session 3 - sundarijal presentation final

Upload: energy-for-all

Post on 04-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    1/28

    Sanjeev Neupane, Managing Director

    South Asia Engineering Pvt. Ltd

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    2/28

    The Power Plant has been in Operation Since 1934

    Sundarijal Hydropower Station is Situated 15 km northeast of

    Kathmandu

    Currently the project is under the ownership of NepalElectricity Authority (NEA), a Nepal Government Owned Body

    Comprises Two 320 kW Pelton Turbines with 640 kW Capacity

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    3/28

    South Asia Engineering Pvt Ltd (SAE) Established under the Company Act of Nepal 2063

    Corporate Office at Trade Tower Nepal Thapathali (4th Floor)

    Aims toward development of Hydropower Projects in Nepal

    Consultancy in Hydropower Sector Our Clients

    Arun Valley Hydropower Development Co. Ltd ( Piluwa

    Khola 3 MW)

    Ridi Hydropower Development Co. Ltd (Ridi Khola 2.4 MW) Rairang Hydropower Development Co. Ltd (500 KW)

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    4/28

    Name Position

    SATISH NEUPANE CHAIRMAN

    SANJEEV NEUPANE MANAGING DIRECTOR

    MAHENDRA NEUPANE CEO

    EK RAJ SIGDEL CHARTERED ACCOUNTANT

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    5/28

    5

    Sundarijal Power Plant site

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    6/28

    Water Supply System to (Kathmandu Upatyaka Khanepani

    Limited) KUKL.

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    7/28

    The plant is shut down during load

    shedding as it cannot handle the

    locally connected loads. Hence, the

    power station is running at a lower

    efficiency.

    The machine used at the project has

    been used for a long period of time

    and it needs to be replaced along with

    renovation work

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    8/28

    The upgrading to 6 MW.

    Will be storage plant with construction of new pondage upstream of the

    current dam site

    Power be transmitted to the local distribution grid of Kathmandu valleyand surrounding VDCs.

    This project will, to some extent, help reduce the power deficiency in the

    valley and provide electricity services to thousands of people.

    The existing intake tunnel and penstock will also have to be upgraded to

    handle the upgraded discharge.

    The hydro-mechanical and electrical will also be replaced and upgraded.

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    9/28

    A 6 MW Hydro Electricity Project connectedto the National Grid

    Power Generation 3 MW for 8 Months (Dry Months)

    6 MW for 4 Months (Wet Months)

    Free energy of 640 kW to NEA

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    10/28

    Reduction of load shedding inside the valley.

    Possibility of developing the areas as a

    recreation centre, resort and picnic spots.

    Help to reduce shortage of drinking water in

    Kathmandu valley.

    It demonstrates new business outlook of hydro

    power plant.

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    11/28

    Gross Head = 235 M

    Net Head = 232 M

    Design Discharge = 3 cubic meter per sec

    Catchment Area = 15 Sq. Km Name of Streams = Bagmati and Nagmati

    Type = Storage

    Capacity = 6 MW

    Pondage = 4 No. Height Dam = 30 m for Bagmati and 20 m for Nagmati

    Length of Penstock Pipe = 1700 m

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    12/28

    Diameter of Penstock (Proposed) = 1.2 m

    Sub Station = Approx. 6 Km

    Transmission Line = 33 KV

    Turbine = 3 Units (Pelton)

    Total Storage Capacity = 10284450 m3

    Pondage Area = Bagmati (0.96 Km2)

    Nagmati (0.18 Km2)Efficiency of Overall Machine = 88%

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    13/28

    Source Amount in Rs in

    Crores

    Amount in Million

    US $

    Total Project Cost 94.40 10.60

    WE ARE OPEN TO BOTH DEBT AND EQUITY

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    14/28

    Total Cost of the Project

    No. Detail Breakdown Rs. (000) Dollar %

    1 Project Development (DPR to PPA) 12200.0 137079 1.17

    2 Land Purchase & Development 23726.6 266591 2.28

    3 Vehicles & Equipments for the Project 23600.0 265169 2.27

    4 Infrastructure Development 33859.9 380448 3.26

    5 Civil Construction Work 306700.0 3446067 29.53

    6 Hydro-Mechanical Equipments 155039.6 1742018 14.93

    7 Electro-Mechanical Equipments 243400.0 2734831 23.44

    8 TL & Electrical Work 33255.6 373659 3.20

    9 Environment/Social Mitigation 23255.9 261303 2.24

    10 Project Design and Supervision 16500.0 185393 1.59

    12 Project Mangement Cost 19200.0 215730 1.85

    14 Project Insurance 20900.0 234831 2.01

    15 Price Escalation 32400.0 364045 3.12

    Total 944037.6 10607165

    16 IDC (interest during construction) 94498.17 1061777 9.10Grand Total 1038536 11668942 100.00

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    15/28

    Pay Back Period = 10 Years

    Return on Equity = 18%

    IRR = 16%

    BC Ratio = 1.42

    Assumption

    1. Debt 70% and 30% Equity

    2. Cost of Fund = 12%3. Lease Period is 30 Years

    4. Free Energy to NEA 640 KW

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    16/28

    Liable to do all daily necessary work.

    Liable to cooperate with the Nepal Electricity

    Authority and other Government related bodies

    Get the lease agreement of this project Conduct feasibility, Environment, social and detailed

    study.

    Get the Power Purchase Agreement

    Construction, Installation and Supervision

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    17/28

    Act as a facilitator

    Provide consultancy services (if possible)

    Help to build a linkage with othertechnical stakeholders for recreation

    centre

    Monitor the progress and achievementson a regular basis

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    18/28

    Pressurize the Nepal Government

    and NEA to give this project onlease basis to SAE

    Technical Support

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    19/28

    Strength

    1. Easy Access

    2. Already Built and tested

    3. Close to Market

    4. Infrastructure (Road, Transmission Line,

    Market)

    5. Contribution toward reduction of LoadShedding

    6. Drinking Water

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    20/28

    Weaknesses1. Conservational Area

    2. Ownership to be Transferred

    3. Approvals to be taken

    Opportunity

    1. New Business Outlook

    2. Multipurpose Project

    Threats

    1. Political Instability

    2. Government Policies

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    21/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    22/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    23/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    24/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    25/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    26/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    27/28

  • 7/29/2019 Session 3 - Sundarijal Presentation Final

    28/28

    THANK YOU !!