    (ASSIGNMENT TEMPLATE ENGLISH VERSION) (COVER PAGE)

    FACULTY OF SCIENCE AND TECHNOLOGY

    MAY / 2011

    SAMPLE

    EBTK 3103

    TENDER AND CONTRACT MANAGEMENT

    MATRICULATION NO :

    IDENTITY CARD NO. :

    TELEPHONE NO. :

    E-MAIL :

    LEARNING CENTRE :

  • 8/2/2019 Sample Tender Bidding

    2/34

    EBTK 3103

    1

    TABLE OF CONTENTS

    DESCRIPTION PAGE

    INTRODUCTION.. 2

    TENDER ADVERTISEMENT.. 4

    INSTRUCTION TO TENDER.. 5

    TENDER DOCUMENTS.. 10

    TENDER EVALUATION AND SELECTION PROCESS.. 12

    EVALUATION CRITERIA.. 15

    FORMATION OF CONTRACT... 16

    CONTRACT AWARD.. 16

    APPENDIX 1 (INVITATION LETTER).. 17

    APPENDIX 2 (TENDER SUBMISSION CHECKLIST). 19

    APPENDIX 3 (SAMPLES OF BOQ) 20

    APPENDIX 4 (SAMPLES OF LETTER OF ACCEPTANCE

    AND CONTRACT AGREEMENT).. 21

    APPENDIX 5 (PERFORMANCE SECURITY) 24

    APPENDIX 6 (PERFORMANCE BOND) 26

    APPENDIX 7 (ADVANCE PAYMENT SECURITY). 29

    APPENDIX 8 (RETENTION MONEY SECURITY)... 31

    REFERENCES. 33

  • 8/2/2019 Sample Tender Bidding

    3/34

    EBTK 3103

    2

    INTRODUCTION

    Track Corporation Berhad has been awarded as main contractor and consultant of

    the Highway Construction Project from Malaysia Government. The Objective of the

    Project was to assist the Government in preserving and improving the federal highwaynetwork to meet the rapid growth of traffic demand safely and adequately. Towards this

    objective, the Project was designed to improve:

    a) Road maintenance planning, programming and management, and to enhance the

    cost and time taken of maintenance operations;

    b) Coordination of highway planning at the state and federal levels;

    c) Existing network of national highways;

    d) Truck-weight control to reduce damage to the roads; and

    e) Road safety.

    A part of this project has been approved by Malaysian Highway Authority to commence

    in the early year of 2012 at the North-South Express Link which the Projects

    components are including construction, rehabilitation and strengthening of 562 km of

    road. Being a consulting service company, Track Corporation Berhad will manage the

    bidding and tendering process of this project as well.

    The Pre-Qualified Tender has been chosen by the project committee in tendering

    process due to the job specifications which required experience contractors. The selected

    contractor needs to have vast experience, high capital, high technology equipment and up

    to date with the latest standards of working procedure. This type of tendering process will

    promote high quality of work because only a qualified contractor will be chosen. This

    tendering model is expected to benefit in terms of workload and paperwork, thus

    increasing productivity and efficiency in daily responsibilities. Therefore, the contractor

    assessment can be done more objectively.

    Pre-Qualification tendering process is to identify qualified constructors based on

    some criteria set by Track Corporation Berhad. Besides that, this stage also certifies all

    the pre-qualification documents that are required to be submitted by constructors. Pre-

    qualification stage is preferred by Track Corporation to minimize the risks and failures. It

    is also will enhance the performance levels of selected constructors.

  • 8/2/2019 Sample Tender Bidding

    4/34

    EBTK 3103

    3

    The procedure of this tender similar to open tender procedure and the selection of

    contractors are based on the criteria of financial status, establishment of company and

    specialties rather than choosing random contractors. Details of procedure for this tender

    can be referring in figure 1.

    Figure 1: Pre-qualification tender procedures.

  • 8/2/2019 Sample Tender Bidding

    5/34

    EBTK 3103

    4

    TENDER ADVERTISEMENT

    The advertising of the project is essential during executing bib and tendering

    process. The document to be advertised is the tender invitation of this particular project.

    The Invitation to Tender process is a special procedure for generating competing offers

    from different bidders looking to obtain an award of business activity in this project. It is

    also used to select one or more constructors to meet the participant of Track Corporation

    Berhad.

