section 23 05 00 common work results for hvac part 1

241
CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085 COMMON WORK RESULTS FOR HVAC 23 05 00 - 1 SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Piping materials and installation instructions common to most piping systems. 2. Transition fittings. 3. Dielectric fittings. 4. Mechanical sleeve seals. 5. Sleeves. 6. Escutcheons. 7. Grout. 8. Equipment installation requirements common to equipment sections. 9. Painting and finishing. 10. Concrete bases. 11. Supports and anchorages. B. General: Work shall be performed in accordance with these specifications and good practice. No modifications to these specifications will be accepted without the expressed written approval of the owner. It is the Contractor's responsibility to document owner's approval of any such modifications prior to the execution of work. Requirements of these Specifications modified by any addenda, change orders, written approvals and written instructions issued by the owner, if any, shall be as specifically identified by Section and Paragraph in those addenda, change orders, written approvals and written instructions. Approvals of submittals are subject to additional limitations described elsewhere in these Specifications. System concept drawing sheets are for information only to show potential system arrangement. Field verify information contained on these drawings and is responsible for design and installation of the system in accordance with the specifications. The bid drawings do not show all information necessary for installation of the system,but are intended to be used as a guide for the purpose of designing the systems and preparing a bid. In case of discrepancy between plans and specifications, specifications shall rule. C. For removal of debris and salvage, refer to Pace Exhibit E. 1.02 DEFINITIONS A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels. B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms. C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations. D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and chases. E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures. Examples include installations within unheated shelters.

Upload: others

Post on 28-Dec-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 1

SECTION 23 05 00

COMMON WORK RESULTS FOR HVAC

PART 1 - GENERAL

1.01 SUMMARY

A. This Section includes the following:

1. Piping materials and installation instructions common to most piping systems. 2. Transition fittings. 3. Dielectric fittings. 4. Mechanical sleeve seals. 5. Sleeves. 6. Escutcheons. 7. Grout. 8. Equipment installation requirements common to equipment sections. 9. Painting and finishing. 10. Concrete bases. 11. Supports and anchorages.

B. General: Work shall be performed in accordance with these specifications and good practice. No modifications to these specifications will be accepted without the expressed written approval of the owner. It is the Contractor's responsibility to document owner's approval of any such modifications prior to the execution of work. Requirements of these Specifications modified by any addenda, change orders, written approvals and written instructions issued by the owner, if any, shall be as specifically identified by Section and Paragraph in those addenda, change orders, written approvals and written instructions. Approvals of submittals are subject to additional limitations described elsewhere in these Specifications. System concept drawing sheets are for information only to show potential system arrangement. Field verify information contained on these drawings and is responsible for design and installation of the system in accordance with the specifications. The bid drawings do not show all information necessary for installation of the system,but are intended to be used as a guide for the purpose of designing the systems and preparing a bid. In case of discrepancy between plans and specifications, specifications shall rule.

C. For removal of debris and salvage, refer to Pace Exhibit E.

1.02 DEFINITIONS

A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels.

B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.

C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.

D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and chases.

E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures. Examples include installations within unheated shelters.

Page 2: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 2

F. The following are industry abbreviations for plastic materials:

1. CPVC: Chlorinated polyvinyl chloride plastic. 2. PE: Polyethylene plastic. 3. PVC: Polyvinyl chloride plastic. 4. HDPE: High density Polyethylene pipe.

G. The following are industry abbreviations for rubber materials:

1. EPDM: Ethylene-propylene-diene terpolymer rubber. 2. NBR: Acrylonitrile-butadiene rubber.

1.03 SUBMITTALS

A. Product Data: For the following:

1. Transition fittings. 2. Dielectric fittings. 3. Mechanical sleeve seals. 4. Escutcheons.

B. Welding certificates.

1.04 QUALITY ASSURANCE

A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel."

B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."

1. Comply with provisions in ASME B31, "Building Services Piping." 2. Certify that each welder has passed AWS qualification tests for welding processes involved

and that certification is current.

C. Electrical Characteristics for HVAC Equipment: Equipment of higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.

B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.

1.06 COORDINATION

A. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of construction, to allow for HVAC installations.

B. Coordinate installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed.

C. Coordinate requirements for access panels and doors for HVAC items requiring access that are concealed behind finished surfaces. Access panels and doors are specified in Section 23 33 00 "Air Duct Accessories."

Page 3: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 3

PART 2 - PRODUCTS

2.01 PIPE, TUBE, AND FITTINGS

A. Refer to individual Division 23 piping Sections for pipe, tube, and fitting materials and joining methods.

B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.

2.02 JOINING MATERIALS

A. Refer to individual Division 23 piping Sections for special joining materials not listed below.

B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.

1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch maximum thickness unless thickness or specific material is indicated.

a. Full-Face Type: For flat-face, Class 125, cast-iron and cast- bronze flanges. b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.

2. AWWA C110, rubber, flat face, 1/8 inch thick, unless otherwise indicated; and full-face or ring type, unless otherwise indicated.

C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.

D. Plastic, Pipe-Flange Gasket, Bolts, and Nuts: Type and material recommended by piping system manufacturer, unless otherwise indicated.

E. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according to ASTM B 813.

F. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver alloy for refrigerant piping, unless otherwise indicated.

G. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

H. Solvent Cements for Joining Plastic Piping:

1. PVC Piping: ASTM D 2564. Include primer according to ASTM F 656.

2.03 TRANSITION FITTINGS

A. Plastic-to-Metal Transition Fittings: PVC one-piece fitting with manufacturer's Schedule 80 equivalent dimensions; one end with threaded brass insert, and one solvent-cement-joint end.

1. Manufacturer: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Eslon Thermoplastics. b. Spears Manufacturing Co. c. Lasco Fittings, Inc.

Page 4: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 4

B. Plastic-to-Metal Transition Adaptors: One-piece fitting with manufacturer's SDR 11 equivalent dimensions; one end with threaded brass insert, and one solvent-cement-joint end.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Thompson Plastics, Inc. b. NIBCO, Inc. c. Eslon Thermoplastic

C. Plastic-to-Metal Transition Unions: MSS SP-107, PVC four-part union. Include brass end, solvent-cement-joint end, rubber O-ring, and union nut.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. NIBCO INC. b. Eslon Thermoplastic c Spears Manufacturing Co.

2.04 DIELECTRIC FITTINGS

A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solder-joint, plain, or weld-neck end connections that match piping system materials.

B. Insulating Material: Suitable for system fluid, pressure, and temperature. C. Dielectric Unions: Factory-fabricated, union assembly, for 250-psig minimum working pressure at 180

Deg F.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Capitol Manufacturing Co. b. Central Plastics Company. c. Eclipse, Inc. d. Epco Sales, Inc. e. Hart Industries, International, Inc. f. Watts Industries, Inc.; Water Products Div. g. Zurn Industries, Inc.; Wilkins Div.

D. Dielectric Flanges: Factory-fabricated, companion-flange assembly, for 150- or 300-psig minimum working pressure as required to suit system pressures.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Capitol Manufacturing Co. b. Central Plastics Company. c. Epco Sales, Inc. d. Watts Industries, Inc.; Water Products Div.

E. Dielectric-Flange Kits: Companion-flange assembly for field assembly. Include flanges, full-face- or ring-type neoprene or phenolic gasket, phenolic or polyethylene bolt sleeves, phenolic washers, and steel backing washers.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Advance Products & Systems, Inc. b. Calpico, Inc.

Page 5: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 5

c. Central Plastics Company. d. Pipeline Seal and Insulator, Inc.

2. Separate companion flanges and steel bolts and nuts shall have 150- or 300-psig minimum working pressure where required to suit system pressures.

F. Dielectric Couplings: Galvanized-steel coupling with inert and noncorrosive, thermoplastic lining; threaded ends; and 300-psig minimum working pressure at 225 Deg F.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Calpico, Inc. b. Lochinvar Corp. c. Advance Products & System Inc.

G. Dielectric Nipples: Electroplated steel nipple with inert and noncorrosive, thermoplastic lining; plain, threaded, or grooved ends; and 300-psig minimum working pressure at 225 Deg F.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Perfection Corp. b. Precision Plumbing Products, Inc. c. Sioux Chief Manufacturing Co., Inc.

2.05 MECHANICAL SLEEVE SEALS

A. Description: Modular sealing element unit, designed for field assembly, to fill annular space between pipe and sleeve.

1. Manufacturers: Subject to compliance with requirements, manufacturers provide products by one of the following:

a. Advance Products & Systems, Inc. b. Calpico, Inc. c. Metraflex Co. d. Pipeline Seal and Insulator, Inc.

2. Sealing Elements: EPDM interlocking links shaped to fit surface of pipe. Include type and number required for pipe material and size of pipe.

3. Pressure Plates: Stainless steel. Include two for each sealing element. 4. Connecting Bolts and Nuts: Stainless steel of length required to secure pressure plates to

sealing elements. Include one for each sealing element.

2.06 SLEEVES

A. Galvanized-Steel Sheet: 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint.

B. Steel Pipe: ASTM A 53, Type E, Grade B, Schedule 40, galvanized, plain ends.

C. Stack Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange. Include clamping ring and bolts and nuts for membrane flashing.

1. Underdeck Clamp: Clamping ring with set screws.

2.07 ESCUTCHEONS

Page 6: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 6

A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an ID to closely fit around pipe, tube, and insulation of insulated piping and an OD that completely covers opening.

B. One-Piece, Deep-Pattern Type: Deep-drawn, box-shaped brass with polished chrome-plated finish.

C. One-Piece, Stamped-Steel Type: With set screw or spring clips and chrome-plated finish.

D. Split-Plate, Stamped-Steel Type: With concealed hinge, set screw or spring clips, and chrome-plated finish.

E. One-Piece, Floor-Plate Type: Cast-iron floor plate.

F. Split-Casting, Floor-Plate Type: Cast brass with concealed hinge and set screw.

2.08 GROUT

A. Description: ASTM C 1107, Grade B, nonshrink and nonmetallic, dry hydraulic-cement grout.

1. Characteristics: Post-hardening, volume-adjusting, nonstaining, noncorrosive, nongaseous, and recommended for interior and exterior applications.

2. Design Mix: 5000-psi, 28-day compressive strength. 3. Packaging: Premixed and factory packaged.

PART 3 - EXECUTION

3.01 PIPING SYSTEMS - COMMON REQUIREMENTS

A. Install piping according to the following requirements and Division 23 Sections specifying piping systems.

B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Drawings.

C. Install piping in concealed locations, unless otherwise indicated and except in equipment rooms and service areas.

D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

F. Install piping to permit valve servicing. G. Install piping at indicated slopes. H. Install piping free of sags and bends.

I. Install fittings for changes in direction and branch connections. J. Install piping to allow application of insulation. K. Select system components with pressure rating equal to or greater than system operating pressure.

L. Install escutcheons for penetrations of walls, ceilings, and floors according to the following:

Page 7: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 7

1. New Piping:

a. Piping with Fitting or Sleeve Protruding from Wall: One-piece, deep-pattern type. b. Chrome-Plated Piping: One-piece, cast-brass type with polished chrome-plated

finish. c. Insulated Piping: One-piece, stamped-steel type with spring clips. d. Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece, cast-

brass type with polished chrome-plated finish. e. Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece,

stamped-steel type. f. Bare Piping at Ceiling Penetrations in Finished Spaces: One- piece, cast-brass

type with polished chrome-plated finish. g. Bare Piping at Ceiling Penetrations in Finished Spaces: One- piece, stamped-steel

type and set screw. h. Bare Piping in Unfinished Service Spaces: One-piece, cast-brass type with

polished chrome-plated finish. i. Bare Piping in Unfinished Service Spaces: One-piece, stamped- steel type with

concealed hinge and set screw or spring clips. j. Bare Piping in Equipment Rooms: One-piece, cast-brass type. k. Bare Piping in Equipment Rooms: One-piece, stamped-steel type with set screw or

spring clips. l. Bare Piping at Floor Penetrations in Equipment Rooms: One- piece, floor-plate

type.

M. Sleeves are not required for core-drilled holes.

N. Permanent sleeves are not required for holes formed by removable PE sleeves.

O. Install sleeves for pipes passing through concrete and masonry walls and concrete floor and roof slabs.

P. Install sleeves for pipes passing through concrete and masonry walls, gypsum-board partitions, and concrete floor and roof slabs.

1. Cut sleeves to length for mounting flush with both surfaces.

a. Exception: Extend sleeves installed in floors of mechanical equipment areas or other wet areas 2 inches above finished floor level. Extend cast-iron sleeve fittings below floor slab as required to secure clamping ring if ring is specified.

2. Install sleeves in new walls and slabs as new walls and slabs are constructed. 3. Install sleeves that are large enough to provide 1/4-inch annular clear space between sleeve

and pipe or pipe insulation. Use the following sleeve materials:

a. Steel Pipe Sleeves: For pipes smaller than NPS 6. b. Steel Sheet Sleeves: For pipes NPS 6 and larger, penetrating gypsum-board

partitions. c. Stack Sleeve Fittings: For pipes penetrating floors with membrane waterproofing.

Secure flashing between clamping flanges. Install section of cast-iron soil pipe to extend sleeve to 2 inches above finished floor level. Refer to Section 07 62 00 "Sheet Metal Flashing and Trim" for flashing.

1) Seal space outside of sleeve fittings with grout.

4. Except for underground wall penetrations, seal annular space between sleeve and pipe or pipe insulation, using joint sealants appropriate for size, depth, and location of joint. Refer to Section 07 92 00 "Joint Sealants" for materials and installation.

Q. Aboveground, Exterior-Wall Pipe Penetrations: Seal penetrations using sleeves and mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for

Page 8: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 8

installing mechanical sleeve seals.

1. Install steel pipe for sleeves smaller than 6 inches in diameter. 2. Install cast-iron "wall pipes" for sleeves 6 inches and larger in diameter. 3. Mechanical Sleeve Seal Installation: Select type and number of sealing elements required for

pipe material and size. Position pipe in center of sleeve. Assemble mechanical sleeve seals and install in annular space between pipe and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

R. Underground, Exterior-Wall Pipe Penetrations: Install cast-iron "wall pipes" for sleeves. Seal pipe penetrations using mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

1. Mechanical Sleeve Seal Installation: Select type and number of sealing elements required for pipe material and size. Position pipe in center of sleeve. Assemble mechanical sleeve seals and install in annular space between pipe and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

S. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe penetrations with firestop materials. Refer to Section 07 84 13 "Penetration Firestopping" for materials.

T. Verify final equipment locations for roughing-in.

U. Refer to equipment specifications in other Sections of these Specifications for roughing-in requirements.

3.02 PIPING JOINT CONSTRUCTION

A. Join pipe and fittings according to the following requirements and Division 23 Sections specifying piping systems.

B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32.

E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube" Chapter, using copper-phosphorus brazing filler metal complying with AWS A5.8.

F. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

G. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article.

H. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

I. Plastic Piping Solvent-Cement Joints: Clean and dry joining surfaces. Join pipe and fittings

Page 9: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 9

according to the following:

1. Comply with ASTM F 402 for safe-handling practice of cleaners, primers, and solvent

cements. 2. PVC Nonpressure Piping: Join according to ASTM D 2855.

J. Plastic Pressure Piping Gasketed Joints: Join according to ASTM D 3139. K. Plastic Nonpressure Piping Gasketed Joints: Join according to ASTM D 3212.

3.03 PIPING CONNECTIONS

A. Make connections according to the following, unless otherwise indicated:

1. Install unions, in piping NPS 2 and smaller, adjacent to each valve and at final connection to each piece of equipment.

2. Install flanges, in piping NPS 2-1/2 and larger, adjacent to flanged valves and at final connection to each piece of equipment.

3. Dry Piping Systems: Install dielectric unions and flanges to connect piping materials of dissimilar metals.

4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals.

3.04 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS

A. Install equipment to allow maximum possible headroom unless specific mounting heights are not indicated.

B. Install equipment level and plumb, parallel and perpendicular to other building systems and components in exposed interior spaces, unless otherwise indicated.

C. Install HVAC equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interference to other installations. Extend grease fittings to accessible locations.

D. Install equipment to allow right of way for piping installed at required slope.

3.05 PAINTING

A. Painting of HVAC systems, equipment, and components is specified in Section 09 90 00 "Painting”, and Section 230503 “Basic Mechanical requirements for HVAC Systems”.

B. Damage and Touchup: Repair marred and damaged factory-painted finishes with materials and

procedures to match original factory finish.

3.06 CONCRETE BASES

A. Concrete Bases: Anchor equipment to concrete base according to equipment manufacturer's written instructions.

1. Construct concrete bases of dimensions indicated, but not less than 6 inches larger in both directions than supported unit.

2. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch centers around the full perimeter of the base.

3. Install epoxy-coated anchor bolts for supported equipment that extend through concrete base, and anchor into structural concrete floor.

4. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

Page 10: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS –

ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR HVAC 23 05 00 - 10

5. Install anchor bolts to elevations required for proper attachment to supported equipment. 6. Install anchor bolts according to anchor-bolt manufacturer's written instructions. 7. Use 5000-psi, 28-day compressive-strength concrete and reinforcement as specified in

Section 03 30 00 "Cast-in-Place Concrete."

3.07 ERECTION OF METAL SUPPORTS AND ANCHORAGES

A. Refer to Section 05 50 00 "Metal Fabrications" for structural steel.

B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor HVAC materials and equipment.

C. Field Welding: Comply with AWS D1.1.

3.08 GROUTING

A. Mix and install grout for HVAC equipment base bearing surfaces, pump and other equipment base plates, and anchors.

B. Clean surfaces that will come into contact with grout. C. Provide forms as required for placement of grout. D. Avoid air entrapment during placement of grout. E. Place grout, completely filling equipment bases. F. Place grout on concrete bases and provide smooth bearing surface for equipment. G. Place grout around anchors. H. Cure placed grout.

END OF SECTION

Page 11: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT230513 - 1

SECTION 230513COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes general requirements for single-phase and polyphase, general-purpose, horizontal, small and medium, squirrel-cage induction motors for use on alternating-current power systems up to 600 V and installed at equipment manufacturer's factory or shipped separately by equipment manufacturer for field installation.

1.3 COORDINATION

A. Coordinate features of motors, installed units, and accessory devices to be compatible with the following:

1. Motor controllers.2. Torque, speed, and horsepower requirements of the load.3. Ratings and characteristics of supply circuit and required control sequence.4. Ambient and environmental conditions of installation location.

PART 2 - PRODUCTS

2.1 GENERAL MOTOR REQUIREMENTS

A. Comply with NEMA MG 1 unless otherwise indicated.

B. Comply with IEEE 841 for severe-duty motors.

2.2 MOTOR CHARACTERISTICS

A. Duty: Continuous duty at ambient temperature of 40 deg C and at altitude of 850 feet above sea level.

B. Capacity and Torque Characteristics: Sufficient to start, accelerate, and operate connected loads at designated speeds, at installed altitude and environment, with indicated operating sequence, and without exceeding nameplate ratings or considering service factor.

2.3 POLYPHASE MOTORS

A. Description: NEMA MG 1, Design B, medium induction motor.

B. Efficiency: Premium efficient, as defined in NEMA MG 1.

C. Service Factor: 1.15.

Page 12: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT230513 - 2

D. Multispeed Motors: Variable torque.

1. For motors with 2:1 speed ratio, consequent pole, single winding.2. For motors with other than 2:1 speed ratio, separate winding for each speed.

E. Multispeed Motors: Separate winding for each speed.

F. Rotor: Random-wound, squirrel cage.

G. Bearings: Regreasable, shielded, antifriction ball bearings suitable for radial and thrust loading.

H. Temperature Rise: Match insulation rating.

I. Insulation: Class F.

J. Code Letter Designation:

1. Motors 15 HP and Larger: NEMA starting Code F or Code G.2. Motors Smaller Than 15 HP: Manufacturer's standard starting characteristic.

K. Enclosure Material: Cast iron for motor frame sizes 324T and larger; rolled steel for motor frame sizes smaller than 324T.

2.4 ADDITIONAL REQUIREMENTS FOR POLYPHASE MOTORS

A. Motors Used with Reduced-Voltage and Multispeed Controllers: Match wiring connection requirements for controller with required motor leads. Provide terminals in motor terminal box, suited to control method.

B. Motors Used with Variable-Frequency Controllers: Ratings, characteristics, and features coordinated with and approved by controller manufacturer.

1. Windings: Copper magnet wire with moisture-resistant insulation varnish, designed and tested to resist transient spikes, high frequencies, and short time rise pulses produced by pulse-width-modulated inverters.

2. Premium-Efficient Motors: Class B temperature rise; Class F insulation.3. Inverter-Duty Motors: Class F temperature rise; Class H insulation.4. Thermal Protection: Comply with NEMA MG 1 requirements for thermally protected motors.

C. Severe-Duty Motors: Comply with IEEE 841, with 1.15 minimum service factor.

2.5 SINGLE-PHASE MOTORS

A. Motors larger than 1/20 hp shall be one of the following, to suit starting torque and requirements of specific motor application:

1. Permanent-split capacitor.2. Split phase.3. Capacitor start, inductor run.4. Capacitor start, capacitor run.

B. Multispeed Motors: Variable-torque, permanent-split-capacitor type.

C. Bearings: Prelubricated, antifriction ball bearings or sleeve bearings suitable for radial and thrust loading.

D. Motors 1/20 HP and Smaller: Shaded-pole type.

Page 13: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT230513 - 3

E. Thermal Protection: Internal protection to automatically open power supply circuit to motor when winding temperature exceeds a safe value calibrated to temperature rating of motor insulation. Thermal-protection device shall automatically reset when motor temperature returns to normal range.

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 230513

Page 14: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT230513 - 4

This page is intentionally left blank.

Page 15: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

VIBRATION CONTROLS FOR HVAC230548.13 - 1

SECTION 230548.13VIBRATION CONTROLS FOR HVAC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:1. Open-spring isolators.2. Housed-spring isolators.3. Restrained-spring isolators.4. Housed-restrained-spring isolators.5. Vibration isolation equipment bases.6. Restrained isolation roof-curb rails.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include rated load, rated deflection, and overload capacity for each vibration isolation device.2. Illustrate and indicate style, material, strength, fastening provision, and finish for each type and size

of vibration isolation device type required.

B. Shop Drawings:

1. Detail fabrication and assembly of equipment bases. Detail fabrication including anchorages and attachments to structure and to supported equipment. Include adjustable motor bases, rails, and frames for equipment mounting.

2. Vibration Isolation Base Details: Detail fabrication including anchorages and attachments to structure and to supported equipment. Include adjustable motor bases, rails, and frames for equipment mounting.

C. Delegated-Design Submittal: For each vibration isolation device.

1. Include design calculations for selecting vibration isolators and for designing vibration isolation bases.

1.4 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: Show coordination of vibration isolation device installation for HVAC piping and equipment with other systems and equipment in the vicinity, including other supports and restraints, if any.

B. Qualification Data: For testing agency.

C. Welding certificates.

Page 16: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

VIBRATION CONTROLS FOR HVAC230548.13 - 2

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For open spring mounts and housed spring mounts to include in operation and maintenance manuals.

1.6 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."

PART 2 - PRODUCTS

2.1 OPEN-SPRING ISOLATORS

A. Freestanding, Laterally Stable, Open-Spring Isolators:.

1. Approved manufacturers:a. Isotechb. Vibrasystemsc. Approved equivalent

2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load.

3. Minimum Additional Travel: 50 percent of the required deflection at rated load.4. Lateral Stiffness: More than 80 percent of rated vertical stiffness.5. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or

failure.6. Baseplates: Factory-drilled steel plate for bolting to structure with an elastomeric isolator pad

attached to the underside. Baseplates shall limit floor load to 500 psig.7. Top Plate and Adjustment Bolt: Threaded top plate with adjustment bolt and cap screw to fasten

and level equipment.

2.2 HOUSED-SPRING ISOLATORS

A. Freestanding, Laterally Stable, Open-Spring Isolators in Two-Part Telescoping Housing: 1. Approved manufacturers:

a. Isotech, Inc.b. Vibrasystemsc. Approved equivalent

2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load.

3. Minimum Additional Travel: 50 percent of the required deflection at rated load.4. Lateral Stiffness: More than 80 percent of rated vertical stiffness.5. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or

failure.6. Two-Part Telescoping Housing: A steel top and bottom frame separated by an elastomeric material

and enclosing the spring isolators.

a. Drilled base housing for bolting to structure with an elastomeric isolator pad attached to the underside. Bases shall limit floor load to 500 psig.

b. Top housing with attachment and leveling bolt

Page 17: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

VIBRATION CONTROLS FOR HVAC230548.13 - 3

2.3 RESTRAINED-SPRING ISOLATORS

A. Freestanding, Laterally Stable, Open-Spring Isolators with Vertical-Limit Stop Restraint: 1. Approved manufacturers:

a. Isotech, Inc.b. Vibrasystemsc. Approved equivalent

2. Housing: Steel housing with vertical-limit stops to prevent spring extension due to weight being removed.

a. Base with holes for bolting to structure with an elastomeric isolator pad attached to the underside. Bases shall limit floor load to 500 psig.

b. Top plate with threaded mounting holes.c. Internal leveling bolt that acts as blocking during installation.

3. Restraint: Limit stop as required for equipment and authorities having jurisdiction.4. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated

load.5. Minimum Additional Travel: 50 percent of the required deflection at rated load.6. Lateral Stiffness: More than 80 percent of rated vertical stiffness.7. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or

failure.

2.4 HOUSED-RESTRAINED-SPRING ISOLATORS

A. Freestanding, Steel, Open-Spring Isolators with Vertical-Limit Stop Restraint in Two-Part Telescoping Housing: 1. Approved manufacturers:

a. Isotech, Inc.b. Vibrasystemsc. Approved equivalent

2.3. Two-Part Telescoping Housing: A steel top and bottom frame separated by an elastomeric material

and enclosing the spring isolators. Housings are equipped with adjustable snubbers to limit vertical movement.

a. Drilled base housing for bolting to structure with an elastomeric isolator pad attached to the underside. Bases shall limit floor load to 500 psig.

b. Threaded top housing with adjustment bolt and cap screw to fasten and level equipment.

4. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load.

5. Minimum Additional Travel: 50 percent of the required deflection at rated load.6. Lateral Stiffness: More than 80 percent of rated vertical stiffness.7. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or

failure.

2.5 RESTRAINED ISOLATION ROOF-CURB RAILS

A. Roof curb by equipment manufacturer or matched to new equipment.

B. Description: Factory-assembled, fully enclosed, insulated, air- and watertight curb rail designed to resiliently support equipment.

C. Upper Frame: Upper frame shall provide continuous and captive support for equipment.

Page 18: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

VIBRATION CONTROLS FOR HVAC230548.13 - 4

D. Lower Support Assembly: The lower support assembly shall be formed sheet metal section containing adjustable and removable steel springs that support upper frame. The lower support assembly shall have a means for attaching to building structure and a wood nailer for attaching roof materials and shall be insulated with a minimum of 2 inches of rigid glass-fiber insulation on inside of assembly. Adjustable, restrained-spring isolators shall be mounted on elastomeric vibration isolation pads and shall have access ports, for level adjustment, with removable waterproof covers at all isolator locations. Isolators shall be located so they are accessible for adjustment at any time during the life of the installation without interfering with the integrity of the roof.

E. Snubber Bushings: All-directional, elastomeric snubber bushings at least 1/4 inch thick.

F. Water Seal: Galvanized sheet metal with EPDM seals at corners, attached to upper support frame, extending down past wood nailer of lower support assembly, and counterflashed over roof materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and equipment to receive vibration isolation control devices for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

B. Examine roughing-in of reinforcement and cast-in-place anchors to verify actual locations before installation.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 VIBRATION CONTROL DEVICE INSTALLATION

A. Coordinate the location of embedded connection hardware with supported equipment attachment and mounting points and with requirements for concrete reinforcement and formwork specified in Section 033000 "Cast-in-Place Concrete."

B. Installation of vibration isolators must not cause any change of position of equipment, piping, or ductwork resulting in stresses or misalignment.

3.3 VIBRATION ISOLATION EQUIPMENT BASES INSTALLATION

A. Coordinate the location of embedded connection hardware with supported equipment attachment and mounting points and with requirements for concrete reinforcement and formwork specified in Section 033000 "Cast-in-Place Concrete."

END OF SECTION 230548.13

Page 19: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 1

SECTION 230593TESTING, ADJUSTING, AND BALANCING FOR HVAC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:1. Testing, Adjusting, and Balancing Equipment:

a. Heat exchangers.b. Motors.c. Chillers.d. Cooling towers.e. Condensing units.f. Heat-transfer coils.

2. Testing, adjusting, and balancing replaced equipment.3. Duct leakage tests.4. Control system verification.

1.3 DEFINITIONS

A. AABC: Associated Air Balance Council.

B. BAS: Building automation systems.

C. NEBB: National Environmental Balancing Bureau.

D. TAB: Testing, adjusting, and balancing.

E. TABB: Testing, Adjusting, and Balancing Bureau.

F. TAB Specialist: An independent entity meeting qualifications to perform TAB work.

G. TDH: Total dynamic head.

1.4 PREINSTALLATION MEETINGS

A. TAB Conference: If requested by the Owner, conduct a TAB conference at project site after approval of the TAB strategies and procedures plan to develop a mutual understanding of the details. Provide a minimum of 14 days' advance notice of scheduled meeting time and location.

1. Minimum Agenda Items:

a. The Contract Documents examination report.b. The TAB plan.

Page 20: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 2

c. Needs for coordination and cooperation of trades and subcontractors.d. Proposed procedures for documentation and communication flow.

1.5 ACTION SUBMITTALS

1. TAB Report: Documentation indicating that Work complies with ASHRAE/IES 90.1, Section 6.7.2.3 - "System Balancing."

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: Within 30 days of Contractor's Notice to Proceed, submit documentation that the TAB specialist and this Project's TAB team members meet the qualifications specified in "Quality Assurance" Article.

B. Contract Documents Examination Report: Within 30 days of Contractor's Notice to Proceed, submit the Contract Documents review report as specified in Part 3.

C. Strategies and Procedures Plan: Within 30 days of Contractor's Notice to Proceed, submit TAB strategies and step-by-step procedures as specified in "Preparation" Article.

D. System Readiness Checklists: Within 30 days of Contractor's Notice to Proceed, submit system readiness checklists as specified in "Preparation" Article.

E. Examination Report: Submit a summary report of the examination review required in "Examination" Article.

F. Certified TAB reports.

G. Sample report forms.

H. Instrument calibration reports, to include the following:

1. Instrument type and make.2. Serial number.3. Application.4. Dates of use.5. Dates of calibration.

1.7 QUALITY ASSURANCE

A. TAB Specialists Qualifications: Certified by AABC.

1. TAB Field Supervisor: Employee of the TAB specialist and certified by AABC.2. TAB Technician: Employee of the TAB specialist and certified by AABC as a TAB technician.

B. TAB Specialists Qualifications: Certified by NEBB or TABB.

1. TAB Field Supervisor: Employee of the TAB specialist and certified by NEBB or TABB.2. TAB Technician: Employee of the TAB specialist and certified by NEBB or TABB as a TAB

technician.

C. Instrumentation Type, Quantity, Accuracy, and Calibration: Comply with requirements in ASHRAE 111, Section 4, "Instrumentation."

D. ASHRAE/IES 90.1 Compliance: Applicable requirements in ASHRAE/IES 90.1, Section 6.7.2.3 - "System Balancing."

Page 21: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 3

1.8 FIELD CONDITIONS

A. Full Owner Occupancy: Owner will occupy the site and existing building during entire TAB period. Cooperate with Owner during TAB operations to minimize conflicts with Owner's operations.

B. Partial Owner Occupancy: Owner may occupy completed areas of building before Substantial Completion. Cooperate with Owner during TAB operations to minimize conflicts with Owner's operations.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine the Contract Documents to become familiar with Project requirements and to discover conditions in systems designs that may preclude proper TAB of systems and equipment.

B. Examine installed systems for balancing devices, such as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, and manual volume dampers. Verify that locations of these balancing devices are applicable for intended purpose and are accessible.

C. Examine the approved submittals for HVAC systems and equipment.

D. Examine design data including HVAC system descriptions, statements of design assumptions for environmental conditions and systems output, and statements of philosophies and assumptions about HVAC system and equipment controls.

E. Examine equipment performance data including fan and pump curves.

1. Relate performance data to Project conditions and requirements, including system effects that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system.

2. Calculate system-effect factors to reduce performance ratings of HVAC equipment when installed under conditions different from the conditions used to rate equipment performance. To calculate system effects for air systems, use tables and charts found in AMCA 201, "Fans and Systems," or in SMACNA's "HVAC Systems - Duct Design." Compare results with the design data and installed conditions.

F. Examine system and equipment installations and verify that field quality-control testing, cleaning, and adjusting specified in individual Sections have been performed.

G. Examine test reports specified in individual system and equipment Sections.

H. Examine HVAC equipment and verify that bearings are greased, belts are aligned and tight, filters are clean, and equipment with functioning controls is ready for operation.

I. Examine strainers. Verify that startup screens have been replaced by permanent screens with indicated perforations.

J. Examine control valves for proper installation for their intended function of throttling, diverting, or mixing fluid flows.

K. Examine heat-transfer coils for correct piping connections and for clean and straight fins.

L. Examine system pumps to ensure absence of entrained air in the suction piping.

M. Examine operating safety interlocks and controls on HVAC equipment.

Page 22: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 4

N. Report deficiencies discovered before and during performance of TAB procedures. Observe and record system reactions to changes in conditions. Record default set points if different from indicated values.

3.2 PREPARATION

A. Prepare a TAB plan that includes the following:

1. Equipment and systems to be tested.2. Strategies and step-by-step procedures for balancing the systems.3. Instrumentation to be used.4. Sample forms with specific identification for all equipment.

B. Perform system-readiness checks of HVAC systems and equipment to verify system readiness for TAB work. Include, at a minimum, the following:

1. Airside:

a. Verify that leakage and pressure tests on air distribution systems have been satisfactorily completed.

b. Volume, smoke, and fire dampers are open and functional.c. Clean filters are installed.d. Fans are operating, free of vibration, and rotating in correct direction.e. Variable-frequency controllers' startup is complete and safeties are verified.f. Automatic temperature-control systems are operational.g. Suitable access to balancing devices and equipment is provided.

2. Hydronics:

a. Verify leakage and pressure tests on water distribution systems have been satisfactorily completed.

b. Water treatment is complete.c. Systems are flushed, filled, and air purged.d. Strainers are pulled and cleaned.e. Control valves are functioning per the sequence of operation.f. Shutoff and balance valves have been verified to be 100 percent open.g. Pumps are started and proper rotation is verified.h. Pump gage connections are installed directly at pump inlet and outlet flanges or in

discharge and suction pipe prior to valves or strainers.i. Variable-frequency controllers' startup is complete and safeties are verified.j. Suitable access to balancing devices and equipment is provided.

3.3 GENERAL PROCEDURES FOR TESTING AND BALANCING

A. Perform testing and balancing procedures on each system according to the procedures contained in AABC's "National Standards for Total System Balance", ASHRAE 111, NEBB's "Procedural Standards for Testing, Adjusting, and Balancing of Environmental Systems", and/or SMACNA's "HVAC Systems - Testing, Adjusting, and Balancing", and in this Section.

B. Cut insulation, ducts, pipes, and equipment cabinets for installation of test probes to the minimum extent necessary for TAB procedures.

1. After testing and balancing, patch probe holes in ducts with same material and thickness as used to construct ducts.

2. After testing and balancing, install test ports and duct access doors that comply with requirements in Section 233300 "Air Duct Accessories."

3. Install and join new insulation that matches removed materials. Restore insulation, coverings, vapor barrier, and finish according to Section 230713 "Duct Insulation," Section 230716 "HVAC Equipment Insulation," and Section 230719 "HVAC Piping Insulation."

Page 23: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 5

C. Mark equipment and balancing devices, including damper-control positions, valve position indicators, fan-speed-control levers, and similar controls and devices, with paint or other suitable, permanent identification material to show final settings.

D. Take and report testing and balancing measurements in inch-pound (IP) units.

3.4 GENERAL PROCEDURES FOR BALANCING AIR SYSTEMS

A. Prepare test reports for both fans and unit outlets. Cross-check the summation of required outlet volumes with required fan volumes. Summation to be taken from existing record drawings.

B. For variable-air-volume systems, develop a plan to simulate diversity.

C. Determine the best locations in main duct for accurate duct-airflow measurements.

D. Check airflow patterns from the outdoor-air louvers and dampers and the return- and exhaust-air dampers through the supply-fan discharge and mixing dampers.

E. Locate start-stop and disconnect switches, electrical interlocks, and motor starters.

F. Verify that motor starters are equipped with properly sized thermal protection.

G. Check dampers for proper position to achieve desired airflow path.

H. Check for airflow blockages.

I. Check condensate drains for proper connections and functioning.

J. Check for proper sealing of air-handling-unit components.

K. Verify that air duct system is sealed as specified in Section 233113 "Metal Ducts."

3.5 PROCEDURES FOR CONSTANT-VOLUME AIR SYSTEMS

A. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by fan manufacturer.

1. Measure total airflow.

a. Set outside-air, return-air, and relief-air dampers for proper position that simulates minimum outdoor-air conditions.

b. Where duct conditions allow, measure airflow by main Pitot-tube traverse. If necessary, perform multiple Pitot-tube traverses, close to the fan and prior to any outlets, to obtain total airflow.

c. Where duct conditions are not suitable for Pitot-tube traverse measurements, a coil traverse may be acceptable.

d. Maximum total air to be calculated from existing record drawings.

2. Measure fan static pressures as follows:

a. Measure static pressure directly at the fan outlet or through the flexible connection.b. Measure static pressure directly at the fan inlet or through the flexible connection.c. Measure static pressure across each component that makes up the air-handling system.d. Report artificial loading of filters at the time static pressures are measured.

Page 24: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 6

3. Review Record Documents to determine variations in design static pressures versus actual static pressures. Calculate actual system-effect factors. Recommend adjustments to accommodate actual conditions.

4. Obtain approval from Owner for adjustment of fan speed higher or lower than indicated speed. Comply with requirements in HVAC Sections for air-handling units for adjustment of fans, belts, and pulley sizes to achieve indicated air-handling-unit performance.

5. Do not make fan-speed adjustments that result in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure that no overload occurs. Measure amperage in full-cooling, full-heating, economizer, and any other operating mode to determine the maximum required brake horsepower.

B. Adjust volume dampers for main duct to indicated airflows.

C. Verify final system conditions.

1. Re-measure and confirm that minimum outdoor, return, and relief airflows are within design. Readjust to design if necessary.

2. Re-measure and confirm that total airflow is within design.3. Re-measure all final fan operating data, rpms, volts, amps, and static profile.4. Mark all final settings.5. Test system in economizer mode. Verify proper operation and adjust if necessary.6. Measure and record all operating data.7. Record final fan-performance data.

3.6 PROCEDURES FOR VARIABLE-AIR-VOLUME SYSTEMS

A. Adjust the variable-air-volume systems as follows:

1. Verify that the system static pressure sensor is located two-thirds of the distance down the duct from the fan discharge.

2. Test and adjust system for total airflow. Adjust fans to deliver total design airflows within the maximum allowable fan speed listed by fan manufacturer.

a. Set outside-air, return-air, and relief-air dampers for proper position that simulates minimum outdoor-air conditions.

b. Where duct conditions allow, measure airflow by Pitot-tube traverse. If necessary, perform multiple Pitot-tube traverses to obtain total airflow.

c. Where duct conditions are not suitable for Pitot-tube traverse measurements, a coil traverse may be acceptable.

d. If a reliable Pitot-tube traverse or coil traverse is not possible, measure airflow at terminals and calculate the total airflow.

3. Measure fan static pressures as follows:

a. Measure static pressure directly at the fan outlet or through the flexible connection.b. Measure static pressure directly at the fan inlet or through the flexible connection.c. Measure static pressure across each component that makes up the air-handling system.d. Report any artificial loading of filters at the time static pressures are measured.

4. Set final return and outside airflow to the fan while operating at maximum return airflow and minimum outdoor airflow.

a. Balance the return-air ducts and inlets the same as described for constant-volume air systems.

5. Verify final system conditions as follows:

a. Re-measure and confirm that minimum outdoor, return, and relief airflows are within design. Readjust to match design if necessary.

Page 25: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 7

b. Re-measure and confirm that total airflow is within design.c. Re-measure final fan operating data, rpms, volts, amps, and static profile.d. Mark final settings.e. Test system in economizer mode. Verify proper operation and adjust if necessary. Measure

and record all operating data.f. Verify tracking between supply and return fans.

3.7 PROCEDURES FOR MULTIZONE SYSTEMS

A. Position the unit's automatic zone dampers for maximum flow through the cooling coil.

B. The procedures for multizone systems will utilize the zone balancing dampers to achieve the indicated airflow within the zone.

C. After balancing, place the unit's automatic zone dampers for maximum heating flow. Retest zone airflows and record any variances.

D. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by fan manufacturer.

1. Measure total airflow.

a. Set outside-air, return-air and relief-air dampers for proper position that simulates minimum outdoor air conditions.

b. Where duct conditions allow, measure airflow by Pitot-tube traverse. If necessary, perform multiple Pitot-tube traverses to obtain total airflow.

c. Where duct conditions are not suitable for Pitot-tube traverse measurements, a coil traverse may be acceptable.

d. If a reliable Pitot-tube traverse or coil traverse is not possible, measure airflow at terminals and calculate the total airflow.

2. Measure fan static pressures as follows:

a. Measure static pressure directly at the fan outlet or through the flexible connection.b. Measure static pressure directly at the fan inlet or through the flexible connection.c. Measure static pressure across each component that makes up the air-handling system.d. Report artificial loading of filters at the time static pressures are measured.

3. Review Record Documents to determine variations in design static pressures versus actual static pressures. Calculate actual system-effect factors. Recommend adjustments to accommodate actual conditions.

4. Obtain approval from Owner for adjustment of fan speed higher or lower than indicated speed. Comply with requirements in HVAC Sections for air-handling units for adjustment of fans, belts, and pulley sizes to achieve indicated air-handling-unit performance.

5. Do not make fan-speed adjustments that result in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure that no overload occurs. Measure amperage in full-cooling, full-heating, economizer, and any other operating mode to determine the maximum required brake horsepower.

E. Adjust volume dampers for main duct to indicated airflows.

F. Verify final system conditions.

1. Re-measure and confirm that minimum outdoor, return, and relief airflows are within design. Readjust to match design if necessary.

2. Re-measure and confirm that total airflow is within design.3. Re-measure all final fan operating data, rpms, volts, amps, and static profile.4. Mark all final settings.5. Test system in economizer mode. Verify proper operation and adjust if necessary.

Page 26: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 8

6. Measure and record all operating data.7. Record final fan-performance data.

3.8 GENERAL PROCEDURES FOR HYDRONIC SYSTEMS

A. Prepare test reports for pumps. Obtain approved submittals and manufacturer-recommended testing procedures. Crosscheck the summation of required coil and heat exchanger flow rates with pump design flow rate.

B. Prepare schematic diagrams of systems' "as-built" piping layouts.

C. In addition to requirements in "Preparation" Article, prepare hydronic systems for testing and balancing as follows:

1. Check liquid level in expansion tank.2. Check highest vent for adequate pressure.3. Check flow-control valves for proper position.4. Locate start-stop and disconnect switches, electrical interlocks, and motor starters.5. Verify that motor starters are equipped with properly sized thermal protection.6. Check that air has been purged from the system.

3.9 PROCEDURES FOR CONSTANT-FLOW HYDRONIC SYSTEMS

A. Adjust pumps to deliver total design gpm.

1. Measure total water flow.

a. Position valves for full flow through equipment.b. Measure flow by main flow meter, if installed.c. If main flow meter is not installed, determine flow by pump TDH or exchanger pressure

drop.

2. Measure pump TDH as follows:

a. Measure discharge pressure directly at the pump outlet flange or in discharge pipe prior to any valves.

b. Measure inlet pressure directly at the pump inlet flange or in suction pipe prior to any valves or strainers.

c. Convert pressure to head and correct for differences in gage heights.d. Verify pump impeller size by measuring the TDH with the discharge valve closed. Note the

point on manufacturer's pump curve at zero flow, and verify that the pump has the intended impeller size.

e. With valves open, read pump TDH. Adjust pump discharge valve until design water flow is achieved.

3. Monitor motor performance during procedures and do not operate motor in an overloaded condition.

B. Adjust flow-measuring devices installed in mains to design water flows.

1. Measure flow in main pipes.2. Adjust main balance valves for design flow.3. Re-measure each main after all have been adjusted.4. Adjust each terminal to design flow.5. Perform temperature tests after flows have been balanced.

C. Verify final system conditions as follows:

Page 27: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 9

1. Re-measure and confirm that total water flow is within design.2. Re-measure final pumps' operating data, TDH, volts, amps, and static profile.3. Mark final settings.

D. Verify that memory stops have been set.

3.10 PROCEDURES FOR VARIABLE-FLOW HYDRONIC SYSTEMS

A. Balance systems with automatic two- and three-way control valves by setting systems at maximum flow through equipment, and proceed as specified above for hydronic systems.

B. Adjust the variable-flow hydronic system as follows:

1. Verify that the differential-pressure sensor is located as indicated.2. Determine whether there is diversity in the system.

C. For systems with no diversity:

1. Adjust pumps to deliver total design gpm.

a. Measure total water flow.

1) Position valves for full flow through coils.2) Measure flow by main flow meter, if installed.3) If main flow meter is not installed, determine flow by pump TDH or exchanger

pressure drop.

b. Measure pump TDH as follows:

1) Measure discharge pressure directly at the pump outlet flange or in discharge pipe prior to any valves.

2) Measure inlet pressure directly at the pump inlet flange or in suction pipe prior to any valves or strainers.

3) Convert pressure to head and correct for differences in gage heights.4) Verify pump impeller size by measuring the TDH with the discharge valve closed.

Note the point on manufacturer's pump curve at zero flow and verify that the pump has the intended impeller size.

5) With valves open, read pump TDH. Adjust pump discharge valve until design water flow is achieved.

c. Monitor motor performance during procedures and do not operate motor in an overloaded condition.

2. Adjust flow-measuring devices installed in mains to design water flows.

a. Measure flow in main and branch pipes.b. Adjust main and branch balance valves for design flow.

D. For systems with diversity:

1. Determine diversity factor.2. Simulate system diversity by closing required number of control valves, as approved by the design

engineer.3. Adjust pumps to deliver total design gpm.

a. Measure total water flow.

1) Position valves for full flow through coils.

Page 28: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 10

2) Measure flow by main flow meter, if installed.3) If main flow meter is not installed, determine flow by pump TDH or exchanger

pressure drop.

b. Measure pump TDH as follows:

1) Measure discharge pressure directly at the pump outlet flange or in discharge pipe prior to any valves.

2) Measure inlet pressure directly at the pump inlet flange or in suction pipe prior to any valves or strainers.

3) Convert pressure to head and correct for differences in gage heights.4) Verify pump impeller size by measuring the TDH with the discharge valve closed.

Note the point on manufacturer's pump curve at zero flow and verify that the pump has the intended impeller size.

5) With valves open, read pump TDH. Adjust pump discharge valve until design water flow is achieved.

c. Monitor motor performance during procedures and do not operate motor in an overloaded condition.

4. Adjust flow-measuring devices installed at terminals for each space to design water flows.

5. Open control valves that were shut. Close a sufficient number of control valves that were previously open to maintain diversity, and balance terminals that were just opened.

6. Prior to verifying final system conditions, determine system differential-pressure set point.7. If the pump discharge valve was used to set total system flow with variable-frequency controller at

60 Hz, at completion open discharge valve 100 percent and allow variable-frequency controller to control system differential-pressure set point. Record pump data under both conditions.

8. Mark final settings and verify that memory stops have been set.9. Verify final system conditions as follows:

a. Re-measure and confirm that total water flow is within design.b. Re-measure final pumps' operating data, TDH, volts, amps, and static profile.c. Mark final settings.

10. Verify that memory stops have been set.

3.11 PROCEDURES FOR MOTORS

A. Motors 1/2 HP and Larger: Test at final balanced conditions and record the following data:

1. Manufacturer's name, model number, and serial number.2. Motor horsepower rating.3. Motor rpm.4. Phase and hertz.5. Nameplate and measured voltage, each phase.6. Nameplate and measured amperage, each phase.7. Starter size and thermal-protection-element rating.8. Service factor and frame size.

B. Motors Driven by Variable-Frequency Controllers: Test manual bypass of controller to prove proper operation.

3.12 PROCEDURES FOR CHILLERS

A. Balance water flow through each evaporator and condenser to within specified tolerances of indicated flow with all pumps operating. With only one chiller operating in a multiple chiller installation, do not exceed the

Page 29: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 11

flow for the maximum tube velocity recommended by the chiller manufacturer. Measure and record the following data with each chiller operating at design conditions:

1. Evaporator-water entering and leaving temperatures, pressure drop, and water flow.2. For water-cooled chillers, condenser-water entering and leaving temperatures, pressure drop, and

water flow.3. Evaporator and condenser refrigerant temperatures and pressures, using instruments furnished by

chiller manufacturer.4. Power factor if factory-installed instrumentation is furnished for measuring kilowatts.5. Kilowatt input if factory-installed instrumentation is furnished for measuring kilowatts.6. Capacity: Calculate in tons of cooling.7. For air-cooled chillers, verify condenser-fan rotation and record fan and motor data including

number of fans and entering- and leaving-air temperatures.

3.13 PROCEDURES FOR COOLING TOWERS

A. Balance total condenser-water flows to towers. Measure and record the following data:

1. Condenser-water flow to each cell of the cooling tower.2. Entering- and leaving-water temperatures.3. Wet- and dry-bulb temperatures of entering air.4. Wet- and dry-bulb temperatures of leaving air.5. Condenser-water flow rate recirculating through the cooling tower.6. Cooling-tower spray pump discharge pressure.7. Condenser-water flow through bypass.8. Fan and motor operating data.

3.14 DUCT LEAKAGE TESTS

A. Witness the duct pressure testing performed by Installer.

B. Verify that proper test methods are used and that leakage rates are within specified tolerances.

C. Report deficiencies observed.

3.15 CONTROLS VERIFICATION

A. In conjunction with system balancing, perform the following:

1. Verify temperature control system is operating within the design limitations.2. Confirm that the sequences of operation are in compliance with Contract Documents.3. Verify that controllers are calibrated and function as intended.4. Verify that controller set points are as indicated.5. Verify the operation of lockout or interlock systems.6. Verify the operation of valve and damper actuators.7. Verify that controlled devices are properly installed and connected to correct controller.8. Verify that controlled devices travel freely and are in position indicated by controller: open, closed,

or modulating.9. Verify location and installation of sensors to ensure that they sense only intended temperature,

humidity, or pressure.

B. Reporting: Include a summary of verifications performed, remaining deficiencies, and variations from indicated conditions.

Page 30: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 12

3.16 PROCEDURES FOR TESTING, ADJUSTING, AND BALANCING EXISTING SYSTEMS

A. Note: Balancing of existing systems is at the option of the Owner and will be accomplished by separate contract.

B. Perform a preconstruction inspection of existing equipment that is to remain and be reused.

1. Measure and record the operating speed, airflow, and static pressure of each fan.2. Measure motor voltage and amperage. Compare the values to motor nameplate information.3. Check the refrigerant charge.4. Check the condition of filters.5. Check the condition of coils.6. Check the operation of the drain pan and condensate-drain trap.7. Check bearings and other lubricated parts for proper lubrication.8. Report on the operating condition of the equipment and the results of the measurements taken.

Report deficiencies.

C. Before performing testing and balancing of existing systems, inspect existing equipment that is to remain and be reused to verify that existing equipment has been cleaned and refurbished. Verify the following:

1. New filters are installed.2. Coils are clean and fins combed.3. Drain pans are clean.4. Fans are clean.5. Bearings and other parts are properly lubricated.6. Deficiencies noted in the preconstruction report are corrected.

D. Perform testing and balancing of existing systems to the extent that existing systems are affected by the renovation work.

1. Compare the indicated airflow of the renovated work to the measured fan airflows, and determine the new fan speed and the face velocity of filters and coils.

2. Verify that the indicated airflows of the renovated work result in filter and coil face velocities and fan speeds that are within the acceptable limits defined by equipment manufacturer.

3. If calculations increase or decrease the airflow rates and water flow rates by more than 5 percent, make equipment adjustments to achieve the calculated rates. If increase or decrease is 5 percent or less, equipment adjustments are not required.

4. Balance each air outlet.

3.17 TOLERANCES

A. Set HVAC system's airflow rates and water flow rates within the following tolerances:

1. Supply, Return, and Exhaust Fans and Equipment with Fans: Plus or minus 10 percent.2. Chiller Water Flow Rate: Plus or minus 10 percent.

B. Maintaining pressure relationships as designed shall have priority over the tolerances specified above.

3.18 PROGRESS REPORTING

A. Initial Construction-Phase Report: Based on examination of the Contract Documents as specified in "Examination" Article, prepare a report on the adequacy of design for systems balancing devices. Recommend changes and additions to systems balancing devices to facilitate proper performance measuring and balancing. Recommend changes and additions to HVAC systems and general construction to allow access for performance measuring and balancing devices.

B. Status Reports: Prepare weekly progress reports to describe completed procedures, procedures in progress, and scheduled procedures. Include a list of deficiencies and problems found in systems being

Page 31: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 13

tested and balanced. Prepare a separate report for each system and each building floor for systems serving multiple floors.

3.19 FINAL REPORT

A. General: Prepare a certified written report; tabulate and divide the report into separate sections for tested systems and balanced systems.

1. Include a certification sheet at the front of the report's binder, signed and sealed by the certified testing and balancing engineer.

2. Include a list of instruments used for procedures, along with proof of calibration.3. Certify validity and accuracy of field data.

B. Final Report Contents: In addition to certified field-report data, include the following:

1. Pump curves.2. Fan curves.3. Manufacturers' test data.4. Field test reports prepared by system and equipment installers.5. Other information relative to equipment performance; do not include Shop Drawings and Product

Data.

C. General Report Data: In addition to form titles and entries, include the following data:

1. Title page.2. Name and address of the TAB specialist.3. Project name.4. Project location.5. Architect's name and address.6. Engineer's name and address.7. Contractor's name and address.8. Report date.9. Signature of TAB supervisor who certifies the report.10. Table of Contents with the total number of pages defined for each section of the report. Number

each page in the report.11. Summary of contents including the following:

a. Indicated versus final performance.b. Notable characteristics of systems.c. Description of system operation sequence if it varies from the Contract Documents.

12. Nomenclature sheets for each item of equipment.13. Data for terminal units, including manufacturer's name, type, size, and fittings.14. Notes to explain why certain final data in the body of reports vary from indicated values.15. Test conditions for fans and pump performance forms including the following:

a. Settings for outdoor-, return-, and exhaust-air dampers.b. Conditions of filters.c. Cooling coil, wet- and dry-bulb conditions.d. Face and bypass damper settings at coils.e. Fan drive settings including settings and percentage of maximum pitch diameter.f. Inlet vane settings for variable-air-volume systems.g. Settings for supply-air, static-pressure controller.h. Other system operating conditions that affect performance.

D. System Diagrams: Include schematic layouts of air and hydronic distribution systems. Present each system with single-line diagram and include the following:

1. Quantities of outdoor, supply, return, and exhaust airflows.

Page 32: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 14

2. Chilled water flow rates.3. Equipment duct, outlet, and inlet sizes.4. Chilled water and condenser water pipe and valve sizes and locations.5. Position of balancing devices.

E. Air-Handling-Unit Test Reports: For air-handling units with coils, include the following:

1. Unit Data:

a. Unit identification.b. Location.c. Make and type.d. Model number and unit size.e. Manufacturer's serial number.f. Unit arrangement and class.g. Discharge arrangement.h. Sheave make, size in inches, and bore.i. Center-to-center dimensions of sheave and amount of adjustments in inches.j. Number, make, and size of belts.k. Number, type, and size of filters.

2. Motor Data:

a. Motor make, and frame type and size.b. Horsepower and rpm.c. Volts, phase, and hertz.d. Full-load amperage and service factor.e. Sheave make, size in inches, and bore.f. Center-to-center dimensions of sheave and amount of adjustments in inches.

3. Test Data (Indicated and Actual Values):

a. Total airflow rate in cfm.b. Total system static pressure in inches wg.c. Fan rpm.d. Discharge static pressure in inches wg.e. Filter static-pressure differential in inches wg.f. Preheat-coil static-pressure differential in inches wg.g. Cooling-coil static-pressure differential in inches wg.h. Heating-coil static-pressure differential in inches wg.i. Outdoor airflow in cfm.j. Return airflow in cfm.k. Outdoor-air damper position.l. Return-air damper position.

F. Apparatus-Coil Test Reports:

1. Coil Data:

a. System identification.b. Location.c. Coil type.d. Number of rows.e. Fin spacing in fins per inch o.c.f. Make and model number.g. Face area in sq. ft.h. Tube size in NPS.i. Tube and fin materials.j. Circuiting arrangement.

Page 33: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 15

2. Test Data (Indicated and Actual Values):

a. Airflow rate in cfm.b. Average face velocity in fpm.c. Air pressure drop in inches wg.d. Outdoor-air, wet- and dry-bulb temperatures in deg F.e. Return-air, wet- and dry-bulb temperatures in deg F.f. Entering-air, wet- and dry-bulb temperatures in deg F.g. Leaving-air, wet- and dry-bulb temperatures in deg F.h. Refrigerant expansion valve and refrigerant types.i. Refrigerant suction pressure in psig.j. Refrigerant suction temperature in deg F.

G. Gas-Fired Heat Apparatus Test Reports: In addition to manufacturer's factory startup equipment reports, include the following:

1. Unit Data:

a. System identification.b. Location.c. Make and type.d. Model number and unit size.e. Manufacturer's serial number.f. Fuel type in input data.g. Output capacity in Btu/h.h. Ignition type.i. Burner-control types.j. Motor horsepower and rpm.k. Motor volts, phase, and hertz.l. Motor full-load amperage and service factor.m. Sheave make, size in inches, and bore.n. Center-to-center dimensions of sheave and amount of adjustments in inches.

2. Test Data (Indicated and Actual Values):

a. Total airflow rate in cfm.b. Entering-air temperature in deg F.c. Leaving-air temperature in deg F.d. Air temperature differential in deg F.e. Entering-air static pressure in inches wg.f. Leaving-air static pressure in inches wg.g. Air static-pressure differential in inches wg.h. Low-fire fuel input in Btu/h.i. High-fire fuel input in Btu/h.j. Manifold pressure in psig.k. High-temperature-limit setting in deg F.l. Operating set point in Btu/h.m. Motor voltage at each connection.n. Motor amperage for each phase.o. Heating value of fuel in Btu/h.

H. Round and Rectangular Duct Traverse Reports: Include a diagram with a grid representing the duct cross-section and record the following:

1. Report Data:

a. System and air-handling-unit number.b. Location and zone.c. Traverse air temperature in deg F.d. Duct static pressure in inches wg.e. Duct size in inches.

Page 34: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 16

f. Duct area in sq. ft.g. Indicated airflow rate in cfm.h. Indicated velocity in fpm.i. Actual airflow rate in cfm.j. Actual average velocity in fpm.k. Barometric pressure in psig.

I. System-Coil Reports: For reheat coils of terminal units, include the following:

1. Unit Data:

a. System and air-handling-unit identification.b. Location and zone.c. Room or riser served.d. Coil make and size.e. Flowmeter type.

2. Test Data (Indicated and Actual Values):

a. Airflow rate in cfm.b. Entering-air temperature in deg F.c. Leaving-air temperature in deg F.

J. Pump Test Reports: Calculate impeller size by plotting the shutoff head on pump curves and include the following:

1. Unit Data:

a. Unit identification.b. Location.c. Service.d. Make and size.e. Model number and serial number.f. Water flow rate in gpm.g. Water pressure differential in feet of head or psig.h. Required net positive suction head in feet of head or psig.i. Pump rpm.j. Impeller diameter in inches.k. Motor make and frame size.l. Motor horsepower and rpm.m. Voltage at each connection.n. Amperage for each phase.o. Full-load amperage and service factor.p. Seal type.

2. Test Data (Indicated and Actual Values):

a. Static head in feet of head or psig.b. Pump shutoff pressure in feet of head or psig.c. Actual impeller size in inches.d. Full-open flow rate in gpm.e. Full-open pressure in feet of head or psig.f. Final discharge pressure in feet of head or psig.g. Final suction pressure in feet of head or psig.h. Final total pressure in feet of head or psig.i. Final water flow rate in gpm.j. Voltage at each connection.k. Amperage for each phase.

K. Instrument Calibration Reports:

Page 35: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

TESTING, ADJUSTING, AND BALANCING FOR HVAC230593 - 17

1. Report Data:

a. Instrument type and make.b. Serial number.c. Application.d. Dates of use.e. Dates of calibration.

3.20 VERIFICATION OF TAB REPORT

A. The TAB specialist's test and balance engineer shall conduct the inspection in the presence of Owner.

B. Owner shall randomly select measurements, documented in the final report, to be rechecked. Rechecking shall be limited to either 10 percent of the total measurements recorded or the extent of measurements that can be accomplished in a normal 8-hour business day.

C. If rechecks yield measurements that differ from the measurements documented in the final report by more than the tolerances allowed, the measurements shall be noted as "FAILED."

D. If the number of "FAILED" measurements is greater than 10 percent of the total measurements checked during the final inspection, the testing and balancing shall be considered incomplete and shall be rejected.

E. If TAB work fails, proceed as follows:

1. TAB specialists shall recheck all measurements and make adjustments. Revise the final report and balancing device settings to include all changes; resubmit the final report and request a second final inspection.

2. If the second final inspection also fails, Owner may contract the services of another TAB specialist to complete TAB work according to the Contract Documents and deduct the cost of the services from the original TAB specialist's final payment.

3. If the second verification also fails, Owner may contact AABC Headquarters regarding the AABC National Performance Guaranty.

F. Prepare test and inspection reports.

3.21 ADDITIONAL TESTS

A. Within 90 days of completing TAB, perform additional TAB to verify that balanced conditions are being maintained throughout and to correct unusual conditions.

B. Seasonal Periods: If initial TAB procedures were not performed during near-peak summer and winter conditions, perform additional TAB during near-peak summer and winter conditions.

END OF SECTION 230593

Page 36: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 1

SECTION 230923DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. The existing DDC system is to be replaced in its entirety during this project. The controls contractor is to be subcontracted under the mechanical contractor.

2. DDC system for monitoring and controlling of HVAC systems.3. Delivery of selected control devices to equipment and systems manufacturers for factory

installation and to HVAC systems installers for field installation.

B. Related Requirements:

1. Section 230923.13 "Energy Meters" for thermal and electric power energy meters that connect to DDC systems.

2. Section 230923.17 "Level Instruments" for liquid-level switches, sensors, and transmitters that connect to DDC systems.

3. Section 230923.22 "Position Instruments" for limit switches that connect to DDC systems.4. Section 230923.33 "Vibration Instruments" for vibration instruments that connect to DDC systems.5. Section 230923.43 "Weather Stations" for weather stations that connect to DDC systems.6. Section 230993.11 "Sequence of Operations for HVAC DDC" for control sequences in DDC

systems.7. Communications Cabling:

a. Section 260523 "Control-Voltage Electrical Power Cables" for balanced twisted pair communications cable.

b. Section 271513 "Communications Copper Horizontal Cabling" for balanced twisted pair communications cable.

c. Section 271523 "Communications Optical Fiber Horizontal Cabling" for optical fiber communications cable.

8. Raceways:

a. Section 260533 "Raceways and Boxes for Electrical Systems" for raceways for low-voltage control cable.

b. Section 270528 "Pathways for Communications Systems" for raceways for balanced twisted pair cabling and optical fiber cable.

9. Section 260553 "Identification for Electrical Systems" for identification requirements for electrical components.

10. Section 270553 "Identification for Communications Systems" for identification requirements for communications components.

Page 37: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 2

1.3 DEFINITIONS

A. Algorithm: A logical procedure for solving a recurrent mathematical problem. A prescribed set of well-defined rules or processes for solving a problem in a finite number of steps.

B. Analog: A continuously varying signal value, such as current, flow, pressure, or temperature.

C. BACnet Specific Definitions:

1. BACnet: Building Automation Control Network Protocol, ASHRAE 135. A communications protocol allowing devices to communicate data over and services over a network.

2. BACnet Interoperability Building Blocks (BIBBs): BIBB defines a small portion of BACnet functionality that is needed to perform a particular task. BIBBs are combined to build the BACnet functional requirements for a device.

3. BACnet/IP: Defines and allows using a reserved UDP socket to transmit BACnet messages over IP networks. A BACnet/IP network is a collection of one or more IP subnetworks that share the same BACnet network number.

4. BACnet Testing Laboratories (BTL): Organization responsible for testing products for compliance with ASHRAE 135, operated under direction of BACnet International.

5. PICS (Protocol Implementation Conformance Statement): Written document that identifies the particular options specified by BACnet that are implemented in a device.

D. Binary: Two-state signal where a high signal level represents ON" or "OPEN" condition and a low signal level represents "OFF" or "CLOSED" condition. "Digital" is sometimes used interchangeably with "Binary" to indicate a two-state signal.

E. Controller: Generic term for any standalone, microprocessor-based, digital controller residing on a network, used for local or global control. Three types of controllers are indicated: Network Controller, Programmable Application Controller, and Application-Specific Controller.

F. Control System Integrator: An entity that assists in expansion of existing enterprise system and support of additional operator interfaces to I/O being added to existing enterprise system.

G. COV: Changes of value.

H. DDC System Provider: Authorized representative of, and trained by, DDC system manufacturer and responsible for execution of DDC system Work indicated.

