SMEC-SIORl-SECEC SSS Joint Venture 720MW Karot Hydropower Project Main Camp,'Ko,tli Road, KAROT Tehsil Kahuta, District Rawalpindi Punjab - Pakistan
-· N.
+92 51 6000 107
-~· .. ..... .. ~.
- KPCL QA/QC Audit Report No. 12
Copy to: Attachments:
- " . ·' lffi~~ AllanG~ Chief Resident Engineer Sl\'.IEC International (Lead Member of SSS JV)
Yours sincerely,
A report has been attached which shows observations and general comments of the EniploydJ''s Engineer Audit team. ·
This is the 121h Quarterly QA/QC Audit which has been conducted on July 13, 2021 of EPC Contractor's laboratories, batching plants and QA/QC department at Karat Hydro power Project Site.
QA/QC AUDIT REPORT NO. 12 APRIL TO JUNE 2021 . Dear Mr. Hou,
~r:_ Hou Jiangang General MClnager Karot Management Department/TGDC Main Camp, Project Site, Ka rot, Tehsil Kahuta Rawalpindi- Pakistan
Date: 151~July 2021 -· ~~I 'I. -.. ...
SMEC-SIDRl-SECEC e--~ SMEC . ® SECEC - ~
Member of the Surbana jurong Group
Our Ref: SSS/5065056/NTM/1.88/7549
KAROT POWER COMPANY (Pvt.) LIMITED
720MW KAROT HYDROPOWER PROJECT
QA/QC Audit Report No. 12
April to June 2021
(Audit Completed in July 2021)
SSS - JV / Employer’s Engineer
House #16-B, Kaghan Road, F-8/4, Islamabad – Pakistan Tel: +92-51-2855143, Fax: +92-51-2261174 Email: [email protected]
DOCUMENTS / REPORT CONTROL FORM
Project Name: 720MW Karot Hydropower Project
Report Name: QA/QC Audit Report No. 12: April to June 2021
Project Number: 5065056
Report for: Karot Power Company (Pvt) Limited (KPCL)
PREPARATION, REVIEW AND AUTHORIZATION:
Revision No.
Date Prepared by Reviewed by Approved for
Issue by
00 July 13, 2021 He Changchun, Zubair Jan Allan G. Christer Allan G. Christer
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
TOC-I
Table of Contents
1. INTRODUCTION 2
1.1 General ...................................................................................................................................... 2
1.2 Project Information .................................................................................................................. 2
1.3 Contract Data ............................................................................................................................ 3
1.4 Employer’s Engineer Services ................................................................................................ 3
1.5 QA / QC – Contractual Obligations of Employer Engineer ................................................... 4
1.6 QA / QC Reporting by the Employer Engineer ...................................................................... 5
1.6.1 QA/QC Audit ............................................................................................................. 6
1.6.2 General comments: ................................................................................................ 11
1.6.3 QA/QC Auditing by Employer Engineer .................................................................. 12
APPENDICES (E&M ISSUES) 20
APPENDIX A: THE LIST OF RFI’S RAISED DURING LOCKDOWN PERIOD 21
APPENDIX-B: THE LIST OF LOST RFI’S RELATED TO MECHANICAL WORKS 22
APPENDIX-C: THE LIST OF LETTERS RELATED TO MECHANICAL WORKS WHICH ARE NOT
RESPONDED BY THE CONTRACTOR 23
APPEDNIX-D: THE LIST OF SOME OTHER PENDING ISSUES 24
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
2
1. INTRODUCTION
1.1 General
Karot Power Company (Pvt.) Limited (hereinafter “KPCL”, or “Employer”), is currently in the process of designing,
developing, constructing, and will own and operate the 720MW Karot Hydropower Project (hereinafter referred to
as “KHPP” or the “Project”) located near Karot Bridge in the District of Rawalpindi in the Province of Punjab,
Pakistan using the water resources of the Jhelum River, under the Policy for Power Generation Projects Year
2002 (“the Policy”) issued by the Government of Pakistan.
