rev 0 to tp-9419-cse96-2104, 'steam generator tube in-situ

30
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 1 of 23 Attachment 2 Test Procedure and Completed Data Sheets qezoa80<04 qesm4 PDR ADQCK 05000335, P PDR ABB Combustion Engineering Nuclear Operations

Upload: others

Post on 24-Feb-2022

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 1 of 23

Attachment 2

Test Procedure and Completed Data Sheets

qezoa80<04 qesm4PDR ADQCK 05000335,P PDR

ABB Combustion Engineering Nuclear Operations

Page 2: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-110 Attachment 2 Page 2 of 23

TP-9419-CSE96-2104, Rev. 0 Page 1 of 11

Test Procedure

Steam Generator Tube

In-Situ Hydrostatic Pressure Test Tool

Hydro Chamber Pressure Determination

Procedure No. TP-9419-CSE96-2104 Rev. 0

ABB Combustion Engineering Nuclear Operations

Prepared By;

Reviewed By: 54'c dt .4c~K F. AUea. Coaaeehene Enynocr

Date;

Approved By: +C eMerero+J. F. HalL Frmcepal C

Date:

Approved By.J. D. FcrreL Manager. Field r Opcranexn

ABB Combustion Engineering Nuctear Operations

ABB Combustion Engineering Nuclear Operations

Page 3: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 3 of 23

TP-9419SE96-2104, Rev. 0 Page 2 of 11

Table of Contents

Section ntents P~ae No

lo

20

3,0

4.0

5.0

6.0

Objective

References

Quality Assurance

Discussion and Background

Prerequisites

Limitations and Precautions

70 Test Procedure

7.1

72

Static Test

Dynamic Test

Figure 1

Data Sheet 1, Static Pressure Test

Data Sheet 2, Dytmnic Pressure Test

Data Sheet 3, Remark Continuation Page

Attachment 1 Faxed cover sheet with Review and Approval Signatures

10

ABB Combustion Engineering Nuclear Operations

ABB Combustion Engineering Nuclear Operations

Page 4: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101,—Rev. 0- Attachment 2 Page 4 of 23

TP-9419-CSE96-2104. Rav. 0 Page 3 of 11

I.O Objective

The objective of this test is to determine the relationship between the hydro pump outletpressure, the hydro chamber pressure and the seal bladder pressure under flow conditionsfor the steam generator localized in-situ presswe test tools. In addition, static testing willbe performed to establish a baseline relationship under non-flow conditions. The dataunder flow conditions willbe used to ensure that in the event ofa leaking defectindication, the leakage rate is measured at the appropriate pressure(s) within the hydrochamber. Testing willbe performed on both the axial and circumferential tools.

20 References

2.1 QAM-100, Fourth Edition, Revison 4

2.2 Final Test Report for the Steam Generator Tube In-Situ Hydrostatic Test Tool.TR-ESE-'030,

Rev, 00, T. R. No. 83D, dated April 5, 1994.

3.0 Quality Assurance

The test described herein is to be treated as Safety Related, Quality Class 1, in accordancewith the requirements in Reference 2.1.

4.0 Discussiori and Background

Reference 2.2 describes the development and qualification testing for the localized in-situtest tool. The tool described in Reference 2.2 was developed to pressure test primarilycircumferential defect indications in steam generator tubes at the tubesheet region. It isalso applicable to the testing ofaxial indications. An additional tool was evolved for thctesting ofaxial defects which are greater in length than those which can be accommodatedby the hydro chamber in thc original tool. Since the tool design for the circumferentialdefects has greater restrictions than those for axial defects, thc test report is bounding forthe axial tool.

The localized test tool contains two pressure circuits; one for seal and gripper bladders,and onc for the hydro chamber. The hydro chamber circuit is pressurized by an airoperated positive displacement pump. The bladder circuit is pressurized by either an air

operated positive displacement pump or a hand pump.

The positive displacement pumps used in the system are able to maintain a precise controlat a given static pressure. Under flow conditions, such as those experienced during a tubeleak. the pump discharge pressure fluctuates between a high and low limitwith each pumppulse. The magnitude of this band is a function of the flow rate and the restrictions withinthe hose/tool assembly. Due to these dynamic head losses, the actual pressure in thchydro chamber willbe less than that observed at the pump discharge.