    NOTICE OF INVITATION TO TENDER

    Malaysian registered construction companies are invited to participate in the following Pre-qualification

    invitation.Date : 10 July 2011

    TITLE/REFERENCEDOCUMENT

    FEE

    TENDER

    BRIEFINGCLOSING DATE

    TENDER:Construction, rehabilitation andstrengthening of North-South Express Link.

    REFERENCE:TC/NSEL011/2011

    RM1000.00 Date:16 Sept2011Venue: TrackBuildingTime: 10:00am

    15 October 2011

    PAYMENTPayment for the pre-qualification invitation document can be made in the form of Banker's Cheque/BankDraft payable to Track Corporation Berhad (133333-P). Purchase and payment of the document can bemade at the:TRACK Corporation Berhad,Contract Documentation & Control, 3

    rdFloor,

    Track Building,Seksyen 72, 81110 Johor Bahru,Johor.The payment made is not refundable.

    INVITATION SUBMISSION

    Completed Proposals are to be submitted by hand in sealed packages to the:Track Corporation Berhad,Submission Box, 3

    rdFloor,

    Track Building,Seksyen 72, 81110 Johor Bahru,Johor.

    Between 9.00 am to 12.00 noon before or on the closing date mentioned above.

    Figure 2: Sample of Invitation to Tender advertisement.

  • 8/2/2019 Sample Tender Bidding

    6/34

    EBTK 3103

    5

    A typical invitation to tender template has following section:

    a) Project background;

    b) Supplier response required;

    c) Timetable for choosing a constructor

    d) Requirement.

    This invitation to tender will be advertised through the Tender Notice in newspapers,

    trade journals and internet. The sample of tender invitation has been designed and can be

    seen in figure 2.

    INSTRUCTIONS TO TENDERER

    Instruction to Tender document is in the general terms and condition of the

    project contract document. Track Corporation Berhad has set this document for interested

    contractor to becomes Tenderer and should go through the document terms and

    conditions stated as below.

    Definition of Terms

    In the Tender and Contract, the following words and expressions shall have the meaning

    stated here under except where the context otherwise requires;

    Terms Definition

    Company Track Corporation Berhad and shall include their assigns andsuccessors in law and their duly authorized representatives to act on

    its behalf

    Contractor The person or persons, firm or company whose tender has been

    accepted by the Company to supply the items or to perform the

    services/works and includes the Contractors duly appointed

    representatives, successors and permitted assigns.

    Items All goods which the Contractor is required to supply under the

    Contract and includes all parts and units thereof.

    Services / Works The work to be executed in accordance with the Contract including

    all permanent works and temporary works and any plant to be

    delivered, installed or supplied.

    Specification Referred to the Tender and Contract and includes general and

  • 8/2/2019 Sample Tender Bidding

    7/34

    EBTK 3103

    6

    technical specification and drawings and any modification thereof

    or addition thereto as may from time to time be furnished or

    approved in writing by the Company.

    Tender The Tender Document duly completed and submitted by the

    Tenderer to the Company.

    Tenderer The person or persons, firm or company who invited by the

    Company to submit a tender.

    Schedule of

    Tender

    Rates/Prices

    Schedule wherein are specified the prices of individual items or

    Service/Work excluding GST.

    Writing Any manuscript, typewritten or printed statement under or over

    signature or seal as the case may be.

    1. General

    1.1.These instructions are designed to ensure that all Tenderer are given equal and fair

    consideration. It is important therefore that you provide all the information asked

    for in the format and order specified. Please contact Project Manager, Mr. Muhd.

    Adam Danish at mail address [email protected] or in their absence please contact

    Project Coordinator, Ms Yasmin Damia at mail address [email protected] if you

    have any doubt as to what is required or will have difficulty in providing the

    information requested.

    1.2.Tenderer should read these instructions carefully before completing the Tender

    documentation. Failure to comply with these requirements for completion and

    submission of the Tender Response may result in the rejection of the Tender.

    Tenderers are advised therefore to acquaint themselves fully with the extent and

    nature of the goods and contractual obligations. These instructions constitute the

    Conditions of Tender. Participation in the tender process automatically signals

    that the Tenderer accepts these Conditions of Participation.

