section 01800 standard specifications scope of work a. furnish all labor, materials, equipment,...

40
STANDARD SPECIFICATIONS - 01800 - 1 SECTION 01800 STANDARD SPECIFICATIONS PART I - GENERAL 1.1 DOCUMENTS The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications. 1.2 STANDARD SPECIFICATIONS A. Work to be done under this contract shall be done in accordance with the Standard Specifications of the State of California Department of Transportation (Caltrans) dated 2010. The term Standard Specifications, where found in the Technical Specifications shall refer to the 2010 edition of the "Standard Specifications" of the State of California, Department of Transportation Caltrans). B. Whenever in the Standard Specifications the following terms are used, they shall be understood to mean and refer to the following: 1. Owner: City of Berkeley 2. Agency: City of Berkeley. 3. City’s Representative: The authorized representative of the City of Berkeley. 4. Engineer, Landscape Architect: The Design Consultant. In case of conflict between the Caltrans Standard Specifications and these Special Provisions, these Special Provisions shall take precedence over and be used in lieu of such conflicting proportions. The term “City” where found in the Technical Provisions, shall refer to the City of Berkeley. END OF SECTION

Upload: lelien

Post on 16-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

STANDARD SPECIFICATIONS - 01800 - 1

SECTION 01800 STANDARD SPECIFICATIONS

PART I - GENERAL 1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 STANDARD SPECIFICATIONS

A. Work to be done under this contract shall be done in accordance with the Standard Specifications of the State of California Department of Transportation (Caltrans) dated 2010. The term Standard Specifications, where found in the Technical Specifications shall refer to the 2010 edition of the "Standard Specifications" of the State of California, Department of Transportation Caltrans).

B. Whenever in the Standard Specifications the following terms are used, they shall be

understood to mean and refer to the following:

1. Owner: City of Berkeley 2. Agency: City of Berkeley. 3. City’s Representative: The authorized representative of the City of Berkeley. 4. Engineer, Landscape Architect: The Design Consultant. In case of conflict between the Caltrans Standard Specifications and these Special Provisions, these Special Provisions shall take precedence over and be used in lieu of such conflicting proportions. The term “City” where found in the Technical Provisions, shall refer to the City of Berkeley.

END OF SECTION

SITE DEMOLITION - 024100 - 1

SECTION 024100

SITE DEMOLITION

PART I - GENERAL 1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

A. Furnish all labor, materials, equipment, facilities, transportation and services to complete all tree and shrub protection, temporary construction fence, clearing, grubbing, demolition and related work as shown on the Drawings and/or specified herein.

B. Work Included: The general extent of the clearing, demolition and removal is shown on the

Drawings and includes, but is not necessarily limited to, the following:

1. Temporary construction barrier. 2. Clearing and grubbing. 3. Demolition and removal of paving and base material. 4. Removal, hauling and disposal of miscellaneous rubble and debris.

1.3 PROTECTION

A. Protection of Existing Improvements 1. Protection shall be provided to prevent damage to existing improvements indicated to

remain in place on City property. 2. Damaged improvements shall be restored to their original condition, as acceptable to the

City’s Representative. 3. Land areas outside the limits of demolition performed under this contract shall be preserved

in their present condition. The Contractor shall confine his demolition activities to areas defined for work on the Drawings.

B. Protection of Existing Utilities

1. The Contractor shall verify all existing utility locations either shown or not shown on the

Drawings. 2. The Contractor shall immediately notify the City’s Representative of any damages to

existing utilities. 3. Repairs to damaged utilities shall be made in accordance with the requirements of the

City’s Representative at no extra cost to the City. 4. The Contractor shall coordinate with the City’s Representative for shutoff of or connection

to active utilities. Existing utility services shall not be interrupted except as authorized in writing by the City’s Representative.

C. Protection of Plant Material: Existing plant material to remain shall be protected from damage.

1. Do not stockpile material or equipment within 25' of dripline of existing trees to remain. 2. Contractor shall take precautions when excavating within tree rootzone. Hand excavation

only is allowed adjacent to surface and subsurface roots of all existing trees to remain.

SITE DEMOLITION - 024100 - 2

3. Root Cutting: This work shall be done under direction of City approved Certified Arborist hired by the Contractor.

4. Do not compact soil within the dripline of existing trees to remain. D. Protection of Work Site: Construction barrier shall provide a construction site perimeter barrier.

Barrier shall be a minimum 6-foot high chain link fence with locked entry gates. Locate the fence to enclose substantially the entire work area, or that portion the Contractor establishes as required to encompass the entire project construction operation. Location shall be as approved by City’s Representative. Adjust location as required during construction to accommodate work in progress.

1.4 JOB CONDITIONS

A. Traffic

1. Demolition operations and the removal of debris shall be conducted in a manner that will

ensure minimum interference with roads, driveways, walks and other adjacent occupied or used facilities.

2. Roads, driveways, walks and other adjacent occupied or used facilities shall not be closed or obstructed without written permission from the City’s Representative.

B. Contractor shall examine the work site and verify existing conditions prior to commencement of

work. PART II - MATERIALS 2.1 EQUIPMENT

Equipment shall be suitable for the work to be done and shall be in first-class condition. Equipment operators and workmen shall be skilled in demolition and removal operations and to be supervised by a competent superintendent.

PART III - EXECUTION 3.1 CONSTRUCTION BARRIER

Fence location shall be as approved by Engineer. Adjust fence location as required during construction to accommodate work in progress.

3.2 DEMOLITION AND REMOVAL

Demolition shall include removal of asphaltic concrete paving and base courses, as indicated on the Drawings.

1. Materials requiring removal and demolition to be removed completely from site. 2. If Contractor encounters unforeseen items during clearing and demolition work, he is to

notify the City’s Representative prior to removal or demolition. 3.3 TREE TRIMMING AND ROOT PRUNING

A. Tree branch and root pruning shall be done in such a manner as not to injure the tree, adjacent trees, plants and/or improvements which are to be preserved. 1. All pruning shall be performed by a tree contractor possessing a State of California

Contractor’s License for Tree Service and supervised by a certified arborist.

SITE DEMOLITION - 024100 - 3

2. All operations shall be in accordance with the ISA pruning guidelines and adhere to ANSI Z133.1 and ANSI A300.

3. Limbs and roots shall not be torn or ripped. All final pruning cuts shall be clean cuts.

B. Pruning shall be kept to the minimum necessary for safety, improving long-term tree structure, and providing the necessary clearance for construction equipment. Heading cuts shall not be used.

C. Root Pruning: Where paving repair work occurs adjacent to or over tree roots where damage

has been caused by root intrusion, the roots shall be removed to a minimum depth to at least 8 inches below the bottom of the new paving improvements. Roots shall be cut as far from the tree as possible alongside the edge of new paving. Roots must be completely severed prior to their removal.

1. This work shall be done under direction of City approved Certified Arborist hired by the

Contractor. 2. Notify City 72 hours prior to pruning roots larger than 2”. 3. Root pruning shall not be performed until after removal of the existing paving improvements

but shall be completed prior to base and subgrade excavations. 4. Root pruning shall be achieved by use of a Vermeer root cutter or equivalent method

approved by Engineer. Tree roots may occasionally be cut by sawing or chopping with sharp saw or axe on an individual case basis, but only with the express approval of the Arborist and the Engineer.

5. If the removal of the root is determined by the Arborist to potentially endanger the stability or health of the tree, the Contractor shall provide the Engineer with the findings and avoid cutting the roots until approval from the Engineer has been received.

6. Where excavation has exposed living roots to the air, Contractor shall cover the exposed roots within two (2) hours of exposure with base rock, soil, moist burlap or other means acceptable to the Arborist and the Engineer. Inspection by the Engineer is required prior to permanent backfill.

7. In addition to root pruning, trimming of the tree crown may be required as determined by the Arborist.

D. Remove all trimmings and debris generated from these operations.

3.4 CLEARING AND GRUBBING

A. Clearing and grubbing consisting of removal and disposal of all rubbish, debris, weeds, brush and other unsuitable materials inside the project area and as shown on Drawings or as specified herein.

B. All vegetation (except where noted on the Drawings) and deleterious material shall be cleared

to a depth of six inches (6”). Areas requiring clearing and grubbing shall be graded to a relatively smooth final grade.

3.5 CLEAN UP

A. Dust Control: At all times during the operations, prevent the formation of an airborne dust

nuisance by watering and/or treating the site of the work in such a manner that will confine dust particles to the immediate area of the work. Contractor shall remove mud tracks from streets, sidewalks or adjacent properties and sweep streets and sidewalks as directed by the City’s Representative.

B. Do not store or permit debris to accumulate on site. Demolished material and spoils from

clearing and grubbing shall be removed from site and properly disposed of, by the Contractor.

SITE DEMOLITION - 024100 - 4

C. On completion of demolition and after removal of all debris, site shall be left in clean condition satisfactory to the City’s Representative.

END OF SECTION

EARTHWORK - 312200 - 1

SECTION 312200

EARTHWORK

PART I - GENERAL 1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

A. Furnish all labor, materials, equipment, facilities, transportation and services to complete all earthwork and grading and related work as shown on the Drawings and/or specified herein.

B. Work Included: The general extent of all excavating, filling and grading is shown on the

Drawings and includes, but is not necessarily limited to, the following:

1. Erosion control materials and maintenance in accordance with Best Management Practices shall be employed throughout the contract period. Straw waddles and erosion control blankets shall be executed and frequently adjusted to prevent erosion off site. Contractor shall make repairs to eroded areas and possible related damage at its own expense.

2. Excavation and removal of unsuitable and/or excess material. 3. Excavation, preparation and moisture conditioning of subgrade for paving and surfacing. 4. Relocation and installation of boulders. 5. Gravel Sump 6. Finish grading.

1.3 PROTECTION

Existing improvements and facilities, adjacent property and utilities which are not to be removed, shall be protected from injury or damage resulting from Contractor’s operations.

1.4 WET WEATHER CONSTRUCTION AND/OR UNSTABLE SOIL CONDITIONS. Seasonal Limits: Soil subgrades may become saturated due to exposure to wet weather conditions

making subgrade compaction levels difficult to achieve No grading or fill shall be placed during weather conditions, which will alter the moisture content of the subgrade or fill materials sufficiently to make adequate compaction impossible. After placing operations have been stopped because of adverse weather conditions, no additional fill material shall be placed until the last layer compacted has been checked and found to be compacted to the specified densities.

