Saudi Aramco’s Saudi Aramco’s Approach to Fieldbus Approach to Fieldbus
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
How will YOUR How will YOUR company approach company approach
Fieldbus on your next Fieldbus on your next project? project?
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FOUNDATION Fieldbus (FF) will be our FOUNDATION Fieldbus (FF) will be our Strategic BusStrategic Bus
–– FF Solutions must be ApprovedFF Solutions must be Approved
–– Start Small & Grow FF ExperienceStart Small & Grow FF Experience
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FOUNDATION Fieldbus (FF) will be our FOUNDATION Fieldbus (FF) will be our Strategic BusStrategic Bus
•• FFH1 is now a Mainstream ProductFFH1 is now a Mainstream Product
•• FF has Benefits We can’t IgnoreFF has Benefits We can’t Ignore
•• What are Our Options?!What are Our Options?!
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachFF H1 is Now a Mainstream ProductFF H1 is Now a Mainstream Product
FF H1 Product is MatureFF H1 Product is Mature
Major Oil & Gas Company’s use of FFMajor Oil & Gas Company’s use of FF
EngrEngr Firm FF Expertise AvailableFirm FF Expertise Available
FF Training Here & Acceptance HighFF Training Here & Acceptance High
Oil & Gas Major’s Use of FF H1Oil & Gas Major’s Use of FF H1
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FOUNDATION Fieldbus (FF) will be our FOUNDATION Fieldbus (FF) will be our Strategic BusStrategic Bus
•• FFH1 is now a Mainstream ProductFFH1 is now a Mainstream Product
•• FF has Benefits We can’t IgnoreFF has Benefits We can’t Ignore
•• What are Our Options?!What are Our Options?!
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachFF has Benefits you can’t IgnoreFF has Benefits you can’t Ignore
–– Project SavingsProject Savings
–– FF Device & Process DiagnosticsFF Device & Process Diagnostics
–– Resistance to ObsolescenceResistance to Obsolescence
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachFF has Benefits you can’t IgnoreFF has Benefits you can’t Ignore
–– Project SavingsProject Savings
–– FF Device & Process DiagnosticsFF Device & Process Diagnostics
–– Resistance to ObsolescenceResistance to Obsolescence
PIB D
“Home Run” Cable (Trunk)
D
Junction Box
DTB’s for FF16 segments
Up to 256 devices
Conventional Wiring TB’s
87 devices
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachFF has Benefits you can’t IgnoreFF has Benefits you can’t Ignore
–– Project SavingsProject Savings
–– FF Device & Process DiagnosticsFF Device & Process Diagnostics
–– Resistance to ObsolescenceResistance to Obsolescence•• No Problem Found Work TicketsNo Problem Found Work Tickets
•• Device & Process DiagnosticsDevice & Process Diagnostics
•• Increase in Plant UptimeIncrease in Plant Uptime
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachFF has Benefits you can’t IgnoreFF has Benefits you can’t Ignore
–– Project SavingsProject Savings
–– FF Device & Process DiagnosticsFF Device & Process Diagnostics
–– Resistance to ObsolescenceResistance to Obsolescence•• Infrastructure to Apply High Value DiagnosticsInfrastructure to Apply High Value Diagnostics
•• Infrastructure to Apply FF HSEInfrastructure to Apply FF HSE
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FOUNDATION Fieldbus (FF) will be our FOUNDATION Fieldbus (FF) will be our Strategic BusStrategic Bus
•• FFH1 is now a Mainstream ProductFFH1 is now a Mainstream Product
•• FF has Benefits We can’t IgnoreFF has Benefits We can’t Ignore
•• What are Our Options?!What are Our Options?!
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachWhat are our Options?What are our Options?
–– Analog or ProprietaryAnalog or Proprietary
–– Analog with HARTAnalog with HART
–– ProfibusProfibus PAPA
–– FOUNDATION FieldbusFOUNDATION Fieldbus
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FOUNDATION Fieldbus (FF) will be our FOUNDATION Fieldbus (FF) will be our Strategic BusStrategic Bus
–– FF Solutions must be ApprovedFF Solutions must be Approved
–– Start Small & Grow FF ExperienceStart Small & Grow FF Experience
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FF Solutions Must be ApprovedFF Solutions Must be Approved
•• Aramco DCS RVL Aramco DCS RVL -- Must bid projectsMust bid projects
•• Each Vendor has a FF ‘solution’Each Vendor has a FF ‘solution’
•• Aramco developed basic FF requirements Aramco developed basic FF requirements
•• Honeywell EPKS is Aramco approved for FF Honeywell EPKS is Aramco approved for FF
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
ExperionExperion PKSPKS
TDC3000 FF (not)TDC3000 FF (not)
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– FOUNDATION Fieldbus (FF) will be our FOUNDATION Fieldbus (FF) will be our Strategic BusStrategic Bus
–– FF Solutions must be ApprovedFF Solutions must be Approved
–– Start Small & Grow FF ExperienceStart Small & Grow FF Experience
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach1.1. Fieldbus StrategyFieldbus Strategy
–– Start Small & Grow FF ExperienceStart Small & Grow FF Experience
•• Aramco ‘Started Small’ to get experienceAramco ‘Started Small’ to get experience
•• Proponent must commit to FFProponent must commit to FF
•• Current Aramco FF Installations:Current Aramco FF Installations:
–– 4 FF Installations (504 FF Installations (50--250 FF points each)250 FF points each)–– 7 projects ongoing (1007 projects ongoing (100--500 FF points each)500 FF points each)–– 1 larger project ongoing (>1000+ FF points)1 larger project ongoing (>1000+ FF points)–– Multiple LARGE FF projects coming ! Multiple LARGE FF projects coming !
