san pablo timeline• pave san pablo avenue february 2020 median improvements from highway 111 to...
TRANSCRIPT
Project Milestones*
Spring 2020
Fall2019
Text to Sign-Up for Updates: Text SANPABLO to 22828
visionsanpablo.com [email protected]
OCTOBER2019
NOVEMBER2019
JANUARY2020
MARCH2020
APRIL2020
West Side Improvements• Storm drain work south of San Gorgonio in front of businesses• Install curb, cutter and sidewalk from Fred Waring toward Hwy 111• Place concrete on the pocket parks
West Side Improvements• Continue placing concrete in front of the businesses• Electrical and landscape improvements
East Side Improvements• Remove and construct sidewalk, curb and gutter from San Gorgonio to Fred Waring• Complete storm drains from San Gorgonio to Fred Waring
DECEMBER2019
West Side Improvements• Complete electrical and landscape improvements
East Side Improvements• Remove and construct sidewalk, curb and gutter in front of businesses• Begin storm drains south of San Gorgonio • Begin electrical and landscape improvements
West Side Improvements• Place site furnishings
East Side Improvements• Install curb, gutter and sidewalk in front of the businesses • Continue electrical and landscaping improvements
West Side Improvements• Continue installing site furnishings
East Side Improvements• Continue electrical and landscaping improvements• Remove sections of San Pablo Avenue
• Grade San Pablo Avenue• Construct median curb and sidewalk• Place concrete in the median and roundabout • Continue electrical and landscaping improvements
• Complete electrical and landscaping improvements• Pave San Pablo Avenue
FEBRUARY2020
Median Improvements from Highway 111 to San Nicholas Avenue
Outside Improvements
Legend
*Note: Due to inclement weather or unforeseen issues, these dates and times are subject to change without notice. If inclement weather occurs, freeway closures will be automatically canceled and rescheduled.
OCT. 2019