PART II - MATERIALS 2.1 EQUIPMENT

Grading equipment shall be suitable for the work to be done and shall be in first-class condition. Equipment operators and workmen shall be skilled in grading operations and to be supervised by a competent superintendent.

2.2 MATERIALS Drain Rock: ¾” round drain rock.

EARTHWORK - 312200 - 2

PART III - EXECUTION 3.1 GEOTECHNICAL RECOMMENDATIONS: Work of this section shall conform to Basketball Court

Pavement Recommendations, ENGEO Geotechnical, Project No.: 12622.000.000. 3.2 SURVEYING

A. Grade Stakes and Lines: All grading, including subgrading and finished grading of unsurfaced and paved areas, to be controlled by transit level and such intermediate grade stakes and lines as may be necessary to obtain the slopes and levels required by the finished grade elevations shown on the Drawings. Compacted subgrade and finished grade surfaces shall parallel and conform to the control planes established by transit level and required grade stakes and lines.

B. Verification of Quantities: Any quantities mentioned and any Grading Sections are for the

Contractor's convenience only. All grading shall conform to the Drawings and/or herein specified.

3.3 EXCAVATION

A. All materials shall be excavated as shown on the Drawings and/or herein specified. This work shall consist of all operations of excavation or filling, earth or rock. Examples of work covered under this section include, but are not limited to the following: excavation of subgrade and site furnishing footings.

B. All deleterious, unsuitable, and organic materials encountered during the excavation operation

(whether shown or not shown on the plan) shall be removed and disposed of from the project site in a legal manner. All excavations from demolition below design grades shall be cleaned to a firm, non-yielding native soil surface. Quantities of removed, unsuitable material (including the material used as replacement) shall be considered paid for under various items of work.

C. Excavation shall be carried to the approximate depth indicated on the plan or as specified.

Should the Contractor, through his negligence or other fault, excavate below the designated depths, he shall replace such excavations with approved materials at his own expense.

3.4 COMPACTION OF ORIGINAL GROUND PRIOR TO PLACING FILL

Following demolition, removals of unsuitable materials, any required subexcavation and stripping, areas of new improvements shall be scarified to a depth of 12 inches, moisture conditioned to at least 3 percent above optimum moisture, thoroughly mixed and recompacted to the requirements for engineered fill. Finished subgrade shall be firm and non-yielding under weight of compaction equipment. Conform to Basketball Court Pavement Recommendations, ENGEO Geotechnical, Project No.: 12622.000.000.

3.5 GRADING AND SUBGRADE PREPARATION

A. Engineered Fill Materials and Compaction Criteria: Conform to Basketball Court Pavement

Recommendations, ENGEO Geotechnical, Project No.: 12622.000.000. B. Contractor to grade site to establish finish grades of constructed elements, such as paving as

indicated on the Drawings. All ground surfaces to be finished to uniform grades and slopes as per the Drawings and in such a manner as to drain properly and be free from depressions, which may cause areas of standing water. At the completion of grading work, the site shall be left in a clean and finished condition conforming to the Drawings.

C. Settling: All backfill including trenches to be flush with adjoining grade in a firm, unyielding

position with no visible settling. All erosion damage shall be repaired.

EARTHWORK - 312200 - 3

D. Gravel Sump: Install per plan and detail.

E. Boulder Placement: Install per plan and detail.

F. Finish grades of adjacent unpaved soil or planting areas to be three inches (3”) below the

surface of adjacent walks, curbs, paved areas, without abrupt change in gradient either in the surface of the soil or where the soil meets such features. Clods to be broken up and the surface of the ground shall be uniformly pulverized and graded to a relatively smooth surface.

G. Guarantee: Any settling which may occur during a one (1) year period after acceptance of the

work to be repaired to the satisfaction of the City, and the City by the Contractor, without expense to the City, including the complete restoration of all damaged planting, paving, or other improvements of any kind.

3.6 FINISH GRADING

Finished surfaces shall be uniform and smooth; true to slopes and grades. Minimum slope shall be 1-1/2%. Swales to direct water away from structures and walks shall drain in a positive manner. In the event that the contractor anticipates a problem installing a swale as shown on the Drawings he/she is to notify the City prior to proceeding.

END OF SECTION

AGGREGATE BASE - 321000 - 1

SECTION 321000

AGGREGATE BASE

PART I - GENERAL

1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

Furnish all labor, materials, equipment, facilities, transportation and services to complete aggregate baserock installation as shown on the Drawings and/or specified herein.

PART II - MATERIALS 2.1 EQUIPMENT

Equipment shall be suitable for the work to be done and shall be in first-class condition. Equipment operators and workmen shall be skilled in aggregate baserock operations and to be supervised by a competent superintendent.

2.2 MATERIALS

Aggregate Base

1. Class 2 conforming to the requirements of CalTrans Standard Specifications Section 26, "Aggregate Bases," except as modified herein.

2. Aggregate base shall be three-quarters of an inch (¾”) maximum and Class 2 (R-value 78 minimum) and shall be of the thickness shown on the Drawings. No waiver of R-value will be allowed. The aggregate base shall be untreated material.

PART III - EXECUTION 3.1 GENERAL

Aggregate Base

1. Material may be spread by the use of motor graders as long as segregation of large or fine particles of aggregate is avoided and the material, as spread, is free from pockets of large or fine materials. Subgrade preparation as specified in Section 312200, "Earthwork" of these Specifications is required when placing aggregate base on native material.

2. Relative compaction shall be not less than ninety-five percent (95%) as determined by ASTM D1557 test method.

3. Protect the aggregate base after it has been placed and compacted.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

ASPHALT CONCRETE- 321216 - 1

SECTION 321216

ASPHALT CONCRETE

PART 1 GENERAL 1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

A. Furnish all labor, materials, equipment, facilities, transportation and services to complete asphalt concrete paving as shown on the Drawings and/or specified herein.

B. Asphalt concrete shall conform to the requirements of Caltrans Standard Specifications Section

39, “Hot Mix Asphalt” and Section 92 “Asphalts” except as modified herein. Aggregate quality, and completed mix quality characteristics shall meet the requirements outlined in Section 39. Asphalt pavement thickness shall be as shown on the plans.

1.3 RELATED DOCUMENTS

A. ASTM

1. D 979: Practice for Sampling Bituminous Paving Mixtures. 2. D 1073: Specification for Fine Aggregate for Bituminous Paving Mixtures. 3. D 1188: Test Method for Bulk Specific Gravity and Density of Compacted Bituminous

Mixtures Using Paraffin-Coated Specimens. 4. D 2041: Test Method for Theoretical Maximum Specific Gravity and Density of Bituminous

Paving Mixtures. 5. D 2726: Test Method for Bulk Specific Gravity and Density of Non-Absorptive Compacted

Bituminous Mixtures. 6. D 2950: Test Method for Density of Bituminous Concrete in Place by Nuclear Method. 7. D 3549: Test Method for Thickness or Height of Compacted Bituminous Paving Mixture

Specimens. 8. D 3666: Specifications for Minimum Requirements for Agencies Testing and Inspecting

Bituminous Paving Mixtures.

B. Caltrans Standard Specifications

1. Section 37: Bituminous Seals. 2. Section 39: Hot Mix Asphalt. 3. Section 92: Asphalts. 4. Section 94: Asphaltic Emulsions.

1.4 DEFINITIONS ASTM: American Society for Testing Materials. 1.5 QUALITY ASSURANCE

A. Thickness of Asphalt Concrete: In-place compacted thickness of asphalt courses will be determined according to ASTM D 3549.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

ASPHALT CONCRETE- 321216 - 2

B. Testing of Pavement Course: Contractor shall provide testing of new asphalt concrete compaction with the use of the nuclear gauge method according to ASTM D2950 and correlated with ASTM D 1188 or ASTM D 2726. One test shall be conducted for each 2,000 square feet of paving, at locations directed by City’s Representative.

C. Contractor shall, in the presence of the City’s Representative, conduct all testing. Cost for

testing shall be included in the unit price for the asphalt concrete. Any work that requires testing will not be accepted until the results have been reviewed and approved by the City’s Representative. The Contractor, at the Contractor’s expense, shall perform any required retesting or material replacement because of test failure.

1.6 SUBMITTALS

A. Job-Mix Designs: Certificates signed by manufacturers certifying that each asphalt concrete mix complies with requirements.

B. Material Certificates: Certificates signed by manufacturers certifying that each material

complies with requirements. 1.7 PROJECT CONDITIONS Environmental Limitations

1. Prime Coat: Minimum surface temperature of 60 deg F at application. 2. Tack Coat: Minimum surface temperature of 60 deg F at application. 3. Asphalt Concrete: Minimum atmospheric temperature of 50 deg F at application.

PART 2 PRODUCTS 2.1 ASPHALT CONCRETE

A. Caltrans Standard Specifications Section 39, 1/2 inch maximum Type A medium. Complete mix quality characteristics shall meet the requirements of Section 39.

B. Asphalt Materials

1. Asphalt Binder: Steam-refined paving asphalt of grade PG 64-10, in accordance with

Caltrans Standard Specifications Section 92. 2. Prime Coat: Caltrans Standard Specifications Section 93, MC-70. 3. Tack Coat: Caltrans Standard Specifications Section 94, SS1 or SS1h.

C. Aggregate: Conform to Caltrans Standard Specifications Section 39-1.02. D. Storing, Proportioning and Mixing Materials: Caltrans Standard Specifications Section 39-3. E. Sand: ASTM D 1073, Grade No. 2 or 3.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify that subgrade is dry and in suitable condition to support paving and imposed loads. B. Proof-roll subbase using heavy pneumatic-tired rollers to locate areas that are unstable or that

require further compaction.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

ASPHALT CONCRETE- 321216 - 3

C. Notify City’s Representative in writing of any unsatisfactory conditions. Do not begin paving until these conditions have been satisfactorily corrected.

3.2 SUBGRADE PREPARATION

A. General: Immediately before placing asphalt materials remove loose and deleterious material from substrate surfaces and ensure that prepared subgrade is ready to receive paving according to the Caltrans Standard Specification Section 39-1.09B and Basketball Court Pavement Recommendations, ENGEO Geotechnical, Project No.: 12622.000.000.

B. The subgrade shall be constructed true to grade, as shown on the Drawings, and in

conformance with Basketball Court Pavement Recommendations, ENGEO Geotechnical, Project No.: 12622.000.000.

C. Required thickness of aggregate baserock shall be placed to depths as indicated on Drawings.

Compact to ninety-five percent (95%) relative compaction under paving areas per ASTM D1557 test method.