  • 8/2/2019 Sample Tender Bidding

    8/34

    EBTK 3103

    7

    1.3.The Tenderer shall ensure that each and every sub-contractor, consortium

    member and adviser abides by terms of these instructions and Conditions of

    Tender.

    1.4.Tenderer shall accept and acknowledge that by issuing this Instruction to Tenderthe Authority shall not be bound to accept any Tender and reserves the right not

    to conclude a Framework Agreement for some or all the goods for which Tenders

    are invited.

    1.5.All material issued in connection with this Instruction to Tenderer shall remain

    the property of the Authority and/or as applicable relevant Other Contracting

    Body and shall be used only for the purpose of this procurement exercise. All

    Due Diligence Information shall be either returned to the Authority or securely

    destroyed by the Contractor (at the Authoritys option) at the conclusion of the

    procurement exercise.

    1.6.The Authority reserves the right to amend, add to or withdraw all or any part of

    this Instruction to Tenderer at any time during the procurement exercise.

    2. Conference

    The conference will provide Tenderer the opportunity to seek clarification on any

    matters related to the Instruction to Contractor and the requirements in an open

    forum. Further details are included in the letter accompanying this Instruction to

    Tenderer.

    3. Cost of Tendering

    The Tenderer will not be reimbursed for any expenses incurred in the preparation and

    submission of his proposal.

    4. The Contractors Organisational Planning

    The Tenderer shall outline their organisation for planning and design works and for

    construction works in their tender.

    5. Inspection of Site

  • 8/2/2019 Sample Tender Bidding

    9/34

    EBTK 3103

    8

    5.1.The Tenderer is required to visit the site and shall have inspected and examined

    the same as well as its surrounding and obtained information in connection

    therewith and have satisfied himself before submitting his Proposal, as to the

    form and nature thereof including the subsurface conditions, the hydrological and

    climatic conditions, existing services, the requirement of the electricity and water

    supply authorities, the requirements of the Syarikat Telekom Malaysia Bhd.

    and/or Jabatan Telekom, the requirements of other authorities such as Jabatan

    Bomba, Jabatan Kilang dan Jentera, Jabatan Alam Sekitar, the relevant planning

    approval and local authorities having jurisdiction over the Works, the extent and

    nature of work and materials necessary for the completion of the Works, the

    means of access to the site and the accommodation he may require and, in

    general, shall have obtained all necessary information, as to risks, contingencies

    and all other circumstances which may influence or affect his Proposal.

    5.2. Any such information forwarded by the Project Director shall not relieve the

    Tenderer of his obligations under the provisions of this Clause. The Company

    gives no guarantee for the information either, as to the accuracy or sufficiency, or

    as to how the same should be interpreted or otherwise howsoever and the

    Tenderer shall make use of and interpret the same entirely on his own risk.

    6. Sufficiency of Proposal

    The Tenderer shall have satisfied himself before submitting his proposal as to the

    correctness and sufficiency of his Proposal for the Works, and the Contract Sum,

    except in so far as is otherwise provided in the Contract, shall cover all his obligations

    under the Contract and all matters and things necessary for the proper design,

    construction, equipping, completion and guarantee of the works.

    7. Drawings, Specifications and Company Requirement

    The Tenderer shall note that the drawings, specifications and Company

    requirements issued are meant to serve as a guide and the Tenderershall submit their

    own proposal for the evaluation and consideration by the Company. The

    specifications proposed shall not be inferior to those described in the Company

    Requirements.

  • 8/2/2019 Sample Tender Bidding

    10/34

    EBTK 3103

    9

    8. Currency to be used in the Tender

    The total of the Tender Sum shall be quoted in Malaysian currency, which is in

    Ringgit Malaysia. Do not apply the dollars sign.

    9. Metric System

    All plans and specifications submitted by the Tenderer shall be in the S.1 Unit

    (System International D'Unites) of measurement, commonly known as the metric

    system as this is a requirement of the approving authorities.

    10.Materials, Equipment and Machinery

    Before the issue of the Certificate of Practical Completion of the whole of the

    Works under this contract, the Tenderer is required to have satisfied the Project

    Director by means of a Statutory Declaration made by the Contractor to the

    effect, that all materials and equipment supplied and incorporated into the Works

    are new and unused and generally are of the best quality with regard to design,

    manufacture and performance.

