rural distribution project - world bank · can tho rural medium voltage network component project...
TRANSCRIPT
ELECTRICITY OF VIETNAM POWER COMPANY -NO. 2
.-.----.-----. 6p ---------------
Rural Distribution Project SUB - PROJECT CAN THO CITY
_---------------------------------------
VOL. 36
Volume 3 Environmental Management Plan
( Final Venian I
-.--
Power Company No. 2 April Power Engineering cYt Cons~~lti~lg Center 2008
PC2-PECC
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version -
Rural Distribution Project
Feasibility Study CAN THO CITY
Volume 3
Environmental Managerment Plan
Prepared by Submitted by
Director Director
ate.. . .&/%??/z#&. . . . . . . . . . . . . . . . Date. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
- @ Power Company No. 2
Power Engineering & Consulting Center
The World Bank In Vletnam
September 4,2008
Mr. Pbam Ngoc Le DeputyDirecfor Powex Company No. 2 72 Hai Ba Trung Ho Chi Minh City
Dcar Mr. Is,
(KN-C~.4444) Rural DiWbutlon Project.. Clearance of Safeguard Documents
I would like to i a f i you that the Bank has received the Resettlement Plan (RP), Environmental Management Plan (BMP) of Tien Giang, Can Tho Provinces and RP of Hau Giang Province. These reports have been reviewed by Worid Bank's safeguard specialists and have been found saiisfactory.
To complete the procedure, you are kindly requested to send us (i) a cadimation letter saying that these reports have been disclosed at the project sites at diffkrmt managcmcnt levels and (ii) 4 copies of English and 1 copy of V i w t s c of each rcport for disclosure purpose at the World Bank office in Vietnam & in Washington D.C.
Sincerely,
Van Tien Hung Project Task Team Leader
Cc: Mr. Vo Quoc Tuan, Director of PMU, Power Company No. 2
T-hone: (84-4) 6346600 Facsimile: (84-4) 934-
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Final Version
TABLE OF CONTENTS
......................................................................................................... ABBREVIATIONS 3
1 . GENERAL OVERVIEW .............................................................................................. 4
....................................................................................................... 1 . 1 Project goals 4
1.2 Location of substations ........................................................................................ 4
................................................................................................... 1.3 Line direction 5
I1 . PROJECT DESCRIPTIONS ........................................................................................ 10
2.1 General description of natural. economic and social conditions of the project site ..................................................................................................................... 12
2.2 Nature protection and reservation area. sensitive zones. cultural works. ....................................... historical site. temples and pagodas in the project site 13
. .............................................................................................. 111 LEGAL FRAMEWORK 13
................................................. 3.1 Vietnamese legal regulations on environment 14
................................................................ 3.2 World Bank's environmental policy 14
...................................................... . IV ENVIRONMENTAL IMPACTS ASSESSMENT 15
............................................................................. . V COhMWNITY CONSULTATION 25
. ...................................................................... VI IMPACT MITIGATION M E A S U ~ . S 28
. VII ENVIRONMENT MONITORING ............................................................................. 4 1
................................................................. VI1I.INTITUTIONAL BUILDING ACTIVITY 52
.................................................................. . IX IMPLEMENTATION ARRANGEMENT 54
........................................................ X . OBSERVATION AND REPORTING SYSTEM 56
. XI ESTIMATED EXPENSES FOR EMP IMPLEMENTATION .................................... 57
ANNEXES .......................................................................................................................... 5 8
Annex 1 : ..........................................................................................................Reference 59
Annex 2: ................................................................... List of staff involving in the report 60
Annex 3 : ...................................................................................... Map of the project site 6 1
Annex 4: .................................................. Minutes of community consultation meeting 62
Annex 5: ................................................... S o images of the community consultation 63
.................................................................................. Annex 6: Other Related Document 64
Power Company No . 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
ABBREVIATIONS
PMU:
IMM:
EVN:
EMP:
WB:
FP:
PC 2:
PCC
Project Management Unit
Impact Mitigation Measure
Vietnam Electricity Group
Environment Management Plan
World Bank
Fire Protection
Power Company No.2
Power Consultancy Center
People's Committee
Rural Distribution Project
City
Resources and Environment
; Vietnamese Dong
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Final Version
I. GENERAL OVERVIEW
1.1 Project goals
The project overall goal:
- Supply enough good quality electricity'for people living in rural areas. Development
goals of RD project are (i) to rehabilitate and upgrade capacity of the existing
distribution line and substations, and standardize them to 22KV to meet demands for effective development, (ii) to supply good quality and enough electricity for
production, (iii) to reduce the electricity network loss.
- Improve the electricity distribution network efficiency in the project site including (i) to rehabilitate 18.2km of 3-phase medium voltage transmission line; (ii) to upgrade the
1-phase medium voltage transmission line to 3-phase medium voltage transmission
line; (iii) to construct 3.4km of new 3-phase medium voltage transmission line; (iv) to
construct 38.0 km of new 1-phase medium voltage transmission line; (vi) to
rehabilitate and upgrade 36 one-phase substations within the area of 15 wards/communes/towns in 06 districts of Can Tho city.
In order to implement project components, the land acquisition shall be carried out at electric
pole foundation and the security corridor of the line. However, the rehabilitation and
expansion of medium voltage and low voltage system shall not cause large scale land
acquisition and resettlement.
Cumnt data show that the existing electricity network can supply electricity to almost
rcsidential areas within the project site, however due to (i) many old existing lines and electric
poles, (ii) disordered lines, (iii) many random connections and, (iv) newly developed
residential areas, many networks are overloaded with high electricity loss and low quality
setvice.
Therefore, the project implementation shall help reduce electricity loss on medium voltage
network and enhance the service capacity, such as: to minimize failures, to enhance safety
level and quality of electricity and to reduce electricity rate for domestic uses in the project
site until 2015.
1.2 Location of substations
m Binh Thuy district
4 Thoi An Dong ward
Substations: Cui canal, Muong Chua canal, Ly Binh canal with capacity of 37.5 kVA.
4 Long Hoa ward
Substations: Cau Chu Y canal with capacity of 37.5 kVA, Ong Huong canal with capacity of 25kVA.
4 Long Tuyen ward
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Final Version
Substations: Nga Cai canal, Chanh - Mieu Ong canal, Chuoi canal, Cay Gua canal with
capacity of 25 KVA and Nuoc Lanh canal with capacity of 37.5 KVA.
6g 0 Mon district
Cai Son 1 substation with capacity of 25kVA
m Pbong Dien district
4 Phong Dien district town .
Substations: Ta Nien 1 and Ta Nien 2 with capacity of 25 KVA.
4 Truong Xuan commune
Substations: Hau KH9 1, Hau KH9 2, Hau Truong Ninh 1, Hau Truong Ninh 2, Vam Bi 1, Vam Bi 2 with total capacity of 25 KVA.
J Giai Xuan commune
Substations: Lo Ren canal, Ba Cao, Ba Voi, Nga Cai, Dong hamlet 1,2 and 3, Ut Tac canal, Nga Cai Dinh canal, Ong Tung channel, Ba Cui canal. All these substations, except Dong hamlet substation, have capacity of 37.5 kVA. Dong hamlet substation has capacity of 25 KVA.
13 Line direction
Total length of the lines is 19.378 m
m Binh Thuy district
4 Thoi An Dong ward
- Construction of new Cui canal 1 one-phase medium voltage transmission
line from post No. 184-471 CN to the adjacence of Mieu Page canal. The
line is 0.8km long.
- Construction of new Muong Chua Ke Ba canal one-phase medium voltage transmission line from post No.2814 1 - 47 1 LH. The line is 0.5 km long.
- Construction of new L y Binh canal one-pbe medium voltage
transmission line from post No.2021U9-47 1CN to the end of Ly Binh
canal. The line is 0.8km.
J Long Hoa ward
- Construction of new Cau Chu Y canal one-phase medium voltage transmission line from post No.T28/7/3 1-47 1 LH along Binh Yen B area. The line is 1.5km long.
- Construction of new Ong Huong canal one-phase medium voltage transmission line from post T2817115-471LH along Binh Yen B area. The
line is 1 krn long.
4 Long Tuyen ward
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Envhnmcnt Management Plan (EMP) Final Version
- Construction of new Nga Cai canal one-phase medium voltage
transmission line fiom post No.7 113 1 -479LH to post No.5 17 NC. The line
is 1 krn long.
- Construction of new Nuoc Lanh canal one-phase medium voltage
transmission line fiom post No.521218-479LH. The line is 2 km long.
- Construction of new Chanh-Mieu Ong canal one-phase medium voltage
transmission line from post No.69126-479LH to post No. 107 MO. The line
is 1 km long.
- Construction of new Chuoi canal one-phase medium voltage transmission line from post No. 8711 1-479LH to post No. 177FlRC. The line is 1 krn
long.
- Construction of new Cay Gua canal one-phase medium voltage
transmission line fiom post No. 52129-479LH. The line is 1 km long.
a Co Do district
4 Truong Thanh commune
- Rehabilitation of the existing Trai Bau one-phase medium voltage
substation to a three-phase medium voltage substation fiom post No.280184
of line 475CN to post No. 28018411 1. The line is 1 km long crossing rice
fields fiom Cau Nhiem canal to Ong Duc canal along the existing line.
- Rehabilitation of Truong Binh one-phase medium voltage substation to a
three-phase medium voltage substation fiom post No.280/116 of line
475CN to post No.2801124120. The line is 2 km long and running along the
existing line on the right side of Bong Gieng canal.
- Rehabilitation of Muong Khai one-phase medium voltage substation to a
three-phase medium voltage substation from post No.280193 of line 475CN
to post No.280193152. The line is 3.5 km long and running along the
existing line on the right of Muong Khai canal.
J Trwng Xuan commune
- Rehabilitation of the Ba Dam channel one-phase medium voltage
substation to a three-phase substation fiom post No.284190 of line 475CN
to post No.284190157. The line is 4.5 km long and running along the
existing line on the right of Ba Dam channel.
88 0 Mon district
di Thoi An ward - Construction of new three-phase medium voltage transmission line and Cai
Son - Cai Dau substation from post No.138/104/32. The line is 2 km long
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Ebvinmment Management Plan (EMP) Final Version
and running along the rural road to Cai Son canal. The line is 3-5m apart fiom the road side along Hau river.
68 Pbong Dien district
4 Nhon Nghia commune - Construction of new Muong Khai line and substation from the post
between post No.5 and post No.6 to the final existing low voltage post. The line is 1.5 km long and running along Muong Khai canal.
Q Phong Dien district town
- Construction of new three-phase medium voltage transmission line and Ta Nien substation from post No. 10 to the final post of the existing low voltage of Nha Tho canal. The line is 2 km long and running along the
existing low voltage line.
4 Truong Xuan commune
- Construction of new one-phase medium voltage transmission line and Hau
KH9 substation from post No. 83" to Truong Long A flooding prevention area. The line is 3km long and running along Hau KH9 road.
- Construction of new one-phase medium voltage transmission line and Hau
Truong Ninh substation. The line is 1.5 km long and running along Hau
Truong Ninh road.
- Construction of new one-phase medium voltage transmission line and Vam Bi substation from post No. 3511 9. The line is lkm long.
4 Giai Xuan cohrmune
- Construction of new one-phase medium line from post No.125-A79LH. The line is 2 krn long and running along the existing low voltage line.
- Construction of new Ba Cao canal one-phase medium line fiom the
junction of Lo Ren canal. The line is 1.5 km long.
- Construction of new Ba Voi Lon and Ba Gua canals one-phase medium voltage transmission line !?om post No. 479LH1141 to the existing low voltage post No. 18. The line is 2 km long.
- Construction of new Cai Ong Tuong junction one-phase medium voltage transmission line fiom post No.471LW28135. The line is 2 km long.
- Construction of new Dong hamlet - Buc road one-phase medium voltage
transmission line fiom post No.2251471CN to Dong hamlet. The line is 1.2 km long and running along Dong hamlet canal.
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Find Version
- Construction of new one-phase medium voltage transmission line fiom Lo
Ren canal to Ut Tac canal. The line is 1.2 km long and running along Ut Tac canal to Khoang Chan canal junction.
- Construction of new Nga Cai Dinh canal one-phase medium voltage transmission line from post No. 145 of 479LH line. The line is 1.5 km long and running along Cai Dinh canal.
- Construction of new Ong Tuong channel one-phase medium voltage
transmission line from post 471LW203 to the low voltage post No.23. The
line is 1 km long and running along Ong Tuong channel.