3.3 ASPHALT CONCRETE SPREADING AND COMPACTING EQUIPMENT Spreading and Compacting Equipment: Caltrans Standard Specification Section 39-3.03 3.4 ASPHALT CONCRETE PLACEMENT

A. Asphalt concrete shall be produced as outlined in Caltrans Standard Specifications Section 39-1.08. Complete mix quality characteristics shall meet the requirements of Section 39.

B. All Hot Mix Asphalt shall be placed in lifts not to exceed three inches (3”). Cold joints shall be

tack coated prior to the adjacent overlay placement. Before compacting joints, all coarse aggregate in the overlapped material that has dislodged through raking shall be removed from the pavement surface and discarded. 1. Place, spread and compact asphalt concrete to required grade, cross section, and

thickness according to the Drawings and Caltrans Standard Specifications Sections 39. 2. After the bituminous mixture has been spread, struck off, and surface irregularities

adjusted, it shall be thoroughly and uniformly compacted by rolling. Rolling shall be performed in such a manner that cracking, shoving or displacement will be avoided.

3. Finish roll paved surfaces to remove roller marks while asphalt is still warm. 4. Edge Shaping: While surface is being compacted and finished, trim edges of pavement to

proper alignment. Bevel edges while still hot, with back of rake or smooth iron. Compact thoroughly using tamper or other satisfactory method.

5. Joints: Construct joints to ensure continuous bond between adjoining paving sections according to the Caltrans Standard Specification Section 39. a. Construct joints free of depressions with same texture and smoothness as other

sections of asphalt course. b. Clean contact surfaces and apply tack coat. c. Offset longitudinal joints in successive courses a minimum of 6 inches. d. Offset transverse joints in successive courses a minimum of 24 inches. e. Compact joints as soon as Hot Mix Asphalt will bear roller weight without excessive

displacement. 6. Smoothness: The completed surfacing shall be thoroughly compacted, smooth, and free

from ruts, humps, depressions, or irregularities. Any ridges, indentations or other objectionable marks left in the surface of the HMA by blading or other equipment shall be eliminated by rolling or other means. The use of any equipment that leaves ridges, indentations, or other objectionable marks in the HMA shall be discontinued, and acceptable equipment shall be furnished by you. Smoothness of the surface shall be as called out in Section 39-2.01C(16).

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

ASPHALT CONCRETE- 321216 - 4

C. Compaction: Compact HMA to an average density of not less than 91 percent of the maximum theoretical density as determined by ASTM D2041, but not less than 90 percent nor greater than 96 percent.

1. Any area, which has an interim result less than 90 percent, shall be re-worked while the

mat is above 250 degrees F until the area is compacted to a density of 91.0 percent. D. Repairs: Remove paved areas that are defective or contaminated with foreign materials and

replace with fresh asphalt. Compact by rolling to specified density and surface smoothness. E. Protection

1. Provide adequate protection of the subgrade, aggregate subbase, aggregate base and

other materials if the Hot Mix Asphalt pavement is not placed within a specified time as determined by the City’s Representative. Retesting of the subgrade, aggregate subbase, aggregate base or other material will be required and will be paid for by the Contractor, if the HMA pavement is not placed within a specified time as determined by the City’s Representative.

2. After final rolling, do not permit vehicular traffic on pavement until it has cooled and hardened. Erect barricades to protect paving from traffic until mixture has cooled enough not to become marked.

3.5 CONFORMS

Where new asphalt concrete pavement is adjacent to existing asphalt concrete, the existing pavement shall be sawcut back to a point as specified on the drawings so as to provide a smooth transition between existing asphalt and new construction. The areas so cut back shall be excavated and graded so as to provide for the placing of aggregate base and asphalt concrete at specified depths, see details. A prime coat of liquid asphalt SC-70 shall be applied to the aggregate base and a paint binder shall be applied to cleaned surfaces of existing asphalt surfacing that will come in contact with the asphalt concrete conform. The asphalt concrete conform will be laid over the prime aggregate base and feathered over the existing asphalt concrete as required by the City’s Representative.

3.6 INSTALLATION TOLERANCE

A. Asphalt Pavement

1. Course thickness and surface smoothness within the tolerances specified in Caltrans Standard Specifications Section 39.

2. Total Thickness: Not less than indicated. B. Trench Patch

1. Compacted surface: Within 0.01 foot of adjacent pavement. 2. Do not create ponding.

C. Adjust Covers

1. Compacted surface: Up to 0.01 foot higher, and no lower, than adjacent pavement. 2. Do not create ponding.

D. Coefficient of Friction: Minimum coefficient of friction = 0.6 (wet) @slopes < 6% and 0.8 (wet)

@ slopes > or = 6%.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

CONCRETE REINFORCING & MISCELLANEOUS STEEL - 321312 - 1

SECTION 321312

CONCRETE REINFORCING & MISCELLANEOUS STEEL

PART I - GENERAL 1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this section of the Specifications.

1.2 SCOPE OF WORK

A. Furnish all labor, materials, equipment, facilities, transportation and services to complete all structural and miscellaneous steel work and related work as shown on the Drawings and/or specified herein.

B. Work Included: The general extent of the structural and miscellaneous steel work is shown on

the Drawings and includes, but is not necessarily limited to, the following:

1. Concrete reinforcement. 2. Miscellaneous hardware and connections.

1.3 GENERAL

A. Abbreviations

1. A.I.S.C. = American Institute of Steel Construction B. Handling and Storing Materials: Material to be stored shall be placed above ground upon

platforms, skids or other supports. It shall be kept free from dirt, grease, and other foreign matter and properly drained and protected from corrosion.

PART II - MATERIALS 2.1 REINFORCING STEEL

A. Reinforcement Bar and Dowels shall conform to ASTM A615 and CalTrans Standard Specifications Section 52, "Reinforcement.” Reinforcing steel shall be standard sizes of deformed bars, intermediate grade, 40 Dia. min. laps, and shall be clean, new stock which is free from rust, scale or other coatings that may affect the bond (ACI 318-05 Section 5.7).

PART III - EXECUTION 3.1 WORKMANSHIP

All work shall be to the best standard of practice in modern steel fabricating shops. Finished work shall be true to line and free of twists, dents, ridges, holes, warp and buckle.

3.2 REINFORCING STEEL FOR CONCRETE Install in accordance with CalTrans Standard Specifications Section 52, “Reinforcement” and

Technical Specification Section 321313 “Cast-in-Place Concrete” and as shown on Drawings.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

CAST-IN-PLACE CONCRETE - 321313- 1

SECTION 321313

CAST-IN-PLACE CONCRETE

PART I - GENERAL

1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

A. Furnish all labor, materials, equipment, facilities, transportation and services to complete all concrete related work as shown on the Drawings and/or specified herein.

B. Work Included: The general extent of the concrete work is shown on the drawings and includes,

but is not necessarily limited to, the following:

1. Concrete paving 2. Miscellaneous footings and pads

PART II – MATERIALS

2.1 EQUIPMENT

Equipment shall be suitable for the work to be done and shall be in first-class condition. Equipment operators and workmen shall be skilled in concrete operations and to be supervised by a competent superintendent.

2.2 CONCRETE MATERIALS

A. Concrete

1. Concrete shall conform to CalTrans Standard Specifications Section 90, "Concrete," except as modified herein.

2. Classes of concrete and combined aggregate grading shall be dependent upon the purpose for which the concrete is intended and shall conform to the table below:

Types of Concrete Work

Concrete

Class

Combined Aggregate

Grading

Min. Cement (Sks/cy)

Max. w/c Ratio (Gal/Sack)

Slump (Inches)

Min. Str. Test Cyl. 28 Days

(PSI)

Paving, Misc. Footings, and Pads

3

3/4" Max.

5.37

7.0

4” (plus or minus 1”)

2,500

B. Exposed concrete surfaces shall be formed with new wood, grade marks not required. Surfaces

of concrete footings which will be concealed may be formed with used wood of strength equivalent to that specified above for exposed surfaces.

1. Plywood: APA Plyform, Grade B-B, Class 1, 5/8” min. thickness 2. Lumber: Douglas Fir, Standard Grade or better.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

CAST-IN-PLACE CONCRETE - 321313- 2

C. Form Coatings and Parting Compounds: Coating shall be non-grain raising, and non-staining type leaving no residual matter on face of concrete as approved by the City’s Representative. Form coatings containing mineral oils or other non-drying materials will not be permitted.

D. Concrete Reinforcement: Reinforcement Bar and Dowels shall conform to Technical

Specification Section 321312 “Concrete Reinforcing and Miscellaneous Steel”.

1. Ancillary Materials: Provide as required, including spacers, chairs, ties, wires, and other devices necessary for properly assembling, placing and supporting reinforcement bars in place. Supports other than of concrete or ferrous metals are not permitted.

E. Curing Compound: Curing compound shall conform to the specifications of AASHTO

Designation M148, Type II, clear, and shall consist of a practically colorless impervious liquid which will thoroughly seal the surface of the concrete and will not impart a slippery surface thereto. The quality and quantity to be used shall be approved by the City’s Representative. The use of any membraned material which would impart a slippery surface to the concrete or alter its natural color will not be permitted. The colorless, impervious liquid shall contain not less than twenty-five percent (25%) solids.

F. Water: Water shall be clean, free from oil, acid, alkali or vegetable matter.

PART III – EXECUTION

3.1 INSTALLATION

A. Subgrade Preparation

1. The subgrade shall be constructed true to grade, as shown on the Drawings, and in

conformance with Basketball Court Pavement Recommendations, ENGEO Geotechnical, Project No.: 12622.000.000.

2. The required thickness of aggregate baserock shall be placed to the depths as indicated on the Drawings. Compact to ninety-five percent (95%) relative compaction under paving areas as tested in conformance with Test Method No. California 216.

B. Construction of Forms: Forms shall be carefully set to alignment and grade and shall conform

to the required dimensions. Forms shall be held rigidly in place by stakes and/or form ties. Clamps, spreaders, rods and braces shall be used where required to insure rigidity in the forms to prevent deformation in the forms. Forms shall be installed with tight joints accurately to line, level and plumb, and clean.

1. Wood forms shall be surfaced on the side placed next to the concrete and shall not be less

than five-eight inches (5/8") thick after being surfaced and thoroughly coated with form oil.

C. Concrete Reinforcement: Install in accordance Technical Specification Section 321312 “Concrete Reinforcing and Miscellaneous Steel” and as shown on Drawings.