    All equipment and machineries which is to be installed and incorporated as

    part of the permanent works shall be manufactured by companies having agents in

    Malaysia for the subsequent maintenance and repair of the equipment and machinery.

    11.Language

    For the purpose of this tender the language used shall be English. All submissions

    including plans, specifications, Conditions of Contract, etc. forming the Tenderer's

    tender document shall accordingly be in English. Provided that nothing in this

    Contract shall be invalidate any instruction or notice or certificate given to the

    Tenderer or his authorised representative in Bahasa Malaysia or English.

    12.Registration

    The Tenderer is required to be registered as a Turnkey Contractor with Pusat KhidmatKontraktor (PKK) of the Ministry of Entrepreneurial Development and CIDB. The

    Contractor shall submit a certified true copy of the current registration certificate

    issued by the said authority together with his Proposal.

    13.Acceptance of Tender

  • 8/2/2019 Sample Tender Bidding

    11/34

    EBTK 3103

    10

    Company reserves the right to accept any tender or to reject all the tenders or to

    accept in whole or in part, a particular tender.

    14.Period of validity

    Tender shall remain valid for a period of up to 180 days from the date of Closing of

    the Tender. However, Company reserves the right to extend the validity of the said

    period.

    15.Period of Completion

    The completion of this project shall be 54 months from the date of the Project

    Directors order to commence the work.

    16.Submission of Tender

    The Tenderer shall submit a proposal containing all information and particulars called

    for in the Pre-bid Documents. In the submission of their tenders, Contractors are

    required to submit their tender documents, filled in a complete in all respects and

    properly sealed.

    TENDER DOCUMENTS

    The documents contained in tender documents are standard forms and it must be

    prepared specifically for the particular contract concerned. The Tender Document shall

    mean and comprise the following:

    a) Letter of Invitation

    Is a written document state with inter alia issued to the Tenderer.

    b) Checklist for Submission

    The documents will assist the Tenderer in making sure that he or she has

    complied fully with the tender requirements.

    c) Articles of Agreement and Condition of Contract

    A contract is a legally enforceable agreement between two or more parties with

    mutual obligations, which may or may not have elements in writing.

    d) Form of Tender

    It is the document used to record the pricing and can also used to highlight the

    operation plan, and for the company to provide additional information on

    breakdown of costing.

  • 8/2/2019 Sample Tender Bidding

    12/34

  • 8/2/2019 Sample Tender Bidding

    13/34

    EBTK 3103

    12

    TENDER EVALUATION AND SELECTION PROCESS

    The contract should be awarded to the best all round bid received. In order to be

    fair, the procedure for selecting contractors should be clear, written down, checked by

    committee and held on file for any future audits.

    The objectives of the evaluation process are:

    a) To select the most appropriate proposal to meet requirements.

    b) To create an evaluation audit trail and set of supporting documentation that will

    support the evaluation process and final decision.

    The document describes the evaluation criteria that were applied to responses to the

    tender. In the formal evaluation, the team or committee may be structured as follow;

    Figure 3: Tender Evaluation committee formation

    The team will be lead by a team manager which may be divided into a number of groups:

    Functional This group will be responsible for evaluating the functional aspects

    of the responses.

    Technical This group will be responsible for evaluating the technical aspects of

    the responses.

    General This group will be responsible for evaluating general factors such as

    the responding companies and the finances.

  • 8/2/2019 Sample Tender Bidding

    14/34

    EBTK 3103

    13

    No members of the evaluation team will be connected with any of the respondents. The

    Team Manager may be assisted by a number of specialists in particular aspects of the

    development and operation of a reporting system. The responsibilities of the Evaluation

    Team Manager will be:

    Managing the evaluation process

    Consulting with specialists as required.

    Documenting the evaluation process.

    Assign weights to the evaluation factors in conjunction with the group leaders.

    Conducting meetings of the evaluation group leaders and of the whole committee.

    Preparing the final report on the evaluation.

    Reviewing and understanding responses from respondents.

    Acting as the single point of contact between respondents and other committee

    members.

    Allocating and scheduling work for the evaluation groups.

    Reviewing the outputs from the evaluation groups and seeking clarification.

    The generalised solution evaluation process can be customised to meet the exact needs.

    In summary the evaluation process consists of the following elements:

    Evaluation Committee the evaluation committee consists of individuals with

    appropriate skills to be able to evaluate responses received from contractors.