- Construction of new Ba Cui medium voltage line fiom post No.479LW 10617137. The line is 1 km long and running along Ba Cui canal.
f&l Cai Rang district
Y Phu Thu ward - Construction of new PT3 primary school one-phase medium voltage
transmission line from- the post No. 1 53147114 - 574CT. The line is 1 km
long and running along the canal.
5 Ba Lang ward
- Construction of new three-phase medium voltage transmission line No. 9 - Ba Lang from post NO. 1350. The line is 1.4 km long and running along the
existing low voltage Iine.
- Rehabilitation of the existing one-phase medium voltage transmission line No.9 - Ba Lang to a new three-phase medium voltage transmission line fiom post No. 135 to post No. 13513. The line is 0.25km long.
f&l Tbot Not district
J Trung Nhar commune
- Rehabilitation of Page Ba one-phase medium voltage transmission line to a three-phase medium voltage transmission line fiom post No.33T115 to post
No.33T1144. The line is 10.0 km long and running along the existing line fiom Trung Nhat commune to Trung Huong commune,
4 Trung Kien commune
- Rehabilitation of Cai Nga one-phase medium voltage transmission Iine to a three-phase medium voltage transmission line from post No.55 to post No.55156. The line is 3.5km long across the forest and running along the rural road.
9 Thoi Thuan commune
Powor Company No. 2 Power Eagiaecriag & Consultiag Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Envinmmcnt Management Plan (EMP) Final Version
- Rehabilitation of Cai Cao one-phase medium voltage transmission line to a three-phase medium voltage transmission line from post No. 5 1 to No.
51/33. The line is 1.5 krn long across fields and running along the rural road and the existing line.
J Tan Loc commune
- Rehabilitation of Tan Loc one-phase medium voltage transmission line to a three-phase medium voltage transmission line from post No.105 to post No.105M00. The line is 18.2 krn long across Hau river and running along the existing line and Tan Loc road.
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT -PROJECT
Environment Management Plan (EMP) Final Version
11. PROJECT DESCRIPTIONS
Power Company No. 2 Power Engineering & Consulting Center
Project
Programme
New construction or Rehabilitation, upgrading project
Project location: Provincelcity, District/Rural district, Ward/Commune/Town
Length& voltage of the line
Width of the line corridor
Quantity and height of posts
Number of substations
Can Tho Rural Medium Voltage Network Component Project
Project "Rural Power Network" funded by World Bank
New constructions Rehabilitation
Province/ city:
Can Tho
Rural Districts:
1) C b D6
2) Phong
3) Th6t ~ 6 t
District:
4) Binh Thuy
5) 0 Man
6) Chi R h g
War& commune/town:
1 ) 02 communes: T m h g XI&, TlUhg Thhh.
2) 03 communes and 01 town: Giai XuBn, Nhun NghTa, T n r h g Long, Phong ~ i k n town.
3) 04 communes: Trung d t , T m g K i h , Th6i Th*, T h Lac.
4) 03 wards: Long T U ~ ~ ,
Long Hba, Th6i An Dang.
5) 01 ward: Th6i An.
6) 02 wards: Phfi Thit, Ba
Lhg.
Length: 87,9 km Voltage: 22 KV
6 m
Quantity: Height:
36 substations
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT.PROJECT Environment Management Plan (EMP) F i ~ f Version
Power Company ~ 0 . ~ 2 Power Engineering & Consulting Center -1 I-
Substation's capacity
Start and completion date of
construction
Construction during rainy
season
Number of households affected by the project
Total affected land area
(housing land)
Affected agricultural land
Affected forest land
Mkcted industrial land
Affected housing land
Other types of land affected
Total project expense
(1 USD = 16.000 VND)
Total capacity of the
substations
1325 kVA
Duration:
y e s o NO
970 households
Temporary: 88 1 m2
(public, land)
Temporary = 7.627 m2
Temporary = 0 m2
Temporary = 0 m2
Temporary = 0 m2
Temporary = 0 m2
VND = 3 8 billion (total
fund)
- WB = 32.3 billion
- Counter-part
fund = 5.7 billion
Long-term = 272 m2
Long-term = 7.026 m2
Long-term = 1 1 .SO0 m2
Long-term = 0 m2
Long-term = 0 m2
Long-term = 0 m2
.
USD = 2.375 million
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) F i ~ l Version
2.1 General description of natural, economic and social conditions of the project site
4 Geographical conditions
Can Tho city is located in Mekong Delta and surrounded by an inter-connected river and canal network. Can Tho city's area is 1,389,599 km2 and bordering with 05 provinces: An Giang province in the North, Hau Giang province in the South, Kien Giang province in the West, Vinh Long and Dong Thap provinces in the East.
4 Climate
The city is located within the inner tropic of Cancer, closed to the equator. The local climate
is wann but temperate. There are 02 separate rainy and dry seasons. The rainy season is from May to November. The dry season is from December to April.
4 Topography, pedology and hydrology
These conditions are not changed during the years: terrain is flat; the difference is not more than 2m. The terrain is lowered in the South west section.
& Natural resources
Water resource
Fresh water resources (including: surface water, rain water and ground water) are abundant and available during the year. This is a great advantage of the city.
Land resources
Agricultural l e d with an area of 116,867 ha is fully used for intensive farming and mutil- cropping.
Mineral resources:
- There is not any metallic resource in the city. The main resource is land for cultivation, fresh water and sand from river (for filling).
- A special resource is sand from Hau river for filling. Hau river bring about 1,000,000d of sand to Can Tho city. This is a big bcmfit to the city. However, it's difficult to manage sand exploitation activities and the exploitation may cause erosion to the banks of Hau river.
4 Population
Population of Can Tho city in 2005 is: 1,137,269 people
4 Culture - Society - Total population of Can Tho city in 2005 is 1,137,269 people with the average
density of 8 12 peopleh2. - There was not any special change in the community health, bird flu was well
controlled.
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT.PROJECT
Envhmment Management Plan (EMP) Final Version
2.2 Nature protection and reservation area, sensitive zones, cultural works, historical site, temples and pagodas in the project site
T h e is not any nature protection and reservation area or sensitive wnes in the project site. The project site is not near any cultural works, historical site, temples and pagodas, either.
111. LEGAL FRAMEWORK
Power Company No. 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Fimi Version
Vietnamese legal regulations on environment
Law on Environment Safeguard issued in 2005.
Decree No.80/2006/ND-CP dated 09/08/2006 of the Government on Detailed regulations and guideline on implementation of some clauses stipulated in the Law on
Environment Safeguard.
Decree No. 81/2006/ND-CP dated 09/08/2006 of the Government on administrative violations in Environment Safeguard.
Circular No. 08/2006lTT-BTNMT date 08/09/2006 of Ministry of Natural Resource and Environment on Guideline on Strategic Environmental Assessment, Environment Impact Assessment and Commitment on Environmental Protection.
Decree No. 106/2005R\TD-CP dated 17/08/2005 of the Govenunent on Detailed Regulations and Guideline on implementation of some clauses stipulated in the Law on Electricity regarding protection of high voltage network.
Decree No. 2412000MD-CP regulating implementation of the Law on Foreign Investment in Vietnam (Clause 82) regarding Environment Safeguard.
Current Vietnamese Standards (TCVN).
World Bank's environmental policy
- OP 4.0 1 : Environmental assessment;
- OP 4.04: Natural habilitation areas;
- OP 4.1 1 : Culturai relics;
- BP 17.50: Information disclosure
Detailed instruction for general assessment measures for transmission line project can be found in:
- World Bank, 199 1 : Source book on Environment Assessment, third edition
- Frame of regulations on Environment Safeguard for Rural Power Network Project.
Power Company No. 2 Power Engineering & Consulting Center -14-
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Find Version
IV. ENVIRONMENTAL IMPACTS ASSESSMENT
Table 4.1: Project Impact assessment . .
Power Company No. 2 Power Engineering & Consulting Center
No. Assessment Impacts
PRE-CONSTRUCTION AND CONSTRUCTION PHASES
1
2
Description Scale Duration
Can be
mitigated
Mitigated
Temporary and long-
term acquired land
Impacts on local
houses and structures
Mediu ml
Major
Minor
Shortnong term
Short
term,
Long term
Total acquired land area for posts erection and for transmission line
corridor is 26.855 m2.
- Total permanently affected land area is: 1 8.798m2.
- Total temporarily affected land area is: 8.507 m2.
Land areas are affected temporary:
Total land areas (m2)
7.626
88 1
8.507
Agriculture Land
Housing land
T0t.l
There is not any temporary or permanent impacts on local houses and
structures (partidentire).
Household(s)
114
39
153
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment hkugement Plan (EMP) Final Version
Power Company No. 2 Power Engineering & Consmlting Center
3 Medium and can be
mitigated
Impacts on trees and crops
- In the project, a 6m-wide corridor along roads shall be cleared to create a safety corridor for the line. This is the project's
major environmental impact which may require cutting down
high trees along the line's safety corridor.
- Total numbers of trees, which are higher than 4m, to be cut
down are 7.719 . Of which, mostly are jack-fruit tree, mango,
eucalyptus, longan and custard-apple trees, etc.
- Number of trees which are permanently affected by the project is
presented below (mostly are eucalyptus, bamboo, mango, coconut, star apple, longan, jack-hit and grape fruit trees, etc.):
Mediu m
Location
Binh Thuy district
CAi RBng district
C b D6 rural district
6 Mdn district
Phong ~ i & n rural
disttict
Thdt ~ d t rural
district
Long term
Unit
Tree
Tree
Tree
Tree
Tree
Tree
Quantity
1.059
260
2.33 1
52
3.034
983
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Fimf Version
Power Company No. 2 Power Engineering & Consulting Center -17-
4
5
6
7
8
No impact
No impact
No impact
Can be
mitigated
No impact
Unbalancing and disrupting natural
habitat
Negative impacts on cultural and historical relics, temple, pagoda and sensitive areas, areas of reservation
Pollution to surface
water sources due to
excavation and filling works
Pollution to surface
water due to waste
water discharged from
workers' camps
Soil erosion and
accumulation due to
excavation and filling
None
None
None
Minor -
Minor
None
None
None
Short tern
Short tern
Total
Permanently affected cultivation land area: 7.267 rn2
There are not any special spices living within project sites, particularly along lines.
During Design phase, location of the project was studied and selected.
There is not any cultural, ,historical relics, temple, pagoda and sensitive area, reservation area within project site.
The project construction are& (electric post foundation) are apart fiom
surface water sources (pond, lake, river and spring). Thus, pollution to surface water sources is prevented.
There are many boarding houses in the proposed areas to be supplied
with electricity. Workers shall rent boarding houses and live with local
people. Number of workers staying in camps shall be limited and thus,
quantity of discharged waste water shall be minimized.
Most of the lines are rehabilitated or upgraded. As a result, number of
electric posts with foundation structure to be changed is minor, In addition, the lines are along rural roads and apart fiom potential areas
Tree 7.719
P & .I w .z
a
3 g -s u .z
-8 23 3 El *a u -8
B 2
" A "
B 3
8 .I CI
3
CI
a
I
€ S 5 .a cn
8 . fi E
s a
I I
€
5 3 c o V1bE
8 c E S 3
I
ti Y 5 E V1
5 E a Y Q-4
E O a a 8 .a c
0 : g 4 P)
3 3 s 3 M &
d - = 2
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
I Traffic obstruction
I during construction process
1 system due to
1 construction and
I transportation of
construction materials
Negative impacts to
local environment
caused by workers
solid wastes, such as excavated materials during construction
process is minor. The quantity of excavation and filling works is about 2-3m31 location.
- The exceeding excavated materials shall be reused for filling
post foundations. Thus, these exceeding materials do not require
treatment and reinstatement.
Can be
mitigated.
Short term
Short term
- Construction works, such as excavation, material collection,
stretching cable along roads may cause obstruction to the local traffic.
Short term
1 - These roads have good foundation structures and covered by a
thick asphalt layer. -In addition, scope of the project is small,
there is small number of means of transport participating in the
project. As a result, damages o the local road system are
limited.
- Estimated number of workers to be mobilized is about 70
people working in 03 districts and 03 rural districts of the city.
- Estimated construction duration at 01 location is about 3
months.
- The highest number of workedworking days in a district/rural
district is 40 worked14 days.