1. Hold all reinforcement bars three inches (3”) clear from paving edges, as shown on the

Drawings. 2. Where new concrete work conforms to existing concrete work, steel dowels (No. 4

reinforcement bars) shall be placed into the existing sidewalk or curb. D. Concrete Placement

1. No concrete shall be placed until formwork, vertical sleeves, and all required embedded

items have been reviewed and approved by the City’s Representative.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

CAST-IN-PLACE CONCRETE - 321313- 3

2. No concrete shall be placed when the air temperature is below forty degrees Fahrenheit (40°F) or during rain.

3. No concrete shall be placed within three (3) hours of sunset. 4. Before placing concrete, form faces shall be thoroughly coated with form oil. 5. Before placing concrete, the aggregate base shall be properly dampened with water to

insure no moisture will be absorbed from the fresh concrete. 6. Immediately before placing concrete, the Contractor shall check and adjust dimensioning,

positioning, supports, sleeves and anchorages. 7. The bottoms of all excavations shall be undisturbed soil properly leveled and moist before

receiving concrete. 8. Concrete shall be placed and compacted into forms by means of mechanical vibrators

without segregation. Vibrators shall not be placed against forms or reinforcement bars and shall not be used to move the material.

9. After the concrete for paving has been placed, a strike-off shall be used to bring the surface to the proper elevation when compacted. It shall be spaded along the form faces and tamped to assure a dense and compact mass, and to force the larger aggregate down while bringing to the surface not less than 3/8 inch of free mortar for finishing purposes.

10. Final finishing operations shall not proceed until all bleed water has evaporated from the surface. Sprinkling of dry cement to absorb excessive surface moisture shall not be allowed.

E. Weakened Planed Joints and Score Lines: Locate in concrete paving where indicated on the

Drawings.

1. Weakened Plane Joint and Score Lines shall be straight and placed at right angles to the paving line and extended into the thickness of the concrete.

2. Weakened Plane Joints shall be scored one inch (1”) depth within the concrete and finished with a tooled ¼” smooth radius edger at intervals as indicated on Drawings

3. Score Lines shall not exceed ¼” in depth within the concrete and finished with a smooth ¼” radius edger tool.

4. Maximum delay between successive pours shall not exceed the time of initial set unless a construction joint is installed.

F. Curing

1. Immediately after placement, protect concrete from premature drying. Fog spray with water

until otherwise protected. 2. Forms shall be wetted and exposed surfaces kept continuously wet for seven days.

G. Removal of Forms: Side forms for paving shall not be removed in less than twenty-four (24) hours after the concrete has been finished, unless otherwise directed by the City’s Representative.

H. Concrete Protection

1. Contractor shall provide all necessary protection devices to protect all curing and

completed concrete work from foot traffic and damage, including gouging and graffiti marks. 2. Conduct the work operations to eliminate any danger of rust stains from formwork materials

onto exposed concrete surfaces.

I. Concrete Flatwork

1. Flatwork shall be formed in place. See Specification Section 321000 for ‘Aggregate Base’. 2. Concrete flatwork for paving adjacent to existing curb or sidewalk respectively, shall be tied

in with metal dowels.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

CAST-IN-PLACE CONCRETE - 321313- 4

a. Dowels shall be No. 4 reinforcement bars with a minimum length of twelve inches (12") and shall be installed at twenty-four inches (24") on-center. Insert dowels to a minimum penetration of four inches (4") into the existing curb or sidewalk. Dowels shall fit tightly into the existing concrete.

3. After the concrete has been placed and consolidated, the surface of the concrete shall receive a preliminary finish. The preliminary finish shall consist of carefully striking off the surface of the concrete with a template or strike board until a uniform surface is obtained. The form on the face of paving shall not be removed while the concrete is sufficiently plastic to slump.

4. Prior to removal of the forms, the surface shall be finished true to grade by means of a straight edge float, operated over the surface of the concrete. Form clamps shall be so constructed as not to interfere with the operation of this float.

5. The finished surface shall receive a uniformly coarse traverse scored texture by drawing a nylon broom across a floated finish. Lines shall be of scored of uniform depth within the concrete surface, straight, parallel and at right angles to the direction of traffic, unless indicated otherwise. The finished broom surface shall be free from blemishes, humps, sags or other irregularities.

6. Any major defects found in the concrete paving shall be repaired by removing and replacing the entire unit between score lines or joints, as directed by the City’s Representative.

7. All discolored concrete paving shall be cleaned to a uniform color. Repairs and cleaning of new concrete shall be at the expense of the Contractor.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PAVEMENT MARKINGS - 321723 - 1

SECTION 321723

PAVEMENT MARKINGS

PART I - GENERAL

1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

Furnish all labor, materials, equipment, transportation and services to complete the preparation, layout and painting of basketball court playing lines as shown on the Drawings and/or specified herein.

1.3 SUBMITTALS

A. Procedures: Furnish certificates of compliance, product data and manufacturer’s installation

instructions as required in this section. Clearly designate which portions of literature are applicable where more than one product is shown. Provide 3 copies of each. All submittals for this section of work shall be forwarded in a single package to Engineer within 15 days of award of contract.

B. Product Information: Provide manufacturer’s descriptive literature and specifications for all

materials, coatings, and equipment to be furnished and installed under this portion of the work. PART II – MATERIALS

2.1 MATERIALS

Playing Line Paint (Basketball): Traffic paint suitable for painted traffic stripes and pavement markings (non-thermoplastic paint) per CalTrans Standard Specifications Section 84-3 “Painted Traffic Stripes and Pavement Markings”. Color: White.

PART III – EXECUTION

3.1 PREPARATION

Layout of Work: Prior to application of the striping, accurately mark the location of striping for review and approval by City representative, prior to proceeding with the application work.

3.2 APPLICATION

A. Entire work surface shall be completely clean and dry prior to layout of playing lines.

B. Apply paint in accordance with CalTrans Standard Specifications Section 84-3 “Painted Traffic

Stripes and Pavement Markings”.

C. Playing Lines: Standard dimensions shall be two inches (2”) wide, 2 coats.

D. Protect area from traffic, and do not open for use for at least 24 hours after finish surface has dried completely.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

FENCING - 323100 - 1

SECTION 323100

FENCING

PART I - GENERAL

1.1 DOCUMENTS

The General Conditions and all other Contract Documents for this project are complementary and applicable to this Section of the Specifications.

1.2 SCOPE OF WORK

Furnish all labor, materials, equipment, facilities, transportation and services to complete all fencing and related work as shown on the Drawings and/or specified herein.

1.3 QUALITY ASSURANCE

Fence shall be erected by skilled mechanics in accordance with the best practice of the trade. Chain link fence shall be erected in accordance with the recommendations of the Chain Link Fence Manufacturer's Institute.

1.4 REFERENCES AND REGULATORY REQUIREMENTS

ASTM A120 – Standard Specification for Pipe, Steel, Black and Hot-Dipped Zinc coated (galvanized) Welded and Seamless, for Ordinary Uses ASTM A123-84 – Standard Specification for Zinc Coating (Hot-Dip Galvanized) on Iron and Steel Products ASTM A153-84 - Standard Specification for Zinc Coating (Hot-Dip Galvanized) on Iron and Steel Hardware

ASTM A392-84 - Standard Specification for Zinc Coating Steel Chain Link Fence Fabric.

Chain Link Fence Manufacturer’s Institute (CLFMI) Industrial Steel Guide for Fence, Rails, Posts, Gates and Accessories

California State Standard Specification Section 80-3 and Standard Plans (A85)

1.5 SUBMITTALS

A. Procedures: Furnish certificates of compliance, product data, shop drawings, manufacturer’s

installation instructions and samples as required in this section. Clearly designate which portions of literature are applicable where more than one product is shown. Provide 3 copies of each. All submittals for this section of work shall be forwarded in a single package to Engineer within 15 days of award of contract.

B. Product Information: Provide manufacturer’s descriptive literature and specifications for all

materials, coatings, fittings and equipment to be furnished and installed under this portion of the work.

1. Galvanizing certification 2. Installation Instructions: Submit as applicable.

C. Shop Drawings: Submit complete shop drawings for all fencing systems including, but not

limited to all information addressing dimensions, clearances, connections, components and any

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

FENCING - 323100 - 2

miscellaneous related appurtenances addressing complete fabrication and hardware for approval.

1.6 SEQUENCING AND SCHEDULING

Contractor shall coordinate fencing installation and related work with paving and all other work.

PART II - MATERIALS

2.1 GENERAL

All fencing, by area, is intended to receive the same finish coating wherever possible. Nuts, bolts, etc. shall be coated to match fencing system.

2.2 CHAIN LINK FENCE

A. Wire: Conform to CLFMI Product Manual and ASTM A392, Class 1. Furnish one-piece fabric

widths. 1. Galvanized Wire: Two (2) inch, 9 gauge GAW (0.148 inch diameter, galvanized after

weaving) mesh zinc coated wire with not less than 1.2 oz. per sq. ft., knuckle finished top and bottom.

B. Fence Framework: Strength requirements for posts and rails shall conform to ASTM F699. Pipe

shall be straight, true to section, material and sizes specified. 1. Galvanized Fence: All posts and rails to be galvanized Sch. 40 pipe. Grade A (1.8 oz. full

weight) with post tops to exclude moisture.

BALLFIELD SIDELINE FENCE

FENCE UNDER BASKETBALL HOOP

FENCE HEIGHT Match Existing 6’

FABRIC Match Existing 6’ width, 2” mesh

POST SPACING (MAXIMUM)

8’ o.c. 8’ o.c.

LINE POST Match Existing 2 3/8” O.D.

CORNER OR TERMINAL POST

Match Existing 2 7/8” O.D.

TOP, BOTTOM & CENTER HORIZONTAL RAILS

Match Existing 1 5/8” O.D.

FENCE POST FOUNDATION

12” dia. x 4’ depth conc. (3’ min. post embedment)

12” dia. x 4’ depth conc. (3’ min. post embedment)

C. Top and Bottom Horizontal Rails: Provide as indicated. Where center rails are required, top and

bottom panels shall have trusses.

D. Fittings and Accessories: Conform to Federal Specification Section RRF-191-4. Comply with ASTM F626.

1. Tension Wire: Class 3, 7-gauge (0.177 inch diameter) coil spring steel with finish to match

fabric.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

FENCING - 323100 - 3

2. Tie Wires: 9 gauge (0.148 inch diameter) steel with finish to match fabric. 3. Post and Line Caps: Provide weather tight closure cap for each post. Provide line posts

with loop to receive wire or top rail with finish to match fabric. 4. Tension Bars: Hot-dip galvanized steel with minimum length 2 inches less than full height of

fabric, minimum cross-section of 3/16 inch by ¾ inch and minimum of 1.2 oz. zinc coating per sq. ft. of surface area.