    Evaluation process the evaluation process is the set of steps to be followed by

    the evaluation team to conduct an evaluation of the responses.

    Evaluation Criteria this is a set of criteria by which the responses will be

    assessed.

    Evaluation Score the score is an objective assessment of the merits of response

    based on the application of the evaluation criteria.

    Evaluation Reports this is a document describing the evaluation process and its

    results.

    Schematically, the high level view of the evaluation process that is proposed to be used

    during the evaluation and selection of a reporting solution as shown below:

  • 8/2/2019 Sample Tender Bidding

    15/34

    EBTK 3103

    14

    Figure 4: Tender Evaluation process flow.

  • 8/2/2019 Sample Tender Bidding

    16/34

    EBTK 3103

    15

    EVALUATION CRITERIA

    The Tender evaluation criteria need to be defined prior to sending out the bid

    document or Request for Proposal (RFP). The thought process is important at this stage

    as the criteria to be used for assessing the tender needs to be communicated to the

    bidders. Tender Evaluation criteria should reflect the risk and value of the contract.

    In the Civil and Highway construction sector it is normal practice to provide both

    the criteria and weightings, i.e. the exact basis on which their offer will be judged. The

    criteria to be used in the tender evaluation process will vary depending on the goods or

    services being sourced. The main criteria as listed below:

    Technical issues and functional ability to fulfil requirements

    Continued technical support and after sales services

    Ability to delivery on time and complete in the required time frame

    Compliance with legal and statutory requirements

    Acceptance of the proposed terms and conditions

    Training and on-site installation

    Tender is complete and signed by an authorized person

    Each separate criterion should have a percentage or a number of marks allocated to it

    highlighting the relative importance of each area, disclosed in the RFP if appropriate.

    Bids should only be assessed against the criteria issued in the invitation and no new

    assumption made when performing tender evaluation.

    Figure 5: Example of the Tender Evaluation weighted score.

  • 8/2/2019 Sample Tender Bidding

    17/34

    EBTK 3103

    16

    FORMATION OF CONTRACTS

    Contract formation process will lead to compilation of contract documents. The

    contracts it is legally binding agreement containing an offer, an acceptance, a

    consideration and an intention to create legal relations. The normal procedure for

    formation of a contract is shown in figure 6.

    Figure 6: Formation of contracts

    CONTRACT AWARDS

    In the contract awards stage, Track Corporation Berhad will notice to a bidding

    contractor of the acceptance of the submitted bid. This notice is commonly known as

    Letter of Acceptance of Offer. The samples of Letter of Acceptance of Offer can be

    referring at Appendix pages session.

  • 8/2/2019 Sample Tender Bidding

    18/34

    EBTK 3103

    17

    Appendix 1

    Invitation Letter

    To: [name of Contractor]

    [address]

    Reference: [Insert IBRD Loan No. or IDA Credit No.]

    Contract Name, and Identification No. ________ / ________1

    Dear Sirs:

    We hereby inform you that you are prequalified for bidding for the above cited

    contract. A list of prequalified and conditionally prequalified Applicants is attached to

    this invitation.

    On the basis of information submitted in your application, you would [not](insert

    if appropriate) appear eligible for application of the domestic bidder price preference in

    bid evaluation. Eligibility is subject to confirmation at bid evaluation.

    We now invite you and other prequalified Applicants to submit sealed bids for the

    execution and completion of the cited contract.

    You may obtain further information from, and inspect and acquire the bidding

    documents at, our offices at:

    Track Corporation Berhad,

    Conference Room 3-1, 3rd

    Floor,

    Track Building,

    Seksyen 72, 81110 Johor Bahru,

    Johor.

    A complete set of bidding documents may be purchased by you at the above

    office, on or after[time and date] and upon payment of a nonrefundable fee of[insert amount

    and currency]

  • 8/2/2019 Sample Tender Bidding

    19/34

    EBTK 3103

    18

    All bids must be accompanied by a security in the form and amount specified in the

    bidding documents, and must be delivered to

    Track Corporation Berhad,

    Conference Room 3-1, 3rd

    Floor,Track Building,

    Seksyen 72, 81110 Johor Bahru,

    Johor.

    at or before12:00 noon 15 October 2011. Bids will be opened immediately thereafter in the

    presence of bidders representatives who choose to attend.2

    Please confirm receipt of this letter immediately in writing by cable, fax, or telex.If you do not intend to bid, we would appreciate being so notified also in writing at your

    earliest opportunity.