ABB Combustion Engineennp Nuciear Operations

ABB Combustion Engineering Nuclear Operations

Page 5: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 50f23

TP-9419-CSE96-2104, Rev: 0 Page 4 of 11

Reference 2.2 describes testing which was performed under flowconditions to establishthe relationship between the hydro pump discharge pressure and the hydro chamberpressure. This test consisted ofmeasuriiig the swing of the pressure gauge at thedischarge ofthe hydro pump at various leak rates at an initial static hydro chamberpressure of4,000 psig as directly measured in a controlled leak test fixture.Implementation ofthis data in an in-situ field test requires an iterative process as the hydrochamber pressure is not directly measurable. The process involves matching the pumpdischarge pressure swing relative to the desired pressure and observe the pump stroke rateas compared to the data in the test report. In addition, the test report explicitly states thatthe leak rate correction data apply only to the as-tested configuration.

For the testing at St. I.ucie Unit I, it was requested that the capability be provided to testin the straight tube portions at elevations well above the tubesheet. This necessitated thefabrication ofhoses longer than those described in Reference 2.2. For non leaking defectindications. the length of the hose does not affect measuring the desired pressure in thehydro chamber as the system is static and the pressure is equal to that at the pumpdischarge. For leaking defects, the change in system resistance due to the change in hoselength does have an effect on the dynamic response ofthe pump discharge pressure gaugeand its subsequent relationship to the hydro chamber pressure. Consequently, for aleaking defect, the actual pressure in the hydro chamber is indeterminate withoutadditional testing.

In order to determine the pressure in the hydro chamber with the current hoseconfiguration, two methods willbe considered.

I) Hydro pump discharge pressure swing correlation method, and,

2) Seal bladder pressure intensification method.

Item l is the method described in Reference 2.2. Item 2 is based upon an observationduring laboratory testing and field application. Experience during previous testing hasshown that the bladder circuit pressure increases as its initial pre-charge pressure isapproached by the increasing pressure in the hydro chamber. This pressure increase hasbeen termed 'intensification.'nce the bladder pre-charge pressure is reached in thehydro chamber, the bladder pressure willincrease with increasing hydro chamber pressure.This pressure has been observed to be approximately 200-300 psid under static conditions.It is expend that the relationship willbe similar under flow (leak) conditions.

Establishing this relationship willprovide an accurate, indirect method of measuring thepressure in the hydro chamber under leaking conditions. As the bladder circuit is not in aflow path, there are no head losses to consider. Pulsations may be evident in the bladdercircuit due to the reciprocating nature of the hydro pump. However, these pulsations willreflect the true pressure in the bladder circuit independent of the head losses experienced

ABB Combustion Engineering Nuctear Operations

ABB Combustion Engineering Nuclear Operations

Page 6: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ
Page 7: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 6 of 23

TP-941&CSE96-2104, Rev. 0 Page 5 of 11

by the hydro circuit. By inference, the pressure in the hydro chamber can then bedeterminNL

This test willfocus on establishing method 2 as the method ofchoice for determining thehydro chamber pressure under flow conditions. However, additional data willbe recordedin order to provide for the use ofmethod 1 should method 2 prove to be invalid.

5 0 Limitations and Precautions

5.1 As noted in Section 4, the method 1 correlation is a Function of system dynamicresistance. Use of the test results in method 1 correlations is limited to systems with anidentical configuration to that tested. The hose configuration in this test is identical to thatin Figure 2 ofReference 2.2 with the exception that the length of the 3/16" braided hosehas been increased from 30 feet to 50 feet. Use of the longer hose length in the test willqualify method 2 fo'r use in the as tested configuration..

6.0 Prerequisites

6.1 Allpressure gauges to be used in the test shall be verified to be within the calibrationperiod.

NoteThe test procedure is intended to provtde a protocol. It is notintended to limitthe type of testing conducted. As an example,«ddittonal pressures may be tested or conditions changed in order toadapt to lessons learned during the test. Any changes or additionsshaH be recorded and explained on the appropriate data sheet. Blankdata sheets may be copied to provide for each parameter change.

NoteMinor leakage may occur during the conduct of this test.Acceptability of leakage with respect to continued operation of thetest is at the discretion of the test operator. However, any leakageshaH be recorded in the remarks section of the data sheet.

7 0 Test Procedure

NoteThe static test will be performed using both the circumferential/axialtool and the long axial tool. The order of performance is at thediscretion of the test operator. Data sheet 1 is used to recordinformation for the static test.

