section 00 01 01 - project manual cover pagebeecroftconstruction.com/plans/delmar-south-campus...26...

718
PROJECT MANUAL Volume 2 of 2 Divisions 20-49 Del Mar College South Campus, Phase 1-A Corpus Christi, Texas CSP 2019-08 Bid Package 1 Central Plant, Utilities & Excavation Prepared by Gensler 711 Louisiana, Suite 300 Houston, Texas 77002 713.844.0000 Fax 713.844.0001 Bid Package 1 - April 2, 2019 Project Number 002.8508.400

Upload: others

Post on 14-Mar-2020

2 views

Category:

Documents


2 download

TRANSCRIPT

  • PROJECT MANUAL

    Volume 2 of 2 Divisions 20-49

    Del Mar College South Campus, Phase 1-A

    Corpus Christi, Texas CSP 2019-08

    Bid Package 1 Central Plant, Utilities & Excavation

    Prepared by Gensler

    711 Louisiana, Suite 300 Houston, Texas 77002

    713.844.0000 Fax 713.844.0001

    Bid Package 1 - April 2, 2019 Project Number 002.8508.400

  • Gensler April 2, 2019 Del Mar College

    002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    TABLE OF CONTENTS 00 01 10 - 1 Copyright 2019 Gensler

    Sealing Architect's Name: Mark Thomas Sullivan

    Texas License No.: 16867

    Issue Date: April 2, 2019

    TABLE OF CONTENTS

    PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

    DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

    INTRODUCTORY INFORMATION Date Document No. Title

    00 01 01 Project Title Page

    00 01 07 Seals Page

    00 01 10 Table of Contents

    PROCUREMENT REQUIREMENTS & CONTRACTING REQUIREMENTS Date Document No. Title

    00 11 16 Notice to Bidders

    00 21 13 Instructions to Bidders

    00 31 32 Geotechnical Data

    00 41 13 Bid Proposal Form - General Contractor

    00 43 23 Bid Alternate Proposal

    00 43 36 Proposed Subcontractors Form

    00 45 16 Statement of Qualifications (SOQ)

    SOQ Questionnaire

    CSP 2016-28 - Acknowledgement of Receipt

    Exhibit A - Insurance Specifications

    Exhibit B - Bonds

    Exhibit C - Warranty and Guarantee

    00 60 00 Project Forms

    Submittal Transmittal

    Data Transfer Agreement

    Subcontractors and Major Material Suppliers List

    Requests for Interpretation

    Substitution Request

    Bulletin

    Change Order

    Punch List

    Certificate of Substantial Completion

    00 65 00 Closeout Forms

    Contractors Release and Waiver of Lien

    Contractor's Lead Free Affidavit

    Contractor's Asbestos Free Affidavit

    Contractor's Non-Use of Urea-Formaldehyde Affidavit

    Subcontractor's/Material Supplier's Affidavit

    Contractor's Affidavit for final Completion

    00 72 00 General Conditions

    Exhibit A - Insurance Specifications

  • Gensler April 2, 2019 Del Mar College

    002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    TABLE OF CONTENTS 00 01 10 - 2 Copyright 2019 Gensler

    Exhibit B - Bonds

    Exhibit C - Warranty and Guarantee

    00 73 43 Prevailing Wage Rates

    SPECIFICATIONS GROUP

    GENERAL REQUIREMENTS SUBGROUP

    DIVISION 01 - GENERAL REQUIREMENTS Date Section No. Title

    01 10 00 Summary of Work

    01 13 00 Delegated Design Requirements

    01 14 00 Work Restrictions

    01 23 00 Alternates

    01 25 00 Substitution Procedures

    01 26 00 Contract Modification Procedures

    01 26 13 Requests for Interpretation (RFI)

    01 29 00 Payment Procedures

    01 31 00 Project Management and Coordination

    01 32 00 Construction Progress Documentation

    01 33 00 Submittal Procedures

    01 35 53 Campus Security

    01 40 00 Quality Requirements

    01 41 19 Windstorm Construction Requirements

    TWIA Insurability Requirements

    WPI-1 Application for Certificate of Compliance

    WPI-2-BC-6 Inspection Verification

    01 42 00 References

    01 45 29 Structural Testing and Inspections (WPM)

    01 50 00 Temporary Facilities and Controls

    01 55 26 Temporary Traffic Controls During Construction (LNV)

    01 60 00 Product Requirements

    01 73 00 Execution

    01 73 23 Cleaning

    01 74 19 Construction Waste Management and Disposal

    01 77 00 Contract Closeout

    01 78 23 Operation and Maintenance Data

    01 78 36 Warranties

    01 78 39 Project Record Documents

    01 79 00 Demonstration and Training

    01 91 13 General Commissioning Requirements

    01 91 19.43 Exterior Enclosure Commissioning

    FACILITY CONSTRUCTION SUBGROUP

    DIVISION 02 - EXISTING CONDITIONS Date Section No. Title

    02 20 21 Control of Ground Water Well Pointing, Dewatering, and Disposal (LNV)

  • Gensler April 2, 2019 Del Mar College

    002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    TABLE OF CONTENTS 00 01 10 - 3 Copyright 2019 Gensler

    DIVISION 03 – CONCRETE Date Section No. Title

    03 10 00 Concrete Forming and Accessories (WPM)

    03 10 01 Concrete Formwork (Civil Sitework) (UE)

    03 20 00 Concrete Reinforcing (WPM)

    03 20 01 Concrete Reinforcement (Civil Sitework) (UE)

    03 30 00 Cast-In-Place Concrete (WPM)

    03 30 02 Normal Weight Aggregate Concrete (Civil Sitework) (UE)

    03 41 00 Precast Concrete Box Culvert (UE)

    DIVISION 04 – MASONRY Date Section No. Title

    04 21 13 Brick Veneer Masonry

    04 22 13 Structural Reinforced Concrete Unit Masonry (WPM)

    04 72 00 Cast Stone Masonry - Building

    DIVISION 05 – METALS Date Section No. Title

    05 12 00 Structural Steel Framing (WPM)

    05 31 00 Steel Decking (WPM)

    05 40 00 Cold-Formed Metal Framing

    05 50 00 Metal Fabrications

    05 51 00 Metal Stairs

    05 52 13 Pipe and Tube Railings

    05 53 13 Bar Gratings

    DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES Date Section No. Title

    06 10 53 Miscellaneous Rough Carpentry

    06 16 00 Sheathing

    DIVISION 07 - THERMAL AND MOISTURE PROTECTION Date Section No. Title

    07 13 26 Self-Adhering Sheet Waterproofing

    07 19 00 Water Repellents

    07 21 00 Thermal Insulation

    07 27 26 Fluid-Applied Membrane Air Barriers

    07 52 16 SBS Modified Bituminous Membrane Roofing (Torch Applied)

    07 62 00 Sheet Metal Flashing and Trim

    07 72 00 Roof Accessories

    07 92 00 Joint Sealants

    DIVISION 08 - OPENINGS Date Section No. Title

    08 11 13 Hollow Metal Doors and Frames

    08 33 23 Overhead Coiling Doors

    08 44 13 Glazed Aluminum Curtain Walls

    08 71 00 Door Hardware (American Door Products)

    08 80 00 Glazing

    08 91 19 Fixed Louvers

  • Gensler April 2, 2019 Del Mar College

    002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    TABLE OF CONTENTS 00 01 10 - 4 Copyright 2019 Gensler

    DIVISION 09 - FINISHES Date Section No. Title

    09 22 16 Non-Structural Metal Framing

    09 29 00 Gypsum Board

    09 30 00 Tiling

    09 61 23 Concrete Flooring Treatment

    09 91 13 Exterior Painting

    09 91 23 Interior Painting

    DIVISION 10 - SPECIALTIES Date Section No. Title

    10 28 00 Toilet Accessories

    10 44 00 Fire-Protection Specialties

    10 51 13 Metal Lockers

    DIVISION 11 - EQUIPMENT - Not Used

    DIVISION 12 - FURNISHINGS - Not Used

    DIVISION 13 - SPECIAL CONSTRUCTION - Not Used

    DIVISION 14 - CONVEYING EQUIPMENT - Not Used

    FACILITY SERVICES SUBGROUP

    DIVISION 21 - FIRE SUPPRESSION Date Section No. Title

    21 00 00 Fire Protection (J*DBR)

    21 02 01 Coordination Drawings (J*DBR)

    21 05 29 Hangers and Supports for Fire Suppression Piping and Equipment (J*DBR)

    21 13 13 Wet Pipe Sprinkler System (J*DBR)

    21 22 00 Ecaro-25 Clean Agent Specifications (J*DBR)

    DIVISION 22 - PLUMBING Date Section No. Title

    22 02 00 Basic Materials and Methods (J*DBR)

    22 02 01 Coordination Drawings (J*DBR)

    22 05 13 Common Motor Requirements for Plumbing Equipment (J*DBR)

    22 05 16 Expansion Fittings and Loops for Plumbing Piping (J*DBR)

    DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING Date Section No. Title

    23 05 93 Testing, Adjusting, and Balancing (J*DBR)

    23 07 13 Duct Insulation (J*DBR)

    23 07 16 HVAC Equipment Insulation (J*DBR)

    23 08 00 Commissioning of HVAC (J*DBR)

    23 09 53 Refrigerant Monitor System (J*DBR)

    23 09 63 Energy Management and Control System (J*DBR)

