![Page 1: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/1.jpg)
0
Second Avenue Subway
Community Board 8 Second Avenue Subway
Task Force Update
June 23, 2014
Anil Parikh
Senior Vice President & Program Executive
MTA Capital Construction
![Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/2.jpg)
11
Phase 2
125th to 96thPhase 3
63rd to Houston
Phase 1
96th to 63rd
Phase 4
Houston to
Hanover
8.5 Route miles
16 new stations
1 renovated station
2 services,
linked to existing line
Transfers to other rail lines
63rd St. Station
Complete Project Profile
![Page 3: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/3.jpg)
22
96th Street Station
(Cut-and-Cover)
86th Street Station
2 Entrances
72nd Street Station
3 Entrances
63rd Street /
Lexington Ave Station
Phase 1: Target Cost-$4.451B--- Ridership 200,000 --- Target Completion Date-2016
• Scope:
Q train service
Tunnels from 92nd St to 63rd St
New Stations at 96th St, 86th St, and 72nd St
63rd St Station Connection
Track & Systems from 105th St to 63rd St
Service between 96th St & Brooklyn via Broadway Line
Phase 1 Overview
96th Street Station
3 Entrances
63rd Street Station
4 New Entrances
![Page 4: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/4.jpg)
33
• Overall Construction Progress – 68.16%Complete (as of June 1, 2014)
• All 10 SAS Contracts have been awarded for Phase 1
• 4 Construction Contracts Completed:
− Tunnel Boring Machine Tunneling
− 86th St Excavation, Utility Relocation, and Road Decking
− 96th St Site Work and Heavy Civil
− 72nd St Cavern Mining, Tunnels and Heavy Civil (1/14/14)
Current Project Status
![Page 5: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/5.jpg)
4
Stations
![Page 6: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/6.jpg)
5
96th Street Station
Finishes, MEP Systems, Ancillary Buildings
and Entrances Contract
Percent Complete: 39%
Contract Value: $324,600,000
Award Date: June 22, 2012
Forecast Completion: June 2016
Heavy Civil, Structural and Utility Relocation
Contract
Percent Complete: 100%
Contract Value: $325,000,000
Award Date: May 28, 2009
Substantial Completion: November 5, 2013
![Page 7: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/7.jpg)
6 6
• Contract 2A; Heavy Civil and
Structural work was completed
November 5, 2013 (one of two
contracts for this station area.
• Completed delivery of all track to
station areas underground for
installation.
• All mezzanine slabs in the main
station completed as of 2/6/14.
96th Street Station Milestones
Rail delivery through former launch box opening between 92-93rd Street
![Page 8: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/8.jpg)
77
Formwork Installation for Platform ConstructionMain Cavern Looking South from 92nd Street
![Page 9: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/9.jpg)
88
Mezzanine Level with Architectural Roof
96th Street looking south
![Page 10: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/10.jpg)
99
Three Month Look Ahead96th Street Station Area
New traffic configuration/work zones:
• 95th Street west of 2nd Ave – A gas pipe fabrication work zone is to
be added on or about 6/27/14.
• 94th Street east side of 2nd Ave – Excavation for Entrance 2 will
begin on/around 6/30/14.
• Completion forecast for the roof slabs is July 2014.
• Continue waterproofing the roof slab.
• Begin removing deck panels and backfilling over roof slab for
roadway.
• Utility work- Prepare to lower the utilities that are currently
suspended on the roadway decking onto the station roof slab.
![Page 11: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/11.jpg)
10
96th Street Ancillary 2 Rendering
SW corner 97th Street and Second Avenue
![Page 12: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/12.jpg)
11
96th Street Entrance 3 Rendering
NW corner 96th Street and Second Avenue
![Page 13: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/13.jpg)
1212
Rendering of 96th Street Station Proposed Art InstallationArtist – Sarah Sze, MTA Arts For Transit commissioned work
![Page 14: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/14.jpg)
13
Ancillary 2 Ancillary 1
Entrance 1
(Inside)
Ancillary 2
86th Street Station
2nd Avenue
Cavern Mining and Lining Contract
Percent Complete: 90%
Contract Value: $332,860,000
Award Date: August 4, 2011
Forecast Completion: December 2014
Finishes, Entrances, Ancillaries, and MEP Systems Contract
Percent Complete : 3.5%
Contract Value: $208,376,000
Award Date: June 12, 2013
Forecast Completion: May 2016
84th 85th 86th 87th
Entrance 2
(outside)
83rd
![Page 15: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/15.jpg)
1414
• All blasting completed on contract and entire
Phase 1 project on November 19, 2013.
• Dismantling of Muck House located
between 83rd and 84th Streets was
completed April 10th.
