simplified configuration management and qualification...
TRANSCRIPT
![Page 1: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/1.jpg)
Simplified Configuration Management and Qualification Testing for
CubeSats
Keith Mashburn
Space Science and Engineering LaboratoryMontana State University
August 11, 2008
1
![Page 2: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/2.jpg)
Agenda
• Overview of Configuration Management
• Example Configuration Management System
• Overview of CubeSat Qualification Testing
• Example CubeSat Qualification Program
![Page 3: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/3.jpg)
Overview of Configuration Management
• Configuration Management (CM) is the process of organizing and maintaining engineering data
• Components of a simple Configuration Management System (CMS)
Document Control
Inventory Management
Manufacturing Control
Flight Assurance
• Dedicated staff members devoted to CMS activities is a must
![Page 4: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/4.jpg)
CMS Implementation
CMS
DOCUMENT CONTROL
PARTS INVENTORYCONTROL
MANUFACTURINGCONTROL
FLIGHT ASSURANCE
![Page 5: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/5.jpg)
Document Control
• Each engineering document issued a sequential number
• All documents undergo a peer review process to ensure quality
• Each document contains a coverpage for review signatures and a revision log to track changes
• After all approval signatures are obtained the document is formally released
• Changes to released documents tracked using Engineering Change Order (ECO)
![Page 6: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/6.jpg)
SSEL Document Control
• Released documents can be accessed using an online database • All document originals are locked in a secure filing cabinet
![Page 7: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/7.jpg)
Parts Inventory Control
• Verify parts meet outgassing requirements
• All parts purchased from commercial vendors
• Maintain detailed records of all flight parts in stock
• All electrical parts stored in ESD safe containers
• All flight parts stored in locked cabinets
![Page 8: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/8.jpg)
SSEL Parts Inventory Control
![Page 9: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/9.jpg)
Manufacturing Control
• Manufacturing Planning should start early in the design phase of the mission
• Inspection and other hold points should be identified early in planning stage
• Identify the necessary fabrication, assembly, and testing procedures for all flight hardware and related ground support equipment (GSE)
• Personnel involved in flight fabrication and testing should be trained in the application area (ESD, Soldering, Polymerics, etc.)
• At least two persons are required during all flight hardware operations
![Page 10: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/10.jpg)
SSEL Manufacturing ControlMANUFACTURING
CONTROL
MPS Acceptance
Review
Prepare MPS Package
Obtain parts kit from
inventory control
Nonconformances that occur during testing will be tracked with Nonconformance Reports (NCR)
Manufacture assembly per
MPS
Workmanship Inspection
Perform Performance
Testing
10
![Page 11: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/11.jpg)
Flight Assurance
• Provide oversight during all phases of the integration and testprogram to ensure the work is performed according to specifications
• Perform workmanship inspections during fabrication and assembly activities
• Certify equipment/GSE setup prior to execution of all qualification tests
• Maintain detailed records of all non-conformances that occur during I&T
• Verify test records and data are adequate to meet test requirements
![Page 12: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/12.jpg)
SSEL Flight Assurance
![Page 13: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/13.jpg)
CubeSat Qualification Testing
![Page 14: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/14.jpg)
Overview of CubeSat Qualification Testing
• Qualification testing ensures that design is acceptable and that the satellite will function in the expected environments
• Qualification begins with the completion of the flight hardware and software and ends with the satellite ready for shipment to CalPoly for acceptance testing
• Qualification testing consists of a series of functional and performance tests, followed by a sequence of environmental exposures
• The requirements for qualification testing are derived from a variety of sources including the individual mission requirements, the CubeSat
program requirements, and the designated launch vehicle requirements
![Page 15: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/15.jpg)
