sche07p calculation 9901
TRANSCRIPT
-
8/8/2019 Sche07P Calculation 9901
1/25
Prof. Awad Hanna
Estimating Activity DurationEstimating Activity DurationTime Interval
Time Interval is selected according to the
nature of the activity (seconds - minutes)
It is common practice in construction
industry to use calendar day.
Use one and only one time unit for anyschedule.
-
8/8/2019 Sche07P Calculation 9901
2/25
Prof. Awad Hanna
Estimating Activity DurationEstimating Activity Duration1.From companys record
2.From standard estimating guide3.Interviewing field personnel.
-
8/8/2019 Sche07P Calculation 9901
3/25
Prof. Awad Hanna
Weather and Contingency
Allowance
Weather and Contingency
Allowance Two approaches for assignment of weather
allowance:
1. Add the Weather Allowance at the end ofthe project as a separate activity.
2. Add Weather Allowance to those affected by
the weather.
3.Add weather allowance at the end of each
construction segment (site preparation,
foundation, etc.)
-
8/8/2019 Sche07P Calculation 9901
4/25
Prof. Awad Hanna
Contingency items
Other activities can be added to allow forcontingency such as strikes
Time ZeroThe close of the work period
immediately preceding the start of the
project.
-
8/8/2019 Sche07P Calculation 9901
5/25
Prof. Awad Hanna
Scheduling Computation for Arrow DiagramScheduling Computation for Arrow Diagram
Four time values associated with each
activity:
1.ESD Early Start Date
2.EFD Early Finish Date
3.LSD Late Start Date
4.LFD Late Finish Date
-
8/8/2019 Sche07P Calculation 9901
6/25
Prof. Awad Hanna
Early Start Date for an activity is the earliest
point in time that any activity bursting from its
beginning node can start.
Late Finish Date is the latest point in time
that any activity which merges at the activitys
ending node can finish.
-
8/8/2019 Sche07P Calculation 9901
7/25
Prof. Awad Hanna
The Four ActivityTimes -Arrow Diagram NotationThe Four ActivityTimes -Arrow Diagram Notation
i jActivity
Tij
Tij TijTime
Available
Activity ij Activity ij
ESDij EFDij LSDij LFDij
(a)
(b)
-
8/8/2019 Sche07P Calculation 9901
8/25
Prof. Awad Hanna
Forward Pass RulesForward Pass Rules
Rule 1The initial project event is assumed to occur at time
zero
Rule 2
All activities are assumed to start as soon as
possible, that is , as soon as all the predecessor
activities are completed.
Rule 3
The early finish time of an activity is merely the sum
of its early start date and the estimated activity
duration.
EFDij
= ESDij
+ Tij
-
8/8/2019 Sche07P Calculation 9901
9/25
Prof. Awad Hanna
Forward Pass Rules (cont.)Forward Pass Rules (cont.)
Rule 4
The late start date LSDij is found by
subtracting the activity duration Tij from the
late finish date LFDij
LSDij = LFDij - Tij
-
8/8/2019 Sche07P Calculation 9901
10/25
-
8/8/2019 Sche07P Calculation 9901
11/25
-
8/8/2019 Sche07P Calculation 9901
12/25
Prof. Awad Hanna
1. Total Float
1. Total Float
Total float may be defined as that time
span in which the completion of an
activity may occur and not delay thetermination of the project.
TFij = LFDij - EFDij
= LSDij - ESDij
-
8/8/2019 Sche07P Calculation 9901
13/25
Prof. Awad Hanna
2. Free
Float2
. Free
Float Free float may be defined as the time
span in which the completion of an
activity may occur and not delay thefinish of the project nor delay the start of
any following activity.
FFij = ESDjk - EFDij
-
8/8/2019 Sche07P Calculation 9901
14/25
Prof. Awad Hanna
3. Interfering Float3. Interfering Float
That part of the total float which remains afterfree float has been deducted is the interfering
float.
It may be defined as: The time span in which
the completion of an activity may occur and
not delay the termination of the project but
within which completion will delay the start of
some other following activity.
INTFij = TFij - FFij
-
8/8/2019 Sche07P Calculation 9901
15/25
Prof. Awad Hanna
4. Independent Float4. Independent Float
The fourth float, independent float, is theamount of scheduling leeway of an activity
that is independent of the early starts and late
finishes of any other activity. It may be
formally defined as:
The time span in which the completion of an
activity may occur and not delay the
termination of the project, not delay the start
of any following activity, and not be delayed
by any preceding activity.
-
8/8/2019 Sche07P Calculation 9901
16/25
-
8/8/2019 Sche07P Calculation 9901
17/25
Critical Path Computations on
the Network
Critical Path Computations on
the Network
-
8/8/2019 Sche07P Calculation 9901
18/25
Prof. Awad Hanna
The
Two Event Approach
Early Start Event
In the forward pass, the ma imum of the
EFD values for all activities merging at a
node is taken as ESD value for all the
activities that burst from the same node.
TEj = Ma I (TEi +Tij)
-
8/8/2019 Sche07P Calculation 9901
19/25
Prof. Awad Hanna
For all activities entering node j,
TEj
is taken as the greatest sum of
all activities merge to the node
-
8/8/2019 Sche07P Calculation 9901
20/25
Prof. Awad Hanna
Late Finish Event
In the backward computations, the
minimum of LSD valves is taken as
the latest finish time for all activitiesthat enter the node.
TLj = MinI (TLi +Tij)
-
8/8/2019 Sche07P Calculation 9901
21/25
Prof. Awad Hanna
Start by the last activity, the TL for
the ne t earlier node is taken as
the minimum value of the late timeevent minus activity duration.
-
8/8/2019 Sche07P Calculation 9901
22/25
Prof. Awad Hanna
-
8/8/2019 Sche07P Calculation 9901
23/25
Prof. Awad Hanna
Float Calculations From EventTimesFloat Calculations From EventTimes
Total Float
Tfij = TLj - TEi - TijE ample
TF2-2 = TL2 - TE2 - T2-2
= 1 - - 1 =
-
8/8/2019 Sche07P Calculation 9901
24/25
Prof. Awad Hanna
Free Float
FFij = TEj - TEi - Tij
E ample
FF2-2 = TE2 - TE2 - T2-2
= 14 - - 1 = 4
-
8/8/2019 Sche07P Calculation 9901
25/25
Prof. Awad Hanna
Interfering Float
INTFij = TLj - TEjE ample
INTF2-2 = TL2 - TE2
= 1 - 14 = 3Inde endent Float
INDFij = TEj - TLi - TijE ample
INDF2-2 = TE2 - TL2 - T2-2= 14 - - 1 = 4