• Muck House located between 86th and 87th
Streets will be dismantled in Fall 2014.
• Access for the Finishes Contractor
Schiavone – Picone, JV (86th Street
Constructors) was provided on April 15th.
• Casting of concrete Wall sections is 92%
complete and casting of arch ceiling
sections is 79% complete.
86th Street Station
Milestones
Muck House at 83-84th Street- January 2013
Muck House Dismantled – April 10, 2014
![Page 16: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/16.jpg)
1515
86th Street Cavern Arch June 2014Looking North from below 86th Street (approx.)
![Page 17: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/17.jpg)
16
86th Street Station Entrance 1303 E83rd Street – Formerly Tony’s Restaurant
![Page 18: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/18.jpg)
17
30 Story High-Rise
Building
5-Story
Brick Buildings
Structural Work includes:
Underpinning Concrete Columns
Cutting openings in slabs
Strengthening columns & slabs
Tunneling in rock
Street Level
Archstone Building Underpinning
![Page 19: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/19.jpg)
18
![Page 20: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/20.jpg)
19
86th Street Entrance 1 Rendering83rd Street and Second Avenue
![Page 21: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/21.jpg)
2020
Three Month Look Ahead86th Street Station Area
E. 78th to E. 79th Streets (Center of Second Avenue)
• Continue to temporarily reduce traffic to one lane east of the center
work zone and two lanes west of the center work zone for concrete
work. This work zone will be removed in the Summer of 2014
E. 83rd to E. 85th Streets – South Cavern
• Continue structural concrete construction at Entrance 1
(Archstone).
• Continue installation of drainage system, waterproofing, and
reinforcing steel in the cavern.
• Continue placing cavern concrete walls and ceiling arch.
E. 86th Street Entrance 2 (Northeast and Southeast side of 86th Street)
• Continue placing structural concrete.
• Continue lowering construction materials down elevator shaft on SE
corner of 86th Street for elevator/escalator passageway
construction.
![Page 22: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/22.jpg)
2121
Three Month Look Ahead86th Street Station Area continued
E. 86th to E. 87th Streets - North Cavern
• Continue to use North Shaft and Ancillary 2 locations to lower
construction equipment, materials, and concrete into the station
cavern.
• Complete installation of waterproofing, reinforcing steel and
structural walls in the cavern.
• Complete installation of ceiling arch.
• Dismantle the Muck House and gantry crane between E. 86th and
E. 87th Street by September 2014.
![Page 23: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/23.jpg)
22
86th Street Ancillary 1 Rendering
NW corner 83rd Street and Second Avenue
![Page 24: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/24.jpg)
23
86th Street Station RenderingPlatform Level
![Page 25: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/25.jpg)
2424
Rendering of 86th Street Station Art InstallationArtist – Chuck Close, MTA Arts For Transit commissioned work
Portraits in mosaic and tile representing NYC cultural figures & family
![Page 26: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/26.jpg)
25
72nd Street Station
Cavern Mining, Tunnels, and Heavy Civil
Contract
Percent Complete : 98%
Contract Value: $447,180,260
Award Date: October 1, 2010
Substantial Completion: January 14, 2014
Muck House Muck HouseHog House
Finishes, MEP Systems, Ancillary Buildings
and Entrances Contract
Percent Complete : 17.5%
Contract Value: $276,400
Award Date: February 14, 2013
Forecast Completion: February 2016
![Page 27: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/27.jpg)
27
72nd Street Cavern
Mezzanine Slab Installation 100% Complete June 2014Looking South
![Page 28: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/28.jpg)
2828
72nd Street Cavern
First Section of Platform Poured June 2014Looking South
![Page 29: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/29.jpg)
29
Muck House DisassemblyRemoval of the muck house
at 69th Street has been
completed.
November 19, 2013
January 9, 2014
![Page 30: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/30.jpg)
3030
Removal of Hoghouse Underway – January 28, 201470th Street and Second Avenue
![Page 31: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/31.jpg)
3131
Hoghouse Removed – February 14, 201470th Street and Second Avenue
![Page 32: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/32.jpg)
3232
Three Month Look Ahead72nd Street Station Area
SURFACE OPERATIONS:• Commence gas and steam main relocation work between 69th and 70th Streets on east
side of Second Avenue and follow immediately with excavation of the street entrance.• The work zone configuration for the above work will have three lanes of traffic with
work zones on both sides of Second Avenue between 69th and 70th Streets. This will be implemented immediately.
• Concrete pumping is continuing at Ancillary 1, Ancillary 2 and Entrance 3.• Concrete truck staging is continuing as needed between 74th and 76th Streets.