I. Distributed Control: Processing of system data is decentralized and control decisions are made at subsystem level. System operational programs and information are provided to remote subsystems and status is reported back. On loss of communication, subsystems shall be capable of operating in a standalone mode using the last best available data.

J. DOCSIS: Data-Over Cable Service Interface Specifications.

K. E/P: Voltage to pneumatic.

L. Gateway: Bidirectional protocol translator that connects control systems that use different communication protocols.

M. HLC: Heavy load conditions.

N. I/O: System through which information is received and transmitted. I/O refers to analog input (AI), binary input (BI), analog output (AO) and binary output (BO). Analog signals are continuous and represent control influences such as flow, level, moisture, pressure, and temperature. Binary signals convert electronic signals to digital pulses (values) and generally represent two-position operating and alarm status. "Digital," (DI and (DO), is sometimes used interchangeably with "Binary," (BI) and (BO), respectively.

O. I/P: Current to pneumatic.

Page 38: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 3

P. LAN: Local area network.

Q. LNS: LonWorks Network Services.

R. LON Specific Definitions:

1. FTT-10: Echelon Transmitter-Free Topology Transceiver.2. LonMark: Association comprising suppliers and installers of LonTalk products. Association provides

guidelines for implementing LonTalk protocol to ensure interoperability through a standard or consistent implementation.

3. LonTalk: An open standard protocol developed by the Echelon Corporation that uses a "Neuron Chip" for communication. LonTalk is a register trademark of Echelon.

4. LonWorks: Network technology developed by Echelon.5. Node: Device that communicates using CEA-709.1-C protocol and that is connected to a CEA-

709.1-C network.6. Node Address: The logical address of a node on the network, consisting of a Domain number,

Subnet number, and Node number. "Node number" portion of an address is a number assigned to device during installation, is unique within a subnet, and is not a factory-set unique Node ID.

7. Node ID: A unique 48-bit identifier assigned at factory to each CEA-709.1-C device. Sometimes called a "Neuron ID."

8. Program ID: An identifier (number) stored in a device (usually EEPROM) that identifies node manufacturer, functionality of device (application and sequence), transceiver used, and intended device usage.

9. Standard Configuration Property Type (SCPT): Pronounced "skip-it." A standard format type maintained by LonMark International for configuration properties.

10. Standard Network Variable Type (SNVT): Pronounced "snivet." A standard format type maintained by LonMark used to define data information transmitted and received by individual nodes. "SNVT" is used in two ways. It is an acronym for "Standard Network Variable Type" and is often used to indicate a network variable itself (i.e., it can mean "a network variable of a standard network variable type").

11. Subnet: Consists of a logical grouping of up to 127 nodes, where logical grouping is defined by node addressing. Each subnet is assigned a number, which is unique within a Domain. See "Node Address."

12. TP/FT-10: Free Topology Twisted Pair network defined by CEA-709.3 and is most common media type for a CEA-709.1-C control network.

13. TP/XF-1250: High-speed, 1.25-Mbps, twisted-pair, doubly terminated bus network defined by "LonMark Interoperability Guidelines" typically used only to connect multiple TP/FT-10 networks.

14. User-Defined Configuration Property Type (UCPT): Pronounced "U-Keep-It." A Configuration Property format type that is defined by device manufacturer.

15. User-Defined Network Variable Type (UNVT): Network variable format defined by device manufacturer. UNVTs create non-standard communications that other vendors' devices may not correctly interpret and may negatively impact system operation. UNVTs are not allowed.

S. Low Voltage: As defined in NFPA 70 for circuits and equipment operating at less than 50 V or for remote-control, signaling power-limited circuits.

T. Mobile Device: A data-enabled phone or tablet computer capable of connecting to a cellular data network and running a native control application or accessing a web interface.

U. Modbus TCP/IP: An open protocol for exchange of process data.

V. MS/TP: Master-slave/token-passing, IEE 8802-3. Datalink protocol LAN option that uses twisted-pair wire for low-speed communication.

W. MTBF: Mean time between failures.

X. Network Controller: Digital controller, which supports a family of programmable application controllers and application-specific controllers, that communicates on peer-to-peer network for transmission of global data.

Y. Network Repeater: Device that receives data packet from one network and rebroadcasts it to another network. No routing information is added to protocol.

Page 39: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 4

Z. Peer to Peer: Networking architecture that treats all network stations as equal partners.

AA. POT: Portable operator's terminal.

BB. PUE: Performance usage effectiveness.

CC. RAM: Random access memory.

DD. RF: Radio frequency.

EE. Router: Device connecting two or more networks at network layer.

FF. Server: Computer used to maintain system configuration, historical and programming database.

GG. TCP/IP: Transport control protocol/Internet protocol.

HH. UPS: Uninterruptible power supply.

II. USB: Universal Serial Bus.

JJ. User Datagram Protocol (UDP): This protocol assumes that the IP is used as the underlying protocol.

KK. VAV: Variable air volume.

LL. WLED: White light emitting diode.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.5 ACTION SUBMITTALS

A. Multiple Submissions:

1. If multiple submissions are required to execute work within schedule, first submit a coordinated schedule clearly defining intent of multiple submissions. Include a proposed date of each submission with a detailed description of submittal content to be included in each submission.

2. Clearly identify each submittal requirement indicated and in which submission the information will be provided.

3. Include an updated schedule in each subsequent submission with changes highlighted to easily track the changes made to previous submitted schedule.

B. Product Data: For each type of product include the following:

1. Construction details, material descriptions, dimensions of individual components and profiles, and finishes.

2. Operating characteristics, electrical characteristics, and furnished accessories indicating process operating range, accuracy over range, control signal over range, default control signal with loss of power, calibration data specific to each unique application, electrical power requirements, and limitations of ambient operating environment, including temperature and humidity.

3. Product description with complete technical data, performance curves, and product specification sheets.

4. Installation, operation and maintenance instructions including factors effecting performance.5. Bill of materials of indicating quantity, manufacturer, and extended model number for each unique

product.

a. Workstations.

Page 40: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 5

b. Printers.c. Gateways.d. Routers.e. Protocol analyzers.f. DDC controllers.g. Enclosures.h. Electrical power devices.i. UPS units.j. Accessories.k. Instruments.l. Control dampers and actuators.m. Control valves and actuators.

6. When manufacturer's product datasheets apply to a product series rather than a specific product model, clearly indicate and highlight only applicable information.

7. Each submitted piece of product literature shall clearly cross reference specification and drawings that submittal is to cover.

C. Software Submittal:

1. Cross-referenced listing of software to be loaded on each operator workstation, server, gateway, and DDC controller.

2. Description and technical data of all software provided, and cross-referenced to products in which software will be installed.

3. Operating system software, operator interface and programming software, color graphic software, DDC controller software, maintenance management software, and third-party software.

4. Include a flow diagram and an outline of each subroutine that indicates each program variable name and units of measure.

5. Listing and description of each engineering equation used with reference source.6. Listing and description of each constant used in engineering equations and a reference source to

prove origin of each constant.7. Description of operator interface to alphanumeric and graphic programming.8. Description of each network communication protocol.9. Description of system database, including all data included in database, database capacity and

limitations to expand database.10. Description of each application program and device drivers to be generated, including specific

information on data acquisition and control strategies showing their relationship to system timing, speed, processing burden and system throughout.

11. Controlled Systems: Instrumentation list with element name, type of device, manufacturer, model number, and product data. Include written description of sequence of operation including schematic diagram.

D. Shop Drawings:

1. General Requirements:

a. Include cover drawing with Project name, location, Owner, Architect, Contractor and issue date with each Shop Drawings submission.

b. Include a drawing index sheet listing each drawing number and title that matches information in each title block.

c. Drawings Size: 11 x 17.

2. Include plans, elevations, sections, and mounting details where applicable.3. Include details of product assemblies. Indicate dimensions, weights, loads, required clearances,

method of field assembly, components, and location and size of each field connection.4. Detail means of vibration isolation and show attachments to rotating equipment.5. Plan Drawings indicating the following:

a. Screened backgrounds of walls, structural grid lines, HVAC equipment, ductwork and piping.

Page 41: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 6

b. Room names and numbers with coordinated placement to avoid interference with control products indicated.

c. Each desktop workstation, server, gateway, router, DDC controller, control panel instrument connecting to DDC controller, and damper and valve connecting to DDC controller, if included in Project.

d. Exact placement of products in rooms, ducts, and piping to reflect proposed installed condition.

e. Network communication cable and raceway routing.f. Information, drawn to acceptable scale.g. Proposed routing of wiring, cabling, conduit, and tubing, coordinated with building services

for review before installation.

6. Schematic drawings for each controlled HVAC system indicating the following:

a. I/O points labeled with point names shown. Indicate instrument range, normal operating set points, and alarm set points. Indicate fail position of each damper and valve, if included in Project.

b. I/O listed in table format showing point name, type of device, manufacturer, model number, and cross-reference to product data sheet number.

c. A graphic showing location of control I/O in proper relationship to HVAC system.d. Wiring diagram with each I/O point having a unique identification and indicating labels for all

wiring terminals.e. Unique identification of each I/O that shall be consistently used between different drawings

showing same point.f. Elementary wiring diagrams of controls for HVAC equipment motor circuits including

interlocks, switches, relays and interface to DDC controllers.g. Narrative sequence of operation.h. Graphic sequence of operation, showing all inputs and output logical blocks.

7. Control panel drawings indicating the following:

a. Panel dimensions, materials, size, and location of field cable, raceways, and tubing connections.

b. Interior subpanel layout, drawn to scale and showing all internal components, cabling and wiring raceways, nameplates and allocated spare space.

c. Front, rear, and side elevations and nameplate legend.d. Unique drawing for each panel.

8. DDC system network riser diagram indicating the following:

a. Each device connected to network with unique identification for each.b. Interconnection of each different network in DDC system.c. For each network, indicate communication protocol, speed and physical means of

interconnecting network devices, such as copper cable type, or optical fiber cable type. Indicate raceway type and size for each.

d. Each network port for connection of an operator workstation or other type of operator interface with unique identification for each.

9. DDC system electrical power riser diagram indicating the following:

a. Each point of connection to field power with requirements (volts/phase//hertz/amperes/connection type) listed for each.

b. Each control power supply including, as applicable, transformers, power-line conditioners, transient voltage suppression and high filter noise units, DC power supplies, and UPS units with unique identification for each.

c. Each product requiring power with requirements (volts/phase//hertz/amperes/connection type) listed for each.

d. Power wiring type and size, race type, and size for each.

10. Monitoring and control signal diagrams indicating the following:

Page 42: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 7

a. Control signal cable and wiring between controllers and I/O.b. Point-to-point schematic wiring diagrams for each product.c. Control signal tubing to sensors, switches and transmitters.d. Process signal tubing to sensors, switches and transmitters.

11. Color graphics indicating the following:

a. Itemized list of color graphic displays to be provided.b. For each display screen to be provided, a true color copy showing layout of pictures,

graphics and data displayed.c. Intended operator access between related hierarchical display screens.

E. System Description:

1. Full description of DDC system architecture, network configuration, operator interfaces and peripherals, servers, controller types and applications, gateways, routers and other network devices, and power supplies.

2. Complete listing and description of each report, log and trend for format and timing and events which initiate generation.

3. System and product operation under each potential failure condition including, but not limited to, the following:

a. Loss of power.b. Loss of network communication signal.c. Loss of controller signals to inputs and outpoints.d. Operator workstation failure.e. Server failure.f. Gateway failure.g. Network failureh. Controller failure.i. Instrument failure.j. Control damper and valve actuator failure.

4. Complete bibliography of documentation and media to be delivered to Owner.5. Description of testing plans and procedures.6. Description of Owner training.

F. Samples:

1. For each of the following exposed product, installed in finished space for approval of selection of aesthetic characteristics:

a. Gas instruments b. Moisture instruments c. Motion instruments d. Pressure instruments e. Temperature instruments

2. Infra-red temperature sensor for ice slab temperature sensing.

G. Delegated-Design Submittal: For DDC system products and installation indicated as being delegated.

1. Supporting documentation showing DDC system design complies with performance requirements indicated, including calculations and other documentation necessary to prove compliance.

2. Schedule and design calculations for control dampers and actuators.

a. Flow at Project design and minimum flow conditions.b. Face velocity at Project design and minimum airflow conditions.c. Pressure drop across damper at Project design and minimum airflow conditions.

Page 43: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 8

d. AMCA 500-D damper installation arrangement used to calculate and schedule pressure drop, as applicable to installation.

e. Maximum close-off pressure.f. Leakage airflow at maximum system pressure differential (fan close-off pressure).g. Torque required at worst case condition for sizing actuator.h. Actuator selection indicating torque provided.i. Actuator signal to control damper (on, close or modulate).j. Actuator position on loss of power.k. Actuator position on loss of control signal.

3. Schedule and design calculations for control valves and actuators.

a. Flow at Project design and minimum flow conditions.b. Pressure-differential drop across valve at Project design flow condition.c. Maximum system pressure-differential drop (pump close-off pressure) across valve at

Project minimum flow condition.d. Design and minimum control valve coefficient with corresponding valve position.e. Maximum close-off pressure.f. Leakage flow at maximum system pressure differential.g. Torque required at worst case condition for sizing actuator.h. Actuator selection indicating torque provided.i. Actuator signal to control damper (on, close or modulate).j. Actuator position on loss of power.k. Actuator position on loss of control signal.

4. Schedule and design calculations for selecting flow instruments.

a. Instrument flow range.b. Project design and minimum flow conditions with corresponding accuracy, control signal to

transmitter and output signal for remote control.c. Extreme points of extended flow range with corresponding accuracy, control signal to

transmitter and output signal for remote control.d. Pressure-differential loss across instrument at Project design flow conditions.e. Where flow sensors are mated with pressure transmitters, provide information for each

instrument separately and as an operating pair.

1.6 INFORMATIONAL SUBMITTALS

A. Coordination Drawings:

1. Plan drawings and corresponding product installation details, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved:

a. Product installation location shown in relationship to room, duct, pipe and equipment.b. Structural members to which products will be attached.c. Wall-mounted instruments located in finished space showing relationship to light switches,

fire-alarm devices and other installed devices.d. Size and location of wall access panels for products installed behind walls and requiring

access.

2. Reflected ceiling plans and other details, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved:

a. Ceiling components.b. Size and location of access panels for products installed above inaccessible ceiling

assemblies and requiring access.c. Items penetrating finished ceiling including the following:

1) Lighting fixtures.

Page 44: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 9

2) Air outlets and inlets.3) Speakers.4) Sprinklers.5) Access panels.6) Motion sensors.7) Pressure sensors.8) Temperature sensors and other DDC control system instruments.

B. Qualification Data:

1. Systems Provider Qualification Data:

a. Resume of project manager assigned to Project.b. Resumes of application engineering staff assigned to Project.c. Resumes of installation and programming technicians assigned to Project.d. Resumes of service technicians assigned to Project.e. Brief description of past project including physical address, floor area, number of floors,

building system cooling and heating capacity and building's primary function.f. Description of past project DDC system, noting similarities to Project scope and complexity

indicated.g. Names of staff assigned to past project that will also be assigned to execute work of this

Project.h. Owner contact information for past project including name, phone number, and e-mail

address.i. Contractor contact information for past project including name, phone number, and e-mail

address.j. Architect and Engineer contact information for past project including name, phone number,

and e-mail address.

2. Manufacturer's qualification data.3. Testing agency's qualifications data.

C. Welding certificates.

D. Product Certificates:

1. Data Communications Protocol Certificates: Certifying that each proposed DDC system component complies with ASHRAE 135.

2. Data Communications Protocol Certificates: Certifying that each proposed DDC system component complies with BacNet standards.

E. \Product Test Reports: For each product that requires testing to be performed by manufacturer.

F. Preconstruction Test Reports: For each separate test performed.

G. Source quality-control reports.

H. Field quality-control reports.

I. Sample Warranty: For manufacturer's warranty.

1.7 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For DDC system to include in emergency, operation and maintenance manuals.

1. In addition to items specified in Section 017823 "Operation and Maintenance Data," include the following:

Page 45: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 10

a. Project Record Drawings of as-built versions of submittal Shop Drawings provided in electronic PDF format.

b. Testing and commissioning reports and checklists of completed final versions of reports, checklists, and trend logs.

c. As-built versions of submittal Product Data.d. Names, addresses, e-mail addresses and 24-hour telephone numbers of Installer and

service representatives for DDC system and products.e. Operator's manual with procedures for operating control systems including logging on and

off, handling alarms, producing point reports, trending data, overriding computer control and changing set points and variables.

f. Programming manuals with description of programming language and syntax, of statements for algorithms and calculations used, of point database creation and modification, of program creation and modification, and of editor use.

g. Engineering, installation, and maintenance manuals that explain how to:

1) Design and install new points, panels, and other hardware.2) Perform preventive maintenance and calibration.3) Debug hardware problems.4) Repair or replace hardware.

h. Documentation of all programs created using custom programming language including set points, tuning parameters, and object database.

i. Backup copy of graphic files, programs, and database on electronic media such as DVDs.j. List of recommended spare parts with part numbers and suppliers.k. Complete original-issue documentation, installation, and maintenance information for

furnished third-party hardware including computer equipment and sensors.l. Complete original-issue copies of furnished software, including operating systems, custom

programming language, operator workstation software, and graphics software.m. Licenses, guarantees, and warranty documents.n. Recommended preventive maintenance procedures for system components, including

schedule of tasks such as inspection, cleaning, and calibration; time between tasks; and task descriptions.

o. Owner training materials.

1.8 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials and parts that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

B. Include product manufacturers' recommended parts lists for proper product operation over four-year period following warranty period. Parts list shall be indicated for each year.

C. Furnish parts, as indicated by manufacturer's recommended parts list, for product operation during two-year period following warranty period.

D. Furnish quantity indicated of matching product(s) in Project inventory for each unique size and type of following:

1. Network Controller: One.2. Programmable Application Controller: One.3. Application-Specific Controller: One.4. Room Carbon Dioxide Sensor and Transmitter: One.5. Room Moisture Sensor and Transmitter: One.6. Room Pressure Sensor and Transmitter: One.7. Room Temperature Sensor and Transmitter: One.8. General-Purpose Relay: One.9. Multifunction Time-Delay Relay: One.10. Latching Relay: One.11. Current-Sensing Relay: One.12. Combination On-Off Status Sensor and On-Off Relay: One.

Page 46: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 11

13. Transformer: One.14. DC Power Supply: One.15. Supply of 20 percent spare optical fiber cable splice organizer cabinets for several re-terminations.

1.9 QUALITY ASSURANCE

A. DDC System Manufacturer Qualifications:

1. Nationally recognized manufacturer of DDC systems and products.2. DDC systems with similar requirements to those indicated for a continuous period of five years

within time of bid.3. DDC systems and products that have been successfully tested and in use on at least three past

projects.4. Having complete published catalog literature, installation, operation and maintenance manuals for

all products intended for use.5. Having full-time in-house employees for the following:

a. Product research and development.b. Product and application engineering.c. Product manufacturing, testing and quality control.d. Technical support for DDC system installation training, commissioning and troubleshooting

of installations.e. Owner operator training.

B. DDC System Provider Qualifications:

1. Authorized representative of, and trained by, DDC system manufacturer.2. In-place facility located within 50 miles of Project.3. Demonstrated past experience with installation of DDC system products being installed for period

within three consecutive years before time of bid.4. Demonstrated past experience on five projects of similar complexity, scope and value.5. Each person assigned to Project shall have demonstrated past experience.6. Staffing resources of competent and experienced full-time employees that are assigned to execute

work according to schedule.7. Service and maintenance staff assigned to support Project during warranty period.8. Product parts inventory to support on-going DDC system operation for a period of not less than 5

years after Substantial Completion.9. DDC system manufacturer's backing to take over execution of Work if necessary to comply with

requirements indicated. Include Project-specific written letter, signed by manufacturer's corporate officer, if requested.

C. Testing Agency Qualifications: Member company of NETA.

1. Testing Agency's Field Supervisor: Certified by NETA to supervise on-site testing.

D. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."2. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum."3. AWS D1.3/D1.3M, "Structural Welding Code - Sheet Steel."4. AWS D1.4/D1.4M, "Structural Welding Code - Reinforcing Steel."

E. Pipe and Pressure-Vessel Welding Qualifications: Qualify procedures and operators according to ASME Boiler and Pressure Vessel Code.

Page 47: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 12

1.10 WARRANTY

A. Manufacturer's Warranty: Manufacturer and Installer agree to repair or replace products that fail in materials or workmanship within specified warranty period.

1. Failures shall be adjusted, repaired, or replaced at no additional cost or reduction in service to Owner.

2. Include updates or upgrades to software and firmware if necessary to resolve deficiencies.

a. Install updates only after receiving Owner's written authorization.

3. Warranty service shall occur during normal business hours and commence within 24 hours of Owner's warranty service request.

4. Warranty Period: Two years from date of Substantial Completion.

a. For Gateway: Three year parts and labor warranty for each.

PART 2 - PRODUCTS

2.1 DDC SYSTEM MANUFACTURERS

A. Approved manufacturers:1. JCI2. Siemens3. Schneider Electric4. Approved equivalent

2.2 DDC SYSTEM DESCRIPTION

A. Microprocessor-based monitoring and control including analog/digital conversion and program logic. A control loop or subsystem in which digital and analog information is received and processed by a microprocessor, and digital control signals are generated based on control algorithms and transmitted to field devices to achieve a set of predefined conditions.

1. DDC system shall consist of a high-speed, peer-to-peer network of distributed DDC controllers, other network devices, operator interfaces, and software.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

2.3 WEB ACCESS

A. DDC system shall be Web based or Web compatible].

1. Web-Based Access to DDC System:

a. DDC system software shall be based on server client architecture, designed around open standards of Web technology. DDC system server shall be accessed using a Web browser over DDC system network, using Owner's LAN, and remotely over Internet through Owner's LAN.

b. Intent of thin-client architecture is to provide operators complete access to DDC system via a Web browser. No special software other than a Web browser shall be required to access graphics, point displays, and trends; to configure trends, points, and controllers; and to edit programming.

c. Web access shall be password protected.

Page 48: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 13

2. Web-Compatible Access to DDC System:

a. Workstation and/or server shall perform overall system supervision and configuration, graphical user interface, management report generation, and alarm annunciation.

b. DDC system shall support Web browser access to building data. Operator using a standard Web browser shall be able to access control graphics and change adjustable set points.

c. Web access shall be password protected.

3. Smart Phone Access to DDC System:

a. Overall system supervision and configuration of the DDC system shall be accessible through smart phone application. Phone app shall allow graphical user interface, management report generation, and alarm annunciation.

b. DDC system shall support smart phone access to building data. Operator using a standard smart phone with Android or Apple operating system shall be able to access control graphics and change adjustable set points.

c. Smart phone access shall be password protected.

2.4 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design DDC system to satisfy requirements indicated.

B. Delegated Design: Engage a qualified professional to design DDC system to satisfy requirements indicated.

1. System Performance Objectives:

a. DDC system shall manage HVAC systems.b. DDC system control shall operate HVAC systems to achieve optimum operating costs while

using least possible energy and maintaining specified performance.c. DDC system shall respond to power failures, HVAC equipment failures, and adverse and

emergency conditions encountered through connected I/O points.d. DDC system shall operate while unattended by an operator and through operator

interaction.e. DDC system shall record trends and transaction of events and produce report information

such as performance, energy, occupancies, and equipment operation.

C. Surface-Burning Characteristics: Products installed in ducts, equipment, and return-air paths shall comply with ASTM E84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1. Flame-Spread Index: 25 or less.2. Smoke-Developed Index: 50 or less.

D. DDC System Speed:

1. Response Time of Connected I/O:

a. AI point values connected to DDC system shall be updated at least every two seconds for use by DDC controllers. Points used globally shall also comply with this requirement.

b. BI point values connected to DDC system shall be updated at least every two seconds for use by DDC controllers. Points used globally shall also comply with this requirement.

c. AO points connected to DDC system shall begin to respond to controller output commands within one second. Global commands shall also comply with this requirement.

d. BO point values connected to DDC system shall respond to controller output commands within one second. Global commands shall also comply with this requirement.

Page 49: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 14

2. Display of Connected I/O:

a. Analog point COV connected to DDC system shall be updated and displayed at least every five seconds for use by operator.

b. Binary point COV connected to DDC system shall be updated and displayed at least every five seconds for use by operator.

c. Alarms of analog and digital points connected to DDC system shall be displayed within 15 seconds of activation or change of state.

d. Graphic display refresh shall update within four seconds.e. Point change of values and alarms displayed from workstation to workstation when multiple

operators are viewing from multiple workstations shall not exceed graphic refresh rate indicated.

E. Network Bandwidth: Design each network of DDC system to include at least 30 percent available spare bandwidth with DDC system operating under normal and heavy load conditions indicated. Calculate bandwidth usage, and apply a safety factor to ensure that requirement is satisfied when subjected to testing under worst case conditions.

F. DDC System Data Storage:

1. Include capability to archive not less than 60 consecutive months of historical data for all I/O points connected to system, including alarms, event histories, transaction logs, trends and other information indicated.

2. Local Storage:

a. Provide workstation with data storage indicated. Server(s) shall use IT industry standard database platforms and be capable of functions described in "DDC Data Access" Paragraph.

3. Cloud Storage:

a. Provide application-based and web browser interfaces to configure, upload, download, and manage data, and service plan with storage adequate to store all data for term indicated. Cloud storage shall use IT industry standard database platforms and be capable of functions described in "DDC Data Access" Paragraph.

G. DDC Data Access:

1. When logged into the system, operator shall be able to also interact with any DDC controller connected to DDC system as required for functional operation of DDC system.

2. System(s) shall be used for application configuration; for archiving, reporting and trending of data; for operator transaction archiving and reporting; for network information management; for alarm annunciation; and for operator interface tasks and controls application management.

H. Future Expandability:

1. DDC system size shall be expandable to an ultimate capacity of at least four] times total I/O points indicated.

2. Additional DDC controllers, I/O and associated wiring shall be all that is needed to achieve ultimate capacity. Initial network infrastructure shall be designed and installed to support ultimate capacity.

3. Operator interfaces installed initially shall not require hardware and software additions and revisions for ultimate capacity.

I. Input Point Displayed Accuracy: Input point displayed values shall meet following end-to-end overall system accuracy, including errors associated with meter, sensor, transmitter, lead wire or cable, and analog to digital conversion.

1. Energy:

a. Thermal: Within 1 percent of reading.

Page 50: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 15

b. Electric Power: Within 1 percent of reading.c. Requirements indicated on Drawings for meters not supplied by utility.

2. Flow:

a. Air: Within 5 percent of design flow rate.b. Air (Terminal Units): Within 5 percent of design flow rate.c. Water: Within 5 percent of design flow rate.

3. Gas:

a. Carbon Dioxide: Within 50 ppm.b. Carbon Monoxide: Within 5 percent of reading.c. Oxygen: Within 5 percent of reading.d. Refrigerant: Within 50 ppm.

4. Moisture (Relative Humidity):

a. Air: Within 2 percent RH.b. Space: Within 2 percent RH.c. Outdoor: Within 2 percent RH.

5. Level: Within 5 percent of reading.6. Pressure:

a. Air, Ducts and Equipment: 1 percent of instrument range.b. Space: Within 1 percent of instrument range.c. Water: Within 1] percent of instrument range.

7. Speed: Within 5 percent of reading.8. Temperature, Dew Point:

a. Air: Within 1 deg F.b. Space: Within 1 deg F.c. Outdoor: Within 3 deg F.

9. Temperature, Dry Bulb:

a. Air: Within 1 deg F.b. Space: Within 1 deg F.c. Outdoor: Within 2 deg F.d. Chilled Water: Within 1 deg F.e. Condenser Water: Within 1 deg F.f. Temperature Difference: Within 0.25 deg F.g. Other Temperatures Not Indicated: Within 1 deg F.

10. Temperature, Wet Bulb:

a. Air: Within 1 deg F.b. Space: Within 1 deg F.c. Outdoor: Within 2 deg F.

J. Precision of I/O Reported Values: Values reported in database and displayed shall have following precision:

1. Current:

a. Milliamperes: Nearest 1/100th of a milliampere.b. Amperes: Nearest 1/10th of an ampere up to 100 A; nearest ampere for 100 A and more.

Page 51: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 16

2. Energy:

a. Electric Power:

1) Rate (Watts): Nearest 1/10th of a watt through 1000 W.2) Rate (Kilowatts): Nearest 1/10th of a kilowatt through 1000 kW; nearest kilowatt

above 1000 kW.3) Usage (Kilowatt-Hours): Nearest kilowatt through 10,000 kW; nearest 10 kW

between 10,000 and 100,000 kW; nearest 100 kW for above 100,000 kW.

b. Thermal, Rate:

1) Heating: For Btu/h, nearest Btu/h up to 1000 Btu/h; nearest 10 Btu/h between 1000 and 10,000 Btu/h; nearest 100 Btu/h for above 10,000 Btu/h. For Mbh, round to nearest Mbh up to 1000 Mbh; nearest 10 Mbh between 1000 and 10,000 Mbh; nearest 100 Mbh above 10,000 Mbh

2) Cooling: For tons, nearest ton up to 1000 tons; nearest 10 tons between 1000 and 10,000 tons; nearest 100 tons above 10,000 tons

c. Thermal, Usage:

1) Heating: For Btu, nearest Btu up to 1000 Btu; nearest 10 Btu between 1000 and 10,000 Btu; nearest 100 Btu for above 10,000 Btu. For Mbtu, round to nearest Mbtu up to 1000 Mbtu; nearest 10 Mbtu between 1000 and 10,000 Mbtu; nearest 100 Mbtu above 10,000 Mbtu

2) Cooling: For ton-hours, nearest ton-hours up to 1000 ton-hours; nearest 10 ton-hours between 1000 and 10,000 ton-hours; nearest 100 tons above 10,000 tons.

3. Flow:

a. Air: Nearest 1/10th of a cfm through 100 cfm; nearest cfm between 100 and 1000 cfm; nearest 10 cfm between 1000 and 10,000 cfm; nearest 100 cfm above 10,000 cfm

b. Water: Nearest 1/10th gpm through 100 gpm; nearest gpm between 100 and 1000 gpm; nearest 10 gpm between 1000 and 10,000 gpm; nearest 100 gpm above 10,000 gpm

c. Steam: Nearest 1/10th lb/hr through 100 lbs/hr; nearest lbs/hr between 100 and 1000 lbs/hr; nearest 10 lbs/hr above 1000 lbs/hr

4. Gas:

a. Carbon Dioxide (ppm): Nearest ppm.b. Carbon Monoxide (ppm): Nearest ppm.c. Oxygen (Percentage): Nearest 1/10th of 1 percent.d. Refrigerant (ppm): Nearest ppm.

5. Moisture (Relative Humidity):

a. Relative Humidity (Percentage): Nearest 1 percent.

6. Level: Nearest 1/100th of an inch through 10 inches; nearest 1/10 of an inch between 10 and 100 inches; nearest inch above 100 inches

a. Rotation (rpm): Nearest 1 rpm.b. Velocity: Nearest 1/10th fpm through 100 fpm; nearest fpm between 100 and 1000 fpm;

nearest 10 fpm above 1000 fpm

7. Position, Dampers and Valves (Percentage Open): Nearest 1 percent.8. Pressure:

a. Air, Ducts and Equipment: Nearest 1/10th in. w.c. b. Space: Nearest 1/100th in. w.c.

Page 52: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 17

c. Steam: Nearest 1/10th psig through 100 psig; nearest psig above 100 psig d. Water: Nearest 1/10 psig through 100 psig; nearest psig above 100 psig

9. Temperature:

a. Air, Ducts and Equipment: Nearest 1/10th of a degree.b. Outdoor: Nearest degree.c. Space: Nearest 1/10th of a degree.d. Chilled Water: Nearest 1/10th of a degree.e. Condenser Water: Nearest 1/10th of a degree.f. Heating Hot Water: Nearest degree.g. Heat Recovery Runaround: Nearest 1/10th of a degree.h. Steam: Nearest degree.

10. Vibration: Nearest 1/10th in/s11. Voltage: Nearest 1/10 volt up to 100 V; nearest volt above 100 V.

K. Control Stability: Control variables indicated within the following limits:

1. Flow:

a. Air, Ducts and Equipment, except Terminal Units: Within 2 percent of design flow rate.b. Air, Terminal Units: Within 5 percent of design flow rate.c. Water: Within 2 percent of design flow rate.

2. Gas:

a. Carbon Dioxide: Within 50 ppm.b. Carbon Monoxide: Within 5 percent of reading.c. Oxygen: Within 5 percent of reading.

3. Moisture (Relative Humidity):

a. Air: Within 5 percent RH.b. Space: Within 5 percent RH.c. Outdoor: Within 5 percent RH.

4. Level: Within 5 percent of reading.5. Pressure:

a. Air, Ducts and Equipment: 1> percent of instrument range.b. Space: Within 1 percent of instrument range.c. Water: Within 1 percent of instrument range.

6. Temperature, Dew Point:

a. Air: Within 1 deg Fb. Space: Within 1 deg F

7. Temperature, Dry Bulb:

a. Air: Within 2 deg F.b. Space: Within 2 deg F.c. Chilled Water: Within 1 deg Fd. Condenser Water: Within 1 deg Fe. Heating Hot Water: Within 2 deg F

8. Temperature, Wet Bulb:

Page 53: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 18

a. Air: Within 1 deg Fb. Space: Within 1 deg F

L. Environmental Conditions for Controllers, Gateways, and Routers:

1. Products shall operate without performance degradation under ambient environmental temperature, pressure and humidity conditions encountered for installed location.

a. If product alone cannot comply with requirement, install product in a protective enclosure that is isolated and protected from conditions impacting performance. Enclosure shall be internally insulated, electrically heated, cooled and ventilated as required by product and application.

2. Products shall be protected with enclosures satisfying the following minimum requirements unless more stringent requirements are indicated. Products not available with integral enclosures complying with requirements indicated shall be housed in protective secondary enclosures. Installed location shall dictate the following NEMA 250 enclosure requirements:

a. Outdoors, Protected: Type 3.b. Outdoors, Unprotected: Type 4X.c. Indoors, Heated with Filtered Ventilation: Type 1.d. Indoors, Heated with Non-Filtered Ventilation: Type 2.e. Indoors, Heated and Air Conditioned: Type 1.f. Mechanical Equipment Rooms:

1) Chiller and Boiler Rooms: Type 4].2) Air-Moving Equipment Rooms: Type 2.

g. Localized Areas Exposed to Washdown: Type 4.h. Within Duct Systems and Air-Moving Equipment Not Exposed to Possible Condensation:

Type 2i. Within Duct Systems and Air-Moving Equipment Exposed to Possible Condensation:

Type 4>.j. Hazardous Locations: Explosion-proof rating for condition.

M. Environmental Conditions for Instruments and Actuators:

1. Instruments and actuators shall operate without performance degradation under the ambient environmental temperature, pressure, humidity, and vibration conditions specified and encountered for installed location.

a. If instruments and actuators alone cannot comply with requirement, install instruments and actuators in protective enclosures that are isolated and protected from conditions impacting performance. Enclosure shall be internally insulated, electrically heated, cooled, and ventilated as required by instrument and application.

2. Instruments, actuators and accessories shall be protected with enclosures satisfying the following minimum requirements unless more stringent requirements are indicated. Instruments and actuators not available with integral enclosures complying with requirements indicated shall be housed in protective secondary enclosures. Installed location shall dictate the following NEMA 250 enclosure requirements:

a. Outdoors, Protected: Type 3b. Outdoors, Unprotected: Type 4X.c. Indoors, Heated with Filtered Ventilation: Type 1.d. Indoors, Heated with Non-Filtered Ventilation: Type 2.e. Indoors, Heated and Air-conditioned: Type 1.f. Mechanical Equipment Rooms:

1) Chiller and Boiler Rooms: Type 12

Page 54: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 19

2) Air-Moving Equipment Rooms: Type 2.

g. Localized Areas Exposed to Washdown: Type 4X.h. Within Duct Systems and Air-Moving Equipment Not Exposed to Possible Condensation:

Type 3.i. Within Duct Systems and Air-Moving Equipment Exposed to Possible Condensation:

Type 4.j. Hazardous Locations: Explosion-proof rating for condition.

N. DDC System Reliability:

1. Design, install and configure DDC controllers, gateways, and routers, to yield a MTBF of at least 40,000 hours, based on a confidence level of at least 90 percent. MTBF value shall include any failure for any reason to any part of products indicated.

2. If required to comply with MTBF indicated, include DDC system and product redundancy to maintain DCC system, and associated systems and equipment that are being controlled, operational and under automatic control.

3. Critical systems and equipment that require a higher degree of DDC system redundancy than MTBF indicated shall be indicated on Drawings.

O. Electric Power Quality:

1. Power-Line Surges:

a. Protect susceptible DDC system products connected to ac power circuits from power-line surges to comply with requirements of IEEE C62.41.

b. Do not use fuses for surge protection.c. Test protection in the normal mode and in the common mode, using the following two

waveforms:

1) 10-by-1000-mic.sec. waveform with a peak voltage of 1500 V and a peak current of 60 A.

2) 8-by-20-mic.sec. waveform with a peak voltage of 1000 V and a peak current of 500 A.

2. Power Conditioning:

a. Protect susceptible DDC system products connected to ac power circuits from irregularities and noise rejection. Characteristics of power-line conditioner shall be as follows:

1) At 85 percent load, output voltage shall not deviate by more than plus or minus 1 percent of nominal when input voltage fluctuates between minus 20 percent to plus 10 percent of nominal.

2) During load changes from zero to full load, output voltage shall not deviate by more than plus or minus 3 percent of nominal.

3) Accomplish full correction of load switching disturbances within five cycles, and 95 percent correction within two cycles of onset of disturbance.

4) Total harmonic distortion shall not exceed 3-1/2 percent at full load.

3. Ground Fault: Protect products from ground fault by providing suitable grounding. Products shall not fail due to ground fault condition.

P. Backup Power Source:

1. HVAC systems and equipment served by a backup power source shall have associated DDC system products that control such systems and equipment also served from a backup power source.

Q. UPS:

Page 55: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 20

1. DDC system products powered by UPS units shall include the following:

a. Desktop workstations.b. Printers.c. Servers.d. Gateways.e. DDC controllers, except application-specific controllers.

R. Continuity of Operation after Electric Power Interruption:

1. Equipment and associated factory-installed controls, field-installed controls, electrical equipment, and power supply connected to building normal and backup power systems shall automatically return equipment and associated controls to operating state occurring immediately before loss of normal power, without need for manual intervention by operator when power is restored either through backup power source or through normal power if restored before backup power is brought online.

2.5 PANEL-MOUNTED, MANUAL OVERRIDE SWITCHES

A. Manual Override of Control Dampers:

1. Include panel-mounted, two-position, selector switch for each automatic control damper being controlled by DDC controller.

2. Label each switch with damper designation served by switch.3. Label switch positions to indicate either "Manual" or "Auto" control signal to damper.4. With switch in "Auto" position signal to control damper actuator shall be control loop output signal

from DDC controller.5. With switch in "Manual" position, signal to damper actuator shall be controlled at panel with either

an integral or separate switch to include local control.

a. For Binary Control Dampers: Manual two-position switch shall have "Close" and "Open" switch positions indicated. With switch in "Close" position, damper shall close. With switch in "Open" position, damper shall open.

b. For Analog Control Dampers: A gradual switch shall have "Close" and "Open" switch limits indicated. Operator shall be able to rotate switch knob to adjust damper to any position from close to open.

6. DDC controller shall monitor and report position of each manual override selector switch. With switch placed in "manual" position, DDC controller shall signal an override condition to alert operator that damper is under manual, not automatic, control.

7. Configure manual override switches to allow operator to manually operate damper while at panel without DDC controller installed and operational.

8. Terminal equipment including VAV units, fan-coil units, and unit heaters do not require manual override unless otherwise indicated by sequence of operation.

B. Manual Override of Control Valves:

1. Include panel-mounted, two-position, selector switch for each automatic control valve being controlled by a DDC controller.

2. Label each switch with valve designation served by switch.3. Label switch positions to indicate either "Manual" or "Auto" control signal to valve.4. With switch in "Auto" position, signal to control-valve actuator shall be a control loop output signal

from DDC controller.5. With switch in "Manual" position, signal to valve actuator shall be controlled at panel with either an

integral or a separate switch to include local control.

a. For Binary Control Dampers: Manual two-position switch shall have "Close" and "Open" switch positions indicated. With switch in "Close" position, damper shall close. With switch in "Open" position, damper shall open.

Page 56: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 21

b. For Analog Control Dampers: A gradual switch shall have "Open" and "Close" switch limits indicated. Operator shall be able to rotate switch knob to adjust damper to any position from close to open.

6. DDC controller shall monitor and report position of each manual override selector switch. With switch placed in "manual" position, DDC controller shall signal an override condition to alert operator that valve is under manual, not automatic, control.

7. Configure manual override switches to allow operator to manually operate valve while at panel without DDC controller installed and operational.

8. Terminal equipment including VAV units, fan-coil units, and unit heaters do not require manual override unless otherwise indicated by sequence of operation.

2.6 SYSTEM ARCHITECTURE

A. System architecture shall consist of no more than two levels of LANs.

1. Level one LAN shall connect network controllers and operator workstations.2. Level one LAN shall connect programmable application controllers to other programmable

application controllers, and to network controllers.3. Level two LAN shall connect application-specific controllers to programmable application controllers

and network controllers.4. Level two LAN shall connect application-specific controllers to application-specific controllers.

B. Minimum Data Transfer and Communication Speed:

1. LAN Connecting Operator Workstations and Network Controllers: 100 Mbps.2. LAN Connecting Programmable Application Controllers: 1000 kbps.3. LAN Connecting Application-Specific Controllers: 115,000 bps.

C. DDC system shall consist of dedicated and separated LANs that are not shared with other building systems and tenant data and communication networks.

D. System architecture shall be modular and have inherent ability to expand to not less than two times system size indicated with no impact to performance indicated.

E. System architecture shall perform modifications without having to remove and replace existing network equipment.

F. Number of LANs and associated communication shall be transparent to operator. All I/O points residing on any LAN shall be capable of global sharing between all system LANs.

G. System design shall eliminate dependence on any single device for system alarm reporting and control execution. Each controller shall operate independently by performing its' own control, alarm management and historical data collection.

H. Special Network Architecture Requirements:

1. Air-Handling Systems: For control applications of an air-handling system that consists of air-handling unit(s) and VAV terminal units, include a dedicated LAN of application-specific controllers serving VAV terminal units connected directly to controller that is controlling air-handling system air-handling unit(s). Basically, create a DDC system LAN that aligns with air-handling system being controlled.

2.7 DDC SYSTEM OPERATOR INTERFACES

A. Operator Means of System Access: Operator shall be able to access entire DDC system through any of multiple means, including, but not limited to, the following:

Page 57: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 22

1. Desktop and portable workstation with hardwired connection through LAN port.2. Portable operator terminal with hardwired connection through LAN port.3. Portable operator workstation with wireless connection through LAN router.4. Mobile device and application with secured wireless connection through LAN router or cellular data

service.5. Remote connection through web access.

B. Access to system, regardless of operator means used, shall be transparent to operator.

C. Network Ports: For hardwired connection of desktop or portable workstation. Network port shall be easily accessible, properly protected, clearly labeled, and installed at the following locations:

1. Each mechanical equipment room.2. Each boiler room.3. Each chiller room or outdoor chiller yard.4. Each cooling tower location.5. Each different roof level with roof-mounted air-handling units or rooftop units.6. Security system command center.7. Fire-alarm system command center.

D. Desktop Workstations:

1. Connect to DDC system Level one LAN through a communications port directly on LAN or through a communications port on a DDC controller.

2. Able to communicate with any device located on any DDC system LAN.

E. Portable Workstations:

1. Connect to DDC system Level one LAN through a communications port directly on LAN or through a communications port on a DDC controller.

2. Able to communicate with any device located on any DDC system LAN.3. Connect to DDC system Level two LAN through a communications port on an application-specific

controller, or a room temperature sensor connected to an application-specific controller.4. Connect to system through a wireless router connected to Level one LAN.5. Connect to system through a cellular data service.6. Portable workstation shall be able to communicate with any device connected to any system LAN

regardless of point of physical connection to system.7. Monitor, program, schedule, adjust set points, and report capabilities of I/O connected anywhere in

system.8. Have dynamic graphic displays that are identical to desktop workstations.

F. POT:

1. Connect DDC controller through a communications port local to controller.2. Able to communicate with any DDC system controller that is directly connected or with LAN or

connected to DDC system.

G. Mobile Device:

1. Connect to system through a wireless router connected to LAN and cellular data service.2. Able to communicate with any DDC controller connected to DDC system using a dedicated

application and secure web access.

H. Telephone Communications:

1. Through use of a standard modem, operator shall be able to communicate with any device connected to any system LAN.

2. Have auto-dial and auto-answer communications to allow desktop and portable workstations and DDC controllers to communicate with remote workstations and remote DDC controllers via telephone lines.

Page 58: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 23

a. Desktop and Portable Workstations:

1) Operators shall be able to perform all control functions, report functions, and database generation and modification functions as if directly connected to system LAN.

2) Have routines to automatically answer calls, and either file or display information sent remotely.

3) Communications taking place over telephone lines shall be completely transparent to operator.

4) Dial-up program shall maintain a user-definable cross-reference and associated telephone numbers so it is not required to remember or manually dial telephone numbers.

b. DDC Controllers:

1) Not have modems unless specifically indicated for a unique controller.2) Controllers with modems shall automatically place calls to report critical alarms, or to

upload trend and historical information for archiving.3) Analyze and prioritize alarms to minimize initiation of calls.4) Buffer noncritical alarms in memory and report them as a group of alarms, or until an

operator manually requests an upload.5) Make provisions for handling busy signals, no-answers, and incomplete data

transfers.6) Call default devices when communications cannot be established with primary

devices.

I. Critical Alarm Reporting:

1. Operator-selected critical alarms shall be sent by DDC system to notify operator of critical alarms that require immediate attention.

2. DDC system shall send alarm notification to multiple recipients that are assigned for each alarm.3. DDC system shall notify recipients by any or all means, including e-mail, text message and

prerecorded phone message to mobile and landline phone numbers.

J. Simultaneous Operator Use: Capable of accommodating up to five simultaneous operators that are accessing DDC system through any one of operator interfaces indicated.

2.8 NETWORKS

A. Acceptable networks for connecting workstations, mobile devices, and network controllers include the following:

1. ATA 878.1, ARCNET.2. CEA-709.1-C.3. IP.4. IEEE 8802-3, Ethernet.

B. Acceptable networks for connecting programmable application controllers include the following:

1. ATA 878.1, ARCNET.2. CEA-709.1-C.3. IP.4. IEEE 8802-3, Ethernet.

C. Acceptable networks for connecting application-specific controllers include the following:

1. ATA 878.1, ARCNET.2. CEA-709.1-C.3. EIA-485A.

Page 59: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 24

4. IP.5. IEEE 8802-3, Ethernet.

2.9 NETWORK COMMUNICATION PROTOCOL

A. Network communication protocol(s) used throughout entire DDC system shall be open to Owner and available to other companies for use in making future modifications to DDC system.

B. ASHRAE 135 Protocol:

1. ASHRAE 135 communication protocol shall be sole and native protocol used throughout entire DDC system.

2. DDC system shall not require use of gateways except to integrate HVAC equipment and other building systems and equipment, not required to use ASHRAE 135 communication protocol.

3. If used, gateways shall connect to DDC system using ASHRAE 135 communication protocol and Project object properties and read/write services indicated by interoperability schedule.

4. Operator workstations, controllers and other network devices shall be tested and listed by BACnet Testing Laboratories.

C. CEA-709.1-C Protocol:

1. DDC system shall be an open implementation of LonWorks technology using CEA 709.1-C communication protocol and using LonMark SNVTs as defined in LonMark SNVT list exclusively for communication throughout DDC system.

2. LNS shall be used for all network management including addressing and binding of network variables.

a. Final LNS database shall be submitted with Project closeout submittals.b. All devices shall be online and commissioned into LNS database.

3. All devices connected to DDC system network(s) shall use CEA-709.1-C protocol and be installed so SCPT output from any node on network can be bound to any other node in the domain.

D. Industry Standard Protocols:

1. DDC system shall use any one or a combination of the following industry standard protocols for network communication while complying with other DDC system requirements indicated:

a. ASHRAE 135.b. CEA-709.1-C.c. Modbus Application Protocol Specification V1.1b.

2. Operator workstations and network controllers shall communicate through ASHRAE 135 or CEA-709.1-C protocol.

3. Portions of DDC system networks using ASHRAE 135 communication protocol shall be an open implementation of network devices complying with ASHRAE 135. Network devices shall be tested and listed by BACnet Testing Laboratories.

4. Portions of DDC system networks using CEA-709.1-C communication protocol shall be an open implementation of LonWorks technology using CEA-709.1-C communication protocol and using LonMark SNVTs as defined in LonMark SNVT list exclusively for DDC system.

5. Portions of DDC system networks using Modbus Application Protocol Specification V1.1b communication protocol shall be an open implementation of network devices and technology complying with Modbus Application Protocol Specification V1.1b.

6. Gateways shall be used to connect networks and network devices using different protocols.

Page 60: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 25

2.10 DDC SYSTEM WIRELESS NETWORKS

A. Use Zigbee or an open industry standard and technology used by multiple DDC system manufacturers technology to create a wireless mesh network to provide wireless connectivity for network devices at multiple system levels including communications from programmable application controllers and application-specific controllers to temperature sensors and from network controllers to programmable application controllers and application-specific controllers.

B. Installer shall design wireless networks to comply with DDC system performance requirements indicated. Wireless network devices shall co-exist on same network with hardwired devices.

C. Hardwired controllers shall be capable of retrofit to wireless devices with no special software.

D. A wireless coordinator shall provide a wireless interface between programmable application controllers, application-specific controllers, and network controllers.

E. Wireless Coordinators:

1. Each wireless mesh network shall use wireless coordinator(s) for initiation and formation of network.

2. Use direct sequence spread spectrum RF technology.3. Operate on the 2.4-GHz ISM Band.4. Comply with IEEE 802.15.4 for low-power, low duty-cycle RF transmitting systems.5. FCC compliant to 47 CFR 15, Subpart B, Class A.6. Operate as a bidirectional transceiver with sensors and routers to confirm and synchronize data

transmission.7. Capable of communication with sensors and routers up to a maximum distance of 250 feet in line of

sight.8. Include visual indicators to provide diagnostic information required for operator verification of

operation.

F. Wireless Routers:

1. Each wireless mesh network shall use wireless routers with any controller to provide a wireless interface to a network controller, through a wireless coordinator.

2. Use direct sequence spread spectrum RF technology.3. Operate on the 2.4-GHz ISM Band.4. Comply with IEEE 802.15.4 for low-power, low duty-cycle RF transmitting systems.5. FCC compliant to 47 CFR 15, Subpart B, Class A.6. Operate as a bidirectional transceiver with other mesh network devices to ensure network integrity.7. Capable of communication with other mesh network devices at a maximum distance of 250 feet in

line of sight.8. Include indication for use in commissioning and troubleshooting.

G. Wireless Temperature Sensors:

1. Wireless temperature sensors shall sense and transmit room temperatures, temperature set point, room occupancy notification and low battery condition to an associated router.

2. Use direct sequence spread spectrum RF technology.3. Operate on the 2.4-GHz ISM Band.4. Comply with IEEE 802.15.4 for low-power, low duty-cycle RF transmitting systems.5. FCC compliant to CFR 15, Subpart B, Class A.6. Include set point adjustment between 55 to 85 deg F.7. Multiple sensors shall be able to report to a router connected to a DDC controller for averaging or

high and low selection.

H. One-to-One Wireless Network Receivers:

Page 61: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 26

1. One-to-one wireless receivers shall receive wireless RF signals containing temperature data from multiple wireless room temperature sensors and communicate information to programmable application controllers or application-specific controllers.

a. Use direct sequence spread spectrum RF technology.b. Operate on the 2.4-GHz ISM Band.c. Comply with IEEE 802.15.4 for low-power, low duty-cycle RF transmitting systems.d. FCC compliant to 47 CFR 15, Subpart B, Class A.e. Operate as a bidirectional transceiver with the sensors to confirm and synchronize data

transmission.f. Capable of communication up to a distance of 200 feet.g. Include visual indication of the following:

1) Power.2) Receiver activity.3) Wireless RF transmission from wireless sensors.4) No transmission, weak signal, adequate signal or excellent signal.

I. One-to-One Wireless Network Sensors:

1. One-to-one wireless sensors shall sense and report room temperatures to one-to-one receiver.

a. Use direct sequence spread spectrum RF technology.b. Operate on the 2.4-GHz ISM Band.c. Comply with IEEE 802.15.4 for low-power, low duty-cycle RF transmitting systems.d. FCC compliant to CFR 15, Subpart B, Class A.e. Include set point adjustment between 55 to 85 deg F.

2.11 DESKTOP WORKSTATIONS

A. Description: A tower or all-in-one computer designed for normal use at a single, semipermanent location.

B. Approved manufacturers:1. Dell2. Lenovo3. Hewlwtt-Packard4. Approved equivalent

C. Performance Requirements:

1. Performance requirements may dictate equipment exceeding minimum requirements indicated.2. Energy Star compliant.

D. Personal Computer:1. RAM:

a. Capacity: 8 GB.b. Speed and Type: 1333 MHz.

2. Hard Drive:

a. Media: Solid stateb. Number of Hard Drives: Two.c. Capacity: 4 TB.

3. Second Hard Drive:

a. Media: Solid state..

Page 62: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 27

b. Capacity: 4TB

c. Average access time of 150 ms or less.d. MTBF of at least 100,000 power-on hours.

4. At least four expansion slots of 64 bit.5. Video Card:

a. Resolution: 1920 by 1200 pixels.

6. Sound Card:

a. At least 128 voice wavetable synthesis.b. Capable of delivering three-dimensional sound effects.c. High-resolution 16-bit stereo digital audio recording and playback with user-selectable

sample rates up to 48,000 Hz.

7. Network Interface Card: Include card with connection, as applicable.

a. 10-100-1000 base TX Ethernet with RJ45 connector port.b. 100 base FX Ethernet with SC or ST port.

E. Wireless Ethernet, 802.11 a/b/g/n.

1. Optical Modem: Full duplex link for connection to optical fiber cable provided.2. I/O Ports:

a. Two USB 3.0 ports on front panel, six on back panel, and three internal on motherboard.b. One serial port.c. One parallel port.d. Two PS/2 ports.e. One RJ-45.f. One stereo line-in and headphone/line-out on back panel.g. One microphone and headphone connector on front panel.h. One IEEE 1394 on front and back panel with PCI-e card.i. One ESATA port on back panel.

3. Battery: Life of at least three years to maintain system clock/calendar and ROM, as a minimum.

F. Keyboard:

1. 101 enhanced keyboard.2. Full upper- and lowercase ASCII keyset, numeric keypad, dedicated cursor control keypad, and 12

programmable function keys.3. Wireless operation within up to 72 inches in front of workstation.

G. Pointing Device:

1. Either a two- or three-button mouse.2. Wireless operation within up to 72 inches in front of workstation.

H. Flat Panel Display Monitor:

1. Display:

a. Color display with 18 inch diagonal viewable area.b. Digital input signal.c. Aspect Ratio: 16 to 9.d. Antiglare display.

Page 63: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 28

e. Dynamic Contrast Ratio: 50000 to 1.f. Brightness: 250 cd/sq. m.g. Tilt adjustable base.h. Energy Star compliant.i. Resolution: 1920 by 1080 pixels at 60 Hz with pixel size of 0.277 or smaller.j. Number of Displays: One..

I. Speakers:

1. Two, with individual controls for volume, bass and treble.2. Signal to Noise Ratio: At least 65 dB.3. Power: At least 4 W per speaker/channel.4. Magnetic shielding to prevent distortion on the video monitor.

J. I/O Cabling: Include applicable cabling to connect I/O devices.

2.12 PORTABLE WORKSTATIONS

A. Description: A self-contained computer designed to allow for normal use in different locations and conditions.

B. Approved manufacturers:1. Dell2. Lenovo3. Hewlwtt-Packard4. Approved equivalent

C. Performance Requirements:

1. Performance requirements may dictate equipment exceeding minimum requirements indicated.2. Energy Star compliant.3. Hardware and software shall support local down-loading to DDC controllers.4. Data transfer rate to DDC controller shall be at network speed.

D. Processor:1. RAM:

a. Capacity: 600 GB.

2. Hard Drive:

a. Number of Hard Drives: One.b. Capacity: 250 GB.

E. Input and Output Ports:

1. Serial port.2. Shared port for external keyboard or mouse.3. Four USB 3.0 ports.4. Ethernet port.5. HDMI port.6. IEEE 1394 port.

F. Battery:

1. Capable of supporting operation of portable workstation for a minimum of 8 hours.2. Battery life of at least three years.3. Battery charge time of less than three hours.

Page 64: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 29

4. Spare Battery. One.

G. Keyboard:

1. 85-key backlit ]keyboard.2. Full upper- and lowercase ASCII keyset.

H. Integral Pointing Device: Touchpad with two buttons. Gesture enabled.

I. Display:

1. High-definition WLED color display.2. Antiglare screen.3. 1920 by 1080 pixel resolution.4. Brightness: 300 nits.

J. Network Interfaces:

1. Network Interface Card: Include card with connection, as application.

a. 10-100-1000 base TX Ethernet with RJ45 connector port.b. 100 base FX Ethernet with SC or ST port.

2. Wireless:

a. Internal with integrated antenna, capable of supporting 802.11 a/b/g/n.

K. Digital Video Disc Rewrite Recorder (DVD+/-RW):

1. Compatible with DVD disks and data, audio, recordable and rewritable compact disks.2. Nominal Data Transfer Rates:

3. 160-ms access time.

L. Accessories:

1. Nylon carrying case.2. Docking station.3. Mobile broadband card.4. Wireless optical mouse.5. Light-sensitive web cam and noise-cancelling digital array microphone.6. Category 6a patch cable. Minimum cable length shall be 6 feet.7. HDMI cable. Minimum cable length shall be 6 feet.

2.13 PORTABLE OPERATOR TERMINAL

A. Description: Handheld device with integral keypad or touch screen operator interface.

B. Display: Multiple lines of text display for use in operator interaction with DDC system.

C. Cable: Flexible coiling cable, at least 36 inches long, with a plug-in jack for connection to DDC controllers, network ports or instruments with an integral LAN port. As an alternative to hardwired connection, POT shall be accessible to DDC controllers through a wireless network connection.

D. POT shall be powered through network connection.

Page 65: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 30

E. Connection of POT to DDC system shall not interrupt or interfere with normal network operation in any way, prevent alarms from being transmitted, or preclude central initiated commands and system modification.

F. POT shall give operator the ability to do the following:

1. Display and monitor BI point status.2. Change BO point set point (on or off, open or closed).3. Display and monitor analog point values.4. Change analog control set points.5. Command a setting of AO point.6. Display and monitor I/O point in alarm.7. Add a new or delete an existing I/O point.8. Enable and disable I/O points, initiators, and programs.9. Display and change time and date.10. Display and change time schedules.11. Display and change run-time counters and run-time limits.12. Display and change time and event initiation.13. Display and change control application and DDC parameters.14. Display and change programmable offset values.15. Access DDC controller initialization routines and diagnostics.

2.14 SYSTEM SOFTWARE

A. System Software Minimum Requirements:

1. Real-time multitasking and multiuser 64-bit operating system that allows concurrent multiple operator workstations operating and concurrent execution of multiple real-time programs and custom program development.

2. Operating system shall be capable of operating DOS and Microsoft Windows applications.3. Database management software shall manage all data on an integrated and non-redundant basis.

Additions and deletions to database shall be without detriment to existing data. Include cross linkages so no data required by a program can be deleted by an operator until that data have been deleted from respective programs.

4. Network communications software shall manage and control multiple network communications to provide exchange of global information and execution of global programs.

5. Operator interface software shall include day-to-day operator transaction processing, alarm and report handling, operator privilege level and data segregation control, custom programming, and online data modification capability.

6. Scheduling software shall schedule centrally based time and event, temporary, and exception day programs.

B. Operator Interface Software:

1. Minimize operator training through use of English language prorating and English language point identification.

2. Minimize use of a typewriter-style keyboard through use of a pointing device similar to a mouse.3. Operator sign-off shall be a manual operation or, if no keyboard or mouse activity takes place, an

automatic sign-off.4. Automatic sign-off period shall be programmable from one to 60 minutes in one-minute increments

on a per operator basis.5. Operator sign-on and sign-off activity shall be recorded and sent to printer.6. Security Access:

a. Operator access to DDC system shall be under password control.b. An alphanumeric password shall be field assignable to each operator.c. Operators shall be able to access DDC system by entry of proper password.d. Operator password shall be same regardless of which computer or other interface means is

used.e. Additions or changes made to passwords shall be updated automatically.

Page 66: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 31

f. Each operator shall be assigned an access level to restrict access to data and functions the operator is cable of performing.

g. Software shall have at least five access levels.h. Each menu item shall be assigned an access level so that a one-for-one correspondence

between operator assigned access level(s) and menu item access level(s) is required to gain access to menu item.

i. Display menu items to operator with those capable of access highlighted. Menu and operator access level assignments shall be online programmable and under password control.

7. Data Segregation:

a. Include data segregation for control of specific data routed to a workstation, to an operator or to a specific output device, such as a printer.

b. Include at least 32 segregation groups.c. Segregation groups shall be selectable such as "fire points," "fire points on second floor,"

"space temperature points," "HVAC points," and so on.d. Points shall be assignable to multiple segregation groups. Display and output of data to

printer or monitor shall occur where there is a match of operator or peripheral segregation group assignment and point segregations.

e. Alarms shall be displayed and printed at each peripheral to which segregation allows, but only those operators assigned to peripheral and having proper authorization level will be allowed to acknowledge alarms.

f. Operators and peripherals shall be assignable to multiple segregation groups and all assignments are to be online programmable and under password control.

8. Operators shall be able to perform commands including, but not limited to, the following:

a. Start or stop selected equipment.b. Adjust set points.c. Add, modify, and delete time programming.d. Enable and disable process execution.e. Lock and unlock alarm reporting for each point.f. Enable and disable totalization for each point.g. Enable and disable trending for each point.h. Override control loop set points.i. Enter temporary override schedules.j. Define holiday schedules.k. Change time and date.l. Enter and modify analog alarm limits.m. Enter and modify analog warning limits.n. View limits.o. Enable and disable demand limiting.p. Enable and disable duty cycle.q. Display logic programming for each control sequence.

9. Reporting:

a. Generated automatically and manually.b. Sent to displays, printers and disk files.c. Types of Reporting:

1) General listing of points.2) List points currently in alarm.3) List of off-line points.4) List points currently in override status.5) List of disabled points.6) List points currently locked out.7) List of items defined in a "Follow-Up" file.8) List weekly schedules.9) List holiday programming.

Page 67: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 32

10) List of limits and deadbands.

10. Summaries: For specific points, for a logical point group, for an operator selected group(s), or for entire system without restriction due to hardware configuration.

C. Graphic Interface Software:

1. Include a full interactive graphical selection means of accessing and displaying system data to operator. Include at least five levels with the penetration path operator assignable (for example, site, building, floor, air-handling unit, and supply temperature loop). Native language descriptors assigned to menu items are to be operator defined and modifiable under password control.

2. Include a hierarchical-linked dynamic graphic operator interface for accessing and displaying system data and commanding and modifying equipment operation. Interface shall use a pointing device with pull-down or penetrating menus, color and animation to facilitate operator understanding of system.

3. Include at least 10 levels of graphic penetration with the hierarchy operator assignable.4. Descriptors for graphics, points, alarms and such shall be modified through operator's workstation

under password control.5. Graphic displays shall be online user definable and modifiable using the hardware and software

provided.6. Data to be displayed within a graphic shall be assignable regardless of physical hardware address,

communication or point type.7. Graphics are to be online programmable and under password control.8. Points may be assignable to multiple graphics where necessary to facilitate operator understanding

of system operation.9. Graphics shall also contain software points.10. Penetration within a graphic hierarchy shall display each graphic name as graphics are selected to

facilitate operator understanding.11. Back-trace feature shall permit operator to move upward in the hierarchy using a pointing device.

Back trace shall show all previous penetration levels. Include operator with option of showing each graphic full screen size with back trace as horizontal header or by showing a "stack" of graphics, each with a back trace.

12. Display operator accessed data on the monitor.13. Operator shall select further penetration using pointing device to click on a site, building, floor, area,

equipment, and so on. Defined and linked graphic below that selection shall then be displayed.14. Include operator with means to directly access graphics without going through penetration path.15. Dynamic data shall be assignable to graphics.16. Display points (physical and software) with dynamic data provided by DDC system with appropriate

text descriptors, status or value, and engineering unit.17. Use color, rotation, or other highly visible means, to denote status and alarm states. Color shall be

variable for each class of points, as chosen by operator.18. Points shall be dynamic with operator adjustable update rates on a per point basis from one

second to over a minute.19. For operators with appropriate privilege, points shall be commanded directly from display using

pointing device.

a. For an analog command point such as set point, current conditions and limits shall be displayed and operator can position new set point using pointing device.

b. For a digital command point such as valve position, valve shall show its current state such as open or closed and operator could select alternative position using pointing device.

c. Keyboard equivalent shall be available for those operators with that preference.

20. Operator shall be able to split or resize viewing screen into quadrants to show one graphic on one quadrant of screen and other graphics or spreadsheet, bar chart, word processing, curve plot and other information on other quadrants on screen. This feature shall allow real-time monitoring of one part of system while displaying other parts of system or data to better facilitate overall system operation.

21. Help Features:

a. On-line context-sensitive help utility to facilitate operator training and understanding.

Page 68: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 33

b. Bridge to further explanation of selected keywords. Document shall contain text and graphics to clarify system operation.