A88 Combustion Engineering Nuciear Operations

ABB Combustion Engineering Nuclear Operations

Page 8: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-110'1. Rev. 0 Attachment2 Page7of23

TP-9419-CSE96-2104, Rev. 0 Page 6 of 11

7,1.1 Assemble the test fixture, in-situ tool and pump circuits as shown in Figure l. Record the

tool (circ. or long axial), hydro pump pressure gauge, hydro chamber pressure gauge and

bladder pressure gauge serial numbers on the data sheet.

712 Operate the bladder pump to fillthe bladder circuit tubing with water. Pressurize the

bladder circuit to approximately 4,000 psig ~200 psig and release the pressure at the

pump discharge. Repeat this process at least 10 times to remove air from the bladder

CIrcuit.

713 Using the bladder pump, pressurize the bladder circuit to an initial pressure of 1,500 psig= 100 psig as indicated by the bladder pressure gauge. Observe the pressure gauge

reading to ensure that there are no significant leaks. Record the initial bladder pressure

9 0 psig hydro chamber pressure on Data Sheet 1.

7,1.4 Close/verify closed'the leak rate control valve.

NoteThe static test is to be conducted at target hydro chamber pressures of1,500, 1,600, 1,800, 3,000, 4,000 and 5,000 psig.

7.1,5 Pressurize the hydro circuit to the target pressure s 100 psig as indicated by the hydro

chamber pressure gauge. Observe for leaks and steady pressure readings on all gauges.

Record all pressure gauge as read values on the data sheet. Repeat this step for each ofthe target pressures fisted on the data sheet.

7.1,6 Ensure all necessary data have been recorded on the data sheet, signature and date signify

completion.

7 1,7 Repeat steps 7.1.3 through 7.1.6 for an initial bladder pressure of 2,000 psig < 100 psig.

7 1.8 Repeat steps 7.1.1 through 7.1,7 for the second tool.

7 2 ~Dggj~g

NoteThe dynamic test willbe performed using both thecircumferential/axial tool and the long axial tool. The order ofperformance is at the discretion of the test operator. Data sheet 2 is

used to record information for the dynamic test.

7 2,1 Assemble the test fixture, in-situ tool and pump circuits as shown in Figure 1. Record the

tool (circ. or long axial), hydro pump pressure gauge, hydro chamber pressure gauge and

bladder pressure gauge serial numbers on the data sheet.

ABB Combustion Engineenng Nuciear Operations

ABB Combustion Engineering Nuclear Operations

I+ W'/

Page 9: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101 Rev. 0. —. Attachment 2 Page 8 of 23

TP-941 94SE96-2104, Rev. 0 Page 7 af 11

,NoteIfthe hydro tool has not beta separated from the hose, the bladdercircuit does not require degassing and the following step is N/A.

7,2.2 Operate the bladder pump to fillthe bladder circuit tubing with water. Pressurize thebladder circuit to approximately 4,000 psig a 200 psig and release the pressure at the

pump discharge. Repeat this process at least 10 times to remove air from the bladderCircuit.

7.2.3 Using the bladder pump, pressurize the bladder circuit to 1,500 psig ~ 100 psig as

indicated by the bladder pressure gauge. Observe the prcssure gauge reading to ensurethat there are no significant leaks. Record the initial bladder pressure 0 psig hydrochamber pressure on Data Sheet 2.

7.2.4 Close/verify closed the leak rate control valve.

NoteThe dynamic test is to be conducted at target hydro chamberpressures of 1,700, 3,000, 4,000 and 5,000 psig. Each target pressurerequires a separate data sheet.

7.2.5 Pressurize the hydro circuit to the target pressure + 100 psig as indicated by the hydrochamber pressure gauge. Observe for leaks and steady pressure readings on all gauges.Record all static pressures as the zero pump rate values.

P

NoteIterative adjustment of the leak rate control valve aad the hydropump air control regulator willbe for establishing the desired pumpstroke rate at a given target hydro chamber pressure.

7 2.6 Slowly open the leak rate control valve to establish a hydro pump stroke rate of 20strokes/minute while maintaining thc target pressure as indicated by thc hydro chamberpressure gauge. Adjust the hydro pump air control regulator and the leak rate controlvalve as necessary. Ifthe hydro chamber pressure is not steady, adjust to the targetpressure at approximately the middle of the swing. Record all prcssure reading's on thedata sheet. Repeat this step for each of the pump stroke rates listed on the data sheet.

7,2.7 Ensure all necessary data have been recorded on the data sheet, signature and date signifycompletion.