    Yours truly,

    Authorized signature

    Name and title

    Employer

  • 8/2/2019 Sample Tender Bidding

    20/34

    EBTK 3103

    19

    Appendix 2

    Tender Submission Checklist

    Schedule 1 Tender Submission Checklist

    Name of Tenderer:________________________

    Address :______________________________

    ______________________________

    ______________________________

    ______________________________

    The Tenderer has submitted the following information with the Tender:

    Schedule

    No.

    Document Please tick if

    enclosed

    1 Tender Submission Checklist

    2 Form of Tender

    3 Declaration of Direct or Indirect Interest

    4 Company Code of Business Conduct

    5 Business Registration Certificate

    6 CIDB Certificate

    7 Certificate of Origin from the PKK

    8 Financial Situation

    9

    To be completed and returned with Schedules 2 9 and Tender Submission.

  • 8/2/2019 Sample Tender Bidding

    21/34

    EBTK 3103

    20

    Appendix 3

    Samples of BOQ

    Bill of Quantities for Improvement Works

    Activity Quantity Unit Unit Price Write in

    Full

    Total Price

    Additional

    Lane between

    Km 50 and80

    30 Km

    Shoulder

    pavingbetween Km

    50 and 80

    30 Km

    Construction

    of Bus stopsin 5 cities

    5 Bus Stop

    type A

    Total Price for Improvement Works

    Bill of Quantities for Rehabilitation Works

    Activity Quantity Unit Unit Price Write in

    Full

    Total Price

    Milling and

    Replacement

    Lane Km

    Shoulder Km

    Retrofiling

    Lane Km

    Shoulder Km

    AsphaltSlurry

    Lane Km

    Shoulder Km

    Etc

    Total Price for Rehabilitation Works

  • 8/2/2019 Sample Tender Bidding

    22/34

    EBTK 3103

    21

    Appendix 4

    Samples of Letter of Acceptance and Contract Agreement

    Notification of AwardLetter of Acceptance

    [date]

    To: [name and address of the Contractor]

    This is to notify you that your Bid dated [date] for execution of the [name of the

    Contract and identification number, as given in the Contract Data] for the Accepted

    Contract Amount of the equivalent of[amount in numbers and words] [name of

    currency], as corrected and modified in accordance with the Instructions to Bidders, is

    hereby accepted by our Agency.

    You are requested to furnish the Performance Security within 28 days in accordance with

    the Conditions of Contract, using for that purpose one of the Performance Security Forms

    included in Section IX, Annex to the Particular Conditions - Contract Forms, of the

    Bidding Document

    Authorized Signature:

    Name and Title of Signatory:

    Name of Agency:

    Attachment: Contract Agreement

  • 8/2/2019 Sample Tender Bidding

    23/34

    EBTK 3103

    22

    Contract Agreement

    THIS AGREEMENT made the ________ day of ________________________, _____,

    between ______________________________________of

    __________________________ (hereinafter the Employer), of the one part, and

    ______________________ of _____________________ (hereinafter the Contractor),

    of the other part:

    WHEREAS the Employer desires that the Works and Services known as

    _______________________________ should be executed by the Contractor, and has

    accepted a Bid by the Contractor for the execution and completion of these Works and

    the remedying of any defects therein,

    The Employer and the Contractor agree as follows:

    1. In this Agreement words and expressions shall have the same meanings as are

    respectively assigned to them in the Contract documents referred to.

    2. The following documents shall be deemed to form and be read and construed as

    part of this Agreement. This Agreement shall prevail over all other Contract documents.

    (i) the Letter of Acceptance

    (ii) the Letter of Bid

    (iii) the addenda Nos ________(if any)

    (iv) the Particular Conditions

    (v) the General Conditions;

    (vi) the Specification

    (vii) the Drawings; and

    (viii)the completed Schedules,

  • 8/2/2019 Sample Tender Bidding

    24/34

    EBTK 3103

    23

    3. In consideration of the payments to be made by the Employer to the Contractor as

    indicated in this Agreement, the Contractor hereby covenants with the Employer to

    execute the Works and Servics, and to remedy defects therein in conformity in all

    respects with the provisions of the Contract.

