safe design and communication 091012

Upload: beqs

Post on 07-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Safe Design and Communication 091012

    1/56

    Safe Design and Communication

    RIBA CDM October 2009

  • 8/6/2019 Safe Design and Communication 091012

    2/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Stakeholder Groups consulted

    Helping clients get bettervalue from theconstruction industry andtheir procurement

    Consultation with variousstakeholder groupsincluding:-

  • 8/6/2019 Safe Design and Communication 091012

    3/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Strategy 2008/9 Be part of the solution

    Judith Hackitt

    CBE (Chair of HSE Board)

    After many years of improvement in health and safety performance

    our rate ofprogress has slowed and we need to regain momentum

    Health and Safety

    is being used increasingly as a synonym

    for unnecessarybureaucracy

    and an excuse for not doing things . It is time for us to regain the value

    of the brand for genuine health and safety and not trivia

    To be truly effective health and safety has to be an everyday process and anintegral part of workplace culture

    Everyone within the Health and safety system has a role but each stakeholder

    hasto understand their role

    and become better at executing their responsibilities

    To encourage strong leadership

    in championing the importance of, and a commonsense approach to , health and safety in the workplace

  • 8/6/2019 Safe Design and Communication 091012

    4/56

  • 8/6/2019 Safe Design and Communication 091012

    5/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Barriers to Improvements to Construction Health and Safety

    Lack of knowledge

    by CDM-Cs

    and others about what Designers

    reallyneed to know

    about Health & Safety

    Expectations

    of CDM-Cs and others of Designers

    Health & Safetyknowledge requirements is often excessive

    Designers can only do so much

    with regard to Health & Safety-

    but how much?

    How can we improve this state of affairs?

  • 8/6/2019 Safe Design and Communication 091012

    6/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Proposed Solutions

    There must be a change of attitude

    within the industry to accept the

    shortcomings of the current procedures and look toimprovements suggested in CDM

    2007.

    We cannot keep doing the same things in the same way and expectnew outcomes .

    Recommendations :-

    Recognition and team agreement on what are the Significantissues

    as early in a project as possible. Then concentrate on

    how to communicate these , as well as any other significantissues that arise.

    So how can this be achieved?

  • 8/6/2019 Safe Design and Communication 091012

    7/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    ..even The Burj

    Al Arab

    .. partly cradle and partly rope accessed

    The Burg al Arab Hotel, Dubai

  • 8/6/2019 Safe Design and Communication 091012

    8/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Aims of the Designer/HSE

    Stakeholder Consultation

    1.

    To highlight the Significant Issues

    that affect CDM

    decisions

    by designers

    on a day to day basis whilst avoiding the trivialor issues that should be obvious or within the remit of acompetent contractor or specialist subcontractor.

    2.

    To provide examples of Proportionate responses

    to CDM issues by designers without unnecessary bureaucracy

    3. To highlight what is - The right information, to the rightpeople, at the right time ?

    4. To provide examples of Notes on Drawings

    in a manner that isintelligible and proportionate

    to the scale and complexity of the

    H&S

    issues of the project whilst improving safety .But what should designers really Do and Not Do!

  • 8/6/2019 Safe Design and Communication 091012

    9/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSEs

    Dos and Don'ts for DesignersThere are a lot of misconceptions about CDM:-

    CDM

    does NOT require

    :-designers to stifle their creativity , limit their design freedom or place safety above aesthetics ;the elimination of attractive features such as atria;designers to choose the safest form of constructiondesigners to have a detailed knowledge of the construction process , or to specify standard

    construction processes or precautionary measures to the contractor;designers to take into account unforeseeable hazards ;designers to exercise any health and safety management functions over contractors or sub-

    contract designers (who often have designer duties themselves)

    CDM

    does

    place certain specific duties directly on designers:to eliminate hazards where feasibleto reduce risks from those hazards that cannot be eliminatedto provide information on residual risks if they are significant

    And in order to discharge these duties a competent designer will

    need some knowledge andexperience of the construction process . For instance:

    to know what the potential hazards will be during the construction, maintenance, cleaning anddismantling of your design.

    to satisfy themselves that there is at least one safe way of constructing their design . (Your clientdoesnt want a design that cant be built or can only be built at disproportionate expense!)

    What do designers really have to do?

  • 8/6/2019 Safe Design and Communication 091012

    10/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Even such futuristic designs as Zaha

    Hadids

    can embrace CDM.!!!!

  • 8/6/2019 Safe Design and Communication 091012

    11/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    SIGNIFICANT RISKS

    Project Specific Not obvious

    to those who use the design

    Not necessarily

    involving the greatest risks

    but those including health andsafety risks that are:-

    Not likely to be obvious to a competent contractor or other designers Unusual Likely to be difficult to manage

    Information

    should be brief, clear ,precise

    and in a form suitable for otherusers.

    This can be achieved by :- Notes on Drawings

    Written information

    provided with the design Suggested construction sequences

    TRIVIAL RISKS

    are ordinary Health and Safety design issues

    or other

    normal construction

    risks obvious

    to a competent contractor

    So how can this be done?

    What are significant & what are trivial risks? CDM

    2007 ACOP

  • 8/6/2019 Safe Design and Communication 091012

    12/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Designer Guidance Design Risk Assessment Documentation

    The Problem / Challenge

    In accordance with the CDM

    Regulations

    it ispreferred to include all significant risk analysis ondrawings rather than on written or numerical DesignHazard and Risk Assessment documents . This is toencourage visual analysis and recording ofsignificant construction, maintenance, anddemolition issues without unnecessary bureaucracy.The risks

    Significant hazards and risks can be hidden

    in thebureaucracy of a project causing them to beoverlooked during design, pricing, construction andmaintenance stages of a projectThe solutionProject drawings to be annotated

    in simple graphicmanner with key to further detail or references. Morecomplex projects may need special CDM

    drawings.Hand annotation for design stage issues can sufficeThe benefitsAll relevant risk information is collated in one place

    with all the associated complexity visually apparentto all participants in the risk reduction process.Key PointsDesigner friendly technique ensures all significantand unusual or specific hidden issues are not missedeven during design changes .Important not to confuse drawings with trivial

    orobvious

    risk information

    which a competentcontractor is expected to understand

    Hazard and riskanalysis sketched andhand annotated

    Keys in margin toamplify if requiredSimple symbols used on survey

    and construction drawings

    X

  • 8/6/2019 Safe Design and Communication 091012

    13/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Team Guidance

    Haskells-

    Designing for safety

    programmeThe Problem / ChallengeTraditionally architects were encouraged to stay away

    from construction safety issues due to potential liabilityclaims . These embedded attitudes need to change.The risksThis claim conscious attitude inhibits good integration

    ofdesign and construction safety and potentially causesaccidents instead of avoiding them.The solutionHaskell Design Build (US) are responsible for design andconstruction and their motto is one company , oneresponsibility.

