1 Second Avenue Subway Quarterly Public Workshop February 25, 2015

Upload: others

Post on 19-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

1

Second Avenue Subway

Quarterly Public Workshop

February 25, 2015

Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

2 MTA Capital Construction

• Overall Construction Progress is 78.7% complete as of 2/1/2015.

• All 10 SAS Contracts have been awarded for Phase 1

• 5 Construction Contracts Completed: − Tunnel Boring Machine Tunneling − 86th St Excavation, Utility Relocation, and Road Decking − 96th St Site Work and Heavy Civil − 72nd St Cavern Mining, Tunnels and Heavy Civil (1/14/14) − 86th St Cavern Mining & Heavy Civil (12/16/14)

Current Project Status

Page 3: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

3

96th Street Proposed Art Installation Artist – Sarah Sze, MTA Arts & Design commissioned work

Station Renderings

63rd Street Mezzanine Fare Array

72nd Street Platform Level

86th Street Mezzanine - South Goto http://www.mta.info/SAS and click on Vision Gallery

3

Page 4: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

4 4

Community Information Center & Community Tours

Hours Monday: 10AM - 6PM Tuesday: 11AM - 7PM Wednesday: 10 AM - 6PM Thursday: 11AM - 7PM Friday: 10AM - 6PM Saturday: 11AM - 3PM* Sunday: Closed Closed most public holidays *Open the second Saturday of every month.

• 9,300 visitors to date • 48 presentations to school groups with over 1,375 students attending • New exhibit coming in March 2015 • Community Tours- we have hosted 47 tours with 1,493 participants

Opened July 2013

Page 5: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

5 MTA Capital Construction

96th Street Station Area

Page 6: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

6 6 Above ground Ancillary 1 work at 93rd Street – January 2015

Page 7: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

7 96th Street Ancillary 1 Rendering NE corner 93rd Street and Second Avenue

7

Page 8: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

8

96th Street Station Area - Utility Installation 93rd – 94th Street & Second Avenue Looking South January 2015

Twin 42” Water Main

30” Gas Main Con Ed Electric

60” Water Main

8

Page 9: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

9

Backfill over Utilities 95th – 96th Street and Second Avenue 9

Page 10: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

10 MTA Capital Construction

86th Street Station Area

Page 11: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

11

11

86th Street Station Mezzanine and Platform Dec. 2014 Looking North

86th Street Milestones

Oct. 3, 2014

All blasting completed on contract and entire Phase 1 project

Nov. 19, 2013

April 10, 2014

Completed dismantling of 83rd - 84th Street Muck House

Aug. 8, 2014

Completed casting of concrete arch ceiling

Completed dismantling of 86th - 87th Street Muck House

Highlight Completed 96% of lower mezzanine slabs in cavern

Dec. 16, 2014

Cavern Mining and Heavy Civil contract substantially completed

11

Page 12: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

12 Muck House removal at 86th Street and Second Avenue October 3, 2014

May 2014

12

Page 13: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

13 MTA Capital Construction 13 Yorkshire Building at 86th Street and Second Avenue January 28, looking East

Page 14: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

14

New 20 foot sidewalks poured on 86th Street

between 1st and 2nd Avenues, East of Yorkshire building

86th Street Station Area

14 Looking east

Page 15: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

15 MTA Capital Construction

72nd Street Station Area

Page 16: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

16 MTA Capital Construction

72nd Street Station Area

New fence wrap installed in January between 69th and 70th Streets, looking south.

Page 17: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

17

72nd Street Station Area

Ancillary 2/Entrance 2 at northwest corner of 72nd Street and Second Ave 17

Page 18: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

18

72nd Street Entrance 2 / Ancillary 2 Rendering NW corner 72nd Street and Second Avenue

Page 19: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

19 19

72nd Street Station - Mezzanine Public Area Looking North at 69th Street

Ductwork

Arch Ceiling

Electrical Conduits Ventilation Ducts

Page 20: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

20 MTA Capital Construction

Lexington Ave / 63rd Street Station Area

Page 21: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

21 MTA Capital Construction

Pre repair Post repair

Sidewalk repair 163 E. 63rd Street

Lexington Ave/63rd Street Station Area

21 Looking east towards Third Ave Looking west towards Lexington Ave

Page 22: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

22

Water treatment tanks removed from the eastside of Third Avenue between E. 62nd and E. 63rd Streets.

Lexington Ave/63rd Street Station Area

Page 23: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

23

Lexington Ave/63rd Street Station Station rehabilitation includes new track wall tiles, ceilings and lighting Lower Level Platform - February 2015

23

Page 24: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

24 MTA Capital Construction

Streetscape “Visioning” Process

Page 25: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

25

Streetscape “Visioning” Process

• MTACC wanted to give the community something better

• Numerous meetings, emails and calls with city agencies, including DOT and Parks

• Community input solicited at a November 3rd workshop

• Meeting with CB8 Second Avenue Subway Taskforce and CB11 Transportation Committee members to select streetscape components

• Full CB8 board meeting on February 18th

MTA Capital Construction

Page 26: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

26

Typical Pre-Construction Block

MTA Capital Construction 26

Page 27: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

27 MTA Capital Construction

For conceptual purposes only. Placement and selection of specific street elements to be decided.

Concept Rendering Post-Construction Block

Page 28: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

28

City Light

Page 29: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

29

Street Trees: Large Canopy Linden Bald Cypress Sweetgum Zelkova

• Red/bronze fall color

• One of the most common street trees • Yellow fall color

• Strong pyramidal shape • Orange/brown fall color

• Strong, yellow fall color

5-inch diameter trees will be used whenever possible

Page 30: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

30

Street Trees: Columnar Form

Fastigiata Oak Zelkova Musachino

Page 31: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

31

Street Trees: Small Understory

Serviceberry Eastern Redbud Japanese Tree Lilac

Community Board committees decided to let Parks Department make decisions as appropriate

Page 32: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

32

Rail Guards for Tree Pits

MTA Capital Construction

Page 33: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

33

City Benches

MTA Capital Construction

Page 34: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

34

Bicycle Rack

MTA Capital Construction

Page 35: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

35

Way-Finding Signage To be installed by DOT at SBS Bus Stops

MTA Capital Construction

Page 36: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/SAS Public Workshop... · 2015-03-16 · MTA Capital Construction 2 • Overall Construction Progress is 78.7% complete as of

36

Second Avenue Subway

Email distribution list:

[email protected]