    23 21 13 Above Ground Hydronic Piping (J*DBR)

    23 21 16 Underground Hydronic Piping (J*DBR)

    23 21 19 Hydronic Specialties (J*DBR)

  • Gensler April 2, 2019 Del Mar College

    002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    TABLE OF CONTENTS 00 01 10 - 5 Copyright 2019 Gensler

    23 21 23 Hydronic Pumps (J*DBR)

    23 23 00 Refrigerant Piping (J*DBR)

    23 25 13 Water Treatment for Closed Loop Hydronic Systems (J*DBR)

    23 25 16 Water Treatment for Open Hydronic Systems (J*DBR)

    23 31 13 Metal Ductwork (J*DBR)

    23 33 00 Ductwork Accessories (J*DBR)

    23 34 00 HVAC Fans (J*DBR)

    23 37 13 Air Distribution Devices (J*DBR)

    23 41 00 Air Filters (J*DBR)

    23 52 16 Condensing Boiler - Gas Fired (J*DBR)

    23 64 16 Centrifugal Liquid Chiller (J*DBR)

    23 65 13 Open Circuit Crossflow Cooling Tower (J*DBR)

    23 82 19 Fan Coil Unit (J*DBR)

    DIVISION 25 - INTEGRATED AUTOMATION - Not Used

    DIVISION 26 - ELECTRICAL Date Section No. Title

    26 02 00 Basic Materials and Methods (J*DBR)

    26 02 01 Coordination Drawings (J*DBR)

    26 05 19 Wire Cable and Related Materials (J*DBR)

    26 05 26 Grounding (J*DBR)

    26 05 33 Raceways (J*DBR)

    26 05 73 Short-Circuit, Coordination Study, Arc Flash Hazard Analysis (J*DBR)

    26 06 34 Low Voltage Raceway System (J*DBR)

    26 08 00 Commissioning of Electrical Systems (J*DBR)

    26 09 13 Electrical Power Monitoring and Control (J*DBR)

    26 09 43 Digital Lighting Controls (J*DBR)

    26 21 13 Electrical Service Entrance (J*DBR)

    26 22 13 Low Voltage Distributions Transformers (J*DBR)

    26 22 22 Low Voltage Harmonic Distribution Transformers (J*DBR)

    26 24 13 Switchboards (J*DBR)

    26 24 16 Panelboards (J*DBR)

    26 27 26 Wiring Devices (J*DBR)

    26 28 16 Safety and Disconnect Switches (J*DBR)

    26 29 01 Motors and Starters (J*DBR)

    26 29 26 Miscellaneous Electrical Controls and Wiring (J*DBR)

    26 32 00 (45) Natural Gas Engine Driven Standby Engine Generating System (J*DBR)

    26 36 23 Automatic Transfer Switches with Bypass Isolation (J*DBR)

    26 41 13.13 Lightning Protection System for Low Rise (J*DBR)

    26 43 13 Surge Protective Device (SPD) - Service Entrance (J*DBR)

    26 43 13.13 Surge Protective Devices (SPD) - Standard Interrupting (J*DBR)

    26 51 00.13 Lighting Fixtures (LED) (J*DBR)

    DIVISION 27 - COMMUNICATIONS

    27 00 00 Communications (DDG)

    27 05 26 Grounding and Bonding (DDG)

    27 05 28 Pathways for Communications Systems (DDG)

    27 05 43 Underground Ducts and Raceways (DDG)

    27 11 00 Communications Equipment Room Fittings (DDG)

  • Gensler April 2, 2019 Del Mar College

    002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    TABLE OF CONTENTS 00 01 10 - 6 Copyright 2019 Gensler

    27 15 00 Horizontal Cabling (DDG)

    DIVISION 28 - ELECTRONIC SAFETY AND SECURITY Date Section No. Title

    28 00 00 Electronic Security (DDG)

    28 02 00 Basic Materials and Methods (J*DBR)

    28 02 01 Coordination Drawings (J*DBR)

    28 10 00 Electronic Access Control and Intrusion Detection (DDG)

    28 23 00 Video Surveillance (DDG)

    28 26 00 Emergency Intercommunications and Duress (DDG)

    28 31 01 Fire Alarm and Smoke Detection System with Voice Evacuation (J*DBR)

    SITE AND INFRASTRUCTURE SUBGROUP

    DIVISION 31 - EARTHWORK Date Section No. Title

    31 10 00 Site Clearing (UE)

    31 20 00 Site Excavation and Fill (UE)

    31 22 13 Rough Grading (UE)

    31 23 00 Excavation and Backfill for Utilities (LNV)

    31 23 00 Excavation and Fill (WPM)

    31 23 17 Trenching (UE)

    31 23 23 Fill (UE)

    31 25 13 Storm Water Pollution Prevention (UE)

    31 63 29 Drilled Concrete Piers (WPM)

    DIVISION 32 - EXTERIOR IMPROVEMENTS - Not Used

    DIVISION 33 - UTILITIES Date Section No. Title

    33 01 10 Grouting Abandoned Utility Lines (LNV)

    33 01 30.12 Hydrostatic Testing of Pressure Systems (LNV)

    33 01 30.13 Vacuum Testing of Sanitary Sewer Manholes and Structures (LNV)

    33 05 13 Manholes (LNV)

    33 05 13.12 Fiberglass Manholes (LNV)

    33 11 00 Waterlines (LNV)

    33 11 13 Polyvinyl Chloride Pipe (AWWA C900-16 Pressure Pipe for Municipal

    Water Mains and Sanitary Sewer Force Mains) (LNV)

    33 11 14 Ductile Iron Pipe and Fittings (LNV)

    33 11 16 Waterline Riser Assemblies (LNV)

    33 12 13 Water Service Lines (LNV)

    33 12 16 Gate Valves for Water Lines (LNV)

    33 12 16 Tapping Sleeves and Tapping Valves (LNV)

    33 12 19 Fire Hydrant (LNV)

    33 31 13 Gravity Sanitary Sewers (LNV)

    33 32 00 Control of Wastewater Flows (Temporary Bypass Pumping

    Systems) (LNV)

    33 49 13 Storm Sewer Manholes (UE)

    END OF TABLE OF CONTENTS

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    FIRE PROTECTION 21 00 00 - 1Copyright 2019 Jones*DBR Engineering Company, LLC

    SECTION 21 00 00 - FIRE PROTECTION

    PART 1 - GENERAL

    1.1 GENERAL REQUIREMENTS

    A. The requirements of the General Conditions and Supplementary Conditions apply to all work herein.

    B. The Basic Materials and Methods, Section 22 02 00, are included as a part of this Section as though written in full in this document.

    1.2 SCOPE

    The scope and work shall include providing treatment for MIC (Microbiologically Influenced Corrosion).

    The Fire Protection Contractor shall provide the Owner with a periodic plan for the testing of the system’s water.

    1.3 WORK INCLUDED: Include the following Work in addition to items normally part of this Section: Stand Pipes, Fire Hose Valves, Siamese Connections, Test Header and Roof Manifolds.

    1.4 REGULATORY CODES

    A. WORK IN ACCORDANCE WITH:

    1. NFPA 13 and 14.2. Local municipal codes that have jurisdiction.

    1.5 CERTIFICATE OF TESTING

    A. Furnish Owner with test certificate certifying the system approved by:

    1. Fire Marshall.2. Insurance Services Officials.

    PART 2 - PRODUCTS

    2.1 STANDPIPE SYSTEM

    A. VALVES:

    1. GATE VALVES: Provide OS & Y gate valves with bronze seat and steel stem with iron body, flanged similar to Jenkins Figure "825A".

    2. CHECK VALVES: Provide flanged, bronze mounted check valves similar to Jenkins Figure "629".

    3. Valves shall be U.L. listed.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    FIRE PROTECTION 21 00 00 - 2Copyright 2019 Jones*DBR Engineering Company, LLC

    B. PIPING:

    1. All piping associated with the standpipe system shall be schedule 40 black steel pipe with Victaulic couplings.

    2. All fitting shall be cast iron rated for 300 psi and in accordance with NFPA 14.

    C. PRODUCTS:

    1. All Piping, fittings, equipment and valves shall be by a domestic manufacturer.

    2.2 FIRE HOSE EQUIPMENT

    A. APPROVED MANUFACTURERS: This specification is based on the first named, other listed below are approved.

    1. Potter-Roemer, Inc.2. Allen.3. Elkhart.4. Croker.

    B. STANDPIPE HOSE VALVES: Potter-Roemer, Inc., 2-1/2" pressure regulating valve #4054 complete with brass cap, chain and visual indicator.

    C. SIAMESE CONNECTIONS: shall be a Potter-Roemer #5761, polished chrome plated, equipped with chrome plated ball drip and with required lettering per N.F.P.A.

    D. TEST HEADER: Potter-Roemer #5865 polished chrome plated on all exposed parts.

    E. CONNECTION THREADS: Conforming to Fire Department requirements.

    F. ROOF MANIFOLD: Potter-Roemer wall mounted or free standing rough chrome plated 3-way.

    PART 3 - EXECUTION

    3.1 DESIGN

    A. The standpipe system shall conform to the requirement of NFPA.

    B. The Contractor shall conform to the National Fire Protection Association's Fire Code No. 14, latest edition. It shall be the Contractor's responsibility to determine if any deficiency or deviations, such as an inadequate water supply, or any other item which would materially affect the acceptability of the system.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    FIRE PROTECTION 21 00 00 - 3Copyright 2019 Jones*DBR Engineering Company, LLC

    3.2 INSTALLATION

    A. Install all items in accordance with applicable codes.

    B. Run piping concealed above furred ceilings to minimize obstructions. Exact routing of piping shall be approved by Architect, and relocated as required at no additional cost to Owner.