    They have corporate liability coverage forall their architects and construction professionals. Theyuse collaborative design-build delivery including a safetyalert system using only 8 types of warning symbols

    on

    drawings to flag potential hazards.The benefitsSafety symbols are placed where the hazard is on adrawing,

    ie. not in other risk analysis documents or in themargins.Key PointsSymbols are explained in the margins and in contractdocuments. Subcontractors are advised that this does notrelieve them of their own safety responsibilities.

    www.thehaskellco.com

  • 8/6/2019 Safe Design and Communication 091012

    14/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Designer Guidance Standard Safety Symbols for Design DrawingsThe Problem / ChallengeProviding graphic significant risk data at the point ofuse on drawings

    for designers and contractors with

    an explanatory key if necessary depending uponcomplexity.The risksDesigners and supervising/pricing contractors

    missing the significant risk issues whilst developingdesigns or cost plans

    and procurementThe solutionUse of an optimal number of standard industry widesymbols

    with explanatory key if required

    The benefitsRisks

    are pinpointed on the actual drawn

    plans

    rather than lost in the margins or other documents.This prevents the likelihood of risks being missed atkey design stages by the entire design and clientteam and during workshop sessionsKey PointsDiscretion of designer

    and CDM-C

    needed to decidethe significance, amount and complexity of riskinformation presented

    Fragile Roof

    http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=100&b=199&prodid=3476http://www.leosignage.com/signage_Danger%2C+Caution%2C+Warning+Signs-129.html
  • 8/6/2019 Safe Design and Communication 091012

    15/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Designer Guidance

    Symbols and SHE Boxes for Design Drawings

    The Problem / Challenge

    How to put hazard and risk data on drawings

    thatare relevant to other designers and other relevantconstruction stakeholdersThe risksDesigners could be other team members even ofthe same discipline and need to see the hazardsgraphically on drawings

    , perhaps crossreferenced to SHE boxes, so the significantissues are clearly obvious, otherwise they can bemissed during the design development process.The solutionSHE box/key cross referenced with symbols

    onthe drawing eg.

    The benefitsDesign team and contractors supervising andpricing team are aware of the significant issuesKey Points

    Avoidance of reference to non-significant

    , tradeor competent contractor risk information

    isessential to prevent over complication ofdrawings. Caveats are included to confirm thatcontractors still have their own responsibilities.

    Typical SHE box as used by Olympic Delivery

    Authority:-

    SAFETY HEALTH AND ENVIRONMENTALINFORMATION

    SITE-WIDE AND GENERAL RISKSFor details, to be read in conjunction with these notes, seeDrg

    No:

    In addition to the risks normally associated with thetypes of work detailed on this drawing, note the

    following significant risks and information:

    CONSTRUCTION RISKSi.Asbestos in existing ceiling void

    ii.Temporary

    stability of trusses during erection, see design assumptions in document ABC/001

    CLEANING AND MAINTENANCE RISKSFor information relating to this see the H&S

    File anddrawing nos.

    DISMANTLING / DEMOLITION RISKS (Future)i.Cantilevered

    beams and suspended staircases, see Structural drawing nos.ii.Concealed

    cable runs under main beam A1/A2, see

    drg

    XYZ/1234

    The design team have highlighted unusual andsignificant risks only that may not be obvious to acompetent contractor. They are to assist with risk

    reduction only and are not necessarily comprehensive.It is assumed that all works will be carried out by a

    competent contractor working, where appropriate, toan approved method statement .

    http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=100&b=199&prodid=3476http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=100&b=199&prodid=3476
  • 8/6/2019 Safe Design and Communication 091012

    16/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Contractor Guidance

    Site Drawing Safety Symbols & SignageThe Problem / ChallengeDeveloping designer drawings to a level of suitability for site

    operative risk identification. The design team cannotpossibly know the contractors preferred method ofconstruction or interface issues unless a Design and Buildproject. Time wasting & abortive risk analysis is to beavoided .The risksToo much un-helpful information can be put on drawings bydesigners which are of no benefit to anyone and diminishthe risk reduction process.The solutionAfter prices, contracts and construction methodologies areagreed the design stage drawings can be augmented by thecontractors team . These can be CAD or simple stickerannotation of drawings and displayed in site huts and at theworkface.The benefitsAll operatives

    irrespective of nationality and educationshould be able to decipher the relevant information at pointof use.Key PointsContractors team may include a designer to update thedrawings or just use their own safety team resources.Not needed for architectural design drawings .Some possible symbols shown, but others exist.

    http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=700&b=799&prodid=5132http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=700&b=799&prodid=5081http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=700&b=799&prodid=5079http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=600&b=699&prodid=3480http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=600&b=699&prodid=3445http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=600&b=699&prodid=3507http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=600&b=699&prodid=3485http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=600&b=699&prodid=3471http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=300&b=399&prodid=4066http://www.archersafetysigns.co.uk/prod-detail.asp?id=6&a=100&b=199&prodid=3465
  • 8/6/2019 Safe Design and Communication 091012

    17/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Contractor Guidance

    Workface-

    Supply Chain Component SignageThe Problem / ChallengeThe delivery of relevant site safety information

    to siteoperatives at the workface

    -

    Trojan Horse Messaging

    The risksThe absence of such information can lead to deaths andinjuries that are relatively easy to avoid

    The solutionUsing links with trade associations, componentmanufacturers and suppliers to provide visually explicitsafety information

    suitable for everyone including foreignworkers and other operatives with reading difficulties.