7,2.8 Repeat step 7.2.4 through 7,2.7 for each of the target pressure values.

7.2.9 Repeat steps 7.2.1 through 7.2.8 for the second tool.

ABB Combustion Engineering Nuciear Operations

ABB Combustion Engineering Nuclear Operations

A.h

Page 10: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

CD0)O0UCr/l

0DfllD(O

(D(D

(0ZCorDQ

0(D

0DVl

OO3FLtO

fn4.

g

82',

Q

0

I I-lydro

Pump

IlydroPumpGauge

In-Situ Tool

Steam GeneratorTube

Bladder Pressure

Gauge

HydroChamber

Figure 1

Test Apparatus Configuration

Hydro ChamberGauge

Leak Rate

Control Valve

Bladder

Pump

Page 11: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, . Rev. 0 Attachment 2 Page 10 of 23

TP-941 &CSE96-2104, Rev. 0 Page 9 of 11

Data Sheet 1

Static Pressure Test

Tool (circ. or long axial)

Initial Bladder Pressnre~sig

Target HydroChamber Pressure

S1

Observed HydroChamber Pressure

S1

Hydro PumpDischarge Pressure

( si

Bladder Pressure

SI

Hydro Pump Discharge Pressure Gauge No.Hydro Chamber Pressure Gauge No.Bladder Pump Discharge Pressure Gauge No.

Remarks:

Completed by:Name tSitsaaatre

Date:

Witnessed by:Name ~signattle

Date:

ABB Combustion Engineenng Nudear Operations

ABB Combustion Engineering Nuclear Operations

/+w ~g

Page 12: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 11 of 23

TP-941&CSE96-2104, Rev. 0 Page 10 of 11

Data Sheet 2

Dynamic Pressure Test

Tool (circ. or long axial)

initial Bladder Pressure psig Hydro Chamber Target Pressure pstg

Pump Rate

Strokes/min

0 static20

40

6080

100

Hydro ChamberPressure"'t

Maximum Minimum

Hydro PumpDischarge Pressure"

( siMaximum

Bladder Pressure"'

siMaximum Minimum

Notes: i) For non-fiuctuaung pressure values. record pressure as the maximum pressure achieved.

Hydro Pump Discharge Pressure Gauge No.Hydro Chamber Pressure Gauge No.Bladder Pump Discharge Pressure Gauge No.

Remarks:

Completed by:Name. Signamre

Date:

Witnessed by:Nuns.signamn

Date:

ABB Combustion Engineering Nuclear Operations

ABB Combustion Engineering Nuclear Operations

Page 13: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101~ev 0. Attachment 2 Page 12 of 23

TP-941 &CSE96-2104, Rev. 0

Data Sheet 3

Remark Continuation Page

Page 11 of 11

Test (static or dynamic

Initial Bladder Pressure

Tool (circ. or long axial)

psig Hydro Chamber Target Pressure pstg

Remarks:

Completed by:.'rane isigaature

Date:

Witnessed by:.'raaa signamre

Date:

ABB Combustion Engineering Nuctear Operations

ABB Combustion Engineering Nuclear Operations

Page 14: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1 1Gi~aLQ Attachment 2 Page 13 of 23

Z8 d~ ZG'%Md 'WLQi ~ M:LZ 966TWV~

~~$w~f g Q ~p j'y6'Msprd-2l/ gcuo

TP-941~EBS-2104. Rev. 0 Pe 1 of 11

Test Procedure

Stcam Generator Tube

In4itu Hydrostatic Pressure Test Tool

Hydro Chamber Pressure Determination

Procedure No. TP-9419 CSE96-2104 Rev. 0

ABB Combuarion Engineering hhclear Operations

Prepared By:

6,5. cd nse:~6- o- L

Approved By:a R A<4 Kaaa~r, fic14 geary~ Dare:

ASS Combuarion Enqinwring Naalaar operations

Jul LG '96 l4:51

ZGrZG'd G6Z~~t Ol telic SSZ G98

TOTAL P.82

ABB Combustion Engineering Nuclear Operations

Page 15: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 14 of 23

TP-9419-CSE96-2104, Rev. 0 Page 9 of 11

Data Sheet 1

Static Pressure Test

T I( '*. I g 'd)~initial Bladder Pressure~Is ~ sig

Target HydroChamber Pressure

S1

/ tabs

Ige'/Ossa

4 >ssn

hatt~

Observed HydroChamber Pressure

Sl

5'oo/4 "c

Hydro PumpDischarge Pressure

S1

I 5oc(ge-r Zo~3cc=

sstC~o

Ste&O

Bladder Pressure

S1

g)h3v~ K'43$ ,0 +

Hydro Pump Discharge Pressure Gauge No. 5,- Io - r~ ~lHvdro Chamber Pressure Gauge No. A- 7 - oo 0Bladder Pump Discharge Pressure Gauge No. W-n' zo>M

