    SCREEN WALLTower - 2

  • 8/3/2019 Screen Wall at Pbp Site

    2/33

    Contents

    Introduction

    Stages

    Roles & Responsibilities

    Flow Chart

    Total Scope & Details

    Dimensions

    Problems Faced Solution Adopted

    Screen Wall Pics

    Conclusion

  • 8/3/2019 Screen Wall at Pbp Site

    3/33

    Introduction

    Erecting structural steel work for

    commercial building construction takes

    place in a dynamic changing environmentwhere there are many risks and hazards

    associated with it.Proper and timely

    planning and coordination are the most

    effective ways to manage these hazardsand risks.

  • 8/3/2019 Screen Wall at Pbp Site

    4/33

    Stages

    Project involving structural steel

    construction have main 4 stages.

    The stages are as follows :Design

    Fabrication

    TransportErection

  • 8/3/2019 Screen Wall at Pbp Site

    5/33

    Roles & Responsibilities

    The person who is responsible for the engineeringdesign of the Structure

    Structural designEngineer

    The party who is responsible for managing theconstruction and who has control over itClient

    The person who is responsible for the engineeringdesign and stability aspects of the erection of the steelstructure

    Erection Engineer

    The person responsible for making the steel work

    Fabricator

    The Employer responsible for engaging the erectioncrew and erecting the structureErector

    The person who will be looking after the safety aspects

    during erection.Safety Inspector

  • 8/3/2019 Screen Wall at Pbp Site

    6/33

    Flow Chart

  • 8/3/2019 Screen Wall at Pbp Site

    7/33

    Total Scope & Details

    Scope of Work 285 MT

    Length ofSW 120 metre

    Width ofS

    W 22 metre Height ofSW 16.5 metre

    Total Columns 18 Nos

    Total Tie Beams 60 Nos

    Total Tube 132 Nos

    Plates - 432 Nos

  • 8/3/2019 Screen Wall at Pbp Site

    8/33

    Dimensions

    Column 450mm x 750mm x 16mm

    Tie Beam 350mm x 750mm x 10mm

    Tube size- 150mm x 150mm x 4mm C-Channel 100mm x 50mm

  • 8/3/2019 Screen Wall at Pbp Site

    9/33

    System Process We Adopted Prior

    ToS

    tructural Erection

  • 8/3/2019 Screen Wall at Pbp Site

    10/33

    What We Do ?

    Define : Understand and specifying the problem

    Measure : Identifying the risks involved

    Analyze : Brainstorming with the Consultants

    and come up with innovative ideas Improve : Bring Change while implementing new

    technologies

    Control : Keep Control while actual erection to

    avoid unprecedented accidents

  • 8/3/2019 Screen Wall at Pbp Site

    11/33

    To Avoid Risk

  • 8/3/2019 Screen Wall at Pbp Site

    12/33

    Prepare be ready

    Respond In a timely manner

    Recover when the need arises Mitigate Eradicate the errors/Reduce the

    errors

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    13/33

    Sequence of Activities during

    Erection Receiving Material from the shop and

    temporarily stacking them, if necessary.

    Lifting and placing the member andtemporarily holding in place.

    Temporarily bracing the system to ensure

    stability during erection.

    Aligning and permanently connecting the

    members either by bolting or welding.

  • 8/3/2019 Screen Wall at Pbp Site

    14/33

    SCREEN WALL Tower 2

    Problems faced : Prior starting theScreen wall fabrication a square hollow

    section of dimension (750x450x16)mm isrequired for Screen wall Vertical Columns

    which isnt easily available in market and if

    we need to manufacture such section it

    would cost at skyrocketing price.

  • 8/3/2019 Screen Wall at Pbp Site

    15/33

    Contd..

    Solution we adopted : We created ashop drawing for the square hollowsection of the required dimension (Cutthe plate and bend it into J section and

    joining the two J shaped plates into 1square hollow section with the help of

    Splice Plates) which we got it approvedfrom the Consultant and Client.

  • 8/3/2019 Screen Wall at Pbp Site

    16/33

    Contd..

    Achievement :

    Saved time

    Provided value engineering ideasReduced time cycle

  • 8/3/2019 Screen Wall at Pbp Site

    17/33

    Problem 2

    Problems Faced : At terrace level (117mheight) about a total of 250 MT of box

    columns needed to be lifted and fixed butthe problem we faced is the unavailability

    of crane and due to the height factor hydra

    cannot be used which is virtually impossible

    to use.

  • 8/3/2019 Screen Wall at Pbp Site

    18/33

    Solution

    Solution We adopted : Usage ofVertical Gadams and chain pulleys

    having a capacity to lift 4MT waserected at Terrace and used to lift the

    2.5m of Column pieces to complete the

    total 16m height of each column.

  • 8/3/2019 Screen Wall at Pbp Site

    19/33

    After Fabrication of two J shaped

    Section

  • 8/3/2019 Screen Wall at Pbp Site

    20/33

    Erection of 1st Screen Wall Section

  • 8/3/2019 Screen Wall at Pbp Site

    21/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    22/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    23/33

    Screen Wall in Progress

  • 8/3/2019 Screen Wall at Pbp Site

    24/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    25/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    26/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    27/33

    Screen Wall in Progress

  • 8/3/2019 Screen Wall at Pbp Site

    28/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    29/33

    Contd..

  • 8/3/2019 Screen Wall at Pbp Site

    30/33

    GOAL IS ATTAINED ONLY IF

    EVERYTHING FALLS

    AT THE RIGHT PLACE

    AT THE RIGHT TIME &

    HAVE THE RIGHT RESOURCES

    MACHINE

    Teamwork Resources

    MANPOWER

    SAFETY

    GOAL

  • 8/3/2019 Screen Wall at Pbp Site

    31/33

  • 8/3/2019 Screen Wall at Pbp Site

    32/33

    Conclusion

    The Structural Heavy work requires pre-

    planning before performing the actual

    erection on site. It involves all the aspects

    of organizing resources , proper job

    allocation and systematic co-ordination ,

    risk assessment to achieve great results

    on site.