SAFE WATER PLAN UPDATE February 1, 2013
-
Background
Renewal / Replacement Program − Water System Replacement Cost = $1Billion
Ideal Funding = Cost of Facilities / Lifespan
Considered Major Facilities
− Wells, pipelines, reservoirs, pumping equipment
-
Background
Board Hearing on March 2, 2006 − 10% increases for five years
Extra 2% in first year for Evans Reservoir Operating and Capital Improvement Funding
Approved by City Council on March 28, 2006
-
Implementation
2005 Water System Master Plan
Pipeline Leak Reports
External Funding Opportunities − Proposition 50 Grants − Caltrans Projects − Lockheed Martin
-
Implementation
New Wells − Tippecanoe (Caltrans) − Scheuer − Raub 7 (Lockheed Martin) − Flume 7 − Gage 31-1R (in progress)
Goal: One well every two years − On target
-
Scheuer Well Replacement
-
Implementation
Reservoirs − Whitegates #1 Reservoir − Whitegates #2 Reservoir − Evans Reservoir − Net Increase of 8 Million Gallons Storage
-
Whitegates I Reservoir
-
Implementation
New / Replacement Booster Stations − Alessandro − Buchanan − Emtman − Victoria − Linden − Mary Evans − Whitegates #1 − Kingdom Drive − Green Orchard − 25% of Booster Stations
-
Alessandro Pump Station Replacement
-
Implementation
New / Replacement Pressure Reducing Stations − Alessandro − La Cadena − Citrus Avenue − Spruce Street
-
Citrus Ave. Pressure Reducing Station
-
Implementation
Transmission Mains − Arlington Ave. TM − Hunts Lane TM − Alpine Meadows TM − Bradley St. TM − Pellissier Ranch TM − Tippecanoe TM − San Bernardino 48-Inch TM (5 Segments) − Columbia 48/54-Inch TM
− 7.3 Miles
-
San Bernardino Transmission Line Replacement – Washington Street
-
Implementation
Distribution Mains (92 Projects) − Central Ave. Phase I Main Replacement − Dufferin Ave. Main Replacement − Magnolia Ave. Grade Separation, Phase I − Eastside Phase I and Main St.
− 37.3 Miles
− About 5% of all pipeline
-
Dufferin Avenue Main Replacement
-
Implementation
Treatment Plants − John W. North WTP (10 MGD)
Recycled Water Pipelines − Central Ave. − Van Buren − Arlington Heights Sports Park
-
John W. North Water Treatment Plant
-
Implementation
Asset Management Booster Pumps
− 123 Pumps, Total − 31 Pumps Rebuilt − 55 Pumps Replaced
Wells
− 41of 51 Wells Refurbished
-
Warren 4 Well Rehabilitation
-
Implementation
Meters − 64,000 Meters − 30,372 Meters Replaced (Large & Small) − 37 Large Meters Rebuilt
System Security
− 89 SCADA Installations − 49 Remote Monitoring Installations − 10 Chlorine Monitor Installations − 24 Well Automations
-
Garner 7 SCADA Field Panel
-
Safe WATER Plan Accomplishments
Expenditure Summary by Category (FY2007 to Present) Pipelines $51,300,073 Pumps, Wells1, & System Security $16,606,979 Wells $3,818,206 Meters $4,136,923 Reservoirs $29,448,386 Pump Stations $5,534,902 Water Treatment $25,659,413 Recycled Water $4,807,710 Total: $141,312,592 Notes:
1. Expenditures for pump rebuilds/replacements and well refurbishments.
-
Safe WATER Plan Accomplishments
FY Pipeline
Repl. (mi)
Pumps Rebuilt/
Repl.
Wells Refurb./
Repl.
Meters Rebuilt/
Repl. Reservoirs
(MG)
System Security (# of Sites)
2007 5 19 7 3,721 0 7 2008 6.7 13 15 4,503 0 21 2009 8.6 20 8 4,726 0 21 2010 6.5 5 5 5,044 9 32 2011 9.9 13 5 5,083 0 35 2012 5.1 10 3 4,240 16 23 2013 3.2 6 0 3,092 0 9
Summary of Accomplishments by Fiscal Year (FY2007 to Present)
-
Upcoming Planning Reports
Integrated Water Management Plan
Water Energy Management Master Plan
-
Recommendation
That the Water Committee receive and file this report
SAFE WATER PLAN UPDATE�February 1, 2013BackgroundBackgroundImplementationImplementationScheuer Well ReplacementImplementationWhitegates I ReservoirImplementationAlessandro Pump Station ReplacementImplementationCitrus Ave. Pressure Reducing StationImplementationSan Bernardino Transmission Line Replacement – Washington StreetImplementationDufferin Avenue Main ReplacementImplementationJohn W. North Water Treatment PlantImplementationWarren 4 Well RehabilitationImplementationGarner 7 SCADA Field PanelSafe WATER Plan AccomplishmentsSafe WATER Plan AccomplishmentsUpcoming Planning ReportsRecommendation