1.2 Project Information
General: Karot Hydropower Station will be the 4th cascade hydropower station planned on the Jhelum River in
Pakistan. The 3rd cascade is Azad Pattan Hydropower Station. The dam is located 1km upstream of the Karot
Bridge on the boundary between Punjab Province and AJK, Pakistan on the left bank and Punjab Province on
the right bank. It is 74km from Mangla Power Station located on the downstream and roughly 55km away from
Islamabad in the west. The project can be approached via the Islamabad - Rawat – Pandori – Kotli Road
(approximately 80km). The travel time from Islamabad is about 2 hours. See location plan below:
The project is designed exclusively for power generation under a Build Own Operate Transfer (BOOT) basis with
a concession period of 30 years. It is designed with an asphaltic concrete core rock-fill Dam of 95.5 m height, a
separate Spillway, an Intake structure, 3 Diversion Tunnels, 4 Power Tunnels and a surface Powerhouse
containing 4 x 180 MW Francis turbines with a mean annual power generation capacity of 3,206 million kW/h.
Construction Time Line: The EPC Contract construction period is 5 years plus a Defects Notification Period of
2 years for Civil Works and 3 years for E & M Works. Trial run and commercial operation is planned at the end of
the 5th year.
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
3
EPC Contractors: The Civil Works and E & M Works are two separate Contracts with the Civil Works Contractor
bearing the responsibility to coordinate and manage the E & M Contractor for timely delivery of the project.
Following are the EPC Contracts:
1. Engineering and Construction Contract: Three Gorges Economy Development Company (TGDC)
2. Equipment Supply Contract: China Machinery & Electric Company (CMEC)
Chinese design company CSPDR has been engaged by the Contractor for the detailed design of the project.
1.3 Contract Data
i. Signing of EPC Contracts February 2015
ii. Date of Project Financial Close February 22, 2017
iii. EPC Contract Commencement Date December 01, 2016
iv. EPC Contract Construction Period 60 months
v. EPC Contract Defects Notification Period 24 m (Civil), 36 m (E&M)
vi. Employer’s Engineer Services Contract signed May 26, 2016
vii. Employer’s Engineer Commencement Date May 31, 2016
viii. Employer’s Engineer Contract Period 96 m (60 + 36)
1.4 Employer’s Engineer Services
The services of Employer’s Engineer broadly cover the following:
a) Project Design Review
Level – I and Level – II Design Review;
Construction Drawings and Method Review;
Review of Project Plans and Schemes;
Review of Variations;
b) Project Supervision
Quality Assurance and Quality Control;
Progress Monitoring;
Health, Safety and Environmental Control (HSE);
Verification of Contractor’s Invoices;
Meeting, Reporting and Documentation;
c) Assistance and Coordination with relevant stakeholders
Assistance to KPCL to manage the EPC Contracts and for fulfilling their obligations under the
Security Agreements & Financial Documents;
Coordination with power purchaser and assist in selection of a ‘Reopener Verifier’, whose function is
to verify costs for variations in geology, civil work escalation and resettlement costs;
Coordination with other agencies: NEPRA, Environmental Protection Agency of AJK and Punjab and
other relevant public entities in Pakistan, Lender’s Engineer
Assist KPCL in claiming compensation in Insurance matters
Assist KPCL in preparing project progress reports as required by the stakeholders;
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
4
For a detailed description of Employer’s Engineer scope refer to the Section IV of the Consultancy Agreement,
Terms of Reference.
1.5 QA / QC – Contractual Obligations of Employer Engineer
The specific scope of services for Quality Assurance and Quality Control activities to be covered by the Employer
Engineer is as follows:
“The Employer’s Engineer will review and approve the Quality Assurance and Quality Control Plan (QA/QC
Plan), which includes the Quality Plan, Quality Assurance Procedures, and Quality Control Procedures
concerning the works of all disciplines; prepared and submitted by the EPC Contractors. The Plan will be in
accordance with ISO 9001:2008 series quality standards and in compliance with the requirements established in
the Project Requirement(s) of the EPC Contracts. The Employer’s Engineer will perform daily compliance
monitoring and will conduct quarterly internal audits to assure compliance with Project ESMS requirements.
Project supervision includes but is not limited to the following:
Quality Assurance and Quality Control
The Employer’s Engineer will, with the approval from KPCL, prepare a draft of the Employer’s Quality Assurance
Program under the framework of the EPC Contracts, which will be independent of the Contractor's QA/QC
programs and will contain all the quality inspection programs, detailed specifications, detailed working
procedures, acceptance standards and programs. The Employer’s Engineer will set up the detailed casual
inspection, off-site testing, additional physical testing and verification testing of the Contractor’s works in the
Employer’s Quality Assurance Program. The Employer’s Quality Assurance Program will also contain the
procedures, methods and specifications for the quality evaluation and assessment of the Contractor’s Work. The
Employer’s Engineer will assume full responsibility to strictly implement the Employer’s Quality Assurance
Program during the Construction Period and Defects Notification Period of the Project.