    3.3 REPLACEMENT

    Upon receipt of written notice of failure of any part of the guaranteed equipment during the guaranteed period, the Contractor will replace the affected part or parts promptly at no additional cost.

    3.4 TESTING

    Upon completion of the installation, test the system and obtain approval of the local fire insurance rating organization having jurisdiction. Particular attention is called to the requirements of NFPA 14 pamphlet.

    3.5 TRAINING

    A. Owner’s people shall be fully briefed in the normal start-up of the system, operation, normal and emergency shutdown, and maintenance of the system.

    B. Routine maintenance, yearly maintenance, winterization, and spring start-up shall be fully discussed and documented.

    C. Names of those instructed and dates, as well as a list of information handed over to the owner, shall be included in the final report.

    END OF SECTION 21 00 00

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    COORDINATION DRAWINGS 21 02 01 - 1Copyright 2019 Jones*DBR Engineering Company, LLC

    SECTION 21 02 01 - COORDINATION DRAWINGS

    PART 1 - GENERAL

    1.1 GENERAL REQUIREMENTS

    A. The requirements of the General Conditions 013100 and Supplementary Conditions apply to all Work herein.

    1.2 COORDINATION DRAWINGS

    A. The Contractor shall take the lead in coordinating the Mechanical, Electrical, Plumbing, and Fire Protection systems within the building.

    B. The Mechanical Contractor shall coordinate a three-dimensional (3D) model of the building which includes the Mechanical, Electrical, Plumbing, and Fire Protection systems. The Electrical, Plumbing, and Fire Protection Contractors shall prepare their work and generate 3D models which will be given to the Mechanical Contractor for coordination. The Contractor will be provided with the REVIT model that was used to generate the contract documents, this file may be used as the background file. The Contractor shall replace the systems drawn with the actual shop drawing models. The Contractor is not limited to using REVIT, but may use any 3-D software in generating and combining the coordination model.

    C. Submitting the contract drawings as coordination drawings will not be acceptable.

    D. The model shall include detailed and accurate representations of all equipment to be installed based upon the reviewed equipment submittals.

    E. The Mechanical Contractor shall hold a 3-D coordination meeting with all sub-contractors present to review the model and discuss coordination of the installation of the building systems.

    F. Upon completion of the coordination meeting, the Contractor shall submit the 3-D model and ¼” scale drawings for review.

    G. The model shall detail major elements, components, and systems in relationship with other systems, installations, and building components. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are of importance to the efficient flow of the Work, including (but not necessarily limited to) the following:

    1. Indicate the proposed locations of pipe, duct, equipment, and other materials. Include the following:

    a. Wall and type locations.b. Clearances for installing and maintaining insulation.c. Locations of light fixtures and sprinkler heads.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    COORDINATION DRAWINGS 21 02 01 - 2Copyright 2019 Jones*DBR Engineering Company, LLC

    d. Clearances for servicing and maintaining equipment, including tube removal, filter removal, and space for equipment disassembly required for periodic maintenance.

    e. Equipment connections and support details.f. Exterior wall and foundation penetrations.g. Routing of storm and sanitary sewer piping.h. Fire-rated wall and floor penetrations.i. Sizes and location of required concrete pads and bases.j. Valve stem movement.k. Structural floor, wall and roof opening sizes and details.

    2. Indicate scheduling, sequencing, movement, and positioning of large equipment into the building during construction.

    3. Prepare floor plans, elevations, and details to indicate penetrations in floors, walls, and ceilings and their relationship to other penetrations and installations.

    4. Prepare reflected ceiling plans to coordinate and integrate installations, air distribution devices, light fixtures, communication systems components, and other ceiling-mounted items.

    A. Sequence of Coordination

    Below is hierarchy of model elements and the sequencing by which the models will be coordinated.

    1. Structural and Architectural model

    2. Miscellaneous steel

    3. Perform preliminary space allocation

    4. Identify hard constraints (locations of access panels, lights, A/V space requirements, etc.)

    5. Main and medium pressure ducts from the shaft out

    6. Main graded plumbing lines and vents

    7. Sprinkler mains and branches

    8. Cold and hot water mains and branches

    9. Lighting fixtures and plumbing fixtures

    10. Smaller sized ducts and flex ducts

    11. Smaller size cold water and hot water piping, flex ducts, etc.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    COORDINATION DRAWINGS 21 02 01 - 3Copyright 2019 Jones*DBR Engineering Company, LLC

    B. The Contractor and Sub-Contractors shall not install any item until the coordination has been completed and reviewed by the Construction Manager, Owner, and A/E team.

    C. This Contractor shall be responsible for coordination of all items that will affect the installation of the work of this Division. This coordination shall include, but not be limited to: voltage, ampacity, capacity, electrical and piping connections, space requirements, sequence of construction, building requirements and special conditions.

    D. By submitting shop drawings on the project, this Contractor is indicating that all necessary coordination has been completed and that the systems, products and equipment submitted can be installed in the building and will operate as specified and intended, in full coordination with all other Contractors and Subcontractors.

    END OF SECTION 21 02 01

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT 21 05 29 - 1Copyright 2019 Jones*DBR Engineering Company, LLC

    SECTION 21 05 29 – HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT

    PART 1 - GENERAL

    1.1 WORK INCLUDED

    A. Pipe, and equipment hangers, supports and associated anchors.

    B. Sleeves and seals.

    C. Flashing and sealing equipment and pipe stacks.

    1.2 RELATED WORK

    A. Section 21 00 00 – Fire Protection

    B. Section 21 13 13 – Wet Pipe Sprinkler System.

    C. Section 21 13 16 – Dry Pipe Sprinkler System.

    1.3 REFERENCES

    A. ANSI/ASME B31.1 - Power Piping.

    B. NFPA 13 - Standard for the Installation of Sprinkler Systems.

    C. NFPA 14 - Standard for the Installation of Standpipe and Hose Systems.

    1.4 QUALITY ASSURANCE

    A. Supports for Sprinkler Piping: In conformance with NFPA 13.

    B. Supports for Standpipes: In conformance with NFPA 14.

    1.5 SUBMITTALS

    A. Submit shop drawings and product data under provisions of Division One.

    B. Indicate hanger and support framing and attachment methods.

    PART 2 - PRODUCTS

    2.1 PIPE HANGERS AND SUPPORTS

    A. Hangers for Pipe Sizes 1/2 to 1-1/2 Inch Malleable iron, adjustable swivel, split ring.

    B. Hangers for Pipe Sizes 2 to 4 Inches Carbon steel, adjustable, clevis.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT 21 05 29 - 2Copyright 2019 Jones*DBR Engineering Company, LLC

    C. Hangers for Pipe Sizes 6 Inches and Over: Adjustable steel yoke, cast iron roll, double hanger.

    D. Multiple or Trapeze Hangers: Steel channels with welded spacers and hanger rods; cast iron roll and stand for pipe sizes 6 inches and over.

    E. Wall Support for Pipe Sizes to 3 Inches: Cast iron hook.

    F. Wall Support for Pipe Sizes 4 Inches and Over: adjustable steel yoke and cast iron roll.

    G. Vertical Support: Steel riser clamp.

    H. Floor Support for Pipe Sizes to 4 Inches: Cast iron adjustable pipe saddle, locknut nipple, floor flange, and concrete pier or steel support.

    I. Floor Support for Pipe Sizes 6 Inches and Over: Adjustable cast iron roll and stand, steel screws, and concrete pier or steel support.

    J. Roof Pipe Supports and Hangers: Galvanized Steel Channel System as manufactured by Portable Pipe Hangers, Inc. or approved equal.

    For pipes 2-1/2” and smaller – Type PP10 with rollerFor pipes 3” through 8” – Type PSFor multiple pipes – Type PSE - Custom

    K. For installation of protective shields refer to specification section 22 05 29 -3.03.

    2.2 HANGER RODS

    A. Galvanized Hanger Rods: Threaded both ends, threaded one end, or continuous threaded.

    2.3 INSERTS

    A. Inserts: Malleable iron case of galvanized steel shell and expander plug for threaded connection with lateral adjustment, top slot for reinforcing rods, lugs for attaching to forms; size inserts to suit threaded hanger rods.

    2.4 FLASHING

    A. Metal Flashing: 20 gage galvanized steel.

    B. Lead Flashing: 4 lb./sq. ft. sheet lead for waterproofing; 1 lb./sq. ft. sheet lead for soundproofing.

    C. Caps: Steel, 20 gage minimum; 16 gage at fire resistant elements.

    D. Coordinate with roofing contractor/architect for type of flashing on metal roofs.

    2.5 EQUIPMENT CURBS

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT 21 05 29 - 3Copyright 2019 Jones*DBR Engineering Company, LLC

    A. Fabricate curbs of hot dipped galvanized steel.

    2.6 SLEEVES

    A. Sleeves for Pipes through Non-fire Rated Floors: Form with 18 gage galvanized steel, tack welded to form a uniform sleeve.

    B. Sleeves for Pipes through Non-fire Rated Beams, Walls, Footings, and Potentially Wet Floors: Form with steel pipe, schedule 40.

