are the new features? In contrast to conventional slab,

    which depend on a full surface bedding, the NFF System is a

    bridge-type construction with a superstructure for rail traffic. The

    load demolition must not directly take place underneath the carri-

    ageway slab, but can be introduced by means of drill or pressure-

    grouted piles directly in (more deeply lying) load-carrying gound

    layers. This innovation renders the soil exchange that is normally

    required redundant, thus leading to tremendous cost savings.

    Our new development the New Slab TrackNFF System has been undergoing thoroughtesting on a test track since 2008. And theresults have been impressive. A licence wasissued for it by the Federal Department ofRails at Aug. 12th. 2010. We are the only ma-nufacturer of the system and as such we cansupply a patented solution throughout Europefor tracks and track sections which are affectedby unfavourable or difficult soil types.

  • 8/10/2019 Slab Track NFF System

    4/8

    04

    Step by step innovation.System and installation.

    System

    The NFF System normally consists of deep

    foundations as individual foundations, which have a

    positive connection to rigid portal systems. Longitudinal

    bearer units (LTE) in the form of prefabricated concrete

    components are installed on these in the correct position

    by means of a positive connection. These LTEs consist

    of two longitudinal sleepers with three lateral connections

    level with the rigid portal systems so as to form a pre-

    fabricated rail support grid. The rail fasteners and

    segment rails are already mounted in the correct posi-

    tion on the longitudinal sleepers.

    The NFF System is suitable for use with all types of

    track such as gradients, bends, superelevations and

    crossings. The rails are fastened using the Krupp ECF

    system from ThyssenKrupp GfT Gleistechnik. This makes

    subsequent height corrections of -4 mm to +26 mm

    and side corrections of 10 mm possible. A rail gradient

    of 1:40 or 1:20, etc. can be achieved using different rib

    plates, while the requisite elasticity is provided by an

    elastic pad beneath the rib plate.

    Installation

    The New Slab Track NFF System is manufactured

    using the following procedures:

    Installation of the deep foundations during

    breaks in service either overnight or at weekends

    Concrete curing during normal operations, extension

    of the sleepers and rails, bedding of the ballast

    Installation of the rigid portal systems by means of

    vacuum, precise adjustment and concreting of the

    openings in the rigid portal systems for connection

    to the threaded rods in the micropiles

    Alignment and installation of the longitudinal bearerunits, prestressing with the rigid portal systems

    Replacement of the segment rails with long rails

    Reinstallation of the ballast material

    Inspection of the rail position, concreting the

    clamping channel

    1

    2 3

    4

  • 8/10/2019 Slab Track NFF System

    5/8

    05

    1 Drill (for producing the deep foundations)

    2 Drilled piles with sub-base course

    3 Rigid portal system with elastomer mat

    4 Swinging the LTEs into position

    5 Measuring the LTEs

    6 Rigid portal system with connected

    reinforcement

    7 Rigid portal system with thrust

    mandrels

    8 Rail installation

    9 Rail installation; ballasting

    10 Transition between ballast and

    NFF System

    11 Finished, ballasted (not padded)

    NFF System section

    5

    7

    8

    9

    11

    10

    6

  • 8/10/2019 Slab Track NFF System

    6/8

    06

    1 Passing the measurement

    equipment zone2 Krupp ECF rail fastener

    3 A fully laden train passing

    4 View of finished NFF System route

    A good drive in every respect.Benefits.

    1 2

    crossfall+100 mm

    15 mm

    15 mm

    15 mm

    crossfall+100 mm

    axis

    ofrail

    L=10.80

    Rmin= 600

    An integral component of any approval involves testing

    under normal operating conditions. For this purpose weset up a test track on the factory premises of Rheinkalk

    AG in Wlfrath in late summer 2008. Here the existing

    ballast track, approximately 120 m in length, was con-

    verted to the NFF System.

    The non-homogeneity of the soil with its wildly fluctu-

    ating (bearing) properties made it ideal for trying out the

    system. Axle loads up to 22.5 metric tonnes and train

    loads up to approx. 1800 metric tonnes were brought to

    bear here meaning a total of no less that 2,000,000

    metric tonnes by mid-2010. Measurements taken by

    the University of Duisburg-Essen showed that over theentire period no major settlement or sagging had taken

    place.

    The result is the issue of an approval from the Eisen-

    bahn Bundesamt (the Federal Railway Authority of

    Germany). Excellent quality!

