setting out works
TRANSCRIPT
-
8/6/2019 Setting Out Works
1/21
SETTING OUT WORKS
TOPIC 5
-
8/6/2019 Setting Out Works
2/21
INTRODUCTION
The process of laying out engineering projects
by placing pegs or marks at the site of works.
The main idea is to define the lines ofexcavation and levels of the works for the
guidance of workers so that construction may
proceed with reference to the already
prepared drawing.
Setting out is the reverse process.
-
8/6/2019 Setting Out Works
3/21
EQUIPMENT USED
SIGHT RAILS
Consists of a horizontal cross-piece nailed to
a single upright or pair of uprights driven intothe ground.
The upper edge of the cross-piece is set to a
convenient height above the required plane
of the structure.
-
8/6/2019 Setting Out Works
4/21
Various forms of sight rails
-
8/6/2019 Setting Out Works
5/21
EQUIPMENT USED
TRAVELLER
Same size and same value with sight rail.
Used to monitor excavation process for cutand fill.
-
8/6/2019 Setting Out Works
6/21
-
8/6/2019 Setting Out Works
7/21
EQUIPMENT USED
SLOPE RAILS
Used for controlling the side slopes in
embankments and in cutting.
-
8/6/2019 Setting Out Works
8/21
-
8/6/2019 Setting Out Works
9/21
-
8/6/2019 Setting Out Works
10/21
CONTROLS FOR SETTING OUT
The setting out of work requires the following
two controls:
a) Horizontal control
b) Vertical control
-
8/6/2019 Setting Out Works
11/21
HORIZONTAL CONTROL
Station must be established within or near the
construction area.
The horizontal control consists of referencemarks of known plan position.
-
8/6/2019 Setting Out Works
12/21
-
8/6/2019 Setting Out Works
13/21
HORIZONTAL CONTROL
REFERENCE GRIDS
Reference grid are used for accurate setting
out of works of large magnitude. The following types of reference grid are used
i. Survey grid
ii. Site grid
-
8/6/2019 Setting Out Works
14/21
SURVEY GRID
The one which drawn on the survey plan, fromthe original traverse.
SITE GRID
Used by the designer
As far as possible, the site grid should be
actually the survey grid.
-
8/6/2019 Setting Out Works
15/21
-
8/6/2019 Setting Out Works
16/21
VERTICAL CONTROL
Establishment of reference marks of knownheight relative to some specified datum.
To establish a number of temporary bench
mark.
The position of TBM should be fixed duringinitial site reconnaissance.
All TBM should be checked, properlyprotected and should be re-checked at regularintervals.
-
8/6/2019 Setting Out Works
17/21
EXAMPLE CALCULATION
QUESTION 1
A 80m long pipeline will be built and the gradient fromA to B is 1 in 110 and falls from A to B. Reduced level ofpoint A are 20.102m and point B are 20.195m. The
invert level at point A is 18.123m.Calculate:
i. The invert level of point B (17.396m)
ii. Height of sight rails at A and B above ground level if a
3m traveler is to be used.(1.021m & 0.201m)
iii. The depth of excavation at point A and B.(1.979m &2.799m)
-
8/6/2019 Setting Out Works
18/21
EXAMPLE CALCULATION
QUESTION 2
A straight length of sewer is to be laid
between three manholes P,Qand R. Thefollowing information is available.
SECTION PQ QR
Horizontal Length 60m 30m
Gradient -1:100 -1:50
MANHOLE P Q R
Ground Level 80.760m 80.200m 80.140m
Invert Level 78.430m - -
-
8/6/2019 Setting Out Works
19/21
continue
Calculate:
i. The invert levels ofQand R. (77.830m &77.230m)
ii. Reduced level of the sight rails at P,Qand R if a3m traveler is to be used to locate the sewerinvert. (81.430m, 80.830m & .m)
iii. The height of sight rails above ground level at
P,Q
and R. (0.670m, 0.630m & m)iv. The depth of excavation at P,Qand R. (2.330m,2.370m & ..m)
-
8/6/2019 Setting Out Works
20/21
EXAMPLE CALCULATION
QUESTION 3
A culvert with 250m length will be built from section
S1 to section S2 and the gradient from S1 to S2 is 1 in
50 and falls from S1 to S2. Reduced level and invertlevel for section S1 are 23.5m and 21.3m. If reduced
level for section S2 is 18.6m and 2.5m rod traveler is
to be used, calculate:
i. Reduced level on top of peg at S1 and S2(23.8m & 18.8m)
ii. Invert level at S2 (16.3m)
-
8/6/2019 Setting Out Works
21/21
EXAMPLE CALCULATION
QUESTION 4
Given the data below get from the construction for drainage.
Reduced level at point A=23.470m
Reduced level at point B=22.855m
Distance from A to B = 40m
Depth of excavation at A = 1m
Gradient falls from A to B = 1:100
Traveler length = 2.5mCalculate:
i. Invert level at A and B (22.470m & 22.070m)
ii. Depth of excavation at B (0.785m)
iii. Reduced level of the sight rails at A and B (1.500m & 1.715m)