    The benefitsSafety information about lifting , handling and fixingprovided by the experts

    ie. the people who design andproduce the actual components .

    Trojan Horse messages are eye-catching cartoons whichcommunicate health and safety information toconstruction site operatives at point of use, i.e. on theactual material or equipment being used.No need for architectural design drawings .

    Key Points

    Manual handlingSite Activities

    Off-loading

    Site handling

  • 8/6/2019 Safe Design and Communication 091012

    18/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Construction Guidance

    The Silent Book-The Problem / Challenge

    The Risks

    Key Points

    The benefits

    The solution

    Misunderstanding by the intended operatives

  • 8/6/2019 Safe Design and Communication 091012

    19/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detailed Design-

    Significant Risks only

    Identified with SymbolsThe Problem / ChallengeProducing clear visual information

    that conveys simple

    messages to all parties about risk.Highlighting significant residual risks

    outside competentcontractors

    expectations or of otherwise hidden risks.The risksImportant information about risk can be easily buried

    inother project paperworkNeed to allow sufficient time for safety planning.The solutionSimple identification on the relevant project drawings

    that can be used at pricing and construction stages.Standardised set of symbols

    used to representcommon hazards. These can be supplemented by textboxes with further clarification if required.Symbols could also be used to identify key safetyissues

    for construction workers on site irrespective oflanguage or reading ability.The benefitsSimple drawing annotation techniques showing keysafety issues economically, with minimal bureaucracy

    Key PointsCommunicate with other designers to agree commonsignificant design safety issues . Provide informationthat meets all intended purposes on one drawing .Try to avoid a separate set of H&S

    drawings but theprincipal is to make the risk information accessible.

    Significant risks only

    identified on drawings

    Key and symbols identifysignificant risks

    Other symbols used for significant risks only

  • 8/6/2019 Safe Design and Communication 091012

    20/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Site Hazard Analysis to facilitate Initial Design & Construction

    Phase Decisions

    The Problem / Challenge

    To find the best building location on the site , from thesite analysis, and the optimum footprint, orientation,size, scale, geometry and sculptural form?The risksHazardous

    local gas installations, railway structures,tracks, viaducts, roads , etc. below ground services,

    tunnels and foundations, retained structures etcThe solutionDrawings

    were produced that show proximity

    to thegasholders and railway viaduct. Shows how closestructure, temporary works, scaffolding, hoardings ,welfare facilities, etc. can be built to the railwayThe benefitsSafe theoretical maximum building envelope

    wasagreed early together with safe site set up principlesavoiding later costs and changes eg. Roads, access etcKey Points

    All such hazards require analysis

    before the footprintand form of the intended structure can be finalised.The Client should provide survey information

    to clarifyall such site issues but analysis drawings neededespecially if scheme revised at later stages.

    Site Plan with significant hazards indicated

    Boundary section to railway viaduct

  • 8/6/2019 Safe Design and Communication 091012

    21/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Site Analysis

    Underground Services for Initial Design and Construction PhaseThe Problem / ChallengeThe identification and location of existing undergroundservices

    prior to the positioning of future structures onsite to minimise the need for excavations.The risksElectrical services and gas supplies are potentiallyhighly hazardous

    with the ability to cause death andinjury if accidentally struck during the constructionphase, and all excavations pose potential risks.The solutionDesigner clearly identified hazardous undergroundservices

    on the drawings and showed other servicessuch as water, fibre optics and drainageThe benefitsThe sub-scan survey costs were significantly

    outweighed by the benefit of avoiding delays, diversionsor bridging. Site safety is enhanced and costs reducedthrough the elimination of earthworks.Key PointsTake account of existing and new services whenconsidering the design footprint on the site.Ask Clients early for adequate survey information

    .Service diversions can be planned by the contractor toavoid programme delays.A competent contractor needs the right information toproperly manage the risks on site.Provide drawings early.

    Undergroundelectrical cables

    Subscan

    Survey -hazards identified with symbols

    http://www.leosignage.com/signage_Danger%2C+Caution%2C+Warning+Signs-129.html
  • 8/6/2019 Safe Design and Communication 091012

    22/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Site Contamination -

    Asbestos Survey Information on design drawingsThe Problem / ChallengeTo avoid exposure to free asbestos fibres

    of designers(on

    site visits) surveyors, site operatives, visitors, neighbours,and users by designer intervention.The risksRisks of asbestosis or mesothelioma

    due to inhalation offibres released during construction activities. This is oftendue to inadequately detailed surveys and lack ofunderstanding of how to interpret the Asbestos Report .The solutionClient to instruct appropriate survey analysis

    of

    buildingand site and provision of accurate asbestos surveydrawings and report to design team. Key issues arelocations of asbestos containing materials (ACMs) andareas inaccessible to survey which must be assumed tocontain asbestos, to be highlighted on drawings . Designerto advise client to remove asbestos but if too expensive orimpracticable the designer must avoid it by designingaround the areas concerned or by encapsulating theACMs

    and recording its residual presence on site in theH&S

    Plan and on record drawings .The benefits

    Reduction in likelihood of asbestos exposure before ,during and after, and in future construction works.Key PointsLiaison and communication between client ,design teamand contractor by interpretation of long reports.Paying for the appropriate type of survey early in project.

    Survey drawings to be used for asbestos survey

    Areas of asbestos and not surveyed identified

  • 8/6/2019 Safe Design and Communication 091012

    23/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detail Design -

    highlighting residual construction risks in the design

    .

    The Problem / Challenge

    Highlighting significant residual risks hidden oroutside of competent contractors

    normalexperience.The risksIf these risks are not identified pre-tender it ispossible that the contractor will under-estimate the

    cost and details

    of the temporary works solution forsafe construction.The solutionSimple drawing and survey annotation techniques

    showing existing features, new proposals andpossible temporary works solution with commonlyrecognised symbols.The benefitsSimple identification on project drawings

    or surveysthat can be used at pricing stages. These can alsoidentify key issues for construction workers on site

    irrespective of language and educational difficulties.Key PointsIdentification only required with symbols and simpleannotation . No need for detailed explanationswhich can be added to risk register or hazardelimination list if required.