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Accepting a Fieldbus SolutionAccepting a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution– Must be an Aramco approved DCS.
– Must meet Aramco’s FF Host Requirements:
– Must Pass 3 Aramco Tests :
FF Basic Functionality consistent with conventional FF Reliability meets that of conventionalFF Configuration consistent with Conventional
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
–– Must Meet Aramco’s FF Host RequirementsMust Meet Aramco’s FF Host RequirementsRedundant H1 Card & Power Online/Offline FF Configuration Consistent with ConventionalBulk Import Config Capability for Large FF ProjectsFF Operation Consistent with ConventionalFF (& HART) Instrument Maintenance Tools FF Training & Support LocallyMust have installed FF baseInternal Interoperability Verification
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
– Must Pass 3 Aramco Tests that Verify:
• FF Basic Functionality consistent with conventional
• FF Reliability meets that of conventional
• FF Configuration consistent with Conventional
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
FF Positioner
FF DP transmitter and flow orifice
Process Simulation PanelProcess Simulation Panel
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
– Must Pass 3 Aramco Tests that Verify:
• FF Basic Functionality consistent with conventional
• FF Reliability meets that of conventional
• FF Configuration consistent with Conventional
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
FC100
RC100 FC101
TC100
Condensate
Bottoms Product
Steam
Column Feed
ColumnC-210
E-200
Test Purpose: Test Purpose:
FF control & I/O operates consistently with conventional by:FF control & I/O operates consistently with conventional by:
1.1. "Invalid Value""Invalid Value" Detection And Propagation. Detection And Propagation. Fail FT100 & then restoreFail FT100 & then restore..
2.2. InitializationInitialization Detection And Propagation. Detection And Propagation. FIC100 to manual then Cascade.FIC100 to manual then Cascade.
3.3. WindupWindup Detection, Propagation And Protection Detection, Propagation And Protection Set output limits on FIC100, then restoreSet output limits on FIC100, then restore..
4.4. Controller Controller DownloadDownload From Configurator to FF Instrumentation. From Configurator to FF Instrumentation. Evaluate control bumpsEvaluate control bumps..
Basic Functionality TestBasic Functionality Test
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
– Must Pass 3 Aramco Tests that Verify:
• FF Basic Functionality consistent with conventional
• FF Reliability meets that of conventional
• FF Configuration consistent with Conventional
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Back
FF Reliability Test
Test Objectives:Test Objectives:
Determine FF device & function block Determine FF device & function block action on the following events:action on the following events:
1.1. Fail Redundant H1 Card & ControllerFail Redundant H1 Card & Controller
2.2. Add / Remove Device from SegmentAdd / Remove Device from Segment
3.3. Modify & Download ConfigurationModify & Download Configuration
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Reliability Test Example Results
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
– Must Pass 3 Aramco Tests that Verify:
• FF Basic Functionality consistent with conventional
• FF Reliability meets that of conventional
• FF Configuration consistent with Conventional
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Configuration Test Purpose
Back
Configuration:Configuration: Verify that both DCS conventional and FF control and I/O configuration is done in similar way and on a consistent configurator.
Offline Configuration:Offline Configuration: Verify that FF configurations may be made off-line , e.g. when no physical I/O is connected to the system.
Displays:Displays: Verify that conventional and FF points operate consistently on faceplates, & custom graphics.
Operator View:Operator View: Verify on-line changes, saves, historization, trending and alarming is consistent for conventional and FF.
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Honeywell FF Test Hardware
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Currently Approved FF Solutions
Emerson DeltaVEmerson DeltaVYokogawa Centum ALF111Yokogawa Centum ALF111Honeywell EPKSHoneywell EPKS
– All 3 FF solutions well integrated in DCS.– High consistency between FF and conventional.– FF Redundancy provided.– A few issues, but...– All committed to make FF project successful.
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach3.3. Requirements for FF Requirements for FF
InstallationInstallation
SAES-J-904:– Requirements for a
Quality FF Installation
– Includes Discussion of ‘Intent’
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach3.3. Requirements for FF InstallationRequirements for FF Installation
J-904 Requirements:– Redundant H1 Interface Cards– Redundant FF Power Supply / Segment– Spur Short Circuit Protection– With Control - Max. 8 devices per Segment – Monitor Only - Max. 12 devices per Segment– Max. 2 final control devices (valves) per Segment– Plus Much More Risk Assessment – Spare Capacity
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
H1 Interface Card
FF Power Supply w/ Terminator
Relcom Megablock w/
Spurguard
TerminatorField Devices
Spur Length & Min Voltage
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus ApproachSAES-J-904: ISS Additions for FFLAS capable (yes/no)
Minimum Operating Voltage (Vdc)
Quiescent Current Draw (mA)
Polarity Sensitive Termination (yes/no)
DD revision level
Channel number and Description, (e.g., Channel 1 - Sensor 1, Channel 2 - Body Temperature, Channel 3 - Sensor 2, etc.).
Function Blocks Available, (e.g., AI_1, AI_2, PID_1, etc.)
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco
Aramco’s Fieldbus Approach
1.1. Fieldbus StrategyFieldbus Strategy
2.2. Approving a Fieldbus SolutionApproving a Fieldbus Solution
3.3. Requirements for Fieldbus InstallationRequirements for Fieldbus Installation
How will YOU approach How will YOU approach Fieldbus on your next project?Fieldbus on your next project?
Honeywell Users Group Meeting 2004 - BahrainCopyright © Saudi Aramco 2004. All rights reserved. No portion of this article may be reproduced by any process or technique without the express written consent of Saudi Aramco