section e: terms of reference (tor) - world...

14
EEPCo Kenyan MoE ETHIOPIA – KENYA POWER SYSTEMS INTERCONNECTION PROJECT TERMS OF REFERENCE FOR ADDITIONAL ESIA AND RAP FOR MODIFIED ROUTE E2402 V4

Upload: hadien

Post on 23-Sep-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

EEPCo Kenyan MoE

ETHIOPIA – KENYA POWER SYSTEMS

INTERCONNECTION PROJECT

TERMS OF REFERENCE FOR ADDITIONAL ESIA AND RAP FOR MODIFIED ROUTE

JULY, 2009

E2402V4

Page 2: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land
Page 3: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

ETHIOPIA- KENYA POWER SYSTEMS INTERCONNECTION PROJECT

TERMS OF REFERENCE for ADDITIONAL ESIA AND RAP FOR MODIFIED ROUTE

1 Background

The feasibility study report of the Ethiopia-Kenya Power Interconnection project proposed the construction of a point-to-point HVDC connection between Wolayita/Sodo in Ethiopia and Longonot in Kenya, with HVAC sections from Longonot to Isinya (Nairobi) in Kenya.

This necessitated a change of some sections of the earlier proposed route, which was going through Mega, Moyale, Marsabit and other ecologically sensitive and highly populated areas.

A new route has been proposed, going straight southwards from Konso in Ethiopia, through Dukana in Kenya to join the earlier route at Rumuruti. There is therefore need to undertake an ESIA and RAP study on the proposed new route sections before the project is implemented. Similar studies had already been undertaken on the earlier proposed line route.

The consultant is therefore expected to update the existing ESIA report, and incorporate all existing issues in the new proposed route section, taking into consideration all safeguard policies.

2 Objectives

The aim of the study is to achieve the following objectives:

1. Review of existing ESIA and RAP reports on sections of the line which are not changed.

2. To identify and assess potential environmental and socials impacts of the project.3. To identify all potential significant adverse environmental and social impacts of the

projects and recommend measures for mitigation. 4. To review and develop an Environmental and Social Management Plan (ESMP) and

RAP.5. To prepare an Environmental and Social Impact Assessment, RAP and ESMP reports

compliant to the relevant authorities, and detailing findings and recommendations.

Page 4: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

3 Scope

The consultant is expected to undertake investigations on social aspects, economic activities, conservation of natural resources, historical and anthropological heritages, public consultations and disclosures. The proposed transmission line route and associated substations will be provided to give a guideline of the facilities to be studied.

The scope of services to be undertaken by the Consultant shall include the following:

Task 1. Detailed Desk-top Review: The Consultant is to review all existing documentation, and previous ESIA, RAP and ESMP reports on other route options. He shall further undertake a detailed study of the proposed new route section, mapping the desktop route on actual map of appropriate scale. The Consultant shall then concisely describe each facility assessed, its geographic, ecological, general layout of facilities including maps at appropriate scale where necessary. Information on size, capacity, facilities and services should also be provided.

Task 2. Line Routing: The consultant shall undertake a route survey from the proposed desktop route, and georeference accordingly on maps of appropriate scale.

Task 3. Description of the baseline environment: The Consultant is required to collect, collate and present baseline information on the environmental characteristics of the existing situation around each facility. This description should involve but not limited to:

a) Physical environment (topography, land cover, geology, climate and meteorology, air quality, hydrology etc.,

b) Biological environment (i.e., flora and fauna types and diversity, endangered species, sensitive habitats etc.)

c) Social and cultural environment, including present and projected, where appropriate (i.e., population, land use, planned development activities, community social structure, employment and labour market, sources and distribution of income, cultural/religious sites and properties, vulnerable groups and indigenous populations etc)

d) Economic activities, agriculture, livestock, fisheries, small scale industries etc.

Task 4. Legislative and Regulatory Framework: The Consultant shall identify and describe the pertinent regulations and standards- both local and international, governing the environmental quality, health and safety, protection of sensitive areas, land use control at the national and local levels and ecological and socio-economic issues. Thereafter, the Consultant shall identify the project activities that should comply with the identified regulations.

Page 5: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

Task 5. Determination of impacts of project facilities and activities: From the detailed field study, the Consultant shall analyse and describe all significant changes brought about by each facility/activity. These would encompass environmental, ecological and social impacts, both positive and negative, as a result of each facility/activity intervention that are likely to bring about changes in the baseline environmental and social conditions discussed in Task 2. The Consultant will make a prioritization of all concerns identified and differentiate between short, medium, long-term and cumulative impacts during construction, operation and decommissioning. The Consultant shall also identify both temporary and permanent impacts. A detailed outline and discussion of specific conditions that might affect the environment which are unique to the type of facility and/or operation being audited should be provided.

Task 6. Occupational health and safety concerns: The Consultant shall analyse and describe all occupational health and safety concerns brought about by activities during all the phases of the project.The Consultant shall make recommendations on corrective and remedial measures to be implemented under the environmental management plan.