- Wastes are mainly domestic wastes discharged by workers or
construction wastes during excavation and transportation. of
Minor
Mitigated
Power Company No. 2 Power Engineering & Conrulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Final Version
Power Company No. 2 Power Engineering & Consultiag Center
18 Risks to health and
safety from camps and materials warehouse
Minor Short
tend
Medium
construction materials.
- Quantity of domestic wastes discharged by workers is small and normally collected to disposal site.
- Quantity of construction wastes discharged during construction process is small and shall be collected by the Contractor and
disposed at local disposal sites. The site shall be reinstated to
the existing conditions before construction.
- There is a risk of contagious diseases among workers and local
people.
- There must be some warehouses (indoor and open) to store
construction materials for the project uses and camps for workers to rest and sleep after working.
- Camps and warehouses may become a risk to health and safety
of local people and workers since materials and equipments are
not stored carefLlly and may become the cause of arguments
between workers and local people.
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMPI Final Version
OPERATION PHASE
Power Company No. 2 Power Engineering & Consulting Center
1 9
20
2 1
22
23
Positive
No impact
No impact
No impact
Can be mitigated
- The project will improve electricity supply service and local supply capacity, such as supply electricity for
irrigation, domestic uses, development of local production activities and agriculture. The improvement of
electricity supply service will help increase labor
productivity and create more jobs.
- Since'the project works are constructed along rural roads, temporary roads for construction are not needed.
- Since the project is implemented in districthral district areas, the existing transformers shall not be dismantled. New transformers will not use PCBs insulators and other toxic chemicals and shall be tested before installation.
- The proposed network is constructed to operate at 22kV, the electric intensity < 5 kV/m, magnetic field intensity <
5 micro Tesla Thus, there will not be any negative
impacts on local people's health.
- During operation phase, risks of fire and explosion and accidents are possible if safety measures are not cmfidly
managed. However, the risk can be properly mitigated by following strictly safety measures for fire and explosion
Support to development and hunger eradication and
poverty elimination
Improve access to natural resources
Oil and chemical pollution
Electromagnetic field
Risks of electric shock and fire
Major
None
None
None
Minor
Long-term
None
None
None
Short term
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (Em) Final Version
POWW Company No. 2 Power Engineering & Comultiag Center
r
- 24
25
26
27
Negative impacts on birds and planes
Risks of disturbing radio and
television wave or other
types of telecommunication
Noise during operation
Pollution due to domestic
waste water and solid wastes
discharged by workers and
operation staff
None
None
Minor
Minor
None
None
Long term
Long term
protection, providing workers with all necessary
protective equiprnents and periodically checking the safety equipments.
- Electric posts are lower than 50 m. Thus, there will not be any negative impacts to birds and planes.
- The project site is far away from telecommunication
works. Thus, there will not be any negative impacts to
telecommunication signals.
- Transformers shall be manufactured in compliance with relevant standards which require the noise lower than
70dB within a distance of 3m and shall be installed
according to relevant technical specifications to limit
noise.
- During operation phase, there will no be any wastes
generated. For wastes generated during project operation
phase, new substations in the project shall be constructed
with septic tank under latrine to preliminarily treat wastes before discharging to the sewerage system. Solid waste
shall be collected and disposed at local disposal sites.
Thus, negative impacts on local environment due to wastes are negligible.
No impact
No impact
Minor
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT
Environment Management Plan (EMP) Find Version
Power Company No. 2 Power Engineering & ConsulUng Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) FinulYersion
V. COMMUNITY CONSULTATION
Power Company 2 Power Engineering & Consulting Center
Result
No response
No response
No response
Received back
Main contents
Consultation
method
Propagandi by delivering documents
Notice on newspapers
Notice on public
broadcast station
Leafldquestio nnaire
-
Description
Days of notice
Location of notice
Days of notice
Name of the newspaper
Days of notice: 15 days
Times of notice Sending date
Number of leailets/questionn aires
Propaganda area
Waiting for response (yedno)
15 days
People's
Committee of cornmunes/wards/t owns in the project
Not implemented
Notice in communes/wards/t owns in the project
Not implemented
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) FindVersion
Date On 18/12/2007 and Attached 191 1212007 meeting Minutes
1 meeting 1 Committee of1 Phong Dien and Co Do \districts
Attendants - People's Committee Women association
I I - Fanner I I 1 association I
I I association I I I - Affected I I I households I
- Can Tho Power Company
Inviting method Sending invitation
Attached content Yes 1 of the meeting I I
I Contents of discussion I - Impact on air
- Impact on water s o m s
- Impact fiom noise
- Impact on cultivation and housing land areas
- Impact on socio- economic activities
- Mitigation measures
I - Responses I - Representative of
the commune People's Committee
- Women association of the commune
- Farmer association of the commune
the commune party
cell
- Officer from power supply service
Representatives of households affected by the project
Power Company 2 Power Engineering & Consulting Center
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Envimmcnt Management Plan (EMP) Final Version
Summary ofmrt ic imnts ' comments in community consultation meetings: - An appropriate compensation policy should be applied for affected land areas
which have been long used for cultivation and agriculture.
- Affected households recommend the Designer to design the lines avoiding local
houses to limit possible negative impacts.
- During construction process, the Contractor must apply mitigation measures to
prevent negative impacts on local people's lives.
- During site clearance for construction of substations, the Contractor should limit cutting trees, particularly old trees with high economical value.
- All local people expect that the project shall be implemented soon to improve the local socio-economic conditions.
- A meeting with affected households is required before implementation of the project.
Power Company 2 Power Engineering & Consulting Center
Form
, .
Can Tho province PC's
oftice, PC at district/rural
district, wards/commune
s /town level
World Bank Vietnam
Development Information
Centre (VDIC)
at building No.
63 Lf Thhi ~8 street, Ha Noi
city
World Bank office in Washington DC
(WB inforshop)
Disclosure
infomation
after implementation of environment
Management
Plan (draft shall
be disclosed in
the project area
to get comments . Then the draft may be &vised
to finalize the
EMP report)
Plac e of
osur e
EMP report and drawings of
substation locations shall be
kept at PC's offices and widely reported to relevant people.
EMP report in English shall be submitted to VDIC and
propagandized to nlevant institutions for reference
EMP report in English shall be
submitted
Estim
ated
durati on
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Menagmcnt Plan (Em) FidVenion
VI. IMPACT MITIGATION MEASURES
Table 6.1: Impact mitigation measures
No. Issues
.
Impact assessment
PRE-CONSTRUCTION AND CONSTRUCTION PHASES
1
2
Mitigation measures
Temporary and Long-
term land acquisition
Impacts on local
houses and
architectural
structures
Expenses Raponsibilit
Y
Can be
mitigated
No impact
- Organize the construction activities so that the temporarily
acquired land area is minimized.
- Reinstate temporarily acquired land areas in as soon as
possible.
- Compensate according to Vietnamese regulations and World
Bank's policies
- No Impact Mitigation Measure is required.
Included in
the project construction
and compensation
expenses
EVN, the
province PC, PMU,
Designer, RP Consultant
CAN THO RURAL MEDIUM VOLTAGE NE'IWORK COMPONENT PR(UECT Environment h h a p n c n t P h (Em) Final Version
No.
3
4
Issues
Impacts on trees and
crops
Unbalancing and
disrupting habitat
I
Impact
assessment
Can be
mitigated
No impact
Mitigation measures
- Limit. unnecessary cutting trees (trees within substation
construction area and trees within safety corridor).
- Clear grass manually, avoids using machines or anti-grass
chemical to protect natural grass as much as possible.
- Avoid burning trees right in the clearance site. Collect trees at
proposed sites for disposal. Encourage local residents to utilize plants cut (such as : grass, wild plants, branches and leaves of
mediumhig trees) for useful purposes for instant composting, fertilizing fields, ect.. .; the bodies of mediumlbig trees can be
used as firewoods except eucalyptuses having economic
values must be collected by a specific plan for utilizing.
- No Mitigation measure needed
Expenses
Included in
construction
Responsibilit
Y
EVN, Province People's
Committee,
RP Consultant
and the
Contractors
who
will execute site clearance
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP,J Final Version
Responsibilit
Y
PMU, The
Construction
Contractor,
the
Construction
Management Supervisor,
the
Independent
Monitoring
Consultant
-
Expenses
Included in
construction
w
No.
9
10
I
Issues
Alkaline pollution to
the soil
Pollution to air due to
excavation,
construction and gas
emission from means
of transport and
machinery during construction process
assessment
None
Minor
Mitigation measures
- No mitigation measure is needed.
- Make sure that all machinery and means of transport are
provided with work permit during the project implementation.
- Minimize working duration at construction sites. Regularly
water on dirty posts and dusty places.
- Check and cover trucks transporting construction materials,
such as soil, excavated materials and sand, etc. to prevent
dropping on the roads.
- Use fence to surround the work site in case of high wind.
- Do not use means of transport or machinery that emit
exhausted gas more than that specified in relevant standards.
- Sites where project activities may increase air pollution: Cai
Rang district, etc.
CAN THO R U R U MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Envhnment Mamgment Pian (Em) Final Version
No.
1 1
12
Issues
Noise and vibration
due to means of
transport and
machinery
Pollution to air, soil
and water sources
due to oil leaking
from machinery and
equipments
Impact
assessment
Minor
Minor
Mitigation measures
- All construction activities are carried out during daytime. If
they are carried out during night time, the Contractor must
inform local people and relevant parties in advance and must try to limit noise.
- Methods to limit noise and machinery causing little noise and
vibration should be mobilized.
- Means of transport must not exceed limited speed and
allowable noise level. Horn is only used when necessary.
- Regularly check means of transport, machinery to detect
possible oil leakage.
- In case on oil leakage, the leakage area must be isolated and
treated to prevent pollution to attached areas.
Expenses
Included in.
construction
expenses
Included in
construction
Responsibilit
Y I
PMU, The
Construction
Contractor,
the
Construction
Management
Supervisor, the
Independent
Monitoring
Consultant
PMU, The
Construction
Contractor,
the
Construction
Management
Supervisor,
the
Independent
Monitoring
Consultant
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Mampment P h (Em) Final Version
No.
13
14
-
Responsibilit
Y
PMU, The
Construction Contractor,
the
Construction
Management
Supervisor,
the
Independent
Monitoring
Consultant
PMU, The
Construction
Contractor,
the
Construction
Management
Supervisor,
the
Independent
Monitoring
Consultant
Expenses
Included in
construction expenses
Included in
construction
expenses
Issuea
Environmental
impacts due to discharging wastes
Solid wastes
generated during
excavation of post
foundation
Impact
assessment
Minor
Minor
Mitigation measures
- Construction wastes shall be reused for site filling (bricks,
stone and girder pieces, etc.) salvage shall be reused or sold to salvage vendors (iron, steel, etc.).
- Waste water generated by workers must be treated by septic
tank before being discharged into surrounding environment.
- Solid domestic wastes shall be collected and disposed at
disposal site.
- Quantity of exceeding materials from construction process is
small since most of them are re-used for post foundation
filling. However, the exceeding quantity must be collected and
covered to prevent dust and waste water in rainy weather.
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment ~ c m c n t Plan (EW) Final Version
Power Endnecrinn & Consultino Crntrr @ PowerCap.ny
Responsibilit
Y
PMU, The
~onstruction Contractor,
the
Construction
Management
Supervisor,
the Independent Monitoring
Consultant
PMU, The Construction Contractor,
the
Construction
Management
Supervisor,
the
Independent
Monitoring
Consultant
Expenses
Included in
construction expenses
Included in
construction expenses
No.
15
16
Mitigation measures
- Provide enough warning signs.
- Minimize traffic obstruction and ensure safety when stretching cable crossing roads.
- Organize construction activities appropriately.
- Trucks transporting construction materials must not be
overloaded. Big machinery must be transported by special
trucks.
- Reinstate roads, bridges and underground structures damaged
during project activities.
Issues
Traffic obstruction
during construction
process
Damages to local
road system due to construction and
transportation of
construction
materials
Impact assessment
Minor
Minor
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plrn (EMP) F i ~ l Version
Responsibilit
Y
PMU, The
Construction Contractor,
the
Construction
Management
Supervisor,
the
Independent
Monitorii.~g
Consultant
Expenses
Included in
construction exPases-
No.
18
I
OPERATION PHASE
Issues
Risks to health and
safety from camps and materials
warehouse.
19
Impact assessment
Minor
Support to
development and
hunger eradication
and poverty
elimination
Mitigation measures
- Arrange camps and warehouse apart from local cultivation
land areas.