The Employer’s Engineer will appoint a QA/QC Manager with a team to implement quality standards in the
Project design, construction, manufacturing, installation, testing, commissioning and operation. His responsibility
will be to evaluate and verify the Contractor's QA/QC operations. Also, the Employer’s Engineer will witness the
following tests for acceptance during different phases/ stages of Construction and Manufacturing.
Tests during construction and installation;
Tests during manufacturing at manufacturer's premises within and outside Pakistan;
Tests on completion and Tests after completion; and
Any other testing required.
The Employer’s Engineer will monitor the implementation of QA/QC Plan by the EPC Contractors closely and
ensure that the EPC Contractors has established competent QA/QC units in its organization with sufficient
expertise and experience in accordance with the QA/QC Plan. The Employer’s Engineer will ensure that the
testing methods, testing procedures, testing equipment /apparatus, testing criteria, sampling inspection methods
and procedures, etc. set forth in the QA/QC Plan is following the Specifications in the Project Requirement of the
EPC Contracts and also meets the requirements of applicable Chinese Standards and mandatory
standards/requirements of Pakistan. The Employer’s Engineer will independently conduct casual inspections of
the construction materials to be incorporated into the Project from time to time and submit inspection reports to
KPCL. If the inspection results show that the quality of the construction materials cannot meet the specifications
and standards, the Employer’s Engineer will, upon approval from KPCL, issue instructions to the EPC
Contractors to rectify the deficiency.
The Employer’s Engineer will supervise and witness the Project Construction works carried out by the EPC
Contractors related to all Project Components and Facilities to ensure that the Project is completed satisfactorily
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
5
and in compliance with the approved drawings, specifications, methods statements, construction schedules and
Contract Documents. The Employer’s Engineer will also supervise the manufacture, factory tests and necessary
quality control tests of the E&M equipment and be responsible for the inspection of the E&M equipment
installation.
The Employer’s Engineer will maintain a necessary presence during execution of the various civil works,
construction, activities and erection / testing / commissioning of E&M works and ensure that the construction of
Project Facilities, Utilities and Components will be in compliance with the specifications and standards in the
EPC contracts. The Employer’s Engineer will review and monitor the records and information management
system established by the EPC Contractors in accordance with the EPC Contracts. The Employer’s Engineer will
also assume responsibility for KPCL’s own Management of Records and Information relating to the Project
during Construction Period and Defects Notification Period.
The Employer’s Engineer will organize the investigation, rectification and summarization of any general
engineering quality incident and will assist KPCL to investigate, rectify and summarize any such incident. The
Employer’s Engineer will assist KPCL to settle disputes arisen from such incidents.
1.6 QA / QC Reporting by the Employer Engineer
The Employer Engineer has been maintaining daily and monthly reporting of all the QA /QC related matters. All
monitoring reports are available on the PMIS System developed exclusively for this Project. The Employer
Engineer’s QA/QC Team participates in almost all QA/QC related meetings on site. Frequent joint visits with
KPCL and the EPC Contractor are part of this monitoring to resolve minor issues on the spot.
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
6
1.6.1 QA/QC Audit
Date: July 8 to 10, 2021
Location: Karot Project Site – All laboratories, Batching Plants and QA/QC Department
Project Name 720MW Karot Hydropower Project
Employer KPCL
Employer’s Engineer SSS-JV
EPC Contractor TGDC
Audit No: 12
Lead Auditor: DCRE / Resident Principal Engineer QA/QC
No. Agenda Audit Issues found Actions
recommended
Target
Dates
DAY1
1 EPC Contractor
Laboratory.
The following have been
audited.
1. Records of Construction
activities.
1. Laboratory have only
records in soft copies
and most of the records
were in Chinese
language.
1. Main Laboratory is
instructed to keep a
copy of all activities in
English or in both
languages.