Remarks:

Completedby: C~>z,,~ <~k.'Nacm s Silttgure

Witnessed by: 3 I ~ < lol.Vattse Sittaatttre

Date: 4 « ~~

Date:~<a/ Rte

ABB Combustion Engineering Nuctear Operations

ABB Combustion Engineering Nuclear Operationsp+->)

Page 16: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-11 Attachment 2 Page 15 of 23

TP-941 &CSE96-2104, Rev. 0 Page 9 of 11

Data Sheet 1

Static Pressure Test

Tool (circ. or long axial)

Initial Bladder Pressnre~gee= sig

Target HydroChamber Pressure

SI

1 Ir"oa

Q tteIOO

tasse~

Observed HydroChamber Pressure

s1

I 5ow

dt OC

Hydro PumpDischarge Pressure

( si

/tssoo

3 05o~ee=miso a

Bladder Pressure

( si

+2 So

Hydro Pump Discharge Pressure Gauge No. rS - r -IWIHydro Chamber Pressure Gauge No. FS — I I - o3~Bladder Pump Discharge Pressure Gauge No. - - o<M

Remarks:

Completed by: Ct=-~Vane; Silsatstrn

Date: ~ " ~8

slatsse St tnatttrts

ABB Combustion Engineenng Nuoiear Operations

ABB Combustion Engineering Nuclear Operations

Page 17: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ
Page 18: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101-,-Rev. 0 Attachment 2 Page 16 of 23

TP-941&CSE96-2104, RN'. 0

Data Sheet 1

Static Pressure Test

Page 9 of 11

Tool (circ. or long axial) r QC .

Initial Bladder Pressure~/3'uc sig

Target HydroChamber Pressure

( si

/4 oo

'3 oooQeo0

OO

Observed HydroChamber Pressure

SI

gooIbm'7

ogoo

Hydro PumpDischarge Pressure

st

i geoIS oel8oG3ccQdf(g ~

Bladder Pressure

( si

I $ 00

20 m-a

Sl ~Ct

~I5ogt go z.

Hydro Pump Discharge Pressure Gauge No. - l - oHydro Chamber Pressure Gauge No. S - I - loO 3~Bladder Pump Discharge Pressure Gauge No. S - ( 7 - laO 33

Remarks:GI<t Lf LH~~ Q ~: A owg 5~,% Qj-sp o, ~ 5th'K-(<) S Q Caw,t

"Is4sa Mi w W k. g I

Completed by: C~u~~a l-r ~kstuns tSirtaarttrc

Wiutessed by: .~ f'f:.'Iarrsc Siltarttrc

Date: < '> ~<

Date:~d-Vd

ABB Combustion Engineering Nuotear Operations

ABB Combustion Engineering Nuclear Operations

Page 19: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment2 Page17of23

TP-9419-CSE96-2104, Revs 0 Page 9 of 11

Data Sheet 1

Static Pressure Test

Tool (circ. or long axial) C QC

Initial Bladder Pressnre~2seo sig

Target HydroChamber Pressure

SI

t ~aO

/bt 4

i go~.tso cd

df dt O a

~C~

Observed HydroChamber Pressure

SI

l g)c

f7~~gg~ oeeoc~oo

Hydro PumpDischarge Pressure

SI

t5ctQs o

IGcc3~

Bladder Pressure

SI

'Coo Ot

sst 35'O

QgaQ

8 20~ (t)Qg6~ Z

Hydro Pump Discharge Pressure Gauge No. 5-i 3 - LdeelHydro Chamber Pressure Gauge No. PS - i l - eo 3

Bladder Pump Discharge Pressure Gauge No. 5- I - leos s

RemarkS: ( ) 5c, 4 gc.40O~ 6 -~d~~ R.A ~i~.- ~ J.~ ~ADO~~S

(2X S< 4 Ittt.a ~ - ~ L1t 2u S Aoo tes

)n ~.~ Q al ( S~t tusaa Z~~. O aWf'0

Completed by: C~t-./eP/aD F/~ IC.'st aalu Sittaatttte

Witnessed by: . Woi.'same Stttatttre

Date: ~6/ / pts

Date: Co-/(-~4

ABB Combustion Engineering Nuotear Operations

ABB Combustion Engineering Nuclear Operations

Page 20: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0- Attachment 2 Page 18 of 23