1) If help feature does not have ability to bridge on keywords for more information, a complete set of user manuals shall be provided in an indexed word-processing program, which shall run concurrently with operating system software.

c. Available for Every Menu Item:

1) Index items for each system menu item.

22. Graphic generation software shall allow operator to add, modify, or delete system graphic displays.

a. Include libraries of symbols depicting HVAC symbols such as fans, coils, filters, dampers, valves pumps, and electrical symbols similar to those indicated.

b. Graphic development package shall use a pointing device in conjunction with a drawing program to allow operator to perform the following:

1) Define background screens.2) Define connecting lines and curves.3) Locate, orient and size descriptive text.4) Define and display colors for all elements.5) Establish correlation between symbols or text and associated system points or other

displays.

D. Project-Specific Graphics: Graphics documentation including, but not limited to, the following:

1. Site plan showing each building, and additional site elements, which are being controlled or monitored by DDC system.

2. Plan for each building floor, including interstitial floors, and each roof level of each building, showing the following:

a. Room layouts with room identification and name.b. Locations and identification of all monitored and controlled HVAC equipment and other

equipment being monitored and controlled by DDC system.c. Location and identification of each hardware point being controlled or monitored by DDC

system.

3. Control schematic for each of following, including a graphic system schematic representation, similar to that indicated on Drawings, with point identification, set point and dynamic value indication, sequence of operation and control logic diagram.

4. Graphic display for each piece of equipment connected to DDC system through a data communications link. Include dynamic indication of all points associated with equipment.

5. DDC system network riser diagram that shows schematic layout for entire system including all networks and all controllers, gateways, operator workstations,and, other network devices.

E. Customizing Software:

1. Software to modify and tailor DDC system to specific and unique requirements of equipment installed, to programs implemented and to staffing and operational practices planned.

2. Online modification of DDC system configuration, program parameters, and database using menu selection and keyboard entry of data into preformatted display templates.

3. As a minimum, include the following modification capability:

a. Operator assignment shall include designation of operator passwords, access levels, point segregation and auto sign-off.

b. Peripheral assignment capability shall include assignment of segregation groups and operators to consoles and printers, designation of backup workstations and printers, designation of workstation header points and enabling and disabling of print-out of operator changes.

Page 69: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 34

c. System configuration and diagnostic capability shall include communications and peripheral port assignments, DDC controller assignments to network, DDC controller enable and disable, assignment of command trace to points and application programs and initiation of diagnostics.

d. System text addition and change capability shall include English or native language descriptors for points, segregation groups and access levels and action messages for alarms, run time and trouble condition.

e. Time and schedule change capability shall include time and date set, time and occupancy schedules, exception and holiday schedules and daylight savings time schedules.

f. Point related change capability shall include the following:

1) System and point enable and disable.2) Run-time enable and disable.3) Assignment of points to segregation groups, calibration tables, lockout, and run time

and to a fixed I/O value.4) Assignment of alarm and warning limits.

g. Application program change capability shall include the following:

1) Enable and disable of software programs.2) Programming changes.3) Assignment of comfort limits, global points, time and event initiators, time and event

schedules and enable and disable time and event programs.

4. Software shall allow operator to add points, or groups of points, to DDC system and to link them to energy optimization and management programs. Additions and modifications shall be online programmable using operator workstation, downloaded to other network devices and entered into their databases. After verification of point additions and associated program operation, database shall be uploaded and recorded on hard drive and disk for archived record.

5. Include high-level language programming software capability for implementation of custom DDC programs. Software shall include a compiler, linker, and up- and down-load capability.

6. Include a library of DDC algorithms, intrinsic control operators, arithmetic, logic and relational operators for implementation of control sequences. Also include, as a minimum, the following:

a. Proportional control (P).b. Proportional plus integral (PI).c. Proportional plus integral plus derivative (PID).d. Adaptive and intelligent self-learning control.

1) Algorithm shall monitor loop response to output corrections and adjust loop response characteristics according to time constant changes imposed.

2) Algorithm shall operate in a continuous self-learning manner and shall retain in memory a stored record of system dynamics so that on system shut down and restart, learning process starts from where it left off.

7. Fully implemented intrinsic control operators including sequence, reversing, ratio, time delay, time of day, highest select AO, lowest select AO, analog controlled digital output, analog control AO, and digitally controlled AO.

8. Logic operators such as "And," "Or," "Not," and others that are part of a standard set available with a high-level language.

9. Arithmetic operators such as "Add," "Subtract," "Multiply," "Divide," and others that are part of a standard set available with a high-level language.

10. Relational operators such as "Equal To," "Not Equal To," "Less Than," "Greater Than," and others that are part of a standard set available with a high-level language.

F. Alarm Handling Software:

1. Include alarm handling software to report all alarm conditions monitored and transmitted through DDC controllers, gateways, and other network devices.

2. Include first in, first out handling of alarms according to alarm priority ranking, with most critical alarms first, and with buffer storage in case of simultaneous and multiple alarms.

Page 70: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 35

3. Alarm handling shall be active at all times to ensure that alarms are processed even if an operator is not currently signed on to DDC system.

4. Alarms display shall include the following:

a. Indication of alarm condition such as "Abnormal Off," "Hi Alarm," and "Low Alarm."b. "Analog Value" or "Status" group and point identification with native language point

descriptor such as "Space Temperature, Building 110, 2nd Floor, Room 212."c. Discrete per point alarm action message, such as "Call Maintenance Dept. Ext-5561."d. Include extended message capability to allow assignment and printing of extended action

messages. Capability shall be operator programmable and assignable on a per point basis.

5. Alarms shall be directed to appropriate operator workstations, printers, and individual operators by privilege level and segregation assignments.

6. Send e-mail alarm messages to designated operators.7. Send e-mail, page, text and voice messages to designated operators for critical alarms.8. Alarms shall be categorized and processed by class.

a. Class 1:

1) Associated with fire, security and other extremely critical equipment monitoring functions; have alarm, trouble, return to normal, and acknowledge conditions printed and displayed.

2) Unacknowledged alarms to be placed in unacknowledged alarm buffer.3) All conditions shall cause an audible sound and shall require individual

acknowledgment to silence audible sound.

b. Class 2:

1) Critical, but not life-safety related, and processed same as Class 1 alarms, except do not require individual acknowledgment.

2) Acknowledgement may be through a multiple alarm acknowledgment.

c. Class 3:

1) General alarms; printed, displayed and placed in unacknowledged alarm buffer queues.

2) Each new alarm received shall cause an audible sound. Audible sound shall be silenced by "acknowledging" alarm or by pressing a "silence" key.

3) Acknowledgement of queued alarms shall be either on an individual basis or through a multiple alarm acknowledgement.

4) Alarms returning to normal condition shall be printed and not cause an audible sound or require acknowledgment.

d. Class 4:

1) Routine maintenance or other types of warning alarms.2) Alarms to be printed only, with no display, no audible sound and no acknowledgment

required.

9. Include an unacknowledged alarm indicator on display to alert operator that there are unacknowledged alarms in system. Operator shall be able to acknowledge alarms on an individual basis or through a multiple alarm acknowledge key, depending on alarm class.

10. To ensure that no alarm records are lost, it shall be possible to assign a backup printer to accept alarms in case of failure of primary printer.

G. Reports and Logs:

1. Include reporting software package that allows operator to select, modify, or create reports using DDC system I/O point data available.

2. Each report shall be definable as to data content, format, interval and date.

Page 71: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 36

3. Report data shall be sampled and stored on DDC controller, within storage limits of DDC controller, and then uploaded to archive on workstation for historical reporting.

4. Operator shall be able to obtain real-time logs of all I/O points by type or status, such as alarm, point lockout, or normal.

5. Reports and logs shall be stored on workstation hard drives in a format that is readily accessible by other standard software applications, including spreadsheets and word processing.

6. Reports and logs shall be readily printed and set to be printed either on operator command or at a specific time each day.

H. Standard Reports: Standard DDC system reports shall be provided and operator shall be able to customize reports later.

1. All I/O: With current status and values.2. Alarm: All current alarms, except those in alarm lockout.3. Disabled I/O: All I/O points that are disabled.4. Alarm Lockout I/O: All I/O points in alarm lockout, whether manual or automatic.5. Alarm Lockout I/O in Alarm: All I/O in alarm lockout that are currently in alarm.6. Logs:

a. Alarm history.b. System messages.c. System events.d. Trends.

I. Custom Reports: Operator shall be able to easily define any system data into a daily, weekly, monthly, or annual report. Reports shall be time and date stamped and shall contain a report title.

J. Tenant Override Reports: Prepare Project-specific reports.

1. Weekly report showing daily total time in hours that each tenant has requested after-hours HVAC.2. Monthly report showing daily total time in hours that each tenant has requested after-hours HVAC.3. Annual summary report that shows after-hours HVAC usage on a monthly basis.

K. HVAC Equipment Reports: Prepare Project-specific reports.

1. Chiller Report: Daily report showing operating conditions of each chiller according to ASHRAE 147, including, but not limited to, the following:

a. Chilled-water entering temperature.b. Chilled-water leaving temperature.c. Chilled-water flow rate.d. Chilled-water inlet and outlet pressures.e. Evaporator refrigerant pressure and temperature.f. Condenser refrigerant pressure and liquid temperature.g. Condenser-water entering temperature.h. Condenser-water leaving temperature.i. Condenser-water flow rate.j. Refrigerant levels.k. Oil pressure and temperature.l. Oil level.m. Compressor refrigerant discharge temperature.n. Compressor refrigerant suction temperature.o. Addition of refrigerant.p. Addition of oil.q. Vibration levels or observation that vibration is not excessive.r. Motor amperes per phase.s. Motor volts per phase.t. Refrigerant monitor level (PPM).u. Purge exhaust time or discharge count.v. Ambient temperature (dry bulb and wet bulb).w. Date and time logged.

Page 72: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 37

L. Utility Reports: Prepare Project-specific reports.

1. Electric Report:

a. Include weekly report showing daily electrical consumption and peak electrical demand with time and date stamp for each meter.

b. Include monthly report showing the daily electrical consumption and peak electrical demand with time and date stamp for each meter.

c. Include annual report showing the monthly electrical consumption and peak electrical demand with time and date stamp for each meter.

d. For each weekly, monthly and annual report, include sum total of submeters combined by load type, such as lighting, receptacles and HVAC equipment showing daily electrical consumption and peak electrical demand.

e. For each weekly, monthly and annual report, include sum total of all submeters in building showing electrical consumption and peak electrical demand.

2. Natural Gas Report:

a. Include weekly report showing daily natural gas consumption and peak natural gas demand with time and date stamp for each meter.

b. Include monthly report showing the daily natural gas consumption and peak natural gas demand with time and date stamp for each meter.

c. Include annual report showing the monthly natural gas consumption and peak natural gas demand with time and date stamp for each meter.

d. For each weekly, monthly and annual report, include sum total of submeters combined by load type, such as boilers and service water heaters showing daily natural gas consumption and peak natural gas demand.

e. For each weekly, monthly and annual report, include sum total of all submeters in building showing natural gas consumption and peak natural gas demand.

3. Service Water Report:

a. Include weekly report showing daily service water consumption and peak service water demand with time and date stamp for each meter.

b. Include monthly report showing the daily service water consumption and peak service water demand with time and date stamp for each meter.

c. Include annual report showing the monthly service water consumption and peak service water demand with time and date stamp for each meter.

d. For each weekly, monthly and annual report, include sum total of submeters combined by load type, such as cooling tower makeup and irrigation showing daily service water consumption and peak service water demand.

e. For each weekly, monthly and annual report, include sum total of all submeters in building showing service water consumption and peak service water demand.

M. Energy Reports: Prepare Project-specific daily, weekly, monthly, annual and since-installed energy reports.

1. Prepare report for each purchased energy utility, indicating the following:

a. Time period being reported with beginning and end date, and time indicated.b. Consumption in units of measure commonly used to report specific utility consumption over

time.c. Gross area served by utility.d. Consumption per unit area served using utility-specific unit of measure.e. Cost per utility unit.f. Utility cost per unit area.g. Convert all utilities to a common energy consumption unit of measure and report for each

utility.h. Consumption per unit area using common unit of measure.

2. Prepare report for each renewable energy source, indicating the following:

Page 73: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 38

a. Time period being reported with beginning and end date, and time indicated.b. Harvested energy in units of measure commonly used to report specific harvested energy

consumption over time.c. Gross area served by renewable energy source.d. Harvested energy per unit area served using specific unit of measure.e. Cost per purchased utility unit displaced by renewable energy.f. Cost savings attributed to harvested energy source.g. Cost savings per unit area attributed to harvested energy.h. Convert all renewable energy sources to a common energy consumption unit of measure

and report for each.i. Harvested energy per unit area using common unit of measure.

3. Prepare purchased energy utility report for each submetered area that indicates the following:

a. Time period being reported with beginning and end date, and time indicated.b. Gross area served.c. Energy consumption by energy utility type.d. Energy consumption per unit area by energy utility type.e. Total energy consumption of all utilities in common units of measure.f. Total energy consumption of all utilities in common units of measure per unit area.g. Unit energy cost by energy utility type.h. Energy cost by energy utility type.i. Energy cost per unit area by energy utility type.j. Total cost of all energy utilities.k. Total cost of all energy utilities per unit area.

4. Prepare Project total purchased energy utility report that combines all purchased energy utilities and all areas served. Project total energy report shall indicate the following:

a. Time period being reported with beginning and end date, and time indicated.b. Gross area served.c. Energy consumption by energy utility type.d. Energy consumption per unit area by energy utility type.e. Total energy consumption of all utilities in common units of measure.f. Total energy consumption of all utilities in common units of measure per unit area.g. Unit energy cost by energy utility type.h. Energy cost by energy utility type.i. Energy cost per unit area by energy utility type.j. Total cost of all energy utilities.k. Total cost of all energy utilities per unit area.

N. HVAC System Efficiency Reports: Prepare Project-specific daily, weekly, monthly, annual and since-installed HVAC system efficiency reports.

1. Prepare report for each chilled-water system, indicating the following:

a. Time period being reported with beginning and end date, and time indicated.b. Cooling energy supplied during time period.c. Power energy consumed during time period by cooling equipment used to produce cooling

energy supplied. List power consumed for each individual piece of equipment in system and summed total of all equipment in system.

d. Energy efficiency coefficient of performance determined by dividing power energy consumed into cooling energy supplied.

e. Energy efficiency determined by dividing cooling energy supplied into power energy consumed.

f. Units of measure used in report shall be consistent with units indicated for system.

2. Prepare report for each condenser-water system, indicating the following:

a. Time period being reported with beginning and end date, and time indicated.b. Cooling tower energy supplied during time period.

Page 74: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 39

c. Energy efficiency determined by dividing heating energy supplied into fuel energy consumed.

d. Units of measure used in report shall be consistent with units indicated for system.

O. Weather Reports:

1. Include daily report showing the following:

a. Daily minimum, maximum, and average outdoor dry-bulb temperature.b. Daily minimum, maximum, and average outdoor wet-bulb temperature.c. Daily minimum, maximum, and average outdoor dew point temperature.d. Number of heating degree-days for each day calculated from a base temperature of 55

deg F.e. Number of cooling degree-days for each day calculated from a base temperature of 65

deg Ff. Daily minimum, maximum, and average outdoor carbon dioxide level.g. Daily minimum, maximum, and average relative humidity.h. Daily minimum, maximum, and average barometric pressure.i. Daily minimum, maximum, and average wind speed and direction.

2. Include weekly report showing the following:

a. Daily minimum, maximum, and average outdoor dry-bulb temperature.b. Daily minimum, maximum, and average outdoor wet-bulb temperature.c. Daily minimum, maximum, and average outdoor dew point temperature.d. Number of heating degree-days for each day calculated from a base temperature of 55

deg F.e. Number of cooling degree-days for each day calculated from a base temperature of 65

deg F.f. Weekly minimum, maximum, and average outdoor carbon dioxide level.g. Daily minimum, maximum, and average relative humidity.h. Daily minimum, maximum, and average barometric pressure.i. Daily minimum, maximum, and average wind speed and direction.

3. Include monthly report showing the following:

a. Daily minimum, maximum, and average outdoor dry-bulb temperature.b. Daily minimum, maximum, and average outdoor wet-bulb temperature.c. Daily minimum, maximum, and average outdoor dew point temperature.d. Number of heating degree-days for each day calculated from a base temperature of 55

deg F.e. Number of cooling degree-days for each day calculated from a base temperature of 65

deg F.f. Monthly minimum, maximum, and average outdoor carbon dioxide level.g. Daily minimum, maximum, and average relative humidity.h. Daily minimum, maximum, and average barometric pressure.i. Daily minimum, maximum, and average wind speed and direction.

4. Include annual (12-month) report showing the following:

a. Monthly minimum, maximum, and average outdoor dry-bulb temperature.b. Monthly minimum, maximum, and average outdoor wet-bulb temperature.c. Monthly minimum, maximum, and average outdoor dew point temperature.d. Number of heating degree-days for each month calculated from a base temperature of 55

deg F.e. Number of cooling degree-days for each month calculated from a base temperature of 65

deg F.f. Annual minimum, maximum, and average outdoor carbon dioxide level.g. Monthly minimum, maximum, and average relative humidity.h. Daily minimum, maximum, and average barometric pressure.i. Daily minimum, maximum, and average wind speed and direction.

Page 75: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 40

P. Standard Trends:

1. Trend all I/O point present values, set points, and other parameters indicated for trending.2. Trends shall be associated into groups, and a trend report shall be set up for each group.3. Trends shall be stored within DDC controller and uploaded to hard drives automatically on reaching

75 of DDC controller buffer limit, or by operator request, or by archiving time schedule.4. Preset trend intervals for each I/O point after review with Owner.5. Trend intervals shall be operator selectable from 10 seconds up to 60 minutes. Minimum number of

consecutive trend values stored at one time shall be 100 per variable.6. When drive storage memory is full, most recent data shall overwrite oldest data.7. Archived and real-time trend data shall be available for viewing numerically and graphically by

operators.

Q. Custom Trends: Operator shall be able to define a custom trend log for any I/O point in DDC system.

1. Each trend shall include interval, start time, and stop time.2. Data shall be sampled and stored on DDC controller, within storage limits of DDC controller, and

then uploaded to archive on workstation hard drives.3. Data shall be retrievable for use in spreadsheets and standard database programs.

R. Programming Software:

1. Include programming software to execute sequences of operation indicated.2. Include programming routines in simple and easy to follow logic with detailed text comments

describing what the logic does and how it corresponds to sequence of operation.3. Programming software shall be as follows:

a. Graphic Based: Programming shall use a library of function blocks made from preprogrammed code designed for DDC control systems.

1) Function blocks shall be assembled with interconnection lines that represent to control sequence in a flowchart.

2) Programming tools shall be viewable in real time to show present values and logical results of each function block.

b. Menu Based: Programming shall be done by entering parameters, definitions, conditions, requirements and constraints.

c. Line by Line and Text Based: Programming shall declare variable types such as local, global, real, integer, and so on, at the beginning of the program. Use descriptive comments frequently to describe programming code.

4. Include means for detecting programming errors and testing software control strategies with a simulation tool before implementing in actual control. Simulation tool may be inherent with programming software or as a separate product.

S. Database Management Software:

1. Where a separate SQL database is used for information storage, DDC system shall include database management software that separates database monitoring and managing functions by supporting multiple separate windows.

2. Database secure access shall be accomplished using standard SQL authentication including ability to access data for use outside of DDC system applications.

3. Database management function shall include summarized information on trend, alarm, event, and audit for the following database management actions:

a. Backup.b. Purge.c. Restore.

4. Database management software shall support the following:

Page 76: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 41

a. Statistics: Display database server information and trend, alarm, event, and audit information on database.

b. Maintenance: Include method of purging records from trend, alarm, event and audit databases by supporting separate screens for creating a backup before purging, selecting database, and allowing for retention of a selected number of day's data.

c. Backup: Include means to create a database backup file and select a storage location.d. Restore: Include a restricted means of restoring a database by requiring operator to have

proper security level.

5. Database management software shall include information of current database activity, including the following:

a. Ready.b. Purging record from a database.c. Action failed.d. Refreshing statistics.e. Restoring database.f. Shrinking a database.g. Backing up a database.h. Resetting Internet information services.i. Starting network device manager.j. Shutting down the network device manager.k. Action successful.

6. Database management software monitoring functions shall continuously read database information once operator has logged on.

7. Include operator notification through on-screen pop-up display and e-mail message when database value has exceeded a warning or alarm limit.

8. Monitoring settings window shall have the following sections:

a. Allow operator to set and review scan intervals and start times.b. E-mail: Allow operator to create and review e-mail and phone text messages to be delivered

when a warning or an alarm is generated.c. Warning: Allow operator to define warning limit parameters, set reminder frequency and link

e-mail message.d. Alarm: Allow operator to define alarm limit parameters, set reminder frequency and link e-

mail message.e. Database Login: Protect system from unauthorized database manipulation by creating a

read access and a write access for each of trend, alarm, event and audit databases as well as operator proper security access to restore a database.

9. Monitoring settings taskbar shall include the following informational icons:

a. Normal: Indicates by color and size, or other easily identifiable means that all databases are within their limits.

b. Warning: Indicates by color and size, or other easily identifiable means that one or more databases have exceeded their warning limit.

c. Alarm: Indicates by color and size, or other easily identifiable means that one or more databases have exceeded their alarm limit.

2.15 OFFICE APPLICATION SOFTWARE

A. Approved manufacturer: Microsoft

B. Include current version of office application software at time of Substantial Completion.

C. Office application software package shall include multiple separate applications and use a common platform for all applications, similar to Microsoft's "Office Professional."

Page 77: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 42

1. Database.2. E-mail.3. Presentation.4. Publisher.5. Spreadsheet.6. Word processing.

2.16 MAINTENANCE MANAGEMENT SOFTWARE

A. Scope:

1. Include complete and functional software-driven maintenance management system. Software shall perform scheduling of preventive maintenance and generation of work orders, for mechanical and electrical equipment and systems.

2. Work orders shall be automatically generated from alarm conditions, run time, and calendar time. Each work order generated shall list parts, tools, craftspeople, and define task to be performed.

3. Work order generated shall be used to schedule a repair or preventive maintenance routine.4. Work order shall be used to track completion of work, parts used and total cost of repair.5. A database shall include an inventory tracking system. Work orders generated shall automatically

update inventory database to show quantity of tools, repair parts and expendables used for a work order.

6. Work orders and preventive maintenance schedules shall be printed on a dedicated printer assigned solely to maintenance management function.

B. Additional Hardware Requirements:

1. Maintenance management software shall not require additional hardware, except for an additional printer that is dedicated to maintenance management.

2. Maintenance management software shall be integrated into DDC system.

C. Software Requirements:

1. From main menu of maintenance management system, it shall be possible through selection of icons to penetrate to individual functions described below.

2. Work Orders:

a. Automatically generate work orders initiated from alarm conditions, accumulated run time or calendar time. Work orders generated shall specify a particular task to be accomplished including the labor, material and tools needed to accomplish work.

b. Include at least two of the following types of work orders:

1) Corrective and emergency maintenance work orders shall be generated for a specific job or repair for emergency, breakdown, or scheduled work.

2) Preventive maintenance that are used on a periodic basis to generate preventive maintenance work orders.

c. Include the following functions:

1) Work Order Tracking: Perform every function related to processing work orders including creating, approving and initiating work orders, checking their status history and closing or reworking them when appropriate.

2) Work Requests: Report any problems that require corrective maintenance activity generated by dispatchers and those people designated to request work orders.

3) Quick Reporting: Report work done on an open work order or a small job.4) Work Manager: Specify the type of labor to be applied to a specific work order at

specific times. It shall include the capability to dispatch one or more laborers to top-priority jobs on as-needed basis and to interrupt work in progress to reassign labor to higher priority tasks.

Page 78: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 43

d. Reports:

1) Daily Maintenance Schedule by Supervisor: List a schedule of open work orders for a specified date by supervisor.

2) Equipment Cost Roll-up Report: Include a roll-up of equipment costs incurred since the date the report was last run.

3) Delinquent Work Order Report: List open work orders whose target completion date is earlier than the date the report is run.

4) Employee Job Assignments: List labor codes that have job assignments for the specified date.

5) Daily Work Order Assignment: List work orders that have labor assignments for the specified date.

6) Estimated versus Actual Work Order Costs: List a cost summary of outstanding work orders.

7) Open Work Orders Report: List open work orders for locations and equipment.

3. Inventory:

a. Include an inventory tracking system to keep track of stocked, non-stocked and special-order items.

b. Link inventory tracking to database and when items are consumed, as noted on a work order issued by system, inventory of stocked items shall be automatically updated.

c. Include the following functions:

1) Inventory Control: Enter, display, and update information on each inventory item. It shall allow viewing of master inventory records that are independent of storeroom locations or item/location records. Include a screen that lists inventory transactions that move items in or out of inventory or from one storeroom location to another. Minimum information tracked shall include the following:

a) Vendors supply items.b) Item balances, including the bin and lot level for each storeroom location.c) Alternative items.

2) Issues and Transfers: Issue stock directly from inventory, with or without a work order. When transfer of stock from one location to another location occurs, provide appropriate adjustments in stock balance record. Include a trace record of stock transfers from one storeroom to another.

3) Item Assembly Structures: Include modeling of equipment with inventory items and building of equipment and location hierarchies.

4) Metered Material Usage:

a) Track usage by a piece of equipment.b) Record against a standing work order for a selected piece of equipment.c) Material usage transaction shall be written for each item of material used and

be provided as an input to calculation for per unit material consumption report for a piece of equipment.

d. Reports:

1) Inventory Analysis Report: List for a given storeroom location, inventory items analysis information that allows quick identification of which inventory items represent greatest monetary investment for dollar value and rate of turnover.

2) Inventory Cycle Count Report: List for a specified storeroom, inventory items that are due to be cycle-counted, based on cycle-count frequency and last count date.

3) Economic Order Quantity Report: For a given storeroom location, display optimum economic ordering quantity for items in selected results set.

4) Inventory Pick Report: A pick list, by work order for items needed to be pulled from a designated storeroom's inventory for work orders having a target start date of specified date.

Page 79: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 44

5) Suggested Order Report: List inventory items in selected results set that are due to be recorded, for a specified storeroom location, based on the following calculation: Suggest a reorder if current balance minus reserve quantity plus on-order quantity is less than reorder point.

6) Reorder Point Report: List selected set of items and optimum minimum level to have in stock based on demand, lead delivery time and a reserve safety stock.

7) Inventory Valuation Report: Gives an accounting of cost of current inventory, for inventory records in a designated storeroom location.

8) Item Order Status: Lists items on order.9) List of Expired Items: Lists expired lot items in a storeroom. Report shall include item

number, description, expiration date, bin number, lot number, manufacturer lot number, and quantity of expired items in that lot and bin.

10) Item Availability at All Locations: Lists alternative storeroom locations for selected items.

11) Where Used Report: List equipment on which item is recorded as being used.

4. Equipment:

a. Include equipment and location records; establish relationships between equipment, between locations, and between equipment and locations; track maintenance costs; and enter and review meter readings.

b. Include the following functions:

1) Equipment: Store equipment numbers and corresponding information including equipment class, location, vendor, up/down status and maintenance costs for each piece of equipment. Include building of equipment assemblies. Equipment assemblies hierarchical ordering shall be provided for arrangement of buildings, departments, equipment and sub-assemblies.

2) Operating Locations: Facilitate creation of records for operating locations of equipment, and track equipment that is used in multiple locations. In addition, allow hierarchical organization of equipment operating in facility by means of grouping equipment locations into areas of responsibility.

3) Failure Codes: Develop and display failure hierarchies to acquire an accurate history of types of failures that affect equipment and operating locations.

4) Condition Monitoring: Display time related or limit measurements recorded for a piece of equipment. It shall be possible to generate work orders from this screen and to take immediate action on problem conditions.

c. Reports:

1) Availability Statistic by Location: List equipment availability by location over a user-specified time period.

2) Equipment Failure Summary: List total number of failures by problem code for a piece of equipment for a specified time period.

3) Detailed Equipment Failure Report by Equipment: List of failure reports for the current piece of equipment for a specified time period.

4) Equipment Hierarchy Report: List of equipment.5) Equipment History Graphs: Include a graphical report in histogram format that

displays equipment breakdown history over a specified period.6) Equipment Measurement Report: Tabular listing and description of each

measurement point for a piece of equipment and the history of measurements taken for that point.

7) Maintenance Cost by Equipment: List of transactions costs for elected equipment in the specified date range.

8) Failure Count by Equipment: Graphically report the number of failures for each piece of equipment showing number of failures for each piece of equipment over a specified time period, occurrence of each problem code within set of failures and failures by problem code.

9) Failure Analysis Graphs: Graphically report number of failures for each piece of equipment over a specified time period, number of occurrences of each problem code within set of failures and failures by problem code.

Page 80: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 45

10) Failure Code Hierarchy Report: List of failure codes in each level of the failure hierarchy.

11) Location Failure Summary: A summary for each selected location of failures reported and any hierarchy level locations for specified time period.

12) Failure Summary by Location: A summary of failures for the selected location and their subordinate locations that are part of the hierarchical system.

13) Detailed Failure Report by Location: List all failures for selected location and its subordinate locations that are part of a hierarchical system.

14) Maintenance Cost by System: List of total costs reported in a given date range for locations in selected hierarchical system.

15) Location Hierarchy Report: Lists member locations of a hierarchical system displayed in hierarchical fashion.

5. Purchasing:

a. Include preparation and generation of purchase requisitions and purchase orders; to report receipt of both items and services, match invoices with purchase orders and receipts and define and convert foreign currencies.

b. Include the following functions:

1) Purchase Requisition: Create and process purchase requisitions for items and services.

2) Purchase Orders: Create and process purchase orders for items and services from scratch or from purchase requisitions. Record receipts of items and services.

3) Invoices: Include functionality to match purchase orders with invoices and receipts. It shall also be possible to match a service receipt to an invoice. Project for entering of an invoice for bills that do not require purchase orders or receipts.

4) Currency Management: Define currencies and specify exchange rates. Include preparation of purchase requisitions and purchase orders in currency of vendor, while tracking costs in systems base currency.

c. Reports:

1) Invoice Approval Report: Include an approval form for entered invoices.2) Inventory Receipts Register: List purchase orders and inventory received for the

user-specified time frame.3) Direct Purchase Back-Order Report: List of items ordered as a direct purchase not

received by the required delivery date.4) Standard Purchase Order: A printing of primary purchase order with vendors

shipping information, and items purchased.5) Purchase Order Status Report: List of purchase orders whose status has changed

during a certain time period.6) Standard Purchase Requisition: A printing of primary purchase requisition, including

vendor name and shipping information.

6. Job Plans:

a. Include creation of a detailed description of work to be performed by a work order. The job plan shall contain operations, procedures and list of estimated material, labor and tools required for work.

7. Labor:

a. Store information on employees, contractors, and crafts and include the following functions:

1) Labor: Create, modify and view employee records. Employee records shall contain pay rate, overtime worked, overtime refused, specials skills and certifications.

2) Crafts: Create, modify and view craftspeople records.3) Labor Reporting: Report labor usage by employee or craft externally from the work

orders module.

Page 81: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 46

b. Reports:

1) Employee Attendance Analysis: List of planned attendance, actual attendance, vacation and sick time in hours as a percentage of planned attendance for selected employees for specified time period.

2) Labor Productivity Analysis: List of actual labor hours by labor report category showing each by percentage.

3) Labor Availability versus Commitments by Crafts: A graphical report that details available labor hours versus committed work order hours by craft and day.

8. Calendars:

a. Establish calendar records indicating working time for equipment, location, craft, and labor records.

9. Resources:

a. Include entry and retrieval of data associated with resources required to maintain facility and to include the following functions:

1) Companies: Establish and update data on vendors and other companies.2) Tools: Create and maintain information on the tools used on jobs. The information

contained within this module shall be available to job plans and work orders.3) Service Contracts: Specify information on service contracts with vendors or

manufacturers.

10. Custom Applications:

a. Include creation of customized database tables and application screens that supplement functions specified.

11. Setup:

a. Include configuration of database, security and setup applications.b. Perform the following functions:

1) Reports and Other Applications: Register reports and other applications for use within system.

2) Documents: Enter, track and link information from Drawings to equipment and inventory items.

3) Chart of Accounts: Add or modify accounts; set up financial periods; enter inventory accounts, company accounts, and resource recovery accounts; and define tax codes and rates.

4) Signature Security: Establish each user's access rights to modules, applications, screens and options.

5) Database Configuration: Customize database, including adjusting field lengths and modifying data types.

6) Application Setup: Change position of icons and menu items on the main menu screen.

7) Application Launching: Allow for connecting of third-party applications to data fields and push buttons.

12. Utilities:

a. Include utilities module that allows system administrator to customize system and to maintain database.

b. Include the following functions:

1) Interactive SQL: Include access to database for database management functions of import/export and backup.

Page 82: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 47

2) Edit Windows: Display a dialog box to customize an application.3) Archive Data: Remove records from database and store them for future reference.

D. Documentation:

1. Include complete documentation for the system consisting of a User Manual and Systems Administrator Guide.

2. User Manual shall describe how to use each application module and screen with step-by-step instructions detailing entry and retrieval of data for functions specified.

3. Include a step-by-step description of how each report is defined and retrieved.4. Bind documentation and clearly title it indicating volume number and use.

2.17 ASHRAE 135 GATEWAYS

A. Include BACnet communication ports, whenever available as an equipment OEM standard option, for integration via a single communication cable. BACnet-controlled plant equipment includes, but is not limited to, chillers, cooling towers, pumps, air handlers, rooftop units, and variable-speed drives.

B. Include gateways to connect BACnet to legacy systems, existing non-BACnet devices, and existing non-BACnet DDC-controlled equipment, only when specifically requested and approved by Owner.

C. Include with each gateway an interoperability schedule showing each point or event on legacy side that BACnet "client" will read, and each parameter that BACnet network will write to. Describe this interoperability of BACnet services, or BIBBs, defined in ASHRAE 135, Annex K.

D. Gateway Minimum Requirements:

1. Read and view all readable object properties on non-BACnet network to BACnet network and vice versa where applicable.

2. Write to all writeable object properties on non-BACnet network from BACnet network and vice versa where applicable.

3. Include single-pass (only one protocol to BACnet without intermediary protocols) translation from non-BACnet protocol to BACnet and vice versa.

4. Comply with requirements of Data Sharing Read Property, Data Sharing Write Property, Device Management Dynamic Device Binding-B, and Device Management Communication Control BIBBs according to ASHRAE 135.

5. Hardware, software, software licenses, and configuration tools for operator-to-gateway communications.

6. Backup programming and parameters on CD media and the ability to modify, download, backup, and restore gateway configuration.

2.18 ASHRAE 135 PROTOCOL ANALYZER

A. Analyzer and required cables and fittings for connection to ASHRAE 135 network.

B. Analyzer shall include the following minimum capabilities:

1. Capture and store to a file data traffic on all network levels.2. Measure bandwidth usage.3. Filtering options with ability to ignore select traffic.

2.19 CEA-709.1-C NETWORK HARDWARE

A. Routers:

Page 83: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 48

1. Network routers, including routers configured as repeaters, shall comply with requirements of CEA-709.1-C and include connection between two or more CEA-709.3 TP/FT-10 channels or between two or more CEA-709.3 TP/FT-10 channels and a TP/XF-1250 channel.

2. IP Routers:

a. Perform layer three routing of CEA-709.1-C packets over an IP network according to CEA-852-B.

b. Include appropriate connection to the IP network and connections to CEA-709.3 TP/FT-10 or TP/XF-1250 network.

c. Support the Dynamic Host Configuration Protocol for IP configuration and use of an CEA-852-B Configuration Server (for CEA-852-B configuration), but shall not rely on these services for configuration.

d. Capable of manual configuration via a console RS-232 port.

B. Gateways:

1. Perform bidirectional protocol translation from one non-CEA-709.1-C protocol to CEA-709.1-C.2. Incorporate a network connection to a TP/FT-10 network according to CEA-709.3 and a connection

for a non-CEA-709.1-C network.

2.20 WIRELESS ROUTERS FOR OPERATOR INTERFACE

A. Single-Band Wireless Routers:

1. Approved manufacturers:a. Linksysb. D-Linkc. Netgeard. Approved equivalent

2. Description: High-speed router with integral Ethernet ports.3. Technology: IEEE 802.11n; 2.4-GHz speed band.4. Speed: Up to 300 Mbps.5. Compatibility: IEEE 802.11n/g/b/a wireless devices.6. Ethernet Ports: Four, gigabit (1000 Mbps).7. Wireless Security: Wi-Fi Protected Access (WPA) and WPA2 according to IEEE 802.11i.

B. Dual-Band Wireless Routers:1. Approved manufacturers:

a. Linksysb. D-Linkc. Netgeard. Approved equivalent

2. Description: High-speed, dual-band router with integral Ethernet ports and USB port.3. Technology: IEEE 802.11n; 2.4- and 5-GHz speed bands.4. Speed: Up to 300 Mbps on 2.4-GHz band and up to 450 Mbps on 5-GHz band.5. Compatibility: IEEE 802.11n/g/b/a wireless devices.6. Ethernet Ports: Four, gigabit (1000 Mbps).7. USB Port: One, USB 2.0 or 3.0.8. Wireless Security: Wi-Fi Protected Access (WPA) and WPA2 according to IEEE 802.11i.

2.21 DDC CONTROLLERS

A. DDC system shall consist of a combination of network controllers, programmable application controllers and application-specific controllers to satisfy performance requirements indicated.

B. DDC controllers shall perform monitoring, control, energy optimization and other requirements indicated.

Page 84: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 49

C. DDC controllers shall use a multitasking, multiuser, real-time digital control microprocessor with a distributed network database and intelligence.

D. Each DDC controller shall be capable of full and complete operation as a completely independent unit and as a part of a DDC system wide distributed network.

E. Environment Requirements:

1. Controller hardware shall be suitable for the anticipated ambient conditions.2. Controllers located in conditioned space shall be rated for operation at 32 to 120 deg F.3. Controllers located outdoors shall be rated for operation at 40 to 150 deg F.

F. Power and Noise Immunity:

1. Controller shall operate at 90 to 110 percent of nominal voltage rating and shall perform an orderly shutdown below 80 percent of nominal voltage.

2. Operation shall be protected against electrical noise of 5 to 120 Hz and from keyed radios with up to 5 W of power located within 36 inches of enclosure.

G. DDC Controller Spare Processing Capacity:

1. Include spare processing memory for each controller. RAM, PROM, or EEPROM will implement requirements indicated with the following spare memory:

a. Network Controllers: 50 percent.b. Programmable Application Controllers: Not less than 70 percent.c. Application-Specific Controllers: Not less than 70 percent.

2. Memory shall support DDC controller's operating system and database and shall include the following:

a. Monitoring and control.b. Energy management, operation and optimization applications.c. Alarm management.d. Historical trend data of all connected I/O points.e. Maintenance applications.f. Operator interfaces.g. Monitoring of manual overrides.

H. DDC Controller Spare I/O Point Capacity: Include spare I/O point capacity for each controller as follows:

1. Network Controllers:

a. 20 percent of each AI, AO, BI, and BO point connected to controller.b. Minimum Spare I/O Points per Controller:

1) AIs: Three.2) AOs: Three.3) BIs: Five.4) BOs: Five.

2. Programmable Application Controllers:

a. 20 percent of each AI, AO, BI, and BO point connected to controller.b. Minimum Spare I/O Points per Controller:

1) AIs: Three.2) AOs: Three3) BIs: Five.

Page 85: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 50

4) BOs:Five.

3. Application-Specific Controllers:

a. 10 percent of each AI, AO, BI, and BO point connected to controller.b. Minimum Spare I/O Points per Controller:

1) AIs: Two2) AOs: Two3) BIs: Two4) BOs: Two.

I. Maintenance and Support: Include the following features to facilitate maintenance and support:

1. Mount microprocessor components on circuit cards for ease of removal and replacement.2. Means to quickly and easily disconnect controller from network.3. Means to quickly and easily access connect to field test equipment.4. Visual indication that controller electric power is on, of communication fault or trouble, and that

controller is receiving and sending signals to network.

J. General Requirements for CEA-709.1-C DDC Controllers:

1. Controllers shall be LonMark certified.2. Distinguishable and accessible switch, button, or pin, when pressed shall broadcast its 48-bit Node

ID and Program ID over network.3. TP/FT-10 transceiver according to CEA-709.3 and connections for TP/FT-10 control network

wiring.4. TP/XF-1250 transceiver according to CEA-709.3 and connections for TP/XF-1250 control network

wiring.5. Communicate using CEA-709.1-C protocol.6. Controllers configured into subnets, as required, to comply with performance requirements

indicated.7. Network communication through LNS network management and database standard for CEA-709.1-

C network devices.8. Locally powered, not powered through network connection.9. Functionality required to support applications indicated, including, but not limited to, the following:

a. Input and outputs indicated and as required to support sequence of operation and application in which it is used. SNVTs shall have meaningful names identifying the value represented by an SNVT. Unless an SNVT of an appropriate engineering type is unavailable, all network variables shall be of an SNVT with engineering units appropriate to value the variable represents.

b. Configurable through SCPTs defined in LonMark SCPT List, operator-defined UCPTs, network configuration inputs (NCIs) of an SNVT type defined in LonMark SNVT List, NCIs of an operator-defined network variable type, or hardware settings on controller itself for all settings and parameters used by application in which it is used.

10. Programmable controllers shall conform to LonMark Interoperability Guidelines and have LonMark certification.

K. Input and Output Point Interface:

1. Hardwired input and output points shall connect to network, programmable application and application-specific controllers.

2. Input and output points shall be protected so shorting of point to itself, to another point, or to ground will not damage controller.

3. Input and output points shall be protected from voltage up to 24 V of any duration so that contact will not damage controller.

4. AIs:

Page 86: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 51

a. AIs shall include monitoring of low-voltage (zero- to 10-V dc), current (4 to 20 mA) and resistance signals from thermistor and RTD sensors.

b. AIs shall be compatible with, and field configurable to, sensor and transmitters installed.c. Controller AIs shall perform analog-to-digital (A-to-D) conversion with a minimum resolution

of 12 bits or better to comply with accuracy requirements indicated.d. Signal conditioning including transient rejection shall be provided for each AI.e. Capable of being individually calibrated for zero and span.f. Incorporate common-mode noise rejection of at least 50 dB from zero to 100 Hz for

differential inputs, and normal-mode noise rejection of at least 20 dB at 60 Hz from a source impedance of 10000 ohms.

5. AOs:

a. Controller AOs shall perform analog-to-digital (A-to-D) conversion with a minimum resolution of 12 bits or better to comply with accuracy requirements indicated.

b. Output signals shall have a range of 4 to 20 mA dc or zero- to 10-V dc as required to include proper control of output device.

c. Capable of being individually calibrated for zero and span.d. AOs shall not exhibit a drift of greater than 0.4 percent of range per year.

6. BIs:

a. Controller BIs shall accept contact closures and shall ignore transients of less than 5-ms duration.

b. Isolation and protection against an applied steady-state voltage of up to 180-V ac peak.c. BIs shall include a wetting current of at least 12 mA to be compatible with commonly

available control devices and shall be protected against effects of contact bounce and noise.

d. BIs shall sense "dry contact" closure without external power (other than that provided by the controller) being applied.

e. Pulse accumulation input points shall comply with all requirements of BIs and accept up to 10 pulses per second for pulse accumulation. Buffer shall be provided to totalize pulses. Pulse accumulator shall accept rates of at least 20 pulses per second. The totalized value shall be reset to zero on operator's command.

7. BOs:

a. Controller BOs shall include relay contact closures or triac outputs for momentary and maintained operation of output devices.

1) Relay contact closures shall have a minimum duration of 0.1 second. Relays shall include at least 180 V of isolation. Electromagnetic interference suppression shall be provided on all output lines to limit transients to non-damaging levels. Minimum contact rating shall be 1 A at 24-V ac.

2) Triac outputs shall include at least 180 V of isolation. Minimum contact rating shall be 1 A at 24-V ac.

b. BOs shall include for two-state operation or a pulsed low-voltage signal for pulse-width modulation control.

c. BOs shall be selectable for either normally open or normally closed operation.d. Include tristate outputs (two coordinated BOs) for control of three-point floating-type

electronic actuators without feedback.e. Limit use of three-point floating devices to VAV terminal unit control applications. Control

algorithms shall operate actuator to one end of its stroke once every 12 hours for verification of operator tracking.

2.22 NETWORK CONTROLLERS

A. General Network Controller Requirements:

Page 87: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 52

1. Include adequate number of controllers to achieve performance indicated.2. System shall consist of one or more independent, standalone, microprocessor-based network

controllers to manage global strategies indicated.3. Controller shall have enough memory to support its operating system, database, and programming

requirements.4. Data shall be shared between networked controllers and other network devices.5. Operating system of controller shall manage input and output communication signals to allow

distributed controllers to share real and virtual object information and allow for central monitoring and alarms.

6. Controllers that perform scheduling shall have a real-time clock.7. Controller shall continually check status of its processor and memory circuits. If an abnormal

operation is detected, controller shall assume a predetermined failure mode and generate an alarm notification.

8. Controllers shall be fully programmable.

B. Communication:

1. Network controllers shall communicate with other devices on DDC system Level one network.2. Network controller also shall perform routing if connected to a network of programmable application

and application-specific controllers.

C. Operator Interface:

1. Controller shall be equipped with a service communications port for connection to a portable operator's workstation or mobile device.

2. Local Keypad and Display:

a. Equip controller with local keypad and digital display for interrogating and editing data.b. Use of keypad and display shall require security password.

D. Serviceability:

1. Controller shall be equipped with diagnostic LEDs or other form of local visual indication of power, communication, and processor.

2. Wiring and cable connections shall be made to field-removable, modular terminal strips or to a termination card connected by a ribbon cable.

3. Controller shall maintain BIOS and programming information in event of a power loss for at least 72 hours.

2.23 PROGRAMMABLE APPLICATION CONTROLLERS

A. General Programmable Application Controller Requirements:

1. Include adequate number of controllers to achieve performance indicated.2. Controller shall have enough memory to support its operating system, database, and programming

requirements.3. Data shall be shared between networked controllers and other network devices.4. Operating system of controller shall manage input and output communication signals to allow

distributed controllers to share real and virtual object information and allow for central monitoring and alarms.

5. Controllers that perform scheduling shall have a real-time clock.6. Controller shall continually check status of its processor and memory circuits. If an abnormal

operation is detected, controller shall assume a predetermined failure mode and generate an alarm notification.

7. Controllers shall be fully programmable.

B. Communication:

1. Programmable application controllers shall communicate with other devices on network.

Page 88: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 53

C. Operator Interface:

1. Controller shall be equipped with a service communications port for connection to a portable operator's workstation or mobile device.

2. Local Keypad and Display:

a. Equip controller with local keypad and digital display for interrogating and editing data.b. Use of keypad and display shall require security password.

D. Serviceability:

1. Controller shall be equipped with diagnostic LEDs or other form of local visual indication of power, communication, and processor.

2. Wiring and cable connections shall be made to field-removable, modular terminal strips or to a termination card connected by a ribbon cable.

3. Controller shall maintain BIOS and programming information in event of a power loss for at least 72 hours.

2.24 APPLICATION-SPECIFIC CONTROLLERS

A. Description: Microprocessor-based controllers, which through hardware or firmware design are dedicated to control a specific piece of equipment. Controllers are not fully user-programmable but are configurable and customizable for operation of equipment they are designed to control.

1. Capable of standalone operation and shall continue to include control functions without being connected to network.

2. Data shall be shared between networked controllers and other network devices.

B. Communication: Application-specific controllers shall communicate with other application-specific controller and devices on network, and to programmable application and network controllers.

C. Operator Interface: Controller shall be equipped with a service communications port for connection to a portable operator's workstation. Connection shall extend to port on space temperature sensor that is connected to controller.

D. Serviceability:

1. Controller shall be equipped with diagnostic LEDs or other form of local visual indication of power, communication, and processor.

2. Wiring and cable connections shall be made to field-removable, modular terminal strips or to a termination card connected by a ribbon cable.

3. Controller shall use nonvolatile memory and maintain all BIOS and programming information in event of power loss.

2.25 CONTROLLER SOFTWARE

A. General Controller Software Requirements:

1. Software applications shall reside and operate in controllers. Editing of applications shall occur at operator workstations.

2. I/O points shall be identified by up to 30 character point name and up to 16 character point descriptor. Same names shall be used at operator workstations.

3. Control functions shall be executed within controllers using DDC algorithms.4. Controllers shall be configured to use stored default values to ensure fail-safe operation. Default

values shall be used when there is a failure of a connected input instrument or loss of communication of a global point value.

Page 89: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 54

B. Security:

1. Operator access shall be secured using individual security passwords and user names.2. Passwords shall restrict operator to points, applications, and system functions as assigned by

system manager.3. Operator log-on and log-off attempts shall be recorded.4. System shall protect itself from unauthorized use by automatically logging off after last keystroke.

The delay time shall be operator-definable.

C. Scheduling: Include capability to schedule each point or group of points in system. Each schedule shall consist of the following:

1. Weekly Schedule:

a. Include separate schedules for each day of week.b. Each schedule should include the capability for start, stop, optimal start, optimal stop, and

night economizer.c. Each schedule may consist of up to 10 events.d. When a group of objects are scheduled together, include capability to adjust start and stop

times for each member.

2. Exception Schedules:

a. Include ability for operator to designate any day of the year as an exception schedule.b. Exception schedules may be defined up to a year in advance. Once an exception schedule

is executed, it will be discarded and replaced by regular schedule for that day of week.

3. Holiday Schedules:

a. Include capability for operator to define up to 99 special or holiday schedules.b. Schedules may be placed on scheduling calendar and will be repeated each year.c. Operator shall be able to define length of each holiday period.

D. System Coordination:

1. Include standard application for proper coordination of equipment.2. Application shall include operator with a method of grouping together equipment based on function

and location.3. Group may then be used for scheduling and other applications.

E. Binary Alarms:

1. Each binary point shall be set to alarm based on operator-specified state.2. Include capability to automatically and manually disable alarming.

F. Analog Alarms:

1. Each analog object shall have both high and low alarm limits.2. Alarming shall be able to be automatically and manually disabled.

G. Alarm Reporting:

1. Operator shall be able to determine action to be taken in event of an alarm.2. Alarms shall be routed to appropriate operator workstations based on time and other conditions.3. Alarm shall be able to start programs, print, be logged in event log, generate custom messages,

and display graphics.

H. Remote Communication:

Page 90: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 55

1. System shall have ability to dial out in the event of an alarm.

I. Electric Power Demand Limiting:

1. Demand-limiting program shall monitor building or other operator-defined electric power consumption from signals connected to electric power meter or from a watt transducer or current transformer.

2. Demand-limiting program shall predict probable power demand such that action can be taken to prevent exceeding demand limit. When demand prediction exceeds demand limit, action will be taken to reduce loads in a predetermined manner. When demand prediction indicates demand limit will not be exceeded, action will be taken to restore loads in a predetermined manner.

3. Demand reduction shall be accomplished by the following means:

a. Reset air-handling unit supply temperature set points.b. Reset space temperature set points.c. De-energize equipment based on priority.

4. Demand-limiting parameters, frequency of calculations, time intervals, and other relevant variables shall be based on the means by which electric power service provider computes demand charges.

5. Include demand-limiting prediction and control for any individual meter monitored by system or for total of any combination of meters.

6. Include means operator to make the following changes online:

a. Addition and deletion of loads controlled.b. Changes in demand intervals.c. Changes in demand limit for meter(s).d. Maximum shutoff time for equipment.e. Minimum shutoff time for equipment.f. Select rotational or sequential shedding and restoring.g. Shed and restore priority.

7. Include the following information and reports, to be available on an hourly, daily, weekly, monthly and annual basis:

a. Total electric consumption.b. Peak demand.c. Date and time of peak demand.d. Daily peak demand.

J. Maintenance Management: System shall monitor equipment status and generate maintenance messages based on operator-designated run-time, starts, and calendar date limits.

K. Sequencing: Include application software based on sequences of operation indicated to properly sequence chillers, boilers, and other applicable HVAC equipment.

L. Control Loops:

1. Support any of the following control loops, as applicable to control required:

a. Two-position (on/off, open/close, slow/fast) control.b. Proportional control.c. Proportional plus integral (PI) control.d. Proportional plus integral plus derivative (PID) control.

1) Include PID algorithms with direct or reverse action and anti-windup.2) Algorithm shall calculate a time-varying analog value used to position an output or

stage a series of outputs.3) Controlled variable, set point, and PID gains shall be operator-selectable.

e. Adaptive (automatic tuning).

Page 91: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 56

M. Staggered Start: Application shall prevent all controlled equipment from simultaneously restarting after a power outage. Order which equipment (or groups of equipment) is started, along with the time delay between starts, shall be operator-selectable.

N. Energy Calculations:

1. Include software to allow instantaneous power or flow rates to be accumulated and converted to energy usage data.

2. Include an algorithm that calculates a sliding-window average (rolling average). Algorithm shall be flexible to allow window intervals to be operator specified (such as 15, 30, or 60 minutes).

3. Include an algorithm that calculates a fixed-window average. A digital input signal shall define start of window period (such as signal from utility meter) to synchronize fixed-window average with that used by utility.

O. Anti-Short Cycling:

1. BO points shall be protected from short cycling.2. Feature shall allow minimum on-time and off-time to be selected.

P. On and Off Control with Differential:

1. Include an algorithm that allows a BO to be cycled based on a controlled variable and set point.2. Algorithm shall be direct- or reverse-acting and incorporate an adjustable differential.

Q. Run-Time Totalization:

1. Include software to totalize run-times for all BI and BO ]points.2. A high run-time alarm shall be assigned, if required, by operator.

2.26 ENCLOSURES

A. General Enclosure Requirements:

1. House each controller and associated control accessories in a single enclosure. Enclosure shall serve as central tie-in point for control devices such as switches, transmitters, transducers, power supplies and transformers.

2. Do not house more than one controller in a single enclosure.3. Include enclosure door with key locking mechanism. Key locks alike for all enclosures and include

one pair of keys per enclosure.4. Equip doors of enclosures housing controllers and components with analog or digital displays with

windows to allow visual observation of displays without opening enclosure door.5. Individual wall-mounted single-door enclosures shall not exceed 36 inches wide and 48 inches

high.6. Individual wall-mounted double-door enclosures shall not exceed 60 inches wide and 36 inches

high.7. Freestanding enclosures shall not exceed 48 inches wide and 72 inches high.8. Include wall-mounted enclosures with brackets suitable for mounting enclosures to wall or

freestanding support stand as indicated.9. Supply each enclosure with a complete set of as-built schematics, tubing, and wiring diagrams and

product literature located in a pocket on inside of door. For enclosures with windows, include pocket on bottom of enclosure.

B. Internal Arrangement:

1. Internal layout of enclosure shall group and protect pneumatic, electric, and electronic components associated with a controller, but not an integral part of controller.

2. Arrange layout to group similar products together.3. Include a barrier between line-voltage and low-voltage electrical and electronic products.

Page 92: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 57

4. Factory or shop install products, tubing, cabling and wiring complying with requirements and standards indicated.

5. Terminate field cable and wire using heavy-duty terminal blocks.6. Include spare terminals, equal to not less than 20 percent of used terminals.7. Include spade lugs for stranded cable and wire.8. Install a maximum of two wires on each side of a terminal.9. Include enclosure field power supply with a toggle-type switch located at entrance inside enclosure

to disconnect power.10. Include enclosure with a line-voltage nominal 20-A GFCI duplex receptacle for service and testing

tools. Wire receptacle on hot side of enclosure disconnect switch and include with a 5-A circuit breaker.

11. Mount products within enclosure on removable internal panel(s).12. Include products mounted in enclosures with engraved, laminated phenolic nameplates (black

letters on a white background). The nameplates shall have at least 1/4-inch high lettering.13. Route tubing cable and wire located inside enclosure within a raceway with a continuous

removable cover.14. Label each end of cable, wire and tubing in enclosure following an approved identification system

that extends from field I/O connection and all intermediate connections throughout length to controller connection.

15. Size enclosure internal panel to include at least 25 percent spare area on face of panel.

C. Environmental Requirements:

1. Evaluate temperature and humidity requirements of each product to be installed within each enclosure.

2. Calculate enclosure internal operating temperature considering heat dissipation of all products installed within enclosure and ambient effects (solar, conduction and wind) on enclosure.

3. Where required by application, include temperature-controlled electrical heat to maintain inside of enclosure above minimum operating temperature of product with most stringent requirement.

4. Where required by application, include temperature-controlled ventilation fans with filtered louver(s) to maintain inside of enclosure below maximum operating temperature of product with most stringent requirement.

5. Include temperature-controlled cooling within the enclosure for applications where ventilation fans cannot maintain inside temperature of enclosure below maximum operating temperature of product with most stringent requirement.

6. Where required by application, include humidity-controlled electric dehumidifier or cooling to maintain inside of enclosure below maximum relative humidity of product with most stringent requirement and to prevent surface condensation within enclosure.

D. Wall-Mounted, NEMA 250, Type 1:

1. Enclosure shall be NRTL listed according to UL 50 or UL 50E.2. Construct enclosure of steel, not less than:

a. Enclosure size less than 24 in., 0.053 in. thick.b. Enclosure size 24 in. and larger: 0.067 in. thick.

3. Finish enclosure inside and out with polyester powder coating that is electrostatically applied and then baked to bond to substrate.

a. Exterior color shall be manufacturer's standard color.b. Interior color shall be manufacturer's standard.

4. Hinged door full size of front face of enclosure and supported using:

a. Enclosures sizes less than 36 in. tall: Multiple butt hinges.b. Enclosures sizes 36 in. tall and larger: Continuous piano hinges.

5. Removable internal panel with a white polyester powder coating that is electrostatically applied and then baked to bond to substrate.

Page 93: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 58

a. Size less than 24 in. Solid or Perforated steel, 0.053 in. thick.b. Size 24 in and larger: Solid aluminum, 0.10 in. or steel, 0.093 in. thick.

6. Internal panel mounting hardware, grounding hardware and sealing washers.7. Grounding stud on enclosure body.8. Thermoplastic pocket on inside of door for record Drawings and Product Data.

E. Wall Mounted NEMA 250, Types 4 and 12:1. Enclosure shall be NRTL listed according to UL 508A.2. Seam and joints are continuously welded and ground smooth.3. Where recessed enclosures are indicated, include enclosures with face flange for flush mounting.4. Externally formed body flange around perimeter of enclosure face for continuous perimeter

seamless gasket door seal.5. Single-door enclosure sizes up to 60 inches tall by 36 inches wide.6. Double-door enclosure sizes up to 36 inches tall by 60 inches wide.7. Construct enclosure of steel, not less than the following:

a. Size Less Than 24 Inches: 0.053 inch thick.b. Size 24 Inches and Larger: 0.067 inch thick.

8. Finish enclosure with polyester powder coating that is electrostatically applied and then baked to bond to substrate.

a. Exterior color shall be standard.b. Interior color shall be manufacturer's standard.

9. Corner-formed door, full size of enclosure face, supported using multiple concealed hinges with easily removable hinge pins.

a. Sizes through 24 Inches Tall: Two hinges.b. Sizes between 24 Inches through 48 Inches Tall: Three hinges.c. Sizes Larger 48 Inches Tall: Four hinges.

10. Double-door enclosures with overlapping door design to include unobstructed full-width access.

a. Single-door enclosures 48 inches and taller, and all double-door enclosures, with three-point (top, middle and bottom) latch system.

11. Removable internal panel with a white polyester powder coating that is electrostatically applied and then baked to bond to substrate.

a. Size Less Than 24 Inches Solid] steel, 0.053 inch thick.b. Size 24 Inches and Larger: Solid aluminum, 0.10 inch or steel, 0.093 inch thick.

12. Internal panel mounting studs with hardware, grounding hardware, and sealing washers.13. Grounding stud on enclosure body.14. Thermoplastic pocket on inside of door for record Drawings and Product Data.

F. Wall-Mounted, NEMA 250, Type 4X SS:1. Enclosure shall be NRTL listed according to UL 508A.2. Seam and joints are continuously welded and ground smooth.3. Externally formed body flange around perimeter of enclosure face for continuous perimeter

seamless gasket door seal.4. Construct enclosure of Type 304 stainless steel, not less than the following:

a. Size Less Than 24 Inches: 0.053 inch thick.b. Size 24 Inches and Larger: 0.067 inch thick.

5. Outside body and door of enclosure with brushed No. 4 finish.

Page 94: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 59

6. Corner-formed door, full size of enclosure face, supported using multiple concealed hinges with easily removable hinge pins.

a. Sizes through 24 Inches Tall: Two hinges.b. Sizes between 24 Inches through 48 Inches Tall: Three hinges.c. Sizes Larger 48 Inches Tall: Four hinges.

7. Corner-formed door, full size of enclosure face, supported using continuous piano hinge full length of door.

8. Doors fitted with three-point (top, middle, and bottom) latch system with single, heavy-duty, liquid-tight Type 316 stainless-steel handle with integral locking mechanism.

9. Removable internal panel shall be 0.093-inch solid steel with a white polyester powder coating that is electrostatically applied and then baked to bond to substrate.

10. Internal panel mounting studs and hardware, grounding hardware, and sealing washers.11. Install corrosion-resistant polyester vent drain in a stainless-steel sleeve at the bottom of enclosure.12. Include enclosure with stainless-steel mounting brackets.

G. Freestanding, NEMA 250, Type 1:1. Enclosure shall be NRTL listed according to UL 508A.2. Seam and joints are continuously welded and ground smooth.3. Externally formed body flange around perimeter of enclosure face.4. Single-door enclosure sizes up to 84 inches tall by 36 inches wide.5. Double-door enclosure sizes up to 84 inches tall by 72 inches wide.6. Construct enclosure of steel, not less than 0.067 inch thick.7. Finish enclosure with polyester powder coating that is electrostatically applied and then baked to

bond to substrate.

a. Exterior color shall be manufacturer's standard.b. Interior color shall be standard.

8. Corner-formed flush door, full size of enclosure face, supported using four concealed hinges with easily removable hinge pins.

9. Double-door enclosures with overlapping door design to include unobstructed full-width access.10. Doors with three-point (top, middle, and bottom) latch system with single heavy-duty handle and

integral locking mechanism.11. Removable back covers.12. Removable solid steel internal panel, 0.093 inch thick, with a white polyester powder coating that is

electrostatically applied and then baked to bond to substrate.13. Internal panel mounting studs with hardware, grounding hardware, and sealing washers.14. Grounding stud on enclosure body.15. Thermoplastic pocket on inside of door for record Drawings and Product Data.16. Nominal 4-inch tall integral lifting base, not less than 0.123 inch thick, with predrilled holes for

attachment to mounting surface.17. Each top end of enclosure fitted with lifting tabs, not less than 0.172 inch thick.18. Internal rack-mount shelves and angles as required by application.

H. Freestanding, NEMA 250, Types 4 and 12:1. Enclosure shall be NRTL listed according to UL 508A.2. Seam and joints are continuously welded and ground smooth.3. Externally formed body flange around perimeter of enclosure face.4. Type 12 Enclosure Sizes:

a. Single-door enclosure sizes up to 90 inches tall by 36 inches wide.b. Double-door enclosure sizes up to 90 inches tall by 72 inches wide.

5. Type 4 Enclosure Sizes:

a. Single-door enclosure sizes up to 72 inches tall by 36 inches wide.

6. Construct enclosure of steel, not less than 0.093 inch thick.

Page 95: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 60

7. Finish enclosure with polyester powder coating that is electrostatically applied and then baked to bond to substrate.

a. Exterior color shall be manufacturer's standard.b. Interior color shall be manufacturer's standard.

8. Corner-formed door with continuous perimeter oil-resistant gasket supported using continuous piano hinge full length of door.

9. Doors fitted with three-point (top, middle, and bottom) latch system with latching rod rollers and single, heavy-duty oil-tight handle with integral locking mechanism.

10. Removable solid steel internal panel, 0.093 inch thick, with a white polyester powder coating that is electrostatically applied and then baked to bond to substrate.

11. Internal panel mounting studs with hardware, grounding hardware, and sealing washers.12. Grounding stud on enclosure body.13. Thermoplastic pocket on inside of door for record Drawings and Product Data.14. Top of enclosure fitted with no fewer than two lifting eyes.15. Internal rack-mount shelves and angles as required by application.

I. Accessories:

1. Electric Heater:

a. Aluminum housing with brushed finish.b. Thermostatic control with adjustable set point from zero to 100 deg F.c. Capacity: 100, 200, 400, and 800 W as required by application.d. Fan draws cool air from bottom of enclosure and passes air across thermostat and heating

elements before being released into enclosure cavity. Heated air is discharged through the top of heater.

2. Ventilation Fans, Filtered Intake and Exhaust Grilles:

a. Number and size of fans, filters and grilles as required by application.b. Compact cooling fans engineered for 50,000 hours of continuous operation without

lubrication or service.c. Fans capable of being installed on any surface and in any position within enclosure for spot

cooling or air circulation.d. Thermostatic control with adjustable set point from 32 to 140 deg F.e. Airflow Capacity at Zero Pressure:

1) 4-Inch Fan: 100 cfm.2) 6-Inch Fan: 240 cfm.3) 10-Inch Fan: 560 cfm.

f. Maximum operating temperature of 158 deg F.g. 4-inch fan thermally protected and provided with permanently lubricated ball-bearings.h. 6- and 10-inch fans with ball-bearing construction and split capacitor motors thermally

protected to avoid premature failure.i. Dynamically balanced impellers molded from polycarbonate material.j. Fan furnished with power cord and polarized plug for power connection.k. Fan brackets, finger guards and mounting hardware provided with fans to complete

installation.l. Removable Intake and Exhaust Grilles: ABS plastic or stainless steel of size to match fan

size and suitable for NEMA 250, Types 1 and 12 enclosures.m. Filters for NEMA 250, Type 1 Enclosures: Washable foam or aluminum, of a size to match

intake grille.n. Filters for NEMA 250, Type 12 Enclosures: Disposable, of a size to match intake grille.