    4. The Employer hereby covenants to pay the Contractor in consideration of the

    execution and completion of the Works and Services, and the remedying of defects

    therein, the Contract Price or such other sum as may become payable under the

    provisions of the Contract at the times and in the manner prescribed by the Contract.

    IN WITNESS whereof the parties hereto have caused this Agreement to be executed in

    accordance with the laws of _____________________________ on the day, month and

    year indicated above.

    Signed by ________________________________________________ (for the

    Employer)

    Signed by __________________________________________________ (for the

    Contractor)

  • 8/2/2019 Sample Tender Bidding

    25/34

    EBTK 3103

    24

    Appendix 5

    Performance Security

    Performance Security

    Option 1: (Demand Guarantee)

    ________________________________[Banks Name, and Address of Issuing Branch or Office]

    Beneficiary: ___________________[Name and Address ofEmployer]

    Date: ________________

    PERFORMANCE GUARANTEE No.: _________________

    We have been informed that ________________ [name of Contractor] (hereinafter called

    "the Contractor") has entered into Contract No. _____________ [reference number of the

    contract] dated ____________ with you, for the execution of _____________________

    [name of contract and brief description of Works and Services] (hereinafter called "the Contract").

    Furthermore, we understand that, according to the conditions of the Contract, a

    performance guarantee is required.

    At the request of the Contractor, we _______________ [name of Bank] hereby irrevocably

    undertake to pay you any sum or sums not exceeding in total an amount of ___________

    [amount in figures]( )[amount in words], such sum being payable in the types and

    proportions of currencies in which the Contract Price is payable, upon receipt by us ofyour first demand in writing accompanied by a written statement stating that the

    Contractor is in breach of its obligation(s) under the Contract, without your needing to

    prove or to show grounds for your demand or the sum specified therein.

  • 8/2/2019 Sample Tender Bidding

    26/34

    EBTK 3103

    25

    This guarantee shall expire, no later than the . Day of , 2, and any demand for

    payment under it must be received by us at this office on or before that date.

    This guarantee is subject to the Uniform Rules for Demand Guarantees, ICC Publication

    No. 458, except that subparagraph (ii) of Sub-article 20(a) is hereby excluded.

    _____________________

    [signature(s)]

    Note: All italicized text (including footnotes) is for use in preparing this form and

    shall be deleted from the final product.

  • 8/2/2019 Sample Tender Bidding

    27/34

  • 8/2/2019 Sample Tender Bidding

    28/34

    EBTK 3103

    27

    Bidder, arrange for a Contract between such Bidder and Employer and make

    available as work progresses (even though there should be a default or a

    succession of defaults under the Contract or Contracts of completion arranged

    under this paragraph) sufficient funds to pay the cost of completion less the

    Balance of the Contract Price; but not exceeding, including other costs and

    damages for which the Surety may be liable hereunder, the amount set forth in

    the first paragraph hereof. The term Balance of the Contract Price, as used

    in this paragraph, shall mean the total amount payable by Employer to

    Contractor under the Contract, less the amount properly paid by Employer to

    Contractor; or

    (3) pay the Employer the amount required by Employer to complete the Contract

    in accordance with its terms and conditions up to a total not exceeding the

    amount of this Bond.

    The Surety shall not be liable for a greater sum than the specified penalty of this Bond.

    Any suit under this Bond must be instituted before the expiration of one year from the

    date of the issuing of the Taking-Over Certificate.

    No right of action shall accrue on this Bond to or for the use of any person or corporation

    other than the Employer named herein or the heirs, executors, administrators, successors,

    and assigns of the Employer.

    In testimony whereof, the Contractor has hereunto set his hand and affixed his seal, and

    the Surety has caused these presents to be sealed with his corporate seal duly attested by

    the signature of his legal representative, this day of 20

    .

    SIGNED ON on behalf of

  • 8/2/2019 Sample Tender Bidding

    29/34

    EBTK 3103

    28

    By in the capacity of

    In the presence of

    SIGNED ON on behalf of

    By in the capacity of

    In the presence of

  • 8/2/2019 Sample Tender Bidding

    30/34

    EBTK 3103

    29

    Appendix 7

    Advance Payment Security

    Advance Payment Security

    Demand Guarantee

    ________________________________[Banks Name, and Address of Issuing Branch or Office]

    Beneficiary: ___________________[Name and Address ofEmployer]

    Date: ________________

    ADVANCE PAYMENT GUARANTEE No.: _________________

    We have been informed that ________________ [name of Contractor] (hereinafter called

    the Contractor) has entered into Contract No. _____________ [reference number of the

    contract] dated ____________ with you, for the execution of _____________________

    [name of contract and brief description ofWorks and Services](hereinafter called "the Contract").