As soon as
possible
2. Records of Tests taken at
site. 2. Available 2. No action required
3. Records of Suppliers. 3. Available 3. No action required
4. Records of Tests taken
from Suppliers. 4. Available 4. No action required
5. Records of In-coming
materials 5. Available 5. No action required
6. Records of Tests taken
from In-coming materials 6. Available 6. No action required
7. Records of Rejected
Materials. 7. Available 7. No action required
8. Records of Equipment
Calibration.
8. Main laboratory is
keeping only their own
record.
8. They are instructed
to record all batching
plants and other site
laboratories
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
7
No. Agenda Audit Issues found Actions
recommended
Target
Dates
2
Sections 1, and 3
(Batching plant
3) Laboratory.
The following were audited.
Note: Section 1 laboratory is working only for shotcrete and Section 2 have closed their laboratory and are using main laboratory. Reporting is made only for batching plant 3 laboratory.
1. Records of Construction
activities. 1. Available 1. No action required
2. Records of Tests taken at
site. 2. Available 2. No action required
3. Records of Suppliers. 3. Available 3. No action required
4. Records of Tests taken
from Suppliers. 4. Available 4. No action required
5. Records of In-coming
materials 5. Available in Soft 5. No action required
6. Records of Tests taken
from In-coming materials 6. Available 6. No action required
7. Records of Rejected
Materials. 7. Available 7. No action required
8. Records of Equipment
Calibration.
8. Laboratory equipment is
calibrated from an
unapproved third party
without being witnessed by
the EE,
8. Calibrate all
laboratory equipment
from an approved
third party in the
presence of the EE.
3 Batching Plants
1, 3.
The following were audited.
Note: We are reporting
only batching plant 3,
batching plant no.1 is
closed.
1. Records of Calibration 1. Available. 1. No action required.
2. Records of In-coming
materials.
2. Available in their office
and not in site laboratory 2. No action required
3. Records of Concrete
requests.
3. Not available in proper
form.
3. Need to keep updated
record.
As soon as
possible
4. Records of Concrete
dispatched. 4. Not available as required.
4. EPC contractor is
required to print out
Records of Concrete
produced and where
As soon as
possible
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
8
No. Agenda Audit Issues found Actions
recommended
Target
Dates
the material is being
dispatched. EE has
already raised 2 NCRs
on this issue.
5. Records of Plant
maintenance.
5. Section 3 staff are just
recording in the note book
only in Chinese
5. EPC Contractor is
instructed to keep
records of batching
Plants equipment
maintenance in
English or both
Languages.
As soon as
possible
DAY 2
1 Site
Implementation.
The sites were visited to
observe the
implementation of the
QA/QC procedure.
No Concrete dispatch slips
are printed out and sent to
site QA/QC staff at pouring
point.
Concrete pouring records
were found without mix
design numbers, dispatch
slip numbers, and was
available only with truck
numbers and concrete
grades.
It is a contract
requirement that TGDC
are to print out Records
of Concrete dispatched.
Site pouring records
should include all
required details like mix
design numbers,
dispatch slip numbers
etc.
EPC contractor needs
to conduct training of all
Sections lab personnel
to avoid any quality
issues.
As soon as
possible.
2
QA/QC
Documentation
and
Administration.
The following were audited.
1. Records of the
Training of QA/QC
Staff.
Not Available
Need to conduct
trainings regularly and
keep record.
As soon as
possible.
2. Records of NCR’s
(Including Issued
dates, Person or
Department
responsible for
closing, Actions taken
and Status).
Available. No action required.
3. Review of the
Implementation of Available. No action required.
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
9
No. Agenda Audit Issues found Actions
recommended
Target
Dates
Project Approved
plans.
4. Review of the
Implementation of
Corrective Actions.
Available. No action required.
3 Mechanical Work
1. Review of test results
record. Test results were available No action required.
2. Status of approved
material.
SSSJV staff inquired about
the approval, technical
specification and data sheet
of protective paint used on
the Rotor and Stator of Unit
1 and epoxy / Glue (DECJ
1209).
No evidence of desired
documents was
available.
As soon as
possible
3. List of rejected
material. Available No action required
4. Record of unapproved
or incomplete test. Available No action required
5. Record of all RFIs.
Inquired about the
mechanical works carried
out during lockdown.
Waiting for
management decision
about the work carried
out without EE’s
supervision.
As soon as
possible
4 Electrical work
1. Review of test results
record. Available. No action required.
2. Status of approve
material. Available Need action required
3. List of rejected
material.