- Arrange fence surrounding the camps and the warehouse to
prevent castle and people &om entering.
- Store all materials (particularly dangerous materials) in locked
sections and provide security guard if necessary. All remaining
materials must be collected after construction.
- Avoid acquiring too much land for building camps.
- Regularly check hygiene conditions of the camps to prevent
possible diseases.
- Provide means for emergency.
- Issue regulations in camps, enhance workers' awareness to
prevent possible arguments between workers and local people.
Major - Propagandize project benefits to local community.
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment M.Mgemcnt Plan (Em) Finalversion
No.
20
21
22
Issues
Improve access to
natural resources
Oil and chemical
pollution
Electromagnetic field
Impact
m m e n t
None
None
None
Mitigation measures
- No mitigation measure needed
- Although new transformers are tested to detect toxic chemicals, a periodic checking and maintenance plan must be
set up to timely detect possible risks of transfoners' failure
and oil leakage and to check the coverage and leakage
possibilities of oil collecting pit.
- There must be methods to cover and drain waste water to
prevent waste water from leaking in oil collecting pits and
pollution due to oil polluted overflowing water.
- No mitigation measure needed
Expenses
Included in
construction
expenses
.
Responsibilit
Y
Can Tho
Power
Company
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment MMogement Phn (EMP) FimlVersion
Power Company 2 Power Endnecrin~ & Co~mlt iag Center -20
No.
23
Issues
Risks of electric ,
shock and fire
Impact assessment
Minor
Expenses
Included in
c ~ n m c t i O n expenses
Mitigation measurea
- Install warning signs at risk locations.
- Regularly check to timely detect and recover electric leakage if any.
- Operation and maintenance workers must strictly follow
regulations on maintenance, operation and repair. Using
worksheets, and other administrative procedures for
maintenance and operation works. Operation workers must
comply the following regulations on safety:
- Safety measures when working with electric equipments: The
worker is properly insulated &om the energized part with
gloves or other approved insulation.
- Safety measures during operation, repair and maintenance :
Allow only trained and certified workers to install, maintain,
or repair electrical equipment
Ensure that live-wire work is conducted by trained workers
with strict adherence to specific safety and insulation
standards.
Follow local legislation, standards, and guidelines relating to
minimum approach distances
- Periodicaily check the system to detect and recover possible
failure and risks of fire and explosion hazards.
Responsibilit
Y
Can Tho
Power
Company
CAN THO RURAL MEDIUM VOLTAGE MWWORK COMPONENT PROJECT Enviro~nmt Murrgemenl P h (EMP) Finalversion
Power Company 2 Power Endneering & Consaltim~ Center - ~ n .
No.
24
25
26
27
Issues
Negative impacts on
birds and planes
Risks of disturbing
radio and television
wave or other types of telecommunication
Noise during
operation
Pollution due to
domestic waste water
and solid wastes
discharged by workers and operation staff
Impact assessment
None
None
Minor
Minor
Responsi bilit
Y
Can Tho
Power Company
Can Tho
Power
Company
Mitigation measures
- Strictly follow regulations on fire protection. . - Regularly check can maintain fire protect equipments.
- Train and maneuver fire protection measures with supports
fiom relevant bodies.
- No mitigation measure needed
- Since the project works are apart fiom communication
facilities, there will not be any negative impacts on these facilities.
- Periodically check and maintain equipments to recover possible failure that may generate noise.
- Set up natural or artificial soundproof fence (tree fence for
instance) to absorb and minimize noise.
- Wastes shall be all collected and disposed at appropriate site.
- Set up a plan to periodically observe wastes collection and
treatment system to make sure that all wastes are collected and
treated appropriately.
Expenses
Included in
construction
Included in
construction expenses
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
VII. ENVIRONMENT MOMTORING
Table 7. I :Table of Environment Monitoring
@j Power Company 2 Pnwer Endneerins & CnnsnlUnv rrntrr A 1
Responsibility Frequency No. Issue
PMU, Designer, RP Consultant, Can
Tho Power
combany,
The Independent
Monitoring
Consultant
The Construction
Contractor, PMU,
the Construction
Management
Supervisor, the
Independent
Monitoring
Consultant
The Construction Contractor, PMU,
the Construction
hhagement
PRE-ONSTRUCTZON AND CONSTRUCTZON PHASES
Parameter
When
compensating
Every 1 month
Every 1 month,
in dry season
and windy
weather
1
2
3
Locations Method
Study affected
households
Observation
Observation
Temporary and
long-term land
acquisition
Negative
impacts on
layer
Air pollution
due to
excavation and
filling works,
Acquired land area and
economic activities on the land
area.
Compensation for affected
households
Quantity of trees to be cut down
Cutting method
Treatment to grass after clearing
trees
Checking coverage of trucks
Spraying water to limit dust
along earth roads during dry season
Substation area, corridor of the line
Affected households
At the substation
Along corridor of the
line
At the disposal site
Project site and roads along residential
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMHINENT PROJECT Environment Managema Plan (Em) Final Yenion
Responsibility
PMU, The Construction
Contractor, the
Construction
Management
Supervisor, the
Independent
Monitoring
Consultant
p m , The
Construction
Contractor, the
Construction
Management
Supervisor, the
Independent
Monitoring
Consultant
PMU, The
Construction
Contractor, the
Construction
Management
Frequency
Periodically Every 1 month
during construction
phase
Periodically
Every 1 month
during
construction
phase
When stretching
cable crossing
No.
7
8
9
cable crossing road.
Transportation of construction
materials
Issue
Other wastes
Negative
impacts on
health and
safety from
camps and
materials
warehouse
Obstructions to
local traffic
Parameter
Wastes collection and treatment system
Hygiene and safety conditions at
camps. Storage of materials and equipments at warehouses
Equipments for emergency cases
Possibility of argument between
workers and local people
Installation of warning signs
Set up scaffold when stretching
Locations
At construction site, temPoW camps
At camps and
warehouse
At network spur
crossing mad
Method
Observation
Observation
Observation
a c1
g 8 Q
a L 0)
0 -0
= " .* V)
s o = g c v v + E 8
5 C
I V)
i? : W
C: 0 .-
0
B CE
5 b
2
8 z O q 1 cw V) 0
b) C) c 0
5 3 % 2 W & #
c g .g '" B r , cw - o a o b ) 8 3 % u 3 9 a s,- M -
6 c1 fi b) u
k 8 3 bo
g . . s $ c1 8 . - s o = b o g s u u + - t 8
5 6 E
V)
2 0
2
C 0 . d c1 d
M 2 b) .- c1 E
V) 8 2
s g a 5 8 . g
E .4 E 2 3 w 3 E Q b C 3
E; 2 Z & Z ~ 3 ' ~ . d 8 % g z Y h
h * O o 0 A
5 8 3 .2
$ 3 p L L
i3 J B n
8 ot
b 8 t k
3 3 d
cn s 'G 8 3
8 2 fc
c1 s E 2 5
s a = . e l s .- s r L g g 8 0 r u u + Z u
6 C
I \O
i? : W
C 0 . - 3 2: 3 0 0 & I -
0 -s s Q c1 0
u 5
.n I
'2 9 E . d 5 - 3 L 5 .; S
2
3 Y
c C ~ Y 9, .c
l . S = c J & 8.8 B:: 6 % ~ 3 E u
0
I CI(
9
3 s 8 M-.
4 a ~AL lruk - LTA ET\. --:< cc ..,, 3m.. . ROJ-\-= Environment Managemem Plan (EW) F i ~ f Version
Powor Company 2 Power Endnuriae & Cowit in Center .A<
- - - - - -- - --- - -- ---.- --- - --- --rr - 1 ! -7 -
No.
13
14
15
Responsibility
Can Tho Power
Company
The Lndependent
Monitoring
Consultant
Can Tho Power
Company
The Independent
Monitoring
Consultant
Can Tho Power
Company
The Independent
Monitoring
Consultant
Issue
Negative
impacts h m noise
Negative
impacts due to
domestic waste water and solid
wastes from workers and
staffs daily
activities
Risk of network
failure, accident
at work
Parameter
Noise level
Waste collection and treatment
system
Evidences of damages to the
line, evidences of network
failure and accident at work
Locations
Where people
complain
At the substation
Along network spur
Method
Standard meter
Observation
Observation
Frequency
In case of
complain
Every 6 month
Every 6 month
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
Table 7.2: Organizations participate in the project EMP
@ The Independent Monitoring Consultant (IMC)
The IMC shall be selected by Can Tho Power Company to monitor the EMP implementation. The IMC shall report the monitoring results every 6 month during the
constmction phase.
IMC's activities include:
Monitor activities in project site and record environmental problems, including but
not limited to these followings:
- Site cleaning after construction
- Disposal of trees after cutting down
Power Company 2 Power Engineering & Consulting Center -46-
Contents and form of teport
According to table 7.3
Page 47
According to table 7.4
Page 48
According to table 7.4
page 48
Responsibilities
- Implement recommended mitigation measures
- Report to PMU about the implementation of mitigation measures
- Supervise and assess the implementation based on
recommended parameters in
EMP report
- Report to PMU
- su~ervise and assess environment quality based on
recommended parameter in the
report.
- Hold community consultation meetings to receive responses
and comments from local people on the project EMP
No.
1
2
3
Organization
Contmctor
PMU Technical supervisor (Can Tho
Power Company)
The Independent Monitoring Consultant
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Envhwunent Manugemant Plan (EMP) Final Version
- The use of temporary roads (temporary roads are demolished or maintained/expanded after construction, how and by who they are managed)
- Impact Mitigation measures applied during site clearance and construction of post foundations, connection lines.
- Existing conditions of the botanical layer within the substation and
corridor of the transmission line.
- Impacts of construction activities (noise level, dust and damages to roads due to excavation, filling works and transportation of construction materials)
- Temporary camps and existing safety conditions at camps
- Applied safety measures (warning signs, restricted areas, fences and
isolated areas, etc.)
Hold community consultation meetings to:
- Assess the local authorities' participation in settling project
environmental problems (negative impacts due to dust, noise and damages to roads due to transportation of construction materials and site
clearance)
- Determine emerging environmental problems and record affected people's complains on environmental problems.
Submit Meeting Minutes with local authorities' certifications which clarify objection or
non-objdon to the project's environmental impacts.
Power Company 2 Power Engineering &Coasulting Center -47-
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) F i ~ f Version
Table 7.3: Form of EMP report
(For the Contractor use - executed at site)
Construction site: Project:
The Contractor:
StW date of the monitoring programme:
~eporcin~ date:
Full name of the staff:
Title:
Address : Telephone No.
No.
1
2
3
4
5
6
7
8
9
Power Company 2 Power Engineering & Consulting Center -48-
Applied mitigation measures
Impacts
CONSTRUCTION PHASE
Impacts on botanical layer due to site
clearance
Pollution to surface water
Noise and vibration kvel
Air pollution
Impacts on agricultural production due to
cultivation land acquisition
Solid wastes due to excavation and filling
works
Impacts on local environment due to workers' activities
Argument between workers and local
people
Health and safety
Remarks
I
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJEff Environment Management Plan (EMP) Find Version
Table 7.4: Form of Environment Observation report
(For PMU Technical supervisor or IMC uses)
Project:
Project location: Provincelcit y: District/rural district CommunesIW arddTown:
Type of report:
Monthly report (yeslno) : Quarterly report to E VN(yedn0):
Quarterly report to WB (yes/no): IMC 's report (redno):
Execution date:
Power Company 2 ,Power Engineering & Consulting Center
No.
1
2
3
4
5
6
7
8
9
10
Assessment of the Consultant/
Community' comments
0 bserved Parameters
CONSTRUCTION PHASE
Quantity of trees cut down during site
clearance
Noise level in attached areas of the site and in
the site
Dust and exhausted gas
Site cleaning after construction
Oil leakage level and impacts on environment quality
Workers' hygiene and safety management
Level of obstruction to traffic
Status safety measures implementation
Management of equipments and construction materials
Operation of domestic and construction wastes collection and treatment systems
Remarks
CAN TRO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROSECT Emironanent Management Plan (EMP) FinaI Version
The Consultant: Observed location:
No.
1
2
3
4
5
Power Company 2 Power Engineering & Consulting Center -50-
Assessment of the Consultant/ Community'
comments
Observed Parameters
OPERATION PHASE
Safety level of electrical system, warning
signs system and frequency of electric shock
accidents
Fire and explosion protective equipments,
service ability in case of emergency
Coverage of oil collecting pits, possibility of
oil leakage from oil collecting pit into
environment
Noise level due to transformer's operation
Status of domestic waste collection and
treatment system operation
Remarks
I
I
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
Table 7.5: Estimated expenresfor EMP implementation
Powu Company 2 Power Engineering & Consulting Center -51-
No.