UNDERGROUND OPERATIONS• Judlau will complete mezzanine construction and commence platform pours in the
main station cavern. • Continue precast panels for the track level walls.• Construction of new rooms for mechanical, electrical, plumbing and communication
systems operation.• Installation of utility conduits in the tunnels and station caverns.• Continue installation of waterproofing and wall construction of the Ancillary 1,
Ancillary 2 and Entrance 3 structures.• Continue excavation work for Entrance 1 construction within 301 E. 69th Street garage.
![Page 33: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/33.jpg)
33
72nd Street Ancillary 1
Rendering
NW corner 69th Street
and Second Avenue
![Page 34: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/34.jpg)
34
72nd Street
Entrance 2 /
Ancillary 2
Rendering
NW corner
72nd Street and
Second Avenue
![Page 35: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/35.jpg)
35
72nd Street Entrance 1 RenderingNE Corner 69th Street and Second Avenue
![Page 36: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/36.jpg)
36
63rd Street
3rd
Ave
Ancillary 1
124 E 63rd St
Top of
Hahn Garage
Entrance 4
(Outside)Entrance 1
(Inside)
Entrance 3
(Outside)
New Elevator Entrance 2
Ancillary 2
Lexin
gto
n A
ve
Existing Elevator Entrance
Existing Entrance
Existing Entrance
Plaza
Station Upgrade Contract
Percent Complete: 75.2%
Contract Value: $185,300,000
Award Date: January 13, 2011
Forecast Completion: June 2015
Rehabilitation of Existing 63rd Street
Station
![Page 37: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/37.jpg)
3737
• Completed construction of Ancillary 1 structure on garage roof of
124 East 63rd Street - October 2013.
• Entrance 1 excavation and demolition inside 200 East 63rd Street -
Summer 2014.
• Commence construction for Entrance 4 (SE corner of 63rd Street
and Third Avenue) - Summer 2014.
• Commence sidewalk restoration and re-opening of sidewalk gratings
– Fall 2014.
• Commence Condo Royale plaza restoration (NE corner of 63rd
Street and Third Avenue) – Fall 2014.
• Complete platform finishes – Summer 2014.
63rd Street Station Milestones
MTA Capital Construction
![Page 38: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/38.jpg)
3838
63rd Street/Lexington Ave Entrance 1Basement Floor Demolition and Excavation - May 2014
![Page 39: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/39.jpg)
3939
Three Month Look Ahead63rd Street Station Area
STATION
• Installation of service carrier, ductwork and electrical conduit at the upper
platform level to continue.
• Continue platform finishes, including ceilings, track wall tile framing, column
covers, platform paving, lighting fixtures, etc.
• Continuation of concrete pours for walls, floor slabs, curbs and equipment
pads.
• Masonry wall, ceiling panel, and door installation throughout station.
• Mechanical, electrical and plumbing systems installation in new station
areas.
ENTRANCE 1
(200 East 63rd Street)
• Begin installation of steel piles via drilling methods.
• Demolition and excavation continuing within building for new
escalator/stairway shaft.
![Page 40: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/40.jpg)
4040
Three Month Look Ahead63rd Street Station Area continued
ANCILLARY 2
(Northwest corner of 63rd St and Third Av)
• Continue construction activities for Ancillary 2 shaft.
• Continue construction of elevator shaft within plaza work zone area.
• Commence utilization of sidewalk access hatch and reconfigure MPT
along 63rd Street.
OTHER SURFACE WORK
• Commence 63rd Street sidewalk restoration in select areas between
Park and Lexington Avenues.
THIRD AVENUE STORAGE/WORK ZONE
(Third Avenue between 63rd and 64th Streets)
•Continue full utilization of space for materials storage and small office
trailer for systems installation contractor.
![Page 41: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/41.jpg)
4141
Proposed Rendering of 63rd Street Plaza (design not finalized)SW Corner of 63rd Street and Third Avenue
![Page 42: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/42.jpg)
4242
Rendering of 63rd Street Station Art InstallationArtist – Jean Shin, MTA Arts For Transit commissioned work
![Page 43: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/43.jpg)
43
Track Installation
![Page 44: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/44.jpg)
44
Track InstallationSouthbound Track below 101st
Street looking North
![Page 45: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/45.jpg)
45
Pettibone machine used for
moving railsSouthbound Track below 103rd St
![Page 46: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/46.jpg)
46
Aluminum 3rd
Rail Installed
![Page 47: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/June 23 CB8 SAS Task Force meeting F… · Task Force Update June 23, 2014 Anil Parikh Senior Vice President & Program Executive](https://reader033.vdocuments.us/reader033/viewer/2022050502/5f948e54c94c060bbd21b911/html5/thumbnails/47.jpg)
47
Questions