No electrical material
rejected No action required
4. Record of unapproved
or incomplete test. No electrical item was found. No action required
5. Record of all RFIs
RFIs and CVI record was
not maintained in a proper
filing system.
Need to maintain RFIs
and CVI records.
As soon as
possible
Day 3 Section 5 Azad Patten
1
Section 5
Contractor
Laboratory.
The following have been audited
1. Records of Available No action required
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
10
No. Agenda Audit Issues found Actions
recommended
Target
Dates
Construction activities.
2. Records of Tests taken at site.
Available No action required
3. Records of suppliers. Available No action required
4. Records of Tests Taken from Supplier.
Available No action required
5. Record of In-coming Materials.
Available in soft copy with
Procurement department,
not in Laboratory.
Need to keep record of
all in-coming materials As soon as
possible
6. Records of tests taken from In-coming Materials.
Available
Need to maintain a hard
copy record in the
laboratory
7. Records of Rejected Material.
Not Available Need to keep record of
rejected material.
As soon as
possible
8. Record of equipment calibration.
Available No action required
2
Section 5
Batching Plant
Azad Patten
1. Record of Calibration. Available No action required
2. Records of In-coming
Materials. Not Available
Need to keep record of
in-coming materials
As soon as
possible
3. Records of concrete
Request.
Available with incomplete
details
Need to improve
concrete request
format.
As soon as
possible
4. Record of concrete
dispatched. Available No action required.
5. Record of Plant of
maintenance. Available No action required
3 Site
Implementation
1. The site was visited in
order to observe the
implementation of
QA/QC procedure.
No concrete was in progress
at site. However, EE
instructed the contractor to
follow the approved / agreed
procedures for site work.
No action required
4
QA/QC
Documentation
and
Administration
1. Record of the training
QA/QC staff. Not Available
Need to conduct
trainings for QA/QC
team regularly.
Before next
audit
2. Records of NCRs
including issue dates. Available No action required
3. Review of the
implementation of
Project Approved
Not Available Quick action required As soon as
possible
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
11
No. Agenda Audit Issues found Actions
recommended
Target
Dates
plans.
4. Review of the project
Implementation of
Corrective Action.
Not Available No action required
1.6.2 General comments:
1. Overall, EE observed that the EPC contractor needs to take action urgently to resolve the issues raised
in the Audit.
2. Most of the following observations are identical to previous audit reports. TGDC is instructed to strictly
implement required actions in all sections.
3. During audit, it was found that no technical staff was available from EPC contractor, EE highlighted this
serious issue by letter (SSS JV 7495 dated June 29.2021). EPC response is still awaiting.
4. During audit, it was recognized that many small issues can be closed with discussion but no one was
available from EPC QA/QC department. EPC contractor must take some urgent action in this regard.
5. Batching plant concrete records were not signed by EPC laboratory Personnel and they are not getting
sign from EE’s QA/QC team.
6. EPC Contractor should submit regularly all concrete records for signing and laboratory should keep one
copy of all signed records structure wise that will help them for the final report of all structures.
7. Section 5 is not conducting training on the site for workers. Urgent action needs to be taken.
8. Some NCRs regarding QA/QC are still open; EPC contractor needs to close all open NCRs on an
urgent basis.
9. For rejected materials, contractor should get signed witnessing from EE’s QA/QC team.
10. Improvement was observed in record keeping in proper manner at Section 1 QA/QC office and it is
expecting from all in future.
11. During signing any testing paper or QA/QC paper, TGDC must record their names in English for clear
identification.
12. The training record was not available with EPC contractor and they did not conduct any training in last
three months, however, Section 1 have that record only in Chinese language and only for Chinese
people.
13. Regular training should be conducted for all staff and record should be maintained in English or in both
languages.
14. EPC contractor should improve materials and testing record system in the asphalt plant laboratory.
15. If EPC contractor is making changes in their internal QA/QC management staff, inform EE and KPCL.
16. EPC Contractor’s Main laboratory staff should visit Azad Pattan site regularly to guide the team and to
keep control on all quality activities.
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
12
17. EPC contractor QA/QC has developed his own document system. Now we can find all hard copy
records in their control room. QA/QC needs to deploy a qualified person for keeping the records up to
date and maintaining the documentation.