    Fragile roof-lights, edge protection, and new stairs

    Plan and sectional drawings highlighted

  • 8/6/2019 Safe Design and Communication 091012

    24/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Tender / Contract Stage Design

    Temporary Fall Protection IssuesThe Problem / ChallengeTo alert the contractors temporary worksdesigners to unprotected slab and roofedges

    where the designer could inserttemporary protection works aides instead ofa traditional perimeter scaffolding system.The risksFalls from height during construction

    ratherthan during future maintenance.

    The solutionDesigners to highlight typical roof edges andslab edges

    which need to be considered bycontractors whilst pricing for temporaryworks. Project drawings can be used for siterisk identification

    to all contracting staffirrespective of language and ability tounderstand drawings.The benefitsEnables contractor to identify key safetyissues that he needs to respond to bytraditional methods eg. full scaffolding . Or bymeans of proprietary edge guarding methods

    to which designers can contribute eg.sockets in slabs, fixing points in steel, etc .Key PointsAvoidance of unnecessary

    bureaucracy

    andutilisation of contractors advice

    at theappropriate stage of the project

    Holes in steel for net guards Sockets in slabs for edge panels

    Areas requiring edge guarding simplyindicated on drawings

    Other methods offall protection eg.Air bags

  • 8/6/2019 Safe Design and Communication 091012

    25/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Guidance-

    Detailed Design-

    Roof-lights and fragile roofing materials

    The Problem / Challenge

    Roof-lights and fragile roofing materials are economic,sustainable and aesthetically desirable features

    whichshould not be eliminated from design projects purely forreasons of safety.The risksFalls through fragile roofing materials are statisticallyhigh

    and often highly injurious or fatalThe solutionConstuction

    Phase

    -Important to identify existing andnew fragile rooflights

    and other fragile roofing materialson drawings as a method of informing the contractor tocontrol the risk of falls through these materials duringconstruction. Contractors to recommend methods of

    temporary protection in tender or construction phase plan

    proposals to show their response .In-use

    -

    Additional protection measures

    are required forthe longer term

    in use condition such as metal railings,barriers, wire mesh or non -

    fragile walk on typerooflights. Avoid in-plane roof-lights or sheeting .The benefitsNatural daylighting

    is a human right and engenders

    healthy and sustainable environmentsKey PointsWalk-on rooflights

    tend to be very expensive

    so controlmitigation measures are necessary. Safe Cleaningmethods

    also need to be considered .

    Fragile roof symbolProtection Methods

    Mesh fall protection Fragile roof-lights identified

    Fragile and Non-fragile roof-lights can be used

  • 8/6/2019 Safe Design and Communication 091012

    26/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Scheme Design -

    Plant and Personnel Roof Plant Access Drawings

    Crane Access dims.

  • 8/6/2019 Safe Design and Communication 091012

    27/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detail Design -

    Plant and Personnel Roof Access Schematic

  • 8/6/2019 Safe Design and Communication 091012

    28/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detail Design -

    Plant and Personnel Roof Access Zonal

    Details

    Fragile roof light

    residual risk

  • 8/6/2019 Safe Design and Communication 091012

    29/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Construction Stage -

    Plant and Personnel Roof Access Details

    Fragile roof light

    residual risk

  • 8/6/2019 Safe Design and Communication 091012

    30/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Summary

    Designers significant CDM risk responsibilities need to be clarified and trivia ignored .

    The project significant risks need to be agreed early and allocated to each discipline .

    The designers need to highlight the significant hazards and risks only on their drawings.

    Simple non-text symbols to be used where possible for visual, educational and linguistic clarity.

    Contractors to augment the Designers drawings with specific site safety information symbols

    Trade associations and specialist suppliers and subcontractors to highlight their own risks .

    As Judith Hackett says:-

    From now on ,if we all work together

    with a clear vision and purpose we canrecommence improvement and bring about a change for the better

  • 8/6/2019 Safe Design and Communication 091012

    31/56

    Safe Design and Communication

    Best Practice Case Studies October 2009

  • 8/6/2019 Safe Design and Communication 091012

    32/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detailed Design Guidance

    Riser DuctsThe Problem / ChallengeMaintaining the safety of floor openings before installation ofservice risers . The programme usually requires theinstallation of services after the riser holes formed.The risksThis can lead to openings in the floor

    that the contractor hasto manage, creating a potential fall risk or trip hazard.The solutionAlert the contractor

    to the issues at tender on drawings. Bykeeping risers adjacent to walls

    they can be easier to protect.

    Co-ordination between M & E designers and structuraldesigners can enable the size of riser openings

    to bereduced. Sleeves or ducts

    can be cast in ready for services.Alternatively, it may be possible to cast mesh

    into the floor.The contractor to agree the preferred solution.The benefitsSignificantly reduce the reliance on scaffolding or coverings

    that can be easily moved. Reduce the likelihood of accidentson site.Key PointsTalk to other designers, involve M & E designers as early aspossible

    to minimize risks and size of riser openings.Consider casting in sleeves or mesh

    to eliminate fall risks.Consider pre-assembly of services, reducing work at height.This is a competent contractor

    issue to manage but thedesign team can assist to prevent accidents.

    Large duct at party wall, fall risk highlighted

    1. Sleeved services 2. Large metal mesh

    3.Small metal mesh prevents falls in open areas

  • 8/6/2019 Safe Design and Communication 091012

    33/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detailed Design Stage

    Heavy Element Handling eg.Glass

    ScreensThe Problem / Challenge

    To install heavy glass screens

    that are specificallyrequired by the designer and client and need to be

    brought into the building and located by other thanmanual handling methods.The risks

    If these heavy elements are not identified oreliminated early the installation methods may not be

    adequately planned or costed. Higher risk manualhandling may occur . Alternatively expensive

    additional hoisting methods may have to be added tothe contract costs at a late stage

    The solutionThe team investigated the feasibility of substitutinglighter materials , for instance smaller componentsthat can be demounted and re-assembled on site.

