3 Update on other RCR Program activities WTP / Pump Stations / Reservoir Final Design Final design ongoing – working on 30% Design Raw Water Pipeline Design / Build RFP RFP has been issued Bids are due on December 1, 2014TRANSCRIPT
Richland Creek Water Supply ProgramContract for WTP and Pump Stations CMAR Services and Program Update
Paulding County, Georgia
Board of Commission Work Session BriefingNovember 11, 2014
2
Richland Creek Water Supply Program Elements1. Dam and Reservoir2. River Intake and
Pump Station3. Raw Water Pipelines4. Water Treatment
Plant, Reservoir Intake and Pump Station
5. Distribution System Improvements
2
3
41
5
3
Update on other RCR Program activitiesWTP / Pump Stations / Reservoir Final Design
• Final design ongoing – working on 30% Design
Raw Water Pipeline Design / Build RFP• RFP has been issued• Bids are due on December 1, 2014
4
WWW.RCRWATER.COM is active• 190 visitors since 10/20/14• 904 page visits• Average 4.7 pages per visit
5
Construction Manager at Risk (CMAR)• CMAR selection based on experience,
qualifications, and other factors (cost)• Engineer designs project • CMAR involved during design
(constructability, value engineering, cost estimates, schedule)
• Owner and CMAR negotiate GMP during design – early determination of construction cost
• During Construction CMAR provides project insurance, bonding, oversight
• Subcontractors can be competitively bid
Program Manager
6
CMAR Contractor Procurement• RFP included evaluation of qualifications,
experience, project approach, and cost
• 8 proposals received
• Shortlisted to 3 companies(Haskell/Layne, Pizzagalli Construction, and Kiewit Construction)
• Pizzagalli Construction was selected
7
Pizzagalli Construction (PC)• 100% Employee Owned Contractor headquartered
in Burlington Vermont• Ranked in top 50 water/wastewater contractors in
ENR• Experience with numerous similar sized water
treatment plant and intake / pump station projects throughout the SE• Local experience includes the recent Gwinnett County Yellow River Water Resources Center (also a CMAR project).
8
CMAR Contractor ScopePreconstruction Services• Will work with WTP / PS designer (ARCADIS) to
develop design and Guaranteed Maximum Price (GMP) at 30%, 60%, and 90% levels
• Once 30% GMP is established, funding can be pursued, and design can be developed to keep this budget
• Preconstruction Services Cost - $300,060Construction Services• PC will serve as general contractor – all project
components will be competitively bid• Future GMP will come before Committee for Approval
9
1. Reservoir
2. Raw Water Pump Station
3. Raw Water Pipeline
4. Treatment Plant, Reservoir Pump Station
5. Distribution System Improvements
Design Phase Construction Phase
Reservoir Designer
Design Build Team
Reservoir Contractor
Pump Station Designer
Distribution Designer
CMAR Contractor
WTP Designer
CMAR Contractor
Distribution Contractor
10
Next StepsReservoir Design to 100%
River Intake/ PS Design to 30%
WTP Design to 30%
Reservoir Intake/ PS Design to 30%
CMAR 30% GMP
CMAR 30% GMP
CMAR 30% GMP
Cos
t Dec
isio
n P
oint
Fi
naliz
e S
izin
g of
Im
prov
emen
ts
Bidding and Construction of Reservoir
River Intake/ PS Design to 100% And Construction
WTP Design to 100% and Construction
Reservoir Intake/ PS Design to 100% And Construction
Raw Water Pipeline D/B Procurement
Final Design and Construction of Raw Water Pipeline
11
OverallProgram Schedule