5. Tension Clips: Minimum ¾ inch wide 12-gauge (.105 inch) thick with finish to match fabric. 6. Truss Rods: Hot dipped galvanized steel rods with a minimum 5/16” diameter

2.2 CONCRETE

Concrete Footing: Conform to Drawings and Concrete Specification Section.

PART III - EXECUTION

3.1 PREPARATION

Prior to excavation, layout all fencing locations for review and acceptance by Engineer. For property line fences, verify locations of surveyed property corner markers to confirm fence is located within property. Locate all adjacent underground utilities before excavating post holes.

3.2 INSTALLATION

A. Install in conformance with ASTM F567. Do not begin installation and erection before layout is

approved. Conform to layout shown on Drawings, except as modified by Engineer. B. Erect in strict conformance with reviewed and accepted Submittals, Shop Drawings, and

manufacturer’s recommendations. C. Footings: Drill or hand-excavate holes for posts to diameter and spacing indicated in firm,

undisturbed or compacted soil. Center and align posts in holes above bottom of excavation as detailed. Install footing in conformance with Drawings and Concrete Specifications Section. Crown footings to shed water.

D. Posts shall be vertical and plumb. All posts shall be spaced at equidistant intervals as shown

on plans, measured from center-to-center of posts.

E. Setting Posts: Center and align posts in holes above bottom of excavation as detailed.

3.3 CHAIN LINK FENCE

A. Top Rails: Run rail continuously through line posts caps forming a continuous brace within each

stretch and securely fasten to terminal posts. Provide expansion couplings as recommended by fence manufacturer. Splices in top rail shall be made with couplings at maximum 20’spacing. Every fifth coupling in a stretch shall be made with a heavy spring to allow for expansion and contraction of rail.

B. Bottom and Mid Rails: Clamp rails between posts with fittings.

C. Fabric: Install fabric on infield or primary use side of fence (unless noted otherwise), and anchor

to framework so that fabric remains in tension after pulling force is released, free from sags and bulges. Pull fabric taut and tie to posts, rails, and tension wires. Attach fabric to line posts using bands or clips spaced 14” apart maximum, and to top rails and tension wires with wire ties at 24” apart maximum. At all corners and vertical ends of fabric, install stretcher bars banded to posts and gate frames at 24” maximum. Fabric and bottom rails shall be two to four inches

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

FENCING - 323100 - 4

clear from finish grade unless otherwise indicated. D. Brace Assemblies: Install braces so posts are plumb when diagonal rod is under proper

tension. E. Tension Wire: As applicable, install at bottom of fabric (and at top if top rail is not specified) as

shown in Drawings. Install tension wire before stretching fabric and attach to each post with ties. Secure wire to fabric with 12.5 gauge hog rings at 24” on center maximum.

F. Tension Bars: Provide one bar for each end post, and two for each corner and pull post, except

where fabric integrally woven into post. Thread through fabric, and secure to end, corner, pull, and gate posts with tension clips spaced not over fifteen (15) inches on center.

G. Tie Wires: Use U-shaped wire of proper length to secure fabric firmly to posts and rails with

ends twisted at least 2 full turns. Bend ends of wire to minimize hazard to persons or clothing. Tie fabric to line posts 12 inches maximum on center and to rails and braces 24 inches maximum on center.

H. Fasteners: Install nuts for tension clips and hardware bolts on side of fence opposite fabric

side. Peen ends of bolts or score threads to prevent removal of nuts.

I. Welding: All welds shall be shop fabricated prior to galvanizing unless otherwise acceptable to City’s Representative. Any and all field welds shall be completed by a Certified Structural Welder and shall be “spray-galvanized” or otherwise treated subject to the discretion of the City’s Representative.

3.4 CONCRETE

Concrete Bands, Footings and Formwork: Conform to Drawings and Concrete Specifications Section. Crown footings to shed water.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

SITE FURNISHINGS - 324000 - 1

SECTION 324000

SITE FURNISHINGS

PART I - GENERAL

1.1 SCOPE OF WORK

Furnish and install site furnishings including basketball pole, backboard and rim including associated concrete footing.

1.2 SUBMITTALS

Manufacturer’s Literature: Furnish manufacturer’s literature, “cut-sheets”, and manufacturer’s installation instructions for each factory-fabricated product and accessories required. Include manufacturer’s recommendations for maintenance of items to be installed. It is the responsibility of the Contractor to obtain installation recommendations from the manufacturer.

1.3 QUALITY ASSURANCE

Code Requirements: Comply with requirements of applicable codes.

1.4 DELIVERY, STORAGE AND HANDLING

Store materials safely and securely, protected from weather, theft, vandalism or other damage. Prevent damage to or staining of site surfaces of other materials.

1.5 PROJECT CONDITIONS

A. Become familiar with site conditions, access and existing on-site and adjacent improvements. B. Protect existing improvements. Replace or repair to original condition improvements that are

damaged during operations or by malfunction of installed items.

1.6 COORDINATION

A. Coordinate delivery and installation of items to be embedded in concrete work. B. Furnish to other trades details, templates, dimensional tolerances or other information required

for coordination of work.

PART II - MATERIALS

2.1 SITE FURNISHINGS

A. General: Site furnishings shall be as specified on the plans and details. When requesting to substitute a product, it is the Contractor’s responsibility to provide a detailed side by side comparison of the specified item and the proposed substitution to demonstrate equality of size, style, finish, quality and strength.

B. Basketball Pole, Backboard and Rim : “Legend Playground” post, backboard and rim:

1. Post: FT1106 heavy-duty fixed height steel post, 6” square x 3/16” wall steel tubing, with

FT1850 Legend 66” extension arm. Color: Black powder-coated. 2. Backboard: FT260 42”x60” steel backboard, white powder-coated.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

SITE FURNISHINGS - 324000 - 2

3. Rim and Net: FT172D unbreakable fixed goal, orange powder-coated goal with nylon net. 4. Manufacturer: First Team Sports, www.firstteaminc.com, 800.649.3688. Available thru L&M

Distribution, 415-459-5565. 5. Warranty: Lifetime Unconditional Warranty.

2.2 MISCELLANEOUS ITEMS

A. Concrete Footings and Pads: Poured-in-place concrete per relevant specification sections. B. Hardware: As provided by manufacturer, unless otherwise noted.

PART III - EXECUTION

3.1 PREPARATION

A. Inspection: Examine subgrades, finished surfaces and installation conditions. Do not start site

furnishings work until unsatisfactory conditions are corrected. B. Remove loose material and debris from base surface before placing site furnishings. C. Locate all site furnishings and obtain the City’s acceptance of layout prior to installation.

3.2 INSTALLATION

A. Concrete Footings and Pads: Poured-in-place concrete and reinforcing as per relevant

sections in these specifications. B. Manufactured Items: Install in accordance with Drawings and in conformance with

manufacturer’s recommendations. Notify the City’s Representative immediately if any conflicts or discrepancies are encountered. Unless otherwise notes, install all site furnishings with their concrete footings sufficiently below finish grade to allow for installation of specified finish materials above.

C. Erect work square, set products accurately in location, alignment, plumb, level and true, and

free from defects detrimental to appearance and performance.

D. Restore protective coverings that have been damaged during shipment or installation of the work. Remove protective coverings only when there is no possibility of damage from other work yet to be performed at the same location.

E. Cleaning: Clean during installation of the work and upon completion of the work. Remove all

excess materials, debris and equipment for site. Repair damage resulting from site furnishings installation work.

3.3 FINAL ACCEPTANCE

A. Protect work from damage or theft until Final Acceptance. Repair or replace damaged work to

original condition. B. At Final Acceptance, site furnishings shall be in place, clean, in perfect condition and ready for

use.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 1

SECTION 328000

IRRIGATION

PART I - GENERAL

1.1 SCOPE

Order and furnish all labor, materials, supplies, tools and transportation and perform all operations in connection with and reasonably incidental to the complete installation of the sprinkler irrigation systems as shown on the Drawings. The work shall include, but shall not necessarily be limited to, the following:

A. Trenching, stockpiling excavation materials and refilling trenches. B. Furnishing materials and installation for complete system including piping, valves, fittings,

sprinkler heads, battery-operated controller, and final adjustment of heads to insure complete coverage. Submittal of data for all equipment required by these specifications or on the drawings.

C. Replacement of unsatisfactory materials. D. Clean-up, inspection and approval. E. All work of every description mentioned in the Specification and/or addenda thereto, and all

other labor and materials reasonably incidental to the satisfactory completion of the work, including clean-up of the site, as directed by the Architect.

F. Tests. G. Record Drawings.

1.2 WORK SPECIFIED UNDER OTHER SECTIONS

Consult all other sections to determine the extent and character of the work specified elsewhere but related to that included in this section. Work specified herein shall be properly coordinated with that specified.

1.3 RULES AND REGULATIONS

A. All work and materials shall be in full accordance with the latest rules and regulations of the

National Electrical Code, the Uniform Plumbing Code published by the Western Plumbing Officials Association, and other applicable state or local laws or regulations. Nothing in these Drawings or Specifications is to be construed to permit work not conforming to these codes.

B. When the Specifications call for materials or construction of a better quality or larger size than

required by the above-mentioned rules and regulations, the provision of the Specifications shall take precedence over the requirements of the said rules and regulations.

C. The Contractor shall furnish, without any extra charge, any additional material and Labor when

required by the compliance with these rules and regulations, though the work be not mentioned in these particular Specifications or shown on the Drawings.

D. The Contractor shall erect and maintain barricades, guards, warning signs and lights as

necessary or required by OSHA regulations for the protection of the public or workmen.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 2

E. Any existing buildings, equipment, piping, pipe-covering sewers, sidewalks, landscaping, etc., damaged by the Contractor during the course of his work shall be Replaced or repaired by the Contractor in a manner satisfactory to the Architect, at the Contractor's own expense and before the final payment is made. The Contractor shall be responsible for damage caused by leaks in the piping systems being installed or having been installed by him. He shall repair at his own expense all damage so caused in a manner satisfactory to the Architect.

F. The Contractor shall pay for all required fees, licenses and permits.

1.4 SUBMITTALS

A. Material List: Within fifteen (15) days after award of contract, submit to City’s Representative

three (3) copies of a complete list of all materials to be used on the project, specifying manufacturer, catalog number, size, etc. Catalog data and full descriptive literature must be submitted whenever the substitution of items different than those specified is proposed. This shall in no way be construed as allowing substitution of any specified item.