    This was not acceptable

    to the client.The position of the heavy elements was identified

    at

    tender stage and their access route indicating verticaland horizontal transportation routes and methods.The benefits

    This allowed the contractor, client and designer torecognise and react to the key heavy lifting issues.

    Mechanical aides used

    to transport the screens.Key Points

    Consider substitution

    for lighter or smaller elements.Use drawings

    to identify areas where heavycomponents are located by simple symbols.Look carefully at component access routes .

    Consult contractor or specialist lifting and equipmentcontractors and request proposals at tender .

    Think about future replacement

    access.

    XX

    Mechanical aides

    Acceptable access route shown and final locations

    Vertical access route

  • 8/6/2019 Safe Design and Communication 091012

    34/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detailed Design

    Heavy Masonry UnitsThe Problem / ChallengeTo eliminate musculo-skeletal injuries

    in the construction industry as a resultof repetitive handling of heavy masonry units requiring a fundamental majorchange in attitudes

    throughout the industry.The risksLifelong injuries

    to operatives and loss of skilled workforce.The solution for designersNBS

    Specification Clause 13.2 Design

    Apart from general construction hazards, such as working from scaffolding,the main risks associated with brick/ block walling are:

    Manual handling :

    The Construction Industry Advisory Committee (CONIAC) has concluded thatthere is a high risk of injury in the singlehanded, repetitive manual lifting ofbuilding blocks heavier than 20 kg, and this should be taken into a ccountbefore specifying heavy units.

    For detailed CONIAC

    guidance see HSE

    Construction sheet number 37

    The solution for contractorsChange in

    traditional

    manhandling attitudes

    to usemechanical aides or less heavy units whilst beingcompetitive in the marketplace.The benefitsRetaining a skilled workforce

    long term by showing

    respect for their health and welfareKey PointsIncreased plant-hire costs can be off-set by fasterconstruction periods but can only be introduced byindustry-wide change in attitude

    to create an evenplaying field for all.

    Weight of units significant

    Traditional attitudes Mechanised approach

    http://topic%3Drefs_01030/http://topic%3Drefs_01030/http://topic%3Drefs_01030/http://topic%3Drefs_01030/http://topic%3Drefs_01030/http://topic%3Drefs_01030/http://topic%3Drefs_01030/
  • 8/6/2019 Safe Design and Communication 091012

    35/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Designer Guidance

    Plasterboard

    Musculoskeletal InjuriesThe Problem / ChallengeLack of information about board weights for operatives .

    Wide range

    from jobbing builders to specialist drylining

    contractors but mainly sub-contract site operatives injured .Sites driven by cost

    not by considerations of Health andSafety

    speed rules! Board handling is part of the projectdelivery, and to be considered by all stakeholders.The risksOperatives are taking excessive risks lifting boards . Oper-

    atives

    treat musculoskeletal injury as a risk that you take andcant be avoided. Musculoskeletal damage is occurring with-

    out being identified. Operatives have a shortened working lifeThe solutionBoards to have heavy lifting symbols attached . Progressthrough working together to find approaches that work. The

    designer can encourage good working practices

    andmechanical moving and lifting aides, hoists, goods lifts, indrawings, specifications, and red, amber, green lists, etc.The benefitsBetter plasterboard installations with more motivatedoperatives, and increased productivity.Longer working life

    of operatives and skills retention.Reduces risk to companies against future injury claims.Key PointsWork with the stakeholders to jointly develop an approach toreduce the risk of musculoskeletal injury .Safeguard the health of individuals working with boards bymechanical aides or good lifting practices .

  • 8/6/2019 Safe Design and Communication 091012

    36/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Case Study

    Prefabrication and Off-Site ManufactureThe Problem / ChallengeIdentification of construction issues involving working atheight in difficult climatic or exposed

    or dangerous

    conditions to encourage safer workingThe risksFalls from height

    and injuries or ill-health due toworking in the above conditions

    The solutionEarly identification

    of the issues to the client andcontractor to encourage off-site working

    where possible.Analysis of the access and cranage

    capabilities of thesite

    are essential to validate the decisions and locationsof large modules

    The benefitsPrefabrication reduces work at height and on cold wetsites allowing off-site fabrication in factory conditions butit increases hazardous heavy lifting, access andtransportation issues.Prefabrication can be advantageous to CDM

    but is notalways the answer.Key PointsReview the buildability

    and access issues

    withcontractor as early as possible

    . Cost benefits

    may bepossible as well as safety benefits.

    Sectional analysis for crane access

    x

    Road closures and traffic issues

    Vaults, trees and crane size issues

  • 8/6/2019 Safe Design and Communication 091012

    37/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Case Study

    Small Property Developers-

    Project Safety IssuesThe Problem / ChallengeSmall and medium sized contractors

    to beencouraged to use safe temporary works systems

    ofscaffolding, shoring and propping and constructionmethods which do not injure operatives.The risksFalls from height, structural collapse duringconstruction and personal injuries to operatives dueto poor constructional techniques.

    The solutionDesigners and developer clients to encourage theuse of recognised safe constructional practices

    andprocedures whilst also maintaining economic andcompetitive costings, by use of appropriate ortraditional construction techniques for the job.Simplicity of designs, drawings and specifications

    to

    be reflected in the simplicity of the constructionalprocesses, highlighting unusual designs, hazards andrisks

    only. Selection of contractors competent forspecific projects

    and tasks is essential.The benefitsProjects should be constructed quicker and moreprecisely with appropriate methods and materials.This will improve cost benefits by shorterprogrammes, less defects and more satisfiedcustomers.Key PointsAvoid complex unusual designs and constructionaltechniques without specialist advice .