1
2
3
Unit rate
-
Man-month/project
Man-monthlproject
(75.000.000VND/pmject)
Items
The Contractor's
.supervisor
PMU Technical
supervisor
Independent
Monitoring Consultant
TOTAL 75.008.000 VND
Quantity
-
Project
Project
Total expenses
Determined in
Contract documents
Included in
investment expense
75.000.000 VND
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
VIII. INTITUTIONAL BUILDING ACTIVITY
9 EVN's training: To give instructions of how to cany out Environment Management
according to EMP report and reporting method according to quarterly report or regular
report-
+ Training of Can Tho Power Company: the training is held for project operation staff
and representatives of relevant bodies or local authorities. The training focus on:
- Training on safety: focus on safety during the system operation and
maintenance.
- Training on observation methods and reporting method of the EMP: focus on how to monitor environmental qualities at site and how to fill in forms of
monitoring reports. The training also provides instructions to representatives of local authorities on roles and participation of the local authorities during
implanmtation of EMP.
Power Company 2 Power Engineering & Consulting Center -52-
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT: Environment Mamge&t Plan (EMP) Final Version
Table 8.1 Estimated expenses for training1
' Training is implemented by Vietnam Electricity Group for the whole project of Rural Distribution Network in different types of training. The expenses arc separately counted for Can 'Iho Rural Medium Voltage Distribution Network Component Project.
Power Company 2 Power Engineering & Consulting Center -53-
Training provider
EVN in co- ordination with relevant bodies
Can Tho Power Company in co-ordination with the Consultant
Place of the training
Selected by EVN (in Ha Noi)
Selected by Can Tho Power Company (at
the office o f Power
Company)
Expenses
15.000.000VND
20.000.000 VND
Totml
Startlcomplet ion date
Befire the project implementatio n
Before the project implementatio n and after the Training on Environment Management
35.000.808 VND
Duratio n
3 days
2 days
lLpeS 01 training
Training on Environme nt
Minagerne nt (EVN's traising)
Training held by Can Tho Power Company
Numbe r of
trainee S
3
10
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Enviromnent Manylement Plan (Em) Find Version
IX. IMPLEMENTATION ARRANGEMENT
Power Company 2 Power Engineering & Consulting Center -54-
Implementation
EVN
PMU, Department of Natural Resources and
Environment
Can Tho Power
Company
Can Tho Power
company
Can Tho Power Company
Can Tho Power Company
h e n c ~
Project Owner
- General Project Management Unit
Environment
Officers
Project Implementing
MY
Project Facilities Operator
Responsibility
- Take the highest responsibility of project management activities, including environment
management
- Carry out construction works, including implementation of environment safeguard
stipulated in EMP.
- Responsible for coordinating and managing the project implementation including giving
instructions and guidance to implementation of
EMP
- Take specific responsibilities and act as
environment infortnation provider.
Responsible for detailed implementation of the project. The activities include:
- Set up plan and implement environment management activities during construction phase.
- Co-ordinate with other partners in Environment Management activities.
- Carry out internal observation activities and monitor independent observation.
- Monitor and fund for observation activities.
- Report environment information to relevant parties.
- Responsible for project operation including environment management and observation activities during operation phase.
CAN TIIO RIJRAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
Power Company 2 Power Engineering & Consulting Center -55-
Implementation
'IT-TVD
The Construction
Management Supervisor of
Can Tho Power Company
The Contractor is selected by Can
Power Company or by EVN
The Contractor is selected by Can Tho Power
Company or by
EVN
4 ! e n c ~ 7
Environment Monitoring Consultant
Construction
Management Consultant
The construction Contractor
The Independent
Monitoring Consultant
Responsibility
- Responsible for establishing EMP documents
- Responsible for supervising the Contractor during
construction process and implementation of environment management activities according to
EMP.
- Responsible for construction works and following relevant regulations for the Contractor in EMP.
i. Apply impact mitigation measures during construction process
ii. Ensure safkty for workers and local people
during construction process.
iii. Follow World Bank's policies in Environment safeguard during construction process.
- Responsible for observing the EMP
CAN TFIO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Environment Management Plan (EMP) Final Version
X. OBSERVATION AND REPORTING SYSTEM
Reports shall be copied and submitted to Can Tho depamnent o f Natural Resources and Environment
Power Company 2 Power Engineering & Consulting Center -56-
V P ~ of report
Environme nt monitoring at site
Environme nt Monitoring Consultant: During constructio n phase
Environme nt Monitoring Consultant: During Operation
phase
From
-
Can Tho Power
Company
CanTho Power
Company
report
Periodically
Once before starting construction and monthly
Quarterly
Fro m
-
EVN
EVN
. From
Contrac tor
Indepen dent
Consult ant
Secondary
To
-
EVN
EVN
Primary
To
Can Tho Power Company
Can Tho Power Company
report
Periodical
IY
-
Quarterly
Annually
- -
Third-kvel
To
-
WB
WB
n p o d
Periodic ally
-
Quarterly
Annually
CAN THO RURAL MEDIUM VOLTAGE NETWORK COMPONENT PROJECT Emhnment h4amgment Plan (EMF') Final Version
XI. ESTIMATED EXPENSES FOR EMP IMPLEMENTATION Table 11.1 Estimated exjDenses for Implementation of Envimnment Management Plan
' Refk table 8.1, page 52 for details
Power Company 2 Power Engineering & Consulting Center -57-
No.
1
2
3
4
5
6
Work items
Expenses for EMP propaganda
Impact Mitigation
Measures
Supervision fee of Technical Supervisor - PMU
Monitoring fee of the independent
monitoring Consultant
Institutional capacity
building activities3
Provisional
GRAND TOTAL
Implementation expenses (VND)
Construction phase Operation p h m
5,000,000 VND
These expenses are
included in Construction
Contract
The fee is included in the project investment
expense
These expenses arc
included in the
project annual
operation expenses
75,OO0,000 VND
35,000,000 VND
Included in provisional sum of the grand estimate approved for the project implementation
1 15,oOO,oOO VND
Vktaam Rural Distribution Project
Cm Tho City Environment Mmnrgonwnt Pkn
m . References Q)
2. List staff involving in the EMP report
Q) 3. Map of tbe project sites
4. Minutes of Community Consultation Meeting
a 5. Some images of Community Consultation Meetings
6. Other Related Documents
Power Engineering & Consulting Center 63 -f c0many2
Annex 1 :
References
Pomr Company 2 Power Engineering & Consulting Center
D AN TH&VH PHAN L U ~ I Bl$N TRUNC AP N ~ N G T H ~ N T ~ N R TIEN CIANC Y K h-h qudn I$ mOi tnrbng (EMP) Sun cudi c ing
Phy lyc 1: CSc tili lieu tham khPo
C. Tili IiCu tidng Viet
1 H u h g d& 14p Dv h dhu tu Dv h lubi di& p h h ph8i nBng thbn; EVN
05/04/2007.
2 ~ h u ~ h t minh Dy h diu tu c b du h; PC2-PECC 1212007.
3 TBi lieu h u h g d h vk m6i b u h g Dy Bn truykn t8i vB p h b ph6i; EVN v$ WB 26/03/2004.
4 IC6 hoqch q u b 1y m6i t m h g c h dv h D u h g dAy 220 KV T h Djnh - Binh
Long; PECC3 2006.
5 ~b hot~ch q d 1y m8i t m h g c b dyr h.n D u h g ddy 220 KV HBm Thugin - Phan
~h ib t ; PECC3 2006.
6 ~6 howh q u h ly m6i tnrhg cua dy bn Trgm bibn Bp 1 LO KV B M Long;
PECC3 2006.
7 K& hoqch q u h ly m6i trutnr( cua dy h Trgm b i b bp 110 KV Phu6c Long;
PECC3 2006.
8 Web site c e UBND tinh ~ i k n Giang: www.tiengiang.gov.vn
8. TAi lieu ti&g Anh
9 Framework for Applying Environment Safeguards to Rural Distribution Project.
10 Environmental assessment template; EVN and WB 05/2004.
11 Environmental Management Plan of Tan Dinh - Binh Long 220 KV
transmission line project; PECC3 2006.
12 Environmental Management Plan of Ham Thuan - Phan Thiet 220 KV transmission line project; PECC3 2006.
13 Environmental Management Plan of Binh Long 110 KV substation project;
PECC3 2006.
14 Environmental Management Plan of Phuoc Long 110 KV substation project;
PECC3 2006.
Environmental Management Plan of Rural MV Network of Ben Tre Province.
K& hoqch quan I$ m6i t r d n g 53
Annex 2
List of Staff involving in the EMP
8 Power Company 2 Power Engineering & Consulting Center
Annex 2: List of staff involving in the report
- No
1
2
3
4
:5
6
7
8
Names of Staff
Nguyen Duc Trung
Nguyen Dai Luan
BPI Van Sang
Ngayen Homg Lam
Tran TLanh Long
D.0 Cong Tan
Nguyen Ngoc 'C'boai
Lc Cao Tbanh Tri
Profewional
Enviromental Engineer
Electricat Engineer
Envirommtal Engineer
Enviromental Engineer
Electrical Engineer
Electrical Engineer
Electrical Engineer
Electrical Engineer
Position
Team leader
Member
Member
Membet
Member
Member
Member
Member
Notes
V l r b u Rmrd Dbtribution Project
CrIkci!y Envlromrrmt Pbn
Annex 3
Map of Project Site
P o w Company 2 Power Engineering & ~ o n s u l t l n ~ Center
p u r n L t=rci Oic&& * ..I UI
1 (, C ( 1 .-
A,.
Figure 3: Plan of Existing electric network in CoDo district - CanTho City
Figure 4: Plan of proposed electric network in OMon district - CanTho City
DIA DU L U ~ I DIEN ~ I G N HOU QUAN CAI RANG - 'TP C.
. I-/.. , *+I. "
-- -- - - .-
-A
Figure 5: Plan of distribution electric network in CaiRang district - CanTho City
Vhbrm Rvml Dbtrlbutlon Project Caa Tbo City Envlronmnt Mnnrgomont Pkn
Minutes, of Community Meetings
Power Engineering & Consulting Center @3
R I ~ N 5hJ H Q P THAM VAN CQNC &N<;
tldm nay, nghy 19 thjrng 12 niim 2007 T$I t&n p l ~ b y I !RND h u v b Phong th&, 7'p Ctn mu.
ChCrng bbi &n 41 dl& cb ca quan. ban nganh, drran thb. td cl ik x l WI. a n dim cC, h n g danh k h dinh LPm.
Salt khi nghe dqi &@I cica Urn Quua 19 Dv iQn then lyl- nlkn Nan 1.~1 I ruuy 1 Am 111, V&I ~b D i h trinh bay t h 1141 dung u& Dy in diu hr v i K$ howh tfQ bu t i i din11 cv (RP)
aha b lu6i dl& aung ip h g thbn fp.rBn *r)l(r, Chdng tci~ ci, cac 4 LiZn dong gcip nhu sau:
w wbE@n BUD QLDA @H#m )1Cc adbn Nam Trrng TAm T r ~b TafCt K& wm *
( 0 ~ ; tioA s.i H~)I CHI' NCH~A \ 1y.r h,\h~ thjr L3p - l y Da - Hqnb Pbuc ----------
B J ~ f f t h HOP TtlAM VAN CQSC D~N(;
m: Dong p6p cac hi& cw cac rhwh ,in vti K; hoqch dl d b t ~ i (il:~I! cu ( R P I crla cic khu vw tbwjc L ~ U an Iir+ri d14n rrlurg ap nimg th6n 'Tp C'h I htr.
H b nay, n@y 18 tlrilg 12 r~am ,017. 'Tpl v h pphbng L:HSl.I hu*n ('ir th. Tp ('in m.