    C. Sleeves for Pipes through Fire Rated and Fire Resistive Floors and Walls, and Fireproofing: Prefabricated fire rated steel sleeves including seals, UL listed.

    D. Fire Stopping Insulation: Glass fiber type, non-combustible, U.L. listed.

    E. Caulk: Paintable 25-year acrylic sealant.

    F. Pipe Alignment Guides: Factory fabricated, of cast semi-steel or heavy fabricated steel, consisting of bolted, two-section outer cylinder and base with two-section guiding spider that bolts tightly to pipe. Length of guides shall be as recommended by manufacturer to allow indicated travel.

    2.7 FABRICATION

    A. Size sleeves large enough to allow for movement due to expansion and contraction. Provide for continuous insulation wrapping.

    B. Design hangers without disengagement of supported pipe.

    C. Design roof supports without roof penetrations, flashing or damage to the roofing material.

    2.8 FINISH

    A. Prime coat exposed steel hangers and supports. Hangers and supports located in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.

    PART 3 - EXECUTION

    3.1 INSERTS

    A. Provide inserts for suspending hangers from reinforced concrete slabs and sides of reinforced concrete beams. Coordinate with structural engineer for placement of inserts.

    B. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.

    C. Where concrete slabs form finished ceiling, provide inserts to be flush with slab surface.

    D. Where inserts are omitted, drill through concrete slab from below and provide thru-bolt

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT 21 05 29 - 4Copyright 2019 Jones*DBR Engineering Company, LLC

    with recessed square steel plate and nut recessed into and grouted flush with slab. Verify with structural engineer prior to start of work.

    3.2 PIPE HANGERS AND SUPPORTS

    A. Support horizontal piping as follows:

    PIPE SIZE MAX. HANGER SPACING HANGER DIAMETER

    (Steel Pipe)1/2 to 1-1/4 inch 7’-0” 3/8"1-1/2 to 3 inch 10'-0" 3/8"4 to 6 inch 10'-0" 1/2"8 to 10 inch 10'-0" 5/8"12 to 14 inch 10'-0" 3/4"15 inch and over 10'-0" 7/8" (Copper Pipe)1/2 to 1-1/4 inch 5'-0" 3/8"1-1/2 to 2-1/2 inch 8'-0" 3/8"3 to 4 inch 10'-0" 3/8"6 to 8 inch 10'-0" 1/2"(PVC Pipe)1-1/2 to 4 inch 4'-0" 3/8"6 to 8 inch 4'-0" 1/2"10 and over 4'-0" 5/8"

    B. Install hangers to provide minimum 1/2 inch space between finished covering and adjacent work.

    C. Place a hanger within 12 inches of each horizontal elbow and at the vertical horizontal transition.

    D. Use hangers with 1-1/2 inch minimum vertical adjustment.

    E. Support horizontal cast iron pipe adjacent to each hub, with 5 feet maximum spacing between hangers.

    F. Support vertical piping at every floor. Support vertical cast iron pipe at each floor at hub.

    G. Where several pipes can be installed in parallel and at same elevation, provide multiple or trapeze hangers.

    H. Support riser piping independently of connected horizontal piping.

    I. Install hangers with nut at base and above hanger; tighten upper nut to hanger after final installation adjustments.

    J. Portable pipe hanger systems shall be installed per manufactures instructions.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT 21 05 29 - 5Copyright 2019 Jones*DBR Engineering Company, LLC

    3.3 Insulated Piping: Comply with the following installation requirements.

    A. Clamps: Attach galvanized clamps, including spacers (if any), to piping with clamps projecting through insulation; do not exceed pipe stresses allowed by ASME B31.9.

    B. Saddles: Install galvanized protection saddles MSS Type 39 where insulation without vapor barrier is indicated. Fill interior voids with segments of insulation that match adjoining pipe insulation.

    C. Shields: Install protective shields MSS Type 40 on cold and chilled water piping that has vapor barrier. Shields shall span an arc of 180 degrees and shall have dimensions in inches not less than the following:

    NPS LENGTH THICKNESS

    1/4 THROUGH 3-1/2 12 0.0484 12 0.0605 & 6 18 0.0608 THROUGH 14 24 0.07516 THROUGH 24 24 0.105

    D. Piping 2” and larger provide galvanized sheet metal shields with calcium silicate at hangers/supports.

    E. Insert material shall be at least as long as the protective shield.

    F. Thermal Hanger Shields: Install where indicated, with insulation of same thickness as piping.

    3.4 EQUIPMENT BASES AND SUPPORTS

    A. Provide equipment bases of concrete.

    B. Provide templates, anchor bolts, and accessories for mounting and anchoring equipment.

    C. Construct support of steel members. Brace and fasten with flanges bolted to structure.

    D. Provide rigid anchors for pipes after vibration isolation components are installed.

    3.5 FLASHING

    A. Provide flexible flashing and metal counter flashing where piping and ductwork penetrate weather or waterproofed walls, floors, and roofs.

    B. Flash vent and soil pipes projecting 8 inches minimum above finished roof surface with lead worked one inch minimum into hub, 8 inches minimum clear on sides with 24 x 24 inches sheet size. For pipes through outside walls, turn flanges back into wall and caulk, metal counter flash and seal.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT 21 05 29 - 6Copyright 2019 Jones*DBR Engineering Company, LLC

    C. Flash floor drains in floors with topping over finished areas with lead, 10 inches clear on sides with minimum 36 x 36 inch sheet size. Fasten flashing to drain clamp device.

    D. Seal floor shower mop sink and all other drains watertight to adjacent materials.

    E. Provide curbs for mechanical roof installations 8 inches minimum high above roofing surface. Contact architect for all flashing details and roof construction. Seal penetrations watertight.

    3.6 SLEEVES

    A. Set sleeves in position in formwork. Provide reinforcing around sleeves.

    B. Extend sleeves through floors minimum one inch above finished floor level. Caulk sleeves full depth with fire rated thermfiber and 3M caulking and provide floor plate.

    C. Where piping penetrates floor, ceiling, or wall, close off space between pipe or duct and adjacent work with U.L. listed fire stopping insulation and caulk seal air tight. Provide close fitting metal collar or escutcheon covers at both sides of penetration.

    D. Fire protection sleeves may be flush with floor of stairways.

    END OF SECTION 21 05 29

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    WET PIPE SPRINKLER SYSTEM 21 13 13 - 1Copyright 2019 Jones*DBR Engineering Company, LLC

    SECTION 21 13 13 - WET PIPE SPRINKLER SYSTEM

    PART 1 - GENERAL

    1.1 GENERAL REQUIREMENTS

    A. The requirements of the General Conditions and Supplementary Conditions apply to all work herein.

    B. The Basic Materials and Methods, Section 22 02 00, are included as a part of this Section as though written in full in this document.

    C. Refer to Section 21 00 00 for integral requirements.

    1.2 SCOPE

    A. Scope of the work shall include the furnishing and complete installation of the equipment covered by this Section, with all auxiliaries, ready for owner's use.

    B. The scope and work shall include providing treatment for MIC (Microbiologically Influenced Corrosion).

    C. The Fire Protection Contractor shall provide the Owner with a periodic plan for the testing of the system’s water.

    1.3 REGULATORY CODES

    A. Work in accordance with:

    1. NFPA.2. Local municipal codes that have jurisdiction.

    B. Products in accordance with:

    1. United Laboratories (UL) listed.2. Factory Mutual (FM) approved.

    1.4 CERTIFICATE OF TESTING

    A. Furnish Owner with test certificate certifying the system approved by:

    1. City Fire Marshall.2. Insurance Services Officials

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    WET PIPE SPRINKLER SYSTEM 21 13 13 - 2Copyright 2019 Jones*DBR Engineering Company, LLC

    PART 2 - PRODUCTS

    2.1 FIRE SPRINKLER SYSTEM

    A. GENERAL:

    1. Work Included:a. Design, coordination and installation of inside and outside piping,

    including sprinkler heads, valves, hangers and supports sleeves.b. The sprinkler system is a wet type and is designed to provide coverage

    for entire building. The Contract Drawings indicate the extent and general arrangement, and the various occupancy classifications.

    c. Sprinkler heads are not shown. d. The plans provide a preliminary layout with riser assembly location, flow

    switch locations, valve locations, and fire department Siamese connections. These are a guide for subsequent preparation of the Contractor's detailed working drawings.

    e. Interface system with building fire and smoke alarm system.2. Quality Assurance: Equipment and installation to meet requirements of NFPA

    Number 13, latest edition and local authority having jurisdiction. All components of the completed system shall be UL listed for the intended service.

    2.2 SUBMITTALS

    A. Submit shop drawings in accordance with Section 22 02 00.

    B. Submit preliminary layout showing only head locations for review by Architect/Engineer. Furnish additional heads which may be required for coordinated ceiling pattern without added cost, even though number of heads may exceed minimum code requirements.

    C. Submit shop drawings of entire sprinkler system including hydraulic calculations to Architect/Engineer.

    D. Provide Architect with six complete sets of final approved shop drawings before starting the installation. Include details of the sprinkler system showing sections, light fixtures, air conditioning, ducts, and a plan giving fire department connections, location of all exposed structures within twenty feet of this structure, and other equipment to be used. Drawings shall bear the stamp of review of the local fire insurance rating organization having jurisdiction.

    E. Service Utility Diagram: Furnish Architect with an accurately marked print showing location of underground pipes and valves as installed upon completion of underground Work.