    Proprietary scaffolding preferred

    Unsafe working methodsdiscouraged

    Scaffolding to beused appropriately

  • 8/6/2019 Safe Design and Communication 091012

    38/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Designer Guidance

    Slips and Trips Avoidance Strategy

    The Problem / Challenge

    Clients and designers like prestigious shiny

    entrance hall floors but many accidents happenas a result of slippery floors

    whether due towetness or to these highly polished finishes.The risksPotentially severe injuries

    to all users especiallyin wet weather conditionsThe solutionSelect suitably slip resistant materials

    andfinishes to give compromise of visual finish withslip performance requirements. Managementsolutions

    such as mopping and warning signagecan further minimise the risk. Provide suitablemat-wells .The benefitsImpressive entrance halls and other areas canstill be designed but are safer to use

    Key PointsDrawings can be annotated early until a suitablefinish is found .Slip resistance values of materials to be checkedor tested prior to specification. See HSE

    Slipassessment tool at [email protected]

    The pendulum test with water spray

    Surface roughnessmeter

    Entrance, mat-well, flooring

    Management response

    Working at Height Single largest cause of construction accidents

  • 8/6/2019 Safe Design and Communication 091012

    39/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Working at Height -

    Single largest cause of construction accidents- WAH

    Regulations 2005 (Amended)

    Requires designers to

    avoid WAH where they can(impossible in most buildings)

    prevent falls

    where theycannot avoid WAH(we can only assist contractors

    and users)

    where they cannot eliminatefalls minimise the

    consequences

    How can designers do this?

  • 8/6/2019 Safe Design and Communication 091012

    40/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design Stage

    Early CDM

    Design Decisions of Mass and FormThe Problem / ChallengeIdentification of the key CDM

    design issues

    toconsider at the concept stage?The risksConstructing, maintaining and cleaning the buildingsstructure and exterior safely . Other detailed CDM

    issues may be explored at later design stages.The solutionIdentify significant CDM

    Issues affecting the design :-1. What is the Cleaning and Maintenance Strategy

    ofthe envelope and any large internal voids such as highspaces, atria or courtyards?2. Can it be built with reasonably practicable , knownor specialist constructional techniques?The benefitsEarly consideration of key CDM

    issues

    can simplify

    safety and set the tone for the entire project.Increased costs and project delays may be avoided.Key PointsLiaise with the client and CDM-C

    in reaching theseearly decisions.

    There are clear advantages to involving a contractor,CDM-C

    or a CDM

    experienced designer

    at theconcept stage.Early consideration of fundamental safety issues andbuildability

    may avoid wasted effort at later stages.

    Challenging forms and structures

  • 8/6/2019 Safe Design and Communication 091012

    41/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design Envelope Maintenance Systems

    Mechanically basedThe Problem / ChallengeCleaning and maintaining glazing

    to elevations at high levelin a safe manner

    The risksFalls from height due to unsuitable systems orinappropriately designed building fabric .Systems of work that require high levels of supervision fortheir effectiveness are susceptible to human error.Falling objects can endanger peopleThe solution

    Early consideration of cleaning options

    should be made inrelation to building form, scale and site constraints.

    Careful selection

    of engineered mechanical systems isneeded to ensure that the required cleaning andmaintenance tasks can be undertaken.The benefitsEconomic and safe maintenance systems

    appropriate to the

    scale, form and type of building.Provide the client with long-term maintenance strategy andbudgetary considerations .Provide a safe working platform

    in line with the Work atHeight Regulations hierarchy.Key PointsReview relevant viable options for mechanical systems atan early stage . Mechanically assisted work placementsystems require early discussion with specialists . Non-

    manned robotic systems

    eliminate work at height but canlimit design

    solutions. Mechanical systems are best suitedto large areas with little geometrical complexity. Any accessfrom the ground , including cherry pickers and MEWPs

    require stable hardstanding

    and influences landscaping

    MEWP

    Cradle

    BMU

    Robotic

  • 8/6/2019 Safe Design and Communication 091012

    42/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design Stage -

    Envelope Maintenance Systems-

    Manually basedThe Problem / ChallengeCleaning glazing to elevations

    at high level and indifficult locationsThe risksFalls from height due to inappropriate work systems,poorly designed fabric or operative error.The solutionEarly design consideration of cleaning options.Relatively low technology and low cost techniques tobe considered ,more reliant on manual efforts thanmechanical assistance. Ladders, opening windows,long water fed pole, reach and wash and ropedaccess systems all rely on trained operators and goodmanagement control systems

    for their safety. All areinherently safe in the appropriate situations and whenimplemented correctly. Limitations of use to be fullyunderstood.The benefitsAllows economies of scale

    to be proportionatelyapplied to all building types. Enables quicker and moreimmediate

    response to cleaning demands. Ropedaccess allows work positioning to difficult undercuts

    and geometrically intricate areas.Key PointsCareful consideration of all relevant associatedlegislation is necessary especially the Working atHeight Regulations to determine the most appropriatesystem or combination of systems for each buildingdesign. Large ,flat and high elevations are less suitedto these systems.

    Ladder limitations Opening window criteria

    Water-fed polesSpecial roped access areas

  • 8/6/2019 Safe Design and Communication 091012

    43/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design

    Visually acceptable Roof Edge Protection

    The Problem / ChallengeTo provide collective roof edge protection

    all aroundthe new building where regular access to roof plant is

    required. Visual roof edge details

    were important tothe design team and planners.

    The risksFalls from height by maintenance operatives during

    roof and plant maintenance operations.The solution

    A built-in 950mm parapet upstand

    design

    withintegral sun shading brise-soliel

    feature.The benefits

    No need to assess frequency of access to roof areas.Edge protection system does not require harness

    training or rescue arrangements .No perimeter handrail due to integral parapet.

    No need for additional edge guardingKey Points

    Permanent edge protection

    provides an optimum

    safety solution and is at the top of the work at heighthierarchy.Co-operation of client and project team required to

    avoid being value engineered

    out.