TP-9419-CSE96-2104, Rev. 0 Page 10 of 11

Data Sheet Z

Dynamic Pressure Testr

Tool (circ. or long axial) 5t 0 L

initial Bladder Pressure I >~> psig Hydro Chamber Target Prmeuref keio pdg

Pump Rate

Strokes/min

Hydro ChamberPressure'"

st

Hydro PumpDischarge Pressure "

( si

BladderPressure"'t

Maximum Minimum Maximum Minimum Maximum Minimum

0 (static)

100

/&5olpga o

/g uO

l7o~l9cc

5ptoo

I '7 >t=e

I 7am

/~>of lo&/go>

/g@ o

j 9co

/EoO

r9su

Notes: t) For non-ftuctuaung pressure values. record pressure as the maximum pressure achieved.

Hydro Pump Discharge Pressure Gauge No. 6's - l7- l c ~ t

eye ch b p* G re.~Bladder Pump Discharge Pressure Gauge No. F5-l'7-l«~9

Remarks:

Completed by:Vgmg rSithggttyg

(:7 Date: < I ~<

Witnessed by:Vgmg ignanae

Date: 6-il-C

ABB Combustion Engineering Nuctear Operations

ABB Combustion Engineering Nuclear Operations

p4-5 i

Page 21: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101„~ev. 0 Attachment 2 Page 19 of 23

TP-941 &ZSE96-2104. Rev. 0 Page 10 of 11

Data Sheet 2

Dynamic Pressure Test

Tool (circ, or long axial) %t AL

Initial Bladder Pressure le~ psig Hydro Chamber Target Pressure 38~~ psig

Pump Rate

Strokesimin

0 static)

Hydro ChamberPressure'"

SI

Maximum Minimum Maximum Minimum

Qqoo

Hydro PumpDischarge Pressure"'l

Bladder Pressure"'

sitMaximum Minimum

geoPZgl40.Qj Q100

'3looQ)v3 5~qD

gqoC0'%co

A/00 f+oo

Q7 oo oc

$ 2Oe-

/goo

gazoo

Notes: l) For non-lluctuating pressure values. record pressure as the maximum pressure achieved.

Hydro Pump Discharge Pressure Gauge No.Hydro Chamber Pressure Gauge No. - s - l s - I 49'

Bladder Pump Discharge Pressure Gauge No. A-(7- Ic933

Remarks:

Completed by: C ~ g CI-i~ 5vame tSiltature

Witnessed by: ec i~V tStttanare

e

Date:~i

A88 Combustion Engineering Nuclear Operations

ABB Combustion Engineering Nuclear Operations

r~-: <

Page 22: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-941 9-CSE96-1 101,>ev 0 Attachment 2 Page 20 of 23

Tp-941 9-CSE96-2104, Rev. 0 Page 10 of 11

Data Sheet 2

Dynamic Pressure Test

Tool (circ. or long axial) 'i(> I >~>aq~~

Initial Bladder Pressure I zc 0 psig Hydro Chamber Target Pressure+~4+ psig

Pump Rate

Strokes/min

Hydro ChamberPressure"'t

Maximum Minimum

Hydro PumpDischarge Pressure '

siMaximum Minimum

Bladder Pressure'"

slMaximum Minimum

0 static) b+~ 8'I~o&20 t8 +ceo

!liO

Q7E)C)

80100

Notes: i) For non-fluctuaung pressure values. record pressure as the maximum pressure achevcd.

Hydro Pump Discharge Pressure Gauge No. PS -l1 - I o~~ IHyd Ch b P G gNBladder Pump Discharge Pressure Gauge No. Cs-t7-too33

Remarks:

Completed by:.'rane isignanue

Date: rl '< 9<

Witnessed by:v siyenee

Date: 6 ~i 5'6

ABB Combustion Engineenng Nuctear Operations

ABB Combustion Engineering Nuclear Operations

+-3 i

Page 23: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101;.Re. e--- Attachment 2 Page 21 of 23

TP-941&CSE96-2104, Rev. 0 Page 10 of 11

sr 'rr

Tool (circ. or long axial)