  • 8/10/2019 Slab Track NFF System

    7/8

    07

    Economic advantages

    No expensive foundation soil work is required during

    the earthworks. The loads are directed through the

    deep foundations. This means that even existing

    destabilized slopes can be upgraded.

    There is generally no waste disposal work because

    the existing ballast can be reinstalled in and next to

    the track grid.

    Mounting the rail on innovative longitudinal sleepers

    means reduced vibration. In turn, this increasestravelling comfort and reduces maintenance costs.

    Advantages as a result of prefabrication

    The high level of prefabrication means considerably

    reduced construction times.

    Prefabrication also allows a high level of mechani-

    sation to be used and facilitates quality assurance.

    Advantages during maintenance and renovation

    Reduction in downtimes due to improved renovation

    and extension facilities.

    The system also provides excellent repair and

    maintenance conditions in the event of damage.

    For converting existing routes, the neighbouring

    track can continue to be used whilst the work is

    being carried out.

    Sagging is minimized by using drilled piles with

    adjusted dimensions.

    Ecological advantages

    No sealing of the foundation soil takes place.

    The existing soil structure (ground water) is not

    altered by the drilled piles.

    If necessary the appropriate modifications can be

    made to the longitudinal bearer units to reduce

    noise emissions.

    The NFF System provides a whole host of advantages.

    3 4

  • 8/10/2019 Slab Track NFF System

    8/8

    Subjectto

    alterations

    09/2012e

    ThyssenKrupp GfT Gleistechnik GmbH

    Hollestr. 7a 45127 Essen Germany

    Phone +49 201 844-563710 Fax +49 201 844-563714

    www.tkgftgleistechnik.de [email protected]

    SALES

    Regional office

    NorthVahrenwalder Str. 20530165 Hannover GermanyPhone:+49 511 6703-25Fax: +49 511 6703-37

    WestHollestr. 7a

    45127 Essen GermanyPhone: +49 201 844-563745Fax: +49 201 844-563750

    EastRotherstr. 710245 Berlin GermanyPhone:+49 30 628901-15Fax: +49 30 628901-20/-21

    SouthFrstenrieder Str. 26781377 Mnchen GermanyPhone:+49 89 7871-300Fax: +49 89 7871-343

    South-West

    Weilimdorfer Str. 74/ 270839 Gerlingen GermanyPhone: +49 7156 430730Fax: +49 7156 430740

    EXPORT SALES

    ExportHollestr. 7a45127 Essen GermanyPhone: +49 201 844-563764Fax: +49 201 844-563757

    MANUFACTURING PLANT

    HolzschwellenwerkAm Bahnhof 229393 Gro Oesingen GermanyPhone:+49 5838 9905-0Fax: +49 5838 9905-79

    Location of sales

    Waidmannstr. 2622769 Hamburg GermanyPhone:+49 40 85340-700Fax: +49 40 85340-701

    An der Kreuzkirche 601067 Dresden GermanyPhone:+49 351 4902040Fax: +49 351 4902480

    Dortmunder Str. 268219 Mannheim GermanyPhone:+49 621 8906-120/-121Fax: +49 621 8906-122

    MRT Track &Services Co., Inc.270 Broad Street07003 Bloomfield NJ-USAPhone:+1 973 748-8899Fax: +1 973 748-9243

    ThyssenKrupp WeichenbauObere Stahlindustrie 444793 Bochum GermanyPhone:+49 234 9114-343Fax: +49 234 9114-557

    Humboldtstr. 304105 Leipzig GermanyPhone: +49 341 6017054Fax: +49 341 6017055

    ThyssenKrupp

    GfT Polska Sp. z o.o.

    Al. Slowackiego 6630-004 Krakw PolandPhone: +48 12 6204130Fax: +48 12 2677548

    Betrieb IndustrieweichenAm Wasserturm 3b06869 Coswig/Anhalt GermanyPhone: +49 34903 4741-0Fax: +49 34903 4741-20

    VertriebsbereichWaggonausrstungRotherstr. 710245 Berlin GermanyPhone:+49 30 628901-15Fax: +49 30 628901-22

    Betrieb SpannmittelAm Wasserturm 3b06869 Coswig/Anhalt GermanyPhone:+49 34903 4741-0Fax: +49 34903 4741-24

    ThyssenKrupp LangschienenLadestr. 839175 Knigsborn GermanyPhone:+49 39292 6958-17Fax: +49 39292 6958-20