    950mm

    Visually hidden edge guarding integrated into cladding

    950mm high guarding View of roof upstand

    950

    mm

  • 8/6/2019 Safe Design and Communication 091012

    44/56

    h d l d l b h d l

  • 8/6/2019 Safe Design and Communication 091012

    45/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Scheme and Detailed Design

    Globe Lighting Access-

    London ColiseumThe Problem / ChallengeThe existing globe at the top of the tower

    of theColiseum Opera House was no longer illuminatedand needed refurbishment . The building is Grade 2*listed so replication of original features was essential.The risksFalls from height during refurbishment and futuremaintenance of the 240 lamps .The solutionRegular man access was rejected on safety andeconomic grounds.A fibre optic design

    was selected with projectors atlower accessible levels of the tower..The tower was fully scaffolded

    during refurbishment,and can be scaffolded

    for periodic maintenance and

    cleaning.The benefitsRisks associated with access to the globe wereeliminated. The fibre optic solution allows client aneconomic method to maintain full lighting

    to the globesky sign without risks to maintenance personnelKey PointsConsultation between the client / FM team and thedesign and contractor team

    allowed early decisionsto be made. (The early involvement of the clientallowed for the increased costs of fibre optics to beaccommodated.) Survey drawings were annotated

    toanalyse the risks and communicate the solutions.

    Existingdark

    tower Proposed lit

    tower

    CDM

    Analysis

    I i i l D i Gl R f Cl i d M i C li

  • 8/6/2019 Safe Design and Communication 091012

    46/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design-

    Glass Roof Cleaning and Maintenance -

    ColiseumThe Problem / ChallengeAccess to the new glass barrel vaulted roof

    for

    cleaning and maintenance purposes.The roof is above refurbished foyers and isdesigned to recreate the original design.The risksWorking at height and over fragile glass

    abovehigh internal and external drops.

    The solutionA Building Maintenance Unit (BMU) with an11metre jib

    and one man cradle. Planningconstraints influenced rejection of other options,eliminating the use of a travelling curved gantrythat would be visible at all times from streetlevel. Increased structural works were required

    to support and conceal the BMU

    behind thetower at roof level.The benefitsBoth visual and safety priorities were met withsome increased complexity and cost.Client has the benefit of increased accessibilityprovided by a bespoke systemKey PointsThe client, the facilities managers and specialistsuppliers of cleaning systems were consultedearly on. The final solution for this project tookaccount of safety, historic constraints andaesthetic considerations.

    Curved GlassRoof

    Proposed gantry solution

    Final BMU

    Design BMU

    Solution

    Cut away view of roof

    D il d D i A T Li h i C li

  • 8/6/2019 Safe Design and Communication 091012

    47/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Detailed Design Access to Tower Lighting -

    ColiseumThe Problem / ChallengeExisting historic freestanding light fittings

    to berefurbished and replace those missing. These arelocated on unguarded parapets

    to the tower and faade.

    The light fittings vary between 2.5m and 3.5m

    andcannot be safely reached unaided.The risksFalls from unguarded parapets during maintenanceaccess.

    The solutionPowered access equipment, and scaffolding werediscounted after careful assessment as unsuitable.A roped access system, allowing safe work positioningand fall restraint , agreed after detailed client, designteam negotiations and specialist consultations.

    Rope attachment anchors

    were built into the structuralsteel and terracotta cladding by design team integration .Long life lamps were chosen to minimise the frequencyof access.The benefitsProvides safe and economic lamp replacement at shortnotice using trained theatre maintenance staff .Key PointsLighting design drawings were annotated

    tocommunicate the risks and solutions to entire team.The annotated drawings were used by the constructionteam as the basis of the construction details

    Historic Light

    Eyebolts installed

    Parapet detail

    CDM

    Analysis

    eyebolts

    I iti l D i F il D d R f li ht L d C li

  • 8/6/2019 Safe Design and Communication 091012

    48/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design

    Fragile Domed Roof-light-

    London ColiseumThe Problem / ChallengeTo refurbish the existing stained glass fragile domed rooflight

    toprevent water ingress and allowing backlit illumination.

    The risksFalls from height during the construction. Falls of people or objectsduring the maintenance and cleaning of the stained glass panels.

    The solutionA glass fibre outer dome

    was installed by crane for weatherproofing.The inner glass domed roof-light was repaired from a birdcagescaffold within the auditorium.Maintenance walkway installed

    between the two domes with a highlevel fall restraint cable fixed to the outer dome.Access to the upper curved areas of glass is via a curved laddergantry with a slidelock

    harness attachment.Easily accessed light fittings fitted at low walkway level reflect off

    the underside of the outer dome to illuminate the rooflight.

    The benefitsThe client has been able to reinstate a spectacular roof-light featurewhilst overcoming the weatherproofing and significant maintenancesafety challenges.

    Key PointsSpecialist design subcontractors consulted early .Communication with the Client and FM team essential in agreeingstrategy and budget at early stage by annotation of drawings.A combination of fall prevention methods were carefully selected,each justified in respect of the hierarchy of control measures.

    Rooflight

    from below

    Curved rotatingladder + slide-lock

    Walkway and up-light

    7-storey high auditoriumwith dome and roof-lightat top

    I iti l D ig R d A T l t t

  • 8/6/2019 Safe Design and Communication 091012

    49/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design-

    Roped Access-

    To unusual structuresThe Problem / ChallengeDesign of landmark or unusual feature

    structures requiring difficult cleaning andmaintenance access to windows and lightfeatures and for painting or inspectionactivities.The risksPrevention of falls

    by methods that respect theWorking at Height Regulations

    hierarchy butprovide the necessary and reasonable accessrequirements whilst facilitating the aestheticand safety aspirations of the design.The solutionA roped access work positioning system inaccordance with HSE

    and specialist IRATA

    installation and operating procedures.The benefitsSpectacular and essential structures can bedesigned with the incorporation of safe accessenabling features and management systemsKey PointsEarly design team and client agreement thatdesign expectations exceed the more commonworking at height prioritisation strategy.Specialist roped access installation advice

    toinform the integration of rope attachmentfittings and features

    The HSEs

    description of RopedAccess

    Terminal 5Heathrow

    SpinnakerTower

    Roped access IRATA

    guidelines

    Best Pr ctice C se St d Spinn ker To er

  • 8/6/2019 Safe Design and Communication 091012

    50/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Best Practice Case Study

    Spinnaker TowerThe Problem / ChallengeConstruction and maintenance of an iconic and unusual

    structureThe risksFalls from height during future maintenance operations

    including aircraft light replacement access , observation deckexternal window cleaning and painting of metal surfacesThe solution

    International Rope Access Trade Association membercompanies IRATA, employed by client to ensure the safedesign of attachment points and methodology of access

    ,and their effect upon the structure during design stages.Long life lamps and paints used to minimise access.The benefitsThe structure does not have to be modified

    for traditionalaccess techniques higher up the hierarchy of working atheight regulations.Key PointsEarly recognition of safety issues and consultation withspecialists

    to prevent sub-contractor design at a later stage.The early client appointment of a specialist

    to assist with the

    design of the unusual structure requires special coordinationof architectural, structural and specialist design skills, andearly client funding.