Data Sheet 2

Dynamic Pressure Test

lultlal Bladder Pressure~the-'h psig Hydro Chamber Target Pressure J1+0 pslg

Pump Rate

Strokes/min

. Hydro ChamberPressure"'I

Hydro PumpDischarge Pressure "

sl

Bladder Pressure "

( siMaximum Minimum Maximum Minimum Maximum Minimum

0 static) l ~ ~ l1+~ tgOO

60 Q gether~o DesWee

]g Cu

1'Voa

< A-ai~5Q/Qoc:I Zcy»

I3o~

IQ~odt I 0t-"s

/dr'eo

/6OO/ 4tao/bet ol7ZO

l7om

7oo

g. Ieto

t75 ot160r Pcycp

Notes: t) For non-fluctuaung pressure values. record pressure as the maxtmum pressure achiared.

Hydro Pump Discharge Pressure Gauge No. s- i7- foalhid Ch I Ih o h*ha.~Bladder Pump Discharge Pressure Gauge No. 5- 6- Ia»>

Remarks: lo

I

Completed by; C vz a I-h~ kVgtttc h St ttgtttye

Witnessed by:V .Sittgtttgg

Date:~th/rr

ABB Combustion Engineering Nuclear Operations

ABB Combustion Engineering Nuclear Operations

Page 24: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-94'i 9-CSE96-1101,,R&V. 0 Attachment 2 Page 22 of 23

TP-9419-CSE96-2104, Rev. 0 Page 10 of 11

Data Sheet 2

Dynamic Pressure Test

Tool (circ. or long axial) A~ <

fnitial Bladder Pressure t ~cs~ psig Hydro Chamber Target Pressure 3t"S o psig

Pump Rate

Strokes/min

Hydro ChamberPressure"'l

Hydro PumpDischarge Pressure"'l

Bladder Pressure'"

Sl

0 static)

Maximum Minimum Maximum

%5 5C'ryos

Minimum

3/o"Maximum Minimum

100

>So~

n es o

3~o

dl e~7~o

$ rfoo

'3 goo

$gOO

9(oestqOsO

Q v~0~

Q clasO

ggoQQ ~c2

IL 9'~o 39~D

Notes: l) For non-Auctuaung pressure values. record pressure as the mmumum pressure achieved.

Hvdro Pump Discharge Pressure Gauge No. 55- I 1 - loooIHvdro Chamber Pressure Gauge No. s -I —I~ >~Bladder Pump Discharge Pressure Gauge No. E5- f '7 -0~2~

Remarks:

Completed by:Vasne rsignantte

Wimessed by.!4 .Signature

Date: » ~>

Date:~~ri c

ABB Combustion Engineenng Nuclear Operations

ABB Combustion Engineering Nuclear Operations'

/f w/

Page 25: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96.-'i iG1,MKLQ. Attachment 2 Page 23 of 23

TP-9419-CSE96-2104, Rev. 0 Page 10 of 11

Data Sheet Z

Dynamic Pressure Test

Tool (circ. or long axial) Cl P<

initial Bladder Pressure I>~ psig Hydro Chamber Target Pressure &3oa psig

Pump Rate

Strokes/min

Hydro ChamberPressure"I

SI

Hydro PumpDischarge Pressure"'

si

Bladder Pressure"'

siMaximum Minimum Maximum Minimum Maximum Minimum

0 static)20AO"+z.

100

~r~+geo

H5~~

gl eQ

~9~C I~o

%5oo

g'leo93~

I toes

3'3goo

"f5~o q$ ocs

Notes: I) For non-fluctuaung pressure values. record pressure as the maximum pressure actueved.

Hydro Pump Discharge Pressure Gauge No. FS. t1- /choo I

Hydro Chamber Pressure Gauge No. S — l - toe >~Bladder Pump Discharge Pressure Gauge No. C" - tv - (eass

Remarks: Low L~K lent

Completed by:Wane.si gaamce

Date: b " <<

Witnessed by:Name Signcun

ABB Combustion Engineering Nuciear Operations

ABB Combustion Engineering Nuclear Operations

Page 26: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-1101, Rev. 0 Attachment 3 Page 1 of 5

Attachment 3

Pressure Gauge Calibration Records

ABB Combustion Engineering Nuclear Operationsp- 4/

Page 27: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

~ ~

~ ~ ~ ~

~ ~ ~

~ ~ ~k

~: ~ ~ .