B. Substitutions: If substitutions of materials specified are requested, submit catalog literature for each item and a statement indicating reason for substitution. Provide the amount of cost savings if substitution is approved. No substitution shall be installed without prior written approval of City’s representative.

C. Record Drawings:

1. The Contractor shall maintain in good order in the field office one (1) complete set of black

line prints of all sprinkler drawings which form a part of the Contract, showing all water lines, quick couplers, sprinklers, valves, controllers and stub-outs.

2. In the event any work is not installed as indicated on the Drawings, such work shall be corrected and dimensioned accurately from the permanent site feature on these record Drawings.

3. Upon completion of the work, obtain reproducible prints from the Landscape Architect and neatly correct the prints to show the as-built conditions.

1.5 INSTRUCTION

After the system has been installed and approved, the Contractor shall instruct the City’s Representative in complete operation and maintenance of the irrigation system.

PART II - PRODUCTS

2.1 MAIN LINES

Main Lines: PVC 1120-Schedule 40 plastic pipe. Join lengths of pipe by means of integrally formed bell end on pipe or by using Schedule 40 PVC solvent weld couplings on Schedule 40 pipe. At changes in direction or branch mains, use appropriate Schedule 40 PVC solvent weld fittings as approved by the Uniform Plumbing Code.

2.2 LATERAL LINES

Lateral Lines (non-pressure): 3/4" and larger shall be 1120-Schedule 40 PVC plastic pipe. All lateral lines shall be connected with Schedule 40, Type I, Grade I, PVC solvent weld fittings.

2.3 CONNECTIONS

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 3

Connections between main lines and RCV's shall be of schedule 80 PVC (threaded both ends) nipples and fittings.

2.4 RISERS

Risers shall be Schedule 80 PVC threaded nipples and Schedule 80 PVC ells as shown in the construction details. Offset risers shall be Cobra connector Model CC-600 (1/2"x6").

2.5 QUICK COUPLER VALVES

Quick coupler valves shall be as listed on the Construction Drawings.

2.6 CONTROLLER

Controller and valves shall be as listed on the Construction Drawings.

2.7 BOXES

A. Boxes for remote control valves shall be Carson 1419 with plastic bolt-down lids. Boxes for

gate valves shall be 10 inches diameter, Carson 910, or equal. B. ID Tags for Valve boxes: Attach a laminated fiberglass tag to each valve box lid that identifies

each valve by number or type. Minimum tag size: 4.5” x 2.25” x1/8”. Face color shall be black. Each tag shall have 4-3/16” holes at each corner and shall be attached to the valve box lid with 1/8"”pop rivets or stainless steel bolts or sheet metal screws. Tags shall have a 20 year warrantee. The top part of the tag shall be lettered “IRRIGATION VALVE” in 24 pt. Helvetica letters, the valve number or type in the center (ie, “B-17”; “QUICK COUPLER”). Tags available through Best Mfg. Co. 1-800-235-2378.

C. Provide identification tags on all valves indicating zone and valve number. D. Do not identify boxes or valves until identification system has been accepted.

2.8 SPRINKLER HEADS

Make and catalog number conform shall conform to the Drawings.

2.9 REMOTE CONTROL VALVES

Remote control valves shall be as listed on the drawings.

2.10 MISCELLANEOUS INSTALLATION MATERIALS

A. If needed, solvent cement and primer for solvent weld joints shall be of make and type

approved by manufacturer(s) of pipe and fittings. Cement shall be maintained at proper consistency throughout use.

B. If needed, pipe joint compound shall be teflon paste or approved equal.

C. Provide to the City of Berkeley, at completion of the maintenance period, three (3) each of all

operating and servicing keys and wrenches required for complete maintenance and operation of all heads and valves. Include all wrenches necessary for complete disassembly of all heads and valves.

PART III - EXECUTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 4

3.1 SUPERVISION AND WORKMANSHIP

The Contractor, personally or through an authorized and competent representative, shall supervise the work constantly and shall, as far as possible, keep the same foreman and workmen on the job from commencement to completion. The workmanship of the entire job must in every way be first class, and only experienced and competent workmen will be allowed on the job.

3.2 LAYOUT

The Contractor shall stake out the irrigation system as shown on the Drawings. These areas shall be checked by the Contractor and the Landscape Architect before construction is started. Any changes, deletions or additions shall be determined at this check.

3.3 PREPARATION

Schedule and coordinate placement of materials and equipment in manner to effect the earliest completion of work in conformance with construction and progress schedule.

3.4 HANDLING AND STORAGE

A. Protect work and materials from damage during construction and storage. B. Handle plastic pipe carefully; especially protect it from prolonged exposure to sunlight.

3.5 LAYOUT

A. Layout of Work

1. Stake our irrigation system as accurately as possible in accordance with diagrammatic

drawings. . Check all Drawings and make work conform to all conditions shown thereon. Exact locations shall be determined on the job to suit actual conditions; verify with City's representative any variations. Do not scale drawings. Locations so determined are the Contractor's responsibility and changes required because of such actions shall be by Contractor at no extra cost to City.

2. Run pipe lines and automatic control wiring in common trenches wherever practical.

B. Adjusting of Existing Irrigation 1. Connect to existing main line as shown. Cap existing lateral lines outside of the

construction zone that service the large turf rotors that will be relocated during construction. 2. The remaining irrigation to the ballfield is to remain operational during construction.

Contractor is responsible to coordinate with the City representative on the adjustment of the full circle rotors to maintain adequate coverage to the field around the construction fencing.

3. Contractor shall locate and protect in place all existing mainline, valves, and quick couplers shown on the plans to remain in service during construction. Any damage to these items will be the responsibility of the contractor to repair or replace.

3.6 EXCAVATING AND TRENCHING

A. Excavation shall be in all cases ample in size to permit the pipes to be laid at the elevations

intended and to permit ample space for joining. B. Make trenches for pipe lines deep enough to provide minimum cover from finish grade as

shown on the drawings.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 5

1. Provide 18-inch minimum cover over main lines to control valves and quick Coupling valves.

2. Provide 18-inch minimum cover over control wires from controller to valves. 3. Provide 12-inch minimum cover over RCV controlled lines to sprinkler heads. 4. Provide 24-inches minimum cover over any lines under vehicular paving.

C. Restore surfaces, existing underground installations, etc., damaged or cut as result of

excavations, to original conditions in manner approved by Landscape Architect.

D. Where other utilities interfere with irrigation trenching and pipe work, adjust the trench depth as instructed by the Landscape Architect.

3.7 ASSEMBLING PIPE LINES

A. All pipe shall be assembled free from dirt and pipe scale. Field cut ends shall be reamed only to

full pipe diameter with rough edges and burrs removed.

B. Solvent Weld Joint 1. Prepare joint by first making sure the pipe end is square. Then, deburr the pipe end, and

clean pipe and fitting of dirt, dust and moisture. 2. Dry insert pipe into fitting to check for mis-sizing. Pipe should enter fitting 1/3 to 2/3 depth

of socket. 3. Coat the inside socket surface of the fitting and the male end of the pipe with P-70 primer

(manufactured by Weld-On). Then without delay, apply Weld-On 711 cement liberally to the male end of the pipe and also apply 711 cement lightly to the inside of the socket. At this time, apply a second coat of cement to the pipe end.

4. Insert pipe immediately into fitting and turn 1/4 turn to distribute cement and remove air bubbles. The pipe must seat to the bottom of the socket and fitting. Check alignment of the fitting. Pipe and fitting shall be aligned properly without strain to either.

5. Hold joint still for approximately thirty (30) seconds and then wipe the excess cement from the pipe and fitting.

6. Cure joint a minimum of thirty (30) minutes before handling, at least six (6) hours before allowing water in the pipe.

C. Threaded Joint

1. Field-threading of plastic pipe or fittings is not permitted. Factory-formed Threads only will

be permitted. 2. Factory-made nipples shall be used wherever possible. Field-cut threads in metallic pipe

will be permitted only where absolutely necessary. When field-threading, cut threads accurately on axis with sharp dies.

3. All threaded joints shall be made up with pipe joint compound. Apply compound to male threads only.

4. Where assembling metallic pipe to metallic fitting or valve, no more than three (3) full threads shall show when joint is made up.

5. Where assembling to threaded plastic fitting, take up joint no more than one full turn beyond hand-tight.

6. Where assembling soft metal (brass or copper) or plastic pipe, use strap-type friction wrench only; do not use metal-jawed wrench.

D. Cap or plug openings as pipeline is assembled to prevent entrance of dirt or obstruction.

Remove caps or plugs only when necessary to continue assembly. E. Where pipes or control wires pass through sleeves, provide removable non-decaying plug at

ends of sleeve to prevent entrance of earth.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 6

3.8 REMOTE CONTROL VALVES

A. Install where shown and group together where practical. Limit one (1) RCV per valve box. B. Install valves no farther than 12 inches from main lines unless absolutely necessary. C. Thoroughly flush main line before installing valve. D. Install in shrub or ground cover areas where possible.

3.9 AUTOMATIC CONTROLLER

Install as shown on Drawings.

3.10 SPRINKLER HEAD AND QUICK COUPLING VALVE

A. After all sprinkler piping and risers are in place and connected, and prior to installation of sprinkler heads or QCVs, control valves shall be opened and a full head of water used to flush out the system.

B. Locate heads and QCVs as designated on the drawings. Adjust heads for proper distribution

and trim. C. Install sprinkler heads at their permanent elevations as shown on drawings. Any adjustment

necessary due to settlement shall be made during maintenance period.

3.11 TESTING

A. The Contractor shall perform test as specified. Remake any faulty joints with all new materials. Use of cement or caulking to seal leaks is absolutely prohibited.

B. Pressure Testing (prior to backfilling pipe trenches):

1. Notify City’s representative at least three (3) days in advance of testing. 2. Perform testing at his own expense. 3. Center load piping with small amount of backfill to prevent arching or slipping under

pressure. No fitting shall be covered. 4. Apply the following tests after welded plastic pipe joints have cured at least 24 hours:

a. Test live (constant pressure) and QCV lines hydrostatically at 125 psi minimum. Lines will be approved if test pressure is maintained for six (6) hours. The Contractor shall make tests and repairs as necessary until test conditions are met.

b. Test RCV-controlled lines with water at line pressure and visually inspect for leaks. Retest after correcting defects.