    HSE Case Study Initial Design Residential Faade Access System

  • 8/6/2019 Safe Design and Communication 091012

    51/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Case Study

    Initial Design-

    Residential Faade Access SystemThe Problem / ChallengeLandlord controlled window cleaning access

    tohigh value flats with balconies to main elevations.Impractical to use a suspended access cradle dueto the need to climb out of cradles and overbalconies. Access via flats not acceptable totenants for security reasons. Access from commonparts not possible , and balconies not continuousfor security reasons.The risksFalls from

    height during window cleaningoperationsThe solutionRoped access solution for operatives to accesseach balcony area from which safe cleaningoperations can take place.The benefitsLandlord can ensure all windows cleaned atregular intervals.

    Operatives clean most windowsfrom safe balconies.Key PointsIRATA

    registered company consulted

    on ropeattachment design and details.IRATA

    trained rope access operatives employed

    to ensure safe systems of working.Highly specific project details justified a ropedaccess solution , which would need to be equally

    justified if proposed on other projects.

    Full length but separated balconies IRATA

    guidelines used

    Section and Elevations analysed for appropriate systems

    Scheme and Detailed Design Fragile Roof lights Wigmore Hall

  • 8/6/2019 Safe Design and Communication 091012

    52/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Scheme and Detailed Design

    Fragile Roof-lights-

    Wigmore

    Hall

    The Problem / ChallengeTo refurbish and modify existing fragile roof-lights

    in alisted concert hall building whilst enhancing theaccessibility for cleaning and lighting maintenance access,with no appreciable affect on the hall acoustics oraesthetics .The risksFalls from height during construction and maintenanceoperations.The solutionThe hall was fully birdcage

    scaffolded

    duringconstruction.This allowed removal of existing cramped crawl-ways andthe installation of a new lightweight central spine walkway .This facilitated access to the lights for performances andgeneral hall lighting within the roof spaceThe benefitsSignificant improvements

    in accessibility and safety ofmaintenance operativesRetention and upgrading of an historic and fragile roof-

    light feature.Key PointsEarly analysis of the structural limitations

    of the roof trussand walls. Access requirements for A/C services andlighting requirements understood through discussions withusers and consultants.Buildability

    issues raised at the beginning of the projectthrough specialist consultation.

    finl

    Drg

    orphoto

    Roof services, rooflight

    and access analysis

    Inner rooflight

    above auditorium

    Original roof-space

    Revised roof-space

    Inner roof-lightand lights

    New centralwalkway

    Outer roof-

    light

    Original

    crawlway

    Initial Design Maintenance Access to Unusual Roofs Dubai Metro

  • 8/6/2019 Safe Design and Communication 091012

    53/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    Initial Design

    Maintenance Access to Unusual Roofs -

    Dubai Metro

    The Problem / ChallengeTo establish an appropriate means of roof surface andglazing cleaning

    on 40 overground

    station roofs of iconicstructural form in the hot Middle Eastern climate of Dubai

    The risksFalls from height and heat exposure

    on curved metalroofs and glazed elevations above operational railway andbusy 6-lane motorway adjacent.

    The solutionVariety of roof access options analysed

    including

    BMUs,cherry pickers and roped access, with possible use of roofcleaning sprinkler system. All discounted on grounds ofimpracticability and safety to operatives and road users.Design team and client agreed solution was a purposedesigned robotic systemThe benefitsMan access to roofs eliminated for general maintenancepurposesKey PointsDetails of sun-shading devices

    critical to allow passage ofrobot. Roof apex robot attachment system, water supply

    and mansafe

    fall restraint harness system to bedeveloped in detailed design with specialistsubcontractors .

    Robotic systemCherrypicker

    option

    Gold metallic curved roof 120m X 30m

    Roped access +sprinkler options analysis

    HSE Designer Guidance Unusual Construction Sequences

  • 8/6/2019 Safe Design and Communication 091012

    54/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Designer Guidance

    Unusual Construction SequencesThe Problem /ChallengeIntelligibility of unusualconstruction sequencesThe risksCollapse duringconstruction

    due toasymetric

    loading andunbalanced cantilevers

    The solutionGraphic presentation ofthe proposed sequence

    for contractors tounderstand the structuraland constructional designintentions.The benefitsInformation sharing withthe construction team atearly stages

    of the projectKey PointsSimple 3-D drawings

    overlaid in an animatedpowerpoint, showing thesite constraints andproposed significantsequences

    HSE Designer Guidance Demolition of unusual structures only

  • 8/6/2019 Safe Design and Communication 091012

    55/56

    Scott Brownrigg DIOHASSafe Design and Communication Oct 2009

    HSE

    Designer Guidance

    Demolition

    of unusual structures onlyThe Problem / ChallengeWhat demolition information

    is required in the Healthand safety file

    for future demolition purposes?Unusual and hidden

    residual risks such assuspended and cantilevered features, post-

    tensioned and pre-stressed elements, etc.The risksUnusual or hidden

    structural or services relatedelements can be accidentally damaged or incorrectly

    cut during future refurbishment or demolition workscausing catastrophic collapse

    of the entire or largeparts of the structure.The solutionIndicate on drawings where these issues are hidden

    so future designers and contractors can planappropriately for temporary support or safedemolition.The benefitsReduced risk of

    collapse and injuriesKey PointsIdentify significant issues only.No need to indicate obvious and normal structuraland constructional issues which are easily identifiedby future competent designers and contractors.Too much irrelevant information will hide the realissues.Indicate on graphic information where possible.

    Suspendedstructures

    21m Cantilevers

  • 8/6/2019 Safe Design and Communication 091012

    56/56

    S i O S

    THANK YOU

    QUESTION TIME