Seismic Design Requirements
City of Medford Municipal CodeChapter 9
Presented by the
Building Safety Department
Seismic Design RequirementsTHESE PROVISIONS PRESCRIBE THE DESIGN REQUIREMENTS OF EXISTING BUILDINGS UNDERGOING:
CHANGE OF OCCUPANCYADDITIONSALTERATIONS
SECTION 9.600
Seismic Design Requirements
FOR CHANGE OF OCCUPANCY AND STRUCTURAL ADDITIONS THE DESIGN STANDARD SHALL BE THE CURRENT EDITION OF OREGON STRUCTURAL SPECIALTY CODE.FOR OTHER WORK COVERED UNDER THESE PROVISIONS THE DESIGN STANDARD SHALL BE FEMA 178, NEHRP HANDBOOK FOR THE SEISMIC EVALUATION OF EXISTING BUILDINGS.
SECTION 9.610
Seismic Design Requirements
THE USE OR CHARACTER OF A QUALIFIED HISTORIC BUILDING OR PROPERTY, OR PORTION THERE OF, SHALL BE PERMITTED TO CONTINUE IN USE REGARDLESS OF ANY PERIOD OF TIME IT MAY HAVE BEEN UNOCCUPIED OR IN OTHER USE;PROVIDED THE BUILDING OR PROPERTY OTHERWISE CONFORMS TO ALL APPLICABLE REQUIREMENTS OF THIS CHAPTER.
SECTION 9.615
Seismic Design Requirements
THE TABLE BELOW IS USED TO CLASSIFY THE RELATIVE HAZARD OF ALL BUILDING OCCUPANCIES;
RELATIVE HAZARD OCC. CLASSIFICATION5 (HIGHEST) A, E,I-1.1, 1-3, H-1, H-3, H-6,
H-7 4 R-1, SR, 1-2, 1-3.13 B, I-1.2, I-1.3, M2 F, S, H-4, H-51 (LOWEST) R-3, U
SECTION 9.620
Seismic Design Requirements
AN OCCUPANCY CHANGE OF THE SAME OR A LOWER RELATIVE HAZARD CLASSIFICATION NUMBER WILL NOT REQUIRE SIESMIC IMPROVEMENTS,UNLESS THE CHANGE RESULTS IN AN OCCUPANT LOAD INCREASE OF MORE THAN 20%
SECTION 9.620
Seismic Design Requirements
AN OCCUPANCY CHANGE TO A HIGHER RELATIVE HAZARD CLASSIFICATION NUMBER WILL NOT REQUIRE SEISMIC IMPROVEMENTS,WHEN THE NET FLOOR AREA OF THE CHANGED PORTION OCCUPIES LESS THAN 15% OF THE NET FLOOR AREA OF THE BUILDING AND WHERE THE CHANGE DOES NOT RESULT IN AN INCREASE IN OCCUPANT LOAD AS DEFINED BY THE OREGON STRUCTURAL SPECIALTY CODE OF MORE THAN 100 PERSONS.
SECTION 9.620
Seismic Design Requirements
ALL OTHER CHANGES TO A HIGHER RELATIVE HAZARD OCUPANCY WILL REQUIRE SEISMIC IMPROVEMENTS USING THE CURRENT EDITION OF THE OREGON STRUCTURAL SPECIALTY CODE.
SECTION 9.620
Seismic Design Requirements
ALL STRUCTURES, WHICH ARE BEING CONVERTED TO ESSENTIAL FACILITIES, AS DEFINED IN THE OREGON STRUCTURAL SPECIALTY CODE, SHALL COMPLY WITH CURRENT SEISMIC REQUIREMENTS, REGARDLESS OF OTHER REQUIREMENTS IN THIS SECTION.