3. Air Conditioner:

Page 96: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 61

a. Electric-powered, self-contained air-conditioning unit specially designed for electrical enclosures to maintain temperature inside enclosure below ambient temperature outside enclosure.

b. Thermostatic control with adjustable set point from 60 to 120 deg F.c. Enclosure side or top mounting with unit capacity as required by application.d. Designed for closed-loop cooling with continuous operation in ambient environments up to

125 deg F.e. HFC refrigerant.f. Reusable and washable air filter.g. High-performance, industrial-grade, and high-efficiency fans.h. Furnished with power cord and polarized plug for power connection.i. Condensate management system with base pan side drain.j. Mounting hardware, gaskets, mounting template and instruction manual furnished with unit.k. Outdoor units equipped with head pressure control for low ambient operation, compressor

heater, coated condenser coil and thermostat.

4. Thermoelectric Humidifier:

a. ABS plastic enclosure.b. Capacity of 8 oz. of water per 24 hours.c. Built-in drain captures moisture and plastic hose directs moisture to outside enclosure

through a drain.d. Controlled to maintain enclosure relative humidity at an adjustable set point.e. Unit power supply shall be internally wired to enclosure electrical power source.

5. Framed Fixed Window Kit for NEMA 250, Types 4, 4X, and 12 Enclosures:

a. 0.25-inch thick, scratch-resistant acrylic or polycarbonate window mounted in a metal frame matching adjacent door material.

b. Enclosure types, except NEMA 250 Type 1, shall have a continuous gasket material around perimeter of window and frame to provide watertight seal.

c. Window kit shall be factory or shop installed before shipment to Project.

6. Frameless Fixed Window Kit for NEMA 250, Type 1 Enclosures:

a. 0.125-inch thick, polycarbonate window mounted in enclosure door material.b. Window attached to door with screw fasteners and continuous strip of high-strength double-

sided tape around window perimeter.c. Window kit shall be factory or shop installed before shipment to Project.

7. Frame Fixed or Hinged Window Kit for NEMA 250, Types 1 and 12 Enclosures:

a. 0.25-inch thick, scratch-resistant acrylic or polycarbonate window mounted in a metal frame matching adjacent door material.

b. Enclosure types, except NEMA 250 Type 1, shall have a continuous gasket material around perimeter of window and frame to provide watertight seal.

c. Window kit shall be factory or shop installed before shipment to Project.

8. Bar handle with keyed cylinder lock set.

2.27 RELAYS

A. General-Purpose Relays:1. Relays shall be heavy duty and rated for at least 10 A at 250-V ac and 60 Hz.2. Relays shall be either double pole double throw (DPDT) or three-pole double throw, depending on

the control application.3. Use a plug-in-style relay with an eight-pin octal plug for DPDT relays and an 11-pin octal plug for

three-pole double-throw relays.4. Construct the contacts of either silver cadmium oxide or gold.

Page 97: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 62

5. Enclose the relay in a clear transparent polycarbonate dust-tight cover.6. Relays shall have LED indication and a manual reset and push-to-test button.7. Performance:

a. Mechanical Life: At least 10 million cycles.b. Electrical Life: At least 100,000 cycles at rated load.c. Pickup Time: 15 ms or less.d. Dropout Time: 10 ms or less.e. Pull-in Voltage: 85 percent of rated voltage.f. Dropout Voltage: 50 percent of nominal rated voltage.g. Power Consumption: 2 VA.h. Ambient Operating Temperatures: Minus 40 to 115 deg F

8. Equip relays with coil transient suppression to limit transients to non-damaging levels.9. Plug each relay into an industry-standard, 35-mm DIN rail socket. Plug all relays located in control

panels into sockets that are mounted on a DIN rail.10. Relay socket shall have screw terminals. Mold into the socket the coincident screw terminal

numbers and associated octal pin numbers.

B. Multifunction Time-Delay Relays:1. Relays shall be continuous duty and rated for at least 10 A at 240-V ac and 60 Hz.2. Relays shall be DPDT relay with up to eight programmable functions to provide on/off delay,

interval and recycle timing functions.3. Use a plug-in-style relay with either an 8- or 11-pin octal plug.4. Construct the contacts of either silver cadmium oxide or gold.5. Enclose the relay in a dust-tight cover.6. Include knob and dial scale for setting delay time.7. Performance:

a. Mechanical Life: At least 10 million cycles.b. Electrical Life: At least 100,000 cycles at rated load.c. Timing Ranges: Multiple ranges from 0.1 seconds to 100 minutes.d. Repeatability: Within 2 percent.e. Recycle Time: 45 ms.f. Minimum Pulse Width Control: 50 ms.g. Power Consumption: 5 VA or less at 120-V ac.h. Ambient Operating Temperatures: Minus 40 to 115 deg F.

8. Equip relays with coil transient suppression to limit transients to non-damaging levels.9. Plug each relay into an industry-standard, 35-mm DIN rail socket. Plug all relays located in control

panels into sockets that are mounted on a DIN rail.10. Relay socket shall have screw terminals. Mold into the socket the coincident screw terminal

numbers and associated octal pin numbers.

C. Latching Relays:1. Relays shall be continuous duty and rated for at least 10 A at 250-V ac and 60 Hz.2. Relays shall be either DPDT or three-pole double throw, depending on the control application.3. Use a plug-in-style relay with a multibladed plug.4. Construct the contacts of either silver cadmium oxide or gold.5. Enclose the relay in a clear transparent polycarbonate dust-tight cover.6. Performance:

a. Mechanical Life: At least 10 million cycles.b. Electrical Life: At least 100,000 cycles at rated load.c. Pickup Time: 15 ms or less.d. Dropout Time: 10 ms or less.e. Pull-in Voltage: 85 percent of rated voltage.f. Dropout Voltage: 50 percent of nominal rated voltage.g. Power Consumption: 2 VA.h. Ambient Operating Temperatures: Minus 40 to 115 deg F.

Page 98: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 63

7. Equip relays with coil transient suppression to limit transients to non-damaging levels.8. Plug each relay into an industry-standard, 35-mm DIN rail socket. Plug all relays located in control

panels into sockets that are mounted on a DIN rail.9. Relay socket shall have screw terminals. Mold into the socket the coincident screw terminal

numbers and associated octal pin numbers.

D. Current Sensing Relay:1. Monitors ac current.2. Independent adjustable controls for pickup and dropout current.3. Energized when supply voltage is present and current is above pickup setting.4. De-energizes when monitored current is below dropout current.5. Dropout current is adjustable from 50 to 95 percent of pickup current.6. Include a current transformer, if required for application.7. House current sensing relay and current transformer in its own enclosure. Use NEMA 250, Type 12

enclosure for indoors and NEMA 250, Type 4 for outdoors.

E. Combination On-Off Status Sensor and On-Off Relay:1. Description:

a. On-off control and status indication in a single device.b. LED status indication of activated relay and current trigger.c. Closed-Open-Auto override switch located on the load side of the relay.

2. Performance:

a. Ambient Temperature: Minus 30 to 140 deg F.b. Voltage Rating: Single-phase loads rated for 300-V ac. Three-phase loads rated for 600-

V ac.

3. Status Indication:

a. Current Sensor: Integral sensing for single-phase loads up to 20 A and external solid or split sensing ring for three-phase loads up to 150 A.

b. Current Sensor Range: As required by application.c. Current Set Point: Adjustable.d. Current Sensor Output:

1) Solid-state, single-pole double-throw contact rated for 30-V ac and dc and for 0.4 A.2) Solid-state, single-pole double-throw contact rated for 120-V ac and 1.0 A.3) Analog, zero- to 5- or 10-V dc.4) Analog, 4 to 20 mA, loop powered.

4. Relay: Single-pole double-throw, continuous-duty coil; rated for 10-million mechanical cycles.5. Enclosure: NEMA 250, Type 1 enclosure.

2.28 ELECTRICAL POWER DEVICES

A. Transformers:

1. Transformer shall be sized for the total connected load, plus an additional 25 percent of connected load.

2. Transformer shall be at least 100 VA.3. Transformer shall have both primary and secondary fuses.

B. Power-Line Conditioner:1. General Power-Line Conditioner Requirements:

a. Design to ensure maximum reliability, serviceability and performance.

Page 99: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 64

b. Overall function of the power-line conditioner is to receive raw, polluted electrical power and purify it for use by electronic equipment. The power-line conditioner shall provide isolated, regulated, transient and noise-free sinusoidal power to loads served.

2. Standards: NRTL listed per UL 1012.3. Performance:

a. Single phase, continuous, 100 percent duty rated KVA/KW capacity. Design to supply power for linear or nonlinear, high crest factor, resistive and reactive loads.

b. Automatically regulate output voltage to within 2 percent or better with input voltage fluctuations of plus 10 to minus 20 percent of nominal when system is loaded 100 percent. Use Variable Range Regulation to obtain improved line voltage regulation when operating under less than full load conditions.

1) At 75 Percent Load: Output voltage automatically regulated to within 3 percent with input voltage fluctuations of plus 10 to minus 35 percent of nominal.

2) At 50 Percent Load: Output voltage automatically regulated to within 3 percent with input voltage fluctuations of plus 10 to minus 40 percent of nominal.

3) At 25 Percent Load: Output voltage automatically regulated to within 3 percent with input voltage fluctuations of plus 10 to minus 45 percent of nominal.

c. With input voltage distortion of up to 40 percent, limit the output voltage sine wave to a maximum harmonic content of 5 percent.

d. Automatically regulate output voltage to within 2.5 percent when load (resistive) changes from zero percent to 100 percent to zero percent.

e. Output voltage returns to 95 percent of nominal level within two cycles and to 100 percent within three cycles when the output is taken from no load to full resistive load or vice-versa. Recovery from partial resistive load changes is corrected in a shorter period of time.

f. K Factor: 30, designed to operate with nonlinear, non-sinusoidal, high crest factor loads without overheating.

g. Input power factor within 0.95 approaching unity with load power factor as poor as 0.6.h. Attenuate load-generated odd current harmonics 23 dB at the input.i. Electrically isolate the primary from the secondary. Meet isolation criteria as defined in

NFPA 70, Article 250-5D.j. Lighting and Surge Protection: Compares to UL 1449 rating of 330 V when subjected to

Category B3 (6000 V/3000 A) combination waveform as established by IEEE C62.41.k. Common-mode noise attenuation of 140 dB.l. Transverse-mode noise attenuation of 120 dB.m. With loss of input power for up to 16.6 ms, the output sine wave remains at usable ac

voltage levels.n. Reliability of 200,000 hours' MTBF.o. At full load, when measured at 1-m distance, audible noise is not to exceed 54 dB.p. Approximately 92 percent efficient at full load.

4. Transformer Construction:

a. Ferroresonant, dry type, convection cooled, 600V class. Transformer windings of Class H (220 deg C) insulated copper.

b. Use a Class H installation system throughout with operating temperatures not to exceed 150 deg C over a 40-deg C ambient temperature.

c. Configure transformer primary for multi-input voltage. Include input terminals for source conductors and ground.

d. Manufacture transformer core using M-6 grade, grain-oriented, stress-relieved transformer steel.

e. Configure transformer secondary in a 240/120-V split with a 208-V tap or straight 120 V, depending on power output size.

f. Electrically isolate the transformer secondary windings from the primary windings. Bond neutral conductor to cabinet enclosure and output neutral terminal.

g. Include interface terminals for output power hot, neutral and ground conductors.h. Label leads, wires and terminals to correspond with circuit wiring diagram.i. Vacuum impregnate transformer with epoxy resin.

Page 100: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 65

5. Cabinet Construction:

a. Design for panel or floor mounting.b. NEMA 250, Type 1, general-purpose, indoor enclosure.c. Manufacture the cabinet from heavy gauge steel complying with UL 50.d. Include a textured baked-on paint finish.

C. Transient Voltage Suppression and High-Frequency Noise Filter Unit:1. The maximum continuous operating voltage shall be at least 125 percent.2. The operating frequency range shall be 47 to 63 Hz.3. Protection modes according to NEMA LS-1.4. The rated single-pulse surge current capacity, for each mode of protection, shall be no less than

the following:

a. Line to Neutral: 45,000 A.b. Neutral to Ground: 45,000 A.c. Line to Ground: 45,000 A.d. Per Phase: 90,000 A.

5. Clamping voltages shall be in compliance with test and evaluation procedures defined in NEMA LS-1. Maximum clamping voltage shall be as follows:

a. Line to Neutral: 360 V.b. Line to Ground: 360 V.c. Neutral to Ground: 360 V.

6. Electromagnetic interference and RF interference noise rejection or attenuation values shall comply with test and evaluation procedures defined in NEMA LS-1.

a. Line to Neutral:

1) 100 kHz: 42 dB.2) 1 MHz: 25 dB.3) 10 MHz: 21 dB.4) 100 MHz: 36 dB.

b. Line to Ground:

1) 100 kHz: 16 dB.2) 1 MHz: 55 dB.3) 10 MHz: 81 dB.4) 100 MHz: 80 dB.

7. Unit shall have LED status indicator that extinguishes to indicate a failure.8. Unit shall be listed by an NRTL as a transient voltage surge suppressor per UL 1449, and as an

electromagnetic interference filter per UL 1283.9. Unit shall not generate any appreciable magnetic field.10. Unit shall not generate an audible noise.

D. DC Power Supply:1. Plug-in style suitable for mating with a standard eight-pin octal socket. Include the power supply

with a mating mounting socket.2. Enclose circuitry in a housing.3. Include both line and load regulation to ensure a stable output. To protect both the power supply

and the load, power supply shall have an automatic current limiting circuit.4. Performance:

a. Output voltage nominally 25-V dc within 5 percent.b. Output current up to 100 mA.c. Input voltage nominally 120-V ac, 60 Hz.

Page 101: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 66

d. Load regulation within 0.5 percent from zero- to 100-mA load.e. Line regulation within 0.5 percent at a 100-mA load for a 10 percent line change.f. Stability within 0.1 percent of rated volts for 24 hours after a 20-minute warmup.

2.29 UNINTERRUPTABLE POWER SUPPLY (UPS) UNITS FOR WORKSTATIONS

A. 250 through 1000 VA:1. UPS units shall provide continuous, regulated output power without using their batteries during

brown-out, surge, and spike conditions.2. Load served shall not exceed 75 percent of UPS rated capacity, including power factor of

connected loads.

a. Larger-capacity units shall be provided for systems with larger connected loads.b. UPS shall provide five minutes of battery power.

3. Performance:

a. Input Voltage: Single phase, 120- or 230-V ac, compatible with field power source.b. Load Power Factor Range (Crest Factor): 0.65 to 1.0.c. Output Voltage: 101- to 132-V ac, while input voltage varies between 89 and 152-V ac.d. On Battery Output Voltage: Sine wave.e. Inverter overload capacity shall be minimum 150 percent for 30 seconds.f. Recharge time shall be a maximum of six hours to 90 percent capacity after full discharge to

cutoff.g. Transfer Time: 6 ms.h. Surge Voltage Withstand Capacity: IEEE C62.41, Categories A and B; 6 kV/200 and 500 A;

100-kHz ringwave.

4. UPS shall be automatic during fault or overload conditions.5. Unit with integral line-interactive, power condition topology to eliminate all power contaminants.6. Include front panel with power switch and visual indication of power, battery, fault and temperature.7. Unit shall include an audible alarm of faults and front panel silence feature.8. Unit with four NEMA WD 1, NEMA WD 6 Configuration 5-15R receptacles.9. UPS shall include dry contacts (digital output points) for low battery condition and battery-on

(primary utility power failure) and connect the points to the DDC system.10. Batteries shall be sealed lead-acid type and be maintenance free. Battery replacement shall be

front accessible by user without dropping load.11. Include tower models installed in ventilated cabinets to the particular installation location.

B. 1000 through 3000 VA:1. UPS units shall provide continuous, regulated output power without using their batteries during

brown-out, surge, and spike conditions.2. Load served shall not exceed 75 percent of UPS rated capacity, including power factor of

connected loads.

a. Larger-capacity units, or multiple units, shall be provided for systems with larger connected loads.

b. UPS shall provide 10 minutes of battery power.

3. Performance:

a. Input Voltage: Single phase, 120-V ac, plus 20 to minus 30 percent.b. Power Factor: Minimum 0.97 at full load.c. Output Voltage: Single phase, 120-V ac, within 3 percent, steady state with rated output

current of 10.0 A, 30.0-A peak.d. Inverter overload capacity shall be minimum 150 percent for 30 seconds.e. Recharge time shall be a maximum of eight hours to 90 percent capacity.

4. UPS bypass shall be automatic during fault or overload conditions.

Page 102: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 67

5. UPS shall include dry contacts (digital output points) for low battery condition and battery-on (primary utility power failure) and connect the points to the DDC system.

6. Batteries shall be sealed lead-acid type and be maintenance free.7. Include tower models installed in ventilated cabinets or rack models installed on matching racks, as

applicable to the particular installation location and space availability/configuration.

2.30 PIPING AND TUBING

A. Pneumatic, and Pressure Instrument Signal Air, Tubing and Piping:

1. Products in this paragraph are intended for use with the following:

a. Main air and signal air to pneumatically controlled instruments, actuators and other control devices and accessories.

b. Signal air between pressure instruments, such as sensors, switches, transmitters, controllers and accessories.

2. Copper Tubing:

a. Seamless phosphor deoxidized copper, soft annealed or drawn tempered, with chemical and physical properties according to ASTM B75.

b. Performance, dimensions, weight and tolerance according to ASTM B280.c. Diameter, as required by application, not less than nominal 0.25 inch.d. Wall thickness, as required by the application, but not less than 0.030 inch.

3. Copper Tubing Connectors and Fittings:

a. Brass, compression type.

b. Brass, solder-joint type.

4. Galvanized-Steel Piping:

a. Galvanized pipe shall be ASTM A53/A53M, Schedule 40.b. Fittings, galvanized malleable iron, ASME B16.3, Class 150.

5. Polyethylene Tubing:

a. Fire-resistant black virgin polyethylene according to ASTM D1248, Type 1, Class C and Grade 5.

b. Tubing shall comply with stress crack test according to ASTM D1693.c. Diameter, as required by application, of not less than nominal 0.25 inch.

6. Polyethylene Tubing Connectors and Fittings:

a. Brass, barbered fittings.

b. Brass, compression type.

B. Process Tubing:

1. Products in this paragraph are intended for signals to instruments connected to liquid and steam systems.

2. Copper Tubing:

a. Seamless phosphor deoxidized copper, soft annealed or drawn tempered with chemical and physical properties according to ASTM B75.

b. Performance, dimensions, weight and tolerance according to ASTM B280.

Page 103: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 68

c. Diameter, as required by application, of not less than nominal 0.25 inch .d. Wall thickness, as required by application, but not less than 0.030 inch .

3. Copper Tubing Connectors and Fittings:

a. Brass, compression type.

b. Brass, solder-joint type.

4. Stainless-Steel Tubing:

a. Seamless Type 316 stainless steel, Grade TP, cold drawn, annealed and pickled, free from scale.

b. Chemical and physical properties according to ASTM A269.c. Diameter, as required by application, of not less than nominal 0.25 inch.d. Wall thickness, as required by application, but not less than 0.035 inch.e. Furnish stainless-steel tubing in 20-foot straight random lengths.

5. Stainless-Steel Tubing Connectors and Fittings:

a. Connectors and fittings shall be stainless steel, with stainless-steel collets, flareless type.

b. Connect instruments to tubing with connectors having compression connector on one end and IPS or NPT thread on other end.

2.31 CONTROL WIRE AND CABLE

A. Wire: Single conductor control wiring above 24 V.

1. Wire size shall be at least No. 18 AWG.2. Conductor shall be 7/24 soft annealed copper strand with 2- to 2.5-inch lay.3. Conductor insulation shall be 600 V, Type THWN or Type THHN, and 90 deg C according to

UL 83.4. Conductor colors shall be black (hot), white (neutral), and green (ground).5. Furnish wire on spools.

B. Single Twisted Shielded Instrumentation Cable above 24 V:

1. Wire size shall be a minimum No. 18 AWG.2. Conductors shall be a twisted, 7/24 soft annealed copper strand with a 2- to 2.5-inch lay.3. Conductor insulation shall have a Type THHN/THWN or Type TFN rating.4. Shielding shall be 100 percent type, 0.35/0.5-mil aluminum/Mylar tape, helically applied with 25

percent overlap, and aluminum side in with tinned copper drain wire.5. Outer jacket insulation shall have a 600-V, 90-deg C rating and shall be Type TC cable.6. For twisted pair, conductor colors shall be black and white. For twisted triad, conductor colors shall

be black, red and white.7. Furnish wire on spools.

C. Single Twisted Shielded Instrumentation Cable 24 V and Less:

1. Wire size shall be a minimum No. 18 AWG.2. Conductors shall be a twisted, 7/24 soft annealed copper stranding with a 2- to 2.5-inch lay.3. Conductor insulation shall have a nominal 15-mil thickness, constructed from flame-retardant PVC.4. Shielding shall be 100 percent type, 1.35-mil aluminum/polymer tape, helically applied with 25

percent overlap, and aluminum side in with tinned copper drain wire.5. Outer jacket insulation shall have a 300-V, 105-deg C rating and shall be Type PLTC cable.6. For twisted pair, conductor colors shall be black and white. For twisted triad, conductor colors shall

be black, red and white.7. Furnish wire on spools.

Page 104: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 69

D. LAN and Communication Cable: Comply with DDC system manufacturer requirements for network being installed.

1. Cable shall be balanced twisted pair.2. Comply with the following requirements and for balanced twisted pair cable described in Section

260523 "Control-Voltage Electrical Power Cables."

a. Cable shall be plenum rated.b. Cable shall have a unique color that is different from other cables used on Project.

2.32 RACEWAYS

A. Comply with requirements in Section 260533 "Raceways and Boxes for Electrical Systems" for electrical power raceways and boxes.

B. Comply with requirements in Section 270528 "Pathways for Communications Systems" for raceways for balanced twisted pair cables and optical fiber cables.

2.33 OPTICAL FIBER CABLE AND CONNECTORS

A. Comply with requirements in Section 271323 "Communications Optical Fiber Backbone Cabling" for optical fiber backbone cabling and connectors.

B. Comply with requirements in Section 271523 "Communications Optical Fiber Horizontal Cabling" for optical fiber horizontal cabling and connectors.

2.34 ACCESSORIES

A. Pressure Electric Switches:

1. Diaphragm-operated snap acting switch.2. Set point adjustable from 3 to 20 psig .3. Differential adjustable from 2 to 6 psig.4. Rated for resistance loads at 120-V ac.5. Body and switch housing shall be metal.

B. Damper Blade Limit Switches:

1. Sense positive open and/or closed position of the damper blades.2. NEMA 250, Type 13, oil-tight construction.3. Arrange for the mounting application.4. Additional waterproof enclosure when required by its environment.5. Arrange to prevent "over-center" operation.

C. I/P and E/P Transducers:

1. Commercial Grade:a. The transducer shall convert an AO signal to a stepped pneumatic signal. Unless otherwise

required by the operating sequence, use a 3- to 15-psig pneumatic signal for pneumatic actuation.

b. Construct the entire assembly so that shock and vibration will neither harm the transducer nor affect its accuracy.

c. Transducer shall have auto/manual output switch, manual output control and an output pressure gage.

d. Accuracy: Within 1.0 percent of the output span.e. Linearity: Within 0.5 percent of the output span.

Page 105: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 70

f. Output Capacity: Not less than 550 scim at 15 psig.g. Transducer shall have separate zero and span calibration adjustments.h. The transducer shall withstand up to 40 psig of supply pressure without damage.i. For use on only modulating pneumatic outputs that are associated with terminal units,

including fan-coil units, VAV units, and unit heaters.

2. Industrial Grade:a. The transducer shall convert an AO signal to a proportional pneumatic signal. Unless

otherwise required by the operating sequence, use a 3- to 15-psig pneumatic signal for pneumatic actuation. A stepped pneumatic signal is unacceptable.

b. Construct the entire assembly so that shock and vibration will neither harm the transducer nor affect its accuracy.

c. Suitable for operation in an ambient temperature range of minus 40 to 150 deg F.d. Accuracy: Within 0.5 percent of the output span.e. Linearity: Within 0.5 percent of the output span.f. Output Capacity: Not less than 5 scfm.g. Transducer shall have zero and span calibration adjustments.h. The transducer shall withstand up to 50 psig of supply pressure without damage.i. For use on all modulating pneumatic outputs, not requiring a commercial-grade transducer.

D. E/P Switch:

1. Construct the body of cast aluminum or brass; three pipe body (common, normally open, and normally closed).

2. Internal construction of steel, copper or brass.3. Air Connections: Barb.4. Rating of 30 psig when installed in systems below 25 psig and of 150 psig when installed in

systems above 25 psig.5. Include coil transient suppression.

E. Instrument Enclosures:1. Include instrument enclosure for secondary protection to comply with requirements indicated in

"Performance Requirements" Article.2. NRTL listed and labeled to UL 50.3. Sized to include at least 25 percent spare area on subpanel.4. Instrument(s) mounted within enclosure on internal subpanel(s).5. Enclosure face with engraved, laminated phenolic nameplate for each instrument within enclosure.6. Enclosures housing pneumatic instruments shall include main pressure gage and a branch

pressure gage for each pneumatic device, installed inside.7. Enclosures housing multiple instruments shall route tubing and wiring within enclosure in a raceway

having a continuous removable cover.8. Enclosures larger than 12 inches shall have a hinged full-size face cover.9. Equip enclosure with lock and common key.

F. Manual Valves:

1. Needle Type:a. PTFE packing.b. Construct of brass for use with copper and polyethylene tubing and of stainless steel for use

with stainless-steel tubing.c. Aluminum T-bar handle.d. Include tubing connections.

2. Ball Type:a. Body: Bronze ASTM B62 or ASTM B61.b. Ball: Type 316 stainless steel.c. Stem: Type 316 stainless steel.d. Seats: Reinforced PTFE.e. Packing Ring: Reinforced PTFE.f. Lever: Stainless steel with a vinyl grip.g. 600 WOG.

Page 106: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 71

h. Threaded end connections.

G. Wall-Mounted Portable Workstation Cabinet:1. Surface-mounted wall cabinet for tilt-out operation of laptop computers and large-format mobile

devices.2. Cabinet shall have a load limit of 50 lb.3. Cabinet shall include the following:

a. Oil-filled dampers for controlled lowering of equipment to operational position.b. 3RU EIA mounting rails.c. Removable laptop shelf.d. Separate top compartment with mounting area, hinged rail and security lock.e. Front ventilation slots.f. Knockouts for conduit connections on top and bottom of cabinet.

4. Cabinet shall be constructed of steel and painted with a powder-coat epoxy.5. Inside center of backbox shall have provision to mount a field-furnished and -installed, single gang

electrical outlet box.

2.35 IDENTIFICATION

A. Instrument Air Pipe and Tubing:

1. Engraved tag shall bear the following information:

a. Service (Example): "Instrument Air."b. Pressure Range (Example): 0 to 30 psig.

2. Letter size shall be a minimum of 0.25 inch high.3. Tag shall consist of white lettering on blue background.4. Tag shall be engraved phenolic consisting of three layers of rigid laminate. Top and bottom layers

are color-coded blue with contrasting white center exposed by engraving through outer layer.5. Include tag with a brass grommet, chain and S-hook.

B. Control Equipment, Instruments, and Control Devices:

1. Laminated acrylic or melamine plastic sign bearing unique identification.

a. Include instruments with unique identification identified by equipment being controlled or monitored, followed by point identification.

2. Letter size shall be as follows:

a. Operator Workstations: Minimum of 0.5 inch high.b. Servers: Minimum of 0.5 inch high.c. Printers: Minimum of 0.5 inch high.d. DDC Controllers: Minimum of 0.5 inch high.e. Gateways: Minimum of 0.5 inch high.f. Repeaters: Minimum of 0.5 inch high.g. Enclosures: Minimum of 0.5 inch high.h. Electrical Power Devices: Minimum of 0.25 inch high.i. UPS units: Minimum of 0.5 inch high.j. Accessories: Minimum of 0.25 inch high.k. Instruments: Minimum of 0.25 inch high.l. Control Damper and Valve Actuators: Minimum of 0.25 inch high.

3. Legend shall consist of white lettering on black background.

Page 107: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 72

4. Laminated acrylic or melamine plastic sign shall be engraved phenolic consisting of three layers of rigid laminate. Top and bottom layers are color-coded black with contrasting white center exposed by engraving through outer layer and shall be fastened with drive pins.

5. Instruments, control devices and actuators with Project-specific identification tags having unique identification numbers following requirements indicated and provided by original manufacturer do not require additional identification.

C. Valve Tags:

1. Brass tags and brass chains attached to valve.2. Tags shall be at least 1.5 inches in diameter.3. Include tag with unique valve identification indicating control influence such as flow, level, pressure,

or temperature; followed by location of valve, and followed by three-digit sequential number. For example: TV-1.001.

4. Valves with Project-specific identification tags having unique identification numbers following requirements indicated and provided by original manufacturer do not require an additional tag.

D. Raceway and Boxes:

1. Comply with requirements for identification specified in Section 260553 "Identification for Electrical Systems."

2. Paint cover plates on junction boxes and conduit same color as the tape banding for conduits. After painting, label cover plate "HVAC Controls," using an engraved phenolic tag.

3. For raceways housing pneumatic tubing, add a phenolic tag labeled "HVAC Instrument Air Tubing."4. For raceways housing air signal tubing, add a phenolic tag labeled "HVAC Air Signal Tubing."

E. Equipment Warning Labels:

1. Self-adhesive label with pressure-sensitive adhesive back and peel-off protective jacket.2. Lettering size shall be at least 14-point type with white lettering on red background.3. Warning label shall read "CAUTION-Equipment operated under remote automatic control and may

start or stop at any time without warning. Switch electric power disconnecting means to OFF position before servicing."

4. Lettering shall be enclosed in a white line border. Edge of label shall extend at least 0.25 inch beyond white border.

2.36 SOURCE QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to evaluate the following according to industry standards for each product, and to verify DDC system reliability specified in performance requirements:

1. DDC controllers.2. Gateways.3. Routers.4. Operator workstations.

B. Products and materials will be considered defective if they do not pass tests and inspections.

C. Prepare test and inspection reports.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

Page 108: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 73

1. Verify compatibility with and suitability of substrates.

B. Examine roughing-in for products to verify actual locations of connections before installation.

1. Examine roughing-in for instruments installed in piping to verify actual locations of connections before installation.

2. Examine roughing-in for instruments installed in duct systems to verify actual locations of connections before installation.

C. Examine walls, floors, roofs, and ceilings for suitable conditions where product will be installed.

D. Prepare written report, endorsed by Installer, listing conditions detrimental to performance of the Work.

E. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 DDC SYSTEM INTERFACE WITH OTHER SYSTEMS AND EQUIPMENT

A. Communication Interface to Equipment with Integral Controls:

1. DDC system shall have communication interface with equipment having integral controls and having a communication interface for remote monitoring or control.

2. Equipment to Be Connected:

a. Domestic water booster pumps.b. Air-terminal units.c. Kitchen hoods.d. Chillerse. Cooling towersf. Heat wheels and heat exchangers g. Air-handling units h. Roof-top units i. Variable-frequency controllers j. UPS k. Refrigerant monitoring.

B. Communication Interface to Other Building Systems:

1. DDC system shall have a communication interface with systems having a communication interface.2. Systems to Be Connected:

a. Power monitoring b. Lighting controls c. Fire-alarm system d. Access controls e. Intrusion detection

3.3 GENERAL INSTALLATION REQUIREMENTS

A. Install products to satisfy more stringent of all requirements indicated.

B. Install products level, plumb, parallel, and perpendicular with building construction.

C. If codes and referenced standards are more stringent than requirements indicated, comply with requirements in codes and referenced standards.

D. Fabricate openings and install sleeves in ceilings, floors, roof, and walls required by installation of products. Before proceeding with drilling, punching, and cutting, check for concealed work to avoid damage. Patch, flash, grout, seal, and refinish openings to match adjacent condition.

Page 109: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 74

E. Seal penetrations made in acoustically rated assemblies. Comply with requirements in Section 079200 "Joint Sealants."

F. Welding Requirements:

1. Restrict welding and burning to supports and bracing.2. No equipment shall be cut or welded without approval. Welding or cutting will not be approved if

there is risk of damage to adjacent Work.3. Welding, where approved, shall be by inert-gas electric arc process and shall be performed by

qualified welders according to applicable welding codes.4. If requested on-site, show satisfactory evidence of welder certificates indicating ability to perform

welding work intended.

G. Fastening Hardware:

1. Stillson wrenches, pliers, and other tools that damage surfaces of rods, nuts, and other parts are prohibited for work of assembling and tightening fasteners.

2. Tighten bolts and nuts firmly and uniformly. Do not overstress threads by excessive force or by oversized wrenches.

3. Lubricate threads of bolts, nuts and screws with graphite and oil before assembly.

H. If product locations are not indicated, install products in locations that are accessible and that will permit service and maintenance from floor, equipment platforms, or catwalks without removal of permanently installed furniture and equipment.

I. Corrosive Environments:

1. Avoid or limit use of materials in corrosive airstreams and environments, including, but not limited to, the following:

a. Laboratory exhaust-air streams.b. Process exhaust-air streams.

2. When conduit is in contact with a corrosive airstream and environment, use Type 316 stainless-steel conduit and fittings or conduit and fittings that are coated with a corrosive-resistant coating that is suitable for environment. Comply with requirements for installation of raceways and boxes specified in Section 260533 "Raceways and Boxes for Electrical Systems."

3. Where instruments are located in a corrosive airstream and are not corrosive resistant from manufacturer, field install products in NEMA 250, Type 4X enclosure constructed of Type 316L stainless steel.

3.4 WORKSTATION INSTALLATION

A. Desktop Workstations Installation:

1. Install workstations)at locations directed by Owner.2. Install multiple-receptacle power strip with cord for use in connecting multiple workstation

components to a single duplex electrical power receptacle.3. Install software on workstations and verify software functions properly.4. Develop Project-specific graphics, trends, reports, logs and historical database.5. Power each workstation through a dedicated UPS unit. Locate UPS adjacent to workstation.

B. Portable Workstations Installation:

1. Turn over portable workstations to Owner at Substantial Completion.2. Install software on workstation(s) and verify software functions properly.

C. Color Graphics Application:

Page 110: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 75

1. Use system schematics indicated as starting point to create graphics.2. Develop Project-specific library of symbols for representing system equipment and products.3. Incorporate digital images of Project-completed installation into graphics where beneficial to

enhance effect.4. Submit sketch of graphic layout with description of all text for each graphic for Owner's review

before creating graphic using graphics software.5. Seek Owner input in graphics development once using graphics software.6. Final editing shall be done on-site with Owner's[ and Architect's]review and feedback.7. Refine graphics as necessary for Owner acceptance.8. On receiving Owner acceptance, print a hard copy for inclusion in operation and maintenance

manual. Prepare a scanned copy PDF file of each graphic and include with softcopy of DDC system operation and maintenance manual.

D. Wall-Mounted Portable Operator's Workstation Cabinet Installation:1. Install wall-mounted portable operator's workstation cabinets at following locations and at locations

directed by Owner:

a. Each mechanical room.b. Chiller room.c. Boiler room.

2. Connect each cabinet to 120-V, single-phase, 60Hz field power source, and install single gang electrical box with NEMA WD 6, Type 20R duplex receptacle and metal cover plate in cabinet. Comply with requirements in Section 262726 "Wiring Devices."

3. Connect each cabinet to Ethernet network and install an Ethernet network port for connection to portable operator workstation Ethernet cable. Comply with requirements in Section 271513 "Communications Copper Horizontal Cabling."

3.5 POT INSTALLATION

A. Install two portable operator terminals.

B. Turn over POTs to Owner at Substantial Completion.

C. Install software on each POT and verify that software functions properly.

3.6 GATEWAY INSTALLATION

A. Install gateways if required for DDC system communication interface requirements indicated.

1. Install gateways required to suit indicated requirements.

B. Test gateway to verify that communication interface functions properly.

3.7 ROUTER INSTALLATION

A. Install routers if required for DDC system communication interface requirements indicated.

1. Install router(s) required to suit indicated requirements.

B. Test router to verify that communication interface functions properly.

3.8 CONTROLLER INSTALLATION

A. Install controllers in enclosures to comply with indicated requirements.

Page 111: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 76

B. Connect controllers to field power supply and to UPS units where indicated.

C. Install controller with latest version of applicable software and configure to execute requirements indicated.

D. Test and adjust controllers to verify operation of connected I/O to achieve performance indicated requirements while executing sequences of operation.

E. Installation of Network Controllers:

1. Quantity and location of network controllers shall be determined by DDC system manufacturer to satisfy requirements indicated.

2. Install controllers in a protected location that is easily accessible by operators.3. Top of controller shall be within 72 inches of finished floor.

F. Installation of Programmable Application Controllers:

1. Quantity and location of programmable application controllers shall be determined by DDC system manufacturer to satisfy requirements indicated.

2. Install controllers in a protected location that is easily accessible by operators.3. Top of controller shall be within 72 inches above top of finished floor.

G. Application-Specific Controllers:

1. Quantity and location of application-specific controllers shall be determined by DDC system manufacturer to satisfy requirements indicated.

2. For controllers not mounted directly on equipment being controlled, install controllers in a protected location that is easily accessible by operators.

3.9 INSTALLATION OF WIRELESS ROUTERS FOR OPERATOR INTERFACE

A. Install wireless routers to achieve optimum performance and best possible coverage.

B. Mount wireless routers in a protected location that is within 60 inches of floor and easily accessible by operators.

C. Connect wireless routers to field power supply and to UPS units if network controllers are powered through UPS units.

D. Install wireless router with latest version of applicable software and configure wireless router with WPA2 security and password protection. Create access password with not less than 12 characters consisting of letters and numbers and at least one special character. Document password in operations and maintenance manuals for reference by operators.

E. Test and adjust wireless routers for proper operation with portable workstation and other wireless devices intended for use by operators.

3.10 ENCLOSURES INSTALLATION

A. Install the following items in enclosures, to comply with indicated requirements:

1. Gateways.2. Routers.3. Controllers.4. Electrical power devices.5. UPS units.6. Relays.7. Accessories.

Page 112: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 77

8. Instruments.9. Actuators

B. Attach wall-mounted enclosures to wall using the following types of steel struts:

1. For NEMA 250, Type 1 Enclosures: Use galvanized-steel strut and hardware.2. For NEMA 250, Type 4 and Type 4X Enclosures and Enclosures Located Outdoors: Use stainless-

steel strut and hardware.3. Install plastic caps on exposed cut edges of strut.

C. Align bottom of adjacent enclosures of like size.

D. Install floor-mounted enclosures located in mechanical equipment rooms on concrete housekeeping pads. Attach enclosure legs using galvanized steel anchors.

E. Install continuous and fully accessible wireways to connect conduit, wire, and cable to multiple adjacent enclosures. Wireway used for application shall have protection equal to NEMA 250 rating of connected enclosures.

3.11 ELECTRIC POWER CONNECTIONS

A. Connect electrical power to DDC system products requiring electrical power connections.

B. Design of electrical power to products not indicated with electric power is delegated to DDC system provider and installing trade. Work shall comply with NFPA 70 and other requirements indicated.

C. Comply with requirements in Section 262816 "Enclosed Switches and Circuit Breakers" for electrical power circuit breakers.

D. Comply with requirements in Section 260519 "Low-Voltage Electrical Power Conductors and Cables" for electrical power conductors and cables.

E. Comply with requirements in Section 260533 "Raceways and Boxes for Electrical Systems" for electrical power raceways and boxes.

3.12 IDENTIFICATION

A. Identify system components, wiring, cabling, and terminals. Comply with requirements in Section 260553 "Identification for Electrical Systems" for identification products and installation.

B. Install laminated acrylic or melamine plastic signs with unique identification on face for each of the following:

1. Operator workstation.2. Gateway.3. Router.4. Protocol analyzer.5. DDC controller.6. Enclosure.7. Electrical power device.8. UPS unit.9. Accessory.

C. Install unique instrument identification on face of each instrument connected to a DDC controller.

D. Install unique identification on face of each control damper and valve actuator connected to a DDC controller.

Page 113: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 78

E. Where product is installed above accessible tile ceiling, also install matching identification on face of ceiling grid located directly below.

F. Where product is installed above an inaccessible ceiling, also install identification on face of access door directly below.

G. Warning Labels and Signs:

1. Shall be permanently attached to equipment that can be automatically started by DDC control system.

2. Shall be located in highly visible location near power service entry points.

3.13 NETWORK INSTALLATION

A. Install balanced twisted pair or optical fiber cable when connecting between the following network devices located in same building:

1. Operator workstations.2. Operator workstations and network controllers.3. Network controllers.

B. Install balanced twisted pair or copper cable (as required by equipment) when connecting between the following:

1. Gateways.2. Gateways and network controllers or programmable application controllers.3. Routers.4. Routers and network controllers or programmable application controllers.5. Network controllers and programmable application controllers.6. Programmable application controllers.7. Programmable application controllers and application-specific controllers.8. Application-specific controllers.

C. Install cable in continuous raceway.

1. Where indicated on Drawings, cable trays may be used for copper cable in lieu of conduit.

3.14 NETWORK NAMING AND NUMBERING

A. Coordinate with Owner and provide unique naming and addressing for networks and devices.

B. ASHRAE 135 Networks:

1. MAC Address:

a. Every network device shall have an assigned and documented MAC address unique to its network.

b. Ethernet Networks: Document MAC address assigned at its creation.c. ARCNET or MS/TP networks: Assign from 00 to 64.

2. Network Numbering:

a. Assign unique numbers to each new network.b. Provide ability for changing network number through device switches or operator interface.c. DDC system, with all possible connected LANs, can contain up to 65,534 unique networks.

3. Device Object Identifier Property Number:

Page 114: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 79

a. Assign unique device object identifier property numbers or device instances for each device network.

b. Provide for future modification of device instance number by device switches or operator interface.

c. LAN shall support up to 4,194,302 unique devices.

4. Device Object Name Property Text:

a. Device object name property field shall support 32 minimum printable characters.b. Assign unique device "Object Name" property names with plain-English descriptive names

for each device.

1) Example 1: Device object name for device controlling boiler plant at Building 1000 would be "HW System B1000."

2) Example 2: Device object name for a VAV terminal unit controller could be "VAV unit 102".

5. Object Name Property Text for Other Than Device Objects:

a. Object name property field shall support 32 minimum printable characters.b. Assign object name properties with plain-English names descriptive of application.

1) Example 1: "Zone 1 Temperature."2) Example 2 "Fan Start and Stop."

3.15 PIPING AND TUBING INSTALLATION

A. Above-Grade Pneumatic and Air Signal Piping and Tubing Installation:

1. Material Application:

a. Install copper tubing, except as follows:

1) Tubing Exposed to View: Polyethylene tubing installed in raceways may be used in lieu of copper tubing.

2) Concealed Tubing: Polyethylene tubing may be used in lieu of copper tubing when concealed behind accessible ceilings.

b. Install copper tubing for sizes up through NPS 1 and install galvanized-steel pipe for larger sizes, except as follows:

1) Tubing Exposed to View: Polyethylene tubing installed in raceways may be used in lieu of copper tubing where exposed to view.

2) Concealed Tubing: Polyethylene tubing may be used in lieu of copper tubing when concealed behind accessible ceilings.

c. Install drawn-temper copper tubing, except within 36 inches of device terminations tubing shall be annealed-tempered copper tubing.

d. Install compression fittings to connect copper tubing to instruments, control devices, and accessories.

e. Install barbed or compression fittings to connect polyethylene tubing to instruments, control devices, and accessories.

2. Routing:

a. Do not expose tubing in finished spaces, such as spaces with ceilings; occupied spaces, offices, and conference rooms, unless expressly approved in writing by Architect. Tubing may be exposed in areas without ceilings.

Page 115: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 80

b. Where tubing is installed in finished occupied spaces, install the tubing in surface metal raceway with appropriate fittings only where not feasible to conceal in wall, above ceiling or behind architectural enclosures or covers.

c. Install piping and tubing plumb and parallel to and at right angles with building construction.d. Install multiple runs of tubing or piping in equally spaced parallel lines.e. Piping and tubing shall not interfere with access to valves, equipment, duct and equipment

access doors, or obstruct personnel access and passageways of any kind.f. Coordinate with other trades before installation to prevent proposed piping and tubing from

interfering with pipe, duct, terminal equipment, light fixtures, conduit and cable tray space. If changes to Shop Drawings are necessary due to field coordination, document changes on record Drawings.

g. Install vibration loops in copper tubing when connecting to instrument and actuators that vibrate.

3. Support:

a. According to MSS SP-69, Table 3, except support spacing shall not exceed 60 inches.b. Support copper tubing with copper hangers, clips, and tube trays.c. Do not use tape for support or dielectric isolation.d. Install supports at each change in direction and at each branch take off.e. Attached supports to building structure independent of work of other trades. Support from

ducts, pipes, cable trays, and conduits is prohibited.f. Attached support from building structure with threaded rods, structural shapes, or channel

strut.g. Install and brace supports to carry static load plus a safety margin, which will allow tubing to

be serviced.h. Brace supports to prevent lateral movement.i. Paint steel support members that are not galvanized or zinc coated.j. Support polyethylene tubing same as copper tubing.

4. Do not attach piping and tubing to equipment that may be removed frequently for maintenance or that may impart vibration and expansion from temperature change.

5. Protect exposed tubing in mechanical equipment rooms from mechanical damage within 76 inches above floor. Use aluminum channel reversed and secured over tubing to protect tubing from damage.

6. Joining and Makeup:

a. Where joining and mating dissimilar metals where galvanic action could occur, install dielectric isolation.

b. Install a dirt leg with an isolation valve and threaded plug at each main air, connection to a panel, pneumatic pilot positioner and PRV station.

c. Make threaded joints for connecting to instrument equipment with connectors with a compression tubing connector on one end and threaded connection on other end.

d. Make tubing bends with a tube-bending tool. Hard bends, wrinkled or flattened bends are unacceptable.

e. Install tube fittings according to manufacturer's written instructions.f. Do not make tubing connections to a fitting before completing makeup of the connection.g. Align tubing with the fitting. Avoid springing tube into position, as this may result in

excessive stress on both tubing and fitting with possible resulting leaks.h. Do not install fittings close to a bend. A length of straight tubing, not deformed by bending,

is required for a proper connection.i. Check tubing for correct diameter and wall thickness.j. Tube ends shall be cut square and deburred. Exercise care during cutting to keep tubing

round.k. Thread pipe on a threading machine. Ream inner edges of pipe ends, file and grind to

remove burrs.l. Wrap pipe threads of fittings on pneumatic lines with a single wrap of PTFE tape.m. Protect piping and tubing from entrance of foreign matter.

7. Conduit in which nonmetallic tubing is installed shall not exceed 50 percent fill. Support conduit according to NFPA 70 unless otherwise indicated.

Page 116: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 81

B. Below-Grade Pneumatic and Air Signal Piping and Tubing Installation:

1. Install tubing below grade in a continuous 4-inch, Schedule 80, PVC conduit.2. Install at a depth of at least 24 inches below finished grade.3. Install tubing in raceways dedicated to tubing. Do not combine electrical conductors and tubing in

raceways.

C. Identify piping and tubing as follows:

1. Every 50 feet of straight run.2. At least once for each branch within 36 inches of main tee.3. At each change in direction.4. Within 36 inches of each ceiling, floor, roof and wall penetration.5. Where exposed to and where concealed from view, including above ceiling plenums, shafts, and

chases.6. At each valve.7. Mark each instrument tube connection with a number-coded identification. Each unique tube shall

have same unique number at instrument connection and termination at opposite end of tube.

D. Isolation Valves Installation:

1. Install valves full size of piping and tubing.2. Install at the following locations:

a. At each branch.b. Before and after each PRV.c. Before and after each air dryer.d. At each control device.

3. Valves shall be located to be readily accessible from floor.

E. Process Tubing Installation:

1. Install process tubing for signal to instruments in liquid and steam systems. Instruments include, but are not limited to, the following:

a. Meters.b. Sensors.c. Switches.d. Transmitters.

2. Support tubing according to MSS SP-69, Table 3, but at intervals no less than 60 inches.3. Install NPS 1/2 process tubing for industrial-grade sensors, transmitters, and switches. Install

stainless-steel bushings where required.4. Make tubing bends with a bending tool. Flattened or wrinkled bends are unacceptable.5. Support tubing independent of other trades.6. Route tubing parallel to and at right angles to building construction.7. Install tubing concealed in areas with ceilings.8. Install a dirt leg with an isolation valve and threaded plug in drain valve at each connection to a

transmitter and switch.9. Insulate process piping connected to hot water and steam systems for personnel protection if the

surface temperature exceeds 120 deg F. Only insulate piping within maintenance personnel reach from floor, platform, or catwalk.

10. Wrap pipe threads of fitting in process tubing with service temperatures below 350 deg F with a single wrap of PTFE tape.

11. Coat pipe threads of fittings on process tubing in services with temperatures exceeding 350 deg F with pipe compound before being made up to reduce the possibility of galling.

12. Do not make tubing connections to a fitting before completing makeup of the connection.13. Check tubing for correct diameter and wall thickness. Cut the tube ends square and deburred.

Exercise care during cutting to keep tubing round.

Page 117: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 82

14. Do not install fittings close to a bend. A length of straight tubing, not deformed by bending, is required for a proper connection.

15. Align tubing with fitting when installed. Avoid springing tube into position.16. Install tubing with extreme care exercised to keep foreign matter out of system. Open tubing ends

shall be kept plugged to keep out dust, dirt and moisture.17. Do not attach tubing to equipment that may be removed frequently for maintenance or may impart

vibration and expansion from temperature change.18. Protect exposed tubing in mechanical equipment rooms from inadvertent mechanical damage

within 76 inches above floor. Use aluminum channel reversed and secured over tubing to protect tubing from damage.

F. Isolation Valves Installation:

1. Install valves full size of piping and tubing.2. Install isolation valves at the following locations:

a. Process connection.b. Inlet to each instrument including, sensors, transmitters, switches, gages, and other control

devices.

3. Locate valves to be readily accessible from floor.

3.16 CONTROL WIRE, CABLE AND RACEWAYS INSTALLATION

A. Comply with NECA 1.

B. Wire and Cable Installation:

1. Comply with installation requirements in Section 260523 "Control-Voltage Electrical Power Cables."2. Comply with installation requirements in Section 271313 "Communications Copper Backbone

Cabling."3. Comply with installation requirements in Section 271513 "Communications Copper Horizontal

Cabling."4. Install cables with protective sheathing that is waterproof and capable of withstanding continuous

temperatures of 90 deg C with no measurable effect on physical and electrical properties of cable.

a. Provide shielding to prevent interference and distortion from adjacent cables and equipment.

5. Terminate wiring in a junction box.

a. Clamp cable over jacket in junction box.b. Individual conductors in the stripped section of the cable shall be slack between the

clamping point and terminal block.

6. Terminate field wiring and cable not directly connected to instruments and control devices having integral wiring terminals using terminal blocks.

7. Install signal transmission components according to IEEE C2, REA Form 511a, NFPA 70, and as indicated.

8. Use shielded cable to transmitters.9. Use shielded cable to temperature sensors.10. Perform continuity and meager testing on wire and cable after installation.

C. Conduit Installation:

1. Comply with Section "260533 "Raceways and Boxes for Electrical Systems" for control-voltage conductors.

2. Comply with Section 270528 "Pathways for Communications Systems" for balanced twisted pair cabling and optical fiber installation.

Page 118: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 83

3.17 OPTICAL FIBER CABLE SYSTEM INSTALLATION

A. Comply with installation requirements in Section 271323 "Communications Optical Fiber Backbone Cabling."

B. Comply with installation requirements in Section 271523 "Communications Optical Fiber Horizontal Cabling."

3.18 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

B. Manufacturer's Field Service: Engage a factory-authorized service representative to test and inspect components, assemblies, and installations, including connections.

C. Perform the following tests and inspections with the assistance of a factory-authorized service representative:

1. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

2. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

3. Testing of Pneumatic and Air-Signal Tubing:

a. Test for leaks and obstructions.b. Disconnect each pipe and tubing line before a test is performed, and blowout dust, dirt,

trash, condensate and other foreign materials with compressed air. Use commercially pure compressed air or nitrogen as distributed in gas cylinders. Air from an oil-free compressor with an air dryer is an acceptable alternative for the test.

c. After foreign matter is expelled and line is free from obstructions, plug far end of tubing run.d. Connect a pressure source to near end of run with a needle valve between air supply and

tubing run.e. Connect a pressure gage accurate to within 0.5 percent of test between the shutoff needle

valve and tubing run under test.f. For system pressures above 30 psig, apply a pressure of 1.5 times operating pressure.

Record pressure in tubing run every 10 minutes for one hour. Allowable drop in pressure in one-hour period shall not exceed 1 psig.

g. For system pressures 30 psig and below, apply a pressure of 2.0 times operating pressure to piping and tubing run. Record pressure in tubing run every 5 minutes for one hour. Allowable drop in pressure in one-hour period shall not exceed 0.5 psig.

D. Testing:

1. Perform preinstallation, in-progress, and final tests, supplemented by additional tests, as necessary.

2. Preinstallation Cable Verification: Verify integrity and serviceability for new cable lengths before installation. This assurance may be provided by using vendor verification documents, testing, or other methods. As a minimum, furnish evidence of verification for cable attenuation and bandwidth parameters.

3. In-Progress Testing: Perform standard tests for correct pair identification and termination during installation to ensure proper installation and cable placement. Perform tests in addition to those specified if there is any reason to question condition of material furnished and installed. Testing accomplished is to be documented by agency conducting tests. Submit test results for Project record.

4. Final Testing: Perform final test of installed system to demonstrate acceptability as installed. Testing shall be performed according to a test plan supplied by DDC system manufacturer. Defective Work or material shall be corrected and retested. As a minimum, final testing for cable system, including spare cable, shall verify conformance of attenuation, length, and bandwidth parameters with performance indicated.

Page 119: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 84

5. Test Equipment: Use an optical fiber time domain reflectometer for testing of length and optical connectivity.

6. Test Results: Record test results and submit copy of test results for Project record.

3.19 DDC SYSTEM I/O CHECKOUT PROCEDURES

A. Check installed products before continuity tests, leak tests and calibration.

B. Check instruments for proper location and accessibility.

C. Check instruments for proper installation on direction of flow, elevation, orientation, insertion depth, or other applicable considerations that will impact performance.

D. Check instrument tubing for proper isolation, fittings, slope, dirt legs, drains, material and support.

E. Control Damper Checkout:1. Verify that control dampers are installed correctly for flow direction.2. Verify that proper blade alignment, either parallel or opposed, has been provided.3. Verify that damper frame attachment is properly secured and sealed.4. Verify that damper actuator and linkage attachment is secure.5. Verify that actuator wiring is complete, enclosed and connected to correct power source.6. Verify that damper blade travel is unobstructed.

F. Control Valve Checkout:1. Verify that control valves are installed correctly for flow direction.2. Verify that valve body attachment is properly secured and sealed.3. Verify that valve actuator and linkage attachment is secure.4. Verify that actuator wiring is complete, enclosed and connected to correct power source.5. Verify that valve ball, disc or plug travel is unobstructed.6. After piping systems have been tested and put into service, but before insulating and balancing,

inspect each valve for leaks. Adjust or replace packing to stop leaks. Replace the valve if leaks persist.

G. Instrument Checkout:

1. Verify that instrument is correctly installed for location, orientation, direction and operating clearances.

2. Verify that attachment is properly secured and sealed.3. Verify that conduit connections are properly secured and sealed.4. Verify that wiring is properly labeled with unique identification, correct type and size and is securely

attached to proper terminals.5. Inspect instrument tag against approved submittal.6. For instruments with tubing connections, verify that tubing attachment is secure and isolation

valves have been provided.7. For flow instruments, verify that recommended upstream and downstream distances have been

maintained.8. For temperature instruments:

a. Verify sensing element type and proper material.b. Verify length and insertion.

3.20 DDC SYSTEM I/O ADJUSTMENT, CALIBRATION AND TESTING:

A. Calibrate each instrument installed that is not factory calibrated and provided with calibration documentation.

B. Provide a written description of proposed field procedures and equipment for calibrating each type of instrument. Submit procedures before calibration and adjustment.

Page 120: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 85

C. For each analog instrument, make a three-point test of calibration for both linearity and accuracy.

D. Equipment and procedures used for calibration shall comply with instrument manufacturer's written instructions.

E. Provide diagnostic and test equipment for calibration and adjustment.

F. Field instruments and equipment used to test and calibrate installed instruments shall have accuracy at least twice the instrument accuracy being calibrated. An installed instrument with an accuracy of 1 percent shall be checked by an instrument with an accuracy of 0.5 percent.

G. Calibrate each instrument according to instrument instruction manual supplied by manufacturer.

H. If after calibration indicated performance cannot be achieved, replace out-of-tolerance instruments.

I. Comply with field testing requirements and procedures indicated by ASHRAE's Guideline 11, "Field Testing of HVAC Control Components," in the absence of specific requirements, and to supplement requirements indicated.

J. Analog Signals:

1. Check analog voltage signals using a precision voltage meter at zero, 50, and 100 percent.2. Check analog current signals using a precision current meter at zero, 50, and 100 percent.3. Check resistance signals for temperature sensors at zero, 50, and 100 percent of operating span

using a precision-resistant source.

K. Digital Signals:

1. Check digital signals using a jumper wire.2. Check digital signals using an ohmmeter to test for contact making or breaking.

L. Control Dampers:

1. Stroke and adjust control dampers following manufacturer's recommended procedure, from 100 percent open to 100 percent closed and back to 100 percent open.

2. Stroke control dampers with pilot positioners. Adjust damper and positioner following manufacturer's recommended procedure, so damper is 100 percent closed, 50 percent closed and 100 percent open at proper air pressure.

3. Check and document open and close cycle times for applications with a cycle time less than 30 seconds.

4. For control dampers equipped with positive position indication, check feedback signal at multiple positions to confirm proper position indication.

M. Control Valves:

1. Stroke and adjust control valves following manufacturer's recommended procedure, from 100 percent open to 100 percent closed and back to 100 percent open.

2. Stroke control valves with pilot positioners. Adjust valve and positioner following manufacturer's recommended procedure, so valve is 100 percent closed, 50 percent closed and 100 percent open at proper air pressures.

3. Check and document open and close cycle times for applications with a cycle time less than 30 seconds.

4. For control valves equipped with positive position indication, check feedback signal at multiple positions to confirm proper position indication.

N. Meters: Check sensors at zero, 50, and 100 percent of Project design values.

O. Sensors: Check sensors at zero, 50, and 100 percent of Project design values.

Page 121: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 86

P. Switches: Calibrate switches to make or break contact at set points indicated.

Q. Transmitters:

1. Check and calibrate transmitters at zero, 50, and 100 percent of Project design values.2. Calibrate resistance temperature transmitters at zero, 50, and 100 percent of span using a

precision-resistant source.

3.21 DDC SYSTEM CONTROLLER CHECKOUT

A. Verify power supply.

1. Verify voltage, phase and hertz.2. Verify that protection from power surges is installed and functioning.3. Verify that ground fault protection is installed.4. If applicable, verify if connected to UPS unit.5. If applicable, verify if connected to a backup power source.6. If applicable, verify that power conditioning units, transient voltage suppression and high-frequency

noise filter units are installed.

B. Verify that wire and cabling is properly secured to terminals and labeled with unique identification.

C. Verify that spare I/O capacity is provided.

3.22 DDC CONTROLLER I/O CONTROL LOOP TESTS

A. Testing:

1. Test every I/O point connected to DDC controller to verify that safety and operating control set points are as indicated and as required to operate controlled system safely and at optimum performance.

2. Test every I/O point throughout its full operating range.3. Test every control loop to verify operation is stable and accurate.4. Adjust control loop proportional, integral and derivative settings to achieve optimum performance

while complying with performance requirements indicated. Document testing of each control loop's precision and stability via trend logs.

5. Test and adjust every control loop for proper operation according to sequence of operation.6. Test software and hardware interlocks for proper operation. Correct deficiencies.7. Operate each analog point at the following:

a. Upper quarter of range.b. Lower quarter of range.c. At midpoint of range.

8. Exercise each binary point.9. For every I/O point in DDC system, read and record each value at operator workstation, at DDC

controller and at field instrument simultaneously. Value displayed at operator workstation, at DDC controller and at field instrument shall match.

10. Prepare and submit a report documenting results for each I/O point in DDC system and include in each I/O point a description of corrective measures and adjustments made to achieve desire results.

3.23 DDC SYSTEM VALIDATION TESTS

A. Perform validation tests before requesting final review of system. Before beginning testing, first submit Pretest Checklist and Test Plan.

Page 122: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 87

B. After approval of Test Plan, execute all tests and procedures indicated in plan.

C. After testing is complete, submit completed test checklist.

D. Pretest Checklist: Submit the following list with items checked off once verified:

1. Detailed explanation for any items that are not completed or verified.2. Required mechanical installation work is successfully completed and HVAC equipment is working

correctly.3. HVAC equipment motors operate below full-load amperage ratings.4. Required DDC system components, wiring, and accessories are installed.5. Installed DDC system architecture matches approved Drawings.6. Control electric power circuits operate at proper voltage and are free from faults.7. Required surge protection is installed.8. DDC system network communications function properly, including uploading and downloading

programming changes.9. Using BACnet protocol analyzer, verify that communications are error free.10. Each controller's programming is backed up.11. Equipment, products, tubing, wiring cable and conduits are properly labeled.12. All I/O points are programmed into controllers.13. Testing, adjusting and balancing work affecting controls is complete.14. Dampers and actuators zero and span adjustments are set properly.15. Each control damper and actuator goes to failed position on loss of power.16. Valves and actuators zero and span adjustments are set properly.17. Each control valve and actuator goes to failed position on loss of power.18. Meter, sensor and transmitter readings are accurate and calibrated.19. Control loops are tuned for smooth and stable operation.20. View trend data where applicable.21. Each controller works properly in standalone mode.22. Safety controls and devices function properly.23. Interfaces with fire-alarm system function properly.24. Electrical interlocks function properly.25. Operator workstations and other interfaces are delivered, all system and database software is

installed, and graphic are created.26. Record Drawings are completed.

E. Test Plan:

1. Prepare and submit a validation test plan including test procedures for performance validation tests.

2. Test plan shall address all specified functions of DDC system and sequences of operation.3. Explain detailed actions and expected results to demonstrate compliance with requirements

indicated.4. Explain method for simulating necessary conditions of operation used to demonstrate performance.5. Include a test checklist to be used to check and initial that each test has been successfully

completed.6. Submit test plan documentation 20 business days before start of tests.

F. Validation Test:

1. Verify operating performance of each I/O point in DDC system.

a. Verify analog I/O points at operating value.b. Make adjustments to out-of-tolerance I/O points.

1) Identify I/O points for future reference.2) Simulate abnormal conditions to demonstrate proper function of safety devices.3) Replace instruments and controllers that cannot maintain performance indicated

after adjustments.

2. Simulate conditions to demonstrate proper sequence of control.

Page 123: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 88

3. Readjust settings to design values and observe ability of DDC system to establish desired conditions.

4. After 24 Hours following Initial Validation Test:

a. Re-check I/O points that required corrections during initial test.b. Identify I/O points that still require additional correction and make corrections necessary to

achieve desired results.

5. After 24 Hours of Second Validation Test:

a. Re-check I/O points that required corrections during second test.b. Continue validation testing until I/O point is normal on two consecutive tests.

6. Completely check out, calibrate, and test all connected hardware and software to ensure that DDC system performs according to requirements indicated.

7. After validation testing is complete, prepare and submit a report indicating all I/O points that required correction and how many validation re-tests it took to pass. Identify adjustments made for each test and indicate instruments that were replaced.

G. DDC System Response Time Test:

1. Simulate HLC.

a. Heavy load shall be an occurrence of 50 percent of total connected binary COV, one-half of which represent an "alarm" condition, and 50 percent of total connected analog COV, one-half of which represent an "alarm" condition, that are initiated simultaneously on a one-time basis.

2. Initiate 10 successive occurrences of HLC and measure response time to typical alarms and status changes.

3. Measure with a timer having at least 0.1-second resolution and 0.01 percent accuracy.4. Purpose of test is to demonstrate DDC system, as follows:

a. Reaction to COV and alarm conditions during HLC.b. Ability to update DDC system database during HLC.

5. Passing test is contingent on the following:

a. Alarm reporting at printer beginning no more than two seconds after the initiation (time zero) of HLC.

b. All alarms, both binary and analog, are reported and printed; none are lost.c. Compliance with response times specified.

6. Prepare and submit a report documenting HLC tested and results of test including time stamp and print out of all alarms.

H. DDC System Network Bandwidth Test:

1. Test network bandwidth usage on all DDC system networks to demonstrate bandwidth usage under DDC system normal operating conditions and under simulated HLC.

2. To pass, none of DDC system networks shall use more than 70 percent of available bandwidth under normal and HLC operation.

3.24 DDC SYSTEM WIRELESS NETWORK VERIFICATION

A. DDC system Installer shall design wireless DDC system networks to comply with performance requirements indicated.

Page 124: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 89

B. Installer shall verify wireless network performance through field testing and shall document results in a field test report.

C. Testing and verification of all wireless devices shall include, but not be limited to, the following:

1. Speed.2. Online status.3. Signal strength.

3.25 FINAL REVIEW

A. Submit written request to Owner when DDC system is ready for final review. Written request shall state the following:

1. DDC system has been thoroughly inspected for compliance with contract documents and found to be in full compliance.

2. DDC system has been calibrated, adjusted and tested and found to comply with requirements of operational stability, accuracy, speed and other performance requirements indicated.