    Furthermore, we understand that, according to the conditions of the Contract, an advance

    payment in the sum ___________[amount in figures]( )[amount in words] is to be

    made against an advance payment guarantee.

    At the request of the Contractor, we _______________ [name of Bank] hereby irrevocably

    undertake to pay you any sum or sums not exceeding in total an amount of ___________

    [amount in figures]( )[amount in words] upon receipt by us of your first demand

    in writing accompanied by a written statement stating that the Contractor is in breach of

    its obligation under the Contract because the Contractor used the advance payment for

    purposes other than the costs of mobilization in respect of the Works.

    It is a condition for any claim and payment under this guarantee to be made that the

    advance payment referred to above must have been received by the Contractor on its

    account number ___________ at _________________[name and address of Bank].

  • 8/2/2019 Sample Tender Bidding

    31/34

  • 8/2/2019 Sample Tender Bidding

    32/34

    EBTK 3103

    31

    Appendix 8

    Retention Money Security

    Retention Money Security

    Demand Guarantee

    ________________________________[Banks Name, and Address of Issuing Branch or Office]

    Beneficiary: ___________________[Name and Address ofEmployer]

    Date: ________________

    RETENTION MONEY GUARANTEE No.: _________________

    We have been informed that ________________ [name of Contractor] (hereinafter called"the Contractor") has entered into Contract No. _____________ [reference number of thecontract] dated ____________ with you, for the execution of _____________________[name of contract and brief description of Works and Services] (hereinafter called "the Contract").

    Furthermore, we understand that, according to the conditions of the Contract, when theTaking-Over Certificate has been issued for the Works and the first half of the Retention

    Money has been certified for payment, payment of[insertthesecond half of the RetentionMoneyorifthe amount guaranteed under the Performance Guarantee when the Taking-

    Over Certificate is issued is less than half of the Retention Money, thedifference betweenhalf of the Retention Money and the amount guaranteed under the Performance Security]

    is to be made against a Retention Money guarantee.

    At the request of the Contractor, we _______________ [name of Bank] hereby irrevocably

    undertake to pay you any sum or sums not exceeding in total an amount of ___________[amount in figures]( )[amount in words]1 upon receipt by us of your first demandin writing accompanied by a written statement stating that the Contractor is in breach of

    its obligation under the Contract because the Contractor used the advance payment for

    purposes other than the costs of mobilization in respect of the Works.

    1The Guarantor shall insert an amount representing the amount of the second half of theRetention Money or or if the amount guaranteed under the Performance Guarantee when theTaking-Over Certificate is issued is less than half of the Retention Money, the differencebetween half of the Retention Money and the amount guaranteed under the PerformanceSecurity and denominated either in the currency(ies) of the second half of the RetentionMoney as specified in the Contract, or in a freely convertible currency acceptable to theEmployer.

  • 8/2/2019 Sample Tender Bidding

    33/34

  • 8/2/2019 Sample Tender Bidding

    34/34

    EBTK 3103

    REFERENCES

    Dimitri, N., Piga, G. & Spagnolo, G. (2006) Handbook of procurement.

    Cambridge: Cambridge University Press

    Hughes, G.A., & Barber, J.N. (1992) Building and civil engineeringclaims in

    perspective. (3rd, ed.) Sussex: Longman Scientific & Technical.

    Marsh, P.D.V. (1989) Successful bidding and tendering. London: Wildwood

    House.

    Robinson, N.M., & Lavers, A.P. (1988) Construction law in Singapore and

    Malaysia. Singapore: Butterworths & Co. (Asia) Pte. Ltd.

    Ministry of Treasury Malaysia . (n.d.). Retrieved June 15, 2011, from

    www.treasury.gov.my

    Uzairi Haji Saidin. (2000). Aturcara kontrak & taksiran. Kuala Lumpur:IBS Buku

    Sdn. Bhd.