Task 7. Development of management plan to mitigate negative impacts: The Consultant shall develop a comprehensive environmental management plan. The plan should recommend a set of mitigation, monitoring and institutional measures to eliminate, minimise or reduce to acceptable levels of adverse environmental impacts and/or maximise socio-economic benefits. The Consultant should provide cost outlays for the proposed mitigation measures as well as their institutional and financial support, time frame and responsibility. This shall be provided for all the project phases.

Task 8. Development of re-settlement action plan: The consultant shall undertake a socio-economic survey of the communities

along the proposed line route. Conduct a census of the affected persons, and identification of vulnerable groups

and indigenous populations. Develop an eligibility criteria, and establishment of a cut-off date. Evaluate and prepare an inventory of the affected properties. Evaluate all other socio-economic costs. Conduct public consultations/awareness creation of the relevant stake-holders,

taking into consideration the gender concerns and vulnerable groups. Identification of alternative relocation sites; where affected persons might have

to be resettled. Develop adequate livelihood restoration mechanisms. Prepare the resettlement implementation costs. Preparation of implementation schedule. Develop a monitoring and evaluation methodology

Page 6: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

Consider the relevant legal provisions for land acquisition and resettlement during preparation of an appropriate re-settlement action plan.

Prepare and submit a detailed resettlement action plan. Develop a conflict resolution mechanism.

Task 9. Development of monitoring plan: The Consultant is required to give a specific description, and technical details, of monitoring measures for both ESMP and RAP, including the parameters to be measured, methods to be used, sampling locations, frequency of measurements, definition of thresholds that will signal the need for corrective actions as well as deliver a monitoring and reporting procedure. The Consultant should provide a time frame and implementation mechanism, staffing requirements, training and cost outlays.

Task 10. Comparison: The consultant shall undertake a comparison of all the earlier routes considered and studied. These other alternatives shall be compared to the proposed final route; and pros/cons of each route selection detailed.

Task 11. Study Reports: The output will be an Environmental and Social Impact Assessment report and Resettlement Action Plan prepared in accordance with the regulatory provisions. The report shall be in the English Language and has to be clear and concise. The reports should be in a format acceptable to local competent authorities, international environmental standards and development partners. The Consultant shall present the reports to relevant environmental authorities for approval in the required number of copies.

Task 12. Approval: The Consultant shall present the report prepared under Task 9 for approval by the relevant authorities. The Consultant shall be responsible for making any modifications that the authorities may demand before approval of the report.

Task 13. Counterpart Staff: For the purpose of capacity building the Consultant shall undertake the study together with counterpart staff seconded by the Client.

4 Schedule of the Study and Reports

The assignment is expected to be completed within eighteen (18) weeks.

The Consultant will submit to the Client:(a) Inception Report: 10 hard copies after the desktop review to each client,

and 2 hard copies each to the two countries’ competent authorities, describing the facilities to be assessed, a detailed work plan outlining the schedule of field work within three (3) weeks of commencement. A soft copy shall also be provided to both clients.

Page 7: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

(b) Interim Report: 10 hard copies to each client, within Twelve (12) weeks of commencement. A soft copy shall also be provided to both clients. This shall include both the ESIA and RAP reports.

(c) Draft Final Report: 20 copies of draft final report incorporating the Clients’ comments on the interim report to each client. The Consultant shall present this report in a stakeholder workshop and incorporate comments thereof. This shall be within fifteen (15) weeks of commencement

(d) Final Report: 20 copies of the final report to both clients, taking into consideration all issues raised during the stakeholders workshop for forwarding to the relevant approval authorities. This should be within eighteen (18) weeks of commencement.

The final reports shall also be provided in computer diskettes/CD-ROM in Microsoft Word for text, tables/graphs and spreadsheets shall be in Microsoft Excel and drawings in AutoCAD.

5 Facilities to be Provided by the Client

The Client will provide the following facilities:a) All previous ESIA studies and RAP reports.b) Desktop map of the proposed route.c) Access to relevant information to the extent of its availability.d) Counterpart staff to assist in route survey.e) Access to the plant and other sites belonging to the Clients as the Consultant

may request.

6 Conduct of Work

The consultant will be expected to be fluent in English and be able to work closely with the clients’ staff and other third parties relevant to the assessment. All documentation shall be in English.

7 Improvement of Terms of Reference

The Consultant may offer suggestions and improvements to the Terms of Reference that he considers would result in better implementation of the project. Such proposals if accepted will form part of the Terms of Reference of the assignment. The effect on time and cost estimates given under the above clause shall be clearly identified.

Page 8: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

8. StaffThe following key staff shall be provided for the assignment:

a) Team leader/ Project managerb) Socio-economistc) Environmental expertd) Biologiste) GIS expertf) Sociologistg) Surveyor

Page 9: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

Overview of sections to be surveyed

Page 10: SECTION E: TERMS OF REFERENCE (TOR) - World …documents.worldbank.org/.../E24020v40P11691nal0ESIA…  · Web viewTERMS OF REFERENCE for ... Physical environment (topography, land

The map below provides an overview on the routings and areas to be investigated and discussed in the routing evaluation report.