3. DDC system monitoring and control of HVAC systems results in operation according to sequences of operation indicated.

4. DDC system is complete and ready for final review.

B. Review by Owner and Engineer shall be made after receipt of written request. A field report shall be issued to document observations and deficiencies.

C. Take prompt action to remedy deficiencies indicated in field report and submit a second written request when all deficiencies have been corrected. Repeat process until no deficiencies are reported.

D. Should more than two reviews be required, DDC system manufacturer and Installer shall compensate entity performing review for total costs, labor and expenses, associated with third and subsequent reviews. Estimated cost of each review shall be submitted and approved by DDC system manufacturer and Installer before making the review.

E. Prepare and submit closeout submittals and begin procedures indicated in "Extended Operation Test" Article when no deficiencies are reported.

F. A part of DDC system final review shall include a demonstration to parties participating in final review.

1. Provide staff familiar with DDC system installed to demonstrate operation of DDC system during final review.

2. Provide testing equipment to demonstrate accuracy and other performance requirements of DDC system that is requested by reviewers during final review.

3. Demonstration shall include, but not be limited to, the following:

a. Accuracy and calibration of 20 I/O points randomly selected by reviewers. If review finds that some I/O points are not properly calibrated and not satisfying performance requirements indicated, additional I/O points may be selected by reviewers until total I/O points being reviewed that satisfy requirements equals quantity indicated.

b. HVAC equipment and system hardwired and software safeties and life-safety functions are operating according to sequence of operation. Up to 20 I/O points shall be randomly selected by reviewers. Additional I/O points may be selected by reviewers to discover problems with operation.

c. Correct sequence of operation after electrical power interruption and resumption after electrical power is restored for randomly selected HVAC systems.

d. Operation of randomly selected dampers and valves in normal-on, normal-off and failed positions.

e. Reporting of alarm conditions for randomly selected alarms, including different classes of alarms, to ensure that alarms are properly received by operators and operator workstations.

f. Trends, summaries, logs and reports set-up for Project.

Page 125: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 90

g. For up to three HVAC systems randomly selected by reviewers, use graph trends to show that sequence of operation is executed in correct manner and that HVAC systems operate properly through complete sequence of operation including different modes of operations indicated. Show that control loops are stable and operating at set points and respond to changes in set point of 20 percent or more.

h. Software's ability to communicate with controllers, operator workstations, uploading and downloading of control programs.

i. Software's ability to edit control programs off-line.j. Data entry to show Project-specific customizing capability including parameter changes.k. Step through penetration tree, display all graphics, demonstrate dynamic update, and direct

access to graphics.l. Execution of digital and analog commands in graphic mode.m. Spreadsheet and curve plot software and its integration with database.n. Online user guide and help functions.o. Multitasking by showing different operations occurring simultaneously on four quadrants of

split screen.p. System speed of response compared to requirements indicated.q. For Each Network and Programmable Application Controller:

1) Memory: Programmed data, parameters, trend and alarm history collected during normal operation is not lost during power failure.

2) Operator Interface: Ability to connect directly to each type of digital controller with a portable workstation and mobile device. Show that maintenance personnel interface tools perform as indicated in manufacturer's technical literature.

3) Standalone Ability: Demonstrate that controllers provide stable and reliable standalone operation using default values or other method for values normally read over network.

4) Electric Power: Ability to disconnect any controller safely from its power source.5) Wiring Labels: Match control drawings.6) Network Communication: Ability to locate a controller's location on network and

communication architecture matches Shop Drawings.7) Nameplates and Tags: Accurate and permanently attached to control panel doors,

instrument, actuators and devices.

r. For Each Operator Workstation:

1) I/O points lists agree with naming conventions.2) Graphics are complete.3) UPS unit, if applicable, operates.

s. Communications and Interoperability: Demonstrate proper interoperability of data sharing, alarm and event management, trending, scheduling, and device and network management. Use ASHRAE 135 protocol analyzer to help identify devices, view network traffic, and verify interoperability. Requirements must be met even if only one manufacturer's equipment is installed.

1) Data Presentation: On each operator workstation, demonstrate graphic display capabilities.

2) Reading of Any Property: Demonstrate ability to read and display any used readable object property of any device on network.

3) Set Point and Parameter Modifications: Show ability to modify set points and tuning parameters indicated. Modifications are made with messages and write services initiated by an operator using workstation graphics, or by completing a field in a menu with instructional text.

4) Peer-to-Peer Data Exchange: Network devices are installed and configured to perform without need for operator intervention to implement Project sequence of operation and to share global data.

5) Alarm and Event Management: Alarms and events are installed and prioritized according to Owner. Demonstrate that time delays and other logic are set up to avoid nuisance tripping. Show that operators with sufficient privileges are permitted.

Page 126: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 91

6) Schedule Lists: Schedules are configured for start and stop, mode change, occupant overrides, and night setback as defined in sequence of operations.

7) Schedule Display and Modification: Ability to display any schedule with start and stop times for calendar year. Show that all calendar entries and schedules are modifiable from any connected operator workstation by an operator with sufficient privilege.

8) Archival Storage of Data: Data archiving is handled by operator workstation and server and local trend archiving and display is accomplished.

9) Modification of Trend Log Object Parameters: Operator with sufficient privilege can change logged data points, sampling rate, and trend duration.

10) Device and Network Management:

a) Display of network device status.b) Display of BACnet Object Information.c) Silencing devices transmitting erroneous data.d) Time synchronization.e) Remote device re-initialization.f) Backup and restore network device programming and master database(s).g) Configuration management of routers.

3.26 EXTENDED OPERATION TEST

A. Extended operation test is intended to simulate normal operation of DDC system by Owner.

B. Operate DDC system for an operating period of 14 consecutive calendar days following Substantial Completion. Coordinate exact start date of testing with Owner.

C. Provide an operator familiar with DDC system installed to man an operator workstation while on-site during eight hours of each normal business day occurring during operating period.

D. During operating period, DDC system shall demonstrate correct operation and accuracy of monitored and controlled points as well as operation capabilities of sequences, logs, trends, reports, specialized control algorithms, diagnostics, and other software indicated.

1. Correct defects of hardware and software when it occurs.

E. Definition of Failures and Downtime during Operating Period:

1. Failed I/O point constituting downtime is an I/O point failing to perform its intended function consistently and a point physically failed due to hardware and software.

2. Downtime is when any I/O point in DDC system is unable to fulfill its' required function.3. Downtime shall be calculated as elapsed time between a detected point failure as confirmed by an

operator and time point is restored to service.4. Maximum time interval allowed between DDC system detection of failure occurrence and operator

confirmation shall be 0.5 hours.5. Downtime shall be logged in hours to nearest 0.1 hour.6. Power outages shall not count as downtime, but shall suspend test hours unless systems are

provided with UPS and served through a backup power source.7. Hardware or software failures caused by power outages shall count as downtime.

F. During operating period, log downtime and operational problems are encountered.

1. Identify source of problem.2. Provide written description of corrective action taken.3. Record duration of downtime.4. Maintain log showing the following:

a. Time of occurrence.b. Description of each occurrence and pertinent written comments for reviewer to understand

scope and extent of occurrence.

Page 127: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 92

c. Downtime for each failed I/O point.d. Running total of downtime and total time of I/O point after each problem has been restored.

5. Log shall be available to Owner for review at any time.

G. For DDC system to pass extended operation test, total downtime shall not exceed 2 percent of total point-hours during operating period.

1. Failure to comply with minimum requirements of passing at end of operating period indicated shall require that operating period be extended one consecutive day at a time until DDC system passes requirement.

H. Evaluation of DDC system passing test shall be based on the following calculation:

1. Downtime shall be counted on a point-hour basis where total number of DDC system point-hours is equal to total number of I/O points in DDC system multiplied by total number of hours during operating period.

2. One point-hour of downtime is one I/O point down for one hour. Three points down for five hours is a total of 15 point-hours of downtime. Four points down for one-half hour is 2 point-hours of downtime.

3. Example Calculation: Maximum allowable downtime for 30-day test when DDC system has 1000 total I/O points (combined analog and binary) and has passing score of 1 percent downtime is computed by 30 days x 24 h/day x 1000 points x 1 percent equals 7200 point-hours of maximum allowable downtime.

I. Prepare test and inspection reports.

3.27 ADJUSTING

A. Occupancy Adjustments: When requested within 12 months from date of Substantial Completion, provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to two visits to Project during other-than-normal occupancy hours for this purpose.

3.28 MAINTENANCE SERVICE

A. Maintenance Service: Beginning at Substantial Completion, maintenance service shall include six months' full maintenance by DDC system manufacturer's authorized service representative. Include monthly preventive maintenance, repair or replacement of worn or defective components, cleaning, calibration and adjusting as required for proper operation. Parts and supplies shall be manufacturer's authorized replacement parts and supplies.

3.29 SOFTWARE SERVICE AGREEMENT

A. Technical Support: Beginning at Substantial Completion, service agreement shall include software support for two years.

B. Upgrade Service: At Substantial Completion, update software to latest version. Install and program software upgrades that become available within one year from date of Substantial Completion. Upgrading software shall include operating system and new or revised licenses for using software.

1. Upgrade Notice: At least 30 days to allow Owner to schedule and access system and to upgrade computer equipment if necessary.

Page 128: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 93

3.30 DEMONSTRATION

A. Engage a factory-authorized service representative with complete knowledge of Project-specific system installed to train Owner's maintenance personnel to adjust, operate, and maintain DDC system.

B. Extent of Training:

1. Base extent of training on scope and complexity of DDC system indicated and training requirements indicated. Provide extent of training required to satisfy requirements indicated even if more than minimum training requirements are indicated.

2. Inform Owner of anticipated training requirements if more than minimum training requirements are indicated.

3. Minimum Training Requirements:

a. Provide not less than 10 days of training total.b. Stagger training over multiple training classes to accommodate Owner's requirements. All

training shall occur before end of warranty period.c. Total days of training shall be broken into not more than three separate training classes.d. Each training class shall be not less than two consecutive days.

C. Training Schedule:

1. Schedule training with Owner 20 business days before expected Substantial Completion.2. Schedule training to provide Owner with at least 10 business days of notice in advance of training.3. Training shall occur within normal business hours at a mutually agreed on time. Unless otherwise

agreed to, training shall occur Monday through Friday, except on U.S. Federal holidays, with two morning sessions and two afternoon sessions. Each morning session and afternoon session shall be split in half with 30minute break between sessions. Morning and afternoon sessions shall be separated by 60-minute lunch period. Training, including breaks and excluding lunch period, shall not exceed eight hours per day.

4. Provide staggered training schedule as requested by Owner.

D. Training Attendee List and Sign-in Sheet:

1. Request from Owner in advance of training a proposed attendee list with name, phone number and e-mail address.

2. Provide a preprinted sign-in sheet for each training session with proposed attendees listed and no fewer than six blank spaces to add additional attendees.

3. Preprinted sign-in sheet shall include training session number, date and time, instructor name, phone number and e-mail address, and brief description of content to be covered during session. List attendees with columns for name, phone number, e-mail address and a column for attendee signature or initials.

4. Circulate sign-in sheet at beginning of each session and solicit attendees to sign or initial in applicable location.

5. At end of each training day, send Owner an e-mail with an attachment of scanned copy (PDF) of circulated sign-in sheet for each session.

E. Training Attendee Headcount:

1. Plan in advance of training for three attendees.2. Make allowance for Owner to add up to two attendees at time of training.3. Headcount may vary depending on training content covered in session. Attendee access may be

restricted to some training content for purposes of maintaining system security.

F. Attendee Training Manuals:

1. Provide each attendee with a color hard copy of all training materials and visual presentations.2. Hard-copy materials shall be organized in a three-ring binder with table of contents and individual

divider tabs marked for each logical grouping of subject matter. Organize material to provide space for attendees to take handwritten notes within training manuals.

Page 129: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 94

3. In addition to hard-copy materials included in training manual, provide each binder with a sleeve or pocket that includes a DVD or flash drive with PDF copy of all hard-copy materials.

G. Instructor Requirements:

1. One or multiple qualified instructors, as required, to provide training.2. Instructors shall have not less than five years of providing instructional training on not less than five

past projects with similar DDC system scope and complexity to DDC system installed.

H. Organization of Training Sessions:

1. Organize training sessions into logical groupings of technical content and to reflect different levels of operators having access to system. Plan training sessions to accommodate the following three levels of operators:

a. Daily operators.b. Advanced operators.c. System managers and administrators.

2. Plan and organize training sessions to group training content to protect DDC system security. Some attendees may be restricted to some training sessions that cover restricted content for purposes of maintaining DDC system security.

I. Training Outline:

1. Submit training outline for Owner review at least 10 business day before scheduling training.2. Outline shall include a detailed agenda for each training day that is broken down into each of four

training sessions that day, training objectives for each training session and synopses for each lesson planned.

J. On-Site Training:

1. Owner will provide conditioned classroom or workspace with ample desks or tables, chairs, power and data connectivity for instructor and each attendee.

2. Instructor shall provide training materials, projector and other audiovisual equipment used in training.

3. Provide as much of training located on-site as deemed feasible and practical by Owner.4. On-site training shall include regular walk-through tours, as required, to observe each unique

product type installed with hands-on review of operation, calibration and service requirements.5. Operator workstation provided with DDC system shall be used in training. If operator workstation is

not indicated, provide a temporary workstation to convey training content.

K. Off-Site Training:

1. Provide conditioned training rooms and workspace with ample tables desks or tables, chairs, power and data connectivity for each attendee.

2. Provide capability to remotely access to Project DDC system for use in training.3. Provide a workstation for use by each attendee.

L. Training Content for Daily Operators:

1. Basic operation of system.2. Understanding DDC system architecture and configuration.3. Understanding each unique product type installed including performance and service requirements

for each.4. Understanding operation of each system and equipment controlled by DDC system including

sequences of operation, each unique control algorithm and each unique optimization routine.5. Operating operator workstations, printers and other peripherals.6. Logging on and off system.7. Accessing graphics, reports and alarms.

Page 130: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 95

8. Adjusting and changing set points and time schedules.9. Recognizing DDC system malfunctions.10. Understanding content of operation and maintenance manuals including control drawings.11. Understanding physical location and placement of DDC controllers and I/O hardware.12. Accessing data from DDC controllers.13. Operating portable operator workstations.14. Review of DDC testing results to establish basic understanding of DDC system operating

performance and HVAC system limitations as of Substantial Completion.15. Running each specified report and log.16. Displaying and demonstrating each data entry to show Project-specific customizing capability.

Demonstrating parameter changes.17. Stepping through graphics penetration tree, displaying all graphics, demonstrating dynamic

updating, and direct access to graphics.18. Executing digital and analog commands in graphic mode.19. Demonstrating control loop precision and stability via trend logs of I/O for not less than 10 percent

of I/O installed.20. Demonstrating DDC system performance through trend logs and command tracing.21. Demonstrating scan, update, and alarm responsiveness.22. Demonstrating spreadsheet and curve plot software, and its integration with database.23. Demonstrating on-line user guide, and help function and mail facility.24. Demonstrating multitasking by showing dynamic curve plot, and graphic construction operating

simultaneously via split screen.25. Demonstrating the following for HVAC systems and equipment controlled by DDC system:

a. Operation of HVAC equipment in normal-off, -on and failed conditions while observing individual equipment, dampers and valves for correct position under each condition.

b. For HVAC equipment with factory-installed software, show that integration into DDC system is able to communicate with DDC controllers or gateways, as applicable.

c. Using graphed trends, show that sequence of operation is executed in correct manner, and HVAC systems operate properly through complete sequence of operation including seasonal change, occupied and unoccupied modes, warm-up and cool-down cycles and other modes of operation indicated.

d. Hardware interlocks and safeties function properly and DDC system performs correct sequence of operation after electrical power interruption and resumption after power is restored.

e. Reporting of alarm conditions for each alarm, and confirm that alarms are received at assigned locations, including operator workstations.

f. Each control loop responds to set point adjustment and stabilizes within time period indicated.

g. Sharing of previously graphed trends of all control loops to demonstrate that each control loop is stable and set points are being maintained.

M. Training Content for Advanced Operators:

1. Making and changing workstation graphics.2. Creating, deleting and modifying alarms including annunciation and routing.3. Creating, deleting and modifying point trend logs including graphing and printing on an ad-hoc

basis and operator-defined time intervals.4. Creating, deleting and modifying reports.5. Creating, deleting and modifying points.6. Creating, deleting and modifying programming including ability to edit control programs off-line.7. Creating, deleting and modifying system graphics and other types of displays.8. Adding DDC controllers and other network communication devices such as gateways and routers.9. Adding operator workstations.10. Performing DDC system checkout and diagnostic procedures.11. Performing DDC controllers operation and maintenance procedures.12. Performing operator workstation operation and maintenance procedures.13. Configuring DDC system hardware including controllers, workstations, communication devices and

I/O points.14. Maintaining, calibrating, troubleshooting, diagnosing and repairing hardware.15. Adjusting, calibrating and replacing DDC system components.

Page 131: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC230923 - 96

N. Training Content for System Managers and Administrators:

1. DDC system software maintenance and backups.2. Uploading, downloading and off-line archiving of all DDC system software and databases.3. Interface with Project-specific, third-party operator software.4. Understanding password and security procedures.5. Adding new operators and making modifications to existing operators.6. Operator password assignments and modification.7. Operator authority assignment and modification.8. Workstation data segregation and modification.

O. Video of Training Sessions:

1. Provide a digital video and audio recording of each training session. Create a separate recording file for each session.

2. Stamp each recording file with training session number, session name and date.3. Provide Owner with two copies of digital files on DVDs or flash drives for later reference and for

use in future training.4. Owner retains right to make additional copies for intended training purposes without having to pay

royalties.

END OF SECTION 230923

Page 132: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 1

SECTION 230993.11SEQUENCE OF OPERATIONS FOR HVAC DDC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes control sequences for DDC for HVAC systems, subsystems, and equipment.

B. Sequences of operation included in this section covers only the HVAC equipment replaced. Any additional sequences of operation associated with existing systems required for programming the new DDC system will need to be coordinated

C. Related Requirements:

1. Section 230923 "DDC Systems for HVAC" for control equipment.

1.3 DEFINITIONS

A. Analog Output: Proportional output signal (zero- to 10-V dc, 4 to 20 mA).

B. Binary Output: On/off output signal or contact closure.

C. DDC: Direct digital control.

D. Digital Output: Data output that must be interpreted digitally.

1.4 ACTION SUBMITTALS

A. Product Data:

1. An instrumentation list for each controlled system. Label each element of the controlled system in table format. Show, in the table element name, type of device, manufacturer, model number, and control device product data sheet number.

2. A complete description of the operation of the control system, including sequences of operation. Include and reference a schematic diagram of the controlled system.

B. Shop Drawings:

1. Riser diagrams showing control network layout, communication protocol, and wire types.2. Schematic diagram of each controlled system. Include all control points labeled with point names

shown or listed. Show the location of control elements in the system.3. Wiring diagram for each controlled system. Show all control elements labels. Where a control

element is the same as that shown on the control system schematic, label with the same name. Label all terminals.

Page 133: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 2

1.5 ICE SLAB CHILLERS

A. Local Mode:

1. To be enabled locally, the Local/Off/Remote switch must be in the local position. The unit can then be enabled with the Local Enable contacts (by others) field wired. Upon the Local Enable contacts opening, or the Local/Off/Remote switch being switched out of Local, the unit will disable.

2. If Local Mode is enabled, the display will read “Yes” on the parameters of Local Switch and Local Enable.

B. Remote Mode1. To operate in Remote Mode, the Local/Off/Remote switch must be in the Remote position. The

unit can then be enabled with Remote Enable via BMS/Network. Upon the remote Enable being taken away, or the Local/Off/Remote switch being switched out of Remote, the unit will disable.

2. If Remote Mode is enabled, the display will read “Yes” on the parameters of Remote Switch and Remote Enable.

C. System Enable1. In order for the pumps to enable, the chiller must be in local or remote mode, the phase monitor

must not be failed, and the flow switch must be made. The System Enabled parameter will read “Yes”.

D. Compressor Staging1. Compressors will be staged off of outlet fluid temperature and equal run time. Once outlet fluid

temperature rises higher than active setpoint, the compressor with the least amount of runtime will start. If the outlet stays above the active setpoint for a time longer than the stage delay, the 2nd stage compressor will start. This process works in reverse to stage the compressors down.

2. For a compressor to be available to run:a. Its OFF/ON switch must be in the RUN position.b. Its guaranteed off time (GOT) must be timed out.c. Its crankcase heater must be proven on, via current switch, for at least five minutes.d. It cannot be failed.e. Flow switch must be made.

E. Capacity Control1. Compressor capacity is determined by the position of its slide valve. Its slide valve modulates

capacity from 25-100%. The slide valve is controlled by a set of solenoid valves on the side of the compressor body. The Unload solenoid is powered to push the slide valve toward the Unload direction, and the Load solenoid is powered to push the slide valve toward the Load direction,

2. To prevent overshooting, the controller’s signal to the Load and Unload solenoids is pulsed to regulate the speed of the slide valve response. (Two seconds on, eight seconds off).

3. Four things determine the need to unload:a. Leaving fluid temperature falling below setpoint.b. Suction pressure falling below freeing.c. High discharge pressure (200 psi).d. Compressor amps above its rated RLA

4. If the compressor is not unloading it is loading.5. For the initial ninety seconds of compressor running, the unload solenoid will remain energized,

and the hot gas regulator will remain de-energized. This time period allows the compressor to build suction pressure without hot gas. After ninety seconds, the loading/unloading solenoids and the hot gas regulator operate as they should.

F. Alarms1. In the event of the Carel controller registering an alarm, the red alarm light will energie on the

controller. The alarm light for that circuit will also energize on the door of the electrical enclosure. The alarm button on the controller can be pushed, or the alarm page can be selected on the main menu of the controller to view the alarm.

2. List of possible alarms:a. Compressor Failure – This indicates one of four things has tripped in that compressor’s

safety string. The high pressure switch, the freezestat, the power module, or one of the compressor overloads. All these issues require a manual reset.

Page 134: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 3

b. Mechanical Low Pressure – The compressor’s suction pressure has fallen below one psi for 30 seconds. This countdown won’t start until the hot gas regulator is energized. This failure will reset itself after 30 seconds.

c. Low Differential Pressure – The pressure differential across the compressor has been less than thirty psi for one hundred and twenty seconds. This countdown won’t start until the hot gas regulator is energized. This failure will reset itself after 30 seconds.

d. Compressor Hard Lockout – The compressor has failed on mechanical low pressure or low differential pressure four times within an hour. The compressor will not be available to run until this lockout is reset by toggling the compressor Off/Run switch.

1.6 COOLING TOWERS

A. Cooling towers are designed to operate in Auto or Hand Mode. In Auto Mode, the sequencing logic controls each component based on a reference signal and a setpoint. The sequencing for the logic does not apply to the remote control selection. In Hand Mode, the user can select which component will operate (all sequencing software is disabled).

B. Hand Mode:1. To enable Hand Mode, turn Fan & Pump Mode selector switch to “Hand” on the panel. The Hand

Enabled light will illuminate. When the Hand Enabled light is illuminated, the operator has manual control of all fans and pumps.

2. While in Hand Mode, the operator can select “Drive” on the Hand Mode selector switch to enable the start VFD/fan motor. The fan motor will operate at the pre-set speed configured during the Startup Wizard.

3. To enable VFD bypass mode (bypasses the VFD to run the fan motor at 100% speed), turn the Hand mode selector switch to “Bypass”.

4. To manually operate the spray pump in Hand Mode, turn the Spray Pump selector switch to “ON”. Note: The Spray Pump selector switch is disabled when the Fan & Pump Mode selector switch is in Auto Mode.

C. Auto Mode:1. To enable the internal Sequencing software, turn the Fan & Pump Mode selector switch to “Auto”.

All manual selector switches will now be disabled.2. To allow the spray pump to cycle automatically in Auto Mode. Turn the Spray Pump Wet/Dry

selector switch to “Wet”. To disable the spray pump from cycling on in Auto Mode, turn the Spray Pump Wet/Dry selector switch to “Dry”. The Wet/Dry selector switch is disabled when the Fan & Pump Mode selector switch is in “Hand Mode”. Once the actual leaving temperature/pressure exceeds the setpoint, the Sequencing Software will be enabled and the fans and spray pump will cycle when required.

3. The Basin Heater selection switch cycles between Auto Mode or OFF. The heater will not operate in Auto Mode, nor in Hand Mode when the fan or spray pump is running.

D. DDC Operation:1. The control module receives a remote start signal.

a. The chiller system is operated independently by the DDC.2. The control module starts reading the leaving fluid temperature/pressure. If the leaving fluid

temperature/pressure is greater than the upper dead band, the VFD will cycle ON.a. The motor will be modulated from minimum to maximum speed based on the output from

the PID loop. The PID loop would be initiated when the leaving fluid temperature/pressure rises above the set point and modulates the motor speed. The job of the control module is to keep the fluid temperature/pressure at the set point within the dead band.

3. The spray pump will be on for a minimum amount of time to prevent short cycling and also to prevent scale buildup on the coil and/or fill material from wetting and drying.a. VFD shall remain ON as lonf=g as the leaving fluid temperature/pressure is greater than the

lower limit.b. VFD shall remain ON at minimum speed as long as the leaving fluid temperature/pressure is

greater than the lower limit and below the setpoint.c. VFD will turn OFF when the leaving fluid temperature/pressure is less than the lower limit.

4. The control module shall switch the spray pump ON if the leaving fluid temperature/pressure exceeds the upper limit.

Page 135: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 4

5. The VFD motor and the spray pump shall remain ON as long as the leaving fluid temperature/pressure is greater than the lower dead band.a. VFD motor will remain ON at minimum speed as long as the leaving fluid

temperature/pressure is greater than the lower limit. The spray pump shall remain ON as long as the leaving fluid temperature/pressure is less than the lower dead band but greater than the lower limit, and the Off-Delay Timer has not expired.

b. The spray pump will turn OFF when the leaving fluid temperature/pressure is less than the lower dead band and the Off-Delay Timer has expired.

c. VFD motor will turn OFF when the leaving fluid temperature/pressure is less than the lower limit.

6. The control module will continue to read the leaving fluid temperature/pressure and continue to operate in remote mode based on this information.

1.7 DESSICANT AIR HANDLING UNIT #11

A. With the correct power supplied to the unit and the main disconnect switch in the ON position and with the Manual-Off-Auto selector switch in the OFF position, the DDC controller is powered and the sensors are activated. The unit is in standby with outside air (OA) damper fully closed and return air (RA) damper fully open.

B. With the Manual-Off-Auto selector switch in the Manual or Auto position and with all safety circuits normal, one of the following airflow modes may be selected.1. For the Auto Mode to function, the operator supplied Run/Stop Contact must be closed and the

jumper installed in place of the Run/Stop Contact must be removed.

C. Airflow modes may include any or all of the following:1. Unoccupied: With “Unoccupied” mode selected, and safety circuits normal; on a call for

dehumidification the DDC controller will enable the supply fan, reactivation fan, dessicant rotor drive and reactivation heat source. On a call for heating or cooling the DDC controller will energize the the supply fan and utilize the post heating and cooling as required to maintain desired temperature set-point. The outside air damper is closed, return damper is open. Enthalpy rotor and exhaust fans are disabled.

2. Occupied: With “Occupied mode selected, and safety circuits normal; supply fan operates continuously, outside air damper drives to 50% (adjustable within DDC controller from 29% to 50%) open and return damper drives to 50% (adjustable within DDC controller 80% to 50%) open. Enthalpy rotor motor and exhaust fan motor VFD are enabled with the exhaust fans operating at 50%(adjustable within the DDC controller from 20% to 50%) capacity. On a call for dehumidification the DDC controller will enable the reactivation fan, dessicant rotor drive and reactivation heat source as required to maintain desired space dew point. Post heating and cooling are utilized as required to maintain desired temperature setpoint.

3. Event: With “Event” mode selected and safety circuits normal; supply fan operates continuously, outside air dampers drive to 100% (adjustable within DDC controller from 50% to 100%) open and return damper drives to 0% (adjustable within DDC controller from 50% to 0%) open. Enthalpy rotor motor and exhaust fan motor VFD are enabled with the exhaust fans operating at 100% (adjustable within DDC controller from 50% to 100%) capacity. On a call for dehumidification the DDC controller will enable the reactivation fan, dessicant rotor drive and reactivation heat source as required to maintain desired space dew point. When there is no call for dehumidification, the reactivation fan, dessicant rotor drive and reactivation heat source are not enabled. Post heating and cooling are utilized as required to maintain desired temperature set-point.

4. IAQ: With “IAQ” mode selected, and safety circuits normal; supply fan operates continuously, outside air damper drives 100% open and return damper drives fully closed. Enthalpy rotor motor and exhaust fan motor VFD are enabled with the exhaust fans operating at 100% (adjustable) capacity. On a call for dehumidification the DDC controller will enable the reactivation fan, dessicant rotor drive and reactivation heat source as required to maintain desired space dew point. Post heating and cooling are utilized as required to maintain desired temperature set-point.

5. Airflow modes listed above will be affected by the following triggers:a. High CO2 Sensor Level – With any mode selected except OFF, when the CO2 sensor

reaches a level of 1200 ppm (adjustable within the DDC controller from 100ppm to 300ppm) below the setpoint and safety circuits normal; supply fan operates continuously, outside air damper modulates between 20% and 80% until the CO2 sensor reaches a level of 300 ppm

Page 136: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 5

below the setpoint. The return damper modulates between 80% and 20% open. Enthalpy rotor motor and exhaust fan motor VFD are enabled with the exhaust fans operating between 80% and 20% capacity. On a call for dehumidification the DDC controller will enable the reactivation fan, dessicant rotor draive and reactivation heat source as required to maintain desired space dew point. Post heating and cooling are utilized as required to maintain desired temperature set-point.

b. Purge – With any mode selected except “OFF”, when the set points (adjustable within DDC controller) of any of the indoor air quality sensors are exceeded and safety circuits normal, or the push button is enabled; supply fan operates continuously, outside air damper drives 100% open and return damper drives fully closed. Enthalpy rotor motor and exhaust fan motor VFD are enabled with the exhaust fans operating 100% (adjustable) capacity. On a call for dehumidification the DDC controller will enable the reactivation fan, dessicant rotor drive and reactivation heat source as required to maintain desired space dew point. Post heating and cooling are utilized as required to maintain desired temperature set-point. When the indoor air quality sensor levels drop below set-point (adjustable .within DDC controller) the unit will remain in Purge mode for a minimum run time of 5 minutes (adjustable within DDC controller).

c. DDC controller alarm indications are visible via DDC controller user interface, remote user interface and BMS interface.

6. Humidity set point is adjusted via controller keypad, remote user interface, or BACnet communication.

7. Space humidity – Dew Point Control: The space air dew point is controlled via the DDC controller. The space air dew point is sensed by the dew point transmitter. When the sensed dew point exceeds set point by 2°F (adjustable) the DDC controller enables a call for dehumidification activating the react circuit, including react fan, DH rotor and heat source.

8. DF React – Reactivation burner ignition and flame management on gas fired units are controlled via a dedicated flame safeguard system proven via flame rectification. Pre-ignition interlocks include reactivation airflow differential pressure proving switch and manual reset high temperature limit switch.a. Reactivation heat source energy rate is controlled by DDC controller as follows:b. ROT Control: As moisture load changes, dessicant ROT (Reactivation Outlet Temperature)

is maintained. Naturally, as the moisture load increases the heater will increase modulation and as the moisture load decreases, the heater will decrease modulation. The RIT will be limited to 320°F.1) Fail-Safe Mode: In order to preserve limited performance, in the event of a sensor

failure, the DDC controller will deliver energy rate as follows:2) With failed RIT sensor, heater output signal is set to a maximum of 50%.3) With failed ROT sensor, heater output signal is set to a maximum of 50%. The RIT

sensor will still limit the RIT to its maximum limit.4) With diminished reactivation airflow (i.e.-dirty filters) RIT is limited in order to prevent

rotor overheat.5) With overheat caused by an abnormal condition, a manual reset high temperature

limit in dessicant reactivation inlet air stream cycles heat source off.9. Unit Alarms – Alarm will occur with each fault and will be displayed on the DDC controller user

interface and available to the BMS.a. Reactivation Low Temp Fault: Occurs when the ROT fails to achieve or falls below 90°F

over a 15 minute period. The unit will continue to run.b. Dessicant Rotor Rotation Fault: Occurs when rotation is not detected within the

programmed time. Reactivation process is disabled. The unit will continue to run.c. External Faults: Other user or factory provided devices may be installed to initiate unit shut-

down via “external faults” input. Unit shut-down occurs upon closing of operator contacts or factory installed contacts.

d. DF Reactivation Flame Safety Fault: Occurs when flame failure is detected by the flame safeguard relay. Reactivation process is disabled. The unit will continue to run.

e. RIT Over Temperature Fault (Manual Reset): Occurs when RIT exceeds 400°F. Reactivation process is disabled. The unit will continue to run. To reset the High Limit Thermostat, cycle the unit power.

f. RIT Over Temperature Fault (Programmed): Occurs when the RIT senses a temperature greater than 360°F. Reactivation process is disabled. The unit will continue to run.

g. ROT Over Temperature Fault (Programmed): Occurs when the ROT senses a temperature greater than 200°F. Reactivation process is disabled. The unit will continue to run.

Page 137: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 6

h. Reactivation Airflow Restriction Fault: Occurs when RIT exceeds 325°F and the reactivation energy modulation is at 0%. Reactivation is disabled. The unit will continue to run.

i. Supply Air Flow Fault: Occurs when airflow is not sensed within 120 seconds of the run enable command or loss of air flow during operation. Reactivation is disabled. The supply fan will continue to run.

j. Supply Air Flow Fault, Smoke Detector Caused: Occurs 120 seconds after smoke is sensed by the smoke detector. The unit will shut down.

k. DAT (Discharge Air Temperature) Low Limit Fault: Occurs 5 minutes (adjustable) after a failure to to achieve DAT above the low limit set point. The unit will shut down.

l. After corrective action is taken, the DDC controller fault conditions may be reset via:1) DDC controller interface2) Cycling of the “Manual-Off-Auto” selector switch to the “Off” position.3) Cycling main unit power4) Remote user interface.5) BMS interface.

10. Space Temperature Controla. The space temperature is measured by the operator provided space temperature/dew point

transmitter. The DDC controller will control post heating and cooling as needed to maintain the space temperature set-point (adjustable)

b. Post Heating: When the space temperature falls below the set point by approximately 1°F (based on adjustable PB) the DDC controller enables the first stage of heating. If the space temperature remains lower than the set-point by approximately 1°F (based on adjustable PB) for the duration of the interstage time delay, the second stage of heat is energized. This process is repeated for the remaining stages.

c. There is an interstage timer for staging to eliminate short cycling. The timer is adjustable and initially set to 3 minutes.

d. When the space temperature has increased above set point by approximately 1°F and the interstage timer has elapsed, the last stage oon will stage off. This process continues until all stages are off.

e. To prevent discharging low temperatures from the unit, the 1st stage will be enabled if the post heat EAT is below 40°F (adjustable) set point. Additional stages are enabled for each additional 20°F the heater EAT is below set point.

f. Post Cooling: When the space temperature rises above the set point by approximately 1°F (based on adjustable PB) the DDC controller enables the first stage of cooling. If the space temperature remains higher than the set-point by approximately 1°F (based on adjustable PB) for the duration of the interstage time delay. The second stage of cooling is energized. This process is repeated for the remaining stages.

g. There is an interstage timer for staging to eliminate short cycling. The timer is adjustable and initially set to 5 minutes.

h. When the space temperature has fallen below set point by approximately 1°F and the interstage timer has elapsed, the last stage on will stage off. This process continues until all stages are off.

1.8 DESSICANT AIR HANDLING UNITS 12 & 13

A. Dessicant air handling units will be remotely controlled through the DDC system.1. Unit will be provided with required sensors and programming.2. Local unit controller will be mounted integral with unit and will be mounted, pre-programmed and

tested by the manufacturer.3. Local control terminal will have LED readout for monitoring and adjusting settings.

B. BMS Interface1. The type of BMS interface will be specified to the manufacturer to provide digital controls interface

card.

C. The stand-alone digital controller will perform the following control sequence.1. Unit Start Command

a. Actuators for all dampers are powered up.b. DDC controller checks damper actuator end switch status.

Page 138: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 7

c. Exhaust fan starts after dampers are open, minimum of 30 seconds delay (adjustable).d. Supply fan and regeneration fan starts 5 seconds (adjustable) after the exhaust fan.

2. Unit Stop Command:a. Fans are de-energized.b. All damper actuators are de-energized and spring return to their fail position after a 30

second delay.3. Defrost: The heat wheel VFD modulates wheel speed in order to maintain the exhaust air

temperature above the defrost set point (20°F default).4. Cooling Mode:

a. Cooling lockout – The cooling will be locked out when the outside air is less than 55°F, 2°F hysteresis. (adjustable)

b. Economizer – The economizer is active only if the outside air enthalpy is less than the return air enthalpy.

c. Economizer (energy recovery reduction type) – The heat wheel VFD modulates wheel speed in order to maintain the supply temperature set point.

d. Sensible Temperature Control – The economizer and cooling are controlled to maintain the supply temperature setpoint. Economizer, if available, will be used as the first stage of cooling.

e. Mechanical Cooling – Mechanical cooling will be used as the second stage of cooling while the economizer is available. The economizer will be held at 100% while mechanical cooling is active as long as it remains available.

f. Sensible Temperature Control – The economizer and cooling are controlled to maintain the supply temperature setpoint. Economizer, if available, will be used as the first stage of cooling.

5. Supply Fan Controla. The supply fan VFD shall be used for manual balancing only.

6. Exhaust Fan Controla. The exhaust fan VFD shall be used for manual balancing only.

7. Regeneration Fan Controla. The regeneration fan VFD shall be used for manual balancing only.

D. Dehumidification Control1. Dehumidification Start Command

a. Dehumidification is required when return dew point is greater than dehumidification set point.

b. Actuator for the regeneration outside air damper is powered, regeneration fan starts after regeneration outside air dampers are open (minimum 30 seconds delay, adjustable).

c. The dessicant wheel shall run at a fixed speed.d. Regeneration heating is allowed.

2. Dehumidification Set Pointa. The DDC controller will reset the supply air dew point set point (range of 50 ° to 55°,

adjustable) up and down in order to maintain the return dew point set pointb. Default return air dew point set point 55°, adjustable.

3. Post Coolinga. Cooling is controlled to maintain a coil leaving air temperature of 64°F (adjustable).

4. Heating (Regeneration Air)a. Regeneration Heating: The regeneration air heating is controlled to maintain the supply air

dew point set point.b. The DDC controller will reset the regeneration wheel inlet temperature set point up and

down between the values listed below. In order to maintain the supply air dew point set point.1) Regeneration wheel inlet temperature minimum set point: 80° (adjustable).2) Regeneration wheel inlet temperature maximum setpoint 200° (adjustable).

c. Fail-Safe Mode: Upon failure of the regeneration wheel inlet temperature sensor. Regeneration heating modulation shall be set to 50%.

5. Regeneration System Post Heat Purge Mode:a. Post heat purge mode will occur anytime the regeneration system switches from active to

inactive.b. Regeneration outside air damper is open.c. Regeneration fan is ON.d. Dessicant wheel is ON.e. Regeneration furnace is OFF.

Page 139: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 8

f. Purge time: 300 seconds, adjustable.6. Dessicant Wheel Bypass Damper Control

a. The process air dessicant wheel bypass damper control is based on a differential pressure transmitter across the process side of the wheel. The dessicant wheel bypass damper will modulate to maintain a constant pressure drop across the process side of the dessicant wheel. Set point 0.87” w.c., adjustable.

7. Remote On/Offa. Unit DDC shall have an input allowing the unit to be started and stopped remotely.

8. Occupied/Unoccupied Modesa. Occupied/Unoccupied mode shall be controlled through the BMS interface.b. Occupied mode:

1) Supply fan ON.2) Regeneration fan per above.3) Exhaust fan ON.4) Heating per above.5) Cooling per above.6) Economizer per above.

c. Unoccupied mode shall be controlled through the BMS interface.1) Supply fan ON.2) Regeneration fan per above.3) Exhaust fan off.4) Exhaust air damper closed.5) Recirculation air damper closed.6) Outside air damper closed.

1.9 PACKAGED ROOFTOP UNITS

A. Cooling with an Economizer1. He economizer is used to control the zone temperature providing the outside air conditions are

suitable. Outside air is drawn into the unit through modulating dampers. When cooling is required and economizing is possible, the unit control processor sends the cooling request to the unit economizer module to open the economizer dampers by energizing the economizer actuator. The controller tries to cool the space utilizing the economizer to slightly below the space setpoint. If the supply air sensor senses that the supply air temperature is below 50°F, the dampers modulate toward the closed position. If the space temperature continues to rise above the space setpoint controlband and the economizer dampers are less than 80% of full open, the controller energizes the compressor contactor.

2. During simultaneous economizing and mechanical cooling (compressor operation), the controller continues to modulate the economizer damper open or closed to keep the supply air temperature in the 50° to 55° range with the compressor operating.

3. If economizing is not possible, the controller drives the damper to the minimum position setpoint when the indoor fan relay is energized and allows mechanical cooling operation.

4. If the supply fan fails to start the fan failure switch will send a signal to the unit controller after 40 seconds. Controller will shut down all cooling functions and send a fault signal to the DDC system.

B. Heating Operation1. When the system swith is set to the “Heat” position ans the space temperature falls below the

heating setpoint controlband, a heat cycle is initiated when the relay coil on the controller is energized. The normally open relay contacts on the controller closes which energizes the heat relay coil and powers the 24V ignition control module. The supply fan then starts and the combustion fan starts as the burner ignites. Once the burner is ignited, the hot surface ignition probe is de-energized by the ignition module and functions as the flame sensing device. If the burner fails to ignite the ignition module will attempt two retries. The unit controller de-energizes the burner and fan when the space sensor determines that the space has reached the space setpoint temperature.

Page 140: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

SEQUENCE OF OPERATIONS FOR HVAC DDC230993.11 - 9

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 230993.11

Page 141: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 1

SECTION 231123FACILITY NATURAL-GAS PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Pipes, tubes, and fittings.2. Piping specialties.3. Piping and tubing joining materials.4. Manual gas shutoff valves.5. Motorized gas valves.6. Pressure regulators.7. Service meters.8. Dielectric fittings.

1.3 DEFINITIONS

A. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.

B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.

C. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of the following:

1. Piping specialties.2. Corrugated, stainless-steel tubing with associated components.3. Valves. Include pressure rating, capacity, settings, and electrical connection data of selected

models.4. Pressure regulators. Indicate pressure ratings and capacities.5. Dielectric fittings.

B. Delegated-Design Submittal: For natural-gas piping and equipment indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1. Detail fabrication and assembly of seismic restraints.2. Design Calculations: Calculate requirements for selecting seismic restraints.

Page 142: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 2

1.5 INFORMATIONAL SUBMITTALS

A. Site Survey: Plans, drawn to scale, on which natural-gas piping is shown and coordinated with other services and utilities.

B. Qualification Data: For qualified professional engineer.

C. Welding certificates.

D. Field quality-control reports.

1.6 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For gas valves and pressure regulators to include in emergency, operation, and maintenance manuals.

1.7 QUALITY ASSURANCE

A. Steel Support Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Pipe Welding Qualifications: Qualify procedures and operators according to ASME Boiler and Pressure Vessel Code.

C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Handling Flammable Liquids: Remove and dispose of liquids from existing natural-gas piping according to requirements of authorities having jurisdiction.

B. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.

C. Store and handle pipes and tubes having factory-applied protective coatings to avoid damaging coating, and protect from direct sunlight.

D. Protect stored PE pipes and valves from direct sunlight.

1.9 PROJECT CONDITIONS

A. Perform site survey, research public utility records, and verify existing utility locations. Contact utility-locating service for area where Project is located.

B. Interruption of Existing Natural-Gas Service: Do not interrupt natural-gas service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide purging and startup of natural-gas supply according to requirements indicated:

1. Notify Owner no fewer than seven days in advance of proposed interruption of natural-gas service.2. Do not proceed with interruption of natural-gas service without Owner's written permission.

Page 143: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 3

1.10 COORDINATION

A. Coordinate sizes and locations of concrete bases with actual equipment provided.

B. Coordinate requirements for access panels and doors for valves installed concealed behind finished surfaces. Comply with requirements in Section 083113 "Access Doors and Frames."

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Minimum Operating-Pressure Ratings:

1. Piping and Valves: 100 psig minimum unless otherwise indicated.2. Service Regulators: 100 psig minimum unless otherwise indicated.

B. Delegated Design: Design restraints and anchors for natural-gas piping and equipment, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.

2.2 PIPES, TUBES, AND FITTINGS

A. Steel Pipe: ASTM A53/A53M, black steel, Schedule 40, Type E or S, Grade B.

1. Malleable-Iron Threaded Fittings: ASME B16.3, Class 150, standard pattern.2. Wrought-Steel Welding Fittings: ASTM A234/A234M for butt welding and socket welding.3. Unions: ASME B16.39, Class 150, malleable iron with brass-to-iron seat, ground joint, and

threaded ends.4. Forged-Steel Flanges and Flanged Fittings: ASME B16.5, minimum Class 150, including bolts,

nuts, and gaskets of the following material group, end connections, and facings:

a. Material Group: 1.1.b. End Connections: Threaded or butt welding to match pipe.c. Lapped Face: Not permitted underground.d. Gasket Materials: ASME B16.20, metallic, flat, asbestos free, aluminum o-rings, and spiral-

wound metal gaskets.e. Bolts and Nuts: ASME B18.2.1, carbon steel aboveground and stainless steel underground.

5. Mechanical Couplings:

a. Approved manufacturers:1) Baker-Hughes2) Smith-Blair3) Approved equivalent

b. Steel flanges and tube with epoxy finish.c. Buna-nitrile seals.d. Steel bolts, washers, and nuts.e. Coupling shall be capable of joining PE pipe to PE pipe, steel pipe to PE pipe, or steel pipe

to steel pipe.f. Steel body couplings installed underground on plastic pipe shall be factory equipped with

anode.

2.3 PIPING SPECIALTIES

A. Y-Pattern Strainers:

Page 144: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 4

1. Body: ASTM A126, Class B, cast iron with bolted cover and bottom drain connection.2. End Connections: Threaded ends for NPS 2 and smaller; flanged ends for NPS 2-1/2 and larger.3. Strainer Screen: 60-mesh startup strainer, and perforated stainless-steel basket with 50 percent

free area.4. CWP Rating: 125 psig.

B. Basket Strainers:

1. Body: ASTM A126, Class B, high-tensile cast iron with bolted cover and bottom drain connection.2. End Connections: Threaded ends for NPS 2 and smaller; flanged ends for NPS 2-1/2 and larger.3. Strainer Screen: 60-mesh startup strainer, and perforated stainless-steel basket with 50 percent

free area.4. CWP Rating: 125 psig.

C. T-Pattern Strainers:

1. Body: Ductile or malleable iron with removable access coupling and end cap for strainer maintenance.

2. End Connections: Grooved ends.3. Strainer Screen: 60-mesh startup strainer, and perforated stainless-steel basket with 57 percent

free area.4. CWP Rating: 750 psig

D. Weatherproof Vent Cap: Cast- or malleable-iron increaser fitting with corrosion-resistant wire screen, with free area at least equal to cross-sectional area of connecting pipe and threaded-end connection.

2.4 JOINING MATERIALS

A. Joint Compound and Tape: Suitable for natural gas.

B. Welding Filler Metals: Comply with AWS D10.12/D10.12M for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

C. Brazing Filler Metals: Alloy with melting point greater than 1000 deg F complying with AWS A5.8/A5.8M. Brazing alloys containing more than 0.05 percent phosphorus are prohibited.

2.5 MANUAL GAS SHUTOFF VALVES

A. See "Underground Manual Gas Shutoff Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles for where each valve type is applied in various services.

B. General Requirements for Metallic Valves, NPS 2 and Smaller: Comply with ASME B16.33.

1. CWP Rating: 125 psig2. Threaded Ends: Comply with ASME B1.20.1.3. Dryseal Threads on Flare Ends: Comply with ASME B1.20.3.4. Tamperproof Feature: Locking feature for valves indicated in "Underground Manual Gas Shutoff

Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.5. Listing: Listed and labeled by an NRTL acceptable to authorities having jurisdiction for valves 1

inch and smaller.6. Service Mark: Valves 1-1/4 inches to NPS 2 shall have initials "WOG" permanently marked on

valve body.

C. General Requirements for Metallic Valves, NPS 2-1/2 and Larger: Comply with ASME B16.38.

1. CWP Rating: 125 psig.2. Flanged Ends: Comply with ASME B16.5 for steel flanges.

Page 145: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 5

3. Tamperproof Feature: Locking feature for valves indicated in "Underground Manual Gas Shutoff Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.

4. Service Mark: Initials "WOG" shall be permanently marked on valve body.

D. One-Piece, Bronze Ball Valve with Bronze Trim: MSS SP-110.

1. Approved manufacturers:a. Apollob. Brasscraftc. Approved equivalent.

2. Body: Bronze, complying with ASTM B584.3. Ball: Chrome-plated brass.4. Stem: Bronze; blowout proof.5. Seats: Reinforced TFE; blowout proof.6. Packing: Separate packnut with adjustable-stem packing threaded ends.7. Ends: Threaded, flared, or socket as indicated in "Underground Manual Gas Shutoff Valve

Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.8. CWP Rating: 600 psig.9. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities

having jurisdiction.10. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

E. Two-Piece, Full-Port, Bronze Ball Valves with Bronze Trim: MSS SP-110.1. Approved manufacturers:

a. Apollob. Brasscraftc. Approved equivalent.

2. Body: Bronze, complying with ASTM B584.3. Ball: Chrome-plated bronze.4. Stem: Bronze; blowout proof.5. Seats: Reinforced TFE; blowout proof.6. Packing: Threaded-body packnut design with adjustable-stem packing.7. Ends: Threaded, flared, or socket as indicated in "Underground Manual Gas Shutoff Valve

Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.8. CWP Rating: 600 psig.9. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities

having jurisdiction.10. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

F. Two-Piece, Regular-Port Bronze Ball Valves with Bronze Trim: MSS SP-110.1. Approved manufacturers:

a. Apollob. Brasscraftc. Approved equivalent.

2. Body: Bronze, complying with ASTM B584.3. Ball: Chrome-plated bronze.4. Stem: Bronze; blowout proof.5. Seats: Reinforced TFE.6. Packing: Threaded-body packnut design with adjustable-stem packing.7. Ends: Threaded, flared, or socket as indicated in "Underground Manual Gas Shutoff Valve

Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.8. CWP Rating: 600 psig.9. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities

having jurisdiction.10. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

G. Bronze Plug Valves: MSS SP-78.1. Approved manufacturers:

a. A.Y. McDonaldb. Lee Brassc. Approved equivalent.

Page 146: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 6

2. Body: Bronze, complying with ASTM B584.3. Plug: Bronze.4. Ends: Threaded, socket, or flanged as indicated in "Underground Manual Gas Shutoff Valve

Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.5. Operator: Square head or lug type with tamperproof feature where indicated.6. Pressure Class: 125 psig.7. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities

having jurisdiction.8. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

H. Cast-Iron, Nonlubricated Plug Valves: MSS SP-78.1. Approved manufacturers:

a. A.Y. McDonaldb. Muellerc. Approved equivalent.

2. Body: Cast iron, complying with ASTM A126, Class B.3. Plug: Bronze or nickel-plated cast iron.4. Seat: Coated with thermoplastic.5. Stem Seal: Compatible with natural gas.6. Ends: Threaded or flanged as indicated in "Underground Manual Gas Shutoff Valve Schedule" and

"Aboveground Manual Gas Shutoff Valve Schedule" Articles.7. Operator: Square head or lug type with tamperproof feature where indicated.8. Pressure Class: 125 psig.9. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities

having jurisdiction.10. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

I. Cast-Iron, Lubricated Plug Valves: MSS SP-78.1. Approved manufacturers:

a. A.Y. McDonaldb. Muellerc. Approved equivalent.

2. Body: Cast iron, complying with ASTM A126, Class B.3. Plug: Bronze or nickel-plated cast iron.4. Seat: Coated with thermoplastic.5. Stem Seal: Compatible with natural gas.6. Ends: Threaded or flanged as indicated in "Underground Manual Gas Shutoff Valve Schedule" and

"Aboveground Manual Gas Shutoff Valve Schedule" Articles.7. Operator: Square head or lug type with tamperproof feature where indicated.8. Pressure Class: 125 psig.9. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities

having jurisdiction.10. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

2.6 PRESSURE REGULATORS

A. General Requirements:

1. Single stage and suitable for natural gas.2. Steel jacket and corrosion-resistant components.3. Elevation compensator.4. End Connections: Threaded for regulators NPS 2 and smaller; flanged for regulators NPS 2-1/2

and larger.

B. Service Pressure Regulators: Comply with ANSI Z21.80.

1. Approved manufacturers:a. American Meter Co.b. Fisher Control Valves

Page 147: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 7

c. Approved equivalent2. Body and Diaphragm Case: Cast iron or die-cast aluminum.3. Springs: Zinc-plated steel; interchangeable.4. Diaphragm Plate: Zinc-plated steel.5. Seat Disc: Nitrile rubber resistant to gas impurities, abrasion, and deformation at the valve port.6. Orifice: Aluminum; interchangeable.7. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.8. Single-port, self-contained regulator with orifice no larger than required at maximum pressure inlet,

and no pressure sensing piping external to the regulator.9. Pressure regulator shall maintain discharge pressure setting downstream, and not exceed 150

percent of design discharge pressure at shutoff.10. Overpressure Protection Device: Factory mounted on pressure regulator.11. Atmospheric Vent: Factory- or field-installed, stainless-steel screen in opening if not connected to

vent piping.12. Maximum Inlet Pressure: 100 psig.

C. Line Pressure Regulators: Comply with ANSI Z21.80.1. Approved manufacturers:

a. American Meter Co.b. Fisher Control Valvesc. Approved equivalent

2. Body and Diaphragm Case: Cast iron or die-cast aluminum.3. Springs: Zinc-plated steel; interchangeable.4. Diaphragm Plate: Zinc-plated steel.5. Seat Disc: Nitrile rubber resistant to gas impurities, abrasion, and deformation at the valve port.6. Orifice: Aluminum; interchangeable.7. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.8. Single-port, self-contained regulator with orifice no larger than required at maximum pressure inlet,

and no pressure sensing piping external to the regulator.9. Pressure regulator shall maintain discharge pressure setting downstream, and not exceed 150

percent of design discharge pressure at shutoff.10. Overpressure Protection Device: Factory mounted on pressure regulator.11. Atmospheric Vent: Factory- or field-installed, stainless-steel screen in opening if not connected to

vent piping.12. Maximum Inlet Pressure: 10 psig.

D. Appliance Pressure Regulators: Comply with ANSI Z21.18.

1. Approved manufacturers:a. Eatonb. Maxitrolc. Approved equivalent

2. Body and Diaphragm Case: Die-cast aluminum.3. Springs: Zinc-plated steel; interchangeable.4. Diaphragm Plate: Zinc-plated steel.5. Seat Disc: Nitrile rubber.6. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.7. Factory-Applied Finish: Minimum three-layer polyester and polyurethane paint finish.8. Regulator may include vent limiting device, instead of vent connection, if approved by authorities

having jurisdiction.9. Maximum Inlet Pressure: 5 psig.

2.7 DIELECTRIC FITTINGS

A. General Requirements: Assembly of copper alloy and ferrous materials with separating nonconductive insulating material. Include end connections compatible with pipes to be joined.

B. Dielectric Unions:

1. Approved manufacturers:

Page 148: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 8

a. A.Y. McDonaldb. Zurnc. Approved equivalent

2. Description:

a. Standard: ASSE 1079.b. Pressure Rating: 125 psigc. End Connections: Solder-joint copper alloy and threaded ferrous.

C. Dielectric Flanges:

1. Approved manufacturers:a. Wattsb. Wilkinsc. Approved equivalent

2. Description:

a. Standard: ASSE 1079.b. Factory-fabricated, bolted, companion-flange assembly.c. Pressure Rating: 125 psig minimum at 180 deg F. d. End Connections: Solder-joint copper alloy and threaded ferrous; threaded solder-joint

copper alloy and threaded ferrous.

D. Dielectric-Flange Insulating Kits:

1. Approved manufacturers:a. Calpicob. Central Plasticsc. Approved equivalent

2. Description:

a. Nonconducting materials for field assembly of companion flanges.b. Pressure Rating: 150 psig.c. Gasket: Neoprene or phenolic.d. Bolt Sleeves: Phenolic or polyethylene.e. Washers: Phenolic with steel backing washers.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine roughing-in for natural-gas piping system to verify actual locations of piping connections before equipment installation.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Close equipment shutoff valves before turning off natural gas to premises or piping section.

B. Inspect natural-gas piping according to the International Fuel Gas Code to determine that natural-gas utilization devices are turned off in piping section affected.

Page 149: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 9

C. Comply with the International Fuel Gas Code requirements for prevention of accidental ignition.

3.3 OUTDOOR PIPING INSTALLATION

A. Comply with the International Fuel Gas Code for installation and purging of natural-gas piping.

B. Steel Piping with Protective Coating:

1. Apply joint cover kits to pipe after joining to cover, seal, and protect joints.2. Repair damage to PE coating on pipe as recommended in writing by protective coating

manufacturer.3. Replace pipe having damaged PE coating with new pipe.

C. Install fittings for changes in direction and branch connections.

D. Install pressure gage downstream from each service regulator.

3.4 VALVE INSTALLATION

A. Install manual gas shutoff valve for each gas appliance ahead of corrugated stainless-steel tubing, aluminum, or copper connector.

B. Install underground valves with valve boxes.

C. Install regulators and overpressure protection devices with maintenance access space adequate for servicing and testing.

D. Install earthquake valves aboveground outside buildings according to listing.

E. Install anode for metallic valves in underground PE piping.

3.5 PIPING JOINT CONSTRUCTION

A. Ream ends of pipes and tubes and remove burrs.

B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

C. Threaded Joints:

1. Thread pipe with tapered pipe threads complying with ASME B1.20.1.2. Cut threads full and clean using sharp dies.3. Ream threaded pipe ends to remove burrs and restore full inside diameter of pipe.4. Apply appropriate tape or thread compound to external pipe threads unless dryseal threading is

specified.5. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do

not use pipe sections that have cracked or open welds.

D. Welded Joints:

1. Construct joints according to AWS D10.12/D10.12M, using qualified processes and welding operators.

2. Bevel plain ends of steel pipe.3. Patch factory-applied protective coating as recommended by manufacturer at field welds and

where damage to coating occurs during construction.

Page 150: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 10

E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube" Chapter.

F. Flanged Joints: Install gasket material, size, type, and thickness appropriate for natural-gas service. Install gasket concentrically positioned.

G. Flared Joints: Cut tubing with roll cutting tool. Flare tube end with tool to result in flare dimensions complying with SAE J513. Tighten finger tight, then use wrench. Do not overtighten.

H. PE Piping Heat-Fusion Joints: Clean and dry joining surfaces by wiping with clean cloth or paper towels. Join according to ASTM D2657.

1. Plain-End Pipe and Fittings: Use butt fusion.2. Plain-End Pipe and Socket Fittings: Use socket fusion.

3.6 HANGER AND SUPPORT INSTALLATION

A. Comply with requirements for seismic-restraint devices specified in Section 230548 "Vibration and Seismic Controls for HVAC."

B. Comply with requirements for pipe hangers and supports specified in Section 230529 "Hangers and Supports for HVAC Piping and Equipment."

C. Install hangers for steel piping, with maximum horizontal spacing and minimum rod diameters, to comply with MSS-58, locally enforced codes, and authorities having jurisdiction requirements, whichever are most stringent.

D. Install hangers for corrugated stainless-steel tubing, with maximum horizontal spacing and minimum rod diameters, to comply with manufacturer's written instructions, locally enforced codes, and authorities having jurisdiction requirements, whichever are most stringent.

E. Support horizontal piping within 12 inches of each fitting.

F. Support vertical runs of steel piping to comply with MSS-58, locally enforced codes, and authorities having jurisdiction requirements, whichever are most stringent.

G. Support vertical runs of corrugated stainless-steel tubing to comply with manufacturer's written instructions, locally enforced codes, and authorities having jurisdiction requirements, whichever are most stringent.

3.7 CONNECTIONS

A. Connect to utility's gas main according to utility's procedures and requirements.

B. Install natural-gas piping electrically continuous, and bonded to gas appliance equipment grounding conductor of the circuit powering the appliance according to NFPA 70.

C. Install piping adjacent to appliances to allow service and maintenance of appliances.

D. Connect piping to appliances using manual gas shutoff valves and unions. Install valve within 72 inches of each gas-fired appliance and equipment. Install union between valve and appliances or equipment.

E. Sediment Traps: Install tee fitting with capped nipple in bottom to form drip, as close as practical to inlet of each appliance.

Page 151: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 11

3.8 PAINTING

A. Paint exposed, exterior metal piping, valves, service regulators, service meters and meter bars, earthquake valves, and piping specialties, except components, with factory-applied paint or protective coating.

1. Alkyd System: MPI EXT 5.1D.

a. Prime Coat: Alkyd anticorrosive metal primer.b. Intermediate Coat: Exterior alkyd enamel matching topcoat.c. Topcoat: Exterior alkyd enamel semigloss.d. Color: Gray.

B. Damage and Touchup: Repair marred and damaged factory-applied finishes with materials and by procedures to match original factory finish.

3.9 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections:

1. Test, inspect, and purge natural gas according to the International Fuel Gas Code and authorities having jurisdiction.

C. Natural-gas piping will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

3.10 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain gas valves.

3.11 OUTDOOR PIPING SCHEDULE

A. Aboveground natural-gas piping shall be one of the following:

1. Steel pipe with malleable-iron fittings and threaded joints.2. Steel pipe with wrought-steel fittings and welded joints.

END OF SECTION 231123

Page 152: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

FACILITY NATURAL-GAS PIPING231123 - 12

This page intentionally left blank.

Page 153: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 1

SECTION 232300REFRIGERANT PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Refrigerant pipes and fittings.2. Refrigerant piping valves and specialties.3. Refrigerants.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of valve, refrigerant piping, and piping specialty.

1. Include pressure drop, based on manufacturer's test data, for the following:

a. Thermostatic expansion valves.b. Solenoid valves.c. Hot-gas bypass valves.d. Filter dryers.e. Strainers.f. Pressure-regulating valves.

1.4 INFORMATIONAL SUBMITTALS

A. Welding certificates.

B. Field quality-control reports.

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For refrigerant valves and piping specialties to include in maintenance manuals.

1.6 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to 2010 ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."

B. Comply with ASHRAE 15, "Safety Code for Refrigeration Systems."

C. Comply with ASME B31.5, "Refrigeration Piping and Heat Transfer Components."

Page 154: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 2

1.7 PRODUCT STORAGE AND HANDLING

A. Store piping with end caps in place to ensure that piping interior and exterior are clean when installed.

PART 2 - PRODUCTS

2.1 COPPER TUBE AND FITTINGS

A. Copper Tube: ASTM B 88, Type K or L.

B. Wrought-Copper Fittings: ASME B16.22.

C. Wrought-Copper Unions: ASME B16.22.

D. Solder Filler Metals: ASTM B 32. Use 95-5 tin antimony or alloy HB solder to join copper socket fittings on copper pipe.

E. Brazing Filler Metals: AWS A5.8/A5.8M.

F. Copper Pressure-Seal Fittings for Refrigerant Piping:

1. Approved manufacturers:a. Conex-Banningerb. Parker-Hannefinc. Approved equivalent

2. Standard: UL 207; certified by UL for field installation. Certification as a UL-recognized component alone is unacceptable.

3. Housing: Copper.4. O-Rings: HNBR or compatible with specific refrigerant.5. Tools: Manufacturer's approved special tools.6. Minimum Rated Pressure: 700 psig.

2.2 STEEL PIPE AND FITTINGS

A. Steel Pipe: ASTM A 53/A 53M, black steel with plain ends; type, grade, and wall thickness as selected in piping application articles.

B. Wrought-Steel Fittings: ASTM A 234/A 234M, for welded joints.

C. Steel Flanges and Flanged Fittings: ASME B16.5, steel, including bolts, nuts, and gaskets, bevel-welded end connection, and raised face.

D. Welding Filler Metals: Comply with AWS D10.12M/D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

E. Flanged Unions:

1. Body: Forged-steel flanges for NPS 1 to NPS 1-1/2 and ductile iron for NPS 2 to NPS 3. Apply rust-resistant finish at factory.

2. Gasket: Fiber asbestos free.3. Fasteners: Four plated-steel bolts, with silicon bronze nuts. Apply rust-resistant finish at factory.4. End Connections: Brass tailpiece adapters for solder-end connections to copper tubing.5. Offset Performance: Capable of minimum 3/4-inch misalignment in minimum 7-inch long assembly.6. Pressure Rating: Factory test at minimum 400 psig.7. Maximum Operating Temperature: 330 deg F.

Page 155: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 3

F. Flexible Connectors:

1. Body: Stainless-steel bellows with woven, flexible, stainless-steel-wire-reinforced protective jacket.2. End Connections:

a. NPS 2 and Smaller: With threaded-end connections.b. NPS 2-1/2 and Larger: With flanged-end connections.

3. Offset Performance: Capable of minimum 3/4-inch misalignment in minimum 7-inch long assembly.4. Pressure Rating: Factory test at minimum 500 psig.5. Maximum Operating Temperature: 250 deg F.