    F. Provide a printed sheet giving brief instructions relative to all necessary aspects of sprinkler controls and emergency procedures next to sprinkler riser mains. Instruction sheet to be protected by glass or a transparent plastic cover.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    WET PIPE SPRINKLER SYSTEM 21 13 13 - 3Copyright 2019 Jones*DBR Engineering Company, LLC

    G. Materials:

    1. Piping:a. All piping above grade shall be:

    - schedule 10 black steel pipe with a rolled groove ends, joined with mechanical coupling and cut groove cast iron fittings for pipe 2-1/2” and greater.

    - schedule 40 black steel threaded pipe and fittings for pipe 2” and smaller.

    b. Acceptable manufacturer:- American Tube- Wheatland Tube- Gem Sprinkler

    c. Acceptable mechanical coupling manufacturer:- Victaulic- Grinnell- Reliable- Gruvlok

    d. In all locations subject to corrosive conditions, ensure to provide a suitable epoxy (spray) coating to all exposed surfaces of pipe and fittings. Such locations shall include, but not necessarily be limited to, the following: natatoriums, pool equipment rooms, chemical and metal process areas, and animal pens. All job-applied protective coatings shall be provided as approved and only after verification that the proper piping has been installed, per the markings along the length of the pipe.

    2. Sprinkler Heads:a. Suspended Ceiling Type: Standard Concealed pendant type with white

    cover plate.b. Exposed Area Type: Standard upright type with brass finish.c. Sidewall Type: Chrome plated finish with matching escutcheon.d. Temperature rating on fusible links to suit specific hazard area with

    minimum margin or safety 50 degrees F.e. Sprinkler heads of the “O”-ring seal type are not acceptable.f. In all locations subject to corrosive conditions provide heads entirely

    constructed of stainless steel or heads with polyester coated finish and dipped in wax. Such locations shall include, but not necessarily be limited to, the following: natatoriums, pool equipment rooms, chemical and metal process areas, and animal pens.

    g. In all locations subject to occupant abuse or vandalism provide institutional type sprinkler heads with tamper-resistant construction and suitable “break-away” weight test documentation from the manufacturer. Such locations shall include, but not necessarily be limited to, the following: patient areas of institutional mental health occupancies, prisoner areas (cells, etc.) of correctional facilities – jails, prisons, juvenile detention facilities.

    h. Flexible type sprinkler head connection systems are not acceptable.i. Acceptable manufacturer:

    - Reliable- Grinnell

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    WET PIPE SPRINKLER SYSTEM 21 13 13 - 4Copyright 2019 Jones*DBR Engineering Company, LLC

    - Viking3. Sprinkler Alarm Valve:

    a. Provide approved automatic sprinkler valve with one or two pole (as required) flow detectors, pressure switch, outside electric gongs, and inside electric gong and circuit breaker.

    b. Acceptable manufacturer:- Reliable- Grinnell- Viking

    4. Valves:a. 2” and smaller: bronze, rising stem, inside screw, solid wedge, U.L.

    listed valve.b. 2-1/2” and larger: iron body, bronze trim, rising stem, OS&Y, solid

    wedge, U.L. listed valve.c. Check valve: cast iron flanged body, bronze fitted, non-slam type.d. Install valves with stems upright or horizontal, not inverted.e. Acceptable manufacturer:

    - Nibco- Grinnell- Stockham- Victaulic

    5. Fire Department Connection: Refer to Section 21 00 00.6. Insulation:

    a. All piping and valves exposed to the weather or within building and exposed to the weather shall be insulated with Phenolic foam with ASJ and all joints sealed. Insulation density shall not be less than 1.5 pounds per cubic foot, and conductivity (K) not higher than 0.25 and 75F mean temperature difference, with factory applied all weather vapor barrier jacket.

    b. All insulated pipe and valves subject to damage shall be protected with an aluminum jacket with sealed joints.

    c. Refer to Section 22 07 19 for detailed specification. 7. Products:

    a. All piping, fitting, equipment, sprinkler heads, and valves shall be by a domestic manufacturer.

    PART 3 - EXECUTION

    3.1 All equipment shall be installed in accordance with the manufacturer’s recommendations and printed installation instructions.

    3.2 All items required for a complete and proper installation are not necessarily indicated on the plans or in the specifications. Provide all items as required by NFPA and installed as per manufacturer’s recommendations.

    3.3 DESIGN

    A. Design spacing of sprinkler heads and selection sizes shall conform to the requirement of NFPA 13 for the indicated occupancy.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    WET PIPE SPRINKLER SYSTEM 21 13 13 - 5Copyright 2019 Jones*DBR Engineering Company, LLC

    B. Uniform discharge density design shall be based on hydraulic calculations utilizing the method outlined in NFPA 13. Density of discharge from sprinkler heads shall conform to NFPA 13.

    C. Friction losses in pipe will be based on a value of "C" =120 in the Hazen - Williams formula.

    D. Design and install the system so that no part will interfere with doors, windows, heating, plumbing, or electrical equipment. Do not locate sprinkler heads within 6 inches of lighting fixtures, HVAC diffusers and other obstructions. Sprinkler piping cannot penetrate ductwork or lighting fixtures.

    E. The Contractor shall conform to the National Fire Protection Association's Fire Code No. 13, latest edition. Special attention shall be given to Article 1-9, working plans. It shall be the Registered Fire Protection Engineer’s responsibility to determine if any deficiency or deviations, such as an inadequate water supply, or any other item which would materially affect the acceptability of the system.

    3.4 INSTALLATION

    A. Install all items in accordance with applicable codes.

    B. Install piping so that mains and branches are not located directly underneath HVAC equipment or other items needing access.

    C. All sprinkler heads shall be located as near the center of ceiling tiles as is practical (1/2”). Location shall present a uniform pattern with all heads aligned when completely installed.

    D. Run piping concealed above furred ceilings and in joists to minimize obstructions. Expose only heads. Exact routing of piping shall be approved by Architect or relocated as required at no additional cost to Owner.

    E. Wire guards on all pendant or upright sprinklers heads in mechanical rooms, gymnasiums, athletic areas, wood and metal shops.

    F. Protect sprinkler heads against mechanical injury with standard guards.

    G. Locate outside alarms on wall of building adjacent to siamese fire department connection.

    H. Provide on wall near sprinkler valve, cabinet containing four extra sprinkler heads of each type and wrench suitable for each head type.

    I. Provide 1 inch diameter nipple and 1 inch x 1/2 inch reducing fitting for each upright head.

    J. Painting shall be as follows:

    1. Exposed sprinkler riser, alarm valve and all related piping shall be painted red.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    WET PIPE SPRINKLER SYSTEM 21 13 13 - 6Copyright 2019 Jones*DBR Engineering Company, LLC

    2. Exposed sprinkler piping in finished areas shall be painted as directed by Architect.

    3.5 REPLACEMENT

    Upon receipt of written notice of failure of any part of the guaranteed equipment during the guaranteed period, the Contractor will replace the affected part or parts promptly at no additional cost.

    3.6 TESTING

    A. Prior to testing, the entire sprinkler system shall be thoroughly flushed clean.

    B. Upon completion of the installation and flushing, test the system and obtain approval of the local fire insurance rating organization having jurisdiction. Particular attention is called to the requirements of NFPA 13 pamphlet.

    3.7 TRAINING

    A. Owner's people shall be fully briefed in the normal start-up of the system, operation, normal and emergency shutdown, and maintenance of the system.

    B. Routine maintenance, yearly maintenance, winterization, and spring start-up shall be fully discussed and documented.

    C. Names of those instructed and dates, as well as a list of information handed over to the owner, shall be included in the final report.

    END OF SECTION 21 13 13

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 1Copyright 2019 Jones*DBR Engineering Company, LLC

    SECTION 21 22 00 - CLEAN AGENT FIRE SUPPRESSION / DETECTION SYSTEM

    PART 1 – GENERAL

    1.1 GENERAL REQUIREMENTS

    A. The Ecaro-25 clean agent system installation shall be made in accordance with the drawings, specifications and applicable standards. Should a conflict occur between the drawings and specifications, the specifications shall prevail. The requirements of the General Conditions and Supplementary Conditions apply to all work herein.

    1.2 RELATED SECTIONS

    A. Section 21 05 29 – Hangers and Supports for Fire Suppression Piping and Equipment.

    B. Section 21 05 53 –Identification for Fire Suppression, Piping and Equipment.

    C. Section 21 05 87 – Sleeves for Fire Suppression Piping.

    D. Division 28 – Fire Alarm System.

    1.3 SCOPE

    A. Scope of the Work shall include the furnishing and complete installation of the equipment covered by this Section, with all auxiliaries, ready for owner's use. The work described in this specification includes all engineering labor, materials, equipment and services necessary, and required, to complete and test the detection and suppression system.

    B. This specification, NFPA 72 and 2001 (latest edition) define the requirements for a Ecaro-25 Clean Agent total flooding fire suppression system. There is to be a complete system provided for Demarc room as shown on construction drawing. Protection is to include detection and suppression for the room, under the raised floor, and in the ceiling plenum.