SECTION 9.620
Seismic Design RequirementsAN ADDITION THAT IS NOT STRUCTURALLY INDEPENDENT FROM AN EXISTING BUILDING SHALL BE DESIGNED AND CONSTRUCTED SUCH THAT THE ENTIRE BUILDING CONFORMS TO THE SEISMIC FORCE RESISTANCE REQUIREMENTS FOR NEW BUILDINGS UNLESS THE FOLLOWING THREE CONDITIONS ARE MET:
SECTION 9.625
Seismic Design Requirements
THE ADDITION SHALL COMPLY WITH THE REQUIREMENTS FOR NEW BUILDINGS, ANDTHE ADDITION SHALL NOT INCREASE THE SEISMIC FORCES IN ANY STRUCTURAL ELEMENT OF THE BUILDING BY MORE THAN 5 PERCENT UNLESS THE CAPACITY OF THE ELEMENT SUBJECT TO THE INCREASED FORCES IS EQUAL TO OR GREATER THAN THAT REQUIRED FOR NEW BUILDINGS, AND
SECTION 9.625
Seismic Design Requirements
THE ADDITION SHALL NOT DECREASE THE SEISMIC RESISTANCE OF ANY STRUCTURAL ELEMENT OF THEEXISTING BUILDING UNLESS THE REDUCED SEISMIC RESISTANCE OF THE ELEMENT IS EQUAL TO OR GREATER THAN THAT REQUIRED FOR NEW BUILDINGS.
SECTION 9.625
Seismic Design Requirements
IF A BUILDING IS DAMAGED BY FIRE, ALL DAMAGED LATERAL LOAD RESISTING COMPONENTS OF A BUILDING’S STRUCTURAL SYSTEM MUST BE DESIGNED AND REBUILT TO CURRENT PROVISIONS OF THE OREGON STRUCTURAL SPECIALTY CODE.
SECTION 9.630
Seismic Design RequirementsTHESE COMPONENTS MUST ALSO BE CONNECTED TO THE BALANCE OF THE UNDAMAGED LATERAL LOAD RESISTING SYSTEM IN CONFORMANCE WITH CURRENT CODE PROVISIONS. UNDAMAGED COMPONENTS NEED NOT BE UPGRADED TO CURRENT LATERAL LOAD PROVISIONS OF THE CURRENT CODE, UNLESS REQUIRED BY OTHER PROVISIONS OF THE OREGON STRUCTURAL SPECIALTY CODE.
SECTION 9.630
Seismic Design RequirementsWHEN AND ALTERATION, FOR WHICH A BUILDING PERMIT IS REQUIRED, HAS A VALUE OF MORE THAN $100,000 A FEMA 178 EVALUATION IS REQUIRED. A LETTER OF INTENT TO HAVE A FEMA 178 EVALUATION PERFORMED MAY BE SUBMITTED ALONG WITH THE PERMIT APPLICATION. THE EVALUATION MUST BE COMPLETED BEFORE ANY FUTURE PERMITS WILL BE ISSUED. THE FOLLOWING SHALL BE EXEMPTED FROM THIS REQUIREMENT:
SECTION 9.635
Seismic Design Requirements
BUILDINGS CONSTRUCTED OR RENOVATED TO SEISMIC ZONE 2, 2B OR 3 UNDER A PERMIT ISSUED AFTER JANUARY 1, 1974.ONE-AND-TWO FAMILY DWELLINGS.SINGLE STORY, LIGHT METAL BUILDINGS LESS THAN 5,000 SQUARE FEET IN AREA.LIGHT WOOD BUILDINGS LESS THAN 5,000 SQUARE FEET IN AREA.A PREVIOUSLY PREPARED SEISMIC STUDY MAY BE SUBMITTED FOR CONSIDERATION BY THE DEPARTMENT AS EQUIVALENT TO A FEMA 178 EVALUATION.
SECTION 9.635
Seismic Design Requirements
SEISMIC HAZARDS SHALL BE MITIGATED IN CONJUCTION WITH BUILDING ALTERATIONS AND REPAIRS IN UNREINFORCED MASONRYBUILDINGS, AS FOLLOWS:WHEN THE ROOF COVERING IS REPAIRED OR REPLACED, THE BUILDING STRUCTURAL ROOF SYSTEM, ANCHORAGE, AND PARAPET SHALL BE REPAIRED AND REHABILITATED PER APPENDIX C OF THE DESIGN STANDARDS-FEMA 178, OR
SECTION 9.640
Seismic Design Requirements
WHEN THE COST OF ALTERATION WORK WHICH REQUIRES A BUILDING PERMIT IN A 2 YEAR PERIOD EXCEEDS A $15 PER SQUARE FOOT FOR THE TOTAL NET FLOOR AREA IN THE BUILDING, THEN THE BUILDING SHALL BE IMPROVED SEISMICALLY PER SECTION 9.610.