2.3 VALVES AND SPECIALTIES

A. Diaphragm Packless Valves:1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body and Bonnet: Forged brass or cast bronze; globe design with straight-through or angle pattern.3. Diaphragm: Phosphor bronze and stainless steel with stainless-steel spring.4. Operator: Rising stem and hand wheel.5. Seat: Nylon.6. End Connections: Socket, union, or flanged.7. Working Pressure Rating: 500 psig.8. Maximum Operating Temperature: 275 deg F.

B. Packed-Angle Valves:1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body and Bonnet: Forged brass or cast bronze.3. Packing: Molded stem, back seating, and replaceable under pressure.4. Operator: Rising stem.5. Seat: Nonrotating, self-aligning polytetrafluoroethylene.6. Seal Cap: Forged-brass or valox hex cap.7. End Connections: Socket, union, threaded, or flanged.8. Working Pressure Rating: 500 psig.9. Maximum Operating Temperature: 275 deg F.

C. Check Valves:1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body: Ductile iron, forged brass, or cast bronze; globe pattern.3. Bonnet: Bolted ductile iron, forged brass, or cast bronze; or brass hex plug.4. Piston: Removable polytetrafluoroethylene seat.5. Closing Spring: Stainless steel.6. Manual Opening Stem: Seal cap, plated-steel stem, and graphite seal.7. End Connections: Socket, union, threaded, or flanged.8. Maximum Opening Pressure: 0.50 psig.9. Working Pressure Rating: 500 psig.10. Maximum Operating Temperature: 275 deg F.

D. Service Valves:1. Approved manufacturers:

a. Danfoss

Page 156: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 4

b. Parker-Hannefinc. Approved equivalent

2. Body: Forged brass with brass cap including key end to remove core.3. Core: Removable ball-type check valve with stainless-steel spring.4. Seat: Polytetrafluoroethylene.5. End Connections: Copper spring.6. Working Pressure Rating: 500 psig.

E. Solenoid Valves: Comply with AHRI 760 and UL 429; listed and labeled by a National Recognized Testing Laboratory (NRTL).1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body and Bonnet: Plated steel.3. Solenoid Tube, Plunger, Closing Spring, and Seat Orifice: Stainless steel.4. Seat: Polytetrafluoroethylene.5. End Connections: Threaded.6. Electrical: Molded, watertight coil in NEMA 250 enclosure of type required by location with 1/2-inch

conduit adapter, and 24-V ac coil.7. Working Pressure Rating: 400 psig.8. Maximum Operating Temperature: 240 deg F.

F. Safety Relief Valves: Comply with 2010 ASME Boiler and Pressure Vessel Code; listed and labeled by an NRTL.1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body and Bonnet: Ductile iron and steel, with neoprene O-ring seal.3. Piston, Closing Spring, and Seat Insert: Stainless steel.4. Seat: Polytetrafluoroethylene.5. End Connections: Threaded.6. Working Pressure Rating: 400 psig.7. Maximum Operating Temperature: 240 deg F.

G. Thermostatic Expansion Valves: Comply with AHRI 750.1. Approved manufacturers:

a. Danfossb. Muellerc. Approved equivalent

2. Body, Bonnet, and Seal Cap: Forged brass or steel.3. Diaphragm, Piston, Closing Spring, and Seat Insert: Stainless steel.4. Packing and Gaskets: Non-asbestos.5. Capillary and Bulb: Copper tubing filled with refrigerant charge.6. Suction Temperature: 40 deg F.7. Superheat: Adjustable.8. End Connections: Socket, flare, or threaded union.9. Working Pressure Rating: 700 psig.

H. Hot-Gas Bypass Valves: Comply with UL 429; listed and labeled by an NRTL.1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body, Bonnet, and Seal Cap: Ductile iron or steel.3. Diaphragm, Piston, Closing Spring, and Seat Insert: Stainless steel.4. Packing and Gaskets: Non-asbestos.5. Solenoid Tube, Plunger, Closing Spring, and Seat Orifice: Stainless steel.6. Seat: Polytetrafluoroethylene.7. Equalizer: External.

Page 157: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 5

8. Electrical: Molded, watertight coil in NEMA 250 enclosure of type required by location with 1/2-inch conduit adapter and 24-V ac coil.

9. End Connections: Socket.10. Throttling Range: Maximum 5 psig.11. Working Pressure Rating: 500 psig.12. Maximum Operating Temperature: 240 deg F.

I. Straight-Type Strainers:1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body: Welded steel with corrosion-resistant coating.3. Screen: 100-mesh stainless steel.4. End Connections: Socket or flare.5. Working Pressure Rating: 500 psig.6. Maximum Operating Temperature: 275 deg F.

J. Angle-Type Strainers:1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body: Forged brass or cast bronze.3. Drain Plug: Brass hex plug.4. Screen: 100-mesh monel.5. End Connections: Socket or flare.6. Working Pressure Rating: 500 psig.7. Maximum Operating Temperature: 275 deg F.

K. Moisture/Liquid Indicators:1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body: Forged brass.3. Window: Replaceable, clear, fused glass window with indicating element protected by filter screen.4. Indicator: Color coded to show moisture content in parts per million (ppm).5. Minimum Moisture Indicator Sensitivity: Indicate moisture above 60 ppm.6. End Connections: Socket or flare.7. Working Pressure Rating: 500 psig.8. Maximum Operating Temperature: 240 deg F.

L. Replaceable-Core Filter Dryers: Comply with AHRI 730.1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body and Cover: Painted-steel shell with ductile-iron cover, stainless-steel screws, and neoprene gaskets.

3. Filter Media: 10 micron, pleated with integral end rings; stainless-steel support.4. Desiccant Media: Activated alumina.5. End Connections: Socket.6. Access Ports: NPS 1/4 connections at entering and leaving sides for pressure differential

measurement.7. Maximum Pressure Loss: 2 psig.8. Rated Flow: 200 tons.9. Working Pressure Rating: 500 psig.10. Maximum Operating Temperature: 240 deg F.

Page 158: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 6

M. Permanent Filter Dryers: Comply with AHRI 730.1. Approved manufacturers:

a. Danfossb. Parker-Hannefinc. Approved equivalent

2. Body and Cover: Painted-steel shell.3. Filter Media: 10 micron, pleated with integral end rings; stainless-steel support.4. Desiccant Media: Activated alumina.5. End Connections: Socket.6. Access Ports: NPS 1/4 connections at entering and leaving sides for pressure differential

measurement.7. Maximum Pressure Loss: 2 psig.8. Rated Flow: 200 tons.9. Working Pressure Rating: 500 psig .10. Maximum Operating Temperature: 240 deg F.

N. Mufflers:1. Approved manufacturers:

a. Danfossb. Emerson Climate Technologyc. Approved equivalent

2. Body: Welded steel with corrosion-resistant coating.3. End Connections: Socket or flare.4. Working Pressure Rating: 500 psig.5. Maximum Operating Temperature: 275 deg F.

O. Receivers: Comply with AHRI 495.1. Approved manufacturers:

a. Heldon Productsb. Approved equivalent

2. Comply with 2010 ASME Boiler and Pressure Vessel Code; listed and labeled by an NRTL.3. Comply with UL 207; listed and labeled by an NRTL.4. Body: Welded steel with corrosion-resistant coating.5. Tappings: Inlet, outlet, liquid level indicator, and safety relief valve.6. End Connections: Socket or threaded.7. Working Pressure Rating: 500 psig.8. Maximum Operating Temperature: 275 deg F.

P. Liquid Accumulators: Comply with AHRI 495.1. Approved manufacturers:

a. Emersonb. Parker-Hannefinc. Approved equivalent

2. Body: Welded steel with corrosion-resistant coating.3. End Connections: Socket or threaded.4. Working Pressure Rating: 500 psig.5. Maximum Operating Temperature: 275 deg F.

2.4 REFRIGERANTS

A. ASHRAE 34, R-448a: Zeotropic blend of R-32, R-125, R-134a, R-1234ze, and R-1234yf.

1. Acceptable manufacturers:a. Honeywellb. Climalifec. Approved equivalent

Page 159: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 7

PART 3 - EXECUTION

3.1 VALVE AND SPECIALTY APPLICATIONS

A. Install diaphragm packless or packed-angle valves in suction and discharge lines of compressor.

B. Install service valves for gage taps at inlet and outlet of hot-gas bypass valves and strainers if they are not an integral part of valves and strainers.

C. Install a check valve at the compressor discharge and a liquid accumulator at the compressor suction connection.

D. Except as otherwise indicated, install diaphragm packless or packed-angle valves on inlet and outlet side of filter dryers.

E. Install a full-size, three-valve bypass around filter dryers.

F. Install solenoid valves upstream from each expansion valve and hot-gas bypass valve. Install solenoid valves in horizontal lines with coil at top.

G. Install thermostatic expansion valves as close as possible to distributors on evaporators.

1. Install valve so diaphragm case is warmer than bulb.2. Secure bulb to clean, straight, horizontal section of suction line using two bulb straps. Do not mount

bulb in a trap or at bottom of the line.3. If external equalizer lines are required, make connection where it will reflect suction-line pressure at

bulb location.

H. Install safety relief valves where required by 2010 ASME Boiler and Pressure Vessel Code. Pipe safety-relief-valve discharge line to outside according to ASHRAE 15.

I. Install moisture/liquid indicators in liquid line at the inlet of the thermostatic expansion valve or at the inlet of the evaporator coil capillary tube.

J. Install strainers upstream from and adjacent to the following unless they are furnished as an integral assembly for the device being protected:

1. Solenoid valves.2. Thermostatic expansion valves.3. Hot-gas bypass valves.4. Compressor.

K. Install filter dryers in liquid line between compressor and thermostatic expansion valve, and in the suction line at the compressor.

L. Install receivers sized to accommodate pump-down charge.

M. Install flexible connectors at compressors.

3.2 PIPING INSTALLATION

A. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems; indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Shop Drawings.

B. Install refrigerant piping according to ASHRAE 15.

Page 160: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 8

C. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

D. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

E. Install piping adjacent to machines to allow service and maintenance.

F. Install piping free of sags and bends.

G. Install fittings for changes in direction and branch connections.

H. Select system components with pressure rating equal to or greater than system operating pressure.

I. Refer to Section 230923 "Direct Digital Control (DDC) System for HVAC" and Section 230993.11 "Sequence of Operations for HVAC DDC" for solenoid valve controllers, control wiring, and sequence of operation.

J. Install piping as short and direct as possible, with a minimum number of joints, elbows, and fittings.

K. Arrange piping to allow inspection and service of refrigeration equipment. Install valves and specialties in accessible locations to allow for service and inspection. Install access doors or panels as specified in Section 083113 "Access Doors and Frames" if valves or equipment requiring maintenance is concealed behind finished surfaces.

L. Install refrigerant piping in rigid or flexible conduit in locations where exposed to mechanical injury.

M. Slope refrigerant piping as follows:

1. Install horizontal hot-gas discharge piping with a uniform slope downward away from compressor.2. Install horizontal suction lines with a uniform slope downward to compressor.3. Install traps and double risers to entrain oil in vertical runs.4. Liquid lines may be installed level.

N. When brazing or soldering, remove solenoid-valve coils and sight glasses; also remove valve stems, seats, and packing, and accessible internal parts of refrigerant specialties. Do not apply heat near expansion-valve bulb.

O. Before installation of steel refrigerant piping, clean pipe and fittings using the following procedures:

1. Shot blast the interior of piping.2. Remove coarse particles of dirt and dust by drawing a clean, lintless cloth through tubing by means

of a wire or electrician's tape.3. Draw a clean, lintless cloth saturated with trichloroethylene through the tube or pipe. Continue this

procedure until cloth is not discolored by dirt.4. Draw a clean, lintless cloth, saturated with compressor oil, squeezed dry, through the tube or pipe

to remove remaining lint. Inspect tube or pipe visually for remaining dirt and lint.5. Finally, draw a clean, dry, lintless cloth through the tube or pipe.6. Safety-relief-valve discharge piping is not required to be cleaned but is required to be open to allow

unrestricted flow.

P. Install piping with adequate clearance between pipe and adjacent walls and hangers or between pipes for insulation installation.

Q. Identify refrigerant piping and valves according to Section 230553 "Identification for HVAC Piping and Equipment."

Page 161: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 9

3.3 PIPE JOINT CONSTRUCTION

A. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

C. Fill pipe and fittings with an inert gas (nitrogen or carbon dioxide), during brazing or welding, to prevent scale formation.

D. Soldered Joints: Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook."

E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," Chapter "Pipe and Tube."

1. Use Type BCuP (copper-phosphorus) alloy for joining copper socket fittings with copper pipe.2. Use Type BAg (cadmium-free silver) alloy for joining copper with bronze or steel.

F. Threaded Joints: Thread steel pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and to restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry-seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

G. Steel pipe can be threaded, but threaded joints must be seal brazed or seal welded.

H. Welded Joints: Construct joints according to AWS D10.12M/D10.12.

I. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

3.4 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. Comply with ASME B31.5, Chapter VI.2. Test refrigerant piping, specialties, and receivers. Isolate compressor, condenser, evaporator, and

safety devices from test pressure if they are not rated above the test pressure.3. Test high- and low-pressure side piping of each system separately at not less than the pressures

indicated in "Performance Requirements" Article.

a. Fill system with nitrogen to the required test pressure.b. System shall maintain test pressure at the manifold gage throughout duration of test.c. Test joints and fittings with electronic leak detector or by brushing a small amount of soap

and glycerin solution over joints.d. Remake leaking joints using new materials, and retest until satisfactory results are

achieved.

B. Prepare test and inspection reports.

3.5 SYSTEM CHARGING

A. Charge system using the following procedures:

1. Install core in filter dryers after leak test but before evacuation.

Page 162: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

REFRIGERANT PIPING232300 - 10

2. Evacuate entire refrigerant system with a vacuum pump to 500 micrometers. If vacuum holds for 12 hours, system is ready for charging.

3. Break vacuum with refrigerant gas, allowing pressure to build up to 2 psig.4. Charge system with a new filter-dryer core in charging line.

3.6 ADJUSTING

A. Adjust thermostatic expansion valve to obtain proper evaporator superheat.

B. Adjust high- and low-pressure switch settings to avoid short cycling in response to fluctuating suction pressure.

C. Adjust set-point temperature of air-conditioning or chilled-water controllers to the system design temperature.

D. Perform the following adjustments before operating the refrigeration system, according to manufacturer's written instructions:

1. Open shutoff valves in condenser water circuit.2. Verify that compressor oil level is correct.3. Open compressor suction and discharge valves.4. Open refrigerant valves except bypass valves that are used for other purposes.5. Check open compressor-motor alignment and verify lubrication for motors and bearings.

E. Replace core of replaceable filter dryer after system has been adjusted and after design flow rates and pressures are established.

END OF SECTION 232300

Page 163: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 1

SECTION 233113METAL DUCTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Single-wall rectangular ducts and fittings.2. Double-wall rectangular ducts and fittings.3. Sheet metal materials.4. Duct liner.5. Sealants and gaskets.6. Hangers and supports.

B. Related Sections:

1. Section 230593 "Testing, Adjusting, and Balancing for HVAC" for testing, adjusting, and balancing requirements for metal ducts.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of the following products:

1. Liners and adhesives.2. Sealants and gaskets.

B. Shop Drawings:

1. Fabrication, assembly, and installation, including plans, elevations, sections, components, and attachments to other work.

2. Factory- and shop-fabricated ducts and fittings.3. Duct layout indicating sizes, configuration, liner material, and static-pressure classes.4. Elevation of top and bottom of ducts.5. Dimensions of all duct runs from building grid lines.6. Fittings.7. Reinforcement and spacing.8. Seam and joint construction.9. Equipment installation based on equipment being used on Project.10. Locations for duct accessories, including dampers, turning vanes, and access doors and panels.11. Hangers and supports, including methods for duct and building attachment, and vibration isolation.

C. Delegated-Design Submittal:

1. Sheet metal thicknesses.2. Joint and seam construction and sealing.3. Reinforcement details and spacing.4. Materials, fabrication, assembly, and spacing of hangers and supports.

Page 164: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 2

1.4 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: A single set of plans or BIM model, drawn to scale, showing the items described in this Section, and coordinated with all existing building features and equipment installation.

B. Welding certificates.

C. Field quality-control reports.

1.5 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel in accordance with the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel," for hangers and supports.2. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum," for aluminum supports.3. AWS D9.1/D9.1M, "Sheet Metal Welding Code," for duct joint and seam welding.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Delegated Duct Design: Duct construction, including sheet metal thicknesses, seam and joint construction, reinforcements, and hangers and supports, shall comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" and with performance requirements and design criteria indicated in "Duct Schedule" Article.

B. Structural Performance: Duct hangers and supports shall withstand the effects of gravity loads and stresses within limits and under conditions described in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" and current Mechanical Codes.

C. Airstream Surfaces: Surfaces in contact with airstream shall comply with requirements in ASHRAE 62.1.

D. ASHRAE Compliance: Applicable requirements in ASHRAE 62.1, Section 5 - "Systems and Equipment," and Section 7 - "Construction and System Startup."

E. ASHRAE/IES Compliance: Applicable requirements in ASHRAE/IES 90.1, Section 6.4.4 - "HVAC System Construction and Insulation."

F. Duct Dimensions: Unless otherwise indicated, all duct dimensions indicated on Drawings are inside clear dimensions and do not include insulation or duct wall thickness.

2.2 SINGLE-WALL RECTANGULAR DUCTS AND FITTINGS

A. General Fabrication Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" based on indicated static-pressure class unless otherwise indicated.

1. Construct ducts of galvanized sheet steel unless otherwise indicated.2. For ducts exposed to weather, construct of Type 304 stainless steel indicated by manufacturer to

be suitable for outdoor installation.

B. Transverse Joints: Fabricate joints in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-1, "Rectangular Duct/Transverse Joints," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

Page 165: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 3

1. For ducts with longest side less than 36 inches, select joint types in accordance with Figure 2-1.2. For ducts with longest side 36 inches or greater, use flange joint connector Type T-22, T-24, T-24A,

T-25a, or T-25b. Factory-fabricated flanged duct connection system may be used if submitted and approved by engineer of record.

C. Longitudinal Seams: Select seam types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-2, "Rectangular Duct/Longitudinal Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." All longitudinal seams shall be Pittsburgh lock seams unless otherwise specified for specific application.

D. Elbows, Transitions, Offsets, Branch Connections, and Other Duct Construction: Select types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Ch. 4, "Fittings and Other Construction," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

2.3 DOUBLE-WALL RECTANGULAR DUCTS AND FITTINGS

A. Acceptable manufacturers:1. United McGill2. MKT Metal Manufacturing3. Approved equivalent

B. Rectangular Ducts: Fabricate ducts with indicated dimensions for clear internal dimensions of the inner duct.

C. Outer Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" based on indicated static-pressure class unless otherwise indicated.

1. Construct ducts of galvanized sheet steel unless otherwise indicated.2. For ducts exposed to weather, construct outer duct of Type 304 stainless steel indicated by

manufacturer to be suitable for outdoor installation.

D. Transverse Joints: Select joint types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-1, "Rectangular Duct/Transverse Joints," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

1. For ducts with longest side less than 36 inches, select joint types in accordance with Figure 2-1.2. For ducts with longest side 36 inches or greater, use flange joint connector Type T-22, T-24, T-24A,

T-25a, or T-25b. Factory-fabricated flanged duct connection system may be used if submitted and approved by engineer of record.

E. Longitudinal Seams: Select seam types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 2-2, "Rectangular Duct/Longitudinal Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible." All longitudinal seams shall be Pittsburgh lock seams unless otherwise specified for specific application.

F. Interstitial Insulation: Fibrous-glass liner complying with ASTM C1071, NFPA 90A, or NFPA 90B; and with NAIMA AH124, "Fibrous Glass Duct Liner Standard."

1. Maximum Thermal Conductivity: 0.27 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature.2. Install spacers that position the inner duct at uniform distance from outer duct without compressing

insulation.3. Coat insulation with antimicrobial coating.4. Cover insulation with polyester film complying with UL 181, Class 1.

Page 166: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 4

G. Interstitial Insulation: Flexible elastomeric duct liner complying with ASTM C534/C534M, Type II for sheet materials, and with NFPA 90A or NFPA 90B.

1. Maximum Thermal Conductivity: 0.25 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature.

H. Inner Duct: Minimum 24-gauge perforated galvanized sheet steel having 3/32-inch diameter perforations, with overall open area of 23 percent..

2.4 SINGLE-WALL ROUND DUCTS AND FITTINGS

A. General Fabrication Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Ch. 3, "Round, Oval, and Flexible Duct," based on indicated static-pressure class unless otherwise indicated.

1. Construct ducts of galvanized sheet steel unless otherwise indicated.2. For ducts exposed to weather, construct of Type 304 stainless steel indicated by manufacturer to

be suitable for outdoor installation.

B. Acceptable manufacturers:1. United McGill2. MKT Metal Manufacturing3. Approved equivalent

C. Transverse Joints: Select joint types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-1, "Round Duct Transverse Joints," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

1. Transverse Joints in Ducts Larger Than 60 Inches in Diameter: Flanged.

D. Longitudinal Seams: Select seam types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-2, "Round Duct Longitudinal Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

1. Fabricate round ducts larger than 90 inches in diameter with butt-welded longitudinal seams.2. Fabricate flat-oval ducts larger than 72 inches in width (major dimension) with butt-welded

longitudinal seams.

E. Tees and Laterals: Select types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-5, "90 Degree Tees and Laterals," and Figure 3-6, "Conical Tees," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

2.5 DOUBLE-WALL ROUND DUCTS AND FITTINGS

A. Acceptable manufacturers:1. United McGill2. MKT Metal Manufacturing3. Approved equivalent

B. Indicated dimensions are the duct diameter of the inner duct.

1. Outer Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Ch. 3, "Round, Oval, and Flexible Duct," based on static-pressure class unless otherwise indicated.

Page 167: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 5

a. Construct ducts of galvanized sheet steel unless otherwise indicated.b. For ducts exposed to weather, construct outer duct of Type 304 stainless steel indicated by

manufacturer to be suitable for outdoor installation.

2. Transverse Joints: Select joint types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-1, "Round Duct Transverse Joints," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

a. Transverse Joints in Ducts Larger Than 60 Inches in Diameter: Flanged.

3. Longitudinal Seams: Select seam types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-2, "Round Duct Longitudinal Seams," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

a. Fabricate round ducts larger than 90 inches in diameter with butt-welded longitudinal seams.

b. Fabricate flat-oval ducts larger than 72 inches in width (major dimension) with butt-welded longitudinal seams.

4. Tees and Laterals: Select types and fabricate in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-5, "90 Degree Tees and Laterals," and Figure 3-6, "Conical Tees," for static-pressure class, applicable sealing requirements, materials involved, duct-support intervals, and other provisions in SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

C. Inner Duct: Minimum 24-gauge perforated galvanized sheet steel having 3/32-inch diameter perforations, with overall open area of 23 percent.

D. Interstitial Insulation: Fibrous-glass liner complying with ASTM C1071, NFPA 90A, or NFPA 90B; and with NAIMA AH124, "Fibrous Glass Duct Liner Standard."

1. Maximum Thermal Conductivity: 0.27 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature.2. Install spacers that position the inner duct at uniform distance from outer duct without compressing

insulation.3. Coat insulation with antimicrobial coating.4. Cover insulation with polyester film complying with UL 181, Class 1.

E. Interstitial Insulation: Flexible elastomeric duct liner complying with ASTM C534/C534M, Type II for sheet materials, and with NFPA 90A or NFPA 90B.

1. Maximum Thermal Conductivity: 0.25 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature.

2.6 SHEET METAL MATERIALS

A. General Material Requirements: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for acceptable materials, material thicknesses, and duct construction methods unless otherwise indicated. Sheet metal materials shall be free of pitting, seam marks, roller marks, stains, discolorations, and other imperfections.

B. Galvanized Sheet Steel: Comply with ASTM A653/A653M.

1. Galvanized Coating Designation: G60.2. Finishes for Surfaces Exposed to View: Mill phosphatized.

C. PVC-Coated, Galvanized Sheet Steel: Comply with ASTM A653/A653M.

Page 168: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 6

1. Galvanized Coating Designation: G60.2. Coating Materials: Acceptable to authorities having jurisdiction for use on ducts listed and labeled

by an NRTL for compliance with UL 181, Class 1.

D. Stainless-Steel Sheets: Comply with ASTM A480/A480M, Type 304, as indicated in "Duct Schedule" Article; cold rolled, annealed, sheet. Exposed surface finish shall be No. 2B, No. 2D, No. 3, or No. 4 as indicated in "Duct Schedule" Article.

E. Aluminum Sheets: Comply with ASTM B209 Alloy 3003, H14 temper; with mill finish for concealed ducts, and standard, one-side bright finish for duct surfaces exposed to view.

F. Factory- or Shop-Applied Antimicrobial Coating:

1. Apply to the surface of sheet metal that will form the interior surface of the duct. An untreated clear coating shall be applied to the exterior surface.

2. Antimicrobial compound shall be tested for efficacy by an NRTL and registered by the EPA for use in HVAC systems.

3. Coating containing the antimicrobial compound shall have a hardness of 2H, minimum, when tested in accordance with ASTM D3363.

4. Surface-Burning Characteristics: Maximum flame-spread index of 25 and maximum smoke-developed index of 50 when tested in accordance with UL 723; certified by an NRTL.

5. Shop-Applied Coating Color: White.6. Antimicrobial coating on sheet metal is not required for duct containing liner treated with

antimicrobial coating.

G. Reinforcement Shapes and Plates: ASTM A36/A36M, steel plates, shapes, and bars; black and galvanized.

1. Where black- and galvanized-steel shapes and plates are used to reinforce aluminum ducts, isolate the different metals with butyl rubber, neoprene, or EPDM gasket materials.

H. Tie Rods: Galvanized steel, 1/4-inch minimum diameter for lengths 36 inches or less; 3/8-inch minimum diameter for lengths longer than 36 inches.

2.7 DUCT LINER

A. Acceptable manufacturers:1. Knauf2. Owens-Corning3. Approved equivalent4. Maximum Thermal Conductivity:

B. Fibrous-Glass Duct Liner: Comply with ASTM C1071, NFPA 90A, or NFPA 90B; and with NAIMA AH124, "Fibrous Glass Duct Liner Standard."

a. Type I, Flexible: 0.27 Btu x in./h x sq. ft. x deg F mean temperature.b. Type II, Rigid: 0.23 Btu x in./h x sq. ft. x deg F mean temperature.

2. Antimicrobial Erosion-Resistant Coating: Apply to the surface of the liner that will form the interior surface of the duct to act as a moisture repellent and erosion-resistant coating. Antimicrobial compound shall be tested for efficacy by an NRTL and registered by the EPA for use in HVAC systems.

3. Solvent-Based Liner Adhesive: Comply with NFPA 90A or NFPA 90B and with ASTM C916.

a. Adhesive shall have a VOC content of 80 g/L or less.b. Adhesive shall comply with the testing and product requirements of the California

Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

Page 169: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 7

C. Flexible Elastomeric Duct Liner: Preformed, cellular, closed-cell, sheet materials complying with ASTM C534/C534M, Type II, Grade 1; and with NFPA 90A or NFPA 90B.

D. Acceptable manufacturers:1. Armacell2. Ductmate3. Approved equivalent

4. Surface-Burning Characteristics: Maximum flame-spread index of 25 and maximum smoke-developed index of 50 when tested in accordance with UL 723; certified by an NRTL.

5. Liner Adhesive: As recommended by insulation manufacturer and complying with NFPA 90A or NFPA 90B.

a. Adhesive shall have a VOC content of 80 g/L or less.b. Adhesive shall comply with the testing and product requirements of the California

Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

E. Fiberglass-Free Duct Liner: Made from partially recycled cotton or polyester products and containing no fiberglass. Airstream surface overlaid with fire-resistant facing to prevent surface erosion by airstream, complying with NFPA 90A or NFPA 90B. Treat natural-fiber products with antimicrobial coating.

F. Acceptable manufacturers:1. United McGill2. MKT Metal Manufacturing3. Approved equivalent4. Maximum Thermal Conductivity: 0.24 Btu x in./h x sq. ft. x deg F at 75 deg F mean temperature

when tested in accordance with ASTM C518.5. Surface-Burning Characteristics: Maximum flame-spread index of 25 and maximum smoke-

developed index of 50 when tested in accordance with ASTM E84; certified by an NRTL.6. Liner Adhesive: As recommended by insulation manufacturer and complying with NFPA 90A or

NFPA 90B.

a. Adhesive shall have a VOC content of 80 g/L or less.b. Adhesive shall comply with the testing and product requirements of the California

Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

G. Insulation Pins and Washers:

1. Cupped-Head, Capacitor-Discharge-Weld Pins: Copper- or zinc-coated steel pin, fully annealed for capacitor-discharge welding, 0.135-inch diameter shank, length to suit depth of insulation indicated with integral 1-1/2-inch galvanized carbon-steel washer.

2. Insulation-Retaining Washers: Self-locking washers formed from 0.016-inch thick galvanized steel with beveled edge sized as required to hold insulation securely in place, but not less than 1-1/2 inches in diameter.

H. Shop Application of Duct Liner: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 7-11, "Flexible Duct Liner Installation."

1. Adhere a single layer of indicated thickness of duct liner with at least 90 percent adhesive coverage at liner contact surface area. Attaining indicated thickness with multiple layers of duct liner is prohibited.

2. Apply adhesive to transverse edges of liner facing upstream that do not receive metal nosing.3. Butt transverse joints without gaps, and coat joint with adhesive.4. Fold and compress liner in corners of rectangular ducts or cut and fit to ensure butted-edge

overlapping.5. Do not apply liner in rectangular ducts with longitudinal joints, except at corners of ducts, unless

duct size and dimensions of standard liner make longitudinal joints necessary.

Page 170: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 8

6. Apply adhesive coating on longitudinal seams in ducts with air velocity of 2500 fpm or greater.7. Secure liner with mechanical fasteners 4 inches from corners and at intervals not exceeding 12

inches transversely; at 3 inches from transverse joints and at intervals not exceeding 18 inches longitudinally.

8. Secure transversely oriented liner edges facing the airstream with metal nosings that have either channel or "Z" profiles or are integrally formed from duct wall. Fabricate edge facings at the following locations:

a. Fan discharges.b. Intervals of lined duct preceding unlined duct.c. Upstream edges of transverse joints in ducts where air velocities are higher than 2500 fpm

or where indicated.

9. Secure insulation between perforated sheet metal inner duct of same thickness as specified for outer shell. Use mechanical fasteners that maintain inner duct at uniform distance from outer shell without compressing insulation.

a. Sheet Metal Inner Duct Perforations: 3/32-inch diameter, with an overall open area of 23 percent.

10. Terminate inner ducts with buildouts attached to fire-damper sleeves, dampers, turning vane assemblies, or other devices. Fabricated buildouts (metal hat sections) or other buildout means are optional; when used, secure buildouts to duct walls with bolts, screws, rivets, or welds.

2.8 SEALANT AND GASKETS

A. General Sealant and Gasket Requirements: Surface-burning characteristics for sealants and gaskets shall be a maximum flame-spread index of 25 and a maximum smoke-developed index of 50 when tested in accordance with UL 723; certified by an NRTL.

B. Two-Part Tape Sealing System:

1. Tape: Woven cotton fiber impregnated with mineral gypsum and modified acrylic/silicone activator to react exothermically with tape to form hard, durable, airtight seal.

2. Tape Width: 4 inches.3. Sealant: Modified styrene acrylic.4. Water resistant.5. Mold and mildew resistant.6. Maximum Static-Pressure Class: 10 inch wg, positive and negative.7. Service: Indoor and outdoor.8. Service Temperature: Minus 40 to plus 200 deg F .9. Substrate: Compatible with galvanized sheet steel (both PVC coated and bare), stainless steel, or

aluminum.10. Sealant shall have a VOC content of 420 g/L or less.11. Sealant shall comply with the testing and product requirements of the California Department of

Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

C. Water-Based Joint and Seam Sealant:

1. Application Method: Brush on.2. Solids Content: Minimum 65 percent.3. Shore A Hardness: Minimum 20.4. Water resistant.5. Mold and mildew resistant.6. VOC: Maximum 75 g/L (less water).7. Maximum Static-Pressure Class: 10 inch wg , positive and negative.8. Service: Indoor or outdoor.

Page 171: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 9

9. Substrate: Compatible with galvanized sheet steel (both PVC coated and bare), stainless steel, or aluminum sheets.

D. Solvent-Based Joint and Seam Sealant:

1. Application Method: Brush on.2. Base: Synthetic rubber resin.3. Solvent: Toluene and heptane.4. Solids Content: Minimum 60 percent.5. Shore A Hardness: Minimum 60.6. Water resistant.7. Mold and mildew resistant.8. Sealant shall have a VOC content of 420 g/L or less.9. Sealant shall comply with the testing and product requirements of the California Department of

Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

10. Maximum Static-Pressure Class: 10-inch wg, positive or negative.11. Service: Indoor or outdoor.12. Substrate: Compatible with galvanized sheet steel (both PVC coated and bare), stainless steel, or

aluminum sheets.

E. Flanged Joint Sealant: Comply with ASTM C920.

1. General: Single-component, acid-curing, silicone, elastomeric.2. Type: S.3. Grade: NS.4. Class: 25.5. Use: O.6. Sealant shall have a VOC content of 420 g/L or less.7. Sealant shall comply with the testing and product requirements of the California Department of

Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

F. Flange Gaskets: Butyl rubber, neoprene, or EPDM polymer with polyisobutylene plasticizer.

G. Round Duct Joint O-Ring Seals:

1. Seal shall provide maximum leakage class of 3 cfm/100 sq. ft. at 1-inch wg and shall be rated for10-inch wg static-pressure class, positive or negative.

2. EPDM O-ring to seal in concave bead in coupling or fitting spigot.3. Double-lipped, EPDM O-ring seal, mechanically fastened to factory-fabricated couplings and fitting

spigots.

2.9 HANGERS AND SUPPORTS

A. Hanger Rods for Noncorrosive Environments: Galvanized-steel rods and nuts.

B. Hanger Rods for Corrosive Environments: Electrogalvanized, all-thread rods or galvanized rods with threads painted with zinc-chromate primer after installation.

C. Strap and Rod Sizes: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Table 5-1 "Rectangular Duct Hangers Minimum Size," and Table 5-2, "Minimum Hanger Sizes for Round Duct."

D. Steel Cables for Galvanized-Steel Ducts: Galvanized steel complying with ASTM A603.

E. Steel Cables for Stainless-Steel Ducts: Stainless steel complying with ASTM A492.

Page 172: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 10

F. Steel Cable End Connections: Galvanized-steel assemblies with brackets, swivel, and bolts designed for duct hanger service; with an automatic-locking and clamping device.

G. Duct Attachments: Sheet metal screws, blind rivets, or self-tapping metal screws; compatible with duct materials.

H. Trapeze and Riser Supports:

1. Supports for Galvanized-Steel Ducts: Galvanized-steel shapes and plates.2. Supports for Stainless-Steel Ducts: Stainless-steel shapes and plates.3. Supports for Aluminum Ducts: Aluminum or galvanized steel coated with zinc chromate.

PART 3 - EXECUTION

3.1 DUCT INSTALLATION

A. Drawing plans, schematics, and diagrams indicate general location and arrangement of duct system. Indicated duct locations, configurations, and arrangements were used to size ducts and calculate friction loss for air-handling equipment sizing and for other design considerations. Install duct systems as indicated unless deviations to layout are approved on Shop Drawings and coordination drawings.

B. Install ducts in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" unless otherwise indicated.

C. Install ducts in maximum practical lengths with fewest possible joints.

D. Install factory- or shop-fabricated fittings for changes in direction, size, and shape and for branch connections.

E. Unless otherwise indicated, install ducts vertically and horizontally, and parallel and perpendicular to building lines.

F. Install ducts close to walls, overhead construction, columns, and other structural and permanent enclosure elements of building.

G. Install ducts with a clearance of 1 inch, plus allowance for insulation thickness.

H. Route ducts to avoid passing through transformer vaults and electrical equipment rooms and enclosures.

I. Where ducts pass through non-fire-rated interior partitions and exterior walls and are exposed to view, cover the opening between the partition and duct or duct insulation with sheet metal flanges of same metal thickness as the duct. Overlap openings on four sides by at least 1-1/2 inches.

J. Install heating coils, cooling coils, air filters, dampers, and all other duct-mounted accessories in air ducts where indicated on Drawings.

K. Protect duct interiors from moisture, construction debris and dust, and other foreign materials both before and after installation. Comply with SMACNA's "IAQ Guidelines for Occupied Buildings Under Construction," Appendix G, "Duct Cleanliness for New Construction Guidelines."

L. Elbows: Use long-radius elbows wherever they fit.

1. Fabricate 90-degree rectangular mitered elbows to include turning vanes.2. Fabricate 90-degree round elbows with a minimum of three segments for 12 inches and smaller

and a minimum of five segments for 14 inches and larger.

M. Branch Connections: Use lateral or conical branch connections.

Page 173: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 11

3.2 INSTALLATION OF EXPOSED DUCTWORK

A. Protect ducts exposed in finished spaces from being dented, scratched, or damaged.

B. Trim duct sealants flush with metal. Create a smooth and uniform exposed bead. Do not use two-part tape sealing system.

C. Grind welds to provide smooth surface free of burrs, sharp edges, and weld splatter. When welding stainless steel with a No. 3 or 4 finish, grind the welds flush, polish the exposed welds, and treat the welds to remove discoloration caused by welding.

D. Maintain consistency, symmetry, and uniformity in arrangement and fabrication of fittings, hangers and supports, duct accessories, and air outlets.

E. Repair or replace damaged sections and finished work that does not comply with these requirements.

3.3 DUCTWORK EXPOSED TO WEATHER

A. All external joints are to have secure watertight mechanical connections. Seal all openings to provide weatherproof construction.

B. Construct ductwork to resist external loads of wind, snow, ice, and other effects of weather. Provide necessary supporting structures.

C. Single Wall:

1. Ductwork shall be Type 304 stainless steel.2. Ductwork shall be galvanized steel.

a. If duct outer surface is uninsulated, protect outer surface with suitable paint.

3. Where ducts have external insulation, provide weatherproof aluminum jacket. See Section 230713 "Duct Insulation."

D. Double Wall:

1. Ductwork shall comply with requirements in "Double-Wall Rectangular Ducts and Fittings" or "Double-Wall Round Ducts and Fittings" Article.

2. Ductwork outer wall shall be Type 304 stainless steel indicated by manufacturer to be suitable for outdoor installation.

3. Provide interstitial insulation.

3.4 DUCT SEALING

A. Seal ducts for duct static-pressure, seal classes, and leakage classes specified in "Duct Schedule" Article in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."

B. Seal ducts at a minimum to the following seal classes in accordance with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible":

1. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible."2. Outdoor, Supply-Air Ducts: Seal Class A.3. Outdoor, Exhaust Ducts: Seal Class C.4. Outdoor, Return-Air Ducts: Seal Class C.5. Unconditioned Space, Supply-Air Ducts in Pressure Classes 2-Inch wg and Lower: Seal Class B.6. Unconditioned Space, Supply-Air Ducts in Pressure Classes Higher Than 2-Inch wg: Seal Class A.7. Unconditioned Space, Exhaust Ducts: Seal Class C.

Page 174: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 12

8. Unconditioned Space, Return-Air Ducts: Seal Class B.9. Conditioned Space, Supply-Air Ducts in Pressure Classes 2-Inch wg and Lower: Seal Class C.10. Conditioned Space, Supply-Air Ducts in Pressure Classes Higher Than 2-Inch wg: Seal Class B.11. Conditioned Space, Exhaust Ducts: Seal Class B.12. Conditioned Space, Return-Air Ducts: Seal Class C.

3.5 HANGER AND SUPPORT INSTALLATION

A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Chapter 5, "Hangers and Supports."

B. Building Attachments: Concrete inserts, powder-actuated fasteners, or structural-steel fasteners appropriate for construction materials to which hangers are being attached.1. Install powder-actuated concrete fasteners after concrete is placed and completely cured.2. Use powder-actuated concrete fasteners for standard-weight aggregate concretes or for slabs

more than 4 inches thick.3. Do not use powder-actuated concrete fasteners for lightweight-aggregate concretes or for slabs

less than 4 inches thick.4. Do not use powder-actuated concrete fasteners for seismic restraints.

C. Hanger Spacing: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Table 5-1, "Rectangular Duct Hangers Minimum Size," and Table 5-2, "Minimum Hanger Sizes for Round Duct," for maximum hanger spacing; install hangers and supports within 24 inches of each elbow and within 48 inches of each branch intersection.

D. Hangers Exposed to View: Threaded rod and angle or channel supports.

E. Support vertical ducts with steel angles or channel secured to the sides of the duct with welds, bolts, sheet metal screws, or blind rivets; support at each floor and at a maximum intervals of 16 feet.

F. Install upper attachments to structures. Select and size upper attachments with pull-out, tension, and shear capacities appropriate for supported loads and building materials where used.

3.6 CONNECTIONS

A. Make connections to equipment with flexible connectors complying with Section 233300 "Air Duct Accessories."

B. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible" for branch, outlet and inlet, and terminal unit connections.

3.7 FIELD QUALITY CONTROL

A. Perform tests and inspections.

1. Disassemble, reassemble, and seal segments of systems to accommodate leakage testing and for compliance with test requirements.

2. Testing of each duct section is to be performed with access doors, coils, filters, dampers, and other duct-mounted devices in place as designed. No devices are to be removed or blanked off so as to reduce or prevent additional leakage.

3. Test for leaks before applying external insulation.4. Conduct tests at static pressures equal to maximum design pressure of system or section being

tested. If static-pressure classes are not indicated, test system at maximum system design pressure. Do not pressurize systems above maximum design operating pressure.

5. Give seven days' advance notice for testing.

Page 175: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 13

B. Duct System Cleanliness Tests:

1. Visually inspect duct system to ensure that no visible contaminants are present.2. Test sections of metal duct system, chosen randomly by Owner, for cleanliness in accordance with

"Description of Method 3 - NADCA Vacuum Test" in NADCA ACR, "Assessment, Cleaning and Restoration of HVAC Systems."

a. Acceptable Cleanliness Level: Net weight of debris collected on the filter media shall not exceed 0.75 mg/100 sq. cm.

C. Duct system will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

3.8 DUCT CLEANING

A. Clean new duct system(s) before testing, adjusting, and balancing.

B. For cleaning of existing ductwork, see Section 230130.52 "Existing HVAC Air Distribution System Cleaning."

C. Use duct cleaning methodology as indicated in NADCA ACR.

D. Use service openings for entry and inspection.

1. Provide openings with access panels appropriate for duct static-pressure and leakage class at dampers, coils, and any other locations where required for inspection and cleaning access. Provide insulated panels for insulated or lined duct. Patch insulation and liner as recommended by duct liner manufacturer. Comply with Section 233300 "Air Duct Accessories" for access panels and doors.

2. Disconnect and reconnect flexible ducts as needed for cleaning and inspection.3. Remove and reinstall ceiling to gain access during the cleaning process.

E. Particulate Collection and Odor Control:

1. When venting vacuuming system inside the building, use HEPA filtration with 99.97 percent collection efficiency for 0.3-micron-size (or larger) particles.

2. When venting vacuuming system to outdoors, use filter to collect debris removed from HVAC system, and locate exhaust downwind and away from air intakes and other points of entry into building.

F. Clean the following components by removing surface contaminants and deposits:

1. Air outlets and inlets (registers, grilles, and diffusers).2. Supply, return, and exhaust fans including fan housings, plenums (except ceiling supply and return

plenums), scrolls, blades or vanes, shafts, baffles, dampers, and drive assemblies.3. Air-handling unit internal surfaces and components including mixing box, coil section, air wash

systems, spray eliminators, condensate drain pans, humidifiers and dehumidifiers, filters and filter sections, and condensate collectors and drains.

4. Coils and related components.5. Return-air ducts, dampers, actuators, and turning vanes except in ceiling plenums and mechanical

equipment rooms.6. Supply-air ducts, dampers, actuators, and turning vanes.7. Dedicated exhaust and ventilation components and makeup air systems.

G. Mechanical Cleaning Methodology:

Page 176: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 14

1. Clean metal duct systems using mechanical cleaning methods that extract contaminants from within duct systems and remove contaminants from building.

2. Use vacuum-collection devices that are operated continuously during cleaning. Connect vacuum device to downstream end of duct sections so areas being cleaned are under negative pressure.

3. Use mechanical agitation to dislodge debris adhered to interior duct surfaces without damaging integrity of metal ducts, duct liner, or duct accessories.

4. Clean fibrous-glass duct liner with HEPA vacuuming equipment; do not permit duct liner to get wet. Replace fibrous-glass duct liner that is damaged, deteriorated, or delaminated or that has friable material, mold, or fungus growth.

5. Clean coils and coil drain pans in accordance with NADCA ACR. Keep drain pan operational. Rinse coils with clean water to remove latent residues and cleaning materials; comb and straighten fins.

6. Provide drainage and cleanup for wash-down procedures.7. Antimicrobial Agents and Coatings: Apply EPA-registered antimicrobial agents if fungus is present.

Apply antimicrobial agents in accordance with manufacturer's written instructions after removal of surface deposits and debris.

3.9 STARTUP

A. Air Balance: Comply with requirements in Section 230593 "Testing, Adjusting, and Balancing for HVAC."

3.10 DUCT SCHEDULE

A. Fabricate ducts with galvanized sheet steel except as otherwise indicated and as follows:

1. Fabricate all ducts to achieve SMACNA pressure class, seal class, and leakage class as indicated below.

B. Supply Ducts:

1. Ducts Connected to Constant-Volume Air-Handling Units:

a. Pressure Class: Positive 3 inch wg.b. Minimum SMACNA Seal Class: B.c. SMACNA Leakage Class for Rectangular: 12.d. SMACNA Leakage Class for Round: 12.

2. Ducts Connected to Variable-Air-Volume Air-Handling Units:

a. Pressure Class: Positive 4 inch wg.b. Minimum SMACNA Seal Class: A.c. SMACNA Leakage Class for Rectangular: 6.d. SMACNA Leakage Class for Round: 6.

3. Ducts Connected to Equipment Not Listed Above:

a. Pressure Class: Positive 3 inch wg .b. Minimum SMACNA Seal Class: B.c. SMACNA Leakage Class for Rectangular: 12.d. SMACNA Leakage Class for Round: 12.

C. Return Ducts:

1. Ducts Connected to Fan Coil Units, Furnaces, Heat Pumps, and Terminal Units:

a. Pressure Class: Positive or negative 2 inch wg.b. Minimum SMACNA Seal Class: A.c. SMACNA Leakage Class for Rectangular: 16.

Page 177: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 15

d. SMACNA Leakage Class for Roundl: 16.

2. Ducts Connected to Air-Handling Units:

a. Pressure Class: Positive or negative 4 inch wg.b. Minimum SMACNA Seal Class: B.c. SMACNA Leakage Class for Rectangular: 12.d. SMACNA Leakage Class for Round: 12.

3. Ducts Connected to Equipment Not Listed above:

a. Pressure Class: Positive or negative 3 inch wg.b. Minimum SMACNA Seal Class: A.c. SMACNA Leakage Class for Rectangular: 6.d. SMACNA Leakage Class for Round: 6.

D. Double-Wall Duct Interstitial Insulation:

1. Supply-Air Ducts: 1-1/2 inches thick.2. Return-Air Ducts: 1-1/2 inches thick.

E. Elbow Configuration:

1. Rectangular Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 4-2, "Rectangular Elbows."

a. Velocity 1000 fpm or Lower:

1) Radius Type RE 1 with minimum 0.5 radius-to-diameter ratio.2) Mitered Type RE 4 without vanes.

b. Velocity 1000 to 1500 fpm:

1) Radius Type RE 1 with minimum 1.0 radius-to-diameter ratio.2) Radius Type RE 3 with minimum 0.5 radius-to-diameter ratio and two vanes.3) Mitered Type RE 2 with vanes complying with SMACNA's "HVAC Duct Construction

Standards - Metal and Flexible," Figure 4-3, "Vanes and Vane Runners," and Figure 4-4, "Vane Support in Elbows."

c. Velocity 1500 fpm or Higher:

1) Radius Type RE 1 with minimum 1.5 radius-to-diameter ratio.2) Radius Type RE 3 with minimum 1.0 radius-to-diameter ratio and two vanes.3) Mitered Type RE 2 with vanes complying with SMACNA's "HVAC Duct Construction

Standards - Metal and Flexible," Figure 4-3, "Vanes and Vane Runners," and Figure 4-4, "Vane Support in Elbows."

2. Rectangular Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 4-2, "Rectangular Elbows."

a. Radius Type RE 1 with minimum 1.5 radius-to-diameter ratio.b. Radius Type RE 3 with minimum 1.0 radius-to-diameter ratio and two vanes.c. Mitered Type RE 2 with vanes complying with SMACNA's "HVAC Duct Construction

Standards - Metal and Flexible," Figure 4-3, "Vanes and Vane Runners," and Figure 4-4, "Vane Support in Elbows."

3. Round Duct: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Figure 3-4, "Round Duct Elbows."

Page 178: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

METAL DUCTS233113 - 16

a. Minimum Radius-to-Diameter Ratio and Elbow Segments: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Table 3-1, "Mitered Elbows." Elbows with less than 90-degree change of direction have proportionately fewer segments.

1) Velocity 1000 fpm or Lower: 0.5 radius-to-diameter ratio and three segments for 90-degree elbow.

2) Velocity 1000 to 1500 fpm: 1.0 radius-to-diameter ratio and four segments for 90-degree elbow.

3) Velocity 1500 fpm or Higher: 1.5 radius-to-diameter ratio and five segments for 90-degree elbow.

4) Radius-to Diameter Ratio: 1.5.

b. Round Elbows, 12 Inches and Smaller in Diameter: Stamped or pleated.c. Round Elbows, 14 Inches and Larger in Diameter: Standing seam or welded.

END OF SECTION 233113

Page 179: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

ROTARY SCREW WATER CHILLERSSection 23 64 26-1

SECTION 23 64 26ROTARY-SCREW WATER CHILLERS

PART 1 - GENERAL

1.01 SCOPE

THIS SPECIFICATION IS PROVIDED FOR INFORMATIONAL PURPOSES ONLY. OWNER IS TO PROVIDE THIS EQUIPMENT AND CONTOR IS TO INSTALL.

Provide microprocessor controlled, twin-screw compressor, water-cooled, liquid chillers of the scheduled capacities as shown and indicated on the drawings, including but not limited to:

A. Chiller package

B. Charge of refrigerant and oil

C. Electrical power and control connections

D. Chilled liquid connections

E. Condenser liquid connections

F. Manufacturer start-up

1.02 QUALITY ASSURANCE

A. The unit shall be rated specifically for the unique requirements for chilling and maintaining proper ice slab conditions for ice arenas.

B. Products must be designed, tested, rated and certified in accordance with, and in- stalled in compliance with applicable sections of the following standards and codes:

1. AHRI 550/590 – Water Chilling Packages Using the Vapor Compression Cycle

2. GB/T 18430.1 – water chilling (heat pump) packages using the vapor compression cycle - Part 1: Water chilling (heat pump) packages for industrial, commercial and similar application

3. AHRI 575 – Method of Measuring Machinery Sound Within an Equipment Space

4. ANSI/ASHRAE 15 – Safety Code for Mechanical Refrigeration

5. ANSI/ASHRAE 34 – Number Designation and Safety Classification of Refrigerants

6. ASHRAE 90.1 – Energy Standard for Buildings Except Low-Rise Residential Build ings

7. ANSI/NFPA 70 – National Electrical Code (NEC)

8. GB150/151 – Steel Pressure Vessels/Tubular Heat Exchangers

9. Conform to Intertek Testing Services for construction of chillers and provide ETL/ cETL Listed Mark

C. Factory Run Test: Chiller must be pressure-tested, evacuated and fully charged with refrigerant and oil, and must be factory operational run tested with water flowing through the vessel.

D. Chiller manufacturer must have a factory trained and supported service organization.

E. Warranty: Manufacturer must warrant all equipment and material of its manufacture against defects in workmanship and material. The warranty is for a period of 18 months from date of shipment or 12 months

Page 180: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0120-155; 555085

ROTARY SCREW WATER CHILLERSSection 23 64 26-2

from date of start-up, whichever occurs first. Compressor warranty shall be five (5) years parts and shall include replacement labor.

1.03 DELIVERY AND HANDLING

A. Unit must be delivered to job site fully assembled with all interconnecting refrigerant piping and internal wiring ready for field installation. Unit must be charged with refriger- ant and oil by the manufacturer.

B. Provide protective covering over vulnerable components for unit protection during shipment. Fit nozzles and open ends with cloth enclosures.

C. Unit must be stored and handled per manufacturer’s instructions.

PART 2 - PRODUCTS

2.01 GENERAL

A. Description: Furnish factory assembled, charged, and operational run tested water-cooled screw compressor chiller as specified herein and shown on the drawings. Chiller must include, but is not limited to: semi hermetic twin screw compressors, shell and tube hybrid falling film type evaporator, flooded condenser, HFC-134a refrigerant, lubrication system, interconnecting wiring, safety and operating controls including capacity controller, control center, motor starting components, and special features as specified herein or required for safe, automatic operation.

B. Operating Characteristics:

1. Chiller is installed in an indoor location and must be capable of operating in room temperatures between 40°F and 110°F (4.4°C and 43.3°C).

2. Provide capacity control system capable of reducing unit capacity to 20% of full load. Compressor must start in unloaded condition. Application of factory installed hot gas bypass must be acceptable as required to meet specified minimum load.

3. Chiller must be completely factory-packaged including evaporator, condenser, compressor, motor, control center and all interconnecting unit piping and wiring. The complete chiller assembly must be painted to meet 500 hour salt spray test in accordance with the ASTM B117 standard.

4. Shipping: Unit must ship in one piece and requires the installer to provide the evaporator and condenser inlet and outlet pipe connections. If providing chiller model that ships in multiple pieces, bid must include all the material and field labor costs for factory authorized personnel to connect the pieces, all interconnecting piping, and wiring.

2.02 COMPRESSOR(S)

A. Compressor(s): Must be direct drive, semi hermetic, rotary twin-screw type, including: terminal box, and precision machined cast iron housing. Design working pressure of entire compressor, suction to discharge, must be 450 psig (31 barg) or higher. Com- pressor must be U.L. recognized.

B. Compressor Motors: Refrigerant suction-gas cooled accessible hermetic compres- sor motor, full suction gas flow through 80 mesh screen, with inherent internal thermal protection and external current overload on all three phases.

C. Balancing Requirements: All rotating parts must be statically balanced.

D. Lubrication System: External oil separators with no moving parts. GB listing must be provided on the chiller. Refrigerant system differ-ential pressure must provide oil flow through service replaceable, 0.5 micron, full flow, cartridge type oil filter. Filter bypass, less restrictive media, or oil pump not acceptable.

E. Capacity Control: Compressors must start at minimum load. Provide microprocessor control to command compressor capacity to balance compressor capacity with cooling load.

Page 181: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

ROTARY SCREW WATER CHILLERSSection 23 64 26-3

2.03 REFRIGERANT CIRCUIT COMPONENTS

A. Refrigerant: HFC-134a. Classified as Safety Group A1 according to ASHRAE 34.

B. Each refrigerant circuit must incorporate an electronic expansion valve controlled by the control center to meter refrigerant flow to the evaporator to accommodate varying head and load conditions.

C. Equipment supplied must comply with LEED Energy & Atmosphere Credit 4, Enhanced Refrigerant Management.

D. Each refrigerant circuit must incorporate all components necessary for the designed operation. Refrigerant isolation valves must be provided to isolate the referent into the condenser for standard water chilling application.

2.04 HEAT EXCHANGERS

A. Evaporator:

1. Evaporator must be shell and tube, hybrid falling film type with at least 2 pass arrangement to optimize efficiency and refrigerant charge. Tubes are copper alloy high-efficiency, and are both externally and internally enhanced to provide optimum performance. The “skip-fin” tube design provides a smooth internal and external surface at each intermediate tube support. It provides extra wall thickness (up to twice as thick) and non work-hardened copper at the support location, which extends the life of the heat exchangers. Each tube is expanded into the tube sheets providing a leak-proof seal, and is individually replaceable.

2. Constructed and tested in accordance with applicable sections of GB pressure vessel code.

3. Waterboxes must be removable to permit tube cleaning and replacement. Liquid nozzle connections must be 300 psig (20.6 barg HG raised-face welded flanges. Companion flanges, bolts, nuts, and gaskets are not included. Flanges are field-welded by contractor.

B. Condenser:

1. Condenser must be shell and tube type, with a discharge gas baffle to prevent direct high velocity impingement on the tubes and to distribute the refrigerant gas flow evenly over the tubes. An integral sub-cooler must be located at the bottom of the condenser shell providing highly effective liquid refrigerant subcooling and highest cycle efficiency. Tubes are copper alloy high-efficiency, and are both externally and internally enhanced to provide optimum performance.

2. Constructed and tested in accordance with applicable sections of GB pressure ves- sel code for minimum 235 psig (16.2 barg) refrigerant side design working pressure and 150 psig (10 barg) liquid side design working pressure.

3. Waterboxes must be removable to permit tube cleaning and replacement. Liquid nozzle connections must be HG raised-face welded flanges. Companion flanges, bolts, nuts, and gaskets are not included.

2.05 INSULATION

A. Material: Closed-cell, flexible, UV protected, thermal insulation complying with ASTM C 534 Type 2 (Sheet) for preformed flexible elastomeric cellular thermal insulation in sheet and tubular form.

B. Thickness: 1 1/2 in. (38 mm)

C. Thermal conductivity: 0.26 (BTU/HR-Ft2-°F/in) maximum at 75°F mean temperature.

D. Factory-applied insulation over cold surfaces of liquid chiller components including evaporator shell, suction line, liquid nozzles and waterbox.

Page 182: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0120-155; 555085

ROTARY SCREW WATER CHILLERSSection 23 64 26-4

E. Adhesive: As recommended by insulation manufacturer and applied to 100 percent of insulation contact surface including all seams and joints.

2.06 ACOUSTICAL DATA

A. Provide unweighted sound power or sound pressure level data in decibels (dB) at the scheduled 8 octave band center frequencies. A-weighted sound data alone is not ac- ceptable.

B. Provide all sound power or sound pressure level data at 100%, 75%, 50%, and 25% load.

C. Supplied equipment must not exceed scheduled sound power or sound pressure level data at any load point. The mechanical contractor must be responsible for any addi- tional costs associated with equipment deviation.

D. Acoustical performance must be evaluated in accordance with AHRI Standard - 575 test data.

2.07 POWER AND ELECTRICAL REQUIREMENTS

A. Power/Control Panel:

1. Factory installed and wired NEMA 1, powder painted steel cabinets with tool lockable, hinged, latched, and gasket sealed outer doors equipped with door latch. Pro- vide main power connection(s), compressor starters, current overloads, and factory wiring.

B. Single Point Power:

1. Provide single point power connection to chiller, must be 3 phase of scheduled voltage.

2. Single Point Circuit Breaker: A unit-mounted circuit breaker with external lockable handle must be supplied to isolate power voltage for servicing. Incoming power wir- ing must comply with local codes. Circuit breaker must be sized to provide chiller equipment with the branch circuit protection, short circuit protection.

C. Control Transformer: Power panel must be supplied with a factory mounted and wired control transformer that supplies all unit control voltage from the main unit power supply. Transformer must utilize scheduled line voltage on the primary side and provide 115V/1Ø on secondary.

D. Motor Starters: Motor starters must be zero electrical inrush current (variable fre- quency drives) for minimum electrical inrush. Open transition Wye-Delta and Across the Line type starters are not acceptable.

1. Provide equipment with power factor correction capacitors as required to maintain a displacement power factor of 95% at all load conditions.

2. The installing contractor is responsible for additional cost to furnish and install pow- er factor correction capacitors if they are not factory mounted and wired.

E. All exposed power wiring must be routed through liquid-tight nonmetallic conduit.

F. Supplied equipment must not exceed scheduled minimum circuit ampacity (MCA). The mechanical contractor must be responsible for any additional costs associated with equipment deviation.

2.08 CONTROLS

A. General:

1. Provide automatic control of chiller operation including compressor start/stop and load/unload, anti-recycle timer, evaporator pump, condenser pump, unit alarm con- tacts and run signal contacts.

2. Chiller must automatically reset to normal chiller operation after power failure.

3. Unit operating software must be stored in nonvolatile memory. Field programmed set points must be retained in lithium battery backed regulated time clock (RTC) memory for minimum 5 years.

4. Alarm controls must be provided to remote alert for any unit or system safety fault.

Page 183: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

ROTARY SCREW WATER CHILLERSSection 23 64 26-5

B. Display and Keypad:

1. Provide minimum 80 character liquid crystal display that is both viewable in direct sunlight and has LED backlighting for nighttime viewing. Provide one keypad and display panel per chiller.

2. Display and keypad must be accessible without opening main control/electrical cabinet doors.

3. Display must provide a minimum of unit set points, status, electrical data, tempera- ture data, pressures, safety lockouts, and diagnostics without the use of a coded display.

4. Descriptions in English (or available language options), numeric data in English (or Metric) units.

5. Sealed keypad must include unit On/Off switch.

C. Programmable Set Points (within manufacturer limits): Display language, chilled liq- uid cooling mode, local/remote control mode, display units mode, remote temperature reset, remote current limit, remote heat recovery kit, leaving chilled liquid set point and range, maximum remote temperature reset.

D. Display Data: Chilled liquid leaving and entering temperatures; flow switch status; evaporator/condenser pump status; active remote control; evaporator pressure, dis- charge, and oil pressures, condenser and economizer pressures per refrigerant circuit; economizer temperature and superheat; subcooler liquid temperature and superheat; compressor discharge temperature and superheat, motor; temperatures, eductor tem- perature, per refrigerant circuit; compressor speed, condenser level, condenser level control valve; economizer superheat; economizer feed valve percentage open; evapo- rator/condenser heater status; oil pump status; compressor number of starts; run time; operating hours; history data for last ten shutdown faults; history data for last 20 nor- mal (non-fault) shutdowns.

E. Predictive Control Points: Unit controls must avoid safety shutdown when operating outside design conditions by optimizing the chiller controls and cooling load output to stay online and avoid safety limits being reached. The system must monitor the follow- ing parameters and maintain the maximum cooling output possible without shutdown of the equipment: motor current, evaporator pressure, condenser pressure, discharge pressure, starter internal ambient temperature, and starter baseplate temperature.

F. System Safeties: Must cause individual compressor systems to perform auto-reset shutdown if: high discharge pressure or temperature, low evaporator pressure, low motor current, high/low differential oil pressure, low discharge and economizer super- heat, smart freeze point protection, high motor temperature, system control voltage, eductor clog.

G. Unit Safeties: Must be automatic reset and cause compressors to shut down if: low leaving chilled liquid temperature, under voltage, flow switch operation. Contractor must provide flow switch and wiring per chiller manufacturer requirements.

H. Manufacturer must provide any controls not listed above, necessary for automatic chiller operation. Mechanical contractor must provide field control wiring necessary to interface sensors to the chiller control system.

2.10 ACCESSORIES AND OPTIONS

Some accessories and options supersede standard product features. All options are fac- tory-mounted unless otherwise noted.

A. Controls Options:

1. Building Automation System Interface: Chiller to accept 4 mA to 20 mA or 0 VDC to 10 VDC input from BAS (by others) to reset the leaving chilled liquid temperature or load limit set point or both.

2. Gateway: Provides communication for BAS, including BACnet (MS/TP), Modbus, N2, and LON. (Field commissioned by BAS manufacturer)

3. Ice making: Provide special control logic and modifications to produce leaving chilled brine temperatures below 40°F (4.4°C.)

B. General Options:

Page 184: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0120-155; 555085

ROTARY SCREW WATER CHILLERSSection 23 64 26-6

1. Flow Switch: Vapor proof SPDT\ switch, 150 psig (10.3 barg), -20°F to 250°F (-28.9°C to 121.1°C.) (Field mounted by contractor.)

2. Differential Pressure Switch: 3 psig to 45 psig (0.2 barg to 3 barg) range with 1/4 in. NPTE pressure connections. (Field mounted by contractor.)

a. Materials Package includes steel mill material reports for vessels in addition to Pressure Vessel Report, Unit Run Test Report, Production System Check Sheet and Final Unit Inspection Check Sheet.

3. Vibration Isolation (All Options Field Mounted by Contractor):

a. Elastomeric isolators.

b. 1 in. deflection spring isolators: level adjustable, spring and cage type isolators for mounting under the unit base rails.

PART 3 - PERFORMANCE

3.1 UNIT PERFORMANCE

A. All information is given on a per unit basis.

B. All bid equipment to meet or exceed existing equipment performance.

C. Chiller Unit #1:1. Existing Chiller Unit to be replaced, Carrier Model 30HXC246R—630CA.

2. Refrigerant: R134a.

3. Evaporator brine solution: 21% Calcium Chloride.

4. Ice Loop Brine Flow Rate: 1200 gpm at 73 feet of head.

5. Ice Loop Discharge Temperature: 15°. Return Temperature 17°

6. Condenser water flow rate: 441 gpm at 5.9 feet of head.

7. Electrical: 460V, 3 phase, 60 Hz. MCA 303, MOCP 400, 350 A recommended fuse.

D. Chiller Unit #2:1. Existing Chiller Unit to be replaced, Carrier Model 30HXC206R—630CA.

2. Refrigerant: R134a.

3. Evaporator brine solution: 21% Calcium Chloride.

4. Ice Loop Brine Flow Rate: 1000 gpm at 84 feet of head.

5. Ice Loop Discharge Temperature: 15°. Return Temperature 17°

6. Condenser water flow rate: 403 gpm at 7.5 feet of head.

7. Electrical: 460V, 3 phase, 60 Hz. MCA 263, MOCP 350, 300 A recommended fuse.

END OF SECTION

Page 185: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COOLING TOWERS23 65 00-1

SECTION 23 65 00COOLING TOWERS

PART 1 - GENERAL

1.1 DESCRIPTION

A. THIS SPECIFICATION SECTION IS PROVIDED FOR INFORMATIONAL PURPOSES ONLY. OWNER TO

PROVIDE THIS EQUIPMENT AND CONTRACTOR IS TO INSTALL.