    C. This installation shall be made in accordance with applicable National Fire Protection Association Standards (latest edition) and the State of Texas.NFPA. 2001 – 2008 Edition – Clean Agent Fire Suppression SystemsNo. 70 - National Electrical CodeNo. 72 – National Fire Alarm CodeFM ApprovalsUnderwriters LaboratoryRequirements of the Authority Having Jurisdiction (AHJ)

    D. Exclusions:

    1. 120VAC dedicated power supply to the system control panel

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 2Copyright 2019 Jones*DBR Engineering Company, LLC

    2. Interlock wiring and conduit for shutdown of HVAC, dampers and/or electric power supplies or shunt trip breakers

    3. Connection to local/remote fire alarm systems for monitoring

    PART 2 – PRODUCTS

    2.1 The contractor shall furnish, install, and test a complete and ready for operation HFC-125, (Ecaro-25), fire suppression system, including charged agent storage containers, piping, nozzles, control panels, detectors, wiring, alarms, graphic annunciator, and all other equipment necessary for completely new, operational conventional systems free from defects for each protected zone.

    2.2 All equipment and devices used shall be listed for their intended use in either the UL Fire Protection Equipment List or the Factory Mutual Approval Guide. All equipment shall be manufactured and/or supplied by Fike Protection Systems or approved equal. For approved equal status the contractor must submit considered equal within 96 hours of the bid date and provide a detailed summary of each specification section, subsection, and paragraph for deviation or equivalent.

    2.3 The manufacturer of the clean agent system hardware and detection components shall have a minimum of 10 years’ experience in the design and manufacture of similar types of suppression system and who refer to similar installations providing satisfactory service.

    2.4 All valves operated automatically shall be provided with independent means for manual operation.

    2.5 The clean agent fire suppression system shall provide a minimum design concentration of 8% by volume, in all areas and/or protected spaces, at the minimum anticipated temperature within the protected area. Per NFPA 2001, the system design shall not exceed a maximum exposure limit concentration level of 11.5%, by volume, unless provisions for room evacuation, before agent release, are provided. All personnel should be able to leave protected space prior to the discharge or at least within 5 minutes of the commencement of discharge.

    2.6 Detection shall consist of conventional, photoelectric detectors with spacing of 250 square feet per detector with a minimum of two per space. All information, such as air changes per minute and total CFM, must be taken into account for the quantity of detectors, per NFPA 72E. If the air changes within the protected space exceed 60 per hour then 1/2 of this quantity or the maximum spacing of one per 250 square feet shall be used, whichever results in a greater number of detectors. Model # 63-1017 detectors shall be located within the protected zone. All detectors, manual pull station, abort stations, low pressure switches, shall be displayed on graphic annunciator.

    2.7 The system shall include a standby power supply. Upon loss of normal power supplying the control unit, the system shall automatically transfer to standby battery power supplied by the control unit and alarm the transfer. The standby system shall be capable of staying on-line for 24 hours and then operate the system for 10 minutes in the alarm condition.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 3Copyright 2019 Jones*DBR Engineering Company, LLC

    2.8 Storage containers and distribution piping shall be in accordance with the latest requirements listed in NFPA Standard 2001. All discharge piping and fittings shall be galvanized. All fittings shall be 300 pound extra heavy.

    2.9 All piping shall be internally swabbed or blown free of residual fabrication oil or particle matter prior to nozzles or discharge devices being installed.

    2.10 All Ecaro-25 containers shall include liquid level indicators. These indicators shall precisely show the level of agent in the container without the need of scales or the removal of these cylinders. A calibrated liquid reading device shall not be accepted. All containers shall also include a supervised low-pressure switch to monitor internal cylinder pressure.

    A. Ecaro-25 containers shall be located on the floor where shown on the drawings. The quantity of cylinders shall be adhered to. This shall ensure the proper maximum cylinder fill quantities and nozzle throw distance.

    2.11 Containers shall be actuated by the following methods:

    A. Single container applications(Electric) – By an Impulse Valve Operator (IVO) wired through a Fike P/N 10-2748 Impulse Releasing Module (IRM). This method allows mechanical release

    2.12 The Fike addressable control unit shall control circuits to the detectors, time delays, initiators, manual discharge switches, alarm horns and lights, pressure switches and other required equipment. All such circuits shall be supervised so that a visible and audible trouble signal occurs at the control unit should a fault occur. The control panel shall be multi zone panel located where shown on the drawings. Panel shall be sized to house all controls, such as time delays, detection/suppression, and aux. relays. This control panel shall be a Fike part number 10-068-R-1.

    Control panel shall be UL and/or FM listed for releasing and shall provide the following capabilities and functions:

    A. Two (2) Class B (Style Y), indicating appliance circuits rated for 2.0 amps @ 24 VDC.

    B. Two (2) Signal Line Circuits, Style 4/6 (Class A/B). Communicates to up to 254 addressable devices per circuit. Addressable devices described below.

    C. Two auxiliary supply circuits rated 2A @ 24Vdc, each

    D. One resettable auxiliary supply circuit rated 2A @ 24 Vdc.

    E. Three (3) Form “C” relays, rated 2 amps @30 Vdc. These relays provide alarm, trouble, and supervisory annunciation.

    F. Optional CRM4, Relay module (P/N 10-2204) provides 4 programmable contacts rated 2A @ 30 Vdc. CHEETAH Xi can support two (2) CRM4 modules.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 4Copyright 2019 Jones*DBR Engineering Company, LLC

    G. Optional SLM, Supplemental Loop Module (P/N 10-2473) provides two additional Signal Line Circuits, Style 4/6 (Class A/B). Communicates to up to 254 addressable devices per circuit. Addressable devices described below.

    H. Optional SPS, Supplemental Power Supply (P/N 10-2474-p). Operates from 120Vac, 50/60 Hz (p=1) or 240 Vac, 50/60 Hz (p=2). Increases CHEETAH XI Xi’s external normal standby current from 2.0A to 4.0A and CHEETAH XI Xi’s external alarm current from 6.0A to 12.0 A. Provides two (2) auxiliary supply circuits rated 2A @ 24 Vdc, each. Supports up to 75 Ah of standby battery capacity.

    I. Ten (10) Status LEDs plus alpha-numeric display for troubleshooting: AC power; alarm; trouble; supervisory; silence; predischarge; release: release disabled: abort and ground fault.

    J. Programmable pre-discharge and discharge timers

    K. Six (6) optional Abort types

    L. Intelligent Transistor protection to prevent noise spikes and microprocessor failure from inadvertently activating release outputs

    M. Disarm function to disable release outputs

    N. Multiple input power source - 120 VAC or 240 VAC @ 50/60 Hz

    O. 6.0 amps @ 24 VDC power supply to operate high current draw horns and strobes. Capable of allowing expansion to 12 amps by use of optional module Supplemental Power Supply (SPS) which also is capable of supporting 75 Ah of standby batteries.

    P. Available in either Red or Gray finish

    Manual Release Station

    A. The electric manual release switch shall be a dual action device which provides a means of manually discharging the ECARO-25 clean agent system.1. The Manual Release switch shall be a P/N 10-1638 or a Manual Pull station, P/N

    02-3710.2. The Manual Release switch or Manual Pull station shall be a dual action device

    requiring two distinct operations to initiate a system actuation.3. Manual actuation shall bypass the time delay and abort functions, shall cause the

    system to discharge and shall cause all release and shutdown devices to operate in the same manner as if the system had operated automatically.

    4. A Manual Release or Manual Pull switch shall be located at each exit from the protected hazard and shall have an advisory sign, P/N 02-10312, provided at each location.

    Abort Station

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 5Copyright 2019 Jones*DBR Engineering Company, LLC

    A. Abort stations shall be located where shown on drawings and shall always be located within the hazard they protect. Model # 10-1639.

    2.13 AUDIBLE DEVICES SHALL BE AS FOLLOWS:

    A. Horn/strobes shall be 90 dBA 10 feet with the horns having the ability to be modulated.

    B. Discharge strobes shall be located outside the protected hazard by each egress door.

    2.14 Design information to be submitted for Engineer's approval shall include the "Sequence of Operation", "Bill of Materials", and drawings.

    2.15 SUBMITTALS

    A. Submit shop drawings in accordance with project requirements.

    B. Submit shop drawings of entire ECARO-25 fire suppression system including calculations to Architects/Engineer.

    C. Provide Architect with six complete sets of final approved shop drawings before starting installation.

    D. All details of system design shall be shown on the plan drawings as follows:Actual Area (ft2)Actual Volume (ft3)Pounds of gaseous agentFilling density of containerAir flowMaximum pipe length (ft)Hydraulic calculationsType of NozzlesPiping detailsPressure of systemSize and type of pipeNumber of fittings (elbows, tees, etc.)Routing of piping including indication that system does not exceed the piping limitationsEquipment usedLocation of detectorsLocation of gas supplyLocation of manual releases and abort switchesElectrical wiring detailsStandby power detailsInterlocks with:

    Duct DampersAir-conditioning UnitsElectrical EquipmentBuilding Fire Alarm- (3) zones (Alarm, Supervisory, Trouble)

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 6Copyright 2019 Jones*DBR Engineering Company, LLC

    PART 3 – EXECUTION

    3.1 All equipment shall be installed in accordance with the manufacturers’ recommendations and printed installation instructions.

    3.2 All items required for a complete and proper installation are not necessarily indicated on the plans or in the specifications. Provide all items required as per manufacturers requirements.

    3.3 The area of unclosable openings shall be minimized with all doors and windows weather-stripped, and where not used on a daily basis, they shall be sealed. Ventilating ducts shall be closed with automatic dampers activated by the Ecaro-25 discharge. The Dampers and the control wiring of these dampers are covered under other Divisions of the work.