C. Coverage Test: Upon completion of irrigation system, Contractor, in the presence of City's

representative shall perform a test that indicates water coverage of planting areas is complete and adequate. Furnish all materials and perform all work required to correct any inadequacies disclosed. Inform City's representative of any deviation from the Drawings required due to wind, planting, soil or site conditions that bear on proper coverage.

3.12 BACKFILLING

A. Backfill only after piping has been inspected and approved.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 7

B. Backfill material shall be the earth excavated from the trenches, free from rocks, concrete chunks and other foreign or coarse materials. Carefully select backfill that is to be placed next to plastic pipe to avoid any sharp objects which may damage the pipe.

C. All pipe under asphalt paving shall be backfilled with 4 inches of clean sand on all sides of pipe. D. Place backfill materials in six (6) inch layers and compact by jetting or tamping to a minimum

compaction of 90 percent of original soil density.

E. Dress off areas to finish grades and remove excess soil, rocks or debris remaining after backfill is completed.

F. If settlement occurs along trenches, and adjustments in pipes, valves and sprinkler heads, soil,

sod or paving are necessary to bring the system, soil, sod or paving to the proper level or the permanent grade, the Contractor, as part of the work under this Contract, shall make all adjustments without extra cost to the City.

3.13 EXISTING EQUIPMENT

Remove all existing above ground irrigation within the scope of this project that is not in use.

3.14 INSPECTION

The Contractor shall be subject to inspections at any and all times by authorized representatives of the City.

3.15 MAINTENANCE

A. Maintain the irrigation system during the progress of the work and for a period of 60 days after

completion or until final acceptance. B. Proper irrigation system maintenance includes the overall supervision of the system, controller

scheduling, routine adjustments and necessary repairs. C. Water: Do not apply water at a rate higher than the infiltration rate of the soil. Regularly utilize a

soil probe to evaluate actual soil moisture levels and irrigation schedule. D. Regularly observe irrigation system operation and make any repairs or adjustments necessary

to maintain effective watering of the plant material. 1. Visual Review: Inspect irrigated areas for unusually wet or dry areas.

2. System Operation: Operate each controller station and visually inspect each dripline are for uniform wetting patterns.

3. Spray Heads: Clean and adjust as required for proper coverage. All replacement heads shall be of same manufacturer, type and application rate.

4. Controller Program: Comprehensively review controller program with consideration for water conservation, overall site conditions, seasonal changes and plant requirements. In windy areas, set controller to operate during periods of low wind velocity. Adjust watering schedule so as not to interfere with the use of the facility. Maintain a record of current irrigation programs, including day, time and length of watering for each station and program for each controller. Flag all areas that appear to be abnormal and make required repairs or adjustments.

5. Valve Operation: Visually inspect valves and components for leaks. Make required repairs or adjustments.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

IRRIGATION - 328000 - 8

E. Repair and Replacement: Any faulty equipment or damage to the system not caused by the Contractor's negligence or operations shall be promptly reported to the City, together with an estimate of costs for repairs. Emergency repairs necessary for the continued viability of the plant material shall be completed without prior authorization.

PART IV - GUARANTEE 4.1 REPAIR

It shall be the responsibility of Irrigation Contractor to fill and repair all depressions and replace all necessary lawn and planting due to the settlement of irrigation trenches for one (1) year following completion and acceptance of the job.

4.2 DEFECTS

The Contractor shall also guarantee all materials, equipment and workmanship furnished by him to be free of all defects of workmanship and materials and shall agree to replace at his expense, at any time within one (1) year after installation is accepted, any and all defective parts that may be found.

END OF SECTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 1

SECTION 329000

PLANTING

PART I - GENERAL

1.1 SCOPE

Furnish all labor, equipment and materials necessary the cultivation, soil preparation, fine grading, planting, mulch installation and landscape maintenance period as shown and specified.

1.2 APPLICABLE DOCUMENTS

The following publications of the issues listed below, but referred to thereafter by basic designation only, form a part of this Specification to the extent indicated by the references thereto:

1. American National Standards Institute (ANSI) Publications (current edition): ANSI A300:

Tree, Shrubs and Other Woody Plant Maintenance - Standard Practices; ANSI Z60.1: Nursery Stock; ANSI Z133.1: Safety Requirements for Tree Pruning, Trimming, Repairing or Removal

1.3 WORK SPECIFIED UNDER OTHER SECTIONS

Consult all other sections to determine extent and character of work specified elsewhere but related to that included in this section. Work specified herein shall be properly coordinated with that specified.

1.4 EQUIPMENT

The Contractor shall at all times furnish and maintain sufficient equipment as necessary to perform the work of this contract. Such equipment shall be subject to the inspection and approval of the City. Note: Gas blowers are not permitted.

1.5 SUBMITTALS

Furnish manufacturer’s literature, laboratory analytical data (soil analysis results and amendment recommendations) as required in this specification section, and samples as noted for the following items:

1. Planting fertilizer(s) 2. Composted Greenwaste Organic Amendment (0.5 cubic foot bag sample) 3. Recycled Mulch (0.5 cubic foot bag sample)

1.6 SUBSTITUTIONS

Any substitutions of materials for any reason shall have prior approval from Landscape Architect.

1.7 DELIVERY, STORAGE AND HANDLING

A. Deliver all items to the site in their original containers with all labels intact and legible. Storage

of materials shall be only in areas designated or as approved by the City’s Representative. B. Handling - Care shall be taken to avoid damaging plants being moved from the nursery or

storage area to the planting site. Plants shall be protected from drying out. Plants shall not be handled by the trunk or stem. Plants shall be protected from freezing or drying out by a

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 2

covering of burlap, tarpaulin, mulching material during transportation from the heeling-in bed to the planting site. Damaged plants shall be rejected and shall be removed from the site.

C. Plants not installed on the day of arrival at the site shall be stored and protected as follows: Outside storage shall be shaded and protected from the sun and wind. Plants stored on the project shall be protected from drying out at all times by covering the balls

or roots with moist sawdust, wood chips, shredded bark, peat moss or other similar mulching material. Plants, including those in containers, shall be kept in a moist condition until planted, by watering. Fertilizer shall not be stored with any landscape materials.

1.8 SITE CONDITIONS

A. Contractor shall familiarize himself with existing site conditions as they may affect his work.

B. Planting of trees, shrubs, vines and ground covers shall be done only during periods which are

normal for such work as determined by the season, weather conditions and accepted practices. C. Water will be provided at the site at no cost to Contractor. Make and remove temporary lines

and connections as necessary for the proper execution of the work.

1.9 GRADING

Contractor shall be responsible for maintaining finish grades in all planting areas and for executing any fine grading as may be necessary or incidental to all planting operations.

1.10 QUALITY ASSURANCE

A. Contractor Qualifications: Provide sufficient experienced workmen and supervisors who shall

be present at all times during execution of this portion of work and who are thoroughly familiar with the type of construction, materials and methods involved. In the acceptance or rejection of the work, no allowance will be made by the Owner for lack of workmen's skill.

B. Requirements of Regulatory Agencies

1. All work to be in accordance with the latest Safety Orders of the Division of Industrial

Safety, O.S.H.A., and applicable State and local laws or regulations. Nothing in the Contract Documents is to be construed to permit work not conforming to these requirements. Furnish without extra charge any additional material and labor required by above.

2. Where conflict exists between requirements of above agencies and/or these Specifications, the more restrictive shall govern.

3. All plants and planting material shall meet or exceed the Specifications of Federal, State, and local laws requiring inspection for plant disease and insect control. All inspection certificates required shall accompany shipments.

C. Source Quality Control: Quality and size shall conform to current edition of "USA Standard for

Nursery Stock" for number one grade nursery stock as adopted by American Associations of Nurserymen. In all cases, botanical names shall take precedence over common names.

1.11 COMPLIANCE WITH CITY OF BERKELEY REQUIREMENTS AND ORDINANCES

City of Berkeley Pest Management Policy: The Contractor shall be aware of the requirements of the City of Berkeley Pest Management Policy and shall select all chemical intended for use on this project in accordance with this policy. In no case shall any chemical be used that has been determined to have evidence of causation of cancer, birth defects, mutations or other severe chronic health effects.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 3

PART II - PRODUCTS

2.1 SOIL AMENDMENTS AND MULCH

First quality, standard brand, agricultural products. Deliver in original containers with brand name marked thereon. Furnish City’s Representative with all certificates or delivery slips for each material delivery in containers or in bulk.

A. Composted Organic Greenwaste Amendment

1. No amendment shall be delivered to the site without prior approval by the City Representative

2. Yard waste compost free of contaminants with pH of 5.5-8.0, minimum organic content of 250 pounds per cubic yard of compost (minimum 50% of compost’s dry weight, TMECC 05.07-A), 35-60% moisture content, salinity measured on the saturation extract solution shall not exceed 8.0 dS/m, maximum 4.0 dS/m Ece, and a minimum of 90% of the material by weight shall pass a ½" screen. Material passing the ½" screen shall meet the following criteria:

Sieve Designation Percent Passing 9.51 mm (3/8”) 85-100% 2.38 mm (No. 8) 50-80% 500 micron (No. 35) 0-40%

3. Carbon to Nitrogen Ratio: Maximum 35:1 if materials claimed to be nitrogen stabilized. 4. Contaminants: Compost shall be free of contaminants such as glass, metal, plastic and

noxious weeds. 5. Maturity: Physical characteristics suggestive of maturity include: Color: dark brown to black. Characterization: Identifiable wood pieces are acceptable but the balance of material

should be soil-like without recognizable grass or leaves. Odor: acceptable = none, soil-like, musty or moldy. Unacceptable = sour, ammonia or

putrid particle 6. Soluble Salts: Soluble nutrients typically account for most of the salinity levels but sodium

should account for less than 25% of the total. To avoid a leaching requirement, the addition of the compost shall result in a final Electrical Conductivity equivalence (ECe) of the amended soil of less than 4.0 dS/m @ 25 degrees C as determined in a saturation extract. Use the following table to determine the maximum allowable ECe (dS/m of saturation extract) of compost at desired use rate and allowable ECe increase.

Desired Use Rate Maximum Allowable ECe Increase from Amendment

Cu. Yds. Amendment per 1000sq. ft.

for incorporation to 6-inch depth

Volume Percentage of Amendment

1 dS/m

2 dS/m

3 dS/m

Maximum ECe of Compost 1 5 14 28 42 2 11 7 14 21 3 16 5 9.5 14 4 22 3.5 7 10.5 5 27 3 5.5 8.5 6 32 2.5 4.5 7

Example: Specification calls for 6 cu. Yards compost per 1000 sq. ft. for incorporation to 6-inch depth, and site soil has an ECe of 2.0. In order to avoid exceeding ECe of 4 in final blend, compost ECe should be less than 4.5 dS/m.

