Sixth Northwest Conservation & Electric Power Plan
Proposed Combined-cycle Power Plant Capital Cost Assumptions
Jeff KingNorthwest Power and Conservation Council
Generating Resources Advisory CommitteePortland, OR
September 25, 2008
![Page 2: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/2.jpg)
September 25, 2008 2Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Combined-cycle cost elements
• Capital costPlant development and construction ($/kW)
• Operating costsFixed operation and maintenance ($/kW/yr)
Variable operation and maintenance ($/MWh)
Fixed fuel (capacity payments) (zone-specific) ($/kW/yr)
Variable fuel (commodity payments) (zone-specific) ($/MMBtu)
Transmission from point of interconnection to LSE wholesale delivery point (BPA Point to Point tariff as proxy) ($/kW/yr)
Emission costs - Cost of CO2 allowances ($/tonCO2)
![Page 3: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/3.jpg)
September 25, 2008 3Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Assessing combined-cycle capital costs• Problems:
Rapid escalation of plant capital costs in recent years
Variety of plant configurations and features
Sensitivity of output to elevation, ambient temperature and certain features
Several recently reported costs are for completions of suspended projects
Reported costs are poorly documented more often than not.
• Sources:Primary: Reported costs for actual and proposed plants
Supplementary: Other surveys and estimates
![Page 4: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/4.jpg)
September 25, 2008 4Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Establishing comparability I
• Initial screen to identify representative projectsOmit completions of suspended projects
Limit to "F, G & H" technology
Omit unusually large (3 & 4 plant) projects
Omit unusual configurations (e.g., 3x1)
Focus on post-2004 completions; closely focus on 2006 & later
• Adjust costs to baseload technology w/evaporative coolingDeduct for dry cooling costs (-6% total cost)
Deduct for fired HSRG (duct firing MW ~ 30% cost of baseload MW)
![Page 5: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/5.jpg)
September 25, 2008 5Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Establishing comparability II
• Normalize capacity to lifecycle ISO conditions at the point of interconnectionProblem - reported capacity may be site-rated or nominal, winter or summer,
typically not reported
Use OEM reference plant ISO ratings from GTW (new & clean nominal capacity, unfired HSRG, wet cooling, adjusted for auxiliary loads)
Reduce capacity 0.5% for main transformer losses (post-analysis)
Reduce capacity 2.7% for lifecycle aging losses (post-analysis)
• Normalize to "overnight" cost in 2006 dollar valuesIPP projects: Assume reported costs are EPC costs, add owner's cost
allowance (5%); development cost allowance (1.4%); financing costs (2% of debt); back-calculate overnight cost for service year using MICROFIN
Utility projects: Assume reported costs are "all-in", back-calculate overnight cost for service year using MICROFIN
![Page 6: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/6.jpg)
September 25, 2008 6Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Assign a vintage to the samples
• Problem: Environment w/significant annual escalation
• Objective: Cost of project w/2010 service
• Reported all-in costs - MICROFIN yields a comparable constant dollar overnight cost for constructing a project for service in year x.
• Cost estimates - generally, costs at time of estimate plus an contingency for anticipated escalation to a future expenditure date - and allowance which may not prove accurate. Vintage is time of cost estimate release.
• Plot all-in and estimates separately - will illustrate changing perception of escalation.
![Page 7: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/7.jpg)
September 25, 2008 7Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Useable reported costsProject Service State Configuration Raw
$/kWType of Est
Arlington Valley (Maricopa) I Aug-02 AZ 2x1 GE7FA $439 Preconstruction announcement
Coyote Springs 2 Jun-02 OR 1x1 GE7FA $641 Preconstruction announcement
Otay Mesa (Original estimate) P2002 CA 2x1 Unannounced $539 Preconstruction announcement
Grays Harbor (Original est.) P2003 WA 2x1 GE7FA $462 Preconstruction announcement
Goldendale Energy Center Sep-04 WA 1x1 GE7FA $531 Preconstruction announcement
Rocky Mountain Energy Center Jun-04 CO 2x1 SW 501F $580 Preconstruction announcement
Blythe Energy Project II P2004 CA 2x1 SWV84.3a $481 Preconstruction announcement
Silver Bow P2004 MT 2x1 SW 501F $680 Preconstruction announcement
Blythe Energy Project I Jan-04 CA 2x1 SWV84.3a $673 As-built
Arlington Valley (Maricopa) II Dec-05 AZ 2x1 GE7FA $333 Preconstruction announcement
Chuck Lenzie (ex Moapa) I Jan-06 NV 2x1 GE7FA $481 Preconst comp. est + acquisition
Chuck Lenzie (ex Moapa) II May-06 NV 2x1 GE7FA $481 Preconst comp. est + acquisition
Cosumnes Phase I Mar-06 CA 2x1 GE7FA $870 Projected at 95% complete.