~ . ~ ~ . ~

0 I iree Ia. ~ . ~ > ~

' ~ ' CS ~ ~ ~ 0

I ~ ~ ~

~ ~ I ~ ' ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~

f>Ir

HEMy ~ I

5

~ ~

~ '

~ '~ ' ~ ' ~ ~ ~

~ ~ ~ ~

~ ~ ' ~

~ '

~ ~ ~ ~ ~ ~ ~ - ~

Page 28: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

~ ~ ~ ~ ~ s

~ ~ ~ ~ >0 ~

~ I

er ~

~ ~

~: ~ ~

~ ~ ~

~ 4 ~ . ~

~ ~ I ~

~ ~ ~

~ ~

~ ~ ~ ~ ' ~ ~

~ ~ ~ t ~ ~ ~ ~ I ~

~, ~ ~ ~ 0 ~

N'%mrf%58W

~ ~

J' ~

~ '~ ' ~ ~ ' ~ ~

' ~ ~

~ '~ ~ ~ ~ ~ '

j - o

~ ~

IJ

i

~ ~ ~ ~ ~ ~ ~ - ~

Page 29: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-9419-CSE96-11 Attachment3 Page4of5

STO-400-159Rev. 00

ABB-Combustion Engineering~ ¹xclear Operations

Page 5 of 5

Attachment 1

CERTlFICATE OF CAUBRATlON

instrunlent Type

Manufaaurer

Range 0- 'O @cc racy

Mfg. Serial No.

C.E lO No P'5 -(7 /db ZB

Calibration Date

Calibration Due Date

Calibration Document:

gl Procedure

[ ) Manutacturer s Specifications

Test Equipment Used To Perform Calibration:

Test EquipmentK~~ Senal or ID No.

V -oo<Test Equipment Serial or lo No.

CAiJBRATlON RESULTS

Standard Value As Found i As Left

(Cg

Standard Value As Found As Left

lo

CAUSRATION HAS afEH P& FORM EO UnUDNQ MEASUREMEHT Ofvlcf5 WHICH H*vE KNOWN RELATIONSIII&To NssSTANOAAOS Wlifaf SUCH ST*NO*ROS KXIS . WHcfaf 5UCH STAHOARO5 Oo NQT Q(IST, AH A~QVEO IVOC OUREWAnicN IH ACCOROAHCE Wnl TH MAHUFA~iRfcL'5RECQMMfiIQATIQNS HA5 BfcEN USEQ AHO THE STAHOAAOSOOCUMEHi co.

REMAR(S:

1 ACCEPTEO ( 1 REJECTEDCALlBRATED BY:

ORGANIZATION:

ABB Combustion Engineering Nuclear Operations

Page 30: Rev 0 to TP-9419-CSE96-2104, 'Steam Generator Tube In-Situ

TR-941 9-CSE96-1 10~ev Q. Attachment 3 Page 5of5

STD-400-159Rev. 00

ABB-Combustion EngineeringNuclear Operations

page 5 of 5

Attachment 1

CERTlFICATE OF CALIBRATlON

Instrunlent Type

Manufacturer

Range 0- ra eevraeyg~2FSMfg. Serial No.

C-E ID No.

Calibrarion Date

Calibration Oue Date

CalIbratIon Oacurnent.

(+ Pracedure ~~~

) Manufacturer's Specifications

Rev.

Test Equipment Used To Perform Calibration:

Test EquipmentHI= ISL=

Serial or IO No.

~rrTest SquIonlent Serial or IO No.

CALIBRATIONRESULTS

Standard Value As Found l As Len

0 Rl<i I lao f46 I locp Q<ciLao CI I Z lou ' 2 lrr0

I~i~ I f~I o~oI ~ I

lo Iio lo

Standard Value As Found As Left

CAUSRATloN H*5 IEKH PEaIFORMKO UnUZINO MEASUREMENT QEVIC'ES WHICH HAVK KNOWN RELATIONSHIPS Ta Nes

STANQARQS WHERE SUCH STANOARQS KXISi. WHERE SUCH 5i ANOARQ5 QO NOT EXIST. AN APPROVEQ PROCEQUR

WRITTEN IN ACCOROANCE VIPiil THE MANUFA~iRER'5 RFCOarIMEVQATloaIS HAS BEgaI USEO ANO THE STANOAROS

QOCUMEN a =O.

R":MAR(S

()Cl ACC:?T"=D I l R"=J"=CT"-OCALIBRAT "0 BY:

ORGAraNaIZATION:

ABB Combustion Engineering Nuclear OperationsIg(