18. Some of Project records are not fully in English or both in English and Chinese. EPC contractor must
ensure all records are in English or in both English and Chinese.
19. EPC contractor QA/QC Department needs to print out copies of concrete production slips for transit
mixers for pouring at site so that the site QA/QC staff can identify where the pour is located and record
the details of all batch concrete to avoid any pouring mistakes. EE has already raised 2 NCRs on this
issue.
20. EE observed a serious communication gap between TGDC and all Sections.
21. TGDC needs to strengthen their field laboratory and QA/QC team to control issues.
22. EPC contractor needs to deploy senior staff to check all QA/QC arrangements of Sections 1, 2, 3 and 5
as per audit requirements.
23. Section 3 and Section 5 filing systems were not to required standards, needed to improve before next
audit.
24. EPC contractor needs to develop their internal QA/QC audit system for all Sections to improve quality of
work.
25. Section 5 needs to get assistance from TGDC for understanding of QA/QC audit requirements.
26. Electrical and Mechanical departments need to improve their QA/QC team and record keeping system.
27. EPC contractor QA/QC team need a strong communication with SSS/JV team to avoid small issues.
28. During audits, SSS JV team recommends that EPC QA/QC team should call a monthly quality meeting
of all Sections, discuss on going issues, and share their findings with SSS JV.
29. For best communication EPC contractor needs English interpreters in different departments.
1.6.3 QA/QC Auditing by Employer Engineer
Following record shows general photographs from the Auditing done by the Employer Engineer’s QA/QC Team
on site, laboratories and batching plants for the current Reporting Period and indicates generally poor but
marginally acceptable practices / systems.
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
13
TGDC Laboratory: Audit of testing records
TGDC Laboratory: Audit of testing records
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
14
Section 2: Labeling of Records needs to be in English
Section 1: Material records need to be in proper filing system
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
15
Section 2: Checking of incoming material invoices
Section 1: Checking of Spillway RFIs record at office
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
16
Concrete Batching Plant: Checking of concrete documents
Concrete Batching Plant: Record of concrete dosage sheet is not in proper form
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
17
Concrete Batching Plant: Records not available in English version
Asphalt Laboratory: Checking documents record of Asphalt Concrete
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
18
Asphalt Laboratory: Checking testing records of Asphalt Concrete
Concrete Batching Plant: Checking of concert request slips record
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
19
Section 2: Records of training of QA/QC staff need to be in English version
TGDC Main office: Audit Completed with QA/QC team and SSSJV staff
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
20
APPENDICES (E&M ISSUES)
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
21
APPENDIX A: THE LIST OF RFI’S RAISED DURING LOCKDOWN PERIOD
No. Description of RFIs
1. Inspection of Installation of Brake Plates of Rotor # 1
2. Inspection of Installation of Lower Press Plates of Rotor # 1
3. Inspection of Elongation Value of Tightened Bolts between Rotor Hub and Generator Shaft # 1
4. Inspection of Assembly of Rotor before Shifting # 1
5. Inspection of Adjustment of Stator Installation # 1
6. Inspection of Installation of Stator Core Lamination # 1
7. Inspection of Rotor Supports Assembly and Installation # 1
8. Inspection of Assembly of Rotor Yoke # 1
9. Inspection of Assembly Rotor Pole # 1
10. Inspection of Rotor before Shifting # 1
11. Inspection of Rotor Heat Wedge Key # 1
12. Inspection of Installation of Brake Plates of Rotor # 2
13. Inspection of Adjustment of Stator Installation # 2
14. Inspection of Installation of Submerged Pump in Powerhouse
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
22
APPENDIX-B: THE LIST OF LOST RFI’S RELATED TO MECHANICAL WORKS
No Description of RFIs
1. Installation of Draft Tube Cone # 1
2. Installation of Draft Tube Cone # 2
3. Installation of Draft Tube Cone # 3
4. Installation of Draft Tube Cone # 4
5. Welding Seam Defect repaired and painting on flowing surface of draft tube elbow # 1
6. Welding Seam Defect repaired and painting on flowing surface of draft tube elbow # 2