B. Packaged, factory assembled, open circuit, counter-flow, blow-through design cooling tower with single side

air entry. All steel construction shall be of G-235 hot-dip galvanized steel

1.2 QUALITY ASSURANCE

A. Performance Criteria:

1. Manufacturer shall certify that performance of cooling towers will meet specified requirements, stating

entering air wet bulb temperature, entering and leaving condenser water temperatures, water flow rates,

fan kW (horsepower). Certification shall be made at the time of submittal.

1.3 SUBMITTALS

A. Provide product data to include rated capacities, dimensions, weights and point loadings, accessories,

required clearances, electrical requirements and wiring diagrams, and location and size of field connections.

Submit schematics indicating capacity controls.

B. Shop Drawings

1. Sufficient information, clearly presented, shall be included to determine compliance with specifications.

2. Include rated capacities, pressure drop, fan performance and rating curves, dimensions, weights,

mounting details, front view, side view, equipment and device arrangement.

3. Include electrical rating, detail wiring for power, signals and controls.

C. Certification:

1. Submit four copies of performance curves, for CTI certified cooling towers, showing compliance with

actual conditions specified.

2. Certification by the manufacturer that the cooling towers conform to the requirements of the drawings

and specifications.

3. Provide one year warranty to include coverage for defects in material and workmanship. Fans,

fanshafts, bearings, sheaves, gearboxes, drive shafts, and couplings must be warranted against defects

in materials and workmanship for a period of five (5) years.

1.4 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are

referenced in the text by the basic designation only.

B. American National Standard Institute (ANSI/ASSE)

A10.18-2007 ....................................Safety Requirements for Temporary Floors, Holes, Wall Openings,

Stairways and Other Unprotected Edges in Construction and Demolition

Operations

C. American Society of Mechanical Engineers (ASME):

PTC 23-03........................................Performance Test Codes on Atmospheric Water Cooling Equipment

Page 186: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COOLING TOWERS23 65 00-2

D. American Society for Testing Materials (ASTM):

A385-08 ...........................................Standard Practice for Providing High-Quality Zinc Coatings (Hot-Dip)

B117-07a .........................................Standard Practice for Operating Salt Spray (Fog) Apparatus

B209-07 ...........................................Standard Specification for Aluminum and Aluminum-Alloy Sheet and

Plate

E84-08a ...........................................Standard Test Method for Surface Burning Characteristics of Building

Materials

E. Cooling Technology Institute (CTI):

ATC-105-00 .....................................Acceptance Test Code for Water-Cooling Towers (CTI Code Tower

Standard Specifications)

ATC-105S-Rev. July 2004 ...............Acceptance Test Code for Closed Circuit Cooling Towers (CTI Code

Tower Standard Specifications)

201-02 (Rev. 04) ..............................Standard for Certification of Water Cooling Tower Thermal Performance

(CTI Code Tower Standard Specifications)

F. National Electrical Manufacturers Association (NEMA):

MG 1-2006 Includes.........................Motors and Generators (ANSI)

250-03..............................................Enclosures for Electrical Equipment (1000 Volts Maximum)

G. National Fire Protection Association (NFPA):

70-08................................................National Electrical Code

PART 2 - PRODUCTS

2.1 FORCED DRAFT CLOSED CIRCUIT FLUID COOLER

A. Basis of design: Marley

Approved manufaturers:1. Evapco2. Baltimore Air Coil

2.2 FORCED DRAFT CLOSED CIRCUIT FLUID COOLER

A. Cooler shall be a factory assembled, forced draft, counter-flow type with a vertical discharge configuration.

B. Casing: Heavy gage (minimum 16 gage) Galvanized Steel

1. Galvanized Steel: Hot-dip galvanized steel complying with ASTM A653/A653M, and having G235

(Z700) coating.

2. Fasteners: Zinc or cadmium coated bolts or tapping screws for assembly. Use stainless steel washers

with neoprene backing where required for preventing leaks.

3. Joints and Seams: Sealed watertight.

4. Welded Connections: Continuous and watertight.

C. Framing: Rolled structural steel shapes, hot-dip galvanized after fabrication or structural shapes cold formed

from galvanized steel sheets or plates, complying with ASTM A653/A653M, and having G235 (Z700)

coating.

D. Cold Water Collection Basin: Heavy gauge zinc-coated or hot-dip galvanized steel, same as the casing

E. Collection Basin Water Level Control: Mechanically operated bronze adjustable make-up water float valve.

Page 187: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COOLING TOWERS23 65 00-3

F. Fans: Centrifugal double width, double inlet, forward curved blades, high efficiency and low noise belt driven

and statically and dynamically balanced at the factory after assembly. Hot-dip galvanized steel centrifugal

fans belt driven by single speed motor. The fan drive and moving parts shall be completely enclosed by

removable hot-dip galvanized screens and panels complying with OSHA regulations. Fan shaft bearings of

the self aligning, grease-lubricated ball or roller bearings with moisture proof seals and premium, moisture-

resistant grease suitable for temperatures between minus 29 and 149 degrees C (minus 20 and plus 300

degrees F). Bearings designed for an L-10 life of 50,000 hours and with extended lubrication lines to an

easily accessible location outside of the wet air stream. Provide access doors for inspection and cleaning.

G. Motors and Drives:

1. The following shall apply:

a. Motors: Totally enclosed fan cooled (TEFC) or epoxy encapsulated NEMA premium efficiency.

Protect fan, bearings, and appurtenances from damage by weather, corrosion, water spray and grit.

Provide motors with severe duty rating with the rotor and stator protected with corrosion-inhibiting

epoxy resin, double shielded, vacuum-degassed bearings lubricated with premium moisture-

resistant grease suitable for temperatures between minus 29 and plus 149 degrees C (minus 20

and plus 300 degrees F), and an internal heater automatically energized when motor is de-

energized. Provide an adjustable motor base or other suitable provision for adjusting belt tension.

b. V-Belt Drive: Fan shall be driven by a one-piece, multi-groove, neoprene/polyester belt, where this

is the manufacturer’s standard. Belt drives shall be "V" type. Belt driven fan and motor shafts shall

have taper-lock sheaves fabricated from corrosion resistant material.

c. Lubrication fittings shall be readily accessible outside the wet air stream. Provide access doors for

inspection and cleaning.

H. Fill:

1. Polyvinyl chloride plastic with flame spread index of 25 or less when tested in accordance with ASTM

E84.

2. Fungal resistance: No growth when tested according to ASTM G21.

I. Drift Eliminators: Three-pass PVC, drift loss limited to 0.005 percent of total water circulated.

2.3 ACCESSORIES

A. Electric Immersion Heaters: In pan suitable to maintain temperature of water in pan at 40 degrees F when

outside temperature is 0 degrees F. Immersion thermostat and float control operate heaters on low

temperature when the pan is filled. Heaters to be constructed of copper.

B. Electric Temperature Controller: In pan, with sensor to cycle fans.

C. Time Delay Relay: Limits fan motor starts to not more than six per hour.

D. Provide electronic remote reset vibration switch with contact for BAS monitoring. The electronic vibration

cutout switch shall be set to trip at a point so as not to cause damage to the cooling tower. The trip point will

be set in a frequency range of 2 to 1000 Hertz and a trip point of 0.45 in/sec.

2.4 CONTROL PANEL

A. Provide factory furnished control panel for each fluid cooler.

B. Control panel shall be a field installed and wired NEMA 250 Type 3 – Drip-proof type enclosure, containing:

1. Unfused disconnect switch.

2. Fan motor starters.

Page 188: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COOLING TOWERS23 65 00-4

3. Interlocks and relays.

4. Pilot lights and push buttons.

5. Provide contacts for remote start/stop and for Building Automation System interface.

PART 3 - PERFORMANCE

3.1 UNIT PERFORMANCE

A. All information is given on a per unit basis.

B. Cooling Tower Unit #1:a. Existing Unit to be replaced, Baltimore Air Coil, Model VTL-152-M.

b. Water flow: 441 gpm

c. Temperature drop: 95° to 85° at 78° entering outdoor wet bulb temperature.

d. Fan motor: (1) 20 hp, 1800 rpm, 3 phase, 60 Hz, 230/460V, standard TEFC enclosure. Fan drives based

on 0” ESP.

C. Cooling Tower Unit #2:a. Existing Unit to be replaced, Baltimore Air Coil, Model VTL-137-M.

b. Water flow: 403 gpm

c. Temperature drop: 95° to 85° at 78° entering outdoor wet bulb temperature.

d. Fan motor: (1) 20 hp, 1800 rpm, 3 phase, 60 Hz, 230/460V, standard TEFC enclosure. Fan drives based

on 0” ESP.

END OF SECTION

Page 189: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 1

SECTION 237416.11PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes packaged, small-capacity, rooftop air-conditioning units (RTUs) with the following components:

1. Casings.2. Fans, drives, and motors.3. Rotary heat exchangers.4. Coils.5. Refrigerant circuit components.6. Air filtration.7. Gas furnaces.8. Dampers.9. Electrical power connections.10. Controls.11. Roof curbs.12. Accessories.

1.3 DEFINITIONS

A. RTU: Rooftop unit. As used in this Section, this abbreviation means packaged, small-capacity, rooftop air-conditioning units. This abbreviation is used regardless of whether the unit is mounted on the roof or on a concrete base on ground.

1.4 ACTION SUBMITTALS

A. Product Data: For each RTU.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes.

2. Include rated capacities, dimensions, required clearances, characteristics, and furnished specialties and accessories.

3. Include unit dimensions and weight.4. Include cabinet material, metal thickness, finishes, insulation, and accessories.5. Fans:

a. Include certified fan-performance curves with system operating conditions indicated.b. Include certified fan-sound power ratings.c. Include fan construction and accessories.d. Include motor ratings, electrical characteristics, and motor accessories.

6. Include certified coil-performance ratings with system operating conditions indicated.7. Include filters with performance characteristics.

Page 190: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 2

8. Include gas furnaces with performance characteristics.9. Include dampers, including housings, linkages, and operators.

B. Shop Drawings: For each packaged, small-capacity, rooftop air-conditioning unit.

1. Include plans, elevations, sections, and mounting details.2. Include details of equipment assemblies. Indicate dimensions, weights, loads, required clearances,

method of field assembly, components, and location and size of each field connection.3. Include diagrams for power, signal, and control wiring.

C. Delegated-Design Submittal: For RTU supports indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1. Include design calculations for selecting vibration isolators and for designing vibration isolation bases.

2. Detail mounting, securing, and flashing of roof curb to roof structure. Indicate coordinating requirements with roof membrane system.

1.5 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: Floor plans and other details, or BIM model, drawn to scale, showing the items described in this Section, and coordinated with all building trades.

B. Sample Warranty: For manufacturer's warranty.

C. Seismic Qualification Data: Certificates, for RTUs, accessories, and components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

4. Restraint of internal components.

D. Product Certificates: Submit certification that specified equipment will withstand wind forces identified in "Performance Requirements" Article and in Section 230548 "Vibration and Seismic Controls for HVAC."

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculations.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of wind force and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

E. Source quality-control reports.

F. System startup reports.

G. Field quality-control reports.

1.6 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For RTUs to include in emergency, operation, and maintenance manuals.

Page 191: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 3

1.7 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Filters: One et of filters for each unit.2. Gaskets:One set for each access door.3. Fan Belts: One set for each belt-driven fan.4. Filters: One set of filters for each unit.

1.8 WARRANTY

A. Warranty: Manufacturer agrees to repair or replace components of outdoor, semi-custom, air-handling unit that fail in materials or workmanship within specified warranty period.

1. Warranty Period: Fiver years from date of Substantial Completion.2. Warranty Period for Heat Exchangers: Manufacturer's standard, but not less than five years from

date of Substantial Completion

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by an NRTL, and marked for intended location and application.

B. NFPA Compliance: Comply with NFPA 90A for design, fabrication, and installation of RTUs and components.

C. ASHRAE 62.1 Compliance: Applicable requirements in ASHRAE 62.1, Section 5 - "Systems and Equipment" and Section 7 - "Construction and Startup."

D. ASHRAE 15 Compliance: For refrigeration system safety.

E. ASHRAE/IES 90.1 Compliance: Applicable requirements in ASHRAE/IES 90.1, Section 6 - "Heating, Ventilating, and Air-Conditioning."

F. UL Compliance: Comply with UL 1995.

G. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design mounting and restraints for RTUs, including comprehensive engineering analysis.

2.2 CAPACITIES AND CHARACTERISTICS

A. Supply-Air Fan:

1. Fan Type: Belt driven, double width, forward curved or backward inclined, centrifugal.2. Fan Type: Double width, forward curved, centrifugal.3. Airflow: As scheduled.4. External Static Pressure: As scheduled.5. Fan Speed: As scheduled.6. Enclosure Type: Totally enclosed, fan cooled.7. Enclosure Materials: Rolled steel.8. Motor Characteristics: As scheduled.

Page 192: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 4

B. Rotary Heat Exchanger: As scheduled.

C. Supply-Air Refrigerant Coil: As scheduled.

D. Gas Furnace: As scheduled.

E. Dampers:

1. Outdoor-Air Damper: Linked damper blades, for outdoor air as scheduled.2. Outdoor- and Return-Air Mixing Dampers: Parallel blade galvanized-steel dampers mechanically

fastened to cadmium plated for galvanized-steel operating rod in reinforced cabinet. Connect operating rods with common linkage and interconnect so dampers operate simultaneously.

3. Relief-Air Damper: Gravity actuated or motorized, as required by ASHRAE/IES 90.1.4. Barometric relief dampers.

F. Recirculating-Air Filters:

1. Minimum Efficiency Reporting Value:

a. MERV Rating: MERV 8 according to ASHRAE 52.2.

G. Outdoor-Air Filters:

1. Type: Pleated.

2. Minimum Efficiency Reporting Value:

a. MERV Rating: MERV 8, according to ASHRAE 52.2.

H. Vibration Isolation Devices: Open spring, with 1” minimum deflection.

I. Electrical Characteristics for Single-Point Connection:

1. Voltage: 460 V.2. Phase: 3 phase.3. Hertz: 60.

2.3 MANUFACTURERS

A. Approved manufacturers:1. Trane2. Carrier3. Daikin4. Approved equivalent.

2.4 UNIT CASINGS

A. General Fabrication Requirements for Casings: Formed and reinforced double-wall insulated panels, fabricated to allow removal for access to internal parts and components, with joints between sections sealed.

B. Double-Wall Construction:

1. Outside Casing Wall: Galvanized steel, minimum 18 gauge thick with manufacturer's standard finish with pitched roof panels and knockouts with grommet seals for electrical and piping connections and lifting lugs.

2. Inside Casing Wall: G90 coated galvanized steel, 0.034 inch thick.

Page 193: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 5

3. Floor Plate: G90 galvanized steel minimum 18 gauge thick.4. Casing Insulation:

a. Materials: Injected polyurethane foam insulation.b. Insulation Thickness: 1 inch minimum.c. Thermal Break: Provide continuity of insulation with no through-casing metal in casing walls,

floors, or roof of unit.

C. Airstream Surfaces: Surfaces in contact with airstream shall comply with requirements in ASHRAE 62.1.

D. Static-Pressure Classifications:

1. For Unit Sections Upstream of Fans: Minus 3-inch wg.2. For Unit Sections Downstream and Including Fans: 3-inch wg.

E. Panels and Doors:

1. Panels:

a. Fabrication: Formed and reinforced with same materials and insulation thickness as casing.b. Fasteners: Two or more camlock type for panel lift-out operation. Arrangement shall allow

panels to be opened against air-pressure differential.c. Gasket: Neoprene, applied around entire perimeters of panel frames.d. Size: Large enough to allow inspection and maintenance of air-handling unit's internal

components.

2. Access Doors:

a. Hinges: A minimum of two ball-bearing hinges or stainless steel piano hinge and two wedge-lever-type latches, operable from inside and outside. Arrange doors to be opened against air-pressure differential.

b. Gasket: Neoprene, applied around entire perimeters of panel frames.c. Size: Large enough to allow inspection and maintenance of air-handling unit's internal

components.

3. Locations and Applications:

a. Fan Section: Inspection and access panelsb. Coil Section: Inspection and access panels.c. Damper Section: Inspection and access panels.d. Filter Section: Inspection and access panels large enough to allow periodic removal and

installation of filters.e. Mixing Section: Doors.

F. Condensate Drain Pans:

1. Location: Each cooling coil and rotary heat exchanger.2. Construction:

a. Single-wall, galvanized-steel or noncorrosive polymer sheet.

3. Drain Connection:

a. Located at lowest point of pan and sized to prevent overflow. Terminate with threaded nipple on one end of pan.

b. Minimum Connection Size: NPS 1.

Page 194: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 6

2.5 FANS, DRIVES, AND MOTORS

A. Fan and Drive Assemblies: Statically and dynamically balanced and designed for continuous operation at maximum-rated fan speed and motor horsepower.

B. Supply-Air Fans: Centrifugal, rated according to AMCA 210; galvanized or painted steel; mounted on solid-steel shaft.

1. Shafts: With field-adjustable alignment.

a. Turned, ground, and polished hot-rolled steel with keyway.

2. Shaft Bearings:

a. Heavy-duty, self-aligning, pillow-block type with an L-50 rated life of minimum 100,000 hours according to ABMA 9.

3. Housings: Formed- and reinforced-steel panels to form curved scroll housings with shaped cutoff and spun-metal inlet bell.

a. Bracing: Steel angle or channel supports for mounting and supporting fan scroll, wheel, motor, and accessories.

4. Centrifugal Fan Wheels: Inlet flange, backplate, and shallow blades with inlet and tip curved forward in direction of airflow and mechanically fastened to flange and backplate; steel or aluminum hub swaged to backplate and fastened to shaft with setscrews.

5. Mounting: For internal vibration isolation. Factory-mount fans with manufacturer's standard vibration isolation mounting devices having a minimum static deflection of 1 inch.

6. Shaft Lubrication Lines: Extended to a location outside the casing.7. Flexible Connector: Factory fabricated with a fabric strip minimum 3-1/2 inches wide, attached to

two strips of minimum 2-3/4-inch wide by 0.028-inch thick, galvanized-steel sheet.

a. Flexible Connector Fabric: Glass fabric, double coated with neoprene. Fabrics, coatings, and adhesives shall comply with UL 181, Class 1.

C. Drives, Direct: Factory-mounted, direct drive.

D. Drives, Belt: Factory-mounted, V-belt drive, with adjustable alignment and belt tensioning, and with 1.5 service factor based on fan motor.

1. Pulleys: Cast iron or cast steel with split, tapered bushing, dynamically balanced at the factory.2. Belts: Oil resistant, non-sparking and nonstatic; in matched sets for multiple-belt drives.3. Belt Guards: Comply with requirements specified by OSHA and fabricate according to SMACNA's

"HVAC Duct Construction Standards"; 0.146-inch thick, 3/4-inch diamond-mesh wire screen, welded to steel angle frame; prime coated.

E. Motors:

1. Comply with NEMA designation, temperature rating, service factor, and efficiency requirements for motors specified in Section 230513 "Common Motor Requirements for HVAC Equipment."

2. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load will not require motor to operate in service factor range above 1.0.

3. Enclosure Type: Totally enclosed, fan cooled..4. Enclosure Materials: Cast iron.5. Efficiency: Premium efficient as defined in NEMA MG 1.6. Motor Pulleys: Adjustable pitch for use with 5-hp motors and smaller; fixed pitch for use with motors

larger than 5 hp. Select pulley size so pitch adjustment is at the middle of adjustment range at fan design conditions.

7. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical devices and connections specified in electrical Sections.

Page 195: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 7

2.6 ROTARY HEAT EXCHANGER

A. Heat exchanger integral with unit.

B. Casing:

1. Galvanized steel, stainless steel, or aluminum with manufacturer's standard factory-painted finish.2. Integral purge section limiting carryover of exhaust air to between 0.05 percent at 1.6-inch wg and

0.20 percent at 4-inch wg differential pressure.3. Casing seals on periphery of rotor and on duct divider and purge section.4. Support vertical rotor on grease-lubricated ball bearings having extended grease fittings. Support

horizontal rotors on tapered roller bearing.

C. Rotor - Aluminum or Polymer: Segmented wheel, strengthened with radial spokes, with nontoxic, noncorrosive, silica-gel desiccant coating.

D. Rotor - Aluminum, Metallic, or Polymer: Aluminum, metallic, or polymer segmented wheel, strengthened with radial spokes impregnated with nonmigrating, water-selective, 3-angstrom molecular-sieve desiccant coating.

E. Drive: Fractional horsepower motor and gear reducer, with speed changed by variable-frequency controller. Permanently lubricated wheel bearings with an L-10 of 400,000 hours.

F. Controls:

1. Starting relay, factory mounted and wired, and manual motor starter for field wiring.2. Variable-frequency controller, factory mounted and wired, permitting input of field connected 4-20

mA or 1-10-V control signal.3. Variable-frequency controller, factory mounted and wired, with exhaust-air sensor to vary rotor

speed and maintain exhaust temperature above freezing.4. Variable-frequency controller, factory mounted and wired, with exhaust- and outdoor-air sensors,

automatic changeover thermostat and set-point adjuster, to vary rotor speed and maintain exhaust temperature above freezing and air differential temperature above set point. Rotor speed shall increase to maximum when exhaust-air temperature is less than outdoor-air temperature.

5. Control energy recovery to permit air economizer operation.

a. Bypass dampers to assist energy recovery control.

6. Pilot-Light Indicator: Display rotor rotation and speed.7. Speed Settings: Adjustable settings for maximum and minimum rotor speed limits.8. Defrost cycle.

2.7 COILS

A. General Requirements for Coils:

1. Comply with AHRI 410.2. Fabricate coils section to allow for removal and replacement of coil for maintenance and to allow in-

place access for service and maintenance of coil(s).3. Coils shall not act as structural component of unit.

B. Supply-Air Refrigerant Coil:

1. Tubes: Copper2. Fins:

a. Material: Aluminum.b. Fin Spacing: Maximum 10 fins per inch.

Page 196: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 8

3. Fin and Tube Joints: Mechanical bond.4. Headers: Seamless-copper headers with brazed connections.5. Frames: Galvanized steel.6. Ratings: Designed, tested, and rated according to ASHRAE 33 and AHRI 410.

a. Working Pressure: Minimum 300 psig.

C. Hot-Gas Reheat Refrigerant Coil:

1. Tubes: Copper.2. Fins:

a. Material: Aluminum.b. Fin Spacing: Maximum: 10 fins per inch.

3. Fin and Tube Joints: Mechanical bond.4. Headers: Seamless-copper headers with brazed connections.5. Frames: Galvanized steel.6. Ratings: Designed, tested, and rated according to ASHRAE 33 and AHRI 410.

a. Working Pressure: Minimum 300 psig.

7. Suction-discharge bypass valve.

2.8 REFRIGERANT CIRCUIT COMPONENTS

A. Compressor: Hermetic, variable-speed scroll, mounted on vibration isolators; with internal overcurrent and high-temperature protection, internal pressure relief, and crankcase heater.

B. Refrigeration Specialties:

1. Refrigerant: R-410A2. Expansion valve with replaceable thermostatic element.3. Refrigerant filter/dryer.4. Manual-reset high-pressure safety switch.5. Automatic-reset low-pressure safety switch.6. Minimum off-time relay.7. Automatic-reset compressor motor thermal overload.8. Brass service valves installed in compressor suction and liquid lines.9. Low-ambient kit high-pressure sensor.10. Hot-gas reheat solenoid valve modulating with a replaceable magnetic coil.11. Hot-gas bypass solenoid valve with a replaceable magnetic coil.12. Four-way reversing valve with a replaceable magnetic coil, thermostatic expansion valves with

bypass check valves, and a suction line accumulator.

2.9 AIR FILTRATION

A. Panel Filters:

1. Description: Pleated factory-fabricated, self-supported, disposable air filters with holding frames.2. Filter Unit Class: UL 900.3. Media: Interlaced glass, synthetic or cotton fibers coated with nonflammable adhesive and

antimicrobial coating.4. Filter-Media Frame: Beverage board with perforated metal retainer, or metal grid, on outlet side.

B. Adhesive, Sustainability Projects: As recommended by air-filter manufacturer and with a VOC content of 80 g/L or less.

Page 197: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 9

C. Adhesive, LEED for Schools Projects: As recommended by air-filter manufacturer and that complies with the testing and product requirements of the California Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

2.10 GAS FURNACES

A. Description: Factory assembled, piped, and wired; complying with ANSI Z21.47/CSA 2.3 and NFPA 54.

B. CSA Approval: Designed and certified by and bearing label of CSA.

C. Burners: Stainless steel.

1. Rated Minimum Turndown Ratio: 30 to 1.2. Fuel: Natural gas.3. Ignition: Electronically controlled electric spark or hot-surface igniter with flame sensor.4. Gas Control Valve: Modulating.5. Gas Train: Single-body, regulated, redundant, 24-V ac gas valve assembly containing pilot solenoid

valve, pilot filter, pressure regulator, pilot shutoff, and manual shutoff.

D. Heat-Exchanger and Drain Pan: Stainless steel.

E. Venting, Gravity: Gravity vented with vertical extension.

F. Safety Controls:

1. Gas Manifold: Safety switches and controls complying with ANSI standards and FM Global.

2.11 DAMPERS

A. Dampers: Comply with requirements in Section 230923.12 "Control Dampers."

B. Outdoor- and Return-Air Dampers: Low-leakage, double-skin, airfoil-blade, galvanized-steel dampers with compressible jamb seals and extruded-vinyl blade edge seals in parallel-blade arrangement with zinc-plated steel operating rods rotating in sintered bronze or nylon bearings mounted in a single galvanized-steel frame, and with operating rods connected with a common linkage. Leakage rate shall not exceed 4 cfm/sq. ft. at 1-inch wg and 8 cfm/sq. ft. at 4-inch wg.

C. Barometric relief dampers.

D. Damper Operators: Comply with requirements in Section 230923.12 "Control Dampers."

E. Electronic Damper Operators:

1. Direct-coupled type designed for minimum 60,000 full-stroke cycles at rated torque.2. Electronic damper position indicator shall have visual scale indicating percent of travel and 2- to 10-

V dc, feedback signal.3. Operator Motors:

a. Comply with NEMA designation, temperature rating, service factor, enclosure type, and efficiency requirements for motors specified in Section 230513 "Common Motor Requirements for HVAC Equipment."

b. Size to operate with sufficient reserve power to provide smooth modulating action or two-position action.

c. Permanent Split-Capacitor or Shaded-Pole Type: Gear trains completely oil immersed and sealed. Equip spring-return motors with integral spiral-spring mechanism in housings

Page 198: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 10

designed for easy removal for service or adjustment of limit switches, auxiliary switches, or feedback potentiometer.

4. Nonspring-Return Motors for Dampers Larger Than 25 Sq. Ft.: Size for running torque of 150 in. x lbf and breakaway torque of 300 in. x lbf.

5. Spring-Return Motors for Dampers Larger Than 25 Sq. Ft.: Size for running and breakaway torque of 150 in. x lbf.

6. Overload Protection: Electronic overload or digital rotation-sensing circuitry.7. Fail-Safe Operation: Mechanical, spring-return mechanism with external, manual gear release on

nonspring-return actuators.8. Power Requirements (Modulating): Maximum 10 VA at 24 V ac or 8 W at 24 V dc.9. Proportional Signal: 2 to 10 V dc or 4 to 20 mA, and 2- to 10-V dc position feedback signal.

2.12 ELECTRICAL POWER CONNECTIONS

A. RTU shall have a single connection of power to unit with unit-mounted disconnect switch accessible from outside unit and control-circuit transformer with built-in overcurrent protection.

2.13 CONTROLS

A. Control equipment and sequence of operation are specified in Section 230923 "Direct Digital Control (DDC) System for HVAC."

B. Basic Unit Controls:

1. Control-voltage transformer.2. Wall-mounted thermostat or sensor with the following features:

a. Heat-cool-off switch.b. Fan on-auto switch.c. Fan-speed switch.d. Automatic changeover.e. Adjustable deadband.f. Exposed set point.g. Exposed indication.h. Degree F indication.i. Unoccupied-period-override push button.j. Data entry and access port to input temperature and humidity set points, occupied and

unoccupied periods, and output room temperature and humidity, supply-air temperature, operating mode, and status.

3. Wall-mounted humidistat or sensor with the following features:

a. Exposed set point.b. Exposed indication.

C. DDC Controller:

1. Controller shall have volatile-memory backup.2. Safety Control Operation:

a. Smoke Detectors: Stop fan and close outdoor-air damper if smoke is detected. Provide additional contacts for alarm interface to fire-alarm control panel.

b. Firestats: Stop fan and close outdoor-air damper if air greater than 130 deg F enters unit. Provide additional contacts for alarm interface to fire-alarm control panel.

c. Low-Discharge Temperature: Stop fan and close outdoor-air damper if supply-air temperature is less than 40 deg F

d. Defrost Control for Condenser Coil: Pressure differential switch to initiate defrost sequence.

Page 199: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 11

3. Scheduled Operation: Occupied and unoccupied periods on 365-day clock with a minimum of four programmable periods per day.

4. Unoccupied Period:

a. Heating Setback: 10 deg F .b. Cooling Setback: System off.c. Override Operation: Two hours.

5. Supply Fan Operation:

a. Occupied Periods: Run fan continuously.b. Unoccupied Periods: Cycle fan to maintain setback temperature.

6. Refrigerant Circuit Operation:

a. Occupied Periods: Cycle or stage compressors, and operate hot-gas bypass to match compressor output to cooling load to maintain room temperature and humidity. Cycle condenser fans to maintain maximum hot-gas pressure. Operate low-ambient control kit to maintain minimum hot-gas pressure.

b. Unoccupied Periods: Cycle compressors and condenser fans for heating to maintain setback temperature.

c. Switch reversing valve for heating or cooling mode on air-to-air heat pump.

7. Hot-Gas Reheat-Coil Operation:

a. Occupied Periods: Humidistat opens hot-gas valve to provide hot-gas reheat, and cycles the compressor.

b. Unoccupied Periods: Reheat not required.

8. Gas Furnace Operation:

a. Occupied Periods: Modulate burner to maintain room temperature.b. Unoccupied Periods: Cycle burner to maintain setback temperature.

9. Fixed Minimum Outdoor-Air Damper Operation:

a. Occupied Periods: Open to outdoor air percent as scheduled.b. Unoccupied Periods: Close the outdoor-air damper.

10. Economizer Outdoor-Air Damper Operation:

a. Morning warm-up/ cool-down cycles.b. Occupied Periods: Open to 10 percent fixed minimum intake, and maximum 100 percent of

the fan capacity. Controller shall permit air-side economizer operation when outdoor air is less than 60 deg F. Use outdoor-air enthalpy to adjust mixing dampers. During economizer cycle operation, lock out cooling.

c. Unoccupied Periods: Close outdoor-air damper and open return-air damper.d. Outdoor-Airflow Monitor: Accuracy maximum plus or minus 5 percent within 15 and 100

percent of total outdoor air. Monitor microprocessor shall adjust for temperature, and output shall range from 4 to 20 mA.

11. Carbon Dioxide Sensor Operation:

a. Occupied Periods: Reset minimum outdoor-air ratio down to minimum 10 percent to maintain maximum 1000-ppm concentration.

b. Unoccupied Periods: Close outdoor-air damper and open return-air damper.

12. Terminal-Unit Relays:

Page 200: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 12

a. Provide heating- and cooling-mode changeover relays compatible with terminal control system required in Section 233600 "Air Terminal Units" and Section 230923 "Direct Digital Control (DDC) System for HVAC."

D. Interface Requirements for HVAC Instrumentation and Control System:

1. Interface relay for scheduled operation.2. Interface relay to provide indication of fault at the central workstation and diagnostic code storage.3. Provide BACnet compatible interface for central HVAC control workstation for the following:

a. Adjusting set points.b. Monitoring supply fan start, stop, and operation.c. Inquiring data to include[ outdoor-air damper position, supply- and room-air

temperature[ and humidity.d. Monitoring occupied and unoccupied operations.e. Monitoring constant and variable motor loads.f. Monitoring variable-frequency drive operation.g. Monitoring cooling load.h. Monitoring economizer cycles.i. Monitoring air-distribution static pressure and ventilation air volume.

2.14 ROOF CURBS

A. Roof curbs with vibration isolators and wind or seismic restraints are specified in Section 230548 "Vibration and Seismic Controls for HVAC."

B. Materials: Galvanized steel with corrosion-protection coating, watertight gaskets, and factory-installed wood nailer; complying with NRCA standards.

1. Curb Insulation and Adhesive: Comply with NFPA 90A or NFPA 90B.

a. Materials: ASTM C1071, Type I or II.b. Thickness: 2 inches.

2. Application: Factory applied with adhesive and mechanical fasteners to the internal surface of curb.

a. Liner Adhesive: Comply with ASTM C916, Type I.b. Mechanical Fasteners: Galvanized steel, suitable for adhesive attachment, mechanical

attachment, or welding attachment to duct without damaging liner when applied as recommended by manufacturer and without causing leakage in cabinet.

c. Liner materials applied in this location shall have airstream surface coated with a temperature-resistant coating or faced with a plain or coated fibrous mat or fabric depending on service air velocity.

d. Liner Adhesive: Comply with ASTM C916, Type I.

C. Curb Dimensions: Adaptable horizontal dimensions as required for existing roof openings.

2.15 ACCESSORIES

A. Duplex, 115-V, ground-fault-interrupter outlet with 15-A overcurrent protection. Include transformer if required. Outlet shall be energized even if the unit main disconnect is open.

B. Low-ambient kit using staged condenser fans for operation down to 35 deg F.

C. Filter differential pressure switch with sensor tubing on either side of filter. Set for final filter pressure loss.

D. Remote potentiometer to adjust minimum economizer damper position.

Page 201: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 13

E. Return-air bypass damper.

F. Factory- or field-installed, demand-controlled ventilation.

G. Safeties:

1. Smoke detector.2. Condensate overflow switch.3. Phase-loss protection.4. High and low pressure control.5. Gas furnace 6. airflow-proving switch.

H. Coil guards of painted, galvanized-steel wire.

I. Hail guards of galvanized steel, painted to match casing.

J. Concentric diffuser with white louvers and polished aluminum return grilles, insulated diffuser box with mounting flanges, and interior transition.

K. Door switches to disable heating or reset set point when open.

L. Outdoor-air intake weather hood with moisture eliminator.

M. Oil separator.

2.16 MATERIALS

A. Steel:

1. ASTM A36/A36M for carbon structural steel.2. ASTM A568/A568M for steel sheet.

B. Stainless Steel:

1. Manufacturer's standard grade for casing.2. Manufacturer's standard type, ASTM A240/A240M for bare steel exposed to airstream or moisture.

C. Galvanized Steel: ASTM A653/A653M.

D. Aluminum: ASTM B209.

E. Comply with Section 230546 "Coatings for HVAC" for corrosion-resistant coating.

2.17 SOURCE QUALITY CONTROL

A. AHRI Compliance:

1. Comply with AHRI 210/240 for testing and rating energy efficiencies for RTUs.2. Comply with AHRI 340/360 for testing and rating energy efficiencies for RTUs.3. Comply with AHRI 270 for testing and rating sound performance for RTUs.4. Comply with AHRI 1060 for testing and rating performance for air-to-air exchanger.

B. AMCA Compliance:

Page 202: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 14

1. Comply with AMCA 11 and bear the AMCA-Certified Ratings Seal for air and sound performance according to AMCA 211 and AMCA 311.

2. Damper leakage tested according to AMCA 500-D.3. Operating Limits: Classify according to AMCA 99.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of RTUs.

B. Examine roughing-in for RTUs to verify actual locations of piping and duct connections before equipment installation.

C. Examine roofs for suitable conditions where RTUs will be installed.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. Roof Curb: Install on roof structure or concrete base, level and secure, according to NRCA's "NRCA Roofing Manual: Membrane Roof Systems." Install RTUs on curbs and coordinate roof penetrations and flashing with roof construction specified in Section 077200 "Roof Accessories." Secure RTUs to upper curb rail, and secure curb base to roof framing or concrete base with anchor bolts. Coordinate sizes and locations of roof curbs with actual equipment provided.

1. Install normal-weight, 3000-psi, compressive strength (28-day) concrete mix inside roof curb, 4 inches thick. Concrete, formwork, and reinforcement are specified with concrete.

B. Unit Support: Install unit level on structural curbs. Coordinate wall penetrations and flashing with wall construction. Secure RTUs to structural support with anchor bolts.

C. Equipment Mounting:

1. Install RTUs on cast-in-place concrete equipment bases. Comply with requirements for equipment bases and foundations specified in Section 033000 "Cast-in-Place Concrete."

2. Comply with requirements for vibration isolation and seismic-control devices specified in Section 230548 "Vibration and Seismic Controls for HVAC."

3. Comply with requirements for vibration isolation devices specified in Section 230548.13 "Vibration Controls for HVAC."

3.3 PIPING CONNECTIONS

A. Piping installation requirements are specified in other Sections. Drawings indicate general arrangement of piping, fittings, and specialties.

B. Where installing piping adjacent to RTU, allow space for service and maintenance.

C. Connect piping to unit mounted on vibration isolators with flexible connectors.

D. Connect condensate drain pans using NPS 1-1/4 ASTM B88, Type M copper tubing. Extend to nearest equipment or roof drain. Construct deep trap at connection to drain pan and install cleanouts at changes in direction.

Page 203: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 15

E. Gas Piping: Comply with applicable requirements in Section 231123 "Facility Natural-Gas Piping." Connect gas piping to burner, full size of gas train inlet, and connect with union and shutoff valve with sufficient clearance for burner removal and service.

F. Hot- and Chilled-Water Piping: Comply with applicable requirements in Section 232113 "Hydronic Piping" and Section 232116 "Hydronic Piping Specialties." Install shutoff valve and union or flange at each coil supply connection. Install balancing valve and union or flange at each coil return connection.

G. Steam and Condensate Piping: Comply with applicable requirements in Section 232213 "Steam and Condensate Heating Piping" and Section 232216 "Steam and Condensate Heating Piping Specialties." Install shutoff valve at steam supply connections, float and thermostatic trap, and union or flange at each coil return connection. Install gate valve and inlet strainer at supply connection of dry steam humidifiers, and inverted bucket steam trap to condensate return connection.

3.4 Refrigerant Piping: Comply with applicable DUCT CONNECTIONS

A. requirements in Section 232300 "Refrigerant Piping." Install shutoff valve and union or flange at each supply and return connection.

B. Comply with duct installation requirements specified in other HVAC Sections. Drawings indicate general arrangement of ducts. The following are specific connection requirements:

1. Install ducts to termination at top of roof curb.2. Remove roof decking only as required for passage of ducts. Do not cut out decking under entire

roof curb.3. Connect supply ducts to RTUs with flexible duct connectors specified in Section 233300 "Air Duct

Accessories."4. Install return-air duct continuously through roof structure.

3.5 ELECTRICAL CONNECTIONS

A. Connect electrical wiring according to Section 260519 "Low-Voltage Electrical Power Conductors and Cables."

B. Ground equipment according to Section 260526 "Grounding and Bonding for Electrical Systems."

C. Install electrical devices furnished by manufacturer, but not factory mounted, according to NFPA 70 and NECA 1.

D. Install nameplate for each electrical connection, indicating electrical equipment designation and circuit number feeding connection.

1. Nameplate shall be laminated acrylic or melamine plastic signs as specified in Section 260553 "Identification for Electrical Systems."

2. Nameplate shall be laminated acrylic or melamine plastic signs as layers of black with engraved white letters at least 1/2 inch high.

3. Locate nameplate where easily visible.

3.6 CONTROL CONNECTIONS

A. Install control and electrical power wiring to field-mounted control devices.

B. Connect control wiring according to Section 260523 "Control-Voltage Electrical Power Cables."

Page 204: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 16

3.7 FIELD QUALITY CONTROL

A. Manufacturer's Field Service: Engage a factory-authorized service representative to test and inspect components, assemblies, and equipment installations, including connections.

B. Perform tests and inspections with the assistance of a factory-authorized service representative.

C. Tests and Inspections:

1. After installing RTUs and after electrical circuitry has been energized, test units for compliance with requirements.

2. Inspect for and remove shipping bolts, blocks, and tie-down straps.3. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor

rotation and unit operation.4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and

equipment.

D. RTU will be considered defective if it does not pass tests and inspections.

E. Prepare test and inspection reports.

3.8 STARTUP SERVICE

A. Engage a factory-authorized service representative to perform startup service.

1. Complete installation and startup checks according to manufacturer's written instructions.2. Inspect for visible damage to unit casing.3. Inspect for visible damage to furnace combustion chamber.4. Inspect for visible damage to compressor, coils, and fans.5. Inspect internal insulation.6. Verify that labels are clearly visible.7. Verify that clearances have been provided for servicing.8. Verify that controls are connected and operable.9. Verify that filters are installed.10. Clean condenser coil and inspect for construction debris.11. Clean furnace flue and inspect for construction debris.12. Connect and purge gas line.13. Remove packing from vibration isolators.14. Inspect operation of barometric relief dampers.15. Verify lubrication on fan and motor bearings.16. Inspect fan-wheel rotation for movement in correct direction without vibration and binding.17. Adjust fan belts to proper alignment and tension.18. Start unit according to manufacturer's written instructions.

a. Start refrigeration system.b. Do not operate below recommended low-ambient temperature.c. Complete startup sheets and attach copy with Contractor's startup report.

19. Inspect and record performance of interlocks and protective devices; verify sequences.20. Operate unit for an initial period as recommended or required by manufacturer.21. Perform the following operations for both minimum and maximum firing. Adjust burner for peak

efficiency:

a. Measure gas pressure on manifold.b. Inspect operation of power vents.c. Measure combustion-air temperature at inlet to combustion chamber.d. Measure flue-gas temperature at furnace discharge.e. Perform flue-gas analysis. Measure and record flue-gas carbon dioxide and oxygen

concentration.

Page 205: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 17

f. Measure supply-air temperature and volume when burner is at maximum firing rate and when burner is off. Calculate useful heat to supply air.

22. Calibrate thermostats.23. Adjust and inspect high-temperature limits.24. Inspect outdoor-air dampers for proper stroke and interlock with return-air dampers.25. Start refrigeration system and measure and record the following when ambient is a minimum of 15

deg F above return-air temperature:

a. Coil leaving-air, dry- and wet-bulb temperatures.b. Coil entering-air, dry- and wet-bulb temperatures.c. Outdoor-air, dry-bulb temperature.d. Outdoor-air-coil, discharge-air, dry-bulb temperature.

26. Inspect controls for correct sequencing of heating, mixing dampers, refrigeration, and normal and emergency shutdown.

27. Measure and record the following minimum and maximum airflows. Plot fan volumes on fan curve.

a. Supply-air volume.b. Return-air volume.c. Relief-air volume.d. Outdoor-air intake volume.

28. Simulate maximum cooling demand and inspect the following:

a. Compressor refrigerant suction and hot-gas pressures.b. Short circuiting of air through condenser coil or from condenser fans to outdoor-air intake.

29. Verify operation of remote panel including pilot-light operation and failure modes. Inspect the following:

a. High-temperature limit on gas-fired heat exchanger.b. Low-temperature safety operation.c. Filter high-pressure differential alarm.d. Economizer to minimum outdoor-air changeover.e. Relief-air fan operation.f. Smoke and firestat alarms.

30. After startup and performance testing and prior to Substantial Completion, replace existing filters with new filters.

3.9 ADJUSTING

A. Adjust damper linkages for proper damper operation.

B. Comply with requirements in Section 230593 "Testing, Adjusting, and Balancing for HVAC" for air-handling system testing, adjusting, and balancing.

C. Occupancy Adjustments: When requested within 12 months from date of Substantial Completion, provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to two visits to Project during other-than-normal occupancy hours for this purpose.

3.10 CLEANING

A. After completing system installation and testing, adjusting, and balancing RTUs and air-distribution systems, clean RTUs internally to remove foreign material and construction dirt and dust. Clean fan wheels, cabinets, dampers, coils, and filter housings, and install new, clean filters.

Page 206: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS237416.11 - 18

3.11 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.

B. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

C. Manufacturer's Field Service: Engage a factory-authorized service representative to test and inspect components, assemblies, and equipment installations, including connections.

D. Perform tests and inspections with the assistance of a factory-authorized service representative.

E. Tests and Inspections:

1. After installing RTUs and after electrical circuitry has been energized, test units for compliance with requirements.

2. Inspect for and remove shipping bolts, blocks, and tie-down straps.3. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor

rotation and unit operation.4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and

equipment.

F. RTU will be considered defective if it does not pass tests and inspections.

G. Prepare test and inspection reports.

3.12 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain RTUs.

END OF SECTION 237416.11

Page 207: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 1

238400 - DESSICANT DEHUMIDIFICATION UNITS

PART 1: GENERAL

1.1 SUMMARY

A. THIS SPECIFICATION IS PROVIDED FOR INFORMATIONAL PURPOSES ONLY. OWNER TO PROVIDE EQUIPMENT WHICH IS TO BE INSTALLED BY CONTRACTOR.

B. This section includes factory designed, assembled, tested and packaged desiccant dehumidification units

C. The unit shall be designed specifically for outdoor mounting and have a clean rectangular silhouette.

D. The unit shall be designed for steel dunnage mounting.

1.2 PERFORMANCE

A. The unit shall be designed specifically to meet the unique dehumidification and ventilation requirements of this application.

B. Desiccant rotor shall be sized for full airflow capacity, without the necessity for bypass airstreams, unless required by specific project requirements.

1.3 SUBMITTALS

A. Data to be provided:

1. Certified fan-performance curves with system operating conditions indicated.2. Certified fan-sound power ratings3. Certified coil-performance ratings with system operating conditions indicated. 4. Motor ratings, electrical characteristics, motor and fan accessories5. Material gauges and finishes.6. Filters and their performance characteristics7. Dampers, including housings linkages, and operators8. Control components.9. Enthalpy rotor performance data with system operating conditions10. Desiccant rotor performance data with system operating conditions11. Include manufacturer detailing dimensions, required clearances, components, shipping splits, unit

weight, method of field assembly, and location and size of each field connection.12. Utility requirements: natural gas, electrical, etc…13. Airflow static pressure drops for each component.14. Owner and contractor responsibilities list that details field installation requirements to

communicate activities that are to be field coordinated, provided, and supplied by others.

B. Submittal Data Availability:

1. All submittal data shall be available electronically. Plan and elevation views of the units shall be in scale and shall be complete with internal scaled components.

1.4 QUALITY CONTROL

A. The unit assembly shall carry an ETL Label and be constructed in accordance to UL 1995 and ANSI Z83.8. All features and options shall be included in the listing, including controls shipped loose.

B. Manufacturer’s Qualifications:

1. Manufacturer shall have a minimum of 10 years experience producing substantially similar equipment, and shall be able to show evidence of at least 100 installations in satisfactory operation for at least 5 years.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Delivery of Units:

Page 208: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 2

1. Deliver units to the Site to ensure uninterrupted progress of the work.2. Comply with manufacturer’s recommendations for rigging of equipment.

B. Storage of Units:

1. Units that are stored in an outdoor environment prior to installation will require the Contractor to provide protection from outdoor weather elements.

2. Store all units in such a manner as to permit easy access for unit inspection and/or identification. Keep all units off the ground, using pallets, platforms, or other supports.

C. Acceptance at Site:

1. All boxes, crates and packages shall be inspected by Owner upon delivery to the Site. Owner shall note any damage or missing components on the Bill of Lading from the carrier at time of delivery. Owner shall also notify Manufacturer’s Representative in writing, if any damaged equipment or lost components exist.

1.6 WARRANTY

A. Manufacturer to warrant desiccant dehumidification unit to be free of defects in material and workmanship for 24 months from the date of factory shipment or 18 months from the date of start-up, whichever is shorter. Manufacturer shall only be liable under this warranty if the product is installed and used according to the directions furnished by the manufacturer.

PART 2: PRODUCTS

2.1 MANUFACTURERS

A. Basis of Design: CDI

B. Approved manufacturers:

1. Xetex2. Innovent3. Arid Ice4. Seresco5. Marcraft6. Semco

2.2 UNIT CONSTRUCTION

A. 2.5” Case Wall

1. Base frame fabrication to utilize a single frame construction for supporting the casing and internal components.

2. The casing walls and roof assemblies shall be constructed as a 2.5” thick wall. Wall design will not use through-metal construction. The exterior and interior components shall be completely independent of one another, free from thermal bridges or metal fastener connections of any kind, and shall make up the insulated self-supporting casing.

3. All casing penetrations shall be provided with a thermal break between the exterior and interior panels.

B. BASE FRAME CONSTRUCTION

1. Units to have an electrically welded structurally formed 12 gauge G-90 galvanized steel. All frames to be suitably reinforced and braced to permit the loading, shipping, unloading and rigging to the installation location. All frames are suitable for general handling of the completed sections without damage or misalignment to the external and internal components.

2. Lifting lugs sets shall be provided on the base. Lifting lug distance shall not exceed a distance of 100” on center.

3. The floor assembly shall be 16 gauge and 20 gauge G-90 galvanized sheet steel for the top and bottom of the floor deck, respectively. Urethane foam insulation 4” minimum nominal thickness shall be used to insulate the base. Minimum 4" deep 12 gauge formed channels shall be used in the floor for support. This floor shall sustain the equipment loading and normal maintenance loading for the unit.

Page 209: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 3

C. CASING CONSTRUCTION

1. Exterior wall panels shall be a minimum of 16 Gauge G-90 galvanized steel and shall be fabricated into self-framing seam type construction. Interior wall panels shall be a minimum of 20 Gauge G-90 galvanized steel and shall be fabricated into self-framing seam type construction. The exterior and interior panels combined, caulked and sealed, shall form a thermal barrier wall casing capable of having no other additional structural supports required.

2. Exterior roof deck panels shall be a minimum of 16 Gauge G-90 galvanized steel and shall have a minimum of 1 ½" standing seams. Each standing seam of the roof deck shall be securely fastened at intervals not exceeding 12 inches, caulked and sealed. Interior roof liners shall be a minimum of 20 Gauge G-90 galvanized steel and shall be designed to provide the roof structure and support. The roof liner deck shall be securely fastened at intervals not exceeding 12 inches, caulked and sealed.

3. All wall and roof assemblies shall be insulated with closed cell polyurethane expandable foam insulation. The foam insulation shall have an R-Value not less than R-6 per inch, and shall conform to DIN 4102.1 Class B2 flame spread and combustibility requirements. Minimum total R-value for the casing and walls to be 15.

4. All joints shall be caulked airtight with a sealant that is 100% Pure RTV silicone; suitable for temperatures in the range of -50°F to 450°F.

5. The exterior of the unit shall be made of G90 galvanized.6. Closures around all components, such as coils, dampers and filters, shall be provided and made

airtight with silicone caulk. Closures shall be a minimum of 16 Gauge G-90 galvanized steel and shall provide solid close-off inside of the unit housing walls.

7. Wall panels to use silicone caulk for sealing and adhesive properties. Gaskets shall not be used to seal wall panels.

D. ACCESS DOOR CONSTRUCTION

1. All process air access doors shall have a no thru metal design including both the door frame and main door panel assembly.

2. Access doors in the unit housing shall be provided to permit ready access to internal components. The access doors shall be provided with an inner sheet of a minimum of 24 gauge, G-90 galvanized steel to protect the insulation. The exterior of the access doors shall be a minimum of 24 gauge galvanized steel. The doors shall be designed, to swing against the fan static (outward on suction side, inward on discharge side).

3. The doors shall be provided with heavy-duty stainless steel hinges and heavy-duty keyed latches, operable from both the exterior and interior of the unit.

4. Extruded aluminum thermally broken frames around the doors are to be used. A continuous EPDM gasket is to be used on the access door frame for maximum air and water seal tightness. Gasket is to be field replaceable.

5. When access panels are furnished in lieu of access doors, access panels shall be fabricated of 16 gauge, G-90 galvanized steel. One access panel shall be mechanically fastened to the exterior casing and the other shall be mechanically fastened to the interior casing maintaining the thermal break.

2.3 ENERGY RECOVERY SYSTEM

A. Energy recovery rotors shall be rotary air-to-air heat exchangers having efficiency as listed in equipment schedules. The manufacturer shall submit performance data to demonstrate conformance to the schedules regarding capacity and efficiency. Wheels shall have a flame-spread rating of 25 or less and smoke-developed rating of 50 or less.

B. Energy Recovery Rotor

1. Total Energy Recovery Type shall be comprised of aluminum coated with 4A Molecular Sieve, non-migrating, water selective desiccant. Aluminum base material shall be a minimum of 70 microns (0.0027”) thick of type 5052 hardened aluminum alloy. Including coating, material shall not be less than 14 LBS/FT3 and media wall thickness shall not be less than 0.005”.

2. Media shall be corrugated with a flute height of 1.5 mm (0.091”) and flute width of 3.0 mm (0.118”), allowing for passage of 800 micron particles, and shall be rated to withstand intermittent exposure to 250 FDB without loss of performance or reduction in structural integrity.

Page 210: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 4

3. Media may be cleaned with mild detergent, water, compressed air, or low pressure steam (< 15 PSI). Rated lifetime shall not be less than 87,600 hours, and shall be defined by media performance < 90% of original capacity. Rotor performance shall be independently tested in accordance with applicable ASHRAE guidelines (Method of Test 84-91), and rated in accordance with ARI Rating Method 1060.

4. Flame resistance and smoke produced indices must also be independently tested in accordance with ASTM E-84 with results of less than 25/50.

C. Energy Recovery Rotor Cassette

1. Seals: Supply and exhaust air stream shall be isolated from each other by means of adjustable seals secured to the cassettes panels and duct dividers. Seals shall consist of a double layer of neoprene wiper seals, labyrinth or brush seals. Wiper and bush seals shall be installed in contact with the wheel flange in order to minimize leakage between the supply air and exhaust air system. Labyrinth seals shall be installed with a minimum gap between the seal and the wheel flange.

D. Energy Recovery Rotor Drive System

1. Wheel Support and Drive: The wheel shall be supported by ball bearings and driven by a belt around the outside of the wheel. The drive motor shall be appropriately sized to ensure operation. The gear-motor shall be factory mounted.

2.4 EXHAUST FANS AND MOTORS

A. Belt drive blowers shall be a minimum of Class 1, double inlet forward curved fans. The wheels shall be supported by two outboard bearings which shall be of a self-aligning, single row, deep groove ball type with eccentric locking ring, and shall be designed for at least 200,000 hours average life.

B. Blower shafts shall be solid ground and polished. The shafts shall not pass through their first critical speed when the unit comes up to the rated RPM. Shaft shall be coated with a rust inhibitor.

C. All V-belt drives shall be standard capacity, furnished in matched sets with reinforced rubber belts. The sheaves shall be of a cast iron type and shall be complete with companion type driver sheave on drives with three belts or more. All drives shall be complete with a split taper bushing.

D. The service factor of the drive set shall be not less than 1.25.

E. An adjustable motor base shall provide variation in center distance and shall be readily adjustable by means of screw adjustments. A locking nut, or similar device, shall be provided to secure the base in proper position.

2.5 BELT DRIVEN FAN MOTORS

A. All belt driven fan motors shall be premium efficiency open drip-proof (ODP).

2.6 SHIPPING SPLITS (OPTIONAL)

A. Shipping splits, are constructed of 12 gauge G-90 galvanized steel in a mating angle design on unit interior walls, roofs, and base. Unit sections shall be fastened together with 3/8 inch bolts 18" on centers. All fasteners caulk, and gaskets required shall be supplied and shipped with unit in a separate box.

2.7 OUTSIDE AIR INLET HOODS

A. Outside air source shall be furnished with either multiple or a single hood and bird screen which shall be sized for no more than 500 fpm of the 100% of the system outside air volume of the adjacent opening through unit casing.

B. Hoods and bird screen shall be manufactured of a minimum of 16 gauge, G-90 galvanized steel. “Chicken wire” is not acceptable.

2.8 DAMPERS

A. Damper frames and blades primarily shall be 16 gauge galvanized steel with plated steel linkages and shafts to ensure a long corrosion free life.

Page 211: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 5

B. The blades shall be a minimum of 16 gauge galvanized steel with a maximum single blade dimension of 7" x 48". Blades shall be of rigid design with minimal twisting, flexing or vibration at the design velocities.

C. Blade-to-blade linkage is concealed in the frame and out of the airstream to protect linkage as well as reduce pressure drop and noise. Linkage is engineered to accurately control each and every blade without need for adjustment.

D. Axles are 1/2 in. diameter square plated steel positively locked to the blades to eliminate slippage between blades and axles. Stainless steel bearings rotate in a polished extruded frame raceway.

E. Dampers shall have extruded vinyl blade seals and “arc” jamb seals which shall be flexible stainless steel compression type. Leakage shall not exceed 10 CFM at 4” W.C. differential pressure.

F. Damper to be provided with motorized actuator.

2.9 PRE-FILTERS

A. Air filters shall be medium efficiency ASHRAE pleated panels consisting of cotton and synthetic media blend, media support grid, and enclosing frame.

B. Construction

1. Filter media shall be a cotton and synthetic blend, lofted to a uniform depth, and formed into a uniform radial pleats. There shall be at least 10 pleats per linear foot for 2” thick filters.

2. A welded wire grid, spot-welded on centers and treated for corrosion resistance, shall be bonded to the downstream side of the media to maintain the radial pleat and prevent media oscillation.

C. Performance

1. The filter shall have a Minimum Efficiency Reporting Value of MERV 13 when evaluated under the guidelines of ASHRAE Standard 52.2.2007.

2. Initial resistance to 500 fpm airflow shall not exceed 0.28” W.C. for a 2” filter.3. The filter shall be classified by Underwriters Laboratories as UL Class 2.4. Manufacturer shall provide evidence of facility certification to ISO 9001:2000 or higher.

D. Filters shall be held in galvanized steel holding frames equipped with gaskets. Filter frames shall be a minimum of 16 gauge G-90 galvanized steel.

2.10 DX COOLING COILS

A. Coils shall be of face area, rows and materials as indicated on the schedule.

B. The steam heating coils shall be constructed of 0.020” 5/8” seamless copper tube mechanically expanded into die formed full height collars in the fins. Fins are to be 0.0075” thick aluminum.

C. The casing and tube sheets shall be a minimum of 16 gauge galvanized steel.

D. Coil tubes shall be pitched to promote drainage.

E. The coils shall have no more than 10 fins per inch.

F. Copper Tube Coils are standard and shall be tested under water at a minimum of 315 PSIG.

G. The maximum face velocity of the air passing over the coil shall not exceed 500 feet per minute if wet and 550 feet per minute if considered a dry coil.

H. The cooling coil drain pans shall extend beyond the coil headers and return bends. The depth of the drain pans shall be at least 1 1/2 inches and shall pitch toward the side of the unit. Drain pans shall be a minimum of 16 gauge 304 stainless steel and shall extend beyond the coil depth in the downstream direction of the airflow a minimum of 1/2 the fin height of the coil. An intermediate condensate drip pan shall be provided on all multiple height coils over 48” high and the intermediate drip pan shall extend a minimum of 6 inches in the downstream direction of the airflow. Each intermediate drain pan shall be piped, to within 2 inches of the bottom drain pan.

2.11 DESICCANT DEHUMIDIFICATION SYSTEM

A. Desiccant Rotor

Page 212: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 6

1. The desiccant shall be made “in-the-flute” encapsulating the fiberglass substrate.2. The rotor shall be both washable and non-shedding. Rotors shall be capable of withstanding

cleaning by vacuum cleaner, with a water or, water and detergent wash.3. The substrate shall be manufactured with a fiberglass matrix meeting the International Agency for

Research on Cancer (IARC) standards for non-respirable fibers.4. The fiberglass substrate shall provide the structural support for the desiccant. The fiberglass

substrate shall be combined with desiccant to form the dehumidifier rotor. The desiccant shall be self-bonding to the fiberglass substrate and to itself through the substrate voids filling in all the voids in the substrate and shall totally encapsulate the fiberglass.

5. The desiccant dehumidification rotor shall be assembled from smooth and corrugated sheets of fiberglass substrate interleaved in a winding to form the rotor creating a large number of axial passages through which the air flows

6. Where a face and by-pass arrangement is indicated the performance shall meet the dew point values of the mixed air downstream of the face and by-pass section.

7. Rotor surfaces shall be ground, polished smooth and coated for long seal life.8. Rated lifetime shall not be less than (87,600) hours and shall be defined by media performance

meeting >90% of original specification.9. Rotor media shall be tested to ASTM-E84 have result in Flame Spread and Smoke Developed

Indices of zero.

B. Desiccant Rotor – Cassette Frame

1. DH rotor cassette frames shall be manufactured from 304 tubular stainless steel. All welds shall be reasonably ground and dressed for appearance. Structural welds shall be continuous and non-structural welds shall be on 4” centers.

2. Cassette face panels and other sheet steel components shall be manufactured from 304 stainless steel material.

C. Desiccant Rotor – Drive System

1. DH Rotor Drives shall be equipped with harden carbon steel ANSI drive sprocket, nickel plated corrosion resistant drive chain and spring type automatic chain tension device.

2. For ease of maintenance and chain alignment the gear motor shall be fastened to a 304 stainless steel gear motor plate which is fastened onto the cassette frame with standard hardware.

3. The drive assembly shall be equipped with a rotation detection circuit which shuts down the dehumidifier and signals the operator through an indicating light on the control cabinet if the wheel is not rotating.

D. Desiccant Rotor – Seals

1. Seals are to be “Viton®”. Rotor seals are rated for lifetime use (87,600 hours). Rotor seals shall be rated for 400°F+ continuous temperature rating. Bulb type seals are not allowed.

2. Low friction tape is to be used as the complementary seal material to the Viton seal mentioned above. The tape shall have an operating temperature range from -65°F to 500°F.

3. If additional sealing material is needed in the rotor assembly it is to be made of 100% Pure RTV silicone is a one-component caulking material that has temperature ranges of -50°F to 450°F.

4. Rotor dividing seals contact the face of the Desiccant Rotor media to seal between the process and reactivation airstreams. Standard hardware shall fasten the dividing seals flanges to the cassette frame partitions and pop rivets shall not be used.

5. All other areas that have a potential for air bypass shall be RTV silicone sealed, this shall eliminate and ensure that no air bypasses the rotor cassette assembly.

E. Reactivation – Direct Fired Burner

1. The reactivation heat source shall be full-modulation direct-fired gas. The capacity of the burner shall be sufficient to provide scheduled performance.

2. The gas burner shall be suitable for burning with a modulating turn-down ratio of 20:1. The gas burner shall have stainless steel baffles and non-clogging gas orifices. The burner assembly and complete pre-piped manifold shall include main and pilot gas regulators, main motorized fuel valve, 2 main safety shut off valves, pilot solenoid valve, main and pilot gas hand valves and manually adjustable burner air flow profile plates. A butterfly type gas valve is not acceptable due to poor control characteristics.

Page 213: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 7

3. Pilot gas shall be automatically lit after a seven-second pre-purge timing by a spark rod that utilizes a 6,000 volt ignition transformer. After a proven flame by the flame rod, the main burner valve(s) open.

4. The gas burner shall be rated at no more than 390 MBH per foot of burner length, in order to limit flame length, and minimize the generation of carbon monoxide.

5. The control safety circuit shall include, but not be limited to: air flow proving device, high temperature limit switch, electronic primary flame safeguard with flame rod rectification, red alarm light to indicate flame failure, microprocessor rate controller, reactivation fan motor starter interlock and seven second combustion area pre-purge. Complete assemblies shall be pre-piped, wired, and tested.

6. Reactivation rate controller shall be as described below. (See Microprocessor Controller section)7. Single point reactivation leaving air temperature controls are not acceptable.8. The direct-fired burner shall have capacities as indicated on the schedule.

F. Reactivation – Outlet Tunnel

1. The outlet tunnel casing shall be double insulated wall constructed of a minimum of 16 gauge interior panels, exterior panels, interior tunnel flooring and 16 gauge interior liners. The interior tunnel flooring shall incorporate a pan with drains. The panels shall form a self-framing casing with no additional structural support required. All joints shall be caulked airtight with silicone sealant. The interior panels, interior liner and the interior tunnel flooring material shall be 304 stainless steel.

2. The outlet tunnel casing shall be insulated with 3.0# per sq. ft. rigid, rot-proof, non-combustible glass fiber insulation.

3. The fiberglass insulation shall conform to 25/50 (per ASTM E 84 and UL 723 and CAN/ULC S102-M88). Meets NFPA 90A and 90B.

4. All joints shall be caulked airtight with silicone sealant. 5. The outlet tunnel drain pan shall have a fabricated drainage connection protruding through the

floor for the purpose of condensation drainage to the unit exterior.6. Closures around all interior components shall be provided airtight. Closures shall be exceptions

but primarily of the same material used in the outlet tunnel interior and shall provide solid close-off inside of the outlet tunnel walls. No air bypass or leakage around the components will be allowed.

7. For ease of rotor shaft and bearing maintenance an access panel of the same material used in the tunnel exterior shall be provided and mounted in the bottom corner located by the rotor axis.

8. Reactivation outlet hood and bird screen are to be made of punched 16 gauge 304 stainless steel.

G. Reactivation – Fan and Motor

1. Reactivation air fan shall be single width, single inlet, and airfoil type direct drive wheel, class III, and fabricated of aluminum to minimize the potential for corrosion.

2. Fan inlet cone shall be of aluminum construction.3. Motors shall be TEFC, NEMA premium efficiency, at the scheduled voltage, 3 phase, 60 Hertz4. Motor horsepower shall be as indicated on the schedule.5. Fan and motor shall be dynamically balanced as an assembly.6. Reactivation motor shall be completely isolated from the reactivation air stream by means of a

shaft sealing plate.