SECTION 9.640
Seismic Design Requirements
COSTS FOR SITE IMPROVEMENTS AND MANDATORY FM41 AGREEMENTS, MANDATED ADA IMPROVEMENTS, MANDATED LANDSCAPING AND MANDATED OR VOLUNTARY SEISMIC IMPROVEMENTS WILL NOT BE INCLUDED IN THE $15 PER SQUARE FOOT AMOUNT.
SECTION 9.640
Seismic Design Requirements
THE BUILDING SAFETY DIRECTOR MAY APPROVE A MULTI-YEAR PHASED PROGRAM OF SEISMIC IMPROVEMENTS WHEN THE IMPROVEMENTS ARE PRE-DESIGNED AND AN IMPROVEMENT/IMPLEMENTATION PLAN IS APPROVED BY THE BUILDING SAFETY DIRECTOR. THE MAXIMUM TOTAL TIME ALLOWED FOR COMPLETION OF PHASED IMPROVEMENTS SHALL BE TEN YEARS.
SECTION 9.645
Seismic Design Requirements
BUILDING PERMIT APPLICATIONS TO IMPROVE THE SEISMIC CAPABILITY OF A BUILDING SHALL NOT TRIGGER:ACCESSIBILITY IMPROVEMENTS SO LONG AS THE SEISMIC IMPROVEMENT DOES NOT LESSEN ACCESSIBILITY.FIRE LIFE SAFETY IMPROVEMENTS SO LONG AS THE SEISMIC IMPROVEMENT DOES NOT LESSON THE BUILDING’S FIRE RESISTANCE OR EXITING CAPABILITY.
SECTION 9.650
Seismic Design Requirements
LANDSCAPE IMPROVEMENTS REQUIRED BY THE LAND DEVELOPMENT CODE CHAPTER 10.STREET TREE IMPROVEMENTS REQUIRED BY THE LAND DEVELOPMENTS CODE.CONFORMANCE WITH THESE INTERIM REGULATIONS MAY NOT EXEMPT BUILDINGS FROM FUTURE SEISMIC REQULATIONS.
SECTION 9.650
Seismic Design Requirements
BUILDING PERMIT, PLAN REVIEW AND FIRE LIFE SAFETY REVIEW FEES ARE WAIVED WHEN SUCH FEES TOTAL LESS THEN $2,500, AND REDUCED BY 50% WHEN SUCH FEES WOULD TOTAL $2,500 OR MORE.
SECTION 9.655
Seismic Design Requirements
BECAUSE UNANTICIPATED CIRCUMSTANCES MAY ARISE IN THE ENFORCEMENT OF THESE REQUIREMENTS FOR EXISTING BUILDINGS, CONSIDERATION AS TO THE REASONABLE APPLICATION OF THIS CHAPTER MAY BE ADDRESSED THROUGH THE UNITED APPEAL BOARD. SEE SECTION 2.475 THROUGH 2.481.
SECTION 9.655
Yes
NoYes
NoYes
No
YesYes
NoYes
No
NoYes
No
REHABILITATE, CONFORM TO
Yes
ATTACH WALLS TO ROOF structureand BRACE PARAPETS as needed
per FEMA 178, appendix c
to become overloaded?(Strength and / or stiffness)
Upgrade building toUBC.1994
Upgrade building toUBC.1994
FEMA 178EVALUATION
FEMA 178, appendix C
Does work cause existing element
New elements conformto UBC.1994
APPLICATION FOR WORKON EXISTING BUILDING
ADDITION with LOAD > 5% on BLDG?
CHANGE OF OCCUPANCY(To higher hazard) OR 20%increase of occupant load?
PERMIT VALUE> $100,000?
URM BLDG.Unreinforced Masonry Bldg?
PERMIT VALUE>$15/Sq Ft?
ROOF REPAIR 50%or more of roof covering?
Any new structural elements requiringstructural design or are fire-damagedstructural elements being replaced?
Any work done to existingstructural elements?
GUIDELINES FOR STRUCTURAL WORK IN EXISTING BUILDINGS
No YesElement must be
improved toUBC.1994
Element can be modified
code for new workwithout conforming to
NO STRUCTURAL REQUIREMENTS