Current Creek Apr-06 UT 2x1 GE7FA $684 Ratebase capitalization
Lake Side Jul-07 UT 2x1 SW SCC6 5000F $650 Ratebase capitalization
Port Westward Jun-07 OR 1x1 MHI 501G $657 As-built
Tracy CC P2008 NV 2x1 GE7FA $778 Nevada Power SEC 10-K
San Gabrial (Low) P2010 CA 2x1 SW SCC6 5000F $762 Preconstruction announcement
San Gabrial (High) P2010 CA 2x1 SW SCC6 5000F $776 Preconstruction announcement
Colusa (Low) P2010 CA 2x1 GE7FA $685 Preconstruction announcement
Colusa (High) P2010 CA 2x1 GE7FA $761 Preconstruction announcement
Avenal Energy Project P2012 CA 2x1 GE7FA $833 Preconstruction announcement
![Page 8: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/8.jpg)
September 25, 2008 8Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Normalized combined-cycle project cost
$0
$200
$400
$600
$800
$1,000
$1,200
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Service Year
Ove
rnig
ht
Cap
ital
Co
st 2
006$
/kW
Preconstruction estimates
As-built costs
Poly. (Preconstruction estimates)
![Page 9: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/9.jpg)
September 25, 2008 9Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Other surveys and estimates
• EIA 2008 Annual Energy Outlook (Jun 2008)
• NETL Cost & Performance Baseline for Fossil Energy Plants (Aug 2007)
• CEC Comparative costs of California Central Station Electricity Generation Technologies (Jun 2007)
• Lazard Levelized Cost of Energy Analysis (Jan 2008)
![Page 10: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/10.jpg)
September 25, 2008 10Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Comparison to other surveys & estimates
$0
$200
$400
$600
$800
$1,000
$1,200
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Service Year
Ove
rnig
ht
Cap
ital
Co
st 2
006
$/kW
Preconstruction estimatesAs-built costCECEIA 2008 AOLLazardNETL
CEC based on survey of projects constructed between 2001 & 06
![Page 11: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/11.jpg)
September 25, 2008 11Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Proposed Sixth Plan costs
$0
$200
$400
$600
$800
$1,000
$1,200
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Service Year
Ove
rnig
ht
Cap
ital
Co
st 2
006$
/kW
Preconstruction estimatesAs-built costCECEIA 2008 AOLLazardNETLProposed 6th Plan
![Page 12: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/12.jpg)
September 25, 2008 12Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Adjustments to model input values
Overnight (2006$)
Derate 0.5% to Station Busbar (2006)
Derate 2.7% for Lifecycle
Aging (2006$)
All-in, 2010 serviceb
(Nominal$)
5th Plan, 2x1 540MW Base + 70 MW DF
$591 $657
Proposed 6th Plan, 2x1 540MW Base, no DF
$850 $854 $877 $976
Proposed 6th Plan, 2x1 540MW Base + 70 MW DF
$782a $786 $807 $897
a. 540 MW @ $850/MW + 70 MW @ 255/MW
b. IOU financing
![Page 13: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/13.jpg)
September 25, 2008 13Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Cost of baseload energy(Point of interconnection)
0
10
20
30
40
50
60
70
5th Plan610 MW
6th Plan540 MW
6th Plan610 MW
Lev
eliz
ed lif
ecycl
e 20
06$/
MW
h
CO2 (Bingaman-Spector cap)Fuel commodity
Variable O&M
Pipeline capacity
Fixed O&M
Capital
IOU financing
2010 service
Westside NG, 2007 NPCC forecast
CapFac ~ 90% of baseload rating
![Page 14: Sixth Northwest Conservation & Electric Power Plan Proposed Combined-cycle Power Plant Capital Cost Assumptions Jeff King Northwest Power and Conservation](https://reader036.vdocuments.us/reader036/viewer/2022083007/56649e975503460f94b9a756/html5/thumbnails/14.jpg)
September 25, 2008 14Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Where things stand
$0
$25
$50
$75
$100
$125
Gas Comb Cycle Gas Turbine Cl 6 Wind (Local)
Level
ized
lif
ecy
cle c
ost
($/
MW
h) Emission (CO2) cost
Operational integration
Plant costs
2010 service
Point of interconnection (wind incl. R & LF)
2008 Federal production tax credits
Baseload operation
Bingaman/Specter CO2 capping cost