C h l g vbi g h &i di* tie cu q- ban n&h. doan th6, th chur ug tl(ji, n h h & & trongdrah*hdi&kim
Sau kbi nghibc dw dl6n d a Bm Quh 19 Dv h Di4n 1~ m~cn ham va 7 rung T h Tu V ~ I I I%& K& DiH trihh M y t b till mjt d u g v2 Qr &I dhrr ru up Ki. hwgch d& hir tai dinh CK (RP, CUP DV ;in Iwh ditjn tnuly ap n6np thdn Tp.C'L1 Th7. Clltiny ~31 cJ ric y k d n J6ng gop nhu srw
--- --_-. - ----- --- _____._ _ _________*_____
CU& trgp kbt thdf litc: . . . .. . . ... . . giir chng ngiiy.
eri dm w diOn Ban QLDA M#Q lye &n Yam 'rrung 'I'Pm Tm vin ~ b r k Kd tM$q -&
Bid wn UBND kryfn Cb CM
~ l k 3 B.4N HQP TH.4M VAN ('QNG WIN(;
C k $ kidn thtic I ~ & C v i dmg gc>p cllil ct31tg 3;)n.g KI? bcqch q w ~ I$ nrk irtrcyng (EMP) cri;l c k Khu v p th@x hn lucii ttiCo rnlllg iy rdng t3~311 l pi 'an I ixi
: 08 ghj 30 phi1 , nglky I0 thing I,' ntim 2C107. VPn phong, UBNU huytn l'& Do. l'p. C&I 'I'hcr.
M: d m 4i 3 i ~ c L w yuan. bw n g h . d o h the. d chuc u& Irih. nhin &\ co rrong dah nkJl &ah k h .
w b u U ~ U tu Dl, h lu j l di)n [rung $ ldng t h h I p.~7:h rhcr trinh hay ~ 6 m &t Mi dung otiaD\r b.
&I d i b T m g T b Tu v$n nidt ki: D~en trtnll biy tom tat b&o cao Uhlh gia t L d w
giai dogn clla ;in : 'fi9n x&y dung, x%y dwg va V&I M h I ' r ljc &np m61 uvQmg cth l3y k g h c k I*: Nhh bj ga t h . hi ch~&n dyng 84 tdng cet v i hinh hng wyih ciy chi tlbll$ k h 1aug tuyk bi cbet Iw bpi - tikg :>n r k thbi - x d ~ tndn - 6 nhidm n&m nu& do v$n chub nguyh v@ litu rh tlu c h y , d i Q tir tnrhng tot nuti di4n ro n dhu nldy hi$ iip tmnp giai dopn vgltl hiin11 va rac: anh h*g VC! mgt xxB h6i v a la ngitykn khL.
Ck dql biCu tham co cilc j. luCn dl& mk. dong gup \.;I I ra Im r~hu a w l
-----_-- --- ----.I-----__------------.-.----._- .,-- ______- __.. _ _ ------------_-----1------------*------.- .-----------------------.----- ------------*------.--..----,.-- * -----..--
C* hqp Lh thtic liic ............ gib cung n@y.
wdle 01. QLDA d n Nam
Dpi dqn UBND buyQa <Ib W
(Cbr ); k i h t h k kn& va dbng gbp m~a d&ng vC KC hqch qruin Iy moi tNimg ( M P ) cira cic khu v\rc t h e Du in l~mi di* [rung Q nbng than f p lhu.
: 08 gjir 30 phut , &y I Q thing I I n h 2007. . V h Wng URND hu*n Phong ~ i h Tp. C&I 'Illcr. m
&: a m dgi dien cL cu qan. ban nghh. doh chi, ti) rhirc x5 h01. nhhn d&-~ co trooy 4rabs&Mohkipl.
n6idmgCdaUyh. Dgi dib Tnmg 'I'm Tu v h TttiCt k2 D i b trlnh My lorn & btio cbo dhh ~ I P & @ng
~ ~ ~ & r n & t j l ~ ~ ~ ~ ~ r ~ ~ v ~ & b i ~ p h a ~ ~ ~ u ~ n h h ~ ~ m p 0 3 ~ r i ~ & ~ y h : ~ & x f l ~ d y a ~ . r i ~ d c m ~ v i v ~ h t a h . ~ ~ ~ k ~ ~ m d i ~ ~ c b ~ ~ \ ~ &ng&mck I*: N ~ B bi ghi ~ l a , d a l bichiknd\pypbC t t h g c @ v ~ h g n h lang t u $ n , ~ & ~ c&i whbblssQ& bi ch&hq, byi- ri&ngh-krlr - xoi mh-- b n h i h ag& nvc'rcdc, % +)$A v$t Beu va thi cbng, di t i ttlr mtiRIg - tat d i b - ri, n r&u mnhy hi& iy, aonggioiQerPr~t3mhvBckBnhhuCm~vi~xihfiva~nguyr?nkhic
~lcdgib&dum~a&cbykiknthk&.dh~~6pt.i,na1bmnhrrsrlu: - _ _ _ l _ _ _ l ~ - _ - - _ - _ _ _ ~ - - - - - - - - - ~ . , - - - - - - - - - - - --.- _ _ _ _ ._____ ------ ___. _&__
Dqi dijn UBND Luyfn Pbong ~drr
B&N BAN HQP TWAM VAN CQNG B&NG
Hbm ary, n#y 18 12 Ram 2M7. Tpi vbl pBbng UEND hu* C6 tM, Tp. & m.
C M q Ibi &I &i d#n c& w quan, ban ngAah. doan ti&. 16 c h k xi[ W, nhb d4n c6 aoagdBuh*hdkJlktm
Sui khi ngbc &i d i b cim Ban W n 1y T)y i o fh& lpc mi& &am vi Tnmg T h 'k V h Tbdt Id Eh& trlnh My t h tiit nQi dung v& Dy in du lu v i K& bwh d h W tiLi ddjnh cu (RP) c h Dlt ia W difa trung &I n6ng tMn T~.C&I Tha, Chbg ~ b i ci, c8c y kien Qi#rg g6p ahu mu.
BI&N Bib4 HQP THAM VAN CONG B ~ N C
rdiQYlPQ*QVbR ~ @ ~ ~ P r n ~ u v h % e t k b ~ a t n b ~ ~ r n & b 0 l , & d b r h g 6 t i c ~
~ ~ b r o ~ o b t 6 c ~ g d a r b n g v i c l r b i ~ ~ p g i b m & a n b h ~ g ~ 0 3 g h i ~ c ~ ~ D t r ~ a : ~ i h x & y d m xPydyngvivbh$lh.Chbbc(t6n8mbitruhg&Dy ( . & n & b @ : N U b j j d i k d Z G c b i b . r 4 . U d ~ & g * t v i h h h l u W t ~ w o b i ~ h j s i h ~ b ) - C n b j c h ~ ~ ~ ~ 1 - - t i b ~ h n - r 6 c t t r s l i whmtm dnhi&nn&nmk& V$I &uy$ nguyCa vi)l lieu va thi cbng, dita tit rmimg - " UI nw den - ro n dh tnhy b i b hp ~ ~ ~ v & ~ n h v i c ~ o c b ~ 1 ~ . v ~ ~ m 8 t r 0 ~ i v ~ t i i n ~ y ~ a 1 c h i f .
~h&i &than1 giadchcjkiihr ~ & , ~ h g g 6 ~ v ~ a ~ h % n h u w : - - . 1 - - - - - - - - - ' I . - - - - - - - " - - - - - p - - - - - - - - - - -
---.--.-.------------------------ 19 -
..,,,,.,
j:'
Cu@ hgp k& thuc luc . . .. . . . . . .. . giu c b g nay.
c:QNG HOA l i ~ l C H ~ N G M ~ VICT NAM ~ ~ - T ' ~ M - ~ b Pb6~
m: ~ k ~ k i i n r h i o & v i d 6 y l y 6 p ~ ~ ~ & ~ d ~ 1 ~ ( ~ b ~ & l ~ & ~ $ (EMP) c k t cgc khu vvc t h 4 c fh$ h l h d i h trung iip n h g thbn T ~ . c ~ nlo.
-_U--~---~.---------------.--.---.---.-.----*--------.---.-.-------~*---._----__-~*.-.~_--- --- i i - b v - & L - + l w + - A i - -
,.I . _ , & k . - ~ i ~ & 4 L & ~ , ~ - & ~ - a . - ~ & : + ~ , ~ ~ i:'
I
L..
L
..,. . , ' , .... : . ,- -. ...> " ^ . j : . ; ..-w.
I:.
, .. 3
/
DANH SACR 031 B&U THAW DV C O W HQP THAM VAN cONG d b T W
omh k&n thao: B i h bin &c tlup ngsiy, 20 Mag 12 n8m 2M7. Tsi v h phihq UBND h u y b ~ Cb Dti, 7'p.rh Tho.
7 T h h h p h h xl b$i I lif tPn --
Ap TNCmg Thanh A, X B TNbng ThAnh. Huyen Cb D6
TI. 1 Hq vh tf a
I . Urn Van Ngoan
1.
3.
4.
T& ~ i k n Ta
LBThjTAm
LeTM Mum
p q 64%'" I
t'
~ j 2 / L L l i & 7 . - c.. .#p c- -
,,*i, [. - ., ,.('I + ' a $ ,
-. f - I
i . . +
i 3 .* !.-- - ,- , ,;* __--
<--
. Ap Tnrbng m n h A. XB Trybg TMnh. Huyen Cb Di,
Ap TnrCIng T W h A. Xa TNbng 1 Mnh. Huyen C;& t)o - - " - . .- -
Ap T W n g Thqnh A, XB Tru&ng ThBnh. Huy4n Cb Ek3 - - - - . ..... - - - - - - .. -. .
Ap Trvlrng Thpnh A, XB T w h g ThBnh. Hu* C& Dd - - - -- - - - - . -- ? - -
Ap TnrCmg Than), A, XB Tndmg Thhnh. Huyen G3 D6
Ap Thtbng T~@I A, XB Tr- Thhnh. Huyen Cu 06 - - .
Ap Tru&ng Thmh A. XB Trwhg ThAnh. HuHn C& Dd - ---
r
:,, !. - d, c
, !...-t- k ~ " ! ! $+
I I
.-/i 4;:-
-6
.
- -
. - -
I
5. 1 Ngu& Thl Hibn
10. Nguyan Thi Bdy IT- T.Il A, X. T W n g W n h * Huyen C ~ Y Dh
I I . ' Qang Van Hdi
Ap TnrCmg Thmh A. Xa Trwtmg ThBnh. Huyen C u f)6 - . . . -- . - -
.
b.
7.
8.
9.
12.
13.
. . . -- .
L&Min)r NhW
Lt lV i lnQu~
Ng6 Van TBm .. .
f)o8n VBn Liet -
Ap Tnt&ng Thqnh A. XB Tnrtvng ThBnh, Huyen C& Dd .. - - - - - - - . - - .
Ngu@n Thi Hweng Ap T N n g ThQnh A. TNCvng Thhnh. Huyen CCr fM -
06 Th! Hbng I rb ~ ~ a n p Ybnh A. XB T&ng TMnh. nuyen C6 W I
1 I 7.1 Nguy6n Van Nhdi Ap Trvbng Tho. X(r Tnnhg XuOll HuyW C& 0 6 . - I I
guye en Van Chanh
Nguyen Van Nge
Pharl Tung Em
.- - ..--.. - Thhmbphbfib4i 1 K j --- (8s -
,/' . - 'a, .;/' +
I ,I- i d . , < - *- -.-- .-. -.p
I ----.- ..-
Hg v i CQn I b/r ehii
Nguykn VBn Khau
LAtn Van Chubt
~ g u y h van ~s
14.
15.
16.
Cao Van ~ A r n
guye en Vdn Kh&
Nguyen Van Chdnh
T r h Thj lqi --
SonViln Nhylt
Nguydn Van Oet
Ap T M g T b , Xa T m h g XuBn. H u y b CtY E)b
Ap Trubng Tho. Xi3 Twtmg XuBn. Huygn C& 06 i . -
i Ap Tnrbng Thg, X 1 Truhg XuAn t luyen Ctr 06
Ap Twang Tho. X D TNtmg Xuan. Huyen C& 06
Ap Trtrbng Thg. XB TnrCrng XuAn t-illyen C6 0 6
Ap Twbng Thg, X 1 T W n g Xu&;. 1 iuygn Cb Dd
b Tfuhg m n h A, X8 TNerng Thknh, H u m Cb fM ----- - - - .--
Ap Tru'&ng Thant~ A, X3 Trvhg ThBnh. Hu* CS Ek3
Ap TNbng Thg, Xii Tnn?mg XuBn. Hiry4n C& 06
1 211.1 Nguydn Van Anh Ap Tnrbng Tho, XB T w h g Xuan, HuHn C& 06 I .- j - ----- - -
~guykn Van Chum - - . - . - -
Nguyzn Van a n . -
Lam Van V ~ n g - - - -
Nguykn Van La
Lam Van Ta
Ptran T ti[ Manh
Ap Tru&ng T~Q. Xd Tnr&ng Xcdn. HuHn Cu 0 6 . . . . . . . . . . . . . . . . . . . . . . . . .