Example of CubeSat Qualification Program (1 of 3)
![Page 16: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/16.jpg)
Example of CubeSat Qualification Program (2 of 3)
SpacecraftBus
Integration
Payload and Flight Battery
IntegrationCPT #1
CPT #2(Pre-
Environmental)
S/C BusBake-Out
EMITesting
VibrationTesting
Thermal/VacuumTesting
FSW 1.0
FSW 1.1
Environmental Testing
Software Development/Validation on EDU Hardware
CPT #3(Post-
Environmental)
Mission OpsTesting
Deliver toCalPoly forAcceptance
Testing
FSW 1.2
Stake and Coat
![Page 17: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/17.jpg)
Example of CubeSat Qualification Program (3 of 3)
![Page 18: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/18.jpg)
CubeSat Environmental Testing (1 of 2)
Vibration Test• Perform low-level sine test to confirm modes
• Perform random vibration to qualification levels
• Perform low frequency sine vibe, only if required
Thermal/Vacuum Test• Operate in thermal/vacuum environment to verify system performance
• Calibrate on-board temperature sensors
• Perform mission simulations
EMI • Operate system on nominal RF link and verify operational integrity (Self-Compatibility)
• Perform conductive/radiated emissions and susceptibility measurements, only if required
Post-Environmental Performance
Testing
![Page 19: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/19.jpg)
CubeSat Environmental Testing(2 of 2)
![Page 20: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/20.jpg)
Pack and Ship• Securely pack satellite and GSE for shipment to CalPoly
• Transport CubeSat via commercial air carrier
CubeSat
Structural Requirements Confirmation
• Cal-Poly to verify conformance to CubeSat Standard
CubeSat Delivery and Acceptance (1of 2)
Delivery • Post-shipment inspection of CubeSat and GSE
• Post-shipment performance test
Acceptance Testing
• Cal-Poly to perform vibration testing to acceptance levels on integrated P-POD
Final Flight Preparation
• Cal-Poly perform final battery charging
• Cal-Poly pull Remove Before Flight (RBF) Pin
P-POD Integration• Cal-Poly to integrate CubeSats into P-POD
![Page 21: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/21.jpg)
CubeSat Delivery and Acceptance (2 of 2)
![Page 22: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/22.jpg)
Acknowledgements I would like to thank Ms. Celena Byers
for all of her hard work on the implementation and maintenance of the
SSEL Configuration Management System.
![Page 23: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/23.jpg)
Contact Info
Keith Mashburn – I&T Team Lead:
Celena Byers – SSEL Configuration Management Specialist:[email protected]
![Page 24: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/24.jpg)
Backup Slides
![Page 25: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/25.jpg)
Processor
Software
Storage
PeripheralI/F
CDH PCB Integration and Test
Perform PCB Assembly
Perform workmanship inspection
Electrical interface testing
Initial Power-up
Oscillator measurement or calibration
Watch dog functional check
Memory read/write verification tests
Verify S/W loading capability
Perform initial checks of the peripheral I/F
CDH
![Page 26: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/26.jpg)
BCR
Solar Array
VoltageRegulators
Digital I/FBoard
EPS PCB Integration and Test
Perform PCB Assembly
Perform Workmanship Inspection
Electrical interface testing
Initial Power-up
Voltage regulator functional testing
Safety inhibit functional testing
EPS
SafetyInhibits
![Page 27: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/27.jpg)
Magnet
DampeningRod
ACS PCB Integration/Verification
Perform PCB Assembly
Perform Workmanship Inspection
Electrical interface testing
Battery charge/discharge testing
ACS
![Page 28: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/28.jpg)
Receiver
Amplifier
COMM PCB Integration/Verification
Perform PCB Assembly
Perform Workmanship Inspection
Electrical interface testing
Initial Power-up
Transmitter/Amplifier functional testing
Receiver functional testing
RF link test and power measurements
Watchdog functional testing
COMM
Transmitter
TNC
Receiver
Amplifier
Transmitter
Antennas
![Page 29: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/29.jpg)
Particle Detector
Payload PCB Integration and Test
Perform PCB Assembly
Perform Workmanship Inspection
Electrical interface testing
Initial Power-up
Preamp noise measurements
I2C Interface functional
Payload Plateau Curves
Payload
![Page 30: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/30.jpg)
Backup Slide: System CPT Plan
![Page 31: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early](https://reader033.vdocuments.us/reader033/viewer/2022060316/5f0bfacd7e708231d4332a0c/html5/thumbnails/31.jpg)
Backup Slide: System Environmental Test Plan