H. Reactivation – Outlet Damper

1. Outlet system balancing damper is to be fabricated of 304 stainless steel material and consist of a single damper blade and a locking quadrant.

I. Microprocessor Reactivation Rate Controller (RRC) (Internal to unit DDC)1. The microprocessor controller shall control the unit’s reactivation rate, and safeguard functions. 2. Reactivation energy shall be controlled as follows:

a. Desiccant reactivation temperature shall be maintained at optimum temperature for maximum dehumidification performance irrespective of outdoor temperature or filter loading.

b. With diminished reactivation airflow (i.e. dirty filters) desiccant reactivation temperature shall be limited to prevent rotor overheat.

c. On gas reactivation units, as moisture load decreases, reactivation outlet temperature rises the microprocessor controller shall reset reactivation inlet temperature down as required to limit reactivation outlet temperature. Reactivation rate control that uses a single temperature sensor in the reactivation outlet airstream is NOT acceptable.

Page 214: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 8

d. Fail-Safe Mode: In order to preserve limited performance, on gas or electric reactivation units, if the desiccant reactivation inlet sensor fails the energy modulation shall be set to 50% or less and if the reactivation outlet sensor fails, desiccant reactivation inlet shall maintain a set-point of 260˚F.

e. On gas reactivation units, to prevent excessive heat on the rotor and seals the unit shall be equipped with a manually reset high temperature limit downstream of the reactivation heat source and upstream of the desiccant rotor. When tripped the reactivation heat source shall cycle off.

f. Adequate reactivation energy shall be proven via reactivation outlet temperature. If the reactivation outlet fails to achieve a minimum temperature set-point over a 15 minute period the controller shall signal a low reactivation outlet temperature warning. The unit shall continue to run.

g. Lack of desiccant rotor rotation shall be detected and shutdown initiated in the event of an abnormal condition.

h. On gas or reactivation units, the reactivation fan shall remain on for two minutes after the reactivation is disabled to allow for proper cool down of the reactivation tunnel.

2.12 SUPPLY FAN AND MOTOR

A. Belt Drive Plenum Fans

1. Belt drive fans shall be airfoil type plenum fans. 2. Fan inlet cone shall be of steel construction.3. The fan wheels shall be supported by two outboard bearings which shall be of a self-aligning, ball

bearing, pillow block type and shall be designed for at least 200,000 hours L50 life. The blower assembly shall be dynamically balanced.

4. Blower shafts shall be solid ground and polished. The shaft diameter shall be sized so that the maximum operating speed for the Class does not exceed 70% of the first critical speed and the shaft shall be coated with a rust inhibitor.

All V-belt drives shall be furnished in matched sets with reinforced rubber belts. The sheaves shall be of a cast iron type and shall be complete with companion type driver sheave on drives with three belts or more. All drives shall be complete with a split taper bushing. Smooth bore sheaves are acceptable for single and dual groove adjustable pitch sheaves.

5. Motors 7.5HP and smaller shall have drive sheaves that are adjustable type6. The service factor of the drive set shall not be less than 1.25.7. An adjustable motor base shall be provided.8. A piezometer flow measurement system shall be provided on all fans. It shall have pressure taps

plumbed to the exterior of the unit for proper system balancing and troubleshooting.

B. Fan Motors

1. Direct drive fan motors shall be NEMA premium efficient, TEFC.2. Belt drive fans motors shall be NEMA premium efficient, ODP.

C. 1” Internal Vibration Isolation

1. The blower, motor, and drive assembly shall be mounted isolation springs with a non-skid acoustical pad, locking screw and adjusting leveling bolt. The springs shall have a minimum of one inch nominal deflection. The isolation base shall be complete with hold down bolts and wood blocking to maintain the spring base in a rigid position for shipping.

2. On the inlet of the plenum fan shall be a minimum of 6" flexible ducting, rigidly fastened to the blower and the blower inlet closure.

2.13 INDIRECT FIRED HEATER SECTION

A. The Duct Furnace module shall be indirect fired and comply with the current edition of ANSI Z83.8 Standard for Gas-Fired Duct Furnaces and be a Recognized Component by Intertek Testing Services ETL.

Page 215: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 9

B. The Duct Furnace module shall employ patented in-shot gas burners with integral carryovers, a tubular heat exchanger assembly, a two speed draft inducer to provide for positive venting of flue gases, air pressure switches to provide proof of air supply for combustion, direct spark ignition of the gas burners with remote flame sensor to prove carryover across all burners, an automatic reset type high limit switch to limit maximum outlet air temperature to less than 250 of, manual reset flame rollout switches and a two stage redundant safety shut-off gas valve which regulates gas pressure to burner supply manifold.

C. Duct Furnace heat exchanger tubes (Type 409 Stainless Steel .044 Min. Wall thickness produced to ASTM A268) shall incorporate patented integral formed dimple restriction to eliminate noise associated with expansion and contraction of internal flueway baffles during heating cycles.

D. Duct Furnace modules shall be listed for application downstream of refrigeration and cooling systems and shall provide means for removal of condensate that occurs in the tubes during cooling operation.

E. Heat exchanger tubes shall have the dimpled restrictors formed to provide for an unobstructed drainage path and tubes shall be formed to provide a positive pitch to promote condensate drainage. Drainage shall be configured so that burners and burner surfaces are not exposed to condensate.

F. Duct Furnace shall incorporate a Direct Spark Ignition control module which is design certified by a recognized national testing agency.

G. The control shall incorporate a 30 second minimum pre-purge period prior to trial for ignition and a 0.8 second flame failure response time. The control shall provide for up to 3 ignition retrials, each preceded by an interpurge period. Control shall provide for automatic reset after one hour, to initiate additional ignition trials if lockout occurs during a call for heat. The control shall incorporate an LED indicator light to provide a flash code to identify the operating condition of the control and conditions preventing normal operation of the ignition system should they occur.

H. The Duct Furnace shall employ a two-stage control system capable of a proven low-fire ignition sequence that minimizes the noise associated with cold start conditions. On a call for heat by the two-stage room thermostat, the control system shall initiate a low fire start sequence at 55% of its maximum input rating.

2.14 VFD CONTROL

A. The unit shall be provided with a VFD for system balancing.

2.15 ELECTRICAL WIRING/LIGHTS/GFI

A. All electrical wiring shall be installed in thin wall EMT steel conduit. Use of lengths of flexible conduit will be permitted when rigid conduit is not applicable; however, all flexible conduit shall be liquid tight, and approved by Underwriter Laboratories

B. Where unit construction is such that wiring must be disconnected for shipment, terminal blocks in an accessible enclosure shall be provided at the section points for future field wiring.

C. Unit panel shall be provided with a terminal strip for ready connection of required external control wiring.

D. 26 Watt CFL Service Lights in Each Process Air Access Section, 1 Switch, 120v Power by Others

E. (1) 20 Amp, GFI Convenience Outlet for Each Unit, 120v Power Provided by Others

F. All work shall conform at the latest National Electric Code.

2.16 CONTROLS

A. The unit control panel shall be supplied with a “dead-front” style disconnect switch, control transformers, microprocessor controller, fuses, terminal strip and IEC motor starter’s with circuit breaker style overload protection. Fan/Blower motors shall be wired to the motor starters.

B. Terminal strip connection shall be available for customer’s smoke detection, fire protection, E-Stop, or “other fault” inputs to shut down the unit.

C. The controller shall include a built-in terminal display. From this display all critical unit functions and alarms may be monitored and adjusted. An optional duplicate display can also be connected for remote monitoring and adjustments of the desiccant unit.

Page 216: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 10

D. The controller shall include interface modules for connectivity to BAS systems using BACnet or Modbus protocols.

E. Where scheduled, unit shall include the following: space mounted CO/NO2 transmitter and a CO2 transmitter. Remote push button station and control logic shall be included to initiate fixed duration building contaminant purge mode. (shipped loose and installed by electrical trades)

F. Unit shall include a space mounted temperature and dew point transmitter. (shipped loose and installed by electrical trades)

G. Unit shall include a remote user interface. The interface shall be identical in function and format to the controller in the main control panel enclosure.

2.17 MARKINGS

A. The unit nameplate shall be 0.020" thick Aluminum with permanent fasteners. The nameplate shall be permanently engraved with: Unit model number, serial number, unit Full Load Amps, supply voltage, and filter schedule.

B. The unit shall be permanently marked with the equipment number as identified on the schedule.

C. Proper warning labels for high voltage and moving parts shall be permanently affixed to access doors and guards.

D. Advisory labels for filter access shall be affixed to applicable doors.

E. Electrical connection, lifting points, air connections, water supply/return, and drains.

F. Indication of correct rotation shall be affixed to all electric motors.

G. An electrical ladder diagram shall be permanently affixed inside of the electrical control panel. The schematic shall be specific to the project and not be a generic type encompassing features or options not present on the unit. The schematic shall include the fuse replacement values and types.

PART 3 - PERFORMANCE

3.1 UNIT PERFORMANCE

A. All information is given on a per unit basis.

B. Bid equipment to perform at an equivalent or greater level.

C. Dessicant Dehumidification Air Handling Unit #1:

a. Existing Unit to be replaced, Munters Drycool Model SAM30ME100GC.

b. Outside Ambient Summer Max: 89°, 102 gr/lb

Outside Ambient: 75°, 110 gr/lb

c. Conditioned space Summer Max: 78°, 64 gr/lb

Conditioned Space: 70°, 48 gr/lb

d. Supply Airflow: 30,000 cfm

e. Makeup Air: 19,210 cfm

f. Supply Fan: 30 hp, TSP 4.35” wg

g. Exhaust Fan: 15 hp, TSP 1.74” wg

h. Reactivation Fan: 3560 cfm, TSP 5.6”wg

i. Reactivation Heater: 750 MBtuh, Natural Gas, 6”-15” wg

j. Dessicant Wheel: 314.4 lb/hr moisture removal, 2.68” wg pressure drop

k. Enthalpy Wheel: 416.86 lb/hr, supply pressure drop .83” wg

l. Post Cooling Coil: Total/Sensible capacity 1333.22 MBtuh, 0.78” wg pressure drop

m. System Electrical: 460V/3 ph/60 Hz, Unit FLA 303, Unit MCA 314.7, Unit MOP 350, Disconnect 400A.

Page 217: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

DESSICANT DEHUMIDIFICATION UNITS238400- 11

D. Dessicant Dehumidification Air Handling Unit #2:

a. Existing Unit to be replaced, Munters Drycool Model AM30GG.

b. Outside Ambient Summer Max: 89°, 102 gr/lb

c. Conditioned space Summer Max: 78°, 64 gr/lb

Conditioned Space: 55°, 32 gr/lb

d. Supply Airflow: 10,000 cfm

e. Makeup Air: 10,500 cfm

f. Supply Fan: 25 hp, TSP 6.43” wg

g. Exhaust Fan: 7.5 hp, TSP 1.26” wg

h. Reactivation Fan: 5 hp, 3020 cfm, TSP 3.55”wg

i. Reactivation Heater: 750 MBtuh, Natural Gas, 6”-15” wg

j. Dessicant Wheel: 257 lb/hr moisture removal, 2.27” wg pressure drop

k. Enthalpy Wheel: 341 lb/hr, supply pressure drop .52” wg

l. Post Cooling Coil: Total/Sensible capacity 409.03 MBtuh, 0.41” wg pressure drop

m. System Electrical: 460V/3 ph/60 Hz, Unit FLA 46.1, Unit MCA 53.1, Unit MOP 80, Disconnect 60A.

END OF SECTION

Page 218: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 1

SECTION 26 05 00COMMON WORK RESULTS FOR ELECTRICAL

PART 1 - GENERAL

1.01 WORK INCLUDES

A. All labor, materials, equipment, tools and services required to perform all work and services for execution, installation and completion of all electrical work including all parts lists, operating instructions, wiring and control diagrams as shown on the drawings and as specified and completely coordinated with work of all other trades.

B. All supplementary or miscellaneous items, appurtenances and devices incidental to or necessary for a sound, secure and complete electrical installation, although such work is not specifically indicated.

C. Complete, in operative condition and to approval of Engineer, materials contemplated herein and shown on drawings.

D. Equipment, materials and accessories for electrical systems as shown and noted on the drawings including but not limited to the following:1. A complete rough-in system including conduit, outlet boxes, pull boxes, junction boxes, sleeves and

hangers.2. Complete wiring system.3. All cutting and patching.4. Wiring devices and coverplates.

a. Interconnecting power raceway and wiring for specified heating and refrigeration equipment, unless otherwise shown.

b. Interconnecting power raceway and wiring for specified ventilating equipment, unless otherwise shown.

c. Starters, controllers and interconnecting power and control raceway and wiring for specified pumps unless otherwise shown.

d. Flashing and sealing of all raceway roof penetration.

1.02 DELIVERY, STORAGE AND HANDLING

A. Manufacturer to prevent damage during shipment shall suitably package materials. Damaged materials will not be acceptable for use.

B. Store materials on site in clean, dry storage area; when outside, elevated above grade and enclosed with durable watertight wrapping.

C. Handle all materials carefully to prevent damage. Minor scratches, marks or blemishes to finish shall be repaired to satisfaction of Engineer.

1.03 QUALITY ASSURANCE

A. Regulatory Requirements:1. Permits: Arrange and pay for all permits, inspections and utility connections required.2. Comply with ANSI C1, National Electrical Code, 2011.3. Reference Publications:

a. American National Standards Institute, ANSI.1) C80.1 - Specification for Rigid Steel Conduit, zinc coated.2) C80.3 - Specification for Electrical Metallic Tubing, zinc coated.3) C80.4 - Specification for fittings for Rigid Metal Conduit and EMT.

b. National Electrical Manufacturers Association, NEMA.1) OS-1 - Sheet steel outlet boxes, device boxes, covers and box supports.2) 250 Enclosures for electrical equipment.3) WC-5 - Thermoplastic insulated wire and cable.4) WD-1, WD-5 - General Purpose Wiring Devices.5) FB-1 - Conduit and cable assemblies.6) KS-1 - Switches.

Page 219: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 2

c. Manufacturer's Catalog.1) Catalogs of specified manufactures current at date of contract documents are incorporated by

reference to same force and effect as if repeated herein. In conflicts between catalogs and project manual. Project Manual governs.

4. Provide all new materials, without blemish or defect, in accord with standards specified and NRTL (Nationally Recognized Testing Laboratory) listed or labeled.

1.04 STANDARDS

A. Provide materials, perform work and install materials in strict accordance with the latest requirements of the following:1. National Electrical Code (NEC) of National Fire Protection Association (NFPA).2. Other applicable codes and standards of NFPA.3. Factory Mutual System (FM).4. American National Standards Institute (ANSI).5. Occupational Safety and Health Act (OSHA).6. Federal, state and local codes, laws, ordinances; and rules and regulations of authorities having

jurisdiction.7. In case of conflict or disagreement between codes, laws, ordinances, rules and regulations or within

either document itself, the more stringent condition shall govern.8. Use electrical materials tested, listed and labeled by NRTL and bearing the NRTL label.

a. All fabricated assemblies, manufactured items or electrically operated equipment shall have NRTL approval or NRTL re-examination listing in every case where such approval has been established for the particular type of materials or devices in question.

1.05 DEFINITIONS

A. Wherever the words “the Contractor”, “this Contractor” or “Electrical Contractor”, appear in this section, they refer to the Contractor for Electrical Work.

B. The term “provide” includes such labor, methods, materials, equipment and transportation or other facilities required to complete the Contract, and the performance of all duties thereby upon the Contractor.

1.06 GUARANTEE

A. In entering into a contract covering this work, the contractor accepts the specifications and guarantees that the work will be carried out in accordance with the requirements of this specification or such modifications as may be made under the contract documents.

B. Contractor further guarantees that the workmanship and material will be of the best procurable and that none but experienced workmen familiar with each particular class of work will be employed.

C. Contractor further guarantees to replace and make good at his own expense all defects, which may develop within 1 year after final payment and acceptance by the Engineer, due to faulty workmanship or material, upon, receipt of written notification from the Owner.

1.07 JOB CONDITIONS

A. Existing conditions:1. In order to become familiar with the scope of the work involved, visit the existing site, before submitting

bid, and carefully examine the existing condition in order to have full knowledge and understanding of the conditions and restrictions affecting the performance of the work required. Include in bid all work which is reasonably inferred by the contract drawings and specifications, whether specifically shown or not, as a result of existing conditions, construction, irregularities and interferences which may affect work. No additional compensation will be considered for misunderstanding the conditions to be met.

2. The layout shown on the drawings is necessarily diagrammatic but shall be followed as closely as other work will permit. Changes from these drawings required to make this work conform to the building construction shall be made only with prior written approval of the Engineer. All proposed changes shall be shown on shop drawings. All measurements shall be verified by actual observation and all work shall fit in place meeting the approval of the Engineer.

3. The contractor shall provide openings required in new and existing construction that may be necessary for the installation of electrical work and all patching and workmen competent in the trade required, at the expense of the contractor shall do repairing. The contractor shall be responsible for arranging the work

Page 220: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 3

so that minimum cutting will be required. All rubbish and excess materials involved in such cutting shall be promptly removed from the site and disposed of by the contractor. Cutting through the floor or roof systems or load bearing walls shall be done only with the prior written approval of Engineer so as to avoid damaging the structural system.

4. Sequencing, scheduling:a. Confer with the contractor regarding the location and size of conduits, equipment, rough-in openings

and special architectural treatments in order that there may be no interferences between the installation or the progress of the work of the contractor on the project. The order of space preference shall be as listed above.

b. In the case of interconnection of the work of two or more contractors, verify at the site or on shop drawings all dimensions relating to such work. All errors due to the failure to so verify any such dimensions shall be promptly rectified.

c. All line voltage wiring and final connections to complete mechanical systems shall be provided by the Electrical Contractor. All electrical conduit, wire, and connections relating to mechanical equipment controls and all wiring associated with starter holding coils, shall be the responsibility of the contractor installing the mechanical equipment unless otherwise indicated on the drawings. The contractor installing the mechanical equipment shall be responsible for magnetic motor starters where such starters are part of the control package of the equipment supplied. All other starters shall be furnished and installed by the Electrical Contractor.

d. Access panels, in walls or ceilings, required for access and maintenance shall be provided by the respective contractor. Access panels are not required in areas where the ceiling system is lay-in tile; however, sufficient space must be available in and through the ceiling system to allow maintenance and adjustment of equipment. Access panels shall be approximately 15 inches by 18 inches wherever possible and shall be provided with flush trim and an allen key operated cam lock fastener. Karp, Milcor, or Bilco shall manufacture panels.

e. Items of equipment may be specified in the singular however, provide and install the number of items of equipment as indicated on the drawings and as required for a complete system.

f. Each contractor shall provide excavating, pumping, backfilling, and compacting required for the installation of their respective work as shown on the drawings.

g. Equipment and devices furnished and installed by electrical contractors, which have factory prime coat, or final surface finish shall be replaced, repaired or refinished if defective or damaged during installation.

h. Arrange all work so a minimum period of interruption or outages will occur in the temporary or permanent transfer of services as required for all electrical revisions. Not less than 10 Day notification to the Owner shall be required before approval will be granted for any disruption of gas, electric, or telephone services. The outage request shall include the extent of the work to be done, length of outage time required, and the time at which the outage is to begin.

i. Submit a "Sequence of Work Schedule" in respect to all temporary and permanent utility and service cutovers after final determination. This schedule shall be submitted for approval to the Engineer. The submittal shall designate priority order, service or utility affected, date of cutover, and time of day to start and finish.

PART 2 - PRODUCTS

2.01 RACEWAYS AND CONDUIT

A. Electrical Metallic Tubing (thin wall conduit, EMT)1. All electrical metallic tubing shall be hot dipped galvanized coated, bear a NRTL label and shall conform

to Federal Specifications WW-C-563, ANSI C80-3, and UL 797.2. Allied Tube and Conduit Corp., Republic Steel Corp., Wheatland Tube Co., Southwire Co. shall

manufacture all electrical metallic tubing, or Engineer approved equal.

B. Rigid Steel Conduit1. All rigid steel conduits shall be hot dipped galvanized coated plus a secondary coat with galvanized

threads bears a NRTL label and shall conform to Federal Specifications WW-C-581d, ANSI C80-1.2. Allied Tube and Conduit Corp., Republic Steel Corp, Wheatland Tube Co., Southwire Co. shall

manufacture all rigid steel conduits, or Engineer approved equal.

C. Intermediate Metal Conduit (IMC)1. Intermediate metal conduit shall be hot dipped galvanized coated; galvanized coated threads bear a

NRTL label and shall conform to a NRTL standard for IMC.2. Allied Tube and Conduit Corp., Republic Steel Corp., Wheatland Tube Co., Southwire Co. shall

Page 221: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 4

manufacture intermediate metal conduit or Engineer approved equal.

D. Flexible Steel Conduit1. All flexible steel conduits shall be hot dipped galvanized coated bears a NRTL label and shall conform to

Federal Specifications WW-C-566C.2. Triangle PWC, American Flexible Conduit Co., Inc., Anaconda Metal Hose, shall manufacture all flexible

steel conduits or Engineer approved equal.

E. Liquid-tight Flexible Steel Conduit1. All liquid-tight flexible steel conduit shall be interlocking flexible galvanized steel conduit with a special

polyvinyl chloride covering extruded over the flexible conduit to make the conduit liquid-tight resistant to moisture, oil, chemicals and corrosive fumes.

2. Anaconda Metal Hose, O-Z/Gedney, Triangle PWC shall manufacture all liquid-tight flexible steel conduits, or Engineer approved equal.

F. PVC Plastic Conduit1. All PVC conduits shall be schedule 40 heavy wall duct. Conduit shall be composed of high impact PVC

(Polyvinyl Chloride-C-200 compound) and shall conform to industry NEMA Standards and be NRTL listed for underground and exposed use. Material shall have tensile strength of 7,000 psi at 73.4°F, flexural strength of 11,000 psi, compression strength of 8,600 psi, and minimum wall thickness in various sizes.

2. All conduit fittings, couplings, terminal adapters, junction boxes and necessary fittings shall be of the solvent welding material.

3. Carlon, Can-Tex, Triangle PWC Inc., shall manufacture all PVC conduits or Engineer approved equal.

2.02 CONDUIT HANGERS AND SUPPORTS

A. Surface Mounted Conduits1. Rigid steel, IMC and EMT conduits 1 inch and smaller shall be supported with hot dipped galvanized one

hole steel pipe straps.2. Rigid steel, IMC and EMT conduits 1 1/4 inches and larger shall be supported with hot dipped galvanized

one hole malleable iron pipe straps with pipe spacers.3. Raco, Efcor, T & B, Appleton shall manufacture all pipe straps, or Engineer approved equal.

B. Suspended Conduits1. Individual rigid steel, IMC and EMT conduit 1 inch and smaller shall be supported with conduit clips of

high carbon spring steel or zinc plated steel and support 100 pounds static load. Conduit clip shall be provided with 1/4” 20 threaded impression for attachment to 1/4 inch 20 threaded rod.

2. Individual rigid steel, IMC and EMT conduit 1 1/4 inches and larger shall be supported with stamped steel conduit clamps with 1/4 inch 20 bolt and nut and support 150 pounds static load. Provide conduit clamps with 3/8 inch 16 threaded boss for attachment to 3/8 inch 16 threaded rod.

3. Support two or more rigid steel, IMC or EMT conduits adjacent to each other by 1 5/8 inches by 1 5/8 inches metal framing channel with minimum of two 1/2 inch 13 threaded rod at each end. Attach conduits to metal framing channel with electro-galvanized split pipe clamps with screw and nut.

4. Raco, Efcor, T & B, Appleton shall manufacture conduit clips and clamps, or Engineer approved equal.5. Unistrut, Super Strut, Kindorf shall manufacture metal framing channel and split pipe clamps, or Engineer

approved equal.6. Conduit shall not be supported from plumbing lines or ductwork.

C. Anchors1. Toggle bolts or spider type expansion anchors shall be used for hollow masonry.2. Lead expansion anchors or preset anchors shall be used for solid masonry.3. Self-drilling anchors or preset anchors shall be used for concrete.4. Machine screws, bolts, self-tapping screws or welded studs shall be used for metal.5. Wood screws shall be used for wood.

2.03 CONDUIT FITTINGS

A. All conduit fittings and box connectors shall be strong in construction and shall be of such material and finish as not to cause any chemical reaction between itself and the conduit or outlet box which it is fastened or supported.

B. All conduit fittings and box connectors shall be listed by a NRTL.

Page 222: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 5

C. Insulated throat fittings are only required on conduits 2” and larger.

D. All conduit fittings, box connectors and lock nuts shall be of steel or malleable iron materials.

E. Fittings for EMT shall be set compression type, rain-tight and concrete-tight. Connectors, couplings, locknuts and other fittings for rigid steel heavy wall and IMC conduit shall be threaded type.

F. Connectors specified in this paragraph can be zinc plated steel in lieu of malleable iron.

G. Liquid-tight flexible conduit connectors shall be steel or malleable iron compression type with insulated throat and “O” ring assembly.

H. Fittings for flexible conduit or liquid-tight flexible conduit shall be of the straight 45 degree or 90 degree connectors and approved for grounding purposes.

I. Provide expansion joint fittings where expansion joints are shown on architectural drawings.

2.04 BOXES AND COVERS

A. All junction boxes pull boxes, fixture outlet boxes and switch boxes shall be listed by a NRTL.

B. All boxes and covers shall meet all requirements of the National Electrical Code.

C. All boxes and covers shall be made of code gauge steel.

D. All boxes shall be of proper size and shape for all conduits and conductors entering them.

E. Install device boxes with bracket attached to box and wall stud to eliminate movement of box in wall.

F. All boxes installed in poured concrete, block, brick or tile shall be masonry type.

G. All multiple gang switch boxes of more than three-gang shall be solid gang box.

H. Surface mount boxes on the ceiling are note required to be FS or FD type boxes. Stamped steel boxes are acceptable for boxes on the ceiling.

II. Where two or more conduits enter a box, the minimum size of boxes shall be 4 inches by 4 inches by 1 1/2 inches minimum depth. For single device installation, install square cut single device cover.

J. Install all device boxes with square cut device covers for number of devices required.

K. All boxes shall have tapped hole for 10-32 ground screw.

L. Raco, Steel City, Appleton shall manufacture boxes and covers, or Engineer approved equal.

2.05 CABLE AND WIRE

A. All wire shall have copper conductors and be listed by a NRTL.

B. Service entrance conductors shall be 600 volts insulation type XHHW-2 90°C. All other wire shall be 600 volts insulation type THWN 90°C insulation for sizes No. 6 to 500 MCM and type THHN 90°C insulation for sizes No. 12 to No. 8.

C. Under ground wire to pole mounted light fixtures shall be type USE in conduit.

D. Provide long barrel, NEMA 2 hole copper compression connectors for all cables connected to the padmounted transformer. Make all connections with stainless steel hardware.

E. All pulling lubricants shall be water based, no exceptions.

F. Minimum wire size shall be No. 12 except for internal fixture wire that shall be minimum size of No. 14 type AF, CF or TFN, 300 volt.

G. All wire (excluding fire alarm and low voltage wiring) shall be stranded, including #12 AWG and #10 AWG

Page 223: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 6

branch circuit wiring.

H. All branch circuit wiring and feeder cables for circuits over 20 amperes shall be sized as noted on the drawings. If size is not specifically noted, size all branch circuit wiring and feeder cables in accordance with the National Electrical Code.

I. Cable and wire not installed in conduit shall be #12 AWG SO or SJO type grounded cord. Cord shall terminate at junction boxes and devices with strain relief cord grids.

J. Triangle, Crescent, Colleyer, and General Cable shall manufacture all wire, or Engineer approved equal.

2.06 METAL CLAD CABLE

A. MC cable is not allowed.

2.07 ELECTRICAL WIRING DEVICES

A. All devices are specified as having black finish in wood, white finish if in drywall. The Engineer reserves the right to change the color.

B. Furnish all special outlets with mating caps with cord grips.

C. Schedule of all electrical devices: 1. Single Pole Switch - 20 amperes at 120 volts

a. Hubbell DS120 (P&S and Plug tail approved equal)2. Three Way Switch - 20 amperes at 120 volts

a. Hubbell DS320 (P&S and Plug tail approved equal)3. Four Way Switch - 20 amperes at 120 volts

a. Hubbell DS420 (P&S and Plug tail approved equal)4. Duplex Convenience Outlet - 20 amperes at 120 volts

a. Hubbell DR20 (P&S and Plug tail approved equal)5. Duplex Convenience Tamper Resistant Outlet - 20 amperes at 120 volts

a. Hubbell D20TR6. Duplex Convenience Outlet - GFI - 20 amperes at 120 volts

a. Hubbell GF20

D. Forward submittals to Engineer for review.

2.08 WIRING DEVICE PLATES

A. All device plates shall be furnished with proper openings for the device with which it is being used. Where required, multiple gang plates for correct combination shall be used.

B. Device plates shall fit tight against the finished walls and shall completely cover the openings in the walls for the boxes.

C. Device plates shall be attached and adjusted so they finish straight and level.

D. Where more than one light switch is gained or a light switch and outlet are installed in a two gang box, install multiple gang device plates with proper openings.

E. Provide 1/2 inch raised galvanized device covers where used for exposed conduit work.

F. All device plates shall be black if located on wood and stainless steel if located on drywall, with the proper openings for the device with which they are being used.

G. All device plates for exterior weatherproof outlets and switches shall be lockable. Cover shall meet NRTL WDL “in use” listing requirement. Cover shall be suitable for standard boxes or FS type boxes.

H. Mounting screws for all plates shall have the same finish as the plate.

I. The same manufacturer shall furnish all device plates as devices for proper color match except stainless steel covers.

Page 224: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 7

J. Forward submittals to Engineer for review.

2.09 SEALS

A. Fire Seal:1. Seal penetrations of fire-rated walls, floors or ceilings by raceways for compliance with NEC 300-21. Fill

void around raceway. Sleeves shall be heavy wall steel pipe, anchored to building construction and finished plug with wall or ceiling. Fire stop material shall be Dow Corning #-6548 Silicone RTV Foam, Chase Technology Corp, CTC PR-855 fire resistant foam sealant, 3M 303 Fire Barrier, T & B S-101 Fire Barrier or Nelson Flameseal.

2. Must be listed as part of a NRTL approved assembly.

B. Water Seal:1. Seal penetrations of perimeter walls or floors below grade to prevent entry of water. Use materials

compatible with wall or floor construction and approved by Engineer.2. Seal all conduit penetrating air handling units air tight including conduit installed by the air handling unit

manufacturer.

PART 3 - EXECUTION

3.01 SPACE PREFERENCE

A. Carefully verify and coordinate the location and level of all lines. Run preliminary levels and check with all other contractors so that conflict in location may be avoided.

B. If conflicts occur, the following preference schedule shall be followed:1. Recessed electric fixtures2. High-pressure duct work3. Soil and waste piping4. Domestic water piping5. Low-pressure ductwork6. Domestic water storm and vent lines.7. Electric conduits

C. No other work shall have preference over plumbing lines below fixtures.

D. No other work shall have preference over conduit above or below electric switchgear and above or below panels.

E. No piping conveying fluids shall be provided directly over electrical, communications or elevator equipment.

3.02 FIELD CORRECTIONS AND CHANGES

A. Carefully and accurately record on field set of drawings, any deviations or changes in location of conduit, wiring and/or equipment made in the field and shall keep the Engineer informed on all deviations and changes.

B. At the completion of the job, furnish the Engineer three complete sets (not the field set) of drawings indicating these deviations or changes. Extra sets of drawings will be provided to the contractor for this purpose. Any changes in the exterior work shall be recorded by dimension.

3.03 LOCATION OF EQUIPMENT

A. The approximate location of all equipment is shown on the drawings.

B. The Engineer reserves the right to change the location of all equipment 5 feet in any direction without these changes being made the subject of an extra charge provided such changes are made before final installation.

3.04 LINES AND LEVELS

A. Determine all grades, maintain necessary lines and levels throughout the progress of the work, and assume full responsibility for their correctness. Where levels are indicated on the drawings, work shall be installed at those levels unless prior written approval to change is obtained from the Engineer.

Page 225: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 8

3.05 CLEANING

A. Upon completion of the contract all remaining materials and rubbish shall be removed from the building and premises and the work areas shall be left clean and free from stains, mortar, paint spots, etc.

B. All switches, controls, and safety devices shall be clearly and permanently marked with embossed or printed plates as to purpose and as to operation and shall be tested in the presence of the Owner's designated representative to insure that their function and purpose is understood.

C. Upon completion of the work, put systems into service maintaining responsibility for the equipment during all testing operations including turning on and off of such apparatus.

3.06 OPENINGS IN NEW CONSTRUCTION

A. Openings required in new construction for Division 26 Work will be provided by the General Contractor at the request of and in accordance with information furnished by the Electrical Contractor. The General Contractor will advise the Electrical Contractor in advance so that he may lay out the required openings. If said Electrical Contractor fails to lay out required openings, he shall be financially responsible for the necessary cutting, patching and repairing. The General Contractor will do the patching and repairing.

3.07 WALL AND FLOOR SLEEVE INSTALLATION

A. Set all wall and floor sleeves during the construction of the portion of the new construction through which the piping is to pass.

B. Provide sleeves of black iron pipe and of proper size to accommodate raceway. Install sleeves flush with walls and ceilings. Coordinate locations of sleeves with other trades to avoid interferences with their work.

C. Anchor all sleeves properly to the building construction.

D. Set floor sleeves plumb, wall sleeves level and center all piping in sleeves.

E. Care shall be taken to set sleeves in formwork and check all dimensions before concrete is poured.

F. Extend floor sleeves in finished areas 1/2 inch above finished floor and neatly level top of sleeve.

G. Finish all wall sleeves flush with wall lines unless otherwise specified.

H. Where sleeves occur in exterior walls above grade, caulk sleeves with sealant.

I. Where sleeves occur in exterior walls below grade, caulk sleeves with oakum and lead wool.

J. Openings between sleeves and conduit through fire or smoke barriers shall be closed with fire stop material to maintain fire or smoke barrier rating.

K. All occupied and unoccupied conduit sleeves in closet shall be fire stop after cable or conduit is in place. Occupied conduit sleeves shall be fire stopped with fire stop material and unoccupied conduit sleeves shall be fire stopped with metal caps on both ends.

3.08 PROTECTION OF WORK

A. Protect work from damage by keeping all conduit and boxes capped and plugged or otherwise protected. This includes damage by freezing and/or stoppage from building materials, sand, dirt or concrete.

3.09 INSTALLATION

A. Coordinate with other contractors engaged in project. Execute work in a manner not to interfere with other contractors or Owner's operation.

B. Coordinate work with other contractors regarding location and size of pipes, raceways, ducts, openings, switches, outlets, so there is no interference between installations or of progress of any contractor.

C. Install all equipment with ample space allowed for removal, repair, or changes to equipment. Provide ready

Page 226: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 9

accessibility to removable parts of equipment and to all wiring without moving equipment installed or already in place. Provide access panels for all devices installed above non-accessible ceilings or within walls or partitions.

D. At project completion, clean all equipment to the original finish. Remove all shipping labels.

E. Provide touch-up painting of all equipment marred in any way during shipment or installation.

3.10 INSTALLATION OF RACEWAYS AND CONDUITS

A. All raceways shall be concealed in wall construction and/or above ceiling construction except in mechanical equipment rooms, where it may be exposed at the ceiling or on walls.

B. There shall not be any branch circuit conduits installed horizontally in the concrete floor slabs throughout the building, except where specifically shown on the drawings.

C. In mechanical and electrical equipment spaces, expose ceiling outlets and conduit with due consideration to ventilating ducts and mechanical piping. Where numerous ducts occur, install conduits and outlets after ventilating ducts. Puncturing of ductwork or hanging equipment such as light fixtures, ceiling hangers, conduit, from ductwork, is prohibited, unless specifically noted otherwise.

D. Lay out all partitions on the project, for proper rough-in locations of all boxes and conduits. Verify all partition locations, door swings, cabinet locations before roughing in, and make any/all changes necessary to ensure that all switches, outlets, systems equipment, rough-ins are located properly. Any changes necessary in locations and rough-ins, due to a partition change and this contractor's failure to coordinate and verify same, shall be made.

E. The routing of conduit shown on the drawings is diagrammatic only, and this contractor shall install conduit as required to complete the systems so as not to interfere with other trades in both elevation and location.

F. The location of all conduit, boxes, fixtures, etc., in all areas finished and unfinished shall be coordinated.

G. Route conduit through roof openings for piping and ductwork where possible. Provide flashing making waterproof joints where conduits pass through roof or roofing membrane.

H. Provide conduit expansion joints at building expansion joints for conduit runs 1 1/2 inches and larger. Provide conduit expansion joints or flexible conduit connection at building expansion joints for conduits less than 1 1/2 inches.

I. Conduit shall be a minimum of 3/4 inch unless otherwise noted on the drawings.

J. All conduit bends shall be long radius with not more than the equivalent of three 90-degree bends between pull points.

K. Provide all open ends of conduit with bush caps to exclude any foreign material during construction.

L. All conduits installed in or under concrete or underground shall have joints sealed to exclude all water or other foreign material.

M. Coordinate the installation of all conduits in mechanical equipment spaces or where large amounts of ductwork and piping are present, with the other contractors so as to avoid interferences.

N. Unless otherwise noted on the drawings, size all conduits according to the National Electrical Code.

O. Install all exposed conduits parallel or perpendicular to adjacent walls, ceilings or floors.

P. All conduit couplings and fittings shall be made up wrench tight.

Q. Make all conduit systems mechanically and electrically continuous from source of current to all outlets, and ground in accordance with the National Electrical Code.

R. Where building construction or other conditions make it impossible to use standard threaded couplings, install watertight threaded unions.

Page 227: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 10

S. Install rigid steel conduit for the following:1. All conduit in poured concrete construction (unless noted as PVC).2. All conduit underground (unless noted as PVC).3. All conduit exposed in exterior areas.4. All conduit installed through foundation or basement wall, below grade, to a minimum of 10'0” beyond

wall.5. All service entrance conduit and all exterior conduit larger than 2” trade size.

T. Install electrical metallic tubing (thin wall) conduit for the following:1. All conduits in block, brick, tile or stud walls.2. All feeders for panelboards and distribution equipment.3. All conduit exposed in interior areas.

U. Install flexible steel conduit for the following: 1. Final connections for all recessed lighting fixtures (fluorescent and incandescent).2. All vibration generating equipment except where flexible liquid-tight is specifically called for.3. A maximum length of flexible steel conduit shall be limited to 6'0”.

V. Install liquid-tight flexible steel conduit for the following: 1. Final connections to all motors, except exhaust fans in ceiling space and wall 1/8 horsepower and less.2. All vibration generating equipment exposed to exterior conditions.3. Maximum length of liquid-tight flexible conduit shall be limited to 6'0”.

W. Install PVC conduit for the following:1. All conduit for underground exterior circuits 2” and smaller. PVC conduit shall be complete with all

accessories, such as, couplings, male and female adapters, expansion couplings, elbows and support straps. Install one expansion coupling for every 100 feet of run, or in any run solidly connected at both ends. Use solvent welding cement recommended by the duct manufacturer, for all conduit terminations at fittings of all types to seal and secure the connections. Support the plastic conduit horizontal conduit runs 4 feet on center and vertical runs every 8 feet.

X. Communications1. Minimum communications raceway size to be 1" conduit, unless otherwise noted on drawings.2. Provide one conduit from each communications box. Horizontal conduit runs between wall boxes are not

allowed.3. Provide insulated grounding bushings on end of conduit.4. Provide flush two-gang box with single gang plaster ring for each communications outlet or as noted on

drawings.5. Conduit bends to be no less than 10 times outside diameter of conduit.6. Conduits shall have no more that (2) 90 degree bends or total of 180 degree bends or offsets without a

pull box. Pull boxes shall be installed in accessible locations.7. No underslab installations allowed.

3.11 RACEWAY SUPPORTS AND HANGERS

A. Securely fasten raceways in place and support from ceiling or walls.1. Maximum Spacing of Supports Material

a. 1/2" through 1” trade size 6 feetb. 1 1/4" through 1 1/2" trade size 8 feetc. 2” through 4” trade size 10 feetd. Flexible metal conduit 4 1/2 feet

B. Support IMC or EMT conduit within three feet of every outlet box, junction box, pull box, cabinet or termination. Support flexible conduit within 12 inches of every outlet box or fitting.

C. Support vertical runs or conduits at each floor level and at interval not to exceed ten feet.

D. Support conduits by pipe straps, wall brackets, hangers, or ceiling trapeze. The use of perforated iron on wire for supporting conduits is prohibited. Fasten with wood screws or screw nails to wood; by toggle bolts on hollow masonry units, by concrete inserts, or expansion steel conduits on steel. Do not weld conduits or pipe straps to steel structures unless specifically indicated.

E. The load applied to fasteners shall not exceed one-third the proof test load of the fasteners.

Page 228: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 11

F. For fasteners attached to concrete, use vibration and shock resistant.

G. In partitions of light steel construction, use sheet metal screws.

H. Conduit shall not be supported from suspended ceiling hangers, ductwork or plumbing lines.

I. Where two or more conduits one inch trade size or larger run parallel, trapeze hangers may be used consisting of threaded solid rods, washers, nuts and galvanized “L” angle or channel iron. Individually fasten conduits to the cross member of every other trapeze hanger with one hole straps or clamp backs with proper size bolts, washers and nuts. When adjustable trapeze hangers are used, use U-bolt type clamps at end of conduit runs, at each elbow and at each third intermediate hanger to fasten each conduit.

J. Make hangers of durable materials suitable for the application involved. Applied loads shall not exceed one-third of their loading capacity.

K. Fabricate all screws, bolts, washers and miscellaneous hardware used for conduit supports from rust-resisting metal. Trapeze hangers shall have hanger assemblies' protected galvanized finish.

3.12 INSTALLATION OF BOXES

A. Provide pull boxes, junction boxes or outlet boxes as shown on the drawings and/or in all runs of conduit having the equivalent of three 90 degree bends or more than 100 feet in length.1. Communications conduit runs shall have no more than 100 linear feet and/or no more than two (2) 90-

degree bends without a pull box.2. Do not provide pull box in lieu of 90-degree bend for communications cable.3. LB type fittings are not to be used for communications cable.

B. Location of outlets shown on the drawings is diagrammatic only. Coordinate exact location of outlets with architectural details, equipment connection requirements and all ceiling outlets with due consideration to clearance from ventilating ducts and piping.

C. Locations of all junction boxes shall be verified on the job.

D. All junction boxes shall be installed so that they are accessible by removing an access door, recessed fixture, coverplate, etc.

E. Where flush coverplates are required in finished areas, they shall be painted to match adjacent wall or ceiling finishes.

F. All junction boxes, other than for power or lighting, shall be identified as to their usage; such as, television, telephone, door security, fire alarm, etc., by permanently attached labels on the inside or outside of the coverplate.

G. Power and communication outlets shall not be installed in the same junction box.

3.13 METHOD OF WIRING

A. Install all the conductors in conduits.

B. Equipment and devices installed and not constructed with cases especially suited for mounting and enclosing all live parts shall be installed in metal cabinets.

C. A complete metal raceway or enclosure shall be provided for all circuiting throughout the extent of the systems specified.

D. Make conductors continuous from outlet to outlet. Do not make splices except in outlet or junction boxes. Make all feeder cables continuous from origin to panel or equipment terminations without running splices in intermediate pull or boxes, unless specifically indicated on the drawings or approved in writing by Engineer.

E. Blow out and swab all conduit until all moisture and grit is removed before any wires are pulled or installed. Use water-based pulling lubricant, compatible with insulation and covering, that will not cause deterioration of insulation or jacket covers of cables on conductors. Use pulling lubricant recommended by wire manufacturer.

Page 229: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 12

F. Provide each cable or conductor in panels, pullboxes or troughs with a permanent pressure-sensitive label with suitable numbers or letter for easy identification. Identify control wires at each end and in junction boxes with designated wire numbers corresponding to control schematic drawings.

G. Provide wires and cables entering equipment or panels with enough slack to eliminate stretched, angular connection. Neatly arrange wiring, bundle and fan out to termination panels. Make minimum bending radius for conductors in accord with National Electrical Code.

H. Support all conductors in vertical raceways in accord with National Electrical Code.

I. Leave at least six-inch loops or ends at each outlet for installation of devices or fixtures. Roll up all wires in outlet boxes not for connection to fixture or device at that outlet, connect together and tape.

J. Size all branch circuit wiring for circuits over 20 amperes as shown on the drawings and/or as required by the National Electrical Code. All home run branch circuit wiring from the first outlet, fixture or device on 120 volt, 1 phase, or 277 volt, 1 phase circuit to the panelboard shall conform to the following wire sizes for amp circuits unless otherwise noted on the drawings:1. 120-VOLT CIRCUITS

a. 0 to 50 feet #12 wireb. 51 to 100 feet #10 wirec. 101 to 150 feet # 8 wired. 151 to 200 feet #6 wire

K. Clarification to the color-coding of conductors is as follows: For all voltages and systems equipment grounds shall be green, isolated grounds shall be green with yellow stripe or with yellow tape bands and travelers for 3-way switches shall be violet.

L. At the Electrical Contractor's option, the three phase power circuits and feeder cables can be installed with color-coded conductors or with three conductors of the same color. If they are installed with the same color of insulation, mark with colored tape in the panelboard and starter.

M. Phase all distribution equipment left-to-right, A, B, and C for continuity of phasing throughout the installation.

N. All stranded cables shall terminate into mechanical type or compression type lugs at termination points.

O. Neatly group all circuits in all distribution equipment and tie with Seine Twine, Ty-Rap or Wrap Tabs.

P. Special care shall be taken to balance connections of circuit wires on different phases at the lighting panelboards using distinguishing colors for identifying the particular phase on which the circuit belongs.

Q. In general, lighting and outlet circuits shall distribute from single pole 20-ampere breakers, 2 wire with solid neutral. Where noted on drawings, run single phase or 3 phase power circuits from two or three pole breakers.

R. A separate neutral conductor shall be pulled for each phase conductor for all 120 volt and 277 volt branch circuits. Common neutrals are not allowed. Provide color tracer matching phase conductor.

3.14 WIRING JOINTS

A. Joints in conductors shall be as few in number as practicable and where they are necessary they shall be mechanically strong, well made and shall provide complete electrical contact.

B. Joints shall be so made that they have an electrical resistance not in excess of that of two feet of the conductor.

C. Make all branch circuit joints for wire up to and including No. 10 AWG with expandable steel spring and polypropylene body type connectors and wire nuts manufactured by Ideal, Scotch, Buchanan or Engineer approved equal.

D. Make all wire splices in wire No. 6 and larger with mechanical compression crimp type connectors of proper size and wire configuration. Cover all connectors with a minimum of three layers of 600 volts tape or heat shrinkable insulation equivalent to 150 percent conductor insulation.

E. Neutral conductors in outlet boxes at receptacles shall be jointed and pigtailed to the outlet. The removal of a receptacle from the circuit shall not affect the continuity of the neutral conductor.

Page 230: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 13

3.15 HEIGHTS OF WALL SWITCHES AND RECEPTACLES

A. Determine the exact height of each light, receptacle outlets, and outlet boxes on the premises and examine the general drawings and details to see that outlets are properly spaced and located with relation to the interior finish and treatment.

B. In order that all outlets may be located in proper relation to paneling and decorated areas, become familiar with the details of these areas. Consult with the other contractors on the project and procure all details of the various areas so as to make the outlet boxes and panelboards come in proper relation to the work of all other contractors. Be responsible for the exact and proper location of the various portions of work. Such work must be entirely satisfactory to the Engineer.

C. Mounting heights of devices shall comply with ADA. The following is a list of mounting heights for equipment:1. Locate wall switches 3'6” above the floor, except where special treatment requires a higher or lower

setting.2. Locate receptacles as follows:

a. In general, locate 18 inches above finished floor except as hereinafter specified or as indicated on the architectural drawings.

b. In block walls, locate either in the bottom or top of the nearest block course.c. In brick walls, mount in the horizontal position, in the fourth brick course.d. In spaces where noted to be above counters, mount in the horizontal position, 4 inches from

backsplash to bottom of box.e. In rooms that house mechanical and electrical equipment, locate 40 inches above finished floor.f. Locate weatherproof receptacles 24 inches above finished grade.

3. F.A. Speakers and Visual Indicators: 84” above finished floor to bottom of device.4. F.A. Pull Stations: 3'6” above finished floor to center of device.5. Disconnect Switches: 5'0” above finished floor.6. Manual and Magnetic Starters or Pushbutton Controls: 5'0” above finished floor.7. Telephone/Data Outlets: Same as receptacles above.

D. All of the above mounting heights shall be held as near as possible to the center line of the equipment.

E. The above list is general in nature. Examine all Architectural Drawings and consult with the Engineer and vary mounting heights as directed.

3.16 TESTING 600 VOLT

A. After wires and cables are in place and before connection to the devices and equipment is made, test the system for shorts and grounds by means of an approved type of constant potential “Megger”, which is to be furnished by the Electrical Contractor.

B. Remove and replace all hot wires if shorted or grounded.

END OF SECTION

Page 231: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

COMMON WORK RESULTS FOR ELECTRICAL26 05 00 - 14

THIS PAGEINTENTIONALLY

LEFT BLANK

Page 232: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 26 - 1

SECTION 26 05 26GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 WORK INCLUDES

A. Base Bid:

1. Contractor: Provide a completely grounded system. Electrical equipment, conduits, supports, cabinets and panels shall be grounded in accord with NEC and as shown on the drawings.

1.2 QUALITY ASSURANCE

A. Codes & Standards:1. UL listed.2. NFPA 70 (NEC), 20173. NEMA4. NEC Articles 250 and 680

PART 2 - PRODUCTS

2.1 NOT APPLICABLE

PART 3 - EXECUTION

3.1 INSTALLATION

A. Electrical System shall be grounded. Grounding shall be in accord with NEC 250 and NEC 680. By reference herein, NEC Sections 250 and 680 shall become a part of this specification and shall be adhered to strictly.

B. All conduit, raceways, equipment, enclosures, panel housings, fixture housings, bus ducts, shall be grounded back to the service equipment location utilizing the continuous metallic conduit system as the grounding means. Discontinuity of the metallic conduit grounding system will not be acceptable.

C. All connections to motors, receptacles and equipment shall contain a separate grounding conductor bonded to the panelboard grounding bus at one end and the motor frame, receptacles, or equipment at the other end.

E. In accordance with NEC 680, all connections to motors, equipment, lights, receptacles, enclosures, piping, all metallic materials (see NEC 680) shall be grounded. Provide a copper ground conductor for bonding of all metallic equipment, devices, and components on project. All connections shall be exothermic welded unless the manufacturer supplies equipment or device with lug.

F. Provide a ground wire in all lighting circuits. Ground all lighting equipment.

G. Provide a ground wire to all cable trays.

H. Provide a ground wire for all 120V receptacle outlet circuits.

I. See Section 26 05 00 for ground type duplex receptacle.

J. See Section 26 05 00 for ground fault interrupting receptacles in wet locations.

K. Transformer neutrals and grounds shall be grounded for “separately derived” systems in accordance with

Page 233: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 26 - 2

NEC.

L. See Sections 26 05 00 for fittings for continuous conduit grounding system.

M. All ground wires shall be run in conduit except where otherwise indicated on the drawings.

N. Color code of ground wire shall be green.

O. Exterior grade mounted equipment shall have enclosures grounded directly to a separate driven ground at the equipment in addition to the building ground connection. This includes grade mounted light fixtures.

END OF SECTION

Page 234: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

IDENTIFICATION FOR ELECTRICAL SYSTEMS Design Development 1-17-2020 26 05 53 - 1

SECTION 26 05 53IDENTIFICATION FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.01 WORK INCLUDES

A. Provide identification as listed below.

1.02 QUALITY ASSURANCE

A. Provide proper identification in accordance with NFPA 70- (NEC), 2011.

1.03 GENERAL

A. Provide identification of electrical system components. All conduits shall be EZ-Pull True Color Metallic Tubing (EMT/Rigid)1. Standard codes for junction boxes and covers:

a. Normal Power – Blueb. Critical Power – Yellowc. Life Safety Power – Greend. Equipment Emergency Power – Orangee. Fire Alarm – Redf. Communications – Black g. Fire Doors – Brown h. Building Controls - White

B. Provide the following items with nameplates:1. All motor starters, motor controls, motor control centers, push-button stations, control panels and time

switches.2. Switchboards, disconnect switches, circuit breakers, contactors or relays in separate enclosures. Power

receptacles where the nominal voltage between any contact is greater than 150V to ground. Use at least 1-1/8” x 2-1/4” signs

3. Special electrical systems shall be properly identified at junction and pull boxes, terminal cabinets and equipment racks.

4. Nameplate inscription: Nameplate shall adequately describe the function or use of the particular equipment involved. Nameplate for panelboards and switchboards shall include the panel designation, voltage and phase of the supply, and where the circuit-feeding panel originates, i.e.:a. Panel Ab. 208/120 V.c. 3 Phase - 4 W.d. FED from “MDS”

5. When equipment has more than one source of power, i.e.: separate control power source. The location of all power sources shall be CLEARLY identified at the equipment location. I.e.: Nameplate on door, etc.

6. Mark all wires in panelboards with the circuit number they serve.7. Legibly mark feeder conduits entering and leaving a panelboard or switchboard with their destination.

1.04 MAIN SWITCHBOARD

A. The main switchboard shall have all switches or breakers labeled with load served or feeder served as directed by the Architect/Engineer. Labeling shall be engraved plastic signage with 1/8 inch to 1/4 inch lettering. Information shall include load or feeder served, amperage, and phase.

B. The switchboard shall contain a label with system voltage, phase amperage, cycles, and manufacturer's name.

1.05 PANELBOARDS

A. Provide a typed card directory for each panel. Directory shall designate breaker number and load served. Panel shall have all breakers individually numbered and panel shall have an interior nameplate provided by manufacturer with voltage, amperage, phase and hertz listed. Provide an exterior engraved plastic signage with the panel name or number or letter designation., and where the panel is served from.

Page 235: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

IDENTIFICATION FOR ELECTRICAL SYSTEMS Design Development 1-17-2020 26 05 53 - 2

PART 2 - PRODUCTS

2.01 MATERIALS

A. Nameplate construction shall be laminated phenolic plastic, black front and back with white core, with lettering engraved through the outer covering. Lettering shall be 3/16 inches high at push-button station starter, receptacles and similar devices where the nameplate is attached to the device plate. At all other locations, lettering shall be 1/4 inch high unless otherwise detailed on the drawings.

B. Other types and sized of signage may be used where appropriate.

PART 3 - EXECUTION

3.01 INSTALLATION

A. Install labels on motor starters, TT switches, relays, disconnect switches, main distribution switchboard, power distribution panels, branch power panels, branch lighting panels and cable trays.

B. Special outlets and receptacles shall be clearly labeled to identify the utilization equipment.

C. Overcurrent devices in panels clearly identify what they feed. This may be accomplished by means of the typewritten panel schedules mounted inside of the front cover doors under glass or plastic.

END OF SECTION

Page 236: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

LOW VOLTAGE CIRCUIT PROTECTIVE DEVICES Design Development 1-17-2020 26 28 00 - 1

SECTION 26 28 00LOW VOLTAGE CIRCUIT PROTECTIVE DEVICES

PART 1 - GENERAL

1.01 WORK INCLUDES

A. Circuit breakers

1.02 QUALITY ASSURANCE

A. Comply with:1. UL listed2. NFPA 70 (NEC), 2011.3. ANSI4. NEMA

1.03 SUBMITTALS

A. Submit manufacturer's data demonstrating compliance with the drawings and these specifications.

B. Shop drawings shall clearly indicate type of breaker, size, trip, characteristics, interrupting capacity, with features listed and identified.

PART 2 - PRODUCTS

2.01 ACCEPTABLE MANUFACTURERS

A. Breakers:1. Square D

2.02 CIRCUIT BREAKERS

A. Circuit breakers shall meet the following:1. Be quick-make, quick-break type.2. Have toggle mechanism insuring full contact pressure until time of opening whether manually or

automatically operated.3. Have inverse time tripping characteristics with fixed thermal trip action to hold on harmless momentary

overload.4. A short circuit condition shall cause the magnetic trip element to instantly trip without damage or injury.5. Have non-welding, non-corroding contacts.6. Have mechanism enclosed in molded bake-lite case, sealed to prevent tampering or unauthorized

changes in calibration.7. Be NRTL listed.8. Meet NEMA standards.9. Be bolt-on type unless otherwise specified for use in common bus equipment.10. Have contacts operate in a multiple plate arc quenching chamber vented to load side of breaker - UL

listed.11. Be fully rated for panel or switchboard bus they are to be used in as scheduled on the drawings.12. Be calibrated for operation in a minimum ambient temperature of 40°C.13. Multi-pole breakers shall have common trip molded inside breaker housing.14. Twenty ampere minimum unless otherwise specifically called for.15. When used as main breaker be minimum 65,000 AIC rated and sized in accordance with UL 67 unless

otherwise noted on drawings.16. Multi-pole breakers shall not require more space than the equivalent number of single pole breakers.17. Have operating handle that visually indicates “on”, “off”, or “tripped”.18. Clearly indicate ampacity and frame size.19. Be labeled as to what circuit number or numbers and load they serve.20. All circuit breakers shall be rated “SWD” indicating they are suitable for switching loads.21. “HID” shall indicate circuit breaker rated for high intensity discharge lighting.22. Single breakers per one-pole space only.

PART 3 - EXECUTION

Page 237: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

LOW VOLTAGE CIRCUIT PROTECTIVE DEVICES Design Development 1-17-2020 26 28 00 - 2

3.01 INSTALLATION

A. No equipment shall be electrically activated without proper overcurrent protection.

B. Breakers shall indicate clearly their size; must clear panel doors and be mounted on frame allowing outward and inward adjustment. The depth of the tubs shall also permit adjustment.

C. Breakers shall be provided with a numerical designation strip.

D. 120V lighting and receptacle circuits shall be run from 20 A. single pole breakers. Unless specifically called for, or NEC required, no breakers less than 20 A. shall be allowed.

E. Snap switch type breakers only.

F. Breakers shall be fully rated.

G. Breakers rated 250 amps and above shall be provided with adjustable magnetic trip

END OF SECTION

Page 238: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

INNOVATIVE ENGINEERS, INC. LIGHTING Project #10159 26 51 00 - 1

SECTION 26 51 00 LIGHTING

PART 1 - GENERAL

1.01 WORK INCLUDES

A. Light fixtures.

B. Lamps.

C. Ballast.

D. Fixture bases.

E. Fixture lens.

F. Accessories.

1.02 QUALITY ASSURANCE

A. All fixtures shall have UL label.

B. Ballasts shall be in accord with ANSI Standards.

C. Comply with:1. NFPA - 702. I.E.S.

D. Verify the ceiling trim requirements for fixtures to assure proper installation for the type of ceiling construction.

1.03 SUBMITTALS

A. Submit in accord with Division 01.

B. Submit manufacturer's data demonstrating compliance with this specification and the schedule on the drawings.

C. Shop Drawings:1. Include data specified herein including fixture “mark” corresponding to the Drawings.2. Clearly indicate type and color of each lamp(s) to be used for each fixture type.3. Submit shop drawings for each type of lamp.

D. Submittals will be reviewed a maximum of three revisions. If after the third submission submittal package does not conform to Specifications herein, CONTRACTOR will be billed at Electrical Engineer's standard hourly rate.

E. Maintenance data for fixtures to include in the operation and maintenance manual specified in Division 1.

PART 2 - PRODUCTS

2.01 FIXTURE SCHEDULE

A. Light fixtures shall be as listed on the drawing Fixture Schedule.

B. The various types of fixtures to be provided are indicated on the drawings. A fixture shall be provided for each ceiling outlet, bracket outlet and other lighting fixture outlets. Where a fixture type is not indicated, provide a fixture of the same type used in similar areas.

2.02 FIXTURES

A. Where installed on combustible surfaces, fixtures shall be specifically UL listed for this condition or be spaced not less than 1-1/2-inch from the combustible surface.

Page 239: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

INNOVATIVE ENGINEERS, INC. LIGHTING Project #10159 26 51 00 - 2

B. All glassware shall be high quality, homogeneous in texture and free from streaks, cords, stones, or blisters and of uniform thickness and properly annealed.

C. Enamel finish shall be baked. The finish of each fixture shall be uniform in quality, durable and free from defects.

D. All plastic molded lenses shall be acrylic prismatic K19, 0.156” type.

E. Disconnecting Means:1. All applicable luminaires must be provided with means to comply with luminaire disconnect

requirements specified in NEC 410.130(G), 2011 Edition.

PART 3 - EXECUTION

3.01 FIXTURE INSTALLATION

A. Light fixtures for all outlets shown on the drawings shall be furnished and installed complete including the assembly, wiring, support materials, and installation of each unit in place. All lenses, glassware and metal parts shall be thoroughly cleaned just prior to final acceptance.

B. Lighting fixtures shall be mounted as specified, and shall include all necessary fittings for a complete installation. Provide all materials to adequately and safely support all fixture installations.

C. Verify ceiling suspension material and systems in the various areas and provide plaster frames and proper fixture trims.

3.02 FIXTURE LOCATION

A. Space fixtures as indicated on the drawings and in keeping with ceiling patterns, air inlets and outlets.

B. Light fixtures recessed in ceiling shall be coordinated with ceiling construction. Recessed fixtures as scheduled serve only as a guide as to the type of fixture, lamp, and lens. Supply fixture that shall integrate with the type of ceiling as scheduled on architectural drawings approved for construction. Recessed light fixtures installed in grid ceiling shall have tee grid clamps.

C. Exit lights shall be coordinated with adjacent architectural work and shall be located and modified as to type of mounting, as directed by Architect/Engineer.

3.03 FIXTURE SUPPORT

A. Conduits run to recessed fixtures shall terminate in a suitable box adjacent to fixture opening with final connections to fixture made with flexible conduit and Type AF wire. Airtight fiberglass gaskets shall be provided around recessed fixtures to eliminate light leakage or hot air dirt streaks between fixture trim and finished ceiling. Fixtures shall be designed, insulated and ventilated to prevent scorching of adjacent construction. Plaster or other special frames, including extension pan for exposed conduit installation, shall be provided.

B. Light fixtures shall have proper supports, flanges, and plaster frames to integrate with the type of ceiling construction. All fixtures shall be constructed so that they may be securely supported. All fixtures shall be supported from 3/8-inch stud in outlet box. Outlet boxes shall have fixture studs and shall be securely hung independently of conduits.

C. Provide auxiliary supports for mounting fixtures in areas without ceilings (i.e., exposed beams and slabs), for proper installation of fixtures. Such supports shall span a minimum of 2 beams for each individual fixture and shall be securely and suitably anchored.

D. Fixtures shall be supported with a stem and “L” hanger on one end and pipe stem on the other end. When conduit is used to support fixtures, 1-inch rigid heavy wall shall be the minimum size. When conduits are used as stems, locknuts and washers shall be employed. Conduit may not be reduced in size between fixtures.

Page 240: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

INNOVATIVE ENGINEERS, INC. LIGHTING Project #10159 26 51 00 - 3

E. Fixtures installed adjacent to unit heaters or mechanical equipment, which may cause fixtures to vibrate, shall be installed so not to sway.

F. Fixtures shall not be supported from underside of metal roof decks, except where specifically noted otherwise on the drawings.

G. Compression or indenter type couplings will not be acceptable for fixtures supports.

H. Recessed grid fixtures shall be provided with T-bar clips. Install 4 per fixture.

I. Fixtures installed in continuous rows shall be supported a minimum of 8'-0” on center. Where fixtures are mounted in continuous rows over 16 feet long, support from Kindorf, Unistrut, or Storack which will limit deflection to acceptable values. When channels are used for a wireway, thus eliminating conduit shown on the drawings as running parallel to the channels. Channels shall have closure plates if used as wireways. Continuous wireways may be used in place of conduit when approved in writing by Architect/Engineer for the installation.

J. In general, support all fluorescent fixtures from the building structure and not from the ceiling suspension system (such as tee bar system for a suspended acoustical tile ceiling.)

K. At the Electrical Contractor's option recessed fluorescent fixtures can be supported from the ceiling suspension system if the Electrical Contractor makes arrangements and pays for additional ceiling hanger wires of adequate strength and quantity to support the fixtures. Where recessed fixtures occur in grid system, install tie wires on all four corners of the grid system about the fixture. Fixtures so supported shall be securely fastened to the grid system members with safety tee bar clips.

3.04 MISCELLANEOUS REQUIREMENTS

A. Color of exit light lettering shall be green LED. All letters shall be 6 inches high by 3/4-inch stroke. Exit signs at an egress shall read “EXIT”.

B. Fixtures marked “WP” shall be waterproof with special waterproof boxes and gaskets as required to keep rain or hose spray from coming into contact with wiring.

C. Letters “a”, “b”, “c”, etc., indicate associated switch or switches. Figures “1”, “2”, “3', etc., indicate associated branch circuit. “F1”, “F2”, “F3”, etc. indicate fixture type.

3.05 LAMP INSTALLATION

A. Provide all lamps for all outlets and fixtures. All fixtures shall be complete with lamps and in operating condition when the building is turned over to the Using Agency. All “burnt out” or broken lamps that occur during the construction period shall be replaced.

B. All fixtures, reflectors, lenses, and lamps shall be cleaned.

END OF SECTION

Page 241: SECTION 23 05 00 COMMON WORK RESULTS FOR HVAC PART 1

CITY OF CEDAR RAPIDS – ImOn ICE ARENA INFRASTRUCTURE IMPROVEMENTS #PUR0420-191; 555085

INNOVATIVE ENGINEERS, INC. LIGHTING Project #10159 26 51 00 - 4

THIS PAGE

INTENTIONALLY

LEFT BLANK