    3.4 Contractor shall provide instruction plates detailing emergency procedures at each system control panel and at each hazard area manual discharge station/abort switch location. Permanent nameplates shall be used in the control panel to identify control logic units, contacts, and major circuits.

    3.5 Sequence of Operations shall be as follows

    A. Upon activation of a photoelectric smoke/heat detector in a ECARO-25 protected zone the following will happen:

    1. Strobes activate in zone of alarm2. Horns pulse slowly in zone of alarm3. Alarm relay is energized for building fire alarm monitoring

    B. Upon activation of a second photoelectric smoke detector in the same ECARO-25 protected zone the following will happen:

    1. Strobes continue in zone of alarm2. Horns pulse fast in zone of alarm3. 30 Second discharge time delay begins4. dedicated relay energizes for ahu/damper shutdown

    C. After completion of the time delay sequence, the following will happen:

    1. Strobes continue in zone of alarm2. Horns sound steady in zone of alarm3. ECARO-25 agent is discharged in zone of alarm4. Discharge strobe activates outside zone of alarm5. Pre-action solenoid is energized

    D. A loss of pressure in the clean agent storage cylinder will cause the following to happen:

    1. Supervisory LED lights up at control panel2. Supervisory relay energizes for building fire alarm monitoring

    E. A trouble condition in the ECARO-25 system will cause the following to happen:

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 7Copyright 2019 Jones*DBR Engineering Company, LLC

    1. Trouble LED lights up at control panel2. Trouble relay energizes for building fire alarm monitoring

    3.6 TRAINING

    A. Owner's personnel shall be fully briefed in the normal start-up of the system, the operation, normal and emergency shutdown, and maintenance of the equipment.

    B. Routine maintenance, yearly maintenance and spring start-up shall be fully discussed and documented.

    C. Names of those instructed and dates, as well as a list of information handed over to the owner, shall be included in the final report.

    3.7 TESTING

    A. After the installation is complete, the system shall be inspected by factory trained personnel in accordance with the manufacturer's recommended procedures.

    B. All wiring shall be tested for proper connection, continuity, and resistance to ground.

    C. The complete system shall be tested by the contractor in the presence of the Owner and the Engineer, and all functions including system and equipment interlocks must be operational.

    D. Contractor shall provide all necessary labor, apparatus, and instrumentation for the test.

    E. A test evaluation team consisting of Engineer's, contractor, distributor, and insurance representative shall meet before the test to establish ground rules and the method of conducting the test in accordance with this specification and manufacturer's recommendations.

    F. ECARO-25 Design and Test Summary, shall be prepared for the acceptance test and completed upon successful test.

    G. The hazards shall be tested for room integrity by use of a fan pressurization unit. The test shall be preformed as described in NFPA 2001. Twelve, (12) hours of testing shall be included. These tests shall be recorded and distributed in a test result format. Should these tests fail, the Fire Protection Contractor shall help determine the cause so the General Contractor may address it.

    H. Testing shall be performed prior to computer equipment installation.

    I. Bid shall include all applicable taxes, permits, and fees.

    J. At a minimum, one two-hour educational seminar shall be given to the owner at his direction.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    ECARO-25 CLEAN AGENT SPECIFICATIONS 21 22 00 - 8Copyright 2019 Jones*DBR Engineering Company, LLC

    K. The Clean Agent System contractor shall be responsible for testing all interconnect and shut down wiring for the following equipment: V.A.V. boxes, self-contained H.V.A.C. units, building H.V.A.C. system, building Fire Alarm system, power distributing unit(s) and dampers etc.

    3.8 CONTRACTOR QUALIFICATIONS

    A. The Clean Agent contractor’s bid shall include the name of the person providing the proposal, and the designer who will “stamp” the drawings. These persons SHALL be a minimum of a N.I.C.E.T. level 3 in Special Hazards, with a State of Texas Planners License.

    B. The Clean Agent contractor’s bid shall employ a C.F.P.S. person. This person shall be “Certified in Fire Protection Systems” by the National Fire Protection Association.

    3.9 WARRANTY

    A. All FIKE system components furnished and installed under this contract, shall be guaranteed against defects in design, materials and workmanship for the full warranty period which is standard with the manufacturer, but no case less than one (1) year from the date of system acceptance.

    END OF SECTION 21 22 00

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 1Copyright 2019 Jones*DBR Engineering Company, LLC

    SECTION 22 02 00 - BASIC MATERIALS AND METHODS

    PART 1 - GENERAL

    1.1 GENERAL REQUIREMENTS

    A. The requirements of the General Conditions and Supplementary Conditions apply to all Work herein.

    B. The Contract Drawings indicate the extent and general arrangement of the systems. If any departure from the Contract Drawings is deemed necessary by the Contractor, details of such departure and the reasons therefore shall be submitted to the Architect/Engineer for approval as soon as reasonably practicable. No such departures shall be made without the prior written approval of the Architect/Engineer.

    C. Notwithstanding any reference in the Specifications to any article, device, product, material, fixture, form or type of construction by name, make or catalog number, such reference shall not be construed as limiting competition; and the Contractor, in such cases, may at his option use any article, device, product, material, fixture, form or type of construction which in the judgment of the Architect/Engineer, expressed in writing, is equal to that specified.

    1.2 SCOPE OF WORK

    A. The Work included under this Contract consists of the furnishing and installation of all equipment and material necessary and required to form the complete and functioning systems in all of their various phases, all as shown on the accompanying Drawings and/or described in these Specifications. The Contractor shall review all pertinent Drawings, including those of other contracts, prior to commencement of Work.

    B. This Division requires the furnishing and installing of all items as specified herein, indicated on the Drawings, or reasonably inferred as necessary for safe and proper operation; including every article, device or accessory (whether or not specifically called for by item) reasonably necessary to facilitate each system's functioning as indicated by the design and the equipment specified. Elements of the work include, but are not limited to: materials, labor, supervision, transportation, storage, equipment, utilities, all required permits, licenses and inspections. All work performed under this Section shall be in accordance with the Project Manual, Drawings and Specifications and is subject to the terms and conditions of the Contract.

    C. The approximate locations of Plumbing and Fire Protection items are indicated on the Drawings. These Drawings are not intended to give complete and accurate details with regards to location of outlets, apparatus, etc. Exact locations are to be determined by actual measurements at the building/job-site, and will in all cases be subject to the Review of the Owner or Engineer, who reserves the right to make any reasonable changes in the locations indicated without additional cost to the Owner.

    D. Items specifically mentioned in the Specifications but not shown on the Drawings and/or items shown on Drawings but not specifically mentioned in the Specifications shall be

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 2Copyright 2019 Jones*DBR Engineering Company, LLC

    installed by the Contractor under the appropriate section of work as if they were both specified and shown.

    E. All discrepancies between the Contract Documents and actual job-site conditions shall be reported to the Owner or Engineer so that they will be resolved prior to bidding. Where this cannot be done at least seven (7) working days prior to bid; the greater or more costly of the discrepancy shall be bid. All labor and materials required to perform the work described shall be included as part of this Contract.

    F. It is the intention of this Section of the specifications to outline minimum requirements to furnish the Owner with a turn-key and fully operating system in cooperation with other trades.

    G. It is the intent of the above "Scope" to give the Contractor a general outline of the extent of the Work involved; however, it is not intended to include each and every item required for the Work. Anything omitted from the "Scope" but shown on the Drawings, or specified elsewhere, or necessary for complete and functioning plumbing systems shall be considered a part of the overall "Scope".

    H. The Contractor shall rough-in fixtures and equipment furnished by others from rough-in and placement drawings furnished by others. The Contractor shall make final connection to fixtures and equipment furnished by others.

    I. The Contractor shall participate in the Commissioning process as required; including, but not necessarily limited to: meeting attendance, completion of checklists, and participation in functional testing.

    1.3 SCHEMATIC NATURE OF CONTRACT DOCUMENTS

    A. The contract documents are schematic in nature in that they are only to establish scope and a minimum level of quality. They are not to be used as actual working construction drawings. The actual working construction drawings shall be the reviewed Shop Drawings.

    B. All piping, fixture, or equipment locations as indicated on the documents do not indicate every transition, offset, or exact location. All transitions, offsets, clearances and exact locations shall be established by actual field measurements, coordination with the structural, architectural and reflected ceiling plans, and other trades. Submit Shop Drawings for review.

    C. All transitions, offsets and relocations as required by actual field conditions shall be performed by the Contractor at no additional cost to the owner.

    D. Additional coordination with Electrical Subcontractor may be required to allow adequate clearances of electrical equipment, fixtures, and associated appurtenances. Contractor to notify Architect and Engineer of unresolved clearances, conflicts, or equipment locations.

    1.4 SITE VISIT AND FAMILIARIZATION

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 3Copyright 2019 Jones*DBR Engineering Company, LLC

    A. Before submitting a bid, it will be necessary for each Contractor whose work is involved to visit the site and ascertain for himself the conditions to be met therein in installing his work and make due provision for same in his bid. It will be assumed that this Contractor in submitting his bid has visited the premises and that his bid covers all work necessary to properly install the piping, fixtures and equipment shown. Failure on the part of the Contractor to comply with this requirement shall not be considered justification for the omission or faulty installation of any work covered by these Specifications and Drawings.

    B. Understand the existing utilities from which services will be supplied; verify locations of utility services, and determine requirements for connections.