& Ttvfmg Thg. X8 Tn~bng XuBn, Huen Cir 0 6 - . - . . - . . . .
Ap Truhg Thg. Xi3 f nrdng XuAn, Hu*n C& 0 6 . . . . . . . . ......
Ap Tru&ng Thg, XB fnrbng Xubn. HuHn C& Dd . . . . . . . . . - .
- Kj tPr -...-- ....
A'
--$":/ti i'l , I ) ...
> -
**I,!; h-'
TF
29. " . 30.
31.
32.
40. ; ~ g u ~ i h Van An I Ap Trv- Thp. XE Tnrhng Xubn, Huym Cb Oi, I I :I r
HQ v i l i m
Nguy6n Th/ tan ......
%uy& V&n Thw -- . *
~ 6 ~ b n g ~ v a i - - -
Huynh Hung Cdmg - -. A i '-.I - -
41. L e Van Ni i 32. ' ~ g u y & Phi Hung
. - - - i 4.3. / ~?)uy&n Van Tarn
ui. &I T w h g ThO, X1 T w b g XuBn, Hum Cb D6
- - --- - - - - - . Ap T h g Thg. Xdl Tnrtvng X&n, Hu* C& Db
- - .-. - -
Ap TnrCmg T ~ Q , W Tnr&ng Xuan, Huw Cb Ob --- - -- , - - - -
Ap Tnrbng Tm, XB T&ng XuPln. tby$n Cb €k5
TI- p l d m x i h@l
- - - -
-
- -
Ap Tfubng Thg Xa Tnrbng X~lbn, Hu*n Clj. 06
Ap Tw&ng Thg. XB Tnr8&ng ~ L I B ~ Huy@ Ctu Db
Ap Tnrdng Thp, XB Tnrbng XuBr.. t-luyen to Oh
)I. :.-
( i l , i . .
-,I[,& L -
17'
I 44.
! 45.
- Thhh d m r l b&
" . - -
4b. Le Mnh Tam I - - -
47.1 ~ r s n V h Em 1
421.1 LB Thi Ch&u i . -
40. I ~ ~ u y a n V h 43- 1 St t . I Vd Hdng Giang
5 1 . 1 Nguyen Dirt Trung
52. ! Ng6 Hbng Lam i
53. i Trhn Thanh Long
!
Ap T W ~ Q Tho, XB Tnrbng U n . Huy@ C& 06 . - . - -. - - - -- -. - - - - - -. - -. - - - . .
Ap Trwbgj ThO, X8 T d m g X d n , HuHn Cb Od - 0-- -
Ap Tnnhq T b, XA TNbng X u h . Huygn Cb 06 . .
h@ TwMg fhs, Xa T r u b g X d n , H u y b C& 06 -. .. *. - - - - .--
Ap TrvlCrng T h . X B T d n g Xuiin. Huyen Cu Dd - - . .
Trung T h Tv Van ~hidt KQ Di4n
Trung T&n Tu vi$n Thibt Kd Dien
T ~ n g Tam Tu VAn Thibt K& Dien
HQ vh bh.
TnvcrngvTv - .-- - .
L ~ ? V B ~ T M ~ I ~
i - .
54. ' LA van Nam Trung T h T w van Thiet KQ Dien i -
Cai
Ap fnn6ng Tb. XB T nrCmg XI&. Huy4n C& D6 - -- ----- -. "- . - - -. - -- - . ~p ~ ~ b n g ~ h g , X& tnrhg Itdin, HU* C& M
. -. - - * -. -
3. 1 LeThiTAm - -
4. t6 Thl Mum
5 . Nguyen Th! Hi#n
( Ld Minh Nhyt 1 . -
7 . I Lh Van Quyt I
s J Ngb Van Tism
0. : OoPn Van Liet I
Ap Trwbng Tbnh A. X6 Trdmg Thbnh, Huy6n C& Dd
Ap Twbng TMnh A, X8 Tnrbng ThBnh, Huyen Ctr €33 . -
Ap T r n g Thgnh A, XR Tnrbng Thhnh. Hu*n C b Dd . - -
Ap Tru&ng Thpnh A. Xd TI wulry VIAI~I~. H ~ ~ I I CCI flb
Ap T m h g Thqnh A, Xa T W n g T M h , Huyen Cb 06
Ap Twbng Thenh A. Xa Trumg ThAnh. Huygn C& Dd
Ap T m h g m n h A, X8 Twbng Thhnh, )tu*n Cb Db -. . . -
I 1 J. Nguyet'l Thi 88y Ap TNLrng Tbnh A, M Tru-bng ThAnh, Huy(Sn C& 0 6 I - .
I 1 . . Oang Van Hii Ap Trubng Thqnh A, Xa Tru&ng Thbnh, Huyen C& Or3 C - 1
12. i Ngityen Thj H w h g Ap Tmbng Thgnh A, X% Tr~l~wng Thbnh, Huyen Cb D6 i I i
f-
0 0
$2
I 4
F..
?-
e =
c 2 4 i
I0
- - -.. I
f \
!
3 ! P '
\ ' . -- 2 d -7; j - . . " 4 ..- -;s - - , < ! 4 %\ ' - XI +
y - ,, - r't . - -
,'$J -\ .. - -+ . d 3 ' \ C .A
4 * - - . ---.- - --_----l_
-
4 4 2 4 4 4 4 4 4 4 Q Q Q Q Q O Q Q Q
P F c
Q h Q . 0 . Q LZ Q C c C c n n f f ' f f f a a z " % f 3 ? ? ? 2 3 $ Z $ ? ? ? c = = & G = - & = ? t k c - m ~ l g ~ d g s a =
. = . Z r 7 3 x * ; i 3 ~ 3 - .- - .- m 5 p : a @ : :q rn ?! i3,3,0 (3 0 0 0 0 0 c 0 0
2 z : 2 9 g g 2 , 2 2 2 2 2 m k i i i . i i s. r a"
C C C C C C C C ~ ~ Z ~ i i i Z Z i G i 5 Z S ~ .- 5 g g p p . s c y a .- E ~ E F , - + ~ + E E ~ ~ g k < I ; ~ i ~ ~ h ~ r r ; c r r t-4 5 7 l - R T - 4 4:- 9 4 ' Q =a 4'4 -0 *O *O b - ~ k - l b - t- I- + I- t - : k - I- t- I-
2 2 2 8 , 8 8 2 8 . 3 8 - 2 2 .---
3 ;id Q .- =I 5 0 = , Q
m ; ~ r ~ 5 a Z c c r C 2 4 c c p , -a Y Q - ~ S , 9 5 9 9 9 & c .-. C C C C % % ? + ' g #g .... #'% , > ; g - 3 S E $ a g Z " g g g 5 2 3 A ---- --- --- -- - .- - .- - -. . -..---- .
- - - - i 1 - r~ r7 -: ~ r , 2 r . .f, ,? - - - J
1
, I
,
1'
4
C
C C C C C % ? ? ¶ i % * Q Q O Q , a O
C c
n
- - - - - - -
' 2 9 2 $ $ 2 2 2 2 3 2 2 2 ---- ..-.-. -.
en
, 1
*
______"_ ______._____I <I_ ..l___l_-.- ---.- x-- - .----1- ------
.----- ---- ----..---- .--
ii'
,;
K$ @a TI' Hg vP tea
2s.
2
1 .
3 I .
. . Db chi
1 1 Ap TrcPbng Phir I, XB Tnrbng Long, My@ Phoclg Dtbn N@VBnL&c ! - .
Huynh Van D8ng l$p Twimg phi) I, Xa TwiPng Long. HuyCn Phong ~ i & n i i
Trbn Van Hai ! Ap Ap Thq It, Xa Twbng Long. Huyen Phong O h i
~ r b n van N&I f &I Ap Thp tl, X& Trw&ng Long. Huyecl Phong f)&n
I
p- )~J*,-L. 4 -kc +--
".'f--- I & i
Think pL(u
x i w
- -
~ 2 2 '- - >- -thh& caul
k 2 4 &
2 I;+ &=t iCf
--
LF~ ,be I ?l.* -
/
Ap Ap Tho I I , X8 Twbng Long, Hum Phong f)&n
Ap Ap Tho II. X0 T h n g Long, Hu* Phqng DiQn
A.p Ap Tho II, Xa T W n g Long. H m n Phong @An . - -"
Ap Ap T ~ Q II. X8 Trvbng Long, H U M Phong DAn
Ap Ap T ~ Q 11, xa ~ w h g ~ong. HU* ~hong ~ i h
-3 2 , I Nguy&n Van Tri i
33.
34.
35.
36.
Nguy&n T Thanh Loan
T d n Vgn Bdy
Nguyan Van G&u -- .
Tr$n Van Ba
3 7 .
38.
39-
Truung Van Sang
Trwng V h Tbt
LOThiChlnh
Ap Nhcm L& IA, Xii TT.Phong a h , Huy& Phong O& - --.-
kip Nhan L# 1A. XO TT.Phong 4. H u m Phong ~ i n
Ap Nhan L@, lA, XB TT.PIIIAI~ H U ~ I Pfwy D$n
Ap Nhcm L& lA. X0 TT.Phong Din, khy@ Phorrg f)lQn . -.- - . - - - - . . . .
b Ap Thi Tw, XB Nhm NgMa. Hu@n Phong f l h --
40.
4 I .
16 V W Nsm
Nguyh Thi Thanh
C I- C - C C
Annex 5
Some 1mages of Community Meetings
Power Company 2 Power Elrginceri~g & Consulting Center b
Annex 3: mme Images or community consulranon meenng
1. Phong Dien District
Picture 1: Preparation for community consultation meeting
Picture 2: Representative of the representative of Power Engineering Consultant Center is reporting the summary of Project and Resettlement - Compensation Plan and Environmental Management Plan
Picture 3: All participations discuss about the issues concerned to Environmental
Picture 4: A representative of Power Engineering Consultant Center is explaining the - -
contents of EMP And R P
Picture 5: A representative of Engineering Consultant Center is reporting the Project content, proposed options for routes and scale for investment.
Picture 6: Sharing opinions in community consultant meeting.
Picture 7: Stakeholders vote "Yes" to support options of Project in community consultant
meeting.
2. Co Do District
Picture 8: Discussing about the Project content.
Picture 9: A representative of community is stating his opinions about the contents of EMP
and RP.
Picture 10: A representative of Power Engineering Consultant Center is clarifiing the
contents concerned to the Project.
Picture 11: Resident is learning about the information of proposed options for rou tes.
Picturel2: Vote "Yes" to support the Project content in community consultant meeting.
Wllur R.nl DMrlbutka Project C a I k C y I Envl--Pbn
Annex 6
Other Related. Documents
Pbwer Company 2 Power Engineering & Consulffng Cenler
J.4 ~ h h t th&i ktiac: C6ng uic din bu giii ph6ng rn@ bing rl! c o chat ti4 cui tret, ttiy611 d t t~ng
iy &i qua nOn sE nay sinh vAn d$ v& thu don coy cui. \'i& lieu huy ndy ch th6 gay dy ho$c r&c &hi. Tuy nhiEn tiic dGng tidu cuc nnBy la kMnp dimp b2
! Cbc tbc 6ing khhc.. X6i mbn &t khi chi t;to v3 phat tri& Lu& di+n truny iip la r;it nh0 do chi m$t
-yt co th& &y xbi lu ia dbo va lap mong cot. I uy nhien m6i mong cgr vui thi b BhBng d h s ~ k5, c6ng trinh n h a khu vyc d6ng bine va duw thw hien trong
r d a kh6. Khdng u6 sp thay d6i rnvc nu6c b6 m&, nuric dub^ dit, xiirn nh8p man, x9m
ip phh; SI,I b i b ddi vi khi hau; SI,X suy thohi chc thinh phan mrn truuuirng; sg bith 101 Ua dgng slnh hqc vB ciic t6 l;h6r.
pH.&' G I ~ TAC DONG f l d ~ CV'C
~k boqch g i h thiiu cho du in Juqc ti& hinh nhu sau.
- -. . -. .. -. .. .<- - . --- .. .. . .. .. . .. . - . - - ~ k w m6i Clic biin phap giam thiiu I' t)m ki chju !