7. Welding Seam Defect repaired and painting on flowing surface of draft tube elbow # 3
8. Welding Seam Defect repaired and painting on flowing surface of draft tube elbow # 4
9. Embedded Support of Stay Ring # 1
10. Embedded Support of Stay Ring # 2
11. Embedded Support of Stay Ring # 3
12. Embedded Support of Stay Ring # 4
13. Installation of Stator Foundation Plates # 1
14. Installation of Stator Foundation Plates # 2
15. Installation of Stator Foundation Plates # 3
16. Installation of Stator Foundation Plates # 4
17. Installation of Foundation Plates of Upper Bracket # 1
18. Installation of Foundation Plates of Upper Bracket # 2
19. Installation of Foundation Plates of Upper Bracket # 3
20. Installation of Foundation Plates of Upper Bracket # 4
21. Installation of Foundation Plates of Spiral Case # 1
22. Installation of Foundation Plates of Spiral Case # 2
23. Installation of Foundation Plates of Spiral Case # 3
24. Installation of Foundation Plates of Spiral Case # 4
25. Installation of Foundation Plates of Stator # 1
26. Installation of Foundation Plates of Stator # 2
27. Installation of Foundation Plates of Stator # 3
28. Installation of Foundation Plates of Stator # 4
29. Installation of Drainage valve Ø500 of Spiral case # 2
30. Installation of Pit Liner # 1
31. Installation of Pit Liner # 2
32. Installation of Pit Liner # 3
33. Installation of Pit Liner # 4
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
23
APPENDIX-C: THE LIST OF LETTERS RELATED TO MECHANICAL WORKS
WHICH ARE NOT RESPONDED BY THE CONTRACTOR
No. Description Letter
No. Remarks
1. Cable Tray Sampling and Testing
7169 Contractor said they will submit the Sample along with Turbine and Generator Samples
2. Corrosion on Steel Components of Rotor (Lower Bracket Assembly – Braking System)
7262 Not Rectified and Responded yet.
3. O&M Requirement 7295
Contractor said there are a lot of documents and their preparation is in progress and will be submitted after the completion. It was suggested to the Contractor to submit the documents stage wise for the Approval from Employer’s Engineer.
4. Turbine Oil Purification System 7289 Will be responded in the coming week.
5. Drainage and Dewatering System
7298 Will be responded in the coming week.
6. Component and Hardware Material Finish Quality
7324 Will be responded in the coming week.
7. HVAC Equipment Layout and Lighting Layout Drawings - Auxiliary Power House Building
7338 Will be responded in the coming week.
8. Unacceptable Quality - Filtration Vessels
7351 Not Rectified and Responded yet.
9. Unit 1 - Oil Pipe Design Issue - Working Clearances
7352 Will be responded in the coming week.
10. Material Inspection Report of Turbine and Generator
7410
Contractor said they have written the letter to the manufacturer for the samples as soon as the Contractor gets the dates from the manufacturer, he will respond to the letter with the dates of samples arrival.
11. Oil Pressure Testing - Unit 1 - Generator Braking System
7426 Will be responded in the coming week.
12. Corroded Pipework and Fittings (Intake Tower)
7462 The Contractor said they already instructed their subcontractor to properly clean the pipework and its fittings before any inspection.
13. Water Supply Pipeline Layout of Switch Station and Fire Pump Room
7474 Will be responded in the coming week.
14. Use of Asbestos Material 7491
The Contractor said they have not used the Asbestos material for insulation of Rotor # 2. They used Glass wool Insulation material in which cotton is insulated in Aluminum Silicate Needled Blanket.
The Contractor was asked to Submit the Test Reports and provide the Sample of above-mentioned Insulation Material for Employer’s Engineer record.
Employer’s Engineer Services for 720MW Karot Hydropower Project QA/QC Audit Report | July 2021
24
APPEDNIX-D: THE LIST OF SOME OTHER PENDING ISSUES
No. Description Remarks
1. Hydraulic Oil Samples Collected from Hoisting System at Intake Tower – Results are awaited
The Contractor said, results will be submitted in two Weeks
2.
Intake and Tailrace Gates have been installed during the Lockdown Period (Nov 2020 – Feb 2021) but no evidence of their inspection has been provided to Employer’s Engineer record.
The Contractor said that they just installed the Gates in that period but inspections will be offered to Employer’s Engineer after the completion (After Painting and after final in-house inspection of the Contractor)
3.
Submit the Method Statement of Installation of Gantry Crane at Shunt Reactor (Ref. Letter no. SSS-7517 dated July 07, 2021)
The Contractor said, they have prepared the Method Statement and will submit it in a couple of days.