routine maintenance.ppt
DESCRIPTION
ROUTINE MAINTENANCE.pptTRANSCRIPT
-
ROUTINE MAINTENANCEMEASUREMENT AND PAYMENT PROCEDURES.
MEASUREMENT OF WORKDONE OF POTHOLE PATCHING IS NET; IN ACCORDANCE WITH THE CIVIL ENGINEERING STANDARD METHOD OF MEASUREMENT, THIRD EDITION (CESMM3)
-
WORK DONE ON SITE MUST CONFORM WITH THE BILL DESCRIPTION AND SPECIFICATION.
A PATCHED POTHOLE MUST LAST AT LEAST ONE CALENDAR YEAR.
IF A PATCHED POTHOLE BECOMES DEFECTIVE IN LESS THAN ONE YEAR (WITHIN THE PERIOD THAT THE CONTRACTOR IS ON SITE), THE CONTRACTOR HAS TO REPATCH IT AT HIS OWN COST.
-
DEDUCTION OF RETENTION
POTHOLE PATCHING IS PERMANENT
WORK AND THEREFORE IS SUBJECT TO RENTENTION DEDUCTION. NORMAL RETENTION DEDUCTION IS 10% OF EACH INTERIM PAYMENT CERTIFICATE AND MAXIMUM DEDUCTION IS 5% OF THE CONTRACT PRICE PLUS ALL VARIATION ORDERS ISSUED.
RELEASE OF RETENTION IS UPON THE ISSUANCE OF THE DEFECT LIABILITY CERTIFICATE WHICH IS DUE THREE MONTHS AFTER COMPLETION OF THE WORKS.
-
THEREFORE THE ATTACHMENT TO THE DEFECT LIABILITY CERTIFICATES ARE THE SAME AS THAT OF PERIODIC MAINTENANCE
1. - TAKING OVER INSPECTION REPORT - SIGNATURES OF TAKING OVER INSPECTION TEAM - TAKING OVER CERTIFICATE 2. - DEFECT LIABILITY INSPECTION REPORT - SIGNATURES OF DEFECTS LIABILITY INSPECTION TEAM - DEFECTS LIABILITY CERTIFICATE - PHOTOGRAPHS SHOWING POTHOLES
-
BACK UPS1. FIELD MEASUREMENT SHEETS
2. RECIEPTS FOR ALL PROVISIONAL SUMS 3. PHOTOGRAPHS ; BEFORE, DURING& AFTER 4. SITE INSTRUCTIONS, NEGOTIATIONS AND APPROVED VARIATION ORDERS.
*
-
GRADING /BLADING OF GRAVEL ROADCLEARING OF LIGHT BUSH IS AN ACTIVITY CARRIED OUT BY A DOZER.
ANY INCIDENTAL BUSH ON THE ROAD ARE DEEMED TO BE PART OF THE GRADING /BLADING ACTIVITY
NOTE THAT MEASUREMENT OF BUSH CLEARING STARTS AFTER THE DITCH
*