7. Composted Organic Amendment shall have ‘STA’ certification from U.S. Composting Council (USCC). Approved products include Super Humus compost available through BFI

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 4

Organics (408.888.7632), Z-Best Organic Compost (408.263.2384), or equal. Provide certificate of conformance and current analysis for approval.

B. Recycled Mulch: 100% clean recycled chipped wood mulch of uniform enhanced color, free

from weeds, seeds, sawdust and shall not contain eucalyptus, resin, tannin, salts or other compounds detrimental to plant life. Sizes of chipped mulch range of ¾ to 2 inches. Color: dark brown-tan. The mulch supplier shall be a member of the U.S. Composting Council that adheres to the standards of the Seal of Testing Assurance Program (STA).

2.2 SOILS

"On-Site" Topsoil: Topsoil from the site without admixture of subsoil, free from rocks, clay or foreign matter.

2.3 PLANT MATERIAL

A. Furnish plant materials to complete work as indicated on Drawings and as specified. B. Plants shall be typical for variety and species; healthy, vigorous, free from disease and insects,

with healthy normal root systems, filling their containers, but shall not be rootbound. Pruning shall not be done prior to delivery except by approval. Quality and size shall conform to best nursery practice. Nursery grown stock only shall be used.

C. Plants shall be subject to review and approval by the Landscape Architect at place of growth and upon delivery for conformity to Specifications. Such approval shall not impair the right of review and rejection during progress of the work.

1. Submit written request for review of plant material at place of growth to the Landscape

Architect. Written request shall state the place of growth and quantity of plants to be inspected. The Landscape Architect reserves the right to refuse review at this time if, in his judgment, a sufficient quantity of plants is not available for review.

2. Inspection for approval or rejection is reserved for the project site upon delivery. Plants shall be inspected for size, variety, condition, root system and defects. Any rejected material shall be promptly removed from site. Notify City’s Representative 48 hours prior to inspection.

D. Contractor shall be responsible for inspection of plant materials required by the City, County or

State at any time before and during progress of the work. Rejected plants shall be removed from the site immediately.

E. Contractor shall adequately protect plants from sun and wind, on site and in transit. F. Plant label shall identify each species and variety. Substitutions are not desired; requests for

substitution shall be made at least 30 days prior to planting. G. Quantities necessary to complete the work as shown on the Drawings shall be furnished.

Quantities shown on Plant List are approximate only and shown for convenience of the Contractor.

2.4 SUPPLIES

A. Wood Header: Per plan and detail. B. Herbicides and Pesticides: City of Berkeley does not use or allow the use of pesticides. PART III – EXECUTION

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 5

3.1 EXAMINATION

A. Prior to the work of this section, inspect existing grades and installed work of other trades and verify that planting may be completed in accordance with Contract Documents.

B. Should sub-surface drainage or soil conditions (high water table, excessive compaction, etc.) be encountered which would be detrimental to growth or survival of plant material, notify City’s Representative in writing, stating conditions and submitting a proposal covering cost of correction. If the Contractor fails to notify City’s Representative of such conditions, he shall be responsible for plant material under the guarantee clause of this Section.

3.2 PREPARATION

A. Layout of Work: Drawings are to be considered schematic unless specifically dimensioned.

Check all Drawings and make work conform to all conditions shown thereon. Stake out exact plant locations on the job to suit actual conditions. Verify with City’s Representative any variations prior to planting. Locations so determined are Contractor's responsibility and changes required because of such actions shall be by Contractor at no extra cost to the City.

B. Debris & Weed Removal: Remove all construction debris, base rock, refuse and paving

material to full depth where occurs in planting areas. Work area shall be free of weeds, native grasses, Bermuda grass, and Kikuyu grass prior to any planting or soil amendment placement

C. Plant Material Protection: Existing plant material to remain shall be protected from damage.

1. Do not stockpile material or equipment within 25' of dripline of existing trees to remain. 2. Contractor shall take precautions when excavating within tree rootzone. Hand excavation

only is allowed adjacent to surface and subsurface roots of all existing trees to remain. 3. Root Cutting: This work shall be done under direction of City approved Certified Arborist

hired by the Contractor. 4. Do not compact soil within the dripline of existing trees to remain.

D. Header: Install per plan and details. E. Topsoil: "On-site" topsoil shall be used where possible. If there is not sufficient soil available to

meet finish grades, add "import" topsoil to complete grading. F. Soil Preparation and Topsoil Placement

1. Do not work soil when moisture content is so great that excessive compaction will occur or

when clods will not break readily. Apply water, if necessary, to bring soil to an optimum moisture content for tilling and planting.

2. Subgrade Preparation: Following completion of rough grading, when planting areas are free from weeds, rip and scarify subgrade in all planting areas to a depth of eight inches (8”) and cultivate to a loose friable condition, free of clods. Extreme care shall be taken to work around planting marked to be saved. Remove all stones 3/4" or larger, dirt clods, debris. This procedure shall provide friable soil, continuously, to specified depth.

G. Finish Grading

1. Do not place topsoil in the drip line of any existing tree. 2. Grades shall conform to those indicated on the Drawings and herein specified. Slope soil

areas adjacent to buildings away from buildings. Finish grades shall be uniform levels or slopes between points where elevations are given or established by paving, curbs, catch basins, existing trees to remain. Grades shall be smooth, uniform planes with no abrupt

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 6

changes. All grades shall provide for natural runoff of water without pockets. Accurately set flow line grades to a minimum of 2% gradient. Compact topsoil to 80% maximum relative compaction.

3. Planting area finish grade shall be one inch (1”) below top of header, pavements, walks and curbs. Particular attention shall be given to the installation of surface drainage swale.

H. Soil Amendment: After topsoiling has been completed and soil water settled, high and low

spots regraded and rough grades approved by City’s Representative, add soil amendment as indicated below and mix until thoroughly mixed to six inch (6") depth. AMOUNT/1,000 SQUARE FEET 6 Cubic Yards Organic Amendment: Composted Greenwaste

3.3 INSTALLATION

A. General

1. Do not install plant material until all construction work has been completed and irrigation system installed and checked. Do not install planting during unfavorable weather.

B. Lawn Installation

1. Do not install lawns until all construction and irrigation work has been completed. This includes cultivation and incorporation of soil amendment as specified. Remove all stones 3/4" or larger.

2. Bring lawn bed to grade by rolling, raking and dragging until surface is smooth and of a uniform fine texture.

3. Sodding: a. Sod shall be “90/10 Tall Fescue”, 90% Tall Fescue, 10% Kentucky Bluegrass,

available thru Delta Bluegrass Company, 800.637.8873. b. Sod shall be machine cut at a uniform thickness of 3/4" excluding top growth and

thatch. It shall be harvested, delivered and planted within 30 hours. Individual slabs shall be no larger than 9 sq. ft. and shall be weed free.

c. Distribute SCU 21-7-14 commercial fertilizer over lawn areas at rate of 10 lbs. per 1000 sq. ft.; water thoroughly.

d. While areas are still damp, lay slabs tightly together without overlapping. Stagger rows of slabs.

e. Lightly roll sod with 200 lb. roller to obtain uniform grade. Correct any irregularities or settlement by lifting sod, regrading area and relay.

f. Water thoroughly to a depth of 8", and keep moist at all times until it has rooted into the soil.

3.4 PRELIMINARY INSPECTION AND APPROVAL

A. Contractor shall request a preliminary inspection of planting work upon completion of all

planting. Inspection and approval of the completed work shall establish the beginning of the maintenance period. No partial approvals will be given.

B. All plant materials shall be in satisfactory growing condition, and all planting areas shall be free

of weeds at time of inspection. C. Work requiring corrective action or replacement shall be performed within 10 days after the

Inspection. This work will not be accepted for the start of the maintenance period until all items noted as deficient during the inspection are corrected or completed. Corrective work and materials replacement shall be in accordance with the Plans and Specifications and shall be made by the Contractor at no cost to the City. Upon approval of work by City’s Representative, maintenance period shall begin.

Glendale - La Loma Park Basketball Court Renovations Specification No. 17-11122

PLANTING - 329000 - 7

3.5 MAINTENANCE

A. Maintenance shall be as specified below; shall immediately follow, coincide with and be continuous with and during the planting operations; and shall continue for 60 calendar days after all planting is complete and accepted.

B. It is Contractor's responsibility to turn over the landscaping in a first-class condition at the end

of the maintenance period. All plants will be healthy and growing; the beds will be free from weeds and generally clean. It is not the intention of these Specifications to allow a "quick cleanup" at the end of the maintenance period, but rather that the work be continuous and ongoing.

C. General Maintenance

1. All clippings, trimmings, cuttings, trash, rubbish and debris shall be promptly removed from the site. Contractor shall not use litter containers on site.

2. All areas shall be kept free from weeds, litter, rocks, glass and debris. Paved areas and adjacent sidewalks shall be swept and cleaned of any soil or mulch that might be washed from adjacent slopes or planted areas as required. Note: Gas blowers are not permitted.

3. Damaged landscaped areas shall be repaired and replanted. Any eroded places shall be repaired by the replacement of topsoil to bring them back to original grade as required.

D. Water Management: Contractor is responsible for setting irrigation controller to apply enough

water to maintain healthy plants at a moderate growth rate. The Contractor shall comply with the water budget approach to irrigation scheduling to match plant need with water application and avoid over-irrigation. The amount of watering will vary with the season and location. Make sure through weekly examination of irrigation system that all heads are operating properly.

3.6 CLEAN-UP AND FINAL INSPECTION

A. Final inspection for approval and acceptance shall be made at the conclusion of the

maintenance period. Written notice requesting such inspection shall be submitted at least ten (10) days before anticipated date.

B. Prior to being considered ready for inspection, Contractor shall have made all corrections and

repairs and have the job cleared of all weeds and debris and presented in a neat, orderly fashion.

3.7 GUARANTEE AND REPLACEMENT

A. Replace all dead plants and plants not in a vigorous condition as soon as directed by

Landscape Architect. Plants used for replacement must be of the same kind and size as specified, planted and maintained as outlined above. All replacement of plants shall be done before the final acceptance. All replacement of plants shall be at the sole expense of the Contractor.

B. Contractor shall not be responsible for failures due to neglect by the City, vandalism, abuse or

damage by others, or unusual phenomenon or incidents above and beyond the Contractor’s control, during Warranty Period. Report such conditions to the City in writing.

END OF SECTION