--v.-- - '--I . -- . trhch nh@m ! -- - .I EG-CH1.Ii" BI Ty CO*G -.-- nhlnzihgdilt - Thi t k6 tuyCn dubg diiy c b g anh huimg it ! EW,
din d6t dai chng tht.
I thibt k&.
r / UBND Tinh , I - D& b l cho chc sb hRu t h n quy dinh cila 1 vb nhh thdu :
... - . -- - .. - - - *. - -- -- -- - - i - 1
' c i y a thyc vgt. : IjBND Tinh '
i - D&XYI bio cay c6i dubi do cao @u chu (4m) I vB ciic nhh - Thvc hib quy trinh an toh in* t r h h bi ' tbhu thyc h u n g do car dB. hien cdng
I - Gotn ely do t$ b3i riic dy kith. , t i ~ c GPMB. i
i - 43th bu cho chc ho bi jnh hui~op theo qu) I I
dinh clia phap lust I
---."- - - -. --. -- -----. -- -.. -.r --' I vtm hod ?T~hi&t kd tuy6n d u h g &y &anh di qua ehc i h?lP - thau ' vimg ahpy c h ~ , wing c6 gi6 tq lich sB v8n 1 thi& kk va / h06. i chc ccu quan
- KC^ hqp cac thii wc lien quan dkn viee x6c hitu gum ; nh&~ vB giai quy6t cac cb v& mang ti~lh v in
I I - .-...-- ho,&ljch sir h6t hi$n trong khi dio. ,-..- -.- - . -- . I -- ---.. - .j it n8 t--" Ph& thqc hifn d pha born min 66i v6i p h b 1 Nhrt th5u ; ' mong cot, h h h hang t u y h vA c i c dtrhny tw ) thvc / h cdng (n6u ?aybn Uu*g diy Ui qua khu \yc j cbng tk
ci, born min). ' GPMB va cc~ I
4% phumg.
, N, N H ~ I CAE N(;u\'&K, NHI&K LLCtf st!' DI,l?(G
4.1 Danh myc nguyen nhitn vgt lieu Th1 & c.j, v$t lii$c, vh thiet bj pliyc v!~ r;ho du an d2\1 ducrc s3n x i ~ i l tlii tic
& mmiy C(I qu y oinll s i n in& b 6 nghiem ng3L bao porn c;ic phu ki& s lu : CP hi. , r i q l y t r h duc sin. d i y dien bing dAng h o ~ c &ern. xi tt~ep. sir -5 & nguy2n v$ lieu M n duqc ch; Qo sh chi u@ uhuybn tir nui s8n .nit & cbnp tiinh b h g xe 6th
~ ~ u b n vat lieu xiy dmg c&c mbny tqi d i h nhli xi mdng. sbl. u i ~ , sqn. neubri , n&y dm cung c$ tu c L m sh kinh doanh. 11l l i miy.
42 Ph-g thirr v@a chuy&n, cung cLp v l bHo quan oguyiin ahiEn v@t lifu CBc v@t nr thikt b/, nguy6n nhih lieu d ~ c v$t chuyen binnp 6tB dn kho bii
Kho b5i chua nguyin vat Ji$u duqc thui tgi Lrung tam c6c sil ( s i n IIljND. dp, i h , chc kho bi?i duc~c xB> dm nrtnlg rho hno qumh, nth YI
Trong qui trinh v$c chuyen xe 6 tB phi1 rhpc hien c5ng ttic che chiin. ring E&l th@ trdnh roi vai, rla 4 ph=t iinh ti& bn vi hui.
Cbng tk. bho quin d c hi& bj, n p y h vat l ieu theu ciic qu) d!nh ohune chinp & & quy trinh tieu chub hi@n hi&. Trong qu6 trinh bin qiian chn che. chdn kh6 & &@ Wnb khd nwg thit tho&. hu h6ng thi sh Nhh nuirc.
'
4 3 Ntru c$u vri nguBn cung cap dien, nvdrc: ViC c6ag nhh r5ng lrong lhn tr@ st2 130 m laqng nuhc thal sir& h o g tuy
a W n g gnh hubg nhih d C d r n ~ nu& vi s l c ~ n g dnhin ir i6n tr+i nit it. ..'B& difn s6 d p g chc y6u IB cho sinh hopt c h c6ng &in s6ng trong lirn triii.
. . v. cAc TAC WNG MOI T R U ~ G " 511 Cbc loqi chit thdi phat sink
5.1.1 KJii thdi Viec xby dwg rnui vh cki t+o hrbi dien trung hp se xu& hien mot luwg bvi
Chc xe t& v$n chuyhi nguyin vgc lieu sC ghy ra nWBn bpi chinh, &c biw Id v b miia kh6. CC xe t8i niy c b g st? tiii v8o hong khi mbt luqng chdt Mi
en, nliirng tiic dQng nLy oiing GO th6 @dm dugc,
b n h i b nuck trong thiri gian th~ cBng la khbng Bang k6 do 3 nguyen nhiin: - Thbi gian lip dmg cOt dien ngh, kha n h g dong chay mat mane, theo dh
dd hb dBo ra khoi, s6ng suai IB rht nhd. - ~ h i i u sdu h6 mong la khohp l,Bm, do v@y khkng giiy hb hvhg din hg
- S& &g & s h e tmng Ih upi kho- 30 ogrrui ndn ciing kh6np giy 6 ngubn nu6c v i Bnh huhg ding nu& ng%n.
':&I3 ch6tWrb T40 d&lg chk €Mi & do dlo mong vd 14rn mdng cQt &PC xcm M ah6 vi chl
~ ~ i 4 c b i o ~ ~ ~ ~ ~ c $ t . ~8irn6ngci)tcbib~ 1-2m v&d&~bdodudupc !*hd* e * c b t .
CQNG HO-4 HQI CHU IVGH1.t VTET N.4M D@c I$p - Ty. do - Hqnh phuc
---- .o( I<,--. .-
BAN CAM KCT BAO I~$ M ~ I ~ ~ u r n ~ - ~ N G TIT% CBUNG
dv h: ih t b h phih lu6i dien trung i p nbng tl~hn '1 p.Crin l'hu. T&n chfi &u tu: CBng ty B i b luc 2.
chi l i h he: 72 Hai Ba Tnmp P.B& N@C, ().I. ' I t'.H('S<t. .* Gj$m &: lu'guyb T h M Du y. - .Hmcmg tien liiin lac: Td: 08.2200341 ; Pax: 08.2200342.
B&M THV'C Hl$N DV' AS' en trung rip n6ng th6n I'p.C'&l .l 'hrv rfuvc ~ r i & khai ~ ~ ~ t h i trb that 06 q u w h ~ ~ e n : huimg: Long ~ u ~ k n . Long Hoa. l ' hh An DBng.
: Ikr* Cb 96 gbm c6 02 x3: Tmhg X u h , Tnrimg WI.
- 6 ~ ~ n ~ a r n 01 phutmg: 'lhcki~a.
h y @ Phong 0i6n g8m 03 x l v i 01 thi tdn: Ciini Xubn, Nhcm Nghia, T ~ h g Long. Uj & Phong Eli&.
- Qu$a CBi Rang g6rn 02 phubng: Phu Thu, Ba 1,hg.
*. Ikryen Th6t ~ 6 t gAm 04 a: Tmng Nhk, Trung K i h , Thdi Th*, TBn J&
tin tridn khai xiiy dpng m6i v i chi tpo ludi dien trung ap va trqm b i h &p #h+6i M n dja M n cis +a tren; khBng c6 chbt thAi v6 khi thsi bong qd uahinh
. 8S)ab& dv h c-hg nhu q u h 19 van hhnh sau nip.
Q@Y MQ) S& XUAT, KINH DOANE Xb dmg m6i rii chi tao lu6i dien trung ap va tqm b i b ip ph8n ph6i trGn
16 x8 thuQc 6 qu&huy$n: Binh Thhy, C ~ Y D6, h M&, Phang ~ i & , Chi
M y m6c thikt bi phyc \y cho du 6n d€u duqc s i n d t tqi chc nhl miy cb +aaroh s8n n$t Lbh n & i b ngbt, dv sir dwg lwi may b i h @ p h h phbi ~ ~ 3 0 ; 6 } ~ , 5 o / d 0 , 4 k ~ , ngo&i ra quh trinh dwg @t c6 thi dimg phumg # & w a g ho& c6 th8 6imp xe du loG 5 th.
Nh8n d9n hoyen Phong ~ ; e n : X i c nhfin B i i ~ ~ g call~ kt?'~ U i o , c6a dq in (cd sd): ..w... &. .... ~hdnh...~b& ..., ~d:.,&&.
...W...Mh.prY,n.:m.%d.. D U ~ C ciip ipifi.y iyic -ST 2 IGXN-UBND nghy$a thiingu. nlim 2 0 q.... Cdn
Phong'~i&n xt t duyet./.
Phong D i h , n g d d ~ t t tdr~g AX r ~ d r t l -7 T% i [ ~ BAN NHAN DAN
4' C H ~ TWH
"-'-.." . - - . - - - - . . . - y - - . . ..- ,-.. . ................. . . . . . . . ....... ' 7 - - " ' ' - l ' i r tmhg Thi% k6 ph&i b60 d h cic ti& chum qu&cte Nhi thd1.1 1
v$ hpn cia& c u h g d? di+ tii uuirng. 1 t h i ~ t LrS v j ~ i e n JUG . ' T c&nu !
... -.. --.....-. ' ,.̂ --..---A" L1-; Thvc hi& c8c chien luqc van bQngf/gitia duc I Bier1 luc :
! vt! an toan dien. : in l'ho I
: - ~ i 6 m tm kp thug1 vri giim siit din11 k$ he i ' ti16na di'n
I
s--k.-: ......‘......... . . . . . . i ........................... j
VII. CAM I&T THIJC HIqN
Chimg t8i xin d3m bjio vk do trung thvc clia cac s8 lieu trong ctic van bhn n2u m!n va cam k& ring Dy a n cua chting t6i khBng sir dvng cric loqi hoa chit, c h w vi sinh v@ bj c& theo quy djnh cua Vie Nam v i quy dinh cua cac c611g ubc
iJ ... qdc t6 mi Vie Nam I t b h v i h . Chung t6i cane xin bb djm &ng c k titu .(. '9. 2-2
9; ,. chub, quy ch& quy dm duqc hlch lyc v l sir +ng trong chc hd w d u u h c h
Q". : < $., ;.
chbg t8i 1A dimg qr th@t v l dmg co hi& lw Bp dwg.
.: I > 'l ,' hku c6 gi sai t~% chung t6i xin huh toin cbju trhch nhiem tm&c pMp lust .+: clia nubc C&g hba xB hai chu ngMa Viet Nam.
T h Wng.
KT. GI& M")c Ph6 Gihm d8c
S6: 32 IGXN-URN0 Phong Didn, ngdy go ~ItJng 12 ,,3m 2W7
G ~ Y xAc N f L i i ~ DANC K* BAN CAM KET B A ~ V&W& TRUONG
CJa dv 4n ThPnh phr(n Wi wn tnmgip lsew tluOn tMnh ph6Cbn Iltd (ChJ cdu u: Cdng ty DMa 13c 2).
Dia chi: S6 72. gai BB Tmg, phudrng B6n Nghb, qua11 1, l l~ i r r r l t ph6 H 3 Clhl
Dien thoa~. C18.220U341; Fax: 08 2200342
Dido I: bigby I9 lhling 12 nHn~ 2007, C6ng ty f3ieu lUc 2 1S chir ddu id dq Bn dil c6 Cbng van 56: 8179tCV-DL2-QLXD nghy 10 ihnng 12 n a ~ u 2U07 JIng k$ bAn cam kg1 b i o ve m6i rr&ng cda D J Bn ThPnb ph4n Irfr31 &en trung 4p ~ J n g tI&n tbPnh pbO' Ch n 'l'hd.
DiPu 2: Chtj clu ;in c6 r i ich nh~ern thvc hien clilrtg vB d l y d6 nhUng n3i dung & b8o v e m6i uubng n6u trong ban cam ke-t bdo ve r11Oi uuirng.
Diau 3: B i n cam kgt b30 vC m8i tntong ctla Jq 4n Ih cct sd dd cilc cd qua0 quin 13 nhb nUUc vk bdo ve m5i tnf1Ing gidm sdl, log~n Ira, thanh ua viec tlr\lc hie11 bile vS rnbi m&ng cira D d An.