    C. Determine in advance that equipment and materials proposed for installation fit into the confines indicated.

    1.5 WORK SPECIFIED IN OTHER SECTIONS

    A. Finish painting is specified. Prime and protective painting is included in the work of this Division.

    B. Owner and General Contractor furnished equipment shall be properly connected to plumbing systems.

    C. Furnishing and installing all required plumbing equipment, control relays and electrical interlock devices, conduit, wire and junction boxes are included in the Work of this Division.

    1.6 PERMITS, TESTS, INSPECTIONS

    A. Arrange and pay for all permits, fees, tests, and all inspections as required by governmental authorities.

    1.7 DATE OF FINAL ACCEPTANCE

    A. The date of final acceptance shall be the date of Owner occupancy, or the date all punch list items have been completed, or the date final payment has been received. Refer to Division 01 for additional requirements.

    B. The date of final acceptance shall be documented in writing and signed by the Architect, Owner and Contractor.

    1.8 DELIVERY, STORAGE, AND HANDLING

    A. Deliver products to the project properly identified with names, model numbers, types, grades, compliance labels, and other information needed for identification.

    B. Deliver products to the project at such times as the project is ready to receive the equipment, pipe or valves - properly protected from incidental damage and weather damage.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 4Copyright 2019 Jones*DBR Engineering Company, LLC

    C. Damaged equipment, valves or pipe shall be promptly removed from the site and new, undamaged equipment, valves and pipe shall be provided in its place promptly with no additional charge to the Owner.

    1.9 NOISE AND VIBRATION

    A. The plumbing systems and the component parts thereof shall be guaranteed to operate without objectionable noise and vibration.

    B. Provide foundations, supports and isolators as specified or indicated, properly adjusted to prevent transmission of vibration to the building structure, piping and other items.

    C. Carefully fabricate pipe and fittings with smooth interior finish to prevent turbulence and generation or regeneration of noise.

    D. All equipment shall be selected to operate with minimum of noise and vibration. If, in the opinion of the Architect/Engineer, objectionable noise or vibration is produced or transmitted to or through the building structure by equipment, piping or other parts of the Work, the Contractor shall rectify such conditions without extra cost to the Owner.

    1.10 APPLICABLE CODES

    A. Obtain all required permits and inspections for all work required by the Contract Documents and pay all required fees in connection thereof.

    B. Arrange with the serving utility companies for the connection, relocation, and upgrade of all required utilities and pay all charges, meter charges, connection fees and inspection fees, if required.

    C. Comply with all applicable codes, specifications, local ordinances, industry standards, utility company regulations and the applicable requirements of the following nationally accepted codes and standards, including, but not necessarily limited to:

    1. American Standards Association, ASA.2. American Society of Heating, Refrigerating, and Air-Conditioning Engineers,

    Inc., ASHRAE.3. American Society of Mechanical Engineers, ASME.4. American Society of Plumbing Engineers, ASPE.5. American Society of Testing Materials, ASTM.6. American Water Works Association, AWWA.7. National Bureau of Standards, NBS.8. National Fire Protection Association, NFPA.9. UL, LLC (formerly Underwriters Laboratories).10. FM Global.11. International Energy Conservation Code, IECC.12. International Fire Code.13. International Gas Code.

    D. Where differences exist between the Contract Documents and applicable state or city building codes, state and local ordinances, industry standards, utility company regulations

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 5Copyright 2019 Jones*DBR Engineering Company, LLC

    and the applicable requirements of the above listed nationally accepted codes and standards, the more stringent or costly application shall govern. Promptly notify the Architect/Engineer in writing of all differences.

    E. When directed in writing by the Architect/Engineer, remove all work installed that does not comply with the Contract Documents and applicable state or city building codes, state and local ordinances, industry standards, utility company regulations and the applicable requirements of the above listed nationally accepted codes and standards. Correct the deficiencies and complete the work at no additional cost to the Owner.

    1.11 DEFINITIONS AND SYMBOLS

    A. General Explanation: A substantial amount of construction and Specification language constitutes definitions for terms found in other Contract Documents, including Drawings which must be recognized as diagrammatic and schematic in nature and not completely descriptive of requirements indicated thereon. Certain terms used in Contract Documents are defined generally in this article, unless defined otherwise in Division 01.

    B. Definitions and explanations of this Section are not necessarily either complete or exclusive, but are general for work to the extent not stated more explicitly in another provision of the Contract Documents.

    C. Indicated: The term "Indicated" is a cross-reference to details, notes or schedules on the Drawings, to other paragraphs or schedules in the Specifications and to similar means of recording requirements in Contract Documents. Where such terms as "Shown", "Noted", "Scheduled", "Specified" and "Detailed" are used in lieu of "Indicated", it is for the purpose of helping the reader locate cross-reference material, and no limitation of location is intended except as specifically shown.

    D. Directed: Where not otherwise explained, terms such as "Directed", "Requested", "Accepted", and "Permitted" mean by the Architect or Engineer. However, no such implied meaning will be interpreted to extend the Architect's or Engineer's responsibility into the Contractor's area of construction supervision.

    E. Reviewed: Where used in conjunction with the Engineer's response to submittals, requests for information, applications, inquiries, reports and claims by the Contractor the meaning of the term "Reviewed" will be held to limitations of Architect's and Engineer's responsibilities and duties as specified in the General and Supplemental Conditions. In no case will "Reviewed" by Engineer be interpreted as a release of the Contractor from responsibility to fulfill the terms and requirements of the Contract Documents.

    F. Furnish: Except as otherwise defined in greater detail, the term "Furnish" is used to mean supply and deliver new to the project site, ready for unloading, unpacking, assembly, installation, etc., as applicable in each instance.

    G. Install: Except as otherwise defined in greater detail, the term "Install" is used to describe operations at the project site including unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protection, cleaning and similar operations, as applicable in each instance.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 6Copyright 2019 Jones*DBR Engineering Company, LLC

    H. Provide: Except as otherwise defined in greater detail, the term "Provide" is used to mean "Furnish and Install", complete and ready for intended use, as applicable in each instance.

    I. Installer: Entity (person or firm) engaged by the Contractor or its Subcontractor for performance of a particular unit of work at the project site, including unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protection, cleaning and similar operations, as applicable in each instance. It is a general requirement that such entities (Installers) be expert in the operations they are engaged to perform.

    J. Imperative Language: Used generally in Specifications. Except as otherwise indicated, requirements expressed imperatively are to be performed by the Contractor. For clarity of reading at certain locations, contrasting subjective language is used to describe responsibilities that must be fulfilled indirectly by the Contractor, or when so noted by other identified installers or entities.

    K. Minimum Quality/Quantity: In every instance, the quality level or quantity shown or specified is intended as minimum quality level or quantity of work to be performed or provided. Except as otherwise specifically indicated, the actual work may either comply exactly with that minimum (within specified tolerances), or may exceed that minimum within reasonable tolerance limits. In complying with requirements, indicated or scheduled numeric values are either minimums or maximums as noted or as appropriate for the context of the requirements. Refer instances of uncertainty to Owner or Engineer via a request for information (RFI) for decision before proceeding.

    L. Abbreviations and Symbols: The language of Specifications and other Contract Documents including Drawings is of an abbreviated type in certain instances, and implies words and meanings which will be appropriately interpreted. Actual word abbreviations of a self-explanatory nature have been included in text of Specifications and Drawings. Specific abbreviations and symbols have been established, principally for lengthy technical terminology and primarily in conjunction with coordination of Specification requirements with notations on Drawings and in Schedules. These are frequently defined in Section at first instance of use or on a Legend and Symbol Drawing. Trade and industry association names and titles of generally recognized industry standards are frequently abbreviated. Singular words will be interpreted as plural and plural words will be interpreted as singular where applicable and where full context of Contract Documents so indicate. Except as otherwise indicated, graphic symbols and abbreviations used on Drawings and in Specifications are those recognized in construction industry for indicated purposes. Where not otherwise noted symbols and abbreviations are defined by 2009 ASHRAE Fundamentals Handbook, chapter 34 "Abbreviations and Symbols", ASME and ASPE published standards.

    1.12 DRAWINGS AND SPECIFICATIONS

    A. These Specifications are intended to supplement the Drawings. It will not be the province of the Specifications to mention any part of the work which the Drawings are competent to fully explain in every particular and such omission shall not to relieve the Contractor from carrying out portions indicated on the Drawings only.

  • Jones*DBR Engineering April 2, 2019 Del Mar College002.8508.400 Bid Package 1 South Campus, Phase 1-A

    Central Plant, Utilities & Excavation Corpus Christi, Texas

    BASIC MATERIALS AND METHODS 22 02 00 - 7Copyright 2019 Jones*DBR Engineering Company, LLC

    B. Should items be required by these Specifications and not indicated on the Drawings, they are to be supplied even if of such nature that they could have been indicated thereon. In case of disagreement between Drawings and Specifications, or within either Drawings or Specifications, the better quality or greater quantity of work shall be estimated and the matter referred to the Architect or Engineer for review with a request for information and clarification at least seven (7) working days prior to bid opening date for issuance of an addendum.

    C. The listing of product manufacturers, materials and methods in the various sections of the Specifications, and indicated on the Drawings, is intended to establish a standard of quality only. It is not the intention of the Owner or Engineer to discriminate against any product, material or method that is equal to the standards as indicated and/or specified, nor is it intended to preclude open, competitive bidding. The fact that a specific manufacturer is listed as an acceptable manufacturer should not be interpreted to mean that the manufacturers' standard product will meet the requirements of the project design, Drawings, Specifications and space constraints.